JP3979646B2 - Concrete building repair method - Google Patents
Concrete building repair method Download PDFInfo
- Publication number
- JP3979646B2 JP3979646B2 JP2003031580A JP2003031580A JP3979646B2 JP 3979646 B2 JP3979646 B2 JP 3979646B2 JP 2003031580 A JP2003031580 A JP 2003031580A JP 2003031580 A JP2003031580 A JP 2003031580A JP 3979646 B2 JP3979646 B2 JP 3979646B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- frame
- concrete building
- opening
- exposed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、機械的衝撃を発生せずに、良好な作業環境を確保しながらコンクリート建造物を補修できるコンクリート建造物補修法に関する。
【0002】
【従来の技術】
例えば、特許文献1は、鉄筋コンクリート建造物のコンクリートをウォータジェットにより破砕・除去し、補強用鉄筋を配筋して補強する既存鉄筋コンクリート構造物の耐震補強工法を示す。この耐震補強工法では、高速道路の橋脚等の既存鉄筋コンクリート構造物に対し、既存鉄筋を切断せず、ウォータジェットにより既存鉄筋の鉛直方向のコンクリートを除去してスリットを設け、スリットを利用して既存鉄筋に補強用鉄筋を組合わせて配筋する。既存鉄筋と補強用鉄筋の表面に増し厚コンクリートを覆って補強できるので、既存鉄筋を破損するおそれがなく、騒音、振動、粉塵等の環境を大幅に改善できると共に、施工の大幅な省力化を図ることができる。
【0003】
特許文献2は、軽量な高強度の連続繊維とを含むFRP格子筋を固定するコンクリートウェブ面のコンクリートをウォータジェットにより除去し、FRP格子筋にリベットアンカーを固定し、コンクリートを充填して固化するコンクリート構造物の補強方法を示す。このコンクリート構造物の補強方法は、複数の補強筋を格子状に配置して形成したFRP格子筋と、FRP格子筋を固定するコンクリート棒部材とを含むコンクリートウェブ面と、固定したFRP格子筋の側に塗付して増厚するセントモルタル又はポリマーモルタルとを備えるコンクリート構造物に対し、ウォータジェットによりコンクリートウェブ面のコンクリートを除去して下地処理する。次に、FRP格子筋を固定するコンクリートウェブ面にリベットアンカーを打ち込み、更に強固に保持し、FRP格子筋をコンクリートウェブ面に確実に固定して補強することにより、コンクリート構造物は、高いせん断補強効果を得る。
【0004】
特許文献3は、ウォータジェットによりコンクリート路盤のコンクリートを除去し、露出した鉄筋上に補強鉄筋を配置してコンクリートを打設する道路の補修方法を示す。この道路の補修方法では、複数の鉄筋に付着されたコンクリートを含むコンクリート路盤の一方の表面を路幅方向と路長方向にウォータジェットにより高速度で水を噴射し、水圧によりコンクリート面を除去して、鉄筋を露出させる。次に、露出した鉄筋に一次補強鉄筋を路幅方向に配筋してコンクリートを打設し、コンクリート路盤の他方の表面にもウォータジェットにより水を噴射し、コンクリート面を除去する。同様に、露出した鉄筋に二次補強鉄筋を路幅方向に配筋してコンクリートを打設する。また、一次補強鉄筋と二次補強鉄筋との間に雄ネジを有する継ぎ筋が設けられるので、コンクリート路盤の路幅方向と路長方向に鉄筋が連続接合され強化される。
【0005】
【特許文献1】
特開平9−67942号公報(第2頁)
【特許文献2】
特開2002−129753号公報(第2頁)
