JP4139350B2 - Two-stage propulsion method - Google Patents
[go: Go Back, main page]

JP4139350B2 - Two-stage propulsion method - Google Patents

Two-stage propulsion method Download PDF

Info

Publication number
JP4139350B2
JP4139350B2 JP2004141448A JP2004141448A JP4139350B2 JP 4139350 B2 JP4139350 B2 JP 4139350B2 JP 2004141448 A JP2004141448 A JP 2004141448A JP 2004141448 A JP2004141448 A JP 2004141448A JP 4139350 B2 JP4139350 B2 JP 4139350B2
Authority
JP
Japan
Prior art keywords
buried pipe
pipe
excavator
buried
propulsion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2004141448A
Other languages
Japanese (ja)
Other versions
JP2005320822A (en
Inventor
信彦 木村
英二 森長
道夫 岡村
圭伺 磯
彰 伊藤
大介 荒木
Original Assignee
機動建設工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 機動建設工業株式会社 filed Critical 機動建設工業株式会社
Priority to JP2004141448A priority Critical patent/JP4139350B2/en
Publication of JP2005320822A publication Critical patent/JP2005320822A/en
Application granted granted Critical
Publication of JP4139350B2 publication Critical patent/JP4139350B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

本発明は、2段階推進工法に関し、詳しくは、1個所の推進区間の前半区間と後半区間とで異なる形態で埋設管を施工する2段階推進工法を対象にしている。   The present invention relates to a two-stage propulsion method, and more particularly, to a two-stage propulsion method in which a buried pipe is constructed in different forms in a first half section and a second half section of one propulsion section.

一般的な推進工法の基本作業は、地盤に掘削された出発立坑の内側壁から地盤内に、掘進機と掘進機の後端に連結された埋設管とを推進させて、掘進機によって地盤に掘削されたトンネルに埋設管を推進埋設していく。掘進機に連結された埋設管列の先端が、到達立坑まで推進されれば、1区間の推進作業が終了することになる。
通常の推進工法では、鋼管やヒューム管などからなる1種類の埋設管を、推進区間の全体にわたって施工する。
これとは別に、2重管推進工法と呼ばれる工法が知られている。2重管推進工法では、1区間の推進区間のうち、出発立坑に近い前半区間には、鋼管などからなる大径の外管と、ヒューム管などからなる小径の内管との2重に埋設管を施工し、到達立坑に近い後半区間には、内管だけを施工する。外管は、前半区間だけに施工され、内管は、前半区間および後半区間の全長に施工されることになる。前半区間では、内管と外管とが2重になった状態で推進埋設されるので、2重管推進工法と呼ばれる。
The basic work of the general propulsion method is to push the excavator and the buried pipe connected to the rear end of the excavator into the ground from the inner wall of the starting shaft excavated in the ground, and use the excavator to The buried pipe will be propelled and buried in the excavated tunnel. If the tip of the buried pipe row connected to the excavator is propelled to the reaching shaft, the propulsion work for one section is completed.
In the normal propulsion method, one type of buried pipe made of steel pipe or fume pipe is constructed over the entire propulsion section.
Apart from this, a construction method called a double pipe propulsion construction method is known. In the double-pipe propulsion method, the first half of the propulsion section close to the starting shaft is buried in a double with a large-diameter outer pipe made of steel pipe and a small-diameter inner pipe made of fume pipe. A pipe will be constructed, and only the inner pipe will be constructed in the latter half of the section near the shaft. The outer pipe is constructed only in the first half section, and the inner pipe is constructed over the entire length of the first half section and the second half section. In the first half section, since the inner pipe and the outer pipe are propelled and buried in a double state, it is called a double pipe propulsion method.

2重管推進工法は、前半区間の地盤上方に、鉄道線路などの構造物が存在する場合に、地盤の過剰な変動や崩落などを防止するのに有効な工法である。また、後半区間の内管を推進埋設する作業では、前半区間で外管の内部空間を移動する内管には、地盤からの抵抗や土圧が加わらないため、全体の抵抗力が格段に減少し、推進力が小さくて済むという利点がある。1種類の埋設管では十分に施工できない長距離の推進工法を可能にする。施工中および施工後に、鉄道線路などの上方の構造物から加わる圧力や振動、衝撃で、内管が損傷することを、外管で保護するという機能も果たせる。
特許文献1には、2重管推進工法に使用する掘進装置に、掘削外径が外管と内管との何れにも対応できるように可変になった回転掘削盤を備えておく技術が示されている。この技術では、後半区間で小径の内管を推進埋設する際に、掘削外径を小さく設定しておくことで、内管の外周と地盤との間に過剰な隙間が生じないという利点がある。内管と地盤の間に裏込め材を注入して埋めるような作業が必要なくなる。
The double-pipe propulsion method is an effective method for preventing excessive fluctuation or collapse of the ground when a structure such as a railway line exists above the ground in the first half section. In addition, in the work of propelling and embedding the inner pipe in the second half section, the resistance from the ground and earth pressure are not applied to the inner pipe that moves in the inner space of the outer pipe in the first half section, so the overall resistance is greatly reduced. However, there is an advantage that the propulsive force is small. A long-distance propulsion method that cannot be sufficiently constructed with one type of buried pipe is possible. The function of protecting the inner pipe from being damaged by pressure, vibration, or impact applied from an upper structure such as a railroad track during and after the construction can be performed.
Patent Document 1 discloses a technique in which a drilling device used in a double pipe propulsion method is provided with a rotary excavator whose outer diameter is variable so that it can be adapted to both the outer pipe and the inner pipe. Has been. In this technology, when a small-diameter inner pipe is propelled and embedded in the latter half section, there is an advantage that an excessive gap is not generated between the outer circumference of the inner pipe and the ground by setting the outer diameter of the excavation small. . It is not necessary to inject a backfill material between the inner pipe and the ground.

特許文献2には、2重管推進工法の後半区間で、内管の外周と地盤との間に滑材を注入することで、内管の推進をスムーズに行い、付加する推進力を軽減する技術が示されている。
特許第2746866号公報 特許第2754172号公報
In Patent Document 2, in the latter half section of the double pipe propulsion method, a lubricant is injected between the outer periphery of the inner pipe and the ground, thereby smoothly propelling the inner pipe and reducing the added propulsive force. Technology is shown.
Japanese Patent No. 2746866 Japanese Patent No. 2754172

従来の2重管推進工法では、埋設管の資材コストが高くつき、作業に手間を要し、作業能率が劣るという問題がある。
前記したように、推進区間のうち、前半区間では、外管と内管とが2重に施工されるので、当然、埋設管の資材コストも2重に必要となる。通常の推進工法に比べて施工コストが高くつくことになる。
また、前半区間で、埋設管列の後端に新たな埋設管を連結する作業では、新たな内管と外管とを2重にした状態で、それぞれを埋設管列の後端に連結することになり、作業の手間がかかる。出発立坑に設置された元押しジャッキで埋設管列に推進力を加える際にも、内外2重の埋設管に同じように推進力を加えるのは難しい。通常は、外管だけに推進力を加えるが、内管の外側で外管だけに確実に推進力を加えるようにするには、技術的にも難しく、面倒な作業が必要である。
In the conventional double pipe propulsion method, there is a problem that the material cost of the buried pipe is high, work is troublesome, and work efficiency is inferior.
As described above, since the outer pipe and the inner pipe are doubled in the first half of the propulsion section, naturally, the material cost of the buried pipe is also doubled. The construction cost is high compared to the normal propulsion method.
In the first half section, in the operation of connecting a new buried pipe to the rear end of the buried pipe row, each of the new inner pipe and the outer pipe is connected to the rear end of the buried pipe row in a doubled state. As a result, it takes time and effort. When applying a propulsive force to the buried pipe row with a main jack installed in the starting shaft, it is difficult to apply a propulsive force to the inner and outer double buried pipes. Usually, a propulsive force is applied only to the outer tube, but it is technically difficult and troublesome to ensure that the propelling force is applied only to the outer tube outside the inner tube.

さらに、前半区間では、推進抵抗を低減するための滑材注入作業が行い難い。推進抵抗を低減するには、外管の外周と地盤との間に滑材を注入しなければならない。しかし、外管の内側には内管が存在している。内管の内部空間に導入した滑材供給管を、内管を貫通させて外管に接続するには、内管の貫通位置と外管への接続位置とを正確に合わせておく必要がある。非常に手間のかかる技術的に難しい作業である。前半区間で滑材の供給を行わないと、外管は大径であるから、地盤との接触面積が大きく地盤抵抗が大きくなり易い。推進がスムーズに行えなくなったり、過大な推進力を要求されたりすることになる。
これらの問題があるため、2重管推進工法は、施工に手間と技術を要し、作業能率も良くない、コストのかかる推進工法であると思われていた。
Further, in the first half section, it is difficult to perform the lubricant injection work for reducing the propulsion resistance. In order to reduce the propulsion resistance, a lubricant must be injected between the outer periphery of the outer tube and the ground. However, an inner tube exists inside the outer tube. In order to connect the lubricant supply pipe introduced into the inner space of the inner pipe to the outer pipe through the inner pipe, it is necessary to accurately match the penetration position of the inner pipe with the connection position to the outer pipe. . This is a very time-consuming and technically difficult task. If the lubricant is not supplied in the first half section, the outer tube has a large diameter, so that the contact area with the ground is large and the ground resistance tends to increase. Propulsion cannot be performed smoothly, or excessive thrust is required.
Because of these problems, the double-pipe propulsion method was thought to be a costly propulsion method that required labor and technology for construction, and had poor work efficiency.

本発明の課題は、従来の2重管推進工法が有する問題点を解消し、施工を容易にして、作業能率を向上させ、施工コストを削減することである。   An object of the present invention is to eliminate the problems of the conventional double pipe propulsion method, to facilitate the construction, improve the work efficiency, and reduce the construction cost.

本発明にかかる2段階推進工法は、
地盤内において出発立坑から到達立坑に至る推進区間のうち、出発立坑側の前半区間には第1の埋設管、到達立坑側の後半区間には第2の埋設管をそれぞれ施工する2段階推進工法であって、前記地盤を掘削する掘進機に、前記第2埋設管は配置せずに前記第1埋設管を連結して、前記出発立坑から地盤内に推進させて、前記前半区間に第1埋設管を推進埋設する前半推進工程(a)と、前記前半推進工程(a)の後、前記掘進機と前記第1埋設管との連結を解除し、前記出発立坑から地盤内に配置された第1埋設管の内部を通して前記掘進機に連結された前記第2埋設管を、掘進機とともに第1埋設管の列先端から地盤内に推進させ、第1埋設管の列先端から到達立坑に至る後半区間に第2埋設管を推進埋設する後半推進工程(b)とを含み、前記後半推進工程(b)が、前記第1埋設管の内部で、前記掘進機に連結された第2埋設管の後端から第1埋設管の後端までにわたって、前記第2埋設管の長さよりも十分に短い長さの鋼枠ブロックからなる推力伝達材を、軸方向に多数並べて配置する工程と、前記出発立坑に設置された元押しジャッキで前記推力伝達材を介して第2埋設管および掘進機に推進力を加える工程とを含む、
ことを特徴とする
The two-stage propulsion method according to the present invention is
Two-stage propulsion method in which the first buried pipe is constructed in the first half section on the starting shaft side and the second buried pipe is constructed in the latter half section on the reaching shaft side among the propulsion sections from the starting shaft to the reaching shaft in the ground. The first buried pipe is connected to the excavator for excavating the ground without arranging the second buried pipe, and is propelled from the starting shaft into the ground, and the first half section is moved to the first half section. After the first half propulsion step (a) for propelling the buried pipe and the first half propulsion step (a), the connection between the excavator and the first buried pipe is released, and the buried pipe is disposed in the ground from the starting shaft. The second buried pipe connected to the excavator through the inside of the first buried pipe is propelled together with the excavator from the row tip of the first buried tube into the ground, and reaches the reach shaft from the row tip of the first buried pipe. including a late promotion step (b) to promote embedding of the second buried pipe in the second half section In the second half propulsion step (b), the second buried pipe extends from the rear end of the second buried pipe connected to the excavator to the rear end of the first buried pipe inside the first buried pipe. A step of arranging a large number of thrust transmission members composed of steel frame blocks having a length sufficiently shorter than the length thereof in an axial direction, and a second embedding through the thrust transmission member by a main push jack installed in the starting shaft Applying a thrust to the pipe and the excavator,
It is characterized by that .

〔2段階推進工法の適用範囲〕
基本的には、通常の2重管推進工法が適用されている施工環境や施工条件に適用できる。
具体的には、上下水道管、ガス管、電力配線用配管、情報通信線線用配管、物資搬送用配管および、これらの配管や配線の複合配管など、地盤内に施工されたトンネル空間を利用する用途に適用できる。
〔推進区間〕
基本的には、通常の推進工法あるいは2重管推進工法と同様に設定される。
[Scope of application of the two-stage propulsion method]
Basically, it can be applied to the construction environment and construction conditions where the normal double pipe propulsion method is applied.
Specifically, use the tunnel space constructed in the ground such as water and sewage pipes, gas pipes, power wiring pipes, information communication line pipes, material transport pipes, and composite pipes of these pipes and wiring. It can be applied to the usage.
[Promotion section]
Basically, it is set in the same manner as the normal propulsion method or double pipe propulsion method.

推進区間は、地盤に垂直方向に掘削された出発立坑と到達立坑との間の区間である。この推進区間の前半区間に、鉄道線路や地上構造物などが存在している状態で、地下に下水道などを施工するときに、2段階推進工法が好ましく適用できる。
鉄道線路などが存在しない通常の地盤の場合でも、1回の推進区間で長い距離にわたって埋設管を施工する場合にも、2段階推進工法が好ましく適用できる。
推進区間の推進経路すなわち埋設管の施工経路は、全長が水平直線である場合のほか、垂直方向に高低差のある傾斜がある場合や、円弧などの曲線である場合、直線と曲線とが混在する場合もある。
The propulsion section is a section between the starting shaft and the reaching shaft excavated in the direction perpendicular to the ground. The two-stage propulsion method can be preferably applied when constructing a sewer underground in the first half of this propulsion section with railroad tracks or ground structures.
Even in the case of ordinary ground where there is no railway track or the like, the two-stage propulsion method can be preferably applied even when a buried pipe is constructed over a long distance in one propulsion section.
The propulsion route of the propulsion section, that is, the construction route of the buried pipe, is not only when the entire length is a horizontal straight line, but also when there is an inclination with a vertical difference in height or when it is a curve such as an arc, a straight line and a curve are mixed. There is also a case.

推進区間の両端には、出発立坑と到達立坑が施工される。通常、出発立坑は元押しジャッキ等を設置したり、掘進機、埋設管などを搬入したりするので、比較的に大きなスペースを取る。到達立坑は、出発立坑よりも狭いスペースでも良い。掘進機などを撤去する場合にはそれを可能にするスペースが必要である。掘進機の撤去などを行わない場合は、既設の人孔(マンホール)などを利用することもできる。建築物や土木構造物の地下部分を、出発立坑や到達立坑に利用することもできる。
〔埋設管〕
基本的には、通常の推進工法で採用されている埋設管と同様の材料や構造が適用できる。
At both ends of the propulsion section, a starting shaft and a reaching shaft are constructed. Usually, the starting shaft has a relatively large space because it installs a jack jack or the like, or carries an excavator, a buried pipe or the like. The reaching shaft may be a smaller space than the starting shaft. When removing excavators etc., a space is needed to make it possible. If the excavator is not removed, an existing manhole can be used. The underground part of the building or civil engineering structure can also be used for the starting shaft and the reaching shaft.
[Built pipe]
Basically, the same material and structure as the buried pipe adopted in the normal propulsion method can be applied.

埋設管の材料には、鋼管、鋼管の内部にリブや補強枠を溶接して補強したもの、コンクリート管、鉄筋コンクリート管、ヒューム管、FRP管、合成樹脂管、セラミック管などがある。複数の材料層が積層された複合管も使用できる。これらの管材の中から、第1埋設管および第2埋設管の要求性能に適した管材を組み合わせればよい。
埋設管の径や長さは、材料の違いや施工条件の違いによっても異なる。通常は、内径で規定する口径を800〜3000mmの範囲に設定することができる。長さは0.6〜4.0mの範囲に設定することができる。
第1埋設管は、相対的に径が大きく、耐力に優れた管材を用いる。例えば、鋼管が使用される。第2埋設管は、相対的に径が小さい管材が使用される。通常、第2埋設管が施工される後半区間は長いので、コストの安価な管材が好ましい。内面に特別な追加加工を加えなくても使用できる管材が好ましい。例えば、下水道の場合、ヒューム管などが使用される。
The material of the buried pipe includes a steel pipe, a steel pipe reinforced by welding a rib or a reinforcing frame, a concrete pipe, a reinforced concrete pipe, a fume pipe, an FRP pipe, a synthetic resin pipe, a ceramic pipe, and the like. A composite tube in which a plurality of material layers are laminated can also be used. From these pipe materials, pipe materials suitable for the required performance of the first buried pipe and the second buried pipe may be combined.
The diameter and length of the buried pipe also differ depending on the difference in materials and construction conditions. Usually, the aperture defined by the inner diameter can be set in the range of 800 to 3000 mm. The length can be set in the range of 0.6 to 4.0 m.
The first buried pipe uses a pipe material having a relatively large diameter and excellent proof stress. For example, a steel pipe is used. A pipe material having a relatively small diameter is used for the second buried pipe. Usually, since the second half section in which the second buried pipe is constructed is long, an inexpensive pipe material is preferable. A tube material that can be used without any special additional processing on the inner surface is preferred. For example, in the case of sewerage, a fume pipe is used.

第2埋設管の外径は、第1埋設管の内径よりも小さくしておく。第1埋設管の内周と第2埋設管の外周との間の隙間が十分にあるほど、第1埋設管の内部を第2埋設管が通過しやすい。但し、第2埋設管の外径が小さくなるので、第1埋設管の施工と同じ掘削径の掘進機では、第2埋設管の外周と地盤との間に大きな隙間が生じ易い。この問題を解消するために、掘削径が可変の掘進機を用い、その掘削径の可変範囲を広く設定することが有効である。通常、第1埋設管の内周と第2埋設管の外周との半径方向の隙間を片側で10〜200mmに設定することができる。
埋設管の端部には、埋設管同士を前後に連結するための嵌合形状や係合形状などの連結構造を設けておくことができる。連結個所からの土砂や地下水の侵入を阻止する封止性を高める封止構造を設けておくこともできる。
The outer diameter of the second buried pipe is made smaller than the inner diameter of the first buried pipe. The more the gap between the inner periphery of the first embedded tube and the outer periphery of the second embedded tube is, the easier the second embedded tube passes through the inside of the first embedded tube. However, since the outer diameter of the second buried pipe is reduced, a large gap is likely to be generated between the outer circumference of the second buried pipe and the ground in the excavator having the same excavation diameter as the construction of the first buried pipe. In order to solve this problem, it is effective to use an excavator having a variable excavation diameter and to set a wide variable range of the excavation diameter. Usually, the radial gap between the inner circumference of the first buried pipe and the outer circumference of the second buried pipe can be set to 10 to 200 mm on one side.
A connecting structure such as a fitting shape or an engaging shape for connecting the embedded tubes back and forth can be provided at the end of the embedded tube. It is also possible to provide a sealing structure that enhances the sealing performance to prevent the intrusion of earth and sand and groundwater from the connection point.

〔掘進機〕
基本的には、通常の推進工法で使用されている掘進機と同様の材料や構造が適用できる。
掘進機のうち、地盤を掘削して埋設管を推進させるトンネルを形成する機構には、前面に掘削ビットや掘削刃を備えて回転する回転掘削盤を備えておくことができる。地盤を周囲に圧密してトンネルを拡げる圧密コーンを設けておくことができる。地盤に泥水を噴出し、泥水とともに土砂を排出させる泥水供給装置を備えておくことができる。
このような種々の掘削構造による掘進機の掘削径が可変であるものが好ましい。掘削径が可変である掘進機の構造は、例えば、特許第2746866号公報に開示された技術が適用できる。具体的には、掘削ビットや掘削刃の一部または全体が、掘進機の放射方向に進退自在になっていればよい。掘削ビットなどを進退させるには、油圧機構や電磁アクチュエータ、リンク機構、カム機構、ギア機構など各種の動作機構が採用できる。
[Digging machine]
Basically, the same material and structure as the excavator used in the normal propulsion method can be applied.
Among the excavators, a mechanism that forms a tunnel for excavating the ground and propelling the buried pipe can be provided with a rotary excavator that rotates with a excavation bit and an excavation blade on the front surface. A consolidation cone can be provided to consolidate the ground to the surroundings and expand the tunnel. A muddy water supply device that ejects muddy water to the ground and discharges the mud with the muddy water can be provided.
It is preferable that the excavation diameter of the excavator with such various excavation structures is variable. For example, the technology disclosed in Japanese Patent No. 2746866 can be applied to the structure of the excavator having a variable excavation diameter. Specifically, a part or the whole of the excavation bit and the excavation blade only needs to be able to advance and retreat in the radial direction of the excavator. In order to move the excavation bit forward and backward, various operation mechanisms such as a hydraulic mechanism, an electromagnetic actuator, a link mechanism, a cam mechanism, and a gear mechanism can be employed.

掘進機の掘削径は、一定の範囲で連続的に可変であれば、施工条件によって異なる任意の外径の埋設管に対応しやすい。少なくとも、施工に用いる第1埋設管に対応する掘削径と第2埋設管に対応する掘削径との2段階で掘削径が可変であるものが望ましい。
掘削径が可変の掘進機を用いることで、第2埋設管を推進埋設する後半区間で、第2埋設管と周囲の地盤との間に過大な隙間があかない。第2埋設管の推進が正確に安定して実施でき、裏込め材を注入して隙間を埋めるような作業が不要になる。
掘進機の後端には、第1埋設管と第2埋設管とを何れも連結できる構造を備えておく。通常の掘進機には、埋設管を連結するための連結構造を備えている。具体的には、例えば、掘進機の後端で周壁材を少し突き出して、そこに埋設管を嵌入して連結する。このような連結構造を、第1埋設管の径に対応する構造と、第2埋設管の径に対応する構造との2種類設けておけばよい。
If the excavating diameter of the excavator is continuously variable within a certain range, it is easy to cope with a buried pipe having an arbitrary outer diameter that varies depending on the construction conditions. It is desirable that the excavation diameter is variable at least in two stages, that is, the excavation diameter corresponding to the first buried pipe used for construction and the excavation diameter corresponding to the second buried pipe.
By using an excavator with a variable excavation diameter, there is no excessive gap between the second buried pipe and the surrounding ground in the latter half section where the second buried pipe is propulsion buried. The propulsion of the second buried pipe can be carried out accurately and stably, and the operation of filling the gap by injecting the backfilling material becomes unnecessary.
The rear end of the excavator is provided with a structure that can connect both the first buried pipe and the second buried pipe. A normal excavator has a connection structure for connecting the buried pipe. Specifically, for example, the peripheral wall material is slightly protruded at the rear end of the excavator, and the buried pipe is inserted and connected there. Two types of connection structures such as a structure corresponding to the diameter of the first buried pipe and a structure corresponding to the diameter of the second buried pipe may be provided.

具体的には、第1埋設管の連結構造に、径を縮小するための環材を着脱自在に追加することで、第2埋設管の連結も可能にすることができる。掘進機の通常の連結構造に第2埋設管が連結され、掘進機の後端外周に径調整用の環材を介して第1埋設管を連結することもできる。第1埋設管のうち、先頭の第1埋設管だけに、掘進機に備えた第2埋設管に連結できる連結器を着脱自在に設けておくこともできる。その他、2種類の埋設管の連結に必要な形状や構造を追加しておくことができる。
掘進機とその後端に連結される第1および第2埋設管との連結個所に、土砂や地下水の侵入を阻止する封止構造を備えておくことができる。
Specifically, the second embedded pipe can be connected by detachably adding a ring material for reducing the diameter to the connection structure of the first embedded pipe. The second embedded pipe can be connected to the normal connection structure of the excavator, and the first embedded pipe can be connected to the outer periphery of the rear end of the excavator through a diameter adjusting ring. Of the first buried pipes, only the leading first buried pipe can be detachably provided with a coupler that can be connected to the second buried pipe provided in the excavator. In addition, a shape and a structure necessary for connecting two types of buried pipes can be added.
A sealing structure that prevents intrusion of earth and sand or groundwater can be provided at a connection portion between the excavator and the first and second buried pipes connected to the rear end thereof.

〔前半推進工程(a)〕
基本的には、埋設管として第1埋設管を用いて、通常の推進工法と同様の作業を行う。
掘進機に第1埋設管を連結する。掘進機の掘削径を第1埋設管に対応する掘削径に設定することができる。出発立坑から、掘進機および第1埋設管を、地盤内に推進させる。前半区間の終点となる所定の距離まで、第1埋設管を推進埋設する。
第1埋設管の推進埋設を行うときに、第1埋設管の内部に導入された滑材供給管から、第1埋設管と地盤との間に滑材を供給することができる。第1埋設管には、滑材を外周面に吐出する滑材供給口を設けておくことができる。滑材供給管や滑材供給口、滑材供給口に滑材供給管を接続するための分岐管構造などは、通常の推進工法における滑材供給構造と共通する構造が採用できる。滑材の供給方法も、通常の推進工法と同様に行える。
[First half propulsion process (a)]
Basically, using the first buried pipe as the buried pipe, the same work as the normal propulsion method is performed.
The first buried pipe is connected to the excavator. The excavation diameter of the excavator can be set to the excavation diameter corresponding to the first buried pipe. From the starting shaft, the excavator and the first buried pipe are propelled into the ground. The first buried pipe is propelled and buried to a predetermined distance that becomes the end point of the first half section.
When propulsion embedding of the first buried pipe, the lubricant can be supplied between the first buried pipe and the ground from the lubricant supply pipe introduced into the first buried pipe. The first buried pipe can be provided with a lubricant supply port for discharging the lubricant to the outer peripheral surface. As the sliding material supply pipe, the lubricating material supply port, and the branch pipe structure for connecting the lubricating material supply tube to the lubricating material supply port, a structure common to the lubricating material supply structure in the normal propulsion method can be adopted. The method for supplying the lubricant can be performed in the same manner as the normal propulsion method.

〔後半推進工程(b)〕
掘進機と第1埋設管との連結を解除する。掘進機と第1埋設管との連結解除は、地盤内で、第1埋設管の内部空間から作業が行えるようにしておく。出発立坑や地上から遠隔操作で連結解除を行えるようにしておくこともできる。
第2埋設管を、出発立坑から地盤内に配置された第1埋設管の内部を通して掘進機に連結する。第2埋設管は、1度に1本だけを連結して推進埋設してもよいし、1度に複数本を連結して推進埋設することもできる。複数本を連結する場合は、前後の埋設管同士を連結しておく。
[Second half promotion process (b)]
Release the connection between the excavator and the first buried pipe. The connection between the excavator and the first buried pipe is released from the internal space of the first buried pipe in the ground. It can also be made possible to release the connection from the starting shaft or from the ground.
The second buried pipe is connected to the excavator through the inside of the first buried pipe disposed in the ground from the starting vertical shaft. Only one of the second buried pipes may be connected to be propulsion embedded at a time, or a plurality of the second embedded pipes may be connected to be propulsion embedded at a time. When connecting a plurality of pipes, the front and rear buried pipes are connected together.

掘進機の掘削径を第2埋設管に対応する掘削径に変更することが望ましい。第1埋設管に対応する掘削径から縮小されることになる。
掘進機に連結された第2埋設管を、第1埋設管の列先端から地盤内に推進させる。第1埋設管と第2埋設管との間に、摺動可能な封止部材を配置しておけば、第1埋設管の先端から内部に土砂や地下水が侵入することが阻止できる。封止部材は、通常の推進工法において、掘進機や埋設管に備える封止部材の技術が適用できる。封止部材は、静止している第1埋設管の先端内周に配置しておくことができる。
第2埋設管の後端が第1埋設管の列先端近くになるまで推進されれば、新たな第2埋設管の連結を行い、再び推進作業を行う。このような推進作業を繰り返して、到達立坑から第1埋設管の列先端までの後半区間に、第2埋設管の列を施工する。第2埋設管は、第1埋設管の列先端あるいは列先端からわずかに第1埋設管側に入ったところまで施工される。第1埋設管の出発立坑に近い前半区間には、第2埋設管は施工されない。
It is desirable to change the excavating diameter of the excavator to an excavating diameter corresponding to the second buried pipe. The excavation diameter corresponding to the first buried pipe is reduced.
The second buried pipe connected to the excavator is propelled into the ground from the row tip of the first buried pipe. If a slidable sealing member is arranged between the first buried pipe and the second buried pipe, it is possible to prevent earth and sand and groundwater from entering from the tip of the first buried pipe. The sealing member can be applied with a sealing member technique provided in an excavating machine or a buried pipe in a normal propulsion method. The sealing member can be disposed on the inner periphery of the distal end of the stationary first buried pipe.
If propulsion is performed until the rear end of the second buried pipe is close to the front end of the first buried pipe, the new second buried pipe is connected and the propulsion operation is performed again. Such a propulsion operation is repeated to construct the second buried pipe row in the second half section from the reaching shaft to the first tip of the first buried pipe row. The second buried pipe is applied to the row tip of the first buried tube or a position where it slightly enters the first buried tube side from the row tip. The second buried pipe is not constructed in the first half section near the starting shaft of the first buried pipe.

推進作業を行う際に、第2埋設管の後端は、第1埋設管の内部にあるので、通常の推進工法において出発立坑に設置される元押しジャッキで、第2埋設管の後端に直接に推進力を加えるのは困難である。
そこで、第1埋設管の内部に存在する第2埋設管の後端に推進力を加える技術手段が必要である。
<推力伝達材の利用>
第1埋設管の内部で、掘進機に連結された第2埋設管の後端から第1埋設管の後端までにわたって、推力伝達材を配置する工程(b−1)と、出発立坑に設置された元押しジャッキで推力伝達材を介して第2埋設管および掘進機に推進力を加える工程(b−2)とを含むことができる。
When the propulsion work is performed, the rear end of the second buried pipe is located inside the first buried pipe, so that a normal push jack installed at the starting shaft in the normal propulsion construction method is used at the rear end of the second buried pipe. It is difficult to apply driving force directly.
Therefore, a technical means for applying a propulsive force to the rear end of the second buried pipe existing inside the first buried pipe is necessary.
<Use of thrust transmission material>
The step (b-1) of arranging the thrust transmission material from the rear end of the second buried pipe connected to the excavator to the rear end of the first buried pipe inside the first buried pipe and installed in the starting shaft And a step (b-2) of applying a propulsive force to the second buried pipe and the excavator through the thrust transmission member with the main push jack.

推力伝達材は、元押しジャッキから第2埋設管まで必要な推進力を伝達できる剛性あるいは耐力を備えていることが要求される。鋼材など機械的強度の高い材料を使用することができる。コンクリートやFRP材などを使用することもできる。形鋼材を枠状に組み立てて溶接やボルト締結で固定して構築された鋼枠材が使用できる。柱材や管材を使用することもできる。
元押しジャッキから第2埋設管までの距離が長い場合は、推力伝達材として、出発立坑から第1埋設管の内部への搬入が行い易い程度の比較的短い寸法のものを、軸方向で前後に並べて配置した状態で推力を伝達させることもできる。この場合、第2埋設管の長さと同じ程度の推力伝達材であれば、第2埋設管を順次連結して行くのと合わせて、推力伝達材も増やして配置するようにできる。第2埋設管の長さより、さらに短い推力伝達材のほうが、搬送などの取り扱いが行い易い。作業状況に合わせて、必要な個数の推力伝達材を組み合わせれば、寸法の異なる第2埋設管の施工にも容易に対応できる。
The thrust transmission material is required to have rigidity or proof strength capable of transmitting a necessary propulsive force from the main pushing jack to the second buried pipe. A material having high mechanical strength such as steel can be used. Concrete or FRP material can also be used. A steel frame material constructed by assembling a shape steel material into a frame shape and fixing it by welding or bolt fastening can be used. Column material and pipe material can also be used.
When the distance from the main jack to the second buried pipe is long, a thrust transmission material with a comparatively short dimension that can easily be carried into the first buried pipe from the starting shaft is moved back and forth in the axial direction. It is also possible to transmit the thrust in a state where they are arranged side by side. In this case, if the thrust transmission material is approximately the same as the length of the second embedded pipe, the thrust transmission material can be increased and arranged together with the sequential connection of the second embedded pipes. A shorter thrust transmission material is easier to handle such as transport than the length of the second buried pipe. By combining the necessary number of thrust transmission materials according to the work situation, it is possible to easily cope with the construction of the second buried pipe having different dimensions.

具体的には、例えば、前記した鋼材で枠状に構築された鋼枠ブロックを多数、軸方向で前後に並べて使用することができる。
推力伝達材には、互いに前後方向に連結固定できる手段を備えておくことができる。嵌合や係合、ボルト締結などの手段が適用できる。但し、推力伝達材は推進方向のみに荷重を伝達できればよいので、特別な固定手段を備えておかなくても、推力の伝達は可能である。施工後の撤去作業は、推力伝達材同士を固定しておかないほうが簡単になる。
第1埋設管の内部には、推力伝達材を支持して推進方向への移動をスムーズにさせるレールや案内部材を設置しておくことができる。このようなレールや案内部材は、第2埋設管を移送したり安定的に支持したりするのにも利用できる。
Specifically, for example, a large number of steel frame blocks constructed in a frame shape with the above-described steel materials can be used side by side in the axial direction.
The thrust transmission member can be provided with means that can be connected and fixed in the front-rear direction. Means such as fitting, engagement, and bolt fastening can be applied. However, since the thrust transmission material only needs to be able to transmit a load only in the propulsion direction, the thrust can be transmitted without a special fixing means. Removal work after construction is easier if the thrust transmission materials are not fixed together.
Inside the first buried pipe, a rail or a guide member that supports the thrust transmission material and smoothly moves in the propulsion direction can be installed. Such rails and guide members can also be used to transport and stably support the second buried pipe.

<移動ジャッキ装置の利用>
第1埋設管の内部に軸方向に移動自在な移動ジャッキ装置を配置する工程(b−3)と、移動ジャッキ装置を第2埋設管の後端に配置して、移動ジャッキ装置から第2埋設管および掘進機に推進力を加える工程(b−4)とを含むことができる。
移動ジャッキ装置には、通常の元押しジャッキと同様に、油圧などで駆動されて作動軸が進退する推力発生ジャッキを備えておく。複数本の推力発生ジャッキを第2埋設管の周方向に沿って間隔をあけて配置しておくこともできる。
移動ジャッキ装置には、第1埋設管の内部を軸方向に移動可能な移動構造を備えておくことができる。推力発生ジャッキを作動させたときの反力を、第1埋設管で支持させるために、移動ジャッキ装置を第1埋設管に着脱自在に固定する固定手段も備えておくことができる。
<Use of mobile jack device>
A step (b-3) of disposing a movable jack device that is movable in the axial direction inside the first buried pipe, and a movable jack device arranged at the rear end of the second buried pipe, And a step (b-4) of applying a driving force to the pipe and the excavator.
The moving jack device is provided with a thrust generating jack that is driven by hydraulic pressure or the like to move the operating shaft back and forth in the same manner as a normal main pushing jack. A plurality of thrust generating jacks may be arranged at intervals along the circumferential direction of the second buried pipe.
The moving jack device can be provided with a moving structure capable of moving in the axial direction inside the first buried pipe. In order to support the reaction force when the thrust generating jack is operated by the first embedded pipe, a fixing means for detachably fixing the movable jack device to the first embedded pipe can be provided.

具体的には、移動構造として、第1埋設管の底面あるいは底部に敷いたレール上を走行する走行車輪を備えておくことができる。固定手段として、移動ジャッキ装置の構造部材と上記レールとを締結する固定ピンや固定ボルトを着脱自在に設けておくことができる。
<滑材の供給>
第2埋設管を推進させる後半推進工程でも、第2埋設管と地盤との間に滑材を供給することができる。具体的には、前記した前半推進工程での滑材供給と共通する技術が適用できる。但し、この段階では推進しない第1埋設管の列には滑材を供給する必要はない。
〔その他の工程〕
第1埋設管および第2埋設管の施工が完了した後は、通常の推進工法あるいは2重管推進工法と同様の後処理工程を行うことができる。
Specifically, a traveling wheel that travels on a rail laid on the bottom or bottom of the first buried pipe can be provided as the moving structure. As the fixing means, a fixing pin or a fixing bolt for fastening the structural member of the movable jack device and the rail can be detachably provided.
<Supply of lubricant>
In the latter half propulsion process of propelling the second buried pipe, the lubricant can be supplied between the second buried pipe and the ground. Specifically, a technique common to the lubricant supply in the first half propulsion process described above can be applied. However, it is not necessary to supply the lubricant to the first buried pipe row that is not propelled at this stage.
[Other processes]
After the construction of the first buried pipe and the second buried pipe is completed, a post-treatment process similar to a normal propulsion method or a double pipe propulsion method can be performed.

例えば、第2埋設管同士の連結個所に封止処理を行うことができる。第2埋設管の列内面に、コーティング層を塗工形成することができる。シートなどで内貼り施工を行うこともできる。第2埋設管の列後端と、第1埋設管の列先端との間に、固定的な封止構造を構築することができる。第1埋設管の内周面と、第2埋設管の内周面との段差を埋める内張り材を第1埋設管の内周面に施工することもできる。第2埋設管および第1埋設管が、出発立坑および到達立坑に開口する個所をモルタルで埋めたり開口枠を取り付けたりすることができる。第1、2埋設管の内部に照明を設置したり、電力配線や通信配線を敷設したりすることができる。   For example, the sealing process can be performed on the connection portion between the second embedded pipes. A coating layer can be formed by coating on the inner surface of the second buried pipe. It is also possible to carry out in-place installation with a sheet or the like. A fixed sealing structure can be constructed between the rear end of the second buried pipe and the front end of the first buried pipe. A lining material that fills a step between the inner peripheral surface of the first embedded pipe and the inner peripheral surface of the second embedded pipe can also be applied to the inner peripheral surface of the first embedded pipe. The second buried pipe and the first buried pipe can be filled with a mortar or attached with an opening frame at a portion opened to the starting shaft and the reaching shaft. Illumination can be installed inside the first and second buried pipes, and power wiring and communication wiring can be laid.

本発明にかかる2段階推進工法は、推進区間のうちの前半区間では、第1埋設管を掘進機および連結器の後端に連結して推進埋設する。通常の推進工法と同じ作業が行えることになる。埋設管列の後端へ新たな埋設管を連結する作業、元押しジャッキによる推進力の付加、滑材の供給作業なども、通常の推進工法と変わりなく、容易かつ能率的に作業ができる。
後半区間の推進工程を実施する際に、第2埋設管を、第1埋設管の列内部を通して連結器の後端に連結される位置まで配置する作業は、地盤からの抵抗を全く受けない第1埋設管列の内部での作業であるから、非常に簡単かつ能率的に行える。後半区間に第2埋設管を推進埋設する作業は、従来における2重管推進工法と同様に、地盤からの抵抗が大幅に低減された状態でスムーズかつ能率的に行える。特に、第1埋設管の列内部には余分の第2埋設管が存在しないので、その分だけ推進力や稼動エネルギーを低減できる。
In the two-stage propulsion method according to the present invention, in the first half section of the propulsion section, the first buried pipe is connected to the rear end of the excavator and the connector for propulsion embedding. The same work as a normal propulsion method can be performed. The work of connecting a new buried pipe to the rear end of the buried pipe row, the addition of a propulsive force by a push jack, the supply of a lubricant, and the like can be performed easily and efficiently, unlike the ordinary propulsion method.
When the propulsion process of the second half section is performed, the work of arranging the second buried pipe to the position where it is connected to the rear end of the coupler through the inside of the first buried pipe is not subjected to any resistance from the ground. Since it is an operation inside one buried pipe row, it can be done very easily and efficiently. The work of propelling and embedding the second buried pipe in the latter half section can be performed smoothly and efficiently in a state where the resistance from the ground is greatly reduced, as in the conventional double pipe propulsion method. In particular, since there is no extra second buried pipe in the first buried pipe row, the propulsive force and the operating energy can be reduced accordingly.

施工完了状態では、前半区間には第1埋設管だけが施工され、後半区間には第2埋設管だけが施工されているので、従来の2重管推進工法に比べて、前半区間の長さに相当する第2埋設管の資材が不要になり、資材コストが削減できる。
その結果、従来の2重管推進工法が備えていた利点を損なうことなく、2重管推進工法の欠点を解消し、経済的に作業能率および作業品質を格段に向上させることができる。
In the construction completion state, only the first buried pipe is constructed in the first half section, and only the second buried pipe is constructed in the second half section. Therefore, the length of the first half section is longer than the conventional double pipe propulsion method. The material for the second buried pipe corresponding to is no longer necessary, and the material cost can be reduced.
As a result, the disadvantages of the double pipe propulsion method can be eliminated without impairing the advantages of the conventional double pipe propulsion method, and the work efficiency and work quality can be significantly improved economically.

図1〜4に示す実施形態は、鉄道線路の下を潜って下水道などを施工する場合を模式的に示している。
〔推進工法の全容〕
図4に示すように、鉄道線路Rの両側で、地盤Eに出発立坑H1と到達立坑H2を掘削施工して、出発立坑H1から到達立坑H2に至る推進区間の地盤E内に埋設管10、20を施工する。
推進区間のうち、出発立坑H1に近い前半区間には、鋼管からなる第1埋設管10の列のみが施工される。到達立坑H2に近い後半区間には、ヒューム管からなる第2埋設管20の列のみが施工される。第2埋設管20の外径は、第1埋設管10の内径よりも小さい。第1埋設管10の先端と第2埋設管20の後端との間は、封止部材16などで封止されている。第1埋設管10から第2埋設管20へと連続した1本のトンネル空間が構成される。第1埋設管10および第2埋設管20の内部空間を、下水道などに利用する。
The embodiment shown in FIGS. 1 to 4 schematically shows a case where a sewer is constructed under a railroad track.
[Overview of the propulsion method]
As shown in FIG. 4, on both sides of the railway track R, the starting shaft H1 and the reaching shaft H2 are excavated on the ground E, and the buried pipe 10 is embedded in the ground E in the propulsion section from the starting shaft H1 to the reaching shaft H2. 20 is constructed.
Of the propulsion section, only the first buried pipe 10 row made of steel pipe is constructed in the first half section close to the starting shaft H1. In the second half section close to the reaching shaft H2, only the row of second buried pipes 20 made of fume pipes is constructed. The outer diameter of the second embedded pipe 20 is smaller than the inner diameter of the first embedded pipe 10. A space between the front end of the first embedded tube 10 and the rear end of the second embedded tube 20 is sealed with a sealing member 16 or the like. One continuous tunnel space from the first buried pipe 10 to the second buried pipe 20 is formed. The internal space of the first buried pipe 10 and the second buried pipe 20 is used for sewerage or the like.

図では、第2埋設管20のみを施工する後半区間の長さを省略して示しており、実際には、前半区間に比べて後半区間のほうが、かなり長くなる。
鉄道線路Rを横断する前半区間では、耐力に優れた第1埋設管10が施工されているので、鉄道線路Rの下方で地盤変動や崩落などの問題が起こるのを有効に防止できる。
〔前半区間の施工〕
図1に示すように、出発立坑H1の内側壁から地盤Eの内部に向かって、掘進機30と掘進機30の後端に連結された第1埋設管10の列を、推進埋設する。
基本的には、通常の1種類の埋設管を用いる推進工法と同じ装置や設備、作業方法が採用される。
In the figure, the length of the latter half section in which only the second buried pipe 20 is constructed is omitted, and actually the latter half section is considerably longer than the first half section.
In the first half section crossing the railroad track R, since the first buried pipe 10 having excellent proof stress is constructed, it is possible to effectively prevent problems such as ground fluctuation and collapse below the railroad track R.
[Construction of the first half section]
As shown in FIG. 1, the row of the first buried pipe 10 connected to the rear end of the excavator 30 and the excavator 30 is propelled and embedded from the inner wall of the starting shaft H1 toward the inside of the ground E.
Basically, the same equipment, equipment, and working method as the propulsion method using one ordinary type of buried pipe are employed.

<掘進機>
掘進機30は、基本的には、通常の推進工法用の掘進機と同様の構造を備えている。
全体が概略円筒状をなす掘進機30の外径は、第2埋設管20の外径に合わせて設定されている。第1埋設管10の外径よりも小さな外径である。掘進機30の先端に備えた回転掘削盤32は、通常の掘削ビットや掘削刃に加えて、可動掘削ビット34を備えている。可動掘削ビット34は、回転掘削盤32の外周縁に沿って複数個所に配置され、放射方向に進退する。図示を省略したが、可動掘削ビット34は、回転掘削盤32に内蔵された油圧アクチュエータによって進退する。図1は、可動掘削ビット34を掘進機30の外径よりも外側まで移動させた状態である。可動掘削ビット34の外径で決まる掘削径が、第1埋設管10の外径に対応している。
<Digging machine>
The excavator 30 basically has the same structure as an ordinary excavator for a propulsion method.
The outer diameter of the excavator 30 that is generally cylindrical as a whole is set according to the outer diameter of the second buried pipe 20. The outer diameter is smaller than the outer diameter of the first buried pipe 10. The rotary excavator 32 provided at the tip of the excavator 30 includes a movable excavation bit 34 in addition to a normal excavation bit and an excavation blade. The movable excavation bits 34 are arranged at a plurality of locations along the outer peripheral edge of the rotary excavator 32 and advance and retract in the radial direction. Although not shown, the movable excavation bit 34 is advanced and retracted by a hydraulic actuator built in the rotary excavator 32. FIG. 1 shows a state where the movable excavation bit 34 is moved to the outside of the outer diameter of the excavator 30. The excavation diameter determined by the outer diameter of the movable excavation bit 34 corresponds to the outer diameter of the first buried pipe 10.

図示を省略しているが、掘進機30には、回転掘削盤32を回転駆動するモータや減速機、回転掘削盤32で掘削された土砂を排出する排土機構、掘進機30の位置を計測する測量装置、掘進機30の掘進方向を変更する変向ジャッキなど、通常の掘進機30と同様の機構や装置が搭載されている。
掘進機30の後端に、鋼材などからなり取り外し可能な連結環材14を介して、掘進機30の外径よりも内径が大きな第1埋設管10を連結している。連結環材14に隣接して第1埋設管10の先端内周に摺動封止部材12が取り付けられている。
<滑材供給>
図1に示すように、地上から出発立坑H1の内部を経て第1埋設管10の列の内部へと、滑材供給管60が導入される。滑材供給管60は、前後の複数個所で分岐して、分岐したそれぞれの先端が、第1埋設管10の管壁に設置された滑材供給口62に接続される。第1埋設管10の内側には第2埋設管20が存在しないので、滑材供給管60から滑材供給口62への配管取付は容易に行える。
Although not shown, the excavator 30 measures the position of the excavator 30 by a motor and a speed reducer that rotate the rotary excavator 32, a soil removal mechanism that discharges the earth and sand excavated by the rotary excavator 32, and the excavator 30. The same mechanism and device as those of the ordinary excavator 30 are mounted, such as a surveying device to be used and a turning jack for changing the excavation direction of the excavator 30.
The first buried pipe 10 having an inner diameter larger than the outer diameter of the excavator 30 is connected to the rear end of the excavator 30 via a detachable connecting ring 14 made of steel or the like. A sliding sealing member 12 is attached to the inner periphery of the distal end of the first buried pipe 10 adjacent to the connecting ring member 14.
<Supplying lubricant>
As shown in FIG. 1, a lubricant supply pipe 60 is introduced from the ground to the inside of the first buried pipe 10 through the inside of the starting shaft H1. The lubricant supply pipe 60 is branched at a plurality of locations on the front and rear sides, and each branched tip is connected to a lubricant supply port 62 installed on the tube wall of the first buried pipe 10. Since the second embedded pipe 20 does not exist inside the first embedded pipe 10, the piping attachment from the lubricant supply pipe 60 to the lubricant supply port 62 can be easily performed.

滑材供給口62から地盤Eとの隙間に供給された滑材が、第1埋設管10が推進されるときに地盤Eから加わる摩擦抵抗を低減する。推進がスムーズに行われ、付加すべき推進力を小さくでき、推進時間を短くできる。
<推進作業>
図1に示すように、出発立坑H1に、元押しジャッキ50が設置される。元押しジャッキ50の作動軸52の先端が、当接板54を介して、第1埋設管10の列後端に当接する。
この状態で、掘進機30の回転掘削盤30を回転させて地盤Eを掘削しながら、元押しジャッキ50の作動軸52を前方に進出させて、掘進機30および第1埋設管10の列を前方に推進させる。
The lubricant supplied to the gap with the ground E from the lubricant supply port 62 reduces the frictional resistance applied from the ground E when the first buried pipe 10 is propelled. Propulsion is performed smoothly, the propulsive force to be added can be reduced, and the propulsion time can be shortened.
<Promotion work>
As shown in FIG. 1, a main jack 50 is installed on the starting shaft H1. The front end of the operating shaft 52 of the main push jack 50 abuts against the rear end of the first buried pipe 10 via the abutment plate 54.
In this state, while rotating the rotary excavator 30 of the excavator 30 and excavating the ground E, the operating shaft 52 of the main push jack 50 is advanced forward, and the row of the excavator 30 and the first buried pipe 10 is moved. Push forward.

第1埋設管10の1本分の推進作業が終了すれば、出発立坑H1内で、第1埋設管10の列の後端に新たな第1埋設管10を連結し、再び、前記した推進作業を行う。なお、図1では、図面スペースの関係で、出発立坑H1の奥行を実際よりも狭く表示している。実際には、元押しジャッキ50と第1埋設管10の列後端との間には、新たな第1埋設管10を挿入配置できるだけの余裕を設けておく。
以上に説明した第1埋設管10の推進作業は、通常の推進工法の場合と基本的に大きな違いはない。
第1埋設管10が、鉄道線路Rの下方領域の全体に推進埋設されれば、前方区間の施工は終了する。
When the propulsion work for one first buried pipe 10 is completed, a new first buried pipe 10 is connected to the rear end of the first buried pipe 10 in the starting shaft H1, and the above-described propulsion is performed again. Do work. In FIG. 1, the depth of the starting shaft H1 is displayed narrower than the actual depth because of the drawing space. Actually, a sufficient margin is provided between the main push jack 50 and the rear end of the first buried pipe 10 for inserting and arranging a new first buried pipe 10.
The propulsion work of the first buried pipe 10 described above is basically not significantly different from the normal propulsion method.
When the first buried pipe 10 is propelled and buried in the entire lower region of the railway track R, the construction of the front section is completed.

〔後半区間の施工〕
図2、3に示すようにして、第2埋設管20の推進埋設を実施する。
<準備作業>
第1埋設管10と掘進機30とを連結していた連結環材14を撤去して、掘進機30が自由に移動できるようにする。
第1埋設管10の列内部で、滑材供給管60のうち、分岐部分よりも先端側および滑材供給口62を撤去したり、塞いだりしておく。滑材供給管60は、第2埋設管20の推進が進行するにしたがって、前方に延ばされる。
[Second half section construction]
As shown in FIGS. 2 and 3, propulsion embedding of the second buried pipe 20 is performed.
<Preparation work>
The connecting ring member 14 that connects the first buried pipe 10 and the excavator 30 is removed so that the excavator 30 can move freely.
Within the row of the first embedded pipes 10, the tip side and the lubricant supply port 62 of the lubricant supply pipe 60 with respect to the branch portion are removed or closed. The lubricant supply pipe 60 is extended forward as the propulsion of the second embedded pipe 20 proceeds.

第1埋設管10の内部には第2埋設管20は存在しないので、これらの作業は余裕のあるスペースで、しかも、簡単に行える。
<第2埋設管の配置>
地上から出発立坑H1に、第2埋設管20を搬入し、第1埋設管10の内部に挿入する。第2埋設管20は、1本だけを挿入する。挿入された第2埋設管20を掘進機30の後端に連結する。
第2埋設管20の挿入作業は、地盤Eからは隔離された第1埋設管10の列内部で行うので、第2埋設管20の移動には大きな抵抗は働かない。元押しジャッキ50で大きな力を作用させなくても、人力で押したり、簡単なウィンチ装置で引き動かしたりするだけでも、挿入作業は可能になる。勿論、元押しジャッキ50を利用して、順次、第2埋設管20を前方側に押し込んでいくこともできる。この場合、元押しジャッキ50で加える押し込み力は、推進作業よりも格段に小さな力でよい。
Since the second embedded pipe 20 does not exist inside the first embedded pipe 10, these operations can be easily performed in a space with a margin.
<Arrangement of second buried pipe>
The second buried pipe 20 is carried from the ground to the starting shaft H 1 and inserted into the first buried pipe 10. Only one second embedded tube 20 is inserted. The inserted second buried pipe 20 is connected to the rear end of the excavator 30.
Since the insertion operation of the second embedded pipe 20 is performed inside the row of the first embedded pipes 10 isolated from the ground E, no great resistance acts on the movement of the second embedded pipe 20. Even if a large force is not applied by the main push jack 50, the insertion work can be performed only by pushing it manually or by pulling it with a simple winch device. Of course, it is also possible to sequentially push the second embedded pipe 20 forward using the main pushing jack 50. In this case, the pushing force applied by the main pushing jack 50 may be much smaller than the propulsion work.

<推力伝達材の配置>
第1埋設管10の内部で掘進機30の後端に連結された第2埋設管20の後端に、推力伝達材40を配置する。
推力伝達材40は、図3にも詳しく示すように、形鋼材を縦横あるいは斜め方向にも枠状に組み立て溶接接合することで、全体が、直方体の箱枠を構成している。推力伝達材40は、クレーンなどを用いて、地上から出発立坑H1の内部に搬入される。さらに、出発立坑H1から第1埋設管10の内部に搬入された推力伝達材40を、第2埋設管20の後端に配置する。図3に示すように、第1埋設管10の底近く左右に軸方向に沿って溶接された丸鋼棒材からなる案内部材42の上に、推力伝達材40を支持させて滑らせるように移動すれば、推力伝達材40の移動が容易に行える。この案内部材42は、第2埋設管20を支持して移動をスムーズにする機能も果たせる。
<Arrangement of thrust transmission material>
The thrust transmission member 40 is disposed at the rear end of the second buried pipe 20 connected to the rear end of the excavator 30 inside the first buried pipe 10.
As shown in detail in FIG. 3, the thrust transmission member 40 is assembled and welded in a frame shape in the vertical and horizontal directions or in an oblique direction to form a rectangular parallelepiped box frame. The thrust transmission material 40 is carried into the start shaft H1 from the ground using a crane or the like. Furthermore, the thrust transmission material 40 carried into the first buried pipe 10 from the starting shaft H <b> 1 is disposed at the rear end of the second buried pipe 20. As shown in FIG. 3, the thrust transmission member 40 is supported and slid on a guide member 42 made of a round steel bar welded along the axial direction to the left and right near the bottom of the first buried pipe 10. If it moves, the thrust transmission member 40 can be easily moved. This guide member 42 can also fulfill the function of supporting the second buried pipe 20 and smoothing the movement.

推力伝達材40は、第2埋設管20の後端から出発立坑H1に開口する第1埋設管10の後端までにわたって配置する。推力伝達材40の一部が、第1埋設管10の後端よりも後方に突き出されている。
<第2埋設管の推進>
基本的には、従来の2重管推進工法における内管すなわち第2埋設管20の推進作業と同じ作業手順が適用できる。
図2に示すように、掘進機30の可動掘削ビット34を中心側に退出させておく。掘削径は、掘進機30および第2埋設管20の外径に相当する。
The thrust transmission member 40 is disposed from the rear end of the second buried pipe 20 to the rear end of the first buried pipe 10 that opens to the starting shaft H1. A part of the thrust transmission member 40 protrudes rearward from the rear end of the first buried pipe 10.
<Promotion of the second buried pipe>
Basically, the same work procedure as the propulsion work of the inner pipe, that is, the second buried pipe 20 in the conventional double pipe propulsion method can be applied.
As shown in FIG. 2, the movable excavation bit 34 of the excavator 30 is withdrawn to the center side. The excavation diameter corresponds to the outer diameter of the excavator 30 and the second buried pipe 20.

元押しジャッキ50の作動軸52を、推力伝達材40の後端面に当接する。図3に示すように、左右一対の元押しジャッキ50で、推力伝達材40の左右2個所に当接させる。元押しジャッキ50の作動軸52を進出させれば、推力伝達材40を介して第2埋設管20および掘進機30に推進力が加えられる。掘進機30の回転掘削盤32を回転駆動すれば、掘進機30の推進に伴って、地盤Eが掘削される。
出発立坑H1に導入された滑材供給管60を、第2埋設管20の列内部空間に敷設する。第1埋設管10の列よりも前方で、第2埋設管20の周壁に設けられた滑材供給口62に、滑材供給管60を接続する。
The operating shaft 52 of the main push jack 50 is brought into contact with the rear end surface of the thrust transmission member 40. As shown in FIG. 3, a pair of right and left main pushing jacks 50 are brought into contact with the left and right portions of the thrust transmission member 40. When the operating shaft 52 of the main push jack 50 is advanced, a propulsive force is applied to the second buried pipe 20 and the excavator 30 via the thrust transmission member 40. If the rotary excavator 32 of the excavator 30 is driven to rotate, the ground E is excavated as the excavator 30 is propelled.
The lubricant supply pipe 60 introduced into the starting shaft H1 is laid in the row internal space of the second buried pipes 20. The lubricant supply pipe 60 is connected to the lubricant supply port 62 provided on the peripheral wall of the second embedded pipe 20 in front of the row of the first embedded pipes 10.

掘進機30の回転掘削盤32で地盤Eを掘削しながら、元押しジャッキ50で加えた推進力によって、掘進機30および第2埋設管20の列を推進させる。第2埋設管20の外周面と地盤Eとの間に滑材を供給して、地盤Eからの抵抗を低減させる。
1本の第2埋設管20が推進されたあと、出発立坑H1内で新たな第2埋設管20を、既に推進された第2埋設管20の列後尾に順次連結していく。このとき、推力伝達材40を一旦、取り除けた状態で、新たな第2埋設管20の挿入を行い、その後、推力段立つ材40を前記同様に配置し直す。
静止した第1埋設管10の中央を第2埋設管20が推進されるときには、第2埋設管20が第1埋設管10の内周面に設けられた摺動封止部材12に当接しながら摺動するので、常に良好な封止状態を維持したままで、第2埋設管20が推進される。
While excavating the ground E with the rotary excavator 32 of the excavator 30, the row of the excavator 30 and the second buried pipe 20 is propelled by the propulsive force applied by the main push jack 50. A lubricant is supplied between the outer peripheral surface of the second buried pipe 20 and the ground E to reduce the resistance from the ground E.
After one second buried pipe 20 is propelled, a new second buried pipe 20 is sequentially connected to the rear end of the row of the second buried pipe 20 that has already been promoted in the starting shaft H1. At this time, in a state where the thrust transmission material 40 is once removed, a new second embedded pipe 20 is inserted, and thereafter, the thrust standing material 40 is rearranged in the same manner as described above.
When the second embedded tube 20 is propelled through the center of the stationary first embedded tube 10, the second embedded tube 20 is in contact with the sliding sealing member 12 provided on the inner peripheral surface of the first embedded tube 10. Since it slides, the 2nd buried pipe 20 is propelled, always maintaining a good sealing state.

第2埋設管20の推進は、第1埋設管10の先端近くから前方に存在する第2埋設管20とその後方に配置された推力伝達材40とを推進させるので、第1埋設管10の内部全長に第2埋設管20が配置される従来の2重管推進工法に比べて、移動させる資材の全体重量あるいは慣性重量が少なくなる。元押しジャッキ50の作動が容易でスムーズに推進させることができる。
〔推進工法の終了〕
図4に示すように、第2埋設管20が、到達立坑H2まで配置されれば、推進作業は終了する。その後の作業は、通常の推進工法の場合と同様に行える。
The propulsion of the second embedded pipe 20 propels the second embedded pipe 20 existing forward from the vicinity of the tip of the first embedded pipe 10 and the thrust transmission member 40 disposed behind the second embedded pipe 10. Compared with the conventional double pipe propulsion method in which the second embedded pipe 20 is disposed in the entire internal length, the total weight or inertia weight of the material to be moved is reduced. The main push jack 50 can be operated easily and smoothly.
[End of propulsion method]
As shown in FIG. 4, when the second buried pipe 20 is arranged up to the reaching shaft H2, the propulsion work is completed. Subsequent operations can be performed in the same manner as in the normal propulsion method.

掘進機30は第2埋設管20の列先頭から取り外し、到達立坑H2から地上に撤去すればよい。出発立坑H1では、元押しジャッキ50などの推進作業用の設備類を撤去する。第1埋設管10の内部では、推力伝達材40を撤去する。第2埋設管20の列内部では、滑材供給管60の撤去や滑材供給口62を塞ぐ作業が行われる。第2埋設管20および第1埋設管10の内面にコーティング層を施工することができる。出発立坑H1および到達立坑H2の内側壁と、第1埋設管10および第2埋設管20の端部との間を、モルタルを打設して塞ぐ処理を行うこともできる。
このようにして施工が完了した地下の埋設管構造は、下水道などに利用することができる。鉄道線路Rの下方領域では、耐力に優れた鋼管からなる第1埋設管10が存在するので、鉄道線路Rの構造物から加わる圧力や列車通過によって変動する地盤の圧力などが作用しても、十分に耐えることができる。
The excavator 30 may be removed from the head of the second buried pipe 20 and removed from the reaching shaft H2 to the ground. In the starting shaft H1, the equipment for propulsion work such as the main jack 50 is removed. Inside the first buried pipe 10, the thrust transmission material 40 is removed. Inside the row of the second buried pipes 20, an operation of removing the lubricant supply pipe 60 and closing the lubricant supply port 62 is performed. A coating layer can be applied to the inner surfaces of the second embedded pipe 20 and the first embedded pipe 10. It is also possible to perform a process of placing mortar between the inner walls of the starting shaft H1 and the reaching shaft H2 and the ends of the first buried pipe 10 and the second buried pipe 20 to close them.
The underground underground pipe structure completed in this way can be used for sewerage and the like. In the lower region of the railroad track R, there is a first buried pipe 10 made of a steel pipe with excellent proof stress, so even if pressure applied from the structure of the railroad track R or ground pressure that fluctuates due to train passage acts, Can withstand enough.

〔移動ジャッキ装置の利用〕
図5〜7に示す実施形態は、前記推力伝達材40を用いる実施形態とは、第2埋設管20の施工工程が異なる。前半工程を含む基本的な技術内容は前記実施形態と共通するので、相違点を主にして説明する。
図5に示すように、出発立坑H1から前半区間に第1埋設管10を施工する作業は、前記実施形態と共通している。
その後、第1埋設管10と掘進機30との連結を解除したり、掘進機30の後端に第2埋設管20を連結したり、第1埋設管10に敷設された滑材供給管60および滑材供給口62を、第2埋設管20のほうに順次敷設し直したりする作業は、前記実施形態と同様に行える。
[Use of moving jack device]
The embodiment shown in FIGS. 5 to 7 is different from the embodiment using the thrust transmission material 40 in the construction process of the second embedded pipe 20. Since the basic technical contents including the first half process are the same as those in the above embodiment, the differences will be mainly described.
As shown in FIG. 5, the work of constructing the first buried pipe 10 from the starting shaft H1 to the first half section is common to the above embodiment.
Thereafter, the connection between the first buried pipe 10 and the excavator 30 is released, the second buried pipe 20 is connected to the rear end of the excavator 30, or the lubricant supply pipe 60 laid on the first buried pipe 10. The operation of sequentially re-laying the lubricant supply port 62 on the second buried pipe 20 can be performed in the same manner as in the above embodiment.

この実施形態では、第2埋設管20の後端に、推力伝達材40を配置する代わりに、移動ジャッキ装置80を設置する。
移動ジャッキ装置80は、図6、7に詳しく示すように、鋼材で構築された本体構造82に、複数本の推力発生ジャッキ90が装着されている。推力発生ジャッキ90の作動軸92の先端が、第2埋設管20の後端面に当接している。図7に示すように、第2埋設管20の後端面で四方の均等な位置に推力発生ジャッキ90が配置されている。本体構造82の中央には軸方向に貫通する空間があいており、この空間をとおして、滑材供給管60や掘進機30への各種配管ケーブルを通過させることができる。
In this embodiment, instead of disposing the thrust transmission member 40 at the rear end of the second embedded pipe 20, a moving jack device 80 is installed.
As shown in detail in FIGS. 6 and 7, the moving jack device 80 has a plurality of thrust generating jacks 90 mounted on a main body structure 82 constructed of steel. The tip of the operating shaft 92 of the thrust generating jack 90 is in contact with the rear end surface of the second embedded pipe 20. As shown in FIG. 7, thrust generating jacks 90 are arranged at equal positions in all directions on the rear end surface of the second embedded pipe 20. There is a space penetrating in the axial direction in the center of the main body structure 82, and various piping cables to the lubricant supply pipe 60 and the excavator 30 can be passed through this space.

図7に詳しく示すように、第1埋設管10の内底近くに、左右一対で対称的に、L形鋼材からなる案内レール70が溶接されている。図6に示すように、案内レール70は、第1埋設管10の略全長にわたって設置されている。
本体構造82の下端には、走行ローラ84が装着されている。走行ローラ84が、案内レール70の上面に載せられる。移動ジャッキ装置80の全体が、走行ローラ84を介して案内レール70に支持される。移動ジャッキ装置80を軸方向に移動させれば、走行ローラ84が案内レール70上をスムーズに回転移動する。比較的に小さな力でも移動ジャッキ装置80を容易に移動させることができる。
As shown in detail in FIG. 7, a guide rail 70 made of L-shaped steel is symmetrically welded near the inner bottom of the first buried pipe 10 in a pair of left and right. As shown in FIG. 6, the guide rail 70 is installed over substantially the entire length of the first buried pipe 10.
A traveling roller 84 is attached to the lower end of the main body structure 82. A travel roller 84 is placed on the upper surface of the guide rail 70. The entire moving jack device 80 is supported by the guide rail 70 via the traveling roller 84. When the moving jack device 80 is moved in the axial direction, the traveling roller 84 smoothly rotates on the guide rail 70. The moving jack device 80 can be easily moved with a relatively small force.

本体構造82の下端で、案内レール70の内側面と対面する個所に、抜き差し自在な固定ピン86が取り付けられる。案内レール70の内側面には一定間隔毎にピン挿入孔72が貫通している。移動ジャッキ装置80を所望の位置に移動させたあと、固定ピン86を本体構造82から案内レール70のピン挿入孔72に嵌入すれば、案内レール70に対して移動ジャッキ装置80が固定される。
図6に示すように、第2埋設管20の後端近くに移動ジャッキ装置80を移動させたあと、固定ピン86で案内レール70に固定する。その後、移動ジャッキ装置80の推力発生ジャッキ90を作動させ、作動軸92で第2埋設管20に推進力を加える。
At the lower end of the main body structure 82, a fixing pin 86 that can be inserted and removed is attached at a position facing the inner surface of the guide rail 70. Pin insertion holes 72 pass through the inner surface of the guide rail 70 at regular intervals. After the movable jack device 80 is moved to a desired position, the movable jack device 80 is fixed to the guide rail 70 by inserting the fixing pin 86 into the pin insertion hole 72 of the guide rail 70 from the main body structure 82.
As shown in FIG. 6, after the moving jack device 80 is moved near the rear end of the second embedded pipe 20, it is fixed to the guide rail 70 with a fixing pin 86. Thereafter, the thrust generating jack 90 of the moving jack device 80 is operated, and a driving force is applied to the second embedded pipe 20 by the operating shaft 92.

図5に示すように、掘進機30で地盤Eを掘削しながら、移動ジャッキ装置90で推進力を加えられた第2埋設管20および掘進機30が地盤E内を推進する。地盤Eからの反力は、移動ジャッキ装置90の固定ピン86を介して、案内レール70および第1埋設管10で受け止める。
第2埋設管20の1本分の推進が終了すれば、一旦、移動ジャッキ装置90を第1埋設管10の後端から出発立坑H1に引き戻したあと、新たな第2埋設管20を、第1埋設管10の内部を通して既に推進された第2埋設管20の後端に連結する。その後、移動ジャッキ装置80を、前記同様にして、第2埋設管20の後端に配置し、前記同様の推進作業を行う。
As shown in FIG. 5, while excavating the ground E with the excavating machine 30, the second buried pipe 20 and the excavating machine 30 to which propulsive force is applied by the moving jack device 90 propel the inside of the ground E. The reaction force from the ground E is received by the guide rail 70 and the first buried pipe 10 via the fixed pin 86 of the moving jack device 90.
Once the propulsion of the second buried pipe 20 is completed, the moving jack device 90 is once pulled back from the rear end of the first buried pipe 10 to the starting shaft H1, and then the new second buried pipe 20 is moved to the second It connects with the rear end of the 2nd buried pipe 20 already propelled through the inside of 1 buried pipe 10. Thereafter, the moving jack device 80 is disposed at the rear end of the second embedded pipe 20 in the same manner as described above, and the same propulsion work as described above is performed.

以上に説明した実施形態では、出発立坑H1に設置された元押しジャッキ50で、第1埋設管10の内部に配置された推力伝達材40を介して第2埋設管20までの長い距離にわたって推進力を伝達させる必要がない。常に、第2埋設管20の後端に配置される移動ジャッキ装置90で推進力を加えるので、効率的に強力な推進力を伝達することができる。
〔別の施工方法〕
前記実施形態では、前半区間の施工は、掘進機30に第1埋設管10だけを連結していたが、掘進機30に、第1埋設管10と第2埋設管20の両方を連結しておくこともできる。この場合、通常の2重管推進工法における前半区間の施工と同じ施工技術が適用される。掘進機30の後端に連結される第1埋設管10のうち、1本だけあるいは一部だけに第2埋設管20を配置しておいてもよいし、全ての第1埋設管10に第2埋設管20を配置しておいてもよい。
In the embodiment described above, the propulsion jack 50 installed in the starting shaft H1 is propelled over a long distance to the second buried pipe 20 via the thrust transmission member 40 arranged inside the first buried pipe 10. There is no need to transmit power. Since the propulsive force is always applied by the moving jack device 90 disposed at the rear end of the second embedded pipe 20, a strong propulsive force can be transmitted efficiently.
[Another construction method]
In the above embodiment, the first half section is constructed by connecting only the first buried pipe 10 to the excavator 30. However, the first buried pipe 10 and the second buried pipe 20 are both connected to the excavator 30. It can also be left. In this case, the same construction technique as the construction of the first half section in the normal double pipe propulsion method is applied. Of the first buried pipes 10 connected to the rear end of the excavating machine 30, the second buried pipes 20 may be arranged in only one or a part of the first buried pipes 10, or all the first buried pipes 10 Two buried pipes 20 may be arranged.

後半区間の施工は、開始時点で、第1埋設管10の内部に第2埋設管20が配置された状態である。その後に、掘進機30と第2埋設管20とを推進させる作業は、前記実施形態と共通している。後半区間の施工が、最初の段階から、掘進機30の後方で第1埋設管10の後尾近くまで第2埋設管20が配置されていれば、第2埋設管20に推進力を加える作業が行い易い。最初の段階では、元押しジャッキ50で直接に第2埋設管20の後端に推進力を加えることもできる。推力伝達材40を挿入配置する場合も、推力伝達材40の使用数を少なくすることができ、手間が省ける。   The construction of the second half section is a state in which the second embedded pipe 20 is arranged inside the first embedded pipe 10 at the start time. Thereafter, the work of propelling the excavator 30 and the second buried pipe 20 is common to the above embodiment. If the second buried pipe 20 is arranged from the first stage to the rear of the first buried pipe 10 near the rear of the first buried pipe 10 in the construction of the second half section, the work of applying a propulsive force to the second buried pipe 20 is performed. Easy to do. In the first stage, it is possible to apply a propulsive force directly to the rear end of the second embedded pipe 20 with the main push jack 50. Even when the thrust transmission member 40 is inserted and arranged, the number of the thrust transmission members 40 used can be reduced and labor can be saved.

本発明の2段階推進工法は、例えば、鉄道線路の下を潜る下水道の施工などに有効に適用できる。鉄道線路に悪影響を与えることなく、鉄道線路から悪影響を受けることもなく、簡単かつ能率的で、しかも経済的に埋設管の施工を行うことができる。   The two-stage propulsion method according to the present invention can be effectively applied to, for example, construction of a sewer under the railroad track. Without adversely affecting the railway track, without being adversely affected by the railway track, the construction of the buried pipe can be carried out simply and efficiently and economically.

本発明の実施形態となる前半区間の施工状態を示す断面図Sectional drawing which shows the construction state of the first half section used as embodiment of this invention 後半区間の施工状態を示す断面図Sectional view showing the construction status of the second half section 前図と直交する断面において推力伝達材の配置構造を示す側面図Side view showing arrangement structure of thrust transmission material in cross section orthogonal to previous figure 推進工法の終了状態を示す断面図Sectional view showing the end state of the propulsion method 別の実施形態における後半区間の施工状態を示す断面図Sectional drawing which shows the construction state of the latter half area in another embodiment 前図における要部の詳細断面図Detailed sectional view of the main part in the previous figure 前図と直交する断面における一部切欠側面図Partially cutaway side view in a cross section orthogonal to the previous figure

符号の説明Explanation of symbols

10 第1埋設管
12 摺動封止部材
14 連結環材
16 連結部封止部材
20 第2埋設管
30 掘進機
32 回転掘削盤
34 可動掘削ビット
40 推力伝達材
50 元押しジャッキ
52 作動軸
60 滑材供給管
62 滑材供給口
E 地盤
R 鉄道線路
DESCRIPTION OF SYMBOLS 10 1st buried pipe 12 Sliding sealing member 14 Connection ring material 16 Connection part sealing member 20 2nd buried pipe 30 Excavator 32 Rotating excavator 34 Movable excavation bit 40 Thrust transmission material 50 Main pushing jack 52 Actuating shaft 60 Sliding Material supply pipe 62 Lubricant supply port E Ground R Railway track

Claims (3)

地盤内において出発立坑から到達立坑に至る推進区間のうち、出発立坑側の前半区間には第1の埋設管、到達立坑側の後半区間には第2の埋設管をそれぞれ施工する2段階推進工法であって、
前記地盤を掘削する掘進機に前記第1埋設管を連結し、前記出発立坑から地盤内に推進させて、前記前半区間に第1埋設管を推進埋設する前半推進工程(a)と、
前記前半推進工程(a)の後、前記掘進機と前記第1埋設管との連結を解除し、前記出発立坑から地盤内に配置された第1埋設管の内部を通して前記掘進機に連結された前記第2埋設管を、掘進機とともに第1埋設管の列先端から地盤内に推進させ、第1埋設管の列先端から到達立坑に至る後半区間に第2埋設管を推進埋設する後半推進工程(b)と
を含み、
前記後半推進工程(b)が、前記第1埋設管の内部で、前記掘進機に連結された第2埋設管の後端から第1埋設管の後端までにわたって、前記第2埋設管の長さよりも十分に短い長さの鋼枠ブロックからなる推力伝達材を、軸方向に多数並べて配置する工程と、前記出発立坑に設置された元押しジャッキで前記推力伝達材を介して第2埋設管および掘進機に推進力を加える工程とを含む、
ことを特徴とする、2段階推進工法。
Two-stage propulsion method in which the first buried pipe is constructed in the first half section on the starting shaft side and the second buried pipe is constructed in the latter half section on the reaching shaft side among the propulsion sections from the starting shaft to the reaching shaft in the ground. Because
A first half propulsion step (a) in which the first buried pipe is connected to an excavating machine for excavating the ground, propelled into the ground from the starting vertical shaft, and the first buried pipe is propelled and buried in the first half section;
After the first half propulsion step (a), the connection between the excavator and the first buried pipe is released, and the excavator is connected to the excavator through the first buried pipe disposed in the ground from the starting shaft. The latter half propulsion step of propelling and burying the second buried pipe in the latter half section from the row leading end of the first buried pipe to the reaching shaft by propelling the second buried pipe together with the excavator from the row leading end of the first buried pipe and (b),
Only including,
In the latter half propulsion step (b), the length of the second buried pipe extends from the rear end of the second buried pipe connected to the excavator to the rear end of the first buried pipe inside the first buried pipe. A step of arranging a large number of thrust transmission members made of steel frame blocks having a length sufficiently shorter than the length of the steel frame block in the axial direction, and a second buried pipe through the thrust transmission member with a push jack installed in the starting shaft And applying a driving force to the excavator,
This is a two-stage propulsion method.
前記前半推進工程(a)が、前記第1埋設管の内部に導入された滑材供給管から、第1埋設管と地盤との間に滑材を供給する工程を含み、
前記後半推進工程(b)が、前記第1埋設管の施工個所よりも前方側で、前記第2埋設管の内部に導入された滑材供給管から、第2埋設管と地盤との間に滑材を供給する工程をも含む
請求項1に記載の2段階推進工法。
First half propulsion step (a) includes the lubricant supply pipe, which is introduced into the interior of the first buried pipe, as engineering supplies lubricant between the first buried pipes and the ground,
The second half propulsion step (b) is a front side of the construction site of the first buried pipe, and from the lubricant supply pipe introduced into the second buried pipe, between the second buried pipe and the ground. lubricant also includes a more engineering and supplies,
The two-stage propulsion method according to claim 1 .
前記掘進機として、前記第1埋設管に対応する掘削径と第1埋設管の内径よりも外径が小さな前記第2埋設管に対応する掘削径とに掘削径が可変である掘進機を用い、
前記前半推進工程(a)では、前記掘進機の掘削径を前記第1埋設管に対応する掘削径に設定して掘進機を推進させ、
前記後半推進工程(b)では、前記掘進機の掘削径を前記第1埋設管に対応する掘削径から前記第埋設管に対応する掘削径に変更したあと、掘進機を推進させる
請求項1または2に記載の2段階推進工法。
As the excavator, an excavator whose excavating diameter is variable between an excavating diameter corresponding to the first buried pipe and an excavating diameter corresponding to the second buried pipe having an outer diameter smaller than the inner diameter of the first buried pipe is used. ,
In the first half propulsion step (a) , the excavator is propelled by setting the excavation diameter of the excavator to the excavation diameter corresponding to the first buried pipe,
In the latter half propulsion step (b) , after changing the excavation diameter of the excavator from the excavation diameter corresponding to the first buried pipe to the excavation diameter corresponding to the second buried pipe, the excavator is propelled .
The two-stage propulsion method according to claim 1 or 2 .
JP2004141448A 2004-05-11 2004-05-11 Two-stage propulsion method Expired - Lifetime JP4139350B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004141448A JP4139350B2 (en) 2004-05-11 2004-05-11 Two-stage propulsion method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004141448A JP4139350B2 (en) 2004-05-11 2004-05-11 Two-stage propulsion method

Publications (2)

Publication Number Publication Date
JP2005320822A JP2005320822A (en) 2005-11-17
JP4139350B2 true JP4139350B2 (en) 2008-08-27

Family

ID=35468287

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004141448A Expired - Lifetime JP4139350B2 (en) 2004-05-11 2004-05-11 Two-stage propulsion method

Country Status (1)

Country Link
JP (1) JP4139350B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101156613B1 (en) * 2009-08-27 2012-06-15 비엔지건설(주) The Construction Method of Shield Tunneling for long distacne
JP2011226204A (en) * 2010-04-22 2011-11-10 Daiho Constr Co Ltd Air pressure maintaining device for tunnel
CN116398697B (en) * 2023-03-24 2025-04-08 中国五冶集团有限公司 A jacking structure and jacking method for mechanical jacking pipe in hard formation
CN117868846B (en) * 2024-01-31 2025-09-26 中交第一航务工程局有限公司 A silt pipe jacking method based on axial constraint
KR102700887B1 (en) * 2024-02-08 2024-08-30 손문준 Method of installing steel pipes underground in a multi-stage manner
CN118774845A (en) * 2024-07-04 2024-10-15 中铁工程装备集团有限公司 A pipe jacking construction method, pipe jacking and pipe jacking excavation system

Also Published As

Publication number Publication date
JP2005320822A (en) 2005-11-17

Similar Documents

Publication Publication Date Title
JP3863888B2 (en) Two-stage propulsion method and coupler
JP4139350B2 (en) Two-stage propulsion method
JP5162316B2 (en) Tunnel excavation method
KR101018889B1 (en) Horizontal drilling device and construction method of non-adhesive underpastel using the same
JP4398485B2 (en) Tunnel excavator and tunnel excavation method
JP4625815B2 (en) Non-open-cutting construction method for underground structures
JP2021080798A (en) Pipeline construction method using propulsion method
JP2005180112A (en) Ground improvement structure and ground improvement method
JP2017145641A (en) Reinforcement method of existing tunnel and tunnel reinforcement device
JP2004060266A (en) Non-open-cut construction method for underground structure
JP4214082B2 (en) Propulsion method excavation equipment and propulsion method
JP4334954B2 (en) Method and apparatus for widening underground space
KR20100135525A (en) Unopened Tunnel Excavation Method by Progressive Propulsion Excavation and Its Structure
JP3867924B2 (en) Diverging type propulsion machine
JPH11173072A (en) Chemical grouting method and chemical grouting equipment
KR102686751B1 (en) Tbm .
KR102700887B1 (en) Method of installing steel pipes underground in a multi-stage manner
JP3616898B2 (en) Method for joining underground structures using propulsion device
JP2009249992A (en) Pipe jacking method for burying pipe
JP2746866B2 (en) Drilling device for propulsion method and propulsion method
KR102712580B1 (en) Construction method of underground structure
JP2863492B2 (en) Propulsion method, excavation device and propulsion device
JP4564895B2 (en) Tunnel widening method
JPH1163299A (en) Execution method of multi-conduit pipe and multi-conduit pipe
JP4842650B2 (en) Tunnel excavator

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070309

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080115

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080307

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080520

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080606

R150 Certificate of patent or registration of utility model

Ref document number: 4139350

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110613

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110613

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120613

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120613

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130613

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130613

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140613

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term