JP5409178B2 - Construction method of concrete bridge and moving work apparatus used in the construction method - Google Patents
[go: Go Back, main page]

JP5409178B2 - Construction method of concrete bridge and moving work apparatus used in the construction method - Google Patents

Construction method of concrete bridge and moving work apparatus used in the construction method Download PDF

Info

Publication number
JP5409178B2
JP5409178B2 JP2009183142A JP2009183142A JP5409178B2 JP 5409178 B2 JP5409178 B2 JP 5409178B2 JP 2009183142 A JP2009183142 A JP 2009183142A JP 2009183142 A JP2009183142 A JP 2009183142A JP 5409178 B2 JP5409178 B2 JP 5409178B2
Authority
JP
Japan
Prior art keywords
block
reinforcing bar
concrete
assembly
next block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2009183142A
Other languages
Japanese (ja)
Other versions
JP2011032841A (en
Inventor
豊 山花
崇 橋本
保明 松尾
浩次 辻
Original Assignee
株式会社錢高組
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社錢高組 filed Critical 株式会社錢高組
Priority to JP2009183142A priority Critical patent/JP5409178B2/en
Publication of JP2011032841A publication Critical patent/JP2011032841A/en
Application granted granted Critical
Publication of JP5409178B2 publication Critical patent/JP5409178B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、一つブロックの施工完成前に次ブロック用の鉄筋構造体の組み立てを先行して行う鉄筋先組みによるコンクリート橋の架設工法及び該工法で用いる移動作業装置に関するものである。   The present invention relates to a concrete bridge erection method using a reinforcing bar tip assembly in which a rebar structure for a next block is assembled prior to the completion of construction of one block, and a mobile work apparatus used in the method.

片持張出し架設方式のコンクリート橋(橋梁)の架設工法における従来の施工サイクルは、図11〜図13に示すように、当該ブロックの型枠・鉄筋・PC鋼材の組み立て後に行う
(1)当該ブロックのコンクリートの打設・養生、
(2)当該ブロックのPC鋼材の緊張・移動作業装置(移動本体)の移動、
(3)次ブロックの型枠・鉄筋・PC鋼材の組み立て
の各工程からなる。そして、これらの工程を当該ブロック、次ブロック、次々ブロックと順次繰り返し実行することによってコンクリート橋の架設を行っていた。
この場合、従来は「当該ブロックのコンクリートの打設・養生(前記(1))」の完了を待って、「PC鋼材の緊張・移動本体の移動(前記(2))」を行い、その後、「次ブロックの型枠・鉄筋・PC鋼材の組み立て(前記(3))」を行っていた。
As shown in FIGS. 11 to 13, the conventional construction cycle in the cantilever erection concrete bridge (bridge) construction method is performed after assembling the block formwork, reinforcing bars and PC steel as shown in FIGS. 11 to 13. Concrete placement and curing,
(2) Tensioning / moving work device (moving body) of PC steel of the block,
(3) Consists of the steps of assembling the next block formwork, rebar, and PC steel. And the concrete bridge was constructed by repeating these processes sequentially with the said block, the following block, and a block one after another.
In this case, in the past, after waiting for completion of “concrete placement and curing of the block ((1))”, “PC steel material tension / movement of the moving body ((2))” is performed, and then “Assembly of next block formwork, rebar and PC steel ((3))” was performed.

しかし、近年、工期の短縮を図るために当該ブロックのコンクリートの打設・養生(前記(1)の工程)のときに、予め次ブロックの鉄筋の組立てを先行させる鉄筋先組みによるコンクリート橋の架設工法が行われるようになってきた(特許文献1:特開平6−185018号公報)。
そして、その特許文献1に開示されているコンクリート橋の架設工法の場合には、当該ブロックのコンクリートの打設、養生時に、先方に張り出して設けた作業足場上に鉄筋組立てヤードを設け、当該鉄筋組立てヤードにおいて次ブロックの鉄筋組立てを先行させる、或は既に先組みされている鉄筋構造体をその位置に吊り上げる等が記載されている。
However, in recent years, in order to shorten the construction period, the concrete bridge has been erected by the reinforcing bar tip assembly that precedes the assembly of the reinforcing bar of the next block in advance when placing and curing the concrete of the block (step (1)). A construction method has been carried out (Patent Document 1: Japanese Patent Laid-Open No. 6-185018).
And, in the case of the concrete bridge erection method disclosed in Patent Document 1, a reinforcing bar assembly yard is provided on a work scaffold that is projected to the front during the concrete placement and curing of the block. In the assembly yard, the rebar assembly of the next block is preceded, or the already assembled rebar structure is lifted to that position.

しかしながら、特許文献1に開示されているコンクリート橋の架設工法の場合は、先行して実施される次ブロックの鉄筋組立ては、別途設けた専用の組立てスペース(次ブロックの位置とは別の位置)において、別個独立して行われる。このように別個独立して組み立てられた次ブロック用の鉄筋構造体が、コンクリート養生中の当該ブロックに隣接する次ブロックの位置まで移動される。そして、養生中のコンクリート端面から突出している軸方向鉄筋の接続用端部と次ブロック用の鉄筋構造体の軸方向鉄筋とが連結される。   However, in the case of the concrete bridge erection method disclosed in Patent Document 1, the rebar assembly of the next block to be carried out in advance is a dedicated assembly space provided separately (position different from the position of the next block). In, it is carried out independently. Thus, the reinforcing bar structure for the next block assembled independently independently is moved to the position of the next block adjacent to the block under concrete curing. And the connection end part of the axial direction reinforcing bar which protrudes from the concrete end surface under curing and the axial direction reinforcing bar of the reinforcing bar structure for the next block are connected.

この場合、施工ないし組み立て時のばらつきや誤差、更に部品の寸法精度等によって前記軸方向鉄筋の接続用端部と鉄筋構造体の軸方向鉄筋との間にどうしても位置ずれが生じる。従って、それを無理やり結束して連結すると軸方向鉄筋の蛇行を招き、各軸方向鉄筋の連続性や直線性を損なわせて各ブロック間の軸方向鉄筋の連結強度を低下させる虞れがあった。   In this case, a positional deviation is inevitably generated between the connecting end of the axial rebar and the axial rebar of the reinforcing bar structure due to variations and errors during construction or assembly, and dimensional accuracy of the parts. Therefore, if it is forcibly bound and connected, the axial rebar will meander, and the continuity and linearity of each axial rebar may be impaired and the connection strength of the axial rebar between each block may be reduced. .

そこで、本発明の目的は、隣り合うブロック同士の鉄筋構造体における、軸方向鉄筋の位置ずれに起因する各ブロック間における軸方向鉄筋の連結強度の低下を解消しつつ、工期の短縮に寄与し得るコンクリート橋の架設工法を提供することにある。また、該工法で用いる移動作業装置を提供することにある。   Therefore, the object of the present invention is to contribute to shortening the construction period while eliminating the decrease in the strength of connection of the axial reinforcing bars between the blocks due to the positional deviation of the axial reinforcing bars in the reinforcing bar structure between adjacent blocks. The purpose is to provide a concrete bridge erection method. Another object of the present invention is to provide a mobile work device used in the construction method.

前記目的を達成するため、本発明の第1の態様は、一つのブロックの施工完成前に次ブロック用の鉄筋構造体の組み立てを先行して行う鉄筋先組みによるコンクリート橋の架設工法であって、施工中の前記一つのブロックの軸方向鉄筋の接続用端部に、次ブロック用の軸方向鉄筋を直接接続し、断面方向鉄筋を前記軸方向鉄筋に組み付けることにより、該次ブロック用の鉄筋構造体を当該次ブロックの位置において組み立てることを特徴とするものである。   In order to achieve the above object, a first aspect of the present invention is a concrete bridge erection method using a reinforcing bar tip assembly in which a reinforcing bar structure for the next block is assembled prior to the completion of construction of one block. Then, by connecting the axial reinforcing bar for the next block directly to the connecting end of the axial reinforcing bar of the one block under construction and assembling the cross sectional reinforcing bar to the axial reinforcing bar, the reinforcing bar for the next block The structure is assembled at the position of the next block.

本態様によれば、次ブロック用の鉄筋構造体を当該次ブロックの位置において組み立てる。すなわち、次ブロック用の鉄筋構造体は、施工中の一つのブロックの軸方向鉄筋の接続用端部に、該次ブロック用の軸方向鉄筋を直接接続し、断面方向鉄筋を前記軸方向鉄筋に組み付けることにより、当該次ブロックの位置において組み立てられる。
従って、隣り合うブロック同士の鉄筋構造体における、軸方向鉄筋の位置ずれは生じない。従って、各ブロック間の軸方向鉄筋の連結強度の増強と、工期の短縮を安価な施工コストで実現することが可能になる。
According to this aspect, the reinforcing bar structure for the next block is assembled at the position of the next block. In other words, the reinforcing bar structure for the next block is directly connected to the axial reinforcing bar for the next block at the connecting end of the axial reinforcing bar of one block under construction, and the sectional reinforcing bar is connected to the axial reinforcing bar. By assembling, it is assembled at the position of the next block.
Accordingly, there is no positional displacement of the axial reinforcing bars in the reinforcing bar structures of adjacent blocks. Therefore, it is possible to increase the connection strength of the axial rebars between the blocks and shorten the construction period at a low construction cost.

本発明の第2の態様は、前記第1の態様のコンクリート橋の架設工法において、前記次ブロックの鉄筋構造体の先行組み立ては、前記一つのブロックの鉄筋構造体の組立て完了後、コンクリートの打設前に開始されることを特徴とするものである。   According to a second aspect of the present invention, in the concrete bridge erection method according to the first aspect, the pre-assembly of the reinforcing bar structure of the next block is performed after the assembly of the reinforcing bar structure of the one block is completed. It is characterized by being started before installation.

本態様によれば、前記第1の態様の作用効果に加えて、早いタイミングで次ブロックの鉄筋構造体の先行組み立てに着手することができ、同時に2ブロック分の鉄筋構造体の組立てを連続して行うことができる。従って、同一の作業を連続して行うことで作業の効率化を図ることができ、以って一層の工期短縮を実現することができる。   According to this aspect, in addition to the effects of the first aspect, it is possible to start the pre-assembly of the reinforcing bar structure of the next block at an early timing, and at the same time, the assembly of the reinforcing bar structures of two blocks is continuously performed. Can be done. Therefore, the efficiency of the work can be improved by continuously performing the same work, and thus the construction period can be further shortened.

尚、前記特許文献1に開示されているコンクリート橋の架設工法によっても、ある程度の工期の短縮は図れるが、上述した組み立て途中の鉄筋構造体の移動の手間や鉄筋構造体の組立てスペースの確保の問題と、当該ブロックの軸方向鉄筋の接続用端部との位置ずれの問題があり、これらの問題によって生ずる作業ロスを考慮すれば、本発明の態様の方が一層の工期短縮を図ることができる。   Although the construction period of the concrete bridge disclosed in Patent Document 1 can be shortened to some extent, the above-described trouble of moving the reinforcing bar structure during assembly and securing of the assembling space of the reinforcing bar structure can be ensured. There is a problem and a problem of misalignment with the connecting end portion of the axial rebar of the block. Considering work loss caused by these problems, the aspect of the present invention can further shorten the work period. it can.

本発明の第3の態様は、前記第1の態様のコンクリート橋の架設工法において、前記次ブロックの鉄筋構造体の先行組み立ては、前記一つのブロックの鉄筋構造体にコンクリートを打設後、該コンクリートの養生と並行して行われることを特徴とするものである。   According to a third aspect of the present invention, in the concrete bridge erection method according to the first aspect, the preceding assembly of the reinforcing bar structure of the next block is performed by placing concrete on the reinforcing bar structure of the one block, It is characterized by being performed in parallel with concrete curing.

本態様によれば、前記第1の態様の作用効果に加えて、当該一つのブロックのコンクリートの養生(硬化)と並行して次ブロックの鉄筋構造体の先行組み立てが行われる。従って、異なる工程を並行して行うことで作業の効率化を図ることができ、一層の工期の短縮を達成することができる。すなわち、コンクリートの養生による硬化の完了を待つ待ち時間の有効利用を通じて作業の効率化を図ることができ、一層の工期の短縮を達成することができる。
また、前記第2の態様と同じ理由で前記特許文献1に開示されているコンクリート橋の架設工法よりも作業効率が良く、より一層の工期の短縮を図ることができる。
According to this aspect, in addition to the effect of the first aspect, the pre-assembly of the reinforcing bar structure of the next block is performed in parallel with the curing (hardening) of the concrete of the one block. Therefore, work efficiency can be improved by performing different processes in parallel, and the construction period can be further shortened. That is, work efficiency can be improved through effective use of waiting time for the completion of hardening due to curing of the concrete, and further shortening of the work period can be achieved.
Further, for the same reason as the second aspect, the work efficiency is better than the concrete bridge erection method disclosed in Patent Document 1, and the construction period can be further shortened.

本発明の第4の態様は、移動作業装置に吊持される作業エリア部に位置する一つブロックの鉄筋構造体にコンクリートを打設後、同じく前記作業エリア部に位置する次ブロックの位置において、前記一つのブロックの軸方向鉄筋の接続用端部を基点として前記鉄筋構造体に連続させて次ブロック用の鉄筋構造体の組み立てを開始する鉄筋先組み工程と、前記一つのブロックのコンクリートの養生後、PC鋼材を緊張させ、該一つのブロックの上流側に位置する前ブロックで荷重を支えられていた前記移動作業装置を前記一つのブロック上に、前記次ブロック用の鉄筋構造体はその位置のままで、前記作業エリアは該移動作業装置と一緒に移動させる移動工程と、前記移動工程の終了時点で、前記次ブロック用の鉄筋構造体の組み立てが完了していない場合は該組み立てを完了する工程と、を有し、組み立てが完了した前記次ブロック用の鉄筋構造体にコンクリートを打設して前記各工程を繰り返すことを特徴とするコンクリート橋の架設工法である。
A fourth aspect of the present invention, concrete after casting the rebar structure of one block located in the working area portion to be hung in the movable work apparatus, also the position of the next block located at the work area portion A rebar pre-assembly step of starting assembly of a rebar structure for the next block by continuing to the rebar structure from the connecting end of the axial rebar of the one block as a base point, and the concrete of the one block After the curing, the PC steel material is tensioned, and the moving work apparatus supported by the front block located upstream of the one block is placed on the one block, the reinforcing bar structure for the next block is In this position, the work area is moved together with the moving work device, and the assembly of the reinforcing bar structure for the next block is completed at the end of the moving process. And a step of completing the assembly if not, and placing the concrete on the rebar structure for the next block that has been assembled, and repeating the steps described above. It is.

本態様によれば、前記各態様と同様に、当該一つのブロックのコンクリートの養生による硬化の完了を待つ待ち時間を利用して、次ブロックの鉄筋構造体の先行組み立てを開始でき、工期の一層の短縮を図ることができる。しかも、移動作業装置は、コンクリートの養生が終了した前記一つのブロックの上に移動する際に、前記次ブロック用の鉄筋構造体はその位置のままで、前記作業エリアを当該移動作業装置と一緒に移動させるので、作業効率が良い。   According to this aspect, similarly to each of the aspects described above, it is possible to start the pre-assembly of the reinforcing bar structure of the next block by using the waiting time for the completion of hardening by curing the concrete of the one block, and to further improve the construction period. Can be shortened. In addition, when the mobile work device moves on the one block after the concrete curing, the rebar structure for the next block remains in its position, and the work area is moved together with the mobile work device. Because it is moved to, work efficiency is good.

また、前記一つのブロックのPC鋼材の緊張後は、PC鋼材の緊張作業に支障になる等という理由で組み立てができなかった次ブロックの鉄筋構造体の残りの組み立てが実行でき、次ブロックのPC鋼材の緊張に先立って行われるPC鋼材の組み立てと並行して次ブロックの鉄筋構造体の組み立てを完成させて、更に次々ブロックの鉄筋構造体の先行組み立てへと移行することが可能になる。   In addition, after the tension of the PC steel material of the one block, the remaining block of the next block rebar structure that could not be assembled due to hindrance to the tension work of the PC steel material can be executed. It is possible to complete the assembly of the reinforcing bar structure of the next block in parallel with the assembly of the PC steel material performed prior to the tension of the steel material, and further shift to the preceding assembly of the reinforcing bar structure of the block one after another.

前記第4の態様のコンクリート橋の架設工法において、前記移動工程で、前記一つのブロックに位置していた型枠も前記移動作業装置と一緒に移動するようにすることができる。   In the concrete bridge erection method according to the fourth aspect, in the moving step, the formwork located in the one block can also be moved together with the moving work device.

このようにすれば、前記移動工程では、当該一つのブロックで使用していた型枠を解体して次ブロックに移動することになるが、前記型枠は移動作業装置と一体に移動するため、該移動作業装置を「前ブロック」上から当該「一つのブロック」上に移動させることによって、前記型枠も同時に当該ブロックから次ブロックに自動的に移動されるようになる。   In this way, in the moving step, the formwork used in the one block is disassembled and moved to the next block, but the formwork moves integrally with the moving work device. By moving the moving work device from the “previous block” to the “one block”, the formwork is automatically moved from the block to the next block at the same time.

本発明の第5の態様に係るコンクリート橋の架設工法で用いる移動作業装置は、脚部より前方に1ブロック分、張り出したトラス構造部を有するコンクリート橋の架設工法で用いる移動作業装置であって、前記トラス構造部の上桁に支持されて前記トラス構造部より前方に1ブロック分、更に張り出すように設けられたメインビームと、前記トラス構造部の下桁及び前記メインビームによって支持されて、前記トラス構造部より前方に1ブロック分、更に張り出すように設けられたサブビームと、前記トラス構造部及びメインビームに吊り持ちされた作業エリア部と、前記サブビームに移動可能に設けられ、鉄筋構造体を保持可能な保持手段と、を備え、前記作業エリア部に位置する一つブロックの鉄筋構造体の組立て完了後、同じく前記作業エリア部に位置する次ブロックの位置において、前記一つのブロックの軸方向鉄筋の接続用端部を基点として前記鉄筋構造体に連続させて次ブロック用の鉄筋構造体の組み立てが開始される状態を実現し、前記一つのブロックのコンクリートの養生後、PC鋼材を緊張させてから、該一つのブロックの上流側に位置する前ブロックで荷重を支えられていた該移動作業装置が前記一つのブロック上に、前記作業エリアと一緒に移動すると共に、前記次ブロック用の鉄筋構造体は前記保持手段で保持され且つその位置のまま保持される状態を実現するように構成されていることを特徴とするものである。
The mobile work device used in the concrete bridge erection method according to the fifth aspect of the present invention is a mobile work device used in the concrete bridge erection method having a truss structure part protruding one block forward from the leg part. the supported digits on the truss structure one block forward Ri by the truss structure, is supported further a main beam which is provided so as to protrude, by the lower digit and the main beam of the truss structure Te, one block forward Ri by the truss structure, further a sub-beams provided as projecting a work area portion which is to have hanging on the truss structure portion及 beauty main beam, movable in the sub-beams And holding means capable of holding the reinforcing bar structure, and after the assembly of the reinforcing bar structure of one block located in the work area portion is completed, At the position of the next block located in the area part, a state where the assembly of the reinforcing bar structure for the next block is started by continuing to the reinforcing bar structure from the connecting end of the axial reinforcing bar of the one block as a base point. After the concrete of the one block is cured, the mobile work device supported by the front block located on the upstream side of the one block after the PC steel material is tensioned is mounted on the one block. In addition, while moving together with the work area, the rebar structure for the next block is held by the holding means and is configured to be held in its position. Is.

本態様によれば、既存の移動作業装置を使用して、メインビームとサブビームを該移動作業装置のトラス構造部に取り付けるだけの簡単な構成によって、移動作業装置が前ブロックに位置している状態で該一つのブロックのコンクリートの打設・養生と次ブロックの鉄筋構造体の先行組立てとを並行して実行することが可能になる。   According to this aspect, the mobile work device is positioned on the front block with a simple configuration in which the main beam and the sub beam are simply attached to the truss structure portion of the mobile work device using the existing mobile work device. Thus, the concrete placement / curing of the one block and the preceding assembly of the reinforcing bar structure of the next block can be executed in parallel.

更に、移動作業装置が前記一つのブロック上に、前記作業エリアと一緒に移動する際に、前記次ブロック用の鉄筋構造体は、前記保持手段で保持され且つその位置のまま保持される状態を実現するように構成されている。従って、該次ブロック用の鉄筋構造体は、そのまま前記一つのブロックの軸方向鉄筋の接続用端部に連結された状態で次ブロックの位置に留まることが可能になり、当該移動作業装置の移動後に直ちに未完成の当該次ブロック用の鉄筋構造体の組み立てを再開することができ、以って工期の短縮を図ることができる。   Furthermore, when the mobile work device moves on the one block together with the work area, the reinforcing bar structure for the next block is held by the holding means and held in its position. It is configured to be realized. Therefore, the reinforcing bar structure for the next block can remain in the position of the next block while being connected to the connecting end of the axial reinforcing bar of the one block as it is. Immediately thereafter, the assembly of the incomplete reinforcing bar structure for the next block can be resumed, thereby shortening the construction period.

本発明によれば、コンクリート橋の架設工法において、隣り合うブロック同士の鉄筋構造体における、軸方向鉄筋の位置ずれは生じない。従って、各ブロック間の軸方向鉄筋の連結強度の増強と、工期の短縮を安価な施工コストで実現することが可能になる。また、コンクリートの養生(硬化)時間を有効に利用して効率的で安価なコンクリート橋の架設施工が可能になり、工期の大幅な短縮が可能になる。   According to this invention, in the construction method of a concrete bridge, the position shift of an axial direction reinforcing bar does not arise in the reinforcing bar structure of adjacent blocks. Therefore, it is possible to increase the connection strength of the axial rebars between the blocks and shorten the construction period at a low construction cost. In addition, the concrete curing (hardening) time can be effectively used to construct a concrete bridge efficiently and inexpensively, and the construction period can be greatly shortened.

本発明の実施例に係るコンクリート橋の架設工法の施工状況の一例を示す斜視図である。It is a perspective view which shows an example of the construction condition of the construction method of the concrete bridge concerning the Example of this invention. 本発明の実施例に係るコンクリート橋の架設工法における一つのブロックのコンクリート打設直後の状態を示す軸方向鉄筋の接続用端部側からの斜視図である。It is a perspective view from the end part for connection of the axial direction reinforcing bar which shows the state immediately after concrete placement of one block in the construction method of the concrete bridge concerning the example of the present invention. 本発明の実施例に係るコンクリート橋の架設工法における一つのブロックのコンクリート養生中、鉄筋構造体を先行組み立てしている状態を示す軸方向鉄筋の連結側からの斜視図である。It is a perspective view from the connection side of the axial direction reinforcement bar which shows the state where the rebar structure is pre-assembled during concrete curing of one block in the construction method of the concrete bridge concerning the example of the present invention. 本発明の実施例に係るコンクリート橋の架設工法における次ブロックの鉄筋先組み工程を示す側断面図である。It is a sectional side view which shows the reinforcing bar tip assembly process of the next block in the construction method of the concrete bridge concerning the Example of this invention. 図4におけるV−V線断面図である。It is the VV sectional view taken on the line in FIG. 本発明の実施例に係るコンクリート橋の架設工法における一つのブロックのPC鋼材緊張・移動作業装置の移動工程を示す側断面図である。It is a sectional side view which shows the movement process of the PC steel material tension | tensile_strength and movement work apparatus of one block in the construction method of the concrete bridge which concerns on the Example of this invention. 本発明の実施例に係るコンクリート橋の架設工法における次ブロックの鉄筋・PC鋼材組み立て完了工程を示す側断面図である。It is a sectional side view which shows the reinforcement block and PC steel material assembly completion process of the next block in the construction method of the concrete bridge concerning the Example of this invention. 本発明の実施例に係るコンクリート橋の架設工法における次々ブロックの鉄筋先組み工程を示す側断面図である。It is a sectional side view which shows the rebar pre-assembly process of a block after another in the construction method of the concrete bridge which concerns on the Example of this invention. 本発明の実施例に係るコンクリート橋の架設工法における次ブロックのPC鋼材緊張・移動作業装置の移動工程を示す側断面図である。It is a sectional side view which shows the movement process of the PC steel material tension | tensile_strength and movement work apparatus of the next block in the construction method of the concrete bridge concerning the Example of this invention. 本発明の実施例に係るコンクリート橋の架設工法における次々ブロックの鉄筋・PC鋼材組立て完了工程を示す側断面図である。It is side sectional drawing which shows the rebar and PC steel material assembly completion process of a block one after another in the construction method of the concrete bridge concerning the Example of this invention. 鉄筋先組みによらない従来例に係るコンクリート橋の架設工法における当該ブロックのコンクリート打設・養生工程を示す側断面図である。It is a sectional side view which shows the concrete placement and curing process of the said block in the construction method of the concrete bridge which concerns on the prior art example which does not depend on a reinforcing bar tip assembly. 鉄筋先組みによらない従来例に係るコンクリート橋の架設工法における当該ブロックのPC鋼材緊張・移動作業装置の移動工程を示す側断面図である。It is a sectional side view which shows the movement process of the PC steel material tension | tensile_strength and movement work apparatus of the said block in the construction method of the concrete bridge which concerns on the prior art example which does not depend on a reinforcing bar tip assembly. 鉄筋先組みによらない従来例に係るコンクリート橋の架設工法における次ブロックの鉄筋・PC鋼材組み立て工程を示す側断面図である。It is a sectional side view which shows the reinforcement block and PC steel material assembly process of the next block in the construction method of the concrete bridge which concerns on the prior art example which does not depend on a reinforcement reinforcement. 本発明のコンクリート橋の架設工法と鉄筋先組みによらない従来工法との施工日数を図表化して示す説明図である。It is explanatory drawing which shows the construction days of the construction method of the concrete bridge of this invention, and the conventional construction method which does not depend on a reinforcing bar tip as a graph.

以下、本発明に係るコンクリート橋の架設工法の実施の形態について詳細に説明する。最初に本発明のコンクリート橋の架設工法を実施する際に使用される移動作業装置1の構造の概略を図1及び図5に基づいて説明する。   Hereinafter, an embodiment of a concrete bridge erection method according to the present invention will be described in detail. The outline of the structure of the mobile work apparatus 1 used when implementing the concrete bridge construction method of this invention first is demonstrated based on FIG.1 and FIG.5.

本発明のコンクリート橋の架設工法は、川や海に架かるコンクリート橋の他、図1に示すように陸地に設けられる自動車道路等の高架橋3の建設に使用される。この種のコンクリート橋の架設工法では、垂直に立ち上げた橋柱5からコンクリート橋7を左右に徐々に張り出させて行く片持ち張出し架設方式のコンクリート製のコンクリート橋の架設工法が多く採用されている。そして、この架設工法において使用されるのが以下述べるコンクリート橋の移動作業装置1である。   The concrete bridge erection method of the present invention is used to construct a viaduct 3 such as a motorway provided on land as shown in FIG. 1 in addition to a concrete bridge over a river or the sea. In this type of concrete bridge erection method, a concrete cantilever concrete bridge erection method is often adopted in which the concrete bridge 7 is gradually extended left and right from the bridge pillar 5 that is set up vertically. ing. A concrete bridge moving work device 1 described below is used in this construction method.

図示のコンクリート橋の移動作業装置1は、構築されたコンクリート橋7の上面に張出し方向に延びるように設置される脚部となるレール9と、前記レール9上を走行する移動本体11と、前記移動本体11に対して設けられるメインビーム13及びサブビーム15と、前記移動本体11とメインビーム13上の横梁2からの吊持体47、49によって支持される横梁6、10によって支持される上下の支保工17、19と、前記支保工17、19と同様に前記移動本体11とメインビーム13上の横梁2からの吊持体51によって支持される横梁4によって支持される作業エリア部21によって構成されている。   The illustrated concrete bridge moving work device 1 includes a rail 9 serving as a leg installed on an upper surface of a constructed concrete bridge 7 so as to extend in an overhanging direction, a moving main body 11 traveling on the rail 9, The main beam 13 and the sub beam 15 provided for the moving main body 11 and the upper and lower beams supported by the horizontal beams 6 and 10 supported by the suspension bodies 47 and 49 from the horizontal beam 2 on the moving main body 11 and the main beam 13. Like the support works 17 and 19, the work body part 21 and the work area part 21 supported by the cross beam 4 supported by the suspension body 51 from the cross beam 2 on the main beam 13 are formed. Has been.

レール9は、H形鋼やI型鋼等の形鋼材によって構成されており、一例として左右1組ずつ計2組設けられている。
移動本体11は、前記レール9上を走行する走行体23と、該走行体23上に支持されるトラス構造部25とを左右に一対ずつ備えることによって構成されている。このうち、走行体23は前記レール9に係合する一例として前後左右4基の走行輪27と、一例として張出し側の走行輪27の回動軸に動力を伝える駆動装置29とを備えることによって構成されている。
The rail 9 is made of a shape steel material such as an H-shaped steel or an I-shaped steel, and two sets of left and right sets are provided as an example.
The moving main body 11 is configured by including a traveling body 23 traveling on the rail 9 and a pair of truss structure portions 25 supported on the traveling body 23 on the left and right. Among these, the traveling body 23 includes four traveling wheels 27 as front and rear, left and right as an example that engages with the rail 9, and a driving device 29 that transmits power to the rotation shaft of the traveling wheel 27 on the overhang side as an example. It is configured.

一方、トラス構造部25は側面視平行四辺形状をした支持構造体であり、前記走行体23上に水平に架け渡される下桁31と、前記下桁31よりも前方に1ブロック分、張り出すように下桁31の上方に水平に架け渡される上桁33と、前記下桁31と上桁33とを接続する傾斜支持枠35、37とを備えることによって構成されている。
尚、前記1ブロックとは、コンクリート橋7を張出し方向に順次張り出させて行く施工単位であり、本明細書では、コンクリート打設・養生等の本施工を行っているブロックのことを「一つのブロック」39、該一つのブロック39の一つ前のブロックを「前ブロック」41、前記一つのブロック39の次のブロックを「次ブロック」43、次ブロック43の次のブロックを「次々ブロック」45としてこれらを区別する。
On the other hand, the truss structure portion 25 is a support structure having a parallelogram shape in a side view, and projects a lower girder 31 laid horizontally on the traveling body 23 and one block ahead of the lower girder 31. As described above, the upper girder 33 extends horizontally above the lower girder 31, and the inclined support frames 35 and 37 that connect the lower girder 31 and the upper girder 33.
The one block is a construction unit in which the concrete bridge 7 is sequentially projected in the projecting direction. In this specification, the block that is performing the actual construction such as concrete placement and curing is referred to as “one block”. "One block" 39, the previous block of the one block 39 is the "previous block" 41, the next block of the one block 39 is the "next block" 43, and the next block of the next block 43 is the "next block" “45” to distinguish them.

メインビーム13は、前記トラス構造部25の上桁33に支持されて前記トラス構造部25より前方に1ブロック分、更に張り出すように設けられている水平支持部材である。メインビーム13も前記レール9と同様、H形鋼等の形鋼材によって構成されている。
サブビーム15は、前記トラス構造部25の下桁31及び前記メインビーム13によって支持されて、前記トラス構造部25より前方に1ブロック分、更に張り出すように設けられている水平支持部材である。サブビーム15も前記レール9と同様、H形鋼等の形鋼材によって構成されている。
The main beam 13 is a horizontal support member that is supported by the upper girder 33 of the truss structure portion 25 and is provided so as to further protrude one block forward from the truss structure portion 25. Similarly to the rail 9, the main beam 13 is also made of a shape steel material such as H-section steel.
The sub beam 15 is a horizontal support member that is supported by the lower beam 31 of the truss structure portion 25 and the main beam 13 and is further extended one block forward from the truss structure portion 25. Similarly to the rail 9, the sub beam 15 is also made of a section steel material such as H-section steel.

上方に設けられる支保工17は、コンクリート橋7の上面に沿うように水平に配置されており、前記移動本体11とメインビーム13上の横梁2から垂下されている吊持体47によって支持される横梁6によって支持され、少なくとも当該一つのブロック39と、次ブロック43との領域をカバーするように設けられている(図4、図5)。
下方に設けられる支保工19は、コンクリート橋7の下面の形状に沿うように幾分、傾斜姿勢で配置されており、前記移動本体11とメインビーム13上の横梁2から垂下されている吊持体49によって支持される横梁10によって支持され、上方の支保工17と同様、少なくとも当該ブロック39と次ブロック43の領域をカバーするように設けられている(図4、図5)。
The upper support 17 is disposed horizontally along the upper surface of the concrete bridge 7 and is supported by a suspension body 47 suspended from the movable body 11 and the cross beam 2 on the main beam 13. It is supported by the cross beam 6 and is provided so as to cover the area of at least the one block 39 and the next block 43 (FIGS. 4 and 5).
The supporting work 19 provided below is arranged in a somewhat inclined posture so as to follow the shape of the lower surface of the concrete bridge 7, and is suspended from the horizontal beam 2 on the moving body 11 and the main beam 13. It is supported by the cross beam 10 supported by the body 49 and is provided so as to cover at least the area of the block 39 and the next block 43 as in the upper support work 17 (FIGS. 4 and 5).

作業足場となる作業エリア部21は、前記移動本体11とメインビーム13上の横梁2から垂下されている吊持体51によって支持される横梁4によって支持され、前ブロック41、一つのブロック39及び次ブロック43の領域をカバーするように設けられている(図4、図5)。
また、前記支保工17、前記支保工19が型枠53を支持している。
また、前記サブビーム15に、前記張り出し方向に沿う方向に摺動自在に保持手段であるチェーンブロック等の支持材57が設けられている。そして、該チェーンブロック等の支持材57を介して組立て途中ないし組立て後の鉄筋構造体55が保持されている。
A work area 21 serving as a work scaffold is supported by a cross beam 4 supported by a suspension body 51 suspended from the cross beam 2 on the main body 13 and the main beam 13, and includes a front block 41, one block 39, and It is provided so as to cover the area of the next block 43 (FIGS. 4 and 5).
Further, the support 17 and the support 19 support the mold 53.
The sub beam 15 is provided with a support member 57 such as a chain block which is a holding means slidably in a direction along the projecting direction. The reinforcing bar structure 55 is held during or after assembly through the support member 57 such as the chain block.

[実施例]
次に、図1〜図10に基づいて、前記コンクリート橋の移動作業装置1を使用することによって実行される本発明のコンクリート橋の架設工法について具体的に説明する。
本発明のコンクリート橋の架設工法は、当該一つのブロック39の施工完成前に次ブロック43の鉄筋組み立てを先行して行う鉄筋先組みによるコンクリート橋の架設工法である。そして、図2、図3に示すように、施工中の当該一つのブロック39を構成する軸方向鉄筋61の接続用端部59に(図2)、次ブロック43の位置において、次ブロック43用の軸方向鉄筋61を直接結束しつつ(図3)、次ブロック43用の断面方向鉄筋63を前記軸方向鉄筋61に結束して、次ブロック43の鉄筋構造体55を先行して組み立てて行くことによって本発明のコンクリート橋の架設工法は実行される。
[Example]
Next, based on FIGS. 1-10, the concrete bridge construction method of this invention performed by using the said concrete bridge moving work apparatus 1 is demonstrated concretely.
The concrete bridge erection method according to the present invention is a concrete bridge erection method by reinforcing bar pre-assembly, in which the reinforcement of the next block 43 is preceded before the construction of the one block 39 is completed. Then, as shown in FIG. 2 and FIG. 3, at the connection end 59 of the axial rebar 61 constituting the one block 39 under construction (FIG. 2), at the position of the next block 43, for the next block 43. The axial rebar 61 is directly bound (FIG. 3), the cross-section reinforcing bar 63 for the next block 43 is bound to the axial rebar 61, and the rebar structure 55 of the next block 43 is assembled in advance. Thus, the concrete bridge erection method of the present invention is executed.

また、本実施例では、前記次ブロック43の鉄筋構造体55の先行組み立ては、当該一つのブロック39の鉄筋構造体55の組立て完了後、コンクリートを打設し、コンクリートの養生(硬化工程)と並行して実行されるようになっている。   In this embodiment, the pre-assembly of the reinforcing bar structure 55 of the next block 43 is performed by placing concrete after the completion of the assembling of the reinforcing bar structure 55 of the one block 39, and curing the concrete (hardening process). It is designed to be executed in parallel.

次に、本実施例に係るコンクリート橋の架設工法を、図4〜図10に基づいて(1)次ブロックの鉄筋先組み工程と、(2)当該一つのブロックのPC鋼材緊張後の移動作業装置の移動工程と、(3)次ブロックの鉄筋組み立て完了工程と、(4)次々ブロックの鉄筋先組み工程と、(5)次ブロックのPC鋼材緊張後の移動作業装置の移動工程と、(6)次々ブロックの鉄筋組み立て完了工程とに分けて具体的に説明する。   Next, the construction method of the concrete bridge according to the present embodiment is based on (1) the rebar pre-assembly process of the next block and (2) the moving work after the tension of the PC steel material of the one block based on FIGS. (3) Rebar assembly completion process of the next block, (4) Rebar pre-assembly process of the next block, (5) Transfer process of the mobile work device after tensioning the PC steel material of the next block, 6) It will be described in detail by dividing it into the rebar assembly completion process of the blocks one after another.

(1)次ブロックの鉄筋先組み工程(図4参照)
次ブロックの鉄筋先組み工程は、当該一つのブロック39のコンクリートの打設後、次ブロック43の位置において直接、次ブロック43の鉄筋構造体55の組立てを開始する工程である。すなわち移動作業装置1に吊持される作業エリア部21に位置する一つブロック39の鉄筋構造体55にコンクリートを打設後、同じく前記作業エリア部21に位置する次ブロック43の位置において、前記一つのブロック39の軸方向鉄筋の接続用端部59を基点として前記一つのブロック39を成す鉄筋構造体55に連続させて次ブロック43用の鉄筋構造体55の組み立てを開始する工程である。
尚、本工程に先立って、当該一つのブロック39の鉄筋構造体55、型枠53、図示しないPC鋼材の組み立てが実施されている。
(1) Rebar pre-assembly process for the next block (see Fig. 4)
The reinforcing block pre-assembly process of the next block is a process of starting the assembly of the reinforcing bar structure 55 of the next block 43 directly at the position of the next block 43 after placing the concrete of the one block 39. That is, after placing concrete on the reinforcing bar structure 55 of one block 39 located in the work area part 21 suspended by the mobile work device 1, at the position of the next block 43 also located in the work area part 21, This is a step of starting assembling of the reinforcing bar structure 55 for the next block 43 in succession to the reinforcing bar structure 55 constituting the one block 39 with the connecting end 59 of the axial reinforcing bar of one block 39 as a base point.
Prior to this step, the rebar structure 55, the mold 53, and the PC steel material (not shown) of the one block 39 are assembled.

本工程では、先ずは、移動作業装置1の前記レール(脚部)9は前ブロック41上に位置しており、型枠53は当該一つのブロック39、組立て途中の鉄筋構造体55は次ブロック43にそれぞれ位置している。
鉄筋構造体55の先行組み立ては、上述したように設置場所である次ブロック43の位置において直接行い、コンクリート養生中の当該一つのブロック39のコンクリート橋7における張出し側端面8から突出している、図2に示す長、短の軸方向鉄筋の接続用端部59を利用して行う。
In this process, first, the rail (leg part) 9 of the mobile work device 1 is positioned on the front block 41, the formwork 53 is the one block 39, and the rebar structure 55 in the middle of the assembly is the next block. 43, respectively.
The preceding assembly of the reinforcing bar structure 55 is directly performed at the position of the next block 43 as the installation place as described above, and protrudes from the overhanging side end face 8 of the concrete bridge 7 of the one block 39 during concrete curing. This is performed using the connecting end 59 of the long and short axial reinforcing bars shown in FIG.

具体的には、図3に示すように前記長、短の軸方向鉄筋の接続用端部59に対して結束線65を使用して次ブロック43の鉄筋構造体55用の軸方向鉄筋61を直接結束して接続し、適宜の間隔で断面方向鉄筋63を同じく結束線65を使用して前記軸方向鉄筋61に順次結束していって鉄筋構造体55を組み立てて行く。
尚、ここでの鉄筋構造体55の先行組み立ては、次工程で行なうPC鋼材の緊張作業等の支障にならない範囲で行う。
Specifically, as shown in FIG. 3, the axial reinforcing bar 61 for the reinforcing bar structure 55 of the next block 43 is connected to the end 59 for connecting the long and short axial reinforcing bars using a binding wire 65. The rebar structures 55 are assembled by directly binding and connecting the cross-section reinforcing bars 63 to the axial reinforcing bars 61 using the binding wires 65 at appropriate intervals.
Here, the prior assembly of the reinforcing bar structure 55 is performed as long as it does not hinder the tension work of the PC steel material performed in the next process.

(2)当該一つのブロックのPC鋼材緊張後の移動作業装置の移動工程(図6参照)
当該移動作業装置の移動工程は、当該一つのブロック39のコンクリートの養生・硬化後、PC鋼材を緊張させ、当該一つのブロック39に位置していた型枠53と一緒に前ブロック41上に位置していた移動作業装置1を移動させて、型枠53を次ブロック43に、レール9及び移動本体11を当該一つのブロック39上にそれぞれ位置させる工程である。
即ち、当該一つのブロック39のコンクリートの養生・硬化後は、前記型枠53を解体して次ブロック43の位置に移動でき、当該一つのブロック39のPC鋼材を図示しないジャッキ等を使用して緊張した後は、当該一つのブロック39もコンクリート橋7の一部となり、移動作業装置1の荷重に耐えられる状態になっている。
(2) Moving process of the moving work device after the PC steel material tension of the one block (see FIG. 6)
The moving process of the moving work apparatus is to position the PC steel material on the front block 41 together with the formwork 53 positioned in the one block 39 after curing and hardening the concrete of the one block 39. This is a step of moving the moving work apparatus 1 that has been performed to position the mold 53 on the next block 43 and the rail 9 and the movable body 11 on the one block 39.
That is, after curing and hardening the concrete of the one block 39, the mold 53 can be disassembled and moved to the position of the next block 43, and the PC steel material of the one block 39 can be used using a jack or the like (not shown). After the tension, the one block 39 also becomes a part of the concrete bridge 7 and can withstand the load of the mobile work device 1.

従って、当該一つのブロック39に構築されたコンクリート橋7の上面にレール9を延ばして行き、走行体23を駆動して移動本体11を1ブロック分、進行方向に移動させることができる。そして、前記支保工17、19に支持されている型枠53が移動本体11と一体になって移動することによって上述のように次ブロック43に至る。
尚、前工程(1)で先行組み立てした組立て途中の鉄筋構造体55は、チェーンブロック等の支持材57に保持された状態で、そのままの位置に残るようになっている。
Therefore, the rail 9 can be extended to the upper surface of the concrete bridge 7 constructed in the one block 39, and the traveling body 23 can be driven to move the moving body 11 by one block in the traveling direction. Then, the mold 53 supported by the supports 17 and 19 moves together with the movable body 11 to reach the next block 43 as described above.
In addition, the rebar structure 55 in the middle of assembling that has been pre-assembled in the previous step (1) remains in a position as it is held by a support member 57 such as a chain block.

(3)次ブロックの鉄筋組み立て完了工程(図7参照)
次ブロックの鉄筋組み立て完了工程は、前記移動本体11の移動と関係なく、次ブロック43の位置において形状が保持されていた先組みされた鉄筋に残りの鉄筋を組み立てて行き、次ブロック43の鉄筋構造体55を完成させ、並行してPC鋼材の組立てを実行する工程である。
即ち、前記一つのブロック39のPC鋼材の緊張後は、PC鋼材の緊張作業の邪魔にならないから、残りの鉄筋の組み立てを実施し、次ブロック43の鉄筋構造体55を完成させる。また、前記作業と並行してPC鋼材の組立て作業を実行し、型枠53を取り付け、当該鉄筋構造体55が配設された型枠53内への次のコンクリートの打設に備える。
(3) Rebar assembly completion process for the next block (see Fig. 7)
The rebar assembly completion process for the next block is performed by assembling the remaining rebars to the reassembled rebar that has been maintained in shape at the position of the next block 43 regardless of the movement of the movable body 11. In this process, the structural body 55 is completed and the PC steel material is assembled in parallel.
That is, after the tension of the PC steel material of the one block 39 does not interfere with the tension work of the PC steel material, the remaining reinforcing bars are assembled and the reinforcing bar structure 55 of the next block 43 is completed. In parallel with the above work, the PC steel material assembly work is executed, the mold 53 is attached, and the next concrete is placed in the mold 53 in which the reinforcing bar structure 55 is disposed.

(4)次々ブロックの鉄筋先組み工程(図8参照)
次々ブロックの鉄筋先組み工程は、次ブロック43のコンクリートの打設後、次々ブロック45の位置において直接、次々ブロック45の鉄筋構造体55の組み立てを開始する工程である。
本工程の具体的構成は前記(1)の次ブロックの鉄筋先行組立て開始工程と同様である。すなわち、コンクリートを打設された状態の次ブロック43を構成する鉄筋構造体55の軸方向鉄筋の接続用端部59を基点として、該次ブロック43を成す鉄筋構造体55に連続させて次々ブロック45用の鉄筋構造体55の組み立てを開始する。
(4) Reinforcing bar pre-assembly process of blocks one after another (see Fig. 8)
The block rebar pre-assembly process of the next block is a process of starting assembling of the rebar structure 55 of the next block 45 directly at the position of the second block 45 after placing the concrete of the next block 43.
The specific configuration of this step is the same as that in the step (1) for starting rebar pre-assembly of the next block. That is, with the connecting end 59 of the axial rebar of the reinforcing bar structure 55 constituting the next block 43 in a state where the concrete has been placed as a base point, the blocks are successively connected to the reinforcing bar structure 55 forming the next block 43. Assembling of the reinforcing bar structure 55 for 45 is started.

(5)次ブロックのPC鋼材緊張後の移動作業装置の移動工程(図9参照)
次ブロックのPC鋼材緊張後の移動作業装置の移動工程は、次ブロック43のコンクリートの養生・硬化後、PC鋼材を緊張させ、次ブロック43に位置していた型枠53と一緒に前記一つのブロック39上に位置していた移動作業装置1を移動させて、型枠53を次々ブロック45に、移動作業装置1を次ブロック43上にそれぞれ位置させる工程である。
本工程の具体的構成は前記(2)の移動工程と同様であるので、ここでの詳細な説明は省略する。
(5) Moving process of moving work device after tension of PC steel of next block (see FIG. 9)
The moving process of the moving work apparatus after the PC steel material tension of the next block includes the above-mentioned one frame together with the formwork 53 located in the next block 43 by tensioning the PC steel material after curing and hardening the concrete of the next block 43. In this step, the mobile work device 1 located on the block 39 is moved to place the mold 53 on the block 45 and the mobile work device 1 on the next block 43.
Since the specific configuration of this step is the same as that of the moving step (2), detailed description thereof is omitted here.

(6)次々ブロックの鉄筋組み立て完了工程(図10参照)
次々ブロックの鉄筋組み立て完了工程は、前記移動本体11の移動と関係なく、次々ブロック45において形状が保持されていた先組みされた鉄筋に残りの鉄筋を組立てて行き、次々ブロック45の鉄筋構造体55を完成させ、並行してPC鋼材の組み立てを実行する工程である。
本工程の具体的構成は前記(3)の完了工程と同様であるので、ここでの詳細な説明は省略する。
(6) Reinforcement assembly process of blocks one after another (see Fig. 10)
In the rebar assembly completion process of the blocks one after another, the rebar structure of the block 45 is assembled one after another by assembling the remaining rebars to the reassembled rebars that have been held in the blocks 45 one after another regardless of the movement of the moving body 11. 55 is a process of completing assembly of PC steel materials in parallel.
Since the specific configuration of this step is the same as the completion step (3), detailed description thereof is omitted here.

以下、順次前記と同様の工程を繰り返してコンクリート橋7を1ブロックずつ伸張させて行き、隣接する他のコンクリート橋7と連結することによって一連の高架橋3の架設工事が完了する。
そして、このような構成の本実施例に係るコンクリート橋の架設工法によれば、図14に示すように、1ブロック目で8日の施工日数、2ブロック目以降で6日の施工日数でコンクリート橋の架設工事を完了することができる。
Thereafter, the steps similar to those described above are sequentially repeated to extend the concrete bridge 7 one block at a time and connect to another adjacent concrete bridge 7 to complete a series of construction work for the viaduct 3.
And according to the construction method of the concrete bridge according to the present embodiment having such a configuration, as shown in FIG. 14, the construction time is 8 days in the first block, and the construction day is 6 days in the second block and thereafter. Bridge construction work can be completed.

一方、鉄筋先組みによらない従来のコンクリート橋の架設工法では、同じく図14に示すように1ブロック目で前記と同じ8日の施工日数、2ブロック目以降でも同じ8日の施工日数を要している。
従って、鉄筋先組みによらない従来のコンクリート橋の架設工法に比べて、本実施例のコンクリート橋の架設工法は、2ブロック目以降で2日ずつ工期を短縮でき、すべてのブロックを累積すれば大幅な工期の短縮が図れることになる。
On the other hand, in the conventional concrete bridge erection method that does not depend on the reinforcing bar pre-assembly, the same number of construction days in the 8th day as above is required in the first block as shown in FIG. doing.
Therefore, compared to the conventional concrete bridge erection method that does not rely on reinforcing steel bars, the concrete bridge erection method of this embodiment can shorten the construction period by two days from the second block onwards, and accumulate all blocks. The construction period can be greatly shortened.

また、鉄筋先組みによる下記の特許文献1に開示されているコンクリート橋の架設工法と比較しても、仮組みした鉄筋構造体の移動の手間の問題や既設の軸方向鉄筋の接続用端部59との位置ずれの問題がない分、作業ロスが少なくなるから工期の短縮が図れ、無理のない軸方向鉄筋61の連結によって、各鉄筋構造体55間の連結強度の増強が図られる。   In addition, compared with the concrete bridge erection method disclosed in Patent Document 1 below using a reinforcing bar assembling method, the problem of moving the temporarily assembled reinforcing bar structure and the end part for connecting an existing axial reinforcing bar Since there is no problem of misalignment with 59, the work loss is reduced, so that the construction period can be shortened, and the connection strength between the reinforcing bar structures 55 can be increased by connecting the axial reinforcing bars 61 without difficulty.

〔他の実施例〕
本発明に係るコンクリート橋の架設工法は以上述べたような構成を基本とするものであるが、本願発明の要旨を逸脱しない範囲内の部分的構成の変更や省略等を行うことも勿論可能である。
[Other Examples]
The concrete bridge erection method according to the present invention is based on the configuration as described above, but it is of course possible to change or omit the partial configuration within the scope not departing from the gist of the present invention. is there.

例えば、前記次ブロック43の鉄筋構造体55の先行組み立てを前記一つのブロック39の鉄筋構造体55の組立て完了後、コンクリートの打設前に実行することも可能である。因みに、このようなタイミングで次ブロック43の鉄筋構造体55の先行組み立てを開始した場合には、同一の作業を連続して行うことで作業の効率化を図ることができる。   For example, the preceding assembly of the reinforcing bar structure 55 of the next block 43 can be performed after the completion of the assembling of the reinforcing bar structure 55 of the one block 39 and before the concrete is placed. Incidentally, when the preceding assembly of the reinforcing bar structure 55 of the next block 43 is started at such timing, the work efficiency can be improved by continuously performing the same work.

この他、本発明を実施するに際して使用したコンクリート橋の移動作業装置1の構成は前述した構成に限らず、次ブロック43での鉄筋構造体55の先行組み立てが可能な種々の構造のコンクリート橋の移動作業装置1が採用可能である。
〔産業上の利用可能性〕
In addition, the configuration of the concrete bridge moving work apparatus 1 used in carrying out the present invention is not limited to the above-described configuration, and the concrete bridges of various structures capable of preceding assembly of the reinforcing bar structure 55 in the next block 43 can be used. The mobile work device 1 can be employed.
[Industrial applicability]

本発明は、一つブロックの施工完成前に次ブロック用の鉄筋構造体の組み立てを先行して行う鉄筋先組みによるコンクリート橋の架設工法の施工現場等において利用可能性を有する。   The present invention has applicability in a construction site or the like of a concrete bridge erection method using a reinforcing bar tip assembly that precedes the assembly of a reinforcing bar structure for the next block before the completion of the construction of one block.

1 コンクリート橋の移動作業装置 2 横梁
3 高架橋 4 横梁
5 橋柱 6 横梁
7 コンクリート橋 8 張り出し側端面
9 レール(脚部) 10 横梁
11 移動本体 13 メインビーム
15 サブビーム 17 支保工
19 支保工 21 作業エリア部
23 走行体 25 トラス構造部
27 走行輪 29 駆動装置
31 下桁 33 上桁
35 傾斜支持枠 37 傾斜支持枠
39 一つのブロック 41 前ブック
43 次ブロック 45 次々ブロック
47 吊持体 49 吊持体
51 吊持体 53 型枠
55 鉄筋構造体 57 チェーンブロック等の支持材
59 軸方向鉄筋の接続用端部 61 軸方向鉄筋
63 断面方向鉄筋 65 結束線
DESCRIPTION OF SYMBOLS 1 Moving work apparatus of concrete bridge 2 Transverse beam 3 Viaduct 4 Lateral beam 5 Bridge pillar 6 Lateral beam 7 Concrete bridge 8 Overhang side end surface 9 Rail (leg part) 10 Lateral beam 11 Main body 13 Main beam 15 Sub beam 17 Supporting work 19 Supporting work 21 Working area part 23 hanging traveling body 25 truss structure portion 27 running wheels 29 driving unit 31 under the digit 33 on girder 35 inclined support frame 37 inclined support frame 39 one block 41 before blanking lock 43 primary block 45 sequentially block 47 Tsujitai 49 Holding body 51 Suspension body 53 Formwork 55 Reinforcing bar structure 57 Support material 59 such as chain block End part for connecting axial reinforcing bar 61 Axial reinforcing bar 63 Cross section reinforcing bar 65 Binding wire

特開平6−185018号公報JP-A-6-185018

Claims (2)

移動作業装置に吊持される作業エリア部に位置する一つブロックの鉄筋構造体にコンクリートを打設後、同じく前記作業エリア部に位置する次ブロックの位置において、前記一つのブロックの軸方向鉄筋の接続用端部を基点として前記鉄筋構造体に連続させて次ブロック用の鉄筋構造体の組み立てを開始する鉄筋先組み工程と、
前記一つのブロックのコンクリートの養生後、PC鋼材を緊張させ、該一つのブロックの上流側に位置する前ブロックで荷重を支えられていた前記移動作業装置を前記一つのブロック上に、前記次ブロック用の鉄筋構造体はその位置のままで、前記作業エリアは該移動作業装置と一緒に移動させる移動工程と、
前記移動工程の終了時点で、前記次ブロック用の鉄筋構造体の組み立てが完了していない場合は該組み立てを完了する工程と、を有し、
組み立てが完了した前記次ブロック用の鉄筋構造体にコンクリートを打設して前記各工程を繰り返すことを特徴とするコンクリート橋の架設工法。
Movable work apparatus striking the concrete reinforcing steel structure of one block located in the working area portion to be hung in after casting, likewise in the position of the next block located at the work area part, the axial direction of the one block Reinforcing bar pre-assembly step that starts assembling of the reinforcing bar structure for the next block by continuing to the reinforcing bar structure from the connecting end of the reinforcing bar,
After curing the concrete of the one block, the PC steel material is tensioned, and the moving work device supported by the front block located on the upstream side of the one block is placed on the one block. A moving step of moving the work area together with the moving work device, while the reinforcing bar structure for the work remains in its position;
And when the assembly of the reinforcing bar structure for the next block is not completed at the end of the moving step, the assembly is completed.
A concrete bridge laying method characterized in that concrete is placed on the rebar structure for the next block that has been assembled and the above steps are repeated.
脚部より前方に1ブロック分、張り出したトラス構造部を有するコンクリート橋の架設工法で用いる移動作業装置であって、
前記トラス構造部の上桁に支持されて前記トラス構造部より前方に1ブロック分、更に張り出すように設けられたメインビームと、
前記トラス構造部の下桁及び前記メインビームによって支持されて、前記トラス構造部より前方に1ブロック分、更に張り出すように設けられたサブビームと、
前記トラス構造部及びメインビームに吊り持ちされた作業エリア部と、
前記サブビームに移動可能に設けられ、鉄筋構造体を保持可能な保持手段と、を備え、
前記作業エリア部に位置する一つブロックの鉄筋構造体の組立て完了後、同じく前記作業エリア部に位置する次ブロックの位置において、前記一つのブロックの軸方向鉄筋の接続用端部を基点として前記鉄筋構造体に連続させて次ブロック用の鉄筋構造体の組み立てが開始される状態を実現し、前記一つのブロックのコンクリートの養生後、PC鋼材を緊張させてから、該一つのブロックの上流側に位置する前ブロックで荷重を支えられていた該移動作業装置が前記一つのブロック上に、前記作業エリアと一緒に移動すると共に、前記次ブロック用の鉄筋構造体は前記保持手段で保持され且つその位置のまま保持される状態を実現するように構成されていることを特徴とするコンクリート橋の架設工法で用いる移動作業装置。
A moving work device used in the construction method of a concrete bridge having a truss structure part protruding one block forward from the leg part,
A main beam that is supported by the upper girder of the truss structure part and is provided so as to protrude further forward by one block from the truss structure part;
A sub beam that is supported by the lower beam of the truss structure portion and the main beam, and is provided so as to protrude further forward by one block from the truss structure portion;
A work area suspended from the truss structure and the main beam;
A holding means provided movably on the sub-beam and capable of holding a reinforcing bar structure;
After the assembly of the reinforcing bar structure of one block located in the work area part, at the position of the next block which is also located in the work area part, the connecting end of the axial reinforcing bar of the one block is used as a base point. Realize the state where the assembly of the reinforcing bar structure for the next block is started in succession to the reinforcing bar structure, and after curing the concrete of the one block, after tensioning the PC steel material, the upstream side of the one block The moving work apparatus supported by the front block located at the position moves together with the work area on the one block, and the reinforcing bar structure for the next block is held by the holding means and A mobile work device used in a concrete bridge erection method, characterized in that it is configured to be held in its position.
JP2009183142A 2009-08-06 2009-08-06 Construction method of concrete bridge and moving work apparatus used in the construction method Active JP5409178B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009183142A JP5409178B2 (en) 2009-08-06 2009-08-06 Construction method of concrete bridge and moving work apparatus used in the construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009183142A JP5409178B2 (en) 2009-08-06 2009-08-06 Construction method of concrete bridge and moving work apparatus used in the construction method

Publications (2)

Publication Number Publication Date
JP2011032841A JP2011032841A (en) 2011-02-17
JP5409178B2 true JP5409178B2 (en) 2014-02-05

Family

ID=43762178

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009183142A Active JP5409178B2 (en) 2009-08-06 2009-08-06 Construction method of concrete bridge and moving work apparatus used in the construction method

Country Status (1)

Country Link
JP (1) JP5409178B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104088226A (en) * 2014-07-20 2014-10-08 华巧波 Vertical column
CN104099877A (en) * 2014-07-20 2014-10-15 华巧波 Connecting bar
JP2017150240A (en) * 2016-02-25 2017-08-31 鹿島建設株式会社 Construction method for mobile work vehicles and structures
JP2018112027A (en) * 2017-01-13 2018-07-19 鹿島建設株式会社 Mobile work vehicle

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174096B (en) * 2013-04-10 2015-04-08 中国十九冶集团有限公司 Suspension connection adjusting method between inner and outer molds and hanger of bridge anti-collision fence
CN103243659B (en) * 2013-05-21 2015-02-11 中铁八局集团第一工程有限公司 Cantilever hanging bracket and using method thereof
JP6533109B2 (en) * 2015-07-14 2019-06-19 オリエンタル白石株式会社 Bridge demolition method
CN106284085B (en) * 2016-08-28 2018-06-01 中铁二十局集团第一工程有限公司 It is close to both wired deep water foundation Large-Span Continuous beam construction methods
CN106351129B (en) * 2016-08-28 2018-08-17 中铁二十局集团有限公司 It is close to both wired large-span continuous beam construction methods
CN106592445A (en) * 2016-11-23 2017-04-26 中铁五局集团有限公司 Full-automatic hydraulic traction walking system for hanging basket of cantilever casting continuous beam
CN107447683A (en) * 2017-09-19 2017-12-08 安徽水利开发股份有限公司 Hanging-basket walking device
JP7213136B2 (en) * 2019-05-09 2023-01-26 鹿島建設株式会社 Box girder construction method and construction system
KR102491148B1 (en) * 2021-07-28 2023-01-19 현대건설(주) Form traveller, construction method for girder segment of fcm bridgeand construction method for fcm bridge using the same

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2556247B2 (en) * 1992-12-18 1996-11-20 鹿島建設株式会社 Construction method of concrete bridge and its construction equipment
JP2003105719A (en) * 2001-10-01 2003-04-09 Nichiei Kensetsu:Kk On-ground assembling device to be used for package erection method
JP3900910B2 (en) * 2001-12-03 2007-04-04 鹿島建設株式会社 Steel web bridge erection method and equipment
JP2008031733A (en) * 2006-07-28 2008-02-14 Oriental Shiraishi Corp Bridge erection method
JP2008031768A (en) * 2006-07-31 2008-02-14 Ps Mitsubishi Construction Co Ltd Cantilever overhanging erection method for corrugated steel plate web box girder bridge

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104088226A (en) * 2014-07-20 2014-10-08 华巧波 Vertical column
CN104099877A (en) * 2014-07-20 2014-10-15 华巧波 Connecting bar
JP2017150240A (en) * 2016-02-25 2017-08-31 鹿島建設株式会社 Construction method for mobile work vehicles and structures
JP2018112027A (en) * 2017-01-13 2018-07-19 鹿島建設株式会社 Mobile work vehicle

Also Published As

Publication number Publication date
JP2011032841A (en) 2011-02-17

Similar Documents

Publication Publication Date Title
JP5409178B2 (en) Construction method of concrete bridge and moving work apparatus used in the construction method
JP4403051B2 (en) Corrugated steel web bridge construction method
JP4569878B2 (en) Bridge girder construction method
JP2008031768A (en) Cantilever overhanging erection method for corrugated steel plate web box girder bridge
JP2008088782A (en) Cantilever overhang erection method of corrugated steel plate web bridge
JP2018053496A (en) Bridge girder erection method for multiple span continuous bridge
JP4777922B2 (en) Mobile suspension support
JP4777319B2 (en) Bridge erection method
JP5053589B2 (en) How to build a bridge girder
JP2006077521A (en) Bridge construction device
JP2006063718A (en) Construction method of overhanging bridge using corrugated steel web
JP2004011196A (en) Arch rib construction method for concrete arch bridge
JP2007315077A (en) Construction method for corrugated steel web bridge using girder wagon
JP4928342B2 (en) Corrugated steel web bridge erection device and corrugated steel web bridge erection method
JP2550846B2 (en) Construction method of the pillar head of PC cable-stayed bridge
JP2003193424A (en) Composite truss bridge and its construction method
JP6509096B2 (en) Extension method
JP2004068286A (en) Construction method of steel PC composite bridge
JP5693869B2 (en) Bridge girder construction method
JP2008031733A (en) Bridge erection method
JP4351523B2 (en) Column head construction method
JP2006112179A (en) Bridge girder construction method
JP4033871B2 (en) How to build a bridge girder
CN111350131A (en) Construction method of three-span bridge tail beam feeding bridge girder erection machine
JP3326724B2 (en) Construction method of concrete cable-stayed bridge and form support trolley used for it

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120731

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130521

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130605

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130726

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20131017

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20131105

R150 Certificate of patent or registration of utility model

Ref document number: 5409178

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250