JP4145669B2 - Inspection frame for legal frame formation - Google Patents
Inspection frame for legal frame formation Download PDFInfo
- Publication number
- JP4145669B2 JP4145669B2 JP2003005356A JP2003005356A JP4145669B2 JP 4145669 B2 JP4145669 B2 JP 4145669B2 JP 2003005356 A JP2003005356 A JP 2003005356A JP 2003005356 A JP2003005356 A JP 2003005356A JP 4145669 B2 JP4145669 B2 JP 4145669B2
- Authority
- JP
- Japan
- Prior art keywords
- frame
- reinforcing bar
- inspection
- slope
- forming
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000007689 inspection Methods 0.000 title claims description 16
- 230000015572 biosynthetic process Effects 0.000 title 1
- 230000003014 reinforcing effect Effects 0.000 claims description 40
- 238000005259 measurement Methods 0.000 claims description 9
- 239000004570 mortar (masonry) Substances 0.000 claims description 5
- 238000005507 spraying Methods 0.000 claims description 5
- 230000002787 reinforcement Effects 0.000 claims description 3
- 238000000034 method Methods 0.000 description 6
- 239000000463 material Substances 0.000 description 5
- 239000002184 metal Substances 0.000 description 4
- 238000005452 bending Methods 0.000 description 3
- 238000003466 welding Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【0001】
【発明の属する技術分野】
この発明は、オープンカット工法などにより造成した高速道路などの法面や各種施設などに面する傾斜した法面枠或いは崩壊のおそれのある急傾斜地などの斜面安定工(緑化のためなどにも)の現場打ち工法の法枠梁を形成する際の外観寸法を規制する法枠形成用の検測枠に関する。
【0002】
【従来の技術及びその課題】
法面に格子状に鉄筋を配筋し、この鉄筋にモルタルまたはコンクリートを吹き付けて法面に格子状の法枠梁を形成するための外観寸法を規制する法枠形成用の検測枠の従来技術としては、特開平8−74261号公報に示すように、並列する第1部材同志を第2部材を介し連結し、左右の第2部材に鉄筋保持部材を架設(横架)して構成されている。
【0003】
法面に配筋した鉄筋は、持ち上げて上方の鉄筋保持部材に当接させながら、鉄筋を鉄筋保持部材と針金を介し結束するようになっている。
【0004】
このような方式によると、鉄筋保持部材に対し針金を介し鉄筋を結束するので、鉄筋の保持作業に著しく手数がかかって大幅なコストアップになると共に、急傾斜地の結束作業に危険がともなうなどの問題もあった。
【0005】
そこで、この発明は、検測枠に対する鉄筋の支持作業が極めて簡単にできて大幅な作業能率の向上をはかるようにすることにある。
【0006】
【課題を解決するための手段】
上記の課題を解決するために、この発明は、法面に格子状に鉄筋を配筋し、この鉄筋にモルタルまたはコンクリートを吹き付けて法面に格子状の法枠梁を形成するための外観寸法を規制する法枠形成用の検測枠であって、上記法枠形成用の検測枠を、法枠梁の外観形状に沿って両端が下方に向く外観部材と、この外観部材の頂部に上端を取付けて垂設すると共に、途中に上記鉄筋を落し込みにより保持する上下二段の開口が斜め上向きのU字状保持凹入部を有する鉄筋保持部材とで構成した検測枠を採用する。
【0007】
また、前記鉄筋保持部材が、外観部材の頂部から二本垂設した構成を採用することもある。
【0008】
【発明の実施の形態】
この発明の実施の形態を添付図面に基づいて説明する。
【0009】
この発明の第1の実施形態では、図1から図4に示すように、法面Aに形成しようとする法枠梁Bの外観形状に沿って両端(接地端)が下方に向く外観部材1と、この外観部材1の頂部に上端を例えばスポット溶接などにより固定して取付けて下方に垂設すると共に、途中に鉄筋Cを落し込みにより保持する保持凹入部2を有する鉄筋保持部材3とで法枠形成用の検測枠Dを形成する。
【0010】
上記の外観部材1は、図示の場合略半弧状の法枠梁Bの外周面に沿う略半弧状に屈曲したが、法枠梁Bの形状、例えば台形の場合台形に沿う形状に屈曲すればよい。
【0011】
そして、外観部材1は、図示の場合金属製の線材を屈曲して用いたが、例えば金属製の帯板などを屈曲して使用することもある。
【0012】
また、上記の保持凹入部2は、図示のように、鉄筋保持部材3の途中をU字状に屈曲すると共に、U字状の屈曲による開口が斜め上方に、底が斜め下方に位置して、落し込んだ鉄筋Cの振動その他の原因によって脱出を防止するようになっている。
【0013】
そして、鉄筋保持部材3も図示の場合外観部材1と同様に金属製の線材を屈曲して用いたが、金属製の帯板を屈曲したり、或いは保持凹入部2をプレスによって打ち抜いた金属製などの板材であってもよい。
【0014】
なお、凹入部2は、図1、2に示すように、1本の鉄筋保持部材3の上下に配置したが、限定されず、図5に示すように左右に並設した2本の鉄筋保持部材3のそれぞれの途中で、2本の鉄筋Cが上下に配筋されるように設ける以外に、図6に示すように、並設した2本の鉄筋保持部材3のそれぞれの途中上下に2個所設けて、計4本の鉄筋Cを配筋するようにしてもよい。
【0015】
次に上記検測枠Dの使用方法を説明する。
【0016】
まず、法面の法枠梁の構築線上に鉄筋Cを置いたのち、検測枠Dの外観部材1が鉄筋Cを跨ぐようにしながら、外観部材1の両端を接地する。
【0017】
しかして、持ち上げた鉄筋Cを図2に示すように鉄筋保持部材3の凹入部2に落し込む。
【0018】
以上の作業の繰り返しによって鉄筋Cの所定間隔位置に検測枠Dを配置しながら、各凹入部2に鉄筋Cを落し込んで、法面Aに対し鉄筋Cを浮上させる。
【0019】
なお、法面Aに前もって金網(図示省略)を敷くこともある。
【0020】
その後にモルタルまたはコンクリートの吹付材5をポンプアップによりホースの先端ノズルから鉄筋Cに向けて吹き付けながら、図4に示すように格子状の法枠梁Bを構築する。
【0021】
その際、吹き付けるモルタルまたはコンクリートの吹付材5の幅及び高さの目安が検測枠Dによって察知できる。
【0022】
当然、検測枠Dは、法枠梁B内に埋設させておく。
【0023】
なお、図7から図9に示すように、第1の実施形態の検測枠Dを構成する外観部材1が少なくとも二本並設してある。
【0024】
並列する少なくとも二本の並列外観部材1、1は、凹入部2を有する並列鉄筋保持部材3、3の上端を連結する連結部材11にスポット溶接により固定してある。
【0025】
なお、図7に示す場合、並列外観部材1、1に補助脚部材12を設けたが、図9に示すように必ずしも必要としない。
【0026】
当然、鉄筋保持部材3は、外観部材1の両端部に並設(図6に示すような)することも可能で、凹入部2の1個所に限定されない。
【0027】
外観部材1の並列検測枠Dの使用方法は、第1の実施形態と同様につき説明を省略する。
【0028】
すると、並列外観部材1によって法面に対し検測枠Dを安定よく起立させることができる。
【0029】
なお、図2、5、6、7及び図9に示すように、鉄筋保持部材3の下端を外観部材1の両端を結ぶ線上に合致させておくと、法面Aに鉄筋保持部材3の下端が接地して、保持鉄筋Cの重量による外観部材1の変形をなくすることができる。
【0030】
【発明の効果】
以上のように、この発明の検測枠によれば、凹入部に鉄筋を落し込んで鉄筋保持部材に鉄筋を保持させるようにしてあるので、鉄筋保持部材に鉄筋を針金を介し取付ける(保持させる)作業が不要になる。
【0031】
このため、検測枠に対する鉄筋の保持作業が極めて能率よく行なうことができる。
【図面の簡単な説明】
【図1】この発明の第1の実施形態の検測枠を示す斜視図
【図2】同上の正面図
【図3】検測枠の使用例の平面図
【図4】法枠梁の縦断正面図
【図5】鉄筋保持部材の他の例を示す正面図
【図6】同正面図
【図7】 検測枠を示す斜視図
【図8】同上の使用を示す平面図
【図9】鉄筋保持部材の他の例を示す斜視図
【符号の説明】
A 法面
B 法枠梁
C 鉄筋
D 検測枠
1 外観部材
2 凹入部
3 鉄筋保持部材
5 吹付材
11 連結部材[0001]
BACKGROUND OF THE INVENTION
This invention is a slope stabilization work (such as for greening) on slopes such as highways and slopes facing various facilities created by an open cut method or steep slopes that may collapse. The present invention relates to a measurement frame for forming a frame that regulates the external dimensions when forming a frame frame for the on-site method.
[0002]
[Prior art and problems]
Conventional measurement frame for forming a frame that regulates the external dimensions to form a grid-like frame beam on the slope by laying reinforcing bars in a grid on the slope and spraying mortar or concrete on the reinforcement As a technique, as shown in Japanese Patent Application Laid-Open No. 8-74261, the first members arranged in parallel are connected via the second member, and the reinforcing bar holding members are installed (horizontally mounted) on the left and right second members. ing.
[0003]
The reinforcing bar arranged on the slope is bound to the reinforcing bar holding member and the wire while being lifted and brought into contact with the upper reinforcing bar holding member.
[0004]
According to such a method, since the reinforcing bars are bound to the reinforcing bar holding member via the wire, the holding work of the reinforcing bars is remarkably troublesome and the cost is greatly increased, and the binding work of steep slopes is dangerous. There was also a problem.
[0005]
SUMMARY OF THE INVENTION Accordingly, the present invention is to enable a rebar support operation with respect to a measurement frame to be extremely simple and to greatly improve work efficiency.
[0006]
[Means for Solving the Problems]
In order to solve the above-described problems, the present invention provides an external dimension for arranging a reinforcing bar in a grid shape on a slope and spraying mortar or concrete on the reinforcing bar to form a grid-like frame frame on the slope. An inspection frame for forming a legal frame that regulates the above-mentioned measurement frame for the above-mentioned legal frame, and an outer appearance member whose both ends are directed downward along the outer shape of the normal frame beam, and a top of the outer appearance member. An inspection frame is used which is vertically installed with an upper end, and a reinforcing bar holding member having a U-shaped holding recessed portion in which two upper and lower openings that hold the reinforcing bar by dropping in the middle are inclined upward .
[0007]
The front Symbol rebar holding member, also possible to adopt a configuration in which two vertically from the top of the exterior member.
[0008]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described with reference to the accompanying drawings.
[0009]
In the first embodiment of the present invention, as shown in FIGS. 1 to 4, the
[0010]
In the illustrated case, the
[0011]
In the illustrated example, the
[0012]
In addition, as shown in the drawing, the holding
[0013]
Further, in the illustrated case, the reinforcing
[0014]
In addition, although the
[0015]
Next, a method for using the inspection frame D will be described.
[0016]
First, the reinforcing bar C is placed on the construction line of the normal frame beam on the slope, and then both ends of the
[0017]
Then, the lifted reinforcing bar C is dropped into the
[0018]
By repeating the above operation, the reinforcing bars C are dropped into the respective recessed
[0019]
In addition, a wire mesh (not shown) may be laid on the slope A in advance.
[0020]
Thereafter, a mortar or concrete spray material 5 is blown from the tip nozzle of the hose toward the reinforcing bar C by pumping up, thereby constructing a grid-like frame frame B as shown in FIG.
[0021]
In that case, the standard of the width and height of the sprayed material 5 of the mortar or concrete sprayed can be detected by the measurement frame D.
[0022]
Naturally, the inspection frame D is embedded in the normal frame beam B.
[0023]
As shown in FIGS. 7 to 9, at least two
[0024]
At least two
[0025]
In the case shown in FIG. 7, the
[0026]
Naturally, the reinforcing
[0027]
The method of using the parallel inspection frame D of the
[0028]
Then, the inspection frame D can be stably erected with respect to the slope by the
[0029]
2, 5, 6, 7, and 9, when the lower end of the reinforcing
[0030]
【The invention's effect】
As described above, according to the inspection frame of the present invention, the reinforcing bar is dropped into the recessed portion and the reinforcing bar holding member is held by the reinforcing bar holding member, so that the reinforcing bar is attached to the reinforcing bar holding member via the wire. ) No need for work.
[0031]
For this reason, the rebar holding work with respect to the measurement frame can be performed very efficiently.
[Brief description of the drawings]
FIG. 1 is a perspective view showing a measurement frame according to a first embodiment of the present invention. FIG. 2 is a front view of the same. FIG. 3 is a plan view of an example of using a measurement frame. front view FIG. 5 is a plan view showing the use of other front view showing an example of FIG. 6 a front view thereof and FIG. 7 is a perspective view showing a test Hakawaku 8 ditto rebar holding member 9 A perspective view showing another example of a reinforcing bar holding member.
A Slope B Span beam C Reinforcement
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003005356A JP4145669B2 (en) | 2003-01-14 | 2003-01-14 | Inspection frame for legal frame formation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2003005356A JP4145669B2 (en) | 2003-01-14 | 2003-01-14 | Inspection frame for legal frame formation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2004218242A JP2004218242A (en) | 2004-08-05 |
| JP4145669B2 true JP4145669B2 (en) | 2008-09-03 |
Family
ID=32896026
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2003005356A Expired - Fee Related JP4145669B2 (en) | 2003-01-14 | 2003-01-14 | Inspection frame for legal frame formation |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4145669B2 (en) |
-
2003
- 2003-01-14 JP JP2003005356A patent/JP4145669B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2004218242A (en) | 2004-08-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR20200045061A (en) | Corrugated Deck Having Integrated Shear Connector | |
| JP4323226B2 (en) | Synthetic ribbed slab | |
| KR102027813B1 (en) | Built-Up Beam | |
| KR100373783B1 (en) | A temporary bracket for construction of precast concrete beam bridge and the temporary work method using the same | |
| JP4145669B2 (en) | Inspection frame for legal frame formation | |
| JP3073932B2 (en) | Floor structural materials | |
| JP3277242B2 (en) | Concrete reinforced metal wire support spacer | |
| KR0166641B1 (en) | Building floor structural materials | |
| JP2775398B2 (en) | Cast-in-place method and construction method | |
| JP3331460B2 (en) | On-site shot blasting method | |
| JP2007262859A (en) | Deck plate | |
| KR100974672B1 (en) | PC beam with reinforced end of pipe using bending steel sheet | |
| JP2006233577A (en) | Form for constructing slope frame and method for constructing slope frame | |
| JP2000073380A (en) | Bar arrangement for mat foundation work execution, bar arrangement structure of mat foundation work execution, and work execution method of the mat foundation | |
| JP2679003B2 (en) | Method frame and method of manufacturing method frame, and method of constructing method frame using method frame body | |
| JP3093930U (en) | Mesh frame | |
| KR200215026Y1 (en) | Deck Plate Spacer | |
| JP2000145017A (en) | Dowel bar, and semi precast concrete slab using it | |
| JPH09242079A (en) | Slope frame and execution method thereof | |
| JP2003184097A (en) | Form reinforcement for forming grating crib | |
| JP3527976B2 (en) | Construction rain shelter | |
| KR100729860B1 (en) | Triangle Truss Deck Panel End Structure | |
| JP6348206B1 (en) | Bar arrangement spacer | |
| JP3019074U (en) | Net formwork equipment | |
| JP3516231B2 (en) | Frame body for forming legal frame |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051121 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20060809 |
|
| RD02 | Notification of acceptance of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7422 Effective date: 20060809 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20071105 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20071120 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080111 Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20080111 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080520 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080618 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110627 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120627 Year of fee payment: 4 |
|
| LAPS | Cancellation because of no payment of annual fees |