JP4416337B2 - Construction method of the replacement composite floor slab girder bridge - Google Patents
Construction method of the replacement composite floor slab girder bridge Download PDFInfo
- Publication number
- JP4416337B2 JP4416337B2 JP2001022917A JP2001022917A JP4416337B2 JP 4416337 B2 JP4416337 B2 JP 4416337B2 JP 2001022917 A JP2001022917 A JP 2001022917A JP 2001022917 A JP2001022917 A JP 2001022917A JP 4416337 B2 JP4416337 B2 JP 4416337B2
- Authority
- JP
- Japan
- Prior art keywords
- floor slab
- support plate
- plate member
- reinforced concrete
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、既存の鉄筋コンクリート床版を打ち替えて鋼板と強度合成(結合して補強)した鉄筋コンクリート床版によって橋梁を構築する打ち替え合成床版鋼桁橋の施工方法に関する。
【0002】
【従来の技術】
橋軸方向に延設された鋼主桁によって床版を支持して構成される鋼桁橋では、その床版に鉄筋コンクリートによって形成された鉄筋コンクリート床版(以下RC床版と記す)が多く用いられている。
【0003】
RC床版は、主桁上に型枠を設けると共に内部に鉄筋を組んでコンクリートを打設することで施工され、鋼主桁とは当該鋼主桁の上面に植設されたジベルがRC床版に埋没して剪断力を伝達可能に結合される。
【0004】
近時、このようなRC床版を用いた既設の鋼桁橋において、重車両の増加や床版厚不足等によってひび割れ等の損傷が発生したRC床版に対し、その裏面に沿って位置させた鋼板を主桁に結合して補強するいわゆるアンダーデッキパネル工法と呼ばれる補強構造が知られている。
【0005】
即ち、その一例によって補強された橋梁の断面斜視図である図9に示すように、橋軸と直交する幅方向は主桁91間のハンチを除くRC床版92の下面を覆い得ると共に橋軸方向は所定長さのアンダーデッキパネル93が、その上面とRC床版92の下面との間に樹脂モルタル等の充填材を介装した状態で主桁91の腹板にブラケット94を介して締着されて構成されるものである。
【0006】
アンダーデッキパネル93は、所定板厚の支持鋼板93Aの下面側に、橋軸方向の縦リブ93Bが橋軸と直交する方向に所定間隔で複数状配設されると共に、橋軸と直交する横リブ93Cが橋軸方向に所定間隔で配設されて強固に形成され、その横リブ93Cの側端部がブラケット94に高力ボルトで締着固定されるようになっている。
【0007】
このようなアンダーデッキパネル工法による補強構造を適用することで、曲げ耐力及び剪断耐力を増すことができると共に床版の損傷の進展を抑制することができる。
【0008】
【発明が解決しようとする課題】
しかしながら、上記のごときアンダーデッキパネル工法によって補強したRC床版鋼桁橋であっても、老朽化が進行するといずれ床版の打ち替えが必要となる。
【0009】
RC床版の打ち替えは、既存のRC床版を切り刻んで除去し、主桁上に従前と同様のRC床版を再構築するのが一般的であり、新設時と同様に型枠を設けると共に内部に鉄筋を組んでコンクリートを打設しなければならないために長い時間を要し、このために施工コストも大きく、既設の床組を利用するものであるために耐久性の高い床版と成し得ないという問題があった。また、当該作業の間行わざるを得ない交通規制期間も長期間に及ぶという問題もある。
【0010】
本発明は、上記解決課題に鑑みてなされたものであって、アンダーデッキパネル工法による補強構造を適用したRC床版鋼桁橋の床版を、アンダーデッキパネルと強度合成(結合して補強)して耐久性の高いRC床版に低コスト且つ短時間で打ち替えることのできる打ち替え合成床版鋼桁橋の施工方法の提供を目的とする。
【0011】
【課題を解決するための手段】
上記目的を達成する本発明の打ち替え合成床版鋼桁橋の施工方法は、既設の鉄筋コンクリート床版の下面に沿って位置する支持板部材が鋼桁に結合され、前記既設の鉄筋コンクリート床版を前記支持板部材を介して前記鋼桁によって支持する補強構造を有する既設の鉄筋コンクリート床版鋼桁橋の当該既設の鉄筋コンクリート床版を除去し新たなコンクリートを打設して打ち替える打ち替え合成床版鋼桁橋の施工方法において、
