JP4182201B2 - Coating block installation method and apparatus - Google Patents
[go: Go Back, main page]

JP4182201B2 - Coating block installation method and apparatus - Google Patents

Coating block installation method and apparatus Download PDF

Info

Publication number
JP4182201B2
JP4182201B2 JP2002218466A JP2002218466A JP4182201B2 JP 4182201 B2 JP4182201 B2 JP 4182201B2 JP 2002218466 A JP2002218466 A JP 2002218466A JP 2002218466 A JP2002218466 A JP 2002218466A JP 4182201 B2 JP4182201 B2 JP 4182201B2
Authority
JP
Japan
Prior art keywords
covering
ship
rings
block
blocks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002218466A
Other languages
Japanese (ja)
Other versions
JP2004059207A (en
Inventor
満 佐々木
弘直 大橋
公一 村上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toa Corp
Original Assignee
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toa Corp filed Critical Toa Corp
Priority to JP2002218466A priority Critical patent/JP4182201B2/en
Publication of JP2004059207A publication Critical patent/JP2004059207A/en
Application granted granted Critical
Publication of JP4182201B2 publication Critical patent/JP4182201B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、主に捨石マウンドの被覆法面上に被覆ブロックを据付ける際に、複数の被覆ブロックを同時に据付けが可能な被覆ブロックの据付方法およびその装置に関する。
【0002】
【従来の技術】
従来、図11に示すごとき水中構築物の捨石マウンド1の法面等の上に、例えばテトラポット(登録商標)のごとき被覆ブロック2を据付ける際には、図12の施工フローに示すように、図11において、クレーン船3の船上に被覆ブロック2を積込み、海上を据付位置まで運搬し、船上のクレーン4により被覆ブロック2を1個ずつ玉掛けし、吊り込みを行ない、潜水士船5からサポートされた潜水士6が指示を出して所定の据付位置に誘導した後、被覆ブロック2を着底させ据付けし、潜水士6により玉掛けワイヤーを外す作業を行ない、このサイクルを繰り返し据付作業を行なっていた。
【0003】
しかしながら、上記従来の方法では、被覆ブロック2を1個ずつ玉掛けし、所定位置に据付けるサイクルを繰り返し行なっているため、作業時間及び工費がかさむと共に、作業の安全性の面でも問題が多かった。
【0004】
【発明が解決しようとする課題】
本発明は、被覆ブロックの据付において、例えば2層積みの被覆ブロックの内の少なくとも1層目のブロックの据付時において、複数の被覆ブロックを同時に据付け可能とすることで、被覆ブロック据付時の工費節減と施工能率向上をはかると共に、作業の安全性の向上を図り得る被覆ブロックの据付方法及び装置を提供する。
【0005】
【課題を解決するための手段】
本発明は、複数の被覆ブロックを船上の所定位置に並べて積込んだクレーン船を据付け場所に運搬し、据付ける複数の被覆ブロックの各先端部に装着可能な複数のリングからなる吊り治具にて玉掛けを行い、所定の据付け位置にクレーンにより吊り込み据付けの後、玉掛け外しを行い、吊り治具を船上に引上げ、その吊り治具にて船上の複数の被覆ブロックの玉掛けを行う被覆ブロックの据付方法において、据付ける複数の被覆ブロックの各先端部に装着可能な複数のリングからなる吊り治具にて玉掛けを行なう際に、複数のリング下部周面にそれぞれ突設した長さの異なる装着ガイドを、長さの長い方から順次被覆ブロックに装着する被覆ブロックの据付方法からなる。
【0006】
さらに、上記の据付方法に適用される本発明の据付装置は、クレーン船の船上に装備されたクレーンと、その船上に並べられた複数の被覆ブロックの各先端部に装着可能な複数のリングからなる玉掛け用の吊り治具と、被覆ブロックの据付後に吊り治具を引上げ可能な玉掛け外し具とからなる被覆ブロックの据付装置において、吊り治具の複数のリングの下部周面のそれぞれに、長さの異なる装着ガイドが突出して設けられている被覆ブロックの据付装置からなる。
【0007】
【発明の実施の形態】
以下図面を参照して本発明の被覆ブロックの据付方法およびその装置の一実施形態につき説明する。
【0008】
まず、図1は本発明の据付方法により捨石マウンド1の法面上に複数個、例えばこの実施形態では3個の被覆ブロック2を据付ける状況を示しており、図11の従来例とそれぞれ同じ部品は同じ符号で示しているが、この実施形態においては、図2の施工フロー図に示しているように、まずクレーン船3の船上に被覆ブロック2を積み込む際に、複数個(本実施形態では3個で説明する)を所定の幅に並べて積み込み、積込み完了後、海上運搬を行ない、船上において図3のごとく据付ける3個の被覆ブロック2に対して、それぞれの先端部に装着可能な図4の平面図で示すようなリング7からなる吊り治具によりそれぞれの被覆ブロック2の玉掛けを行なう。
【0009】
ここで、上記3個の被覆ブロック2の各上方先端部に装着される3個のリング7は、各リング7の下部周面にそれぞれ図5、図6および図7のごとく複数の装着ガイド10が突出して設けられており、これらの装着ガイド10は、それぞれの長さが異なって設けられており、図5は図3の左側のリング7を示し、図6は図3の中央部のリング7を示し、そして図7は図3の右側のリングを示しており、図5のリング7に比べ図6のリング7はその装着ガイド10の長さが短くなっており、図7のリング7は装着ガイド10がさらに短くなっており、例えば図7のごとく装着ガイド10がない場合でもよい。。
【0010】
これら3個の被覆ブロック2に対し、上記の3個のリング7等からなる吊り治具にて玉掛けを行なう状態を、図10に示しており、図1のクレーン4の主巻きフック11からの吊りワイヤーを図8で示す角パイプコラム12の吊ジグを介して図4の吊りピース17で各リング7を同時に吊りながら、図5のリング7、図6のリング7、そして図7のリング7の順序で長さの長い装着ガイド10付きのリング7から長さの短い装着リング10付きのリング7への順序、即ち図3の左側から右側へと順次各リング7を被覆ブロック2に装着し、それぞれの被覆ブロック2に対してそれぞれ玉掛けワイヤーを掛けて玉掛けする。
【0011】
この場合、3個のリング7の各装着ガイド10の長さが異なっており、長さの長い方から順次被覆ブロック2にリング7を装着することにより、その玉掛け作業が容易になり、例えば1人または2人で3個の玉掛け作業を行なう場合、まず図10の左側のリング7の装着ガイド10の下端が被覆ブロック2の先端で保持され、次に中央のリング7の装着ガイド10の下端が左側より高い位置で保持され、最後に右側のリング7が被覆ブロック2の先端に装着されるので、3個の玉掛け作業を円滑にかつ少ない人員で能率良く行なうことができ、しかも安全な玉掛けができる。
【0012】
なお、上記のごとく各被覆ブロック2を1個ずつ玉掛け時には、図9に示すごとく玉掛けワイヤー16の端部に玉掛け外し具13を介在させて行なうが、玉掛け外し具13のレバー20を玉掛け解除ロープ15で図10に示すクレーン5の補巻きフック14により図9の矢印U方向に引き上げることにより、玉掛け外しが自動的にできるようになっており、この玉掛け解除ロープ15は図4のリング7に設けられた解除ロープ通し口18内を遊貫して引き上げられるようになっている。
【0013】
また、この実施形態に示した玉掛け外し具13は玉掛け解除ロープ15を引き上げることで自動的に玉掛け外しができるようになっているが、この玉掛け外し具13に限定するものではなく、どのような玉掛け外し装置を使用してもよい。
【0014】
さらに3個の被覆ブロック2は図3で並べられた状態で各リング7の外周に設けた連結ワイヤー取付部9を介して連結ワイヤー8を、図3に示すように3個の被覆ブロック2のまわりをまわしてその両端部を止めることで、3個の被覆ブロックの回転を防止するようにしている。
【0015】
次に、図12の施工フロー図に示すように、専用の吊り治具を介して玉掛けした3個の被覆ブロック2を図3の状態に組み付けた状態でクレーン5の主巻きフック11により、各リング7の吊ピース17を介して吊り込み、所定の据付位置に誘導し、据付けを行ない、潜水士6が被覆ブロック2の方向と位置を確認の後、玉掛け解除ロープ15を引き上げることにより、玉掛け外しを行い、リング7等の吊り治具を船上に引き上げる。
【0016】
その後、引き上げた吊り治具により、船上の次に据付ける3個の被覆ブロック2の玉掛けを行なう以降の操作を順次繰り返して、捨石マウンド1の所定の位置上に被覆ブロック2の据付けを行なう。
【0017】
以上に説明した本発明の据付方法およびその装置を採用することにより、複数個の被覆ブロック2を各突起状部を喰み合わせた状態で並べて船上に並べておき、複数のリング7や連結ワイヤー8により複数のグループを一体化して玉掛けし、同時に据付けすることで施工効率を高めることを特徴としているが、複数の被覆ブロック2の玉掛けに使用する吊り治具の複数のリング7の下部周面にそれぞれ設けた装着ガイド10の長さを変化させているので、複数の被覆ブロック2の先端にリングを順次装着する作業を容易にできることも本発明のもう一つの特徴である。
【0018】
なお、本発明は、例えば商品名テトラポットのような被覆ブロック2の適用に限定されず、喰み合わせたり組合わせ可能な被覆ブロック2であれば、どのような被覆ブロック2を複数個同時に据付ける際に有効であり、また同時据付けする個数も、2個または3個以上の複数個に対して適用可能である。
【0019】
【発明の効果】
以上に説明した本発明の据付方法およびその装置によれば、複数の被覆ブロックを同時に据付けることが可能となり、被覆ブロック据付時の工費の節減と施工能率の向上をはかれると共に、作業の安全性の向上をはかることができる。
【0020】
さらに、上記の据付時に、複数の被覆ブロックのそれぞれに玉掛けする際の吊り治具の各被覆ブロックに対する装着用の吊り治具の各リングの装着ガイドの長さを変化させたことで、玉掛けが容易になり、玉掛作業の要因の数を低減でき経済的で安全な施工が可能になる。
【図面の簡単な説明】
【図1】本発明の据付け方法を適用した一実施形態における据付施工状況を示す概略図である。
【図2】図1の方法による据付施工のフロー図である。
【図3】図1の3個の被覆ブロックを一体化して玉掛けする状態の平面図である。
【図4】図1の吊り治具のリングの平面図である。
【図5】図3の左側のリングの拡大側面図である。
【図6】図3の中央のリングの拡大側面図である。
【図7】図3の右側のリングの拡大側面図である。
【図8】図10の角パイプコラムの拡大平面図である。
【図9】図10の玉掛け外し具の拡大説明図である。
【図10】図1の吊り治具を示す全体側面図である。
【図11】従来の据付方法による据付施工状況を示す概略図である。
【図12】図11の方法による据付施工フロー図である。
【符号の説明】
2 被覆ブロック
3 クレーン船
4 クレーン
7 リング
10 装着ガイド
11 玉掛外し具
[0001]
BACKGROUND OF THE INVENTION
The present invention mainly relates to a method and apparatus for installing a covering block capable of simultaneously installing a plurality of covering blocks when installing the covering block on a covering surface of a rubble mound.
[0002]
[Prior art]
Conventionally, when installing the covering block 2 such as Tetrapot (registered trademark) on the slope of the rubble mound 1 of the underwater structure as shown in FIG. 11, as shown in the construction flow of FIG. In FIG. 11, the covering block 2 is loaded on the ship of the crane ship 3, transported to the installation position on the sea, the covering blocks 2 are slung one by one by the crane 4 on the ship, suspended, and supported from the submarine ship 5. After the diver 6 gives an instruction and guides to a predetermined installation position, the covering block 2 is bottomed and installed, and the dive wire is removed by the diver 6, and this cycle is repeated to perform the installation operation. It was.
[0003]
However, in the above-described conventional method, since the cycle of installing the covering blocks 2 one by one and installing them at predetermined positions is repeatedly performed, the working time and work cost are increased, and there are many problems in terms of work safety. .
[0004]
[Problems to be solved by the invention]
According to the present invention, when installing the covering block, for example, when installing at least the first layer of the two-layered covering blocks, a plurality of covering blocks can be installed simultaneously. Provided are a method and an apparatus for installing a covering block capable of saving and improving construction efficiency and improving work safety.
[0005]
[Means for Solving the Problems]
The present invention, a plurality of coated blocks arranged in a predetermined position of the ship and transported to the location installation crane ship embarked, the installing hanging jig comprising a plurality of rings which can be mounted to each distal end of the plurality of coated blocks Of a covering block that hangs a plurality of covering blocks on the ship with the lifting jig. In the installation method , when carrying out slinging with a lifting jig consisting of a plurality of rings that can be mounted on the respective tip portions of a plurality of covering blocks to be installed, mounting with different lengths protruding from the peripheral surfaces of the plurality of rings. It consists of a method of installing a covering block in which guides are sequentially attached to the covering block from the longer one.
[0006]
Furthermore, the installation device of the present invention applied to the above-described installation method includes a crane equipped on a ship of a crane ship and a plurality of rings that can be attached to respective tip portions of a plurality of covering blocks arranged on the ship. A covering block installation device comprising a sling jig for hanging and a sling remover capable of lifting the hanging jig after the covering block is installed. It consists of a covering block installation device provided with different mounting guides.
[0007]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, an embodiment of a coating block installation method and apparatus according to the present invention will be described with reference to the drawings.
[0008]
First, FIG. 1 shows a situation where a plurality of, for example, three covering blocks 2 in this embodiment are installed on the slope of the rubble mound 1 by the installation method of the present invention, which is the same as the conventional example of FIG. Although the parts are indicated by the same reference numerals, in this embodiment, as shown in the construction flow diagram of FIG. 2, when the covering block 2 is first loaded on the ship of the crane ship 3, a plurality of (this embodiment) Can be mounted at the tip of each of the three covering blocks 2 installed on the ship as shown in FIG. Each covering block 2 is slung by a hanging jig comprising a ring 7 as shown in the plan view of FIG.
[0009]
Here, the three rings 7 to be attached to the upper end portions of the three covering blocks 2 are provided on the lower peripheral surface of each ring 7, as shown in FIGS. 5, 6, and 7. These mounting guides 10 are provided with different lengths. FIG. 5 shows the ring 7 on the left side of FIG. 3, and FIG. 6 shows the ring at the center of FIG. 7 and FIG. 7 shows the ring on the right side of FIG. 3. The ring 7 of FIG. 6 has a shorter mounting guide 10 than the ring 7 of FIG. The mounting guide 10 is further shortened. For example, the mounting guide 10 may be omitted as shown in FIG. .
[0010]
FIG. 10 shows a state in which the three covering blocks 2 are slung with the hanging jig composed of the above three rings 7 and the like, from the main winding hook 11 of the crane 4 in FIG. While simultaneously suspending the rings 7 with the suspension piece 17 of FIG. 4 through the suspension jig of the square pipe column 12 shown in FIG. 8, the ring 7 of FIG. 5, the ring 7 of FIG. 6, and the ring 7 of FIG. From the ring 7 with the long mounting guide 10 to the ring 7 with the short mounting ring 10 in this order, that is, from the left side to the right side of FIG. Then, each covering block 2 is hung with a sling wire.
[0011]
In this case, the lengths of the mounting guides 10 of the three rings 7 are different. By sequentially mounting the rings 7 on the covering block 2 from the longer one, the slinging operation becomes easier, for example, 1 When three people or two people perform the sling operation, the lower end of the mounting guide 10 of the ring 7 on the left side of FIG. 10 is first held by the tip of the covering block 2, and then the lower end of the mounting guide 10 of the center ring 7 Is held at a higher position than the left side, and finally the right ring 7 is attached to the tip of the covering block 2, so that the three slinging operations can be performed smoothly and efficiently with a small number of people and a safe slinging. Can do.
[0012]
In addition, as shown above, when each of the covering blocks 2 is slung one by one, as shown in FIG. 10 is automatically pulled out in the direction of the arrow U in FIG. 9 by the auxiliary winding hook 14 of the crane 5 shown in FIG. 10, and this sling releasing rope 15 is attached to the ring 7 in FIG. The inside of the provided release rope through-hole 18 is loosened and pulled up.
[0013]
In addition, the sling remover 13 shown in this embodiment can be automatically slung off by pulling up the sling releasing rope 15, but is not limited to this sling remover 13. A sling remover may be used.
[0014]
Further, the three covering blocks 2 are arranged in the state shown in FIG. 3, and the connecting wires 8 are connected to the three covering blocks 2 as shown in FIG. By turning around and stopping both ends, rotation of the three covering blocks is prevented.
[0015]
Next, as shown in the construction flow diagram of FIG. 12, each of the three covering blocks 2 slung through a dedicated hanging jig is assembled in the state of FIG. 3 by the main winding hook 11 of the crane 5. It is suspended through the suspension piece 17 of the ring 7, guided to a predetermined installation position, installed, and after the diver 6 confirms the direction and position of the covering block 2, the sling release rope 15 is pulled up, Remove and lift the lifting jig such as the ring 7 onto the ship.
[0016]
Thereafter, the operation after the staking of the three covering blocks 2 to be installed next on the ship is sequentially repeated with the lifted lifting jig to install the covering block 2 on a predetermined position of the rubble mound 1.
[0017]
By adopting the above-described installation method and apparatus of the present invention, a plurality of covering blocks 2 are arranged in a state where the protruding portions are engaged with each other, arranged on the ship, and a plurality of rings 7 and connecting wires 8 are arranged. It is characterized in that the construction efficiency is improved by integrating a plurality of groups together and installing them simultaneously, but on the lower peripheral surface of a plurality of rings 7 of a hanging jig used for slinging a plurality of covering blocks 2 Another feature of the present invention is that the operation of sequentially attaching the rings to the tips of the plurality of covering blocks 2 can be facilitated because the lengths of the respective mounting guides 10 are changed.
[0018]
The present invention is not limited to the application of the covering block 2 such as the trade name Tetrapot. For example, as long as the covering block 2 can be bitten or combined, any number of covering blocks 2 can be installed simultaneously. It is effective when attaching, and the number of units installed simultaneously can be applied to two or more than two.
[0019]
【The invention's effect】
According to the installation method and apparatus of the present invention described above, a plurality of coating blocks can be installed at the same time, so that the construction cost can be reduced and the construction efficiency can be improved, and the work safety can be improved. Can be improved.
[0020]
Furthermore, at the time of the above installation, by changing the length of the mounting guide of each ring of the hanging jig for mounting with respect to each covering block of the hanging jig when hanging on each of the plurality of covering blocks, It becomes easy and the number of slinging factors can be reduced, and economical and safe construction becomes possible.
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a schematic diagram showing an installation construction status in an embodiment to which an installation method of the present invention is applied.
FIG. 2 is a flowchart of installation work by the method of FIG. 1;
FIG. 3 is a plan view showing a state where the three covering blocks of FIG.
4 is a plan view of a ring of the hanging jig of FIG. 1. FIG.
FIG. 5 is an enlarged side view of the left ring of FIG. 3;
6 is an enlarged side view of the center ring of FIG. 3. FIG.
7 is an enlarged side view of the right ring of FIG. 3;
8 is an enlarged plan view of the square pipe column of FIG.
9 is an enlarged explanatory view of the sling remover of FIG.
10 is an overall side view showing the hanging jig of FIG. 1. FIG.
FIG. 11 is a schematic view showing a state of installation by a conventional installation method.
12 is a flow chart of installation work by the method of FIG.
[Explanation of symbols]
2 Covering Block 3 Crane Ship 4 Crane 7 Ring 10 Mounting Guide 11 Catch Remover

Claims (2)

複数の被覆ブロックを船上の所定位置に並べて積込んだクレーン船を据付け場所に運搬し、据付ける複数の被覆ブロックの各先端部に装着可能な複数のリングからなる吊り治具にて玉掛けを行い、所定の据付け位置にクレーンにより吊り込み据付けの後、玉掛け外しを行い、吊り治具を船上に引上げ、その吊り治具にて船上の複数の被覆ブロックの玉掛けを行う被覆ブロックの据付方法において、据付ける複数の被覆ブロックの各先端部に装着可能な複数のリングからなる吊り治具にて玉掛けを行なう際に、複数のリング下部周面にそれぞれ突設した長さの異なる装着ガイドを、長さの長い方から順次被覆ブロックに装着する被覆ブロックの据付方法。 A crane ship loaded with a plurality of covering blocks arranged in place on the ship is transported to the installation location, and slung with a hanging jig consisting of a plurality of rings that can be attached to the tip of each of the plurality of covering blocks to be installed. In the installation method of the covering block, after hanging and installing by a crane at a predetermined installation position, removing the sling, lifting the lifting jig onto the ship, and slugging a plurality of covering blocks on the ship with the hanging jig . When using a hanging jig consisting of multiple rings that can be mounted on the tip of each of the multiple covering blocks to be installed, the mounting guides with different lengths protruding from the peripheral surfaces of the lower rings A method for installing a covering block that is sequentially attached to the covering block from the longest one. クレーン船の船上に装備されたクレーンと、その船上に並べられた複数の被覆ブロックの各先端部に装着可能な複数のリングからなる玉掛け用の吊り治具と、被覆ブロックの据付後に吊り治具を引上げ可能な玉掛け外し具とからなる被覆ブロックの据付装置において、吊り治具の複数のリングの下部周面のそれぞれに、長さの異なる装着ガイドが突出して設けられている被覆ブロックの据付装置。A crane mounted on a ship of a crane ship, a sling jig for a sling consisting of a plurality of rings that can be attached to the respective tip portions of a plurality of covering blocks arranged on the ship, and a hanging jig after the covering block is installed In a covering block installation device comprising a sling remover capable of pulling up a mounting block, a covering block installation device in which mounting guides of different lengths are provided to project on each of the lower peripheral surfaces of the plurality of rings of the hanging jig .
JP2002218466A 2002-07-26 2002-07-26 Coating block installation method and apparatus Expired - Lifetime JP4182201B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002218466A JP4182201B2 (en) 2002-07-26 2002-07-26 Coating block installation method and apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002218466A JP4182201B2 (en) 2002-07-26 2002-07-26 Coating block installation method and apparatus

Publications (2)

Publication Number Publication Date
JP2004059207A JP2004059207A (en) 2004-02-26
JP4182201B2 true JP4182201B2 (en) 2008-11-19

Family

ID=31939648

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002218466A Expired - Lifetime JP4182201B2 (en) 2002-07-26 2002-07-26 Coating block installation method and apparatus

Country Status (1)

Country Link
JP (1) JP4182201B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4994153B2 (en) * 2007-08-23 2012-08-08 水工技研株式会社 Block construction method
JP5706031B1 (en) * 2014-09-05 2015-04-22 鹿島建設株式会社 Lifting device and lifting method of suspended load
CN114753295B (en) * 2022-03-28 2024-04-16 中交第四航务工程局有限公司 Square block installation positioning method

Also Published As

Publication number Publication date
JP2004059207A (en) 2004-02-26

Similar Documents

Publication Publication Date Title
JP2008128253A (en) Wind turbine blade handling method and apparatus for mounting a wind turbine blade, in particular for mounting a blade on a wind turbine
CN110789669B (en) A deep-water single-point mooring reclaimed water buoy recovery and lowering system and method
JP5855523B2 (en) 4 conductor transmission line insulator device replacement method and replacement device used for the method
JP4182201B2 (en) Coating block installation method and apparatus
CN102213085A (en) Installation method of vertical pipe of guide pipe rack
CN102586784A (en) Method for assembling direct current cathode protection system outside platform
JP2004135420A (en) Cable grip
JP2000143122A (en) Main rope replacing method for side fork elevator
JPH11246166A (en) Concrete lock slinging equipment
CN211198371U (en) Assembled building element hoist device
JP2000219476A (en) One-man slinging accessory
JP3063550U (en) Hanging bracket
JP4956286B2 (en) Winding drum wire winding method at crane installation
JPH07144850A (en) Shackle equipped with roller and car suspending device
CN116216537B (en) An underwater robot deployment system for firefighting and rescue
JP2006044851A (en) Deep water cargo lifting device for floating crane
CN105464066B (en) The construction method that a kind of Bailey bracket of the high drop beam slab closing of large span is removed
JPH11180393A (en) Diving apparatus system
CN220662811U (en) Water surface photovoltaic panel installation equipment
JPH03216490A (en) Wave eliminating block transfer device
JPH11278367A (en) Suspension hanging joint
JP2582244Y2 (en) Sling belt
JPH08333076A (en) Hanger for take-up drum or the like
JPH0435346Y2 (en)
JP3088153U (en) Hanger for transfer of suspended load transfer

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050726

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20050912

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20050912

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080404

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080603

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080625

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080722

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20080807

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20080807

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20080807

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20080807

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110912

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4182201

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110912

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120912

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130912

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130912

Year of fee payment: 5

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term