JP4149028B2 - Scheduling / arrangement management system - Google Patents
Scheduling / arrangement management system Download PDFInfo
- Publication number
- JP4149028B2 JP4149028B2 JP12020598A JP12020598A JP4149028B2 JP 4149028 B2 JP4149028 B2 JP 4149028B2 JP 12020598 A JP12020598 A JP 12020598A JP 12020598 A JP12020598 A JP 12020598A JP 4149028 B2 JP4149028 B2 JP 4149028B2
- Authority
- JP
- Japan
- Prior art keywords
- schedule
- master
- model
- shop
- lead time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- General Factory Administration (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は各種製品の日程計画や手配の管理を行う日程計画・手配管理システムに関し、特に大型機械・設備加工組立産業等の製品で部品点数が多く、部品の標準化が難しく、製品の価格が高価でかなり複雑な部品構成から成り立っている製品の製造工場で、その製品の購入部品の発注時期及び納入時期の設定や指定並びに工場内の各種製品の作業工程単位の日程計画の作成及び修正の業務で用いられる日程計画・手配管理システムに適用して有効な技術に関するものである。
【0002】
【従来の技術】
従来の日程計画及び手配を管理する業務では、一般的には機種別に部品手配用の部品構成を示す部品表を設計で作成し、この設計の部品表を基に日程計画の作業工程のショップ構成を含めた部品表を製造側で別に作成し、製造の部品表に各作業工程単位のリードタイムを登録し、その製造の部品表の情報から品目構成(PN)や作業工程のショップ構成を含む部品構成(PS)の作成及び登録をコンピュータで行って運用している。
【0003】
その為、部品構成の作成の際には各部品毎や作業工程毎に日程展開の為のリードタイムの登録を行っており、各製品単位で全体の製造リードタイムを持っている。
【0004】
【発明が解決しようとする課題】
従来は各機種単位の日程計画及び手配のマスタとして、最終的に製造で作成した1つの部品表に手配部品構成と作業構成の両方を合わせた構成マスタを持ち(但し構成マスタは部品構成及び品目構成からなる)、日程計画及び手配はそれら品目構成及び部品構成を用いて行っている。
【0005】
しかしこの場合、設計で作成した部品表に製造で作業工程及びリードタイム等の登録を行う為、それらのコンピュータへの登録迄に時間が掛かるという問題がある。
【0006】
また、従来の日程計画は製品の機種単位の部品構成で行われているが、その部品構成は内容的には作業工程単位の様に階層的にはかなり深く詳細に成っている為、顧客からの納期変更で短納期の指示の場合等、どの作業工程のリードタイムを変更すべきかを検討するのに時間を要し、その日程変更及び修正に時間が掛かるという問題がある。
【0007】
本発明の目的は上記問題を解決し、日程計画の作成、修正及び変更を容易に行うことが可能な技術を提供することにある。
【0008】
本発明の他の目的はMRP展開の処理時間を短縮することが可能な技術を提供することにある。
【0009】
【課題を解決するための手段】
本発明は製品を製造する際の日程計画や購入品及び外注加工品の手配の管理を行う日程計画・手配管理システムにおいて、製品のサブユニット内の各部品の構成を示す部品構成マスタと、製品を製造する各作業工程の構成を示すショップ構成マスタとから作業工程別に集計したリードタイムを示す機種別日程展開マスタを作成し、作業工程別のリードタイムから各サブユニットの納入必要日を決定し、各サブユニット内の各部品の日程展開を行って各部品の発注日を決定して手配処理を行うものである。
【0010】
従来は日程計画及び手配のマスタを1つの構成マスタとして持ち、日程計画及び手配はその品目構成及び部品構成を用いて行っている。この場合、日程計画用の部品構成を示す項目は、先にも述べた様にかなり階層的に深く成っている為、日程変更及び修正に時間が掛かっている。
【0011】
そこで本発明では、作業工程単位で集計した職場単位の日程展開用のマスタである機種別日程展開マスタを持つ様にし、ある程度大枠の機種別日程展開マスタで日程計画の修正を行う様にする。
【0012】
本発明のマスタ登録処理部では、資材所要量計画(MRP:MaterialRequirements Planning)展開の手配及び調達用の部品構成マスタとして、サブユニットの1レベル毎の部品構成を示す品名、品目コード、数量及びサブユニット全体のリードタイムと、サブユニット及び作業工程間の関連付けを行うのに必要なショップコードとを予め登録することにより、各サブユニットをある製番でショップコードを用いて関連付け出来る構成にしておく。
【0013】
ここでMRPは、製品毎に展開計算を行い、部品・原材料毎に必要量を集約し、在庫の引き当て、発注などある製品を製造するのに必要な部品・原材料の種類と数量を計算する処理のことをいう。
【0014】
次にマスタ登録処理部では、日程展開用のショップ構成マスタとして、工場を職場単位、例えば検査、組立、部品組立及び機械加工と言った作業工程に分類し、各作業工程をレベルで関連付ける関連付け構成を行い、それぞれの作業工程とサブユニットとを関連付ける為のショップコードを登録する。
【0015】
次に日程計画処理部で見込み生産の日程計画処理を行う場合には、予め日程展開用のショップ構成マスタとサブユニットの部品構成マスタを関連付けて製品の機種単位で作業工程別にリードタイムを集計して機種別日程展開マスタとして登録する。
【0016】
また受注生産の日程計画処理では、日程展開用のショップ構成マスタをその都度作成し、サブユニットの部品構成マスタへの関連付けをその都度行い、作業工程別にリードタイムを集計して受注機種単位の機種別日程展開マスタを登録する。
【0017】
なお機種別日程展開マスタの各作業工程のリードタイムは、部品構成マスタとショップ構成マスタの関連付け時点に於いて、部品構成マスタのリードタイムが集計されることにより作成される。
【0018】
次に手配処理部は、この機種別日程展開マスタの各作業工程のリードタイムから各サブユニットの納入必要日を決定し、各サブユニット単位で部品構成マスタのMRP展開を行って、当該サブユニットを構成する部品が前記納入必要日までに納入される様に各部品の発注日及び納入日を決定する。
【0019】
また日程変更処理部は、通常発生する日程計画変更時にはこの機種別日程展開マスタのリードタイムの変更により日程計画の変更を行い、設計変更時等にサブユニットそのものが変更となる場合のみショップ構成マスタを変更する。
【0020】
