JP4194584B2 - Dam construction method - Google Patents
Dam construction method Download PDFInfo
- Publication number
- JP4194584B2 JP4194584B2 JP2005218136A JP2005218136A JP4194584B2 JP 4194584 B2 JP4194584 B2 JP 4194584B2 JP 2005218136 A JP2005218136 A JP 2005218136A JP 2005218136 A JP2005218136 A JP 2005218136A JP 4194584 B2 JP4194584 B2 JP 4194584B2
- Authority
- JP
- Japan
- Prior art keywords
- dam
- commutation
- channel
- construction
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Revetment (AREA)
Description
本発明は一般に、ダムの施工方法に関する。より詳細には、本発明は、1次切替え仮水路をダム本体として活用する台形CSGダム及びコンクリートダムの施工方法に関する。 The present invention generally relates to dam construction methods. In more detail, this invention relates to the construction method of the trapezoid CSG dam and concrete dam which utilize a primary switching temporary waterway as a dam main body.
湛水(止水)機能と高い安全性を要求されるダムは一般的に、河川の横断方向に延びるように築造されるため、工事に際しては、施工性および出水による安全性に配慮した河流処理対策が必要となる。従来、河流処理の方法としては、仮排水路トンネル方式、半川締切方式、仮排水開渠方式などがあり、対象となる河川の河流水量、地形地質条件、ダム型式などを勘案し、安全性、施工性、経済性などを総合的に考慮して最適な方式が選定される。 Dams that require a flooding (water stoppage) function and high safety are generally constructed so as to extend in the transverse direction of the river. Countermeasures are required. Conventional river flow treatment methods include the temporary drainage tunnel method, the half river deadline method, and the temporary drainage reclamation method, etc., taking into consideration the river flow volume of the target river, topographic geological conditions, dam type, etc. The optimum method is selected with comprehensive consideration of the workability and economic efficiency.
このうち仮排水路トンネル方式は、地山斜面内にトンネルを掘削して河川を切り替える方法であり、ダム本体工事を河流水と無関係に実施することができるという利点を有するものの、トンネル工事に要する工期と工事費が別途必要となる。
また、半川締切方式は、河川を片側に寄せて開水路(1次水路)を設置し、本体工事を分割して行う方法であり、河幅が広く、河川流量も大きいため、仮排水路トンネル方式や仮排水開渠方式を採用することが著しく不経済である場合に採用されるが、分割施工に伴い、一般的に、ダム本体の工事期間が長くなるという課題がある。
さらに、仮排水開渠方式は、U字溝、コルゲート管などを用いて簡易水路(1次水路)を設置し、本体工事を分割して行う方法であり、対象となる河川の河川水量が少ない場合に採用されるが、半川締切方式の一種と考えることもできる。
Of these, the temporary drainage tunnel method is a method of excavating a tunnel in the natural slope and switching the river, and has the advantage that the dam body construction can be carried out independently of the river water, but is required for tunnel construction Construction period and construction cost are required separately.
In addition, the Hankawa deadline method is a method in which the river is moved to one side and an open channel (primary channel) is installed, and the main work is divided, and the river is wide and the river flow is large. Although it is adopted when it is extremely uneconomical to adopt the tunnel method or the temporary drainage opening method, there is a problem that the construction period of the dam body generally becomes longer due to the divided construction.
Furthermore, the temporary drainage opening method is a method that installs a simple water channel (primary water channel) using U-shaped grooves, corrugated pipes, etc., and divides the main body construction, and the amount of river water in the target river is small Although it is adopted in some cases, it can be considered as a kind of the Hankawa deadline method.
上述の半川締切方式や仮排水開渠方式では、分割施工が行われるため、先行ブロックには後続ブロックを施工するための堤内仮排水路(2次水路)を必要とする。そして、2次水路が完成した後、河川を切り替え、後行ブロックおよび堤内仮排水路より上部全体が施工される。堤内仮排水路は、ダムが完成した後、閉塞され、湛水が開始される。したがって、安全かつ確実に湛水するために、堤内仮排水路には、閉塞ゲートなどの設備が設けられる。一方、ダム高15m未満の低ダムでは、仮排水開渠を設置し、その開渠を本体の一部としてそのまま埋設している事例が見受けられるが、その場合、2次水路を必要としないため、工程上有利となる。 In the above-mentioned Hankawa deadline method and temporary drainage opening method, division construction is performed, and therefore, the preceding block requires a temporary drainage channel (secondary channel) in the levee for constructing the subsequent block. Then, after the secondary waterway is completed, the river is switched, and the entire upper part is constructed from the succeeding block and the temporary drainage channel in the bank. The dam temporary drainage channel is closed after the dam is completed and flooding begins. Therefore, in order to flood safely and reliably, facilities such as a closed gate are provided in the levee temporary drainage channel. On the other hand, in low dams with a dam height of less than 15m, there are cases where temporary drainage culverts are installed and the culverts are buried as part of the main body, but in that case, secondary waterways are not required. This is advantageous in terms of the process.
上述のように、ダム高15m未満の低ダムでは、仮排水開渠を本体の一部として利用している例があるが、河川法に基づく重要構造物であるダムにおいては、以下に示す3つの理由により、仮排水開渠(1次水路)を埋設した事例は見当たらない。
(1)コンクリート水路やコンクリート管などを設置した場合、水路や管周辺での恒久的で確実な止水機能の確保が困難であり、また、ダムが完成して湛水が開始された後には、異常発生時の補修が困難である。
(2)ダムには一般的に、揚圧力の軽減および漏水量の管理のため、通廊が設置されており、通廊の設置標高は、その設置目的から、ダム底付近となる。1次水路を本体の一部として埋設した場合には、1次水路が河床付近の標高となるため、通廊と1次水路が交錯するおそれがある。そのような場合には、通廊は、1次水路を避けて配置しなければならないが、管理・機能上からは適当な配置とは言い難い。
(3)ダムは、設計条件に見合った良好な岩盤上に築造する必要がある。そのため、ダムの築造に際しては、他の土木構造物とは異なる地質調査および評価・解析を行ってダムの基盤が決定されるが、それにもかかわらず、掘削時に想定外の断層などの弱層が発見されて、基盤を変更する場合も少なくない。したがって、1次水路を本体の一部として先行打設する場合、その周辺をも含めた比較的広い範囲の岩盤の状況を確認したうえで施工する必要がある。このため、1次水路を本体に活用することはなく、2次水路を設置するのが慣例とされている。
As mentioned above, in low dams with a dam height of less than 15 m, there is an example where temporary drainage is used as part of the main body. However, in dams that are important structures based on the river law, the following 3 For one reason, there are no cases where temporary drainage (primary waterway) was buried.
(1) When a concrete waterway or concrete pipe is installed, it is difficult to secure a permanent and reliable water stop function around the waterway or pipe, and after the dam is completed and flooding is started It is difficult to repair when an abnormality occurs.
(2) A dam is generally provided with a corridor for the purpose of reducing lifting pressure and managing the amount of water leakage, and the altitude of the corridor is near the dam bottom for the purpose of installation. When the primary waterway is buried as a part of the main body, the primary waterway is at an altitude near the riverbed, so there is a possibility that the corridor and the primary waterway may cross each other. In such a case, the corridor must be arranged avoiding the primary waterway, but it is difficult to say that the arrangement is appropriate from the viewpoint of management and function.
(3) The dam must be built on a good bedrock that meets the design conditions. Therefore, when building a dam, the foundation of the dam is determined by conducting geological surveys and evaluation / analysis different from those of other civil engineering structures, but nevertheless there are weak layers such as unexpected faults during excavation. There are many cases where the foundation is changed after being discovered. Therefore, when placing the primary waterway as a part of the main body, it is necessary to perform construction after confirming the condition of the rock in a relatively wide range including the periphery. For this reason, it is customary to install a secondary waterway without using a primary waterway for a main body.
以上より、ダム建設工事においては、通常、河流を1次水路と2次水路に切り替えることが必要とされており、そのため、施工が分断され、工期の延長の一因になるとともに、施工の一層の合理化が阻害されている。 From the above, in dam construction work, it is usually necessary to switch the river flow to the primary and secondary canals, which divides the construction and contributes to the extension of the construction period. The streamlining of is being hampered.
本発明は、このような状況に鑑みて開発されたものであって、1次切替え仮水路をダム本体として活用することにより、通常は2回行われる河流の切替えを1回にすることを可能にするダムの施工方法を提供することを目的としている。 The present invention was developed in view of such a situation, and by using the primary switching temporary waterway as a dam body, it is possible to switch the river flow that is normally performed once twice. The purpose is to provide a construction method for the dam.
本発明は、台形CSGダム及びコンクリートダムに使用される(CSGとは、Cement Sand and Gravelの略であり、以下「CSG」という)。台形CSGダムの堤体は、台形形状であるため、一般のコンクリートダムと比較して、発生応力が小さくなり、これにより、ダムの基礎岩盤への要求性能も低くなる。したがって、台形CSGダムとした場合、上述の(3)の課題は、解消されることとなる。ここで、CSGとは、河床砂礫や掘削土などの現地発生材とセメントとを混合することによって形成される材料である。また、一般のコンクリートダムであっても、当初から本発明の施工方法の使用を想定して十分な調査を行い、基礎岩盤への要求性能を満たしていると判断された場合には、台形CSGダムと同様に、本発明の方法を適用することができる。 The present invention is used for trapezoidal CSG dams and concrete dams (CSG is an abbreviation for Cement Sand and Gravel, hereinafter referred to as “CSG”). Since the trapezoidal CSG dam has a trapezoidal shape, the generated stress is smaller than that of a general concrete dam, and the required performance of the dam foundation rock is also reduced. Therefore, when the trapezoidal CSG dam is used, the above-described problem (3) is solved. Here, CSG is a material formed by mixing locally generated materials such as riverbed gravel and excavated soil with cement. Moreover, even if it is a general concrete dam, it is assumed that the construction method of the present invention is used from the beginning, and if it is judged that the required performance for the foundation rock is satisfied, trapezoidal CSG As with dams, the method of the present invention can be applied.
本願請求項1に記載の台形CSGダム及びコンクリートダムの施工方法は、転流水路の設置箇所を掘削する工程と、前記転流水路の基礎を打設する工程と、前記基礎上への転流水路用プレキャスト部材の設置又は場所打ちコンクリートによって転流水路を構築する工程と、河川の上流側に仮締切り部を構築して、河流を前記転流水路に切り替える工程と、ダム堤体の設置箇所のうち前記転流水路以外の箇所を掘削する工程と、CSG又はコンクリートを用いてダム堤体の下部の打設を行う工程と、前記ダム堤体に通廊を構築する工程と、CSG又はコンクリートを用いてダム堤体の上部の打設を行う工程と、前記転流水路の呑口の湛水ゲートを閉鎖する工程と、前記転流水路と前記通廊との交差部の施工を行う工程と、前記転流水路を閉塞する工程とを含むことを特徴とするものである。 The construction method of the trapezoidal CSG dam and the concrete dam according to claim 1 includes a step of excavating a place where a commutation channel is installed, a step of placing a foundation of the commutation channel, and a commutation water on the foundation. Installation of precast members for roads or construction of commutation water channels by cast-in-place concrete, construction of a temporary cutoff on the upstream side of the river, switching the river flow to the commutation water channels, and installation locations of dam dam bodies A step of excavating a portion other than the commutation channel, a step of placing a lower portion of the dam dam body using CSG or concrete, a step of constructing a passage in the dam dam body, CSG or concrete A step of placing the upper portion of the dam dam body using a step, a step of closing the inundation gate at the entrance of the commutation waterway, and a step of constructing an intersection of the commutation waterway and the corridor; Block the commutation channel It is characterized in that comprises a step.
本発明の施工方法によれば、保護・遮水コンクリートと接する転流水路上流側を場所打ちコンクリートとすることにより、上述の課題(1)が解消され、転流水路および通廊の交差部に止水壁を構築することにより、上述の課題(2)が解消され、さらに、台形CSGダムとする、及びコンクリートダムにおいては基礎岩盤への要求性能を確認することにより、上述の課題(3)が解消されるため、転流水路をダム本体として活用することが可能になり、工期の短縮、建設コストの低減、施工の合理化を達成することができる。 According to the construction method of the present invention, the above-mentioned problem (1) is solved by using cast-in-place concrete on the upstream side of the commutation water channel in contact with the protective / water-impervious concrete, and at the intersection of the commutation water channel and the passage By constructing the water blocking wall, the above-mentioned problem (2) is solved. Furthermore, in the case of a trapezoidal CSG dam, and in concrete dams, by confirming the required performance of the foundation rock, the above-mentioned problem (3) Therefore, the commutation channel can be used as the dam body, and the construction period can be shortened, the construction cost can be reduced, and the construction can be rationalized.
次に図面を参照して、本発明の好ましい実施の形態に係るダム施工方法について詳細に説明する。図1は、本発明の好ましい実施の形態に係るダム施工方法を示したフロー図、図2は、本発明の方法によりダムが施工される地域を模式的に示した図である(図2において破線で示したのが、施工されるダム堤体である)。本例において施工されるのは、台形CSGダム及びコンクリートダムである。ここで、台形CSGダムとは、CSGを用いて構築される台形状のダムをいう。 Next, a dam construction method according to a preferred embodiment of the present invention will be described in detail with reference to the drawings. FIG. 1 is a flow diagram showing a dam construction method according to a preferred embodiment of the present invention, and FIG. 2 is a diagram schematically showing an area where a dam is constructed by the method of the present invention (in FIG. 2). The broken line shows the dam body to be constructed). In this example, a trapezoidal CSG dam and a concrete dam are constructed. Here, the trapezoidal CSG dam refers to a trapezoidal dam constructed using CSG.
まず最初に、転流水路の設置箇所を掘削する(工程1)。図2に示される例では、転流水路設置箇所に斜面部が含まれているので、斜面部も掘削する(図3参照)。次いで、転流水路の基礎を打設する(工程2)。基礎の打設には、通常のコンクリートの他、CSGを使用してもよい。 First, the installation location of the commutation waterway is excavated (step 1). In the example shown in FIG. 2, since the slope portion is included in the commutation water channel installation location, the slope portion is also excavated (see FIG. 3). Next, the foundation of the commutation channel is placed (step 2). In addition to normal concrete, CSG may be used for placing the foundation.
次いで、基礎上への、転流水路用プレキャスト部材の設置又は場所打ちコンクリートによって、転流水路を構築する(工程3)。しかる後、図4に示されるように、上流側に仮締切り部を構築して、河流を転流水路に切り替える(工程4)。その後、上流側および下流側に締切り部を構築する。 Next, a commutation water channel is constructed by installing a precast member for the commutation water channel or cast-in-place concrete on the foundation (step 3). Thereafter, as shown in FIG. 4, a temporary cutoff part is constructed on the upstream side, and the river flow is switched to the commutation channel (step 4). Thereafter, the cutoff part is constructed on the upstream side and the downstream side.
次いで、ダム堤体の設置箇所のうち転流水路以外の箇所を掘削する(工程5)。次いで、ダム堤体の下部のCSG又はコンクリート打設を行う(工程6)。 Next, a portion other than the commutation channel is excavated among the locations where the dam dam body is installed (step 5). Next, CSG or concrete placement at the lower part of the dam body is performed (step 6).
次いで、ダム堤体に通廊を構築する(工程7)。通廊とは、ダム完成後の監査、各種測定、堤体および基礎の排水、グラウト作業、ゲート操作などを行うために、ダム堤体内部に設けられる通路のことであり、監査廊とも呼ばれる。通廊の構築は、プレキャスト部材を用いてもよいし、場所打ちコンクリート方式としてもよいが、工期短縮が可能となることの他、後述する交差箇所の段階的施工を容易にする等の利点を有するため、前者の方式が好ましい。一般に逆U形の横断面形状を有する通廊の構築にプレキャスト部材を用いる場合には、プレキャスト部材を所定箇所に設置し、プレキャスト部材の下面部に高流動コンクリートを充填することによって施工される。 Next, a corridor is constructed in the dam body (step 7). The corridor is a passage provided inside the dam body to perform audits after completion of the dam, various measurements, drainage of the dam body and foundation, grout work, gate operation, etc., and is also called an audit gallery. The construction of the corridor may use precast members or a cast-in-place concrete method, but in addition to being able to shorten the construction period, there are advantages such as facilitating the gradual construction of intersections described later. Therefore, the former method is preferable. In general, when a precast member is used to construct a corridor having an inverted U-shaped cross section, the precast member is installed at a predetermined location, and the lower surface portion of the precast member is filled with high-fluidity concrete.
通廊を構築した後、ダム堤体の上部のCSG又はコンクリート打設を行う(工程8)。これにより、ダム堤体が完成する(図5参照)。次いで、転流水路の呑口の湛水ゲートを閉鎖する(工程9)。これにより、転流水路への通水が遮断される。 After constructing the corridor, CSG or concrete placement is performed on the upper part of the dam body (step 8). Thereby, the dam body is completed (see FIG. 5). Next, the inundation gate at the entrance of the commutation channel is closed (step 9). Thereby, the water flow to a commutation waterway is interrupted | blocked.
次いで、転流水路と通廊との交差部の施工を行う(工程10)。交差部の施工においては、転流水路を閉塞する際、保護・遮水コンクリートと接する転流水路上流側を場所打ちコンクリートとし、交差面を止水壁(例えば、鋼板、コンクリート壁)で予め覆う。図6(a)は、転流水路と通廊との交差部を上流側から見た模式図である。止水壁で覆う場合には、転流水路と交差する箇所の通廊開口部に鋼板を設置し又はコンクリート壁を打設し(図6(b)参照)、転流水路を閉塞する工事を行った後に、止水壁を撤去し、通廊のプレキャスト部材又は通廊型枠を設置する(図6(c)参照)。 Subsequently, construction of the intersection of a commutation waterway and a corridor is performed (process 10). In the construction of the intersection, when the commutation channel is closed, the upstream side of the commutation channel in contact with the protection / water-blocking concrete is cast in place, and the intersection surface is covered with a water blocking wall (for example, steel plate, concrete wall) in advance. . Fig.6 (a) is the schematic diagram which looked at the crossing part of a commutation water channel and a corridor from the upstream. When covering with a still water wall, install a steel plate or a concrete wall in the opening of the corridor where it intersects the commutation channel (see Fig. 6 (b)), and work to close the commutation channel. After going, the water blocking wall is removed, and a precast member of the corridor or a corridor formwork is installed (see FIG. 6C).
最後に、図7に示されるように、転流水路を閉塞して、ダムの施工が完成する(工程11)。 Finally, as shown in FIG. 7, the commutation waterway is closed and the construction of the dam is completed (step 11).
なお、上述の実施の形態では、通廊を備えたダムの施工に関連して説明されているが、小規模ダム等のように通廊を設置しない場合には、上述の説明における工程6、7、10は不要となる。 In addition, in the above-mentioned embodiment, although it explained in connection with construction of a dam provided with a corridor, when not installing a corridor like a small-scale dam, Step 6 in the above-mentioned explanation, 7 and 10 become unnecessary.
本発明は、以上の発明の実施の形態に限定されることなく、特許請求の範囲に記載された発明の範囲内で、種々の変更が可能であり、それらも本発明の範囲内に包含されるものであることはいうまでもない。 The present invention is not limited to the embodiments of the invention described above, and various modifications can be made within the scope of the invention described in the claims, and these are also included in the scope of the present invention. Needless to say, it is something.
Claims (1)
転流水路の設置箇所を掘削する工程と、
前記転流水路の基礎を打設する工程と、
前記基礎上への転流水路用プレキャスト部材の設置又は場所打ちコンクリートによって転流水路を構築する工程と、
河川の上流側に仮締切り部を構築して、河流を前記転流水路に切り替える工程と、
ダム堤体の設置箇所のうち前記転流水路以外の箇所を掘削する工程と、
CSG又はコンクリートを用いてダム堤体の下部の打設を行う工程と、
前記ダム堤体に通廊を構築する工程と、
CSG又はコンクリートを用いてダム堤体の上部の打設を行う工程と、
前記転流水路の呑口の湛水ゲートを閉鎖する工程と、
前記転流水路と前記通廊との交差部の施工を行う工程と、
前記転流水路を閉塞する工程と、
を含むことを特徴とする方法。 A trapezoidal CSG dam and a concrete dam construction method,
Excavating the location of the commutation channel;
Placing the foundation of the commutation channel;
A step of constructing a commutation water channel by installing a precast member for the commutation water channel on the foundation or cast-in-place concrete;
Constructing a temporary cutoff on the upstream side of the river and switching the river flow to the commutation channel,
A step of excavating a place other than the commutation waterway among the installation places of the dam body,
A process of placing the lower part of the dam body using CSG or concrete;
Building a corridor in the dam body;
A process for placing the upper part of the dam body using CSG or concrete;
Closing the inundation gate at the mouth of the commutation channel;
Performing the construction of the intersection of the commutation waterway and the corridor;
Clogging the commutation channel;
A method comprising the steps of:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2005218136A JP4194584B2 (en) | 2005-07-28 | 2005-07-28 | Dam construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2005218136A JP4194584B2 (en) | 2005-07-28 | 2005-07-28 | Dam construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2007032129A JP2007032129A (en) | 2007-02-08 |
| JP4194584B2 true JP4194584B2 (en) | 2008-12-10 |
Family
ID=37791705
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2005218136A Expired - Lifetime JP4194584B2 (en) | 2005-07-28 | 2005-07-28 | Dam construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4194584B2 (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108677892B (en) * | 2018-07-27 | 2024-04-19 | 中国电建集团成都勘测设计研究院有限公司 | Reconstruction structure for ecological water supply tunnel by diversion tunnel construction branch tunnel |
| CN109853490B (en) * | 2019-03-15 | 2024-03-01 | 中国电建集团贵阳勘测设计研究院有限公司 | Method and device for temporarily lowering ecological flow in water storage period of concrete dam |
| CN113136838B (en) * | 2021-04-06 | 2022-10-18 | 河北省水利水电勘测设计研究院 | Modular construction system and method for dam |
| CN113136839B (en) * | 2021-04-06 | 2022-10-18 | 河北省水利水电勘测设计研究院 | Dam construction automation system and method |
-
2005
- 2005-07-28 JP JP2005218136A patent/JP4194584B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JP2007032129A (en) | 2007-02-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US10138616B2 (en) | Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure | |
| CN109371918B (en) | Dam structure with permanent combination of multifunctional drainage box culvert and construction method thereof | |
| CN217630349U (en) | Sewage new and old pipe network connection system based on reverse construction method pipe jacking well | |
| CN112523233B (en) | Construction method of water-through type river-blocking cofferdam | |
| CN114657949A (en) | Construction method for diversion of flood discharge channel | |
| JP5846150B2 (en) | Construction method of river revetment structure | |
| CN106812131B (en) | A kind of permanent sheet pile underground structure and its construction method | |
| JP4194584B2 (en) | Dam construction method | |
| KR100924794B1 (en) | Influent treatment method of connection structure of underground structure and underground tunnel structure | |
| CN115613480B (en) | Connection node of new and old water inlet box culvert and construction method | |
| CN112982319A (en) | Structure and method for conducting diversion, emptying and water taking through dam foundation culvert | |
| CN116479981B (en) | A method for permanent sealing of sewage connection pipes inside a drainage box | |
| CN114032846B (en) | A diversion structure for a large diameter buried pipe passing through a gully | |
| CN117888954A (en) | A structure and construction method for protecting the original underground water system channel in a tunnel | |
| CN119021251A (en) | Construction method of bridge main piers suitable for complex embankment areas in tidal rivers | |
| RU2770187C1 (en) | Method for structure construction in the under-runner space of rivers and canals in urban development | |
| CN217026767U (en) | Existing culvert structure is striden on open cut tunnel | |
| Swetman et al. | Upper Carno: A case study of multidisciplinary remedial works to an embankment dam | |
| CN115749870A (en) | Method for plugging centralized water burst channel of underground engineering | |
| CN110219279B (en) | Concrete anti-scour guide wall structure and construction method | |
| CN117328410B (en) | Dam blocking construction method with low excavation quantity and rapid construction | |
| CN214993969U (en) | An enclosure structure of a water-passing cofferdam | |
| CN219825274U (en) | A supporting structure to prevent groundwater surge in foundation pits | |
| KR200232653Y1 (en) | A repaired part of damage using grouting | |
| Oakland et al. | Design-build of a jet grout access shaft for tunnel rehabilitation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070606 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070615 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20071121 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071220 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20071226 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A821 Effective date: 20071221 |
|
| A911 | Transfer to examiner for re-examination before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20080304 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080829 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080922 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 4194584 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111003 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111003 Year of fee payment: 3 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111003 Year of fee payment: 3 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111003 Year of fee payment: 3 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111003 Year of fee payment: 3 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111003 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141003 Year of fee payment: 6 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141003 Year of fee payment: 6 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141003 Year of fee payment: 6 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| EXPY | Cancellation because of completion of term |