Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP5472878B2 - Labor-saving track lift-up device and lift-up method - Google Patents
[go: Go Back, main page]

JP5472878B2 - Labor-saving track lift-up device and lift-up method - Google Patents

Labor-saving track lift-up device and lift-up method Download PDF

Info

Publication number
JP5472878B2
JP5472878B2 JP2010174180A JP2010174180A JP5472878B2 JP 5472878 B2 JP5472878 B2 JP 5472878B2 JP 2010174180 A JP2010174180 A JP 2010174180A JP 2010174180 A JP2010174180 A JP 2010174180A JP 5472878 B2 JP5472878 B2 JP 5472878B2
Authority
JP
Japan
Prior art keywords
labor
track
saving
lift
reaction force
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2010174180A
Other languages
Japanese (ja)
Other versions
JP2012031698A (en
Inventor
武 井上
Original Assignee
株式会社ケー・エフ・シー
株式会社アレン
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社ケー・エフ・シー, 株式会社アレン filed Critical 株式会社ケー・エフ・シー
Priority to JP2010174180A priority Critical patent/JP5472878B2/en
Publication of JP2012031698A publication Critical patent/JP2012031698A/en
Application granted granted Critical
Publication of JP5472878B2 publication Critical patent/JP5472878B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Description

本発明は省力化軌道のリフトアップ装置及びリフトアップ方法に係り、特に地盤上に形成された填充層を備え、該填充層に設けられた枕木によりレールを支持する省力化軌道のリフトアップ装置及びリフトアップ方法に関する。   The present invention relates to a lift-up device and a lift-up method for a labor-saving track, and more particularly, a lift-up device for a labor-saving track that includes a filling layer formed on the ground and supports the rail with sleepers provided on the filling layer, and It relates to a lift-up method.

バラスト軌道の上部50cm程度のバラスト(レールの下に敷き詰められている砕石)をセメント注入材で固結して填充層とした省力化軌道は、バラストの抜け出しを防ぐことができる。また、省力化軌道は、バラスト上に直接枕木を設置したバラスト軌道より道床劣化や軌道狂いが生じにくい等の利点があり、さらには、バラストの補充等の作業を低減することができる利点がある。
しかし、バラスト軌道より軌道狂いが生じにくいとはいえ、軌道下の地盤は殆どがN値自沈(構造物自体の重みで沈んでしまう)からN値が5以下程度のローム層の軟弱な盛土(軟弱地盤)となっており、列車の振動加重等で省力化軌道毎に異なる地盤沈下(不同沈下)を起こしている。
従来、レール面での許容沈下量は2cm程度であり、この許容沈下量を超えた部分では、軌道両サイドの掘削を行い、ジャッキを差し込み、省力化軌道全体をリフトアップさせ、リフトアップ状態において省力化軌道底盤部の間隙にセメント系注入材を填充材として補充し、補充後レールを許容高さに調整して列車を通している(特許文献1)。図12は、地盤沈下対策の工程を示す断面図であり、バラスト軌道1の上部50cm程度のバラスト部分がセメント注入材で固結されて填充層2が形成されており、該填充層2上に枕木3の一部が埋設、固定され、その上にレール4a、4bが取り付けられて省力化軌道5が形成されている。
図12(A)に示すように、沈下量が許容沈下量を超えると、図12(B)に示すように、省力化軌道5の両サイドのバラスト部分1a、1bを掘削し、掘削部にジャッキ6a、6bを差し込み、省力化軌道全体を所定の高さまでリフトアップさせ、かかる状態で軌道底盤部の間隙7にセメント系注入材8を填充材として補充し(A矢印参照)、補充完了後レールを許容高さに調整し、最後に図12(C)に示すように、軌道両サイドの掘削部にバラストを埋め込んで地盤沈下対策を完了する。
The labor-saving track, which uses ballast (the crushed stone spread under the rail) about 50 cm above the ballast track, cemented with cement, can prevent ballast from coming out. In addition, the labor-saving trajectory has advantages such as less prone to bed deterioration and trajectory deviation than the ballast trajectory in which the sleepers are installed directly on the ballast, and further has the advantage that work such as replenishment of ballast can be reduced. .
However, although trajectory deviation is less likely to occur than the ballast trajectory, most of the ground under the trajectory is N-value self-settled (since it sinks due to the weight of the structure itself) and the soft embankment of the ROHM layer with an N-value of about 5 or less ( Soft ground), and subsidence (dissimilar subsidence) is occurring for each labor-saving track due to the vibration load of the train.
Conventionally, the allowable subsidence amount on the rail surface is about 2cm, and at the part exceeding this allowable subsidence amount, excavation on both sides of the track, inserting jacks, lifting up the entire labor-saving track, The cement-based injecting material is replenished as a filler in the space between the labor-saving track bottoms, and the rail is adjusted to an allowable height after replenishment (Patent Document 1). FIG. 12 is a cross-sectional view showing a process for countermeasures against land subsidence. A ballast portion about 50 cm above the ballast track 1 is consolidated with a cement injecting material to form a filling layer 2 on the filling layer 2. A part of the sleeper 3 is embedded and fixed, and rails 4 a and 4 b are attached thereon to form a labor-saving track 5.
As shown in FIG. 12 (A), when the subsidence amount exceeds the allowable subsidence amount, as shown in FIG. 12 (B), the ballast portions 1a and 1b on both sides of the labor-saving track 5 are excavated, and the excavation part The jacks 6a and 6b are inserted, the entire labor-saving track is lifted up to a predetermined height, and in this state, the cement-based injection material 8 is replenished as a filler in the gap 7 of the track base (see arrow A), and after completion of refilling The rail is adjusted to an allowable height, and finally, as shown in FIG. 12 (C), ballast is buried in the excavated portions on both sides of the track to complete the ground settlement measures.

特開2007−247356号公報JP 2007-247356 A

しかし、かかる従来方法では、1)軌道両サイドの掘削とジャッキの差込作業、2)軌道のリフトアップと填充材の注入作業、3)バラストの埋め戻しと軌道整備作業、という3つの工程が必要となり、地盤沈下対策、特にリフトアップ作業が大掛かりになると共に、修復工期が長くなる問題がある。しかも、従来方法の填充材の注入は基本的な地盤沈下対策でないため、軌道が許容沈下量を超えるたびに大掛かりなリフトアップ作業を行なわなければならない問題がある。
以上から、本発明の目的は、掘削作業やバラストの埋め戻し作業無しでレール高さを効率的に調整可能にすることである。
本願発明の別の目的は、ジャッキを用いずに省力化軌道をリフトアップしてレール高さを調整可能にすることである。
本願発明の別の目的は、地盤沈下の修復工と同時に基本的な地盤沈下対策工を行なえるようにすることである。
However, in this conventional method, there are three processes: 1) excavation on both sides of the track and jack insertion work, 2) track lift-up and filling material injection, and 3) ballast backfilling and track maintenance work. This is necessary, and there is a problem that ground subsidence measures, particularly lift-up work, become large, and the repair period is prolonged. In addition, since the injection of the filler of the conventional method is not a basic countermeasure for ground subsidence, there is a problem that a large lift-up operation must be performed every time the track exceeds the allowable subsidence amount.
From the above, an object of the present invention is to enable the rail height to be adjusted efficiently without excavation work or ballast backfilling work.
Another object of the present invention is to make it possible to adjust the rail height by lifting the labor-saving track without using a jack.
Another object of the present invention is to make it possible to perform a basic ground settlement countermeasure simultaneously with a ground settlement repair work.

本発明は、地盤上に形成された填充層を備え、該填充層に設けられた枕木によりレールを支持する省力化軌道のリフトアップ装置および省力化軌道のリフトアップ方法である。
・省力化軌道のリフトアップ装置
本願発明の省力化軌道のリフトアップ装置は、省力化軌道の両側にそれぞれ設置される複数の支持部、該支持部により軌道上方において支持される反力用架台、該反力用架台に取り付けられると共に、前記省力化軌道の前記填充層に打設された複数本のボルト材とそれぞれ連結されて該省力化軌道を引き上げる引き上げ部を備え、前記引き上げ部に引き上げ力を発生し、該引き上げ力の反力を、前記反力用架台を介して前記支持部で受け止めて前記省力化軌道を引き上げる。
・省力化軌道のリフトアップ方法
本発明の省力化軌道のリフトアップ方法では、枕木を介して前記填充層に複数本のボルト材を打設し、省力化軌道の両側にそれぞれ複数の支持部を設置し、該支持部により軌道上方において反力用架台を支持し、前記反力用架台に前記各ボルト材と連結されて省力化軌道を引き上げる引き上げ部を取り付け、前記引き上げ部に引き上げ力を発生し、該引き上げ力の反力を、前記反力用架台を介して前記支持部で受け止めて前記省力化軌道を引き上げる。
The present invention is a labor-saving track lift-up device and a labor-saving track lift-up method that includes a filling layer formed on the ground and supports rails with sleepers provided on the filling layer.
-Labor-saving track lift-up device The labor-saving track lift-up device of the present invention comprises a plurality of support portions respectively installed on both sides of the labor-saving track, a reaction force support supported above the track by the support portions, A lifting part that is attached to the reaction force mount and is connected to a plurality of bolt members placed on the filling layer of the labor-saving track and pulls up the labor-saving track, and has a lifting force on the lifting portion. The reaction force of the lifting force is received by the support portion via the reaction force mount, and the labor-saving track is pulled up.
-Labor-saving track lift-up method In the labor-saving track lift-up method of the present invention, a plurality of bolt members are placed on the filling layer via sleepers, and a plurality of support portions are provided on both sides of the labor-saving track. Install and support the reaction force pedestal above the track by the support, and attach a lifting part that pulls up the labor-saving track connected to each bolt material to the reaction force pedestal and generates a lifting force in the lifting part Then, the reaction force of the lifting force is received by the support portion through the reaction force mount, and the labor saving track is pulled up.

本発明によれば、枕木を介して前記填充層に複数本のボルト材を打設し、省力化軌道の両側にそれぞれ複数の支持部を設置し、該支持部により軌道上方において反力用架台を支持し、前記反力用架台に前記各ボルト材と連結されて省力化軌道を引き上げる引き上げ部を取り付け、前記引き上げ部に引き上げ力を発生し、該引き上げ力の反力を、前記反力用架台を介して前記支持部で受け止めて前記省力化軌道を引き上げるようにしたから、掘削作業やバラストの埋め戻し作業が不要であり、しかも、ジャッキを用いずに省力化軌道をリフトアップしてレール高さを効率的に調整することができる。
本願発明によれば、省力化軌道のリフトアップ前後に、枕木および填充層を貫通して地中に孔あき鋼管を打設する工程を容易に追加でき、該孔あき鋼管より、孔あき鋼管周囲の地中、及びリフトアップにより生じた省力化軌道との空隙部に注入材を注入することにより、地盤沈下の修復工と同時に基本的な地盤沈下対策工を行なうことできる。
According to the present invention, a plurality of bolt members are placed on the filling layer via sleepers, and a plurality of support portions are installed on both sides of the labor-saving track. A lifting portion that is connected to each bolt member and pulls up a labor-saving track is attached to the reaction force mount, and a lifting force is generated in the lifting portion, and the reaction force of the lifting force is used for the reaction force. The labor-saving track is lifted by being received by the support portion via a gantry, so there is no need for excavation work or back-filling of the ballast, and the rail is lifted up without using a jack. The height can be adjusted efficiently.
According to the present invention, before and after lifting the labor-saving track, it is possible to easily add a step of placing a perforated steel pipe in the ground through the sleepers and the filling layer, and from the perforated steel pipe, By injecting the injection material into the gap between the ground and the labor-saving track generated by lift-up, it is possible to perform basic ground subsidence countermeasure work simultaneously with the ground subsidence repair work.

本願発明の省力化軌道のリフトアップ装置の構成図である。It is a block diagram of the lift-up apparatus of the labor saving track | orbit of this invention. リフトアップ装置の平面図、側面図である。It is the top view and side view of a lift-up apparatus. ボルト材の省力化軌道への打設説明図である。It is an explanatory view of placing bolt material on a labor-saving track. 孔あき鋼管の打設説明図である。FIG. 3 is an explanatory diagram for placing a perforated steel pipe. 孔あき鋼管である注入管併用マイクロパイルを、マイクロパイル設置用削孔機を用いて打設する説明図である。It is explanatory drawing which drives the injection pipe combined micropile which is a perforated steel pipe using the drilling machine for micropile installation. リフトアップ装置の設置説明図である。It is installation explanatory drawing of a lift-up apparatus. リフトアップ装置による省力化軌道の引き上げ説明図である。It is explanatory drawing of raising the labor saving track | orbit by a lift-up apparatus. 地盤強化工程説明図である。It is ground reinforcement process explanatory drawing. 図8の一部拡大図である。FIG. 9 is a partially enlarged view of FIG. 8. 省力化軌道下の地盤修復工程説明図である。It is a ground repair process explanatory drawing under a labor-saving track. 省力化軌道下の地盤修復と地盤補強完了後の断面図である。It is sectional drawing after ground restoration under a labor-saving track and ground reinforcement completion. 従来の地盤沈下対策の工程を示す断面図である。It is sectional drawing which shows the process of the conventional ground subsidence countermeasure.

(A)省力化軌道のリフトアップ装置
図1は本発明の省力化軌道のリフトアップ装置の構成図である。
図1において、バラスト軌道11の上部50cm程度のバラスト部分がセメント注入材で固結されて填充層12が形成されており、該填充層12上にコンクリート製の枕木13が埋設、固定され、その上にレール14a、14bが取り付けられて省力化軌道15が構成されている。バラスト軌道11は路盤(地盤)16上に設置され、省力化軌道15を除いたバラスト部11aは透水層を形成する。
枕木13を介して填充層12に複数本のボルト材17a、17b、17cが打設されており、また、枕木13、填充層12、透水層11aを貫通して地盤16に2本の孔あき鋼管(注入管)18が貫入され、注入口に防護蓋19が設置されている。孔あき鋼管18の周辺部の適所にはセメント系注入材を周囲の地中(地盤)16及びリフトアップにより生じる省力化軌道15と地盤16間の空隙部(図示せず)に注入材を注入するための孔18aが多数設けられている。ボルト材17a〜17cや孔あき鋼管18は予め取り付けておいてもよいし、あるいは地盤沈下修復に際して打設してもよい。
(A) Labor-saving track lift-up device FIG. 1 is a configuration diagram of a labor-saving track lift-up device according to the present invention.
In FIG. 1, a ballast portion about 50 cm above the ballast track 11 is consolidated with a cement injection material to form a filling layer 12, and a concrete sleeper 13 is embedded and fixed on the filling layer 12. The rails 14a and 14b are attached to the upper part to constitute a labor saving track 15. The ballast track 11 is installed on a roadbed (ground) 16, and the ballast portion 11a excluding the labor saving track 15 forms a water permeable layer.
A plurality of bolt members 17a, 17b, 17c are placed in the filling layer 12 through the sleepers 13, and two holes are formed in the ground 16 through the sleepers 13, the filling layer 12, and the water permeable layer 11a. A steel pipe (injection pipe) 18 is penetrated, and a protective lid 19 is installed at the injection port. Cement-based injecting material is injected into the surrounding area of the perforated steel pipe 18 into the surrounding underground (ground) 16 and the space (not shown) between the labor-saving track 15 and the ground 16 generated by lift-up. A large number of holes 18a are provided. The bolt members 17a to 17c and the perforated steel pipe 18 may be attached in advance, or may be placed when ground subsidence is repaired.

リフトアップ装置は省力化軌道15の両側それぞれ2箇所ずつに設置された支持部21a〜21b、該支持部により軌道上方において支持される反力用架台22、該反力用架台の適所に固定され、後述の引き上げ部を取り付けて牽引手段となるI型鋼23a〜23c、引き上げ用PC鋼材24a〜24c、I型鋼23a〜23cにそれぞれ取り付けられると共に、引き上げ用PC鋼材24a〜24cを介してボルト材17a〜17cと接続され、油圧により省力化軌道15を引き上げる引き上げ部25a〜25cを備えている。
各支持部21a、21bは、例えば耐力1000KN、質量75Kgのリフト用ジャッキ(キリンジャッキ)であり、反力用架台22は、仮設山留め材H鋼である。図2(A)、(B)の平面図、側面図に示すように反力用架台22は、省力化軌道の周囲4箇所に設置された支持部(リフト用ジャッキ)21a〜21b上にボルト止め(図示せず)により固定され、該反力用架台22の設置高さはリフト用ジャッキ21a〜21bにより調整可能となっている。牽引手段としてのI型鋼23a〜23cは、引き上げ部25a〜25cがボルト材17a〜17cの真上になるように反力用架台22上に万力固定される。引き上げ部25a〜25cは油圧センターホールジャッキであり、それぞれがボルト材17a〜17cの真上位置となるようにI型鋼23a〜23cに設置される。また、引き上げ部(油圧センターホールジャッキ)25a〜25cはそれぞれ引き上げ用PC鋼材24a〜24cを介してボルト材17a〜17cと接続され、かつ、個別に油圧ユニット(図示せず)に接続され、油圧により引き上げ力を発生する。なお、引き上げ用PC鋼材24a〜24cの一旦にはネジ部が形成され、該ネジ部により後述するナットを介してボルト材17a〜17cと接続される。
リフトアップ装置は通常設置されておらず、地盤沈下により省力化軌道をリフティングする際に省力化軌道周辺に設置される。
The lift-up device is fixed at appropriate positions of the support portions 21a to 21b installed at two positions on each side of the labor-saving track 15, the reaction force mount 22 supported above the track by the support portions, and the reaction force mount. These are attached to the I-shaped steels 23a to 23c, the lifting PC steel materials 24a to 24c, and the I-shaped steels 23a to 23c, which serve as traction means by attaching a lifting portion to be described later, and the bolt material 17a via the lifting PC steel materials 24a to 24c. To 17c, and includes lifting portions 25a to 25c for lifting the labor saving track 15 by hydraulic pressure.
Each of the support portions 21a and 21b is, for example, a lift jack (kirin jack) having a yield strength of 1000 KN and a mass of 75 Kg, and the reaction force mount 22 is a temporary mountain retaining material H steel. As shown in the plan view and side view of FIGS. 2 (A) and 2 (B), the reaction force mount 22 is bolted on support portions (lift jacks) 21a to 21b installed at four locations around the labor-saving track. It is fixed by a stopper (not shown), and the installation height of the reaction force base 22 can be adjusted by lift jacks 21a to 21b. The I-shaped steels 23a to 23c as traction means are vise fixed on the reaction force base 22 so that the lifting portions 25a to 25c are directly above the bolt members 17a to 17c. The lifting portions 25a to 25c are hydraulic center hole jacks, and are installed on the I-shaped steels 23a to 23c so as to be respectively located above the bolt members 17a to 17c. Further, the lifting portions (hydraulic center hole jacks) 25a to 25c are connected to bolt members 17a to 17c through the lifting PC steel materials 24a to 24c, respectively, and individually connected to a hydraulic unit (not shown), Generates a pulling force. In addition, a screw part is once formed in PC steel materials 24a-24c for raising, and it connects with bolt material 17a-17c through the nut mentioned later by this screw part.
The lift-up device is not normally installed, and is installed around the labor-saving track when lifting the labor-saving track due to ground subsidence.

(B)地盤修復工程
地盤沈下が許容沈下量を超えて地盤修復を行なうには、まず、ボルト材17a〜17cを打設する。なお、既にボルト材17a〜17cの打設がなされている場合にはこの工程は不要である。
ボルト材17a〜17cは例えばケミカルアンカーである。図3(A)に示すように、(1)ハンマードリルにより枕木13を介して填充層12の所定深さまで削孔し、(2)削孔後、削孔部にボルト材17a〜17cを打設すると共に、各アンカー材の手元側ボルト部に接続ナット17dを設置し、(3)打設後、ナット17dに防護蓋17eをはめ込む。図3(B)は詳細なボルト材の打設手順説明図であり、(1)枕木13を介して填充層12を削孔し、孔内を清掃し、(2)削孔・清掃後、削孔部に定着材カプセル
17fを挿入し、(3)カプセル挿入後、手元側にネジ部を有するボルト材17aを挿入すると共に、該ネジ部にナット17dをはめ込み、(4)最後に防護蓋17eを被せる。なお、省力化軌道のリフティングに際して、(5)各ボルト材17a〜17cの防護蓋17eを外し、引き上げ用PC鋼材24a〜24c(図1参照)を各ボルト材17a〜17cに設置してあるナット17dにねじ込んで、ボルト材17a〜17cと引き上げ部25a〜25c間をそれぞれ接続する。
(B) Ground repairing process In order to perform ground repairing when the ground settlement exceeds the allowable settlement, bolt materials 17a to 17c are first placed. Note that this step is not necessary when the bolt members 17a to 17c are already placed.
The bolt members 17a to 17c are, for example, chemical anchors. As shown in FIG. 3A, (1) a hole is drilled with a hammer drill to a predetermined depth of the filling layer 12 through the sleeper 13, and (2) after drilling, bolts 17a to 17c are driven into the drilled part. At the same time, a connecting nut 17d is installed on the proximal bolt portion of each anchor material. (3) After placing, a protective lid 17e is fitted into the nut 17d. FIG. 3 (B) is a detailed explanatory drawing of the bolt material placing procedure. (1) The filling layer 12 is drilled through the sleepers 13 and the inside of the hole is cleaned. (2) After drilling and cleaning, The fixing material capsule 17f is inserted into the drilling portion, (3) after the capsule is inserted, the bolt material 17a having a screw portion on the hand side is inserted, and the nut 17d is fitted into the screw portion, and (4) finally a protective cover 17e. When lifting the labor-saving track, (5) the protective lid 17e of each bolt member 17a to 17c is removed, and the PC steel members 24a to 24c for lifting (see FIG. 1) are installed on the bolt members 17a to 17c. The bolt members 17a to 17c and the lifting portions 25a to 25c are respectively connected by screwing into 17d.

ボルト材17a〜17cの打設が終了すれば、地盤沈下の修復工と同時に地盤沈下対策工(地盤補強工)を行なうために、図4に示すように孔あき鋼管18を枕木13および填充層12を貫通して地中16に打設する。孔あき鋼管18は、例えば注入管併用マイクロパイルであり、注入管併用マイクロパイルを打設するには、図5に示すように枕木13上に削孔機用鋼製架台31を設置し、その上に公知のマイクロパイル設置用削孔機32を載せ、(1)該マイクロパイル設置用削孔機32により枕木13、填充層12、透水層11aを貫通して地盤16まで削孔し、(2)削孔完了後、注入管併用マイクロパイル18を貫入し、その注入口に防護蓋19を設置する。なお、打設に際して、少なくも1つの孔18aが、省力化軌道をリフティングすることにより発生する空隙部(図示せず)に位置するように注入管併用マイクロパイル18を打設する必要がある。また、注入管併用マイクロパイル18の下方には後述する布袋(図示せず)が被せられている。
孔あき鋼管(注入管併用マイクロパイル)18の貫入が完了すれば、削孔機用鋼製架台31およびマイクロパイル設置用削孔機32を撤去し、リフトアップ装置をセットする。すなわち、図6に示すように、省力化軌道15の両側4箇所にそれぞれ支持部(リフト用ジャッキ)21a〜21bを設置し、該支持部に反力用架台22を載せてボルト止め固定し、架台を軌道上方に作成する。ついで、反力用架台22に牽引手段としてのI型鋼23a〜23cを反力用架台22上に万力固定し、しかる後、支持部(リフト用ジャッキ)21a〜21bにより反力用架台22の設置高さを調整する。
When the installation of the bolt members 17a to 17c is completed, in order to perform ground subsidence countermeasure work (ground reinforcement work) simultaneously with ground subsidence repair work, as shown in FIG. 12 is pierced through the underground 16. The perforated steel pipe 18 is, for example, an injection pipe combined micropile, and in order to place the injection pipe combined micropile, as shown in FIG. A well-known micropile installation drilling machine 32 is placed on top, and (1) the micropile installation drilling machine 32 penetrates through the sleepers 13, the filling layer 12, and the water permeable layer 11a to the ground 16; 2) After completion of drilling, the micropile 18 combined with an injection tube is inserted, and a protective lid 19 is installed at the injection port. When placing, the injection pipe combined micropile 18 needs to be placed so that at least one hole 18a is located in a gap (not shown) generated by lifting the labor-saving track. Further, a cloth bag (not shown), which will be described later, is placed under the injection pipe combined micropile 18.
When the penetration of the perforated steel pipe (micropile combined with the injection pipe) 18 is completed, the steel mount 31 for drilling machine and the drilling machine 32 for installing micropile are removed, and the lift-up device is set. That is, as shown in FIG. 6, support portions (lift jacks) 21 a to 21 b are installed at four locations on both sides of the labor-saving track 15, and a reaction force base 22 is placed on the support portions and fixed with bolts. Create the platform above the track. Subsequently, I-shaped steels 23a to 23c as traction means are fixed to the reaction force gantry 22 on the reaction force gantry 22, and then the reaction force gantry 22 is supported by the support portions (lift jacks) 21a to 21b. Adjust the installation height.

設置高さの調整が完了すれば、ボルト材17a〜17cの防護蓋17eを外し、引き上げ用PC鋼材24a〜24cの先端ネジ部をナット17dにねじ込んでボルト材17a〜17cと接続する。ついで、ボルト材17a〜17cの真上位置において、各油圧センターホールジャッキ25a〜25cをI型鋼23a〜23cに万力固定すると共に、引き上げ用PC鋼材24a〜24cの他端をセンターホールジャッキ25a〜25cに設置する。また、各油圧センターホールジャッキ25a〜25cを個別に油圧ユニット(図示せず)に接続する。
以上により、リフトアップ装置のセットが完了し、図1に示す状態になる。
かかる状態において、油圧ユニットより引き上げ部である油圧センターホールジャッキ25a〜25cに省力化軌道の引き上げ力を発生すると、該引き上げ力の反力が反力用架台22を介して支持部21a、21bに受け止められて、図7に示すように省力化軌道15が引き上がり、該省力化軌道15の底盤部と地盤間に空隙部20が発生する。
When the adjustment of the installation height is completed, the protective lid 17e of the bolt members 17a to 17c is removed, and the tip screw portions of the lifting PC steel materials 24a to 24c are screwed into the nut 17d and connected to the bolt members 17a to 17c. Next, at the position directly above the bolt members 17a to 17c, the hydraulic center hole jacks 25a to 25c are visely fixed to the I-shaped steels 23a to 23c, and the other ends of the lifting PC steel materials 24a to 24c are connected to the center hole jacks 25a to 25c. 25c. Moreover, each hydraulic center hole jack 25a-25c is individually connected to a hydraulic unit (not shown).
With the above, the setting of the lift-up device is completed, and the state shown in FIG. 1 is obtained.
In this state, when the lifting force of the labor-saving track is generated from the hydraulic unit to the hydraulic center hole jacks 25a to 25c which are the lifting portions, the reaction force of the lifting force is applied to the support portions 21a and 21b via the reaction force base 22. As shown in FIG. 7, the labor-saving track 15 is pulled up, and a gap 20 is generated between the bottom plate portion and the ground of the labor-saving track 15.

ついで、一端が注入プラント(図示せず)に接続された注入パイプ41を、図8の(1)に示すように、注入管併用マイクロパイル18にスキングラウト用高圧パッカー42が空隙部20辺りに位置するまで挿入し、該パッカー42に水圧3Mpを加えて加圧膨張する。図9は図8のA部分の拡大図であり、43は注入管併用マイクロパイル18を被覆する布製パッカー43である。
(2)かかる状態で、セメントミルク(地盤改良用グラウト)を注入パイプ41より注入する。注入されたセメントミルクは注入管併用マイクロパイル18に形成された多数の孔18aから吐き出される。この結果、注入管併用マイクロパイル18を被覆する布製パッカー43が吐き出されたセメントミルクにより周辺地盤16及び透水層11aにおいて加圧膨張し、地盤を強化改良する。なお、注入管併用マイクロパイル18の内部もセメントミルクで満たされる。
布製パッカー43により、透水層11aへのセメントミルク(地盤改良用グラウト)の逸走が防止されて限定的な地盤改良を図ることが可能となり、より確実な地盤補強効果を得ることができる。しかし、布製パッカー43は必須ではない。布製パッカー43がない場合には、セメントミルクが直接注入管併用マイクロパイル18の周辺地盤16及び透水層11aに注入されてゆき地盤を強化改良する。
Next, an injection pipe 41 having one end connected to an injection plant (not shown) is connected to a micropile 18 combined with an injection pipe and a high pressure packer 42 for sking trout around the gap 20 as shown in FIG. It is inserted until it is positioned, and a pressure of 3 Mp is applied to the packer 42 to expand it under pressure. FIG. 9 is an enlarged view of a portion A in FIG. 8, and 43 is a cloth packer 43 that covers the micropile 18 combined with an injection tube.
(2) In this state, cement milk (ground improvement grout) is injected from the injection pipe 41. The injected cement milk is discharged from a large number of holes 18a formed in the injection pipe combined micropile 18. As a result, the fabric packer 43 covering the micropile 18 combined with the injection tube is pressurized and expanded in the surrounding ground 16 and the water permeable layer 11a by the discharged cement milk, thereby strengthening and improving the ground. In addition, the inside of the injection pipe combined micropile 18 is also filled with cement milk.
By the cloth packer 43, the escape of cement milk (grouting for ground improvement) to the water permeable layer 11a is prevented, so that limited ground improvement can be achieved, and a more reliable ground reinforcement effect can be obtained. However, the cloth packer 43 is not essential. When there is no cloth packer 43, cement milk is directly injected into the surrounding ground 16 and the water permeable layer 11a of the micropile 18 combined with the injection pipe to strengthen and improve the ground.

周辺地盤へのセメントミルクの注入が完了すれば、パッカー42を収縮させ、該パッカー42が填充部12の中間部辺りに位置するまで引き上げ、ついで、該パッカー42に水圧3Mpを加えて加圧膨張する。この状態で、セメントミルクを注入パイプ41より注入する。注入されたセメントミルクは、注入管併用マイクロパイル18に形成された孔18aから省力化軌道15の底盤部と地盤間に生成された空隙部20に注入され、図10に示すように該空隙部20を充填する。しかる後、パッカー42を口元まで引き上げて注入管併用マイクロパイル18の内部をセメントミルクで満たし、注入装置やリフトアップ装置を撤去すれば、省力化軌道下の地盤修復と地盤補強が完了する。図11は省力化軌道下の地盤修復と地盤補強完了後の断面図である。   When the injection of the cement milk to the surrounding ground is completed, the packer 42 is contracted and pulled up until the packer 42 is positioned around the middle part of the filling part 12, and then the water pressure 3Mp is applied to the packer 42 and pressurized expansion is performed. To do. In this state, cement milk is injected from the injection pipe 41. The injected cement milk is injected from the hole 18a formed in the injection pipe combined micropile 18 into the gap 20 generated between the bottom and the ground of the labor-saving track 15, and as shown in FIG. 20 is filled. After that, if the packer 42 is pulled up to the mouth, the inside of the micropile 18 combined with the injection tube is filled with cement milk, and the injection device and the lift-up device are removed, the ground restoration under the labor saving orbit and the ground reinforcement are completed. FIG. 11 is a cross-sectional view after the ground restoration under the labor saving orbit and the ground reinforcement completed.

以上のように、本発明によれば、リフトアップ装置により省力化軌道を引き上げるようにしているため、掘削作業やバラストの埋め戻し作業が不要となる。また、省力化軌道をリフトアップしてレール高さを効率的に調整することができる。さらに、地盤沈下の修復工と同時に基本的な地盤沈下対策工(地盤補強工)を行なうことができる。
以上の説明では、孔あき鋼管の外側を布製パッカーで覆った場合について説明したが、布製パッカーは必ずしも必要ではない。
また、以上の説明では、バラスト軌道の上部50cm程度のバラストをセメント注入材で固結して填充層とした軌道を省力化軌道として説明したが、省力化軌道は、かかる構成に限らない。例えば、幅は実施例と同等で、全深さのバラストをセメント注入材で固結して填充層とする省力化軌道のリフトアップにも本発明は適用可能である。
As described above, according to the present invention, since the labor-saving track is pulled up by the lift-up device, excavation work and ballast backfilling work become unnecessary. Further, the rail height can be adjusted efficiently by lifting the labor-saving track. Furthermore, basic ground subsidence countermeasure work (ground reinforcement work) can be performed simultaneously with ground subsidence repair work.
In the above description, the case where the outer side of the perforated steel pipe is covered with the cloth packer has been described, but the cloth packer is not necessarily required.
Further, in the above description, the trajectory in which the ballast about 50 cm above the ballast trajectory is solidified with a cement injection material as a filling layer is described as a labor-saving trajectory, but the labor-saving trajectory is not limited to such a configuration. For example, the width is the same as in the embodiment, and the present invention can be applied to lift-up of a labor-saving track in which a ballast of the entire depth is consolidated with a cement injection material to form a filling layer.

11 バラスト軌道
12 填充層
13 枕木
14a、14b レール
15 省力化軌道
16 路盤(地盤)
17a、17b、17c ボルト材
18 孔あき鋼管
20 空隙部
21a〜21b 支持部(リフト用ジャッキ)
22 反力用架台
23a〜23c I型鋼
24a〜24c 引き上げ用PC鋼材
25a〜25c 引き上げ部(センターホールジャッキ)
11 Ballast track 12 Filling layer 13 Sleepers 14a, 14b Rail 15 Labor-saving track 16 Roadbed (ground)
17a, 17b, 17c Bolt material 18 Perforated steel pipe 20 Gap part 21a-21b Support part (lift jack)
22 Reaction Force Bases 23a-23c I-Shaped Steels 24a-24c PC Steel Materials 25a-25c for Lifting Lifting Center (Center Hole Jack)

Claims (2)

地盤上に形成された填充層を備え、該填充層に設けられた枕木によりレールを支持する省力化軌道のリフトアップ装置において、
省力化軌道の両側にそれぞれ設置される複数の支持部、
該支持部により軌道上方において支持される反力用架台、
該反力用架台に取り付けられると共に、前記省力化軌道の前記填充層に打設された複数本のボルト材とそれぞれ連結されて該省力化軌道を引き上げる引き上げ部、
を有し、前記引き上げ部に引き上げ力を発生し、該引き上げ力の反力を、前記反力用架台を介して前記支持部で受け止めて前記省力化軌道を引き上げる、
ことを特徴とする省力化軌道のリフトアップ装置。
In a lift-up device for a labor-saving track comprising a filling layer formed on the ground, and supporting a rail by a sleeper provided in the filling layer,
A plurality of support portions installed on both sides of the labor-saving track,
A reaction force support supported above the track by the support,
A lifting portion that is attached to the reaction force gantry and is connected to each of a plurality of bolt members placed on the filling layer of the labor-saving track to raise the labor-saving track,
A pulling force is generated in the pulling portion, and the reaction force of the pulling force is received by the support portion via the reaction force mount to pull up the labor-saving track.
Labor-saving track lift-up device.
地盤上に形成された填充層を備え、該填充層に設けられた枕木によりレールを支持する省力化軌道のリフトアップ方法において、
枕木を介して前記填充層に複数本のボルト材を打設し、
省力化軌道の両側にそれぞれ複数の支持部を設置し、
該支持部により軌道上方において反力用架台を支持し、
前記反力用架台に前記各ボルト材と連結されて省力化軌道を引き上げる引き上げ部を取り付け、
前記引き上げ部に引き上げ力を発生し、
該引き上げ力の反力を、前記反力用架台を介して前記支持部で受け止めて前記省力化軌道を引き上げる、
ことを特徴とする省力化軌道のリフトアップ方法。
In a lift-up method of a labor-saving track comprising a filling layer formed on the ground, and supporting rails by sleepers provided in the filling layer,
Placing a plurality of bolt materials on the filling layer through sleepers,
Install multiple supports on both sides of the labor-saving track,
Supporting the reaction force gantry above the track by the support,
Attach a lifting part that is connected to each bolt material to raise the labor-saving orbit to the reaction force mount,
A pulling force is generated in the pulling portion;
The reaction force of the lifting force is received by the support portion via the reaction force mount, and the labor-saving track is lifted.
A lift-up method for a labor-saving orbit characterized by that.
JP2010174180A 2010-08-03 2010-08-03 Labor-saving track lift-up device and lift-up method Expired - Fee Related JP5472878B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010174180A JP5472878B2 (en) 2010-08-03 2010-08-03 Labor-saving track lift-up device and lift-up method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010174180A JP5472878B2 (en) 2010-08-03 2010-08-03 Labor-saving track lift-up device and lift-up method

Publications (2)

Publication Number Publication Date
JP2012031698A JP2012031698A (en) 2012-02-16
JP5472878B2 true JP5472878B2 (en) 2014-04-16

Family

ID=45845413

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010174180A Expired - Fee Related JP5472878B2 (en) 2010-08-03 2010-08-03 Labor-saving track lift-up device and lift-up method

Country Status (1)

Country Link
JP (1) JP5472878B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101886657B1 (en) * 2017-10-18 2018-08-09 박문신 Stand frame for manufacturing pre-flexed beams using earth pressure and pre-flexed beam manufactured therewith
KR102187297B1 (en) * 2018-04-27 2020-12-04 콘비젼스 주식회사 Guide Rail Rubber Wheel AGT Separable Driving Road Construction Jig and Method for constructing AGT Separable Main Road using this same
KR102319784B1 (en) * 2020-04-10 2021-11-01 로드캐스트 주식회사 Traffic Control Reduction Rapid Packaging Method Due to Ground Deposition on Roads

Also Published As

Publication number Publication date
JP2012031698A (en) 2012-02-16

Similar Documents

Publication Publication Date Title
JP5554176B2 (en) Method for reinforcing bearing capacity of track
US20220380996A1 (en) Methods for constructing tensionless concrete pier foundations and foundations constructed thereby
KR20130085353A (en) Construction method for retaining wall and construction apparatus for thereof and retaining wall structure
KR101283672B1 (en) Non open cut method using the lifting device
JP5472878B2 (en) Labor-saving track lift-up device and lift-up method
CN105926637B (en) Prestress supporting system for protecting existing subway and design
CN101929159B (en) Protective method of pipelines in natural gas pipeline full-section excavation construction
JP2013044126A (en) Track deviation repair method for track
CN112878358A (en) Existing retaining wall reinforcing construction method and reinforcing structure thereof
CN108755701A (en) The construction method of the support construction of deep basal pit
CN104452775B (en) Pre-loaded support struts and construction method for foundation ditch
EP3124705A1 (en) Formers
KR100963880B1 (en) Excavating method for underground plaza using steel casing retaining wall
CN1361333A (en) Tracing compensation and grouting process to control formation displacement
KR101297679B1 (en) Self-supporting Temporary Structure Using Steel Wire And Method Of The Same
JP5504951B2 (en) Seismic reinforcement method for structures and seismic reinforcement structure for structures
US10138626B1 (en) Method and apparatus for repairing a tilt wall construction
JP2005201038A (en) Ground improvement method
JP2005201038A5 (en)
KR101184444B1 (en) Column reinforcing method using load trans apparatus and micro-pile
CN110029653A (en) A kind of treatment method of steel pipe pile foundation for riprap seabed foundation
CN108457200B (en) Temporary support structure and construction method for pile foundation underpinning in curved bridge section
CN113266019A (en) Construction method of foundation pit steel pipe support system
CN207513221U (en) A kind of structure of post-tensioned prestressing foundation stabilization
JP6792239B2 (en) Scuttling prevention device for steel pipe piles and scuttling prevention method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130718

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140117

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140128

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140128

R150 Certificate of patent or registration of utility model

Ref document number: 5472878

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140313

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees