JP4158293B2 JP26884799A JP26884799A JP4158293B2 JP 4158293 B2 JP4158293 B2 JP 4158293B2 JP 26884799 A JP26884799 A JP 26884799A JP 26884799 A JP26884799 A JP 26884799A JP 4158293 B2 JP4158293 B2 JP 4158293B2
Authority
JP
Japan
Prior art keywords
lock bolt
carriage
lock
moving body
supply device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP26884799A
Other languages
Japanese (ja)
Other versions
JP2001090494A (en
Inventor
智文 石野
宏明 富松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP26884799A priority Critical patent/JP4158293B2/en
Priority to AU61277/00A priority patent/AU769721B2/en
Publication of JP2001090494A publication Critical patent/JP2001090494A/en
Application granted granted Critical
Publication of JP4158293B2 publication Critical patent/JP4158293B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Automatic Assembly (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、ロックボルトを打設機に供給するロックボルト供給装置に関する。
【0002】
【従来の技術】
炭坑等の坑道では、掘削後の天井部および側壁部(坑道内壁)にロックボルトを打設し、トンネルの崩壊を防ぐ工法が採用されている。従来、ロックボルトを打設するためには、ロックボルトを1本ずつ手作業によって打設機にセットし、ロックボルトの打設を行っていた。
【0003】
【発明が解決しようとする課題】
しかし、この場合、手作業で毎回ロックボルトのセットを行うため効率が悪く、施工速度を上げることが困難であった。また、炭坑の場合、粉炭雰囲気という環境が悪く安全性上も万全とはいい難い場所に常に作業者が付いてロックボルトセット作業をしなければならず、好ましいとはいえない。
【0004】
【課題を解決するための手段】
上記課題を解決すべく創案された本発明は、坑道内壁に打設されるロックボルトを打設機に供給するロックボルト供給装置であって、坑道内に配置された台車と、該台車に設けられロックボルトを坑道内壁に打設する打設機と、該打設機の後方に位置して上記台車に設けられ複数のロックボルトをストックするストック部と、該ストック部のロックボルトを打設機へ移送すべく上記台車に設けられた移送手段とを備え、該移送手段は、上記台車に設けられ前後方向に移動する第1移動体と、該第1移動体に設けられ左右方向に移動する第2移動体と、該第2移動体に設けられロックボルトを把持する把持部とを備えたものである。
【0005】
本発明によれば、ストック部にストックされた複数のロックボルトは、移送手段によって必要本数だけ取り出されて順次打設機に供給される。よって、予めストック部に多量のロックボルトをストックしておくことにより、作業者は打設場所から離れた安全な場所から遠隔操作または自動でロックボルト打設作業を行うことができる。また、作業者が毎回ロックボルトをセットする必要がなくなるため、作業効率が向上して施工の高速化を推進できる。また、打設機とストック部とは、坑道の長手方向に沿って前後に配置されるので、坑道断面積の拡大を招くことはない。
【0006】
上記ストック部に、長いロックボルトと短いロックボルトとが坑道の長手方向に沿って複数ストックされ、上記第2移動体に、長いロックボルトと短いロックボルトとに対応するため、上記把持部が複数夫々坑道の長手方向に移動自在に設けられてもよい。
【0007】
上記台車に、上記ロックボルトが複数載置されたカセット体を、交換可能に取り付けてもよい。
【0008】
【発明の実施の形態】
本発明の実施形態を添付図面に基いて説明する。
【0009】
第1の実施形態に係るロックボルト供給装置を図1乃至図7に示す。
【0010】
このロックボルト供給装置1は、図1および図3に示すように、炭坑等の坑道内に配置された台車2を有する。台車2は、本実施形態では一対のクローラ3を有して自走可能なものであるが、より前方に配置された牽引台車に接続されて牽引されるものであってもよい。台車2の前部には、図5に示すように、ロックボルト4を坑道内壁に打設する打設機5が設けられている。打設機5は、坑道の天井面にロックボルト4aを打設する天井面打設機5aと、坑道の側面にロックボルト4bを打設する側面打設機5bとからなる。
【0011】
天井面打設機5aは、台車2上に載置された位置から前方へ突出するように前後方向に移動自在に設けられ、図6に示すように、台車2の前方へ突出した後に水平軸廻りに90度回動して鉛直状態となるようになっている。天井面打設機5aは、図5および図6に実線で示すように、台車2上に前後方向に沿って載置された状態にてロックボルト4aを受け取り、その後一点鎖線で示すように台車2より前方に移動し、更に二点鎖線で示すように鉛直に立った状態となり、受け取ったロックボルト4aを坑道の天井面に打設するものである。
【0012】
側面打設機5bは、図5および図7に示すように、台車2上に載置された状態から鉛直軸廻りに90度回動するようになっている。側面打設機5bは、図5および図7に実線で示すように台車2上に前後方向に沿って載置された状態にてロックボルト4bを受け取り、その後一点鎖線で示すように90度水平に旋回した状態となり、受け取ったロックボルト4bを坑道の側面に打設するものである。
【0013】
上記台車2上には、打設機5a、5bの後方に位置して、複数のロックボルト4a、4bをストックするストック部6が設けられている。ストック部6には、図1、図3および図5に示すように、天井面に打設される長いロックボルト4aと、側面に打設される短いロックボルト4bとが夫々複数配置されている。各ロックボルト4a、4bには、夫々図示しないナット部が設けられており、後述するカセット体に収容されている(図4参照)。
【0014】
また、ストック部6には、天井面に用いられる長い棒状のケミカルアンカ(ケミカルアンカーは登録商標である)7aと、側面に用いられる短いケミカルアンカ7bとが夫々複数配置されている。各ケミカルアンカ7a、7bも、後述するカセット体に収容されている(図4参照)。各ケミカルアンカ7a、7bは、ソーセージ状の袋内に固着剤が充填されて構成されており、打設機5a、5bによってロックボルト4a、4bを打設する前にその打設穴に押し込まれる。すなわち、各打設機5a、5bは、先ず坑道の天井面または側面に打設穴を形成し、その打設穴にケミカルアンカ7a、7bを押し込み、最後にロックボルト4a、4bを打設する。
【0015】
これらケミカルアンカ7a、7bおよびロックボルト4a、4bは、図4に示すカセット体8に載置されている。カセット体8は、図5に示すロックボルト4a、4bの集合部およびケミカルアンカ7a、7bの集合部ごとに、計8個台車2上に設けられる。カセット体8は、台車2上に前後左右方向に夫々所定間隔を隔てて配置された縦ロッド9と、縦ロッド9に傾動自在に取り付けられた載置台10とを有する。
【0016】
各載置台10には、ケミカルアンカ7またはロックボルト4が、坑道の前後方向に沿って夫々載置される。各載置台10上のケミカルアンカ7またはロックボルト4は、後述する移送手段によって順に上から把持されて引き上げられる。ここで、空になった各載置台10は、それより下方のケミカルアンカ7およびロックボルト4が後述する移送手段によって把持されて持ち上げられるとき、上方の載置台10を跳ね上げるため、ケミカルアンカ7およびロックボルト4の取り出しの邪魔にならない。
【0017】
台車2には、ストック部6のロックボルト4およびケミカルアンカ7を打設機5a、5bへ移送する移送手段11が設けられている。移送手段11は、図1乃至図3に示すように、台車2上に伸縮ロッド12を介して設けられたレールフレーム13に設けられている。レールフレーム13は、台車2の幅方向の左右端部と幅方向の中央部とに、夫々前後方向に沿って形成されている。各レールフレーム13は、横桁14、15によって接続されており、シリンダ16によって昇降されるようになっている。シリンダ16は、坑道の高さに応じて適宜伸縮されると共に、掘削終了後に台車2を坑道内にて後退させるとき伸縮させられ、坑道天井面との間に所定のクリアランスを形成する。
【0018】
各レールフレーム13の下面には、図1および図2に示すようにその長手方向に沿ってガイドレール17が夫々設けられている。各ガイドレール17には、これに沿って移動する第1移動体18が夫々係合されている。第1移動体18aと18b、18cと18dは、ガイドロッド19およびネジロッド20を介して接続されている。よって、第1移動体18a、18bが一体的に移動し、これとは別に第1移動体18c、18dが一体的に移動する。ガイドロッド19およびネジロッド20には、第2移動体21が貫通して設けられている。
【0019】
各第2移動体21は、ネジロッド20をモータ22で回転させることにより、ガイドロッド19に沿って幅方向に移動する。各第2移動体21は、各モータ22によって夫々別々に移動される。第2移動体21(a、b、c、d、i、j、k、l)には、図1および図3に示すように、ロックボルト4a、4bを把持する把持部23が設けられている。ロックボルト用把持部23は、図6および図7に示すように坑道の長手方向に移動自在となっている。天井面用の長いロックボルト4aと、側面用の短いロックボルト4bとに対応するためである。
【0020】
また、別の第2移動体21(e、f、g、h)には、図1および図3に示すように、ケミカルアンカ7a、7bを把持する把持部24が設けられている。ケミカルアンカ用把持部23は、ソーセージ状の袋内に固着剤が充填されてなる軟らかいケミカルアンカ7a、7bを潰さないように、ケミカルアンカ7a、7bとの接触面積を稼ぐように曲面状に形成されたハンド25を有する。
【0021】
また、ケミカルアンカ用把持部24は、図6および図7に示すように、ロックボルト用把持部23より長さが短く設定されている。よって、ケミカルアンカ用把持部24に把持したケミカルアンカ7が、ロックボルト用把持部23に把持したロックボルト4の上方を、幅方向に通過可能となる。
【0022】
以上の構成からなる本実施形態の作用を述べる。
【0023】
天井面用の打設機5aにロックボルト4aおよびケミカルアンカ7aを供給するときには、先ず、天井面用打設機5aを図5および図6に実線で示すように台車2上に引き込んだ状態とする。そして、図1乃至図3に示す第1移動体18をガイドレール17に沿って移動させ、図5に示す天井面用の長いロックボルト4aおよび長いケミカルアンカ7aの上方に位置させる。
【0024】
そして、各第2移動体21を各モータ22によって夫々独立してガイドロッド19に沿って移動させ、ロックボルト用の第2移動体21(a、b、c、d、i、j、k、l)を長いロックボルト4aの上方に位置させ、ケミカルアンカ用の第2移動体21(e、f、g、h)を長いケミカルアンカ7aの上方に位置させる。このとき、長いケミカルアンカ7aは長いロックボルト4aに隣接してその略中央に配置されており、これに合わせてケミカルアンカ用第2移動体21(e、f、g、h)がロックボルト用第2移動体21(a、b、c、d、i、j、k、l)の略中央に配置されているので、ケミカルアンカ用第2移動体21(e、f、g、h)をケミカルアンカ7aの中央部上方に位置させたとき、ロックボルト用第2移動体21(a、b、c、d、i、j、k、l)がロックボルト4aの両端部上方に位置することになる。
【0025】
そして、ケミカルアンカ用第2移動体21(e、f、g、h)に設けられたケミカルアンカ用把持部24を図示しない昇降機構によって下降させてこれに長いケミカルアンカ7aの略中央部を把持し、ロックボルト用第2移動体21(a、b、c、d、i、j、k、l)に設けられたロックボルト用把持部23を図示しない昇降機構によって下降させてこれに長いロックボルト4aの両端部を把持する。そして、各ケミカルアンカ用把持部24およびロックボルト用把持部23を図示しない昇降機構によって上昇させ、図4に示すカセット体8から夫々長いロックボルト4aおよびケミカルアンカ7aを取り出す。
【0026】
その後、図6に示すように、第1移動体18をガイドレール17に沿って前方へ移動させると共に第2移動体21を幅方向に適宜移動させ、把持した長いロックボルト4aおよびケミカルアンカ7aを天井面用打設機5aに夫々装着する。このとき、4個の天井面用打設機5aに対して、4本のケミカルアンカ7aおよび4本のロックボルト4aを供給できるので、各打設機5aに夫々ロックボルト4aおよびケミカルアンカ7aを1本ずつ一度に供給できる。
【0027】
他方、側面用の打設機5bにロックボルト4bおよびケミカルアンカ7bを供給するときには、先ず、側面用打設機5bを図5および図7に実線で示すように台車5b上に引き込んだ状態とする。このとき、天井面用打設機5aは、側面用打設機5bと干渉しないように前方に突出させておく。そして、以降は天井面用打設機5aと同様の手順によって、側面用の短いロックボルト4bおよびケミカルアンカ7bを側面用打設機5bに供給する。ここで、ロックボルト用把持部23は、第2移動体21に対して前後方向に近接するように移動され、その間隔が狭められる(図6参照)。短いロックボルト4bを空振りしないようにバランスよく把持するためである。
【0028】
以上説明したように、本実施形態によれば、ストック部6にストックされた複数のロックボルト4およびケミカルアンカ7は、移送手段11によって必要本数だけ取り出されて順次各打設機5に供給される。よって、予めストック部6に多量のロックボルト4をストックしておくことにより、作業者は打設場所から離れた安全な場所から遠隔操作または自動でロックボルト打設作業を行うことができる。打設場所は、粉炭雰囲気であって環境が悪くしかも坑道天盤崩落の可能性もあり安全性上も万全とはいい難いため、このような場所で作業員が作業することはなるべく避けるべきである。
【0029】
また、作業者が毎回ロックボルト4を打設機5にセットする必要がなくなるため、作業効率が向上して施工の高速化を推進できる。台車2上のカセット体8からロックボルト4またはケミカルアンカ7が無くなったなら、空になったカセット体8をロックボルト4またはケミカルアンカ7が収容された新たなカセット体8と交換する。このようにカセット体8を交換することにより、作業効率が更に向上する。
【0030】
また、打設機5とストック部6とは、坑道の長手方向に沿って前後に配置されるので、坑道断面積の拡大を招くことはない。すなわち、ストック部6から打設機5までのロックボルト4およびケミカルアンカ7の移動の手間を考えれば、打設機5の出来るだけ近くにストック部6を配置するのが好ましいわけであるが、仮に坑道の上下方向に重ねて打設機5とストック部6とを配置したり、坑道の幅方向に隣接させて打設機5とストック部6とを配置したりすると、坑道断面積が大きくなってしまうのである。よって、本実施形態では、打設機5の前投影面積に重なるようにストック部6を配置し、坑道断面積の拡大を回避したのである。
【0031】
ところで、上記実施形態においては、図2に示すように、各レールフレーム17の前端部を接続するように横桁14が掛け渡されているため、その横桁14との干渉を避けるべく、天井面用の打設機5aを図5および図6に示すように一旦完全に台車2より前方に飛び出た状態とし、その後90度回動させる必要がある。このため天井面用の打設機5aの移動機構が複雑化し易い。これを鑑みて改良されたものが図8乃至図10に示す第2の実施形態に係るロックボルト供給装置1aである。
【0032】
図示するように、このロックボルト供給装置1aは、台車2上にガイドレール26を敷設し、そのガイドレール26に台車2を移動自在に載置したものである。この構成によれば、前述の横桁14(図2参照)が存在しないので、図8に示すように、天井面用打設機5aを半分程度台車2から飛び出た状態で90度回動させるようにしても、打設機5aが横桁14と干渉することはなく、天井面用の打設機5aの移動機構を単純化できる。
【0033】
なお、前実施形態と同様の構成要素には同一の符号を付して説明を省略する。ガイドレール26は、台車2の幅方向の両端部に敷設される。ガイドレール26には、第1移動体18が係合される。第1移動体18には、伸縮ロッド12を介してフレーム27が設けられている。フレーム27と第1移動体18との間には、シリンダ16およびリンク28が介設されている。リンク28は、シリンダ16を収縮させるときには取り外される。
【0034】
左右の各フレーム27、27は、横桁29によって接続されている。左右の各フレーム27、27の間には、ガイドロッド19およびネジロッド20が掛け渡されている。ガイドロッド19およびネジロッド20には、第2移動体21が設けられている。第2移動体21には、ロックボルト用の把持部23と、ケミカルアンカ用の把持部24とが設けられている。
【0035】
【発明の効果】
以上説明したように本発明に係るロックボルト供給装置によれば、次のような優れた効果を発揮できる。
【0036】
(1)作業者は打設場所から離れた安全な場所から遠隔操作または自動でロックボルト打設作業を行うことができる。
【0037】
(2)作業者が毎回ロックボルトをセットする必要がなくなるため、作業効率が向上して施工の高速化を推進できる。
【0038】
(3)打設機とストック部とは、坑道の長手方向に沿って前後に配置されるので、坑道断面積の拡大を招くことはない。
【図面の簡単な説明】
【図1】本発明の一実施形態に係るロックボルト供給装置の側面図である。
【図2】図1の II-II線断面図である。
【図3】上記ロックボルト供給装置の正面図である。
【図4】ストック部の拡大図である。
【図5】上記ロックボルト供給装置の透視平面図である。
【図6】上記ロックボルト供給装置の作用を示す側面図である。
【図7】上記ロックボルト供給装置の作用を示す側面図である。
【図8】別の実施形態を示すロックボルト供給装置の側面図である。
【図9】上記ロックボルト供給装置の平面図である。
【図10】上記ロックボルト供給装置の正面図である。
【符号の説明】
1 ロックボルト供給装置
2 台車
4 ロックボルト
5 打設機
6 ストック部
7 ケミカルアンカ
11 移送手段
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a lock bolt supply device that supplies a lock bolt to a driving machine.
[0002]
[Prior art]
In a mine such as a coal mine, a construction method is employed in which rock bolts are placed on the ceiling and side walls (the inner wall of the mine) after excavation to prevent the tunnel from collapsing. Conventionally, in order to drive the lock bolts, the lock bolts are manually set on the driving machine one by one and the lock bolts are driven.
[0003]
[Problems to be solved by the invention]
However, in this case, since the lock bolt is set manually every time, the efficiency is poor and it is difficult to increase the construction speed. Further, in the case of a coal mine, it is not preferable because a rock bolt setting work must always be performed with an operator attached to a place where the environment of pulverized coal is bad and safety is not perfect.
[0004]
[Means for Solving the Problems]
The present invention devised to solve the above problems is a lock bolt supply device for supplying a lock bolt to be placed on the inner wall of a tunnel to a driving machine, and a carriage disposed in the tunnel, and provided on the carriage A driving machine for driving the lock bolt on the inner wall of the mine shaft, a stock part provided behind the driving machine and stocked with the plurality of lock bolts, and a lock bolt for the stock part A transfer means provided on the carriage for transfer to a machine, the transfer means provided on the carriage for moving in the front-rear direction, and provided in the first mover for moving in the left-right direction. And a gripping portion that is provided on the second moving body and grips a lock bolt .
[0005]
According to the present invention, the required number of the plurality of lock bolts stocked in the stock section is taken out by the transfer means and sequentially supplied to the placing machine. Therefore, by storing a large amount of lock bolts in advance in the stock section, the operator can perform a lock bolt driving operation remotely or automatically from a safe place away from the driving site. Further, since it is not necessary for the operator to set the lock bolt every time, the work efficiency can be improved and the construction can be accelerated. Moreover, since a driving machine and a stock part are arrange | positioned back and forth along the longitudinal direction of a mine shaft, the expansion of a mine cross-sectional area is not caused.
[0006]
In the stock part, a plurality of long lock bolts and short lock bolts are stocked along the longitudinal direction of the mine shaft, and the second moving body corresponds to a long lock bolt and a short lock bolt. Each may be provided so as to be movable in the longitudinal direction of the mine shaft .
[0007]
A cassette body on which a plurality of the lock bolts are placed may be attached to the carriage in a replaceable manner .
[0008]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described with reference to the accompanying drawings.
[0009]
A lock bolt supply device according to a first embodiment is shown in FIGS.
[0010]
As shown in FIGS. 1 and 3, the lock bolt supply device 1 has a carriage 2 arranged in a mine shaft such as a coal mine. In this embodiment, the carriage 2 has a pair of crawlers 3 and can be self-propelled. However, the carriage 2 may be towed by being connected to a towing carriage arranged further forward. As shown in FIG. 5, a placing machine 5 for placing the lock bolt 4 on the inner wall of the tunnel is provided at the front portion of the carriage 2. The placing machine 5 includes a ceiling surface placing machine 5a for placing a lock bolt 4a on a ceiling surface of a mine shaft, and a side surface placing machine 5b for placing a lock bolt 4b on a side surface of the mine shaft.
[0011]
The ceiling surface placing machine 5a is provided so as to be movable in the front-rear direction so as to protrude forward from a position placed on the carriage 2, and as shown in FIG. It rotates 90 degrees around and is in a vertical state. As shown by solid lines in FIGS. 5 and 6, the ceiling surface placing machine 5 a receives the lock bolt 4 a while being placed on the carriage 2 along the front-rear direction, and then, as shown by the one-dot chain line, It moves forward from 2 and stands in a vertical position as indicated by a two-dot chain line, and the received lock bolt 4a is driven on the ceiling surface of the tunnel.
[0012]
As shown in FIGS. 5 and 7, the side surface placing machine 5 b is rotated 90 degrees around the vertical axis from the state of being placed on the carriage 2. The side surface placing machine 5b receives the lock bolt 4b while being placed on the carriage 2 along the front-rear direction as shown by solid lines in FIGS. 5 and 7, and then horizontally 90 degrees as shown by the one-dot chain line. And the received lock bolt 4b is driven on the side of the mine shaft.
[0013]
On the carriage 2, a stock portion 6 is provided, which is located behind the placing machines 5a and 5b and stocks a plurality of lock bolts 4a and 4b. As shown in FIGS. 1, 3, and 5, a plurality of long lock bolts 4a that are driven on the ceiling surface and a plurality of short lock bolts 4b that are driven on the side surfaces are arranged on the stock portion 6, respectively. . Each of the lock bolts 4a and 4b is provided with a nut portion (not shown) and is accommodated in a cassette body described later (see FIG. 4).
[0014]