前記の様に本発明では、作業工程単位の詳細なリードタイムの内容を機種別日程展開マスタとして持ち、日程計画の作成や日程計画の修正及び変更が必要な場合には、通常は機種別日程展開マスタ中の作業工程単位のリードタイムを用いる為、日程計画の修正及び変更を容易に行えるメリットがある。
【0021】
またMRP展開ではサブユニット単位の部品構成マスタのみで行える為、MRP展開の処理時間が短縮される。また設計の部品表に無い作業工程で作業が行われる場合には、日程展開のショップ構成マスタのみの変更及び追加で容易に対応出来るメリットがある。
【0022】
以上の様に本発明の日程計画・手配管理システムによれば、機種別日程展開マスタ中の作業工程別に集計したリードタイムとサブユニット単位の部品構成マスタとを用いて日程計画の作成、修正及び変更を行うので、日程計画の作成、修正及び変更を容易に行うことが可能である。
【0023】
【発明の実施の形態】
以下に製品のサブユニット単位の部品構成を示す部品構成マスタと作業工程の構成を示すショップ構成マスタとを組み合わせて作業工程別にリードタイムを集計した機種別日程展開マスタを作成し、日程計画及び手配の管理を行う一実施形態の日程計画・手配管理システムについて説明する。
【0024】
本実施形態の日程計画・手配管理システムでは、最終組立製品が幾つかのサブユニットで構成され、それらサブユニット単位でも幾つかの機種構成があり、最終組立製品単位でも幾つかの機種構成からなる製品で、最終組立製品及びそのサブユニットは、それぞれ見込み生産または受注生産の形態を取る製品の日程計画・手配管理を行う際に、日程計画及び手配関連の構成マスタに関して、手配用の部品構成マスタ及び日程計画用のショップ構成マスタの組合せから機種別日程展開マスタを作成し、日程計画及び手配の管理を行なう。
【0025】
図1は本実施形態の日程計画・手配管理システムの処理概要を示す図である。図1に示す様に本実施形態の日程計画・手配管理システムは、ショップ構成マスタ格納部01と、部品構成マスタ格納部02と、日程展開マスタ作成処理5と、設計部品表情報50と、製造基準情報51と、受注情報52と、日程変更情報53と、部品構成マスタ101と、部品品目マスタ102と、ショップ構成マスタ103と、ショップマスタ104と、機種別日程展開マスタ105とを有している。
【0026】
ショップ構成マスタ格納部01はショップ構成マスタ103及びショップマスタ104を格納する記憶装置である。部品構成マスタ格納部02は部品構成マスタ101及び部品品目マスタ102を格納する装置である。
【0027】
日程展開マスタ作成処理5は部品構成マスタ101及びショップ構成マスタ103中の内容をショップコードにより関連付けて、機種別日程展開マスタ105を作成する処理である。設計部品表情報50は設計部品を表す部品手配用の情報である。
【0028】
製造基準情報51は製造の基準を示す情報である。受注情報52は受注の内容を示す情報である。日程変更情報53は日程変更を示す情報である。部品構成マスタ101は製品のサブユニット内の各部品の構成を示す項目及び当該サブユニットの各部品を作業工程に関連付ける為のショップコードを有するファイルである。
【0029】
部品品目マスタ102は部品の内容を示すファイルである。ショップ構成マスタ103は製品を製造する各作業工程の構成を示す項目及び当該作業工程をサブユニットの部品に関連付ける為のショップコードを有するファイルである。
【0030】
ショップマスタ104は作業工程の内容を示すファイルである。機種別日程展開マスタ105はある機種の製品を製造する際の各作業工程のリードタイム及び標準時間を有するファイルである。
【0031】
本システムは大きくはマスタ登録処理、日程計画処理、手配処理及び日程変更処理を行う4つの処理部より成っている。
【0032】
図2は本実施形態の日程計画・手配管理システムの概略構成を示す図である。図2に示す様に本実施形態の日程計画・手配管理装置200は、CPU201と、メモリ202と、磁気ディスク装置203と、キーボード204と、ディスプレイ装置205と、CD−ROM装置206とを有している。
【0033】
CPU201は日程計画・手配管理装置200全体の動作を制御する装置である。メモリ202はマスタ登録処理部210、日程計画処理部211、手配処理部212及び日程変更処理部213として機能させる為の処理プログラムやそのデータをロードする記憶装置である。
【0034】
磁気ディスク装置203はショップ構成マスタ格納部01及び部品構成マスタ格納部02に相当し、前記処理プログラムや部品構成マスタ101、部品品目マスタ102及び機種別日程展開マスタ105等のデータを格納する記憶装置である。
【0035】
キーボード204は前記処理プログラムの処理に伴う操作指示やデータの入力を行う装置である。ディスプレイ装置205は前記処理プログラムの処理に伴う処理結果等の表示を行う装置である。CD−ROM装置206は前記処理プログラムを記録した媒体を読み込む装置である。
【0036】
また日程計画・手配管理装置200は、マスタ登録処理部210と、日程計画処理部211と、手配処理部212と、日程変更処理部213とを有している。
【0037】
マスタ登録処理部210は部品構成マスタ101及び部品品目マスタ102とショップ構成マスタ103及びショップマスタ104とを登録する処理部である。日程計画処理部211は日程展開マスタ作成処理5により機種別日程展開マスタ105を作成して登録する処理部である。
【0038】
手配処理部212は機種別日程展開マスタ105で日程展開を行って各サブユニットの納入必要日を決定し、各サブユニット単位で部品構成マスタ101の日程展開を行って当該サブユニットの各部品が前記納入必要日までに納入される様に各部品の発注日及び納入日を決定する処理部である。
【0039】
日程変更処理部213は日程変更情報53により日程計画の変更を行う製品の機種を選定し、選定された機種の機種別日程展開マスタ105を呼び出し、機種別日程展開マスタ105のリードタイムを変更することにより日程変更を行う処理部である。
【0040】
日程計画・手配管理装置200をマスタ登録処理部210、日程計画処理部211、手配処理部212及び日程変更処理部213として機能させる為のプログラムは、CD−ROM等の記録媒体に記録され磁気ディスク等に格納された後、メモリにロードされて実行されるものとする。なお前記プログラムを記録する媒体はCD−ROM以外の他の媒体でも良い。
【0041】
マスタ登録処理部210では、部品手配用の設計部品表情報50に応じて部品構成及び部品品目を入力して部品構成マスタ格納部02の部品構成マスタ101及び部品品目マスタ102を登録し、日程計画用の製造基準情報51に応じてショップ構成及びショップ品目を入力してショップ構成マスタ格納部01のショップ構成マスタ103及びショップマスタ104を登録する。
【0042】
次に日程計画処理部211の日程展開マスタ作成処理5では、部品構成マスタ101及びショップ構成マスタ103をショップコードにより関連付けて、それらの各種組合せによって作業工程別に集計したリードタイム及び標準時間を持つ機種別日程展開マスタ105を作成して登録する。
【0043】
手配処理部212では、機種別日程展開マスタ105の作業工程別のリードタイムにより各サブユニットの納入必要日を決定し、各サブユニット単位で部品構成マスタ101の日程展開を行って当該サブユニットの各部品が前記納入必要日までに納入される様に各部品の発注日及び納入日を決定する。
【0044】
その際、手配処理部212は、各サブユニットの部品構成マスタ101のみを用いてサブユニット単位で日程展開を行って、当該サブユニットで最初に必要となる部品の納入日に全部品が納入される様に各部品の納入必要日を決定し、前記納入必要日に各部品が納入される様に各部品の納入リードタイムでバックワード展開して各部品の発注日を決定しても良い。
【0045】
日程変更処理部213では、日程変更情報53より日程変更を行う製品機種の選定を行い、選定機種に合った機種別日程展開マスタ105を呼び出し、機種別日程展開マスタ105中のリードタイムの変更修正を行って再日程計画を行う。
【0046】
なお図2ではマスタ登録処理部210、日程計画処理部211、手配処理部212及び日程変更処理部213の各処理を同一の装置で行うものとしたが、各処理を別の装置で行うものとし、複数の装置から成るシステム構成としても良い。
【0047】
以下に本実施形態の日程計画・手配管理システムのマスタ登録処理、日程計画処理及び手配処理について詳細説明を行う。まずマスタ登録処理について説明する。
【0048】
図3は本実施形態の部品構成の概要を示す図である。図3において、破線で囲まれた各領域は製品を構成するサブユニットを表しており、例えば本体Xはサブユニットである部組A及び購入品Gで構成され、サブユニットの部組Aはそのサブユニットである部組B及び部組Cから構成されている。
【0049】
図4は本実施形態の部品構成マスタ101の例を示す図である。MRP展開の為の手配用の部品構成マスタ101の登録では、予め図3の破線の様に製品本体をサブユニット単位で階層的に分割し、それぞれのサブユニットが属している階層を示すレベル番号を付加する。
【0050】
次に図4の様に、製品のサブユニット内の各部品の構成を示す項目として、その品目のレベル、品名、品目コード、数量、リードタイム(LT)及び標準時間(ST)を登録し、また、最終組立製品単位、各サブユニット間及びサブユニット内の各部品を作業工程に関連付ける為のショップコード(部署構成を示すコード)を登録する。
【0051】
本実施形態の日程計画・手配管理システムにおいて、MRP展開時には従来の様に製品単位で全部品を展開するのではなく、ショップコードにより関連付けされた各サブユニットの部品構成単位のみで展開をする。要するにショップコードが同一である部品構成単位で展開を行う。
【0052】
この場合、製品単位またはサブユニット単位で製番を付け、各サブユニットの部品構成マスタ101のショップコード及びショップ構成マスタ103のショップコードにより、製品単位やサブユニット単位内での製番で各部品作業を図5及び図6の様に直接調達/作業品目に関連付け出来る構成になっている。
【0053】
図5は本実施形態の製番の直接調達/作業品目への関連付けの例を示す図である。図5に示す様に製番#Aで示される製品またはサブユニットは、各サブユニットの部品構成マスタ101のショップコード及びショップ構成マスタ103のショップコードを関連付けることにより、例えばKUで表される組立調整作業に関連付けられる。
【0054】
図6は本実施形態の各サブユニットで複数の機種構成を持つ場合の関連付けの例を示す図である。最終組立製品やそれを構成するサブユニットで幾つかの機種構成がある場合でも、その製品やサブユニットは特定の部品作業に関連付けることが可能であり、各サブユニットの部品構成マスタ101のショップコード及びショップ構成マスタ103のショップコードを関連付けることにより、例えば図6の破線で示す半製品Bやサブユニットを組立調整等の部品作業に関連付けられる。
【0055】
次に日程展開用のショップ構成マスタ103の登録では、例えば図7の様に作業工程の作業内容を分類し、ショップ構成を作成する。
【0056】
図7は本実施形態のショップ構成の一例を示す図である。図7に示す様に本実施形態の日程計画・手配管理システムでは、最終組立製品や各サブユニットの製造を行う作業工程を、例えば検査、組立調整、機械部組、基板組立及び機械加工と言った作業工程に分類し、それらのショップコードとしてそれぞれKE、KU、MB、PB及びMTを設定する。
【0057】
図8は本実施形態のショップ構成マスタ103の例を示す図である。図8に示す様に本実施形態の日程計画・手配管理システムでは、図7の様に製品を製造する各作業工程の構成を示す項目として、前記分類された作業工程のレベル、その作業工程の名称を示すショップ名、当該作業工程をサブユニットの部品に関連付ける為のショップコード、LT及びSTをショップ構成マスタ103に登録する。ショップ構成マスタ103には、ショップ構成マスタ103のショップ名に示された作業工程とサブユニットとの関連付けを行う為に、図8の様にショップ名に対応するショップコードが登録されている。
【0058】
見込み生産を行う場合の日程計画処理では、図9の様に生産に必要な機種単位でのショップ構成マスタ103とその機種に適用するサブユニットの部品構成マスタ101を展開し、ショップコードにて自動関連付けを行って機種単位に登録し、図10の様な機種別の機種別日程展開マスタ105を登録する。
【0059】
また受注生産を行う場合の日程計画処理では、日程展開用のショップ構成マスタ103をその都度作成し、サブユニットの部品構成マスタ101とマニュアルで関連付けを行い、受注機種単位の機種別日程展開マスタ105を作成して登録する。
【0060】
図9は本実施形態の生産に必要な機種単位でのショップ構成マスタ103とその機種に適用するサブユニットの部品構成マスタ101の展開の概要を示す図である。図9に示す様にショップ構成マスタ103の組立調整、機械部組、基板組立及び機械加工の各作業工程に、サブユニットの部品構成マスタ101−1〜部品構成マスタ101−4が関連付けられている。
【0061】
図10は本実施形態の機種別日程展開マスタ105の例を示す図である。図10に示した機種別日程展開マスタ105の各作業工程のリードタイムは、部品構成マスタ101とショップ構成マスタ103の関連付け時点に於いて、各サブユニットの部品構成マスタ101のリードタイムが集計されることにより設定される。
【0062】
次に手配処理では、この機種別日程展開マスタ105の各作業工程のリードタイムから各サブユニットの納入必要日を決定し、各サブユニット単位で部品構成マスタ101のMRP展開を行って、当該サブユニットを構成する部品が前記納入必要日までに納入される様に各部品の発注日及び納入日を決定する。
【0063】
また日程計画の変更が生じた場合に日程変更処理では、日程変更情報53により日程計画の変更を行う製品の機種を選定し、選定された機種の機種別日程展開マスタ105を呼び出し、その機種別日程展開マスタ105のみを変更する。手配処理では、この変更した機種別日程展開マスタ105の各作業工程のリードタイムから各サブユニットの納入必要日を決定し、各サブユニット単位で部品構成マスタ101のMRP展開を行って、日程計画変更後の各部品の発注日及び納入日を決定する。
【0064】
図11は本実施形態の日程変更時の機種別日程展開マスタ105の修正例を示す図である。日程計画のデーリに発生する内乱や外乱(客先の納期変更、不良や欠品等)による日程変更時には、部品構成マスタ101やショップ構成マスタ103での変更はせず、図11の様に機種別日程展開マスタ105のリードタイム等を変更する。
【0065】
但し設計変更等で部品構成マスタ101のリードタイムが大幅に変わる場合には、部品構成マスタ101の変更を行う様にし、日程変更を容易に行なえる様にする。
【0066】
図12は本実施形態の納入日決定の概要を示す図である。MRP展開による手配処理では、サブユニット単位でのみの部品構成マスタ101の展開を行って、発注日及び納入日を決定する。
【0067】
但し、図12の様に機種別日程展開マスタ105での日程展開により納入日の決定を行い、各サブユニットでの納入必要日が確定したら、各サブユニット単位の最も早い部品の納入必要日にそれぞれの部品単位の納入リードタイムでバックワードタイプで発注日を決めた後に纏めての納入する方法と、サブユニットの各作業工程の納入必要日に合わせて納入する2通りの納入方法が取れるものとする。
【0068】
図12に示した様に例えば部品構成マスタ101−4を用いるサブユニットにおいて、納入日が10月20日で最長納入リードタイムが10日である場合、サブユニット単位の最も早い部品の発注日を10月10日に決めた後に、その発注日に合わせて他の部品も纏めての納入する様にしても良いし、サブユニットの各作業工程の納入必要日に合わせて各部品を納入しても良い。
【0069】
以上説明した様に本実施形態の日程計画・手配管理システムによれば、機種別日程展開マスタ中の作業工程別に集計したリードタイムとサブユニット単位の部品構成マスタとを用いて日程計画の作成、修正及び変更を行うので、日程計画の作成、修正及び変更を容易に行うことが可能である。
【0070】
また本実施形態の日程計画・手配管理システムによれば、サブユニット単位の部品構成マスタのみでMRP展開を行うので、MRP展開の処理時間を短縮することが可能である。
【0071】
【発明の効果】
本発明によれば機種別日程展開マスタ中の作業工程別に集計したリードタイムとサブユニット単位の部品構成マスタとを用いて日程計画の作成、修正及び変更を行うので、日程計画の作成、修正及び変更を容易に行うことが可能である。
【図面の簡単な説明】
【図1】本実施形態の日程計画・手配管理システムの処理概要を示す図である。
【図2】本実施形態の日程計画・手配管理システムの概略構成を示す図である。
【図3】本実施形態の部品構成の概要を示す図である。
【図4】本実施形態の部品構成マスタ101の例を示す図である。
【図5】本実施形態の製番の直接調達/作業品目への関連付けの例を示す図である。
【図6】本実施形態の各サブユニットで複数の機種構成を持つ場合の関連付けの例を示す図である。
【図7】本実施形態のショップ構成の一例を示す図である。
【図8】本実施形態のショップ構成マスタ103の例を示す図である。
【図9】本実施形態の生産に必要な機種単位でのショップ構成マスタ103とその機種に適用するサブユニットの部品構成マスタ101の展開の概要を示す図である。
【図10】本実施形態の機種別日程展開マスタ105の例を示す図である。
【図11】本実施形態の日程変更時の機種別日程展開マスタ105の修正例を示す図である。
【図12】本実施形態の納入日決定の概要を示す図である。
【符号の説明】
01…ショップ構成マスタ格納部、02…部品構成マスタ格納部、5…日程展開マスタ作成処理、50…設計部品表情報、51…製造基準情報、52…受注情報、53…日程変更情報、101…部品構成マスタ、102…部品品目マスタ、103…ショップ構成マスタ、104…ショップマスタ、105…機種別日程展開マスタ、200…日程計画・手配管理装置、201…CPU、202…メモリ、203…磁気ディスク装置、204…キーボード、205…ディスプレイ装置、206…CD−ROM装置、210…マスタ登録処理部、211…日程計画処理部、212…手配処理部、213…日程変更処理部。[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a schedule planning / arrangement management system for scheduling various products and managing arrangements, and in particular, there are many parts in products such as large machinery / equipment processing / assembly industries, standardization of parts is difficult, and the price of products is expensive. In the manufacturing factory of a product consisting of fairly complex parts, the setting and designation of the ordering and delivery times of purchased parts of the product, and the creation and correction of schedule plans for each work process unit of various products in the factory This technology relates to a technology that is effective when applied to the scheduling / arrangement management system used in Japan.
[0002]
[Prior art]
In the conventional schedule management and arrangement management, generally, a bill of materials showing the parts configuration for parts arrangement is created by design for each model, and the shop structure of the schedule planning work process is based on this design bill of materials. Create a separate bill of materials including manufacturing, register the lead time of each work process unit in the manufacturing bill of material, and include the item structure (PN) and shop structure of the work process from the information of the bill of manufacturing. Parts configuration (PS) is created and registered by a computer.
