JP4132706B2 - Power consignment system, management device, and computer program - Google Patents
[go: Go Back, main page]

JP4132706B2 - Power consignment system, management device, and computer program - Google Patents

Power consignment system, management device, and computer program Download PDF

Info

Publication number
JP4132706B2
JP4132706B2 JP2001093861A JP2001093861A JP4132706B2 JP 4132706 B2 JP4132706 B2 JP 4132706B2 JP 2001093861 A JP2001093861 A JP 2001093861A JP 2001093861 A JP2001093861 A JP 2001093861A JP 4132706 B2 JP4132706 B2 JP 4132706B2
Authority
JP
Japan
Prior art keywords
power
generated
generator
sub
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001093861A
Other languages
Japanese (ja)
Other versions
JP2002291163A (en
Inventor
光男 坂本
史樹 乾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Osaka Gas Co Ltd
Original Assignee
Osaka Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Osaka Gas Co Ltd filed Critical Osaka Gas Co Ltd
Priority to JP2001093861A priority Critical patent/JP4132706B2/en
Publication of JP2002291163A publication Critical patent/JP2002291163A/en
Application granted granted Critical
Publication of JP4132706B2 publication Critical patent/JP4132706B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Description

【0001】
【発明の属する技術分野】
本発明はコージェネレーション設備等の自家発電を行う主発電機から電力を供給される電力負荷へ、主発電機の予備として運用される複数の従発電機を有する従発電機群から、電力会社が管理する電力線を介して電力を託送する電力託送システム、そのシステムに用いられる管理装置、及びその装置を実現するためのコンピュータプログラムに関し、特に主発電機の停止時に従発電機群から電力を託送する電力託送システム、管理装置、及びコンピュータプログラムに関する。
【0002】
【従来の技術】
コージェネレーション設備等の自家発電を行う主発電機が設置された施設においては、施設内に配設された電力負荷に供給する電力の全部又は一部を主発電機による電力にて賄い、不足分の電力を電力会社から購入する商用電力にて賄っている。
【0003】
このようなシステムにおいて主発電機が定期検査及び定期補修並びに故障等の理由により、主発電機が停止して電力を供給することができない場合に、本来主発電機で賄うべき電力を、自家発補給電力として電力会社から購入すると、通常契約している商用電力より割高な価格で購入しなければならない。
【0004】
このため主発電機の予備として複数の従発電機を有する従発電機群を管理し、従発電機群から、電力会社の電力線を介して電力負荷へ託送するシステムがあり、このような従発電機群は、複数の主発電機を夫々管理する管理事業体の共同管理、及び管理事業体と契約しているサービス事業体による管理等の方法にて運営されている。
【0005】
また発電機の停止に対して電力供給源を確保するシステムは、特開平9−103098号公報及び特開平7−295626号公報によっても提案されている。
特開平9−103098号公報では、複数の自家発電機により電力を供給する離島等の地域において、1台の発電機の事故停止に対して、停止している他の発電機を速やかに起動させる自動運転システムを開示している。
特開平7−295626号公報では、ガス製造工場等の施設において、過負荷運転を防止しながらも停電時に速やかに複数の自家発電機を起動させる起動システムを開示している。
【0006】
【発明が解決しようとする課題】
しかしながら特開平7−295626号公報及び特開平9−103098号公報にて提案されているシステムは、電力の託送という概念が無く、従発電機群にて発電した電力を託送するというシステムに、そのまま適用することは困難である。
【0007】
また特開平7−295626号公報及び特開平9−103098号公報にて提案されているシステムは、停止している発電機を起動させるという対応を行うものであり、主発電機の停止に対して、従発電機を起動させるという方法を適用した場合、例えばガスタービンエンジンを用いた従発電機では起動に15分程度の時間を要するため、その間の電力を割高な自家発補給電力として電力会社から購入せねばならず、電力に対する費用負担が増加するという問題がある。
【0008】
本発明は斯かる事情に鑑みてなされたものであり、主発電機から電力を供給することができない場合に、運転している従発電機の発電出力を上げて、電力負荷へ供給することにより、電力費用を増加させることなく電力を供給することが可能な電力託送システム、そのシステムに用いられる管理装置、及びその装置を実現するためのコンピュータプログラムの提供を主たる目的とする。
さらに本発明では、電力負荷へ供給すべき電力の増加に備え、停止している従発電機を起動させる電力託送システム等の提供を他の目的とする。
【0009】
【課題を解決するための手段】
第1発明に係る電力託送システムは、主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、複数の従発電機を有する従発電機群から前記電力線を介して電力を託送する電力託送システムにおいて、主発電機が発電している発電電力値を記録する手段と、主発電機から電力を供給することができない場合に、正常時に記録している発電電力値を必要発電電力値として求める手段と、求めた必要発電電力値を、運転している従発電機の発電電力値及び発電能力値の差を示す増加可能電力値と比較する比較手段と、該比較手段による比較により、増加可能電力値が、必要発電電力値以上であると判断したときに、運転している従発電機の発電電力値を、必要発電電力値分増加させる手段と、従発電機群から、必要発電電力値分の電力を前記電力負荷へ託送させる手段とを備えることを特徴とする。
【0010】
第1発明に係る電力託送システムでは、コージェネレーション設備等の自家発電を行う主発電機が、定期検査及び定期補修並びに故障等の理由により停止して電力を供給することができない場合に、運転している従発電機の発電電力値を増加させて、必要発電電力値分を賄うことにより、従発電機の発電電力値の増加は数秒から数十秒で行うことができるため、停止している従発電機を起動させる場合と比べて速やかに託送を行うことが可能であり、このため割高な自家発補給電力を購入する必要がない。
【0011】
第2発明に係る電力託送システムは、主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、複数の従発電機を有する従発電機群から前記電力線を介して電力を託送する電力託送システムにおいて、主発電機が発電している発電電力値を記録する手段と、主発電機から電力を供給することができない場合に、正常時に記録している発電電力値を必要発電電力値として求める手段と、求めた必要発電電力値を、従発電機群の中で運転している複数の従発電機の発電電力の合計を示す発電電力値及び運転している複数の従発電機の発電能力の合計を示す発電能力値の差を示す増加可能電力値と比較する比較手段と、該比較手段による比較により、増加可能電力値が、必要発電電力値以上であると判断したときに、運転している従発電機群の発電電力値を、必要発電電力値分増加させる手段と、従発電機群から、必要発電電力値分の電力を前記電力負荷へ託送させる手段とを備えることを特徴とする。
【0012】
第2発明に係る電力託送システムでは、定期検査及び定期補修並びに故障等の理由により、主発電機が停止して電力を供給することができない場合に、受発電機群の中で運転している複数の従発電機の発電電力値を増加させて、必要発電電力値分を賄うことにより、従発電機の発電電力値の増加は数秒から数十秒で行うことができるため、停止している従発電機を起動させる場合と比べて速やかに託送を行うことが可能であり、このため割高な自家発補給電力を購入する必要がない。
【0013】
第3発明に係る電力託送システムは、第1発明又は第2発明において、前記比較手段による比較により、増加可能電力値が、必要電力値未満であると判断したときに、停止している従発電機を起動させる手段と、運転させた従発電機に、必要電力値分発電させる手段とを更に備えることを特徴とする。
【0014】
第3発明に係る電力託送システムでは、運転している一又は複数の従発電機の発電電力値を増加させても、必要発電電力値分の発電を行うことができないときには、停止している従発電機を起動させることにより、必要発電電力値分を賄うことが可能である。
【0015】
第4発明に係る電力託送システムは、第1発明乃至第3発明のいずれかにおいて、記録されている主発電機の発電電力値の履歴に基づいて、従発電機群から託送する電力の増加要否を判断する手段と、増加要と判断したときに、停止している従発電機を起動させる手段とを更に備えることを特徴とする。
【0016】
第4発明に係る電力託送システムでは、前日及び前週等の所定期間分の履歴に基づいて、必要発電電力値の推移を推定し、必要発電電力の増加が予想される場合に、停止している従発電機を起動させておくことにより、必要発電電力の増加に対して速やかに対応して託送することが可能であり、このため割高な自家発補給電力を購入する必要がない。
【0017】
第5発明に係る管理装置は、主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、前記電力線を介して電力を託送する複数の従発電機を有する従発電機群を管理する管理装置において、主発電機と通信する手段と、主発電機が発電する発電電力値を記録する手段と、主発電機から電力を供給することができない場合に、正常時に記録している発電電力値を必要発電電力値として求める手段と、従発電機群の中で運転している複数の従発電機の発電電力の合計を示す発電電力値を検出する手段と、求めた必要発電電力値を、運転している複数の従発電機の発電能力の合計を示す発電能力値及び検出した発電電力値の差を示す増加可能電力値と比較する手段と、比較により、増加可能電力値が、必要発電電力値以上であると判断したときに、運転している従発電機群の発電電力値を、必要発電電力値分増加させる手段と、従発電機群から、必要発電電力値分の電力を電力負荷へ託送させる手段とを備えることを特徴とする。
【0018】
第5発明に係る管理装置では、コージェネレーション設備等の自家発電を行う主発電機が定期検査及び定期補修並びに故障等の理由により、電力を供給することができない場合に、運転している従発電機の発電電力値を増加させ、商用電力を販売する電力会社の電力線を介して、必要発電電力値分の電力を電力負荷へ託送することで、必要発電電力値分を賄うという管理をすることにより、従発電機の発電電力値の増加は数秒から数十秒で行うことができるため、停止している従発電機を起動させる場合と比べて速やかに託送を行うことが可能であり、このため割高な自家発補給電力を購入する必要がない。
【0019】
第6発明に係るコンピュータプログラムは、コンピュータに、主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、前記電力線を介して電力を託送する複数の従発電機を有する従発電機群を管理させるコンピュータプログラムにおいて、コンピュータに、主発電機が発電する発電電力値を記録させる手順と、コンピュータに、主発電機から電力を供給することができない場合に、正常時に記録している発電電力値を必要発電電力値として求めさせる手順と、コンピュータに、従発電機群の中で運転している複数の従発電機の発電電力の合計を示す発電電力値を検出させる手順と、コンピュータに、求めた必要発電電力値を、運転している複数の従発電機の発電能力の合計を示す発電能力値及び検出した発電電力値の差を示す増加可能電力値と比較させる手順と、コンピュータに、比較により、増加可能電力値が、必要発電電力値以上であると判断したときに、運転している従発電機群の発電電力値を、必要発電電力値分増加させる手順と、コンピュータに、従発電機群から、必要発電電力値分の電力を電力負荷へ託送させる手順とを含むことを特徴とする。
【0020】
第6発明に係るコンピュータプログラムでは、サーバコンピュータ等のコンピュータにて実行することで、コンピュータが従発電機群を管理する管理装置として動作するので、コージェネレーション設備等の自家発電を行う主発電機が定期検査及び定期補修並びに故障等の理由により、電力を供給することができない場合に、運転している従発電機の発電電力値を増加させ、商用電力を販売する電力会社の電力線を介して、必要発電電力値分の電力を電力負荷へ託送することで、必要発電電力値分を賄うという管理をすることにより、従発電機の発電電力値の増加は数秒から数十秒で行うことができるため、停止している従発電機を起動させる場合と比べて速やかに託送を行うことが可能であり、このため割高な自家発補給電力を購入する必要がない。
【0021】
その他の発明では、主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、従発電機から前記電力線を介して電力を託送する電力託送方法において、主発電機から電力を供給することができない場合に、主発電機が発電すべき必要発電電力値を求め、求めた必要発電電力値を、運転している従発電機の発電電力値及び発電能力値の差を示す増加可能電力値と比較し、増加可能電力値が、必要発電電力値以上であるときに、運転している従発電機の発電電力値を、必要発電電力値分増加し、従発電機から、必要発電電力値分の電力を前記電力負荷へ託送することを特徴とする。
【0022】
その他の発明では、コージェネレーション設備等の自家発電を行う主発電機から電力を供給することができない場合に、運転している従発電機の発電電力値を増加させ、商用電力を販売する電力会社の電力線を介して、必要発電電力値分の電力を電力負荷へ託送することにより、従発電機の発電電力値の増加は数秒から数十秒で行うことができるため、停止している従発電機を起動させる場合と比べて速やかに託送を行うことが可能であり、このため主発電機の停止から電力を託送するまでが非常に短く、割高な自家発補給電力を購入する必要がない。
【0023】
【発明の実施の形態】
以下、本発明をその実施の形態を示す図面に基づいて詳述する。
図1は本発明の電力託送システムを概念的に示す説明図である。
図中10,10,…はコージェネレーション設備等の自家発電を行う主発電機であり、主発電機10,10,…は夫々電力負荷10a,10a,…へ電力を供給している。
また各電力負荷10a,10a,…には、一般電気事業者である電力業者が管理する外部発電機20からも電力線ELを介して商用電力を供給することができる。
電力線ELには、ガスタービンエンジン発電機等の従発電機30,30,…を有する従発電機群300が接続されており、従発電機群300にて発電した電力を、電力線ELを介して電力負荷10a,10a,…へ託送することができる。
【0024】
従発電機群300は、LAN等の内部通信網NWiを介して、サーバコンピュータを用いた管理装置40に管理されており、管理装置40は、インターネット等の外部通信網NWoに接続し、外部通信網NWoを介して主発電機10,10,…と通信する。
そして主発電機10,10,…、従発電機群300、及び管理装置40は、管理事業体によって維持管理されている。
【0025】
図2は本発明の電力託送システムの構成を示すブロック図である。
主発電機10は、装置全体を制御する制御部11、発電を行う発電部12、発電部12が発電した発電電力値等の情報を記録する記録部13、発電部12が発電した電力を電力負荷10aへ供給する送電部14、及び外部通信網NWoに接続する外部通信部15を備えている。
【0026】
従発電機30は、制御部31、発電部32、発電部32が発電した電力を電力線ELを介して電力負荷10a,10a,…へ託送する送電部33、及び内部通信網NWiに接続する内部通信部34を備えている。
【0027】
管理装置40は、制御部41、本発明の管理装置用のコンピュータプログラム及びデータ等の情報を記録する記録部42、内部通信部43、並びに外部通信部44を備え、記録部42に記録している本発明の管理装置用のコンピュータプログラムを制御部41により実行することで、サーバコンピュータは本発明の管理装置40として動作する。
また記録部42の記録領域の一部は、内部通信部43及び外部通信部44により、5分等の所定間隔で受信している主発電機10,10,…及び従発電機群300の発電電力値、並びに発電能力値等の情報を記録する発電データベース等の各種データベースとしても用いられている。
なお記録部42の記録領域の一部を各種データベースとして用いるのではなく、管理装置40に接続する他の装置が備える記録部を各種データベースとして用いてもよい。
【0028】
次に本発明の管理装置40の処理を図3に示すフローチャートを用いて説明する。
主発電機10が故障等の理由により停止し、電力負荷10aへ電力を供給することができない場合、主発電機10が正常に運転されていた時期の発電電力値の記録から、停止する直前の発電電力値を主発電機10が発電すべき必要発電電力値として求める(ステップS1)。
【0029】
なお定期検査及び定期補修等の理由にて事前に停止が判明している場合、必要発電電力値を記録から求めるのではなく、別途計算により求められた必要発電電力値の入力を受け付けるようにしてもよい。
また正常時に記録されている発電電力値とは、5分等の所定間隔で外部通信網NWoを介して主発電機10から管理装置40へ送信される発電電力値を記録した発電データベースから抽出する値を示す。
ただし主発電機10の記録部13に記録されている電力値から、主発電機10にて必要発電電力値を求め、外部通信網NWoを介して管理装置40へ送信するようにしてもよい。
【0030】
そして従発電機群300に含まれる従発電機30,30,…の中で、運転している従発電機30,30,…の発電電力の合計を示す発電電力値を検出し(ステップS2)、検出した発電電力値と、発電データベースに記録している従発電機30,30,…の定格電力である発電能力の合計を示す発電能力値との差、即ち従発電機30,30,…の余力の合計を示す増加可能電力値を算出し(ステップS3)、算出した増加可能電力値及びステップS1で求めた必要発電電力値を比較する(ステップS4)。
【0031】
ステップS4の比較により、増加可能電力値が必要発電電力値以上であると判断した場合(ステップS5:Y)、余力を有する従発電機30,30,…の出力を上げて発電電力値を必要発電電力値分増加させ(ステップS6)、増加させた必要発電電力値分の電力を、従発電機群300から供給する電力として、電力線ELを介して電力負荷10aへ託送する(ステップS7)。
【0032】
ステップS4の比較により、増加可能電力値が必要発電電力値未満であると判断した場合(ステップS5:N)、停止している従発電機30を起動して(ステップS8)、必要発電電力値分の電力を発電させ(ステップS9)、ステップS7に進み、発電した必要発電電力値分の電力を、従発電機群300から供給する電力として、電力線ELを介して電力負荷10aへ託送する(ステップS7)。
【0033】
そして発電データベースに記録されている前日及び前週等の所定期間分の履歴に基づいて、従発電機群300から託送する電力の増加要否を判断し(ステップS10)、増加要と判断した場合に(ステップS11:Y)、停止している従発電機30を起動させ(ステップS12)、託送に備える。
【0034】
ステップS10にて増加不要と判断した場合(ステップS11:N)、ステップS12の起動処理は行わない。
また増加要と判断した場合であっても、運転している従発電機30,30,…の出力を上げるだけで対応することができるときは、ステップS12の起動処理は行わない。
【0035】
前記実施の形態では、必要発電電力値分の電力の増加を運転している複数台の従発電機30,30,…にて賄う形態を示したが、本発明はこれに限らず、各従発電機30,30,…について夫々の増加可能電力値を算出し、算出した一台毎の増加可能電力値に基づいて、一台の従発電機30の発電電力値の増加により必要発電電力値分を賄えるか否かを検討するようにしてもよい。
【0036】
【発明の効果】
以上詳述した如く本発明に係る電力託送システム、管理装置、及びコンピュータプログラムでは、コージェネレーション設備等の自家発電を行う主発電機が定期検査及び定期補修並びに故障等の理由により、電力負荷へ電力を供給することができない場合に、運転している従発電機の発電電力値を増加させ、商用電力を販売する電力会社の電力線を介して、必要発電電力値分の電力を電力負荷へ託送することで、必要発電電力値分を賄うという管理をすることにより、従発電機の発電電力値の増加は数秒から数十秒で行うことができるため、停止している従発電機を起動させる場合と比べて速やかに託送を行うことが可能であり、このため主発電機の停止から電力の託送までの時間が非常に短く割高な自家発補給電力を購入する必要がない等、優れた効果を奏する。
【0037】
また本発明では、前日及び前週等の所定期間分の履歴に基づいて、必要発電電力値の推移を推定し、必要発電電力の増加が予想される場合に、停止している従発電機を起動させておくことにより、必要発電電力の増加に対して速やかに対応して託送することが可能であり、このため割高な自家発補給電力を購入する必要がない等、優れた効果を奏する。
【図面の簡単な説明】
【図1】本発明の電力託送システムを概念的に示す説明図である。
【図2】本発明の電力託送システムの構成を示すブロック図である。
【図3】本発明の管理装置の処理を示すフローチャートである。
【符号の説明】
10 主発電機
10a 電力負荷
20 外部発電機
30 従発電機
300 従発電機群
40 管理装置
EL 電力線
NWi 内部通信網
NWo 外部通信網
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an electric power company from a group of sub-generators having a plurality of sub-generators operated as backups of the main generator, to a power load supplied with power from a main generator that performs private power generation such as cogeneration facilities. The present invention relates to a power consignment system that consigns power via a power line to be managed, a management device used in the system, and a computer program for realizing the device, and particularly consigns power from a generator group when the main generator is stopped. The present invention relates to a power consignment system, a management device, and a computer program.
[0002]
[Prior art]
In facilities where main generators that perform in-house power generation such as cogeneration facilities are installed, all or part of the power supplied to the power load installed in the facility is covered by the power generated by the main generator. Is supplied by commercial power purchased from power companies.
[0003]
In such a system, if the main generator stops and cannot supply power due to periodic inspections, periodic repairs, or malfunctions, the power that should be provided by the main generator is self-generated. If it is purchased from a power company as supplementary power, it must be purchased at a price that is higher than the contracted commercial power.
[0004]
For this reason, there is a system that manages a sub-generator group having a plurality of sub-generators as a spare for the main generator and entrusts the sub-generator group to a power load via the power line of the power company. The aircraft group is operated by a method such as joint management of a management entity that manages a plurality of main generators, and management by a service entity that is contracted with the management entity.
[0005]
A system for securing an electric power supply source for stopping the generator is also proposed by Japanese Patent Laid-Open Nos. 9-103098 and 7-295626.
In Japanese Patent Application Laid-Open No. 9-103098, in a region such as a remote island where power is supplied by a plurality of private generators, the other generators that are stopped are quickly activated in response to an accidental stop of one generator. An automatic driving system is disclosed.
Japanese Patent Application Laid-Open No. 7-295626 discloses a start-up system for quickly starting a plurality of private generators in the event of a power failure while preventing overload operation in a facility such as a gas manufacturing factory.
[0006]
[Problems to be solved by the invention]
However, the systems proposed in Japanese Patent Laid-Open Nos. 7-295626 and 9-103098 do not have the concept of power consignment, and the system that consigns the power generated by the sub-generator group is used as it is. It is difficult to apply.
[0007]
In addition, the systems proposed in Japanese Patent Laid-Open Nos. 7-295626 and 9-103098 perform a response of starting a generator that is stopped. When a method of starting a sub-generator is applied, for example, a sub-generator using a gas turbine engine requires about 15 minutes to start up. There is a problem that the cost burden for electric power increases because it must be purchased.
[0008]
The present invention has been made in view of such circumstances. When power cannot be supplied from the main generator, the power generation output of the operating sub generator is increased and supplied to the power load. The main object is to provide a power consignment system capable of supplying power without increasing power costs, a management device used in the system, and a computer program for realizing the device.
Furthermore, another object of the present invention is to provide a power consignment system or the like that activates a stopped sub-generator in preparation for an increase in power to be supplied to a power load.
[0009]
[Means for Solving the Problems]
A power consignment system according to a first aspect of the present invention is a sub-generator having a plurality of sub-generators to a power load that is supplied with power from a main generator and is connected to a power line that transmits power generated by an external generator. In a power consignment system for consigning power from a group via the power line, a means for recording the generated power value generated by the main generator, and when normal power is not supplied from the main generator, is recorded when normal The means for obtaining the generated power value as the required power value, and comparing the obtained necessary power value with the increaseable power value indicating the difference between the generated power value and the power generation capacity value of the operating sub-generator When it is determined by the comparison means and the comparison by the comparison means that the increaseable power value is equal to or greater than the required generated power value, the generated power value of the operating slave generator is increased by the required generated power value. Means and followers From machine group, characterized in that it comprises a means for wheeling power needs generated power value amount to the power load.
[0010]
In the power consignment system according to the first aspect of the invention, the main generator that performs in-house power generation such as cogeneration facilities is operated when it cannot be stopped and supplied with power due to periodic inspections, periodic repairs, or failure. By increasing the generated power value of the slave generator to cover the necessary generated power value, the generated power value of the slave generator can be increased in a few seconds to tens of seconds, so it has stopped. Compared to the case of starting the sub-generator, it is possible to carry out consignment promptly, and therefore it is not necessary to purchase expensive self-supplied power supply.
[0011]
The power consignment system according to the second aspect of the present invention is a slave generator having a plurality of slave generators to a power load connected to a power line that is supplied with power from the master generator and transmits the power generated by the external generator. In a power consignment system for consigning power from a group via the power line, a means for recording the generated power value generated by the main generator, and when normal power is not supplied from the main generator, is recorded when normal Means for determining the generated power value as the required generated power value, and the generated power value indicating the sum of the generated power of the plurality of slave generators operating in the slave generator group. And a comparison means for comparing with an increaseable power value indicating a difference in power generation capacity values indicating the sum of the power generation capacities of a plurality of operating sub-generators, and the increaseable power value is obtained by the comparison by the comparison means. If it is above the power value Means for increasing the generated power value of the operating sub-generator group by the required generated power value, and means for entrusting the electric power for the required generated power value from the sub-generator group to the power load It is characterized by providing.
[0012]
In the power consignment system according to the second invention, when the main generator stops and cannot supply power due to periodic inspections, periodic repairs, malfunctions, etc., the system is operated in the receiver group. By increasing the power generation value of multiple sub-generators to cover the required power generation value, the power generation value of the sub-generator can be increased in a few seconds to tens of seconds, so it has stopped. Compared to the case of starting the sub-generator, it is possible to carry out consignment promptly, and therefore it is not necessary to purchase expensive self-supplied power supply.
[0013]
The power consignment system according to the third aspect of the present invention is the subordinate power generation system that is stopped when the increaseable power value is determined to be less than the required power value by the comparison by the comparison means in the first or second aspect of the invention. The apparatus further comprises means for starting the machine and means for causing the operated sub-generator to generate power for the required power value.
[0014]
In the power consignment system according to the third aspect of the invention, when the generated power value of one or more sub-generators in operation cannot be increased even when the required power generation value cannot be generated, It is possible to cover the necessary power generation value by starting the generator.
[0015]
The power consignment system according to a fourth aspect of the present invention is the power consignment system according to any one of the first to third aspects, wherein the power to be consigned from the sub-generator group is increased based on the recorded history of the power generation value of the main generator. It is further characterized by further comprising means for determining NO, and means for starting the stopped sub-generator when it is determined that the increase is necessary.
[0016]
In the power consignment system according to the fourth aspect of the invention, the transition of the required generated power value is estimated based on the history for a predetermined period such as the previous day and the previous week, and is stopped when an increase in the required generated power is expected. By starting the slave generator, it is possible to promptly respond to an increase in the required generated power, and it is not necessary to purchase expensive self-supplied power.
[0017]
A management device according to a fifth aspect of the present invention provides a plurality of devices that consign power through the power line to a power load that is supplied with power from the main generator and is connected to a power line that transmits power generated by the external generator. In a management device for managing a sub-generator group having sub-generators, means for communicating with the main generator, means for recording a generated power value generated by the main generator, and supplying power from the main generator If this is not possible, a means for obtaining the generated power value recorded during normal operation as a required generated power value and a generated power value indicating the sum of the generated power of a plurality of slave generators operating in the slave generator group Means for detecting and means for comparing the obtained required power generation value with a power generation capacity value indicating the sum of power generation capacities of a plurality of operating sub-generators and an increaseable power value indicating a difference between the detected power generation power values. By comparison, the power value that can be increased is When it is determined that the power generation value is more than the required power generation value, means for increasing the power generation value of the operating sub-generator group by the required power generation power value and the power for the necessary power generation value from the sub-generator group And a means for entrusting to a power load.
[0018]
In the management device according to the fifth aspect of the invention, the sub-power generator that is operating when the main generator that performs in-house power generation, such as cogeneration facilities, cannot supply power due to periodic inspections, periodic repairs, malfunctions, etc. Management to cover the necessary generated power value by increasing the generated power value of the machine and consigning the required generated power value to the power load via the power line of the power company that sells commercial power Therefore, since the power generation value of the sub-generator can be increased in a few seconds to tens of seconds, it is possible to carry out consignment more quickly than when the sub-generator is stopped. Therefore, it is not necessary to purchase expensive self-supplied power.
[0019]
According to a sixth aspect of the present invention, there is provided a computer program for entrusting power to a computer via a power line to a power load that is supplied with power from a main generator and connected to a power line that transmits power generated by an external generator. In a computer program for managing a sub-generator group having a plurality of sub-generators, a procedure for causing the computer to record a generated power value generated by the main generator, and supplying power from the main generator to the computer If this is not possible, the computer will indicate the total generated power of the multiple sub-generators operating in the sub-generator group, and the computer will give the generated power value recorded during normal operation as the required generated power value. A procedure for detecting the generated power value and a power generation capacity value indicating the total required power generation value of a plurality of operating sub-generators for the computer to obtain the required generated power value. And a procedure for comparing the detected power generation value with an increaseable power value indicating a difference between the detected power generation values and a comparison by the computer when the increase power value is determined to be greater than or equal to the required power generation power value by comparison. Including a procedure for increasing the generated power value of the generator group by the required generated power value and a procedure for causing the computer to entrust the power corresponding to the required generated power value from the slave generator group to the power load. .
[0020]
In the computer program according to the sixth aspect of the invention, when executed by a computer such as a server computer, the computer operates as a management device for managing the sub-generator group. When power cannot be supplied due to periodic inspections, periodic repairs, and breakdowns, increase the generated power value of the operating sub-generator, via the power line of the power company that sells commercial power, By entrusting the required generation power value to the power load and managing to cover the necessary generation power value, the generation power value of the slave generator can be increased in seconds to tens of seconds. Therefore, it is possible to perform consignment promptly compared with the case of starting a stopped sub-generator. For this reason, it is necessary to purchase expensive self-supplied power. There is no.
[0021]
In another invention, the power consignment in which power is supplied from the main generator to the power load connected to the power line for transmitting the power generated by the external generator from the sub generator via the power line In the method, when power cannot be supplied from the main generator, the required generated power value to be generated by the main generator is determined, and the determined required generated power value is calculated as the generated power value of the operating sub-generator. When the increaseable power value is greater than or equal to the required generation power value, the generated power value of the operating sub-generator is set to the required generation power value. The power is increased, and the power corresponding to the necessary generated power value is transferred from the slave generator to the power load.
[0022]
In other inventions, an electric power company that sells commercial power by increasing the power generation value of a sub-operator that is operating when power cannot be supplied from a main generator that performs private power generation such as cogeneration facilities. Since the power generation value of the sub-generator can be increased in several seconds to several tens of seconds by entrusting the power for the required power generation value to the power load via the power line of Compared with the case of starting the machine, it is possible to carry out the delivery promptly. Therefore, it is very short from the stop of the main generator to the delivery of power, and it is not necessary to purchase expensive self-supplied power supply.
[0023]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described in detail with reference to the drawings illustrating embodiments thereof.
FIG. 1 is an explanatory diagram conceptually showing the power consignment system of the present invention.
In the figure, 10, 10,... Are main generators that perform private power generation such as cogeneration facilities, and the main generators 10, 10,... Supply power to the power loads 10a, 10a,.
Moreover, commercial electric power can be supplied to each electric power load 10a, 10a, ... from the external generator 20 which the electric power supplier who is a general electric power company manages via electric power line EL.
A slave generator group 300 having slave generators 30, 30,... Such as gas turbine engine generators is connected to the power line EL, and the power generated by the slave generator group 300 is transmitted via the power line EL. It can be entrusted to the electric power loads 10a, 10a,.
[0024]
The slave generator group 300 is managed by a management device 40 using a server computer via an internal communication network NWi such as a LAN, and the management device 40 is connected to an external communication network NWo such as the Internet for external communication. Communicate with the main generators 10, 10,... Via the network NWo.
The main generators 10, 10,..., The sub generator group 300, and the management device 40 are maintained and managed by the management business entity.
[0025]
FIG. 2 is a block diagram showing the configuration of the power consignment system of the present invention.
The main generator 10 includes a control unit 11 that controls the entire apparatus, a power generation unit 12 that generates power, a recording unit 13 that records information such as a power generation value generated by the power generation unit 12, and power generated by the power generation unit 12 A power transmission unit 14 that supplies power to the load 10a and an external communication unit 15 connected to the external communication network NWo are provided.
[0026]
The slave generator 30 includes a control unit 31, a power generation unit 32, a power transmission unit 33 that entrusts the power generated by the power generation unit 32 to the power loads 10a, 10a,... Via the power line EL, and an internal connection to the internal communication network NWi. A communication unit 34 is provided.
[0027]
The management device 40 includes a control unit 41, a recording unit 42 that records information such as a computer program and data for the management device of the present invention, an internal communication unit 43, and an external communication unit 44. The server computer operates as the management apparatus 40 of the present invention by executing the computer program for the management apparatus of the present invention by the control unit 41.
Further, a part of the recording area of the recording unit 42 is generated by the main generators 10, 10,... And the sub generator group 300 received by the internal communication unit 43 and the external communication unit 44 at a predetermined interval such as 5 minutes. It is also used as various databases such as a power generation database that records information such as power values and power generation capacity values.
Instead of using a part of the recording area of the recording unit 42 as various databases, a recording unit provided in another device connected to the management apparatus 40 may be used as various databases.
[0028]
Next, the processing of the management apparatus 40 of the present invention will be described using the flowchart shown in FIG.
When the main generator 10 stops due to a failure or the like and cannot supply power to the power load 10a, the generated power value at the time when the main generator 10 was normally operated is recorded immediately before the stop. The generated power value is obtained as a necessary generated power value to be generated by the main generator 10 (step S1).
[0029]
If the outage is known in advance for reasons such as periodic inspections and periodic repairs, instead of obtaining the required generated power value from the record, accept the input of the required generated power value obtained separately by calculation. Also good.
The generated power value recorded at normal time is extracted from the generated power database in which the generated power value transmitted from the main generator 10 to the management device 40 via the external communication network NW at a predetermined interval such as 5 minutes is recorded. Indicates the value.
However, the required power generation value may be obtained by the main generator 10 from the power value recorded in the recording unit 13 of the main generator 10 and transmitted to the management apparatus 40 via the external communication network NWo.
[0030]
Then, a generated power value indicating the total generated power of the operating sub-generators 30, 30,... Included in the sub-generator group 300 is detected (step S 2). , And the difference between the detected power generation value and the power generation capacity value indicating the total power generation capacity of the power generators 30, 30,... Recorded in the power generation database, that is, the sub generators 30, 30,. An increaseable power value indicating the total remaining power is calculated (step S3), and the calculated increaseable power value and the necessary generated power value obtained in step S1 are compared (step S4).
[0031]
If it is determined from the comparison in step S4 that the increaseable power value is greater than or equal to the required generated power value (step S5: Y), the generated power value is required by increasing the output of the slave generators 30, 30,. The generated power value is increased (step S6), and the increased required generated power value is sent to the power load 10a via the power line EL as the power supplied from the slave generator group 300 (step S7).
[0032]
If it is determined from the comparison in step S4 that the increaseable power value is less than the required generated power value (step S5: N), the stopped sub-generator 30 is started (step S8), and the required generated power value Power is generated (step S9), the process proceeds to step S7, and the generated power for the required power generation value is consigned to the power load 10a via the power line EL as power supplied from the slave generator group 300 ( Step S7).
[0033]
Then, based on the history for a predetermined period such as the previous day and the previous week recorded in the power generation database, it is determined whether or not the power to be entrusted from the slave generator group 300 needs to be increased (step S10). (Step S11: Y), the stopped sub-generator 30 is activated (Step S12) to prepare for consignment.
[0034]
When it is determined in step S10 that no increase is necessary (step S11: N), the activation process in step S12 is not performed.
Even if it is determined that the increase is necessary, the activation process of step S12 is not performed if it is possible to cope with the problem by simply increasing the output of the operating sub-generators 30, 30,.
[0035]
In the above-described embodiment, the embodiment has been described in which a plurality of sub-generators 30, 30,... Each of the generators 30, 30,..., Calculates an increaseable electric power value, and based on the calculated increaseable electric power value for each unit, an increase in the generated electric power value of one slave generator 30 requires the necessary generated electric power value It may be possible to consider whether or not to cover the portion.
[0036]
【The invention's effect】
As described above in detail, in the power consignment system, the management device, and the computer program according to the present invention, the main generator that performs in-house power generation such as cogeneration facilities supplies power to the power load due to periodic inspections, periodic repairs, and breakdowns. When it is not possible to supply power, the generated power value of the operating sub-generator is increased, and the power for the required generated power value is entrusted to the power load via the power line of the power company that sells commercial power Therefore, by managing to cover the necessary power generation value, the power generation value of the sub-generator can be increased in a few seconds to tens of seconds. It is possible to carry out consignment promptly compared to the time required for this, so it is not necessary to purchase self-supplied electric power that is very short from the time the main generator stops to the consignment of power, etc. It exhibits an excellent effect.
[0037]
Further, in the present invention, the transition of the required generated power value is estimated based on the history for a predetermined period such as the previous day and the previous week, and when the required generated power is expected to increase, the stopped sub-generator is started. By doing so, it is possible to promptly respond to an increase in the required generated power, and therefore, there is an excellent effect that it is not necessary to purchase expensive self-supplied power supply.
[Brief description of the drawings]
FIG. 1 is an explanatory diagram conceptually showing a power consignment system of the present invention.
FIG. 2 is a block diagram showing a configuration of a power consignment system according to the present invention.
FIG. 3 is a flowchart showing processing of the management apparatus of the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 10 Main generator 10a Electric load 20 External generator 30 Sub generator 300 Sub generator group 40 Management apparatus EL Power line NWi Internal communication network NWo External communication network

Claims (6)

主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、複数の従発電機を有する従発電機群から前記電力線を介して電力を託送する電力託送システムにおいて、
主発電機が発電している発電電力値を記録する手段と、
主発電機から電力を供給することができない場合に、正常時に記録している発電電力値を必要発電電力値として求める手段と、
求めた必要発電電力値を、運転している従発電機の発電電力値及び発電能力値の差を示す増加可能電力値と比較する比較手段と、
該比較手段による比較により、増加可能電力値が、必要発電電力値以上であると判断したときに、運転している従発電機の発電電力値を、必要発電電力値分増加させる手段と、
従発電機群から、必要発電電力値分の電力を前記電力負荷へ託送させる手段と
を備えることを特徴とする電力託送システム。
Power is supplied from the main generator and is transferred from the sub-generator group having a plurality of sub-generators to the power load connected to the power line that transmits the power generated by the external generator via the power line. In the power consignment system
Means for recording the generated power value generated by the main generator;
Means for obtaining the generated power value recorded as normal when the power cannot be supplied from the main generator as the required generated power value;
Comparing means for comparing the obtained required generated power value with an increaseable power value indicating a difference between the generated power value and the power generation capacity value of the operating sub-generator;
Means for increasing the generated power value of the operating sub-generator by the required generated power value when the increaseable power value is determined to be greater than or equal to the required generated power value by comparison by the comparing means;
A power consignment system comprising: means for consigning power corresponding to a necessary generated power value from the sub-generator group to the power load.
主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、複数の従発電機を有する従発電機群から前記電力線を介して電力を託送する電力託送システムにおいて、
主発電機が発電している発電電力値を記録する手段と、
主発電機から電力を供給することができない場合に、正常時に記録している発電電力値を必要発電電力値として求める手段と、
求めた必要発電電力値を、従発電機群の中で運転している複数の従発電機の発電電力の合計を示す発電電力値及び運転している複数の従発電機の発電能力の合計を示す発電能力値の差を示す増加可能電力値と比較する比較手段と、
該比較手段による比較により、増加可能電力値が、必要発電電力値以上であると判断したときに、運転している従発電機群の発電電力値を、必要発電電力値分増加させる手段と、
従発電機群から、必要発電電力値分の電力を前記電力負荷へ託送させる手段とを備えることを特徴とする電力託送システム。
Power is supplied from the main generator and is transferred from the sub-generator group having a plurality of sub-generators to the power load connected to the power line that transmits the power generated by the external generator via the power line. In the power consignment system
Means for recording the generated power value generated by the main generator;
Means for obtaining the generated power value recorded as normal when the power cannot be supplied from the main generator as the required generated power value;
The calculated required power value is calculated as the generated power value indicating the sum of the generated power of the plurality of sub-generators operating in the sub-generator group and the total generation capacity of the plurality of sub-generators operating. A comparison means for comparing with an increaseable electric power value indicating a difference between the power generation capacity values indicated;
Means for increasing the generated power value of the operating sub-generator group by the required generated power value when the increaseable power value is determined to be equal to or greater than the required generated power value by comparison by the comparing means;
A power consignment system comprising: means for consigning power corresponding to a necessary generated power value from the sub-generator group to the power load.
前記比較手段による比較により、増加可能電力値が、必要電力値未満であると判断したときに、停止している従発電機を起動させる手段と、
運転させた従発電機に、必要電力値分発電させる手段と
を更に備えることを特徴とする請求項1又は請求項2に記載の電力託送システム。
Means for activating the stopped sub-generator when it is determined by the comparison by the comparison means that the increaseable power value is less than the required power value;
The power consignment system according to claim 1 or 2, further comprising means for causing the operated sub-generator to generate power for a required power value.
記録されている主発電機の発電電力値の履歴に基づいて、従発電機群から託送する電力の増加要否を判断する手段と、
増加要と判断したときに、停止している従発電機を起動させる手段と
を更に備えることを特徴とする請求項1乃至請求項3のいずれかに記載の電力託送システム。
Means for determining whether or not it is necessary to increase the power to be consigned from the sub-generator group based on the recorded history of the generated power value of the main generator;
The power consignment system according to any one of claims 1 to 3, further comprising means for starting a stopped sub-generator when it is determined that the increase is necessary.
主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、前記電力線を介して電力を託送する複数の従発電機を有する従発電機群を管理する管理装置において、
主発電機と通信する手段と、
主発電機が発電する発電電力値を記録する手段と、
主発電機から電力を供給することができない場合に、正常時に記録している発電電力値を必要発電電力値として求める手段と、
従発電機群の中で運転している複数の従発電機の発電電力の合計を示す発電電力値を検出する手段と、
求めた必要発電電力値を、運転している複数の従発電機の発電能力の合計を示す発電能力値及び検出した発電電力値の差を示す増加可能電力値と比較する手段と、
比較により、増加可能電力値が、必要発電電力値以上であると判断したときに、運転している従発電機群の発電電力値を、必要発電電力値分増加させる手段と、
従発電機群から、必要発電電力値分の電力を電力負荷へ託送させる手段と
を備えることを特徴とする管理装置。
A sub-generator group having a plurality of sub-generators for entrusting power through the power line to a power load that is supplied with power from the main generator and connected to a power line that transmits power generated by the external generator In the management device that manages
Means for communicating with the main generator;
Means for recording the value of power generated by the main generator;
Means for obtaining the generated power value recorded as normal when the power cannot be supplied from the main generator as the required generated power value;
Means for detecting a generated power value indicating the sum of the generated power of a plurality of sub-generators operating in the sub-generator group;
Means for comparing the determined required power generation value with a power generation capacity value indicating the total power generation capacity of a plurality of operating sub-generators and an increaseable power value indicating a difference between the detected power generation values;
Means for increasing the generated power value of the operating sub-generator group by the required generated power value when it is determined by comparison that the increaseable power value is equal to or greater than the required generated power value;
A management device comprising: means for entrusting power corresponding to a required generated power value from a sub-generator group to a power load.
コンピュータに、主発電機から電力を供給され、外部発電機にて発電した電力を送電する電力線に接続している電力負荷へ、前記電力線を介して電力を託送する複数の従発電機を有する従発電機群を管理させるコンピュータプログラムにおいて、
コンピュータに、主発電機が発電する発電電力値を記録させる手順と、
コンピュータに、主発電機から電力を供給することができない場合に、正常時に記録している発電電力値を必要発電電力値として求めさせる手順と、
コンピュータに、従発電機群の中で運転している複数の従発電機の発電電力の合計を示す発電電力値を検出させる手順と、
コンピュータに、求めた必要発電電力値を、運転している複数の従発電機の発電能力の合計を示す発電能力値及び検出した発電電力値の差を示す増加可能電力値と比較させる手順と、
コンピュータに、比較により、増加可能電力値が、必要発電電力値以上であると判断したときに、運転している従発電機群の発電電力値を、必要発電電力値分増加させる手順と、
コンピュータに、従発電機群から、必要発電電力値分の電力を電力負荷へ託送させる手順と
を含むことを特徴とするコンピュータプログラム。
The computer is provided with a plurality of slave generators that are supplied with power from the main generator and are consigned to the power load connected to the power line that transmits the power generated by the external generator via the power line. In a computer program for managing generator groups,
A procedure for causing a computer to record the value of power generated by the main generator;
When the computer cannot supply power from the main generator, the procedure for obtaining the generated power value recorded at the normal time as the required generated power value;
A procedure for causing a computer to detect a generated power value indicating a total of generated power of a plurality of sub-generators operating in the sub-generator group;
A procedure for causing the computer to compare the obtained required power generation value with a power generation capacity value indicating the total power generation capacity of a plurality of operating sub-generators and an increaseable power value indicating a difference between the detected power generation values;
When the computer determines that the power value that can be increased is greater than or equal to the required generated power value by comparison, a procedure for increasing the generated power value of the operating sub-generator group by the required generated power value;
A computer program comprising: a procedure for causing a computer to entrust power corresponding to a required power generation value from a sub-generator group to a power load.
JP2001093861A 2001-03-28 2001-03-28 Power consignment system, management device, and computer program Expired - Fee Related JP4132706B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001093861A JP4132706B2 (en) 2001-03-28 2001-03-28 Power consignment system, management device, and computer program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001093861A JP4132706B2 (en) 2001-03-28 2001-03-28 Power consignment system, management device, and computer program

Publications (2)

Publication Number Publication Date
JP2002291163A JP2002291163A (en) 2002-10-04
JP4132706B2 true JP4132706B2 (en) 2008-08-13

Family

ID=18948143

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001093861A Expired - Fee Related JP4132706B2 (en) 2001-03-28 2001-03-28 Power consignment system, management device, and computer program

Country Status (1)

Country Link
JP (1) JP4132706B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4761639B2 (en) * 2001-03-30 2011-08-31 東京瓦斯株式会社 Consignment system
JP4053965B2 (en) * 2003-11-18 2008-02-27 株式会社日立製作所 Combined heat and power system control method and combined heat and power system controller

Also Published As

Publication number Publication date
JP2002291163A (en) 2002-10-04

Similar Documents

Publication Publication Date Title
US7979355B2 (en) Content bank for objects
JP4280003B2 (en) Remote maintenance method and industrial equipment
US8903559B2 (en) Energy grid device commissioning
JP4299996B2 (en) Remote maintenance system and remote maintenance method
US20030163217A1 (en) Semiconductor manufacturing apparatus and its diagnosis apparatus and operating system
US20080215628A1 (en) Replacement part order processing apparatus, method for ordering replacement parts and computer-readable recording medium
JP2019003440A (en) Maintenance management system, abnormality detection device, and maintenance plan creation device
JP4132706B2 (en) Power consignment system, management device, and computer program
JP2003173207A (en) Remote fault diagnosis method and system
CN104423963A (en) Control program management device, information processing device, and control program processing method
US7225168B2 (en) Method and system for providing a service on demand
JP2004274937A (en) Electric power supply and demand management system
JP7814643B1 (en) Pricing system, pricing method, and program
JP5124355B2 (en) Remote maintenance system
JP2002132540A (en) Method of support service for system monitoring and operating
JP2003125539A (en) Power transfer management method and system
KR20250128079A (en) Charging device monitoring server device and method thereof
JP2004070741A (en) Manufacturing device or inspection device, network system, and part ordering method
JP2004088840A (en) Power transmission plan making method and program
JP2003235156A (en) Power supply and demand system
JP2004030020A (en) Plant data distribution system and plant data distribution method
JP2002140582A (en) Ordering agency system
KR20260063856A (en) SKU-based shopping mall integration system
KR20240082228A (en) Server
JP2003134889A5 (en)

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070118

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080502

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080513

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080602

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110606

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees