Track repair method Download PDF

Info

Publication number
JP6175337B2
JP6175337B2 JP2013204253A JP2013204253A JP6175337B2 JP 6175337 B2 JP6175337 B2 JP 6175337B2 JP 2013204253 A JP2013204253 A JP 2013204253A JP 2013204253 A JP2013204253 A JP 2013204253A JP 6175337 B2 JP6175337 B2 JP 6175337B2
Authority
JP
Japan
Prior art keywords
ballast
repair
repair material
track
sleeper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2013204253A
Other languages
Japanese (ja)
Other versions
JP2015068090A (en
Inventor
勝己 村本
勝己 村本
貴久 中村
貴久 中村
隆人 咲村
隆人 咲村
恵一 黒坂
恵一 黒坂
哲史 山名
哲史 山名
松岡 敏文
敏文 松岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Railway Technical Research Institute
Kunimine Industries Co Ltd
Japan Vam and Poval Co Ltd
Original Assignee
Railway Technical Research Institute
Kunimine Industries Co Ltd
Japan Vam and Poval Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Railway Technical Research Institute, Kunimine Industries Co Ltd, Japan Vam and Poval Co Ltd filed Critical Railway Technical Research Institute
Priority to JP2013204253A priority Critical patent/JP6175337B2/en
Publication of JP2015068090A publication Critical patent/JP2015068090A/en
Application granted granted Critical
Publication of JP6175337B2 publication Critical patent/JP6175337B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Description

本発明は、まくらぎがバラスト上に敷設されるバラスト軌道の軌道補修方法に関し、バラストが劣化しているバラスト軌道の軌道補修方法に関する。   The present invention relates to a track repair method for a ballast track in which a sleeper is laid on the ballast, and to a track repair method for a ballast track in which the ballast has deteriorated.

図10(a)に示すように、バラスト1上に敷設されたまくらぎ2にレール3を締結したバラスト軌道においては、レール3の継ぎ目等の近辺で荷重変動が生じ、レール3及びまくらぎ2を支持するバラスト1に局所的な沈下が生ずることがある。なお、図10(a)に示す一点鎖線hは、列車荷重が作用しない場合の所定のレールレベルである。例えば、軌道の局所的沈下が生じやすいレール継目部Aで、バラスト1の沈下が発生した場合、列車が通過した後のレール3の弾性回復により、図10(b)に示すように、レール3に締結されているまくらぎ2が持ち上げられて、まくらぎ2とバラスト1との間に空隙Xが生じる、いわゆる「浮まくらぎ」の状態になってしまう。「浮まくらぎ」は、軌道を支持する剛性(以下、軌道支持剛性という。)が低下した状態であり、列車の乗り心地が悪くなると共に、列車に動揺を与えて安全走行の妨げになる。   As shown in FIG. 10A, in the ballast track in which the rail 3 is fastened to the sleeper 2 laid on the ballast 1, load fluctuation occurs in the vicinity of the joint of the rail 3, and the rail 3 and the sleeper 2. There is a case where local settlement occurs in the ballast 1 supporting In addition, the dashed-dotted line h shown to Fig.10 (a) is a predetermined rail level when a train load does not act. For example, when the ballast 1 is sunk in the rail joint A where the track is likely to be locally sunk, the rail 3 is elastically restored after the train passes, as shown in FIG. As a result, the sleeper 2 fastened to the lifter 2 is lifted, and a gap X is generated between the sleeper 2 and the ballast 1. “Float sleeper” is a state in which the rigidity for supporting the track (hereinafter referred to as the track support rigidity) is lowered, and the ride comfort of the train is deteriorated, and the train is shaken and hinders safe driving.

この「浮きまくらぎ」の補修には、通常、図11に示すように、タイタンパー10のような保線用の専用の機器を用いてバラスト1をまくらぎ2下につき固める軌道補修が行われている。タイタンパー10による軌道補修は、図11(a)に示すように、タイタンパー用つき固めツール(以下、単にツールと称す)20と称されるヘラ状部材をバラスト1に射し込み、タイタンパー10の起振部30で発生した振動をツール20からバラスト1に伝達しながら、図11(b)に示すように、まくらぎ2下にバラスト1を掻き寄せてつき固める。このため、列車荷重によって締め固まっていたバラスト1を若干緩めてしまうという問題点もあるが、粒径が揃った単粒度である健全なバラスト1の場合には、軌道補修前後の密度変化が小さいため、軌道補修後の軌道沈下が生じにくく、タイタンパー10による軌道補修が効果的に作用する。   In order to repair the “floating sleeper”, as shown in FIG. 11, a track repair is usually performed in which the ballast 1 is fixed to the lower part of the sleeper 2 by using a dedicated wire retaining device such as a tie tamper 10. Yes. As shown in FIG. 11A, the track repair by the tie tamper 10 is performed by injecting a spatula-like member called a tie tamper tightening tool (hereinafter simply referred to as a tool) 20 into the ballast 1. While transmitting the vibration generated in the vibration generating unit 30 from the tool 20 to the ballast 1, as shown in FIG. 11B, the ballast 1 is scraped down and solidified. For this reason, there is a problem that the ballast 1 that has been compacted by the train load is slightly loosened, but in the case of a healthy ballast 1 that is a single grain size with a uniform particle size, the density change before and after the track repair is small. Therefore, track settlement after track repair hardly occurs, and track repair by the tie tamper 10 acts effectively.

これに対し、劣化しているバラスト1、すなわち、使用しているうちに破砕や摩耗が進行したり、外部から土砂が混入したりして、粒径が小さくなり、粒径分布も広くなったバラスト1の場合には、タイタンパー10の軌道補修によって軌道補修前後の密度変化が大きくなり、列車荷重によって締め固められていたバラスト1の密度が著しく低下するため、軌道補修後に軌道沈下が再発してしまう。また、劣化しているバラスト1は、滞水時の強度低下が著しく、滞水時には、軌道沈下がさらに増大しやすいという性質も有しており、バラスト1が劣化しているバラスト軌道には、タイタンパー10を用いてまくらぎ下の道床を緩めることなく、まくらぎ2下面の空隙Xに何らかの材料を充填する軌道補修方法が望ましいとされていた。   On the other hand, the deteriorated ballast 1, that is, crushing and abrasion progressed during use, or earth and sand were mixed from the outside, the particle size became smaller and the particle size distribution became wider. In the case of ballast 1, since the density change before and after the track repair is increased by the track repair of the tie tamper 10 and the density of the ballast 1 that has been compacted by the train load is significantly reduced, the track settlement recurs after the track repair. End up. In addition, the deteriorated ballast 1 has a property that the strength is significantly reduced when the water is stagnant and the subsidence of the orbit is more likely to increase when the water is stagnant. It has been considered desirable to have a track repairing method in which a material is filled in the gap X on the lower surface of the sleeper 2 without using the tie tamper 10 to loosen the roadbed under the sleeper.

そこで、本出願人は、締め固められた道床を緩めずに行う軌道補修として、軌道補修箇所のまくらぎ2下の空隙Xに空圧で充填した粒状充填材(粒状体、ケイ酸ソーダ)と、ポリマー水溶液とを接触させる技術を提案している(例えば、特許文献1参照)。まくらぎ2下の空隙で粒状充填材とポリマー水溶液とが接触すると、ケイ酸ソーダとポリマーの複合ゲルが生成されて粒状体と絡み合い、高いまくらぎ支持強度を得ることができると共に、耐水性を発揮する。   Therefore, the present applicant, as a track repair to be performed without loosening the compacted road bed, a granular filler (granular body, sodium silicate) filled with air pressure in the gap X under the sleeper 2 of the track repair location, Have proposed a technique of bringing a polymer aqueous solution into contact with the polymer aqueous solution (for example, see Patent Document 1). When the granular filler and the aqueous polymer solution come into contact with each other in the gap below the sleeper 2, a composite gel of sodium silicate and polymer is generated and entangled with the granular material, so that high sleeper support strength can be obtained and water resistance can be improved. Demonstrate.

特開2009−167687号公報JP 2009-167687 A

しかしながら、特許文献1の技術では、粒状充填材を空圧によって充填しているため、まくらぎ2下の空隙Xに充填した粒状充填材の充填密度が上がらず、初期沈下が生じやすいと共に、健全なバラストの軌道補修作業では使用しないコンプレッサーやエアガン等の空圧機器が別途必要となるという問題点があった。また、粒状充填材とポリマー水溶液との混合は、列車の繰り返し荷重によってまくらぎ2下で行われ、作業員が混合状態を確認することができないため、ゲル化が不十分となり、軌道補修材の性能が十分に発揮されない場合がある。   However, in the technique of Patent Document 1, since the granular filler is filled by air pressure, the packing density of the granular filler filled in the gap X under the sleeper 2 does not increase, and initial subsidence easily occurs and is sound. There is a problem in that pneumatic equipment such as a compressor and an air gun which are not used in track repair work for a ballast is required separately. In addition, the mixing of the granular filler and the aqueous polymer solution is performed under the sleeper 2 due to the repeated load of the train, and the worker cannot check the mixed state. Performance may not be fully demonstrated.

本発明は、このような状況に鑑みてなされたものであり、上述の課題を解消し、特別な機器を用いることなく、バラストが劣化しているバラスト軌道の軌道補修を効果的に行うことができる軌道補修方法を提供することを目的とする。   The present invention has been made in view of such a situation, and can solve the above-described problems and effectively perform track repair of a ballast track in which the ballast has deteriorated without using special equipment. It aims at providing the track repair method which can be done.

本発明の軌道補修方法は、バラスト上に敷設されたまくらぎの脇に補修材を投入する補修材投入口を形成させた後、前記補修材投入口に前記補修材としてポリマー水溶液と当該ポリマー水溶液をゲル化させる反応材とをそれぞれ投入して、タイタンパーを用いて前記まくらぎ下につき込むことで、ゲル化した前記ポリマーによって既設の前記バラストを内包する固結体を前記まくらぎ下に形成させることを特徴とする
らに、本発明の軌道補修方法において、前記補修材を投入した前記補修材投入口に前
記バラストを補充するバラスト補充工程を有し、補充された前記バラストと前記補修材と
を前記まくらぎ下につき込むようにしても良い。
さらに、本発明の軌道補修方法において、前記タイタンパーには、先端部がくし歯状に
形成されたタイタンパー用つき固めツールが装着されていても良い。
さらに、本発明の軌道補修方法において、前記ポリマー水溶液は、生分解性高分子材を
主剤としても良い。
さらに、本発明の軌道補修方法において、前記反応材は、珪酸ナトリウム、塩化ナトリ
ウム、水酸化ナトリウム、水酸化リチウム、炭酸ナトリウム、炭酸カリウム、硫酸アルミ
ニウム、硫酸ナトリウム、シリカゲル、ベントナイト、吸水性ポリマーのいずれかを含ん
でいても良い
According to the track repair method of the present invention, a repair material input port for supplying a repair material is formed on the side of a sleeper laid on a ballast, and then a polymer aqueous solution and the polymer aqueous solution are used as the repair material in the repair material input port. Each of the reaction materials to be gelled is charged, and a tie tamper is used to fit under the sleeper, so that a solidified body containing the existing ballast is formed under the sleeper by the gelled polymer. It is characterized by that .
Et al is in orbit repair method of the present invention, said said repair material to have a ballast replenishing step of replenishing the ballast to the repair material inlet which supplied the repair material and supplemented the ballast sleepers You may make it go down.
Furthermore, in the track repair method of the present invention, the tie tamper may be provided with a tie tamper tightening tool having a tip portion formed in a comb-tooth shape.
Furthermore, in the track repairing method of the present invention, the polymer aqueous solution may be mainly composed of a biodegradable polymer material.
Furthermore, in the track repair method of the present invention, the reaction material is any of sodium silicate, sodium chloride, sodium hydroxide, lithium hydroxide, sodium carbonate, potassium carbonate, aluminum sulfate, sodium sulfate, silica gel, bentonite, and a water-absorbing polymer. May contain

本発明によれば、ポリマー水溶液と反応材とを混合させた補修材を形成した補修材投入口に投入してまくらぎ下につき固めれば良いため、空圧機器等の特別な機器を用いることなく、バラストが劣化しているバラスト軌道の軌道補修を効果的に行うことができる。また、ポリマー水溶液と反応材との混合状態を作業員が確認することができるため、まくらぎ下につき込んだ補修材を十分にゲル化させることができ、補修材の性能を十分に発揮させることができる。   According to the present invention, a special device such as a pneumatic device may be used because it may be set in a repair material inlet formed with a repair material in which a polymer aqueous solution and a reaction material are mixed and hardened under the sleeper. In addition, it is possible to effectively repair the ballast track whose ballast has deteriorated. In addition, since the worker can check the mixed state of the polymer aqueous solution and the reaction material, the repair material caught under the sleeper can be sufficiently gelled, and the performance of the repair material can be fully demonstrated. Can do.

本発明に係る軌道補修方法の実施の形態の工程を説明するフローチャートである。It is a flowchart explaining the process of embodiment of the track repair method which concerns on this invention. 本発明に係る軌道補修方法の実施の形態の工程を説明するための断面図である。It is sectional drawing for demonstrating the process of embodiment of the track repair method which concerns on this invention. タイタンパーに取り付けられるツールの構成例を示す図である。It is a figure which shows the structural example of the tool attached to a tie tamper. 図3に示すツールの先端形状例を示す正面図である。FIG. 4 is a front view showing an example of a tip shape of the tool shown in FIG. 3. 図3に示すツールの基部に対する先端部の曲げ角の設定条件を説明するための説明図である。It is explanatory drawing for demonstrating the setting conditions of the bending angle of the front-end | tip part with respect to the base of the tool shown in FIG. 本発明に係る軌道補修方法の実施の形態の工程を説明するための断面図である。It is sectional drawing for demonstrating the process of embodiment of the track repair method which concerns on this invention. 本発明に係る軌道補修方法の他の実施の形態の手順を説明するフローチャートである。It is a flowchart explaining the procedure of other embodiment of the track repair method which concerns on this invention. 図1に示す補修材生成工程で用いる反応材の検討結果を示す表である。It is a table | surface which shows the examination result of the reactive material used at the repair material production | generation process shown in FIG. 本発明に係る軌道補修方法の実施の形態の効果を検証するための実物大模型試験を説明するための図である。It is a figure for demonstrating the full-scale model test for verifying the effect of embodiment of the track repair method which concerns on this invention. 浮まくらぎの状態を説明する断面図である。It is sectional drawing explaining the state of a floating sleeper. タイタンパーを用いた軌道補修例を説明する断面図である。It is sectional drawing explaining the track | orbit repair example using a tie tamper.

次に、本発明の実施の形態を、図面を参照して具体的に説明する。
本実施の形態の軌道補修方法は、図1を参照すると、まず、投入口形成工程として、図2(a)に示すように、まくらぎ2の脇のバラスト1に補修材投入口4を形成する(ステップ101)。図2(a)には、まくらぎ2の長手方向側面に沿って補修材投入口4を形成した例が示されているが、補修材投入口4は、必ずしもまくらぎ2に接して形成しなくても良く、まくらぎ2から少し離れた位置に形成するようにしても良い。
Next, embodiments of the present invention will be specifically described with reference to the drawings.
In the track repairing method of the present embodiment, referring to FIG. 1, first, as shown in FIG. 2A, a repairing material input port 4 is formed in the ballast 1 on the side of the sleeper 2 as an input port forming step. (Step 101). FIG. 2A shows an example in which the repair material inlet 4 is formed along the longitudinal side surface of the sleeper 2, but the repair material inlet 4 is not necessarily formed in contact with the sleeper 2. It may not be necessary, and may be formed at a position slightly away from the sleeper 2.

次に、タイタンパーセット工程として、タイタンパー10のツール40を、図2(b)に示すように、補修材投入口4にセットする(ステップ102)。補修材投入口4にセットするツール40は、図3(a)に示すヘラ状の通常のツール20ではなく、図3(b)に示す異形のものを用いると好適である。   Next, as a tie tamper setting step, the tool 40 of the tie tamper 10 is set in the repair material charging port 4 as shown in FIG. 2B (step 102). As the tool 40 set in the repairing material input port 4, it is preferable to use a deformed tool shown in FIG. 3B instead of the spatula-shaped normal tool 20 shown in FIG.

通常のツール20は、図3(a)に示すように、タイタンパー10に固定される基部22から先端部21にかけて1箇所以上の曲げ部23が形成されているヘラ状部材であり、基部22の幅と、先端部21の幅とは略同一に形成されている。   As shown in FIG. 3A, the normal tool 20 is a spatula-like member in which one or more bent portions 23 are formed from the base portion 22 fixed to the tie tamper 10 to the distal end portion 21. And the width of the tip 21 are formed substantially the same.

これに対して、図3(b)に示す異形のツール40は、バラスト1に挿し込まれる先端部41が、拡幅して複数本に分岐されているくし歯状であり、タイタンパー10に固定される基部42の幅よりも先端部41の全幅Wが大きく広がっている。先端部41の最先端の全幅Wは、バラスト1の最大粒径の3倍以上であり、先端部41における歯の隙間の最大幅Lは、バラスト最大粒径の略半分に形成されている。なお、本実施の形態で用いるツール40は、バラスト1の最大粒径が60mmであることを想定しており、図3(b)に示すように、先端部41の全幅Wが、基部42の幅(100mm)よりも2倍広く、且つバラスト1の最大粒径60mmの3倍以上である200mmに形成されている。そして、ツール40の先端部41におけるくし歯の間隔隙間の最大幅Lがバラスト1の最大粒径60mmの半分である30mmに形成されている。このように、先端部41の歯の隙間の最大幅Lをバラスト1の最大粒径の略半分に形成することで、先端部41の全幅Wを広くしてもバラスト1に容易に射し込むことができ、且つ先端部41の歯の隙間をバラスト1が通り抜けることがない。そして、先端部41の全幅Wを広く形成することで、使用による破砕や摩耗の進行等に起因して粒径が小さいバラスト1を効果的につき固めることが可能になる。   On the other hand, the deformed tool 40 shown in FIG. 3B has a comb-like shape in which the tip 41 inserted into the ballast 1 is widened and branched into a plurality of pieces, and is fixed to the tie tamper 10. The entire width W of the distal end portion 41 is larger than the width of the base portion 42 to be formed. The leading edge full width W of the tip portion 41 is at least three times the maximum particle size of the ballast 1, and the maximum width L of the tooth gap at the tip portion 41 is formed to be approximately half of the maximum ballast particle size. Note that the tool 40 used in the present embodiment assumes that the maximum particle size of the ballast 1 is 60 mm, and as shown in FIG. It is formed to be 200 mm, which is twice as wide as the width (100 mm) and more than three times the maximum particle size 60 mm of the ballast 1. Further, the maximum width L of the inter-gap spacing gap at the tip portion 41 of the tool 40 is 30 mm, which is half of the maximum particle size 60 mm of the ballast 1. In this way, by forming the maximum width L of the tooth gap of the tip portion 41 to approximately half of the maximum particle size of the ballast 1, it is possible to easily shoot into the ballast 1 even if the total width W of the tip portion 41 is widened. The ballast 1 does not pass through the gap between the teeth of the tip 41. Further, by forming the full width W of the tip portion 41, it becomes possible to effectively harden the ballast 1 having a small particle diameter due to crushing due to use, progress of wear, or the like.

なお、本実施の形態では、歯の先端をフラット、すなわち挿し込む方向に対して直交する直線状に構成したが、歯の先端形状は、バラスト1への挿し込みを容易に行える形状を適宜採用することもできる。例えば、図4(a)、(b)に示すように、挿し込む方向に対して傾斜した直線状に形成したり、図4(c)に示すように、曲線状に形成したりしても良い。   In the present embodiment, the tip of the tooth is flat, that is, configured to be a straight line orthogonal to the insertion direction, but the shape of the tip of the tooth is appropriately adopted as a shape that can be easily inserted into the ballast 1. You can also For example, as shown in FIGS. 4 (a) and 4 (b), it may be formed in a straight line inclined with respect to the inserting direction, or may be formed in a curved line as shown in FIG. 4 (c). good.

また、ツール40には、タイタンパー10に固定される基部42から先端部41にかけて、間隔をおいて2箇所の曲げ部43が形成され、曲げ部43の曲げ角は、先端に行くほど大きくなるように形成されている。そして、基部42に対する先端部41の曲げ角は、45°以上に形成されている。これにより、接続部44と、先端部41とで凹領域Aが形成される。なお、曲げ部43の代わりに、接続部44や先端部41を曲面で構成するようにしても良い。本実施の形態では、図3(b)に示すように、2箇所の曲げ部43が形成されており、基部42と、基部42と先端部41とを接続する接続部44との曲げ角(17°)よりも、接続部44と先端部41との曲げ角(28°)が大きくなるように形成され、基部42に対する先端部41の曲げ角が45°に形成されている。そして、基部42を鉛直に支持した状態での先端部41の鉛直方向の長さは、100mm程度の薄い道床厚のバラスト1への挿し込みを想定して、100mmに形成され、接続部44までの鉛直長さは、200mm程度の通常の道床厚のバラスト1への挿し込みを想定して、230mmに形成されている。   Further, the tool 40 is formed with two bent portions 43 at an interval from the base portion 42 fixed to the tie tamper 10 to the distal end portion 41, and the bending angle of the bent portion 43 increases toward the distal end. It is formed as follows. And the bending angle of the front-end | tip part 41 with respect to the base 42 is formed at 45 degrees or more. As a result, the recessed area A is formed by the connecting portion 44 and the tip portion 41. In place of the bent portion 43, the connecting portion 44 and the distal end portion 41 may be formed of a curved surface. In the present embodiment, as shown in FIG. 3B, two bent portions 43 are formed, and the bending angle between the base portion 42 and the connecting portion 44 that connects the base portion 42 and the tip portion 41 ( The bending angle (28 °) between the connecting portion 44 and the distal end portion 41 is larger than 17 °), and the bending angle of the distal end portion 41 with respect to the base portion 42 is 45 °. The vertical length of the distal end portion 41 in a state where the base portion 42 is vertically supported is 100 mm, assuming insertion into the ballast 1 having a thin road bed thickness of about 100 mm, and up to the connection portion 44. The vertical length of is assumed to be 230 mm on the assumption that it is inserted into a ballast 1 having a normal road bed thickness of about 200 mm.

さらに、ツール40の基部42に対する先端部41の曲げ角は、バラスト1の道床厚Bと、まくらぎ1の底面幅Sとに応じて設定すると良い。すなわち、ツール40を用いてまくらぎ2下にバラスト1をつき固めるためには、図5に示すように、基部42を鉛直に立てた際に、先端部41をまくらぎ1の底面幅Sの1/2まで到達させる必要がある。従って、先端部41の基部42に対する折れ角αをバラスト1の道床厚Bとまくらぎ1の底面幅Sの半分の長さS/2との比以上、すなわち、tanα > S/2B の関係を満たすように設定すると良い。具体的には、バラスト1の道床厚Bと、まくらぎ1の底面幅Sとに応じた複数本のツール40を用意し、付け替えて使用することができる。例えば、木まくらぎ用に、バラスト1の道床厚B100mm、200mm、250mmのそれぞれに対応する先端部41の基部42に対する折れ角αが45°、27°、22°に設定された3本のツール40を用意すると良い。また、木まくらぎよりも幅が広いPCまくらぎ用に、バラスト1の道床厚B100mm、200mm、250mmのそれぞれに対応する先端部41の基部42に対する折れ角αが50°、31°、26°に設定された3本のツール40を用意すると良い。   Furthermore, the bending angle of the tip 41 with respect to the base 42 of the tool 40 may be set according to the road bed thickness B of the ballast 1 and the bottom surface width S of the sleeper 1. That is, in order to fix the ballast 1 under the sleeper 2 using the tool 40, as shown in FIG. 5, when the base portion 42 is set up vertically, the tip 41 is set to the bottom width S of the sleeper 1. It is necessary to reach 1/2. Therefore, the bending angle α with respect to the base portion 42 of the distal end portion 41 is equal to or greater than the ratio of the road bed thickness B of the ballast 1 to the half length S / 2 of the bottom width S of the sleeper 1, that is, the relationship of tan α> S / 2B. It is good to set to meet. Specifically, a plurality of tools 40 corresponding to the road bed thickness B of the ballast 1 and the bottom surface width S of the sleeper 1 can be prepared and used by changing them. For example, for wood sleepers, three tools in which the bending angle α with respect to the base 42 of the tip 41 corresponding to each of the road bed thicknesses B 100 mm, 200 mm, and 250 mm of the ballast 1 is set to 45 °, 27 °, and 22 ° 40 should be prepared. Further, for PC sleepers having a width wider than that of a wood sleeper, the folding angle α with respect to the base portion 42 of the tip 41 corresponding to each of the road bed thicknesses B 100 mm, 200 mm, and 250 mm of the ballast 1 is 50 °, 31 °, and 26 °. It is preferable to prepare three tools 40 set in the above.

次に、補修材生成工程及び補修材投入工程として、ポリマー水溶液と、ポリマー水溶液と反応してゲル化させる反応材とを混合し、まくらぎ2下の空隙Xに充填する補修材5を生成し(ステップ103)、図6(a)に示すように、生成した補修材5を補修材投入口4に投入する(ステップ104)。ポリマー水溶液は、生分解性高分子材(生分解性プラスチック)を主剤として構成すると好適であり、例えば、化学合成系のポリビニルアルコール(PVA)を用いることができる。なお、生分解性高分子材は、化学合成系に限ることなく、微生物系、天然高分子系であっても良い。また、反応材としては、例えば、珪酸ナトリウムを用いることができる。珪酸ナトリウムは、粉状、粒状、液状のいずれもあっても良い。ポリマー水溶液と珪酸ナトリウムとを混合することで、相互にゲル化し、有機的に絡み合って強固な複合ゲルが補修材として生成される。なお、ポリマー水溶液と反応材との反応速度は、ポリマー水溶液の重合度やケン化度、水素イオン指数(PH)等で調整することができ、補修材5は、完全にゲル化されていない反応過程の状態で補修材投入口4に投入する。また、本実施の形態では、投入口形成工程とタイタンパーセット工程との後に補修材生成工程を行うようにしたが、補修材生成工程は、投入口形成工程やタイタンパーセット工程と並行して行うようにしても良い。   Next, as a repair material generation process and a repair material input process, a polymer aqueous solution and a reaction material that reacts with the polymer aqueous solution to be gelled are mixed to generate a repair material 5 that fills the gap X under the sleeper 2. (Step 103), as shown in FIG. 6A, the generated repair material 5 is put into the repair material inlet 4 (step 104). The aqueous polymer solution is preferably composed of a biodegradable polymer material (biodegradable plastic) as a main agent, and for example, chemically synthesized polyvinyl alcohol (PVA) can be used. The biodegradable polymer material is not limited to a chemical synthesis system, and may be a microbial system or a natural polymer system. Moreover, as a reaction material, sodium silicate can be used, for example. Sodium silicate may be powdery, granular, or liquid. By mixing the polymer aqueous solution and sodium silicate, they gel each other and are entangled organically to form a strong composite gel as a repair material. The reaction rate between the aqueous polymer solution and the reaction material can be adjusted by the degree of polymerization or saponification of the aqueous polymer solution, the hydrogen ion index (PH), etc. The repair material 5 is a reaction that is not completely gelled. In the state of the process, it is introduced into the repair material inlet 4. In the present embodiment, the repair material generation process is performed after the input port formation process and the tie tamper setting process, but the repair material generation process is performed in parallel with the input port formation process and the tie tamper setting process. You may make it do.

次に、バラスト補充工程及びつき固め工程として、新たに用意したバラスト1を補充バラスト6として補修材投入口4に投入した後(ステップ105)、タイタンパー10の起振部30を起動させ、タイタンパー10の起振部30で発生した振動をツール40からバラスト1に伝達しながら、ツール40をまくらぎ2下につき込む(ステップ106)。これにより、図6(b)に示すように、補修材5と補充バラスト6とが混合されながらまくらぎ2下につき込まれ、補充バラスト6を取り込んだ状態で補修材5がゲル化される。これにより、ゲル化したポリマーによってバラスト1を内包する固結体がまくらぎ2下に形成される。ゲル化された補修材5は、弾性(柔軟性)を有するため、強制的な変形を受けたときにその変形に追従し、復元できる性質(靭性)を有する。従って、補充バラスト6を取り込んだ状態でゲル化された補修材5は、圧縮強度と靭性を有し、まくらぎ2からの衝撃荷重を吸収する性能を発揮し、レール3の継ぎ目下等の、衝撃荷重の大きい箇所でも高い耐久性を発揮できる。   Next, as the ballast replenishment step and the compaction step, the newly prepared ballast 1 is charged as the replenishment ballast 6 into the repair material input port 4 (step 105), and then the vibration generator 30 of the tie tamper 10 is activated to activate the Titan. While transmitting the vibration generated in the vibration generating unit 30 of the par 10 from the tool 40 to the ballast 1, the tool 40 is placed under the sleeper 2 (step 106). Thereby, as shown in FIG. 6B, the repair material 5 and the supplementary ballast 6 are mixed under the sleeper 2 while being mixed, and the repair material 5 is gelated in a state where the supplementary ballast 6 is taken in. Thereby, the solidified body which includes the ballast 1 with the gelatinized polymer is formed under the sleeper 2. Since the gelated repair material 5 has elasticity (flexibility), it has a property (toughness) that can follow the deformation and recover when subjected to forced deformation. Therefore, the repair material 5 that has been gelated in the state in which the replenishment ballast 6 is taken in has compression strength and toughness, exhibits the performance of absorbing the impact load from the sleeper 2, such as under the joint of the rail 3, High durability can be exhibited even in locations with large impact loads.

以下、各補修箇所においてステップ101からステップ106の工程が繰り返されることになる。   Thereafter, the process from step 101 to step 106 is repeated at each repair location.

なお、本実施の形態では、ステップ104の補修材投入工程の後に、ステップ105のバラスト補充工程を行うように構成したが、ステップ104の補修材投入工程の後に、ステップ105のバラスト補充工程で補充バラスト6を投入することなく、ステップ106のつき固め工程を行っても一定の効果を得ることができる。この場合には、タイタンパー10のつき込みによって、補修材5と既設のバラスト1とが混合されながらまくらぎ2下につき込まれ、既設のバラスト1を取り込んだ状態で補修材5がゲル化される。   In the present embodiment, the ballast replenishment process of step 105 is performed after the repair material supply process of step 104. However, replenishment is performed in the ballast replenishment process of step 105 after the repair material input process of step 104. Even if the compacting step of step 106 is performed without introducing the ballast 6, a certain effect can be obtained. In this case, the repair material 5 and the existing ballast 1 are mixed under the sleeper 2 while being mixed with the tie tamper 10, and the repair material 5 is gelated with the existing ballast 1 taken in. The

また、本実施の形態では、ステップ103の補修材生成で補修材5を生成した後に、ステップ104の補修材投入工程で補修材5を補修材投入口4に投入するように構成したが、補修材5を生成は、補修材投入口4への投入後であっても良い。すなわち、図7に示すように、ステップ102のタイタンパーセット工程の後、原材料投入工程として、ポリマー水溶液と反応材とをそれぞれ補修材投入口4に投入し(ステップ201)、補修材投入口4内でステップ103の補修材生成工程を行うようにしても良い。この場合には、ポリマー水溶液と反応材とを混合して補修材5を生成するための容器を用意する必要がなく、また、補修材5を生成した後の容器の後始末が必要なくなるため、作業量を軽減させることができる。   Further, in the present embodiment, after the repair material 5 is generated by generating the repair material in Step 103, the repair material 5 is input to the repair material input port 4 in the repair material input process of Step 104. The material 5 may be generated after the material 5 is input to the repair material inlet 4. That is, as shown in FIG. 7, after the titan tamper setting process in step 102, as a raw material input process, an aqueous polymer solution and a reaction material are respectively input to the repair material input port 4 (step 201). The repair material generation process of step 103 may be performed in the process. In this case, it is not necessary to prepare a container for generating the repair material 5 by mixing the aqueous polymer solution and the reaction material, and since it is not necessary to clean up the container after the repair material 5 is generated, The amount of work can be reduced.

本実施の形態では、反応材としてはケイ酸ナトリウムを用いる例について説明したが、使用可能な他の反応材について検討した結果を図8に示す。図8に示すように、21種類について検討した結果、塩化ナトリウム、水酸化ナトリウム、水酸化リチウム、炭酸ナトリウム、炭酸カリウム、硫酸アルミニウム、硫酸ナトリウム、珪酸ナトリウム、シリカゲル、ベントナイト、吸水性ポリマーの11種類が使用できることが分かった。特に、塩化ナトリウム、水酸化ナトリウム、水酸化リチウム、炭酸ナトリウム、炭酸カリウム、硫酸アルミニウム、硫酸ナトリウム、珪酸ナトリウムでは、ゲル化の硬化原理が塩析であるため、ポリマー水溶液の生分解性を維持した状態でゲル化させることができ、好適である。   In the present embodiment, an example in which sodium silicate is used as a reaction material has been described, but the results of studying other usable reaction materials are shown in FIG. As shown in FIG. 8, as a result of examining 21 types, 11 types of sodium chloride, sodium hydroxide, lithium hydroxide, sodium carbonate, potassium carbonate, aluminum sulfate, sodium sulfate, sodium silicate, silica gel, bentonite, and a water-absorbing polymer were used. It was found that can be used. In particular, sodium chloride, sodium hydroxide, lithium hydroxide, sodium carbonate, potassium carbonate, aluminum sulfate, sodium sulfate, and sodium silicate maintained the biodegradability of the aqueous polymer solution because the gelation hardening principle is salting out. It can be gelled in a state and is suitable.

次に、本実施の形態の軌道補修方法による効果を検証するための実物大模型試験について図9を参照して詳細に説明する。
図9(a)に示すように、土砂を混入したバラスト1上に試験用のまくらぎ2を敷設さし、レール3状から列車の通過を模擬した載荷梁7を載荷して、載荷の繰り返し回数の増加に伴う軌道沈下量の変化を検証した。
Next, a full-scale model test for verifying the effect of the track repair method of the present embodiment will be described in detail with reference to FIG.
As shown in FIG. 9 (a), a test sleeper 2 is laid on a ballast 1 mixed with earth and sand, and a loading beam 7 simulating the passage of a train is loaded from the shape of a rail 3, and loading is repeated. The change of the orbital settlement with the increase of the frequency was verified.

図9(b)は、載荷回数の増加に伴う軌道沈下量の変化を示すグラフであり、ケース1は、補修作業を行わなかった場合を、ケース2は、ステップ105のバラスト補充工程を行うことなく、本実施の形態の軌道補修方法で補修を行った場合を、ケース3は、本実施の形態の軌道補修方法で補修を行った場合をそれぞれ示している。また、載荷の繰り返し回数が30万回に達した時点で、土砂を混入したバラスト1に注水を行い、その後の軌道沈下量の変化を検証した。   FIG. 9B is a graph showing changes in the amount of trajectory settlement with an increase in the number of times of loading. Case 1 is a case where repair work is not performed, and case 2 is that the ballast replenishing step of step 105 is performed. However, Case 3 shows a case where repair is performed by the track repair method of the present embodiment, and Case 3 shows a case where repair is performed by the track repair method of the present embodiment. In addition, when the number of loadings reached 300,000 times, water was poured into the ballast 1 mixed with earth and sand, and the change in the amount of orbital settlement thereafter was verified.

ケース1では、タイタンパー10によるつき固め後の初期沈下量が少なく、その後の定常沈下量も繰り返し回数が30万回までは安定しているが、注水が行われると、急激に軌道沈下量が増大する。これにより、土砂を混入したバラスト1は、締め固められた状態であっても滞水時の強度低下が著しく、軌道沈下が増大することがわかる。   In Case 1, the initial subsidence amount after compaction by the tie tamper 10 is small, and the subsequent steady subsidence amount is stable up to 300,000 repetitions, but when water injection is performed, the orbital subsidence amount suddenly increases. Increase. Thereby, even if the ballast 1 mixed with earth and sand is in a compacted state, it can be seen that the strength is significantly reduced when the water is stagnant and the orbital settlement is increased.

ケース2、ケース3では、タイタンパー10によって土砂を混入したバラスト1が緩められるため、初期沈下量が大きくなっている。しかし、その後の定常沈下量は、注水に拘わらず安定している。従って、初期沈下量さえ勘案すれば、本実施の形態の軌道補修方法によって、劣化しているバラスト1の軌道補修を効果的に行えることがわかる。また、ケース2に比べてケース3の初期沈下量は少なく、ステップ105のバラスト補充工程によって初期沈下量を削減できることがわかる。   In cases 2 and 3, since the ballast 1 mixed with earth and sand is loosened by the tie tamper 10, the initial subsidence amount is large. However, the subsequent steady settlement is stable regardless of water injection. Therefore, it is understood that the track repair of the deteriorated ballast 1 can be effectively performed by the track repair method of the present embodiment, even if the initial settlement amount is taken into consideration. In addition, it can be seen that the amount of initial settlement in case 3 is smaller than that in case 2, and the amount of initial settlement can be reduced by the ballast replenishment process in step 105.

以上説明したように本実施の形態の軌道補修方法は、バラスト1上に敷設されたまくらぎ2の脇に補修材を投入する補修材投入口4を形成させた後、補修材投入口4に補修材5としてポリマー水溶液と当該ポリマー水溶液をゲル化させる反応材とを投入して、タイタンパー10を用いてまくらぎ2下につき込むことで、ゲル化したポリマーによってバラスト1を内包する固結体をまくらぎ2下に形成させる。
この構成により、ポリマー水溶液と当該ポリマー水溶液をゲル化させる反応材とを補修材5として補修材投入口4に投入し、まくらぎ下につき固めれば良いため、空圧機器等の特別な機器を用いることなく、通常のタイタンパー10による補修技術で対応することが可能であり、バラストが劣化しているバラスト軌道の軌道補修を効果的に行うことができる。さらに、混合によって短時間で補修材の強度を増加させることができ、施工直後の短時間で列車の運行が可能である。そして、通常のタイタンパー10による補修作業と同程度の作業量であり、わずかな列車間合いで施工が可能である。
As described above, the track repair method according to the present embodiment forms the repair material input port 4 for supplying the repair material on the side of the sleeper 2 laid on the ballast 1, and then the repair material input port 4. A solid solution containing the ballast 1 by the gelled polymer by introducing a polymer aqueous solution and a reaction material that gels the polymer aqueous solution as the repair material 5 and using a tie tamper 10 to enter the sleeper 2. Is formed under sleeper 2.
With this configuration, since a polymer aqueous solution and a reaction material that gels the polymer aqueous solution are put into the repair material inlet 4 as the repair material 5 and hardened under the sleeper, a special device such as a pneumatic device can be used. Without using it, it is possible to cope with a repair technique using a normal tie tamper 10, and it is possible to effectively repair the ballast track in which the ballast has deteriorated. Furthermore, the strength of the repair material can be increased in a short time by mixing, and the train can be operated in a short time immediately after construction. And it is a work amount comparable to the repair work by the normal tie tamper 10, and construction is possible in a slight train interval.

また、本実施の形態の軌道補修方法は、バラスト1上に敷設されたまくらぎ2の脇に補修材5を投入する補修材投入口4を形成する投入口形成工程と、補修材投入口4にてポリマー水溶液と当該ポリマー水溶液をゲル化させる反応材とを混合させて補修材5を生成する補修材生成工程と、タイタンパー10を用いて生成した補修材5をまくらぎ2下につき込むつき固め工程とを備えている。
この構成により、ポリマー水溶液と反応材とを混合して補修材5を生成するための容器を用意する必要がなく、また、補修材5を生成した後の容器の後始末が必要なくなるため、作業量を軽減させることができる。
Further, the track repairing method of the present embodiment includes an input port forming step for forming a repair material input port 4 for supplying the repair material 5 to the side of the sleeper 2 laid on the ballast 1, and a repair material input port 4. A repair material generating step of generating a repair material 5 by mixing a polymer aqueous solution and a reaction material that gels the polymer aqueous solution in the above, and a repair material 5 generated using the tie tamper 10 And a hardening process.
With this configuration, it is not necessary to prepare a container for generating the repair material 5 by mixing the polymer aqueous solution and the reaction material, and it is not necessary to clean up the container after the repair material 5 is generated. The amount can be reduced.

さらに、本実施の形態の軌道補修方法は、補修材5を投入した補修材投入口4に補充バラスト6を補充するバラスト補充工程を備え、補充バラスト6と補修材5とをバラスト2下につき込むように構成されている。
この構成により、補修材5と補充バラスト6とが混合されながらまくらぎ2下につき込まれ、補充バラスト6を取り込んだ状態で補修材5がゲル化され、軌道補修後の初期沈下量を低減させることができる。
Furthermore, the track repair method of the present embodiment includes a ballast replenishment step of replenishing the replenishment ballast 6 to the repair material inlet 4 into which the repair material 5 has been charged, and the replenishment ballast 6 and the repair material 5 are placed under the ballast 2. It is configured as follows.
With this configuration, the repair material 5 and the supplementary ballast 6 are mixed under the sleeper 2 while being mixed, and the repair material 5 is gelled in a state in which the supplementary ballast 6 is incorporated, thereby reducing the initial settlement after the track repair. be able to.

さらに、本実施の形態の軌道補修方法において、タイタンパー10には、先端部41がくし歯状に形成された異形のツール40を装着したものを用いると良い。
この構成により、バラスト1と補修材5とを効率的に混合させることができる。
Furthermore, in the track repairing method of the present embodiment, it is preferable to use a tie tamper 10 with a deformed tool 40 having a tip portion 41 formed in a comb shape.
With this configuration, the ballast 1 and the repair material 5 can be mixed efficiently.

さらに、本実施の形態の軌道補修方法において、ポリマー水溶液は、生分解性高分子材を主剤としている。
この構成により、生分解性を維持しながら軌道補修材として効果を発揮させることができるため、環境負荷が低い軌道補修を実現することができる。
Furthermore, in the track repair method of the present embodiment, the polymer aqueous solution is mainly composed of a biodegradable polymer material.
With this configuration, since the effect as a track repair material can be exhibited while maintaining biodegradability, track repair with a low environmental load can be realized.

なお、上記実施の形態の構成及び動作は例であって、本発明の趣旨を逸脱しない範囲で適宜変更して実行することができることは言うまでもない。   Note that the configuration and operation of the above-described embodiment are examples, and it is needless to say that the configuration and operation can be appropriately changed and executed without departing from the gist of the present invention.

1 バラスト
2 まくらぎ
3 レール
4 補修材投入口
5 補修材
6 補充バラスト
7 載荷梁
10 タイタンパー
20 ツール(通常)
21 先端部
22 基部
23 曲げ部
30 起振部
40 ツール(異形)
41 先端部
42 基部
43 曲げ部
44 接続部
1 Ballast 2 Sleeper 3 Rail 4 Repair material slot 5 Repair material 6 Supplement ballast 7 Loading beam 10 Tie tamper 20 Tool (normal)
21 Tip 22 Base 23 Bend 30 Excitation 40 Tool (Deformed)
41 Tip portion 42 Base portion 43 Bending portion 44 Connection portion

Claims (5)

バラスト上に敷設されたまくらぎの脇に補修材を投入する補修材投入口を形成させた後、前記補修材投入口に前記補修材としてポリマー水溶液と当該ポリマー水溶液をゲル化させる反応材とをそれぞれ投入して、タイタンパーを用いて前記まくらぎ下につき込むことで、ゲル化した前記ポリマーによって既設の前記バラストを内包する固結体を前記まくらぎ下に形成させることを特徴とする軌道補修方法。 After forming a repair material input port for charging a repair material on the side of the sleeper laid on the ballast, a polymer aqueous solution as the repair material and a reaction material that gels the polymer aqueous solution as the repair material in the repair material input port, respectively The track repairing method is characterized in that a solidified body containing the existing ballast is formed under the sleeper by the polymer that has been gelled by being put in and under the sleeper using a tie tamper. . 前記補修材を投入した前記補修材投入口に前記バラストを補充するバラスト補充工程を有し、
補充された前記バラストと前記補修材とを前記まくらぎ下につき込むことを特徴とする請求項記載の軌道補修方法。
Having a ballast replenishment step of replenishing the ballast to the repair material input port into which the repair material has been charged;
Orbital repair method according to claim 1, wherein the a replenished the ballast and the repair material, characterized in a way to push per under the sleepers.
前記タイタンパーには、先端部がくし歯状に形成されたタイタンパー用つき固めツールが装着されていることを特徴とする請求項1又は2記載の軌道補修方法。 The track repairing method according to claim 1 or 2 , wherein a tie tamper tapping tool having a tip portion formed in a comb shape is attached to the tie tamper. 前記ポリマー水溶液は、生分解性高分子材を主剤とすることを特徴とする請求項1乃至3のいずれかに記載の軌道補修方法。 The aqueous polymer solution, the track repair method according to any one of claims 1 to 3, characterized in that a main component a biodegradable polymer material. 前記反応材は、珪酸ナトリウム、塩化ナトリウム、水酸化ナトリウム、水酸化リチウム、炭酸ナトリウム、炭酸カリウム、硫酸アルミニウム、硫酸ナトリウム、シリカゲル、ベントナイト、吸水性ポリマーのいずれかを含むことを特徴とする請求項1乃至4のいずれかに記載の軌道補修方法。 The reaction material contains any of sodium silicate, sodium chloride, sodium hydroxide, lithium hydroxide, sodium carbonate, potassium carbonate, aluminum sulfate, sodium sulfate, silica gel, bentonite, and a water-absorbing polymer. The track repair method according to any one of 1 to 4 .
JP2013204253A 2013-09-30 2013-09-30 Track repair method Active JP6175337B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013204253A JP6175337B2 (en) 2013-09-30 2013-09-30 Track repair method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013204253A JP6175337B2 (en) 2013-09-30 2013-09-30 Track repair method

Publications (2)

Publication Number Publication Date
JP2015068090A JP2015068090A (en) 2015-04-13
JP6175337B2 true JP6175337B2 (en) 2017-08-02

Family

ID=52835057

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013204253A Active JP6175337B2 (en) 2013-09-30 2013-09-30 Track repair method

Country Status (1)

Country Link
JP (1) JP6175337B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395075A (en) * 2020-03-09 2020-07-10 朔黄铁路发展有限责任公司 Maintenance method of ballast track bed
JP7664199B2 (en) * 2021-07-08 2025-04-17 公益財団法人鉄道総合技術研究所 Ballast track repair method and repair materials, and ballast track

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2155713A (en) * 1935-01-09 1939-04-25 Electric Tamper & Equipment Co Ballast working implement and method
US2137842A (en) * 1935-10-28 1938-11-22 Jackson Corwill Ballast working implement
JPH11209903A (en) * 1998-01-28 1999-08-03 East Japan Railway Co Elasticization of tracked track
JP4955329B2 (en) * 2006-07-13 2012-06-20 公益財団法人鉄道総合技術研究所 Mud prevention method
JP5118325B2 (en) * 2006-10-03 2013-01-16 株式会社アレン Ballast track repair method
JP4956451B2 (en) * 2008-01-16 2012-06-20 公益財団法人鉄道総合技術研究所 Track repair method, mixed filler used in the method, and consolidated body forming material
JP2011106097A (en) * 2009-11-13 2011-06-02 Daido Kasei Kogyo Kk One-component moisture-curable ballast stabilizer uninfluenced by ballast surface condition such as water wetting
JP2015059329A (en) * 2013-09-18 2015-03-30 公益財団法人鉄道総合技術研究所 Tamping tool for tie tamper

Also Published As

Publication number Publication date
JP2015068090A (en) 2015-04-13

Similar Documents

Publication Publication Date Title
CN102094464B (en) Pressure stress water-stopping plate
CN104937170B (en) Composite railway sleeper and railroad track
JP6175337B2 (en) Track repair method
EP2677023A3 (en) Pressed, waxy, solid cleaning compositions and methods of making them
JP6961143B2 (en) Column reinforcement method for column-type coal mining method
JP2008285870A (en) Method of reinforcing closed rib steel floor slab
CN105888107A (en) Vertical light partition wall installation and fixation structure and construction method thereof
JP2015059329A (en) Tamping tool for tie tamper
JP4956451B2 (en) Track repair method, mixed filler used in the method, and consolidated body forming material
CN108570896A (en) A method of repairing sleeper hole
CN109338840A (en) A kind of high-strength pavement and its construction technology
JP6493834B2 (en) Ground liquefaction countermeasure method
KR102352120B1 (en) Eco-friendly slope greening method for Ecological Restoration
JP2010071067A (en) Repair method for base course or the like
CN206646823U (en) Outer wall screw hole capping tools
Sturm et al. Tensile Performance of GFRP Bars after Being Sprayed with Shotcrete
JP2005344475A (en) Roadbed repair method and roadbed
JP5254051B2 (en) Repair method of roadbed to prevent uplift and destruction due to expansion
RU180233U1 (en) Lining
JP4940462B1 (en) Ground improvement method
JP3678732B2 (en) Partially hydrated molded body of hydraulic composition, method for producing the same and method for using the same
CN117948186A (en) Construction method for treating floor heave of roadway
CN206495099U (en) Reinforced concrete prefabricated board shape sleeper fixator
JP3037929B2 (en) How to fill underground cavities
CN202544400U (en) Pressing mold board for wall pipe trough

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160610

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170425

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170428

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170623

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170704

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170710

R150 Certificate of patent or registration of utility model

Ref document number: 6175337

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250