Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP4085294B2 - Blast furnace assembly and disassembly equipment - Google Patents
[go: Go Back, main page]

JP4085294B2 - Blast furnace assembly and disassembly equipment - Google Patents

Blast furnace assembly and disassembly equipment Download PDF

Info

Publication number
JP4085294B2
JP4085294B2 JP28373397A JP28373397A JP4085294B2 JP 4085294 B2 JP4085294 B2 JP 4085294B2 JP 28373397 A JP28373397 A JP 28373397A JP 28373397 A JP28373397 A JP 28373397A JP 4085294 B2 JP4085294 B2 JP 4085294B2
Authority
JP
Japan
Prior art keywords
mantel
blast furnace
partial
furnace
furnace body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP28373397A
Other languages
Japanese (ja)
Other versions
JPH11124611A (en
Inventor
実 浜田
Original Assignee
山九株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 山九株式会社 filed Critical 山九株式会社
Priority to JP28373397A priority Critical patent/JP4085294B2/en
Publication of JPH11124611A publication Critical patent/JPH11124611A/en
Application granted granted Critical
Publication of JP4085294B2 publication Critical patent/JP4085294B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、高炉の炉体を組み立てる又は解体する高炉の組立解体装置及び組立解体方法に関するものである。尚、以下に記載する「マンテル」は、鉄皮のみのものと、鉄皮にステーブ(又はステーブクーラ)やレンガが一体となったものとの双方を含むものとする。
【0002】
【従来の技術】
従来、高炉の炉体を組み立て又は解体する高炉の組立解体装置或いは組立解体方法は、据付用に炉頂櫓に取り付けられた揚重機(一般には走行する炉頂アウトリガークレーン)を利用して、炉体を組み立て又は解体するものが知られている。
【0003】
一方、炉体を例えば5つの大ブロック(トップマンテル、上部シャフトマンテル、下部シャフトマンテル、ボッシュマンテル及びハースマンテル)に分割し、各ブロックを炉底より取り込むものがある。
【0004】
【発明が解決しようとする課題】
しかしながら、上記揚重機は吊り上げ能力が通常60〜200トン程度であり、炉体は全体重量で数千トン、水平方向にリング状に分割したリング状マンテルでもステーブの取り付けられた状態では数百トン規模となることが通常である。このため、炉体を短冊形のピースに分割したもので組立(据付)乃至解体を行なっていた。又、炉体をリング状に分割することも行なわれるが、この場合、ステーブ(内張部)の事前取付は、重量が大きくなるので不可であり、又、解体に当たっては、事前にステーブの撤去が必要であり、工期短縮上のネックになっていた。高炉新設時のマンテル組立、据付においても全く同様であった。
【0005】
一方、先に記した炉体を5つの大ブロックに分割するものは、大容量の揚重機構と極めて大規模な仮設を要すると共に、炉底周りの作業空間を多く必要とし、高炉全体構造や周辺の空間的制約を受けるもので、汎用的装置又は方法ではなかった。
【0006】
本発明の課題は、高炉の組立解体装置において、工期短縮が可能で、且つ効率的、経済的なことである。
【0007】
【課題を解決するための手段】
上記課題を解決するため本発明は、高炉炉体を水平方向に複数に分割した部分マンテルを順次組み立てる又は解体する高炉の組立解体装置において、前記高炉の羽口近傍の高さに設けられた鋳床部から前記炉体前面にかけて設けられた鋳床受梁と、該鋳床受梁に走行可能に設けられ搬入又は搬出すべき部分マンテルを載置する台車と、前記高炉の炉体櫓中間デッキに設けられ前記炉体の両外側にかけ渡されたデッキ受梁と、該デッキ受梁に設けられ前記搬入又は搬出すべき部分マンテルを吊り上げる又は吊り下げるセンターホールジャッキと、前記搬入又は搬出すべき部分マンテルを横引きする横引手段とを備えたことである。
【0008】
高炉の組立の際は、台車は鋳床受梁を走行可能に形成されているので、台車に載置した部分マンテルは、炉体前面まで容易に搬入される。炉体前面まで搬入された部分マンテルは、デッキ受梁に設けられたセンターホールジャッキによって、当初斜め上方向に吊られる。デッキ受梁のセンターホールジャッキを徐々に炉体中心部側に移動させ高さ調整を行ないながら、同時に、部分マンテルを横引手段により鋳床部から炉体中心部側に横引きする。部分マンテルが炉体中心部に来た時に、部分マンテルは垂直方向に吊られた状態となる。この状態から、センターホールジャッキによって部分マンテルを吊り上げることによって部分マンテルを既に組み上げた炉体に接続し組み立てることが出来る。
【0009】
高炉の解体の際は、炉体から分離された搬出すべき部分マンテルは、センターホールジャッキによって鋳床レベルまで垂直に吊り下げられる。この状態から、横引手段により炉体中心部側から鋳床部に横引きされることにより、部分マンテルの一端は、鋳床受梁を走行可能に形成されている台車上に載せられる。更に、横引きすることにより部分マンテルは台車上に載置され、この台車により鋳床部に移動され搬出される。このように、本発明の高炉の組立解体装置は、簡便な装置により効率的に搬入又は搬出が行なわれ、工期短縮が図られ経済的である。
【0010】
更に、上記高炉の組立解体装置において、前記鋳床受梁から前記炉体中心部にかけて水平方向に可動可能な安全天井を備えることも出来る。この場合は、この安全天井の上側空間と下側空間で各々同時、又は独立に安全に組立、解体作業が出来る。水平方向に可動可能な安全天井は、上記高炉の組立解体装置の作用に加え、安全天井の着脱作業を迅速、容易にし、且つこの安全天井の上側空間と下側空間で各々安全に同時、又は独立に組立又は解体作業が出来、高炉の組立、解体作業を効率化する。
【0012】
搬入又は搬出すべき部分マンテルを吊りながら、高炉の鋳床部から炉体中心部に又は炉体中心部から鋳床部に横引きして搬送することにより、簡便に容易に部分マンテルを搬送することが出来、工期短縮が可能で効率的、経済的である。
【0013】
【発明の実施の形態】
以下、本発明に係る高炉の組立解体装置及び組立解体方法の実施の形態を図面に基づいて詳細に説明する。尚、図1〜4において、同一又は同等部分には同一符号を付けて示す。
【0014】
図1は、本発明に係る高炉の組立解体装置の一実施の形態を示す正面図である。本実施の形態の高炉の組立解体装置25は、高炉炉体2を水平方向に複数、例えば10ブロックに分割して予め製作しておいた部分マンテル4を順次搬入して組み立てる又は既設の高炉炉体2を予め水平方向に10ブロックの部分マンテル4に分割して順次分離し解体するものである。
【0015】
更に、高炉の組立解体装置25は、高炉の鋳床部9から炉体2前面にかけて、好ましくは炉体2前面まで設けられた鋳床受梁27と、この鋳床受梁27に走行可能に設けられ搬入又は搬出すべき部分マンテル4を載置するマンテル台車(請求項1の台車)29と、高炉の炉体櫓16の中間デッキ20に設けられ炉体2の両外側にかけ渡されたデッキ受梁31と、このデッキ受梁31に設けられ搬入又は搬出すべき部分マンテル4を吊り上げる又は吊り下げる吊手段としてのセンターホールジャッキ32と、搬入又は搬出すべき部分マンテルを横引きする横引手段36とを備えている。
【0016】
そして、高炉の組立解体装置25は、炉体中心部3にかけて水平方向に可動可能な羽口可動安全天井(安全天井)39を備えることも出来、この羽口可動安全天井39の上側空間41と下側空間42で各々安全に、しかも同時に又は独立に組立、解体作業が出来る。
【0017】
ここで、横引手段36は、炉体櫓の支持柱17側に設けられ、部分マンテル4に固定したワイヤー38aを巻き取る巻取機37a又は鋳床受梁27の他端寄りに設けられ、部分マンテル4に固定したワイヤー38bを巻き取る巻取機37bによって巻き取り、横引きするものである。
【0018】
図2は図1の I−I 線要部断面図である。デッキ受梁31は、シャフトマンテル4bとして示されている炉体の両外側で中間デッキ20aと中間デッキ20bの間にかけ渡され、各々のデッキ受梁31はIビームを2本を1組としてかけ渡されている。中間デッキ20cと中間デッキ20dの側に設けられた一対のデッキ受梁31、31は、炉体櫓16の中心に示されているシャフトマンテル4bが内側に入る間隔でかけ渡される。同じ個所に示されているボッシュマンテル(炉腹マンテル)4cは、デッキ受梁31より下側に配置されるので、ボッシュマンテル4cの外径よりも小さくても良い。更に、センターホールジャッキ32は、この実施の形態の場合、上記各デッキ受梁31に3基づつ合計6基が設けられている。
【0019】
図3は、図1の II−II 線要部断面図である。Iビーム2本1組みのデッキ受梁31の内、片側のIビームは、中間デッキ20dに載置され、もう片側のIビームは、中間デッキ20aと中間デッキ20bにかけ渡されている。更に、センターホールジャッキ32は、デッキ受梁31を形成する二つのIビーム31aの各上側フランジに複数の転動ローラを有するチルタンク33を介して走行可能に設けられている。
【0020】
又、横引きによる下記テンションバーにかかる荷重は、センターホールジャッキ32の支持ベースとセンターホールジャッキ32の間を球面座或いはトラニオン等を介して接続支持すれば緩和される。ここで、センターホールジャッキ32は、油圧によって上下に移動するテンションバーを中心軸に持つもので、このテンションバーにワイヤー35が接続され、重量物を吊り上げ又は吊り下げるもので、1基当りの吊り上げ又は吊り下げ容量は、例えば200トンで、このセンターホールジャッキの他に油圧ポンプユニット、電気制御装置等を備え、公知のものを使用することが出来る。油圧ポンプユニット、電気制御装置等は、複数基のセンターホールジャッキ32の上下移動速度や移動量を制御し、センターホールジャッキ32を複数基設けることによって、数百トンの合計容量となり、例えば鉄皮及びステーブを有する部分マンテルの重量が500トンあれば、少なくとも3〜4基のセンターホールジャッキ32を使用することになる。
【0021】
図4は、図1の III−III 線要部断面図である。部分マンテル4を載置したマンテル台車29は、鋳床受梁27の上側フランジ28a上面を走行可能に形成され、複数の転動ローラを有するチルタンク30を介して鋳床受梁27の上面を走行し、炉体2の前面まで移動することが可能である。鋳床受梁27は、鋳床11上に複数の受座13を介して設置されている。又、左右で1対の鋳床受梁27は、炉体2の前面までで仮設を止められているので、鋳床受梁27の間隔を小さくすることも出来る。これに伴ってマンテル台車の小型化も可能である。
【0022】
図1、4に示すように、本実施の形態の羽口可動安全天井39は、炉体2の前面までは、鋳床受梁27の下側フランジ28b内面に設置されたレール上を、上記チルタンク30と同じ構造のチルタンク40を介して走行するが、更に炉体2側に走行する場合は、鋳床受梁27とは別の受梁上を炉体中心部3にかけて水平方向に可動可能である。羽口可動安全天井39の下側には分廻し用ビーム43が設けられ、ハースマンテル4d内の作業に供される。尚、1対の鋳床受梁27の間隔が炉体2より狭く仮設された場合には、羽口可動安全天井39の走行のための別の受梁は、炉体2の巾(外径)より大きい間隔で鋳床部9と炉体2との間に設けられる。
【0023】
以上の構造を有する本実施の形態の高炉の組立解体装置25は、次のように作用する。即ち、図1において、高炉の組立の際は、予めリング状に製作された部分マンテルを公知の重量物搬送車両等で鋳床部9まで搬送し、図示していない重量物吊り上げ機によってマンテル台車29上に載置する。マンテル台車29は鋳床受梁27を走行可能であるので、マンテル台車29に載置された部分マンテル4は、炉体前面まで搬入される。炉体前面まで搬入された部分マンテル4は、デッキ受梁31に設けられたセンターホールジャッキ32によって、当初ワイヤー35で斜め上方向に吊られる。そして、センターホールジャッキ32を徐々に矢印44の方向に移動させレベルを調整しつつ、同時に、部分マンテル4を巻取機37aでワイヤー38aを巻き取ることにより鋳床部9から炉体中心部3側に横引きされる。部分マンテル4が炉体中心部3に来た時に、部分マンテル4は垂直方向に吊られた状態となる。この状態から、センターホールジャッキ32によって部分マンテル4を吊り上げることによって部分マンテル4を既に一部組み上げられている炉体に接続し組み立てることが出来る。
【0024】
高炉の解体の際は、炉体から分離され搬出すべき部分マンテルを、センターホールジャッキ32によって鋳床レベルまで垂直に吊り下げる。そして、センターホールジャッキ32を徐々に矢印44と反対の向きに移動させレベルを調整しつつ、巻取機37bでワイヤー38bを巻き取り、炉体中心部3側から鋳床部9に横引きすることにより、部分マンテル4の一端を、鋳床受梁27上を走行可能なマンテル台車29に載せる。更に、横引きすることにより部分マンテル4はマンテル台車29上に載置され、このマンテル台車29により鋳床部9に移動、搬出され、先に記した重量物吊り上げ機、重量物搬送車両等によって、旧マンテルを外部に撤去する。このように、本発明の高炉の組立解体装置25によれば、簡便な装置により効率的に部分マンテルの搬入又は搬出が行なわれ、工期短縮が図られ経済的である。又、先に記したように、左右で1対の受梁27は、炉体2の前面までで仮設を止められているので、受梁27の間隔を小さく出来、マンテル台車29の小型化をすることも出来る。
【0025】
更に、水平方向に可動可能な羽口可動安全天井39の着脱作業が迅速、容易に行なわれ、且つこの安全天井の上側空間41と下側空間42で同時に又は独立に各々安全に組立又は解体作業が出来、高炉の組立、解体作業を効率化する。
【0026】
尚、炉体櫓の8床21上或は他の床に設けられた別のセンターホールジャッキ34についても適宜、部分マンテル4を吊り上げ又は吊り下げに利用することが出来る。
【0027】
高炉新設時は、上記組立、解体時と全く同じ方法により部分マンテルを据付けることが出来る。
【0028】
次に、本実施の形態の高炉の組立解体方法について、図1、2を利用して説明する。
【0029】
本実施の形態の高炉の組立解体方法は、高炉炉体を水平方向に複数に分割した部分マンテル4を順次搬入し組み立てる又は順次搬出し解体する高炉の組立解体方法であって、搬入すべき部分マンテル4を吊りながら、高炉の鋳床部9から炉体中心部3に横引きして搬入し部分マンテル4を組み立てる、又は炉体から分離した搬出すべき部分マンテル4を吊りながら、炉体中心部3から鋳床部9に横引きして搬出し高炉を解体することである。
【0030】
搬入又は搬出すべき部分マンテル4を吊りながら、高炉の鋳床部9から炉体中心部3に又は炉体中心部3から鋳床部9に横引きして搬送することにより、簡便に容易に部分マンテル4を搬送することが出来、工期短縮が可能で効率的、経済的である。
【0031】
【発明の効果】
本発明の高炉の組立解体装置及び組立解体方法によれば、工期短縮が可能で、且つ効率的、経済的である。
【図面の簡単な説明】
【図1】本発明に係る高炉の組立解体装置の一実施の形態を示す正面図である。
【図2】図1の I−I 線要部断面図である。
【図3】図1の II−II 線要部断面図である。
【図4】図1の III−III 線要部断面図である。
【符号の説明】
2 炉体
3 中心部
4 部分マンテル
9 鋳床部
16 炉体櫓
20、20a〜20d 中間デッキ
25 高炉の組立解体装置
27 鋳床受梁
29 マンテル台車(台車)
31 デッキ受梁
32 センターホールジャッキ(吊手段)
36 横引手段
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a blast furnace assembly / disassembly apparatus and assembly / disassembly method for assembling or dismantling a blast furnace furnace body. In addition, the “Mantel” described below includes both an iron skin only and an iron core in which a stave (or stave cooler) or a brick is integrated.
[0002]
[Prior art]
Conventionally, a blast furnace assembling / disassembling apparatus or disassembling method for assembling or disassembling a furnace body of a blast furnace uses a lifting machine (generally a traveling furnace top outrigger crane) attached to the furnace top for installation. Those that assemble or disassemble the body are known.
[0003]
On the other hand, there is one in which the furnace body is divided into, for example, five large blocks (top mantel, upper shaft mantel, lower shaft mantel, Bosch mantel and Haas mantel), and each block is taken in from the furnace bottom.
[0004]
[Problems to be solved by the invention]
However, the lifting machine usually has a lifting capacity of about 60 to 200 tons, the furnace body has a total weight of several thousand tons, and even a ring-shaped mantel divided into a ring shape in the horizontal direction has a few hundred tons when the stave is attached. It is usually scale. For this reason, the furnace body is divided into strip-shaped pieces and assembled (installed) or disassembled. The furnace body can also be divided into rings, but in this case, pre-installation of the stave (lining part) is not possible due to its increased weight, and the stave must be removed before disassembly. Is necessary, and has become a bottleneck in shortening the construction period. The same was true for mantel assembly and installation when the blast furnace was newly installed.
[0005]
On the other hand, what divides the furnace body described above into five large blocks requires a large capacity lifting mechanism and an extremely large temporary construction, and requires a large work space around the bottom of the furnace. It is not a general-purpose device or method because it is subject to spatial constraints around it.
[0006]
An object of the present invention is to reduce the work period in an assembly / disassembly apparatus for a blast furnace, and to be efficient and economical.
[0007]
[Means for Solving the Problems]
In order to solve the above problems, the present invention provides an assembly / disassembly apparatus for a blast furnace that sequentially assembles or disassembles partial mantels obtained by dividing a blast furnace furnace body into a plurality of parts in a horizontal direction, and a casting provided at a height near the tuyere of the blast furnace. Cast floor receiving beam provided from the floor to the front of the furnace body, a carriage on which the partial mantel is provided so as to be able to run on the cast floor receiving beam and to be carried in or out, and a furnace core intermediate deck of the blast furnace A deck receiving beam provided on both outer sides of the furnace body, a center hole jack provided on the deck receiving beam to lift or suspend the partial mantel to be loaded or unloaded, and the portion to be loaded or unloaded And a horizontal pulling means for horizontal pulling of the mantel.
[0008]
At the time of assembling the blast furnace, the carriage is formed so as to be able to travel on the cast-beam receiving beam, so that the partial mantel placed on the carriage is easily carried to the front surface of the furnace body. The partial mantel carried to the front of the furnace body is initially suspended obliquely upward by a center hole jack provided on the deck receiving beam. While the center hole jack of the deck receiving beam is gradually moved to the furnace body center side to adjust the height, at the same time, the partial mantel is laterally pulled from the cast floor part to the furnace body center side by the horizontal pulling means. When the partial mantel comes to the center of the furnace body, the partial mantel is suspended in the vertical direction. From this state, it is possible to connect and assemble the partial mantel to the already assembled furnace body by lifting the partial mantel with the center hole jack .
[0009]
At the time of dismantling the blast furnace, the partial mantel to be removed separated from the furnace body is suspended vertically to the cast floor level by a center hole jack . From this state, one end of the partial mantel is placed on a carriage formed so as to be able to travel on the cast-in-place support beam by being horizontally pulled from the furnace body center side to the cast-in floor by the horizontal pulling means. Further, the partial mantel is placed on the carriage by lateral pulling, and is moved to the casting floor by the carriage and carried out. As described above, the assembly / disassembly apparatus for a blast furnace according to the present invention is economically carried in or out efficiently by a simple apparatus, shortening the work period, and economical.
[0010]
Furthermore, in the blast furnace assembling and disassembling apparatus, a safety ceiling that can move in the horizontal direction from the cast floor receiving beam to the center of the furnace body can be provided. In this case, the upper and lower spaces of the safety ceiling can be assembled and disassembled safely at the same time or independently. In addition to the action of the blast furnace assembling and disassembling apparatus, the safety ceiling that can be moved in the horizontal direction makes it possible to quickly and easily attach and detach the safety ceiling and at the same time safely and simultaneously in the upper space and the lower space of the safety ceiling, or Assembling or dismantling work can be done independently, and the assembly and dismantling work of the blast furnace is made efficient.
[0012]
While hanging the partial mantel to be carried in or out, the partial mantel can be easily and easily transported by pulling it from the blast furnace cast floor to the furnace center or from the furnace center to the cast floor. It is possible to shorten the construction period, and it is efficient and economical.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of an assembly / disassembly apparatus and assembly / disassembly method for a blast furnace according to the present invention will be described below in detail with reference to the drawings. 1 to 4, the same or equivalent parts are denoted by the same reference numerals.
[0014]
FIG. 1 is a front view showing an embodiment of a blast furnace assembly / disassembly apparatus according to the present invention. The blast furnace assembly / disassembly apparatus 25 according to the present embodiment is configured to sequentially carry in and assemble the partial mantel 4 that has been manufactured in advance by dividing the blast furnace body 2 into a plurality of, for example, 10 blocks in the horizontal direction, or an existing blast furnace furnace. The body 2 is divided into 10 blocks of partial mantels 4 in the horizontal direction in advance and sequentially separated and disassembled.
[0015]
Further, the blast furnace assembly / disassembly apparatus 25 is capable of traveling on the cast-in-place support beam 27 provided from the cast-floor portion 9 of the blast furnace to the front surface of the furnace body 2, preferably up to the front surface of the furnace body 2, and the cast-in-place support beam 27. A mantel carriage (carriage of claim 1) 29 on which the partial mantel 4 to be loaded or unloaded is mounted, and a deck provided on the intermediate deck 20 of the furnace shell 16 of the blast furnace and spanned on both outer sides of the furnace body 2 A receiving beam 31, a center hole jack 32 as lifting means for lifting or hanging the partial mantel 4 to be loaded or unloaded provided on the deck receiving beam 31, and a horizontal pulling means for horizontally pulling the partial mantel to be loaded or unloaded 36.
[0016]
The blast furnace assembling / disassembling apparatus 25 can also include a tuyere movable safety ceiling (safety ceiling) 39 that is movable in the horizontal direction over the central part 3 of the furnace body. The lower space 42 can be assembled and disassembled safely and simultaneously or independently.
[0017]
Here, the horizontal pulling means 36 is provided on the side of the support pillar 17 of the furnace body rod, and is provided near the other end of the winder 37a or the casting bed receiving beam 27 that winds the wire 38a fixed to the partial mantel 4. The wire 38b fixed to the partial mantel 4 is wound up by a winder 37b and wound horizontally.
[0018]
FIG. 2 is a sectional view taken along the line II of FIG. The deck receiving beams 31 are passed between the intermediate deck 20a and the intermediate deck 20b on both outer sides of the furnace body shown as the shaft mantel 4b, and each deck receiving beam 31 hangs two I beams as a set. Has been passed. A pair of deck receiving beams 31 and 31 provided on the side of the intermediate deck 20c and the intermediate deck 20d are spanned at intervals at which the shaft mantel 4b shown at the center of the furnace shell 16 enters inside. Since the Bosch Mantel (furnace mantel) 4c shown in the same location is arranged below the deck receiving beam 31, it may be smaller than the outer diameter of the Bosch Mantel 4c. Further, in the case of this embodiment, a total of six center hole jacks 32 are provided for each of the deck receiving beams 31.
[0019]
FIG. 3 is a sectional view taken along the line II-II in FIG. Of the deck receiving beams 31 of one set of two I beams, one I beam is placed on the intermediate deck 20d, and the other I beam is passed over the intermediate deck 20a and the intermediate deck 20b. Further, the center hole jack 32 is provided so as to be able to travel via a chill tank 33 having a plurality of rolling rollers on the upper flanges of the two I beams 31 a forming the deck receiving beam 31.
[0020]
Further, the load applied to the following tension bar due to lateral pulling can be alleviated if the support base of the center hole jack 32 and the center hole jack 32 are connected and supported via a spherical seat or a trunnion. Here, the center hole jack 32 has a tension bar that moves up and down by hydraulic pressure as a central axis, and a wire 35 is connected to the tension bar to lift or suspend heavy objects. Alternatively, the suspension capacity is, for example, 200 tons, and in addition to the center hole jack, a hydraulic pump unit, an electric control device, and the like can be used, and known ones can be used. The hydraulic pump unit, the electric control device, etc. control the vertical movement speed and the movement amount of the plurality of center hole jacks 32, and by providing a plurality of center hole jacks 32, the total capacity becomes several hundred tons. If the partial mantel having a stave has a weight of 500 tons, at least 3 to 4 center hole jacks 32 are used.
[0021]
4 is a cross-sectional view taken along the line III-III in FIG. The mantel carriage 29 on which the partial mantel 4 is mounted is formed so as to be able to travel on the upper surface of the upper flange 28a of the cast-in beam receiving beam 27, and travels on the upper surface of the cast-in beam receiving beam 27 via a chill tank 30 having a plurality of rolling rollers. However, it is possible to move to the front surface of the furnace body 2. The cast floor receiving beam 27 is installed on the cast floor 11 via a plurality of receiving seats 13. Further, since the pair of cast floor receiving beams 27 on the left and right are temporarily stopped up to the front surface of the furnace body 2, the interval between the cast floor receiving beams 27 can be reduced. Along with this, the mantel cart can be downsized.
[0022]
As shown in FIGS. 1 and 4, the tuyere movable safety ceiling 39 according to the present embodiment is arranged on the rail installed on the inner surface of the lower flange 28 b of the cast-in support beam 27 up to the front surface of the furnace body 2. The vehicle travels through the chill tank 40 having the same structure as the chill tank 30, but when traveling further to the furnace body 2, it can be moved in the horizontal direction on a receiving beam other than the casting bed receiving beam 27 toward the furnace body center 3. It is. A shunting beam 43 is provided below the tuyere movable safety ceiling 39, and is used for work in the Hearthmantel 4d. When the distance between the pair of cast floor receiving beams 27 is temporarily set smaller than that of the furnace body 2, another receiving beam for traveling the tuyere movable safety ceiling 39 has a width (outer diameter) of the furnace body 2. It is provided between the casting floor portion 9 and the furnace body 2 at a larger interval.
[0023]
The blast furnace assembly / disassembly apparatus 25 of the present embodiment having the above-described structure operates as follows. That is, in FIG. 1, when assembling the blast furnace, a partial mantel manufactured in a ring shape in advance is transported to the casting floor 9 by a known heavy material transport vehicle or the like, and the mantel carriage is transported by a heavy material lifting machine (not shown). 29. Since the mantel carriage 29 can travel on the cast-in-place receiving beam 27, the partial mantel 4 placed on the mantel carriage 29 is carried to the front surface of the furnace body. The partial mantel 4 carried to the front of the furnace body is initially suspended obliquely upward by the wire 35 by the center hole jack 32 provided on the deck receiving beam 31. Then, the center hole jack 32 is gradually moved in the direction of the arrow 44 to adjust the level, and at the same time, the partial mantel 4 is wound around the wire 38a by the winder 37a so that the center part 3 of the furnace body 3 is cast from the cast floor part 9. It is pulled sideways. When the partial mantel 4 comes to the furnace body central part 3, the partial mantel 4 is suspended in the vertical direction. From this state, by lifting the partial mantel 4 by the center hole jack 32, the partial mantel 4 can be connected and assembled to the furnace body that has already been partially assembled.
[0024]
At the time of dismantling the blast furnace, the partial mantel separated from the furnace body and suspended is vertically suspended by the center hole jack 32 to the cast floor level. Then, the center hole jack 32 is gradually moved in the direction opposite to the arrow 44 to adjust the level, and the wire 38b is wound up by the winder 37b and laterally drawn from the furnace body center 3 side to the cast floor 9. As a result, one end of the partial mantel 4 is placed on the mantel carriage 29 that can travel on the cast-in beam receiving beam 27. Furthermore, the partial mantel 4 is placed on the mantel carriage 29 by lateral pulling, and is moved to the casting floor portion 9 by the mantel carriage 29 and is carried out by the above-described heavy lifting machine, heavy goods transporting vehicle, etc. The old mantel is removed outside. Thus, according to the blast furnace assembly / disassembly apparatus 25 of the present invention, the partial mantel can be efficiently carried in or out by a simple apparatus, and the construction period can be shortened, which is economical. Further, as described above, the pair of receiving beams 27 on the left and right sides is temporarily stopped up to the front surface of the furnace body 2, so that the interval between the receiving beams 27 can be reduced and the mantel carriage 29 can be downsized. You can also
[0025]
Further, the attaching and detaching work of the tuyere movable safety ceiling 39 movable in the horizontal direction is performed quickly and easily, and the upper space 41 and the lower space 42 of the safety ceiling can be safely assembled or disassembled safely or separately. Can improve the efficiency of assembly and dismantling of the blast furnace.
[0026]
It should be noted that the partial mantel 4 can be appropriately used for lifting or hanging the center hole jack 34 provided on the eighth floor 21 of the furnace body or on another floor.
[0027]
When the blast furnace is newly installed, the partial mantel can be installed in exactly the same way as when assembling and dismantling.
[0028]
Next, a method for assembling and disassembling a blast furnace according to the present embodiment will be described with reference to FIGS.
[0029]
The blast furnace assembly / disassembly method of the present embodiment is a blast furnace assembly / disassembly method in which partial mantels 4 obtained by dividing a blast furnace furnace body into a plurality of parts in the horizontal direction are sequentially loaded and assembled, or sequentially carried out and disassembled. While suspending the mantel 4, the center mantle 4 is assembled by pulling it from the blast furnace casting floor portion 9 to the furnace body central portion 3 and assembling the partial mantel 4, or hanging the mantle 4 to be unloaded separated from the furnace body. It is to draw the blast furnace from the part 3 to the cast floor part 9 and dismantle the blast furnace.
[0030]
While hanging the partial mantel 4 to be loaded or unloaded, it is easily and easily transported by being pulled horizontally from the blast furnace casting bed part 9 to the furnace body center part 3 or from the furnace body center part 3 to the casting bed part 9. The partial mantel 4 can be transported, the work period can be shortened, and it is efficient and economical.
[0031]
【The invention's effect】
According to the assembly / disassembly apparatus and assembly / disassembly method for a blast furnace according to the present invention, the work period can be shortened, and it is efficient and economical.
[Brief description of the drawings]
FIG. 1 is a front view showing an embodiment of an assembly / disassembly apparatus for a blast furnace according to the present invention.
FIG. 2 is a cross-sectional view taken along the line II of FIG.
3 is a sectional view taken along the line II-II in FIG.
4 is a sectional view taken along line III-III in FIG.
[Explanation of symbols]
2 Furnace body 3 Center part 4 Partial mantel 9 Cast floor part 16 Furnace pit 20, 20a-20d Intermediate deck 25 Blast furnace assembly and disassembly device 27 Cast floor receiver 29 Mantel carriage (cart)
31 Deck support 32 Center hole jack (suspending means)
36 Horizontal pulling means

Claims (2)

高炉炉体を水平方向に複数に分割した部分マンテルを順次組み立てる又は解体する高炉の組立解体装置において、前記高炉の羽口近傍の高さに設けられた鋳床部から前記炉体前面にかけて設けられた鋳床受梁と、該鋳床受梁に走行可能に設けられ搬入又は搬出すべき部分マンテルを載置する台車と、前記高炉の炉体櫓中間デッキに設けられ前記炉体の両外側にかけ渡されたデッキ受梁と、該デッキ受梁に設けられ前記搬入又は搬出すべき部分マンテルを吊り上げる又は吊り下げるセンターホールジャッキと、前記搬入又は搬出すべき部分マンテルを横引きする横引手段とを備えたことを特徴とする高炉の組立解体装置。In a blast furnace assembly / disassembly device for sequentially assembling or disassembling partial mantels obtained by dividing a blast furnace furnace body into a plurality of parts in the horizontal direction, the blast furnace furnace body is provided from the cast floor portion provided at a height near the tuyere of the blast furnace to the front surface of the furnace body. A cast floor receiving beam, a carriage provided on the cast floor receiving beam, on which a partial mantel to be carried in or out is placed, and a furnace deck intermediate deck of the blast furnace provided on both outer sides of the furnace body A passed deck receiving beam, a center hole jack provided on the deck receiving beam to lift or suspend the partial mantel to be loaded or unloaded, and a horizontal pulling means for horizontally pulling the partial mantel to be loaded or unloaded. An assembly / disassembly device for a blast furnace, comprising: 請求項1に記載の高炉の組立解体装置において、前記鋳床部から前記炉体中心部にかけて水平方向に移動可能に設けられ、前記高炉の上側空間と下側空間を仕切ることができる安全天井を備えたことを特徴とする高炉の組立解体装置。The blast furnace assembling and disassembling apparatus according to claim 1, wherein a safety ceiling is provided so as to be movable in a horizontal direction from the cast floor part to the center part of the furnace body and partitioning the upper space and the lower space of the blast furnace. An assembly / disassembly device for a blast furnace, comprising:
JP28373397A 1997-10-16 1997-10-16 Blast furnace assembly and disassembly equipment Expired - Fee Related JP4085294B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28373397A JP4085294B2 (en) 1997-10-16 1997-10-16 Blast furnace assembly and disassembly equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28373397A JP4085294B2 (en) 1997-10-16 1997-10-16 Blast furnace assembly and disassembly equipment

Publications (2)

Publication Number Publication Date
JPH11124611A JPH11124611A (en) 1999-05-11
JP4085294B2 true JP4085294B2 (en) 2008-05-14

Family

ID=17669405

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28373397A Expired - Fee Related JP4085294B2 (en) 1997-10-16 1997-10-16 Blast furnace assembly and disassembly equipment

Country Status (1)

Country Link
JP (1) JP4085294B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4583536B2 (en) * 2000-02-01 2010-11-17 山九株式会社 Ring mantel centering method

Also Published As

Publication number Publication date
JPH11124611A (en) 1999-05-11

Similar Documents

Publication Publication Date Title
CN101486091A (en) Integral replacing method of ladle turret with limited upper lifting space
CN204958963U (en) Jacking device that converter trunnion ring was changed
JP4085294B2 (en) Blast furnace assembly and disassembly equipment
JP4126469B2 (en) Blast furnace body disassembly and assembly equipment
CN208844424U (en) Multifunctional assembled construction trolley
JP3180203B2 (en) Material lifting assembly equipment used for construction of high-rise structures
CN105540433B (en) One kind tilts installation site overweight equipment hanging method
CN221318885U (en) Self-balancing guiding lifting device
CN208716689U (en) Force bearing frame for installing reinforcement cage
JP2000143139A (en) Hoisting jig for crane
CN110409803B (en) Hoisting method for disassembling central drum ring of hydraulic mold lifting device
JP4472115B2 (en) Blast furnace assembly method
JP4085293B2 (en) Blast furnace assembly / disassembly apparatus and assembly / disassembly method
CN101537983B (en) Hoisting method of large-scale equipment in factory building for high-altitude positioning
JP4592860B2 (en) Blast furnace component installation method
CN109110655A (en) Cable crane T-type overhead traveling crane and matched cable saddle
CN211004358U (en) Special equipment for disassembling and installing hydraulic support
CN115367616A (en) Furnace shell hoisting device for blast furnace overhaul and installation and use method thereof
CN210915091U (en) Shot blasting conveying cart
CN208200187U (en) A kind of novel lifting beam machine
CN216141120U (en) A hoist device for assembled coincide beam slab
CN221415011U (en) Metallurgical transport vechicle of hot metal bottle
CN115849274B (en) A replacement device for a hydraulic jacking cylinder and its installation and disassembly method.
JP4156746B2 (en) How to install or remove the tuyere safety ceiling
JP3656523B2 (en) Furnace body support method during blast furnace renovation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040510

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050325

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070904

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071105

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080122

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080206

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110228

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120229

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130228

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140228

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees