JP4061362B2 - Repair method for concrete viaduct - Google Patents
Repair method for concrete viaduct Download PDFInfo
- Publication number
- JP4061362B2 JP4061362B2 JP2002254194A JP2002254194A JP4061362B2 JP 4061362 B2 JP4061362 B2 JP 4061362B2 JP 2002254194 A JP2002254194 A JP 2002254194A JP 2002254194 A JP2002254194 A JP 2002254194A JP 4061362 B2 JP4061362 B2 JP 4061362B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- coating layer
- viaduct
- primer
- aerial work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明はコンクリート製の高架橋の補修方法に関するものである。
【0002】
【従来の技術】
コンクリート製の高架橋は劣化により損傷するため、その補修が必要になってくる。例えば、大半がコンクリート製の高架橋である高速道路の高欄、桁および橋脚などは、コンクリートの中性化とひび割れによる水分の浸透によって遊離石灰が流失したり、鉄筋が腐食、膨張して被りコンクリートを浮き上がらせて落下させるという問題があった。
【0003】
このような場合、コンクリートの劣化進行を抑制するとともにコンクリート片が落下するのを防ぐため、高欄、桁および橋脚などの表面を塗装したり、FRPで補修したりしている。また前記高欄の外面と水切部についてはFRP補修とコンクリート塗装とを併用した補修が行われている。
【0004】
この補修は、図6および下記の表1に示したように、高欄20の素地調整21から上塗工22まで8つの工程23をそれぞれ手作業で行なっており、各工程の間には時間単位あるいは日単位の塗装間隔を空けている。
【0005】
【表1】
【0006】
【発明が解決しようとする課題】
しかし、上記のコンクリート製の高架橋の補修方法は、材料の伸びが2%程度と非常に少なく、例えば高欄の亀裂などに対しては追従性がないため、その亀裂とともにひび割れが発生し、該ひび割れ部から浸透した雨水により鉄筋が腐食したり、コンクリートの遊離石灰が流失したり、被りコンクリート片が落下するという問題があった。また、床版下面の水切りは、床版下面に切込みを入れて形成するため、該切込部に亀裂が発生するという問題があった。また、従来の補修材料はプライマー、含浸材、中塗材および上塗材の養生期間が長いため施工期間が長くなって交通規制が長期にわたるという問題があった。さらに、従来の補修方法は、補修後のコンクリート表面の見栄えが悪く、美観を損なうという問題があった。
【0007】
本発明はこのような問題に鑑みてなされたものであり、その目的は、短期間で補修ができるとともに、高欄などの亀裂に対する追従性がよく、水切り部に亀裂を発生させず、しかも補修表面の美観が保てるコンクリート製の高架橋の補修方法を提供することである。
【0008】
以上の課題を解決するための本願発明のコンクリート製の高架橋の補修方法は、コンクリート製の高架橋の劣化部を除去し、該除去部に樹脂モルタルを詰めて平滑にして、その表面にプライマーを塗布するとともに、該プライマーの上から指触乾燥時間が8〜20秒の超速硬化性樹脂をスプレーガンでミスト状に吹き付け塗布して被覆層を形成し、該被覆層の表面に上塗層を塗布した後、該上塗層と被覆層との端部にシーリング材を充填したことを特徴とする。また超速硬化性樹脂は伸び率が350〜410%であることを含むものである。
またコンクリート製の高架橋の補修方法は、コンクリート製の高架橋の下側における道路に複数台の高所作業車を適宜間隔をもって連ね、先頭の高所作業車で高架橋表面の素地調整を行い、次の高所作業車でプライマーの塗布を行い、次の高所作業車でプライマーの上から指触乾燥時間が8〜20秒の超速硬化性樹脂をスプレーガンでミスト状に吹付塗布して被覆層を形成し、次の高所作業車で被覆層への上塗層の吹き付け塗布および、該上塗層と被覆層との端部にシーリング材の充填を行うことを特徴とする。また超速硬化性樹脂は伸び率が350〜410%であることを含むものである。
【0009】
コンクリート製の高架橋の補修が短期間でかつ簡単にできるとともに、高欄などの亀裂に対する追従性がよいためコンクリートの劣化部分の落下などを防ぐことができ、かつ補修表面の美観を損なうことがない。また複数台の高所作業車を連続して用いて各作業車で1工程または2工程の作業を行うことにより、効率の良い施工作業ができるとともに、作業の短縮化および交通規制の短期化を図ることができる。
【0014】
【発明の実施の形態】
以下、本発明における実施の形態を図面に基づいて詳細に説明する。
図1の(1)は高架橋である高速道路の高欄および床版下部の補修方法の断面図、(2)は交通規制を示した平面図、図2は複数の高所作業車と高速道路の平面図、図3の(1)は補修部位の断面図、(2)は同拡大断面図を示したものである。
【0015】
この補修方法は図1の(1)に示すように、高速道路の高架橋1の下側における道路2から4台の高所作業車3を用いて行い、先頭の高所作業車3aで高欄4外面および床版5下面の素地調整を行い、2台目の高所作業車3bで水切用突起6の取り付けとプライマー7の塗布を行い、3台目の高所作業車3cで被覆層8の吹付け塗布を行い、4台目の高所作業車3dで上塗層9の吹き付けまたは手塗り塗布を行う。この高所作業車3は車体の定位置で前後各約10mの施工が可能であるため、約20m間隔をあけて連続的に作業を行う。
【0016】
また、これらの高所作業車3が作業している間は、図1の(2)に示すように交通規制10が行われる。
【0017】
この作業は、図2に示すように、先頭の高所作業車3aにより、高欄4の表面を十分に清掃して砂塵およびその他の有害な物質を除去するとともに、エポキシ樹脂系(例えば、ボンドE-350:三井化学製)のパテ材(図示せず)でジャンカなどの素地調整処理を行い、床版5の下部に硬質ウレタン発泡材、ウレタン合成木材、プラスチック材などで水切用突起6を設ける。
【0018】
次に、2台目の高所作業車3bにより、素地調整処理が行われたコンクリート表面にウレタン樹脂系(例えばサンPC-F/セメント:三井化学製)のプライマー7の吹き付けまたは手塗り塗布を行う。
【0019】
そして、3台目の高所作業車3cにより、前記プライマー7の表面にポリウレタン系吹付樹脂(例えばリムスプレーF−1000:三井化学社製)や、ポリウレア系吹付樹脂(例えばスワエール:三井石化産資社製)などの超速硬化性樹脂材を吹き付けて所定厚の被覆層8を形成する。
【0020】
次に、前記被覆層8の形成後に、4台目の高所作業車3dにより上塗層9の吹き付けまたは手塗り塗布を行うとともに、この被覆層8と上塗層9との端部にシリコーン系、ポリサルファイド系、ポリウレタン系などのシーリング材11を塗布する。
【0021】
前記リムスプレーF−1000(三井化学社製)は、下記の表2のように、指触乾燥時間が8〜20秒、硬化時間が30分、伸び率が350〜410%という物性を備えている。
【0022】
【表2】
【0023】
リムスプレーF−1000(三井化学社製)は、主材のイソシアネート成分12に硬化剤13としての特殊混合レジンを1対1の配合比(容積比)で混合した超速硬化型の吹付樹脂であり、図4に示すように、前記の2液がドラムポンプ14から2成分系の高圧定量ポンプ15に送られて60〜200kg/cm2に加圧される。これらの2液は、吹付機械を内蔵したヒータ16で各々加熱され、ヒータ付ホース17を介して2液衝突混合型のスプレーガン18に送られ、ここで衝突混合されながらミスト状態で吹き付けられると同時に硬化して塗膜を形成する。
【0024】
この吹き付け方法は、図1に示すように、路肩に配置した高所作業車3に搭載した吹付機械(図示せず)からヒータ付ホース17を施工位置まで伸ばし、その先端のスプレーガン18を作業者19が持って行う。
【0025】
このように機械で吹付施工することにより施工能率の向上が図れ、しかも超速硬化性樹脂であるため吹き付けと同時に硬化して、垂直面および天井面での垂れが発生せずに継目のない被覆層8が形成できる。
【0026】
またその他、ダイフレックス防水工事業協同組合のクイックスプレーSP−100、200、旭硝子コートアンドレジン社製のサレセーヌS、保土ヶ谷建材社製のHCスプレー、日本特殊塗料社製のスプレーニュータック、ニッタ社製のニッテック、大日本インキ社製のステラコート、東洋ゴム工業社製のソフランレック400、三井石化産資社製のスワエール、横浜ゴム社製のアーバンルーフU-3000Jなどの超速硬化性樹脂を使用することもできる。
【0027】
最後に、この被覆層8の表面に耐紫外線保護材としてアクリルウレタン塗料およびフッ素塗料などで上塗層9を吹き付け/手塗り塗布する。
【0028】
下記の表3は従来のコンクリート塗装における塗装材料の規格と、本発明の補修方法による塗膜の試験結果とを比較したものである。このうち試験材令は、コンクリート塗料材料が28日であるのに対して、本発明のポリウレタン系樹脂膜は7日としている。これはポリウレタン系樹脂膜の物性が材令7日で安定することによる。またコンクリート塗装材料に関する規格による屋外暴路1年後の試料に対する試験として、ポリウレタン系樹脂膜はウエザー・オ・メータによる1000時間促進試験(換算年数4年)の結果を示している。
【0029】
【表3】
【0030】
また、以下の表4は本発明による高欄の補修方法と、従来の高欄の補修方法ととを比較したものである。この結果、本発明の補修方法が従来の補修方法と比べて優れていることを確認することができた。
【0031】
【表4】
【0032】
【発明の効果】
コンクリート製の高架橋の補修が短期間でかつ簡単にできるとともに、高欄などの亀裂に対する追従性がよいためコンクリートの劣化部分の落下などを防ぐことができ、かつ補修表面の美観を損なうことがない。
【0033】
床版下面の水切りを水切用突起で行うことにより、水切部の亀裂を防ぐことができる。
【0034】
複数の高所作業車を連続して用いて各作業車で1工程または2工程の作業を行うことにより、効率の良い施工作業ができるとともに、作業の短縮化および交通規制の短期化を図ることができる。
【図面の簡単な説明】
【図1】(1)は高速道路の高欄の補修方法を示す断面図、(2)は交通規制範囲を示した平面図である。
【図2】複数の高所作業車と高速道路の平面図である。
【図3】(1)は補修部位の断面図、(2)は同拡大断面図である。
【図4】 吹付機械の概略図である。
【図5】(1)および(2)は高速道路の高欄の補修方法を示した断面図である。
【図6】(1) は高速道路の高欄および床版下部の従来の補修方法を示す断面図、(2)は従来の補修方法による補修部位の膜層の断面図である。
【符号の説明】
1 高架橋
2 道路
3 高所作業車
4、20 高欄
5 床版
6 水切用突起
7 プライマー
8 被覆層
9 上塗層
10 交通規制
11 シーリング材
12 イソシアネート成分
13 硬化剤
14 ドラムポンプ
15 高圧定量ポンプ
16 ヒータ
17 ヒータ付ホース
18 スプレーガン
19 作業者
21 素地調整
22 上塗[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for repairing a concrete viaduct.
[0002]
[Prior art]
Since concrete viaducts are damaged by deterioration, they need to be repaired. For example, railroads, girders and piers on expressways, which are mostly viaducts made of concrete, are washed away by free lime due to the neutralization of concrete and the penetration of moisture due to cracks, and the reinforcing bars corrode and expand. There was a problem of rising and dropping.
[0003]
In such a case, surfaces such as railings, girders and bridge piers are painted or repaired with FRP in order to suppress the deterioration of concrete and prevent the concrete pieces from falling. In addition, the outer surface of the balustrade and the drainage portion are repaired using both FRP repair and concrete coating.
[0004]
In this repair, as shown in FIG. 6 and Table 1 below, eight steps 23 from the
[0005]
[Table 1]
[0006]
[Problems to be solved by the invention]
However, the above-mentioned concrete viaduct repair method has an extremely low material elongation of about 2%, and has no followability to cracks in the railing, for example, and cracks are generated along with the cracks. There was a problem that the reinforcing bar was corroded by the rainwater permeated from the part, the free lime of the concrete was washed away, and the covered concrete piece dropped. Further, since the draining of the bottom surface of the floor slab is formed by making a cut on the bottom surface of the floor slab, there is a problem that a crack occurs in the notched portion. In addition, the conventional repair material has a problem that the construction period becomes longer due to a long curing period of the primer, the impregnating material, the intermediate coating material, and the top coating material, and the traffic regulation is prolonged. Furthermore, the conventional repair method has a problem that the concrete surface after repair is not good in appearance and the appearance is impaired.
[0007]
The present invention has been made in view of such problems, and its purpose is to repair in a short period of time, and to have good followability to cracks such as railings, and does not cause cracks in the drainage part, and the repair surface It is to provide a concrete viaduct repair method that can maintain the beauty of
[0008]
In order to solve the above problems, the method for repairing a concrete viaduct according to the present invention is to remove a deteriorated part of a concrete viaduct, smooth the resin mortar by filling the removed part, and apply a primer to the surface. as well as, tack time to form a coating to the coating layer sprayed mist spray gun 8 to 20 seconds of ultra fast curing resin from above of the primer, a topcoat layer on the surface of the coating layer applied After that, a sealing material is filled in the end portions of the top coat layer and the coating layer. The ultra-fast curable resin includes an elongation percentage of 350 to 410% .
In addition, the concrete viaduct repair method is to connect multiple aerial work vehicles to the road below the concrete viaduct at appropriate intervals, and adjust the surface of the viaduct surface with the leading aerial work vehicle. The primer is applied on an aerial work vehicle, and the next high work vehicle is sprayed onto the primer with a spray gun and sprayed with a super-fast curable resin with a touch drying time of 8 to 20 seconds. It is formed , and the coating layer is sprayed and applied to the coating layer at the next aerial work vehicle, and the sealing material is filled into the end portions of the coating layer and the coating layer. The ultra-fast curable resin includes an elongation percentage of 350 to 410% .
[0009]
Repair of the viaduct made of concrete can be easily done in a short period of time, and since it has good followability to cracks such as railings, it can prevent the fall of the deteriorated part of the concrete and does not impair the appearance of the repair surface. In addition, by using multiple aerial work platforms in succession and performing one or two processes on each work vehicle, efficient construction work can be performed while shortening work and shortening traffic regulations. Can be planned.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
(1) in FIG. 1 is a cross-sectional view of a repair method for a railing of a highway that is a viaduct and the lower part of a floor slab, (2) is a plan view showing traffic regulation, and FIG. 3 is a plan view, (1) in FIG. 3 is a cross-sectional view of the repair site, and (2) is an enlarged cross-sectional view thereof.
[0015]
As shown in FIG. 1 (1), this repairing method is performed using four
[0016]
Further, while these
[0017]
As shown in FIG. 2, this work is performed by thoroughly cleaning the surface of the
[0018]
Next, spray the primer 7 of the urethane resin system (for example, Sun PC-F / cement: made by Mitsui Chemicals) on the concrete surface that has been subjected to the substrate preparation treatment or hand-coating by the second
[0019]
Then, a polyurethane spray resin (for example, rim spray F-1000: manufactured by Mitsui Chemicals) or a polyurea spray resin (for example, SWALE: Mitsui Chemicals) is applied to the surface of the primer 7 by a third
[0020]
Next, after the coating layer 8 is formed, the top coating layer 9 is sprayed or hand-coated by the
[0021]
As shown in Table 2 below, the rim spray F-1000 (manufactured by Mitsui Chemicals, Inc.) has physical properties such as a touch drying time of 8 to 20 seconds, a curing time of 30 minutes, and an elongation rate of 350 to 410%. Yes.
[0022]
[Table 2]
[0023]
Rim spray F-1000 (Mitsui Chemicals Co., Ltd.) is a super-fast curing type spray resin in which a special mixing resin as a
[0024]
In this spraying method, as shown in FIG. 1, a
[0025]
By applying spraying with a machine in this way, construction efficiency can be improved, and since it is a super fast curable resin, it cures at the same time as spraying and does not cause dripping on the vertical surface and ceiling surface, and it is a seamless coating layer 8 can be formed.
[0026]
In addition, quick spray SP-100, 200 of the die flex waterproofing business cooperative, SALESAINE S manufactured by Asahi Glass Coat and Resin, HC spray manufactured by Hodogaya Construction Materials Co., Ltd. Nittec, Dainippon Ink Co., Ltd. Stella Coat, Toyo Tire & Rubber Co., Ltd. Soflan Rec 400, Mitsui Ishika Co., Ltd. Swaeru, Yokohama Rubber Co., Ltd. Urban Roof U-3000J You can also.
[0027]
Finally, the top coat layer 9 is sprayed / hand-coated on the surface of the coating layer 8 with an acrylic urethane paint, a fluorine paint or the like as a UV-resistant protective material.
[0028]
Table 3 below compares the standard of the coating material in the conventional concrete coating and the test result of the coating film by the repair method of the present invention. Among these, the test material age is 28 days for the concrete coating material, but 7 days for the polyurethane resin film of the present invention. This is because the physical properties of the polyurethane-based resin film are stabilized after 7 days of material age. In addition, as a test for a sample one year after the outdoor rampage according to the standard for concrete coating materials, the polyurethane resin film shows the result of a 1000 hour accelerated test (
[0029]
[Table 3]
[0030]
Table 4 below compares the railing repair method according to the present invention and the conventional railing repair method. As a result, it was confirmed that the repair method of the present invention was superior to the conventional repair method.
[0031]
[Table 4]
[0032]
【The invention's effect】
Repair of the viaduct made of concrete can be easily done in a short period of time, and since it has good followability to cracks such as railings, it can prevent the fall of the deteriorated part of the concrete and does not impair the appearance of the repair surface.
[0033]
By performing draining on the bottom surface of the floor slab with the draining projection, it is possible to prevent cracks in the draining portion.
[0034]
To perform efficient construction work by shortening work and shortening traffic regulations by performing work in one or two steps on each work vehicle using multiple work platforms Can do.
[Brief description of the drawings]
FIG. 1A is a cross-sectional view showing a method for repairing a railing of an expressway, and FIG. 1B is a plan view showing a traffic regulation range.
FIG. 2 is a plan view of a plurality of aerial work platforms and a highway.
3A is a cross-sectional view of a repair site, and FIG. 3B is an enlarged cross-sectional view of the same.
FIG. 4 is a schematic view of a spraying machine.
FIGS. 5A and 5B are cross-sectional views showing a method for repairing a railing of a highway. FIGS.
FIGS. 6A and 6B are cross-sectional views showing a conventional repair method for a railing and a floor slab of a highway, and FIG. 6B is a cross-sectional view of a film layer at a repair site by the conventional repair method.
[Explanation of symbols]
DESCRIPTION OF
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002254194A JP4061362B2 (en) | 2002-08-30 | 2002-08-30 | Repair method for concrete viaduct |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002254194A JP4061362B2 (en) | 2002-08-30 | 2002-08-30 | Repair method for concrete viaduct |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004092171A JP2004092171A (en) | 2004-03-25 |
| JP4061362B2 true JP4061362B2 (en) | 2008-03-19 |
Family
ID=32060003
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2002254194A Expired - Lifetime JP4061362B2 (en) | 2002-08-30 | 2002-08-30 | Repair method for concrete viaduct |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4061362B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7021386B1 (en) | 2021-07-20 | 2022-02-16 | 中日本高速道路株式会社 | How to replace the wall rail |
-
2002
- 2002-08-30 JP JP2002254194A patent/JP4061362B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004092171A (en) | 2004-03-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR102238516B1 (en) | The combined waterproofing method of the floor surface of a parking lot using eco-friendly polyurea resin and TPM-enhanced reactive wetting type waterproof sheet | |
| EP0983801A3 (en) | Method for repairing the coated surface of a vehicle | |
| JP2003524693A5 (en) | ||
| KR101741798B1 (en) | Waterproofing layer structure of concrete bridge deck | |
| KR101177349B1 (en) | Paint composition concrete | |
| KR102145949B1 (en) | Polyurea coatings for quick-curing water treatment and a coating method using the same | |
| US20150040330A1 (en) | Monolithic protective waterproofing system | |
| CN105863188A (en) | Prefabricated staircase integrated with guardrail, prefabricated air conditioner plate and construction method thereof | |
| US9556631B2 (en) | System and method for the selective repair of roofing shingles | |
| JP4061362B2 (en) | Repair method for concrete viaduct | |
| US4689268A (en) | Coated concrete surface and process for coating | |
| KR101725513B1 (en) | Construction method of external shape restoration for vehicle and in, out wall conclusion material of building construction | |
| JPH0626002A (en) | Elastic paving body and forming method therefor | |
| JPH11172654A (en) | Repairing method of concrete waterway | |
| WO2017009593A1 (en) | Improvements in or relating to a coating for an artificial climbing wall | |
| KR20170114855A (en) | Method of waterproofing concrete floor as hydraulicity polyurethane paint film | |
| JP3239269U (en) | Continuous movement spraying equipment for weed control resin | |
| Farrington | PLACING THE ACCESS PLATFORM ON THE THROGS NECK BRIDGE | |
| CN216517088U (en) | Railway concrete roof renovating waterproof coating | |
| JP2015052239A (en) | Outer covering reinforcement method | |
| JP3280606B2 (en) | Coating method of cable and its coating | |
| KR101562170B1 (en) | Applying Material on the wall and the applying method on the wall by using the same | |
| JP2003206635A (en) | Reinforced fiber sheet of structure, its manufacturing method and repair method of the structure | |
| KR102521617B1 (en) | Environmentally friendly recycling reclamation construction method for the old coating membrane of parking lot | |
| RU2212487C2 (en) | Process of repair of concrete and reinforced concrete coverings and structures |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050826 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070620 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070704 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070824 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070905 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20071029 |
|
| A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A712 Effective date: 20071127 Free format text: JAPANESE INTERMEDIATE CODE: A711 Effective date: 20071127 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20071127 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20071127 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071128 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 4061362 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110111 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120111 Year of fee payment: 4 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130111 Year of fee payment: 5 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130111 Year of fee payment: 5 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313114 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130111 Year of fee payment: 5 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140111 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| EXPY | Cancellation because of completion of term |