前記既設の鉄筋コンクリート床版を前記支持板部材を残して除去し、残された当該支持板部材の上面に結合手段を配設した後、残された前記支持板部材上にコンクリートを打設して当該コンクリートを前記結合手段を介して前記支持板部材と結合して補強した鉄筋コンクリート床版を形成するようにしたことを特徴とする。
【0013】
【発明の実施の形態】
以下、添付図面を参照して本発明の実施の形態について説明する。
【0014】
図1は本発明に係る打ち替え合成床版鋼桁橋の一構成例であるRC床版鋼桁橋の横断面図であり、図2はそのA−A断面に相当する縦断面図である。尚、図1は略左半分を示して図中右側の側縁部は省略してある。また、図3は本構成例における床版の打ち替え以前の既設の鉄筋コンクリート床版鋼桁橋を示し、(A)はアンダーデッキパネル工法による補強を施す前の横断面,(B)はアンダーデッキパネル工法による補強施工後の横断面である。
【0015】
図示RC床版鋼桁橋10は、橋軸と直交する方向に所定間隔で複数設けられた橋軸方向に延びる主桁11によって、鉄筋コンクリートによる床版12を支持して構成されており、主桁11が支承を介して図示しない橋脚に支持され設置されているものである。
【0016】
主桁11は、所定高さの腹板11Wの上下端縁にそれぞれ所定幅のフランジ(上フランジ11U,下フランジ11L)を備えたI形断面の鋼桁であって、その下フランジ11Lが橋脚上に支承を介して支持されるようになっている。
【0017】
床版12は、内部に鉄筋12Aが配設された鉄筋コンクリートによって形成され、主桁11の上フランジ11Uの上面に植設されたジベル11Aによって主桁11と剪断力を伝達可能に結合している。また、その上側にはアスファルト等によって所定厚さの舗装14が施工されている。
【0018】
また、主桁11の間に支持板部材としてのアンダーデッキパネル20が架設されてアンダーデッキパネル工法による補強構造が設けられており、そのアンダーデッキパネル20の支持鋼板21の上面には結合手段としての結合構造部材30が設けられ、この結合構造部材30によって当該アンダーデッキパネル20は床版12と強度合成(結合して補強)可能に結合一体化している。
【0019】
アンダーデッキパネル20は、所定板厚の支持鋼板21の下面側に、橋軸方向の縦リブ22が橋軸と直交する方向に所定間隔で複数状配設されると共に、橋軸と直交する横リブ23が橋軸方向に所定間隔で配設されて強固に形成され、その横リブ23の端部が主桁11の腹板11Wにブラケット14を介して高力ボルトで締着されて強固に設置されるものである。尚、図中15は主桁11の間に架設された対傾構であって橋軸方向に所定間隔で配設されているものである。アンダーデッキパネル20の橋軸方向の長さは、この対傾構15と干渉しないように設定される。
【0020】
結合構造部材30は、床版12のコンクリートを除いた部分平面図である図4(A)及びその側面図である(B)に示すように、アンダーデッキパネル20の支持鋼板21の上面に植設された所定長さのネジ付きジベル31と、このジベル31にナット33で締着される補強結合形鋼32とにより構成されている。
【0021】
ジベル31は、先端にネジが形成された所定長さの軸状で、支持鋼板21の上面の補強結合形鋼32を配設すべき位置に列状に植設されている。尚、その植設位置は結合強度の必要に応じて補強結合形鋼32の配設位置以外に植設しても良いものである。
【0022】
補強結合形鋼32は、鉛直な腹板32Wの上下両縁にそれぞれ所定幅のフランジ32U,32Lが互いに逆方向に延設された断面形状Z字形の形鋼であり、その下側のフランジ32Lを貫通させたジベル31の先端ネジ部に螺合したナット33によって支持鋼板21の上面に締着固定されている。その長さは、床版12の幅方向略全域に亘り、主桁11による支持部位より側方に張り出した側端部に達しており、これによって主桁11を挟んで位置する別個のアンダーデッキパネル20が当該補強結合形鋼32を介して連結されているものである。
【0023】
上記のごとき構成の結合構造部材30が床版12のコンクリートに没入することで、主桁11に固定されたアンダーデッキパネル20と床版12とが強度合成(結合して補強)可能に結合一体化し、高剛性で耐久性の高い合成床版と成し得る。補強結合形鋼32は、床版12の下側内部に位置してその長手方向である橋軸と直交する方向に補強するため当該部位の鉄筋は少なくて良く、また、主桁11より外側の側縁部に達しているため、主桁11から側方に突出する側部の剛性を向上できるものである。
【0024】
次に、図3に示す既設のRC床版鋼桁橋10′の床版12′を打ち替えて、上記RC床版鋼桁橋10を構成する施工方法を説明する。
【0025】
まず、図3(B)に示すアンダーデッキパネル工法によって補強されたRC床版鋼桁橋10′の床版12′を適宜細分化する等して除去し、図5に部分断面図を示すようにアンダーデッキパネル20と主桁11が残存した状態とする。
【0026】
次いで、図6に示すようにアンダーデッキパネル20の支持鋼板21の上面及び主桁11の上フランジ11Uの上面にジベル31,11Aを植設すると共に、このアンダーデッキパネル20に立設されたジベル31に図7(A),(B)に拡大断面図を示すように補強結合形鋼32をナット33で締結固定して結合構造部材30を形成し、更に、補強結合形鋼32の上フランジ32Uの上側に鉄筋12Aを配筋して図8に示す状態とした後、コンクリートを打設して床版12を形成し、これによって図1に示すように施工完了するものである。
【0027】
このような施工方法によれば、アンダーデッキパネル20がコンクリート打設時に下面側の型枠として機能するために型枠設置が不要となるために施工時間を短縮でき、また、施工後はアンダーデッキパネル20が床版12と強度合成(結合して補強)されるために打ち替え前と比較して剛性が大幅に向上する。このため、同一の耐荷重であれば床版12を薄く軽く(死荷重を小さく)構成でき、同一の厚さとすれば耐荷重を大きくできるものである。
【0028】
尚、結合手段としての補強結合形鋼の形状やその固定構造は上記構成例に限らず適宜変更可能なものであり、また、必ずしも補強結合形鋼を用いなければならないものではなく、上記構成例において主桁11の上フランジ11Uに植設したジベル11Aと同様の先端部に大径部を有するジベルを多数植設しても良いものである。
【0029】
【発明の効果】
以上述べたように、本発明に係る打ち替え合成床版鋼桁橋の施工方法によれば、既設の鉄筋コンクリート床版の下面に沿って位置する支持板部材が鋼桁に結合され、前記既設の鉄筋コンクリート床版を前記支持板部材を介して前記鋼桁によって支持する補強構造を有する既設の鉄筋コンクリート床版鋼桁橋の当該既設の鉄筋コンクリート床版を除去し新たなコンクリートを打設して打ち替える打ち替え合成床版鋼桁橋の施工方法において、前記既設の鉄筋コンクリート床版を前記支持板部材を残して除去し、残された当該支持板部材の上面に結合手段を配設した後、残された前記支持板部材上にコンクリートを打設して当該コンクリートを前記結合手段を介して前記支持板部材と結合して補強した鉄筋コンクリート床版を形成するようにしたので、鉄筋コンクリート床版を除去し、支持板部材の上面に結合手段を配設した後、コンクリートを打設して支持板部材と結合した鉄筋コンクリート床版を形成することにより、支持板部材が鉄筋コンクリート床版構築の際のコンクリート打設時に下面側の型枠として機能するために型枠設置が不要となり、合理的な施工が可能となって工期も短縮できる。また、施工後は支持板部材が鉄筋コンクリート床版と強度合成(結合して補強)されるために打ち替え前と比較して剛性が大幅に向上する。このため、同一の耐荷重であれば鉄筋コンクリート床版を薄く軽く構成でき、同一の厚さとすれば耐荷重を大きくできるものである。
【図面の簡単な説明】
【図1】本発明に係る打ち替え合成床版鋼桁橋の一構成例である鉄筋コンクリート床版鋼桁橋の横断面図である。
【図2】そのA−A断面図に相当する縦断面図である。
【図3】(A)はアンダーデッキパネル工法による補強を施す前のRC床版鋼桁橋の横断面,(B)はアンダーデッキパネル工法による補強施工後の横断面である。
【図4】(A)は床版のコンクリートを除いた部分平面図,(B)はその側面図である。
【図5】施工工程を説明する断面図である。
【図6】施工工程を説明する断面図である。
【図7】結合構造部材の設置工程を説明する部分断面図である。
【図8】施工工程を説明する断面図である。
【図9】従来例としてのアンダーデッキパネル工法によって補強された橋梁の断面斜視図である。
【符号の説明】
10 RC床版鋼桁橋(鉄筋コンクリート床版鋼桁橋)
11 主桁
12 床版(鉄筋コンクリート床版)
20 アンダーデッキパネル(支持板部材)
30 結合構造部材(結合手段)[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method of a replacement composite slab steel girder bridge in which an existing reinforced concrete floor slab is replaced and a bridge is constructed by a reinforced concrete floor slab that is strength-combined (bonded and reinforced) with a steel plate.
[0002]
[Prior art]
In a steel girder bridge constructed by supporting a slab with a steel main girder extending in the direction of the bridge axis, reinforced concrete slabs (hereinafter referred to as RC slabs) formed of reinforced concrete are often used for the slabs. ing.
[0003]
RC floor slabs are constructed by placing a formwork on the main girder and placing concrete inside the steel bar. The steel main girder is a gibber planted on the upper surface of the steel main girder. It is buried in the plate and coupled so that shear force can be transmitted.
[0004]
Recently, in existing steel girder bridges using such RC slabs, the RC slabs that have been damaged due to the increase in heavy vehicles, lack of floor slab thickness, etc. are positioned along the back side. A so-called under deck panel method is known in which a steel plate is joined to a main girder for reinforcement.
[0005]
That is, as shown in FIG. 9 which is a cross-sectional perspective view of a bridge reinforced by the example, the width direction orthogonal to the bridge axis can cover the lower surface of the
[0006]
In the under
[0007]
By applying such a reinforcing structure by the under deck panel method, it is possible to increase the bending strength and the shear strength and to suppress the progress of damage to the floor slab.
[0008]
[Problems to be solved by the invention]
However, even the RC slab steel girder bridge reinforced by the under deck panel construction method as described above will eventually need to be replaced with a new slab.
[0009]
For RC floor slab replacement, it is common to cut and remove the existing RC floor slab and reconstruct the same RC floor slab on the main girder as before. In addition, it takes a long time to lay concrete with steel bars inside, and for this reason, the construction cost is high and the existing floor assembly is used. There was a problem that it could not be achieved. There is also a problem that the traffic regulation period that must be performed during the work is long.
[0010]
The present invention has been made in view of the above-mentioned problem, and the floor deck of the RC floor slab steel girder bridge to which the reinforcement structure by the under deck panel method is applied is combined with the under deck panel ( strengthened by combining ). Then, it aims at provision of the construction method of the replacement synthetic floor slab steel girder bridge which can be replaced to RC floor slab with high durability at low cost for a short time.
[0011]
[Means for Solving the Problems]
The construction method of the replacement composite floor slab steel girder bridge of the present invention that achieves the above object is that the supporting plate member positioned along the lower surface of the existing reinforced concrete floor slab is coupled to the steel girder, and the existing reinforced concrete floor slab is used. Replacing composite floor slab that removes existing reinforced concrete floor slab of existing reinforced concrete floor slab steel girder bridge having reinforcing structure supported by said steel girder via said support plate member and replaces it with new concrete. In the construction method of steel girder bridge,
The existing reinforced concrete floor slab is removed leaving the support plate member, and a coupling means is disposed on the remaining upper surface of the support plate member, and then concrete is placed on the remaining support plate member. A reinforced concrete slab reinforced by combining the concrete with the support plate member via the coupling means is formed.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.
[0014]
FIG. 1 is a transverse cross-sectional view of an RC floor slab steel girder bridge which is an example of the structure of a replaceable composite floor slab girder bridge according to the present invention, and FIG. 2 is a vertical cross-sectional view corresponding to the AA cross section thereof. . Note that FIG. 1 shows a substantially left half, and the right side edge in the figure is omitted. 3 shows the existing reinforced concrete floor slab steel girder bridge before the floor slab replacement in this configuration example, (A) is a cross section before reinforcement by the under deck panel method, and (B) is an under deck. It is a cross section after reinforcement construction by a panel construction method.
[0015]
The illustrated RC floor slab
[0016]
The
[0017]
The
[0018]
In addition, an under
[0019]
The under
[0020]
The connecting
[0021]
The
[0022]
The reinforcing
[0023]
When the connecting
[0024]
Next, a construction method for replacing the floor slab 12 'of the existing RC floor slab girder bridge 10' shown in FIG.
[0025]
First, the floor slab 12 'of the RC floor slab steel girder bridge 10' reinforced by the under deck panel method shown in FIG. 3 (B) is removed by appropriately subdividing it, and a partial sectional view is shown in FIG. The under
[0026]
Next, as shown in FIG. 6, the
[0027]
According to such a construction method, since the
[0028]
In addition, the shape of the reinforced bonded section steel as a coupling means and its fixing structure are not limited to the above configuration example, and can be changed as appropriate, and the reinforced coupled section steel is not necessarily used, and the above configuration example In FIG. 8, a large number of gibber having a large diameter portion at the tip end similar to the gibber 11A planted on the upper flange 11U of the
[0029]
【The invention's effect】
As described above, according to the construction method of the replaceable composite slab steel girder bridge according to the present invention, the support plate member positioned along the lower surface of the existing reinforced concrete floor slab is coupled to the steel girder, and the existing girder is installed. The existing reinforced concrete floor slab steel girder bridge having a reinforcing structure for supporting the reinforced concrete floor slab by the steel girder through the support plate member is removed, and the existing reinforced concrete floor slab is removed and replaced with new concrete. In the construction method of the replacement composite slab steel girder bridge, the existing reinforced concrete floor slab is removed leaving the support plate member, and after the coupling means is disposed on the upper surface of the remaining support plate member, the remaining is left Concrete is placed on the support plate member, and the concrete is combined with the support plate member via the coupling means to form a reinforced concrete slab. Then, after removing the reinforced concrete slab and arranging the coupling means on the upper surface of the support plate member, the support plate member is reinforced concrete floor by placing concrete and forming the reinforced concrete floor slab combined with the support plate member. Since it functions as a formwork on the lower surface side when placing concrete during plate construction, it is not necessary to install a formwork, enabling rational construction and shortening the construction period. In addition, since the support plate member is strength-combined (bonded and reinforced) with the reinforced concrete floor slab after construction, the rigidity is greatly improved compared to before replacement. For this reason, the reinforced concrete floor slab can be configured to be thin and light if the load is the same, and the load can be increased if the thickness is the same.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view of a reinforced concrete floor slab steel girder bridge which is an example of the configuration of a replaceable composite floor slab steel girder according to the present invention.
FIG. 2 is a longitudinal sectional view corresponding to the AA sectional view.
3A is a cross section of an RC floor slab steel girder bridge before reinforcement by the under deck panel method, and FIG. 3B is a cross section after reinforcement work by the under deck panel method.
4A is a partial plan view of a floor slab with concrete removed, and FIG. 4B is a side view thereof.
FIG. 5 is a cross-sectional view illustrating a construction process.
FIG. 6 is a cross-sectional view illustrating a construction process.
FIG. 7 is a partial cross-sectional view illustrating an installation process of a coupling structural member.
FIG. 8 is a cross-sectional view illustrating a construction process.
FIG. 9 is a cross-sectional perspective view of a bridge reinforced by an under deck panel method as a conventional example.
[Explanation of symbols]
10 RC floor slab steel girder bridge (Reinforced concrete floor slab girder bridge)
11
20 Under deck panel (support plate member)
30 Joining structural member (joining means)
Claims (1)
前記既設の鉄筋コンクリート床版を前記支持板部材を残して除去し、残された当該支持板部材の上面に結合手段を配設した後、残された前記支持板部材上にコンクリートを打設して当該コンクリートを前記結合手段を介して前記支持板部材と結合して補強した鉄筋コンクリート床版を形成するようにしたことを特徴とする打ち替え合成床版鋼桁橋の施工方法。Support plate member positioned along the lower surface of the existing concrete deck is bonded to the steel girder, existing reinforced concrete floor with a reinforcing structure for supporting a reinforced concrete floor slab of the existing by the steel girder through said support plate member In the construction method of the replacement composite floor slab girder bridge in which the existing reinforced concrete floor slab of the plate steel girder bridge is removed and new concrete is placed and replaced,
The reinforced concrete slab of the existing removed leaving the support plate member, after providing the coupling means on the upper surface of the remaining said support plate member, and Da設the concrete remaining the support plate member on construction method threshing replacement synthesis slab steel girder bridges, characterized in that as the concrete to form the reinforced concrete floor slab reinforced in conjunction with the support plate member through said coupling means.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2001022917A JP4416337B2 (en) | 2001-01-31 | 2001-01-31 | Construction method of the replacement composite floor slab girder bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2001022917A JP4416337B2 (en) | 2001-01-31 | 2001-01-31 | Construction method of the replacement composite floor slab girder bridge |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2002227133A JP2002227133A (en) | 2002-08-14 |
| JP4416337B2 true JP4416337B2 (en) | 2010-02-17 |
Family
ID=18888260
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2001022917A Expired - Fee Related JP4416337B2 (en) | 2001-01-31 | 2001-01-31 | Construction method of the replacement composite floor slab girder bridge |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP4416337B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105507146A (en) * | 2015-11-27 | 2016-04-20 | 中铁大桥勘测设计院集团有限公司 | Glass bridge floor stiffening girder used for pedestrian suspension bridge |
Families Citing this family (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008169573A (en) * | 2007-01-10 | 2008-07-24 | Mitsui Eng & Shipbuild Co Ltd | Minority main girder bridge |
| CN102995567B (en) * | 2012-12-24 | 2014-12-03 | 武汉理工大学 | Preparation method of cement concrete and asphalt concrete composite bridge deck pavement structure capable of eliminating steel-bar net pieces |
| CN104060547B (en) * | 2014-07-10 | 2016-02-10 | 中交二航局第四工程有限公司 | A kind of temporary steel trestle construction method |
| CN104110002B (en) * | 2014-07-10 | 2017-09-19 | 中铁大桥局武汉桥梁特种技术有限公司 | A method for replacing steel truss bridge deck |
| CN104314003A (en) * | 2014-08-06 | 2015-01-28 | 重庆交通大学 | Long-life reinforcing mesh flexible fiber reinforced concrete bridge deck pavement structure |
| CN105297642B (en) * | 2015-11-06 | 2016-11-23 | 沈阳建筑大学 | A kind of bent cap external prestressing strengthening structure and construction method thereof |
| KR101840763B1 (en) * | 2017-05-02 | 2018-03-21 | 주식회사 신원알피씨 | Cantilever bridge with t-type fixinf support bracket construction method |
| KR102080492B1 (en) * | 2017-08-04 | 2020-02-24 | 한국도로공사 | Construction method for cantilever in steel composite girder bridge |
| CN107815968B (en) * | 2017-10-30 | 2023-04-11 | 中铁二十四局集团安徽工程有限公司 | Large-beam combined steel plate beam bridge deck cast-in-place construction sliding formwork system and application thereof |
| CN108221648B (en) * | 2018-03-01 | 2023-07-28 | 华侨大学 | New Concrete-filled Steel Tube Bridge Pier with Restoration Function Embedded with Mild Steel |
| CN109778660A (en) * | 2019-03-18 | 2019-05-21 | 浙江兴土桥梁专用装备制造有限公司 | Steel bridges installed with fabricated abutments |
| KR102542437B1 (en) * | 2022-06-13 | 2023-06-14 | 주식회사 하이드로코리아 | Composite girder with steel slab and composite girder bridge constrution method using the same |
-
2001
- 2001-01-31 JP JP2001022917A patent/JP4416337B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105507146A (en) * | 2015-11-27 | 2016-04-20 | 中铁大桥勘测设计院集团有限公司 | Glass bridge floor stiffening girder used for pedestrian suspension bridge |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2002227133A (en) | 2002-08-14 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP4416337B2 (en) | Construction method of the replacement composite floor slab girder bridge | |
| JP4347500B2 (en) | Bridge girder | |
| KR100483083B1 (en) | Composite Deck having Frame and Concrete | |
| JP2003119718A (en) | Bridge | |
| CN109594484B (en) | Bridge reinforcing device, reinforcing structure, reinforcing construction method and reinforcing repair method | |
| KR101037478B1 (en) | Partial recessed composite deck | |
| CN111851264A (en) | A joint structure of steel-UHPC composite board | |
| WO1998038386A1 (en) | Pre-cast concrete decking for load supporting structures | |
| JP5833616B2 (en) | Construction method of joint structure of concrete precast slab for bridge | |
| JPH0959929A (en) | Repair / reinforcement method for the upper surface of reinforced concrete floor slabs | |
| JPH06101212A (en) | Reinforced structure of reinforced concrete floor slab | |
| JP4021588B2 (en) | Beam / floor concrete casting method and beam / floor structure by concrete casting | |
| JP4293696B2 (en) | Construction method of composite floor slab bridge | |
| JP3586829B2 (en) | Repair construction method for joints of viaduct | |
| CN110392758A (en) | Hybrid Prestressed Concrete Beam with Inverted T Section and Its Panel Construction Method | |
| JP4627383B2 (en) | Replaced steel deck bridge | |
| JPH11293626A (en) | Bridge structure | |
| JP4359731B2 (en) | Method of replacing concrete floor slab bridge with steel slab and structure of replacing concrete floor slab bridge with steel slab | |
| JP2508677B2 (en) | Reinforcement method of bridge reinforced concrete slab | |
| KR101044469B1 (en) | Prestressed concrete girders with extruded beams | |
| JP2008088634A (en) | Steel concrete composite slab | |
| KR102325276B1 (en) | Half Precast Concrete continuous slab and construction method of the same | |
| CN212247834U (en) | A joint structure of steel-UHPC composite board | |
| KR100485060B1 (en) | Joint between steel superstructure and reinforced concrete substructure of rahmen typed hybrid bridge | |
| KR102139851B1 (en) | PSC Girder With Variable Cross Section And Slab Construction Method Using Thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20071004 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090624 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090908 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20091027 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20091119 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20091124 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 4416337 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121204 Year of fee payment: 3 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313115 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121204 Year of fee payment: 3 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121204 Year of fee payment: 3 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121204 Year of fee payment: 3 |
|
| S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313117 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121204 Year of fee payment: 3 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131204 Year of fee payment: 4 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| LAPS | Cancellation because of no payment of annual fees |