JP4044858B2 - Seismic isolation building - Google Patents
Seismic isolation building Download PDFInfo
- Publication number
- JP4044858B2 JP4044858B2 JP2003067052A JP2003067052A JP4044858B2 JP 4044858 B2 JP4044858 B2 JP 4044858B2 JP 2003067052 A JP2003067052 A JP 2003067052A JP 2003067052 A JP2003067052 A JP 2003067052A JP 4044858 B2 JP4044858 B2 JP 4044858B2
- Authority
- JP
- Japan
- Prior art keywords
- plate
- decorative member
- waterproof decorative
- building
- seismic isolation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Building Environments (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Description
【0001】
【発明の属する技術分野】
この発明は免震建物に関する。
【0002】
【従来の技術】
免震建物は、通常、地面に固定された下部構造体の上に免震装置を介して上部構造体が設置されたものである。
ここで使用される免震装置は、スプリングバネやゴム等の弾性体や、弾性体と粘稠な液体を組み合わせたダンパーや、平行な板体の間に設けた球状体からなるもの等であって、地震が発生して下部構造体が地面と共に水平方向に振動すると、スプリングバネやゴムの弾性体が変形したり、ダンパーの弾性体と粘稠な液体の振動サイクルの差によって制振したり、球状体が下部構造体の上を転がる等して、この地震の振動を吸収し、上部構造体を振動し難くするものである。この際、下部構造体と上部構造体が相対的に移動する。
【0003】
このように下部構造体と上部構造体が相対的に移動する構造になっているので、下部構造体と上部構造体とが分離していて、必ず、下部構造体と上部構造体の間に隙間が存在する。
そして、この下部構造体と上部構造体の間に存在する隙間が見えると、この隙間を通して内部の免震装置が外側から見えて見苦しいし、この隙間に雨や土や砂等が侵入し、免震装置が十分に稼働しない危険性がある。
【0004】
かかる問題を解決した免震建物としては種々ある。例えば、特許文献1〜特許文献7に記載されている建物が知られている。
先ず、特許文献1と特許文献2に記載されている免震建物を、図7を参照しながら説明すると、免震建物105は、地面101に固定されている下部構造体としての基礎100の上に、免震装置102を介して、架台103に支持された上部構造体としての建物本体104が設置され、下部構造体(基礎)100と上部構造体(建物本体)104の間の隙間を覆う側板(化粧板、カバー)106が架台103の側部に軸部106aを回動中心として揺動可能に設けられている建物である。
【0005】
この免震建物105では、図7(イ)に示すように、平常時は、基礎(下部構造体)100と建物本体(上部構造体)104の間に存在する隙間及び免震装置102がこの側板106によって覆われて、下部構造体100と上部構造体104の間に存在する隙間が見え難くいし、隙間に雨や土や砂等が侵入し難くなっている。
【0006】
そして、地震が発生し、基礎(下部構造体)100と建物本体(上部構造体)104の相対位置が移動すると、図7(ロ)に示すように、側板106が軸部106aを回動中心にして、下部構造体100と上部構造体104の相対位置の移動に応じて揺動して、側板106が破損しないようになっている。
【0007】
また、特許文献3に記載されている免震建物は地面より低い位置に下部構造体である基礎を設け、この基礎の上に免震装置を介して上部構造体である建物本体が据え付けられた建物であって、この建物本体と周囲の地面との間に溝が形成されていている。そして、建物本体の下部外周面には溝蓋本体が、溝の上方を覆い、更に、延長されて地面の上方に大きく突出する状態に取り付けられ、溝の内周面には補助溝蓋が、溝蓋本体の下方位置に、溝の中央部まで突出した状態に回動自在に取り付けられていて、建物本体が近づくと、補助溝蓋に取り付けられているスプリングバネの作用で補助溝蓋が下方に回動するようになっている。この溝蓋本体と補助溝蓋とで溝の内部に存在する免震装置等が見え難くなっている。
【0008】
地震が発生して基礎と建物本体の相対的位置が変化すると、溝蓋本体が地面の上方を略水平に移動する。そして、建物本体が境界を越えるように大きく振動しても、補助溝蓋が下方に回動して、建物本体に衝突しないようになっている。
【0009】
また、特許文献4と特許文献5に記載されている免震建物では、上部構造体には、外側方向に突出したはね出し板を設け、玄関ステップの上を滑る支持機構でこのはね出し板の先端部を支持するようにしたものであって、このはね出し板で基礎と免震装置等が見えなくなっている。そして、地震が発生して上部構造体と地面に固定されている下部構造体との間の相対的位置が変化すると、上部構造体に取り付けられているはね出し板が地面に固定されている玄関ステップの上を滑るようになっている。
【0010】
また、特許文献6に記載されている免震建物では、下部構造体の上に免震装置を介して上部構造体が設置された免震建物であって、上部構造体の下部に略水平に外側方向に突出した犬走りを設け、この犬走りの先端部に対応する地面に化粧壁を立設し、この犬走りと化粧壁とで免震装置等が見え難くなっている。
【0011】
また、特許文献7に記載されている免震建物では上部構造体には、周囲に下方に突出した上側化粧体が設けられ、下部構造体には、上側化粧体と対峙する位置に下側化粧体が設けられていて、この上側化粧体と下側化粧体とで床下空間を隠すようになっている。
【0012】
【特許文献1】
特開2000−234394号公報
【特許文献2】
特開2001−262864号公報
【特許文献3】
特開2000−120187号公報
【特許文献4】
特開2000−352221号公報
【特許文献5】
特開2001−73473号公報
【特許文献6】
特開2000−320184号公報
【特許文献7】
特開2001−182366号公報
【0013】
【発明が解決しようとする課題】
しかし、上記特許文献1〜7に記載されている免震建物に使用される上部構造体と下部構造体の間の隙間を覆う部材、(特許文献1及び2に記載されている側板、特許文献3に記載されている溝蓋本体、特許文献4及び特許文献5に記載されているはね出し板、特許文献6に記載されている犬走りと化粧壁、特許文献7に記載されている上側化粧体と下側化粧体)は、すべて露出している。
このように上部構造体と下部構造体の間の隙間を覆う部材が露出していると、劣化し易いために、外観品質と高い耐久性を要求され、コストの高い部材となってしまう。
【0014】
また、特許文献1及び2に記載されている免震建物では、上部構造体に対して側板を揺動可能に取り付ける必要があるので、複雑な構造になりコストが上昇する。又、側板を揺動可能に取り付けると、通常の自然風でも側板が揺動してバタツキ音が発生する。これを防止しようと、この揺動を抑制するダンパー機構を設けと、構造が複雑になり製造コストが上昇するという問題がある。又、子供や犬、猫等が側板を開いていたずらをする恐れや風で側板が開いたときに上部構造体と下部構造体の間の隙間から異物が侵入する恐れがあり免震装置の動作に影響を及ぼす可能性がある。
【0015】
また、特許文献7を除いて上部構造体と下部構造体の間を覆うすべての部材は、建物本体の下端から外側方向に突出しているために、この突出分を考慮して建物の配置を計画する必要があり、敷地利用への影響が大きい。
そこで、この発明の目的は、上部構造体と下部構造体の間を覆う部材が、露出したり、外側方向に大きく突出しない状態に取り付けられた免震建物を提供することである。
【0016】
【課題を解決するための手段】
本発明は、上記課題を解決するためになされたものであって、請求項1に記載の発明は、地面に固定された下部構造体の上に免震装置を介して上部構造体が設置された免震建物であって、前記下部構造体には、前記上部構造体の外周部分に対応する下方位置に立上部材が設けられ、この立上部材の上端部には、上部構造体の下方に内側方向に略水平に突出した板体部材が設けられ、この板体部材と上部構造体の間の隙間が小さくなされているものである。
【0017】
この請求項1記載の立上部材は、建物本体の周囲に建物本体と地面との間に設けられるものであって、壁であってもよいし、基礎であってもよい。一般に、建物の周囲には、通常、基礎があるので、この基礎を利用することが好ましい。そして、基礎の場合には、請求項2記載のように基礎の上に連結板を取り付けると、基礎と建物本体との間に連結板の高さと略等しい空間が形成され、この空間に免震装置を設けることができるので好ましい。
【0018】
即ち、請求項2記載の発明は、請求項1記載の発明に係り、前記立上部材は、前記板体部材と、基礎と、この基礎と板体部材とを連結する連結板とからなるものである。
【0019】
この請求項2記載の基礎は、適宜でよいが、通常、コンクリート製である。又、板体部材と連結板も適宜でよいが、金属製が好ましい。そして、この板体部材と連結部材は一体になっていてもよいし、連結されたものであってもよい。
【0020】
請求項3記載の発明は、請求項1記載の発明に係り、前記上部構造体には、上部構造体の下部外側面から板体部材の上端より若干高い位置までを覆う上側防水化粧部材が設けられ、前記下部構造体には、立上部材の上端と略等しい高さより下の立上部材の外側面を覆う下側防水化粧部材が設けられ、この下側防水化粧部材の上端と上側防水化粧部材の下端が対峙する状態に下側防水化粧部材と上側防水化粧部材が配置されているものである。
【0021】
請求項4記載の発明は、請求項3記載の発明に係り、前記上側防水化粧部材が上部構造体に着脱自在に取り付けられ、前記下部防水化粧部材と板体部材がそれぞれ別個に立上部材に着脱自在に取り付けられているものである。
【0022】
(作用)
請求項1記載の発明では、地面に固定された下部構造体の上に免震装置を介して上部構造体が設置された免震建物であって、前記下部構造体には、前記上部構造体の外周部分に対応する下方位置に立上部材が設けられ、この立上部材の上端部には、上部構造体の下に内側方向に略水平に突出した板体部材が設けられ、この板体部材と上部構造体の間の隙間が小さくなされているので、上部構造体と下部構造体に設けられている板体部材との間に存在する隙間は、小さく、しかも、内側方向に略水平に長く、この隙間から内部の免震装置が見え難いし、雨、土、砂等が侵入し難い。
【0023】
そして、この板体部材は、立上部材から上部構造体の内側方向に略水平に突出していて、外側に顕れないので、劣化し難い。従って、この板体部材を安価な材料で製造することができる。
また、揺動可能に取り付けた側板がないので、側板のバタツキ音が発生しないし、子供や犬、猫が側板を開く恐れがない。
【0024】
請求項2記載の発明では、請求項1記載の発明に係り、前記立上部材は、前記板体部材と、基礎と、この基礎と板体部材とを連結する連結板とからなるので、基礎と上部構造体の間には連結板の高さに略等しい空間が形成され、この空間と略等しい高さの免震装置を基礎に設けることができ、便利である。又、板体部材と連結板とを連結する構造であると、基礎に予め連結板を取り付け、この連結板に板体部材を連結すればよく、板体部材を直接コンクリート等の基礎に取り付けるより、基礎に取り付け易くなる。
【0025】
請求項3記載の発明では、請求項1記載の発明に係り、前記上部構造体には、上部構造体の下部外側面から板体部材の上端より若干高い位置までを覆う上側防水化粧部材が設けられ、前記下部構造体には、立上部材の上端と略等しい高さより下の立上部材の外側面を覆う下側防水化粧部材が設けられ、この下側防水化粧部材の上端と上側防水化粧部材の下端が対峙する状態に下側防水化粧部材と上側防水化粧部材が配置されているので、上側防水化粧部材と下側防水化粧部材で覆われている下部構造体と上部構造体と間に存在する隙間と板体部材が見え難い。
【0026】
従って、この隙間の内側にある免震装置が更に見難いし、この部分から雨や土や砂等が更に侵入し難く、この隙間の内側に直射日光が入らなくなり、内部に存在する板体部材等が更に劣化し難くなる。又、この上側防水化粧部材と下側防水化粧部材を防水性と意匠性に優れたものにすることにより、この隙間部分が美麗になるし、内側に雨水が侵入し難い。
【0027】
また、上側防水化粧部材は板体部材の上端より若干高い位置までを覆っているだけであるので、大きな地震が発生して、上部構造体が基礎の内側方向に大きく移動し、上側防水化粧部材が屋内側にある立上部材を越えることがあっても、立上部材の上端より高い上側防水化粧部材は、立上部材に衝突しない。
【0028】
また、下側防水化粧部材は立上部材の上端と略等しい高さより下の立上部材の外側面を覆っているだけであるので、大きな地震が発生して、上部構造体が基礎の外側方向に大きく移動し、その結果、下側防水化粧部材が上部構造体の内側に移動しても、下側防水化粧部材は、立上部材の上端と略等しい高さより下の立上部材の外側面を覆っているだけで、立上部材より低く、従って、立上部材より高い上部構造体が下側防水化粧部材に衝突しない。
【0029】
請求項4記載の発明では、上側防水化粧部材が上部構造体に着脱自在に取り付けられ、前記下側防水化粧部材と板体部材がそれぞれ別個に立上部材に着脱自在に取り付けられているので、長期間使用し、上側防水化粧部材、下側防水化粧部材、板体部材が劣化しても、劣化した部材のみを取り外して簡単に取り替えることができる。
【0030】
【発明の実施の形態】
以下、本発明の実施の形態を実施例で説明する。
(実施例)
図1〜図6は本発明をユニット建物に適用した一実施例を示すもので、図1は、ユニット建物である免震建物を示す斜視図、図2は、免震建物の下部構造体と上部構造体の連結部分を示す断面図、図3は、地震時に図2に示す免震建物の建物本体が基礎の内側方向に大きく移動した状態を示す断面図、図4は、免震建物の免震装置が取り付けられている部分を示す断面図、図5は、図2に示す免震建物を判り易く説明するために主要部のみを示すもので、(イ)は通常の状態を示す模式図、(ロ)は建物本体が基礎の内側に大きく移動したときの状態を示す模式図、(ハ)は建物本体が基礎の外側に大きく移動したときの状態を示す模式図、図6は、建物ユニットを示す一部切欠斜視図である。
【0031】
図1〜図6において、Hはユニット建物である免震建物であり、この免震建物Hは図1〜図5に示すように、地面に固定されている下部構造体2の上に免震装置3を介して上部構造体4が設置されたものである。
下部構造体2は、地面に固定されている基礎5、束及び基礎5や束に付属しているもの等のように地面に固定されるものをいう。
【0032】
基礎5は図2及び図3に示すように、プレキャストコンクリート製であり、地面1に据え付けられている。
なお、この基礎5は後述の建物ユニット8を架け渡して据えつけることができるように、建物ユニット8の両側の下方位置に設けられてる。従って、複数個の建物ユニット8が据え付けられた上部構造体4の外周部分だけでなく、中央部分にも基礎5が存在する。
【0033】
そして、上部構造材の外周部分に対応する下方位置には、図2及び図3に示すように、基礎5と、連結板6と、板体部材7とからなる立上部材Aが設けられている。即ち、基礎の5の上には連結板6が設けられ、この連結板6の先端には板体部材7が設けられている。
【0034】
連結板6は、厚み2.3mmの合金(ZAM)製の板2枚をL字形に成形したものであって、このL字形の一方の片61をビス65で基礎5の屋内側面に取り付けられていて、このビス65を螺出することにより連結板6を取り外すことができるようになっている。即ち、着脱自在になっている。
【0035】
なお、この連結板6の他方の片62の上端には板体部材7を取り付けるためのL字形の取付金具63が溶接で取り付けられているし、基礎5とL字形の一方の片61との隙間から雨水が侵入しないように、コールタール等の液状の防水剤を含ませたウレタン樹脂シート69が基礎5と一方の片61のコーナーに貼り付けられている。
【0036】
板体部材7は、厚み2.3mmのZAM製の板であって、連結板6の他方の片に溶接されているL字形の取付金具63にビス75で取り付けられていて、このビス75を螺出することにより板体部材7を取り外すことができるようになっている。即ち、着脱自在になっている。
そして、この板体部材7は外側縁が基礎5の上面の略中心線から内側方向に長く突出した状態に取り付けられている。従って、後述するように、上方に上部構造体4を据え付けると、この板体部材7は上部構造体4の下方に位置し、内側方向に大きく突出している。そして、この上部構造体4と板体部材7との間には、極めて小さいスリット状の略水平な隙間Sが形成される。
【0037】
この基礎5の屋外側上面にアルミニウム製の下側防水化粧部材55が取り付けられている。
この下側防水化粧部材55の上端は板体部材7の上端と略同じ高さになっていて、この下側防水化粧部材55が板体部材7と基礎5の上端部とを覆った状態になっている。
【0038】
免震装置3は、球状体を有する免震装置31と図示しないオイルダンパーの2種類が使用されている。球状体を有する免震装置31は、図4に示すように、上板32と下板33との間に設けられた球体34とからなる。そして、上板32と下板33の対面は略中央が外側に窪んだ球面となっていて、通常は、この窪んだ球面の略中央に球体33が位置していて、地震が発生して上板32や下板33に略水平に移動する力が加わると、球体34が回転して上板32と下板33が相対的位置が略水平方向にに移動する構造になっている。
【0039】
そして、後述の建物ユニット8が架け渡されて据え付けられる基礎5の上に固定台35が架け渡されて取り付けられ、この固定台35の上に球状体を有する複数個の免震装置31が据え付けられている。
なお、図示しないオイルダンパーの免震装置も固定台35の上に設けられている。この複数個の球状体を有する免震装置31とオイルダンパーは、この上方に据えつけられる建物ユニット8の下方に略均等に配置される。
【0040】
この免震装置8は、地震が発生すると、上板32の上方の上部構造体4と下板33の下方の下部構造体2との相対的位置が変化するが、地震が終了すると、免震装置3(図示しないオイルダンパーと球状体を有する免震装置31)の作用で、元の状態に戻るようになっている。
上部構造体4は、架台41と、この架台41の上に据え付けられた1階の9個の建物ユニット8と、この9個の建物ユニット1の上に据え付けられた2階の9個の建物ユニット8と、この2階の建物ユニット1の上に取り付けられた屋根パネル99とからなる。
【0041】
この際使用される建物ユニット8は、図6に示すように、矩形状の四隅に立設した4本の鋼製四角筒状体の柱81と、この4本の柱81の下端部を矩形状の辺に沿って連結した4本の鋼製断面コ字形長尺体の床梁82と、この4本の柱81の上端部を矩形状の辺に沿って連結した4本の鋼製断面コ字形長尺体の天井梁83からなる骨格を有する。
【0042】
そして、建物ユニット8は、この骨格の相対する床梁82に鋼製四角筒状体の床小梁84が差し渡され、この床小梁84の上に木製の床根太85が取り付けられ、この床根太85の上にパーチクルボードの床面材86が取り付けられて床が形成され、骨格の相対する天井梁83に木製の天井野縁87が差し渡され取り付けられ、この天井野縁87の下面に石膏ボードの天井面材88が取り付けられて天井が形成されたものである。
【0043】
また、外壁を設ける場所には床梁82と天井梁83との間に間柱89が差し渡され、この間柱89に、図2及び図3に一部が示されている外壁パネル9と図示しない内壁パネルが取り付けられ、この外壁パネル9と内壁パネルとの間に図示しないグラスウールの断熱材が取り付けられて外壁が形成されている。
【0044】
外壁パネル9は矩形状の厚み略12mmの硬質木片セメント板の外壁面材91と、この外壁面材91の周囲に設けられた鋼製四角筒状体を矩形状に組み立てた枠92と、この枠両側の枠92に差し渡された図示しない鋼製四角筒状体の桟93とからなる。
そして、複数個の免震装置3の上にそれぞれ免震装置固定部材36が取り付けられ、この複数個の免震装置固定部材36と図示しないオイルダンパーの上に架台41が架け渡されて据え付けられ、この架台41の上に工場で製造した建物ユニット8が据え付けられている。
【0045】
上部構造体2の外周部分の下方に顕れている架台41の側面には、屋外側上部にアルミニウム製の上側防水化粧部材45が取り付けられている。
この上側防水化粧部材45の上端は、固定材39の上端と略同じ高さで、下端が下部構造体2の上端より若干上方の高さとなっている。
そして、この上側防水化粧部材45の下端と下側防水化粧部材55と上端とは対峙するように上側防水化粧部剤45と下側防水化粧部剤55が配置されている。
【0046】
この上側防水化粧部材45と下側防水化粧部材55はアルミニウム製で意匠性と防水性に優れたものである。
屋根パネル99は従来の折版屋根パネルと略同じであるので、説明を省略する。
【0047】
次に、この免震建物Hの施工方法及び作用について説明する。
工場で建物ユニット8、屋根パネル99、免震装置3等を製造し、施工現場にこれ等を運搬する。
施工現場では、予め地面1に基礎5を設けおく。そして、上部構造体4の外周部分の下方の基礎5には連結板6を取り付け、この連結板6の上端に板体部材7を取り付けて立上部材Aを設けたり、基礎5に下側防水化粧部材55を取り付ける。
【0048】
また、建物ユニット8を架け渡して取り付ける予定の基礎5の上に固定台34を架け渡して取り付け、この固定台34の上に球状体を有する免震装置31や図示しないオイルダンパー等の免震装置3を据え付け、この免震装置3とオイルダンパーをビス38で固定する。
次に、この球状体を有する免震装置31の上に免震装置固定部材36を取り付け、ビス39で固定して、このオイルダンパーと免震装置固定部材36の上面を略同じにする。
【0049】
この免震固定部材36とオイルダンパーの上に架台41を取り付け、ボルト・ナット42で固定する。
そして、この免震装置固定部材36とオイルダンパーの上に建物ユニット8を据え付け、ボルト49で固定する。
このようにして、9個の建物ユニット8を据え付けて1階を形成し、この1階の建物ユニット8の上に9個の建物ユニット8を据え付けて2階を形成し、この2階の建物ユニット8の上に屋根パネル99を取り付けて屋根99を形成し、架台41の屋外側上部に上側防水化粧部材45を取り付ける。最後に、その他の種々な仕上げを行うと、免震建物Hが完成する。
【0050】
このようにして完成した免震建物Hは、地面1に固定された下部構造体2の上に免震装置3を介して上部構造体4が設置された建物である。
そして、この免震建物Hの下部構造体2には、上部構造体4の外周部分に対応する下方位置に立上部材Aが設けられ、この立上部材Aの上端部には、上部構造体4の下に内側方向に略水平に突出した板体部材7が設けられている。
【0051】
この板体部材7と上部構造体4の間の隙間は小さく、しかも、内側方向に略水平に長くなっていて、この隙間から内部の免震装置が見え難いし、雨、土、砂等が侵入し難くなっているし、この板体部材7は、立上部材Aから上部構造体4の内側方向に略水平に突出していて、外側に顕れないので、劣化し難く、この板体部材7を安価な材料で製造することができる。
【0052】
更に、上部構造体4には、上部構造体4の下部外側面から板体部材7の上端より若干高い位置までを覆う上側防水化粧部材45が設けられ、下部構造体2には、立上部材7の上端と略等しい高さから下の立上部材Aの外側面を覆う下側防水化粧部材55が設けられ、この下側防水化粧部材55の上端と上側防水化粧部材45の下端が対峙する状態に下側防水化粧部材55と上側防水化粧部材45が配置されているので、上側防水部化粧部材35と下側防水化粧部材55で覆われている下部構造体2と上部構造体4と間に存在する隙間や板体部材7が見え難い。従って、従って、免震装置が更に見難くなっているし、この部分から雨や土や砂等が更に侵入し難く、この隙間の内側に直射日光が入らなくなり、内部に存在する板体部材等が更に劣化し難くなっている。
【0053】
また、この上側防水化粧部材45と下側防水化粧部材55は防水性と意匠性に優れていて、この隙間部分が美麗になるし、内側に雨水が入り難い。
また、上側防水化粧部材45は板体部材7の上端より若干高い位置までを覆っているだけであるので、大きな地震が発生して、図5(ロ)に示すように、上部構造体4が基礎5の内側方向に大きく移動し、上側防水化粧部材45が屋内側にある立上部材Aを越えることがあっても、立上部材Aの上端より高い上側防水化粧部材45は、立上部材Aに衝突しない。
【0054】
また、下側防水化粧部材55は立上部材Aの上端と略等しい高さより下の立上部材Aの外側面を覆っているだけであるので、大きな地震が発生して、図5(ハ)に示すように、上部構造体4が基礎の外側方向に大きく移動し、その結果、下側防水化粧部材55が上部構造体4の内側に移動しても、下側防水化粧部材55は、立上部材Aの上端と略等しい高さより下の立上部材Aの外側面を覆っているだけで、立上部材Aより低く、従って、立上部材より高い上部構造体55が下側防水化粧部材55に衝突しない。
【0055】
また、上側防水化粧部材45が上部構造体4に着脱自在に取り付けられ、前記下側防水化粧部材55と板体部材7がそれぞれ別個に立上部材Aに着脱自在に取り付けられているので、長期間使用し、上側防水化粧部材45、下側化粧部材55、板体部材7が劣化しても、劣化した部材のみを取り外して簡単に取り替えることができる。
【0056】
また、この立上部材Aは、板体部材7と、基礎5と、連結板6とからなるので、板体部材7の上に上部構造体4が設けられているので、基礎5と上部構造体4の間には連結板6の高さに略等しい空間が形成され、この空間と略等しい高さの免震装置3を基礎に設けることができ、便利である。又、板体部材7と連結板6がビス75で連結されているので、予め、連結板6を基礎に取り付けていて、この連結板6に板体部材7を取り付ければよく、板体部材7を基礎5に取り付け易い。
【0057】
【発明の効果】
以上説明してきたように、請求項1に記載の発明は、地面に固定された下部構造体の上に免震装置を介して上部構造体が設置された免震建物であって、前記下部構造体には、前記上部構造体の外周部分に対応する下方位置に立上部材が設けられ、この立上部材の上端部には、上部構造体の下方に内側方向に略水平に突出した板体部材が設けられ、この板体部材と上部構造体の間の隙間が小さくなされているから、上部構造体と上部構造体の板体部材との間に存在する隙間は、小さく、しかも、内側方向に略水平に長く、この隙間から内部の免震装置が見え難いし、雨、土、砂等が侵入し難い。又、この板体部材は、上部構造体の内側方向に略水平に突出していて、外側に顕れず、劣化し難い。従って、この板体部材を安価な材料で製造することができる。
【0058】
請求項2記載の発明は、請求項1記載の発明に係り、前記立上部材は、前記板体部材と、基礎と、この基礎と板体部材とを連結する連結板とからなるから、基礎と上部構造体の間には連結板の高さに略等しい空間が形成され、この空間と略等しい高さの免震装置を基礎に設けることができ、便利である。
【0059】
請求項3記載の発明は、請求項1記載の発明に係り、前記上部構造体には、上部構造体の下部外側面から板体部材の上端より若干高い位置までを覆う上側防水化粧部材が設けられ、前記下部構造体には、立上部材の上端と略等しい高さより下の立上部材の外側面を覆う下側防水化粧部材が設けられ、この下側防水化粧部材の上端と上側防水化粧部材の下端が対峙する状態に下側防水化粧部材と上側防水化粧部材が配置されているから、上側防水化粧部材と下側防水化粧部材で覆われている下部構造体と上部構造体と間に存在する隙間と板体部材が見え難い。従って、この隙間の内側にある免震装置が更に見難いし、この部分から雨や土や砂等が更に侵入し難く、この隙間の内側に直射日光が入らなくなり、内部に存在する板体部材等が更に劣化し難くなる。又、この上側防水化粧部材と下側防水化粧部材を防水性と意匠性に優れたものにすることにより、この隙間部分が美麗になるし、内側に雨水が侵入し難い。
【0060】
また、上側防水化粧部材は板体部材の上端より若干高い位置までを覆っているだけであり、下側防水化粧部材は立上部材の上端と略等しい高さより下の立上部材の外側面を覆っているだけであるので、大きな地震が発生して、上部構造体が基礎の内側方向や外側方向に大きく移動しても、立上部材の上端より高い上側防水化粧部材は、立上部材に衝突しないし、下側防水化粧部材は、立上部材より低く、立上部材より高い上部構造体が下側防水化粧部材に衝突しない。
【0061】
請求項4記載の発明は、上側防水化粧部材が上部構造体に着脱自在に取り付けられ、前記下側防水化粧部材と板体部材がそれぞれ別個に立上部材に着脱自在に取り付けられているから、長期間使用し、上側防水化粧部材、下側防水化粧部材、板体部材が劣化しても、劣化した部材のみを取り外して簡単に取り替えることができる。
【図面の簡単な説明】
【図1】本発明をユニット建物に適用した一実施例を示すもので、ユニット建物である免震建物を示す斜視図である。
【図2】免震建物の下部構造体と上部構造体の連結部分を示す断面図である。
【図3】地震時に図2に示す免震建物の建物本体が土台の内側方向に大きく移動した状態を示す断面図である。
【図4】免震建物の免震装置が取り付けられている部分を示す断面図である。
【図5】図2に示す免震建物を判り易く説明するために主要部のみを示すもので、(イ)は通常の状態を示す模式図、(ロ)は建物本体が土台の内側に大きく移動したときの状態を示す模式図、(ハ)は建物本体が土台の外側に大きく移動したときの状態を示す模式図である。
【図6】建物ユニットを示す一部切欠斜視図である。
【図7】従来の免震建物の一例の主要部を示す模式図である。
【符号の説明】
H 免震建物
S 隙間
A 立上部材
1 地面
2 下部構造体
3 免震装置
4 上部構造体
45 上側防水化粧材
5 基礎
55 下側防水化粧材
6 連結板
7 板体部材
8 建物ユニット[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a seismic isolation building.
[0002]
[Prior art]
A base-isolated building is usually a structure in which an upper structure is installed on a lower structure fixed to the ground via a base isolation device.
The seismic isolation device used here is an elastic body such as a spring spring or rubber, a damper that combines an elastic body and a viscous liquid, or a spherical body provided between parallel plates. When an earthquake occurs and the lower structure vibrates horizontally with the ground, the spring spring or rubber elastic body is deformed, or the vibration is controlled by the difference in vibration cycle between the elastic body of the damper and the viscous liquid. The spherical body rolls on the lower structure to absorb the vibration of this earthquake and make it difficult for the upper structure to vibrate. At this time, the lower structure and the upper structure move relatively.
[0003]
Since the lower structure and the upper structure are relatively moved in this way, the lower structure and the upper structure are separated from each other, and there is always a gap between the lower structure and the upper structure. Exists.
If a gap existing between the lower structure and the upper structure is seen, the internal seismic isolation device can be seen from the outside through this gap, and rain, soil, sand, etc. invade into this gap, and There is a risk that the seismic device will not operate sufficiently.
[0004]
There are various types of base-isolated buildings that have solved this problem. For example, buildings described in
First, the seismic isolation building described in
[0005]
In this
[0006]
Then, when an earthquake occurs and the relative position of the foundation (lower structure) 100 and the building main body (upper structure) 104 moves, the
[0007]
In addition, the base-isolated building described in
[0008]
When an earthquake occurs and the relative position of the foundation and the building body changes, the groove lid body moves substantially horizontally above the ground. And even if a building main body vibrates large so that a boundary may be exceeded, an auxiliary groove lid will rotate below and it will not collide with a building main body.
[0009]
Moreover, in the base-isolated building described in
[0010]
Further, the base-isolated building described in
[0011]
Further, in the base-isolated building described in
[0012]
[Patent Document 1]
JP 2000-234394 A
[Patent Document 2]
JP 2001-262864 A
[Patent Document 3]
JP 2000-120187 A
[Patent Document 4]
JP 2000-352221 A
[Patent Document 5]
JP 2001-73473 A
[Patent Document 6]
JP 2000-320184 A
[Patent Document 7]
JP 2001-182366 A
[0013]
[Problems to be solved by the invention]
However, the member which covers the clearance gap between the upper structure and lower structure used for the base-isolated building described in the said patent documents 1-7 (the side plate described in
Thus, since the member which covers the clearance gap between an upper structure and a lower structure is exposed, since it will deteriorate easily, external appearance quality and high durability are requested | required and it will become a high-cost member.
[0014]
Moreover, in the seismic isolation building described in
[0015]
Moreover, since all the members covering between the upper structure and the lower structure except for
SUMMARY OF THE INVENTION An object of the present invention is to provide a seismic isolation building in which a member that covers between an upper structure and a lower structure is attached so that it is not exposed or protrudes greatly outward.
[0016]
[Means for Solving the Problems]
The present invention has been made in order to solve the above-described problems. In the invention according to
[0017]
The rising member according to
[0018]
That is, the invention according to
[0019]
The foundation according to
[0020]
The invention according to
[0021]
The invention according to
[0022]
(Function)
The invention according to
[0023]
The plate member protrudes substantially horizontally from the upright member toward the inner side of the upper structure and does not appear outward, so that it is difficult to deteriorate. Therefore, this plate member can be manufactured with an inexpensive material.
Moreover, since there is no side plate attached so that rocking | fluctuation is possible, there is no possibility that the noise of a side plate will generate | occur | produce and a child, a dog, and a cat will open a side plate.
[0024]
The invention according to
[0025]
The invention according to
[0026]
Therefore, it is more difficult to see the seismic isolation device inside this gap, and rain, earth, sand, etc. are more difficult to enter from this part, so that direct sunlight does not enter inside this gap, and the plate member existing inside Etc. are more difficult to deteriorate. Further, by making the upper waterproof decorative member and the lower waterproof decorative member excellent in waterproofness and design, this gap portion becomes beautiful, and rainwater hardly enters inside.
[0027]
Further, since the upper waterproof decorative member only covers up to a position slightly higher than the upper end of the plate member, a large earthquake occurs and the upper structure moves greatly in the inner direction of the foundation, and the upper waterproof decorative member Even if it exceeds the rising member on the indoor side, the upper waterproof decorative member higher than the upper end of the rising member does not collide with the rising member.
[0028]
In addition, since the lower waterproof decorative member only covers the outer surface of the rising member below a height substantially equal to the upper end of the rising member, a large earthquake occurs, and the upper structure is directed toward the outer side of the foundation. As a result, even if the lower waterproof decorative member moves to the inner side of the upper structure, the lower waterproof decorative member remains on the outer surface of the rising member below a height substantially equal to the upper end of the rising member. The upper structure which is lower than the rising member and thus higher than the rising member does not collide with the lower waterproof decorative member.
[0029]
In the invention of
[0030]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described by way of examples.
(Example)
1 to 6 show an embodiment in which the present invention is applied to a unit building. FIG. 1 is a perspective view showing a base-isolated building that is a unit building, and FIG. FIG. 3 is a cross-sectional view showing the connecting portion of the superstructure, FIG. 3 is a cross-sectional view showing a state in which the main body of the base-isolated building shown in FIG. FIG. 5 is a cross-sectional view showing a portion to which a seismic isolation device is attached. FIG. 5 shows only the main part for easy understanding of the seismic isolation building shown in FIG. (B) is a schematic diagram showing a state when the building main body is largely moved inside the foundation, (c) is a schematic diagram showing a state when the building main body is largely moved outside the foundation, and FIG. It is a partially cutaway perspective view showing a building unit.
[0031]
1 to 6, H is a base-isolated building which is a unit building. As shown in FIGS. 1 to 5, this base-isolated building H is isolated on the
The
[0032]
As shown in FIGS. 2 and 3, the
The
[0033]
As shown in FIGS. 2 and 3, a rising member A including a
[0034]
The connecting
[0035]
An L-shaped mounting
[0036]
The
The
[0037]
A lower waterproof
The upper end of the lower waterproof
[0038]
As the
[0039]
Then, a fixed
An oil damper seismic isolation device (not shown) is also provided on the fixed
[0040]
The
The
[0041]
As shown in FIG. 6, the
[0042]
Then, the
[0043]
In addition, a
[0044]
The
A seismic isolation device fixing member 36 is attached on each of the plurality of
[0045]
An upper waterproof
The upper end of the upper waterproof
Then, the upper waterproof
[0046]
The upper waterproof
Since the roof panel 99 is substantially the same as a conventional folded roof panel, description thereof is omitted.
[0047]
Next, the construction method and effect | action of this seismic isolation building H are demonstrated.
The
At the construction site, a
[0048]
Further, a fixed
Next, the seismic isolation device fixing member 36 is attached on the
[0049]
A
Then, the
In this way, nine
[0050]
The seismically isolated building H thus completed is a building in which the
The
[0051]
The gap between the
[0052]
Furthermore, the
[0053]
Further, the upper waterproof
Further, since the upper waterproof
[0054]
Further, since the lower waterproof
[0055]
Further, since the upper waterproof
[0056]
Further, since the rising member A includes the
[0057]
【The invention's effect】
As described above, the invention described in
[0058]
The invention according to
[0059]
The invention according to
[0060]
Further, the upper waterproof decorative member only covers up to a position slightly higher than the upper end of the plate member, and the lower waterproof decorative member covers the outer surface of the rising member below a height substantially equal to the upper end of the rising member. Even if a large earthquake occurs and the upper structure moves greatly inward or outward of the foundation, the upper waterproof decorative member that is higher than the upper end of the rising member becomes the rising member. The upper waterproof decorative member is lower than the rising member and the upper structure higher than the rising member does not collide with the lower waterproof decorative member.
[0061]
In the invention according to
[Brief description of the drawings]
FIG. 1 is a perspective view showing a base-isolated building as a unit building according to an embodiment in which the present invention is applied to a unit building.
FIG. 2 is a cross-sectional view showing a connecting portion between a lower structure and an upper structure of a base-isolated building.
3 is a cross-sectional view showing a state in which the building main body of the base-isolated building shown in FIG. 2 has greatly moved inward of the base during an earthquake.
FIG. 4 is a cross-sectional view showing a portion where a seismic isolation device for a seismic isolation building is attached.
FIG. 5 shows only the main part for easy understanding of the base-isolated building shown in FIG. 2. (A) is a schematic diagram showing a normal state, and (B) is a large building body inside the base. The schematic diagram which shows a state when it moves, (c) is a schematic diagram which shows a state when a building main body has moved largely outside the foundation.
FIG. 6 is a partially cutaway perspective view showing a building unit.
FIG. 7 is a schematic diagram showing the main part of an example of a conventional seismic isolation building.
[Explanation of symbols]
H Seismic isolation building
S clearance
A Standing member
1 ground
2 Substructure
3 Seismic isolation device
4 Superstructure
45 Upper waterproofing cosmetic
5 basics
55 Lower waterproof cosmetic
6 Connecting plate
7 Plate members
8 Building units
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003067052A JP4044858B2 (en) | 2003-03-12 | 2003-03-12 | Seismic isolation building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003067052A JP4044858B2 (en) | 2003-03-12 | 2003-03-12 | Seismic isolation building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004278011A JP2004278011A (en) | 2004-10-07 |
| JP4044858B2 true JP4044858B2 (en) | 2008-02-06 |
Family
ID=33284777
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2003067052A Expired - Fee Related JP4044858B2 (en) | 2003-03-12 | 2003-03-12 | Seismic isolation building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4044858B2 (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4736884B2 (en) * | 2006-03-24 | 2011-07-27 | 積水ハウス株式会社 | Gap closing member |
| JP2008223229A (en) * | 2007-03-08 | 2008-09-25 | Asahi Kasei Homes Kk | Piping structure of base-isolated building |
| JP5398960B2 (en) * | 2007-03-08 | 2014-01-29 | 旭化成ホームズ株式会社 | Base structure of base-isolated building |
| JP6365618B2 (en) * | 2016-10-13 | 2018-08-01 | 積水ハウス株式会社 | Basic ventilation waterproof structure |
-
2003
- 2003-03-12 JP JP2003067052A patent/JP4044858B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004278011A (en) | 2004-10-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP4044858B2 (en) | Seismic isolation building | |
| CN216340631U (en) | Modular passing-through stone structure | |
| JP2013113049A (en) | Column base protective structure and protective cover | |
| JP5541729B2 (en) | Vibration control device and vibration control structure of wooden building using the same | |
| JPH03122376A (en) | Dynamic vibration reducer utilizing curtain wall | |
| JP2001073473A (en) | Entrance / exit structure of seismic isolation building, unit-type seismic isolation building having the entrance / exit structure, and building unit | |
| KR100569839B1 (en) | Soundproof Wall Using Membrane Composite Laminate | |
| JP3962758B1 (en) | Middle-rise base-isolated building | |
| JP4005862B2 (en) | Entrance structure | |
| JP2012102539A (en) | Vibration control device and vibration control structure of wooden building using the same | |
| JP2001182366A (en) | Underfloor makeup, seismic isolation bearing device and seismic isolation building | |
| JP2007009450A (en) | Base isolation device and base isolation structure of building of panel construction method | |
| JP5465378B2 (en) | Seismic isolation building | |
| KR20210150240A (en) | A soundproofing wall system that can reduce howling by height difference between wood parts | |
| JP7369095B2 (en) | Structure of overhang part of building | |
| JP2008008055A (en) | Seismic isolation building | |
| JP4296099B2 (en) | Edge cutting structure of the outer wall in a base-isolated house | |
| JP2004137859A (en) | Wooden moving building | |
| JP5615525B2 (en) | Inspection door construction method | |
| KR200467064Y1 (en) | Pergola post | |
| JPH0352376Y2 (en) | ||
| JPS6137714Y2 (en) | ||
| JP2001040904A (en) | Three-storey house with dynamic vibration absorber | |
| JPH0547813Y2 (en) | ||
| KR200361591Y1 (en) | A noise reducer for soundproof wall |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051118 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070709 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20071024 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20071116 |
|
| R151 | Written notification of patent or utility model registration |
Ref document number: 4044858 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R151 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101122 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101122 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111122 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111122 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121122 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131122 Year of fee payment: 6 |
|
| LAPS | Cancellation because of no payment of annual fees |