Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP6239686B2 - Construction material of tunnel shaft internal structure, construction lift and material transport cart - Google Patents
[go: Go Back, main page]

JP6239686B2 - Construction material of tunnel shaft internal structure, construction lift and material transport cart - Google Patents

Construction material of tunnel shaft internal structure, construction lift and material transport cart Download PDF

Info

Publication number
JP6239686B2
JP6239686B2 JP2016095403A JP2016095403A JP6239686B2 JP 6239686 B2 JP6239686 B2 JP 6239686B2 JP 2016095403 A JP2016095403 A JP 2016095403A JP 2016095403 A JP2016095403 A JP 2016095403A JP 6239686 B2 JP6239686 B2 JP 6239686B2
Authority
JP
Japan
Prior art keywords
construction
shaft
internal structure
tunnel
shaft internal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016095403A
Other languages
Japanese (ja)
Other versions
JP2017203294A (en
Inventor
星野 明夫
明夫 星野
肇 棚橋
棚橋  肇
Original Assignee
本清鋼材株式会社
丸栄コンクリート工業株式会社
ゲートアップ合同会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 本清鋼材株式会社, 丸栄コンクリート工業株式会社, ゲートアップ合同会社 filed Critical 本清鋼材株式会社
Priority to JP2016095403A priority Critical patent/JP6239686B2/en
Publication of JP2017203294A publication Critical patent/JP2017203294A/en
Application granted granted Critical
Publication of JP6239686B2 publication Critical patent/JP6239686B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Types And Forms Of Lifts (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Description

本発明は、都市部等の大断面トンネルの、立坑内部構造の構築部材、工事用リフト及び資材搬送台車に関する。   The present invention relates to a construction member for a shaft internal structure, a construction lift, and a material transport carriage for a large-section tunnel in an urban area or the like.

道路や鉄道に使用される、大断面トンネルの、立坑・シールドの工事手順は、まず、矩形や円形の土留め壁及び立坑躯体を築造し、発進及び到達の立坑とする。続いて、この立坑工事の終了後、大型クレーンを使って、発進立坑の底部にて、所定の架台上に分割したシールド機を一体に組立てる。次に、シールド機の、動力・制御設備(以下、「後続設備」という)、掘削土搬出設備及び資機材搬送設備を地上ヤードに整備し、続いて、予め設けた発進立坑のエントランスよりシールド機を土中に貫入、発進させる。   The construction procedures for shafts and shields of large-section tunnels used for roads and railways are to build rectangular and circular retaining walls and shafts, and use them as starting and reaching shafts. Subsequently, after completion of the shaft construction, a shield machine divided on a predetermined mount is assembled integrally at the bottom of the start shaft using a large crane. Next, power / control equipment (hereinafter referred to as “follow-up equipment”), excavation soil carry-out equipment and material / material transport equipment for the shield machine will be installed in the ground yard, and then the shield machine will be installed from the entrance of the previously established start shaft. Penetration into the ground and start.

このような、シールド機の初期段階の掘進(以下、「初期掘進」という)後、後続設備を、そのスペースがシールド機後方のトンネル坑内に確保できる段階で、ここに移動する。一方で、地上には、掘削土搬出設備、資機材搬送設備及び防音ハウスを再整備し、発進立坑には、覆工用セグメントの搬入に供するための工事用リフトなどを設置する。その上で、到達立坑へ本格的な掘進(以下、「本掘進」という)を開始する。   After such initial excavation of the shield machine (hereinafter referred to as “initial excavation”), the subsequent equipment is moved here at a stage where the space can be secured in the tunnel mine behind the shield machine. On the other hand, excavated soil unloading equipment, equipment transporting equipment and soundproof house will be redeveloped on the ground, and a construction lift will be installed on the starting shaft for carrying the lining segment. In addition, full-scale excavation (hereinafter referred to as “main excavation”) is started to the reaching shaft.

到達後、シールド機及び後続設備を両立坑から解体搬出し、発進立坑の工事用リフトを撤去する。次いで、両立坑内部の空いたスペースに、立坑内部構築工事として、立坑内部に床版や柱を下方から上方へ順に型枠支保工を積み立てつつ構築し、コンクリート強度の発現後に型枠支保工を撤去する。そして、本設リフト及び換気設備などの本設設備を設置し、トンネル坑内設備の工事終了後、工事完了としていた。   After arrival, dismantle the shield machine and the following equipment from the compatible mine, and remove the lift for the construction of the start pit. Next, in the vacant space inside the compatible pit, as a construction work inside the shaft, floor slabs and pillars are built inside the shaft in order from the bottom to the top. Remove. Then, permanent equipment such as a permanent lift and ventilation equipment was installed, and after the construction of tunnel tunnel facilities was completed, the construction was completed.

ここで、大断面のシールド機の組立ての場合、総重量は3000tfに及ぶ。これに付随する後続設備、工事用リフトなどの資機材搬送設備の規模も大きく、それらを整備するには通常1年程度の工期を要する。その後、初期掘進に半年程度、本掘進に数年を要し到達する。到達後にも工事完了までには、工事用リフトなどの資機材搬送設備を撤去の上、本設リフトや換気設備の設置を含む立坑内部構築工事、トンネル坑内設備工事などに数年を要する。このように、大断面の場合、工期の長期化が常であった。   Here, in the case of assembling a shield machine having a large cross section, the total weight reaches 3000 tf. The accompanying equipment and materials and equipment transportation facilities such as construction lifts accompanying this are large in scale, and it usually takes about one year to construct them. After that, it takes about half a year for the initial excavation and several years for the main excavation. After completion, it takes several years to complete the construction of the vertical shaft, including the installation of the main lift and ventilation equipment, and the construction of the tunnel mine, after removing materials and equipment transport equipment such as a construction lift. In this way, in the case of a large cross section, the construction period was usually prolonged.

また、都市部の騒音対策上必須の道路などに設置する、立坑・シールド工事の作業帯に設ける防音ハウスは、この屋根に障害する大型クレーンが、シールド機組立後に不要になった後に、設置する。そして、昼夜間に及ぶ本掘進が終了しシールド機の到達以降に、防音ハウスが必要なくなるので解体し、工事終了後、作業帯を撤去し道路を解放する。   In addition, a soundproof house to be installed on a work shaft for shafts and shield construction, which is installed on roads essential for noise countermeasures in urban areas, will be installed after the large crane that obstructs this roof is no longer necessary after the shield machine is assembled. . After the main excavation for day and night ends and the shield machine arrives, the soundproof house is no longer necessary, so it is dismantled, and after the construction is completed, the work zone is removed and the road is released.

したがって、工期の長期化は、作業帯占有による渋滞などによる都市機能の低下を深刻化させる。上述のような深刻な事態となるのは、シールド掘進工事(初期掘進及び本掘進)、立坑内部構築工事やトンネル坑内設備工事を同時並行で行える工期短縮の方法が見出されていないことに起因する。   Therefore, the longer construction period will worsen the deterioration of urban functions due to traffic congestion due to occupation of work zones. The serious situation described above is due to the fact that no shield shortening method has been found that can simultaneously perform shield tunneling work (initial drilling and main drilling), shaft internal construction work, and tunnel tunnel equipment construction. To do.

特開平7−71197号公報Japanese Patent Laid-Open No. 7-71197 特開昭57−38283号公報JP-A-57-38283

特許文献1には、立坑セグメント搬送装置として、パレットに載せたセグメントを地上より立坑下方へ搬送するリフトが示されている。   Patent Document 1 discloses a lift for transporting a segment placed on a pallet from the ground to the bottom of the shaft as a shaft segment transporting device.

特許文献2には、一般的な工事用リフトとして、上端に巻き上げ機を配し、下方に釣り合い錘及びケージを配する構成が示されている。   Patent Document 2 discloses a general construction lift in which a hoisting machine is disposed at the upper end and a counterweight and a cage are disposed below.

ここで、特許文献1に記載の立坑セグメント搬送装置は、セグメントを地上でフォークリフトにてパレットに積み込めば、機械的に立坑底部へ搬送でき、その点では効率がよい。しかし、セグメント搬送に特化され、作業員はもとより他の配管材などを搬送できず、利便性が悪かった。一方、特許文献2などに示される一般的な工事用リフトを活用する場合は、セグメント以外に、他の配管材など多目的に活用できるため、利便性はよいが、積み込み、積み替えに関しては機械化されておらず、効率はさらに悪化する。いずれにしても、立坑・シールドの工事に対して、従来の工事用リフトの技術は十分ではない。   Here, the shaft segment conveying apparatus described in Patent Document 1 can be conveyed to the bottom of the shaft mechanically by loading the segments onto the pallet with a forklift on the ground, and is efficient in that respect. However, specializing in segment transportation, workers and other piping materials could not be transported, and convenience was poor. On the other hand, when using a general lift for construction shown in Patent Document 2 and the like, it can be used for other purposes such as other piping materials in addition to the segments, so it is convenient, but it is mechanized for loading and transshipment. The efficiency is further deteriorated. In any case, conventional construction lift technology is not sufficient for shaft and shield construction.

そもそも、立坑内部構造においては、一般に床版や柱を下方から上方へ順に型枠支保工を積み立てつつ構築するので、トンネル坑内への物流を途絶する。したがって、立坑内部構築工事の後に設置する本設リフトは、シールド掘進工事やトンネル坑内設備工事には使えないため、別途、工事用リフトやこれを支持する仮設支柱が必要となり無駄であった。
何よりも物流途絶の問題から、立坑内部構築工事とシールド掘進工事やトンネル坑内設備工事とを同時並行で行える方法がなく、工期を大きく遅延させていたのが実状であった。
In the first place, in the internal structure of a vertical shaft, since floor slabs and pillars are generally constructed by stacking formwork support works in order from the bottom to the top, distribution to the tunnel shaft is interrupted. Therefore, since the main lift installed after the vertical shaft construction work cannot be used for shield excavation work or tunnel tunnel equipment construction, a separate work lift and a temporary support column for supporting the work are required.
Above all, due to the problem of logistics disruption, there was no way to carry out shaft shaft construction work, shield tunneling work and tunnel tunnel equipment work in parallel, and the construction period was greatly delayed.

以上に、従来技術の工事用リフトや立坑内部構造に関する問題点を詳述したが、以下にこれを整理する。
1)従来の立坑セグメント搬送装置は、セグメント搬送に特化したもので、掘進に必要な他の配管材やレール材、さらに作業員などを搬送できず、利便性に欠けるものであった。
The problems related to the prior art work lift and the shaft internal structure have been described in detail above.
1) Conventional shaft segment transport devices are specialized for segment transport, and cannot deliver other piping materials, rail materials, and workers necessary for excavation, and lack convenience.

2)一般的な工事用リフトは、セグメントの積み込みや積み替えに関して機械化しておらず、効率を悪化させていた。 2) General construction lifts were not mechanized in terms of segment loading and re-loading, deteriorating efficiency.

3)工事用リフトは、初期掘進としてシールド機が立坑底部から発進して、そのスペースが空いた後に設置され、シールド機の到達後、立坑内部構築工事を開始する前に撤去し、立坑のスペースを空けていた。そのため、設置・撤去が工期のクリティカルパスに入り、工期遅延の原因であった。 3) The construction lift is installed after the shield machine starts from the bottom of the shaft as the initial excavation, and the space is vacant. After the shield machine arrives, it is removed before starting the construction work inside the shaft. Was empty. For this reason, installation / removal entered the critical path of the construction period, causing delays in the construction period.

4)立坑内部構築工事においては、一般に、床版や柱を下方から上方へ順に型枠支保工を積み立てつつ構築するので、トンネル坑内への物流が途絶し、これとシールド掘進工事やトンネル坑内設備工事との並行作業ができず、工期遅延の原因であった。 4) Generally, in the construction work inside the shaft, the floor slabs and pillars are built in order from the bottom to the top. It was impossible to work in parallel with the construction work, which caused the construction period to be delayed.

5)工事用リフトはあくまで仮設であり、立坑内部構築工事の一部先行を前提とする本設のリフトの先行活用は、その構築に伴いシールド掘進工事の物流を途絶させることから、両者を兼ねることはできず不経済であった。 5) The construction lift is only temporary, and the advanced use of the main lift, which presupposes part of the construction work inside the vertical shaft, will be disrupted by the construction of the shield digging work. It was impossible to do so.

6)工事用リフトは、そのガイドの支持の利便から、多くは立坑内壁面に接して設置されることから、立坑内壁面とトンネル坑内中央側の軌条とのセグメントの受け渡しに距離が出るので、その受け渡しの分、別途機械設備が必要となり、物流の効率低下を招いた。 6) Because the lift for construction is mostly installed in contact with the inner wall surface of the shaft for the convenience of supporting the guide, there is a distance in the delivery of the segment between the inner wall surface of the shaft and the rail on the center side of the tunnel shaft. For the delivery, separate mechanical equipment was required, which led to a decline in logistics efficiency.

7)立坑内部構造は、鉛直に配する支保工や足場に、工期及び工費がかかる。そのため、プレキャスト化が求められるところ、プレキャスト化の場合には部材は大重量となり、クレーンは大型化するため、クレーンブームやクレーンが防音ハウスの屋根やその他資機材搬送設備や掘進設備の障害となり、採用を困難にしていた。 7) The internal structure of the shaft will require a construction period and cost for supporting works and scaffolds arranged vertically. Therefore, when precasting is required, in the case of precasting, the members are heavy, and the crane is enlarged, so the crane boom and crane become an obstacle to the soundproof house roof and other equipment transportation equipment and excavation equipment, Hiring was difficult.

8)立坑内部構造は、プレキャスト化しつつ、シールド掘進工事と並行に構築をして、工期短縮を図ろうにも、立坑に設置される資機材搬送設備やシールド掘進設備に支障することのない構造や手順が提供されていないのが実状であった。 8) The shaft internal structure is precast and constructed in parallel with the shield excavation work, so that the construction period will not be hindered to shorten the construction period, but will not interfere with the equipment transport equipment and shield excavation equipment installed in the shaft. The actual situation is that no procedures are provided.

9)立坑内部構造は、シールド機組立や初期掘進段階であれば、立坑底部以外はスペースが空いているので、構築できれば工期は短縮するが、荷重を支持する柱材はシールド機と障害するので、実際には工法として成立しなかった。 9) If the shaft internal structure is a shield machine assembly or initial excavation stage, there is space in the area other than the bottom of the shaft, so if it can be built, the construction period will be shortened, but the column material supporting the load will interfere with the shield machine. Actually, it was not established as a construction method.

10)立坑内部構築工事と、シールド掘進工事やトンネル坑内設備工事とを同時並行できる工事用リフトは、物流を途絶させない立坑内部構造や組立手順がないため成立せず、工期遅延が常態化していた。 10) The construction lift that can simultaneously perform the shaft internal construction work, shield tunneling work, and tunnel tunnel equipment construction was not realized because there was no shaft internal structure and assembly procedure that would not disrupt logistics, and the construction delay was normal .

さらに、シールド掘進工事に供せられる資機材搬送設備や工事用リフトには、以下の問題点がある。
11)各資材の時系列の所在や状況を、コンピュータ通信を用いて、長いトンネル坑内隅々に至るまで記録及び確認できる物流管理のシステム及び設備がない。そのため、誤搬送の防止や欠品補充の効率性に欠ける。
Furthermore, the equipment and materials transport equipment and the construction lifts used for shield excavation work have the following problems.
11) There is no physical distribution management system and equipment that can record and confirm the location and status of each material in time series to every corner of a long tunnel using computer communication. For this reason, there is a lack of efficiency in preventing erroneous conveyance and replenishment of missing parts.

12)地上ヤードから長いトンネル坑内隅々に至る、資機材の受け渡しを不要とするシームレスな物流設備がない。そのため、効率性に欠ける。 12) There is no seamless physical distribution facility from the ground yard to every corner of a long tunnel mine that does not require delivery of materials and equipment. Therefore, efficiency is lacking.

13)コンクリート二次製品であるセグメントは重量が重く、それを効率的かつ安定して坑内へ運搬するに際し、工事用リフトは揺れが大きく、積み替えのタイムロスや損傷も多い。そのため、効率性、安定性に欠ける。 13) The segment, which is a concrete secondary product, is heavy, and when it is transported efficiently and stably into the mine, the construction lift is greatly swayed, and there is a lot of time loss and damage during transshipment. Therefore, efficiency and stability are lacking.

上述の課題を解決するために、本発明に係るトンネルの立坑内部構造の構築部材は、トンネルの軸方向と自らの1方向が合致し、同一水平面上で立坑の内壁面近傍に矩形対角に設けた4点の交差部と、隣り合う交差部を直交して接続する水平材と、交差部それぞれを鉛直方向に隣り合う層の対応する交差部それぞれと鉛直に接続する柱材と、交差部と内壁面に設けた接続部それぞれとを個別に接続する接続材とから構成される、平面視で少なくとも井形状構造のプレキャスト部材から成る構築部材を一層とし、柱材による鉛直方向に隣り合う層との連結により当該構築部材を複数積層した重層構造であることを特徴とする。また、前記接続材は、柱材の位置と立坑の内壁面との離隔を調整可能にする。さらに、立坑の内壁面又はトンネルの直上に突出する框部から、上面に位置する最下層の交差部として配備した交差部材及び柱材と接続して該交差部材及び該柱材を支持する斜材を有する。   In order to solve the above-mentioned problem, the construction member of the tunnel internal structure of the tunnel according to the present invention has a rectangular diagonal in the vicinity of the inner wall surface of the shaft on the same horizontal plane so that the axial direction of the tunnel coincides with its own direction. The four intersections provided, a horizontal member that connects the adjacent intersections orthogonally, a column member that connects each of the intersections vertically with each of the corresponding intersections of the layers adjacent in the vertical direction, and the intersection And a connecting member that individually connects each of the connecting portions provided on the inner wall surface, and includes a construction member made of a precast member having at least a well-shaped structure in a plan view, and a layer adjacent to the vertical direction by the pillar material It is characterized by having a multi-layered structure in which a plurality of the construction members are stacked by being connected to. Moreover, the said connection material enables adjustment of the separation of the position of a pillar material, and the inner wall face of a shaft. Further, the diagonal member that supports the cross member and the column member by connecting to the cross member and the column member arranged as the lowest cross point located on the upper surface from the inner wall of the shaft or the ridge protruding directly above the tunnel. Have

本発明によれば、工事用リフトは、ケージ昇降用のガイドが、井形状構造体の内部において水平材に保持され、この水平材を支持する柱材は、初期掘進の段階で、框上面より斜材によって支持しつつ、同ガイドをシールド機発進後、下方の立坑底部へ延伸する。本発明に係る工事用リフトにより、以下の作用効果を奏することができる。   According to the present invention, in the construction lift, the guide for raising and lowering the cage is held by the horizontal member inside the well-shaped structure, and the column member that supports the horizontal member is from the upper surface of the fence at the initial excavation stage. The guide is extended to the lower shaft bottom after starting the shield machine while being supported by diagonal members. With the work lift according to the present invention, the following effects can be obtained.

ア 本設リフトとして先行設置できるため、シールド機の到達後、立坑内部構築において撤去が不要となり引き続き活用ができることにより、仮設リフトを不用とし、工期と工費の縮減が図れる。 A Since it can be installed in advance as a permanent lift, it is not necessary to remove it in the construction of the shaft after the shield machine arrives, so it can be used continuously, making it unnecessary to use a temporary lift and reducing the work period and cost.

イ 立坑内部構築工事として、前半には、柱材及び水平材を初期掘進時に併せて設置でき、後半には、本設の床や階段及び換気設備を、到達後において井形外部のシールド掘進工事のための動力線や配管類などを撤去すれば、トンネル坑内設備工事の物流に支障なく設置できるため、他工事の支障とならない。 In the first half, pillars and horizontal members can be installed during the initial excavation in the first half, and the floor, stairs, and ventilation equipment for the main building are installed in the first half for shield excavation work outside the well. If the power line and piping are removed, it can be installed without any trouble in the distribution of tunnel tunnel equipment construction, so other construction will not be hindered.

ウ シールド掘進工事に留まらず、立坑内部構築工事とトンネル坑内設備工事の物流も、常に途絶させず、工事全体を効率化する。 C) Not only shield excavation work, but also the construction of shafts and the construction of tunnel tunnels will not be interrupted at all times, improving the efficiency of the entire work.

エ ケージ昇降用のガイドを、立坑の内壁面に接することなく、井形内部にて水平材に取り付けるので、ここを昇降するケージ内の軌条が、トンネル坑内の中央付近の軌条に直接降下・接続できる。それにより、ケージ内のセグメント台車は、そのままトンネル坑内の軌条に入線することができるため、従来同ガイドが立坑内壁面に接する場合に必要となるセグメントの受け渡しの設備や作業を省くことができ、サイクルタイムが短縮する。 The guide for raising and lowering the cage is attached to the horizontal material inside the well without touching the inner wall of the shaft, so that the rail in the cage that moves up and down can be lowered and connected directly to the rail near the center of the tunnel shaft. . As a result, since the segment carriage in the cage can be directly entered into the rail in the tunnel mine, it is possible to omit the segment delivery equipment and work required when the guide is in contact with the vertical wall of the shaft, Cycle time is shortened.

オ 地上ヤードにおいて、トンネル坑内と同様に、トンネルの軸方向に軌条を配するので、ケージ内部の台車はそのまま、短辺の開閉口から軸方向に双方の軌条に入線できる。これにより、地上から掘進に必要な他の配管材やレール材も、トンネル坑内にシームレスに入線できるため、物流効率の向上が図れる。 In the ground yard, rails are arranged in the axial direction of the tunnel as in the tunnel mine, so that the carriage inside the cage can be directly connected to both rails in the axial direction from the short side opening and closing port. As a result, other piping materials and rail materials necessary for excavation from the ground can be seamlessly entered into the tunnel mine, thereby improving distribution efficiency.

カ ケージ昇降用のガイドを保持する仮設支柱や仮設ブラケットが不要となり、コストダウンが図れる。 There is no need for a temporary support column or temporary bracket to hold the guide for raising and lowering the cage, thus reducing costs.

キ 工事用リフトは専用搬送装置でないことから、台車の積載がない場合には、タイヤ車両や作業員の搬送も可能となる。また、トンネル坑内において、床版下方をセグメント台車の搬送路とし、床版上方をPca床版の搬送路とし、ケージを両2階層に停止させれば、両資材を効率よく搬送できる。 Since the construction lift is not a dedicated transport device, it is possible to transport tire vehicles and workers when there is no truck loaded. Further, in the tunnel mine, if the lower part of the floor slab is used as the transport path for the segment carriage, the upper part of the floor slab is used as the transport path for the Pca floor slab, and the cage is stopped at both two levels, both materials can be transported efficiently.

ク セグメント台車を積載したケージは大重量であるところ、ケージ、釣り合い錘を受ける滑車及び巻き上げ機の重量を、堅牢な井形状構造体の水平材を通じて柱材で安定して支持できるため、揺れを抑制し昇降をスムーズにできる。 The cage loaded with the k-segment truck is heavy, and the weight of the cage, pulleys that receive the counterweight, and the hoisting machine can be stably supported by the pillar material through the solid material of the solid well-shaped structure. It can be suppressed and lifted smoothly.

ケ 工事用リフトの運転に際して、ケージレベルの水平性や昇降速度を計測管理しつつ、複数の巻き上げ機を同調制御するので、異常な振動や傾斜などを抑止しつつ、高速運転できる。 I When operating a lift for construction work, it is possible to operate at high speed while suppressing abnormal vibrations and inclinations, etc., because it controls and synchronizes a plurality of hoisting machines while measuring and managing the level and lifting speed at the cage level.

次に、本発明に係る立坑内部構造は、プレキャスト部材を組み立てるものとし、交差部材で交差する、井形状の構築部材の重層構造であり、交差部材において、鉛直間は柱材で連結、水平間は水平材で連結、柱材の下方で框上面の斜材に支持し、交差部材と立坑内壁面は接続材にて離隔を調整しつつ接続・保持される。これにより、以下の作用効果を奏することができる。   Next, the vertical shaft internal structure according to the present invention is a multi-layered structure of well-shaped construction members that preassembles precast members and intersects with crossing members. Are connected by a horizontal member, and supported by a diagonal member on the upper surface of the eaves below the column member, and the cross member and the inner wall surface of the shaft are connected and held while the separation is adjusted by the connecting member. Thereby, the following effects can be obtained.

コ プレキャスト化により立坑底部より順に組み立てる型枠支保工は不用となり、構築時、トンネル坑内への物流は途絶しない。そのため、並行して施工するシールド掘進工事、トンネル坑内設備工事を遅延させない。 As a result of co-casting, the formwork support work that is assembled in order from the bottom of the shaft becomes unnecessary, and distribution to the tunnel mine is not interrupted during construction. Therefore, shield excavation work and tunnel pit equipment work to be performed in parallel are not delayed.

サ 斜材を設置することにより、初期掘進の段階に、立坑底部で分割したシールド機を組立てしていても、これにプレキャスト部材の組立は支障しない。そのため、シールド機組立用の大型クレーンにて引き続き効率よく、これらプレキャスト部材を組み立てることができ、新たな大型クレーンを必要とせず、工期及び工費の低減が図れる。 By installing the diagonal material, even if the shield machine divided at the bottom of the shaft is assembled at the initial excavation stage, the assembly of the precast member is not hindered. Therefore, these precast members can be assembled efficiently and efficiently with a large crane for assembling a shield machine, and a new large crane is not required and the construction period and cost can be reduced.

シ 斜材の機能により、立坑内部構造のプレキャスト部材は、シールド機組立以降の初期掘進中の組立とできるので、1台の大型クレーンを兼用でき、クレーンブームの防音ハウスの屋根に障害する問題は、防音ハウスを初期掘進中に壁のみ先行設置して最小限の遮音を実現し、残る屋根は、本掘進の本格的な昼夜の騒音発生前に大型クレーンを撤去して設置すれば、これ以降完全遮音できる。これにより、周辺に騒音を波及させることなく、スムーズに全体の工期短縮が図れる。 With the function of diagonal materials, the precast member of the shaft internal structure can be assembled during the initial excavation after the shield machine assembly, so it can be used as one large crane, and the problem of hindering the roof of the soundproof house of the crane boom is In the initial excavation, only the walls are installed in advance to achieve the minimum sound insulation, and the remaining roof can be removed by installing a large crane before the full day and night noise of the main excavation. Sound insulation is possible. As a result, the entire construction period can be shortened smoothly without causing noise to spread to the periphery.

ス 斜材は、その部材特性により、立坑内壁面と框上面の交差付近より上方の柱材に斜め内側に、柱荷重に対して圧縮材として配置してもよい。また、斜材は、任意の層の水平材及び柱材の交差部からその上方の立坑内壁面の接続材の接続部に斜め外側に引っ張り材として配置してもよい。これにより、プレキャスト部材の構成を自在に選定できる。 Depending on the characteristics of the members, the diagonal members may be placed as a compression member against the column load, diagonally inside the column material above the vicinity of the intersection between the shaft inner wall surface and the upper surface of the shaft. Further, the diagonal member may be disposed as a tensile member diagonally outward from the intersection of the horizontal member and the pillar member of an arbitrary layer to the connecting portion of the connecting member on the inner wall surface of the vertical shaft. Thereby, the structure of a precast member can be selected freely.

セ 昼間作業の機械調整が主となる初期掘進中に、斜材を利用した立坑内部構造のプレキャスト部材の大半を夜間作業にてその上方に構築する。その後、シールド機が土中に貫入発進すれば、立坑底部の空いたスペースに最下方の柱をリフトのガイドとともに延伸するので、本掘進時には必要なセグメントなどの物流経路を速やかにリフトにて確保でき、無駄なく全体の工期短縮が図れる。 During the initial excavation, which mainly involves machine adjustment for daytime work, most of the precast members of the shaft internal structure using diagonal materials are constructed above it for nighttime work. After that, if the shield machine penetrates into the ground and starts, the bottom pillar is extended with the lift guide in the empty space at the bottom of the shaft. And the entire construction period can be shortened without waste.

ソ 柱材は、中空のプレキャスト材の構造とし、また、シールド機発進以降に、最下方の柱材を立坑底部へ延伸し、内部に軸圧縮力に耐荷性の高いコンクリートを充填して、最終的に斜材を撤去し受け替える。これにより、仮設系では、軽量な中空のプレキャスト材を短期間で組立てられ、完成系では、さらに大重量の設備荷重に耐え得る構造にすることができる。 The pillar material has a hollow precast structure, and after the shield machine starts, the bottom pillar material is extended to the bottom of the shaft, and the interior is filled with concrete with high load resistance against axial compression force. The diagonal is removed and replaced. Thereby, in a temporary system, a lightweight hollow precast material can be assembled in a short period of time, and in a completed system, it can be set as a structure which can endure a heavy equipment load.

タ 交差部材は、6方(水平前後左右及び鉛直上下)で各部材を分断できるから、各プレキャスト材は細分化し、クレーン能力上の揚重不能や、公道運搬上の運搬不能の場合の問題を解決する。また逆に、支障のない限りまで一体化できるから、架設や運搬の効率を最大化できる。 The cross members can divide each member in 6 directions (horizontal front and back, left and right and vertical top and bottom), so each precast material is subdivided, and there is a problem in the case that it is impossible to lift on the crane capacity or transport on public roads. Solve. Conversely, since it can be integrated as long as there is no hindrance, the efficiency of erection and transportation can be maximized.

チ 交差部材は、6方(水平前後左右及び鉛直上下)で各部材を自在に分断できるから、架設時に、柱材と立坑内壁面との離隔を微調整できる2方の接続材を予め一体化して架設すれば、この平面位置を精度よく効率的に固定できる。併せて設置する水平材には、シールド掘進工事のための動力線や配管類、ベルトコンベヤー、昇降階段などが即座に設置できる。よって、これらプレキャスト部材の組立は、初期掘進の工程に遅延を生じさせない。 H Cross members can be divided into 6 directions (horizontal front / back / left / right and vertical top / bottom) freely, so when connecting, two connecting materials that can finely adjust the separation between the pillar material and the inner wall surface of the shaft are integrated in advance. This flat position can be fixed accurately and efficiently. The horizontal material to be installed can be immediately installed with power lines, piping, belt conveyors, ascending / descending stairs, etc. for shield excavation work. Therefore, the assembly of these precast members does not cause a delay in the initial excavation process.

ツ 架設時に、予め地上ヤードで、大型クレーンによって、少なくとも交差部材、水平材を矩形に水平に一体化し、架設済の4本の柱材に嵌合する形で一体架設すれば、さらに初期掘進の工程を短縮できる。一方で、 Tsu At the time of erection, if at least the crossing member and the horizontal member are integrated horizontally in a rectangular shape with a large crane in advance in the ground yard, and if they are erected integrally with the four pillar members that have already been erected, further initial digging The process can be shortened. On the other hand,

テ 補強材としてさらに、交差部の取り合いに火打ち材や、水平材取り合いに新たな柱材を入れれば全体の剛性を著しく向上できる。また予め、床や階段を水平材に取り付ければ、立坑内部構築工事を簡略化でき工期を短縮できる。 As a reinforcing material, the overall rigidity can be remarkably improved by adding fire struts to the intersections and new pillars to the horizontal joints. Moreover, if floors and stairs are attached to a horizontal member in advance, the construction work inside the shaft can be simplified and the construction period can be shortened.

ト 水平材は、トンネルの軸方向と一方向が合致するから、組み立て途上に、井形外部にシールド掘進工事のための動力線や配管類、ベルトコンベヤー、昇降階段などを即座に設置でき、井形内部にはリフトと材料搬入開口が設置でき、設備上不都合はない。よって、初期掘進及び本掘進を効率化すると共に、このことは矩形又は円形の立坑形状を選ばない。 G Since the horizontal material matches the axial direction of the tunnel, the power line, piping, belt conveyor, elevating stairs, etc. for shield excavation work can be installed immediately outside the well during assembly. There is no inconvenience in equipment because a lift and a material loading opening can be installed. Therefore, the initial excavation and the main excavation are made efficient, and this does not select a rectangular or circular shaft shape.

ナ 井形状の構築部材を全てメタルで構成すれば、その軽量ゆえに、重層の一括架設などにより、施工を高速化する。 If all of the well-shaped construction members are made of metal, the construction will be speeded up, for example, by laying multiple layers together.

二 井形状の構築部材を構成するトンネル横断方向の水平材について、立坑底部の坑内物流を遮断する新たな柱材を補強材として配置できないため、仮設時には軽量な鋼材を配し、到達後の完成段階には、この鋼材を外包するよう配筋の上、安価な現場打のポストテンション方式のプレストレストコンクリート構造として構成する。これによれば、桁剛性を増大できるので、フルメタルに比べさらに材料費用を減じることができる。 As for the horizontal material in the tunnel crossing direction that constitutes the well-shaped construction member, a new pillar material that blocks the underground logistics at the bottom of the shaft cannot be placed as a reinforcing material. In the stage, the steel material is arranged in an external post-tensioned prestressed concrete structure with a reinforcement to enclose the steel material. According to this, since the girder rigidity can be increased, the material cost can be further reduced as compared with the full metal.

ヌ 井形状の構築部材を初期掘進時に先行して構築することから、シールド掘進工事で通常必要となる動力線や配管類、ベルトコンベヤー、昇降階段などのための仮設ステージや仮設ブラケットを代替でき、この分の工費を縮減できる。 Since a well-shaped construction member is constructed prior to the initial excavation, it can replace temporary stages and temporary brackets for power lines and piping, belt conveyors, elevating stairs, etc. that are normally required for shield excavation work. This cost can be reduced.

ネ 接続材は、立坑内壁面の接続部に予め内壁にアンカー固定する概箱断面の受け材に、接続材側から突出するアンカーをモルタル定着にて接合するので、柱材の位置と立坑の内壁面との離隔を自在に調整可能にする。よって、立坑躯体の内壁面の施工精度が悪くても、立坑内部構造体を精度よく設置できる。 The connecting material is joined to the receiving material of the cross section of the box that is anchored to the inner wall in advance at the connecting part of the inner wall of the shaft, and the anchor protruding from the connecting material side is joined by mortar fixing. The distance from the wall can be adjusted freely. Therefore, even if the construction accuracy of the inner wall surface of the shaft shaft is poor, the shaft internal structure can be installed with high accuracy.

ノ 接続材は、2方向にて、立坑内壁面に予め固定する受け材との仮ボルトにて、柱材の位置を調整するから、架設の効率がよい。 Since the connecting material adjusts the position of the column material in two directions with a temporary bolt with a receiving material fixed in advance to the inner wall surface of the shaft, the efficiency of the construction is good.

ハ 接続部は、接続材と受け材を一体化するアンカーの径や本数、モルタル強度などにより、自在に剛性を変更でき、設計の自由度を拡大する。 C The connection part can be freely changed in rigidity according to the diameter and number of anchors integrating the connecting material and the receiving material, the mortar strength, etc., and the degree of freedom in design can be expanded.

ヒ 接続部は、接続材と受け材を一体化するアンカーを定着するモルタル部を地震振動に対し局部破損するように構成することにより、耐震性を高めつつ、立坑躯体の損壊を防止でき、損壊復旧のコストを最小化できる。 The connecting part is constructed so that the mortar part that anchors the anchor that integrates the connecting material and the receiving material is locally damaged against earthquake vibration, thereby improving the earthquake resistance and preventing damage to the shaft structure. The cost of recovery can be minimized.

さらに、本発明に係る資材搬送については、軌条を、ケージ内部、地上ヤード及び坑内においてトンネル軸方向に敷設し、資材搬送台車にICタグリーダを搭載し、各資材にはその内容を、また、搬送箇所の各位置や各距離程にはその位置を示すICタグを設置する。そして、資材搬送台車に搭載したICタグリーダによりこれらICタグを読み取り、時系列に遠隔集中管理することにより、以下の作用効果を奏することができる。   Furthermore, for material transportation according to the present invention, rails are laid in the tunnel axial direction inside the cage, on the ground yard and in the mine, and an IC tag reader is mounted on the material transportation carriage. An IC tag indicating the position is installed at each position and distance. Then, by reading these IC tags with an IC tag reader mounted on the material transport carriage and performing remote centralized management in time series, the following effects can be obtained.

フ トンネル隅々へ行き渡るシームレスな軌条上に存在する各資材に対して、時系列の所在や状況を遠隔集中管理できるので、誤搬送を防止し、欠品補充の効率が向上する。 It is possible to remotely manage the location and situation of the time series for each material that exists on the seamless rail that runs through every corner of the tunnel, thus preventing erroneous transport and improving the efficiency of stocking missing items.

ヘ ICタグを、各作業員のヘルメットなどにも同様に具備すれば、労務、安全管理の精度を向上できる。 If the IC tag is also provided in each worker's helmet, etc., the accuracy of labor and safety management can be improved.

ホ シールド掘進工事、立坑内部構築工事及びトンネル坑内設備工事に至る工事全体の物品管理や品質管理に対して、その効率と精度の向上が図れる。 E. It is possible to improve the efficiency and accuracy of the article management and quality control of the entire construction from shield excavation work, vertical shaft construction work and tunnel tunnel construction work.

マ 立坑上部の地上ヤードに敷設される軌条は、堅牢な井形状構造体の水平材を通じて柱材で安定して支持できるため、別途立坑上部に橋梁は不用となり、構造上安定性が高い。 The rails laid in the ground yard above the vertical shaft can be stably supported by the pillar material through the horizontal material of the solid well-shaped structure, so there is no need for a bridge at the top of the vertical shaft and the structural stability is high.

図1は、工事用リフトの構造の概観をトンネルの横断面(幅)方向から示す図である。FIG. 1 is a diagram showing an overview of the construction of a work lift from the direction of the cross section (width) of the tunnel. 図2は、図1の機械室近傍の構造及びトンネル近傍の構造を拡大した図である。FIG. 2 is an enlarged view of the structure in the vicinity of the machine room and the structure in the vicinity of the tunnel in FIG. 図3は、工事用リフトの構造の概観をトンネルの縦断面(長手)方向から示す図である。FIG. 3 is a diagram showing an overview of the construction of the work lift from the longitudinal section (longitudinal) direction of the tunnel. 図4は、図3の機械室近傍の構造及びトンネル近傍の構造を拡大した図である。FIG. 4 is an enlarged view of the structure in the vicinity of the machine room and the structure in the vicinity of the tunnel in FIG. 図5は、工事用リフトの立坑内における鉛直方向の各位置での断面を示す図である。FIG. 5 is a view showing a cross section at each position in the vertical direction in the shaft of the work lift. 図6は、立坑をトンネルの掘削位置まで掘り下げて基本形状を形成した時点を示す図である。FIG. 6 is a diagram illustrating a point in time when the basic shape is formed by digging the vertical shaft to the excavation position of the tunnel. 図7は、シールド機をトンネルの掘削位置まで搬入させた時点を示す図である。FIG. 7 is a diagram illustrating a point in time when the shield machine is brought into the tunnel excavation position. 図8は、立坑躯体に第1層目の井形状構造体を設けた時点を示す図である。FIG. 8 is a view showing a point in time when the first-layer well-shaped structure is provided on the shaft shaft. 図9は、立坑躯体の框上面より上部に立坑内部構造体を構築した時点を示す図である。FIG. 9 is a diagram illustrating a point in time when the shaft internal structure is constructed above the vertical surface of the shaft shaft. 図10は、立坑底部に残る立坑構造体の構築を開始した時点を示す図である。FIG. 10 is a diagram showing a point in time when construction of the shaft structure remaining at the bottom of the shaft is started. 図11は、立坑の内部構造体が完成し、工事用リフトが設置されてセグメント台車が立坑の底部まで降ろされた時点を示す図である。FIG. 11 is a diagram illustrating a point in time when the internal structure of the shaft is completed, the construction lift is installed, and the segment cart is lowered to the bottom of the shaft. 図12は、ケージにより立坑の底部に降ろされたセグメント台車が資材搬送台車に連接された様子を示す平面図である。FIG. 12 is a plan view showing a state where the segment cart lowered to the bottom of the shaft by the cage is connected to the material transport cart. 図13は、斜材を、引っ張り材として作用する形態で配置する場合を示す図である。FIG. 13 is a diagram illustrating a case where the diagonal member is arranged in a form that acts as a tension member. 図14は、交差部材と柱材との嵌合の手順を示す図である。FIG. 14 is a diagram illustrating a procedure for fitting the cross member and the column member. 図15は、接続材を立坑内壁面と柱材との離隔を微調整しつつ設置する手順を示す図である。FIG. 15 is a diagram showing a procedure for installing the connecting material while finely adjusting the separation between the shaft inner wall surface and the pillar material. 図16は、中空のプレキャスト柱材の構造を示す図である。FIG. 16 is a diagram showing a structure of a hollow precast column material. 図17は、中空のプレキャスト柱材の場合の嵌合の手順を示す図である。FIG. 17 is a diagram showing a fitting procedure in the case of a hollow precast column. 図18は、立坑の底部から井形状構造体を構築する工程(ステップd〜ステップf)を示す図である。FIG. 18 is a diagram illustrating a process (step d to step f) for constructing a well-shaped structure from the bottom of a vertical shaft. 図19は、立坑の底部から井形状構造体を構築する工程(ステップg〜ステップi)を示す図である。FIG. 19 is a diagram illustrating steps (step g to step i) for constructing a well-shaped structure from the bottom of a vertical shaft. 図20は、立坑・シールド工事の工程例を線表で示す図である。FIG. 20 is a diagram illustrating an example of a shaft / shield construction process.

本発明を実施するための形態として、以下図面を参照にしながら、本発明に係る実施例を説明する。すなわち、立坑内部構造の好適な例、立坑内部構築工事とシールド掘進工事やトンネル坑内設備工事とを同時並行する例等について説明する。   As modes for carrying out the present invention, embodiments according to the present invention will be described below with reference to the drawings. That is, a suitable example of the shaft internal structure, an example in which the shaft internal construction work, the shield tunneling work, and the tunnel tunnel equipment work are simultaneously performed will be described.

(1)工事用リフト
図1は、立坑内部に設けた工事用リフトの構造の概観をトンネルの横断面(幅)方向から示す図である。図2は、図1の地上の機械室4近傍の構造(上図)およびケージ1を含むトンネル近傍の構造(下図)を拡大した図である。
(1) Construction Lift FIG. 1 is a diagram showing an overview of the construction of a construction lift provided inside a shaft from the direction of the cross section (width) of the tunnel. FIG. 2 is an enlarged view of the structure in the vicinity of the machine room 4 on the ground (upper figure) and the structure in the vicinity of the tunnel including the cage 1 (lower figure) in FIG.

工事用リフトは、立坑内の地上からトンネルまでの間で、ケージ1及びその重量との釣り合いをとるための釣り合い錘2を昇降させる装置である。この昇降用の巻き上げ機3は、複数台から成り、立坑直上に設置した機械室4上部に材柱に支持させて設置される。運転に際しては、ケージレベルの水平性や昇降速度を計測管理しつつ、複数の巻き上げ機3を同調制御する。   The construction lift is a device that lifts and lowers the balance weight 2 for balancing the cage 1 and its weight between the ground in the shaft and the tunnel. The hoisting machine 3 for raising and lowering is composed of a plurality of units, and is installed on the upper part of the machine room 4 installed immediately above the shaft while being supported by a material column. During operation, a plurality of hoisting machines 3 are synchronously controlled while measuring and managing the levelness of the cage level and the lifting speed.

立坑は、図2に示すように、水平材6及びこの水平材6を支持する鉛直方向の柱材5とから構成される井形状構造体によって形成される。なお、この柱材5は、最終的にはトンネル位置まで形成されるところ、初期掘進時にシールド機が発進する前の段階では、框上面より斜材によって支持される構造である。この点については後述する。   As shown in FIG. 2, the vertical shaft is formed by a well-shaped structure including a horizontal member 6 and a vertical column member 5 that supports the horizontal member 6. The pillar material 5 is finally formed up to the tunnel position, and is a structure supported by the diagonal material from the upper surface of the eaves before the shield machine starts at the time of initial excavation. This point will be described later.

工事用リフトの昇降用ガイドは、上述の井形状構造体の内部において水平材に保持される。また、工事用リフトの設置位置としては、ケージ1の背面(開閉口対面)がトンネルの横断方向の一端面に位置するように設置する。   The lifting guide for the construction lift is held by a horizontal member inside the well-shaped structure. The construction lift is installed such that the rear surface of the cage 1 (facing the opening / closing opening) is located at one end surface in the transverse direction of the tunnel.

図3は、立坑内部に設けた工事用リフトの構造の概観をトンネルの縦断面(長手)方向から示す図である。図4は、図3の地上の機械室4近傍の構造(上図)およびケージを含むトンネル近傍の構造(下図)を拡大した図である。   FIG. 3 is a view showing an overview of the structure of the work lift provided inside the shaft from the longitudinal section (longitudinal) direction of the tunnel. FIG. 4 is an enlarged view of the structure in the vicinity of the machine room 4 on the ground in FIG. 3 (upper figure) and the structure in the vicinity of the tunnel including the cage (lower figure).

地上側で資材搬送台車9により搬送されたセグメント台車11は、ユニット単位(図では、2台で1ユニット)でケージ1に搬入され、ケージ1は巻き上げ機3によってトンネル位置まで降下される。セグメント台車11は、トンネル位置に到達すると、トンネル内を搬送させる別の資材搬送台車9に連結され、トンネル内を移動する。   The segment cart 11 transported by the material transport cart 9 on the ground side is carried into the cage 1 in unit units (two units in the figure), and the cage 1 is lowered to the tunnel position by the hoisting machine 3. When the segment cart 11 reaches the tunnel position, it is connected to another material transport cart 9 that transports the inside of the tunnel, and moves in the tunnel.

図5は、工事用リフトの立坑内における鉛直方向の各位置での断面を示す図(平面図)で、例えば、図4に示す矢印断面の平面図である。図5(a)は、機械室4内で巻き上げ機3の設置位置での平面図、図5(b)は、立坑内の一断面の平面図、図5(c)は、トンネル位置にあるケージ1が何も載せていない時の平面図、図5(d)は、トンネル位置にあるケージ1がセグメント台車11を載せ資材搬送台車9に連結されている時の平面図である。   FIG. 5 is a diagram (plan view) showing a cross section at each position in the vertical direction in the shaft of the construction lift, for example, a plan view of the cross section of the arrow shown in FIG. FIG. 5A is a plan view at the installation position of the hoisting machine 3 in the machine room 4, FIG. 5B is a plan view of a section in the shaft, and FIG. 5C is at the tunnel position. FIG. 5 (d) is a plan view when the cage 1 at the tunnel position is loaded with the segment carriage 11 and connected to the material transport carriage 9.

図5(a)〜(c)に示すように、ケージ1と釣り合い錘2を、ワイヤーにより滑車を介して4点で直接接続する。複数の巻き上げ機3は、機械室4の上部に点対称に設置され(図5(a))、複数の巻き上げ機3から滑車を介して、ケージ1の上面に点対称にワイヤーを接続して昇降動力の伝達を行う。滑車に関しては、ケージ1と釣り合い錘2の重量を受けることになるところ、柱材5上部の機械室4に配置されるので、それら重量は、柱材5で安定して支持される。また、図5(b)に示すように、ケージ1と釣り合い錘2の昇降時のガイドとなるガイド8及びガイドフレーム7が、立坑の井形状構造体の内部に設置保持される。   As shown in FIGS. 5A to 5C, the cage 1 and the counterweight 2 are directly connected to each other at four points via a pulley by a wire. The plurality of hoisting machines 3 are installed point-symmetrically on the upper part of the machine room 4 (FIG. 5A), and wires are connected to the upper surface of the cage 1 in a point-symmetrical manner from the plural hoisting machines 3 via pulleys. Transmits lifting power. As for the pulley, the weight of the cage 1 and the counterweight 2 is received. However, since the pulley is disposed in the machine room 4 above the column member 5, the weight is stably supported by the column member 5. Moreover, as shown in FIG.5 (b), the guide 8 used as the guide at the time of raising / lowering of the cage 1 and the balance weight 2 and the guide frame 7 are installed and hold | maintained inside the well-shaped structure of a shaft.

(2)立坑内部構造
立坑の内部構造として、立坑の生成から内部構造体の初期形成、工事用リフトの設置を経て最終的な内部構造体を形成するまでを、6つのステップに分けて順に説明する。
図6〜図11は、立坑の内部構造構築までの過程をステップ1〜6として示す図である。
図6は、ステップ1として、土留め壁の設置後、トンネルの掘削位置まで掘り下げた上で、立坑躯体の基本形状を形成した時点を示す図である。
(2) Vertical shaft internal structure The internal structure of the vertical shaft is divided into six steps from the generation of the vertical shaft to the initial formation of the internal structure and the final internal structure through the installation of the construction lift. To do.
FIGS. 6-11 is a figure which shows the process until the internal structure construction of a shaft as steps 1-6.
FIG. 6 is a diagram showing a point in time when the basic shape of the shaft shaft is formed after stepping down to the excavation position of the tunnel after the installation of the retaining wall as Step 1.

本発明に係る立坑は、後述する斜材をその上方に設置できる框上面を、立坑躯体の途中部分の所定高さの位置に設けることを特徴とする。立坑として、まず土留壁が、次いで立坑躯体が形成され、その際に框上面が形成される。ここで框上面は、水平でも傾斜でもよい。前者は構築が容易な反面、応力集中による脆弱不安があり、後者はその逆の特徴がある。また、図6のA断面平面図に示すように、トンネルの掘進を始めるためのエントランス開口が形成され、シールド機の貫入時の止水性能を確保し、切削し掘進することができる。框部以下がその上部に比べ壁厚が増大することで、エントランス開口の断面欠損に対し、構造壁の耐力低下を補う効果がある。他方、地上ヤードには、工事騒音を遮音するための防音壁が、周囲を一定程度の高さで作業帯を囲う形で設置される。   The vertical shaft according to the present invention is characterized in that a vertical surface on which a diagonal member, which will be described later, can be installed, is provided at a predetermined height in the middle of the vertical shaft. As a vertical shaft, a retaining wall is first formed, and then a vertical shaft body is formed, and a vertical surface is formed at that time. Here, the upper surface of the ridge may be horizontal or inclined. While the former is easy to build, there is a fear of weakness due to stress concentration, and the latter has the opposite feature. Moreover, as shown in the A sectional plan view of FIG. 6, an entrance opening for starting tunnel excavation is formed, so that the water stop performance at the time of penetration of the shield machine can be secured, and cutting and excavation can be performed. By increasing the wall thickness below the buttocks compared to the upper part, there is an effect of compensating for a decrease in the proof stress of the structural wall against the cross-sectional defect of the entrance opening. On the other hand, in the ground yard, a soundproof wall for insulating construction noise is installed around the work zone at a certain height.

図7は、ステップ2として、シールド機を搬入させた時点を示す図である。シールド機組立用の大型クレーンを地上ヤードに設置し、地上ヤードまで持ち込んだ分割したシールド機をこの大型クレーンを使用して立坑の底部のトンネルの掘削位置まで順次荷卸しをする。立坑の底部には架台を設け、その上に分割したシールド機が、大型クレーンによって一体に組立てつつ載置される。シールド機は、図7のB断面平面図に示すように、エントランス側にカッタフェースを対向させて載置される。また、地上ヤードにおいては、防音壁に屋根をかけた防音ハウスを設置する。ただし、大型クレーンの稼働範囲及び期間は、クレーンブームの障害のため、屋根の一部に欠損を設けざるを得ないため、屋根を欠損させる壁部のみにより必要最小限の遮音を行う。   FIG. 7 is a diagram showing a point in time when the shield machine is carried in as Step 2. A large crane for assembling the shield machine is installed in the ground yard, and the divided shield machine brought to the ground yard is sequentially unloaded to the excavation position of the tunnel at the bottom of the shaft using this large crane. A stand is provided at the bottom of the shaft, and the shield machine divided thereon is placed while being assembled together by a large crane. As shown in the B cross-sectional plan view of FIG. 7, the shield machine is placed with the cutter face facing the entrance side. In the ground yard, a soundproof house with a soundproof wall covered with a roof will be installed. However, the operating range and period of the large crane is limited to the necessary sound insulation only by the walls that cause the roof to be damaged because the crane boom is obstructed and a part of the roof must be damaged.

図8は、ステップ3として、立坑躯体に第1層目の井形状構造体を設けた時点を示す図である。この第1層目として、立坑躯体の框上面から、図8のD断面平面図に示す配置構造を形成するために、交差部材22と結合した斜材24及び接続材23を矩形対角に設置する。設置手順としては、図8の右側中段に示すように、交差部材22と結合した斜材24及び接続材23を、斜材24を框上面に固定させつつ、框上方の、立坑躯体の内壁面に予め設けた2箇所の接続部21の受け材と接続材23を接合することで、立坑躯体の内壁面に固定し、これを矩形対角に4か所設置する。この設置形態では、斜材24は、柱荷重に圧縮材として作用するものである。他に、図13に示すように、斜材24を、引っ張り材として作用する形態で配置してもよい。この場合には、斜材24は、框部上面に配置する交差部材22から框上方の立坑内壁面の接続部21に対して斜め外側に引っ張り材として接続する。組成的には、圧縮に耐荷力のあるコンクリート製が、図8に示す斜材24に適し、座屈しやすく引っ張りに耐荷力のある鋼製が、図13に示す斜材24に適する。尚、接続材23は、立坑内壁面と柱材との離隔を微調整しつつ設置する。   FIG. 8 is a diagram showing a point in time when the first-layer well-shaped structure is provided in the vertical shaft as Step 3. As this first layer, diagonal members 24 and connecting members 23 combined with the crossing members 22 are installed diagonally diagonally to form the arrangement structure shown in the D sectional plan view of FIG. To do. As an installation procedure, as shown in the middle of the right side of FIG. 8, the diagonal member 24 and the connecting member 23 combined with the cross member 22 are fixed to the upper surface of the diagonal member 24, and the inner wall surface of the shaft shaft above the vertical shaft. By joining the receiving material of the connecting portion 21 and the connecting material 23 provided in advance at the two locations, the shaft is fixed to the inner wall surface of the shaft shaft, and is installed at four locations on a rectangular diagonal. In this installation form, the diagonal member 24 acts as a compression member on the column load. In addition, as shown in FIG. 13, the diagonal member 24 may be arranged in a form that acts as a tensile member. In this case, the diagonal member 24 is connected to the connecting portion 21 on the inner wall surface of the vertical shaft above the shaft as a pulling material obliquely outward from the cross member 22 disposed on the upper surface of the shaft. In terms of composition, a concrete material having a load resistance against compression is suitable for the diagonal member 24 shown in FIG. 8, and a steel member that is easily buckled and has a load resistance against tension is suitable for the diagonal member 24 shown in FIG. The connecting member 23 is installed while finely adjusting the separation between the shaft inner wall surface and the column member.

図15は、この設置の手順を3つのステップで示す図である(最下図に、受け部を有する受け材が、立坑内壁面の接続部21に予め内壁面にアンカー固定され、接続材23と接合する様子を拡大して示す)。まず、ステップaで、接続材23の接続部21側に突出するアンカー筋を、概箱断面の受け材に挿入し、2方向の接続材23をそれぞれ、交差部材22側は溶接接合し、受け材側は受け部にて仮受けしつつ仮ボルトにて仮固定する。次に、ステップbで、4本の柱材5の芯の平面位置が設計位置に合うように、各柱材5に直交する2方向の接続材23において仮ボルトを緩めつつ位置調整し、再固定しながら、水平材6と交差部材22同志を溶接などにより接合する。この場合、各接続材23は、受け部で仮受けしつつ仮ボルトで仮固定されているから、クレーンの吊りフックより玉かけがはずされても、もはや脱落することはない。最後に、ステップcで、接続材23のアンカー筋の挿入を受ける概箱断面の受け材内部に、無収縮モルタルを充填しアンカー筋を定着し、柱材5の芯の平面位置を本固定する。この際、受け部取り合いの開口部には、モルタル漏出を防止する型枠を組みつける。   FIG. 15 is a diagram showing this installation procedure in three steps (in the bottom view, a receiving material having a receiving portion is anchored to the inner wall surface in advance at the connecting portion 21 of the shaft inner wall surface, Enlarged view of joining.) First, in step a, the anchor bar protruding to the connection portion 21 side of the connection material 23 is inserted into the receiving material of the cross section of the approximate box, and the two-direction connection material 23 is welded to the cross member 22 side, respectively. The material side is temporarily fixed with a temporary bolt while being temporarily received at the receiving portion. Next, in step b, the positions of the four pillar members 5 are adjusted while loosening the temporary bolts in the connecting members 23 in the two directions perpendicular to the pillar members 5 so that the planar positions of the cores of the pillar members 5 match the design positions. While fixing, the horizontal member 6 and the cross member 22 are joined together by welding or the like. In this case, since each connecting member 23 is temporarily fixed with a temporary bolt while being temporarily received by the receiving portion, even if the sling is removed from the hanging hook of the crane, it will no longer fall off. Finally, in step c, the non-shrinkable mortar is filled in the receiving material of the cross section of the box that receives the insertion of the anchor bar of the connecting member 23, the anchor bar is fixed, and the planar position of the core of the column member 5 is permanently fixed. . At this time, a mold for preventing leakage of the mortar is assembled to the opening of the receiving portion.

以上のように、接続材23の再固定を4隅に繰り返し行いつつ、水平材6によって交差部材22同士を縦横に接合して、最終的に接続材を受け材に本固定し、第1層目の井形状構造体を構築する(図8の右側中段)。   As described above, while re-fixing the connecting material 23 at the four corners, the cross members 22 are joined vertically and horizontally by the horizontal material 6, and finally fixed to the receiving material by the first layer. An eye-well structure is constructed (middle of the right side of FIG. 8).

また、一層の井形状構造体の強度を上げるために、この井形状構造体の隅角にさらに火打ち材を組み入れても、4本の柱材の中間に新たな柱材を組み入れてもよい。以上のように、斜材24を用いて立坑躯体の途中部分から井形状構造体を構築することが可能となり、従来の下方から型枠支保工を順に組み立てる工法を不用とし、立坑の底部からトンネル坑内への物流が途絶することを回避できる。この斜材24の効果は、プレキャスト部材を立坑底部から組み上げる構造への適応の場合でも同様である。これにより、物流においては、初期掘削及び本掘進を効率化し、立坑内部構築工事は他工事と並行でき、全体工期を短縮する。   In addition, in order to increase the strength of a single well-shaped structure, a fire striking material may be further incorporated in the corner of the well-shaped structure, or a new pillar material may be incorporated in the middle of the four pillar materials. As described above, it is possible to construct a well-shaped structure from the middle part of the shaft shaft using the diagonal member 24, and the conventional method of assembling the formwork support from the bottom is unnecessary, and the tunnel is formed from the bottom of the shaft. It is possible to avoid the disruption of logistics to the mine. The effect of the diagonal member 24 is the same even when applied to a structure in which the precast member is assembled from the shaft bottom. As a result, in logistics, the initial excavation and the main excavation are made more efficient, and the shaft internal construction work can be performed in parallel with other works, thereby shortening the overall construction period.

図9は、ステップ4として、立坑躯体の框上面より上部に立坑内部構造体を構築した時点を示す図である。
第1層目から順に柱材5で以て上方に井形状構造体を積み上げていく要領で、立坑躯体の框上面より上部に立坑内部構造体を構築する。図9の右側中段に示すように、低い層の交差部材22の上部に結合した柱材5に次の層の交差部材22を結合し、接続材23によって立坑躯体の内壁面に設けた接続部21に仮固定する。それを4隅に行った後に、水平材6によって交差部材22同士を縦横に接合し、接続部21にて立坑内壁との離隔を最終調整の上再固定する。その後、接続部21で接続材23側のアンカー筋を接続部側の受け材内に無収縮モルタル充填し定着することで本固定して、次の層の井形状構造体を構築する。このプロセスを地上部分まで繰り返すことになる。交差部材22は、水平前後左右及び鉛直上下の6方向で各部材を分断するものであって、架設時に、柱材5に連結した上で立坑内周面へ接続材23をその離隔を微調整しつつ接続して、この平面位置を精度よく効率的に固定・保持する。
FIG. 9 is a diagram showing a point in time when a shaft internal structure is built above the vertical surface of the shaft as Step 4.
The shaft internal structure is constructed above the vertical surface of the vertical shaft in the manner of stacking the well-shaped structure upward with the pillar material 5 in order from the first layer. As shown in the middle stage on the right side of FIG. 9, the connecting member provided on the inner wall surface of the shaft shaft by connecting the cross member 22 of the next layer to the column member 5 connected to the upper portion of the cross member 22 of the lower layer and connecting member 23. Temporarily fix to 21. After performing it in the four corners, the cross members 22 are joined to each other vertically and horizontally by the horizontal member 6, and the distance from the shaft inner wall is re-fixed at the connection portion 21 after final adjustment. Thereafter, the anchor bars on the connecting member 23 side are fixed in the connecting member 21 by filling and fixing the non-shrink mortar in the receiving member on the connecting portion side, thereby constructing a well-shaped structure of the next layer. This process will be repeated up to the ground. The cross member 22 divides each member in the six directions of horizontal front and rear, right and left, and vertical top and bottom, and is connected to the column member 5 at the time of erection, and the connection member 23 is finely adjusted to the inner peripheral surface of the shaft. However, the plane position is fixed and held accurately and efficiently while being connected.

ここで、予め地上ヤードで、大型クレーンにて、少なくとも交差部材及び水平材、を井形に地上ヤードにて水平に一体化し、架設済の4本の柱材に嵌合する形で一体架設すれば、さらに作業効率は向上する。さらに、接続材も併せて井形に地上ヤードにて水平に一体化する場合は、架設時、接続材側に一体のアンカー筋が、概箱断面の受け材に対し障害しないよう、接続材側から分離しておき、架設後組み立てれば雑作はない。これらの場合、交差部材22は、架設時に水平材6及び接続材23に連結した上で、立坑内周面に予めアンカー固定する受け材へ接続材23をその離隔を微調整しつつ仮固定して、その後分離しておいたアンカー筋を接続材23と受け材に亘るよう組み立て、ここに無収縮モルタルを充填し定着することで、この平面位置を精度よく効率的に本固定する。   Here, if at least a crossing member and a horizontal member are integrated into a well shape horizontally in a ground yard in a large yard in advance in a ground yard, and are integrated in a form that fits into four already installed pillars. In addition, work efficiency is improved. In addition, when the connection material is also integrated horizontally with the well in the ground yard, when connecting, from the connection material side, the anchor bars integrated on the connection material side should not interfere with the receiving material of the cross section of the box. If it is separated and assembled after erection, there is no miscellaneous work. In these cases, the cross member 22 is connected to the horizontal member 6 and the connecting member 23 at the time of erection, and is temporarily fixed to the receiving member that is anchored in advance to the inner peripheral surface of the shaft while finely adjusting the separation. Then, the anchor bars separated after that are assembled so as to extend over the connecting member 23 and the receiving member, and the non-shrinkage mortar is filled and fixed therein, thereby fixing the plane position with high accuracy and efficiency.

図14に、交差部材22と柱材5との嵌合の手順を示す。交差部材22の柱材接合部分の下端部に凸形状の突起部分を、また上端部に凹形状の孔部分を設け、柱材5の交差部材22との接合部分の下端部に凸形状の突起部分(図示せず)を、また上端部に凹形状の孔部分を設け、双方を鉛直方向に嵌合する。また、柱材に対し、交差部材を工場製作段階で一体に形成することによっても、架設時の部材重量は増加する反面、嵌合箇所は半減しつつ、同様の効果が得られる。またこれらの場合、嵌合の凹凸を逆にしてもよい。
また、図9のF断面平面図には、その後に設置する工事用リフトのガイドフレーム7及びガイド8を設けた井形状構造体を示す。
FIG. 14 shows a procedure for fitting the cross member 22 and the column member 5 together. Protruding protrusions are provided at the lower end of the column member joint portion of the cross member 22, and concave hole portions are provided at the upper end portion, and the convex protrusion is provided at the lower end portion of the joint portion of the column member 5 with the cross member 22. A part (not shown) and a concave hole part are provided at the upper end, and both are fitted in the vertical direction. In addition, even if the cross members are integrally formed with the pillar material at the factory production stage, the weight of the member at the time of erection increases, but the same effect can be obtained while the fitting portion is halved. In these cases, the unevenness of the fitting may be reversed.
Moreover, the F cross-sectional plan view of FIG. 9 shows a well-shaped structure provided with a guide frame 7 and a guide 8 of a work lift to be installed thereafter.

図10は、ステップ5として、シールド機がエントランスから掘進を始め前進した後に、立坑底部に残る立坑構造体の構築を開始した時点を示す図である。
図10のG断面平面図に示すように、シールド機が前進し立坑の底部が空くと、この底部からも井形状構造体を構築していき、立坑躯体の框上面より上部に既設した井形状構造体に連結することになる。この部分については、底部から框部へ組み上げても、框部から吊り下げつつ底部へ組み下げてもよい。
FIG. 10 is a diagram showing a point in time at Step 5 when the construction of the shaft structure remaining in the shaft bottom is started after the shield machine starts excavating from the entrance and advances.
As shown in the G cross-sectional plan view of FIG. 10, when the shield machine moves forward and the bottom of the vertical shaft is vacant, a well-shaped structure is constructed from this bottom, and the well shape already established above the vertical surface of the vertical shaft It will be connected to the structure. About this part, even if it assembles | assembles from a bottom part to a collar part, it may assemble to a bottom part, hanging from a collar part.

また、この箇所の柱材5を中空のプレキャスト材の構造とし、初期掘進以降に、その内部に軸圧縮力に耐荷性の高いコンクリートを充填して、最終的には、斜材を撤去し受け替えるようにしてもよい。これにより、完成系では、さらに大重量の設備荷重に耐え得る構造にすることができる。   In addition, the column material 5 at this location has a structure of a hollow precast material, and after the initial excavation, the interior is filled with concrete having high load resistance against the axial compression force, and finally the diagonal material is removed and received. You may make it change. As a result, the completed system can have a structure capable of withstanding a larger equipment load.

図16は、中空のプレキャスト柱材の構造を示す図である。上下両端の接合部は、嵌合させるために、放射状に嵌合材を両端の接続リングに固定する。接合の際の手順としては、嵌合の上、平面位置及び高さを設計上の位置に調整後、上下の接続リングを溶接し接合する。
先の図14では、交差部材22と柱材5との嵌合の手順を示したが、図17に、柱材5が中空プレキャスト材の場合の嵌合の手順を示す。嵌合材と接続リングを使った嵌合の手順は、上述の図16の場合と同様である。
FIG. 16 is a diagram showing a structure of a hollow precast column material. In order to fit the joints at both the upper and lower ends, the fitting material is radially fixed to the connection rings at both ends in order to fit. As a procedure at the time of joining, after fitting and adjusting the planar position and height to the designed position, the upper and lower connecting rings are welded and joined.
In FIG. 14, the fitting procedure between the cross member 22 and the pillar material 5 is shown. FIG. 17 shows the fitting procedure when the pillar material 5 is a hollow precast material. The fitting procedure using the fitting material and the connection ring is the same as in the case of FIG.

次に、立坑の底部から井形状構造体を構築する工程(ステップd〜ステップi)を、図18及び図19により説明する。図18に、ステップd〜ステップfを、図19に、ステップg〜ステップiを、それぞれ示す。   Next, the process (step d-step i) which builds a well-shaped structure from the bottom of a shaft will be described with reference to FIGS. FIG. 18 shows step d to step f, and FIG. 19 shows step g to step i.

先ず、図18に示すステップdで、立坑の底部の柱位置に、予め下床に定着する鉄筋と接続リングを固定しておく。続く図18に示すステップeで、中空のプレキャスト柱材5を、立坑の底部の接続リングに、嵌合させつつはめ込み高さを調整し仮溶接する。続いてステップfで、2方向の接続材23で柱材5の立坑内壁面との離隔を調整しつつ、柱材5の各接続リング同士及び水平材6と交差部材22同士を溶接固定する(この手順は、図15による説明と同様)。   First, in step d shown in FIG. 18, a reinforcing bar and a connection ring that are fixed to the lower floor are fixed in advance at the column position at the bottom of the shaft. In the subsequent step e shown in FIG. 18, the hollow precast column 5 is fitted to the connecting ring at the bottom of the shaft while adjusting the fitting height and temporarily welded. Subsequently, in step f, the connection rings 23 of the column member 5 and the horizontal members 6 and the cross members 22 are welded and fixed while adjusting the distance between the column member 5 and the inner wall surface of the shaft with the connection member 23 in two directions ( This procedure is the same as described with reference to FIG.

図19に示すステップgでは、上述のステップd〜ステップfの手順で、框取り合いの段まで、各部材を固定する。次に、ステップhで、接続リングの外面の縦鉄筋をラップ接続しフープ筋を配筋の上、中空部及び接続リングの外面部に型枠を組みつけて高流動コンクリートを打設する。最後に、ステップiで、高流動コンクリートの硬化後、残る最終接合の柱材5を上下に接合する。ここで、最終接合の柱材5は、配筋の上コンクリート打設するRC構造としてもよく、またメタル構造によってもよい。前者は、軸方向の耐力に優れる反面、工程が遅延する。後者は、その逆の効果がある。   In step g shown in FIG. 19, each member is fixed up to the stage where the rivets are joined in the procedure of steps d to f described above. Next, in step h, the vertical reinforcing bars on the outer surface of the connection ring are lap-connected, the hoop bars are arranged, the mold is assembled on the hollow portion and the outer surface portion of the connection ring, and high-fluidity concrete is placed. Finally, in step i, after the high-fluidity concrete is cured, the remaining post-joining column members 5 are joined up and down. Here, the pillar material 5 for final joining may be an RC structure in which the upper concrete is placed, or a metal structure. The former is excellent in axial yield strength, but the process is delayed. The latter has the opposite effect.

図11は、ステップ6として、立坑の内部構造体が完成し、工事用リフトが設置されてセグメント台車11が立坑の底部まで降ろされた時点を示す図である。
上述のように、立坑の底部から構築開始した井形状構造体が、立坑躯体の框上面より上部に既設した井形状構造体に連結されて、立坑全体の内部構造体が完成すると、続いてガイドを設置の上、工事用リフトの据え付け設置を行う。その後には、地上ヤードの大型クレーンを撤去し、防音ハウスの屋根の欠損部を補完して防音ハウスを完成させる。
FIG. 11 is a diagram showing a point in time when the internal structure of the shaft is completed, the construction lift is installed, and the segment carriage 11 is lowered to the bottom of the shaft as step 6.
As described above, the well-shaped structure started to be constructed from the bottom of the shaft is connected to the well-shaped structure existing above the shaft upper surface of the shaft, and the internal structure of the entire shaft is completed. After installation, install the lift for construction. After that, the large crane in the ground yard is removed and the soundproof house is completed by complementing the missing part of the roof of the soundproof house.

また、地下のトンネル側では初期掘進から本掘進に移行し、トンネル内に軌条も敷設され、セグメント台車等の搬入が始まることになる。その際には、図11のI断面図に示すように、ケージ1内に長辺方向に設けた軌条とトンネル内の軸方向の軌条及び地上ヤードの同方向の軌条とが接続されるように構成する。これにより、セグメントは、受け渡しの必要なしにセグメント台車に積載したままで、ケージ1の短辺の開閉口を経由し、地上ヤードからトンネル内にシームレスに運搬できる。   In addition, the underground tunnel side shifts from the initial excavation to the main excavation, rails are also laid in the tunnel, and the delivery of segment carts, etc. begins. At that time, as shown in the I sectional view of FIG. 11, the rail provided in the long side direction in the cage 1 is connected to the rail in the axial direction in the tunnel and the rail in the same direction of the ground yard. Configure. As a result, the segments can be transported seamlessly from the ground yard into the tunnel via the opening on the short side of the cage 1 while being loaded on the segment cart without the need for delivery.

ここで、ケージ1は、セグメント台車等の専用搬送装置とする必要はないことから、台車の積載がない場合には、タイヤ車両や作業員の搬送も可能となる。
さらに、図20に、実施例1及び実施例2に基づく、立坑・シールド工事の工程例を、線表で示す。図に示すとおり、本発明による工程は、従来工程に対して、立坑内部構築工事において、主にプレキャスト化と先行設置により、到達後の同工事期間を著しく短縮できる。
Here, since the cage 1 does not need to be a dedicated transport device such as a segment cart, the tire vehicle and the worker can be transported when the cart is not loaded.
Furthermore, in FIG. 20, the process example of a shaft and shield construction based on Example 1 and Example 2 is shown with a line table. As shown in the figure, the process according to the present invention can significantly shorten the construction period after reaching the conventional process mainly by precasting and prior installation in the shaft internal construction work.

(3)資材搬送台車
図12は、ケージ1により立坑の底部に降ろされたセグメント台車11が資材搬送台車に連結された様子を示す平面図である。
上述のように、ケージ1内底面に設けた軌条と立坑の底部及びトンネル坑内に敷設する軌条とが直に接続できるように、立坑の底部及びトンネル坑内に敷設する軌条の構成(レイアウト)を工夫する。例えば、図12に示すように、立坑の底部及びトンネル坑内の軌条を構成することにより、ケージ1に載置したセグメント台車11を直接に資材搬送台車9に連結させて輸送することができる。ここで、ケージ1内底面に設ける軌条に代替し、例えば、両側の内壁面もしくは天井面に概ビームの軌条を配し、ここにセグメント台車11がローラーを介しガイドを受けるような軌条構成にしても同様の効果が得られる(図示せず)。前者は、設備構成が簡易な反面、床面の軌条がタイヤ車両運搬の際の支障となり、後者は、その逆の特徴を有する。
(3) Material Carriage Cart FIG. 12 is a plan view showing a state in which the segment car 11 lowered to the bottom of the shaft by the cage 1 is connected to the material transport car.
As described above, the configuration (layout) of the rail laid in the bottom of the shaft and the tunnel mine is devised so that the rail provided on the inner bottom surface of the cage 1 and the rail laid in the tunnel and the tunnel mine can be directly connected. To do. For example, as shown in FIG. 12, the segment cart 11 placed on the cage 1 can be directly connected to the material transport cart 9 and transported by configuring the bottom of the shaft and the rails in the tunnel shaft. Here, instead of the rail provided on the inner bottom surface of the cage 1, for example, a rail of an approximate beam is arranged on the inner wall surface or ceiling surface on both sides, and the segment cart 11 receives a guide via a roller. Can achieve the same effect (not shown). The former has a simple equipment configuration, while the rails on the floor obstruct the transportation of the tire vehicle, and the latter has the opposite characteristics.

また、トンネル坑内における資材搬送管理システムを構築するために、資材搬送台車9にICタグリーダ10および無線機(図示せず)を搭載し、セグメント台車の積荷である資材にICタグ12を付帯させる。併せて、トンネル坑内の搬送場所の特定の位置や特定の距離程にその位置を示すICタグを別途設置する(図示せず)。そして、ICタグリーダ10がこれらICタグから読み取った情報を、無線機により坑内ネットワークを介して管理用コンピュータ(図示せず)に送信する。これにより、資材の識別と資材の所在情報等を時系列に記録して管理する。   In order to construct a material transport management system in the tunnel mine, an IC tag reader 10 and a radio (not shown) are mounted on the material transport cart 9, and the IC tag 12 is attached to the material that is the load of the segment cart. At the same time, an IC tag indicating the position at a specific position or a specific distance of the transport location in the tunnel mine is separately installed (not shown). Then, the information read from these IC tags by the IC tag reader 10 is transmitted to a management computer (not shown) via the underground network by a wireless device. Thereby, the identification of the material and the location information of the material are recorded and managed in time series.

ICタグ12は、リーダ/ライタからのエネルギーにて非接触で情報の送受を行うパシッブ型を採用し(ただし、このタイプに限定されるものではないが、メンテナンス等の運用を考慮すると最も効率的)、ICタグ12には、資材識別や所在位置等を示すコードを保持させる。また、ICタグリーダ10がICタグ12から読み取ったデータ等は、データベースとして格納し、資材搬送管理システムにおいて使用する。   The IC tag 12 adopts a passive type that transmits and receives information in a non-contact manner with energy from a reader / writer (however, it is not limited to this type, but is most efficient in consideration of operations such as maintenance) ), The IC tag 12 holds a code indicating material identification, location, and the like. Further, data read from the IC tag 12 by the IC tag reader 10 is stored as a database and used in the material transport management system.

1 ケージ、2 釣り合い錘、3 巻き上げ機、4 機械室、5 柱材、6 水平材、7 ガイドフレーム、8 ガイド、9 資材搬送台車、10 ICタグリーダ、11 セグメント台車、12 ICタグ、21 接続部、22 交差部材、23 接続材、24 斜材

DESCRIPTION OF SYMBOLS 1 Cage, 2 Counterweight, 3 Hoisting machine, 4 Machine room, 5 Column material, 6 Horizontal material, 7 Guide frame, 8 Guide, 9 Material conveyance cart, 10 IC tag reader, 11 Segment cart, 12 IC tag, 21 Connection part , 22 Cross member, 23 Connecting material, 24 Diagonal material

Claims (8)

シールドトンネルの立坑内部構造を構築する構築部材であって
平面視で井形状構造であるプレキャスト部材を当該構築部材の鉛直方向の一層とし、
前記プレキャスト部材は、同一水平面上で前記立坑の内壁面の近傍に矩形対角に設けた4点の交差部と、隣り合う前記交差部を同一水平面内で直交して接続する水平材と、前記交差部それぞれを鉛直方向に隣り合う対応する交差部それぞれと鉛直方向に接続するために少なくとも自らの上端または下端のいずれかが前記交差部と嵌合する柱材と、前記交差部と前記内壁面に設けた接続部それぞれとを個別に接続する接続材とから構成され、前記井形状構造の長辺方向の前記水平材の方向を前記シールドトンネルの軸方向に概ね合致させ
当該構築部材は、前記プレキャスト部材を前記柱材によ鉛直方向に隣り合う前記交差部を連結して複数積層した重層構造である
ことを特徴とする立坑内部構造の構築部材。
A construction member for constructing the internal structure of a shield tunnel shaft,
A precast member having a well-shaped structure in plan view is a layer in the vertical direction of the construction member,
The precast member has a cross-section of the four points provided in a rectangular diagonal in the vicinity of the inner wall surface of the shafts on the same horizontal plane, a horizontal member which connects the intersection adjacent orthogonal in the same horizontal plane, the and the bar material or at least its upper or lower end for connecting the respective intersection portions in a vertical direction and crossing portions, respectively for engagement cormorants corresponds adjacent in the vertical direction is mated with the cross section, the said intersection It is composed of connecting members that individually connect each of the connecting portions provided on the inner wall surface, and the direction of the horizontal member in the long side direction of the well-shaped structure is generally matched with the axial direction of the shield tunnel ,
The construction member construction member of the vertical shaft internal structure which is a layered structure in which a plurality of laminated connecting the intersection adjacent to the precast member by Ri vertically on the pillar <br/>.
請求項1に記載の立坑内部構造の構築部材であって、
前記交差部として配備した交差部材は、前記柱材と一体化した状態で鉛直方向に隣り合う別の交差部材と嵌合により接続する構造である
ことを特徴とする立坑内部構造の構築部材。
A construction member for a shaft internal structure according to claim 1,
The deployed cross-member as intersections, building members of shafts internal structure which is a structure in which more connection to another cross member and the fitting adjacent to the vertical direction in a state integrated with the pillar.
請求項1に記載の立坑内部構造の構築部材であって、
前記交差部として配備した交差部材は、前記水平材と一体化した状態で、鉛直方向上下の前記柱材と嵌合により接続する構造を有し、前記4点の交差部への配備により少なくとも矩形状を構成する
ことを特徴とする立坑内部構造の構築部材。
A construction member for a shaft internal structure according to claim 1,
Cross member which is deployed as the intersection in a state integrated with the horizontal member has a structure in which more connected to the column member and the fitting in the vertical direction up and down, at least the deployment to the four-point intersections The construction member of the shaft internal structure characterized by comprising rectangular shape.
請求項1に記載の立坑内部構造の構築部材であって、
前記接続材は、前記柱材の位置と前記内壁面との離隔を調整可能にする
ことを特徴とする立坑内部構造の構築部材。
A construction member for a shaft internal structure according to claim 1,
The connecting member is a construction member for a shaft internal structure, wherein the distance between the column member and the inner wall surface can be adjusted.
請求項1記載の立坑内部構造の構築部材であって、
前記柱材は、自らの内部にコンクリート充填を可能にする中空構造である
ことを特徴とする立坑内部構造の構築部材。
A construction member for a shaft internal structure according to claim 1,
The column member has a hollow structure that allows concrete to be filled inside itself, and is a construction member for a shaft internal structure.
請求項1に記載の立坑内部構造の構築部材であって、
前記内壁面又は前記トンネルの直上に突出する框部から、前記交差部として配備した交差部材及び前記柱材と接続して当該交差部材及び当該柱材を支持する斜材を有する
ことを特徴とする立坑内部構造の構築部材。
A construction member for a shaft internal structure according to claim 1,
It has an oblique member which supports the cross member and the pillar material by connecting to the cross member and the pillar material provided as the intersection from the inner wall or the flange portion protruding directly above the tunnel. Construction member of the shaft internal structure.
請求項1に記載の立坑内部構造の構築部材に設置する工事用リフトであって、
直方体のケージと、釣り合い錘と、前記ケージと前記釣り合い錘の昇降を案内するガイドと、前記昇降を行う複数の巻き上げ機とを備え、
前記ケージは、当該ケージの短辺側でかつ前記トンネルの断面側の、少なくとも1方の側面に設けた開閉口を有し、前記ケージと前記釣り合い錘は、前記柱材にて支持され、
前記ガイドは、前記水平材の前記4点の交差部の内側に取り付けられ
前記複数の巻き上げ機は、前記重層構造の地上部分に設置される
ことを特徴とする工事用リフト。
A work lift installed on the construction member of the shaft internal structure according to claim 1,
A rectangular parallelepiped cage, a counterweight, a guide for guiding the cage and the counterweight to be raised and lowered, and a plurality of hoisting machines for raising and lowering,
The cage has an opening / closing port provided on at least one side surface on the short side of the cage and on the cross-sectional side of the tunnel, and the cage and the counterweight are supported by the pillar material,
The guide is attached to the inside of the intersection of the four points of the horizontal member ,
The work lift, wherein the plurality of hoisting machines are installed on a ground portion of the multi-layer structure .
請求項7に記載の工事用リフトにより運搬された資材を搬送する資材搬送台車であって、
ICタグリーダ及び無線機を搭載し、前記ICタグリーダが前記資材に付帯させたICタグ及び前記資材を搬送する範囲内の特定箇所や特定距離程に設けたICタグから読み取った情報を前記無線機により管理用コンピュータに送信することを特徴とする資材搬送台車。
A material transport cart for transporting material transported by the construction lift according to claim 7,
An IC tag reader and a wireless device are mounted, and the IC tag attached to the material by the IC tag reader and information read from an IC tag provided at a specific location or a specific distance within a range in which the material is transported by the wireless device. A material transport cart that is transmitted to a management computer.
JP2016095403A 2016-05-11 2016-05-11 Construction material of tunnel shaft internal structure, construction lift and material transport cart Active JP6239686B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016095403A JP6239686B2 (en) 2016-05-11 2016-05-11 Construction material of tunnel shaft internal structure, construction lift and material transport cart

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016095403A JP6239686B2 (en) 2016-05-11 2016-05-11 Construction material of tunnel shaft internal structure, construction lift and material transport cart

Publications (2)

Publication Number Publication Date
JP2017203294A JP2017203294A (en) 2017-11-16
JP6239686B2 true JP6239686B2 (en) 2017-11-29

Family

ID=60321413

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016095403A Active JP6239686B2 (en) 2016-05-11 2016-05-11 Construction material of tunnel shaft internal structure, construction lift and material transport cart

Country Status (1)

Country Link
JP (1) JP6239686B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112412468B (en) * 2020-09-25 2023-10-17 浙江科技学院 Multifunctional anti-blocking and dredging method for blasting and excavation of tunnel ventilation shafts
CN113309523B (en) * 2021-06-04 2023-01-24 上海市基础工程集团有限公司 Large-diameter overall tool type template lifting system for construction of vertical shaft lining wall
CN113389564B (en) * 2021-06-29 2023-09-05 中铁建工集团有限公司 Safety auxiliary structure for underground tunnel construction material
CN115163162B (en) * 2022-07-14 2022-12-16 中国矿业大学(北京) A smoke exhaust and drainage system for construction shafts
CN115749809B (en) * 2022-11-29 2026-01-27 中国电建集团成都勘测设计研究院有限公司 Ultra-deep stratum inclined shaft assembly type construction excavation supporting system

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63110396A (en) * 1986-10-27 1988-05-14 株式会社熊谷組 Mucking device
JPH0694800B2 (en) * 1989-10-06 1994-11-24 清水建設株式会社 Conveyor device using rail traveling type trolley
JP3097010B2 (en) * 1993-05-10 2000-10-10 清水建設株式会社 Elevator device for underground construction and underground construction method using it
JPH0771197A (en) * 1993-09-03 1995-03-14 Komatsu Ltd Segment transfer device
JP2839872B2 (en) * 1996-07-29 1998-12-16 株式会社サノヤス・ヒシノ明昌 Rope elevator for shaft
JP5325351B1 (en) * 2013-03-29 2013-10-23 伊藤忠建機株式会社 Excavation Sediment / Equipment Import / Removal System and Excavation Sediment / Equipment Import / Export Method

Also Published As

Publication number Publication date
JP2017203294A (en) 2017-11-16

Similar Documents

Publication Publication Date Title
JP6239686B2 (en) Construction material of tunnel shaft internal structure, construction lift and material transport cart
KR101794085B1 (en) Construction system and method for multi-floor buildings
RU2519321C2 (en) Method to erect underground structure
KR101614842B1 (en) frame system of buildings using the pc-column with overhanging beam applicable various span without increase of story-height
CN114961335A (en) Demolition construction method for large-span reinforced concrete supporting beam
CN115075291B (en) Underground warehouse modularized structure utilizing prefabricated segment vertical holes and construction method
JP2020002778A (en) Bridge pier construction method
CN115142428B (en) Advanced construction method for deep foundation pit storage yard
EP1108675B1 (en) Working method and protection system for passenger conveyer
Tanijiri et al. Development of automated weather-unaffected building construction system
CN110316662B (en) Installation and construction method of large-span portal crane
CN117466118A (en) Construction method of long and steep slope passageway inner long and large escalator
CN116856543A (en) Construction method of stacked dome steel structure
CN104372804A (en) Anchoring device for the foundations of a ski lift structure, and method for manufacturing such a device
JP6944900B2 (en) Construction method of linear structure
CN107587722A (en) A kind of advanced mounting process of crane beam on rock wall for underground power house reinforcing bar and its reinforcing bar are from steady structure
JP4694859B2 (en) Inclined passenger conveyor equipment, installation method thereof, and delivery method thereof
KR102785167B1 (en) Precast vertical core structureand construction method therewith
JP3212231B2 (en) Plant construction method and construction equipment
JP2022009519A (en) Superstructure member conveyance facility and superstructure member conveyance method
JP6898161B2 (en) Temporary passage system and repair method for high-rise structures
JP2004176322A (en) Method of forming floor slab of road tunnel
JP6798527B2 (en) Superstructure material transportation equipment and superstructure material transportation method
JP3241469B2 (en) How to build an underground multilayer structure
KR20250061777A (en) Construction method of the structure of the elevator machine room on the rooftop of an apartment building by recycling the gangform of typical floor

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170901

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20171003

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20171101

R150 Certificate of patent or registration of utility model

Ref document number: 6239686

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250