The stock section 6 is provided with a plurality of long bar-shaped chemical anchors (chemical anchor is a registered trademark) 7a used for the ceiling surface and a plurality of short chemical anchors 7b used for the side surfaces. Each chemical anchor 7a, 7b is also accommodated in a cassette body described later (see FIG. 4). Each chemical anchor 7a, 7b is configured by filling a sausage-like bag with a sticking agent, and is pushed into the placement hole before the lock bolts 4a, 4b are placed by the placement machines 5a, 5b. . That is, each driving machine 5a, 5b first forms a driving hole on the ceiling surface or side surface of the mine shaft, pushes the chemical anchors 7a, 7b into the driving hole, and finally drives the lock bolts 4a, 4b. .
[0015]
These chemical anchors 7a and 7b and the lock bolts 4a and 4b are placed on the cassette body 8 shown in FIG. The cassette body 8 is provided on a total of eight carts 2 for each of the aggregate portions of the lock bolts 4a and 4b and the aggregate portions of the chemical anchors 7a and 7b shown in FIG. The cassette body 8 includes a vertical rod 9 disposed on the carriage 2 in the front-rear and left-right directions at predetermined intervals, and a mounting table 10 attached to the vertical rod 9 so as to be tiltable.
[0016]
A chemical anchor 7 or a lock bolt 4 is placed on each mounting table 10 along the longitudinal direction of the tunnel. The chemical anchors 7 or the lock bolts 4 on each mounting table 10 are sequentially gripped and pulled up from above by transfer means described later. Here, each empty mounting table 10 raises the upper mounting table 10 when the lower chemical anchor 7 and the lock bolt 4 are gripped and lifted by transfer means described later. And it does not interfere with the removal of the lock bolt 4.
[0017]
The carriage 2 is provided with transfer means 11 for transferring the lock bolt 4 and the chemical anchor 7 of the stock unit 6 to the placing machines 5a and 5b. As shown in FIGS. 1 to 3, the transfer means 11 is provided on a rail frame 13 provided on the carriage 2 via an extendable rod 12. The rail frame 13 is formed along the front-rear direction at the left and right end portions in the width direction of the carriage 2 and the center portion in the width direction, respectively. Each rail frame 13 is connected by horizontal beams 14 and 15, and is moved up and down by a cylinder 16. The cylinder 16 is appropriately expanded and contracted according to the height of the mine shaft, and is expanded and contracted when the carriage 2 is retracted in the mine shaft after excavation, thereby forming a predetermined clearance with the mine ceiling surface.
[0018]
As shown in FIGS. 1 and 2, guide rails 17 are provided on the lower surface of each rail frame 13 along the longitudinal direction thereof. A first moving body 18 that moves along each guide rail 17 is engaged with each guide rail 17. The first moving bodies 18a and 18b, 18c and 18d are connected via a guide rod 19 and a screw rod 20. Accordingly, the first moving bodies 18a and 18b move integrally, and separately from this, the first moving bodies 18c and 18d move integrally. The guide rod 19 and the screw rod 20 are provided with a second moving body 21 therethrough.
[0019]
Each second moving body 21 moves in the width direction along the guide rod 19 by rotating the screw rod 20 with the motor 22. Each second moving body 21 is moved separately by each motor 22. As shown in FIGS. 1 and 3, the second moving body 21 (a, b, c, d, i, j, k, l) is provided with a gripping portion 23 for gripping the lock bolts 4a and 4b. Yes. The lock bolt gripping portion 23 is movable in the longitudinal direction of the tunnel as shown in FIGS. This is to cope with the long lock bolt 4a for the ceiling surface and the short lock bolt 4b for the side surface.
[0020]
Further, as shown in FIGS. 1 and 3, another second moving body 21 (e, f, g, h) is provided with a gripping portion 24 that grips the chemical anchors 7a, 7b. The chemical anchor grip 23 is formed in a curved surface so as to increase the contact area with the chemical anchors 7a and 7b so as not to crush the soft chemical anchors 7a and 7b formed by filling the sausage-shaped bag with the fixing agent. Hand 25 is provided.
[0021]
Further, as shown in FIGS. 6 and 7, the chemical anchor gripping portion 24 is set to be shorter than the lock bolt gripping portion 23. Therefore, the chemical anchor 7 gripped by the chemical anchor gripping portion 24 can pass in the width direction above the lock bolt 4 gripped by the lock bolt gripping portion 23.
[0022]
The operation of the present embodiment having the above configuration will be described.
[0023]
When the lock bolt 4a and the chemical anchor 7a are supplied to the ceiling surface placing machine 5a, first, the ceiling surface placing machine 5a is drawn onto the carriage 2 as shown by the solid lines in FIGS. To do. Then, the first moving body 18 shown in FIGS. 1 to 3 is moved along the guide rail 17 and positioned above the long lock bolt 4a for the ceiling surface and the long chemical anchor 7a shown in FIG.
[0024]
And each 2nd moving body 21 is independently moved along the guide rod 19 by each motor 22, respectively, and the 2nd moving body 21 for lock bolts (a, b, c, d, i, j, k, l) is positioned above the long lock bolt 4a, and the second movable body 21 (e, f, g, h) for chemical anchor is positioned above the long chemical anchor 7a. At this time, the long chemical anchor 7a is arranged in the approximate center adjacent to the long lock bolt 4a, and the second chemical anchor moving body 21 (e, f, g, h) is used for the lock bolt accordingly. Since the second moving body 21 (a, b, c, d, i, j, k, l) is arranged at the approximate center, the second moving body 21 for chemical anchor (e, f, g, h) When the chemical anchor 7a is positioned above the central portion, the second movable body 21 (a, b, c, d, i, j, k, l) for the lock bolt is positioned above both ends of the lock bolt 4a. become.
[0025]
Then, the chemical anchor holding portion 24 provided on the second chemical anchor moving body 21 (e, f, g, h) is lowered by a lifting mechanism (not shown) to hold the substantially central portion of the long chemical anchor 7a. Then, the lock bolt gripping portion 23 provided on the second moving body 21 for lock bolt (a, b, c, d, i, j, k, l) is lowered by an elevating mechanism (not shown) to lock it long. Hold both ends of the bolt 4a. Then, each chemical anchor gripping portion 24 and the lock bolt gripping portion 23 are raised by a lifting mechanism (not shown), and the long lock bolt 4a and the chemical anchor 7a are taken out from the cassette body 8 shown in FIG.
[0026]
Thereafter, as shown in FIG. 6, the first moving body 18 is moved forward along the guide rail 17 and the second moving body 21 is appropriately moved in the width direction, and the long lock bolt 4 a and the chemical anchor 7 a thus grasped are moved. Each is mounted on the ceiling surface placing machine 5a. At this time, since four chemical anchors 7a and four lock bolts 4a can be supplied to the four ceiling surface placing machines 5a, each of the placing machines 5a is provided with a lock bolt 4a and a chemical anchor 7a, respectively. Can be supplied one at a time.
[0027]
On the other hand, when supplying the lock bolt 4b and the chemical anchor 7b to the side placing machine 5b, first, the side placing machine 5b is drawn into the carriage 5b as shown by the solid line in FIGS. To do. At this time, the ceiling surface placing machine 5a is projected forward so as not to interfere with the side surface placing machine 5b. Thereafter, the short side lock bolt 4b and the chemical anchor 7b are supplied to the side surface placing machine 5b by the same procedure as the ceiling surface placement machine 5a. Here, the holding part 23 for lock bolts is moved so that it may adjoin to the 2nd moving body 21 in the front-back direction, and the space | interval is narrowed (refer FIG. 6). This is because the short lock bolt 4b is gripped with a good balance so as not to be swung.
[0028]
As described above, according to the present embodiment, the plurality of rock bolts 4 and chemical anchors 7 stocked in the stock unit 6 are taken out by the transfer means 11 in a necessary number and are sequentially supplied to the driving machines 5. The Therefore, by storing a large amount of the lock bolts 4 in the stock unit 6 in advance, the operator can perform a lock bolt driving operation remotely or automatically from a safe place away from the driving site. The placement site is a pulverized coal atmosphere, the environment is bad, there is a possibility that the mine roof will collapse, and it is difficult to ensure safety. Therefore, workers should avoid working in such places as much as possible. is there.
[0029]
Further, since it is not necessary for the operator to set the lock bolt 4 on the driving machine 5 every time, the work efficiency can be improved and the construction can be accelerated. When the lock bolt 4 or the chemical anchor 7 disappears from the cassette body 8 on the carriage 2, the emptied cassette body 8 is replaced with a new cassette body 8 in which the lock bolt 4 or the chemical anchor 7 is accommodated. By exchanging the cassette body 8 in this way, the work efficiency is further improved.
[0030]
Moreover, since the driving machine 5 and the stock part 6 are arrange | positioned back and forth along the longitudinal direction of a mine shaft, the expansion of a mine cross-sectional area is not caused. That is, considering the trouble of moving the lock bolt 4 and the chemical anchor 7 from the stock unit 6 to the placement machine 5, it is preferable to arrange the stock unit 6 as close as possible to the placement machine 5. If the driving machine 5 and the stock part 6 are arranged in the vertical direction of the tunnel, or if the driving machine 5 and the stock part 6 are arranged adjacent to each other in the width direction of the tunnel, the cross-sectional area of the tunnel becomes large. It will end up. Therefore, in the present embodiment, the stock portion 6 is disposed so as to overlap with the front projection area of the driving machine 5, and the enlargement of the cross-sectional area of the tunnel is avoided.
[0031]
In the above embodiment, as shown in FIG. 2, since the cross beam 14 is spanned so as to connect the front end portions of the rail frames 17, the ceiling is used to avoid interference with the cross beam 14. As shown in FIGS. 5 and 6, it is necessary that the surface placing machine 5 a is once completely projected forward from the carriage 2 and then rotated 90 degrees. For this reason, the moving mechanism of the ceiling surface placing machine 5a is likely to be complicated. The thing improved in view of this is the lock bolt supply apparatus 1a which concerns on 2nd Embodiment shown in FIG. 8 thru | or FIG.
[0032]
As shown in the figure, the lock bolt supply device 1 a is configured such that a guide rail 26 is laid on a carriage 2 and the carriage 2 is movably mounted on the guide rail 26. According to this configuration, since the above-mentioned cross beam 14 (see FIG. 2) does not exist, as shown in FIG. 8, the ceiling surface placing machine 5a is rotated 90 degrees in a state of jumping out from the carriage 2 by about half. Even if it does in this way, the driving machine 5a does not interfere with the cross beam 14, and the moving mechanism of the driving machine 5a for the ceiling surface can be simplified.
[0033]
In addition, the same code | symbol is attached | subjected to the component similar to previous embodiment, and description is abbreviate | omitted. The guide rails 26 are laid at both ends in the width direction of the carriage 2. The first moving body 18 is engaged with the guide rail 26. A frame 27 is provided on the first moving body 18 via the telescopic rod 12. The cylinder 16 and the link 28 are interposed between the frame 27 and the first moving body 18. The link 28 is removed when the cylinder 16 is contracted.
[0034]
The left and right frames 27 and 27 are connected by a horizontal beam 29. A guide rod 19 and a screw rod 20 are spanned between the left and right frames 27 and 27. A second moving body 21 is provided on the guide rod 19 and the screw rod 20. The second moving body 21 is provided with a gripping portion 23 for a lock bolt and a gripping portion 24 for a chemical anchor.
[0035]
【The invention's effect】
As described above, according to the lock bolt supply device of the present invention, the following excellent effects can be exhibited.
[0036]
(1) An operator can perform a rock bolt driving operation remotely or automatically from a safe place away from the driving site.
[0037]
(2) Since it is not necessary for the operator to set the lock bolt every time, the work efficiency is improved and the construction can be accelerated.
[0038]
(3) Since the driving machine and the stock portion are arranged back and forth along the longitudinal direction of the tunnel, there is no increase in the cross-sectional area of the tunnel.
[Brief description of the drawings]
FIG. 1 is a side view of a lock bolt supply device according to an embodiment of the present invention.
2 is a cross-sectional view taken along line II-II in FIG.
FIG. 3 is a front view of the lock bolt supply device.
FIG. 4 is an enlarged view of a stock portion.
FIG. 5 is a perspective plan view of the lock bolt supply device.
FIG. 6 is a side view showing the operation of the lock bolt supply device.
FIG. 7 is a side view showing the operation of the lock bolt supply device.
FIG. 8 is a side view of a lock bolt supply device showing another embodiment.
FIG. 9 is a plan view of the lock bolt supply device.
FIG. 10 is a front view of the lock bolt supply device.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Rock bolt supply apparatus 2 Carriage 4 Rock bolt 5 Placing machine 6 Stock part 7 Chemical anchor 11 Transfer means

Claims (3)

坑道内壁に打設されるロックボルトを打設機に供給するロックボルト供給装置であって、
坑道内に配置された台車と、該台車に設けられロックボルトを坑道内壁に打設する打設機と、該打設機の後方に位置して上記台車に設けられ複数のロックボルトをストックするストック部と、該ストック部のロックボルトを打設機へ移送すべく上記台車に設けられた移送手段とを備え
該移送手段は、上記台車に設けられ前後方向に移動する第1移動体と、該第1移動体に設けられ左右方向に移動する第2移動体と、該第2移動体に設けられロックボルトを把持する把持部とを備えたことを特徴とするロックボルト供給装置。
A lock bolt supply device that supplies a lock bolt to be driven to the inner wall of a tunnel to a driving machine,
A cart disposed in the tunnel, a driving machine provided on the carriage for driving a lock bolt on the inner wall of the tunnel, and a plurality of lock bolts provided on the carriage located behind the driving machine and stocked comprising a stock unit, and a transfer means provided in the carriage in order to transfer the lock bolt of the stock unit to hit 設機,
The transfer means includes a first moving body provided in the carriage and moving in the front-rear direction, a second moving body provided in the first moving body and moving in the left-right direction, and a lock bolt provided in the second moving body. A lock bolt supply device comprising: a grip portion for gripping the handle .
上記ストック部に、長いロックボルトと短いロックボルトとが坑道の長手方向に沿って複数ストックされ、
上記第2移動体に、長いロックボルトと短いロックボルトとに対応するため、上記把持部が複数夫々坑道の長手方向に移動自在に設けられた
請求項1記載のロックボルト供給装置。
In the stock part, a plurality of long lock bolts and short lock bolts are stocked along the longitudinal direction of the tunnel,
2. The lock bolt supply device according to claim 1 , wherein the second moving body is provided with a plurality of gripping portions movably in the longitudinal direction of the mine shaft in order to correspond to a long lock bolt and a short lock bolt .
上記台車に、上記ロックボルトが複数載置されたカセット体を、交換可能に取り付けた
請求項1又は2に記載のロックボルト供給装置。
The lock bolt supply device according to claim 1 or 2, wherein a cassette body on which a plurality of the lock bolts are mounted is attached to the carriage in a replaceable manner .
JP26884799A 1999-09-22 1999-09-22 Lock bolt supply device Expired - Fee Related JP4158293B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP26884799A JP4158293B2 (en) 1999-09-22 1999-09-22 Lock bolt supply device
AU61277/00A AU769721B2 (en) 1999-09-22 2000-09-21 Arrangement for supplying rock bolt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26884799A JP4158293B2 (en) 1999-09-22 1999-09-22 Lock bolt supply device

Publications (2)

Publication Number Publication Date
JP2001090494A JP2001090494A (en) 2001-04-03
JP4158293B2 true JP4158293B2 (en) 2008-10-01

Family

ID=17464104

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26884799A Expired - Fee Related JP4158293B2 (en) 1999-09-22 1999-09-22 Lock bolt supply device

Country Status (1)

Country Link
JP (1) JP4158293B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109483214B (en) * 2018-12-25 2023-09-08 三门核电有限公司 Main bolt pair dismounting tool for reactor pressure vessel

Also Published As

Publication number Publication date
JP2001090494A (en) 2001-04-03

Similar Documents

Publication Publication Date Title
CN115217502B (en) Airborne support system, heading machine and heading support operation method
AU761775B2 (en) Three dimensional multi-phase tunneling method and equipments thereof
US8485608B2 (en) Heading or extraction machine
US3346300A (en) Blast furnace lining removing machine
JP7248535B2 (en) Rock bolt driving method, rock bolt driving device, and rock bolt driving work vehicle provided with the same
JP2017089150A (en) Boring robot
WO2017115240A1 (en) Apparatus and method for production of holes for mounting of equipment elements on tunnel walls
JP4158293B2 (en) Lock bolt supply device
JPH08254099A (en) Working device in tunnel
JP3355235B2 (en) Tunnel construction method and device
CN120042618A (en) Multifunctional integrated unit
KR100351270B1 (en) 3 dimensional multi phase tunneling mathod and apparatus corresponding same
JP2008248604A (en) Method of advancing shield machine and shield machine
JP4120742B2 (en) Lock bolt supply device
CN117588226A (en) Double-drill-arm tunneling and anchoring integrated machine
US4861112A (en) Apparatus for cleaning aluminum cells
JP7413173B2 (en) Rock bolt driving vehicle and rock bolt driving method
JP3760311B2 (en) Tunnel excavator
JP3803161B2 (en) The posture changing mechanism of the volta head of the rock bolt driving machine
JP3844166B2 (en) Slope drilling machine and slope drilling method
JP2021195819A (en) Rock bolt placing vehicle and method of placing rock bolt
JP2588458Y2 (en) Segment installation equipment
JP4034442B2 (en) Electa interlocking segment assembly scaffold
RU2819392C1 (en) Complex for drilling wells in rocks
JP2020143561A (en) Work vehicle for rock bolt placement

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060824

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080402

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080516

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080624

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080707

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110725

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110725

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120725

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120725

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120725

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees