JP5418456B2 JP2010220873A JP2010220873A JP5418456B2 JP 5418456 B2 JP5418456 B2 JP 5418456B2 JP 2010220873 A JP2010220873 A JP 2010220873A JP 2010220873 A JP2010220873 A JP 2010220873A JP 5418456 B2 JP5418456 B2 JP 5418456B2
Authority
JP
Japan
Prior art keywords
roadbed
hydraulic composition
ballast
water
powder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010220873A
Other languages
Japanese (ja)
Other versions
JP2012077453A (en
Inventor
賢司 宮脇
正博 吉原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Osaka Cement Co Ltd
Original Assignee
Sumitomo Osaka Cement Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Osaka Cement Co Ltd filed Critical Sumitomo Osaka Cement Co Ltd
Priority to JP2010220873A priority Critical patent/JP5418456B2/en
Publication of JP2012077453A publication Critical patent/JP2012077453A/en
Application granted granted Critical
Publication of JP5418456B2 publication Critical patent/JP5418456B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)
  • Railway Tracks (AREA)

Description

本発明は、路盤改良工法に関し、特に鉄道のバラスト軌道下の路盤に雨水等が侵入することにより変状、泥化した路盤を補強改良する工法に関する。   The present invention relates to a roadbed improvement method, and more particularly to a method for reinforcing and improving a roadbed that has been deformed and muddy due to rainwater or the like entering a roadbed under a ballast track of a railway.

鉄道の軌道は、地表を(路床)を切り取り、または土を盛って路盤を形成し、砕石と砂利(バラスト)を敷いて道床とし、その上に枕木及びレールを敷設する、いわゆるバラスト軌道が一般的である。   The railroad track is a so-called ballast track that cuts the surface (the roadbed) or piles up soil to form a roadbed, lays crushed stones and gravel (ballast) as a roadbed, and lays sleepers and rails on it. It is common.

かかるバラスト軌道においては、長年の列車の振動や、地下水の上昇及び雨水や長期の浸水等により、路盤表面などが軟弱化して泥となり、この状態で列車の荷重等の圧力がかかった際に、路盤から泥が噴出する、いわゆる路盤噴泥が発生することがある。また、バラスト道床においても、枕木に対する列車の荷重の載荷と除荷が交互に起こり、除荷時に泥水が吸引されて、再載荷時にバラストの隙間を泥が上昇して道床表面に泥が噴出する、いわゆる道床噴泥が発生することもある。   In such a ballast track, the surface of the roadbed becomes soft and mud due to long-term vibration of the train, rise of groundwater, rainwater and long-term inundation, etc., and when pressure such as train load is applied in this state, There is a case where so-called roadbed mud is generated from which mud is ejected from the roadbed. Also on the ballast roadbed, loading and unloading of the train load on the sleepers occur alternately, mud water is sucked at the time of unloading, mud rises through the gap of the ballast at the time of reloading, and mud jets to the roadbed surface So-called roadbed mud may be generated.

かかる噴泥が発生すると、レールと枕木を支えているバラスト道床の弾性力が失われ、振動、騒音の増加を招くとともに、陥没、張り出し等の軌道変状の危険性が大きくなってしまう。軌道の沈下や軌道狂いの増加は、安全面での懸念事項や乗り心地の悪化等の問題を引き起こすものである。このことから、道床を安全に安定的に保持することが重要であり、保線保守作業の軽減・簡略化が望まれている。   When such mud is generated, the elastic force of the ballast road bed that supports the rails and sleepers is lost, which increases vibration and noise, and increases the risk of track deformation such as depression and overhang. The increase in track subsidence and track misalignment causes problems such as safety concerns and deterioration in ride comfort. For this reason, it is important to hold the roadbed safely and stably, and reduction and simplification of track maintenance work is desired.

従って従来では、定期的にバラストを交換したり、バラスト道床を厚くしたり、路盤面に遮水シート等の被覆を施したり、路盤を取り替える方法等が行なわれている。
定期的にバラストを交換する方法やバラスト道床を厚くする方法は、軟弱化した路盤を補強補修することはできない。
Therefore, conventionally, methods such as periodically changing the ballast, thickening the ballast roadbed, coating the roadbed surface with a water shielding sheet or the like, or replacing the roadbed are performed.
The method of periodically replacing ballast and the method of thickening the ballast roadbed cannot reinforce and repair a weakened roadbed.

また、路盤面に遮水シート等の被覆する方法は、バラスト道床のバラストを全て取り除いた後、該取り除いた路盤面に適当な遮水シート等の積層シート材を敷きこんだり、又は樹脂組成物で被覆したりする方法であり、シートを設置したり、樹脂で被覆した後には、再度バラスト及び枕木を埋め戻す必要があり、その作業面やコスト面での負担はきわめて大きい。   In addition, the method of covering the roadbed surface with a water shielding sheet or the like is to remove all ballast from the ballast roadbed, and then lay a laminated sheet material such as a suitable water shielding sheet on the removed roadbed surface, or resin composition After installing the sheet or covering with resin, it is necessary to backfill the ballast and sleepers again, which is extremely burdensome in terms of work and cost.

特開2002−363903号公報(特許文献1)では、鉄道線路下のバラスト道床のバラストを取り除いた後、その取り除いた路盤面に二液型ウレタン被覆剤を散布して、次いでバラストを埋め戻す、噴泥防止工法が記載されている。   In JP-A-2002-363903 (Patent Document 1), after removing the ballast of the ballast roadbed under the railroad track, the two-part urethane coating agent is sprayed on the removed roadbed surface, and then the ballast is backfilled. A mud prevention method is described.

特開2007−112912号公報(特許文献2)では、枕木周辺のバラストを一部除去した後、バラストを一部除去した箇所に、エチレンオキサイド基および/またはプロピレンオキサイド基を含む末端イソシアネート基含有ウレタンプレポリマー(A)および高沸点希釈剤(B)を含んでなり、イソシアネート基含有率が5質量%を超え15質量%未満であり、粘度が10mPa・s/23℃を超え300mPa・s/23℃未満であることを特徴とする一液湿気硬化型の噴泥固結剤を散布して、次いでバラストを埋め戻す、噴泥防止・抑制施工方法が記載されている。   In Japanese Patent Application Laid-Open No. 2007-112912 (Patent Document 2), a terminal isocyanate group-containing urethane containing an ethylene oxide group and / or a propylene oxide group at a place where the ballast is partially removed after the ballast around the sleeper is partially removed. It comprises a prepolymer (A) and a high-boiling diluent (B), has an isocyanate group content of more than 5% by mass and less than 15% by mass, and a viscosity of more than 10 mPa · s / 23 ° C. and 300 mPa · s / 23. There is described a mud prevention / inhibition construction method in which a one-part moisture-curing type mud consolidation agent, characterized by being less than 0 ° C., is sprayed and then the ballast is backfilled.

しかし、上記いずれの方法も、軟弱化して変状、泥化した路盤を改修することはできず、結局現状では、レール、枕木、バラストを全て除去して、路盤自体を取り替える方法や、バラスト軌道に排水溝を設置する方法が実施されている。
現在は早朝から深夜まで列車が運行しており、改修工事時間も非常に短いことが要求されており、路盤を取り替える方法は作業工程が多く、また作業時間も長くかかる等の作業負担が大きい。
排水設備設置方法では、排水設備をあらたに設けなければならず、コストがかかり、更に排水設備は長年の土砂等により詰まってしまい、設備に寿命がある。
However, none of the above methods can repair softened, deformed and muddy roadbeds, and in the current situation, all the rails, sleepers and ballasts are removed and the roadbed itself is replaced. A method of installing a drainage channel is being implemented.
Currently, trains run from early morning to midnight, and the time required for renovation work is required to be very short, and the method of replacing the roadbed requires a large number of work processes and a long work time.
In the drainage installation method, the drainage has to be newly provided, which is costly. Further, the drainage is clogged with soil and sand for many years, and the equipment has a lifetime.

特開2002−363903号公報JP 2002-363903 A 特開2007−112912号公報JP 2007-1112912 A

本発明の目的は、雨水等による流動化で変状、泥化した軌道下の軟弱路盤を固化させて安定した改良土の路盤を形成することができる、路盤改良工法を提供することである。
また、本発明の目的は、泥化した路盤を直接改質でき、簡便かつ作用負担の少ない、路盤改良工法を提供することである。
An object of the present invention is to provide a roadbed improvement method capable of solidifying a soft roadbed under a track that has been deformed and muddy by fluidization with rainwater or the like to form a stable improved soil roadbed.
Another object of the present invention is to provide a roadbed improvement method that can directly modify a muddy roadbed and that is simple and less burdensome.

本発明は、バラストの一部に、水硬性組成物の部分硬化体を混入させることで、列車走行時の繰り替えし荷重によって、該水硬性組成物の部分硬化体が破砕或いは摩耗して路盤の土中に混合されて、路盤の土を固化改良することにより達成されたものである。   According to the present invention, a partially cured body of the hydraulic composition is mixed into a part of the ballast, so that the partially cured body of the hydraulic composition is crushed or worn by a repeated load during train traveling. It was achieved by mixing in the soil and solidifying and improving the soil of the roadbed.

すなわち、本発明の路盤改良工法は、鉄道線路下のバラストの一部を除去した後、バラストを一部除去した箇所にバラストを埋め戻す際に、埋め戻すバラストの一部を、水硬性組成物の理論水和量より少ない水を含有させて該水硬性組成物が部分的に水和硬化してなる該水硬性組成物の部分硬化体で置換することを特徴とする、路盤改良方法である。   That is, the roadbed improvement method of the present invention is a hydraulic composition that removes part of the ballast under the railroad track and then backfills the part of the ballast that is backfilled when the ballast is backfilled in the part where the part of the ballast is removed A method for improving a roadbed, comprising substituting a partially cured body of the hydraulic composition obtained by containing less water than the theoretical hydration amount of the hydraulic composition and partially hydrating and hardening the hydraulic composition. .

好適には、上記本発明の路盤改良方法において、前記水硬性組成物の部分硬化体は、水硬性組成物と水とが質量比で100:10〜100:15で含有されてなることを特徴とする、路盤改良方法である。   Preferably, in the above-described roadbed improving method of the present invention, the partially cured body of the hydraulic composition includes the hydraulic composition and water in a mass ratio of 100: 10 to 100: 15. It is a roadbed improvement method.

さらに好適には、上記本発明の路盤改良方法において、前記水硬性組成物の部分硬化体は、JIS A 1121「ロサンゼルス試験機により粗骨材のすりへり試験」によるすりへり減量が20〜30質量%であることを特徴とする、路盤改良方法である。   More preferably, in the above-described roadbed improvement method of the present invention, the partially hardened body of the hydraulic composition has a wear loss of 20 to 30% by mass according to JIS A 1121 “Screw test of coarse aggregate using a Los Angeles tester”. There is a method for improving a roadbed.

本発明の路盤改良方法は、バラストの一部を上記水硬性組成物の部分硬化体で置換することで、列車走行時の繰り返し荷重によって、該水硬性組成物の部分硬化体は破砕・摩砕
し、バラストの下方に位置する路盤に落下して路盤の土や泥に混ざり、泥中の水や雨水等の水により、路盤を固化、特に軟弱化して変状した路盤を固化させて、安定した改良土の路盤を形成することが可能となる。
また、本発明の路盤改良方法は、バラストの一部を上記水硬性組成物の部分硬化体で置換することで足りるので、枕木やバラストを全部取り除いたり、路盤の土を入れ替えたりする等の作業は必要でなく、改良時間を短縮することができ、作業性もよく、簡便な路盤改良方法である。
The roadbed improving method of the present invention replaces a part of the ballast with the partially cured body of the hydraulic composition, so that the partially cured body of the hydraulic composition is crushed and ground by repeated loads during train travel. Then, it falls on the roadbed located below the ballast and mixes with the soil and mud of the roadbed, and the roadbed is solidified by water such as water in the mud and rainwater, especially the softened and deformed roadbed is solidified and stabilized. It is possible to form the improved soil roadbed.
In addition, since the roadbed improving method of the present invention is sufficient to replace a part of the ballast with the partially cured body of the hydraulic composition, work such as removing all sleepers and ballast, or replacing the soil of the roadbed. Is not necessary, the improvement time can be shortened, the workability is good, and the road base improvement method is simple.

さらに簡便な方法で路盤を補強・固化することができるため、路盤噴泥や道床噴泥を容易に抑制することができ、軌道の陥没や張り出し等の軌道変状の危険性を防止することができ、従って安全性や良好な乗り心地が容易に維持できることとなる。   Furthermore, since the roadbed can be reinforced and solidified by a simple method, roadbed mud and roadbed mud can be easily suppressed, and the risk of track deformation such as track depression and overhang can be prevented. Therefore, safety and good riding comfort can be easily maintained.

本発明を以下の一例の形態によって説明するが、これらに限定されるものではない。
本発明の路盤改良方法は、鉄道線路下のバラストの一部を除去した後、バラストを一部除去した箇所にバラストを埋め戻す際に、埋め戻すバラストの一部を、水硬性組成物の理論水和量より少ない水を含有させて該水硬性組成物が部分的に水和硬化してなる該水硬性組成物の部分硬化体で置換することを特徴とする、路盤改良方法である。
The present invention will be described by way of the following examples, but is not limited thereto.
The method for improving the roadbed of the present invention, after removing a part of the ballast under the railroad track and then backfilling the ballast in a part where the ballast has been partially removed, A method for improving a roadbed comprising replacing the partially hardened body of the hydraulic composition obtained by containing less water than the amount of hydration and partially hydrating and hardening the hydraulic composition.

本発明においては、路盤を改良するにあたり、レール、枕木等を取り除く必要はなくそのままの状態で、鉄道路面下のバラストの一部を取り除き、この取り除いた箇所にバラストを埋め戻す際に、その一部を上記水硬性組成物の部分硬化体に置換して混入させることで、列車走行時の繰り替えし荷重によって、該水硬性組成物の部分硬化体が破砕或いは摩耗して、その下方に位置する路盤に落下する。その後、路盤を形成する土中に混合して、路盤の泥中の水や雨水等の水により残存する水和活性が発現して固化し、路盤の土を改良する工法である。
本発明の路盤改良方法は、枕木やバラスト、変状した路盤等をすべて取り除く必要がないため、すでに泥化して変状した路盤に対しての改良に特に有効である。
In the present invention, when improving the roadbed, it is not necessary to remove rails, sleepers, etc., and a part of the ballast under the railway road is removed, and when the ballast is refilled in the removed part, one of them is used. By replacing the part with the partially cured body of the hydraulic composition and mixing it, the partially cured body of the hydraulic composition is crushed or worn by the repeated load during train traveling, and is positioned below Fall on the roadbed. After that, it is mixed in the soil forming the roadbed, and the remaining hydration activity is expressed and solidified by water such as water in the mud of the roadbed and rainwater, and solidifies to improve the soil of the roadbed.
The roadbed improving method of the present invention is particularly effective in improving a roadbed that has already been muddy and deformed because it is not necessary to remove all sleepers, ballasts, and deformed roadbeds.

ここで、一般にバラストとして使用する砕石・砂利は、JIS A 1121「ロサンゼルス試験機により粗骨材のすりへり試験」によるすりへり減量が10〜20質量%である。
本発明で用いる水硬性組成物の部分硬化体は、JIS A 1121「ロサンゼルス試験機により粗骨材のすりへり試験」によるすりへり減量が、上記一般のバラスト用の砕石、砂利等と比較して大きければ特に限定されないが、好適には20〜30質量%である。
Here, the crushed stone and gravel generally used as a ballast have a wear loss of 10 to 20% by mass according to JIS A 1121 “Coarse aggregate grinding test using a Los Angeles testing machine”.
The partially cured body of the hydraulic composition used in the present invention has a large amount of grinding loss according to JIS A 1121 “Coarse aggregate grinding test using Los Angeles testing machine” as compared with the above-mentioned general ballast crushed stone, gravel and the like. Although it does not specifically limit, It is 20-30 mass% suitably.

これにより、造粒したときに形状を維持できるとともに、バラストよりも水硬性組成物の部分硬化体のほうが先に破砕或いは摩耗して粉砕化し、バラストの隙間を下方に向かって落下し、路盤の泥分等と混合されて固化することで改良土を形成することができる。または路盤に落下して路盤の土と混ざり合い、雨水等の水により固化して改良土を形成することもできる。
また、バラストと置換される水硬性組成物の部分硬化体の量は、流動化して変状した路盤の状態に応じて、適宜決定することができる。
As a result, the shape can be maintained when granulated, and the partially cured body of the hydraulic composition is crushed or worn earlier than the ballast and pulverized, and the ballast gap falls downward, Improved soil can be formed by mixing with mud and solidifying. Or it can fall on the roadbed, mix with the soil of the roadbed, and solidify with water such as rain water to form improved soil.
Further, the amount of the partially cured body of the hydraulic composition that is replaced with the ballast can be appropriately determined according to the state of the roadbed that has been fluidized and deformed.

本発明に用いる部分硬化体は、水和活性を当該部分水和硬化体内に残存させており、列車走行時の繰り替えし荷重によって、該水硬性組成物の部分硬化体が破砕或いは摩耗して路盤に入り込み、路盤内の泥等の水と接触することで、残存する水和活性を利用して完全水和して、路盤の土壌を固化して補強改良することができるものである。   The partially cured body used in the present invention has hydration activity remaining in the partially hydrated cured body, and the partially cured body of the hydraulic composition is crushed or worn by repeated loading during train traveling. By entering and coming into contact with water such as mud in the roadbed, the remaining hydration activity can be used to completely hydrate and solidify the soil of the roadbed for reinforcement improvement.

水硬性組成物と水とは、理論水和量未満の水を含有するようにして、未水和部分を残存させるが、好適には水硬性組成物と水とは質量比で100:10〜100:15質量部の割合で混合する。通常、水硬性組成物の理論水和量は、水硬性組成物100質量部に対する水比が約27〜28質量部であり、本発明においては、理論水和量未満の水、即ち水硬性組成物100質量部に対して水比が15質量部以下の含水率になるようにし、また造粒するためには、水硬性組成物と水とは質量比で100:10以上となるようにすることが好ましい。   The hydraulic composition and water contain water that is less than the theoretical hydration amount to leave an unhydrated portion. Preferably, the hydraulic composition and water have a mass ratio of 100: 10 to 10:10. Mix at a ratio of 100: 15 parts by mass. Usually, the theoretical hydration amount of the hydraulic composition is about 27 to 28 parts by mass of water with respect to 100 parts by mass of the hydraulic composition. In the present invention, water having less than the theoretical hydration amount, ie, hydraulic composition. In order to achieve a water content of 15 parts by mass or less with respect to 100 parts by mass of the product, and to granulate, the hydraulic composition and water should have a mass ratio of 100: 10 or more. It is preferable.

また、本発明の水硬性組成物の部分硬化体は、水硬性組成物と、当該水硬性組成物が完全水和反応を呈する理論量より少ない量の水とを混合して、造粒することで製造する。造粒径は特に限定されないが、バラストに用いる砕石や砂利等との大きさとの関係から、ほぼ同様の大きさである粒径10〜40mm(JIS篩)のものが好適に使用できる。   In addition, the partially cured body of the hydraulic composition of the present invention is granulated by mixing the hydraulic composition and a smaller amount of water than the theoretical amount at which the hydraulic composition exhibits a complete hydration reaction. Manufactured by. Although the particle size is not particularly limited, those having a particle size of 10 to 40 mm (JIS sieve), which is approximately the same size, can be suitably used in view of the relationship with the size of crushed stone and gravel used for ballast.

ここで、本件明細書中における「部分硬化体」とは、JIS R 5202の「セメントの強熱減量」に規定される強熱減量値(イグニッションロス)が15質量%未満のものを表す。例えばイグニッションロスが15質量%である場合には、その理論水量は通常28質量%であるから、残部の13質量%が水和活性を保持したまま造粒体内に含有保持されており、部分硬化体となる。   Here, the “partially cured body” in the present specification represents an ignition loss value (ignition loss) defined by “cement ignition loss” of JIS R 5202 of less than 15% by mass. For example, when the ignition loss is 15% by mass, the theoretical water amount is usually 28% by mass, so that the remaining 13% by mass is retained and retained in the granulation body while maintaining the hydration activity, and is partially cured. Become a body.

ここで、水硬性組成物の理論水和量とは、例えば、通常の普通ポルトランドセメントの場合には、普通ポルトランドセメントの理論的水量、即ち普通ポルトランドセメントの鉱物組成が全て水和反応によって水和物になるのに必要とされる水量であり、普通ポルトランドセメント100質量部に対し27〜28質量部である。具体的には、100gの普通ポルトランドセメントと28gの水とを混合して良好に硬化させた場合、時間の経過と共に水和が完全に進行して完全水和硬化体が得られるが、この完全水和硬化体を得ることができる程度の水量を表すものである。   Here, the theoretical hydration amount of the hydraulic composition is, for example, in the case of ordinary ordinary Portland cement, the theoretical water amount of ordinary Portland cement, that is, the mineral composition of ordinary Portland cement is all hydrated by the hydration reaction. It is the amount of water required to become a product, and is 27 to 28 parts by mass with respect to 100 parts by mass of ordinary Portland cement. Specifically, when 100 g of ordinary Portland cement and 28 g of water are mixed and cured well, hydration proceeds completely over time, and a fully hydrated cured product is obtained. It represents the amount of water to the extent that a hydrated cured product can be obtained.

一方、例えば、普通ポルトランドセメント100質量部に対して水を約10質量部添加混合して得られた混合物を混練するような場合には、水和反応を完結せしめるには水が不足の混合物、即ち本来理論水量として水硬性組成物100質量部対28質量部の水を要するのに対し10質量部しか添加されていない混合物は、丁度湿潤した粉状体の状態である。
これを任意の公知の造粒装置により造粒して、本発明に用いる部分硬化体とする。
On the other hand, for example, when kneading a mixture obtained by adding about 10 parts by mass of water to 100 parts by mass of ordinary Portland cement, a mixture lacking water to complete the hydration reaction, That is, a mixture in which only 10 parts by mass of water is required as the theoretical amount of water, but 100 parts by mass of the hydraulic composition is 28 parts by mass, is just a wet powder.
This is granulated by any known granulating apparatus to obtain a partially cured body used in the present invention.

本発明の部分硬化体で用いられる水硬性組成物は、粉体原料としては水硬性粉体のみからなることができる。
ここで、水硬性粉体とは、水によって硬化する粉体を意味し、好ましくは普通ポルトランドセメント、ジェットセメント、アルミナセメント、超速硬セメント、珪酸カルシウム、カルシウムアルミネート、カルシウムフルオロアルミネート、カルシウムサルフォアルミネート、カルシウムアルミノフェライト、リン酸カルシウム、スラグ、半水又は無水石膏及生石灰の粉体からなる群より選ばれた少なくとも一種類の粉体が使用される。
The hydraulic composition used in the partially cured body of the present invention can consist only of hydraulic powder as a powder raw material.
Here, the hydraulic powder means a powder that is hardened by water, preferably ordinary Portland cement, jet cement, alumina cement, super-hard cement, calcium silicate, calcium aluminate, calcium fluoroaluminate, calcium salp. At least one powder selected from the group consisting of foaluminate, calcium aluminoferrite, calcium phosphate, slag, semi-water or anhydrous gypsum and quicklime powder is used.

前記水硬性粉体の粒径等は特に制限されないが、造粒時の可使時間ならびに得られる造粒体の形状維持強度の点から、平均粒径10〜40μm程度のものが好ましく、また、造粒体の形状維持強度を確保する点から、ブレーン比表面積が2500cm/g以上であることが好ましい。 The particle size and the like of the hydraulic powder is not particularly limited, but in terms of the pot life during granulation and the shape maintaining strength of the resulting granulated body, those having an average particle size of about 10 to 40 μm are preferable. From the viewpoint of securing the shape-maintaining strength of the granulated body, it is preferable that the brain specific surface area is 2500 cm 2 / g or more.

また、本発明に用いる水硬性組成物は、上記水硬性粉体のほかに、非水硬性粉体を含有してなることもできる。
当該非水硬性粉体は、単体では水と接触しても硬化することがない粉体を意味するが、アルカリ性若しくは酸性状態、あるいは高圧蒸気雰囲気においてその成分が溶出し、他の既溶出成分と反応して生成物を形成する粉体も含む意である。
Further, the hydraulic composition used in the present invention may contain a non-hydraulic powder in addition to the hydraulic powder.
The non-hydraulic powder means a powder that does not harden when contacted with water alone, but its components are eluted in an alkaline or acidic state, or in a high-pressure steam atmosphere, and other already-eluting components. It also includes powders that react to form products.

非水硬性粉体としては、水酸化カルシウム粉末、二水石膏粉末、炭酸カルシウム粉末、スラグ粉末、フライアッシュ粉末、珪石粉末、粘土粉末及びシリカヒューム粉末からなる群より選ばれた少なくとも一種類の粉体を好適に用いることができる。
これらの非水硬性粉体は、ポゾラン反応もしくはマイクロフィラー効果により、強度を増進する機能を有する。
The non-hydraulic powder includes at least one powder selected from the group consisting of calcium hydroxide powder, dihydrate gypsum powder, calcium carbonate powder, slag powder, fly ash powder, silica stone powder, clay powder and silica fume powder. The body can be preferably used.
These non-hydraulic powders have a function of increasing strength by a pozzolanic reaction or a microfiller effect.

これらの非水硬性粉体の平均粒径は、好ましくは水硬性組成物粉体の平均粒径より一桁以上小さく、より好ましくは2桁以上小さいものが、水硬性粉体の間隙を充填し、造粒体が緻密となる点から好ましいが、細かさの下限は特に限定されず、本発明の効果を害することがなければ特に制限されることはないが、通常水硬性粉体の平均粒径の1/500程度であることが造粒性の点から好ましい。
このような粒径の非水硬性粉体を用いることによって、造粒体の形状維持性を更に向上させることができる。
The average particle diameter of these non-hydraulic powders is preferably one or more orders of magnitude smaller than the average particle diameter of the hydraulic composition powder, more preferably two or more orders of magnitude smaller than that of the hydraulic composition powder. However, the lower limit of the fineness is not particularly limited and is not particularly limited as long as it does not impair the effects of the present invention, but is usually an average particle of a hydraulic powder. It is preferable from the point of granulation property to be about 1/500 of the diameter.
By using the non-hydraulic powder having such a particle size, the shape maintaining property of the granulated body can be further improved.

本発明に用いる部分硬化体を調製するには、まず、上記水硬性組成物と水とを上記配合割合で混合して調製するが、その混合方法については、均一に混合できれば、任意の公知の方法を用いて混合することが可能である。
特に、水硬性粉体と非水硬性粉体とを含む水硬性組成物を用いる場合には、強力な剪断力を加えることができる混合方法を採用することが好ましく、例えば、プロシェア型ミキサ等を用いて混練する。この様な剪断力の高い混合機を用いて混合することによって、混合に要する時間を短縮することができる。
In order to prepare the partially cured body used in the present invention, first, the hydraulic composition and water are prepared by mixing at the above-mentioned mixing ratio. The mixing method is arbitrary known as long as it can be mixed uniformly. It is possible to mix using methods.
In particular, when using a hydraulic composition containing a hydraulic powder and a non-hydraulic powder, it is preferable to employ a mixing method capable of applying a strong shearing force, such as a proshear type mixer, etc. Knead using By mixing using such a mixer having a high shearing force, the time required for mixing can be shortened.

また、水の添加方法としては、上記したように、水硬性組成物と、当該水硬性組成物が完全水和反応を呈する理論量より少ない量の水とを混合して湿潤粉体を得て造粒するとともに当該粉体の水和反応を進行させて、部分的に水和活性を残存させる。この場合、湿潤粉体を得た後に造粒しても、湿潤粉体を得ると同時に造粒しても、当該水硬性組成物を均一に添加する方法であれば任意の方法が利用できる。前記水硬性組成物に前記量の水を添加して得られた湿潤粉体を安定して製造するためには、いわゆる練りダマが発生しないように留意する必要がある。   In addition, as described above, as a method for adding water, a wet composition is obtained by mixing a hydraulic composition and a smaller amount of water than the theoretical amount at which the hydraulic composition exhibits a complete hydration reaction. While granulating, the hydration reaction of the powder proceeds to partially leave hydration activity. In this case, any method can be used as long as it is a method of adding the hydraulic composition uniformly, whether it is granulated after obtaining the wet powder, or granulated simultaneously with obtaining the wet powder. In order to stably produce a wet powder obtained by adding the above amount of water to the hydraulic composition, it is necessary to pay attention not to cause so-called kneading.

練りだまの生成を防止するためには、添加する水の液滴径を水硬性組成物粉体の粒子径以下とすることが望ましい。このための水の添加方法としては、例えば好適には市販のドライフォグ・ノズルと称される、粉体粒子と同等以下の液滴径の噴霧が可能となる専用のスプレーノズルが有効に使用できる。   In order to prevent the formation of kneading balls, it is desirable that the droplet diameter of the added water be equal to or smaller than the particle diameter of the hydraulic composition powder. As a water addition method for this purpose, for example, a dedicated spray nozzle that can be sprayed with a droplet diameter equal to or smaller than that of powder particles, preferably called a commercially available dry fog nozzle, can be used effectively. .

具体的には、水硬性組成物の粉体をミキサ内に投入し、当該ミキサを回転あるいは混合動作させながら連続的にドライフォグを噴霧供給する方法が好適に用いられる。
このように行なうことにより、練りダマが全く無い、完全に均一な水硬性組成物と水との混合物、即ち水硬性組成物の湿粉体を得ることができ、これを造粒することにより、本発明に用いる部分硬化体を得ることができる。
Specifically, a method is preferably used in which powder of the hydraulic composition is put into a mixer, and dry fog is sprayed continuously while the mixer is rotated or mixed.
By carrying out in this way, it is possible to obtain a completely uniform hydraulic composition and water mixture, ie, a wet powder of the hydraulic composition, without any kneading, and by granulating this, A partially cured body used in the present invention can be obtained.

さらに好適には、得られた部分水和硬化体の表面に、パラフィンワックスや有機塗料等の極薄いコーティング処理を施すことも可能である。このようなコーティングを設けることにより、残存した水和活性が当該部分硬化体の保管期間中に空気中の湿気によって損失されることを防止することが可能となる。   More preferably, the surface of the obtained partially hydrated cured product can be subjected to an extremely thin coating treatment such as paraffin wax or organic paint. By providing such a coating, it is possible to prevent the remaining hydration activity from being lost by moisture in the air during the storage period of the partially cured body.

かかる水硬性組成物の部分硬化体を用いることで、本発明の路盤改良方法は、枕木やバラストをすべて取り除く必要なく、バラストと置換してバラストの一部として混入させることで、列車走行時の繰り替えし荷重によって、該水硬性組成物の部分硬化体が破砕或いは摩耗して、路盤に落下する。その後路盤を形成する土中に混合されて、路盤の泥中の水により残存する、未水和部分の水和活性が発現して固化し、路盤の土を固化して改良することができる。従って、変状した路盤を取り替える必要がなく、極めて簡便な路盤補強を施工することができる。   By using such a partially cured body of the hydraulic composition, the roadbed improving method of the present invention does not need to remove all the sleepers and ballasts, but replaces the ballast and mixes it as a part of the ballast, thereby The partially hardened body of the hydraulic composition is crushed or worn by the repeated load and falls to the roadbed. Thereafter, it is mixed in the soil forming the roadbed, and the hydration activity of the unhydrated portion remaining by the water in the mud of the roadbed is developed and solidified, and the soil of the roadbed can be solidified and improved. Therefore, it is not necessary to replace the deformed roadbed, and extremely simple roadbed reinforcement can be applied.

本発明は、鉄道線路下のバラスト軌道の変状または流動化した路盤の土壌の補強改良に有効に用いられ、路盤噴泥や道床噴泥等の噴泥を抑制・防止に有用に適用できる。   INDUSTRIAL APPLICABILITY The present invention is effectively used for reinforcing and improving soil of a roadbed that has been deformed or fluidized in a ballast track under a railway track, and can be usefully applied to suppress and prevent mud such as roadbed mud and roadbed mud.

Claims (3)

鉄道線路下のバラストの一部を除去した後、バラストを一部除去した箇所にバラストを埋め戻す際に、埋め戻すバラストの一部を、水硬性組成物の理論水和量より少ない水を含有させて該水硬性組成物が部分的に水和硬化してなる該水硬性組成物の部分硬化体で置換することを特徴とする、路盤改良工法。 After removing part of the ballast under the railroad track, when refilling the ballast in the part where the ballast has been partially removed, the part of the ballast to be refilled contains less water than the theoretical hydration amount of the hydraulic composition. A roadbed improvement method comprising replacing the hydraulic composition with a partially cured body of the hydraulic composition obtained by partially hydrating and hardening the hydraulic composition. 請求項1記載の路盤改良工法において、前記水硬性組成物の部分硬化体は、水硬性組成物と水とが質量比で100:10〜100:15で含有されてなることを特徴とする、路盤改良方法。   In the roadbed improvement method according to claim 1, the partially cured body of the hydraulic composition is characterized in that the hydraulic composition and water are contained in a mass ratio of 100: 10 to 100: 15. Subbase improvement method. 請求項1又は2記載の路盤改良工法において、前記水硬性組成物の部分硬化体は、JIS A 1121「ロサンゼルス試験機により粗骨材のすりへり試験」によるすりへり減量が20〜30質量%であることを特徴とする、路盤改良工法。   3. The roadbed improvement method according to claim 1, wherein the partially cured body of the hydraulic composition has a wear loss of 20 to 30% by mass according to JIS A 1121 “Screw test of coarse aggregate using a Los Angeles tester”. A roadbed improvement method characterized by
JP2010220873A 2010-09-30 2010-09-30 Roadbed improvement method Active JP5418456B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010220873A JP5418456B2 (en) 2010-09-30 2010-09-30 Roadbed improvement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010220873A JP5418456B2 (en) 2010-09-30 2010-09-30 Roadbed improvement method

Publications (2)

Publication Number Publication Date
JP2012077453A JP2012077453A (en) 2012-04-19
JP5418456B2 true JP5418456B2 (en) 2014-02-19

Family

ID=46238020

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010220873A Active JP5418456B2 (en) 2010-09-30 2010-09-30 Roadbed improvement method

Country Status (1)

Country Link
JP (1) JP5418456B2 (en)

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62116686A (en) * 1985-11-12 1987-05-28 Kobe Steel Ltd Production of banking material having high strength
JP2578692B2 (en) * 1991-01-30 1997-02-05 株式会社田口研究所 Permeable roadbed material and permeated roadbed construction method
JP3473998B2 (en) * 1994-09-08 2003-12-08 財団法人鉄道総合技術研究所 Improvement method of track ground
JPH0925605A (en) * 1995-07-12 1997-01-28 Central Japan Railway Co Tenten dojo and its construction method
JP3973377B2 (en) * 2001-06-05 2007-09-12 サンスター技研株式会社 Mud prevention method under railway tracks
JP2003206501A (en) * 2002-01-10 2003-07-25 Sumitomo Osaka Cement Co Ltd Labor saving track with high bending strength

Also Published As

Publication number Publication date
JP2012077453A (en) 2012-04-19

Similar Documents

Publication Publication Date Title
JP5765125B2 (en) Simple paving material and simple paving method
KR101289825B1 (en) Sludge solidified agent and menufacturing method of artificial soil usign the same
CN102899048B (en) Desulfurization gypsum alkali slag soil stabilizer
JP6531022B2 (en) Method for producing cold construction type asphalt mixture and cold construction type asphalt mixture
CN101476274A (en) Elastic material to be used for paving road and method for manufacturing thereof and method for paving road using the elastic material
JP4088434B2 (en) Hydrated cured body
KR101525034B1 (en) Environment-conscious embankment material using high-volume industrial waste by hydration reaction of phosphogypsum-slag
JP2003055025A (en) Hydrated hydrate
KR101363860B1 (en) A super high early strength concrete composition using the eco-friendly cycling silica sand and repairing method of concrete pavement using the same
US20170144932A1 (en) Method for the Production of Cold-Process Bituminous Coatings
JP5418456B2 (en) Roadbed improvement method
JP4850777B2 (en) Method for producing steelmaking slag solidified body, and steelmaking slag solidified body
JP4696851B2 (en) Simple paving slag and simple paving body, civil engineering slag and civil engineering construction body
KR101300680B1 (en) Concrete composite and bank protection block by using slag
JP5950544B2 (en) Roadbed material with glass foam
JP6595964B2 (en) Repair method for roadbed
JP5531888B2 (en) Roadbed improvement method
JP3973377B2 (en) Mud prevention method under railway tracks
KR101482329B1 (en) Fill-up Materials using iron and steelmaking slag
KR100709388B1 (en) Landfill for fill or fill using steel by-products and its manufacturing method
CN101260638A (en) A rapid hardening method that can be used for muddy floor of mine roadway
KR101747316B1 (en) Water permeable block for roadway and sidewalk
JP2013040069A (en) Steel slag subbase and method of producing the same
JP2007314393A (en) Method for inhibiting alkali silica reaction of concrete
KR101461788B1 (en) Method for treating fill-up materials using steelmaking slag

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130214

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131011

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20131022

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20131104

R150 Certificate of patent or registration of utility model

Ref document number: 5418456

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007