[0003]
For this reason, when creating a component configuration, the lead time for schedule development is registered for each part and each work process, and each product has an overall production lead time.
[0004]
[Problems to be solved by the invention]
Conventionally, as a master for scheduling and ordering for each model unit, it has a composition master that combines both the ordered part structure and the work structure in one bill of materials that was finally created in manufacturing (however, the composition master is the part composition and item) Scheduling and arrangements are made using these item and part configurations.
[0005]
However, in this case, since the work process, lead time, and the like are registered in the parts table created by design, there is a problem that it takes time to register them in the computer.
[0006]
In addition, the conventional scheduling is carried out with the parts structure of each product model, but the contents of the parts are quite deep and detailed hierarchically like the work process unit. There is a problem that it takes time to consider which work process lead time should be changed, such as in the case of a short delivery date instruction due to the delivery date change, and it takes time to change and correct the schedule.
[0007]
An object of the present invention is to provide a technique capable of solving the above problems and easily creating, modifying and changing a schedule.
[0008]
Another object of the present invention is to provide a technique capable of reducing the processing time of MRP expansion.
[0009]
[Means for Solving the Problems]
The present invention relates to a schedule configuration / arrangement management system for managing schedules when manufacturing products and scheduling of purchased products and subcontracted processed products, a component configuration master indicating the configuration of each part in a product subunit, and a product Create a schedule expansion master for each model showing the lead time aggregated for each work process from the shop structure master that shows the structure of each work process to manufacture, and determine the delivery date for each subunit from the lead time for each work process The schedule development of each part in each subunit is performed to determine the order date of each part, and the arrangement process is performed.
[0010]
Conventionally, a schedule planning and ordering master is provided as one configuration master, and the scheduling and ordering are performed using the item configuration and part configuration. In this case, since the items indicating the parts configuration for the schedule plan are considerably hierarchically deep as described above, it takes time to change and modify the schedule.
[0011]
Therefore, in the present invention, a model-specific schedule development master, which is a master for schedule development for each workplace, aggregated in units of work processes, is provided, and a schedule plan is corrected with a model-based schedule development master of a somewhat large frame.
[0012]
In the master registration processing unit of the present invention, as a parts configuration master for arrangement and procurement of material requirement planning (MRP) development, a product name, item code, quantity and sub By registering in advance the lead time of the entire unit and the shop code necessary for associating the subunits and the work processes, each subunit can be associated with a certain product number using the shop code. .
[0013]
Here, MRP performs a calculation for each product, aggregates the required amount for each part / raw material, and calculates the type and quantity of parts / raw materials necessary for manufacturing a certain product, such as inventory allocation and ordering. I mean.
[0014]
Next, in the master registration processing unit, as a shop configuration master for schedule development, the factory is classified into work units such as inspection, assembly, parts assembly, and machining, for example, and an association configuration that associates each work process at a level. And register a shop code to associate each work process with a subunit.
[0015]
Next, when performing schedule planning for prospective production in the schedule planning processing unit, the shop configuration master for schedule expansion and the component configuration master for subunits are linked in advance, and the lead time is tabulated for each work process for each product model. And register as a schedule expansion master by model.
[0016]
In the schedule planning process for build-to-order production, a shop configuration master for schedule expansion is created each time, the subunits are linked to the part configuration master each time, and the lead time is aggregated for each work process. Register another schedule expansion master.
[0017]
The lead time of each work process of the model-specific schedule development master is created by summing up the lead times of the part configuration master at the time of association between the part configuration master and the shop configuration master.
[0018]
Next, the arrangement processing unit determines the delivery required date of each subunit from the lead time of each work process of this model-specific schedule development master, performs MRP deployment of the component configuration master for each subunit, and The order date and the delivery date of each part are determined so that the parts constituting the system are delivered by the required delivery date.
[0019]
In addition, the schedule change processing unit changes the schedule plan by changing the lead time of this model-specific schedule development master when changing the schedule plan that normally occurs, and only when the subunit itself is changed at the time of design change etc. To change.
[0020]
As described above, according to the present invention, the detailed lead time content of each work process unit is provided as a model-specific schedule development master, and when schedule schedule creation or schedule plan correction and change are necessary, the model schedule is usually used. Since the lead time of the work process unit in the development master is used, there is an advantage that the schedule can be easily corrected and changed.
[0021]
Further, since the MRP expansion can be performed only with the component configuration master in units of subunits, the processing time of the MRP expansion is shortened. In addition, when work is performed in a work process not included in the parts list of the design, there is an advantage that it can be easily handled by changing and adding only the shop configuration master for schedule development.
[0022]
As described above, according to the schedule planning / arrangement management system of the present invention, a schedule plan can be created, corrected, and corrected using the lead time and the component unit master for each subunit in the schedule development master by model. Since changes are made, it is possible to easily create, modify and change schedules.
[0023]
DETAILED DESCRIPTION OF THE INVENTION
Create a schedule expansion master for each model by summarizing the lead time for each work process by combining the part structure master that indicates the part structure of each product subunit and the shop structure master that indicates the structure of the work process. A schedule planning / arrangement management system according to an embodiment for performing the above management will be described.
[0024]
In the scheduling / arrangement management system of the present embodiment, the final assembly product is composed of several subunits, and there are several model configurations even in units of those subunits, and there are several model configurations in the final assembly product unit. The final assembly product and its sub-units are the parts configuration masters for arrangements with respect to the scheduling masters and arrangement related configuration masters when performing scheduling and order management of products that take the form of prospective production or make-to-order production, respectively. A schedule development master for each model is created from a combination of shop configuration masters for schedule planning, and schedule planning and arrangement management are performed.
[0025]
FIG. 1 is a diagram showing a processing outline of a schedule planning / arrangement management system according to the present embodiment. As shown in FIG. 1, the schedule planning / arrangement management system of this embodiment includes a shop configuration
[0026]
The shop configuration
[0027]
The schedule development
[0028]
The production standard information 51 is information indicating a production standard. The order information 52 is information indicating the contents of the order. The
[0029]
The
[0030]
The
[0031]
This system mainly includes four processing units that perform master registration processing, schedule planning processing, arrangement processing, and schedule change processing.
[0032]
FIG. 2 is a diagram showing a schematic configuration of the schedule planning / arrangement management system of the present embodiment. As shown in FIG. 2, the schedule planning /
[0033]
The
[0034]
The
[0035]
A
[0036]
The schedule planning /
[0037]
The master
[0038]
The
[0039]
The schedule
[0040]
A program for causing the schedule planning /
[0041]
The master
[0042]
Next, in the schedule development
[0043]
In the
[0044]
At that time, the
[0045]
The schedule
[0046]
In FIG. 2, the master
[0047]
The master registration process, schedule planning process, and arrangement process of the schedule planning / arrangement management system of this embodiment will be described in detail below. First, the master registration process will be described.
[0048]
FIG. 3 is a diagram showing an outline of the component configuration of the present embodiment. In FIG. 3, each area surrounded by a broken line represents a subunit that constitutes a product. For example, the main body X is composed of a group A that is a subunit and a purchased product G. It consists of a group B and a group C which are subunits.
[0049]
FIG. 4 is a diagram illustrating an example of the
[0050]
Next, as shown in FIG. 4, the item level, item name, item code, quantity, lead time (LT) and standard time (ST) are registered as items indicating the configuration of each part in the product subunit. In addition, a shop code (a code indicating a department structure) for associating the final assembly product unit, each sub-unit, and each part in the sub-unit with the work process is registered.
[0051]
In the schedule planning / arrangement management system of this embodiment, at the time of MRP expansion, not all the parts are expanded in units of products as in the prior art, but are expanded only in the component constituent units of each subunit associated by the shop code. In short, the development is performed in the unit of component parts having the same shop code.
[0052]
In this case, the product number is assigned in units of products or subunits, and each part is identified by the product number in the product unit or subunit unit according to the shop code of the
[0053]
FIG. 5 is a diagram illustrating an example of direct procurement / association of work numbers with work items according to the present embodiment. As shown in FIG. 5, the product or subunit indicated by the product number #A is an assembly represented by KU, for example, by associating the shop code of the
[0054]
FIG. 6 is a diagram showing an example of association when each subunit of the present embodiment has a plurality of model configurations. Even if there are several model configurations of the final assembled product and the subunits constituting it, the products and subunits can be associated with specific parts work, and the shop code of the
[0055]
Next, in the registration of the
[0056]
FIG. 7 is a diagram showing an example of the shop configuration of the present embodiment. As shown in FIG. 7, in the schedule planning / arrangement management system of this embodiment, the work processes for manufacturing the final assembly product and each subunit are referred to as inspection, assembly adjustment, machine assembly, board assembly, and machining, for example. And KE, KU, MB, PB and MT are set as the shop codes.
[0057]
FIG. 8 is a diagram illustrating an example of the
[0058]
In the schedule planning process when performing prospective production, as shown in FIG. 9, the
[0059]
Further, in the schedule planning process when order production is performed, a
[0060]
FIG. 9 is a diagram showing an overview of the development of the
[0061]
FIG. 10 is a diagram showing an example of the model-specific
[0062]
Next, in the arrangement processing, the delivery required date of each subunit is determined from the lead time of each work process of this model-specific
[0063]
When the schedule change occurs, in the schedule change process, the model of the product whose schedule is changed is selected by the
[0064]
FIG. 11 is a diagram illustrating a modification example of the model-specific
[0065]
However, when the lead time of the
[0066]
FIG. 12 is a diagram showing an outline of delivery date determination according to this embodiment. In the arrangement process by MRP expansion, the
[0067]
However, as shown in FIG. 12, when the delivery date is determined by the schedule development in the model-specific
[0068]
As shown in FIG. 12, in the subunit using the component configuration master 101-4, for example, when the delivery date is October 20 and the longest delivery lead time is 10 days, the earliest part order date of the subunit unit is set. After deciding on October 10th, other parts may be delivered together according to the order date, or each part will be delivered according to the required delivery date of each work process of the subunit. Also good.
[0069]
As described above, according to the schedule planning / arrangement management system of this embodiment, a schedule plan is created using the lead time calculated for each work process in the model-specific schedule development master and the component configuration master for each subunit, Since corrections and changes are made, it is possible to easily create, correct and change schedules.
[0070]
Further, according to the schedule planning / arrangement management system of the present embodiment, since the MRP deployment is performed only by the component configuration master for each subunit, it is possible to shorten the processing time of the MRP deployment.
[0071]
【The invention's effect】
According to the present invention, the schedule is created, modified, and changed using the lead time tabulated for each work process in the schedule development master for each model and the component unit master for each subunit. Changes can be made easily.
[Brief description of the drawings]
FIG. 1 is a diagram showing an outline of processing of a schedule planning / arrangement management system according to an embodiment.
FIG. 2 is a diagram showing a schematic configuration of a schedule planning / arrangement management system according to the present embodiment.
FIG. 3 is a diagram showing an outline of a component configuration of the present embodiment.
FIG. 4 is a diagram illustrating an example of a
FIG. 5 is a diagram illustrating an example of direct procurement / association of work numbers with work items according to the present embodiment.
FIG. 6 is a diagram showing an example of association when each subunit of the present embodiment has a plurality of model configurations.
FIG. 7 is a diagram illustrating an example of a shop configuration according to the present embodiment.
FIG. 8 is a diagram illustrating an example of a
FIG. 9 is a diagram showing an outline of development of a
FIG. 10 is a diagram illustrating an example of a model-specific
FIG. 11 is a diagram illustrating a modification example of the model-specific
FIG. 12 is a diagram showing an outline of delivery date determination according to the present embodiment.
[Explanation of symbols]
DESCRIPTION OF
Claims (2)
製品のサブユニット内の各部品のリードタイム及び当該サブユニットの各部品を作業工程に関連付ける為のショップコードを有する部品構成マスタと、製品を製造する各作業工程名及び当該作業工程をサブユニットの部品に関連付ける為のショップコードを有するショップ構成マスタとを格納する記憶装置と、
前記ショップ構成マスタ中のショップコードをキーに、部品構成マスタにおいて当該キーに対応するリードタイムを前記記憶装置から機種単位で読み出し、作業工程別に前記読み出したリードタイムを集計し、機種単位で各作業工程名と前記集計したリードタイムとを対応付ける機種別日程展開マスタを作成して前記記憶装置に格納する日程計画処理部と、
前記機種別日程展開マスタ中の作業工程別リードタイムを前記記憶装置から読み出し、読み出した各作業工程別リードタイムから各サブユニットの納入必要日を決定し、各サブユニット単位で部品構成マスタの各部品のリードタイムを前記記憶装置から読み出して当該サブユニットの各部品が前記納入必要日までに納入される様に各部品の発注日及び納入日を決定する手配処理部と、
日程変更情報により日程計画の変更を行う製品の機種を選定し、選定された機種の機種別日程展開マスタを前記記憶装置から読み出し、当該機種別日程展開マスタのリードタイムを変更して前記記憶装置に格納することにより日程変更を行う日程変更処理部とを備えることを特徴とする日程計画・手配管理システム。In the scheduling / arrangement management system that manages scheduling and parts arrangement when manufacturing products,
A component configuration master having a shop code for associating each sub-unit lead time with a work process, the name of each work process for manufacturing the product, and the work process of the sub-unit. A storage device for storing a shop configuration master having a shop code for associating with a part;
Using the shop code in the shop configuration master as a key, the lead time corresponding to the key in the component configuration master is read from the storage unit in units of models, and the read lead times are totaled for each work process, and each work is performed in units of models. A schedule planning processing unit for creating a model-specific schedule development master for associating a process name with the totaled lead time and storing it in the storage device;
The lead time for each work process in the schedule development master for each model is read from the storage device, the delivery required date of each subunit is determined from the read lead time for each work process, and each component unit master for each sub unit is determined. An arrangement processing unit that reads out the lead time of the parts from the storage device and determines the order date and the delivery date of each part so that each part of the sub-unit is delivered by the delivery required date ;
Select the model of the product whose schedule is to be changed based on the schedule change information, read the model-specific schedule development master of the selected model from the storage device, change the lead time of the model-specific schedule development master, and store the storage device A schedule planning / arrangement management system comprising: a schedule change processing unit for changing a schedule by storing in a schedule.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12020598A JP4149028B2 (en) | 1998-04-30 | 1998-04-30 | Scheduling / arrangement management system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP12020598A JP4149028B2 (en) | 1998-04-30 | 1998-04-30 | Scheduling / arrangement management system |
Related Child Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2005140999A Division JP2005302050A (en) | 2005-05-13 | 2005-05-13 | Scheduling / arrangement management system |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH11312197A JPH11312197A (en) | 1999-11-09 |
| JP4149028B2 true JP4149028B2 (en) | 2008-09-10 |
Family
ID=14780513
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP12020598A Expired - Fee Related JP4149028B2 (en) | 1998-04-30 | 1998-04-30 | Scheduling / arrangement management system |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4149028B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3680264B2 (en) * | 2000-07-21 | 2005-08-10 | トヨタ自動車株式会社 | Parts procurement system |
| JP4617550B2 (en) | 2000-09-07 | 2011-01-26 | セイコーエプソン株式会社 | Delivery information management system |
| KR101131094B1 (en) * | 2004-02-20 | 2012-04-02 | 대우조선해양 주식회사 | Demanding and supplying method when vessel is constructed |
| JP2006331262A (en) * | 2005-05-30 | 2006-12-07 | Mitsubishi Electric Corp | Material requirement planning device |
| JP2018197895A (en) * | 2017-05-23 | 2018-12-13 | 三菱電機株式会社 | Production plan generation device, production plan generation method and program |
-
1998
- 1998-04-30 JP JP12020598A patent/JP4149028B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JPH11312197A (en) | 1999-11-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5101352A (en) | Material requirements planning system | |
| US6119102A (en) | MRP system with viewable master production schedule | |
| JP2599536B2 (en) | Method and system for managing product configuration | |
| JP6997830B2 (en) | Cost control equipment, cost control methods, and cost control programs | |
| US20100287020A1 (en) | Constraint-based production planning and scheduling | |
| US20060129462A1 (en) | Automated planning and manufacturing systems | |
| JP2003015722A (en) | Custom-order assembly production system and custom-order assembly production method | |
| JP3452801B2 (en) | Factory plan creation device | |
| US20060129461A1 (en) | Data entry and system for automated order, design, and manufacture of ordered parts | |
| JP3419216B2 (en) | Production plan creation device | |
| JP4149028B2 (en) | Scheduling / arrangement management system | |
| US20080052143A1 (en) | Sales Plan Evaluation Support System | |
| JP5145547B2 (en) | Multi-variety low-volume electronic equipment production support system and multi-product low-volume electronic equipment production support program | |
| US20060129270A1 (en) | Processes and systems for creation of machine control for specialty machines requiring manual input | |
| JP4239767B2 (en) | Design change support system, design change method, design change support program, and recording medium recording the same | |
| JP2005302050A (en) | Scheduling / arrangement management system | |
| JP2007193525A (en) | Traceability information collection method, traceability information collection system, purchased parts information input terminal and product information input terminal | |
| Naples | By the Numbers: Principles of Automotive Parts Management | |
| JP3491558B2 (en) | Alternative lot determination system | |
| JPH03136753A (en) | Automatic system for putting technical change into practice and its method | |
| EP1193630A1 (en) | Agile information system and management method | |
| JPH05181871A (en) | Production planning device | |
| JP3296318B2 (en) | Demand forecasting method, demand forecasting device, and storage medium storing demand forecasting program | |
| US20040122739A1 (en) | Material shortage simulation management system and method | |
| JP7566053B2 (en) | Management system, management method, and program |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20040611 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20040622 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20040823 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20050315 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050513 |
|
| A911 | Transfer to examiner for re-examination before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20050602 |
|
| A912 | Re-examination (zenchi) completed and case transferred to appeal board |
Free format text: JAPANESE INTERMEDIATE CODE: A912 Effective date: 20050722 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080604 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080625 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110704 Year of fee payment: 3 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110704 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120704 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130704 Year of fee payment: 5 |
|
| LAPS | Cancellation because of no payment of annual fees |