JP4098581B2 - Overpass bridge construction method - Google Patents
Overpass bridge construction method Download PDFInfo
- Publication number
- JP4098581B2 JP4098581B2 JP2002241574A JP2002241574A JP4098581B2 JP 4098581 B2 JP4098581 B2 JP 4098581B2 JP 2002241574 A JP2002241574 A JP 2002241574A JP 2002241574 A JP2002241574 A JP 2002241574A JP 4098581 B2 JP4098581 B2 JP 4098581B2
- Authority
- JP
- Japan
- Prior art keywords
- overpass
- road
- protection body
- bridge
- existing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title claims description 29
- 238000000034 method Methods 0.000 claims description 22
- 230000001012 protector Effects 0.000 claims description 10
- 239000000463 material Substances 0.000 claims description 6
- 239000004035 construction material Substances 0.000 claims description 5
- 229910000831 Steel Inorganic materials 0.000 description 8
- 239000010959 steel Substances 0.000 description 8
- 239000011178 precast concrete Substances 0.000 description 6
- 239000004567 concrete Substances 0.000 description 3
- 238000011900 installation process Methods 0.000 description 3
- 238000009434 installation Methods 0.000 description 2
- 230000000903 blocking effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明が属する技術分野】
本発明は、跨道橋の架替工法に関する。
【0002】
【従来の技術】
供用中の道路のうえに架設された既設跨道橋を撤去し、新たな跨道橋を架設するため、従来は以下のような方法が用いられている。
▲1▼通行車両を迂回道路に誘導し、供用中の道路を完全に通行止めにして、下方の道路面で跨道橋の架替工事を行なう。しかしながら、この方法は、迂回道路が確保できない場合には適用することができない。
▲2▼供用中の道路の車線半分を交互に通行止めにして、この通行止めの車線上で既設跨道橋を解体・撤去し、その後に、全車線を夜間通行止めにして鋼桁またはプレキャストコンクリート桁を架設して新たな跨道橋を構築する。しかしながら、この方法は、長期間におよぶ交通規制が必要になるため、交通量の多い都市部の幹線道路には適用不可能である。
▲3▼供用中の道路を夜間交通規制し、クレーンにて既設跨道橋を一括撤去し、トレーラーで搬送し、その後に、鋼桁またはプレキャストコンクリート桁を架設して新たな跨道橋を構築する。しかしながら、この方法は、供用中の道路に設置可能なクレーンの揚重能力やトレーラーの積載能力には限界があるため、プレキャストコンクリート橋のように自重が大きい跨道橋には適用不可能である。
▲4▼供用中の道路を夜間交通規制し、一括撤去した既設跨道橋を大型特殊台車により作業ヤードまで搬送し、この作業ヤードで既設跨道橋を解体し、その後に、鋼桁またはプレキャストコンクリート桁を架設して新たな跨道橋を構築する。しかしながら、この方法は、作業ヤードを跨道橋の近くに確保できない場合には適用不可能である。
