Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP4847790B2 - Steel pipe tower brace assembly reinforcement structure - Google Patents
[go: Go Back, main page]

JP4847790B2 - Steel pipe tower brace assembly reinforcement structure - Google Patents

Steel pipe tower brace assembly reinforcement structure Download PDF

Info

Publication number
JP4847790B2
JP4847790B2 JP2006149917A JP2006149917A JP4847790B2 JP 4847790 B2 JP4847790 B2 JP 4847790B2 JP 2006149917 A JP2006149917 A JP 2006149917A JP 2006149917 A JP2006149917 A JP 2006149917A JP 4847790 B2 JP4847790 B2 JP 4847790B2
Authority
JP
Japan
Prior art keywords
horizontal
steel pipe
steel
pair
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2006149917A
Other languages
Japanese (ja)
Other versions
JP2007321359A (en
Inventor
真二 岩尾
Original Assignee
日本鉄塔工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 日本鉄塔工業株式会社 filed Critical 日本鉄塔工業株式会社
Priority to JP2006149917A priority Critical patent/JP4847790B2/en
Publication of JP2007321359A publication Critical patent/JP2007321359A/en
Application granted granted Critical
Publication of JP4847790B2 publication Critical patent/JP4847790B2/en
Anticipated expiration legal-status Critical
Active legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)
  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a bracket assembly reinforcing structure of a steel-pipe steel tower, which enables a bracket assembly of the existing steel-pipe steel tower to be simply/rapidly reinforced on a job site. <P>SOLUTION: The bracket assembly of the steel-pipe steel tower comprises right and left bracket portions which overhang in a rightward and leftward horizontal directions (X-directions) from a top portion of a steel-tower body. Each of the right and left bracket portions comprises a pair of horizontal overhanging materials and a pair of diagonal lifting materials. A free end of the horizontal overhanging material and that of the diagonal lifting material are joined to each other by means of a joint. The bracket assembly reinforcing structure of the steel-pipe steel tower comprises: front and back supporting materials which are laid in forward and backward horizontal directions (Y-directions) near a base end of the diagonal lifting material of each of the right and left bracket portions; a horizontal reinforcing material which is laid in the horizontal direction (X-direction) on each of the front and back supporting materials; a diagonal reinforcing material (stay) for connecting both end portions of each of the front and back supporting materials and an intermediate portion between both the ends of the horizontal reinforcing material in a horizontal plane (XY-surface); a tension adjusting joint which is provided in the intermediate portion of the horizontal reinforcing material; and a thrust-up material which is diagonally connected to both the ends of each of the front and back supporting materials and the steel-tower body in a vertical direction (Z-direction). <P>COPYRIGHT: (C)2008,JPO&amp;INPIT

Description

本発明は、鋼管鉄塔の腕金組立体補強構造に関し、特に、腕金釣合方式を用いた鋼管鉄塔腕金組立体の斜め吊上げ材取付け部補強構造に関する。   The present invention relates to a reinforcing structure for a steel tube tower arm bracket assembly, and more particularly, to a structure for reinforcing an oblique lifting member attachment portion of a steel pipe tower arm metal assembly using an arm metal balance method.

鋼管鉄塔は、送電、送信等に広く用いられている。例えば、送電用鋼管鉄塔は、鉄塔本体頂部から水平方向左右に張り出した腕金組立体を有している。腕金組立体には、送電線等が懸架され、腕金組立体の斜め吊上げ材取付け部には送電線等の自重および隣接する鉄塔の高低差による電線張力の引下げ成分が作用し、長期間にわたって内部引張応力が継続的に作用する。台風等の強風によって送電線等には過酷な衝撃荷重が作用し、腕金組立体の斜め吊上げ材取付け部には局部的に大きな引張応力度が発生する。   Steel pipe towers are widely used for power transmission and transmission. For example, a steel pipe tower for power transmission has a brace assembly that protrudes horizontally from the top of the tower main body. A transmission line etc. is suspended in the armrest assembly, and the component for lowering the wire tension due to the weight of the power transmission line etc. and the height difference between adjacent steel towers acts on the slanted lifting material attachment part of the armrest assembly, and the The internal tensile stress acts continuously throughout. A severe impact load acts on the power transmission line or the like due to a strong wind such as a typhoon, and a large tensile stress is locally generated in the slanted lifting material mounting portion of the armor assembly.

設立初期の鋼管鉄塔については未だ節点耐力の調査・分析が十分に行われていない。従って、ガセットプレートと鋼管からなる継手のうち軽微な部位では補強もなされていないのが実情である。また、この継手の終局耐力時には中空鋼管の断面は局部的に偏平化し、この断面変形が継手耐力を低下させる一因となる。   Investigation and analysis of the nodal strength of the steel pipe tower in the early days of establishment has not been sufficiently conducted. Therefore, the fact is that the light parts of the joint made of the gusset plate and the steel pipe are not reinforced. Further, at the time of ultimate strength of the joint, the cross section of the hollow steel pipe is locally flattened, and this cross-sectional deformation contributes to lowering the joint strength.

そのため、中空鋼管内にセメントを流し込む補強方法も考えられるが、鋼管鉄塔自体の重量が増すばかりではなく、山岳地帯等の現場においては、セメント注入作業は極めて困難である。   For this reason, a reinforcing method in which cement is poured into the hollow steel pipe is conceivable. However, not only the weight of the steel pipe tower itself increases, but also cement injection work is extremely difficult in a site such as a mountainous area.

特に、腕金組立体は鉄塔本体の頂部付近にあるので、その補強作業は一層困難を極めている。
特願平10‐083556号公報
In particular, since the brace assembly is near the top of the steel tower body, the reinforcement work is more difficult.
Japanese Patent Application No. 10-083556

本発明の課題は、既設鋼管鉄塔の腕金組立体を現場にて簡易・迅速に補強できる鋼管鉄塔の腕金組立体補強構造を得ることにある。   It is an object of the present invention to obtain a steel pipe tower arm brace assembly reinforcing structure that can easily and quickly reinforce an existing steel pipe tower arm bracket assembly on site.

鋼管鉄塔の腕金組立体は、鉄塔本体頂部から左右水平方向(X方向)張り出した右側腕金部と左側腕金部とを有する。各側腕金部は1対の水平張出し材と1対の斜め吊上げ材とからなる。水平張出し材および斜め吊上げ材の各自由端がジョイントによって相互に結合される。鋼管鉄塔の腕金組立体補強構造は、各側腕金部の斜め吊上げ材の基端付近で前後水平方向(Y方向)に差し渡された前後支持材と、各前後支持材に左右水平方向(X方向)に差し渡された水平補強材と、各前後支持材の両端部分と水平補強材の両端中間部分とを水平面(XY面)内で連結する斜補強材(ステー)と、水平補強材の中間に設けられた張力調整ジョイントと、各前後支持材の両端部と鉄塔本体とに上下鉛直方向(Z方向)斜めに連結された突上げ材とからなる。   The arm assembly of the steel pipe tower has a right arm part and a left arm part protruding from the top of the steel tower body in the horizontal direction (X direction). Each side arm part is composed of a pair of horizontal projecting members and a pair of diagonal lifting members. The free ends of the horizontal overhanging material and the oblique lifting material are connected to each other by a joint. The steel pipe tower arm brace assembly reinforcement structure consists of front and rear support members that are passed in the front and rear horizontal direction (Y direction) near the base end of the slanted lifting member of each side arm portion, and left and right horizontal directions to each front and rear support member Horizontal reinforcement members (in the X direction), diagonal reinforcement members (stays) that connect both end portions of each of the front and rear support members and intermediate end portions of the horizontal reinforcement members in a horizontal plane (XY plane), and horizontal reinforcement It consists of a tension adjusting joint provided in the middle of the material, and a push-up material that is obliquely connected to both ends of each front and rear support material and the tower main body in the vertical and vertical directions (Z direction).

ここで、左右水平方向(X方向)とは、鋼管鉄塔の腕金組立体の突出方向に平行な左右水平方向を言う。上下鉛直方向(Z方向)とは、基礎土台に関して上下鉛直方向を言う。前後水平方向(Y方向)とは、の腕金組立体の突出方向に直交する前後奥行き方向を言う。   Here, the horizontal direction (X direction) refers to the horizontal direction parallel to the protruding direction of the armrest assembly of the steel pipe tower. The vertical direction (Z direction) refers to the vertical direction with respect to the foundation foundation. The front-rear horizontal direction (Y direction) refers to the front-rear depth direction perpendicular to the protruding direction of the armband assembly.

張力調整ジョイントは、水平補強材の中間部を左右水平方向(X方向)に分離離間し、各離間端に対向フランジを設け、各フランジ間にスペーサを挿入し、各フランジおよびスペーサを一体にボルト締めした構成になっている。張力調整ジョイントにおけるボルト締付け力は、各側腕金部の1対の斜め吊上げ材の基端間を連結する鉄塔本体の左右水平方向の吊材つなぎ水平材に作用する張力の約50−100%に設定されることが好ましい。50%以下では、補強効果が少なく、100%以上では吊材つなぎ水平材が鉛直支柱材に取付けられるガセットプレートの取付部に過大な応力度が発生する。   The tension adjustment joint separates and separates the middle part of the horizontal reinforcement in the horizontal and horizontal directions (X direction), provides opposing flanges at each spaced end, inserts a spacer between the flanges, and bolts the flange and the spacer together. It has a tightened configuration. The bolt tightening force in the tension adjusting joint is about 50-100% of the tension acting on the horizontal member of the horizontal horizontal connecting member of the tower body connecting the base ends of the pair of diagonal lifting members of each side armor part. It is preferable to set to. If it is 50% or less, the reinforcing effect is small, and if it is 100% or more, an excessive stress level is generated in the attachment portion of the gusset plate where the hanging material connecting horizontal material is attached to the vertical support material.

各前後支持材の両端部分と水平補強材の両端中間部分とを水平面(XY面)内で連結する斜補強材(ステー)を設けることが好ましい。   It is preferable to provide a diagonal reinforcing material (stay) that connects both end portions of each front and rear support member and both end intermediate portions of the horizontal reinforcing material within a horizontal plane (XY plane).

本発明の鋼管鉄塔の腕金組立体補強構造は、構成が簡単であり、既設鋼管鉄塔の現場で腕金組立体を簡易・迅速に補強できる。   The steel pipe tower arm brace assembly reinforcing structure of the present invention has a simple structure, and can easily and quickly reinforce the arm bracket assembly at the site of the existing steel pipe tower.

図1−8を参照して、本発明に基づく鋼管鉄塔の腕金組立体補強構造の実施例について説明する。本発明が適用される鋼管鉄塔の代表例として、送電用鋼管鉄塔を図1−3に示す。送電用鋼管鉄塔1は、鉄塔本体頂部に腕金組立体2が設けられている。腕金組立体2は、送電線等(図示せず)を懸架する。ここで、左右水平方向(X方向)とは、図1−3に示すように、腕金組立体2の突出方向に平行な左右水平方向を言う。上下鉛直方向(Z方向)とは、基礎土台(図示せず)に関して上下鉛直方向を言う。前後水平方向(Y方向)とは、腕金組立体2の突出方向に直交する前後奥行き方向を言う。   With reference to FIGS. 1-8, the Example of the armrest assembly reinforcement structure of the steel pipe tower based on this invention is described. As a typical example of a steel pipe tower to which the present invention is applied, a steel pipe tower for power transmission is shown in FIG. The steel pipe tower 1 for power transmission is provided with a brace assembly 2 at the top of the tower body. The armband assembly 2 suspends a transmission line or the like (not shown). Here, the horizontal horizontal direction (X direction) refers to a horizontal horizontal direction parallel to the protruding direction of the bracelet assembly 2 as shown in FIG. The vertical direction (Z direction) refers to the vertical direction with respect to a foundation foundation (not shown). The front-rear horizontal direction (Y direction) refers to the front-rear depth direction orthogonal to the protruding direction of the armband assembly 2.

腕金組立体2は、鉄塔本体頂部から左右水平方向(X方向)に張り出した右側腕金部2Rと左側腕金部2Lとからなる。右側腕金部2Rは1対の水平張出し材21Rと1対の斜め吊上げ材22Rとからなり、また、左側腕金部2Lは1対の水平張出し材21Lと1対の斜め吊上げ材22Lとからなる。右側腕金部2Rの1対の水平張出し材21R、21Rおよび1対の斜め吊上げ材22R、22Rの各自由端がジョイント23Rによって相互に結合される。同様に、左側腕金部2Lの1対の水平張出し材21L、21Lおよび1対の斜め吊上げ材22L、22Lの各自由端がジョイント23Lによって相互に結合される。   The arm metal assembly 2 includes a right arm metal part 2R and a left arm metal part 2L that protrude in the horizontal direction (X direction) from the top of the steel tower body. The right arm part 2R is composed of a pair of horizontal projecting members 21R and a pair of oblique lifting members 22R, and the left arm part 2L is composed of a pair of horizontal projecting members 21L and a pair of oblique lifting members 22L. Become. The free ends of the pair of horizontal projecting members 21R and 21R and the pair of oblique lifting members 22R and 22R of the right arm portion 2R are coupled to each other by a joint 23R. Similarly, the free ends of the pair of horizontal projecting members 21L, 21L and the pair of oblique lifting members 22L, 22L of the left arm portion 2L are coupled to each other by a joint 23L.

本発明に基づく鋼管鉄塔の腕金組立体補強構造は、図4、5に最もよく示すように、右側腕金部2Rの1対の斜め吊上げ材22R、22Rの基端付近で前後方向(Y方向)に差し渡された前後支持材24Rと、左側腕金部2Lの1対の斜め吊上げ材22L、22Lの基端付近で前後方向(Y方向)に差し渡された前後支持材24Lと、各前後支持材24R、24Lに左右水平方向(X方向)に差し渡された水平補強材25と、各前後支持材の両端部分と水平補強材の両端中間部分とを水平面(XY面)内で連結する斜補強材(ステー)30と、水平補強材25の中間に設けられた張力調整ジョイント26と、右側腕金部2Rの前後支持材24Rの両端部と鉄塔本体とに上下鉛直方向(Z方向)斜めに連結された突上げ材27Rと、左側腕金部2Lの前後支持材24Lの両端部と鉄塔本体とに上下鉛直方向(Z方向)斜めに連結された突上げ材27Lとからなる。図4、5に示す実施例では、前後支持材24R、24Lが連結される鉄塔本体は、水平張出し材21R、21Lの基端部ジョイント28R、28Lである。   As shown best in FIGS. 4 and 5, the steel pipe tower arm brace assembly reinforcing structure according to the present invention is provided in the front-rear direction (Y The front and rear support members 24R passed in the direction), and the front and rear support members 24L passed in the front and rear direction (Y direction) near the base ends of the pair of oblique lifting members 22L and 22L of the left arm 2L, A horizontal reinforcing member 25 passed in the left and right horizontal direction (X direction) to each of the front and rear support members 24R and 24L, and both end portions of each front and rear support member and both end intermediate portions of the horizontal reinforcing member in a horizontal plane (XY plane). Up and down vertical direction (Z) to the diagonal reinforcement member (stay) 30 to be connected, the tension adjustment joint 26 provided in the middle of the horizontal reinforcement member 25, both ends of the front and rear support member 24R of the right armrest portion 2R, and the tower body. Direction) Push-up material 27R connected diagonally, and left armband part L consists of a vertical (Z direction) the push-up member 27L connected diagonally to the two ends and the steel tower body around support 24L of. 4 and 5, the steel tower main body to which the front and rear support members 24R and 24L are connected is the base end joints 28R and 28L of the horizontal projecting members 21R and 21L.

張力調整ジョイント26は、図6〜8に最もよく示すように、水平補強材25の中間部を左右水平方向(X方向)に分離離間し、各離間端に対向フランジ261、261を設け、各フランジ261間にスペーサ262を挿入し、各フランジ261およびスペーサ262を一体にボルト263によって締め付ける構成になっている。張力調整ジョイント26におけるボルト締付け力は、各側腕金部2R、2Lの1対の斜め吊上げ材22R、22Lの基端間を連結する鉄塔本体の左右水平方向の吊材つなぎ水平材29(図5参照)に作用する張力の約50〜100%に設定されることが好ましい。50%以下では、補強効果が少なく、100%以上では吊材つなぎ水平材が鉛直支柱材に取付けられるガセットプレートの取付部に過大な応力度が発生する。   6-8, the tension adjusting joint 26 separates and separates the intermediate portion of the horizontal reinforcing member 25 in the left and right horizontal direction (X direction), and is provided with opposing flanges 261 and 261 at each separated end. A spacer 262 is inserted between the flanges 261 and the flanges 261 and the spacers 262 are tightened together by bolts 263. The bolt tightening force in the tension adjusting joint 26 is obtained by connecting the horizontal ends 29 of the tower main body connecting the base ends of the pair of oblique lifting members 22R and 22L of the side arm portions 2R and 2L in the horizontal direction (see FIG. 5) is preferably set to about 50 to 100% of the tension acting on. If it is 50% or less, the reinforcing effect is small, and if it is 100% or more, an excessive stress level is generated in the attachment portion of the gusset plate where the hanging material connecting horizontal material is attached to the vertical support material.

水平補強材25の取付け位置を安定化させ、かつ、前後支持材を曲げ材でなくトラスの軸力材とするために、図3、4に示すように、各前後支持材24R、24Lの両端部分と水平補強材25の両端中間部分とを水平面(XY面)内で連結する斜補強材(ステー)30を設けることが好ましい。   In order to stabilize the mounting position of the horizontal reinforcing member 25 and to use the truss axial force member as the front and rear support member instead of the bending member, both ends of the front and rear support members 24R and 24L as shown in FIGS. It is preferable to provide an oblique reinforcing member (stay) 30 that connects the portion and the intermediate portion at both ends of the horizontal reinforcing member 25 in a horizontal plane (XY plane).

次に、図9−11を参照して、本発明に基づく鋼管鉄塔の腕金組立体補強構造の作用について説明する。   Next, with reference to FIGS. 9-11, the effect | action of the armrest assembly reinforcement structure of the steel pipe tower based on this invention is demonstrated.

図9は、従来の鋼管鉄塔1の腕金組立体2の側面図であって、(A)図は腕金組立体2の概略骨組み構造を示し、(B)図は(A)図の骨組みに作用する荷重を示す。従来の鋼管鉄塔1には、(A)図に示すように、腕金組立体補強構造を構成する水平補強材および突上げ材が設けられていない。従って、(B)図に示すように、右側および左側腕金部2Rおよび2Lが懸架する送電線等(図示せず)の各重量W1およびW2は、鉄塔本体の吊材つなぎ水平材29および鉛直支柱材31にそれぞれ水平分力H1、H2および鉛直分力V1、V2として作用する。   FIG. 9 is a side view of the armrest assembly 2 of the conventional steel pipe tower 1, wherein FIG. 9 (A) shows a schematic framework structure of the armrest assembly 2, and FIG. 9 (B) shows the framework of FIG. The load acting on is shown. As shown in FIG. 1A, the conventional steel pipe tower 1 is not provided with the horizontal reinforcing member and the push-up member that constitute the armrest assembly reinforcing structure. Therefore, as shown in FIG. (B), the weights W1 and W2 of the transmission line (not shown) on which the right and left arm portions 2R and 2L are suspended are the horizontal connecting material 29 and the vertical material connecting the suspension material of the tower body. It acts on the column material 31 as horizontal component forces H1 and H2 and vertical component forces V1 and V2, respectively.

図10は、図9と同様な図面であって、従来の鋼管鉄塔1の腕金組立体2に水平補強材25のみを設けた場合において、(A)図は腕金組立体2の概略骨組み構造を示し、(B)図は(A)図の骨組みに作用する荷重を示し、(C)図は斜め吊上げ材22R、22Lに作用する曲げモーメントを示す。(B)図に示すように、水平補強材25によって初期張力Hを導入した場合、初期張力Hによって水平分力H1、H2は軽減される。導入初期張力Hは、左右水平方向の吊材つなぎ水平材29に作用する水平軸力(H1若しくはH2)の50〜100%に設定することが好ましい。50%以下では水平分力軽減効果が少ない。100%以上では吊材つなぎ水平材が鉛直支柱材に取付けられるガセットプレートの取付部に過大な応力度が発生する。初期張力Hは、前述の張力調整ジョイント26によって調節する。   FIG. 10 is a drawing similar to FIG. 9, and in the case where only the horizontal reinforcing member 25 is provided in the arm metal assembly 2 of the conventional steel tube tower 1, FIG. 10A is a schematic skeleton of the arm metal assembly 2. A structure is shown, (B) figure shows the load which acts on the framework of (A) figure, (C) figure shows the bending moment which acts on diagonal lifting material 22R, 22L. (B) As shown in the figure, when the initial tension H is introduced by the horizontal reinforcing member 25, the horizontal component forces H1 and H2 are reduced by the initial tension H. The initial tension H to be introduced is preferably set to 50 to 100% of the horizontal axial force (H1 or H2) acting on the horizontal connecting member 29 in the horizontal direction. Below 50%, the horizontal component force reduction effect is small. If it is 100% or more, an excessive stress level is generated in the attachment portion of the gusset plate where the hanging material connecting horizontal material is attached to the vertical support material. The initial tension H is adjusted by the tension adjusting joint 26 described above.

しかし、初期張力Hの導入によって、(C)図に示すように、斜め吊上げ材22R、22Lには新たに曲げモーメントが発生する。   However, with the introduction of the initial tension H, a bending moment is newly generated in the oblique lifting members 22R and 22L as shown in FIG.

図11は、本発明に基づく腕金組立体補強構造を適用された鋼管鉄塔1の腕金組立体2の側面図であって、(A)図は腕金組立体2の概略骨組み構造を示し、(B)図は(A)図の骨組みに作用する荷重を示す。(A)図に示すように、本発明に基づく腕金組立体補強構造は、水平補強材25に加えて突上げ材27R、27Lが設けられている。突上げ材27R、27Lの新設によって斜め鉛直力V3、V4が発生し、水平補強材25の導入によって発生した曲げモーメント(図10の(C)図参照)が消滅される。補強のために使用された材料の総重量は、突上げ材27R、27Lが支持する。補強構造の荷重Wの増加分は、天秤の原理により、左右の腕金部で釣り合う。   FIG. 11 is a side view of the armrest assembly 2 of the steel pipe tower 1 to which the armrest assembly reinforcing structure according to the present invention is applied, and FIG. 11A shows a schematic framework structure of the armrest assembly 2. (B) The figure shows the load which acts on the framework of (A) figure. (A) As shown in the figure, the brace assembly reinforcement structure according to the present invention is provided with push-up members 27R and 27L in addition to the horizontal reinforcement member 25. By installing the push-up members 27R and 27L, oblique vertical forces V3 and V4 are generated, and the bending moment generated by the introduction of the horizontal reinforcing member 25 (see FIG. 10C) disappears. The total weight of the material used for reinforcement is supported by the push-up materials 27R and 27L. The increase in the load W of the reinforcing structure is balanced between the left and right arm parts according to the balance principle.

腕金組立体の近傍パネルをモデル化した骨組みモデルの腕金部先端に鉛直荷重を載荷した。試験体は、補強なしモデル(M0)、補強有りモデル(M1)を準備した。直径101.6mm鋼管についての強度試験結果を下記の表1に示す。載荷荷重は、試験設備能力により、200kNを上限とした。   A vertical load was loaded on the end of the armrest part of the frame model that modeled the panel near the armrest assembly. As the test body, a model without reinforcement (M0) and a model with reinforcement (M1) were prepared. Table 1 below shows the strength test results for a steel pipe having a diameter of 101.6 mm. The loading load was set to 200 kN as the upper limit depending on the test facility capacity.

Figure 0004847790
Figure 0004847790

補強特性評価を図12の(A)図から(D)図までに示す。(A)図は試験荷重と斜め吊上げ材ガセット中央位置での鋼管変形(へこみ)量との関係を示す。荷重が60kN程度で鋼管変形量の傾きが異なるが、荷重200kNまで直線的に推移している。補強有りモデル(M1)は、補強なしモデル(M0)に比較して鋼管変形の抑制効果が高いことがわかる。(B)図は試験荷重と斜め吊上げ材軸力との関係を示す。補強なしモデル(M0)は荷重に比例して軸力が増加していることがわかる。補強有りモデル(M1)では約60kNまでは補強なしモデル(M1)とほぼ同じ傾きを示しているが、それ以上では傾きが立ち上がり、斜め吊上げ材へ伝達される軸力が小さくなっていることがわかる。(C)図は試験荷重と補強材へ伝達される軸力との関係を示す。試験荷重が60kNを超えたあたりから伝達される軸力が安定し、直線的に増加している。60kNまでの伝達軸力のバラツキは、補強材のボルト穴間隙によるものと推定される。(D)図は試験荷重と補強材の鉛直荷重分担率との関係を示す。試験開始前は、補強材に予備張力が加わるように張力調整ジョイント26に初期張力を与えている。このため、分担率は80%以上と高い値から開始しているが、試験荷重の増加に伴い、ボルト穴間隙の影響も少なくなり、分担率も減少している。試験荷重が60kNを超えたあたりからは補強材への伝達が安定するため、直線的な変化となっている。   The reinforcement characteristic evaluation is shown in FIGS. 12A to 12D. (A) The figure shows the relationship between the test load and the amount of deformation (dent) in the steel pipe at the center position of the oblique lifting material gusset. Although the inclination of the steel pipe deformation amount is different at a load of about 60 kN, it changes linearly up to a load of 200 kN. It can be seen that the model with reinforcement (M1) has a higher effect of suppressing steel pipe deformation than the model without reinforcement (M0). (B) The figure shows the relationship between the test load and the oblique lifting material axial force. It can be seen that in the unreinforced model (M0), the axial force increases in proportion to the load. The model with reinforcement (M1) shows almost the same inclination as the model without reinforcement (M1) up to about 60 kN, but the inclination rises beyond this and the axial force transmitted to the slanting lifting material is small. Recognize. (C) The figure shows the relationship between the test load and the axial force transmitted to the reinforcement. The axial force transmitted from when the test load exceeds 60 kN is stable and increases linearly. The variation in transmission shaft force up to 60 kN is estimated to be due to the bolt hole gap of the reinforcing material. (D) The figure shows the relationship between the test load and the vertical load share of the reinforcing material. Prior to the start of the test, an initial tension is applied to the tension adjustment joint 26 so that a preliminary tension is applied to the reinforcing material. For this reason, the sharing rate starts from a high value of 80% or more. However, as the test load increases, the influence of the bolt hole gap decreases, and the sharing rate also decreases. Since the transmission to the reinforcing material is stable after the test load exceeds 60 kN, the change is linear.

以上要約すれば、補強がない場合には、吊材つなぎ水平材29の取付用ガセットプレートの溶接止端部で管壁が局部破壊した。補強有りモデル(M1)では、主柱材鋼管に伝達される力を逃がすバイパス効果が顕著に現れ、鋼管が25mm偏平化する時の耐力で見ると、補強がない場合に対する耐力増加率280%という優れた補強効果が確認できた。   In summary, in the absence of reinforcement, the tube wall locally broke at the weld toe of the gusset plate for attachment of the hanger tie horizontal member 29. In the model with reinforcement (M1), the bypass effect of escaping the force transmitted to the main column steel pipe appears prominently, and when looking at the yield strength when the steel pipe is flattened by 25 mm, the yield increase rate with respect to the case without reinforcement is 280%. An excellent reinforcing effect was confirmed.

本発明は、鋼管鉄塔だけではなく、既設鋼管構造物の張出し片持ち梁等の補強にも広く適用可能である。   The present invention is widely applicable not only to steel pipe towers but also to reinforcement of overhanging cantilever beams and the like of existing steel pipe structures.

鋼管鉄塔の腕金組立体の側面図であって、本発明に基づく鋼管鉄塔の腕金組立体補強構造を示す。It is a side view of the armrest assembly of a steel pipe tower, and shows the armature assembly reinforcement structure of the steel pipe tower based on the present invention. 図1のII−II線から見た腕金組立体の平面図である。FIG. 2 is a plan view of a bracelet assembly as viewed from line II-II in FIG. 図1のIII−III線から見た腕金組立体の平面図である。FIG. 3 is a plan view of a bracelet assembly as viewed from line III-III in FIG. 図3の一部拡大平面図であって、本発明の腕金組立体補強構造を示す。FIG. 4 is a partially enlarged plan view of FIG. 3 showing a brace assembly reinforcement structure of the present invention. 図1の一部拡大側面図であって、本発明の腕金組立体補強構造を示す。It is a partially expanded side view of FIG. 1, Comprising: The armrest assembly reinforcement structure of this invention is shown. 図5のVI−VI円包囲部分の拡大側面図であって、水平補強材の張力調整ジョイントを示す。FIG. 6 is an enlarged side view of the VI-VI circle encircled portion of FIG. 5, showing a tension adjusting joint of a horizontal reinforcing material. 図6のVII−VII線から見た張力調整ジョイントのフランジ部分の背面図である。It is a rear view of the flange part of the tension adjustment joint seen from the VII-VII line of FIG. 図6のVIII−VIII線から見た張力調整ジョイントのスペーサ部分の背面図である。It is a rear view of the spacer part of the tension adjustment joint seen from the VIII-VIII line of FIG. 従来の鋼管鉄塔の腕金組立体の側面図であって、(A)図は腕金組立体の概略骨組み構造を示し、(B)図は(A)図の骨組みに作用する荷重を示す。It is a side view of the armature assembly of the conventional steel pipe tower, (A) figure shows the outline frame structure of an armrest assembly, and (B) figure shows the load which acts on the frame of (A) figure. 図9と同様な図面であって、従来の鋼管鉄塔の腕金組立体に水平補強材のみを設けた場合において、(A)図は腕金組立体の概略骨組み構造を示し、(B)図は(A)図の骨組みに作用する荷重を示し、(C)図は(A)図の斜め吊上げ材に作用する曲げモーメントを示す。FIG. 9 is a drawing similar to FIG. 9, and in the case where only the horizontal reinforcing material is provided in the arm bracket assembly of the conventional steel tube tower, FIG. 9A shows a schematic framework structure of the arm bracket assembly, and FIG. (A) shows the load acting on the framework of FIG. (A), and (C) shows the bending moment acting on the diagonal lifting material of (A). 本発明に基づく腕金組立体補強構造を適用された鋼管鉄塔の腕金組立体の側面図であって、(A)図は腕金組立体の概略骨組み構造を示し、(B)図は(A)図の骨組みに作用する荷重を示す。BRIEF DESCRIPTION OF THE DRAWINGS It is a side view of the armrest assembly of the steel pipe tower to which the armrest assembly reinforcement structure based on this invention is applied, Comprising: (A) A figure shows the general | schematic framework structure of an armrest assembly, (B) FIG. A) A load acting on the framework of the figure is shown. 本発明に基づく腕金組立体補強構造を適用された鋼管鉄塔の腕金組立体の耐力特性を表すグラフであって、(A)図は荷重−鋼管変形量特性を示し、(B)図は荷重−斜め吊上げ材軸力特性を示し、(C)図は荷重−水平補強材軸力特性を示し、(D)図は鉛直荷重分担特性をそれぞれ示す。It is a graph showing the proof stress characteristic of the armrest assembly of the steel pipe tower to which the armrest assembly reinforcement structure based on this invention is applied, Comprising: (A) The figure shows the load-steel pipe deformation amount characteristic, (B) The load-diagonal lifting material axial force characteristics are shown, (C) shows the load-horizontal reinforcement axial force characteristics, and (D) shows the vertical load sharing characteristics.

符号の説明Explanation of symbols

1 (送電用)鋼管鉄塔 2 腕金組立体
2R 右側腕金部 2L 左側腕金部
21R、21L 水平張出し材 22R、22L 斜め吊上げ材
23R、23L ジョイント 24R、24L 前後支持材
25 水平補強材 26 張力調整ジョイント
27R、27L 突上げ材 28R、28L 基端部ジョイント
29 吊材つなぎ水平材 30 斜補強材(ステー)
31 鉛直支柱材 261 対向フランジ
262 スペーサ 263 ボルト
1 (For power transmission) Steel pipe tower 2 Arm assembly
2R Right arm part 2L Left arm part 21R, 21L Horizontal projecting material 22R, 22L Diagonal lifting material 23R, 23L Joint 24R, 24L Front / rear support material
25 Horizontal reinforcement 26 Tension adjustment joint 27R, 27L Push-up material 28R, 28L Base end joint
29 Horizontal materials for suspension material 30 Diagonal reinforcement (stay)
31 Vertical support material 261 Opposing flange
262 Spacer 263 Bolt

Claims (3)

鋼管鉄塔の鉄塔本体頂部から左右水平方向(X方向)に張り出した右側腕金部と左側腕金部とを有し、各側腕金部は1対の水平張出し材と1対の斜め吊上げ材とからなり、前記1対の水平張出し材の自由端と前記1対の斜め吊上げ材の自由端とがジョイントによって相互に結合された腕金組立体において、
前記各側腕金部の前記1対の斜め吊上げ材の基端付近で前後水平方向(Y方向)に差し渡された前後支持材と、
前記各前後支持材に左右水平方向(X方向)に差し渡された水平補強材と、
各前後支持材の両端部分と水平補強材の両端中間部分とを水平面(XY面)内で連結する斜補強材(ステー)と、
前記水平補強材の中間に設けられた張力調整ジョイントと、
前記各前後支持材の両端部と鉄塔本体とに上下鉛直方向(Z方向)斜めに連結された突上げ材とからなる、
鋼管鉄塔の腕金組立体補強構造。
The steel pipe tower has a right arm and a left arm extending from the top of the steel tower main body in the horizontal direction (X direction), and each side arm has a pair of horizontal overhangs and a pair of diagonal lifting members. A bracelet assembly in which the free ends of the pair of horizontal projecting members and the free ends of the pair of slanted lifting members are connected to each other by a joint,
Front and rear support members passed in the front and rear horizontal direction (Y direction) in the vicinity of the base ends of the pair of slanting lifting members of each side armrest part;
A horizontal reinforcing material passed in the horizontal direction (X direction) to the front and rear support members;
Diagonal reinforcements (stays) for connecting both end portions of each front and rear support member and both end intermediate portions of the horizontal reinforcement member in a horizontal plane (XY plane);
A tension adjusting joint provided in the middle of the horizontal reinforcing material;
It consists of a push-up material that is obliquely connected to both ends of each of the front and rear support members and the steel tower body in the vertical and vertical directions (Z direction).
Steel pipe tower arm brace assembly reinforcement structure.
前記張力調整ジョイントは、前記水平補強材の中間部を左右水平方向(X方向)に分離離間し、各離間端に対向フランジを設け、各フランジ間にスペーサを挿入し、各フランジおよびスペーサを一体にボルト締めした構成になっている、請求項1に記載の鋼管鉄塔の腕金組立体補強構造。   The tension adjustment joint separates and separates the horizontal portion of the horizontal reinforcing member in the horizontal and horizontal directions (X direction), provides opposing flanges at the respective separation ends, inserts a spacer between the flanges, and integrates the flange and the spacer. The armature assembly reinforcement structure of a steel pipe tower according to claim 1, wherein the structure is bolted to the armature. 前記張力調整ジョイントにおけるボルト締付け力は、前記各側腕金部の前記1対の斜め吊上げ材の基端間を連結する前記鉄塔本体の左右水平方向の吊材つなぎ水平材に作用する張力の約50−100%に設定された、請求項2に記載の鋼管鉄塔の腕金組立体補強構造。   The bolt tightening force in the tension adjusting joint is approximately the tension acting on the horizontal member of the horizontal horizontal direction of the tower body connecting the base ends of the pair of oblique lifting members of each side armrest part. The armature assembly reinforcing structure for a steel pipe tower according to claim 2, set to 50-100%.
JP2006149917A 2006-05-30 2006-05-30 Steel pipe tower brace assembly reinforcement structure Active JP4847790B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006149917A JP4847790B2 (en) 2006-05-30 2006-05-30 Steel pipe tower brace assembly reinforcement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006149917A JP4847790B2 (en) 2006-05-30 2006-05-30 Steel pipe tower brace assembly reinforcement structure

Publications (2)

Publication Number Publication Date
JP2007321359A JP2007321359A (en) 2007-12-13
JP4847790B2 true JP4847790B2 (en) 2011-12-28

Family

ID=38854416

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006149917A Active JP4847790B2 (en) 2006-05-30 2006-05-30 Steel pipe tower brace assembly reinforcement structure

Country Status (1)

Country Link
JP (1) JP4847790B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101019425B1 (en) 2008-09-26 2011-03-07 한국전력공사 Compression Buckling Strength Reinforcement Mechanism and Its Fastening Method
JP5649556B2 (en) * 2011-11-29 2015-01-07 電気興業株式会社 Steel tower lifting device
JP5806629B2 (en) * 2012-02-17 2015-11-10 日本鉄塔工業株式会社 Length adjustment member for new structural member for steel tower restoration
CN110306859A (en) * 2019-07-23 2019-10-08 广东电网有限责任公司 A kind of power transmission tower and its X-braced panels gusset plate

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0368270A (en) * 1989-08-08 1991-03-25 Fuji Xerox Co Ltd Picture processor

Also Published As

Publication number Publication date
JP2007321359A (en) 2007-12-13

Similar Documents

Publication Publication Date Title
CN201560400U (en) Stayed-cable hanging basket
JP2001515978A (en) Moment-resistant structure, support member, and construction method
JP2009287286A (en) Support for overhanging floor slab
JP2009287285A (en) Support for overhanging floor slab
JP2021031884A (en) Bridge upper structure removal method
JP4847790B2 (en) Steel pipe tower brace assembly reinforcement structure
CN107059880A (en) The ruggedized construction and its construction method of the concrete assembled shaped steel mixing support system of super-sized foundation pit
CN210134352U (en) Hoop type support for single-column pier capping beam construction
CN103243649A (en) System and method for quickly installing and positioning cable saddle
KR101392833B1 (en) Truss bridge structure
CN110820566A (en) Corrugated steel web part bearing type hanging basket suspension casting construction method
CN109680923A (en) A kind of mounting structure and building method of builder&#39;s jack bottom platform
CN106894349B (en) A kind of bridge of high-mechanic intensity
CN211872663U (en) Buckling cable saddle platform for assembled tower
CN110080121B (en) Hanging basket uplink system and construction method
CN219824879U (en) Bridge stay bar assembly
CN117306403A (en) A multi-purpose cable hanging basket bearing platform and multi-position pouring method
KR102491179B1 (en) Preflex steel girder and the manufacturing method
CN110820567A (en) Bearing type hanging basket for PC box girder part with corrugated steel web plate
CN214245330U (en) Novel large-tonnage tension swing pier structure of cable-stayed bridge auxiliary pier
CN100557153C (en) Attachment system for a beam
CN209082344U (en) A kind of cable-stayed type large-span steel roof beam structure
CN209620620U (en) A kind of Combined type reinforced binding auxiliary stand
CN102127962A (en) Improved bidirectionally stressed foundation knot attached to lifting scaffold
JP2009108591A (en) Structural member

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090527

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110914

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110920

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20111014

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141021

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4847790

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250