JP4958028B2 - Construction method of pile hole rooting layer, foundation pile construction management device, foundation pile construction management method - Google Patents
[go: Go Back, main page]

JP4958028B2 - Construction method of pile hole rooting layer, foundation pile construction management device, foundation pile construction management method - Google Patents

Construction method of pile hole rooting layer, foundation pile construction management device, foundation pile construction management method Download PDF

Info

Publication number
JP4958028B2
JP4958028B2 JP2001175402A JP2001175402A JP4958028B2 JP 4958028 B2 JP4958028 B2 JP 4958028B2 JP 2001175402 A JP2001175402 A JP 2001175402A JP 2001175402 A JP2001175402 A JP 2001175402A JP 4958028 B2 JP4958028 B2 JP 4958028B2
Authority
JP
Japan
Prior art keywords
pile
excavation
cement milk
construction
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2001175402A
Other languages
Japanese (ja)
Other versions
JP2002348868A (en
Inventor
洋一 加藤
好伸 木谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitani Sekisan Co Ltd
Original Assignee
Mitani Sekisan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitani Sekisan Co Ltd filed Critical Mitani Sekisan Co Ltd
Priority to JP2001175402A priority Critical patent/JP4958028B2/en
Publication of JP2002348868A publication Critical patent/JP2002348868A/en
Application granted granted Critical
Publication of JP4958028B2 publication Critical patent/JP4958028B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【0001】
【発明の属する技術分野】
この発明は、杭穴内に既製杭を埋設する際に使用する、セメントミルクの注入に特徴を有する杭穴根固め層の構築方法、
及びこの杭穴根固め層の構築方法を含む基礎杭の構築を管理する基礎杭の施工管理方法、並びに施工管理方法に使用する施工管理装置に関する。
【0002】
【従来の技術】
杭穴を掘削して、杭穴底部にセメントミルクを注入して、根固め層を形成し、杭穴内に既製杭を沈設して、既製杭の下端部を根固め層に定着させる工法が行われている。
【0003】
従来、根固め層の品質については、根固め部に注入前のセメントミルク自体の所定期間経過後の一軸圧縮強度のみで管理しており、根固め層を形成時の構築方法、管理方法などまで、行き渡っていなかった。
【0004】
また最近、杭穴に少なくとも下端部に突起部を有する既製杭を沈設して、該既製杭の下端部の突起部を、拡底部を有する根固め層に定着させる工法が行われている。この場合、根固め層と突起部を有する既製杭が強固に固結するため、支持力が大幅に向上する。
【0005】
また、従来、地盤強度等を調査するために、基礎杭の施工に先だって施工現場の広さに応じて標準貫入試験による土質調査が行われる。この土質調査においては、ボーリングによって鋼製のサンプラを30cm打ち込むのに要する打撃回数(N値)を測定して地盤強度を推定し、採取した試料から土質名の判定が行われ、これらによって土質柱状図が作成される。
【0006】
この場合、支持層の確認においては、掘削機による電流値(積算電流値(Amp・sec)等)と別紙の土質柱状図を対比する方法、又は深度を基準として土質柱状図のN値と積分電流値を同一画面に表示する方法が知られている(特開平5-280031号「杭支持層検出装置」)。
【0007】
【発明が解決しようとする課題】
既製杭の下端部に形成した突起部あるいは、鉄筋篭等の高支持力に主として寄与する構造体を根固め層に沈設する工法によれば、従来工法に比べ約2倍の高支持力の性能を保有しているため、その高支持力を発現する根固め層の施工において、その根固め層の築造品質が重要である。
【0008】
その根固め層の築造における、杭穴底部の掘削後、掘削土を撹拌し、セメントミルクを注入・混合しソイルセメント化する工程で、このソイルセメント層を均質な高固化強度の品質に築造するために、新たな根固め層の構築方法やセメントミルクの品質管理が求められている。根固め層が所定強度の土層に確実に形成されることが必要であると共に、とりわけ、硬化性材料の品質及び充填量の管理が問われている。
【0009】
例えば、拡底部を有する杭穴の拡底根固め部に根固液を、杭穴軸部に杭周固定液を注入して、各々掘削土と混合させてソイルセメント化し、該拡底部内に少なくとも下端部に1つ以上の突起部を有する突起付き杭の該下端部を埋設し、該杭の下端面及び突起部からの支圧力によって支持力並びに引抜力を大幅に向上させた施工法においては、根固め層の地盤強度、充填される根固液、杭周固定液の所定深度あたりの充填量及びソイルセメント化した際の品質が重要な管理項目となっている。
【0010】
前記特開平5-280031号に記載の発明においては、掘削開始からの積分電流値と予め入力されているN値を、深度を基準として同一画面上で表示し、支持層確認後はその役目を終えている。通常、セメントミルク等の硬化性材料の充填を開始するのは、支持層確認後に行われるが、これまで掘削開始時から積算電流値の測定による支持層の確認、硬化性材料の注入、杭挿入に至るまでの各工程のデータを関連付けた施工管理機能を備えた装置は開発されていなかった。
【0011】
さらに、深度を基準としたボーリングデータ、積算電流値に加えて、硬化性材料の注入状況等の施工管理データを同一画面上に表示して施工状況を確認する装置はなかった。
【0012】
【課題を解決するための手段】
然るにこの発明では、各杭穴の実際の掘削時のデータ(深度、土質)に適合させて注入手段を昇降させ、吐出口を少なくとも2回上下移動せながら、注入すべきセメントミルクを複数回に分けて、前記吐出口から注入して杭穴底部に根固め層を形成するので、前記問題点を解決した。
【0013】
即ちこの発明は、杭穴底部に根固め層を形成し、かつ杭穴軸部内に杭周固定液層を形成し、該杭穴内に既製杭を埋設して、根固め層内に既製杭の下端部を定着させる基礎杭の構築に際して、該杭穴底部にセメントミルクを注入して根固め層を構築する方法において、掘削ヘッドを有する掘削ロッドの下端部に吐出口を形成し、(1) 前記杭穴を掘削後、前記掘削ヘッドを杭穴底に保持して、吐出口から注入すべき全セメントミルク量の3分の1宛セメントミルクを吐出し、
(2) 続いて、前記掘削ロッドを形成予定の根固め層の上縁付近まで上昇させながら全セメントミルク量の3分の1のセメントミルクを吐出し、根固め層内の強度上良くない混入物を前記根固め層の上方に押し上げ、
(3) 次に、杭穴底との間で、前記掘削ロッドを複数回昇降させながら、残りのセメントミルクを吐出して、前記掘削ロッドを引き上げて根固め層を形成する。
ことを特徴とした杭穴根固め層の構築方法である。
【0016】
また、前記において、「根固め液又は杭周固定液用の」セメントミルクの注入状況を、施工操作室内、施工機械あるいは施工エリアの施工管理室内に設置された表示装置に表示させて、周辺地盤及び杭穴内の築造状態とを確認しながら、セメントミルクを注入し、前記表示装置の表示を、横軸を施工開始からの時間とし、縦軸に「流量計から得られる根固め液又は杭周固定液の時間当たりの流量」、「流量計から得られる吐出物の総流量」及び「深度計から得られる前記掘削ヘッド位置」をグラフ化して同時に表示するとすることを特徴とした杭穴根固め層の構築方法である。
【0018】
また、装置の発明は、掘削ロッド又は既製杭を装着する回転駆動装置と、該回転駆動装置を昇降させる昇降手段と、掘削ロッドに水又は「根固め液又は杭周固定液用の」セメントミルク供給する液体供給手段とを備える杭打ち機であって、各種センサーを備え、前記各種センサーからの情報をまとめて演算処理し、画面に表示すると共に情報を蓄積記録することができる情報処理手段を有する杭打ち装置において、
(1) 前記各種センサーは、前記回転駆動装置の負荷電流を測定する負荷電流計と、前記回転駆動装置の昇降量を感知して前記掘削ロッド又は既製杭の地上からの深さ位置を測定する深度計と、前記液体供給手段からの液体の供給量を測定する流量計とを含む構成とし、
(2) 前記情報処理手段は、前記流量計からのデータを、前記深度計からのデータから設定した各深度毎に、表示すると共に、予め設定した各深度毎の規定流量と実際の流量とを比較して表示する機能と、前記負荷電流計からのデータを、所定深度毎に積算して蓄積表示すると共に、予め設定した対応する前記所定深度毎のN値データとを対比して表示する機能と、前記情報を各杭穴毎に読み出し、表示、記憶、蓄積できる機能とを有した
(3) 前記情報処理手段によるデータの表示は、横軸を施工開始からの時間とし、縦軸に「流量計から得られる水、根固め液又は杭周固定液の時間当たりの流量」、「流量計から得られる吐出物の総流量」及び「深度計から得られる前記掘削ヘッド位置」をグラフ化して同時に表示する。
ことを特徴とする基礎杭の施工管理装置である。
【0019】
また、前記装置において、掘削ヘッドを有する掘削ロッドの下端部に吐出口を形成し、
杭穴根固め層にセメントミルクを注入する際に
(1) 前記杭穴を掘削後、前記掘削ヘッドを杭穴底に保持して、吐出口から注入すべき全セメントミルク量の3分の1宛セメントミルクを吐出し、
(2) 続いて、前記掘削ロッドを形成予定の根固め層の上縁付近まで上昇させながら全セメントミルク量の3分の1のセメントミルクを吐出し、根固め層内の強度上良くない混入物を前記根固め層の上方に押し上げ、
(3) 次に、杭穴底との間で、前記掘削ロッドを複数回昇降させながら、残りのセメントミルクを吐出して、前記掘削ロッドを引き上げて根固め層を形成する。
基礎杭の施工管理装置である。
【0020】
また、管理方法の発明は、掘削ロッド又は既製杭を装着する回転駆動装置と、該回転駆動装置を昇降させる昇降手段と、掘削ロッドに水又は「根固め液又は杭周固定液用の」セメントミルクを供給する液体供給手段とを備える杭打ち機を使用して、杭穴を掘削する掘削工程、該杭穴内にセメントミルクを注入する注入工程、セメントミルクが注入された杭穴内に既製杭を埋設する杭挿入工程からなる構築方法を管理する方法であって、
前記回転駆動装置の負荷電流を測定する負荷電流計からのデータと、前記回転駆動装置の昇降量を感知して前記掘削ロッド先端部又は既製杭先端部の地上からの深さ位置を測定する深度計からのデータと、
前記液体供給手段からの液体の供給量を測定する流量計からのデータとを演算処理して、これらデータを各杭穴毎に読み出しできるように記憶しておき、
各杭穴毎に、
(1) 掘削工程では、前記負荷電流計からのデータを、所定深度毎に積算して蓄積表示すると共に、予め設定した対応する前記所定深度毎のN値データとを対比して表示して、支持層を確認する。
(2) 注入工程では、横軸を施工開始からの時間とし、縦軸に「流量計から得られる水、根固め液又は杭周固定液の時間当たりの流量」、「流量計から得られる吐出物の総流量」及び「深度計から得られる前記掘削ヘッド位置」をグラフ化して同時に表示すると共に、
予め設定した各深度毎の規定流量と実際の流量とを比較して表示して、深度毎のセメントミルク量を管理する。
(3)杭挿入工程では、前記深度計からのデータから杭先端位置を管理して支持層に既製杭が定着することを管理する。
ことを特徴とした基礎杭の施工管理方法。
【0021】
また、前記において、掘削ヘッドを有する掘削ロッドの下端部に吐出口を形成し、杭穴根固め層にセメントミルクを注入する際に、
(1) 前記杭穴を掘削後、前記掘削ヘッドを杭穴底に保持して、吐出口から注入すべき全セメントミルク量の3分の1宛セメントミルクを吐出し、
(2) 続いて、前記掘削ロッドを形成予定の根固め層の上縁付近まで上昇させながら全セメントミルク量の3分の1のセメントミルクを吐出し、根固め層内の強度上良くない混入物を前記根固め層の上方に押し上げ、
(3) 次に、杭穴底との間で、前記掘削ロッドを複数回昇降させながら、残りのセメントミルクを吐出して、前記掘削ロッドを引き上げて根固め層を形成する。
特徴とした請求項記載の基礎杭の施工管理方法。
【0022】
前記において、注入手段とは、セメントミルクを注入できる装置であり、一般に下端部に掘削ヘッドを有する中空の掘削ロッドを使用するが、掘削ロッドを引き上げた後、撹拌手段を設けた注入パイプ等の注入手段を別途用意して使用することもできる。
【0023】
また、前記において、根固め層は、軸部と同一穴径とする場合の他、拡大掘削した拡大根固め層の場合には、一般に根固め層で高支持力を発現させるため、該根固め層の高品質が要求されているので、より顕著な効果が期待できる。
【0024】
また、前記において、周辺地盤の状態は、その他の杭穴のデータ、標準貫入試験のデータ、試験掘りのデータ等を基にし、これらあるいはいずれか1つと本杭穴のデータを表示装置に表示するため、セメントミルクの注入の際に対比して確認しながら高精度の施工を行うことができる。
【0025】
また、前記におけるセメントミルクは、水硬性材料の総称であり、各種セメント類をはじめ根固め層を形成できる材料であれば、任意である。
【0026】
尚、施工管理とは施工の条件・設定値と実データを比較し、差異がある時はその条件・設定値に合わせるよう調整することをいう。
【0027】
【発明の実施の形態】
下端に掘削ヘッド(掘削刃付き)を有する掘削ロッドが中空に形成され、セメントミルク注入手段を構成し、下端部に吐出口が形成されている。掘削完了後、掘削ヘッドを杭穴底に保持した状態で掘削ヘッドで撹拌しながら、吐出口から全セメントミルク量の3分の1宛セメントミルクを吐出する。続いて、掘削ヘッドで撹拌しながら、掘削ロッドを杭穴の根固め部の上縁付近まで上昇させながら全セメントミルク量の3分の1を吐出する。次に、掘削ヘッドを根固め部内で(杭穴底と根固め部の上縁との間を)複数回昇降させながら、残りのセメントミルクの3分の1を吐出して、撹拌及び混合を行い掘削ロッドを引き上げて根固め層を形成する。
【0028】
形成された根固め層内に、既製杭の下端部に形成して高支持力を発現させる構造体である。例えば、既製杭の下端部に形成した突起部分を定着させて、セメントミルクが固化後にセメントミルクと既製杭とが一体となり、高支持力を発揮する基礎杭を構築できる。
【0029】
ここで、撹拌とは掘削ヘッドを回転させる工程を指し、混合とは掘削ヘッドを回転しつつ昇降させる(又は回転と昇降とを繰り返す)工程を指す。
【0030】
この場合、高支持力を発現する高品質な根固め部築造においては、注入されるセメントミルクの品質を初め、杭穴の掘削、基礎杭の埋設等を含む従来と異なる新たな施工が、確実に実施されていることを保証するする仕組みが必要である。
【0031】
本発明を含む新施工方法は、従来の施工方法に比べ、その施工手順・方法が緻密であり、従来の施工時のデータを一部記録するだけの仕組みでは品質保証が困難であり、新施工管理システムの構築により、高支持力根固め部の施工内容・品質を保証している。
【0032】
尚、従来の根固め部を有する基礎杭施工方法は、手順および方法ともに比較的単純であり、掘削機の掘削負荷電流を表示・記録し、杭を支持地盤に埋設したことを証明する資料としている程度であった。すなわち、基礎杭の要求品質・信頼性の面から、それ以上の維持・管理システムは必要とされていなかった。
【0033】
表示としてはその掘削電流値に掘削した地層の深さを併記し、事前のボーリングデータから想定されていた杭埋設深さとの差異がどの程度かの目安として利用されていた程度で、掘削負荷電流以外の各基礎杭毎の設定条件ごとの実績値が、リアルに、記録、かつ比較照合され、施工現場で、基礎杭の施工内容が確認され、品質維持、管理を目的として記録し、利用されることはなく、せいぜい施工後に記録値が整理比較される程度であった。実際の各杭基礎の施工時あるいは各杭の施工毎に確認・照合しながらに施工作業に常時フィードバックされることは実工事では殆どなかった。
【0034】
【試験例】
本発明の方法による根固め層と従来方法による根固め層との比較実験を行った。セメントミルクの注入時期と撹拌混合の方法の改良により均質な高品質のソイルセメント層からなる根固め層が得られていることが確認された。
【0035】
1. 試験条件・仕様
【0036】
(1)杭穴、掘削方法等
支持層地質:N値30 〜35、砂質土
杭穴:軸部径 800mm
軸部長 950mm
拡大根固め部 径1200mm
拡大根固め部 長2500mm
造成方法概要:注入口が形成された特殊掘削ヘッドで、水を注入しながら、先ず杭穴軸部を掘削し、地面から9.5m掘削したところで、特殊掘削ヘッドを拡大掘削径とし、12mまで掘削し、充分撹拌し拡大根固め部(構築予定の根固め層)を形成する。次に、下記の仕様のセメントミルクを注入して掘削土と混合し、その根固め部をソイルセメント層とする(図3)。
【0037】
(2)セメントミルク配合
セメント量:1090kg
水:654リットル
練り上がり量: 1m
【0038】
(3)セメントミルクの撹拌の仕様
セメントミルクと掘削土との撹拌混合する仕様としては、撹拌する装置は、掘削ヘッド2付きの掘削ロッド1をそのまま用いる。即ち、掘削土を細かく粉砕できる特徴を有する掘削ヘッド2は、掘削ロッド1の軸部に連結するヘッド本体6aの両側に揺動する掘削アーム6、6を取り付けてなり、掘削アーム6の広面積の先端部57は外側に開いて形成され、掘削刃58、58が取り付けてある(図18(a)(b))。
【0039】
杭穴の根固め部の掘削径80〜110cmにおいて、揺動する掘削アーム6の長さD(=約50〜80cm)とした場合、広面積の先端部57の長さをLとして、LをDの約30〜40%の長さとする。掘削刃58、58を含めて広い面積の先端部57の外側の面積をS(図18(a)の網線部分)とした場合、
S=「(Lの約70〜80%」
とすることにより、良好で均質な撹拌混合が得られる。
【0040】
また、掘削ロッド1(掘削ヘッド2)を回転させる撹拌動力も掘削時のオーガーマシンをそのまま使用する。通常、掘削時はオーガーマシンの電源電圧を一定として出力を上げる方式を取っており、掘削電流を上下して回転数を一定になるように制御している。尚、一般に地質や地盤強度等に応じて、出力が異なるオーガマシンを使い分けている。
【0041】
そして、撹拌時には、掘削時の掘削ロッド1の平均回転数の1.5〜2.0倍まで回転数を上げるように制御して、後述するようにセメントミルクを注入しながら撹拌混合する仕様を採用した。
【0042】
(4)セメントミルクの注入の仕様
杭穴底部を拡大掘削して、所定の形状の根固め部を有する杭穴を形成した後、その根固め部へセメントミルクを、吐出速度約200リットル/分 で注入するが、その注入仕様として下記4仕様で比較した(図3(a)〜(d))。
【0043】
(a) 仕様1(Case1):従来例(図3(a))
先ず、セメントミルクの注入口を根固め部の底部のほぼ中央位置に設置し、注入口をゆっくり引き上げながらセメントミルクを注入し、根固め部の最上部に達するまでに全量吐出しソイルセメント層からなる根固め層を形成する。
根固め部への総注入量:2.4m
【0044】
(b) 仕様2 (Case2):本発明(図3(b))
全吐出量を 1/3量づつ3回に分けて吐出する。
第1回目: 1/3量を構築予定の根固め層の底部で撹拌しながら吐出する。
第2回目: 1/3量を引き上げ、撹拌しながら吐出する。
第3回目: 1/3量を撹拌しながら根固め部内で、上下2往復させながら吐出を完了させる。
【0045】
(c) 仕様3(Case3):本発明(図3(c))
先ず、セメントミルクの注入口を構築予定の根固め層の底部のほぼ中央に設置し、撹拌・吐出しながら根固め部内を上下2往復させて、最上部で完了させる。
【0046】
(d) 仕様4(Case4):従来例(図3(d))
先ず、セメントミルクの注入口を根固め部の底部のほぼ中央に設置し、その注入口を移動させずにセメントミルクを全量吐出しソイルセメント層を形成する。これはシルト等が混入し、地層が良くない場合に主に採用される方法である。
【0047】
(5)試験評価方法
(a) 電気比抵抗の測定試験
セメントミルク吐出完了して根固め層を形成した直後に、比抵抗ロッドをその根固め層内に挿入し、その根固め層の上層から下層まで電気比抵抗を測定した。
(b) 採取コアの一軸圧縮強度試験
拡大根固め層のセメントミルクが固化後に、拡大根固め層のコアボーリングを行い、上下方向に略4等分して、それぞれの一軸圧縮強度試験をおこなった。
【0048】
2.試験結果
試験結果の概要は次の表1の通りである。
【0049】
【表1】

Figure 0004958028
【0050】
なお、試験の各測定値の絶対値は、測定タイミング、測定地点ごとの地質強度等により本質的に差異があるため、測定値のバラツキで工法比較するのが適切である。一軸圧縮強度の測定値は、22N/mm前後で、電気比抵抗の測定値は、5Ωm 前後であった。
【0051】
3.試験結果のまとめ
(a) 新仕様(Case2、Case3)の圧縮強度バラツキは、10%以下で安定しており、従来の仕様(Case1、Case4)に比べ、1/2 以下に改善されている。更に、新仕様同士の電気比抵抗でのミクロな比較では、仕様2がより均質であることが分る。
従って、セメントミルクを撹拌しながら吐出し、少なくとも2回上下させる方法に効果があることが分る。
(b) 掘削土に強度上良くないシルトなどが混入している場合には、底部で(撹拌せずに)セメントミルクを吐出して拡大根固め層より上方(軸部)に押し上げることが望ましいので、この視点からも仕様2が望ましいことが言える。
(c) 今回、比較はしていないが、本試験の結果から、根固め層の掘削とセメントミルクの注入を併行実施する施工方法では、底部でセメントミルクを吐出できないために、新仕様に比べ層内のセメントミルクがバラツキ、根固め層の性能が劣ると判断される。
【0052】
(d) 撹拌方法としては、上記のような仕様で、撹拌混合した場合、撹拌装置として掘削ヘッド2をそのまま使用したので、掘削ロッド1の交換による時間的ロスが無く、簡便で、かつ撹拌に最も寄与する(撹拌時に外周側に位置する)掘削アーム6の先端部57を面積を大きく形成したので、杭穴の周辺部での撹拌効率が良く、更に粉砕不十分な掘削土があったとしても、更により細かく粉砕できるので、均一な混合が可能である。また、掘削時の1.5〜2.0倍の高速の回転をするので、更に撹拌効率が良い。
【0053】
また、撹拌動力源としても掘削時に使用したオーガーマシンを使用したので、その土質に適合した撹拌動力源として機能すると共に、掘削時の2倍の回転数まで回転した場合であっても確実かつ安定な撹拌混合が可能になった。
【0054】
従って、その杭穴掘削時の掘削ヘッド2、掘削ロッド1、オーガーマシン等の掘削装置をそのまま使用して、均質な撹拌混合ができる経済的にも優れた工法が確立できた。
【0055】
【実施例1】
図1乃至図10に基づきこの発明の実施例を説明する。
【0056】
(1)杭穴軸部8の掘削
【0057】
施工場所において、掘削機を据え付け、所定の杭埋設位置で、先端に掘削ヘッド2を有する掘削ロッド1で、杭穴7を掘削する(図1(a)(b))。前記掘削ロッド1は、中間部に撹拌バー3、3及び杭穴内壁を均す練付ドラム4、4を設けてある。また、杭穴7の掘削に当たり、掘削機のオペレータ室において、掘削状況(各種情報)が表示装置(各種ディスプレイ装置)に画面表示される(図4)。
【0058】
杭穴7の掘削径は、埋設予定の既製杭の節部径(750φ)+30mmを確保した杭穴軸部8とする。途中、掘削ヘッド2に設けられた吐出口5より適量の水を注水しながら掘削し、その掘削土を撹拌バー3、3で充分撹拌し、泥土化し、練付ドラム4、4で内壁7aに練り付けし、深さ46.5mまで掘削する。
【0059】
事前に、施工地盤において得られている標準貫入試験による測定結果が「N値表示欄27」に表示され(図5)、この測定結果に基づき、掘削深度とその深度でのN値を表示しながら、「積算電流値表示欄30」で掘削負荷電流の蓄積値(記録値)を並列表示し(図8)、両者を比較・確認しながら掘削する。もし、予定深さでの支持地盤における該記録値が適合しない場合には掘削深度を調整する。また、同時に、「流量・ヘッド位置表示欄28」にその時刻での深度と掘削中の注水量(A1)も一緒に表示・記録される(図6)ので、確認・調整する。
【0060】
表示装置における「積算電流値表示欄30」の掘削負荷電流の蓄積値としての記録値は、貫入試験のN値(打ち込み寸法30cm)と適合させるために、記録値としての掘削負荷電流の蓄積値の幅を、所定深度毎に、掘削寸法を30〜50cmの範囲で適当に可変・設定する。ここでは、深度50cm毎に50cm幅の負荷電流を蓄積して表示した結果、貫入試験のN値の変化と相対的にほぼ合致した傾向の値が得られることを確認した(図8)。従って、記録値は50cm幅の負荷電流蓄積値でA・sec(アンペア・秒)で表示してある。
【0061】
また、50cm毎に負荷電流値を表示することによって、通常の標準貫入試験の1m間隔の測定よりも精度を約2倍に向上させることができる。
【0062】
すなわち、標準貫入試験におけるN値の測定が、重量63.5kgのサンプラーを深度方向で土層範囲30cm打ち込む打撃数を示しており、本手法はその打撃前後に利用されている土層範囲50cm毎にその地盤の強度を仕事量に比例する数値で表示することができるようになっている。
【0063】
そこで、通常の掘削機の電源が定電圧で制御されていることを利用し、さらに、この掘削機の掘削時の負荷電流が地盤強度に比例することを前提として、標準貫入試験で利用する土層幅と略同一範囲(30〜50cm)でこの負荷電流を蓄積し、負荷電流の時間積(アンペア・秒)すなわち地盤強度と比例する仕事量単位でそのまま簡便に表示をすることにより、その現場の各掘削穴毎にその掘削地点での地盤強度とN値とを対比して、根固め層の築造位置が確かな工事ができるようにしたものである。ここで、蓄積土層幅は、土質のバラツキが多い、あるいは土層幅の広さなど必要により30〜50cmの範囲で調整するのが標準貫入試験での測定土層幅寸法と近似しており整合性が良い。
【0064】
即ち、このように掘削機の負荷電流の時間積を表示する構成としたので、杭穴掘削時の掘削電流に関して、標準貫入試験のN値測定で使用される土層巾とほぼ同一の範囲(30〜50cm)で連続して蓄積して、その蓄積完了時に、その深度毎に記録・表示するので、標準貫入試験の場合における、「深度毎(50cm毎)」の打撃回数の表示の当該「深度毎」にも対応できるようにしたものである。
【0065】
従って、施工現場の地盤強度に関して、数少ない標準貫入試験データを補い、施工現場全体の精度の高い地盤状況が把握できると共に、各杭基礎ごとにより適切な支持層を設定でき、より安全で確かな基礎を容易に提供することができる。
【0066】
その後、掘削土を撹拌しながら掘削ヘッド2を上下に反復移動させ、杭穴軸部8を築造する(図1(b))。また、支持地盤は、砂質土で、N値は30以上であった。この掘削結果(掘削深度等)に基づき、各杭穴毎に「基本データ表示欄26」の設定値を変更させることも可能である。
【0067】
(2)杭穴7の拡大根固め部9の掘削
【0068】
次に、掘削径を拡大し、吐出口5から注水しながら、拡大径1100mmで、深さ2.5mの拡大根固め部9を築造し、掘削土を撹拌しながら上下2回反復させる(図1(c))。
【0069】
表示装置における「流量・ヘッド位置表示欄28」で、表示記録としては、掘削深さと注水量を確認・調整する(図6)。
【0070】
(3)拡大根固め部9でのセメントミルク注入(根固め層の形成)
【0071】
本発明の方法を利用して、セメントミルクを注入し、均質な根固め層(ソイルセメント層)13を形成する。
【0072】
根固め用のセメントミルクは、セメント(JASS4 2節 4.2.1による)2590kg、水1554kgで、練上がり2.38mとする。
【0073】
先ず、掘削ヘッド2の吐出口5を拡大根固め部9の中央の底10付近に保持し、根固め液(前記の混合比のセメントミルク)全部の使用量(2.38m)の 1/3 をその位置のまま、掘削ヘッド2で撹拌しながら、毎分約200リットルで吐出する(1回目の吐出。図1(c)、図3(b))。
【0074】
次に、根固め液を同様に吐出しながら掘削ヘッド2を最上部まで撹拌しながら引き上げる(図1(d))。その間に根固め液全使用量の 1/3を吐出する(2回目の吐出。図3(b))。
【0075】
次に、根固め液を同様に吐出しながら、掘削ヘッド2を上下2回往復させ、底10に到達し終了するまでの間に根固め液使用量の残量の 1/3すなわち、規格以上のセメントミルクを注入しながら、掘削土と撹拌及び混合を行いソイルセメント層を形成する(3回目の吐出。図3(b))。
【0076】
表示装置の「流量・ヘッド位置表示欄28」には、その時刻での掘削ヘッド2の位置(深度m)、セメントミルク流量(m/ h )を表示・記録しており(図6)、表示切替により掘削ヘッド2の位置と根固め液注入量(m)のみの拡大表示を選択すれば、容易に根固め液注入量の対比・調整ができ管理精度を向上させることができ、また、「根固め液注入量表示欄31」で深度毎の根固め液注入量が確認できる(図9)。例えば、注入量不足時は再注入による修正をする。また、各施工条件、実績記録値が対比記録されており、施工後においても工事の証明資料としても利用できる。
【0077】
(4)杭穴軸部8でのセメントミルク注入(ソイルセメント層形成)
【0078】
杭穴軸部用のセメントミルクは、根固め液と調合比は同じであるが、杭周固定液(周辺固定液)とも言う。セメントミルクの吐出量を毎分100リットルで注入し、注入総量は2.22m以上とする(「基本データ表示欄26」図4)。
【0079】
先ず、拡大根固め部9の上端部15から吐出開始し、撹拌しながら深さ30mまで掘削ヘッド(注入口)を上下1往復させ、次に、深さ12mまで同様に吐出・撹拌しながら掘削ヘッド2を上下1往復させ、次に、深さ2m まで同様に吐出・撹拌しながら掘削ヘッド2を上下1往復させ、最後に杭穴口12まで同様に吐出・撹拌しながら掘削ヘッド2を上下往復させ注入を完了させる(図2(a)(b))。このようにして、杭穴軸部8内に杭周固定液層(ソイルセメント層)16を形成する。
【0080】
表示装置の「杭周固定液注入量表示欄32」には、その時刻での掘削ヘッド2の位置(深度m)とセメントミルク流量(m/h)を表示・記録しており、表示切替により掘削ヘッド2位置と注入量(m/h)のみの拡大表示を選択すれば、容易にセメントミルクの注入が手順通り実施されたか確認できる(図6、図10)。
【0081】
従って、各基礎杭の施工途中で、セメントミルク注入の補充などの修正ができ、また、所定の手順通りに施工された証明とすることもできる。
【0082】
尚、「流量・ヘッド位置表示欄」(図6)において、グラフAが時間当たりの吐出量(単位m/h)が縦軸として横軸を施工所要時間として表示され、0〜37分までは吐出口5から水を吐出して(A1)、37分〜46分までは根固め液を吐出し(A2)、46分以降は周辺固定液を吐出している(A3)ことを示す。また、グラフBで、吐出口5から吐出される水・根固め液・周辺固定液の総流量が逐次表示される。また、グラフCでは、縦軸を地上からの深度(m)に設定し、横軸を施工所要時間とし、掘削ヘッド2の位置が表示される。
【0083】
(5)既製杭20、22の埋設
【0084】
掘削ロッド1から掘削ヘッド2を取り外して、先ず、「BF6075―5m」既製杭20(軸径:φ600、節径:φ750、節杭)(「BF」は三谷セキサン株式会社の節杭の商標。以下、同じ。)をロッド1に装着し、回転させながらソイルセメントの充填された杭穴7へ沈設する。次に、「SCφ600−14m」既製杭22を連結・沈設し、以降、「SCφ600−15m」既製杭22、「SCφ600−15m」既製杭22と順次同様に連結し、連結杭の先端の「BF6075―5m」既製杭20の先端21を、拡大根固め層13の底14から約50cmの位置に押し込み埋設させ、既製杭20、22の埋設を完了させる(図2(c)(d))。ソイルセメントが固化後に、杭穴7内で既製杭20、22と根固め層13及び杭周固定液層16(ソイルセメント)とが一体となった基礎杭24を構築する。
【0085】
また、表示装置の「杭先端位置表示欄29」には、既製杭20、22の埋設時間が記録されると共に既製杭20の先端21の位置が記録され、その施工結果を既製杭20、22を埋設しながら、また各基礎杭24施工毎に確認できるとともに、施工内容の保証データとしても利用できる(図4、図7)。
【0086】
(6)完成した基礎杭24の評価
【0087】
(a) 最大荷重
根固め部(既製杭20と根固め層13)上部の載荷試験における節径の0.1D(Dは節杭軸部の径)沈下時の荷重は、7000kN以上が得られ、高支持力の品質が造成されていることが確認できた。すなわち、通常の基礎杭の2倍以上が得られた。
【0088】
(b) 根固め部の健全性
根固め部(既製杭20と根固め層13)を掘り出し、その外観および形状寸法を調査した結果、クラックや大きな欠損箇所はなく、掘削所定径以上の根固め部が造成されていることが確認された。
【0089】
(7)表示記録の効果
【0090】
図4(図5〜図10)の様式での表示装置に各種データが表示、出力が可能である。また、表示装置の表示欄の上端部の「基本データ表示欄26」には、予め「使用する既製杭の仕様」「掘削長」「杭天端位置」「セメントミルクの配合」「根固め液注入量及び杭周固定液注入量」が表示される(図4)。「根固め液注入量及び杭周固定液注入量」は規格量(設計値)が施工前に表示されると共に、施工中に実際の使用量が逐次表示される。
【0091】
(a) 掘削穴の深度、掘削負荷電流の蓄積値(N値代用特性記録値)、流量計の実計測値を対比表示するので、根固め部等の施工状況をリアルタイムで確認・管理できる(図5、図6、図8〜図10)。
(b) 地盤強度をN値の近似代用特性(負荷電流蓄積値)で確認掘削できるので適正な支持層が設定できる(図5、図8)。
(c) セメントミルクの注入、撹拌の状況が経過時間と深度とで併行確認、管理ができる。また、杭穴の実際の掘削データ(支持層位置等)に基づき、セメントミルクの注入位置、量等の設定条件等を修正できる。
(d) 施工が確実に実施されたか否かの総合的品質証明資料となり、従来に比べ、より緻密な施工報告書の実記録として活用できる(図4)。
【0092】
【実施例2】
次にこの発明の他の実施例を説明する。
【0093】
(1)杭打ち機42の基本的構成
【0094】
この発明の実施に使用する杭打機42には、自走できるベース34の一側にリーダー35が起立されており、このリーダー35の上先端に設けたトップシーブ36を介してワイヤ37が昇降自在に吊り下げられ、ワイヤ37の先端にオーガマシン38が接続されている。ワイヤー37の基端は、ベース34上に取り付けられた巻出し装置41を介して、巻出し用のモータ(図示していない)の軸に取り付けてある。
【0095】
オーガマシン38の基端には駆動モータ40を収納したボックス39が取付けられており、このボックス39の下部には駆動モータ40で回転駆動される掘削ロッド1が垂下されている。掘削ロッド1は、前記実施例1と同様で、下端に掘削ヘッド2が取り付けられていると共に、掘削ロッド1には所定間隔を置いて軸方向に沿って複数の撹拌棒3、3と練付ドラム4、4が配設されている。
【0096】
また、図中43は、オーガマシン38の駆動モータ40、ワイヤー巻出し用のモータ等に電気を供給する発電機である(図11)。発電機43から供給される電気は杭打機42に設けられている配電盤43aに送られ、そこからオーガマシン38等に配電される。
【0097】
(2)施工管理装置の構成
【0098】
次にこの装置の制御系統を説明する。
【0099】
(a) センサー類
杭打ち機42に設けられている配電盤43a又は発電機43にはオーガマシン38の駆動モータ40の負荷電流を測定する負荷電流計44が接続されている。負荷電流計44からのデータは、オペレータ室内のアンプボックス50に入力される(図12)。
【0100】
また、杭打機42のリーダー35の下端部にロータリーエンコーダからなる深度計45が設置され(図11)、深度計測用ワイヤ37aが深度計45を介してリーダー35に沿ってオーガマシン38に取付けられている。これによって、オーガマシン38の降下量、すなわち掘削深度を検知する。深度計45からのデータはオペレータ室内のアンプボックス50に入力される(図12)。尚、深度計45はロータリーエンコーダに限らず、他の計測具とすることもでき、またオーガマシン38に取付けられているワイヤ37の繰り出し量から深度を計測してもよい。
【0101】
また、ここでは深度計45をリーダー35の下端部としたが、リーダー35のどの位置に設けてもよく、またオーガマシン38に設置してもよい。
【0102】
また、構築現場内(又は構築現場に近接して)に、水やセメントミルク等の硬化性材料を生成して送り出すプラント46が設置され、プラント46と杭打ち機42とは耐圧ホース47でつながっている。耐圧ホース47は、掘削ロッド1を通って掘削ヘッド2の吐出口5から吐出できるようにオーガマシン38に連結されている。この耐圧ホース47の中間部、例えば、ベース34の杭打ち機42側に、吐出量を検知するための流量計48が設置されている(図11)。流量計48のデータは、オペレータ室内のアンプボックス50に入力される(図12)。
【0103】
また、オーガマシン38の下降開始(深度計45の作動)に対応して、掘削開始からの施工所要時間(min.)が計測される。
【0104】
(b) 管理装置
アンプボックス50で、まとめられた各センサー44、45、48からのデータは、パーソナルコンピュータ(以下、PC)51で制御、演算、処理されて画面(データー表示装置)52に表示されるとともに、PC51からの操作により、印刷機53に紙出力も可能である。また、負荷電流計44、深度計45及び流量計48から得られるデータは、一般にアナログ信号であるため、アンプボックス50内のA/D変換器によってデジタル信号に変換して、PC51に送られる。
【0105】
ここで、オペレータ室55内とは、プラント内、現場施工管理者等の常駐事務所内等の現場敷地内の施設や、あるいは杭打ち機の操作室内、または現場外の独立した施設内に配置される。また、オペレータ室は、雨天等を考慮して屋根のある施設(例えば、仮設建物、仮設テント等)が望ましいが、作動に支障が無ければ、屋根の有無は問わない。
【0106】
また、アンプボックス50でまとめられて、PC51で処理されたデータは、以下のように画面52に、各表示欄27〜32毎に分割して表示される(図4)。また、各表示欄27〜32を単独で切り替えて拡大表示することもできる(図5〜図10)。また、複数欄を組み合わせて並べて表示することもできる(図示していない)。
【0107】
即ち、深度計45からのデータは処理され、地面18からの杭先端位置(m)を縦軸に、杭挿入所要時間(min.)を横軸にして、対応させたグラフが、画面52の「杭先端位置表示欄29」に表示される(図7、図4)。
【0108】
また、深度計45及び負荷電流計44からのデータは、一定掘削範囲(例えば、深さ30cm毎)に要した駆動モータ40の負荷電流を、該掘削範囲に要した時間で積算し、蓄積した積算電流記録値(Amp×sec)として処理される。深度計45からのデータは、別途処理され地面18からの深度(m)を縦軸に、前記積算電流記録値を横軸にして、対応してグラフ化され、画面52の「積算電流値表示欄30」に表示される(図8、図4)。
【0109】
また、杭穴の実際の掘削データ(支持層位置等)に基づき、各杭穴毎に「基本データ表示欄26」の設定値も必要により修正され、表示される。
【0110】
また、流量計48からの根固め液の注入量(m)のデータを横軸に、深度計45からのデータは、地面18からの深度(m)として縦軸に設定し、対応してグラフ化され、画面52の「根固め液注入量表示欄31」に表示される。この際、各深度毎の「設計時の根固め液の規定量」が、同時に表示され、掘削データにより見直しされた設計量と実際の注入量とを比較できる(図9、図4)。この場合、各深度毎に実際の注入量が設計量に達した場合に、画面52に案内表示を点滅させ、あるいは警告を促す音を発するようにすることもできる。
【0111】
また、同様に、流量計48からの杭周固定液の注入量(m)のデータを横軸に、深度計45からのデータは、地面18からの深度(m)として縦軸に設定し、対応してグラフ化され、画面52の「杭周固定液注入量表示欄32」に表示される。この際、各深度毎の「設計時の杭周固定液の規定量」が、同時に表示され、設計量と実際の注入量とを比較できる(図10、図4)。この場合、各深度毎に実際の注入量が設計量に達した場合に、画面52に案内表示を点滅させ、あるいは了解音を発するようにすることもできる。
【0112】
また、予め標準貫入試験時のボーリングデータ(N値、土質名等)をPC51に入力しておく。深度計45からの受ける地面18からの深度(m)のデータを縦軸に、各深度(m)毎の「N値」を横軸にして、対応させてグラフ化され、画面52の「N値表示欄27」に表示される(図5、図4)。この場合、N値以外の他のボーリングデータ(土質名等)を各深度(m)毎に、N値に対応させて同時に表示することもできる(図示していない)。
【0113】
また、施工開始からの所要時間(min.)を横軸として、縦軸に、流量計48から「掘削用の水、根固め液又は杭周固定液」の時間当たりの流量(m/h)を表示する。また、同じく縦軸に、流量計48から吐出物の総流量(累積流量。m)を同時に表示する。また、同じく縦軸に、深度計45から得られる地面18からの「ヘッドの位置(m)」を同時に表示する。所要時間(min.)を共通の横軸とした3つのグラフが、画面52の「流量・ヘッド位置表示欄28」に、同時に表示される(図6、図4)。
【0114】
以上のような情報処理機能(演算、制御)、画面52、内蔵又は外付けの記憶手段を持った「PC51」と「印刷機53」、深度計45、流量計48、負荷電流計44からなるセンサー類を接続した「アンプボックス50」と、PC51、アンプボックス50、印刷機53に定格電源を供給する「電源装置(例えば、発電機54、蓄電器など)」により、この発明の施工管理装置を構成する。
【0115】
また、深度計45、流量計48、電流検出器44からなるセンサー類を接続した「アンプボックス50」に無線送信アンテナを取付け、遠隔地(例えば施工現場の事務所内)に設置したPC51に無線受信アンテナを取付け、アンプボックス50に収集される種々のデータを無線で送受信することもできる(図示していない)。このように、施工管理データの記憶、制御装置類を施工中の場所以外に設置するによって、施工現場の塵、土泥飛散や雨天等、また施工機械の震動による破損トラブルから隔離され、施工管理情報を安定して利用できる。
【0116】
また、インターネット等を利用することにより、施工現場外から施工情報を随時取得し、施工進捗管理等に使用することが可能である。
【0117】
【実施例3】
次に、本施工管理装置を使用した施工管理方法について述べる(図13)。
【0118】
(1) 杭施工位置での、「使用杭(ここでは上杭、中杭、下杭を使用し、各杭の種類外径、長さ等)」「掘削孔の深さ(GL(地面18)からの深さ」「杭天端(GL(地面18)からの位置)」「(1バッチ毎の)セメントミルク配合(ここではセメント750kg、水450kg、錬り上り量0.69m)」「根固め液注入量の規格値(ここでは2.38m)」「杭周固定液注入量の規格値(ここでは、2.22m)」を入力する。これらのデータは、画面52の上部の「基本データ表示欄26」に表示される(図4)。尚、「根固め液注入量」「杭周固定液注入量」は掘削データにより見直しされた規格値に並列して、実際の注入量が逐次表示される。
【0119】
前記規格値は、例えば、
杭軸部径 600mm
突起部径 750mm
杭穴軸部径 780mm
杭穴拡底部径 1100mm
の場合に、
根固め液の充填量は、10cm毎に0.061m
杭周固定液の充填量は、 1m毎に0.0478m
程度となる。
【0120】
(2) また、予め入手しているボーリングデータ(N値、土質名等)をPC51に入力し、ボーリングデータの深度と掘削深度を対応させ、深度を基準とした積算電流値が「積算電流値表示欄30」に表示される(図8、図4)。
【0121】
このとき、施工情報(例えば、施工法、掘削深度、掘削径、硬化性材料の注入量等)、施工機械情報(例えば、低速ベース電流値(Amp)、低速回転数(回/分)、高速ベース電流値(Amp)、高速回転数(回/分)等)などを入力しておく。これらのデータも切り替えて画面52に表示することもできる(図示していない)。
【0122】
(3) 掘削ロッド1を搭載した杭打ち機42を所望の杭打ち位置に移動し(図11)、駆動モータ40で掘削ロッド1を正回転(例えば時計周り)させつつ、ワイヤ37を介して、リーダー35に沿って、オーガマシン38を徐々に降下させる。掘削ロッド1の先端には、本体6aと2本の掘削アーム6、6とからなる掘削ヘッド2が取付けられており、掘削ロッド1の回転と共に2本の掘削アーム6、6が開き、掘削アーム6、6先端の掘削刃と本体6a下端部の掘削刃によって杭穴軸部の掘削を行う(図11、図15(b))。
【0123】
この際、オーガマシン38の下降量は、掘削深度として、深度計45で検出されており、掘削ヘッド1の掘削刃が地面と接した状態で深度を「0(ゼロ)」とするように初期設定を行う(図15(a))。また、駆動モータ40の負荷電流は、負荷電流計44で連続的に検出されており、無負荷時の測定電流が初期電流として設定される。
【0124】
(4) オーガマシン38を引き続き下降させることによって、掘削ヘッド1の先端より水等を吐出しながら地盤が掘削され、撹拌バー3、3で掘削土を撹拌しつつ、練付ドラム4、4で杭穴7の内壁7aに練付ける。このとき、吐出する水の量は流量計48によって、各深度毎の吐出量がグラフ化されて、PC51の画面52上に表示される。
【0125】
掘削に際して、地盤の固さにより、駆動モータ40に対する負荷が変わり、これに応じて負荷電流が変化する。これによって、所定掘削間隔(例えば50cm毎)ごとに負荷電流値を蓄積し、該掘削間隔に要した掘削時間とを演算処理し、積算電流値として、予め入力されているボーリングデータのN値、土質名と共に深度を基準として掘削と同時に表示される(図5、図8、図4)。積算電流値は、N値と近似的な曲線を描くため、仮に掘削中に積算電流値がN値と異なる曲線を描いた場合、ボーリングと異なる地盤が存在することが確認でき、施工中に適切な対応をとることができる。
【0126】
(5) 引き続き掘削を続行し、所定強度の支持層に到達したことをPCの画面52に表示されているN値と積算電流値とによって確認し(図5、図8)、支持層を所定深度掘削した後、掘削ロッド1を逆回転させて、掘削ロッド1を引上げながら杭穴拡大根固め部9の掘削を行う。拡大根固め部9の掘削時には、掘削ロッド1を逆回転させ、掘削ヘッド2の掘削アーム6、6を通常掘削時とは逆に揺動して拡開し、拡大掘削状態となる。杭穴の拡大根固め部は所定高さ(例えば、250cm)設ける必要があるが、深度計45によって掘削ヘッド2の位置がPCの画面52に表示されているため(図6、図4)、所定高さの拡大根固め部9の掘削を行うことができる。
【0127】
(6) 所定大きさの杭穴7の拡大根固め部9を形成した後、バルブ(図示していない)を切り替えて、吐出物を水からセメントミルクに切り替える。プラント46から耐圧ホース47を通して、掘削ヘッド2の吐出口5からセメントミルクが杭穴内に供給される。
【0128】
(7) PC51の画面52の「基本データー表示欄26」「根固め液注入量表示欄31」「杭周固定液注入量表示欄32」には、先に入力した根固液、杭周固定液の規格値が表示される。また、所定深度間隔毎の充填量はグラフ化されて、画面52の「流量・ヘッド位置表示欄28」「積算電流値表示欄30」「根固め液注入量表示欄31」「杭周固定液注入量表示欄32」に表示し(図6、図9、図10、図4)、規格値以上のセメントミルクが注入されているかどうかを目視で、確認しながら施工を行う。また、同時に根固め液、杭周固定液の実際の使用量が、規格値と共に並列して「基本データー表示欄26」表示される(図4)。
【0129】
(8) 先ず、杭穴7の拡大根固め部9内に根固液としてのセメントミルク(固化強度20N/mm)を注入する。所定深度間隔毎の充填量を画面52で確認しながら、拡大根固め部9内において、掘削ロッド1(掘削ヘッド2)を逆回転させながら上下反復して、掘削土と撹拌・混合し、根固め層13(ソイルセメント層。固化強度20N/mm以上)を形成する。
【0130】
このとき、セメントミルク量が規格値を超えていない場合には、該当深度で、セメントミルクを再注入する。
【0131】
(9) 前記における根固め層13の構築、即ち、杭穴7の拡大根固め部9内でのセメントミルクの注入は、根固め層13内のソイルセメントの品質のばらつきを少なくするために、前記実施例1と同様に行うことが望ましい。
【0132】
即ち、杭穴7の掘削完了後、掘削ヘッド2を杭穴底10に保持した状態で掘削ヘッド2で撹拌しながら、掘削ヘッド2下端の吐出口5から根固液としての全セメントミルク量の3分の1宛セメントミルクを吐出する。続いて、掘削ヘッド2で撹拌しながら、掘削ロッド1を杭穴7の拡大根固め部9の上端部15付近まで上昇させながら全セメントミルク量の3分の1宛を吐出する。次に、掘削ヘッド2を拡大根固め部9内で(杭穴7の底14と拡大根固め部9の上端部15との間を)複数回昇降させながら、残りのセメントミルクの3分の1宛を吐出して、撹拌及び混合を行い、掘削ロッド1を引き上げて拡大根固め部9内にソイルセメント層からなる根固め層13を形成する(図3(b)、Case 2)。
【0133】
このような複雑な施工であっても、画面52の「流量・ヘッド位置表示欄28」「根固め液注入量表示欄31」等で、根固め液(セメントミルク)、掘削ヘッド2の位置を目視により確認しながら行うことができ、細かい施工管理が極めて容易かつ確実にできる。
【0134】
(10) また、他の望ましいセメントミルクの注入方法は、先ず、掘削ヘッド2の吐出口5を杭穴7の拡大根固め部9の底(構築予定の根固め層の底部)のほぼ中央に設置し、撹拌・吐出しながら拡大根固め部9内を上下2往復させて、上端部15で注入を完了させる(図3(c)、Case 3)。
【0135】
また、拡大根固め部9の底10で掘削ヘッド2の吐出口5から全量のセメントミルクを注入して、拡大根固め部9内の掘削泥土を押し上げて、掘削泥土をセメントミルクと置換してセメントミルク層からなる拡大根固め層13を形成することもできる(図3(d)、Case 4)。
【0136】
(11) 次に、拡大根固め部9内にセメントミルクを注入し、根固め層13の構築が完了した後、掘削ロッド1を正回転に戻し、掘削ヘッド2を通常掘削状態にして、引き続き杭穴7の軸部8内に杭周固定液(固化強度20N/mm)の注入を開始する。杭周固定液に関しても、根固液の注入と同様に、所定深度間隔毎の充填量を規格量とをPC51の画面52の「流量・ヘッド位置表示欄28」「杭周固定液注入量表示欄32」で比較して確認しながら、杭穴7の軸部8内にソイルセメント層からなる杭周固定液層16(固化強度2N/mm以上)を形成する。このとき規格充填量を満たしていない場合には、根固液と同様に該当深度に再注入を行う。
【0137】
(12) 前記における杭穴7の軸部8内でのセメントミルクの注入方法、即ち杭周固定液層(ソイルセメント層)16の形成についても、根固め層13の上端部15の位置より上方に、掘削長さに応じて、1又は複数の所定深度を決め、根固め層13の上端部15からセメントミルクの注入を開始し、その所定深度間ごとに往復して、掘削土と撹拌・混合しながら、杭周固定層16を形成する。
【0138】
杭周固定液(セメントミルク)の充填量の管理については、杭穴7の軸部8の一定範囲(例えば1m毎に)において、所定深度間隔毎に注入したセメントミルク量の平均値を算出し、該平均値が規格充填量を超えていれば、施工は適当とすることもできる。
【0139】
(13) 続いて、セメントミルクを基準充填量以上充填した後、前記実施例1と同様に、上杭、中杭及び下杭とからなる既製杭を挿入し、基礎杭24を構築する。
【0140】
掘削ロッド1から掘削ヘッド2を取り外して、回転キャップを取付け、先ず、「BF6075―5m」既製杭(下杭)20(軸径:φ600、節径:φ750、節杭)(「BF」は三谷セキサン株式会社の節杭の商標。以下、同じ。)を回転キャップに装着し、回転させながらソイルセメントの充填された杭穴7へ沈設する。次に、「SCφ600−14m」既製杭(中杭)22を連結・沈設し、以降、「SCφ600−15m」既製杭22、「SCφ600−15m」既製杭(上杭)22と順次同様に連結し、連結杭の先端の「BF6075―5m」既製杭20の先端21を、拡大根固め層13の底14から約50cmの位置に押し込み埋設させ、既製杭20、22、22の埋設を完了させる(図2(c)(d))。ソイルセメントが固化後に、杭穴7内で既製杭20、22、22と根固め層13及び杭周固定液層16(ソイルセメント)とが一体となった基礎杭24を構築する。
【0141】
また、PC51の画面52の「杭先端位置表示欄29」には、既製杭20、22の埋設時間が記録されると共に既製杭20の先端21の位置が記録され、その施工結果を既製杭20、22を埋設しながら、また各基礎杭24施工毎に確認できるとともに、施工内容の保証データとしても利用できる(図4、図7)。
【0142】
【実施例4】
次に、図16、図17、図14に基づき、杭長が長尺となった場合(例えば50m程度)の施工について説明する(図14)。
【0143】
杭長が長尺(例えば50m)となった場合、杭打ち機42のリーダー35は通常20m程度であり、長さに限界があるため、掘削ロッド1の上端に他のロッド(掘削ロッド1から掘削ヘッド2を外した構造)の下端を連結して、当該他のロッドの上端をオーガマシン38に取り付けて掘削を続ける。
【0144】
また、逆に、杭穴掘削が完了し、セメントミルクを注入して掘削ロッド1を杭穴7から引上げる際に、杭打ち機42のリーダー35の長さに限界があるため、セメントミルクの注入を中断して掘削ロッド1から他のロッド25を所定長切り離す必要があった。
【0145】
即ち、以下の手順で施工を行う。セメントミルクの注入方法、基礎杭20、22の埋設方法は、前記実施例2、3と同様である。
【0146】
(1)一方の杭芯A側
【0147】
前記実施例3のように、杭打ち機42のオーガマシン38に取り付けた掘削ロッド1Aで、所定の深さまで杭穴7Aの軸部8Aの上部を掘削し、続いて、掘削ロッド1Aをオーガマシン38から取り外し、掘削ロッド1Aの上端部1aを杭穴7Aの上方で仮設支持する。掘削ロッド1Aの上端1aに、他の掘削ロッド25の下端25bを連結すると共に、他の掘削ロッド25の上端25aをオーガマシン38に連結して、残り(下部)の杭穴軸部8A、拡大根固め部9Aを掘削する(図16、図17(a))。
【0148】
続いて、掘削ロッド1Aの掘削ヘッド2Aの吐出口5Aからセメントミルクを吐出して、根固め層13Aを形成する。続いて、掘削ロッド1A及びロッド1aを引き上げながら、同様に吐出口5Aからセメントミルクを吐出して、杭周固定液層16Aの下部を形成する。
【0149】
この状態で、掘削ロッド1Aの上端部1aが地面18上に現れるので、掘削ロッド1Aの上端部1aを杭穴7Aの上方で仮設支持する。同時に、掘削ロッド1Aから他の掘削ロッド25を取り外す(図16(A−1)、図17(b))。この状態までの、一方の杭芯A側での杭穴掘削データは、前記実施例3と同様の管理装置で、施工管理されており、そこまでの管理内容が、PC51に保存記憶される。杭芯Aには杭番号が付与されており、この杭番号でPC51に記憶されるため、容易に読み出し、保存することができる。
【0150】
(2)他方の杭芯B側
【0151】
先端に掘削ヘッド2Aの取付けられている方の掘削ロッド1Aはそのまま杭穴7A内に保留する。
【0152】
同じ杭打ち機42のオーガマシン38に、取付けられている他の掘削ロッド25の先端に他の掘削ヘッド2Bを取付けて(図17(c))、杭打ち機42は、次の杭芯B側で、杭穴7Bの掘削を開始する(図16(B−1))。この際、施工管理は、前記記憶した杭穴7A側の管理とは別に、杭穴8Bの施工管理として、実施例3と同じように(杭穴7Aと同じように)施工管理される。即ち、1台の杭打機42によって、2つの杭芯(杭埋設位置)A、Bで、一方はセメントミルクの充填工程、他方では掘削工程が進行することになる。
【0153】
同様に、他の掘削ロッド25で、杭穴7Bの軸部8Bの上部を掘削した状態で(図17(d))、掘削ロッド1Bの上端1aを杭穴7Bの上方で仮設支持し、オーガマシン38から他の掘削ロッド25を取り外す(図16(B−2)、図17(e))。
【0154】
以上の管理内容は、杭芯B側の管理内容として、アンプボックス50内あるいは、PC51内の記憶装置に一時保存される。また、杭芯Bについても杭番号が付されているため、杭穴7Aと交互に、あるいは同時にPC51のPCの画面52に表示することができる。
【0155】
(3)一方の杭芯A側
【0156】
先端に他の掘削ヘッド2Bの取付けられている方の他の掘削ロッド25はそのまま杭穴7B内に保留する。
【0157】
杭打ち機42を杭芯A付近に移動し、オーガマシン38に、杭穴7A内に保留された掘削ロッド1Aの上端部1aを連結する(図17(f))。アンプボックス50内あるいは、PC51内の記憶装置に一時保存されていた、杭芯A側の管理情報を読み出し、掘削ロッド1Aの仮設支持を解除する。
【0158】
掘削ロッド1Aの吐出口5Aからセメントミルクを吐出して、杭周固定液層16Aの上部を形成しながら掘削ロッド1Aを引き上げる。この際、必要ならば、掘削ロッド1Aを若干下方に戻してからセメントミルクの吐出を開始することもできる。この場合も掘削ヘッド2Aの位置は、深度計45で測定されている。
【0159】
掘削ロッド1Aを杭穴7Aから引き抜けば(図17(g))、根固め層13A、杭周固定液層16Aが形成された杭穴7Aが構築される(図16(A−2))。
【0160】
以下、同様に、杭打ち機42のオーガマシン38から掘削ロッド1Aを取り外し、既製杭20、22を埋設して、杭芯Aに基礎杭24を構築する。
【0161】
(4)他方の杭芯B側
【0162】
杭打ち機42を杭芯B付近に移動し、杭穴7Bに保留されていた他の掘削ロッド25の上端部に掘削ロッド1Bの下端部を連結すると共に、掘削ロッド1Bの上端部を杭打ち機42のオーガマシン38に連結する(図17(h))。アンプボックス50内あるいは、PC51内の記憶装置に一時保存されていた、杭芯B側の管理情報を読み出し、掘削ロッド1Bの仮設支持を解除する。
【0163】
尚、ここで、掘削ロッド1Bを使用したが、杭芯A側での構築において、取り外した掘削ロッド1A(図17(g))をそのまま転用することもできる(図示していない)。
【0164】
以下同様に、杭穴軸部8Bの下部、杭穴拡底部9Bを掘削し(図17(i))、根固め層13B、杭周固定液層16Bの下部を形成した状態で、図16(A−1)と同様に、掘削ロッド1Bを杭穴7Bの上方で仮設保持する(図示していない)。
【0165】
この状態で、杭芯B側の管理情報を、アンプボックス50内あるいは、PC51内の記憶装置に、再び一時保存する。
【0166】
(5) 続いて、杭芯Bと同様に、他の杭芯C側で、施工をする。
【0167】
このように、杭芯ごとに杭番号を付して施工管理状況を記憶しているため一方の杭芯Aの施工管理表示をアンプボックス50内あるいは、PC51内の記憶装置に一時保存した状態で、他方の杭芯Bの施工管理状況を表示することができ、また他方の杭芯Bの施工管理状況を一時保存して、一方の杭芯Aの施工管理状況を再度読み出し、セメントミルクの注入が完了、必要とあれば杭埋設完了までの施工管理状況を表示することができる。
【0168】
従って、少ない杭打ち機42でも効率よく活用して、基礎杭を施工することができ、この場合でも、同様の施工管理ができる。
【0169】
【発明の効果】
この発明は、注入すべきセメントミルクを複数回に分けて、セメントミルクの吐出口を杭穴底部内で少なくとも2回上下移動させながらセメントミルクを注入するので、固化後形成される根固め層は、外径のバラツキ、圧縮強度のバラツキも少なく安定しており、均質に形成でき、根固め層の品質を高められる効果がある。また、従って、強固な根固め層を形成でき、基礎杭と一体になり杭穴内の基礎杭及び固化物の全体で、杭穴径に相当する高支持力を発揮できる。また、根固め層の固化前の初期沈下に関しても、これを防止できることが期待できる。
【0170】
更に、根固め層内を撹拌する装置として、根固め層を掘削した時の掘削ヘッド及びオーガマシン等の掘削装置をそのまま使用して、高支持力を有する均質な層を形成できるように各種の撹拌条件を確立できたので、別途に新たな撹拌装置を準備することもなく、簡便で経済的な撹拌・混合ができた。
【0171】
とりわけ、杭穴の底で、全セメントミルク量の 1/3宛をまず吐出する場合には、支持地盤の地質に良くない成分が杭穴内に残存している場合でも、比重の低いこれらの成分をセメントミルクが押し上げ、噴出させることができ、更に安定した高品質の根固め層が得られる。
【0172】
この発明の管理方法又は管理装置によれば、杭穴掘削時には、オーガーが負担する負荷電流を積算電流値に変換して、掘削と同時に表示することによって、掘削時の状況及び支持層の設定・確認を行い、引続きセメントミルクを注入の際には、所定深度間隔毎の充填量を注入と同時に表示することによって、注入状況の確認ができ、一貫した基礎杭の施工精度を向上させることができる効果がある。
【0173】
注入状況を注入と同時にパーソナルコンピュータ等の情報処理手段で処理して表示することによって、所定深度間隔毎のセメントミルクを、深さに応じた充填量を確実に基準量以上注入できる効果がある。
【0174】
杭穴内の所定深度間隔毎に基準量以上のセメントミルクを注入できるため、深さに応じた必要でかつ安定した支持力を得られると共に、構築現場の隣接する基礎杭同士の支持力の不均衡を極力抑えることができる効果がある。
【0175】
また、施工管理にあたり、杭穴1つずつ情報処理手段で処理した内容を表示し保存蓄積できるので、各杭穴毎の施工条件をオペレータが混乱することなく、1つの杭打ち機を使用して、1つの杭穴を工程を分割して隣接する杭穴を交互に構築する際にも、一時保存されている施工途中のデータをそのまま継続使用して施工管理できるので、基礎杭を構築する施工効率を高めることができる効果がある。
【図面の簡単な説明】
【図1】(a)〜(d)は、この発明の実施例のセメントミルク注入方法を説明する縦断面図である。
【図2】(a)〜(d)は、同じくこの発明の実施例のセメントミルク注入方法を説明する縦断面図である。
【図3】セメントミルクの吐出仕様を説明する「セメントミルク吐出量−深さ」のグラフで、(b)(c)は本発明の仕様、(a)(d)は比較例の仕様を夫々表す。
【図4】この発明の実施例に使用する掘削中の施工データー表示例である。
【図5】図4の施工データの「N値表示欄」の拡大図で、縦軸に深度、横軸にN値を表示したグラフである。
【図6】図4の施工データの「流量・ヘッド位置表示欄」の拡大図で、縦軸に深度又は流量、横軸に施工所要時間(分)で表示したグラフである。
【図7】図4の施工データの「杭先端位置表示欄」の拡大図で、縦軸に杭先端位置(深度)、横軸に杭を挿入開始してからの所要時間(分)を表示したグラフである。
【図8】図4の施工データの「積算電流値表示欄」の拡大図で、縦軸に深度、横軸に積算電流値を表示したグラフである。
【図9】図4の施工データの「根固め液注入量表示欄」の拡大図で、縦軸に根固め部深度、横軸に根固め液注入量を表示したグラフである。
【図10】図4の施工データの「杭周固定液注入量表示欄」の拡大図で、縦軸に深度、横軸に杭周固定液注入量を表示したグラフである。
【図11】この発明の実施に使用する杭打ち機の正面図である。
【図12】この発明の施工管理装置の実施例で、構成を表す図である。
【図13】この発明の施工管理方法の実施例のフロー図である。
【図14】この発明の施工管理方法の他の実施例(実施例4)のフロー図である。
【図15】この発明の施工方法を説明する縦断面図である。
【図16】この発明の実施例4の施工方法を説明する縦断面図である。
【図17】(a)〜(i)は、同じく実施例4の施工方法を説明する概略した縦断面図である。
【図18】この発明の実施に使用する掘削ヘッドで、(a)は拡大正面図、(b)は一部を破切した部分拡大側面図である。
【符号の説明】
1 掘削ロッド
2 掘削ヘッド
3 撹拌バー
4 練付ドラム
5 吐出口
6 掘削アーム
7 杭穴
7a 杭穴内壁
8 杭穴の軸部
9 杭穴の拡大根固め部
10 底(拡大根固め部)
11 上縁(拡大根固め部)
12 杭穴口
13 根固め層
14 底(根固め層)
15 上端部(根固め層)
20 既製杭
21 既製杭の先端
22 既製杭
24 基礎杭
26 基本データー表示欄
27 N値表示欄
28 流量・ヘッド位置表示欄
29 杭先端位置表示欄
30 積算電流値表示欄
31 根固め液注入量表示欄
32 杭周固定液注入量表示欄
38 オーガマシン
40 駆動モーター(オーガマシン用)
41 巻出し装置(杭打ち機)
42 杭打ち機
44 負荷電流計
45 深度計
46 プラント
47 耐圧ホース
48 流量計
50 アンプ・ボックス
51 パーソナルコンピュータ(PC)
52 PCの画面
53 印刷機
55 オペレータ室
57 掘削アームの先端部
58 掘削アームの掘削刃[0001]
BACKGROUND OF THE INVENTION
This invention is a method for constructing a pile hole consolidation layer characterized by cement milk injection, which is used when burying a ready-made pile in a pile hole,
Further, the present invention relates to a construction management method for a foundation pile that manages construction of a foundation pile including a construction method for this pile hole consolidation layer, and a construction management device used for the construction management method.
[0002]
[Prior art]
Drilling a pile hole, injecting cement milk into the bottom of the pile hole, forming a consolidation layer, sinking a ready-made pile in the pile hole, and fixing the lower end of the pre-made pile to the consolidation layer It has been broken.
[0003]
Conventionally, the quality of the root hardening layer is managed only by the uniaxial compressive strength after the lapse of a predetermined period of the cement milk itself before pouring into the root hardening part, up to the construction method and management method when forming the root hardening layer. , Did not go around.
[0004]
Further, recently, a method has been performed in which a pre-made pile having a protrusion at least at the lower end is sunk in the pile hole, and the protrusion at the lower end of the pre-made pile is fixed to a rooting layer having an expanded bottom. In this case, since the ready-made pile having the root hardening layer and the protrusion is firmly consolidated, the supporting force is greatly improved.
[0005]
Conventionally, in order to investigate the ground strength and the like, a soil investigation by a standard penetration test is performed according to the size of the construction site prior to the foundation pile construction. In this soil investigation, ground strength is estimated by measuring the number of impacts (N value) required to drive a steel sampler 30cm by boring, and the soil name is determined from the collected samples. A diagram is created.
[0006]
In this case, in confirming the support layer, the current value (integrated current value (Amp · sec), etc.) from the excavator is compared with the soil column diagram of the attached sheet, or the N value of the soil column diagram is integrated with the depth as a reference. A method of displaying current values on the same screen is known (Japanese Patent Laid-Open No. 5-280031 “Pile support layer detection device”).
[0007]
[Problems to be solved by the invention]
According to the construction method in which the structure that mainly contributes to the high bearing capacity, such as the protrusions formed at the lower end of the ready-made piles, is laid in the rooting layer, the performance of the high bearing capacity is approximately twice that of the conventional method. Therefore, in the construction of the root hardening layer that expresses its high bearing capacity, the construction quality of the root hardening layer is important.
[0008]
After excavation of the bottom of the pile hole in the construction of the root solidification layer, this soil cement layer is built to a uniform high solidification strength quality in the process of agitating the excavated soil, injecting and mixing cement milk to form a soil cement. Therefore, there is a demand for a method for constructing a new root hardening layer and quality control of cement milk. While it is necessary for the root-capping layer to be reliably formed in a soil layer of a predetermined strength, in particular, management of the quality and filling amount of the curable material is in question.
[0009]
For example, the root solids of a pile hole having an enlarged bottom part is injected with a root solid liquid, and a pile circumference fixing liquid is injected into the shaft part of the pile hole, and each is mixed with excavated soil to form soil cement, and at least the lower end in the bottom part In the construction method in which the lower end of the pile with protrusions having one or more protrusions in the part is embedded, and the supporting force and the pulling force are greatly improved by the support pressure from the lower end surface of the pile and the protrusions, The ground strength of the root hardening layer, the root solid liquid to be filled, the filling amount per predetermined depth of the pile periphery fixing liquid, and the quality when the soil cement is formed are important management items.
[0010]
In the invention described in Japanese Patent Laid-Open No. 5-280031, the integrated current value from the start of excavation and the N value input in advance are displayed on the same screen with reference to the depth, and the role is played after confirmation of the support layer. Finished. Normally, filling of curable materials such as cement milk is started after the support layer is confirmed, but until now the confirmation of the support layer by measuring the accumulated current value from the beginning of excavation, injection of the curable material, and pile insertion No device has been developed that has a construction management function that correlates the data of each process up to.
[0011]
Furthermore, in addition to the drilling data based on the depth and the integrated current value, there has been no device for confirming the construction status by displaying construction management data such as the injection status of the curable material on the same screen.
[0012]
[Means for Solving the Problems]
However, according to the present invention, the cement milk to be injected is moved into the plurality of times while the injection means is moved up and down in accordance with the data (depth, soil quality) at the time of actual excavation of each pile hole and the discharge port is moved up and down at least twice. The problem was solved because it was divided and injected from the discharge port to form a solidified layer at the bottom of the pile hole.
[0013]
  That is, the present invention forms a rooting layer at the bottom of the pile hole.And, a pile circumference fixed liquid layer is formed in the pile hole shaft,In the method of constructing the foundation layer by injecting cement milk into the bottom of the pile hole when constructing a foundation pile that embeds the ready-made pile in the pile hole and fixes the lower end of the ready-made pile in the root consolidation layer,(1) After excavating the pile hole, the excavation head is held at the bottom of the pile hole, and the total amount of cement milk to be injected from the discharge port is 3 Discharging cement milk addressed to a minute,
(2) Next, while raising the excavating rod to the vicinity of the upper edge of the root consolidation layer to be formed, one third of the total amount of cement milk is discharged, and the strength in the root consolidation layer is not good. The object is pushed up above the rooting layer,
(3) Next, while raising and lowering the excavation rod a plurality of times between the bottoms of the pile holes, the remaining cement milk is discharged, and the excavation rod is pulled up to form a solidified layer.
This is a method for constructing a pile hole consolidation layer characterized by that.
[0016]
  In the above,"For root hardening liquid or pile circumference fixing liquid"Cement milk is injected while displaying the state of cement milk injection on the display unit installed in the construction operation room, construction machine, or construction control room in the construction area, and confirming the construction conditions in the surrounding ground and pile holes., The display on the display unit is the time from the start of construction on the horizontal axis, and the vertical axis indicates "flow rate per hour of the rooting liquid or pile circumference fixing liquid obtained from the flow meter", "discharged material obtained from the flow meter ”Total flow rate” and “the excavation head position obtained from the depth gauge” are graphed and displayed simultaneously.This is a method for constructing a pile hole consolidation layer characterized by that.
[0018]
  Further, the invention of the device includes a rotary drive device for mounting the excavation rod or the ready-made pile, an elevating means for raising and lowering the rotary drive device, and water or"For root hardening liquid or pile circumference fixing liquid"A pile driving machine provided with a liquid supply means for supplying cement milk, comprising various sensors, collectively processing information from the various sensors, displaying the information on the screen, and storing and recording the information In a pile driving device having means,
(1) The various sensors include a load ammeter that measures a load current of the rotary drive device, a depth meter that senses the amount of elevation of the rotary drive device and measures the depth position of the excavation rod or the ready-made pile from the ground, And a flow meter for measuring the amount of liquid supplied from the liquid supply means,
(2) The information processing means displays the data from the flow meter for each depth set from the data from the depth meter, and compares the prescribed flow rate for each preset depth with the actual flow rate. A function for displaying, a function for accumulating and displaying the data from the load ammeter for each predetermined depth, and displaying the corresponding N value data for each predetermined depth set in advance, It has a function that can read, display, store and accumulate information for each pile hole.
(3) The display of data by the information processing means, the horizontal axis is the time from the start of construction, and the vertical axis is "flow rate per hour of water, rooting liquid or pile circumference fixing liquid obtained from a flow meter", " The “total discharge flow rate obtained from the flow meter” and the “excavation head position obtained from the depth meter” are graphed and displayed simultaneously.
This is a construction management device for foundation piles.
[0019]
  Also,In the apparatus, a discharge port is formed at a lower end portion of a drilling rod having a drilling head,
When pouring cement milk into the pile hole root hardening layer,
(1) After excavating the pile hole, hold the excavation head at the bottom of the pile hole, and discharge the cement milk addressed to one third of the total amount of cement milk to be injected from the discharge port;
(2) Next, while raising the excavating rod to the vicinity of the upper edge of the root consolidation layer to be formed, one third of the total amount of cement milk is discharged, and the strength in the root consolidation layer is not good. The object is pushed up above the rooting layer,
(3) Next, while raising and lowering the excavation rod a plurality of times between the bottoms of the pile holes, the remaining cement milk is discharged, and the excavation rod is pulled up to form a solidified layer.
It is a construction management device for foundation piles.
[0020]
  Further, the invention of the management method includes a rotary drive device to which the excavation rod or the ready-made pile is attached, an elevating means for moving the rotary drive device up and down, and water or"For root hardening liquid or pile circumference fixing liquid"Excavation process for excavating a pile hole using a pile driving machine provided with a liquid supply means for supplying cement milk, an injection process for injecting cement milk into the pile hole, and a ready-made pile in the pile hole into which cement milk has been injected A method of managing a construction method comprising a pile insertion process of burying
Depth for measuring the depth position from the ground of the excavation rod tip or ready-made pile tip by sensing the data from the load ammeter that measures the load current of the rotary drive and the amount of lift of the rotary drive Data from the total,
Calculate and process data from a flow meter that measures the amount of liquid supplied from the liquid supply means, and store these data so that they can be read for each pile hole,
For each pile hole,
(1) In the excavation process, the data from the load ammeter is accumulated and displayed for each predetermined depth, and displayed in comparison with the corresponding N value data for each predetermined depth, Check the support layer.
(2) In the injection process, The horizontal axis is the time from the start of construction, and the vertical axis is "flow per hour of water, solidification liquid or pile circumference fixing liquid obtained from the flow meter", "total flow rate of discharge obtained from the flow meter" and While graphing the "position of the excavation head obtained from the depth gauge" simultaneously,
The prescribed flow rate at each depth set in advance and the actual flow rate are compared and displayed, and the amount of cement milk at each depth is managed.
(3) In the pile insertion process, the pile tip position is managed from the data from the depth gauge, and it is managed that the ready-made pile is fixed on the support layer.
A construction management method for foundation piles characterized by that.
[0021]
  In the above,Forming a discharge port at the lower end of a drilling rod having a drilling head;When injecting cement milk into the pile hole consolidation layer,
(1) After excavating the pile hole, hold the excavation head at the bottom of the pile hole, and discharge the cement milk addressed to one third of the total amount of cement milk to be injected from the discharge port;
(2) Next, while raising the excavating rod to the vicinity of the upper edge of the root consolidation layer to be formed, one third of the total amount of cement milk is discharged, and the strength in the root consolidation layer is not good. The object is pushed up above the rooting layer,
(3) Next, while raising and lowering the excavation rod a plurality of times between the bottoms of the pile holes, the remaining cement milk is discharged, and the excavation rod is pulled up to form a solidified layer.
Characterized claims5The construction management method of the foundation pile described.
[0022]
In the above, the injection means is a device capable of injecting cement milk, and generally uses a hollow excavation rod having an excavation head at the lower end, but after raising the excavation rod, such as an injection pipe provided with stirring means An injection means can be separately prepared and used.
[0023]
In addition, in the above, in addition to the case where the root consolidation layer has the same hole diameter as that of the shaft portion, and in the case of the expanded root consolidation layer that has been expanded and drilled, the root consolidation layer generally exhibits a high bearing capacity. Since a high quality of the layer is required, a more remarkable effect can be expected.
[0024]
In the above, the surrounding ground state is based on other pile hole data, standard penetration test data, test digging data, etc., and these or any one of them and the data of this pile hole are displayed on the display device. Therefore, highly accurate construction can be performed while confirming in comparison with the injection of cement milk.
[0025]
Moreover, the cement milk in the above is a general term for hydraulic materials, and any material can be used as long as it can form a solidified layer including various cements.
[0026]
The construction management means that the construction conditions / set values are compared with the actual data, and if there is a difference, adjustment is made to match the conditions / set values.
[0027]
DETAILED DESCRIPTION OF THE INVENTION
A drilling rod having a drilling head (with a drilling blade) at the lower end is formed in a hollow shape, constitutes cement milk injection means, and a discharge port is formed at the lower end. After excavation is completed, cement milk addressed to one third of the total amount of cement milk is discharged from the discharge port while stirring with the excavation head while holding the excavation head at the bottom of the pile hole. Subsequently, while agitating with the excavation head, one third of the total amount of cement milk is discharged while the excavation rod is raised to the vicinity of the upper edge of the pile hole root consolidation part. Next, while raising and lowering the excavation head several times within the rooting part (between the bottom of the pile hole and the upper edge of the rooting part), one third of the remaining cement milk is discharged, and stirring and mixing are performed. The drilling rod is pulled up to form a rooting layer.
[0028]
It is a structure which is formed in the lower end part of a ready-made pile and expresses high bearing power in the formed root hardening layer. For example, by fixing the protruding portion formed on the lower end portion of the ready-made pile, the cement milk and the ready-made pile are integrated after the cement milk is solidified, and a foundation pile that exhibits high supporting force can be constructed.
[0029]
Here, agitation refers to a step of rotating the excavation head, and mixing refers to a step of moving the excavation head up and down (or repeating rotation and elevation).
[0030]
In this case, in the construction of a high-quality root consolidation part that expresses a high bearing capacity, new construction different from conventional ones, including the quality of the injected cement milk, excavation of pile holes, embedding of foundation piles, etc., must be ensured. It is necessary to have a mechanism to ensure that the system is implemented.
[0031]
The new construction method including the present invention has a more precise construction procedure and method than the conventional construction method, and it is difficult to guarantee the quality with a mechanism that only records part of the data at the time of the conventional construction. Construction of the management system guarantees the construction content and quality of the high bearing capacity consolidation part.
[0032]
In addition, the conventional foundation pile construction method with a root consolidation part is relatively simple in both procedure and method, and displays and records the excavation load current of the excavator as a document to prove that the pile was buried in the supporting ground. It was only about. That is, no further maintenance / management system was required in terms of the required quality and reliability of foundation piles.
[0033]
The display shows the excavation current value along with the depth of the excavated stratum, and the excavation load current is the extent to which the difference from the pile burial depth assumed from the previous boring data was used as an indication. The actual values for each set condition other than those for each foundation pile are recorded and compared in real time, and the construction contents of the foundation pile are confirmed at the construction site, recorded and used for quality maintenance and management purposes. There was nothing, and at most, the recorded values were sorted and compared after construction. In actual construction, there was almost no constant feedback to the construction work while confirming and checking each pile foundation construction or each pile construction.
[0034]
[Test example]
A comparative experiment was carried out between the root hardening layer obtained by the method of the present invention and the root hardening layer obtained by the conventional method. It was confirmed that a solidified layer consisting of a homogeneous high-quality soil cement layer was obtained by improving the timing of cement milk injection and stirring and mixing.
[0035]
1. Test conditions and specifications
[0036]
(1) Pile hole, excavation method, etc.
Support layer geology: N value 30-35, sandy soil
Pile hole: Shaft diameter 800mm
Shaft length 950mm
Expanded root firming part diameter 1200mm
Expanded root hardening part length 2500mm
Outline of creation method: With a special excavation head with an injection port, water is poured into the pile hole shaft, and 9.5m is excavated from the ground. Excavate and stir well to form an enlarged root consolidation part (root consolidation layer to be constructed). Next, cement milk having the following specifications is injected and mixed with the excavated soil, and the solidified portion is used as a soil cement layer (FIG. 3).
[0037]
(2) Cement milk combination
Cement amount: 1090 kg
Water: 654 liters
Kneading amount: 1m3
[0038]
(3) Specification of cement milk agitation
As a specification for stirring and mixing cement milk and excavated soil, the excavating rod 1 with the excavating head 2 is used as it is as a stirring apparatus. That is, the excavation head 2 having a feature capable of finely crushing excavated soil is provided with excavating arms 6 and 6 that swing on both sides of the head body 6 a connected to the shaft portion of the excavating rod 1. The front end portion 57 of this is formed to open to the outside, and excavation blades 58 and 58 are attached (FIGS. 18A and 18B).
[0039]
Length D of swinging excavating arm 6 at an excavation diameter of 80 to 110 cm at the root of the pile hole0(= About 50 to 80 cm), the length of the tip 57 of the large area is L1As L1D0About 30-40% of the length. When the area outside the distal end portion 57 having a large area including the excavating blades 58, 58 is S (the net line portion in FIG. 18A),
S = “(L1)2About 70-80% "
As a result, good and homogeneous stirring and mixing can be obtained.
[0040]
Further, the agitating power for rotating the excavation rod 1 (excavation head 2) is also used as it is for the auger machine during excavation. Normally, during excavation, the auger machine power supply voltage is kept constant and the output is increased, and the excavation current is raised and lowered to control the rotational speed to be constant. In general, auger machines with different outputs are used depending on the geology and ground strength.
[0041]
And at the time of agitation, it is controlled so as to increase the number of revolutions to 1.5 to 2.0 times the average number of revolutions of the excavating rod 1 at the time of excavation, and a specification for stirring and mixing while injecting cement milk as will be described later. Adopted.
[0042]
(4) Specification of cement milk injection
After excavating the bottom of the pile hole to form a pile hole having a root shape with a predetermined shape, cement milk is injected into the root shape at a discharge rate of about 200 liters / minute. Comparison was made according to the following four specifications (FIGS. 3A to 3D).
[0043]
(a) Specification 1 (Case 1): Conventional example (Fig. 3 (a))
First, place the cement milk inlet at the center of the bottom of the root-clamping part. Forming a root hardening layer.
Total injection amount to root consolidation: 2.4m3
[0044]
(b) Specification 2 (Case 2): The present invention (FIG. 3 (b))
Dispense the total discharge amount in 1/3 of 3 times.
1st time: Dispense 1/3 amount with stirring at the bottom of the planned solidification layer.
2nd: Raise 1/3 volume and discharge while stirring.
Third time: Discharge is completed while reciprocating up and down two times in the rooting portion while stirring 1/3 amount.
[0045]
(c) Specification 3 (Case 3): the present invention (FIG. 3 (c))
First, the cement milk injection port is installed at substantially the center of the bottom of the root consolidation layer to be constructed, and the inside of the root consolidation is reciprocated up and down twice while stirring and discharging, and is completed at the top.
[0046]
(d) Specification 4 (Case 4): Conventional example (Fig. 3 (d))
First, the cement milk injection port is installed at the approximate center of the bottom of the rooting portion, and the entire amount of cement milk is discharged without moving the injection port to form a soil cement layer. This method is mainly used when silt or the like is mixed and the formation is not good.
[0047]
(5) Test evaluation method
(a) Electrical resistivity measurement test
Immediately after completion of the cement milk discharge and formation of the rooting layer, a specific resistance rod was inserted into the rooting layer, and the electrical resistivity was measured from the upper layer to the lower layer of the rooting layer.
(b) Uniaxial compressive strength test of sampled core
After the cement milk of the expanded root-solidified layer was solidified, core-boring of the expanded root-hardened layer was performed and divided into approximately 4 equal parts in the vertical direction, and each uniaxial compressive strength test was performed.
[0048]
2. Test results
The summary of the test results is shown in Table 1 below.
[0049]
[Table 1]
Figure 0004958028
[0050]
In addition, since the absolute value of each measured value of the test is essentially different depending on the measurement timing, the geological strength at each measurement point, etc., it is appropriate to compare the construction methods with variations in measured values. The measured value of uniaxial compressive strength is 22 N / mm2Before and after, the measured value of electrical resistivity was around 5 Ωm.
[0051]
3. Summary of test results
(a) The compressive strength variation of the new specifications (Case 2 and Case 3) is stable at 10% or less, which is improved to 1/2 or less compared to the conventional specifications (Case 1 and Case 4). Furthermore, a micro comparison of the electrical specifications between the new specifications shows that the specifications 2 are more homogeneous.
Therefore, it can be seen that the method of discharging cement milk while stirring and raising and lowering it at least twice is effective.
(b) If the excavated soil contains silt or the like that is not good in strength, it is desirable to discharge cement milk at the bottom (without stirring) and push it upward (shaft) above the expanded root-solidified layer. Therefore, it can be said that the specification 2 is desirable also from this viewpoint.
(c) Although not compared this time, the results of this test show that the construction method in which excavation of the solidified layer and injection of cement milk cannot be performed at the bottom makes it impossible to discharge cement milk. It is judged that the cement milk in the layer varies and the performance of the root hardening layer is inferior.
[0052]
(d) As a stirring method, when mixing with the above specifications, the drilling head 2 is used as it is as a stirring device, so there is no time loss due to exchanging the drilling rod 1, and it is simple and easy to mix. Since the tip 57 of the excavating arm 6 that contributes most (located on the outer peripheral side during agitation) is formed with a large area, the agitation efficiency at the periphery of the pile hole is good, and there is further excavated soil that is not sufficiently crushed However, since it can be further finely pulverized, uniform mixing is possible. Moreover, since it rotates at a high speed 1.5 to 2.0 times during excavation, the stirring efficiency is further improved.
[0053]
In addition, since the auger machine used at the time of excavation was used as the agitation power source, it functions as an agitation power source suitable for the soil quality and is reliable and stable even when rotating up to twice the number of revolutions at the time of excavation. Stirring and mixing became possible.
[0054]
Therefore, it was possible to establish an economically excellent construction method capable of carrying out homogeneous stirring and mixing by using the excavating apparatus such as the excavating head 2, the excavating rod 1 and the auger machine when excavating the pile hole.
[0055]
[Example 1]
An embodiment of the present invention will be described with reference to FIGS.
[0056]
(1) Excavation of pile hole shaft 8
[0057]
At the construction site, the excavator is installed, and the pile hole 7 is excavated with the excavation rod 1 having the excavation head 2 at the tip at a predetermined pile embedding position (FIGS. 1A and 1B). The excavation rod 1 is provided with kneading drums 4 and 4 for leveling the stirring bars 3 and 3 and the inner walls of the pile holes in the middle part. Further, when excavating the pile hole 7, the excavation status (various information) is displayed on the display device (various display devices) in the operator room of the excavator (FIG. 4).
[0058]
The excavation diameter of the pile hole 7 is the pile hole shaft portion 8 in which the diameter (750φ) +30 mm of the ready-made pile to be buried is secured. In the middle of the excavation, an appropriate amount of water is poured from the discharge port 5 provided in the excavation head 2, and the excavated soil is sufficiently agitated by the agitation bars 3 and 3 to be mud, and the kneading drums 4 and 4 are applied to the inner wall 7 a. Kneading and excavating to a depth of 46.5m.
[0059]
The measurement result of the standard penetration test obtained on the construction ground is displayed in the “N value display column 27” in advance (FIG. 5), and based on this measurement result, the excavation depth and the N value at that depth are displayed. On the other hand, the accumulated value (recorded value) of the excavation load current is displayed in parallel in the “integrated current value display field 30” (FIG. 8), and excavation is performed while comparing and confirming both. If the recorded value in the support ground at the planned depth does not match, the excavation depth is adjusted. At the same time, the depth at that time and the amount of water injected during excavation (A1) are also displayed and recorded together in the “flow rate / head position display column 28” (FIG. 6), so confirmation and adjustment are performed.
[0060]
The recorded value as the accumulated value of the digging load current in the “accumulated current value display field 30” in the display device is the accumulated value of the digging load current as the recorded value in order to match the N value (indentation size 30 cm) of the penetration test. The excavation size is appropriately variably set within a range of 30 to 50 cm for each predetermined depth. Here, as a result of accumulating and displaying a load current having a width of 50 cm at every depth of 50 cm, it was confirmed that a value of a tendency that substantially matched the change in the N value of the penetration test was obtained (FIG. 8). Therefore, the recorded value is a load current accumulation value with a width of 50 cm and is displayed in A · sec (ampere · second).
[0061]
In addition, by displaying the load current value every 50 cm, the accuracy can be improved by a factor of about 2 times compared to the measurement at a 1 m interval in the normal standard penetration test.
[0062]
That is, the measurement of the N value in the standard penetration test indicates the number of hits in which the sampler having a weight of 63.5 kg is driven in the depth direction by 30 cm in the soil layer range, and this method is used for every 50 cm soil layer range used before and after the hitting. In addition, the strength of the ground can be displayed as a numerical value proportional to the amount of work.
[0063]
Therefore, using the fact that the power supply of a normal excavator is controlled at a constant voltage, and further assuming that the load current during excavation of this excavator is proportional to the ground strength, the soil used in the standard penetration test is used. By accumulating this load current in the same range (30-50cm) as the layer width and displaying it simply in units of work proportional to the time product (ampere-second) of the load current, that is, the ground strength, By comparing the ground strength at the excavation point and the N value for each excavation hole, it is possible to perform construction with a reliable construction position of the foundation layer. Here, the accumulated soil layer width is close to the measured soil layer width dimension in the standard penetration test, if there is much variation in soil quality, or adjusting the range of the soil layer width in the range of 30-50cm if necessary. Good consistency.
[0064]
That is, since the time product of the load current of the excavator is displayed in this way, the excavation current at the time of excavating the pile hole is almost the same range as the soil layer width used in the N value measurement of the standard penetration test ( 30 to 50 cm), and when the accumulation is completed, it is recorded and displayed at each depth. Therefore, in the case of the standard penetration test, the “number of depths (every 50 cm)” indication of the number of hits is displayed. It can be adapted to “every depth”.
[0065]
Therefore, with respect to the ground strength at the construction site, it is possible to supplement the few standard penetration test data and grasp the high-precision ground condition of the entire construction site, and to set an appropriate support layer for each pile foundation, making it a safer and more reliable foundation. Can be provided easily.
[0066]
Thereafter, the excavation head 2 is repeatedly moved up and down while stirring the excavated soil, and the pile hole shaft portion 8 is constructed (FIG. 1B). The supporting ground was sandy soil, and the N value was 30 or more. Based on this excavation result (excavation depth, etc.), it is also possible to change the set value of the “basic data display column 26” for each pile hole.
[0067]
(2) Excavation of the enlarged solidified portion 9 of the pile hole 7
[0068]
Next, the excavation diameter is expanded, and water is poured from the discharge port 5 to construct an enlarged root consolidation portion 9 having an enlargement diameter of 1100 mm and a depth of 2.5 m, and the excavated soil is stirred up and down twice (see FIG. 1 (c)).
[0069]
In the "flow rate / head position display field 28" in the display device, the display record is to confirm and adjust the excavation depth and the water injection amount (FIG. 6).
[0070]
(3) Cement milk injection at the enlarged root consolidation part 9 (formation of root consolidation layer)
[0071]
Using the method of the present invention, cement milk is injected to form a homogeneous root hardening layer (soil cement layer) 13.
[0072]
Cement milk for root consolidation is 2590 kg of cement (according to JASS4 Section 2.2.1), 1554 kg of water, and kneaded to 2.38 m.3And
[0073]
First, the discharge port 5 of the excavation head 2 is held in the vicinity of the bottom 10 at the center of the enlarged root consolidation portion 9, and the total amount of root consolidation liquid (cement milk of the above-mentioned mixing ratio) (2.38 m) is used.31/3 is discharged at about 200 liters per minute while being agitated by the excavation head 2 (first discharge, FIG. 1 (c), FIG. 3 (b)).
[0074]
Next, the excavating head 2 is pulled up to the top while stirring the root-setting liquid in the same manner (FIG. 1 (d)). In the meantime, 1/3 of the total use amount of the root hardening liquid is discharged (second discharge, FIG. 3 (b)).
[0075]
Next, while discharging the root-setting liquid in the same manner, the excavation head 2 is reciprocated twice up and down to reach the bottom 10 and to 1/3 of the remaining amount of the root-setting liquid until the end, that is, above the standard While injecting the cement milk, the soil is stirred and mixed with the excavated soil to form a soil cement layer (the third discharge, FIG. 3B).
[0076]
In the “flow rate / head position display field 28” of the display device, the position (depth m) of the excavation head 2 at that time, the cement milk flow rate (m3/ h) is displayed and recorded (Fig. 6), and the position of the excavation head 2 and the amount of solidification liquid injection (m3) Only enlarged display can be easily compared and adjusted for the amount of root hardening liquid injection, and the management accuracy can be improved. The liquid injection amount can be confirmed (FIG. 9). For example, when the injection amount is insufficient, correction is performed by reinjection. In addition, each construction condition and actual record value are recorded by comparison, and can be used as construction proof material even after construction.
[0077]
(4) Cement milk injection at pile hole shaft 8 (formation of soil cement layer)
[0078]
Cement milk for pile hole shafts has the same mixing ratio as the root hardening liquid, but is also called a pile circumference fixing liquid (peripheral fixing liquid). Cement milk is discharged at a rate of 100 liters per minute. The total injection volume is 2.22m.3This is the above ("basic data display field 26" in FIG. 4).
[0079]
First, discharge starts from the upper end 15 of the enlarged root-setting part 9, and the excavation head (injection port) moves up and down once to a depth of 30 m while stirring, and then excavates while discharging and stirring in the same manner up to a depth of 12 m. The head 2 is reciprocated up and down once, then the excavation head 2 is reciprocated up and down one time while discharging and stirring in the same manner up to a depth of 2 m, and finally the excavation head 2 is reciprocated up and down while discharging and stirring similarly to the pile hole 12. The injection is completed (FIGS. 2A and 2B). In this way, a pile periphery fixing liquid layer (soil cement layer) 16 is formed in the pile hole shaft portion 8.
[0080]
In the “pile circumference fixed liquid injection amount display field 32” of the display device, the position (depth m) of the excavation head 2 and the cement milk flow rate (m3/ H) is displayed and recorded, and the position of the excavation head 2 and the injection amount (m3If the enlarged display of only / h) is selected, it can be easily confirmed whether cement milk has been injected according to the procedure (FIGS. 6 and 10).
[0081]
Therefore, correction such as replenishment of cement milk injection can be performed during the construction of each foundation pile, and it can be proved that the construction has been performed according to a predetermined procedure.
[0082]
In the “flow rate / head position display column” (FIG. 6), the graph A shows the discharge amount per unit (unit m).3/ H) is displayed with the vertical axis as the required time for construction, the water is discharged from the discharge port 5 from 0 to 37 minutes (A1), and the rooting liquid is discharged from 37 to 46 minutes ( A2) After 46 minutes, the peripheral fixative is being discharged (A3). Further, in graph B, the total flow rate of water, root hardening liquid, and peripheral fixing liquid discharged from the discharge port 5 is sequentially displayed. In the graph C, the vertical axis is set to the depth (m) from the ground, the horizontal axis is the time required for construction, and the position of the excavation head 2 is displayed.
[0083]
(5) Burial of ready-made piles 20 and 22
[0084]
The excavation head 2 is removed from the excavation rod 1 and, first, “BF6075-5m” ready-made pile 20 (shaft diameter: φ600, nodal diameter: φ750, nodal pile) (“BF” is a trademark of the nodal pile of Mitani Sexan Corporation. The same applies hereinafter) to the rod 1 and is placed in a pile hole 7 filled with soil cement while rotating. Next, the “SCφ600-14m” ready-made pile 22 is connected and laid, and thereafter, the “SCφ600-15m” ready-made pile 22 and the “SCφ600-15m” ready-made pile 22 are sequentially connected in the same manner, and the “BF6075” at the tip of the connected pile is connected. “-5 m” The tip 21 of the ready-made pile 20 is pushed and embedded at a position of about 50 cm from the bottom 14 of the expanded root-sealing layer 13 to complete the embedding of the ready-made piles 20 and 22 (FIGS. 2C and 2D). After the soil cement is solidified, a foundation pile 24 in which the ready-made piles 20 and 22, the root hardening layer 13, and the pile circumferential fixed liquid layer 16 (soil cement) are integrated in the pile hole 7 is constructed.
[0085]
Further, in the “pile tip position display field 29” of the display device, the burying time of the ready-made piles 20 and 22 is recorded, and the position of the tip 21 of the ready-made pile 20 is recorded. While being buried, it can be confirmed for each foundation pile 24 construction, and can also be used as guarantee data for construction contents (FIGS. 4 and 7).
[0086]
(6) Evaluation of completed foundation pile 24
[0087]
(a) Maximum load
The load at the time of subsidence of 0.1D (D is the diameter of the nose pile shaft) in the loading test of the upper part of the root consolidation part (the ready-made pile 20 and the root consolidation layer 13) is 7000 kN or more, and has a high bearing capacity. It was confirmed that the quality was established. That is, more than twice the normal foundation pile was obtained.
[0088]
(b) Soundness of root consolidation
As a result of digging up the root consolidation part (the ready-made pile 20 and the root consolidation layer 13) and investigating its external appearance and shape dimensions, it was confirmed that there was no crack or large defect and that a root consolidation part with a diameter larger than a predetermined excavation diameter was created. It was done.
[0089]
(7) Effect of display recording
[0090]
Various data can be displayed and output on the display device in the format of FIG. 4 (FIGS. 5 to 10). In the “basic data display field 26” at the upper end of the display field of the display device, the “specification of ready-made piles to be used”, “excavation length”, “pile top position”, “combination of cement milk”, “amount of rooting liquid injection” And “pile circumference fixed liquid injection amount” are displayed (FIG. 4). As for the “solidification liquid injection amount and pile circumference fixing liquid injection amount”, the standard amount (design value) is displayed before construction, and the actual usage amount is sequentially displayed during construction.
[0091]
(a) Since the depth of the drilling hole, the accumulated value of the drilling load current (recorded value of N value substitute characteristics), and the actual measurement value of the flow meter are displayed in comparison, the construction status of the rooting part etc. can be confirmed and managed in real time ( FIG.5, FIG.6, FIG.8-10.
(b) Since the ground strength can be confirmed by the approximate substitution characteristic (load current accumulation value) of N value, an appropriate support layer can be set (FIGS. 5 and 8).
(c) Cement milk injection and agitation can be confirmed and managed in parallel by elapsed time and depth. Moreover, based on the actual excavation data (support layer position, etc.) of the pile hole, the setting conditions such as the injection position and amount of cement milk can be corrected.
(d) Comprehensive quality certification material that confirms whether or not construction has been carried out, and can be used as an actual record of a more detailed construction report than before (Figure 4).
[0092]
[Example 2]
Next, another embodiment of the present invention will be described.
[0093]
(1) Basic configuration of the pile driver 42
[0094]
In the pile driving machine 42 used for carrying out the present invention, a leader 35 is erected on one side of a base 34 that can be self-propelled, and a wire 37 is moved up and down via a top sheave 36 provided at the upper end of the leader 35. The auger machine 38 is connected to the tip of the wire 37. The base end of the wire 37 is attached to the shaft of an unwinding motor (not shown) via an unwinding device 41 attached on the base 34.
[0095]
A box 39 containing a drive motor 40 is attached to the base end of the auger machine 38, and a drilling rod 1 that is rotationally driven by the drive motor 40 is suspended below the box 39. The excavation rod 1 is the same as in the first embodiment, and the excavation head 2 is attached to the lower end, and the excavation rod 1 is kneaded with a plurality of stirring rods 3 and 3 along the axial direction at a predetermined interval. Drums 4 and 4 are disposed.
[0096]
Reference numeral 43 in the figure denotes a generator for supplying electricity to the drive motor 40 of the auger machine 38, the wire unwinding motor, and the like (FIG. 11). The electricity supplied from the generator 43 is sent to the switchboard 43a provided in the pile driver 42, and is then distributed to the auger machine 38 and the like.
[0097]
(2) Configuration of construction management device
[0098]
Next, the control system of this apparatus will be described.
[0099]
(a) Sensors
A load ammeter 44 for measuring the load current of the drive motor 40 of the auger machine 38 is connected to the switchboard 43 a or the generator 43 provided in the pile driving machine 42. Data from the load ammeter 44 is input to the amplifier box 50 in the operator room (FIG. 12).
[0100]
Further, a depth meter 45 comprising a rotary encoder is installed at the lower end of the leader 35 of the pile driver 42 (FIG. 11), and a depth measuring wire 37a is attached to the auger machine 38 along the leader 35 via the depth meter 45. It has been. Thereby, the amount of descent of the auger machine 38, that is, the excavation depth is detected. Data from the depth meter 45 is input to the amplifier box 50 in the operator room (FIG. 12). The depth meter 45 is not limited to the rotary encoder, and may be another measuring tool. The depth meter 45 may measure the depth from the amount of the wire 37 attached to the auger machine 38.
[0101]
Here, the depth meter 45 is the lower end portion of the leader 35, but it may be provided at any position of the leader 35 or in the auger machine 38.
[0102]
In addition, a plant 46 for generating and sending curable materials such as water and cement milk is installed in the construction site (or close to the construction site), and the plant 46 and the pile driving machine 42 are connected by a pressure hose 47. ing. The pressure hose 47 is connected to the auger machine 38 so as to be discharged from the discharge port 5 of the excavation head 2 through the excavation rod 1. A flow meter 48 for detecting the discharge amount is installed at an intermediate portion of the pressure-resistant hose 47, for example, on the pile driving machine 42 side of the base 34 (FIG. 11). The data of the flow meter 48 is input to the amplifier box 50 in the operator room (FIG. 12).
[0103]
Corresponding to the start of lowering of the auger machine 38 (operation of the depth gauge 45), the required construction time (min.) From the start of excavation is measured.
[0104]
(b) Management device
Data collected from the sensors 44, 45, and 48 in the amplifier box 50 are controlled, calculated, and processed by a personal computer (hereinafter, PC) 51 and displayed on a screen (data display device) 52. The paper output to the printing machine 53 is also possible by the operation from. Since the data obtained from the load ammeter 44, the depth meter 45, and the flow meter 48 are generally analog signals, they are converted into digital signals by the A / D converter in the amplifier box 50 and sent to the PC 51.
[0105]
Here, the operator room 55 is arranged in a plant, a facility in a site site such as a resident office of a site construction manager or the like, a control room of a pile driving machine, or an independent facility outside the site. The The operator's room is preferably a facility with a roof (for example, a temporary building, a temporary tent, etc.) in consideration of rainy weather or the like.
[0106]
Further, the data collected by the amplifier box 50 and processed by the PC 51 is displayed on the screen 52 as shown below, divided into display columns 27 to 32 (FIG. 4). Moreover, each display column 27-32 can be switched independently, and can be expanded and displayed (FIGS. 5-10). Also, a plurality of columns can be combined and displayed (not shown).
[0107]
That is, the data from the depth meter 45 is processed, and a graph corresponding to the pile tip position (m) from the ground 18 on the vertical axis and the pile insertion time (min.) On the horizontal axis is displayed on the screen 52. It is displayed in the “pile tip position display field 29” (FIGS. 7 and 4).
[0108]
Further, the data from the depth meter 45 and the load ammeter 44 are accumulated by accumulating the load current of the drive motor 40 required for a certain excavation range (for example, every depth of 30 cm) in the time required for the excavation range. It is processed as an integrated current recording value (Amp × sec). The data from the depth meter 45 is separately processed and graphed correspondingly with the depth (m) from the ground 18 as the vertical axis and the accumulated current recorded value as the horizontal axis. Column 30 "(FIGS. 8 and 4).
[0109]
Further, based on actual excavation data (support layer position, etc.) of the pile holes, the set value of the “basic data display field 26” is corrected and displayed for each pile hole as necessary.
[0110]
Also, the amount of root hardening liquid injected from the flow meter 48 (m3) On the horizontal axis, and the data from the depth meter 45 is set on the vertical axis as the depth (m) from the ground 18, and is graphed correspondingly. Is displayed. At this time, the “specified amount of the root hardening liquid at the time of design” for each depth is displayed at the same time, and the design amount reviewed by the excavation data can be compared with the actual injection amount (FIGS. 9 and 4). In this case, when the actual injection amount reaches the design amount for each depth, the guidance display can be blinked on the screen 52 or a warning sound can be generated.
[0111]
Similarly, the amount of pile circumference fixing liquid injected from the flow meter 48 (m3) On the horizontal axis, the data from the depth meter 45 is set on the vertical axis as the depth (m) from the ground 18, and is graphed correspondingly. 32 ”. At this time, the “specified amount of pile periphery fixing liquid at the time of design” for each depth is displayed at the same time, and the design amount and the actual injection amount can be compared (FIGS. 10 and 4). In this case, when the actual injection amount reaches the design amount for each depth, the guidance display can be blinked on the screen 52 or an audible sound can be emitted.
[0112]
In addition, boring data (N value, soil name, etc.) at the time of the standard penetration test is input to the PC 51 in advance. The data of the depth (m) received from the depth meter 45 from the depth meter 45 is plotted on the vertical axis, and the “N value” for each depth (m) is plotted on the horizontal axis. Is displayed in the value display field 27 "(FIGS. 5 and 4). In this case, other boring data (soil name, etc.) other than the N value can be simultaneously displayed for each depth (m) corresponding to the N value (not shown).
[0113]
Further, the flow rate per hour (m for excavation water, root hardening liquid or pile circumference fixing liquid) from the flowmeter 48 on the vertical axis and on the vertical axis on the required time (min.) From the start of construction (m.)3/ H) is displayed. Similarly, on the vertical axis, the total flow rate of the discharged material (cumulative flow rate. M3) Are displayed at the same time. Similarly, on the vertical axis, “head position (m)” from the ground 18 obtained from the depth meter 45 is simultaneously displayed. Three graphs having the required time (min.) As a common horizontal axis are simultaneously displayed in the “flow rate / head position display column 28” of the screen 52 (FIGS. 6 and 4).
[0114]
Information processing function (calculation, control) as described above, screen 52, “PC 51” and “printer 53” with built-in or external storage means, depth meter 45, flow meter 48, and load ammeter 44 The “amp box 50” to which the sensors are connected and the “power supply device (for example, generator 54, capacitor etc.)” that supplies the rated power to the PC 51, the amplifier box 50, and the printing press 53 provide the construction management device of the present invention. Constitute.
[0115]
In addition, a wireless transmission antenna is attached to an “amplifier box 50” to which sensors including a depth meter 45, a flow meter 48, and a current detector 44 are connected, and wireless reception is performed by a PC 51 installed in a remote place (for example, in the office of a construction site). It is also possible to wirelessly transmit and receive various data collected in the amplifier box 50 by attaching an antenna (not shown). In this way, storage of construction management data and installation of control devices outside the construction site isolates the construction site from dust, mud scattering, rain, etc., and damage caused by construction machine vibrations. Information can be used stably.
[0116]
In addition, by using the Internet or the like, it is possible to obtain construction information from outside the construction site at any time and use it for construction progress management and the like.
[0117]
[Example 3]
Next, a construction management method using this construction management apparatus will be described (FIG. 13).
[0118]
(1) “Pile used (here, upper pile, middle pile, lower pile, type outer diameter, length, etc.)” and “depth of drilling hole (GL (ground 18 ) Depth from ”“ Pile crest (position from GL (ground 18)) ”“ Contained cement milk (per batch) 750 kg of cement, 450 kg of water, scoured 0.69 m3) "" Standard value of the root hardening liquid injection amount (here 2.38 m3) "" Standard value of the amount of fixed fluid injected around the pile (here 2.22m)3) ". These data are displayed in the “basic data display field 26” at the top of the screen 52 (FIG. 4). Note that the “injection amount of root hardening liquid” and “injection amount of fixed fluid around the pile” are sequentially displayed in parallel with the standard values reviewed by the excavation data.
[0119]
The standard value is, for example,
Pile shaft diameter 600mm
Protrusion diameter 750mm
Pile hole shaft diameter 780mm
Pile hole widening part diameter 1100mm
In the case of
The filling amount of root hardening liquid is 0.061m every 10cm.3,
Filling amount of pile fixing liquid is 0.0478m per 1m3,
It will be about.
[0120]
(2) Also, previously obtained boring data (N value, soil name, etc.) is input to the PC 51, the boring data depth is associated with the excavation depth, and the accumulated current value based on the depth is “integrated current value” Is displayed in the display column 30 "(FIGS. 8 and 4).
[0121]
At this time, construction information (for example, construction method, excavation depth, excavation diameter, injection amount of curable material, etc.), construction machine information (for example, low speed base current value (Amp), low speed rotation speed (times / minute), high speed) Base current value (Amp), high-speed rotation speed (times / minute), etc.) are input. These data can also be switched and displayed on the screen 52 (not shown).
[0122]
(3) The pile driving machine 42 on which the excavation rod 1 is mounted is moved to a desired pile driving position (FIG. 11), and the excavation rod 1 is rotated forward (for example, clockwise) by the drive motor 40 via the wire 37. The auger machine 38 is gradually lowered along the leader 35. An excavation head 2 comprising a main body 6a and two excavation arms 6 and 6 is attached to the tip of the excavation rod 1, and when the excavation rod 1 rotates, the two excavation arms 6 and 6 open, The pile hole shaft is excavated by the excavating blades at the tips of 6 and 6 and the excavating blade at the lower end of the main body 6a (FIGS. 11 and 15B).
[0123]
At this time, the descending amount of the auger machine 38 is detected by the depth meter 45 as the excavation depth, and is initially set so that the depth is set to “0 (zero)” while the excavation blade of the excavation head 1 is in contact with the ground. Setting is performed (FIG. 15A). Further, the load current of the drive motor 40 is continuously detected by the load ammeter 44, and the measurement current at no load is set as the initial current.
[0124]
(4) By continuously lowering the auger machine 38, the ground is excavated while discharging water or the like from the tip of the excavating head 1, and the agitating drums 4 and 4 Kneaded to the inner wall 7a of the pile hole 7. At this time, the amount of water to be discharged is displayed on the screen 52 of the PC 51 by the flow meter 48 graphing the discharge amount for each depth.
[0125]
During excavation, the load on the drive motor 40 changes depending on the hardness of the ground, and the load current changes accordingly. Thereby, the load current value is accumulated at every predetermined excavation interval (for example, every 50 cm), the excavation time required for the excavation interval is calculated, and the N value of the boring data input in advance as an integrated current value, It is displayed together with the soil name at the same time as excavation with reference to the depth (FIGS. 5, 8, and 4). Since the accumulated current value draws an approximate curve with the N value, if the accumulated current value is different from the N value during excavation, it can be confirmed that there is a ground different from the boring and is appropriate during construction. Can take a good response.
[0126]
(5) The excavation is continued, and it is confirmed from the N value and the integrated current value displayed on the screen 52 of the PC that the support layer having the predetermined strength has been reached (FIGS. 5 and 8). After deep excavation, the excavation rod 1 is rotated in the reverse direction, and the excavation of the pile hole expansion root consolidation portion 9 is performed while the excavation rod 1 is pulled up. At the time of excavation of the enlarged solidification portion 9, the excavation rod 1 is rotated in the reverse direction, and the excavation arms 6 and 6 of the excavation head 2 are swung and expanded in the opposite direction to those at the time of normal excavation, so that an expanded excavation state is obtained. The enlarged solidified portion of the pile hole needs to be provided at a predetermined height (for example, 250 cm), but the position of the excavation head 2 is displayed on the screen 52 of the PC by the depth gauge 45 (FIGS. 6 and 4). Excavation of the enlarged root consolidation portion 9 having a predetermined height can be performed.
[0127]
(6) After forming the enlarged rooted portion 9 of the pile hole 7 having a predetermined size, the valve (not shown) is switched to switch the discharged material from water to cement milk. Cement milk is supplied into the pile hole from the discharge port 5 of the excavation head 2 through the pressure hose 47 from the plant 46.
[0128]
(7) In the “basic data display field 26”, “root hardening liquid injection amount display field 31” and “pile circumference fixed liquid injection amount display field 32” on the screen 52 of the PC 51, the root solid liquid and the pile circumference fixed previously input are displayed. The standard value of the liquid is displayed. In addition, the filling amount for each predetermined depth interval is graphed, and “flow rate / head position display column 28”, “integrated current value display column 30”, “rooting fluid injection amount display column 31”, “pile circumference fixing fluid” on the screen 52 are displayed. It is displayed in the “injection amount display column 32” (FIGS. 6, 9, 10, and 4), and the construction is performed while visually confirming whether cement milk of a standard value or more has been injected. At the same time, the actual usage amount of the root hardening liquid and the pile circumference fixing liquid is displayed together with the standard value in the “basic data display field 26” (FIG. 4).
[0129]
(8) First, cement milk as a solid solution (solidification strength 20 N / mm) in the enlarged root consolidation part 9 of the pile hole 7.2). While confirming the filling amount for each predetermined depth interval on the screen 52, the digging rod 1 (digging head 2) is rotated up and down repeatedly in the enlarged root consolidation portion 9, and stirred and mixed with the excavated soil. Solidified layer 13 (soil cement layer. Solidification strength 20 N / mm2Above).
[0130]
At this time, if the amount of cement milk does not exceed the standard value, the cement milk is reinjected at the relevant depth.
[0131]
(9) Construction of the root consolidation layer 13 in the above, that is, injection of cement milk in the enlarged root consolidation portion 9 of the pile hole 7 is performed in order to reduce variation in the quality of the soil cement in the root consolidation layer 13. It is desirable to perform the same as in the first embodiment.
[0132]
That is, after the excavation of the pile hole 7 is completed, the total amount of cement milk as root solid liquid is obtained from the discharge port 5 at the lower end of the excavation head 2 while stirring the excavation head 2 while the excavation head 2 is held at the pile hole bottom 10. Discharge cement milk addressed to one third. Subsequently, while agitating with the excavation head 2, the excavation rod 1 is raised to the vicinity of the upper end portion 15 of the enlarged rooting portion 9 of the pile hole 7, and one third of the total amount of cement milk is discharged. Next, the excavation head 2 is moved up and down a plurality of times in the enlarged rooting part 9 (between the bottom 14 of the pile hole 7 and the upper end part 15 of the enlarged rooting part 9), while remaining 3 minutes of the remaining cement milk. 1 is discharged, stirring and mixing are performed, and the excavation rod 1 is pulled up to form a root hardening layer 13 made of a soil cement layer in the enlarged root hardening portion 9 (FIG. 3 (b), Case 2).
[0133]
Even in such a complicated construction, the positions of the rooting liquid (cement milk) and the excavation head 2 can be determined by the “flow rate / head position display field 28”, “rooting liquid injection amount display field 31”, etc. on the screen 52. It can be performed while visually confirming, and fine construction management can be performed very easily and reliably.
[0134]
(10) Further, another desirable method for injecting cement milk is to place the discharge port 5 of the excavation head 2 at substantially the center of the bottom of the enlarged rooting portion 9 of the pile hole 7 (the bottom portion of the rooting layer to be constructed). Install and reciprocate up and down two times in the enlarged root-setting part 9 while stirring and discharging to complete the injection at the upper end part 15 (FIG. 3 (c), Case 3).
[0135]
Further, the entire amount of cement milk is injected from the discharge port 5 of the excavation head 2 at the bottom 10 of the enlarged root consolidation part 9 to push up the excavation mud in the enlarged root consolidation part 9 and replace the excavation mud with cement milk. It is also possible to form an expanded root hardening layer 13 composed of a cement milk layer (FIG. 3 (d), Case 4).
[0136]
(11) Next, cement milk is poured into the enlarged root consolidation portion 9 and after the construction of the root consolidation layer 13 is completed, the excavation rod 1 is returned to the normal rotation, the excavation head 2 is brought into a normal excavation state, and Pile circumference fixing liquid (solidification strength 20 N / mm) in the shaft portion 8 of the pile hole 72) Start infusion. Regarding the pile circumference fixing liquid, similarly to the injection of the root solid liquid, the filling amount for each predetermined depth interval is set as the standard quantity, “flow rate / head position display field 28” on the screen 52 of the PC 51, “pile circumference fixed liquid injection amount display” While comparing and confirming in "Column 32", the pile periphery fixed liquid layer 16 (solidification strength 2N / mm) which consists of a soil cement layer in the axial part 8 of the pile hole 7 is confirmed.2Above). At this time, if the standard filling amount is not satisfied, re-injection is performed at the corresponding depth in the same manner as the root solid liquid.
[0137]
(12) The cement milk injection method in the shaft portion 8 of the pile hole 7 described above, that is, the formation of the pile circumference fixing liquid layer (soil cement layer) 16 is also higher than the position of the upper end portion 15 of the root hardening layer 13. Then, according to the excavation length, one or a plurality of predetermined depths are determined, and cement milk injection is started from the upper end portion 15 of the root-solidifying layer 13, and the reciprocation is repeated between the predetermined depths. The pile circumference fixed layer 16 is formed while mixing.
[0138]
Regarding the management of the filling amount of the pile circumference fixing liquid (cement milk), the average value of the amount of cement milk injected at every predetermined depth interval is calculated in a certain range (for example, every 1 m) of the shaft portion 8 of the pile hole 7. If the average value exceeds the standard filling amount, the construction can be appropriate.
[0139]
(13) Subsequently, after the cement milk is filled more than the reference filling amount, a ready-made pile composed of an upper pile, a middle pile and a lower pile is inserted and the foundation pile 24 is constructed as in the first embodiment.
[0140]
The excavation head 2 is removed from the excavation rod 1 and a rotation cap is attached. First, “BF6075-5m” ready-made pile (lower pile) 20 (shaft diameter: φ600, nodal diameter: φ750, nodal pile) (“BF” is Mitani A trademark of SEXAN CO., LTD. (Hereinafter the same) is attached to a rotating cap, and is placed in a pile hole 7 filled with soil cement while rotating. Next, “SCφ600-14m” ready-made pile (middle pile) 22 is connected and set, and thereafter “SCφ600-15m” ready-made pile 22 and “SCφ600-15m” ready-made pile (upper pile) 22 are connected in the same manner. The tip 21 of the “BF6075-5m” ready-made pile 20 at the tip of the connecting pile is pushed and embedded at a position of about 50 cm from the bottom 14 of the enlarged root-sealed layer 13 to complete the embedding of the ready-made piles 20, 22, 22 ( FIG. 2 (c) (d)). After the soil cement is solidified, a foundation pile 24 in which the ready-made piles 20, 22, 22, the root hardening layer 13, and the pile circumference fixing liquid layer 16 (soil cement) are integrated in the pile hole 7 is constructed.
[0141]
Further, in the “pile tip position display field 29” of the screen 52 of the PC 51, the burying time of the ready-made piles 20 and 22 is recorded, and the position of the tip 21 of the ready-made pile 20 is recorded. , 22 can be confirmed for each construction of each foundation pile 24, and can also be used as guarantee data for construction contents (FIGS. 4 and 7).
[0142]
[Example 4]
Next, construction when the pile length is long (for example, about 50 m) will be described with reference to FIGS. 16, 17, and 14 (FIG. 14).
[0143]
When the pile length becomes long (for example, 50 m), the leader 35 of the pile driving machine 42 is usually about 20 m, and the length is limited. Therefore, another rod (from the excavation rod 1 is attached to the upper end of the excavation rod 1. The lower end of the structure (with the excavation head 2 removed) is connected, and the upper end of the other rod is attached to the auger machine 38 to continue excavation.
[0144]
Conversely, when the pile hole excavation is completed and cement milk is injected and the excavation rod 1 is pulled up from the pile hole 7, the length of the leader 35 of the pile driving machine 42 is limited. The injection was interrupted, and the other rod 25 had to be separated from the excavation rod 1 by a predetermined length.
[0145]
That is, construction is performed according to the following procedure. The method for injecting cement milk and the method for burying the foundation piles 20 and 22 are the same as those in Examples 2 and 3.
[0146]
(1) One pile core A side
[0147]
As in the third embodiment, the excavation rod 1A attached to the auger machine 38 of the pile driving machine 42 excavates the upper part of the shaft portion 8A of the pile hole 7A to a predetermined depth, and then the excavation rod 1A is used as the auger machine. The upper end 1a of the excavation rod 1A is temporarily supported above the pile hole 7A. The lower end 25b of the other excavation rod 25 is connected to the upper end 1a of the excavation rod 1A, and the upper end 25a of the other excavation rod 25 is connected to the auger machine 38 to expand the remaining (lower) pile hole shaft portion 8A. The root consolidation part 9A is excavated (FIG. 16, FIG. 17 (a)).
[0148]
Subsequently, cement milk is discharged from the discharge port 5A of the excavation head 2A of the excavation rod 1A to form the root hardening layer 13A. Subsequently, while lifting the excavating rod 1A and the rod 1a, cement milk is similarly discharged from the discharge port 5A to form the lower portion of the pile circumference fixing liquid layer 16A.
[0149]
In this state, the upper end portion 1a of the excavation rod 1A appears on the ground 18, so that the upper end portion 1a of the excavation rod 1A is temporarily supported above the pile hole 7A. At the same time, the other excavation rod 25 is removed from the excavation rod 1A (FIGS. 16A-1 and 17B). The pile hole excavation data on the one pile core A side up to this state is managed by the same management device as in the third embodiment, and the management content up to that point is stored and stored in the PC 51. A pile number is assigned to the pile core A, and since this pile number is stored in the PC 51, it can be easily read and stored.
[0150]
(2) The other pile core B side
[0151]
The excavation rod 1A to which the excavation head 2A is attached at the tip is retained in the pile hole 7A as it is.
[0152]
The other excavation head 2B is attached to the tip of the other excavation rod 25 attached to the auger machine 38 of the same pile driving machine 42 (FIG. 17 (c)). On the side, excavation of the pile hole 7B is started (FIG. 16 (B-1)). At this time, the construction management is performed in the same manner as in the third embodiment (similar to the pile hole 7A) as the construction management of the pile hole 8B, separately from the stored management on the pile hole 7A side. That is, by one pile driving machine 42, one of the two pile cores (pile burying positions) A and B is subjected to a cement milk filling process and the other a drilling process.
[0153]
Similarly, with the other excavation rod 25 excavating the upper portion of the shaft portion 8B of the pile hole 7B (FIG. 17 (d)), the upper end 1a of the excavation rod 1B is temporarily supported above the pile hole 7B, and the auger The other excavation rod 25 is removed from the machine 38 (FIG. 16 (B-2), FIG. 17 (e)).
[0154]
The above management content is temporarily stored in the storage device in the amplifier box 50 or the PC 51 as the management content on the pile core B side. Moreover, since the pile number is attached | subjected also about the pile core B, it can display on the screen 52 of PC of PC51 alternately or simultaneously with the pile hole 7A.
[0155]
(3) One pile core A side
[0156]
The other excavation rod 25 to which the other excavation head 2B is attached at the tip is retained in the pile hole 7B as it is.
[0157]
The pile driving machine 42 is moved to the vicinity of the pile core A, and the upper end portion 1a of the excavating rod 1A held in the pile hole 7A is connected to the auger machine 38 (FIG. 17 (f)). The management information on the pile core A side temporarily stored in the storage device in the amplifier box 50 or the PC 51 is read, and the temporary support of the excavation rod 1A is released.
[0158]
Cement milk is discharged from the discharge port 5A of the excavation rod 1A, and the excavation rod 1A is pulled up while forming the upper part of the pile circumference fixed liquid layer 16A. At this time, if necessary, the discharge of cement milk can be started after the excavating rod 1A is slightly lowered downward. Also in this case, the position of the excavation head 2 </ b> A is measured by the depth meter 45.
[0159]
If the excavation rod 1A is pulled out from the pile hole 7A (FIG. 17 (g)), the pile hole 7A in which the root hardening layer 13A and the pile circumference fixing liquid layer 16A are formed is constructed (FIG. 16 (A-2)). .
[0160]
Hereinafter, similarly, the excavation rod 1A is removed from the auger machine 38 of the pile driving machine 42, the ready-made piles 20 and 22 are embedded, and the foundation pile 24 is constructed on the pile core A.
[0161]
(4) The other pile core B side
[0162]
The pile driving machine 42 is moved to the vicinity of the pile core B, and the lower end of the excavation rod 1B is connected to the upper end of another excavation rod 25 held in the pile hole 7B, and the upper end of the excavation rod 1B is piled. It connects with the auger machine 38 of the machine 42 (FIG.17 (h)). The management information on the pile core B side temporarily stored in the storage device in the amplifier box 50 or the PC 51 is read, and the temporary support of the excavation rod 1B is released.
[0163]
Although the excavation rod 1B is used here, the excavation rod 1A (FIG. 17 (g)) that has been removed can be used as it is in the construction on the pile core A side (not shown).
[0164]
Similarly, in the state where the lower part of the pile hole shaft 8B and the pile hole widened part 9B are excavated (FIG. 17 (i)) and the lower part of the root consolidation layer 13B and the pile peripheral fixed liquid layer 16B is formed, FIG. Similarly to A-1), the excavation rod 1B is temporarily held above the pile hole 7B (not shown).
[0165]
In this state, the management information on the pile core B side is temporarily stored again in the storage device in the amplifier box 50 or the PC 51.
[0166]
(5) Then, similarly to the pile core B, construction is performed on the other pile core C side.
[0167]
Thus, since the pile management number is assigned to each pile core and the construction management status is stored, the construction management display of one pile core A is temporarily stored in the storage device in the amplifier box 50 or the PC 51. The construction management status of the other pile core B can be displayed, the construction management status of the other pile core B can be temporarily stored, the construction management status of one pile core A is read again, and cement milk is injected. Is completed, and if necessary, the construction management status up to the completion of pile burial can be displayed.
[0168]
Therefore, the foundation pile can be constructed by efficiently using even a few pile driving machines 42. Even in this case, the same construction management can be performed.
[0169]
【The invention's effect】
In this invention, the cement milk to be injected is divided into a plurality of times, and the cement milk is injected while moving the cement milk discharge port up and down at least twice in the bottom of the pile hole. It is stable with little variation in outer diameter and variation in compressive strength, and it can be formed uniformly and has the effect of improving the quality of the root hardening layer. Therefore, a strong root-solidifying layer can be formed, and a high supporting force corresponding to the diameter of the pile hole can be exhibited by the foundation pile and the solidified body integrated with the foundation pile. It can also be expected that this can be prevented with respect to the initial settlement before solidification of the root hardening layer.
[0170]
Furthermore, as a device for agitating the inside of the root consolidation layer, various excavation devices such as an excavation head and an auger machine when excavating the root consolidation layer can be used as they are so that a homogeneous layer having a high bearing force can be formed. Since the stirring conditions could be established, simple and economical stirring and mixing could be performed without preparing a new stirring device.
[0171]
In particular, when discharging to 1/3 of the total amount of cement milk at the bottom of the pile hole, these components with low specific gravity are used even if components that are not good for the geology of the supporting ground remain in the pile hole. Cement milk can be pushed up and ejected, and a stable and high quality rooting layer can be obtained.
[0172]
According to the management method or the management device of the present invention, when excavating a pile hole, the load current borne by the auger is converted into an integrated current value and displayed at the same time as excavation. When confirming and subsequently injecting cement milk, the filling amount at every predetermined depth interval is displayed at the same time as the injection, so that the injection status can be confirmed and the construction accuracy of the foundation pile can be improved consistently. effective.
[0173]
By processing and displaying the injection status at the same time as the injection with an information processing means such as a personal computer, there is an effect that the cement milk at every predetermined depth interval can be reliably injected more than the reference amount according to the depth.
[0174]
Since a certain amount or more of cement milk can be injected at predetermined depth intervals in the pile hole, it is possible to obtain necessary and stable support force according to the depth, and imbalance of support force between adjacent foundation piles at the construction site There is an effect that can be suppressed as much as possible.
[0175]
In addition, in the construction management, the information processed by the information processing means can be displayed and stored one by one, so that the operator can use one pile driver without confusion about the construction conditions for each pile hole. Even when one pile hole is divided and the adjacent pile holes are constructed alternately, it is possible to continue using the temporarily stored data in the middle of construction as it is, so construction can be built. There is an effect of increasing the efficiency.
[Brief description of the drawings]
FIGS. 1A to 1D are longitudinal sectional views illustrating a cement milk injection method according to an embodiment of the present invention.
FIGS. 2A to 2D are longitudinal sectional views for explaining a cement milk injection method according to an embodiment of the present invention. FIG.
FIGS. 3A and 3B are graphs of “cement milk discharge amount-depth” for explaining the discharge specifications of cement milk. FIGS. 3B and 3C show the specifications of the present invention, and FIGS. To express.
FIG. 4 is an example of construction data display during excavation used in the embodiment of the present invention.
5 is an enlarged view of the “N value display column” of the construction data in FIG. 4, and is a graph in which the vertical axis indicates depth and the horizontal axis indicates N value.
6 is an enlarged view of the “flow rate / head position display column” of the construction data in FIG. 4, and is a graph with depth or flow rate on the vertical axis and time required for construction (minutes) on the horizontal axis.
7 is an enlarged view of the “pile tip position display field” in the construction data of FIG. 4, where the vertical axis indicates the pile tip position (depth), and the horizontal axis indicates the required time (minutes) since the start of pile insertion. It is a graph.
8 is an enlarged view of the “integrated current value display column” of the construction data in FIG. 4, and is a graph in which the vertical axis indicates depth and the horizontal axis indicates the integrated current value.
9 is an enlarged view of the “root filling liquid injection amount display column” of the construction data in FIG. 4, and is a graph in which the vertical axis indicates the depth of the root hardening portion and the horizontal axis indicates the root hardening liquid injection amount.
10 is an enlarged view of the “pile circumference fixed liquid injection amount display column” of the construction data in FIG. 4, and is a graph in which the vertical axis indicates depth and the horizontal axis indicates the pile circumference fixed liquid injection amount.
FIG. 11 is a front view of a pile driving machine used for carrying out the present invention.
FIG. 12 is a diagram showing the configuration of an embodiment of the construction management device according to the present invention.
FIG. 13 is a flowchart of an embodiment of the construction management method of the present invention.
FIG. 14 is a flowchart of another embodiment (embodiment 4) of the construction management method of the present invention.
FIG. 15 is a longitudinal sectional view for explaining the construction method of the present invention.
FIG. 16 is a longitudinal sectional view for explaining a construction method according to Embodiment 4 of the present invention;
FIGS. 17A to 17I are schematic longitudinal sectional views for explaining the construction method of the fourth embodiment.
18A is an enlarged front view and FIG. 18B is a partially enlarged side view with a part broken away; FIG.
[Explanation of symbols]
1 Drilling rod
2 Drilling head
3 Stir bar
4 Kneading drum
5 Discharge port
6 Drilling arm
7 Pile hole
7a Pile hole inner wall
8 Shaft hole shaft
9 Expanded root consolidation part of pile hole
10 Bottom (enlarged root)
11 Upper edge
12 Pile hole
13 Rooting layer
14 Bottom (root hardening layer)
15 Upper end (root hardening layer)
20 Ready-made piles
21 Tip of ready-made pile
22 Ready-made piles
24 Foundation pile
26 Basic data display field
27 N value display field
28 Flow rate / head position display field
29 Pile tip position display field
30 Integrated current value display field
31 Root hardening liquid injection amount display column
32 Pile circumference fixed liquid injection amount display column
38 auger machine
40 Drive motor (for auger machine)
41 Unwinding device (pile driver)
42 Pile driver
44 Load ammeter
45 Depth meter
46 plants
47 Pressure hose
48 Flowmeter
50 Amp Box
51 Personal computer (PC)
52 PC screen
53 printing press
55 Operator room
57 Drilling arm tip
58 Drilling blade of drilling arm

Claims (6)

杭穴底部に根固め層を形成し、かつ杭穴軸部内に杭周固定液層を形成し、該杭穴内に既製杭を埋設して、根固め層内に既製杭の下端部を定着させる基礎杭の構築に際して、該杭穴底部にセメントミルクを注入して根固め層を構築する方法において、掘削ヘッドを有する掘削ロッドの下端部に吐出口を形成し、
(1) 前記杭穴を掘削後、前記掘削ヘッドを杭穴底に保持して、吐出口から注入すべき全セメントミルク量の3分の1宛セメントミルクを吐出し、
(2) 続いて、前記掘削ロッドを形成予定の根固め層の上縁付近まで上昇させながら全セメントミルク量の3分の1のセメントミルクを吐出し、根固め層内の強度上良くない混入物を前記根固め層の上方に押し上げ、
(3) 次に、杭穴底との間で、前記掘削ロッドを複数回昇降させながら、残りのセメントミルクを吐出して、前記掘削ロッドを引き上げて根固め層を形成する。
ことを特徴とした杭穴根固め層の構築方法。
A root consolidation layer is formed at the bottom of the pile hole, and a pile periphery fixing liquid layer is formed within the pile hole shaft, and the ready-made pile is buried in the pile hole, and the lower end of the ready-made pile is fixed in the consolidation layer. In the construction of the foundation pile, in the method of injecting cement milk into the bottom of the pile hole to construct the rooting layer , a discharge port is formed at the lower end of the excavation rod having the excavation head,
(1) After excavating the pile hole, hold the excavation head at the bottom of the pile hole, and discharge the cement milk addressed to one third of the total amount of cement milk to be injected from the discharge port;
(2) Next, while raising the excavating rod to the vicinity of the upper edge of the root consolidation layer to be formed, one third of the total amount of cement milk is discharged, and the strength in the root consolidation layer is not good. The object is pushed up above the rooting layer,
(3) Next, while raising and lowering the excavation rod a plurality of times between the bottoms of the pile holes, the remaining cement milk is discharged, and the excavation rod is pulled up to form a solidified layer.
A method for constructing a pile hole consolidation layer characterized by that.
「根固め液又は杭周固定液用の」セメントミルクの注入状況を、施工操作室内、施工機械あるいは施工エリアの施工管理室内に設置された表示装置に表示させて、周辺地盤及び杭穴内の築造状態とを確認しながら、セメントミルクを注入し、前記表示装置の表示を、
、横軸を施工開始からの時間とし、縦軸に「流量計から得られる根固め液又は杭周固定液の時間当たりの流量」、「流量計から得られる吐出物の総流量」及び「深度計から得られる前記掘削ヘッド位置」をグラフ化して同時に表示するとする
ことを特徴とした請求項記載の杭穴根固め層の構築方法。
The cement milk injection status for "root- setting liquid or pile circumference fixing liquid" is displayed on the display device installed in the construction operation room, construction machine, or construction control room in the construction area, and the surrounding ground and pile holes are built. While confirming the state, inject cement milk, and display the display device,
, The horizontal axis is the time from the start of construction, and the vertical axis is "flow rate per hour of the rooting liquid or pile circumference fixing liquid obtained from the flow meter", "total discharge flow rate obtained from the flow meter" and "depth" construction method of the excavating head position "a pile hole roots solidified layer of claim 1, wherein that said <br/> be graphed simultaneously displayed obtained from meter.
掘削ロッド又は既製杭を装着する回転駆動装置と、該回転駆動装置を昇降させる昇降手段と、掘削ロッドに水又は「根固め液又は杭周固定液用の」セメントミルク供給する液体供給手段とを備える杭打ち機であって、各種センサーを備え、前記各種センサーからの情報をまとめて演算処理し、画面に表示すると共に情報を蓄積記録することができる情報処理手段を有する杭打ち装置において、
(1) 前記各種センサーは、前記回転駆動装置の負荷電流を測定する負荷電流計と、前記回転駆動装置の昇降量を感知して前記掘削ロッド又は既製杭の地上からの深さ位置を測定する深度計と、前記液体供給手段からの液体の供給量を測定する流量計とを含む構成とし、
(2) 前記情報処理手段は、前記流量計からのデータを、前記深度計からのデータから設定した各深度毎に、表示すると共に、予め設定した各深度毎の規定流量と実際の流量とを比較して表示する機能と、前記負荷電流計からのデータを、所定深度毎に積算して蓄積表示すると共に、予め設定した対応する前記所定深度毎のN値データとを対比して表示する機能と、前記情報を各杭穴毎に読み出し、表示、記憶、蓄積できる機能とを有した
(3) 前記情報処理手段によるデータの表示は、横軸を施工開始からの時間とし、縦軸に「流量計から得られる水、根固め液又は杭周固定液の時間当たりの流量」、「流量計から得られる吐出物の総流量」及び「深度計から得られる前記掘削ヘッド位置」をグラフ化して同時に表示する。
ことを特徴とする基礎杭の施工管理装置。
A rotary drive device for mounting the excavation rod or the ready-made pile, an elevating means for raising and lowering the rotary drive device, and a liquid supply means for supplying water or " cement milk or pile circumference fixing liquid" to the excavation rod In the pile driving device comprising the various sensors, comprising the various sensors, collectively processing the information from the various sensors, displaying the information on the screen and storing and recording information.
(1) The various sensors measure a load ammeter that measures the load current of the rotary drive device and a depth position of the excavation rod or the ready-made pile from the ground by sensing the amount of lift of the rotary drive device. A depth meter, and a flow meter for measuring the amount of liquid supplied from the liquid supply means,
(2) The information processing means displays the data from the flow meter for each depth set from the data from the depth meter, and sets a predetermined flow rate and an actual flow rate for each preset depth. A function for displaying in comparison with a function for accumulating and displaying data from the load ammeter for each predetermined depth, and for comparing and displaying the corresponding N value data for each predetermined depth. And the function of reading out, displaying, storing and accumulating the information for each pile hole .
(3) The display of data by the information processing means, the horizontal axis is the time from the start of construction, and the vertical axis is "flow rate per hour of water, rooting liquid or pile circumference fixing liquid obtained from a flow meter", " The “total discharge flow rate obtained from the flow meter” and the “excavation head position obtained from the depth meter” are graphed and displayed simultaneously.
A construction management device for foundation piles.
掘削ヘッドを有する掘削ロッドの下端部に吐出口を形成し、
杭穴根固め層にセメントミルクを注入する際に
(1) 前記杭穴を掘削後、前記掘削ヘッドを杭穴底に保持して、吐出口から注入すべき全セメントミルク量の3分の1宛セメントミルクを吐出し、
(2) 続いて、前記掘削ロッドを形成予定の根固め層の上縁付近まで上昇させながら全セメントミルク量の3分の1のセメントミルクを吐出し、根固め層内の強度上良くない混入物を前記根固め層の上方に押し上げ、
(3) 次に、杭穴底との間で、前記掘削ロッドを複数回昇降させながら、残りのセメントミルクを吐出して、前記掘削ロッドを引き上げて根固め層を形成する。
請求項記載の基礎杭の施工管理装置。
Forming a discharge port at the lower end of a drilling rod having a drilling head;
When injecting cement milk into the pile hole consolidation layer ,
(1) After excavating the pile hole, hold the excavation head at the bottom of the pile hole, and discharge the cement milk addressed to one third of the total amount of cement milk to be injected from the discharge port;
(2) Next, while raising the excavating rod to the vicinity of the upper edge of the root consolidation layer to be formed, one third of the total amount of cement milk is discharged, and the strength in the root consolidation layer is not good. The object is pushed up above the rooting layer,
(3) Next, while raising and lowering the excavation rod a plurality of times between the bottoms of the pile holes, the remaining cement milk is discharged, and the excavation rod is pulled up to form a solidified layer.
The construction management apparatus for foundation piles according to claim 3 .
掘削ロッド又は既製杭を装着する回転駆動装置と、該回転駆動装置を昇降させる昇降手段と、掘削ロッドに水又は「根固め液又は杭周固定液用の」セメントミルクを供給する液体供給手段とを備える杭打ち機を使用して、杭穴を掘削する掘削工程、該杭穴内にセメントミルクを注入する注入工程、セメントミルクが注入された杭穴内に既製杭を埋設する杭挿入工程からなる構築方法を管理する方法であって、
前記回転駆動装置の負荷電流を測定する負荷電流計からのデータと、前記回転駆動装置の昇降量を感知して前記掘削ロッド先端部又は既製杭先端部の地上からの深さ位置を測定する深度計からのデータと、
前記液体供給手段からの液体の供給量を測定する流量計からのデータとを演算処理して、これらデータを各杭穴毎に読み出しできるように記憶しておき、
各杭穴毎に、
(1) 掘削工程では、前記負荷電流計からのデータを、所定深度毎に積算して蓄積表示すると共に、予め設定した対応する前記所定深度毎のN値データとを対比して表示して、支持層を確認する。
(2) 注入工程では、横軸を施工開始からの時間とし、縦軸に「流量計から得られる水、根固め液又は杭周固定液の時間当たりの流量」、「流量計から得られる吐出物の総流量」及び「深度計から得られる前記掘削ヘッド位置」をグラフ化して同時に表示すると共に、
予め設定した各深度毎の規定流量と実際の流量とを比較して表示して、深度毎のセメントミルク量を管理する。
(3)杭挿入工程では、前記深度計からのデータから杭先端位置を管理して支持層に既製杭が定着することを管理する。
ことを特徴とした基礎杭の施工管理方法。
A rotary drive device for mounting the excavation rod or the ready-made pile, an elevating means for raising and lowering the rotary drive device, and a liquid supply means for supplying water or cement milk for “root- setting liquid or pile circumference fixing liquid” to the excavation rod; Construction comprising a drilling process for excavating a pile hole using a pile driving machine equipped with, an injection process for injecting cement milk into the pile hole, and a pile insertion process for burying a ready-made pile in the pile hole into which cement milk has been injected A method of managing methods,
Depth for measuring the depth position from the ground of the excavation rod tip or ready-made pile tip by sensing the data from the load ammeter that measures the load current of the rotary drive and the amount of lift of the rotary drive Data from the total,
Calculate and process data from a flow meter that measures the amount of liquid supplied from the liquid supply means, and store these data so that they can be read for each pile hole,
For each pile hole,
(1) In the excavation process, the data from the load ammeter is accumulated and displayed for each predetermined depth, and displayed in comparison with the corresponding N value data for each predetermined depth, Check the support layer.
(2) In the injection process, the horizontal axis is the time from the start of construction, and the vertical axis is "flow rate per hour of water, rooting liquid or pile circumference fixing liquid obtained from the flow meter", "discharge obtained from the flow meter. The total flow of the object and the position of the excavation head obtained from the depth gauge are graphed and displayed simultaneously,
The prescribed flow rate at each depth set in advance and the actual flow rate are compared and displayed, and the amount of cement milk at each depth is managed.
(3) In the pile insertion process, the pile tip position is managed from the data from the depth gauge, and it is managed that the ready-made pile is fixed on the support layer.
A construction management method for foundation piles characterized by that.
掘削ヘッドを有する掘削ロッドの下端部に吐出口を形成し、杭穴根固め層にセメントミルクを注入する際に、
(1) 前記杭穴を掘削後、前記掘削ヘッドを杭穴底に保持して、吐出口から注入すべき全セメントミルク量の3分の1宛セメントミルクを吐出し、
(2) 続いて、前記掘削ロッドを形成予定の根固め層の上縁付近まで上昇させながら全セメントミルク量の3分の1のセメントミルクを吐出し、根固め層内の強度上良くない混入物を前記根固め層の上方に押し上げ、
(3) 次に、杭穴底との間で、前記掘削ロッドを複数回昇降させながら、残りのセメントミルクを吐出して、前記掘削ロッドを引き上げて根固め層を形成する。
特徴とした請求項記載の基礎杭の施工管理方法。
When forming the discharge port at the lower end of the drilling rod with the drilling head and injecting cement milk into the pile hole consolidation layer,
(1) After excavating the pile hole, hold the excavation head at the bottom of the pile hole, and discharge the cement milk addressed to one third of the total amount of cement milk to be injected from the discharge port;
(2) Next, while raising the excavating rod to the vicinity of the upper edge of the root consolidation layer to be formed, one third of the total amount of cement milk is discharged, and the strength in the root consolidation layer is not good. The object is pushed up above the rooting layer,
(3) Next, while raising and lowering the excavation rod a plurality of times between the bottoms of the pile holes, the remaining cement milk is discharged, and the excavation rod is pulled up to form a solidified layer.
The construction management method for a foundation pile according to claim 5, characterized in that it is a feature.
JP2001175402A 2000-06-12 2001-06-11 Construction method of pile hole rooting layer, foundation pile construction management device, foundation pile construction management method Expired - Lifetime JP4958028B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001175402A JP4958028B2 (en) 2000-06-12 2001-06-11 Construction method of pile hole rooting layer, foundation pile construction management device, foundation pile construction management method

Applications Claiming Priority (7)

Application Number Priority Date Filing Date Title
JP2000175220 2000-06-12
JP2000175220 2000-06-12
JP2001083234 2001-03-22
JP2000-175220 2001-03-22
JP2001083234 2001-03-22
JP2001-83234 2001-03-22
JP2001175402A JP4958028B2 (en) 2000-06-12 2001-06-11 Construction method of pile hole rooting layer, foundation pile construction management device, foundation pile construction management method

Publications (2)

Publication Number Publication Date
JP2002348868A JP2002348868A (en) 2002-12-04
JP4958028B2 true JP4958028B2 (en) 2012-06-20

Family

ID=27343695

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001175402A Expired - Lifetime JP4958028B2 (en) 2000-06-12 2001-06-11 Construction method of pile hole rooting layer, foundation pile construction management device, foundation pile construction management method

Country Status (1)

Country Link
JP (1) JP4958028B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6048860B1 (en) * 2016-05-12 2016-12-21 ジャパンパイル株式会社 Pile hole excavation management method
JP2018035635A (en) * 2016-09-02 2018-03-08 ジャパンパイル株式会社 Device and method for determining arrival at bearing layer
JP2018080534A (en) * 2016-11-17 2018-05-24 あおみ建設株式会社 Management equipment for deep mixing equipment
JP2022045659A (en) * 2020-09-09 2022-03-22 ジャパンパイル株式会社 Information processing equipment, information processing programs and learning equipment

Families Citing this family (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4491274B2 (en) * 2004-05-12 2010-06-30 新日本製鐵株式会社 Steel pile construction management method
JP4517236B2 (en) * 2004-12-16 2010-08-04 三谷セキサン株式会社 Pile hole drilling method
JP4753132B2 (en) * 2005-06-14 2011-08-24 三谷セキサン株式会社 Pile hole drilling method
JP4599511B2 (en) * 2006-05-25 2010-12-15 三谷セキサン株式会社 Foundation pile construction method, foundation pile structure, foundation pile design method
JP2009162034A (en) * 2008-01-10 2009-07-23 Tokyo Electric Power Co Inc:The Construction method for structure foundation
JP5071858B2 (en) * 2008-03-31 2012-11-14 日本ヒューム株式会社 Ready-made pile construction management equipment
JP5700639B2 (en) * 2010-12-27 2015-04-15 三谷セキサン株式会社 Pile hole construction method
JP6319938B2 (en) * 2013-02-15 2018-05-09 ジャパンパイル株式会社 Pile construction management system
JP6634251B2 (en) * 2015-09-17 2020-01-22 株式会社トーヨーアサノ Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device
JP6702730B2 (en) * 2016-01-19 2020-06-03 株式会社トーヨーアサノ Ready-made pile construction method
JP6048861B1 (en) * 2016-05-12 2016-12-21 ジャパンパイル株式会社 Pile foundation construction management method
JP6754077B2 (en) * 2016-08-02 2020-09-09 ジャパンパイル株式会社 Pile construction management system and construction management method
JP6851760B2 (en) * 2016-09-27 2021-03-31 三谷セキサン株式会社 Foundation pile construction result management method, foundation pile construction result management system
JP2018111982A (en) * 2017-01-11 2018-07-19 株式会社不動テトラ Construction management system for ground improvement
JP6969899B2 (en) * 2017-05-15 2021-11-24 清水建設株式会社 Strength estimation method for root consolidation
JP7139100B2 (en) * 2017-09-06 2022-09-20 三谷セキサン株式会社 Method for injecting solidification agent into drilled hole and drilling rod
JP7092300B2 (en) * 2018-01-18 2022-06-28 油電機テック株式会社 Underground propagation signal transmitter / receiver, underground work head, underground work machine and underground work system, and underground work management method
JP7311244B2 (en) * 2018-03-07 2023-07-19 株式会社大林組 Ground evaluation system and ground evaluation method
JP7332004B2 (en) * 2018-03-07 2023-08-23 株式会社大林組 Ground evaluation system and ground evaluation method
JP2023105560A (en) * 2022-01-19 2023-07-31 ジャパンパイル株式会社 Pile construction method and pile
CN116591161B (en) * 2023-05-04 2024-01-16 中交广州航道局有限公司 Cement mixing pile construction device and use method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01116112A (en) * 1987-10-27 1989-05-09 Sadao Takenaka Settling work of concrete pile and concrete pile
JPH03212512A (en) * 1990-01-18 1991-09-18 Tenotsukusu:Kk Rotating settling engineering method for pile
JP2735733B2 (en) * 1992-04-01 1998-04-02 日本コンクリート工業株式会社 Pile support layer detection device
JP3364854B2 (en) * 1993-09-08 2003-01-08 大同コンクリート工業株式会社 Construction method of excavation hole in pre-boring
JP3126909B2 (en) * 1995-11-15 2001-01-22 株式会社鴻池組 Automatic soil augmentation control method of soil cement column in foundation ground

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6048860B1 (en) * 2016-05-12 2016-12-21 ジャパンパイル株式会社 Pile hole excavation management method
JP2018035635A (en) * 2016-09-02 2018-03-08 ジャパンパイル株式会社 Device and method for determining arrival at bearing layer
JP2018080534A (en) * 2016-11-17 2018-05-24 あおみ建設株式会社 Management equipment for deep mixing equipment
JP2022045659A (en) * 2020-09-09 2022-03-22 ジャパンパイル株式会社 Information processing equipment, information processing programs and learning equipment
JP7518370B2 (en) 2020-09-09 2024-07-18 ジャパンパイル株式会社 Information processing device, information processing program, and learning device

Also Published As

Publication number Publication date
JP2002348868A (en) 2002-12-04

Similar Documents

Publication Publication Date Title
JP4958028B2 (en) Construction method of pile hole rooting layer, foundation pile construction management device, foundation pile construction management method
CN102758430B (en) Large-diameter rotary digging pile construction process for ultra-deep throwing and filling unconsolidated soil body
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
US20120093590A1 (en) Methods of Providing a Support Column
US9243379B2 (en) Method of providing a support column
CN109488202A (en) A kind of gravel rock stratum pile foundation drilling construction engineering method containing gravel-boulder bed
JP6049844B1 (en) Uneven settlement control structure and construction method
JP2004263561A (en) Cast-in-place pile and its construction method
CN112813967A (en) Intelligent control method for pile length operation in construction of cement-soil mixing pile
CN115387328B (en) Beach cast-in-place pile construction method based on ultra-long spiral drilling machine
CN107130579B (en) Reinforcement-free expanded foundation construction device and rigid-flexible dual composite foundation construction method
JP2010133140A (en) Rotary penetrating pile construction system
JP4753132B2 (en) Pile hole drilling method
CN119041407B (en) A construction method for a water-stop curtain of triaxial cement-soil mixing piles in a pebble layer
JP6409196B2 (en) Hydraulic solidifying material liquid replacement column building method and column building apparatus used for the building method
CN214149946U (en) A soil extraction device for subgrade solidity detection
CN211504747U (en) Road compactness test detection device
JP4490710B2 (en) Pile foundation construction equipment and construction method
CN101629470B (en) Drilling construction method for dry rock-socketed bored pile
JP3734976B2 (en) Construction management device and construction management method for Nakabori Root Firming Method
JPH07507362A (en) Method for constructing concrete structures from ground level on coarse material and equipment for carrying out said method
CN111719558B (en) CFG pile composite foundation construction process
JP4188286B2 (en) Ground improvement method
CN118257253B (en) Construction structure and construction method of cast-in-place pile under karst cave geology
CN218211134U (en) Bridge bored concrete pile post-grouting amount measuring device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080522

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100204

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110322

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110523

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120124

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120309

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150330

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4958028

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term