▲5▼供用中の道路を夜間交通規制し、エレクションガーダーを用いて既設跨道橋を一括撤去し、その後に、鋼桁またはプレキャストコンクリート桁を架設して新たな跨道橋を構築する。しかしながら、この方法は、橋台の背面に架設桁を組み立てて、橋体を解体するための広い作業ヤードを要するため、この作業ヤードが確保できない場合には適用不可能である。
【0003】
従来の方法に関して、以上に説明したように、交通量が非常に多く、頻繁に渋滞が発生するような首都圏の幹線道路では、数日にわたる交通規制がもたらす経済的な損失は膨大であり、道路管理者から許可を得ることは困難である。したがって、車線規制して、既設跨道橋を順次分割、撤去、架替えするような工法の適用は不可能である。
また付近に民家や店舗が立ち並ぶ環境に位置する跨道橋おいては、隣接して作業ヤードを確保することは困難である。なぜならば、立ち退き交渉などに時間が掛かり過ぎると共に、交通量の多い幹線道路では当局からの一部占用許可も得られない。
さらに、幹線道路に対して、それと同等の機能を果たす迂回路は無いのが現状である。仮に迂回路があったとしても、その迂回路の交通渋滞は避け得ない。一括架設・撤去のような工法においては、分割施工は効率的ではなく、跨道橋自体の交通確保は事実上、不可能である。
【0004】
【発明が解決しようとする課題】
本発明は上記のような問題点を解決するためになされたものであり、その課題は、既設跨道橋の下方に位置する道路の通行止めや交通規制を最小限にすることが可能な跨道橋の架替工法を提供することにある。
【0005】
本発明の別の課題は、付近に民家や店舗が立ち並ぶ環境に位置する跨道橋においても、施工現場周囲の土地を作業ヤードとして確保する必要がなく、工期の短縮化が可能な跨道橋の架替工法を提供することにある。
【0006】
また本発明の別の課題は、新たな跨道橋の構造形式を決定する際に、例えば、夜間一括架設が可能な鋼桁もしくはプレキャストコンクリート桁に限定されることなく、これら以外の構造形式の選択も可能にする跨道橋の架替工法を提供することにある。
【0007】
さらに本発明の別の課題は、既設跨道橋の下方に位置する道路交通による制約を受けことなく、既設跨道橋の解体・撤去工法および新設跨道橋の施工法を決定することが可能な跨道橋の架替工法を提供することにある。
【0008】
また本発明の別の課題は、既設跨道橋を撤去し、新たな跨道橋を架設する施工中においても、跨道橋自体の交通を確保することが可能な跨道橋の架替工法を提供することにある。
【0009】
【課題を解決するための手段】
本発明によれば、道路の上方と側方を覆うことが可能で且つ内部を車両が通過可能な所定長の道路防護体を作業ヤードで予め形成し、前記道路防護体を作業ヤードから搬送して跨道橋の下方に設置し、跨道橋の下方を左右側方から通過する道路の所定区間の上方と側方を前記道路防護体により覆い、前記道路防護体の上に作業用機器及び工事用資材を設置し、前記道路防護体の上を作業ヤード及び資材置場として使用しながら、既設の跨道橋を撤去する作業と新たな跨道橋を架設する作業とを前記道路防護体の上で行なうことを特徴とする跨道橋の架替工法が提供される。
本発明では、跨道橋の下方に道路防護体を設置し、跨道橋の下方を左右側方から通過する道路の所定区間を道路防護体で覆うことにより、既設跨道橋の解体・撤去、跨道橋の新設時における、建設資材やコンクリート片などの下方道路上への落下を防止することが可能になった。したがって、道路防護体を搬送して跨道橋の下方の道路に設置する工程時以外は、跨道橋の下方道路の交通規制が不要であり、通行止めや交通規制を最小限にできる。そして、それ故に、既設跨道橋の下方に位置する道路交通による制約を受けことなく、既設跨道橋の解体・撤去工法および新設跨道橋の施工法を決定することが可能になった。
【0010】
本発明では、跨道橋の下方に位置する道路に、跨道橋の前方から後方までの所定区間で道路防護体を設け、この道路防護体は道路の上方と側方を覆うものであり、道路防護体の上を少なくとも作業用機器の設置場所として使用し、さらには、道路防護体の上を工事用資材置場として使用しても良い。したがって、このような工法によれば、付近に民家や店舗が立ち並ぶ環境に位置する跨道橋においても、施工現場周囲の土地を作業ヤードとして確保する必要がなく、工期の短縮化が可能である。また施工に際して、跨道橋の下方の道路を資機材により占用する必要がないため、施工可能時間の制約を受けず、新たな跨道橋の構造形式を自由に選択することができる。
【0011】
本発明では、既設跨道橋の下方の道路を覆うように、既設跨道橋の下方に道路防護体を設置し、道路防護体と既設跨道橋との間に複数のジャッキを設置し、これら複数のジャッキを介して道路防護体で既設跨道橋を支持しながら、既設跨道橋の切断作業を行なっても良い。したがって、このような工法によれば、跨道橋をジャッキで支持しながら、片側ずつ撤去することが可能になり、跨道橋の架替え施工中であっても、跨道橋自体の交通を維持することが可能になった。
【0012】
本発明では、新たな跨道橋を架設する工程において、道路防護体の上を橋梁の支保工として使用しても良く、それ故に、跨道橋の下方に位置する道路交通による制約を受けことなく、新設跨道橋の施工法を決定することが可能になった。
【0013】
【発明の実施の形態】
以下、添付図面を参照して本発明の好適な実施形態を説明する。
図1は跨道橋10の架替工法の一工程における平面図であり、図2は図1の跨道橋10を左側から見た側面図であり、図3は図1の道路防護体20の桁直下での側面図であり、図4は図1の道路防護体20を車線に沿って切断した断面図である。
図1において、幹線道路11には上下各二車線ずつが設けられており、幹線道路11の路肩に設けられたスぺースが道路防護体を組立てる際の作業ヤード12として使用される。また幹線道路11の上方には跨道橋10が架設されており、上下各一車線ずつが設けられている。
幹線道路11には、跨道橋10の前方から後方までの所定区間を覆い、且つ、跨道橋10の下を通過するように、上下線ごとに道路防護体20が設けられる。道路防護体20の内部には、図2に示すように、車両が通行可能な空間が確保される。各道路防護体20は、一対の縦材21bを横材21aで連結してコ字形状に形成されたフレーム21を、水平梁23の上に所定間隔で複数並べ、この複数のフレーム21の外側に鋼板22を取り付けて構成される。また道路防護体20は、その上面に建設資材や作業用機器を置くことができるように、充分な構造耐力を有し、且つ上面が平らになるように形成されている。道路防護体20の水平梁23は、中央分離帯と車線両側で車線方向に延設された高さ調整用基礎24の上に固定される。
なお、フレーム21及び水平梁23はH形鋼から構成することができる。
【0014】
本発明の跨道橋の架替工法は、道路防護体20を作業ヤード12で予め形成し、この道路防護体20を作業ヤード12から跨道橋10の下方まで搬送し、この下方の幹線道路11における跨道橋10の前方から後方までの所定長を道路防護体20で覆い、既設の跨道橋10を撤去する作業と新たな跨道橋を架設する作業とを道路防護体20の上で行なうことを特徴とする。
【0015】
以下、本発明の跨道橋10の架替工法について、図5および図6を参照し、更に詳細に説明する。
<道路防護体の組立・設置工程>
最初に、跨道橋10付近における幹線道路11の路肩に作業ヤード12を設ける。この作業ヤード12では、道路防護体20の組立てを行なうだけであるため、それほど広い面積を確保する必要はなく、幅が7〜10m程度、長さが30〜40m程度あることが望ましい。また道路防護体20の設置予定箇所には、予め高さ調整用基礎24を中央分離帯と車線両側に設ける。
次に、小型クレーン30や、工場などで予め形成したフレーム21及び水平梁23を作業ヤード12に搬入し、小型クレーン30により一対の水平梁23を平行に並べ、これら水平梁23の上に複数のフレーム21を所定間隔で並べて固定し、フレーム21の両側面と上面に鋼板22を取り付ければ道路防護体20の組立て作業が終了する。
図5(a)における中央分離帯11cの点線で図示した部分を撤去し、上下車線を全て通行止めにしたら、特殊大型台車32を道路防護体20の内部に配置して若干上方に持ち上げて、特殊大型台車32を矢印Mのように移動させて道路防護体20を車線11Bの跨道橋10の下まで搬送する。跨道橋10の下方で道路防護体20を下降させ、その水平梁23を高さ調整用基礎24の上に載置させて固定する。なお、路肩に狭い作業ヤード12しか確保できないときには、短い道路防護体20を形成し、その都度、跨道橋10の下まで搬送してこれを複数接続することにより形成しても良い。
次に、車線11Aに設置する道路防護体20も、同様に、作業ヤード12で組立て、特殊大型台車32により搬送して跨道橋10の下に設置する。
なお、上下両車線11A,11Bに沿った歩道において、跨道橋10の下に防護体33を配置しても良い。この防護体33は両側面と天井面が一体に形成されたプレキャストコンクリートで構成することができて、内部を歩行者が通行可能なように空洞状に形成する。
【0016】
<道路防護体上への設備設置工程>
上下両車線11A,11Bへの道路防護体20の設置が終了したら、道路防護体20の上に、図3及び図4に示したような作業架台縦桁28を設置し、その上に作業架台横桁27を設置し、さらに、その上に覆工板26を設置する。そして、覆工板26と跨道橋10との間に段差がある場合には、覆工板26の上に進入車路(図示せず)を設置する。道路防護体20の上面外周には手摺29や安全ネット(図示せず)を張り巡らす。また道路防護体20と既設跨道橋10との間には、図2に示したような配置でジャッキ25を設置する。
次に、図5(b)に示したように、小型クレーン30を跨道橋10から道路防護体20の上に進入させて、覆工板26の上に配置する。
【0017】
<跨道橋の片側車線の撤去・新設工程>
道路防護体20の上への資機材の搬入が終了したら、既設跨道橋10の片側車線10Aのみを通行可能にし、片側車線10Bを交通止めにして、片側車線10Bの桁、梁、床版などをジャッキ25で支持しながら、ワイヤーソー等の装置を使用して片側車線10Bの桁、梁、床版などを切断する作業を行なう。これら既設跨道橋10の撤去作業の全ては道路防護体20の上で行なわれる。切断した跨道橋を小型クレーン30で吊り上げて搬送車両で搬出すると、図6(a)に示したように、既設跨道橋10の片側車線10Bは撤去され、既設跨道橋10の片側車線10Aのみが通行可能な状態で残される。
次に、道路防護体20の上を作業ヤード、資材置場として使用しながら、新たな跨道橋を片側車線10Bに架設する。この新たな跨道橋は、構造形式が特に限定されるものでは無く、例えば、現場打ちコンクリート、プレキャストコンクリート部材、鋼桁などにより構築することができる。
【0018】
<跨道橋の残り片側車線の撤去・新設工程>
既設跨道橋10の片側車線10Bの撤去工事と、新たな片側車線10Bの架設工事が終了したら、跨道橋10の新たな片側車線10Bのみを通行可能にし、既設部分である片側車線10Aは通行止めにする。そして、道路防護体20の上を作業ヤード、資材置場として使用しながら、上記と同様に施工することにより、図6(b)に示したように、既設の片側車線10Aは撤去され、新たな片側車線10Bのみが通行可能な状態で残される。さらに、上記と同様に施工することにより、新たな片側車線10Aの架設も終了する。
【0019】
以上のように、幹線道路11の上下両車線11A,11Bにおいて、跨道橋10の前方から後方までの所定区間が道路防護体20で覆われ、且つ、この道路防護体20が内部に車両が通行可能な空間を確保するように形成されているため、道路防護体20を搬送して跨道橋10の下方の幹線道路11に設置する工程以外は、幹線道路11の交通規制が不要であり、通行止めや交通規制を最小限にすることが可能になった。
【0020】
【発明の効果】
本発明の跨道橋の架替工法では、跨道橋の下方に道路防護体を設置し、この道路における跨道橋の前方から後方までの所定長を道路防護体で覆うことにより、下方の道路を通行する車両は、道路防護体の内部を通過することができるため、道路防護体の搬送・設置工程以外は、跨道橋の下方道路の交通規制が不要になり、通行止めや交通規制を最小限にできる。また跨道橋を片側ずつ撤去・新設することにより、跨道橋自体の交通も確保することができる。
【図面の簡単な説明】
【図1】本発明の実施の態様を示す平面図である。
【図2】図1における跨道橋を左側から見た側面図である。
【図3】図1における道路防護体を右側から見た側面図である。
【図4】図1における道路防護体を車線に沿って切断した断面図である。
【図5】(a)(b)は本発明の跨道橋の架替工法における一工程を示す平面図である。
【図6】(a)(b)はそれぞれ図5に続く工程を示す平面図である。
【符号の説明】
10 跨道橋
11 幹線道路(下方の道路)
12 作業ヤード
20 道路防護体
26 覆工板
30 小型クレーン[0001]
[Technical field to which the invention belongs]
The present invention relates to a method for replacing a bridge.
[0002]
[Prior art]
Conventionally, the following methods are used to remove an existing overpass bridge installed on a road in service and construct a new overpass bridge.
(1) Guide the passing vehicle to the detour road, completely stop the road in service, and perform the construction of the overpass on the lower road surface. However, this method cannot be applied when a detour road cannot be secured.
(2) Half of the lanes of the road in service are alternately closed, and the existing overpass is dismantled and removed from the closed lane. Build a new bridge over the bridge. However, this method is not applicable to highways in urban areas where traffic is heavy because traffic regulation over a long period of time is necessary.
(3) Night traffic restriction on the road in service, the existing overpass bridge is removed with a crane and transported with a trailer, and then a new overpass bridge is constructed by installing steel girders or precast concrete girders. To do. However, this method cannot be applied to overpasses that have a high weight, such as precast concrete bridges, because the lifting capacity of cranes and trailer loading capacity that can be installed on roads in service are limited. .
(4) Nightly traffic restriction on the road in service, and the existing overpass bridge that has been removed in bulk is transported to a work yard by a large special cart, and the existing overpass bridge is dismantled in this work yard, and then steel girders or precast Build a new overpass with concrete girders. However, this method is not applicable when the work yard cannot be secured near the overpass.
(5) Night traffic restrictions on the roads in service, and the existing overpass bridge will be removed at once using an erection girder, and then a new overpass bridge will be constructed by installing steel girders or precast concrete girders. However, this method requires a wide work yard for disassembling the bridge body by assembling a construction girder on the back surface of the abutment, and therefore cannot be applied when this work yard cannot be secured.
[0003]
As explained above with regard to conventional methods, the economic loss caused by traffic regulation over several days is enormous on highways in the metropolitan area where traffic volume is very high and traffic congestion frequently occurs. It is difficult to obtain permission from the road administrator. Therefore, it is impossible to apply a construction method that divides, removes, and replaces existing overpass bridges in lane restrictions.
In addition, it is difficult to secure a work yard adjacent to an overpass in an environment where private houses and stores are lined up nearby. This is because it takes too much time to negotiate evictions, and it is not possible to obtain permission for private use from the authorities on high-traffic highways.
Furthermore, there is currently no detour on the main road that performs the same function. Even if there is a detour, traffic congestion on the detour is inevitable. In construction methods such as collective erection and removal, split construction is not efficient, and it is virtually impossible to secure traffic on the overpass.
[0004]
[Problems to be solved by the invention]
The present invention has been made in order to solve the above-described problems, and the problem is that the roadway located below the existing overpass bridge can be closed and traffic control can be minimized. The purpose is to provide a bridge replacement method.
[0005]
Another problem of the present invention is that it is not necessary to secure the land around the construction site as a work yard even in an overpass bridge located in an environment where private houses and stores are lined up nearby, and the overpass bridge capable of shortening the construction period It is to provide a replacement construction method.
[0006]
Another problem of the present invention is that when determining the structure type of a new overpass, for example, it is not limited to steel girders or precast concrete girders that can be laid at night, but other structural types. The purpose is to provide an overpass bridge construction method that allows selection.
[0007]
Furthermore, another problem of the present invention is that it is possible to determine the dismantling / removal method of the existing overpass and the construction method of the new overpass without being restricted by road traffic located below the existing overpass The purpose of this project is to provide a method for replacing the overpass bridge.
[0008]
Another subject of the present invention is a method of replacing the overpass that can secure the traffic of the overpass even when the existing overpass is removed and a new overpass is installed. Is to provide.
[0009]
[Means for Solving the Problems]
According to the present invention, a road protection body having a predetermined length that can cover the upper side and the side of the road and through which a vehicle can pass is formed in advance in the work yard, and the road protection body is transported from the work yard. Installed below the overpass, covering the upper and side of the predetermined section of the road that passes from the left and right sides below the overpass with the road protection body, working equipment on the road protection body and While installing construction materials and using the road protection body as a work yard and material storage area, the work of removing the existing overpass and the work of constructing a new overpass are performed by the road protection body. An overpass bridge construction method characterized by the above is provided.
In the present invention, a road protection body is installed below the overpass, and a predetermined section of the road passing from the left and right sides below the overpass is covered with the road protection body, thereby dismantling and removing the existing overpass bridge. It is now possible to prevent falling of construction materials and concrete pieces on the road when the bridge is newly constructed. Accordingly, traffic regulation of the road below the bridge bridge is not required except during the process of transporting the road protection body and installing it on the road below the bridge bridge, and traffic closure and traffic regulation can be minimized. Therefore, it has become possible to determine the dismantling / removal method of the existing overpass and the construction method of the new overpass without being restricted by the road traffic located below the existing overpass.
[0010]
In the present invention, a road protector is provided in a predetermined section from the front to the back of the overpass on the road located below the overpass, and the road protector covers the upper side and the side of the road. The road protection body may be used at least as a place for installing work equipment, and further, the road protection body may be used as a construction material storage place. Therefore, according to such a construction method, it is not necessary to secure the land around the construction site as a work yard even in an overpass bridge located in an environment where private houses and stores are lined up nearby, and the construction period can be shortened. . In addition, since it is not necessary to occupy the road below the overpass with materials and equipment during construction, the construction form of the new overpass can be freely selected without being restricted by the construction time.
[0011]
In the present invention, a road protector is installed below the existing overpass so as to cover the road below the existing overpass, and a plurality of jacks are installed between the road protector and the existing overpass, The existing overpass bridge may be cut while supporting the existing overpass bridge with the road protection body through the plurality of jacks. Therefore, according to such a construction method, it becomes possible to remove one side at a time while supporting the overpass with a jack, and even when the overpass is being replaced, the traffic of the overpass itself It became possible to maintain.
[0012]
In the present invention, in the process of constructing a new overpass, the road protection body may be used as a support for the bridge, and therefore it is subject to restrictions due to road traffic located below the overpass. It is now possible to determine the construction method for the newly constructed overpass.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, preferred embodiments of the invention will be described with reference to the accompanying drawings.
FIG. 1 is a plan view in one step of the method of replacing the
In FIG. 1, a
The
The
[0014]
In the overpass bridge replacement method according to the present invention, the
[0015]
Hereinafter, the replacement method of the
<Assembly and installation process of road protection body>
First, a
Next, the
After removing the portion shown by the dotted line of the
Next, the
In addition, you may arrange | position the
[0016]
<Equipment installation process on road protection body>
When the installation of the
Next, as shown in FIG. 5 (b), the
[0017]
<Removal / new construction process of one side lane of overpass>
When the materials and equipment on the
Next, a new overpass is installed in the one-
[0018]
<Removal / new construction process of the remaining lane on the overpass>
When the removal work of the one-
[0019]
As described above, in both the upper and
[0020]
【The invention's effect】
In the overpass bridge construction method of the present invention, a road protector is installed below the overpass, and a predetermined length from the front to the back of the overpass on this road is covered with the road protector, Since vehicles traveling on the road can pass inside the road protection body, traffic control on the road below the overpass is unnecessary, except for the transportation and installation process of the road protection body. Can be minimized. In addition, by removing and constructing the overpass one by one, it is possible to secure the traffic of the overpass itself.
[Brief description of the drawings]
FIG. 1 is a plan view showing an embodiment of the present invention.
FIG. 2 is a side view of the overpass in FIG. 1 as viewed from the left side.
FIG. 3 is a side view of the road protection body in FIG. 1 as viewed from the right side.
4 is a cross-sectional view of the road protection body in FIG. 1 cut along a lane.
5 (a) and 5 (b) are plan views showing one step in the overpass bridge replacement method according to the present invention.
FIGS. 6A and 6B are plan views showing steps subsequent to FIG.
[Explanation of symbols]
10
12
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002241574A JP4098581B2 (en) | 2002-08-22 | 2002-08-22 | Overpass bridge construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2002241574A JP4098581B2 (en) | 2002-08-22 | 2002-08-22 | Overpass bridge construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004076513A JP2004076513A (en) | 2004-03-11 |
| JP4098581B2 true JP4098581B2 (en) | 2008-06-11 |
Family
ID=32024015
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2002241574A Expired - Lifetime JP4098581B2 (en) | 2002-08-22 | 2002-08-22 | Overpass bridge construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4098581B2 (en) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4719179B2 (en) * | 2007-03-29 | 2011-07-06 | オリエンタル白石株式会社 | Dismantling / removal method of support work and upper support work |
| JP6116086B2 (en) * | 2012-08-31 | 2017-04-19 | 岩佐 隆 | Portal culvert structure |
| CN114214943A (en) * | 2021-12-02 | 2022-03-22 | 中交一公局第六工程有限公司 | Construction method for installing steel box girder by crossing existing high-speed short-time interrupted traffic |
| CN115198646B (en) * | 2022-07-14 | 2024-08-09 | 中国十九冶集团有限公司 | Method for erecting roadway for construction bridge |
| CN116104135B (en) * | 2023-01-07 | 2025-10-21 | 中铁大桥局集团第一工程有限公司 | A foundation protection structure and construction method suitable for existing bridges |
| CN116623570B (en) * | 2023-06-01 | 2025-06-06 | 中交第二航务工程局有限公司 | A construction method for dismantling frame beams |
-
2002
- 2002-08-22 JP JP2002241574A patent/JP4098581B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004076513A (en) | 2004-03-11 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6081117B2 (en) | How to remove existing bridge and update existing bridge | |
| KR100866106B1 (en) | Highway construction method and equipment, and the highway | |
| JP6004353B2 (en) | Replacement method of concrete floor slab for elevated road | |
| JP3954869B2 (en) | Bridge girder replacement method | |
| CN111270618B (en) | A construction method for bridge reconstruction based on half-width guarantee | |
| JP6793542B2 (en) | Floor slab erection method and floor slab erection equipment | |
| JP5184248B2 (en) | Construction method of level crossing | |
| JP3579897B1 (en) | Construction method of split bridge type traffic route and split bridge type traffic route | |
| JP2004176531A (en) | Bridge construction method and bridge superstructure | |
| JP5613294B1 (en) | Bridge repair method | |
| JPH0959930A (en) | Bridge girder erection method and device | |
| JP4098581B2 (en) | Overpass bridge construction method | |
| JP3841958B2 (en) | Replacement method of concrete bridge to steel bridge | |
| JP6974233B2 (en) | Floor slab replacement method and floor slab replacement device | |
| JP7020978B2 (en) | How to remove the floor slab of synthetic girders | |
| KR102499696B1 (en) | Replacement method of an old bridge using a transporters and a temporary girders | |
| JP3954905B2 (en) | Three-dimensional crossing method of plane intersection and viaduct | |
| JP4263935B2 (en) | Construction method and elevated detour | |
| CN107245960A (en) | A kind of segmented construction system updated for urban viaduct and method | |
| JPH11293628A (en) | Hung scaffold assembling method for bridge | |
| JP3940587B2 (en) | Construction method of divided bridge type traffic route | |
| JP4233025B2 (en) | How to construct a three-dimensional intersection | |
| CN208455503U (en) | Bridge Demolition Structural System | |
| JPH0312172B2 (en) | ||
| JPS60258311A (en) | Construction of high structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050519 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070426 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070605 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20070806 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070828 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071029 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080219 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080313 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 4098581 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110321 Year of fee payment: 3 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140321 Year of fee payment: 6 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| EXPY | Cancellation because of completion of term |