JP4286971B2 - Tower crane removal method - Google Patents
Tower crane removal method Download PDFInfo
- Publication number
- JP4286971B2 JP4286971B2 JP16580599A JP16580599A JP4286971B2 JP 4286971 B2 JP4286971 B2 JP 4286971B2 JP 16580599 A JP16580599 A JP 16580599A JP 16580599 A JP16580599 A JP 16580599A JP 4286971 B2 JP4286971 B2 JP 4286971B2
- Authority
- JP
- Japan
- Prior art keywords
- crane
- mast
- load
- tower crane
- around
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title claims description 10
- 239000000725 suspension Substances 0.000 claims description 18
- 239000000463 material Substances 0.000 description 18
- 230000003014 reinforcing effect Effects 0.000 description 8
- 238000010276 construction Methods 0.000 description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 238000009435 building construction Methods 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Images
Landscapes
- Jib Cranes (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、自身の解体部品の撤去を容易に行えるタワークレーン撤去方法に関するものである。
【0002】
【従来の技術】
建築構造物の躯体を建築する際、資材を吊り上げる手段としてタワークレーンを用いる。
建築構造物の外側でタワークレーンを用いる場合、まず建築構造物の外側の所定の位置にマストを起設し、壁つなぎ材によって躯体の壁面とマストを堅固に繋ぐ。そして、旋回可能で起伏可能なクレーン本体をマストの上部に設け、躯体工事の進行につれてマストを逐次上方に増設し、クレーン本体に備えた昇降装置によって、クレーン本体をマストに沿って上昇させる。
そして、最上階の工事完了後、不用となったタワークレーンを解体撤去するが、壁つなぎ材などのタワークレーンの解体部品をクレーン自身で吊り、撤去している。
【0003】
【発明が解決しようとする課題】
しかしながら、タワークレーンが躯体と接近している場合、クレーン本体が躯体に接触するため、クレーン本体が旋回することが不可能である。
そのため、解体部品の撤去を行う際、解体部品をクレーン本体自身で吊ることができる方向は、クレーン本体のブームの起伏方向だけである。したがって、ブームの起伏方向にない解体部品を撤去する場合、タワークレーン解体用の移動式クレーンを用いて解体部品を撤去するが、移動式クレーンを使用することは、撤去作業の効率が悪い。
そこで、クレーン本体自身で解体部品を吊ることができるように、例えば、マストから取ったチェーンブロックなどで解体部品をブームの起伏方向まで旋回し、それから、解体部品をクレーン本体に吊り替えて、クレーン本体自身で解体部品を撤去するが、高所作業となり危険である。
【0004】
本発明は上記事情に鑑みてなされたものであり、クレーン本体の旋回が行えない条件下において、壁つなぎ材などのタワークレーンの解体部品を安全に旋回して、かつ、効率的に撤去できるタワークレーン及びタワークレーン撤去方法を提供することを目的とする。
【0005】
【課題を解決するための手段】
上記課題を解決するため、本発明は、マスト(30)に沿って昇降自在なクレーン本体(10)を備えたタワークレーン(1)において、マストの周囲を旋回可能な荷吊り装置(20)を、前記クレーン本体に備えた構成を特徴としている。
【0006】
このように、本発明によれば、例えば、クレーン本体が旋回することができない場合、前記クレーン本体が吊ることができない方向にある壁つなぎ材などの荷を、荷吊り装置によって吊り、そして、前記荷とともに前記荷吊り装置がマストの周囲を旋回することによって、前記荷を前記クレーン本体が吊ることができる方向(ブームの起伏方向)まで容易に旋回して、前記クレーン本体によって前記荷を吊ることが可能になる。
【0007】
本発明は、前記荷吊り装置が、クレーン本体の下部にマストを囲むように固定されている軌道(例えば、レール21)と、この軌道に沿ってマストの周囲を旋回する走行装置(例えば、トロリ22)と、この走行装置に備えられ、荷(例えば、壁つなぎ材40、ステー枠41、補強材42などのタワークレーンの解体部品)を吊るための吊り具(例えば、チェーンブロック23)と、で構成されていること、を特徴としている。
【0008】
なお、軌道とは走行装置をマストの周囲に沿って案内するものである。このように、本発明によれば、吊り具によって荷を吊り、クレーン下部にマストを囲むように固定されている軌道に沿ってマストの周囲を走行装置が旋回可能であり、前記荷をクレーン本体が吊ることができる方向(ブームの起伏方向)まで容易に旋回して、前記クレーン本体によって前記荷を吊ることが可能となる。
【0009】
本発明は、上記の荷吊り装置を備えたタワークレーンを用いて、クレーン本体に対し荷吊り装置をマストの周囲に旋回動作させて、荷吊り装置に少なくともタワークレーンと建築構造物の躯体(100)との間に架設される解体部品(例えば、壁つなぎ材40、ステー枠41,補強材42)を吊る工程と、次に、この解体部品を吊った荷吊り装置をマストの周囲に旋回動作させる工程と、次に、この荷吊り装置に吊った解体部品を前記クレーン本体に吊り替える工程と、からなるタワークレーン撤去方法を特徴としている。
【0010】
このように、本発明によれば、荷吊り装置によってタワークレーンの解体部品を吊り、そして、マストの周囲をクレーン本体が吊ることができる方向(ブームの起伏方向)まで前記解体部品を旋回して、そして、前記クレーン本体によって前記解体部品を吊る。したがって、前記クレーン本体の旋回が行えない場合でも、前記クレーン本体によって撤去することが可能となる。
【0011】
【発明の実施の形態】
以下に、本発明の実施の形態の第一例を図を参照して説明する。
図1は、本発明を適用したタワークレーンを示す正面図で、10はクレーン本体、11は昇降装置、12はブーム、13はフック、20は荷吊り装置、30はマスト、40は壁つなぎ材、100は建築構造物の躯体である。
【0012】
図1に示すように、下部に昇降装置11を備えているクレーン本体10は、マスト30の上部に設置されている、即ち、クレーン本体10は、建築構造物の躯体工事の進行につれてマスト30を逐次上方に増設し、昇降装置11によって、クレーン本体10をマスト30に沿って上昇させ、マスト30の上方に設置する。また、建築構造物の躯体工事完了後、クレーン本体10は昇降装置11によって、マスト30に沿って下降することができる。
【0013】
ブーム12はクレーン本体10に備えられており、ブーム12は起伏装置(図示略)によって起伏することができる。荷の吊り上げは、ブーム12の先端から下げられたフック13をロープ14を介して巻上装置(図示略)で行う。
【0014】
クレーン本体10は旋回装置(図示略)を備えており、マスト30の上方で旋回することが可能である。
以上のように、タワークレーン1は工事の状況に応じて、旋回可能で起伏可能であり、建築構造物の資材やタワークレーンの解体部品などの荷を吊ることが可能になる。
【0015】
図2は、クレーン本体10の下部を拡大した図であり、横方向からみた側面図である。壁つなぎ材40はマスト30と建築構造物の躯体100を繋ぐ部材である。ステー枠41はマスト30を囲むようにマスト30に固定されており、壁つなぎ材40をマスト30に支持する部材である。補強材42は上下方向にマスト30に固定されており、ステー枠41とマスト30をさらに堅固に固定するための部材である。図に示すように、壁つなぎ材40はステー枠41によってマスト30に支持されており、ステー枠41とマスト30は補強材42によって堅固に固定されている。そして、壁つなぎ材40は建築構造物の躯体100の壁に固定されている。こうして、壁つなぎ材40、ステー枠41及び補強材42によってマスト30は建築構造物の躯体100に堅固に固定されている。
【0016】
荷吊り装置20は、タワークレーンの解体時において、取り外した壁つなぎ材40、ステー枠41及び補強材42を吊ることが可能な装置である。図3に拡大して示すように、荷吊り装置20は取り付け架台24の下部に取り付けられている。そして、取り付け架台24と取り付け鉄柱26によって昇降装置11の下部を上下方向にはさむように、取り付けボルト25、25、25、25によって取り付け架台24と取り付け鉄柱26を固定する。こうして、荷吊り装置20は、クレーン本体10に備えてある昇降装置11に取り付けられている。
【0017】
荷吊り装置20は、レール21、トロリ22、チェーンブロック23から構成されている。
軌道であるレール21は、トロリ22をマスト30の周囲に沿って案内するものである。レール21は断面がI形状のレールであり、図3に示すように、昇降装置11の下部に取り付けられている。また、図4に示すように、レール21は円形状をしており、マスト30を囲むように取り付けられている。
【0018】
走行装置であるトロリ22は、移動可能とするために車輪221を前後左右に備えている。左右の車輪がレール21をはさむようにレール21の溝に挿入されている。このようにして、トロリ22はレール21に沿って、マスト30の周囲を旋回することが可能である。
【0019】
吊り具であるチェーンブロック23は、荷を吊るための装置であり、チェーンブロック23に鎖231とフック232が備えられており、これらによって荷を吊ることが可能となる。そして、チェーンブロック23はトロリ22に取り付けられており、トロリ22とともにレール21に沿って、マストの周囲を旋回することが可能である。
【0020】
こうして、荷吊り装置20は、チェーンブロック23によって荷を吊ることが可能となり、レール21及びトロリ22によってマスト30の周囲を旋回することが可能となる。
【0021】
建築構造物の最上階の躯体工事が完了後、例えば、タワークレーン1が建築構造物の躯体100と接近している場合、クレーン本体10が建築構造物の躯体100と接触するため、クレーン本体10が旋回することができない。
このような場合について、以上のように構成されたタワークレーン1の解体手順を説明する。
【0022】
踊り場31にいる作業者は建築構造物の躯体100にマスト30を固定していた壁つなぎ材40を取り外す。そして、作業者はチェーンブロック23にこの取り外した壁つなぎ材40を吊れるように、チェーンブロック23をトロリ22によって旋回する。そして、作業者はこの取り外した壁つなぎ材40をチェーンブロック23のフック232に係止し、または、壁つなぎ材40を鎖231で直接結び、チェーンブロック23に吊り下げる。そして、作業者はチェーンブロック23に吊り下げた壁つなぎ材40とともにトロリ22を、レール21に沿って、マスト30の周囲を旋回する。こうして、作業者は、壁つなぎ材40をクレーン本体10が吊ることができる方向(ブーム12の起伏方向)まで容易に旋回することができる。そして、クレーン本体10が吊ることができる方向まで旋回した壁つなぎ材40を、クレーン本体10のフック13に吊り替える。そして、ブーム12を伏せて、ロープ14を伸ばし、壁つなぎ材40を地上まで吊り下げて撤去する。
【0023】
同様にして、ステー枠41と補強材42もチェーンブロック23に吊り下げ、トロリ22によって、マスト30の周囲を旋回し、クレーン本体10が吊ることができる方向(ブーム12の起伏方向)まで旋回し、クレーン本体10に吊り替えて撤去する。
【0024】
以上のように、クレーン本体10の下部で、チェーンブロック23がトロリ22によってマスト30の周囲をレール21に沿って旋回可能となり、クレーン本体10の下部にあり、クレーン本体10が吊ることができない方向にある壁つなぎ材40、ステー枠41及び補強材42などの解体部品をチェーンブロック23によって吊り、そして、チェーンブロック23及びこれらの解体部品とともにトロリ22がマスト30の周囲を旋回することによって、これらの解体部品をクレーン本体10が吊ることができる方向(ブーム12の起伏方向)まで旋回することができ、そして、クレーン本体10に吊り替え、クレーン本体10によってこれらの解体部品を吊ることが可能となり、クレーン本体10によって撤去することが可能となる。
【0025】
なお、以上の実施の形態例において、吊り具はチェーンブロック23としたが、荷を吊ることが可能な装置であればよい。
軌道はI断面形状で円形状のレールとしたが、トロリをマストの周囲に沿って、案内するものであれば形状は問わない。
壁つなぎ材40などの解体部品をチェーンブロック23のフック232、または鎖231によって吊るようにしてあるが、例えば、板材に解体部品を載せ、そして、フック232、または鎖231によって吊るように、他の部材を介して吊ってもよい。これは、クレーン本体10のフック13に吊る場合も同様である。その他、壁つなぎ材の取り外し方法、荷吊り装置の旋回方法、タワークレーン、クレーン本体、トロリ、マストの壁つなぎ材などの細部についても適宜に変更可能であることは勿論である。
【0026】
【発明の効果】
本発明によれば、例えば、クレーン本体が旋回することができない場合、前記クレーン本体が吊ることができない方向にある荷を、荷吊り装置によって吊り、そして、前記荷とともに前記荷吊り装置がマストの周囲を旋回することによって、前記荷を前記クレーン本体が吊ることができる方向(ブームの起伏方向)まで容易に旋回することができる。したがって、高所での撤去作業の安全性が向上する。また、クレーン本体自身が荷を吊ることが可能となり、例えば、タワークレーン解体用の移動式クレーンを用いて解体部品を撤去する必要がなくなり、タワークレーンの撤去作業の効率が向上する。
【0027】
本発明によれば、吊り具によって荷を吊り、クレーン下部にマストを囲むように固定されている軌道に沿ってマストの周囲を走行装置が旋回可能であり、前記荷をクレーン本体が吊ることができる方向(ブームの起伏方向)まで容易に旋回することができる。したがって、高所での撤去作業の安全性が向上する。また、クレーン本体自身が荷を吊ることが可能となり、例えば、タワークレーン解体用の移動式クレーンを用いて解体部品を撤去する必要がなくなり、タワークレーンの撤去作業の効率が向上する。
【0028】
本発明によれば、荷吊り装置によってタワークレーンの解体部品を吊り、そして、前記解体部品をクレーン本体が吊ることができる方向(ブームの起伏方向)まで旋回して、そして、前記クレーン本体によって前記解体部品を吊る。したがって、前記クレーン本体の旋回が行えない場合でも、前記クレーン本体によって撤去することが可能となり、例えば、タワークレーン解体用の移動式クレーンを用いて解体部品を撤去する必要がなくなり、タワークレーンの撤去作業の効率が向上する。
【図面の簡単な説明】
【図1】本発明を適用した一例としてのタワークレーンを示す正面図である。
【図2】図1のクレーン本体下部を拡大して示す側面図である。
【図3】図1の荷吊り装置の具体例を示す拡大図である。
【図4】図3の荷吊り装置の具体例を上方から示す図である。
【符号の説明】
1 タワークレーン
10 クレーン本体
11 昇降装置
12 ブーム
20 荷吊り装置
21 レール(軌道)
22 トロリ(走行装置)
23 チェーンブロック(吊り具)
30 マスト
40 壁つなぎ材(荷)
41 ステー枠(荷)
42 補強材(荷)[0001]
BACKGROUND OF THE INVENTION
The present invention relates to filter workpiece lane removing method easily performed removal of its dismantled parts.
[0002]
[Prior art]
When building a building structure, a tower crane is used as a means for lifting materials.
When a tower crane is used outside the building structure, a mast is first set up at a predetermined position outside the building structure, and the wall surface of the frame and the mast are firmly connected by a wall connecting material. And the crane main body which can be swung and can be raised / lowered is provided in the upper part of a mast, a mast is sequentially added upwards with the progress of frame construction, and a crane main body is raised along a mast with the raising / lowering apparatus with which the crane main body was equipped.
After the construction on the top floor is completed, the tower crane that has become unnecessary is dismantled and removed, but the dismantled parts of the tower crane, such as wall connecting materials, are suspended and removed by the crane itself.
[0003]
[Problems to be solved by the invention]
However, when the tower crane is in close proximity to the housing, the crane body is unable to turn because the crane body contacts the housing.
Therefore, when removing the dismantled parts, the direction in which the dismantled parts can be hung by the crane body itself is only the hoisting direction of the boom of the crane body. Therefore, when removing a dismantled part that is not in the boom up-and-down direction, the dismantled part is removed using a mobile crane for tower crane dismantling, but the use of the mobile crane is inefficient in removing work.
So, for example, the dismantling part is swung to the boom hoisting direction with a chain block taken from the mast so that the dismantling part can be hung by the crane itself, and then the dismantling part is suspended on the crane body, Although the dismantling parts are removed by the main body itself, it is dangerous to work at a high place.
[0004]
The present invention has been made in view of the above circumstances, and a tower that can safely turn and dismantle the dismantled parts of a tower crane such as a wall connecting material under conditions where the crane body cannot be turned. It aims at providing the removal method of a crane and a tower crane.
[0005]
[Means for Solving the Problems]
In order to solve the above-mentioned problems, the present invention provides a load suspension device (20) capable of turning around a mast in a tower crane (1) provided with a crane body (10) that can be moved up and down along the mast (30). The construction provided in the crane body is characterized.
[0006]
Thus, according to the present invention , for example, when the crane main body cannot be turned, a load such as a wall connecting material in a direction in which the crane main body cannot be hung is suspended by a load lifting device, and The load suspension device swivels around the mast together with the load, so that the load can be easily swung to the direction in which the crane main body can be hung (the boom undulation direction) and the load is hung by the crane main body. Is possible.
[0007]
The present invention relates to a track (for example, rail 21) in which the load suspension device is fixed to surround the mast at the lower part of the crane body, and a traveling device (for example, a trolley) that rotates around the mast along the track. 22), and a suspension device (for example, a chain block 23) provided in the traveling device, for suspending a load (for example, a dismantling part of a tower crane such as a
[0008]
In addition, a track | orbit guides a traveling apparatus along the circumference | surroundings of a mast. Thus, according to the present invention, hanging load by crane, Ri is pivotable der traveling device around the mast along a track which is fixed so as to surround the mast to the crane bottom, front yn It becomes possible to easily turn to the direction in which the crane main body can be hung (the boom hoisting direction) and to suspend the load by the crane main body.
[0009]
The present invention uses a tower crane provided with the above-described load suspension device, and swings the load suspension device around the mast with respect to the crane main body so that the load suspension device has at least a tower crane and a building structure (100). ) And a process of suspending a dismantling part (for example, a
[0010]
Thus, according to the present invention , the dismantling part of the tower crane is suspended by the load lifting device, and the dismantling part is swung to the direction in which the crane body can be hung around the mast (the boom undulation direction). Then, the dismantling part is suspended by the crane body. Therefore, even when the crane body cannot be turned, the crane body can be removed.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Below, the 1st example of embodiment of this invention is demonstrated with reference to figures.
FIG. 1 is a front view showing a tower crane to which the present invention is applied. 10 is a crane body, 11 is a lifting device, 12 is a boom, 13 is a hook, 20 is a load lifting device, 30 is a mast, and 40 is a wall connecting material. , 100 is a building structure.
[0012]
As shown in FIG. 1, the
[0013]
The
[0014]
The
As described above, the
[0015]
FIG. 2 is an enlarged view of the lower part of the
[0016]
The
[0017]
The
The
[0018]
The
[0019]
The
[0020]
Thus, the
[0021]
For example, when the
In such a case, a disassembly procedure of the
[0022]
The worker in the
[0023]
Similarly, the
[0024]
As described above, in the lower part of the
[0025]
In addition, in the above embodiment, although the hanging tool was the
The track is a circular rail having an I cross-sectional shape, but any shape can be used as long as it guides the trolley along the periphery of the mast.
The dismantling part such as the
[0026]
【The invention's effect】
According to the present invention , for example, when the crane main body cannot turn, a load in a direction in which the crane main body cannot be hung is hung by the load hanger, and the load hanger is mast together with the load. By turning around, the load can be easily turned to the direction in which the crane main body can be hung (boom hoisting direction). Therefore, the safety of the removal work at a high place is improved. Also, the crane body itself can suspend the load, and for example, it is not necessary to remove the dismantling parts using a mobile crane for dismantling the tower crane, and the efficiency of the tower crane removing operation is improved.
[0027]
According to the present invention, hanging load by crane, Ri traveling device pivotally der around the mast along has been fixed track to surround the mast to the crane bottom, front yn crane body flown It is possible to easily turn to the direction in which it is possible (boom hoisting direction). Therefore, the safety of the removal work at a high place is improved. Further, the crane body itself can hang the load, and for example, it is not necessary to remove the dismantling parts using a mobile crane for dismantling the tower crane, and the efficiency of the tower crane removing operation is improved.
[0028]
According to the present invention , the dismantling part of the tower crane is hung by the load lifting device, and the dismantling part is swung in a direction in which the crane main body can be hung (boom hoisting direction). Hanging dismantling parts. Therefore, even when the crane body cannot be turned, it can be removed by the crane body. For example, it is not necessary to remove the dismantling parts using a mobile crane for dismantling the tower crane, and the tower crane can be removed. Work efficiency is improved.
[Brief description of the drawings]
FIG. 1 is a front view showing a tower crane as an example to which the present invention is applied.
FIG. 2 is an enlarged side view showing a lower part of a crane body in FIG.
FIG. 3 is an enlarged view showing a specific example of the load suspension device of FIG. 1;
4 is a diagram showing a specific example of the load suspension device of FIG. 3 from above. FIG.
[Explanation of symbols]
DESCRIPTION OF
22 Trolley (travel device)
23 Chain block (suspender)
30
41 Stay frame (load)
42 Reinforcement material (load)
Claims (2)
クレーン本体に対し荷吊り装置をマストの周囲に旋回動作させて、荷吊り装置に少なくともタワークレーンと建築構造物の躯体との間に架設される解体部品を吊る工程と、
次に、この解体部品を吊った荷吊り装置をマストの周囲に旋回動作させる工程と、
次に、この荷吊り装置に吊った解体部品を前記クレーン本体に吊り替える工程と、からなることを特徴とするタワークレーン撤去方法。Using a tower crane equipped with a crane that can swivel around the mast on the crane body that can move up and down along the mast ,
Swiveling the load suspension device around the mast with respect to the crane body, and suspending at least a dismantling part constructed between the tower crane and the frame of the building structure on the load suspension device;
Next, a step of swiveling the load lifting device that suspends the dismantling part around the mast;
Next, the tower crane removal method characterized by comprising the step of suspending the dismantled parts suspended on the load suspension device to the crane body.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16580599A JP4286971B2 (en) | 1999-06-11 | 1999-06-11 | Tower crane removal method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP16580599A JP4286971B2 (en) | 1999-06-11 | 1999-06-11 | Tower crane removal method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2000351576A JP2000351576A (en) | 2000-12-19 |
| JP4286971B2 true JP4286971B2 (en) | 2009-07-01 |
Family
ID=15819339
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP16580599A Expired - Fee Related JP4286971B2 (en) | 1999-06-11 | 1999-06-11 | Tower crane removal method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4286971B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101922047B1 (en) * | 2018-05-21 | 2018-11-26 | 이은경 | bracing removing apparatus of tower crane |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104477791B (en) * | 2014-12-12 | 2016-11-23 | 中建三局集团有限公司 | Novel tower crane attached wall attachment lattice bracing frame auxiliary device |
| CN116161564A (en) * | 2022-12-09 | 2023-05-26 | 四川庞源机械工程有限公司 | Disassembly construction method of tower crane |
-
1999
- 1999-06-11 JP JP16580599A patent/JP4286971B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101922047B1 (en) * | 2018-05-21 | 2018-11-26 | 이은경 | bracing removing apparatus of tower crane |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2000351576A (en) | 2000-12-19 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109231023A (en) | The installation method of high pedestal jib crane boom system | |
| CN108002244B (en) | Hoisting system and method for high pier column steel bar formwork | |
| JP6098453B2 (en) | Jib hanger | |
| JP4286971B2 (en) | Tower crane removal method | |
| JP5473294B2 (en) | Overhead crane installation method and installation system | |
| JPH0616388A (en) | Mounting and demounting of crawler of crawler crane | |
| JP2000143139A (en) | Hoisting jig for crane | |
| CN102861881B (en) | Switching trolley for mold for core making machine | |
| JPH11147690A (en) | Low head rebar construction equipment | |
| JPH10159025A (en) | Girder carrying machine and girder carrying method | |
| JP2003054876A (en) | Device and method for attaching and detaching side frame | |
| CN215626628U (en) | Trolley for removing horizontal support of foundation pit | |
| JP2000302389A (en) | Work cage lifting device | |
| CN110205939A (en) | Trolley and method for mobile dismounting formwork of bridge rail | |
| JPH11199908A (en) | Device for dissembling/assembling blast furnace | |
| CN207581240U (en) | Pipeline conveying device | |
| CN108002251A (en) | A kind of narrow space crane | |
| JP5458385B2 (en) | crane | |
| CN217808426U (en) | Indoor detachable movable lifting plate vehicle | |
| JPH07291578A (en) | Reverse desorption device for continuous casting equipment | |
| CN119660594B (en) | Steel framework hoisting equipment and hoisting method | |
| CN217079747U (en) | Auxiliary device for steel structure installation | |
| JP2004155538A (en) | Suspension tool | |
| CN210619979U (en) | General cab lifting appliance | |
| CN219826168U (en) | T roof beam template is demolishd and is used support |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060328 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20081106 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20081111 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20081216 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20090310 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20090326 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120403 Year of fee payment: 3 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120403 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130403 Year of fee payment: 4 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140403 Year of fee payment: 5 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313532 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| LAPS | Cancellation because of no payment of annual fees |