【特許文献3】
特開2002−180417号公報(第3頁)
【0006】
【発明が解決しようとする課題】
従来のコンクリート建造物補修法では、補修箇所の全コンクリートをウォータジェットにより除去するため、修理に手間と時間を必要とし、短期間で補修工事を完了することができない。また、例えば、ワイヤーソーイング、ウォールソーイング又はドリルソーイング等のソーイング切断装置を用いて、コンクリート建造物を破砕すると、コンクリート材の破壊時に発生する大きな衝撃、振動により、健全な鉄筋及びコンクリート材にマイクロクラック等の損傷が発生するのみならず、振動及び騒音が発生して、コンクリート材の粉塵が周囲に飛散するため、環境に悪影響を与える。ソーイング切断装置を用いて、コンクリート建造物を切断した後に、コンクリート建造物を補強するには、更に、コンクリート材に鑽孔して、形成される凹部にエポキシ樹脂等の接着剤を注入する。その後、補強鉄筋を凹部内に挿入して、エポキシ樹脂により凹部内に接着させるため、既存の鉄筋に対して接続されず、機械的強度が極めて不十分になる欠点がある。
そこで、本発明は、補修時に大きな衝撃及び振動をコンクリート建造物に発生させずかつ短時間で完了できるコンクリート建造物補修法を提供することを目的とする。
【0007】
【課題を解決するための手段】
本発明によるコンクリート建造物補修法では、金属製の複数のフレーム(4)と、複数のフレーム(4)を骨格として複数のフレーム(4)の周囲に固定されたコンクリート材(5)とにより形成された基礎部(2)と、基礎部(2)と一体に形成された壁部(3)とを含むコンクリート建造物(1)の壁部(3)に向かってノズル(6)から水流を高速で噴出させて、コンクリート建造物(1)の表層面を破砕する。ハイドロデモリッション工法により、コンクリート建造物(1)に大きな衝撃及び振動が発生せず、フレーム(4)にマイクロクラック等の損傷が発生しない。また、効率的で安全にかつ環境を悪化させずに、コンクリート建造物(1)の表層面を破砕することができる。更にノズル(6)から水流を高速で噴出させて、コンクリート建造物(1)からコンクリート材(5)を厚さ方向に完全に破砕しかつ除去して壁部(3)の一部に開口部(7)を形成する。次に、コンクリート建造物(1)に基礎部(2)と未削部(8)(みはつりぶ)とを残しながら、ノズル(6)を移動して、開口部(7)を帯状に形成することにより、コンクリート材(5)に埋設されたフレーム(4)の一部を開口部(7)内に露出させる。開口部(7)内のコンクリート材(5)は既に除去されているので、開口部(7)内に露出するフレーム(4)を容易に切断することができる。その後、切断により分離したコンクリート材(5)の未削部(8)を除去する。続いて、コンクリート材(5)から露出するフレーム(4)に補強フレーム(9)を固定した後、補強フレーム(9)の周囲にコンクリート材を供給して、コンクリート材を固化させる。このように、コンクリート建造物(1)の使用寿命のある基礎部(2)を残し、改修後もそのまま使用できるので、基礎部(2)を有効に活用し、補修工期を短縮することができる。
【0008】
【発明の実施の形態】
以下、本発明によるコンクリート建造物補修法の実施の形態を図1〜図6について説明する。
【0009】
本実施の形態のコンクリート建造物補修法では、最初に、図1に示すように、金属製の複数のフレーム(4)と、複数のフレーム(4)を骨格として複数のフレーム(4)の周囲に固定されたコンクリート材(5)とにより形成された基礎部(2)と、基礎部(2)と一体に形成された壁部(3)とを含むコンクリート建造物(1)の壁部(3)に向かってウォータジェットのノズル(6)から高速度で水流を噴出させて、ハイドロデモリッション工法によりコンクリート建造物(1)の表層面を破砕する。本実施の形態では、コンクリート建造物(1)は陸橋であり、基礎部(2)は橋梁、橋脚又は橋桁であり、壁部(3)は欄干である。使用するウォータジェットは、直径2〜3mmのノズル(6)から100MPaの圧力を加えた水をコンクリート建造物(1)に向かい、毎分200リットルの流量で噴出する構造を備えている。噴出する水速は、マッハ1〜マッハ7、好適には500m/s〜1000m/sである。図示の例では、複数の鉄筋(4)は、針金等の緊締具又は固定具(11)により互いに連結させて、コンクリート建造物(1)のコンクリート材(5)中に埋設されている。コンクリート建造物(1)にジェット水流を衝突させるので、コンクリート建造物(1)に大きな衝撃及び振動が発生せず、鉄筋(4)にマイクロクラック等の損傷が発生しない。効率的で安全にかつ環境を悪化させずに、コンクリート建造物(1)の表層面を破砕することができる。
【0010】
更にノズル(6)から水流を噴出させて、壁部(3)からコンクリート材(5)を厚さ方向に完全に破砕しかつ除去して、壁部(3)の一部に開口部(7)を形成する。ノズル(6)から噴出する水流のコンクリート建造物(1)に対する衝突面積は極めて小さいが、衝撃力が大きいので、コンクリート建造物(1)の厚さ方向に破砕による開口部(7)を形成して、コンクリート建造物(1)からコンクリート材(5)を完全に破砕しかつ除去することができる。この場合に、コンクリート建造物(1)の後方に防護シート等の防御膜を配置すれば、粉塵の周囲への飛散を完全に防止できる。また、粉塵は、ウォータジェットによる水分を吸収して質量を増加するので、空中に吹き飛ばされた後に、運動エネルギの低下に伴って直ちに落下するので、あまり飛散しない。しかしながら、コンクリート材(5)の破砕屑は乾燥する前に所定の場所で処分することが望ましい。鉄筋(4)の直径をdとすると、開口部(7)内の鉄筋(4)が露出する開口部(7)の幅(L)は、例えば、10d〜50d、好ましくは、25d〜45dの範囲にある。開口部(7)内に露出する鉄筋(4)は、基礎部(2)内に埋設された基礎鉄筋(4)又は基礎鉄骨に連結される。
【0011】
次に、コンクリート建造物(1)に基礎部(2)と未削部(8)(みはつりぶ)とを残しながら、水平方向及び垂直方向にノズル(6)を移動して、未削部(8)と並行に一定の幅かつ一定の長さで、コンクリート材(5)を破砕して、コンクリート材(5)に埋設された鉄筋(4)の一部を帯状に露出させる。ハイドロデモリッション工法では、ノズル(6)の移動によってコンクリート建造物(1)の所望の領域を所望の範囲でコンクリート材(5)を破砕して、開口部(7)を形成することが可能である。ワイヤーソーイング、ウォールソーイング又はドリルソーイング法のように、基礎部(2)を構成するコンクリート材(5)又は鉄筋(4)に衝撃又は振動を与えて、マイクロクラック等の損傷を基礎部(2)に与える弊害を完全に防止することができる。また、耐久性が残存するコンクリート製建造物のベース部をそのまま使用できるので、低資源化を図ることができる。
【0012】
コンクリート建造物(1)の基準平面から一定高さの水平面(12)に沿って露出した鉄筋(4)を切断するとき、コンクリート材(5)は既に除去されているので、コンクリート建造物(1)の基準平面から一定高さの水平面(12)又は基準垂直面から一定距離離間する垂直面(13)に沿って露出した鉄筋(4)を容易に切断することができる。その後、図2に示すように、切断により分離したコンクリート材(5)の未削部(8)にワイヤ(10)を捲回して、未削部(8)を除去する。
【0013】
次に、図3に示すように、コンクリート材(5)から露出する鉄筋(4)にワイヤ等の結束線(11)を巻き付けて、補強鉄筋(補強フレーム)(7)を鉄筋(4)に固定する。
【0014】
最後に、図4に示すように、補強フレーム(9)の周囲にコンクリート材を供給して、コンクリート材を固化させる。また、コンクリート建造物(1)の使用寿命のある基礎部(2)を残し、改修後もそのまま使用できるので、基礎部(2)を有効に活用し、補修工期を短縮することができる。
【0015】
本発明の前記の実施の形態は変更が可能である。例えば、図1では、コンクリート建造物(1)に水平の開口部(7)を形成し、水平面(12)に沿って鉄筋(4)を切断し、未削部(8)を除去する例を示したが、図5及び図6に示すように、コンクリート建造物(1)に垂直の開口部(7)を形成し、垂直面(13)に沿って鉄筋(4)を切断し、未削部(8)を除去してもよい。また、開口部(7)は、一定の幅又は任意の幅を有する長方形、正方形に限定されず、円弧状、波形等種々の形状に形成することができる。更に、鉄筋(4)を使用するコンクリート建造物(1)の代わりに、フレームとして互いに接合された複数の鉄骨又は鉄筋と鉄骨との組み合わせ構造のコンクリート建造物(1)にも本発明を適用することができる。鉄骨を使用して建造されたコンクリート建造物(1)に対して、鉄骨の矩形断面の縦寸法若しくは横寸法の一方をdとすると、フレーム(4)が露出する開口部(7)の幅は、10d〜50d、好ましくは25d〜45dの範囲である。また、陸橋以外のビルディング、競技場、ダム、堰、倉庫、護岸、渠壁等の一般の又は特殊のコンクリート建造物にも本発明を適用することができる。
【0016】
本発明によるコンクリート建造物補修法の実施の形態では、下記の作用効果が得られる。
[1] コンクリート建造物(1)から部分的にコンクリートの一部のみを効率的に破砕するハイドロデモリションでは、コンクリート建造物(1)に機械的衝撃及び振動を与えず、環境適合性を有する。
[2] コンクリート建造物(1)をカッタで機械的に切断して大きな騒音を発生するワイヤーソーイング、ウォールソーイング又はドリルソーイングに比べて、噴出水の水流音のみが発生するウォータジェットは、騒音を著しく低減することができる。
[3] コンクリート建造物(1)に機械的衝撃及び振動を与えないので、再利用するコンクリート建造物(1)部分に、微少な割れ目、クラック等の脆弱部の発生を完全に防ぐことができる。
[4] 基礎部(2)の健全な鉄筋(4)を利用して壁を再構築するため、施工期間を大幅に短縮し、施工費を大幅に低減することができる。
[5] コンクリート建造物(1)の後方に、シート等の防御膜を配置して養生を行えば、ウォータジェットによる粉塵は水分を吸収して質量を増加するので、周囲への飛散を完全に防止でき、低公害で施工できる。
[6] ノズル(6)の遠隔操作による完全自走システム、無人水流破砕が可能となる。
[7] 補修以前のコンクリート建造物(1)と略同等又はそれ以上の強度をコンクリート建造物(1)に与えることができる。
【0017】
【発明の効果】
前記のように、本発明では、コンクリート建造物の基礎部に損傷を与えずにかつ大きな衝撃、振動及び粉塵を発生せずに、コンクリート建造物を補修することができる利点がある。
【図面の簡単な説明】
【図1】 ハイドロデモリッション工法によりコンクリート建造物の表層面を破砕して、水平な開口部を形成する状態を示す斜視図
【図2】 未削部を基礎部から除去する状態を示す斜視図
【図3】 露出フレームに補強フレームを固定する状態を示す斜視図
【図4】 補強フレームの周囲にコンクリート材を供給して再構築されたコンクリート建造物の斜視図
【図5】 ハイドロデモリッション工法によりコンクリート建造物の表層面を破砕して、垂直な開口部を形成する状態を示す斜視図
【図6】 図5に示す未削部を基礎部から除去する状態を示す斜視図
【符号の説明】
(1)・・コンクリート建造物、 (2)・・基礎部、 (3)・・未削部、 (4)・・鉄筋(フレーム)、 (5)・・コンクリート材、 (6)・・ノズル、 (7)・・開口部、 (8)・・未削部、 (9)・・補強フレーム、[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a concrete building repair method capable of repairing a concrete building while ensuring a good working environment without generating mechanical impact.
[0002]
[Prior art]
For example,
[0003]
[0004]
[0005]
[Patent Document 1]
JP-A-9-67942 (2nd page)
[Patent Document 2]
JP 2002-129753 A (page 2)
[Patent Document 3]
JP 2002-180417 A (page 3)
[0006]
[Problems to be solved by the invention]
In the conventional concrete building repair method, since all the concrete at the repair site is removed by the water jet, the repair requires labor and time, and the repair work cannot be completed in a short period of time. Also, for example, when a concrete building is crushed using a sawing and cutting device such as wire sawing, wall sawing or drill sawing, microcracks are produced in healthy reinforcing bars and concrete materials due to large impacts and vibrations generated when the concrete materials are destroyed. In addition to damage such as the above, vibration and noise are generated, and the dust of the concrete material is scattered around, which adversely affects the environment. In order to reinforce the concrete building after cutting the concrete building using the sawing and cutting device, the concrete material is further pierced and an adhesive such as epoxy resin is injected into the formed recess. After that, the reinforcing reinforcing bars are inserted into the recesses and bonded to the recesses by the epoxy resin, so that there is a disadvantage that the mechanical strength is extremely insufficient because the reinforcing bars are not connected to the existing reinforcing bars.
Then, an object of this invention is to provide the concrete building repair method which can be completed in a short time, without generating a big impact and vibration in a concrete building at the time of repair.
[0007]
[Means for Solving the Problems]
In the concrete building repair method according to the present invention, a plurality of metal frames (4) and a concrete material (5) fixed around the plurality of frames (4) using the plurality of frames (4) as a skeleton. Water flow from the nozzle (6) toward the wall (3) of the concrete building (1) including the formed foundation (2) and the wall (3) formed integrally with the foundation (2). The surface of the concrete building (1) is crushed by ejecting at high speed. Due to the hydro-demolition method, large impacts and vibrations do not occur in the concrete building (1), and damage such as microcracks does not occur in the frame (4). Further, the surface layer of the concrete building (1) can be crushed efficiently, safely and without deteriorating the environment. Further, the water flow is ejected from the nozzle (6) at high speed, and the concrete material (5) is completely crushed and removed from the concrete building (1) in the thickness direction, and an opening is formed in a part of the wall (3). Form (7). Next, the nozzle (6) is moved to leave the foundation (2) and the unmachined part (8) (Mihamariburi) in the concrete building (1), and the opening (7) is formed in a strip shape. As a result, a part of the frame (4) embedded in the concrete material (5) is exposed in the opening (7). Since the concrete material (5) in the opening (7) has already been removed, the frame (4) exposed in the opening (7) can be easily cut. Thereafter, the uncut portion (8) of the concrete material (5) separated by cutting is removed. Subsequently, after fixing the reinforcing frame (9) to the frame (4) exposed from the concrete material (5), the concrete material is supplied around the reinforcing frame (9) to solidify the concrete material. In this way, the foundation part (2) with a usable life of the concrete building (1) is left and can be used as it is after the repair, so the foundation part (2) can be used effectively and the repair work period can be shortened. .
[0008]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of a concrete building repair method according to the present invention will be described with reference to FIGS.
[0009]
In the concrete building repair method according to the present embodiment, first, as shown in FIG. 1, a plurality of metal frames (4) and a plurality of frames (4) as a skeleton around a plurality of frames (4). A wall portion of a concrete building (1) including a base portion (2) formed by a concrete material (5) fixed to a wall portion (3) formed integrally with the base portion (2) ( A water stream is ejected from the water jet nozzle (6) at a high speed toward 3), and the surface layer of the concrete building (1) is crushed by the hydro-demolition method. In the present embodiment, the concrete building (1) is an overpass, the foundation (2) is a bridge, a pier or a bridge girder, and the wall (3) is a balustrade. The water jet used has a structure in which water applied with a pressure of 100 MPa is jetted from a nozzle (6) having a diameter of 2 to 3 mm to the concrete building (1) at a flow rate of 200 liters per minute. The water speed to be ejected is Mach 1 to Mach 7, preferably 500 m / s to 1000 m / s. In the illustrated example, the plurality of reinforcing bars (4) are connected to each other by a fastening tool such as a wire or a fixing tool (11) and embedded in the concrete material (5) of the concrete building (1). Since the jet water flow collides with the concrete building (1), the concrete building (1) is not subjected to large impacts and vibrations, and the rebar (4) is not damaged such as microcracks. The surface of the concrete building (1) can be crushed efficiently and safely without deteriorating the environment.
[0010]
Further, a water flow is ejected from the nozzle (6), and the concrete material (5) is completely crushed and removed from the wall (3) in the thickness direction, and an opening (7) is formed in a part of the wall (3). ). Although the impact area of the water flow spouted from the nozzle (6) on the concrete structure (1) is extremely small, the impact force is large, so an opening (7) is formed by crushing in the thickness direction of the concrete structure (1). Thus, the concrete material (5) can be completely crushed and removed from the concrete building (1). In this case, if a protective film such as a protective sheet is arranged behind the concrete building (1), dust can be completely prevented from being scattered around. Moreover, since dust absorbs the water | moisture content by a water jet and increases mass, since it falls immediately with the fall of a kinetic energy after being blown away in the air, it does not scatter very much. However, it is desirable to dispose of the crushed waste of the concrete material (5) at a predetermined place before drying. When the diameter of the reinforcing bar (4) is d, the width (L) of the opening (7) where the reinforcing bar (4) in the opening (7) is exposed is, for example, 10d to 50d, preferably 25d to 45d. Is in range. The reinforcing bar (4) exposed in the opening (7) is connected to the basic reinforcing bar (4) or the basic steel frame embedded in the basic part (2).
[0011]
Next, moving the nozzle (6) horizontally and vertically while leaving the foundation (2) and the unmachined part (8) in the concrete building (1), the unmachined part In parallel with (8), the concrete material (5) is crushed with a certain width and a certain length, and a part of the reinforcing bar (4) embedded in the concrete material (5) is exposed in a strip shape. In the hydro-demolition method, it is possible to crush the concrete material (5) in the desired area of the concrete building (1) by moving the nozzle (6) to form the opening (7). . Like the wire sawing, wall sawing or drill sawing methods, the concrete part (5) or the reinforcing bar (4) constituting the foundation part (2) is subjected to impact or vibration to cause damage such as microcracks (2). It is possible to completely prevent harmful effects on Moreover, since the base part of the concrete structure where durability remains can be used as it is, resource reduction can be achieved.
[0012]
When cutting the rebar (4) exposed along the horizontal plane (12) of a certain height from the reference plane of the concrete building (1), the concrete material (5) has already been removed, so the concrete building (1 The rebar (4) exposed along the horizontal plane (12) having a certain height from the reference plane or the vertical plane (13) spaced a certain distance from the reference vertical plane can be easily cut. Then, as shown in FIG. 2, the wire (10) is wound around the uncut portion (8) of the concrete material (5) separated by cutting, and the uncut portion (8) is removed.
[0013]
Next, as shown in FIG. 3, a binding wire (11) such as a wire is wrapped around the reinforcing bar (4) exposed from the concrete material (5), and the reinforcing bar (reinforcement frame) (7) is wrapped around the reinforcing bar (4). Fix it.
[0014]
Finally, as shown in FIG. 4, the concrete material is supplied around the reinforcing frame (9) to solidify the concrete material. Moreover, since the foundation part (2) with a useful life of the concrete building (1) is left and can be used as it is after the repair, the foundation part (2) can be used effectively and the repair work period can be shortened.
[0015]
The above-described embodiment of the present invention can be modified. For example, in Fig. 1, the horizontal opening (7) is formed in the concrete building (1), the rebar (4) is cut along the horizontal plane (12), and the uncut portion (8) is removed. As shown in FIGS. 5 and 6, a vertical opening (7) is formed in the concrete building (1), the rebar (4) is cut along the vertical surface (13), and uncut. The part (8) may be removed. Further, the opening (7) is not limited to a rectangle or a square having a constant width or an arbitrary width, and can be formed in various shapes such as an arc shape and a waveform. Furthermore, instead of the concrete building (1) using the reinforcing bar (4), the present invention is also applied to a concrete building (1) having a plurality of steel frames joined together as a frame or a combination structure of reinforcing bars and steel frames. be able to. For a concrete structure (1) built using steel, if one of the vertical or horizontal dimensions of the rectangular cross section of the steel frame is d, the width of the opening (7) where the frame (4) is exposed is It is in the range of 10d to 50d, preferably 25d to 45d. In addition, the present invention can be applied to general or special concrete structures such as buildings other than overpasses, stadiums, dams, weirs, warehouses, revetments, and dredging walls.
[0016]
In the embodiment of the concrete building repair method according to the present invention, the following effects are obtained.
[1] Hydrodemolition that efficiently crushes only a part of concrete from the concrete building (1) does not give mechanical shock and vibration to the concrete building (1) and has environmental compatibility.
[2] Compared to wire sawing, wall sawing or drill sawing, where a concrete building (1) is mechanically cut with a cutter to generate a large amount of noise, a water jet that produces only the water flow noise of jet water is less sensitive to noise. It can be significantly reduced.
[3] Because mechanical shock and vibration are not applied to the concrete building (1), it is possible to completely prevent the occurrence of fragile parts such as small cracks and cracks in the reused concrete building (1). .
[4] Since the wall is rebuilt using the sound reinforcement (4) of the foundation (2), the construction period can be greatly shortened and the construction cost can be greatly reduced.
[5] If a protective film, such as a sheet, is placed behind the concrete building (1) and cured, the water jet dust absorbs moisture and increases its mass, so it is possible to completely disperse to the surroundings. It can be prevented and can be constructed with low pollution.
[6] Fully self-propelled system by remote control of nozzle (6), unmanned water flow crushing becomes possible.
[7] The concrete structure (1) can be given a strength substantially equal to or higher than that of the concrete structure (1) before repair.
[0017]
【The invention's effect】
As described above, the present invention has an advantage that the concrete building can be repaired without damaging the foundation of the concrete building and without generating large impact, vibration and dust.
[Brief description of the drawings]
[Fig. 1] A perspective view showing a state where a surface layer of a concrete building is crushed by a hydro-demolition method to form a horizontal opening. [Fig. 2] A perspective view showing a state where an uncut portion is removed from a foundation portion. [Fig. 3] Perspective view showing the state in which the reinforcing frame is fixed to the exposed frame [Fig. 4] Perspective view of the concrete structure reconstructed by supplying concrete around the reinforcing frame [Fig. 5] Concrete by the hydro-demolition method FIG. 6 is a perspective view showing a state in which a surface layer surface of a building is crushed to form a vertical opening. FIG. 6 is a perspective view showing a state in which an uncut portion shown in FIG. 5 is removed from a base portion.
(1) ... Concrete building, (2) ... Foundation, (3) ... Uncut part, (4) ... Reinforcement (frame), (5) ... Concrete material, (6) ... Nozzle , (7) ・ ・ Opening, (8) ・ ・ Uncut part, (9) ・ ・ Reinforcement frame,
Claims (5)
更にノズルから水流を高速で噴出させて、壁部からコンクリート材を厚さ方向に完全に破砕しかつ除去して壁部の一部に開口部を形成する過程と、
コンクリート建造物に基礎部と未削部(みはつりぶ)とを残しながら、ノズルを移動して、開口部を帯状に形成することにより、コンクリート材に埋設されたフレームの一部を開口部内に露出させる過程と、
開口部内に露出する複数のフレームを切断して、未削部を基礎部から分離する過程と、
分離したコンクリート材の未削部を除去する過程と、
コンクリート材から露出するフレームに補強フレームを固定する過程と、
補強フレームの周囲にコンクリート材を供給して、コンクリート材を固化させる過程とを含むことを特徴とするコンクリート建造物補修法。A concrete structure including a plurality of metal frames, a foundation portion formed of a concrete material fixed around the plurality of frames using the plurality of frames as a skeleton, and a wall portion formed integrally with the foundation portion The process of crushing the surface layer of the wall by ejecting a water flow from the nozzle at high speed toward the wall of
Furthermore, a process of ejecting a water flow from the nozzle at high speed to completely crush and remove the concrete material from the wall in the thickness direction to form an opening in a part of the wall,
A part of the frame embedded in the concrete material is placed in the opening by moving the nozzle and forming the opening in a band shape while leaving the foundation part and the uncut part in the concrete building. The process of exposing,
Cutting a plurality of frames exposed in the opening, and separating the uncut portion from the base portion;
The process of removing the uncut parts of the separated concrete material;
Fixing the reinforcing frame to the frame exposed from the concrete material;
A method for repairing a concrete structure, comprising: supplying concrete material around a reinforcing frame to solidify the concrete material.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003031580A JP3979646B2 (en) | 2003-02-07 | 2003-02-07 | Concrete building repair method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003031580A JP3979646B2 (en) | 2003-02-07 | 2003-02-07 | Concrete building repair method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004239007A JP2004239007A (en) | 2004-08-26 |
| JP3979646B2 true JP3979646B2 (en) | 2007-09-19 |
Family
ID=32958120
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2003031580A Expired - Fee Related JP3979646B2 (en) | 2003-02-07 | 2003-02-07 | Concrete building repair method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3979646B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4866106B2 (en) * | 2006-03-07 | 2012-02-01 | 株式会社フジタ | Repair method for concrete structures |
| JP4926851B2 (en) * | 2007-06-26 | 2012-05-09 | 東亜建設工業株式会社 | Repair method of elevated floor slab |
| JP5182929B2 (en) * | 2008-05-21 | 2013-04-17 | 大成建設株式会社 | Reinforcing method for existing concrete structures |
| JP6715230B2 (en) * | 2017-12-08 | 2020-07-01 | 飛島建設株式会社 | Method of removing slab of composite girder bridge and reinforcing member used for it |
| JP2024134234A (en) * | 2023-03-20 | 2024-10-03 | 鹿島建設株式会社 | Methods for reinforcing existing concrete structures |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH01102174A (en) * | 1987-10-14 | 1989-04-19 | Yokogawa Medical Syst Ltd | Method of boring and repairing wall in building |
| JPH08296209A (en) * | 1995-04-26 | 1996-11-12 | Mitsubishi Heavy Ind Ltd | Method for reinforcing foundation part of elevated bridge |
-
2003
- 2003-02-07 JP JP2003031580A patent/JP3979646B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004239007A (en) | 2004-08-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3979646B2 (en) | Concrete building repair method | |
| JP2006063732A (en) | Seismic reinforcement structure | |
| CN106049503B (en) | The preprocess method of reinforced concrete brace demolition blasting in a kind of foundation ditch | |
| CN213898233U (en) | Underground construction reinforced structure | |
| JP5795232B2 (en) | Dismantling method | |
| JPH07138911A (en) | Expansion joint removal method for expansion joints of concrete bridges | |
| JP3751258B2 (en) | Reinforcement method for concrete structures | |
| JP6338860B2 (en) | Structure crushing method | |
| JP6715230B2 (en) | Method of removing slab of composite girder bridge and reinforcing member used for it | |
| KR100583880B1 (en) | Foundation construction method using concrete pile | |
| JP4666639B2 (en) | Guard fence device | |
| JP2005023693A (en) | How to repair incomplete grout | |
| JP3371131B2 (en) | Expansion method of reinforced concrete structures | |
| JP6088883B2 (en) | Connection method and connection structure of fiber reinforced pile material for shield excavation | |
| JPH03136812A (en) | Concrete cutter with two blades | |
| CN205688447U (en) | Reinforced concrete brace in a kind of foundation ditch based on demolition blasting pretreatment | |
| JP3030638U (en) | Steel plate structure for seismic reinforcement of concrete piers | |
| JP2005036636A (en) | Method for repairing masonry | |
| JP6770878B2 (en) | Concrete processing method, crushing jig, concrete processing system | |
| CN213625232U (en) | Suspension casting beam for preventing construction equipment and construction residues from falling under beam | |
| JP2004060388A (en) | Permeable sand control dam | |
| JP2002242125A (en) | Prebeam girder web fabrication method | |
| CN208899328U (en) | A kind of assembled type platform guardrail upright pole convenient for Fast Installation | |
| JP2025063401A (en) | How to remove the deck | |
| JPH0334527B2 (en) |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060206 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070615 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070625 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070625 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100706 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100706 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110706 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110706 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120706 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120706 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130706 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |