JP4057005B2 - Converter operation method - Google Patents
[go: Go Back, main page]

JP4057005B2 - Converter operation method - Google Patents

Converter operation method Download PDF

Info

Publication number
JP4057005B2
JP4057005B2 JP2004304862A JP2004304862A JP4057005B2 JP 4057005 B2 JP4057005 B2 JP 4057005B2 JP 2004304862 A JP2004304862 A JP 2004304862A JP 2004304862 A JP2004304862 A JP 2004304862A JP 4057005 B2 JP4057005 B2 JP 4057005B2
Authority
JP
Japan
Prior art keywords
converter
blowing
time
converters
repair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2004304862A
Other languages
Japanese (ja)
Other versions
JP2006117972A (en
Inventor
康一郎 瀬村
正信 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP2004304862A priority Critical patent/JP4057005B2/en
Publication of JP2006117972A publication Critical patent/JP2006117972A/en
Application granted granted Critical
Publication of JP4057005B2 publication Critical patent/JP4057005B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Carbon Steel Or Casting Steel Manufacturing (AREA)

Description

本発明は、複数の転炉を効率的に使用する際における転炉の操業方法に関するものである。   The present invention relates to a method of operating a converter when efficiently using a plurality of converters.

周知のように、転炉工程では、溶銑を転炉に装入し、副原料添加と酸素吹込みを行うことで脱りん・脱炭を行って、りん濃度や炭素濃度が所定の値となっている溶鋼を生産している。
図11は、従来からある転炉設備を示しているものであって、転炉と、これら転炉に溶銑を供給する取鍋と、この取鍋を搬送するクレーンとを有している。転炉に関しては、全部で3基あり、その中の2基を稼働させ、残るもう1基は休止状態としていた。
詳しくは、転炉には溶銑が装入されるためその内壁は常に高温にさらされており、内壁を構成する耐火レンガは徐々に溶損してゆく。つまり、転炉は、耐火レンガが溶け減って転炉自身の機能を失う炉体寿命をもっている。この寿命を超えて転炉を長期間に亘って稼働させることは不可能であり、転炉は、一定期間稼働した後、転炉内の耐火レンガを張り替えたりする大規模な修理、「炉修」が行われるものとなっている。前記休止中の1基の転炉は、かかる炉修作業中及びそれに続く休止状態中であった。
As is well known, in the converter process, hot metal is charged into the converter, dephosphorization and decarburization are performed by adding auxiliary materials and blowing oxygen, and the phosphorus concentration and carbon concentration reach predetermined values. Is producing molten steel.
FIG. 11 shows a conventional converter facility, which includes a converter, a ladle that supplies hot metal to the converter, and a crane that conveys the ladle. There were three converters in total, two of them were in operation, and the remaining one was in a dormant state.
In detail, since the hot metal is charged into the converter, the inner wall is always exposed to high temperature, and the refractory bricks constituting the inner wall are gradually melted. That is, the converter has a furnace body life in which the refractory bricks melt and lose the function of the converter itself. It is impossible to operate the converter over a long period of time beyond this life, and after the converter has been operating for a certain period of time, a large-scale repair, such as replacing the refractory bricks in the converter, Is to be performed. The one converter that was out of service was in such a furnace repair operation and in the subsequent stop state.

図12は、図11の転炉設備における操業スケジュールを示したものであって、図12(a)には、3基の転炉A,B,Cに関して転炉稼働期間(すなわち転炉寿命)と炉修とのスケジュールが示されている。このスケジュールの如く、転炉寿命内にある2基の転炉では溶銑の精錬を行い、残りの1基の転炉で炉修を行って休業状態としていた。図中のPで示される部分のように、転炉Aと転炉Bとが稼働中であったとして、転炉Aの内壁に張りつけられている耐火レンガを張り替える時期が近づいたとする。そうした場合、転炉Aは炉修作業に入り、その代わりに、今まで休業中であった転炉Cを稼働状態とする。その後、転炉Aの炉修が終了したとしても、転炉Aをバックアップと考え、稼働状態とはせず休業状態のままとしていた。言い換えれば、使用している2基の転炉B,Cの内、1基が故障したり、炉修を行う必要が生じた場合に、その転炉B,Cの稼働を止めて現在休業中の転炉Aを再稼働するようにしていた。   FIG. 12 shows an operation schedule in the converter equipment of FIG. 11, and FIG. 12 (a) shows converter operation periods (that is, converter life) for three converters A, B, and C. And the schedule of furnace repairs are shown. As in this schedule, the two converters within the converter life were refined with hot metal, and the remaining one converter was repaired and closed. Assuming that converter A and converter B are in operation as indicated by P in the figure, it is assumed that it is time to replace the refractory bricks attached to the inner wall of converter A. In such a case, the converter A enters the furnace repair work, and instead, the converter C that has been closed until now is put into operation. Then, even if the furnace repair of the converter A was completed, the converter A was considered as a backup, and was not in operation, but was in a closed state. In other words, if one of the two converters B, C used is out of order or needs to be repaired, the converters B, C are stopped and are currently closed. The converter A was restarted.

図12(b)には、2基の転炉B,Cが稼働している場合における、各転炉B,Cでのチャージ状況を示したものである。転炉のチャージとは、転炉に溶銑が装入され、装入された溶銑に対して吹錬が行われ、生産された溶鋼が排出される一連の工程をいい、この一連の作業の開始から終了までの時間を製鋼時間という。1回の転炉寿命内では約5000回のチャージが行われるのが通常である。図に示すように、必要に応じて、各チャージ間に転炉休止時間を設け、この時間を、転炉の内壁に耐火補修材を吹き付けるなどして簡易的ながら炉寿命を大幅に向上させる修理である「補修」を行う時間としている。   FIG. 12 (b) shows the charge status at each converter B, C when two converters B, C are operating. Converter charge refers to a series of processes in which molten iron is charged into the converter, blown into the molten iron, and the produced molten steel is discharged. The time from the end to the end is called steelmaking time. Usually, about 5000 charges are performed within one converter life. As shown in the figure, if necessary, there is a converter downtime between each charge, and this time is a simple repair that greatly improves the furnace life by spraying fireproof repair material on the inner wall of the converter. It is time to perform “repair”.

転炉寿命を日数に直すと、大雑把ではあるが150日前後であり、炉修は約20日前後である。一方、転炉での1チャージ分の製鋼時間は約35分前後であり、転炉の補修は10分〜数時間を有するものである。このことを鑑みた上で、図12を要約すると、図12(a)は、転炉工程を日単位でマクロ的(巨視的)に見て、炉修期間と稼働期間とに分けたものであり、図12(b)は、転炉工程を時間単位でミクロ的(微視的)に見て、チャージと補修期間で分けたものとなっている。
以上のことから判るように、従来からの一般的な転炉設備においては、マクロ、ミクロいかなる観点からも、転炉は常に2基のみが稼働中であり、残り1基はバックアップとして休業状態にあることが普通である。したがって、転炉の周辺設備、例えば、排ガス処理設備や酸素供給設備は2基の転炉のみを吹錬させる能力しか有さないものとなっていた。
If the converter life is converted to days, it is roughly around 150 days, and the furnace repair is around 20 days. On the other hand, the steelmaking time for one charge in the converter is about 35 minutes, and the repair of the converter has 10 minutes to several hours. In view of this, FIG. 12 is summarized as follows. FIG. 12 (a) shows the converter process divided into a furnace repair period and an operation period as seen macroscopically on a daily basis. Yes, FIG. 12 (b) shows the converter process divided into charge and repair period when viewed in a microscopic (microscopic) manner in time units.
As can be seen from the above, in conventional conventional converter facilities, only two converters are always in operation from the macro and micro perspectives, and the remaining one is closed as a backup. It is normal to be. Therefore, peripheral equipment of the converter, for example, exhaust gas treatment equipment and oxygen supply equipment, has only the ability to blow only two converters.

このような転炉設備において、2基の転炉を効率よく稼働させることに関し、特許文献1や特許文献2の技術が既に開示されている。
特許文献1の技術は、1の転炉で脱りん精錬をした溶湯を受湯鍋に受け、この受湯鍋を作業床開口部を通して他の1の転炉に運搬し、ここで脱炭精錬を行なうものであって、脱燐精錬でのスラグの排さい時間等を少なくすると共に、脱燐精錬時間と脱炭精錬時間とを同程度にすることで、脱炭精錬炉の遊び時間を無くし全体として製鋼能率を向上するものである。換言すれば、1の転炉でのチャージ時間と他の転炉でのチャージ時間とを同程度にすることで、製鋼能率をあげる技術である。
In such a converter facility, the techniques of Patent Document 1 and Patent Document 2 have already been disclosed for efficiently operating two converters.
In the technique of Patent Document 1, the molten metal dephosphorized and refined in one converter is received in a receiving hot pot, and the hot pot is transported to the other one through the work floor opening, where decarburization refining is performed. In addition to reducing the slag removal time in dephosphorization refining and reducing the dephosphorization refining time and decarburization refining time to the same extent, the play time of the decarburization refining furnace is eliminated as a whole. It improves the steelmaking efficiency. In other words, it is a technique for increasing the steelmaking efficiency by making the charge time in one converter the same as the charge time in another converter.

特許文献2の技術は、2基の転炉において、吹錬を開始する転炉の煙道のダンパーを開く動作と、吹錬を終了した転炉の煙道のダンパーを閉じる動作とを1段階のダンパー操作で同時並列的に行い、切替え時の停風時間を短縮させるものであって、転炉のチャージ切替時における煙道のダンパー操作方法に関するものである。
特許第3486886号公報 特開平6−65653号公報
In the technology of Patent Document 2, the operation of opening the flue damper of the converter that starts blowing and the operation of closing the damper of the flue of the converter that has finished blowing are performed in one stage in two converters. The damper operation is performed simultaneously and in parallel to shorten the wind stop time at the time of switching, and relates to a method for operating the damper of the flue at the time of charge switching of the converter.
Japanese Patent No. 3486886 JP-A-6-65653

前述した転炉設備で、溶鋼生産能力を上げようと考えた場合、2基の転炉を稼働させることはもちろん、休業状態にあるもう1基の転炉を稼働させ、マクロ視で3基の転炉が同時に稼働している状況とするとよい。しかしながら、転炉周辺設備は、2基の転炉を稼働させる能力しかないため、単純に3基を同時に稼働することは不可能である。
この問題を解決するために、前述した特許文献1や特許文献2に着目したとしても、これらの技術は、転炉工程をミクロ視した上で2基の転炉稼働における効率アップを図るものであり、該技術を適用したとしても、マクロ視での転炉3基稼働を実現させ、溶鋼生産能力を大幅に向上させることは困難である。
In the converter equipment mentioned above, when thinking about increasing the production capacity of molten steel, not only two converters will be operated, but another converter that is in a closed state will be operated, The converter should be operating at the same time. However, since the converter peripheral equipment has only the ability to operate two converters, it is simply impossible to operate three simultaneously.
In order to solve this problem, even if attention is given to Patent Document 1 and Patent Document 2 described above, these technologies are intended to increase efficiency in the operation of two converters after microscopically viewing the converter process. Even if this technology is applied, it is difficult to realize the operation of three converters in a macro view and to greatly improve the molten steel production capacity.

そこで、本発明は、上記問題点に鑑み、2基の転炉を吹錬させる能力しか備えていない転炉周辺設備を有する転炉設備で、3基の転炉の同時稼働状況を操業スケジュールに組み込むことのできる転炉の操業方法を提供することを目的とする。   Therefore, in view of the above problems, the present invention is a converter facility having a converter peripheral facility that has only the ability to blow down two converters, and the operation schedule of the simultaneous operation status of the three converters is used. The object is to provide a converter operating method that can be incorporated.

前記目的を達成するため、本発明においては以下の技術的手段を講じた。
すなわち、本発明における課題解決のための技術的手段は、溶銑の吹錬を行う3基の転炉と、最大2基の転炉を吹錬可能とする能力を備えた転炉周辺設備とを有する転炉設備で、前記転炉周辺設備の能力を超えずに3基の転炉を操業すべく、各転炉のチャージの順番を、第1の転炉での吹錬が終了する前に、第2の転炉での吹錬を開始するように設定し、第3の転炉の吹錬開始を、第2の転炉での吹錬が終了する前で且つ第1の転炉での前回吹錬終了〜次回吹錬開始の間に設定していることを特徴とする。
In order to achieve the above object, the present invention takes the following technical means.
That is, the technical means for solving the problems in the present invention include three converters that perform hot metal blowing, and converter peripheral equipment that has the capability of blowing up to two converters. In order to operate the three converters without exceeding the capacity of the converter peripheral equipment with the converter equipment that has, before the end of the blowing in the first converter, the order of charge of each converter The second converter is set to start blowing, and the third converter is started before the second converter is finished and before the first converter It is set between the end of the previous blowing and the start of the next blowing.

溶銑の吹錬を行う3基の転炉と、最大2基の転炉を吹錬可能とする能力を備えた転炉周辺設備とを有する転炉設備で、溶鋼生産能力を上げようと考えた場合、前述の如く、マクロ的に3基の転炉が略同時に稼働している状況(3/3基稼働)とするとよい。しかしながら、転炉周辺設備は2基の転炉を吹錬させる能力しかないため、単純に3基を同時に稼働することは不可能である。
そこで本願発明者は、様々な操業状況を検討した結果、図1(a)に示す如く、マクロ的には転炉が3基稼働している状況であるものの、図1(b)のように、ミクロ的には2基の転炉が吹錬しチャージが順次行われているようにすることで、転炉周辺設備の能力を超えることなく、大きく生産性を向上させることができるという技術思想を得るに至った。
We thought to increase the production capacity of molten steel with a converter facility that has three converters that perform hot metal blowing and peripheral equipment that has the capability of blowing up to two converters. In this case, as described above, it is preferable that the three converters are operated substantially at the same time (3/3 operation). However, since the converter peripheral equipment has only the capability of blowing two converters, it is impossible to simply operate three units simultaneously.
Therefore, as a result of studying various operation situations, the inventor of the present application, as shown in FIG. 1 (a), is in a situation where three converters are operating in a macro manner, as shown in FIG. 1 (b). Microscopically, the technical idea that two converters can be blown and charged one after another so that productivity can be greatly improved without exceeding the capacity of peripheral equipment. I came to get.

すなわち、図1(b)に示すように、転炉Aと転炉Bのチャージの順番を、転炉A(第1の転炉)での吹錬が終了する前に、転炉B(第2の転炉)での吹錬を開始するように設定することにより、両者が同時に吹錬を行う状況としている。さらに、転炉C(第3の転炉)の吹錬開始を、転炉Bでの吹錬が終了する前とすることで、転炉Bと転炉Cでも同時に吹錬を行わせている。加えて、転炉Cの吹錬開始を、転炉Aでの前回吹錬終了〜次回吹錬開始の間、換言すれば転炉Aが吹錬を行っていないときに設定しているため、転炉Aと転炉Cとが同時に吹錬する状況にはならず、全体として3基の転炉A,B,C が同時に吹錬状況となることはない。   That is, as shown in FIG. 1 (b), the charging order of the converter A and the converter B is changed to the converter B (first converter) before the blowing in the converter A (first converter) is completed. By setting so as to start blowing in the converter (2), the situation is that both perform blowing simultaneously. Furthermore, by starting the blowing of the converter C (third converter) before the end of the blowing in the converter B, the converter B and the converter C are simultaneously blown. . In addition, since the start of blowing of the converter C is set between the end of the previous blowing in the converter A and the start of the next blowing, in other words, when the converter A is not blowing, The converter A and the converter C are not in a state where they are simultaneously blown, and as a whole, the three converters A, B, C are not in the state of blowing at the same time.

このような稼働状況とすることで、転炉周辺設備の能力を超えることなく、マクロ的に3基の転炉を休止期間無く同時に稼働させることができるようになり、大きく溶鋼生産性を向上させることができる。
なお、好ましくは、1の転炉の前回吹錬開始と次回吹錬開始との間に他の2つの転炉の吹錬開始がそれぞれ1回ずつ存在する状況を順次稼働状況とし、前記第1〜第3の転炉の少なくとも1つが該順次稼働状況を有するとよい。
加えて、前記順次稼働状況となっている転炉のチャージ数が、全チャージ数に占める割合を転炉の順次稼働比率とし、この転炉の順次稼働比率が40%〜95%となるように3基の転炉を操業するとよい。
By adopting such an operating situation, it becomes possible to operate three converters at the same time macroscopically without exceeding the capacity of the peripheral equipment of the converter, and greatly improve the molten steel productivity. be able to.
Preferably, a situation in which there is one each of the other two converters at the start of the next blowing operation between the previous blowing start of the first converter and the next blowing start is referred to as the operating state sequentially. It is good that at least one of the third converters has the sequential operation status.
In addition, the ratio of the number of charges of the converter in the sequential operation status to the total number of charges is the sequential operation ratio of the converter, and the sequential operation ratio of the converter is 40% to 95%. It is good to operate three converters.

1の転炉の吹錬開始と吹錬終了との間に他の2つの転炉の吹錬開始が存在する状況を1の転炉が順次稼働状況であると定義すると共に、この順次稼働状況となっている転炉のチャージ数が、全チャージ数に占める割合を転炉の順次稼働比率とし、当該転炉の順次稼働比率を40%〜95%にするとよい。それは以下に述べる根拠に基づく。
すなわち、上記のように順次稼働比率を定義した上で、図1(b)を詳しく描いた図2、図3を見ると、順次稼働比率の高い状況は図2中のP部が対応し、転炉A,B,Cが順番に滞りなく吹錬を行っている。一方、Q部は順次稼働比率が低く、転炉Aなどは休止している時間が長いものとなっている。このことより考えて、順次稼働比率が大きくなる、すなわち転炉のチャージが順次続くことで、3基の転炉が待ち時間なくフル稼働していることになり、転炉設備の溶鋼生産性が非常によくなる。
The situation in which the other two converters start blowing between the start of blowing and the end of blowing of one converter is defined as the sequential operation of one converter, and this sequential operation status The ratio of the number of charges in the converter to the total number of charges is the sequential operation ratio of the converter, and the sequential operation ratio of the converter is preferably 40% to 95%. It is based on the grounds described below.
That is, after defining the sequential operation ratio as described above, when looking at FIG. 2 and FIG. 3 depicting FIG. 1B in detail, the situation where the sequential operation ratio is high corresponds to the P part in FIG. Converters A, B, and C perform blowing without any delay. On the other hand, the operation ratio of the Q section is low sequentially, and the converter A and the like have a long pause time. Considering this, the operation ratio increases sequentially, that is, the converter charge continues in sequence, so that the three converters are fully operating without waiting time, and the molten steel productivity of the converter equipment is increased. Become very good.

ところが、実際の転炉操業においては、転炉に対する地金取りや孔巻き、耐火物の補修などの補修作業が随時行われる。これらの作業は転炉の安定操業のためには必須であるものの、転炉の順次稼働比率が大きい場合、かかる補修作業を行う時間を確保することが困難となり逆に溶鋼生産性が落ちるようになる。
そこで本願出願人は、順次稼働比率を変化させた場合における溶銑生産性を変化をシミュレーションし、最適な順次稼働比率を求めるようにした。その結果が図4,図5に示されている。図4は計算結果であり、それを基にグラフ化したものが図5である。
However, in actual converter operation, repair work such as metal bulging, hole winding, and refractory repair for the converter is performed as needed. These operations are indispensable for stable operation of the converter, but if the sequential operation ratio of the converter is large, it will be difficult to secure time for performing such repair work, and conversely, the productivity of molten steel will decrease. Become.
Therefore, the applicant of the present application simulated the change in hot metal productivity when the operating ratio was sequentially changed to obtain an optimum sequential operating ratio. The results are shown in FIGS. FIG. 4 shows the calculation results, and FIG. 5 is a graph based on the calculation results.

図5には、クレーンの能力により決定される転炉への溶銑供給時間が10分、15分、20分と3つの異なる条件下で、順次稼働比率を毎々変化させたときの溶鋼生産性の変化が記載されている。なお、各条件での製鋼時間は35分、35分、40分である。
図の横軸は転炉の順次稼働比率であり、縦軸は溶鋼生産性を示したもので1時間あたりのチャージ数であって、溶銑供給時間が10分の結果がグラフI、15分がグラフII、20分がグラフIIIである。溶銑供給時間が短いということは、クレーンの溶銑供給能力が大きく転炉の処理能力に対して多くの溶銑を供給できることを意味し、グラフIの傾きが最も大きいものとなっている。
Fig. 5 shows the molten steel productivity when the operating ratio is changed one after another under three different conditions of the hot metal supply time to the converter determined by the capacity of the crane: 10 minutes, 15 minutes and 20 minutes. Changes are described. In addition, the steelmaking time in each condition is 35 minutes, 35 minutes, and 40 minutes.
The horizontal axis in the figure is the sequential operation ratio of the converter, the vertical axis shows the molten steel productivity, the number of charges per hour, the result of the hot metal supply time 10 minutes is graph I, 15 minutes Graph II, 20 minutes is graph III. The short hot metal supply time means that the hot metal supply capacity of the crane is large and that much hot metal can be supplied with respect to the processing capacity of the converter, and the slope of graph I is the largest.

グラフIIは、通常のクレーン能力を有する場合の計算結果であり、そのグラフで溶鋼生産性が最大値をとるのは、順次稼働比率が75%の時である。本願発明者は、かかる最大値の略95%を常に確保するようにすると、転炉操業全体に亘って溶鋼生産性が非常によくなるものとなると考え、転炉の順次稼働比率を40%〜95%とした。なお、より好ましくは、50%〜90%の範囲とするとよい。
なお、グラフIIIで示される状況は、転炉自体の処理能力に対してクレーンの溶銑供給能力が小さい場合であり、この場合、順次稼働比率を上げたとしても溶銑生産性は向上しないばかりか逆に低下する結果となっている。
Graph II is a calculation result in the case of having a normal crane capacity. In the graph, the molten steel productivity takes the maximum value when the operation ratio is sequentially 75%. The inventor of the present application thinks that, when ensuring about 95% of the maximum value is always secured, the molten steel productivity becomes very good over the entire converter operation, and the sequential operation ratio of the converter is 40% to 95%. %. More preferably, the range is 50% to 90%.
The situation shown in Graph III is when the hot metal supply capacity of the crane is smaller than the processing capacity of the converter itself. In this case, even if the operating ratio is increased, the hot metal productivity will not be improved. It is a result to fall to.

グラフIは、クレーンの供給能力が非常に大きい場合である。クレーンの溶銑供給能力は、通常、転炉2基の稼働に合わせて設計されているため、本ケースのようになることはまれではあるが、この場合でも、順次稼働比率を40%〜95%に保てば溶鋼生産性を高位に保つことが可能である。
また、本発明における課題解決のための技術的手段は、前記転炉の内壁に対する簡易的な修理である「補修」を行うに必要とされる補修時間を確保すべく、第1→第2→第3としていた転炉の操業順序を逆順にすることを特徴とする。
Graph I is when the crane's supply capacity is very large. Since the hot metal supply capacity of the crane is usually designed for the operation of two converters, it is rare that it will be like this case, but even in this case, the operation ratio is gradually increased from 40% to 95%. If it is kept at, it is possible to keep the molten steel productivity high.
Further, the technical means for solving the problems in the present invention are: first → second → to secure a repair time required for performing “repair” which is a simple repair to the inner wall of the converter. The operation order of the converter, which was the third, is reversed.

前述した如く、転炉の補修作業は転炉操業に必要不可欠なものであり、かかる補修を行う時間である補修期間を、3基の転炉の各チャージ間にうまく確保することで、溶鋼生産性を下げることなく、補修を行うことができるようになる。
図6には、第1→第2→第3としていた3基の転炉のチャージ順序を逆にすることで、転炉A(第1の転炉)で補修期間を確保した様子が示されている。
つまり、転炉Aでの吹錬が終了する前に、転炉B(第2の転炉)での吹錬を開始するようにしており、転炉C(第3の転炉)の吹錬開始を、転炉Bの吹錬が終了する前で、且つ転炉Aの吹錬終了後としている。
As mentioned above, converter repair work is indispensable for converter operation, and it is possible to produce molten steel by securing a repair period, which is the time for performing such repair, between each charge of the three converters. It becomes possible to perform repairs without lowering the performance.
FIG. 6 shows a state in which the repair period is secured in the converter A (first converter) by reversing the charging order of the three converters which have been first → second → third. ing.
That is, before the blowing in the converter A is completed, the blowing in the converter B (second converter) is started, and the blowing in the converter C (third converter) is started. The start is before the end of blowing of the converter B and after the end of blowing of the converter A.

ここで、転炉Aで補修作業を行う必要が生じた場合(図6のP)、転炉Cのチャージ後に、転炉Aではなく転炉Bのチャージを行い、転炉Bの吹錬が終了する前に、転炉Aの吹錬を開始するようにする。(C0→B1→A1)。その後は、転炉C、転炉B、転炉Aと逆順で3基の転炉のチャージを行う(C1→B2→A2、すなわち、第3→第2→第1)。
このようにすることで、吹錬A0からA1間での間に、転炉Aの長い休止時間を確保することができるようになり、この休止時間を補修期間とすることで、3基の転炉の順次稼働を行い且つ補修を行ったとしても、溶鋼生産性を高いままでキープ可能である。
Here, when it becomes necessary to perform repair work in the converter A (P in FIG. 6), after the converter C is charged, the converter B is charged instead of the converter A, and the converter B is blown. Before finishing, the blowing of the converter A is started. (C0 → B1 → A1). Thereafter, the three converters are charged in the reverse order of the converter C, the converter B, and the converter A (C1 → B2 → A2, that is, third → second → first).
By doing in this way, it becomes possible to ensure a long downtime of the converter A between the blowing A0 and A1, and by making this downtime a repair period, Even if the furnaces are operated sequentially and repaired, the molten steel productivity can be kept high.

なお、前記補修時間を、T/4〜3Tの範囲内(Tは製鋼時間)とすることは非常に好ましい。以下、その理由を説明する。
図8,図9には、補修時間が約5〜600分まで変化した場合における、転炉寿命の延長の度合い(補修効果)と、地金取りにかかる時間とをシミュレーションした結果が示されている。図8は計算結果であり、それをグラフ化したものが図9である。全ての計算において、製鋼時間は35分であり、クレーンでの溶銑供給時間は15分である。
図9の横軸は製鋼時間Tで換算された補修時間であり、縦軸には補修効果ならびに地金取り時間が示されている。
In addition, it is very preferable that the repair time is within a range of T / 4 to 3T (T is a steelmaking time). The reason will be described below.
FIGS. 8 and 9 show the results of simulating the degree of extension of the converter life (repair effect) and the time required for collecting the metal when the repair time varies from about 5 to 600 minutes. Yes. FIG. 8 shows the calculation results, and FIG. 9 is a graph of the calculation results. In all calculations, the steelmaking time is 35 minutes and the hot metal supply time at the crane is 15 minutes.
The horizontal axis in FIG. 9 is the repair time converted in terms of the steelmaking time T, and the vertical axis shows the repair effect and the bullion collecting time.

図中のグラフIは、補修効果の変化を示したものであり、補修時間を長くすることで、補修作業を確実に行うことができて1回の補修で延びるチャージ数が多くなることが示されている。補修時間を約0.25T(T/4)まで長くすると、転炉寿命が約3チャージ延長する。その一方、補修時間を約0.4T以上とすると、補修効果=5.0チャージでそれ以上は増えなくなる。
グラフIIは、地金取りにかかる時間の変化を示したものである。補修時間が3T以下では、地金取り時間はゼロであり、補修時間が3T以上になると、地金取り時間が発生するようになる。このことは、補修時間が長くなることで転炉自体の温度が降下し、転炉の装入口に地金等が付着する可能性が大きくなることを反映している。ゆえに、補修時間を極端に長くすることは得策ではなく、グラフIIからわかるように、補修時間を3T以下とすれば、地金取り作業の作業時間をなしとすることができる。
Graph I in the figure shows the change in the repair effect. By making the repair time longer, the repair work can be performed reliably, and the number of charges extending in one repair increases. Has been. Increasing the repair time to about 0.25 T (T / 4) extends the converter life by about 3 charges. On the other hand, if the repair time is about 0.4 T or more, the repair effect = 5.0 charge will not increase any more.
Graph II shows the change in the time required for collecting bullion. When the repair time is 3T or less, the bullion collecting time is zero, and when the repair time is 3T or more, the bullion collecting time is generated. This reflects that the longer the repair time, the lower the temperature of the converter itself, and the greater the possibility that metal will adhere to the converter inlet. Therefore, it is not a good idea to make the repair time extremely long. As can be seen from the graph II, if the repair time is set to 3T or less, the work time for the bullion collecting operation can be reduced.

これらのことを鑑み、補修時間をT/4〜3Tの範囲内とすることで、補修効果を適切なものとしつつ、地金取り作業の時間増加を防ぐことができるようになる。   In view of these matters, by setting the repair time within the range of T / 4 to 3T, it is possible to prevent an increase in the time for the bullion collecting operation while making the repair effect appropriate.

本発明によれば、2基の転炉を吹錬させる能力しか備えていない転炉周辺設備を有する転炉設備で、3基の転炉を効率的に稼働させることができる。   According to the present invention, it is possible to efficiently operate three converters in a converter facility having a converter peripheral facility having only the capability of blowing two converters.

以下、本発明にかかる転炉への溶銑供給方法の実施形態を、図を基に説明する。
本実施形態の転炉設備1は、図11に示される従来例とほぼ同一であり、3基の転炉2と、これら転炉2に溶銑を供給する取鍋3と、この取鍋3を搬送する2基のクレーン4とを有している。さらに、3基の転炉2のそれぞれには、吹錬で発生した排ガスを集煙して有害物質を除去したり一酸化炭素を回収したりする排ガス処理設備5が備えられていると共に、各転炉2に酸素を供給したりする酸素供給設備6が設けられている。この酸素供給設備6は、転炉1基が吹錬に使用する酸素量の2倍を供給できるものであると共に、排ガス処理設備5は、2基の転炉1から排出されるCOガスなどを回収する能力を有している。つまり、排ガス処理設備5や酸素供給設備6から構成される転炉周辺設備7は、2基の転炉2で同時に吹錬を行わせる能力を有するものとなっており、3基の転炉2での同時吹錬は不可能なものとなっている。
Hereinafter, an embodiment of a hot metal supply method to a converter according to the present invention will be described with reference to the drawings.
The converter equipment 1 of this embodiment is substantially the same as the conventional example shown in FIG. 11, and includes three converters 2, a ladle 3 that supplies hot metal to these converters 2, and this ladle 3. It has two cranes 4 to convey. Further, each of the three converters 2 is provided with an exhaust gas treatment facility 5 that collects exhaust gas generated by blowing and removes harmful substances or collects carbon monoxide. An oxygen supply facility 6 for supplying oxygen to the converter 2 is provided. The oxygen supply equipment 6 can supply twice the amount of oxygen used by one converter for blowing, and the exhaust gas treatment equipment 5 can supply CO gas discharged from the two converters 1. Has the ability to collect. That is, the converter peripheral equipment 7 composed of the exhaust gas treatment equipment 5 and the oxygen supply equipment 6 has the ability to simultaneously perform blowing in the two converters 2, and the three converters 2 Simultaneous blowing in is impossible.

本願発明は、図1〜図3に示す如く、かかる転炉設備1において、操業工程を日単位で見ることをマクロ的、時間単位で見ることをミクロ的と定義した上で、マクロ的には転炉2が3基稼働している状況であるものの、ミクロ的には2基の転炉2が吹錬し、チャージが順次行われているようにすることで、転炉周辺設備7の能力を超えることなく、大きく生産性を向上させようとするものである。
前記転炉設備1での各工程を詳しく説明すると、まず、取鍋3に入った溶銑はクレーン4により搬送され、転炉2に装入される。具体的には、転炉2を傾動し、炉内にスクラップ等を装入した上で溶銑を流し入れるようにする。
The present invention, as shown in FIGS. 1 to 3, in the converter equipment 1, defining the operation process in units of days as macroscopic, and in units of time as microscopic, Although three converters 2 are in operation, microscopically, two converters 2 are blown and charged sequentially so that the capacity of the converter peripheral equipment 7 is increased. It is intended to greatly improve productivity without exceeding.
Explaining each process in the converter equipment 1 in detail, first, the hot metal in the ladle 3 is conveyed by the crane 4 and charged into the converter 2. Specifically, the converter 2 is tilted, and scraps and the like are charged into the furnace, and then molten iron is poured.

その後、溶銑中のりんPを主に取り除くと共に炭素Cを適切なものとするために、転炉2の炉口からランス(図示せず)を挿入し、溶銑上面に近づけ、酸素ガスを吹き付けると同時に、炉底から吹き込みガスで溶銑を撹拌しつつ吹錬(精錬)を開始する。同時に、石灰CaO等の造滓材や酸化鉄Fexy等の冷却材、すなわち副原料を投入することで、りんPは投入された酸素と反応してスラグ相に移行し、溶銑の上方に浮いた状態で積層するようになる。
このように、転炉2に溶銑が装入され、この溶銑が吹錬されることで成分調整された溶鋼となり、この溶鋼が転炉2から排出される一連の工程を「チャージ」といい、1チャージ分の製鋼時間は約35分程度である。
Thereafter, in order to remove mainly phosphorus P in the hot metal and make carbon C suitable, a lance (not shown) is inserted from the furnace port of the converter 2 and is brought close to the upper surface of the hot metal, and oxygen gas is blown. At the same time, blowing (refining) is started while the hot metal is stirred from the bottom of the furnace. At the same time, the coolant such as the slag forming and iron oxide Fe x O y, such as lime CaO, i.e. by turning on the auxiliary materials, phosphorus P is shifted to the slag phase to react with the entered oxygen, above the hot metal Laminate in a floating state.
Thus, the molten iron is charged into the converter 2 and the molten steel is blown and the molten steel is adjusted in composition, and a series of processes in which the molten steel is discharged from the converter 2 is referred to as “charging”. The steelmaking time for one charge is about 35 minutes.

一方、転炉2の内壁は溶銑により常に高温にさらされていて、内壁を構成する耐火レンガは徐々に溶け減ってゆく。ゆえに、転炉2は、耐火レンガが溶け減って転炉自身の機能を失う「寿命」をもっている。この寿命を超えて転炉2を長期間に亘って稼働させることは不可能であるため、図1(a)に示すように、転炉2では、一定期間稼働した後、転炉2内の耐火レンガを張り替えたりする大規模な修理、「炉修」が行われるものとなっている。転炉2の寿命を日数に直すと、大雑把ではあるが150日前後であり、炉修は約20日前後である。また、1回の転炉寿命内では約5000回のチャージが行われるのが通常である。   On the other hand, the inner wall of the converter 2 is always exposed to a high temperature by the hot metal, and the refractory bricks constituting the inner wall are gradually melted down. Therefore, the converter 2 has a “lifetime” in which the refractory bricks melt and lose the function of the converter itself. Since it is impossible to operate the converter 2 over a long period of time beyond this life, the converter 2 operates in the converter 2 after being operated for a certain period as shown in FIG. Large-scale repairs, such as replacing refractory bricks, "furnace repairs" are being carried out. When the life of the converter 2 is converted to days, it is roughly 150 days, but the furnace repair is about 20 days. Moreover, it is normal that about 5000 charge is performed within one converter lifetime.

加えて、通常の転炉操業においては、転炉2に対する地金取りや孔巻き、耐火物の補修などの補修作業が随時行われ、これらの作業は転炉2の安定操業のためには必須である。
ここでいう地金取り作業とは、転炉2の溶銑装入口近傍にスロッピング等により溶銑が固着し地金となっており、この地金を除去する作業である。約10チャージに1回程度行われるもので約30分程度の時間を有する。
孔巻き作業とは、転炉2の出銑口の耐火レンガが溶鋼により徐々に劣化していくため、所定間隔で、かかる耐火レンガを取り替える作業である。孔巻き作業は約100チャージに1回行われるものであり、約60分の作業時間を必要とする。
In addition, in normal converter operation, repair work such as metal removal, hole winding, and refractory repair for the converter 2 is performed as needed. These operations are essential for stable operation of the converter 2. It is.
The bullion removing operation referred to here is an operation of removing the bullion because the molten iron is fixed to the vicinity of the molten metal inlet of the converter 2 by slapping or the like. This is performed about once every 10 charges and has a time of about 30 minutes.
The hole winding operation is an operation of replacing the refractory bricks at predetermined intervals because the refractory bricks at the outlet of the converter 2 are gradually deteriorated by the molten steel. The hole winding operation is performed once for about 100 charges, and requires an operation time of about 60 minutes.

耐火レンガ(耐火物)の補修は、転炉2の内壁に耐火補修材を吹き付けるなどして簡易的ながら炉寿命を大幅に向上させる修理であって、約10チャージ毎に行われ、1回の補修に約30分の時間を必要とする。
図2,図3は、図1(b)を詳しくしたものであり、転炉2の操業状況をミクロ視したもので、本実施形態における3基の転炉2でのチャージの順番を示したものである。
まず、第1の転炉2(転炉A)での吹錬が終了する前に、第2の転炉2(転炉B)での吹錬を開始するように設定し、第3の転炉2(転炉C)の吹錬開始を、第2の転炉2での吹錬が終了する前で、且つ第1の転炉2での前回吹錬終了〜次回吹錬開始の間に設定している。
Repair of refractory bricks (refractories) is a simple repair that greatly improves the life of the furnace by spraying fireproof repair material on the inner wall of the converter 2, and is performed once every 10 charges. Repair takes about 30 minutes.
2 and 3 are detailed views of FIG. 1 (b), which are microscopic views of the operation status of the converter 2, and show the order of charging in the three converters 2 in the present embodiment. Is.
First, before the end of blowing in the first converter 2 (converter A), the second converter 2 (converter B) is set to start blowing, and the third converter Blowing start of the furnace 2 (converter C) is performed before the end of blowing in the second converter 2 and between the end of the previous blowing in the first converter 2 and the start of the next blowing. It is set.

詳しくは、転炉Aでは、時間0minの前から溶銑装入が開始され、時間0minを過ぎたあたりで吹錬が開始される。吹錬は20min過ぎに終了し、その後、溶鋼の払い出しが行われ、30min過ぎに出鋼が完了する。
転炉Bでは、時間10minの前から溶銑装入が開始され、時間10minを過ぎたあたりで吹錬が開始される。吹錬は30min過ぎに終了し、その後、溶鋼の払い出しが行われ、40min過ぎに出鋼が完了する。図からわかるように、転炉Bでの吹錬の開始は転炉Aの吹錬途中であり、時間10min〜20minの間では、転炉A,Bの両者で吹錬が行われるものとなっている。
Specifically, in the converter A, the hot metal charging is started before the time 0 min, and the blowing is started around the time 0 min. Blowing ends after 20 minutes, and then the molten steel is dispensed, and the steel output is completed after 30 minutes.
In the converter B, the hot metal charging is started before the time 10 minutes, and the blowing is started around the time 10 minutes. Blowing ends after 30 minutes, and then the molten steel is dispensed, and the steel output is completed after 40 minutes. As can be seen from the figure, the start of the blowing in the converter B is in the middle of the blowing of the converter A, and during the time of 10 min to 20 min, the blowing is performed in both the converters A and B. ing.

転炉Cでは、時間20minの前から溶銑装入が開始され、時間25minあたりで吹錬が開始される。吹錬は45min過ぎに終了し、その後、溶鋼の払い出しが行われ、55min過ぎに出鋼が完了する。転炉Cでの吹錬の開始は転炉Bの吹錬途中であると共に、転炉Aでの吹錬終了後である。すなわち、吹錬が行われる順番はA0→B0→C0であり、図上で右斜め下がりの矢印上に並ぶものとなっている。
さらに、当該転炉Cでの吹錬が終了する前に、再び転炉Aへの溶銑装入が開始され、それに続いて吹錬が行われるようになる。その後同様に、転炉Aでの吹錬途中に、転炉Bでの吹錬が開始され、転炉Bの吹錬途中であって転炉Aの吹錬終了後に、転炉Cでの吹錬が開始されるようになっている。つまり、吹錬が行われる順番はA1→B1→C1であり、図上で右斜め下がりの矢印上に並ぶものとなる。
In the converter C, the hot metal charging is started before 20 minutes, and blowing is started around 25 minutes. Blowing ends after 45 minutes, and then the molten steel is dispensed, and the steel output is completed after 55 minutes. The start of blowing in the converter C is during the blowing of the converter B and after the end of the blowing in the converter A. That is, the order in which blowing is performed is A0->B0-> C0, and is lined up on the diagonally downward arrow in the figure.
Further, before the blowing in the converter C is completed, the hot metal charging into the converter A is started again, and the blowing is performed subsequently. Similarly, in the middle of blowing in the converter A, the blowing in the converter B is started. In the middle of the blowing of the converter B and after the completion of the blowing of the converter A, the blowing in the converter C is performed. Alchemy is to be started. That is, the order in which blowing is performed is A1 → B1 → C1, and is arranged on an arrow that is slanted to the right in the figure.

このようにすることで、いかなるフェーズ(時間)においても、吹錬中の転炉2は2基であり、転炉周辺設備7の能力を超えるものとはなっていない。しかしながら、マクロ的に見ると、図1(a)の如く、3基が同時に稼働している3/3基稼働期間となっており、溶銑生産能力が著しく向上可能な状況となっている。図3においては、約35分間の間に3回の吹錬開始が含まれているため、本稼働状態の転炉設備1は、35分で3チャージ、すなわち1時間で5チャージの生産能力を有していることになる。
図3の吹錬A0を含むチャージに着目してみると、かかる吹錬A0の開始から、次チャージでの吹錬A1の開始との間には、転炉Bの吹錬開始と転炉Cの吹錬開始がそれぞれ1回ずつ存在することがわかる。このような状況下にあるチャージを「順次稼働している転炉」におけるチャージであると定義する。加えて、3基の転炉2による全チャージ数に対する、順次稼働している転炉のチャージ数を「順次稼働比率」と定義するようにする。
By doing in this way, in any phase (time), there are two converters 2 during blowing, which does not exceed the capacity of the converter peripheral equipment 7. However, when viewed macroscopically, as shown in FIG. 1A, it is a 3/3 unit operation period in which three units are operating at the same time, and the hot metal production capacity can be significantly improved. In FIG. 3, since the start of three blows is included in about 35 minutes, the converter 1 in the operational state has a production capacity of 3 charges in 35 minutes, that is, 5 charges in 1 hour. Will have.
When attention is paid to the charge including the blowing A0 in FIG. 3, the start of the blowing of the converter B and the converter C between the start of the blowing A0 and the start of the blowing A1 in the next charge. It can be seen that there is one start of blowing each. A charge under such circumstances is defined as a charge in a “sequentially operating converter”. In addition, the number of charges of the converters that are operating sequentially with respect to the total number of charges of the three converters 2 is defined as the “sequential operation ratio”.

この順次稼働比率が上がれば上がるほど、3基の転炉2が待ち時間なく稼働していることになり、理論上は溶銑生産能力が向上することになる。
しかしながら、現実には、前述した「転炉の補修」のための時間(期間)が必ず必要であり、転炉2の順次稼働比率が大きい場合、これらの補修時間を確保することが困難となり、溶鋼生産性が落ちるようになる。
本実施形態の場合は、溶鋼生産性のシミュレーション結果である図5のグラフIIから明らかなように、3基の転炉2の順次稼働比率を40%〜95%の間としている。より好ましくは50%〜90%の範囲とするとよく、順次稼働比率を75%とすることで生産性の最大値を得ることができるようになる。
As this sequential operation ratio increases, the three converters 2 are operating without waiting time, and theoretically, the hot metal production capacity is improved.
However, in reality, the time (period) for the above-mentioned “repair of the converter” is necessarily required, and when the sequential operation ratio of the converter 2 is large, it becomes difficult to secure these repair times, Molten steel productivity falls.
In the case of this embodiment, the sequential operation ratio of the three converters 2 is set between 40% and 95%, as is apparent from the graph II of FIG. 5 which is a simulation result of molten steel productivity. More preferably, it is in the range of 50% to 90%, and the maximum value of productivity can be obtained by sequentially setting the operation ratio to 75%.

また、本実施形態では、かかる補修時間を確実に得るために、図6に示すように、A→B→Cと続いていた転炉2の稼働順番をC→B→Aと変えることで、転炉Aに補修を行うことのできる時間を作るようにしている。つまり、転炉Cを稼働した後、転炉Bを稼働させ、その後転炉Aを稼働させることで、転炉Aにおける1チャージ分の製鋼時間に近い時間を非稼働状態とでき、その期間を補修時間とするようにしている。
一方、転炉2の補修作業に関しては、補修の後すぐに転炉2を稼働させるのではなく、所定時間何もせず放置し、吹き付けた補修材が確実に内壁を補修するに必要な時間を確保することもある。これを静置時間という。加えて、通常の補修以上の修理を行うことがありそのための修理時間を必要とすることがある。
Further, in the present embodiment, in order to reliably obtain such repair time, as shown in FIG. 6, by changing the operation order of the converter 2 that has continued from A → B → C from C → B → A, The converter A has time for repairs. That is, after operating the converter C, operating the converter B, and then operating the converter A, the time close to the steel making time for one charge in the converter A can be set in a non-operating state, and the period is It is set as repair time.
On the other hand, regarding the repair work of the converter 2, the converter 2 is not operated immediately after the repair, but is left for a predetermined period of time and the time required for the repair material sprayed to repair the inner wall reliably. It may be secured. This is called standing time. In addition, repairs beyond normal repairs may be performed and repair time may be required.

これら静置時間や修理時間を転炉Bで確保するためには、図7に示すように、A→B→Cと続いていた転炉2の稼働順番を一旦、C→AとしてBをとばした形に変え、その後C→B→Aと逆順にすることで、転炉Bに補修、静置、修理の時間を確保するようにしている。
なお、以上述べた補修時間は、図9に示すように、T/4〜3Tの範囲内とすることで、補修効果を適切なものとしつつ、地金取り作業の時間増加を防ぐことができるようになる。より好ましくは、補修時間をT/4〜1.5Tとするとよい。
In order to secure these stationary time and repair time in the converter B, as shown in FIG. 7, the operation order of the converter 2 that has continued from A → B → C is temporarily changed to C → A and B is skipped. In the reverse order of C → B → A after that, the converter B is secured for repair, stationary, and repair time.
The repair time described above is within the range of T / 4 to 3T, as shown in FIG. 9, so that the repair effect can be made appropriate and an increase in the time for the bullion collecting operation can be prevented. It becomes like this. More preferably, the repair time is set to T / 4 to 1.5T.

以上述べた転炉2の操業方法は、1つの転炉2で脱りんと脱炭を行う、いわゆるダブルスラグ法を行っている転炉設備1にも適用可能である。
ダブルスラグ法とは、1つの転炉2において溶銑中のりんPを取る「脱りん工程」と炭素を取る「脱炭工程」とを行うものである。
脱りん工程は、転炉2の炉口からランスを挿入し、溶銑上面に近づけ、酸素ガスを吹き付けると同時に、炉底から吹き込みガスで溶銑を撹拌しつつ精錬(吹錬)を行う。同時に、石灰CaO等の造滓材や酸化鉄Fexy等の冷却材、すなわち副原料を投入することで、りんPは投入された酸素と反応してスラグ相に移行し、溶銑の上方に浮いた状態で積層するようになる。このスラグの中には未反応のCaOが多く含まれるため、脱りん能力を有するものとなっている。
The operation method of the converter 2 described above can also be applied to the converter facility 1 performing a so-called double slag method in which dephosphorization and decarburization are performed in one converter 2.
The double slag method is to perform a “dephosphorization step” for removing phosphorus P in the molten iron and a “decarburization step” for removing carbon in one converter 2.
In the dephosphorization step, a lance is inserted from the furnace port of the converter 2 and is brought close to the upper surface of the hot metal, and oxygen gas is blown. At the same time, refining (blowing) is performed while the hot metal is stirred from the bottom of the furnace. At the same time, the coolant such as the slag forming and iron oxide Fe x O y, such as lime CaO, i.e. by turning on the auxiliary materials, phosphorus P is shifted to the slag phase to react with the entered oxygen, above the hot metal Laminate in a floating state. Since this slag contains a lot of unreacted CaO, it has a dephosphorization ability.

次に、脱りん工程により生成されたスラグを、転炉2を炉前側へ傾けることで、外部に排出するようにしている。排出されたスラグは、転炉2下方に配置された移送手段により運び出されるようになっている(排出工程)。
排出工程を経た転炉2は、再び元の姿勢に戻され、酸素吹き込みや副原料の投入をなされることで、主に溶銑中の炭素Cを取り除く脱炭工程へと進む。脱炭工程後は、転炉2を傾動させ、転炉2の上部側方に設けられた出鋼口より溶鋼を外へ流し出すようにしている。その際、脱炭工程で生成されたスラグを残すことも可能であり、次に精錬する溶銑を装入するようにする(次チャージの装入工程)。このようにすることで、脱りん能力が十分にあるスラグを前チャージスラグとしてリサイクルさせて有効利用し、廃棄スラグ量を減少することが可能である。
Next, the slag produced by the dephosphorization process is discharged to the outside by tilting the converter 2 toward the furnace front side. The discharged slag is carried out by the transfer means arranged below the converter 2 (discharge process).
The converter 2 that has undergone the discharge process is returned to its original position again, and then proceeds to a decarburization process that mainly removes carbon C in the molten iron by blowing oxygen and adding auxiliary materials. After the decarburization step, the converter 2 is tilted so that the molten steel flows out from a steel outlet provided on the upper side of the converter 2. At that time, it is possible to leave the slag generated in the decarburization process, and the hot metal to be refined next is charged (charging process of the next charge). By doing so, it is possible to recycle slag having sufficient dephosphorization ability as the precharge slag and effectively use it, thereby reducing the amount of waste slag.

図10は、ダブルスラグ法を行っている転炉A,Bに図3のチャージスケジュールを採用したものである。
ダブルスラグ法は通常の転炉2における吹錬工程と比して、約8分程度の処理時間延長(図10のEXT)を伴うのみであるため、転炉2をA→B→Cと順次稼働したとしても、例えば、転炉Aでの前回の出鋼終了と次回の溶銑装入とがほぼ同時刻になるのみで、両工程が重なることはない。
以上述べた転炉2の操業方法を適用した場合、3基の転炉2はフル稼働に近い状況となり、転炉2にスクラップ等を装入する装入クレーン4の能力が、転炉稼働のサイクルに追いつかない場合がある。そのような際は、転炉2にスクラップを装入することなく、全て高炉から搬送されてくる溶銑を用いて操業を行うようにするとよい。
FIG. 10 employs the charge schedule of FIG. 3 for converters A and B performing the double slag method.
Since the double slag method only involves a processing time extension of about 8 minutes (EXT in FIG. 10) compared with the blowing process in the ordinary converter 2, the converter 2 is sequentially changed from A → B → C. Even if it is in operation, for example, the end of the last steel output in the converter A and the next hot metal charging are almost the same time, and both processes do not overlap.
When the operation method of the converter 2 described above is applied, the three converters 2 are almost in full operation, and the capacity of the charging crane 4 for charging the converter 2 with scraps or the like is You may not be able to keep up with the cycle. In such a case, the operation may be performed using the hot metal conveyed from the blast furnace without charging scrap into the converter 2.

また、転炉2の操業においては、ランスが装入口から挿入できないなどの転炉周辺設備7の故障が発生することがある。そのような場合、その修理は、短時間(30分程度)で済むこともあれば比較的長い時間(例えば5時間以上)かかることもある。
そこで、転炉周辺設備7の修理時間が短時間である場合は、3/3基稼働とした上で、本実施形態で述べたように、チャージの順番を逆順とするなどして補修時間を確保し、この補修時間を転炉周辺設備7の修理時間として利用すると、溶鋼生産性の観点からは非常に有利である。
Further, in the operation of the converter 2, there may be a failure of the converter peripheral equipment 7 such that the lance cannot be inserted from the loading port. In such a case, the repair may take a short time (about 30 minutes) or may take a relatively long time (for example, 5 hours or more).
Therefore, when the repair time of the converter peripheral equipment 7 is short, the repair time is reduced by, for example, reversing the charge order as described in the present embodiment after the 3/3 operation. If it is ensured and this repair time is used as the repair time of the converter peripheral equipment 7, it is very advantageous from the viewpoint of molten steel productivity.

一方、転炉周辺設備7の修理時間が5時間以上かかるような場合は、逆順などで修理時間を確保するよりは、修理に該当する転炉2を休止し、炉修の際と同じように2基の転炉2を稼働状態(2/3基稼働)とすると、溶鋼生産性の観点から有利である。転炉周辺設備7の修理時間を確保すべく、転炉2を3/3基稼働とするか2/3基稼働とするかの境としては、転炉2の再稼働時の昇温に必要な約3時間を採用し「修理時間=3時間」を境界値とすることが好ましい。
なお、本発明の転炉2への溶銑供給方法は、上記実施の形態に限定されるものではない。また、転炉2は上吹き転炉、底吹き転炉、又は上底吹き転炉のいずれであってもよい。
On the other hand, when the repair time of the converter peripheral equipment 7 takes 5 hours or more, rather than securing the repair time in the reverse order or the like, the converter 2 corresponding to the repair is suspended and the same as in the repair of the furnace. It is advantageous from the viewpoint of molten steel productivity when the two converters 2 are in an operating state (2/3 operation). In order to secure the repair time for the converter peripheral equipment 7, the boundary of whether the converter 2 is operated by 3/3 or 2/3 is necessary for the temperature rise when the converter 2 is restarted. Preferably, about 3 hours are adopted, and “repair time = 3 hours” is set as the boundary value.
In addition, the hot metal supply method to the converter 2 of this invention is not limited to the said embodiment. Further, the converter 2 may be any one of a top blowing converter, a bottom blowing converter, and an upper bottom blowing converter.

本発明にかかる転炉操業の順番を示したものであり、(a)はマクロ的に見たもの、(b)はミクロ的に見たものである。The order of the converter operation concerning this invention is shown, (a) was seen macroscopically, (b) was seen microscopically. 転炉のチャージの順番を示した図である。It is the figure which showed the order of the charge of a converter. 転炉のチャージの順番を示した図である。It is the figure which showed the order of the charge of a converter. 転炉の順次稼働比率と溶鋼生産性との関係のシミュレーション結果である。It is the simulation result of the relationship between the sequential operation ratio of a converter and molten steel productivity. 転炉の順次稼働比率と溶鋼生産性との関係を示した図である。It is the figure which showed the relationship between the sequential operation ratio of a converter, and molten steel productivity. 転炉のチャージの順番を示した図である(逆順の場合)。It is the figure which showed the order of the charge of a converter (in the case of reverse order). 転炉のチャージの順番を示した図である(逆順、静置時間ありの場合)。It is the figure which showed the order of the charge of a converter (in the case of reverse order and stationary time). 補修時間と補修効果ならびに地金取り時間との関係のシミュレーション結果である。It is a simulation result of the relationship between repair time, repair effect and bullion collection time. 補修時間と補修効果ならびに地金取り時間との関係を示した図である。It is the figure which showed the relationship between repair time, repair effect, and bullion taking time. ダブルスラグ法を使用した際における転炉のチャージの順番を示した図である。It is the figure which showed the order of the charge of the converter at the time of using a double slag method. 従来及び本発明にかかる転炉設備の正面概略図である。It is the front schematic of the converter equipment concerning the past and this invention. 従来の転炉操業の順番を示したものであり、(a)はマクロ的に見たもの、(b)はミクロ的に見たものである。The order of the conventional converter operation is shown, (a) is a macro view, and (b) is a micro view.

符号の説明Explanation of symbols

1 転炉設備
2 転炉
7 転炉周辺設備
1 Converter 2 Converter 7 Converter peripheral equipment

Claims (5)

溶銑の吹錬を行う3基の転炉と、最大2基の転炉を吹錬可能とする能力を備えた転炉周辺設備とを有する転炉設備で、
前記転炉周辺設備の能力を超えずに3基の転炉を操業すべく、各転炉のチャージの順番を、第1の転炉での吹錬が終了する前に、第2の転炉での吹錬を開始するように設定し、第3の転炉の吹錬開始を、第2の転炉での吹錬が終了する前で且つ第1の転炉での前回吹錬終了〜次回吹錬開始の間に設定していることを特徴とする転炉の操業方法。
A converter facility that has three converters that perform hot metal blowing and converter peripheral facilities that are capable of blowing up to two converters.
In order to operate the three converters without exceeding the capacity of the converter peripheral equipment, the order of the charge of each converter is changed to the second converter before the blowing in the first converter is completed. Was set to start blowing at the end of the third converter, before the end of the blowing at the second converter and the end of the previous blowing at the first converter The operation method of the converter, which is set during the next start of blowing.
1の転炉の前回吹錬開始と次回吹錬開始との間に他の2つの転炉の吹錬開始がそれぞれ1回ずつ存在する状況を順次稼働状況とし、前記第1〜第3の転炉の少なくとも1つが該順次稼働状況を有することを特徴とする請求項1に記載の転炉の操業方法。   The situation in which the other two converters start blowing each time between the start of the previous one and the next start of the next converter is sequentially designated as the operating state, and the first to third converters The method of operating a converter according to claim 1, wherein at least one of the furnaces has the sequential operation state. 前記順次稼働状況となっている転炉のチャージ数が、全チャージ数に占める割合を転炉の順次稼働比率とし、この転炉の順次稼働比率が40%〜95%となるように3基の転炉を操業することを特徴とする請求項2に記載の転炉の操業方法。   The ratio of the number of charges of the converter in the sequential operation state to the total number of charges is defined as the sequential operation ratio of the converter, and three converters are set so that the sequential operation ratio of the converter is 40% to 95%. The converter operation method according to claim 2, wherein the converter is operated. 前記転炉の内壁に対する簡易的な修理である「補修」を行うに必要とされる補修時間を確保すべく、第1→第2→第3としていた転炉の操業順序を逆順にすることを特徴とする請求項1〜3のいずれかに記載の転炉の操業方法。   In order to secure the repair time required for performing “repair”, which is a simple repair to the inner wall of the converter, the operation sequence of the converter, which is the first → second → third, is reversed. The operating method of the converter in any one of Claims 1-3 characterized by the above-mentioned. 前記補修時間を、T/4〜3Tの範囲内(Tは製鋼時間)としていることを特徴とする請求項4に記載の転炉の操業方法。   The method for operating a converter according to claim 4, wherein the repair time is set within a range of T / 4 to 3T (T is a time for steelmaking).
JP2004304862A 2004-10-19 2004-10-19 Converter operation method Expired - Fee Related JP4057005B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004304862A JP4057005B2 (en) 2004-10-19 2004-10-19 Converter operation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004304862A JP4057005B2 (en) 2004-10-19 2004-10-19 Converter operation method

Publications (2)

Publication Number Publication Date
JP2006117972A JP2006117972A (en) 2006-05-11
JP4057005B2 true JP4057005B2 (en) 2008-03-05

Family

ID=36536126

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004304862A Expired - Fee Related JP4057005B2 (en) 2004-10-19 2004-10-19 Converter operation method

Country Status (1)

Country Link
JP (1) JP4057005B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011190501A (en) * 2010-03-15 2011-09-29 Kobe Steel Ltd Method for operating converter facility
JP2011190500A (en) * 2010-03-15 2011-09-29 Kobe Steel Ltd Converter facility operation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011190501A (en) * 2010-03-15 2011-09-29 Kobe Steel Ltd Method for operating converter facility
JP2011190500A (en) * 2010-03-15 2011-09-29 Kobe Steel Ltd Converter facility operation method

Also Published As

Publication number Publication date
JP2006117972A (en) 2006-05-11

Similar Documents

Publication Publication Date Title
US9932649B2 (en) Fixed-type electric furnace and molten steel production method
CA2332153C (en) A method of relining a vessel
CN101886150A (en) Recycling method and system for steel ladle pouring afterheat-state steel slag
JP5526565B2 (en) Converter steelmaking
JP2020180322A (en) Production method of molten steel using converter
JP4057005B2 (en) Converter operation method
CN111801431A (en) Melting plants for steel production
US20060272447A1 (en) Continuous steel production and apparatus
JP4353880B2 (en) Converter operation method
CN117943532A (en) 220T hot-metal bottle mouth masonry method
JP7311771B2 (en) Method of melting iron-containing materials
JP7508022B2 (en) Refining Method
JP2007113029A (en) Converter refining method and converter refining equipment
JP6492820B2 (en) Converter operation method
JP5526564B2 (en) Converter steelmaking
JPH01234510A (en) Method for starting reblowing in dead blast furnace
JP7667423B2 (en) Method for producing molten steel and method for removing slag
JP4484717B2 (en) How to operate steelmaking equipment
JP2000146452A (en) Fixed smelting furnace
Peter et al. Introduction of a novel, scrap-based, fully continuous steelmaking process
RU2787016C2 (en) Melting unit for steel production
Lückhoff et al. WIRLD’S FIRST EAF QUANTUM
CN115478124A (en) Recycling method of converter splashed objects
US6004369A (en) Steel production method
AU2004242510B2 (en) A method of relining a vessel

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071211

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071212

R150 Certificate of patent or registration of utility model

Ref document number: 4057005

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101221

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101221

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111221

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121221

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131221

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees