JP6289912B2 - Temporary receiving method and structure of vertical load in seismic isolation retrofit work - Google Patents
[go: Go Back, main page]

JP6289912B2 - Temporary receiving method and structure of vertical load in seismic isolation retrofit work - Google Patents

Temporary receiving method and structure of vertical load in seismic isolation retrofit work Download PDF

Info

Publication number
JP6289912B2
JP6289912B2 JP2014002287A JP2014002287A JP6289912B2 JP 6289912 B2 JP6289912 B2 JP 6289912B2 JP 2014002287 A JP2014002287 A JP 2014002287A JP 2014002287 A JP2014002287 A JP 2014002287A JP 6289912 B2 JP6289912 B2 JP 6289912B2
Authority
JP
Japan
Prior art keywords
precast concrete
seismic isolation
bracket
existing pillar
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2014002287A
Other languages
Japanese (ja)
Other versions
JP2015129425A (en
Inventor
中村 保則
保則 中村
佐藤 直樹
直樹 佐藤
三輪 明広
明広 三輪
繁美 菊田
繁美 菊田
信也 鈴木
信也 鈴木
手塚 純一
純一 手塚
舘野 孝信
孝信 舘野
悟司 高瀬
悟司 高瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP2014002287A priority Critical patent/JP6289912B2/en
Publication of JP2015129425A publication Critical patent/JP2015129425A/en
Application granted granted Critical
Publication of JP6289912B2 publication Critical patent/JP6289912B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

本発明は、例えば、既存建物の中間層における柱などに免震装置を新しく入れたり、免震装置を交換したり等する場合の、免震レトロフィット工事における鉛直荷重の仮受け方法と仮受け構造に関するものである。   The present invention relates to a vertical load provisional receiving method and provisional reception in a seismic isolation retrofit work, for example, when a seismic isolation device is newly installed in a column in an intermediate layer of an existing building, or the seismic isolation device is replaced. Concerning structure.

従来、免震レトロフィットの鉛直荷重の仮受けは、免震装置を新規に設置する既存柱に作用する鉛直軸力を、そのまま受けかえるため、数千kN以上の大きな荷重を支えることになる。また、仮受けする方法も、直接、仮設支柱で軸力を受ける他に、鋼製や鉄筋コンクリート(RC)の荷重受けブラケットを既存躯体にPC鋼材で圧着するものまで多彩である。例えば、図4(A)に示すように、RCブラケットの例として特許文献1に記載の免震装置設置方法が知られている。また、図4(B)に示すように、鋼製ブラケットの例としては、特許文献2に記載の免震化工法、その他、特許文献3に記載の免震装置の設置方法(図示せず)が知られている。   Conventionally, the provisional receiving of the vertical load of the seismic isolation retrofit supports a large load of several thousand kN or more because the vertical axial force acting on the existing column where the seismic isolation device is newly installed is directly received. In addition to the method of receiving the axial force directly by the temporary support column, there are various methods of temporarily receiving the load receiving bracket made of steel or reinforced concrete (RC) to the existing housing with the PC steel material. For example, as shown in FIG. 4A, a seismic isolation device installation method described in Patent Document 1 is known as an example of an RC bracket. Moreover, as shown in FIG. 4 (B), as an example of the steel bracket, the seismic isolation method described in Patent Document 2 and the other method of installing the seismic isolation device described in Patent Document 3 (not shown). It has been known.

特開2001−49873号公報JP 2001-49873 A 特許第3725818号公報Japanese Patent No. 3725818 特開2002−227425号公報JP 2002-227425 A

しかし、従来の免震レトロフィット工事における鉛直荷重の仮受け方法においては、例えば、前記鋼製ブラケットの例では、剛性が低く、負担できる軸力は800t未満である。また、RCブラケットの例では、剛性は高いものの、設置するのにコンクリートの養生期間が必要で工期が長くなる。更に、前記RCブラケットに係るコンクリートを撤去するために、費用が掛かると言う課題がある。本発明に係る免震レトロフィット工事における鉛直荷重の仮受け方法は、このような課題を解決するために提案されたものである。   However, in the conventional method for temporarily receiving the vertical load in the seismic isolation retrofit work, for example, in the example of the steel bracket, the rigidity is low and the axial force that can be borne is less than 800 t. Further, in the example of the RC bracket, although the rigidity is high, a concrete curing period is required for installation, and the construction period becomes long. Furthermore, in order to remove the concrete which concerns on the said RC bracket, there exists a subject said that it costs. The provisional receiving method of the vertical load in the seismic isolation retrofit construction according to the present invention has been proposed in order to solve such a problem.

本発明に係る免震レトロフィット工事における鉛直荷重の仮受け方法の上記課題を解決して目的を達成するための要旨は、建物の既存柱の一部を切断した箇所に免震装置を設置する際に、前記建物の軸力を仮受けする仮受け部材を当該既存柱に貫通させた圧着部材で圧着し、前記既存柱に掛かる軸力を前記仮受け部材および該仮受け部材に載置したジャッキで一旦仮受けする仮受け方法において、前記仮受け部材が上下に分割したプレキャストコンクリート(PCaと記載することあり、以下同じ)ブラケットである場合に、そのブラケットの水平方向の分割面は、前記既存柱に上下のプレキャストコンクリートブラケットを設置した状態でこれらを側面視して、上側のプレキャストコンクリートブラケットの上面で軸力の掛かる位置と下側のプレキャストコンクリートブラケットの下部の内側角部を結んだ仮想線に対して直交する傾斜面となっていることである。 The gist for solving the above problems of the vertical load provisional receiving method in the seismic isolation retrofit construction according to the present invention is to install a seismic isolation device at a location where a part of an existing pillar of a building is cut. At this time, the temporary receiving member that temporarily receives the axial force of the building is crimped by a crimping member that penetrates the existing column, and the axial force applied to the existing column is placed on the temporary receiving member and the temporary receiving member. In the temporary receiving method of temporarily receiving with a jack, when the temporary receiving member is a precast concrete (PCa, sometimes referred to below) bracket divided into upper and lower parts, the horizontal dividing surface of the bracket is With the upper and lower precast concrete brackets installed on the existing columns, these are viewed from the side, and the position where the axial force is applied on the upper surface of the upper precast concrete bracket and the lower side It is that is an inclined face perpendicular to the connecting inner corners of the bottom of the precast concrete bracket phantom.

前記プレキャストコンクリートブラケットにおける既存柱との接合面には、該接合面と対向した既存柱の接合面との間に介在する高強度モルタルに突出するシアキーが突設されていることである。   A shear key projecting from a high-strength mortar interposed between the joint surface of the precast concrete bracket and the existing column is interposed between the joint surface of the existing column and the joint surface.

前記仮受け部材が上下に分割したプレキャストコンクリートブラケットである場合に、分割された上下のプレキャストコンクリートブラケットを、水平方向の圧着材のみで既存柱に設置することを含むものである。   In the case where the temporary support member is a precast concrete bracket divided into upper and lower parts, the divided upper and lower precast concrete brackets are installed on an existing column only with a horizontal pressure bonding material.

本発明に係る免震レトロフィット工事における鉛直荷重の仮受け構造の上記課題を解決して目的を達成するための要旨は、建物の既存柱の一部を切断した箇所に免震装置を設置する際に、前記建物の軸力を仮受けする仮受け部材を当該既存柱に貫通させた圧着部材で圧着し、前記既存柱に掛かる軸力を前記仮受け部材および該仮受け部材に載置したジャッキで一旦仮受けする仮受け構造において、前記仮受け部材が上下に分割したプレキャストコンクリートブラケットである場合に、そのブラケットの水平方向の分割面は、前記既存柱に上下のプレキャストコンクリートブラケットを設置した状態でこれらを側面視して、上側のプレキャストコンクリートブラケットの上面で軸力の掛かる位置と下側のプレキャストコンクリートブラケットの下部の内側角部を結んだ仮想線に対して直交する傾斜面となっていることである。 The gist for solving the above-mentioned problems of the vertical load provisional receiving structure in the seismic isolation retrofit construction according to the present invention is to install a seismic isolation device at a location where a part of an existing pillar of a building is cut. At this time, the temporary receiving member that temporarily receives the axial force of the building is crimped by a crimping member that penetrates the existing column, and the axial force applied to the existing column is placed on the temporary receiving member and the temporary receiving member. In the temporary receiving structure for temporarily receiving with a jack, when the temporary receiving member is a precast concrete bracket divided vertically, the horizontal dividing surface of the bracket has the upper and lower precast concrete brackets installed on the existing pillars. When these are viewed from the side, the position where the axial force is applied to the upper surface of the upper precast concrete bracket and the lower precast concrete bracket It is that is an inclined face perpendicular to the connecting inner corners of the parts phantom.

前記プレキャストコンクリートブラケットにおける既存柱との接合面には、該接合面と対向した既存柱の接合面との間に介在する高強度モルタルに突出するシアキーが突設されていることである。   A shear key projecting from a high-strength mortar interposed between the joint surface of the precast concrete bracket and the existing column is interposed between the joint surface of the existing column and the joint surface.

前記仮受け部材が上下に分割したプレキャストコンクリートブラケットである場合に、分割された上下のプレキャストコンクリートブラケットが、水平方向の圧着材のみで既存柱に設置されていることである。   In the case where the temporary support member is a precast concrete bracket divided into upper and lower parts, the divided upper and lower precast concrete brackets are installed on the existing pillars only with the horizontal pressure bonding material.

本発明の免震レトロフィット工事における鉛直荷重の仮受け方法とその構造によれば、小型化・軽量化されたPCaブラケットを使用するので、高軸力(8000kN以上)の免震レトロフィット工事が可能となる。また、PCaブラケットを使用することで、RCブラケットに比べて強度発現までの養生時間が省略され、現場の作業時間を短縮できる。このほか、前記PCaブラケットにして分割されていることで、軽くて取り扱いやすくなり、現場の施工性が向上する。更に、PCaブラケットを撤去することも容易になると言う優れた効果を奏するものである。   According to the provisional receiving method and structure of the vertical load in the seismic isolation retrofit construction of the present invention, since the PCa bracket reduced in size and weight is used, the seismic isolation retrofit construction with a high axial force (8000 kN or more) is possible. It becomes possible. Further, by using the PCa bracket, the curing time until the strength is developed compared to the RC bracket can be omitted, and the work time at the site can be shortened. In addition, by being divided into the PCa bracket, it becomes light and easy to handle, and the workability on site is improved. Furthermore, an excellent effect is obtained that it is easy to remove the PCa bracket.

本発明に係る免震レトロフィット工事における鉛直荷重の仮受け構造で、仮受け部材を水平方向に分割した例の一部拡大斜視図である。It is a partially expanded perspective view of the example which divided | segmented the temporary support member into the horizontal direction in the temporary support structure of the vertical load in the seismic isolation retrofit construction which concerns on this invention. 同本発明の免震レトロフィット工事における鉛直荷重の仮受け構造で、仮受け部材を水平方向に分割した例の一部側面図である。It is a partial side view of the example which divided | segmented the temporary support member into the horizontal direction in the temporary support structure of the vertical load in the seismic isolation retrofit construction of the same invention. 本発明に係る免震レトロフィット工事における鉛直荷重の仮受け構造で、仮受け部材を垂直方向に分割した例の一部拡大斜視図である。It is a partially expanded perspective view of the example which divided | segmented the temporary support member into the perpendicular direction by the temporary support structure of the vertical load in the seismic isolation retrofit construction which concerns on this invention. 従来例に係る免震レトロフィット工事を示す、RCブラケットの例を示す側面図(A)、鋼製ブラケットの例を示す側面図(B)である。It is the side view (A) which shows the example of RC bracket which shows the seismic isolation retrofit construction concerning a prior art example, and the side view (B) which shows the example of steel brackets.

本発明に係る免震レトロフィット工事における鉛直荷重の仮受け方法は、図1に示すように、分割したPCaブラケット3a,3bを、若しくは、図3に示すように、分割したPCaブラケット3dを使用するものである。   The vertical load provisional method in the seismic isolation retrofit work according to the present invention uses the divided PCa brackets 3a and 3b as shown in FIG. 1, or the divided PCa bracket 3d as shown in FIG. To do.

本発明に係る免震レトロフィット工事においては、図1に示すように、建物の既存柱2の一部を切断した箇所に、免震装置10を設置する工事である。その際に、前記建物の荷重を仮受けする仮受け部材(PCaブラケット3a,3b)を、該仮受け部材と前記既存柱2の表面との間に高強度モルタル4を充填・固化させて、当該既存柱2に貫通させた圧着部材(PC鋼棒7)で圧着し、建物の既存柱に掛かる軸力を前記仮受け部材および該仮受け部材に載置したジャッキ9で、一旦仮受けする鉛直荷重の仮受け方法である。   In the seismic isolation retrofit construction according to the present invention, as shown in FIG. 1, the seismic isolation device 10 is installed at a location where a part of the existing pillar 2 of the building is cut. At that time, temporary receiving members (PCa brackets 3a, 3b) for temporarily receiving the load of the building are filled and solidified with high-strength mortar 4 between the temporary receiving member and the surface of the existing pillar 2, Crimping is performed with a crimping member (PC steel rod 7) penetrating the existing pillar 2, and the axial force applied to the existing pillar of the building is temporarily received with the temporary receiving member and the jack 9 placed on the temporary receiving member. This is a method for temporarily receiving a vertical load.

上記鉛直荷重の仮受け方法の手順を説明する。まず、工場(場合によってはサイト)等においてPCaブラケット3a,3bを形成する。前記仮受け部材であるPCaブラケット3a,3bを、前記既存柱2に設置する状態において、予め上下に分割した状態で、小型化・軽量化したプレキャストコンクリートブラケットとして形成しておくものである。   The procedure of the method for temporarily receiving the vertical load will be described. First, the PCa brackets 3a and 3b are formed in a factory (or a site in some cases). The PCa brackets 3a and 3b, which are the temporary receiving members, are formed as precast concrete brackets that are reduced in size and weight in a state where the PCa brackets 3a and 3b are divided into upper and lower parts in advance.

そして、前記仮受け部材が上下に分割した、上側のPCaブラケット3a,下側のPCaブラケット3bである場合に、図2に示すように、そのブラケットの水平方向の分割面3cは、既存柱2に上下のPCaブラケット3a,3bを設置した状態で、これらを側面視して、上側のPCaブラケット3aの上面で軸力の掛かる位置と、下側のPCaブラケット3bの下部の内側角部を結んだ仮想線8に対して直交する傾斜面となっている。   When the temporary receiving member is an upper PCa bracket 3a and a lower PCa bracket 3b, which are divided into upper and lower parts, as shown in FIG. When the upper and lower PCa brackets 3a and 3b are installed on the upper side of the PCa bracket 3a, the positions where the axial force is applied to the upper surface of the upper PCa bracket 3a and the lower inner corners of the lower PCa bracket 3b are connected. The inclined surface is perpendicular to the imaginary line 8.

前記分割面3cを傾斜させたのは、増設柱2,既存柱2aに掛かる軸力を仮受けする際に、実際に仮受け部材(PCaブラケット)に掛かる軸力に対して、上側のPCaブラケット3a,下側のPCaブラケット3bの分割面3cにおいて、軸力に対して垂直な面になるようにするためである。   The reason why the dividing surface 3c is inclined is that the upper PCa bracket is against the axial force actually applied to the temporary receiving member (PCa bracket) when temporarily receiving the axial force applied to the additional column 2 and the existing column 2a. This is because the split surface 3c of the lower PCa bracket 3b is a surface perpendicular to the axial force.

また、PCaブラケット3a,3bにおける既存柱2との接合面には、該接合面と対向した既存柱2の接合面との間に介在させる高強度モルタル4に突出すべく、シアキー5が適宜の数・配置にて突設されている。   Further, a shear key 5 is appropriately provided on the joint surface of the PCa brackets 3a and 3b with the existing column 2 so as to protrude into the high-strength mortar 4 interposed between the joint surface and the joint surface of the existing column 2 facing the joint surface. Projected in number and arrangement.

前記シアキー5により、すべり破壊面が高強度モルタル4と既存柱2との接合面になる。また、PCaブラケット3a,3bに、PC鋼棒挿通用の貫通孔を水平方向と垂直方向とに形成しておく。このように、予めPCaブラケット3a,3bを工場で製作しておき、現場へトラック等で運搬・搬入する。   With the shear key 5, the slip fracture surface becomes a joint surface between the high-strength mortar 4 and the existing pillar 2. Further, through holes for inserting a PC steel rod are formed in the PCa brackets 3a and 3b in the horizontal direction and the vertical direction. In this way, the PCa brackets 3a and 3b are manufactured in advance at the factory, and transported and carried into the site by a truck or the like.

次に、建物の既存柱2aにおいて、鉛直荷重を仮受けするための補強を行う。それには、図1に示すように、既存柱2aにPC鋼棒用の孔を水平に穿孔する工事を行う。そして、その後、前記既存柱2aの柱頭において、油圧ジャッキ9を受けるためにキャピタルを増設する。また、増設柱2にPC鋼棒用の鞘管を既存柱2aに穿孔した孔に合わせて設置しておいて、柱脚に補強コンクリートを打設して、既存柱2aを増設し「フカシ」を施工する。こうして増設柱2を形成する。   Next, the existing pillar 2a of the building is reinforced to temporarily receive a vertical load. For this purpose, as shown in FIG. 1, a construction for horizontally drilling holes for PC steel bars in the existing pillar 2a is performed. Thereafter, a capital is added to receive the hydraulic jack 9 at the stigma of the existing pillar 2a. In addition, a PC steel rod sheath tube is installed in the extension column 2 according to the hole drilled in the existing column 2a, and reinforced concrete is placed on the column base to expand the existing column 2a. Install. In this way, the extension pillar 2 is formed.

前記キャピタルのコンクリートが固化して所定の強度に達した後、ポストテンション方式で埋設しておいた緊張材をジャッキで引張り、所定の張力を導入してプレストレスを付与する。   After the concrete of the capital is solidified and reaches a predetermined strength, the tension material embedded by the post tension method is pulled with a jack, and a predetermined tension is introduced to apply prestress.

次に、前記PCaブラケット3a,3bを現場に搬入して、増設柱2の鞘管に前記PC鋼棒7を挿通させて、当該PCaブラケット3a,3bを前記既存柱2に設置する。また、図2に示すように同時に、PCaブラケット3a,3bにおける上下方向の貫通孔に貫通させるPC鋼棒6によって、水平方向に分割した当該PCaブラケット3a,3b同士を、プレート6a,定着ナット6bで締め付けることで、圧着し一体化する。   Next, the PCa brackets 3 a and 3 b are carried into the site, the PC steel rod 7 is inserted into the sheath tube of the extension column 2, and the PCa brackets 3 a and 3 b are installed on the existing column 2. Further, as shown in FIG. 2, at the same time, the PCa brackets 3a and 3b divided in the horizontal direction by the PC steel rods 6 penetrating through the vertical through holes in the PCa brackets 3a and 3b are connected to each other with the plate 6a and the fixing nut 6b. Tighten with to crimp and integrate.

更に、図2に示すように、このPCaブラケット3a,3bと増設柱2との隙間(一例として20〜30mm程度)に、間隙維持用のスペーサ等を挟んでおき、更に、モルタル用の型枠を前記隙間の周囲に組んだ後、高強度モルタル4を充填する。   Further, as shown in FIG. 2, a gap maintaining spacer or the like is sandwiched in the gap (about 20 to 30 mm as an example) between the PCa brackets 3a and 3b and the extension pillar 2, and a mortar formwork is further formed. After assembling around the gap, high strength mortar 4 is filled.

前記増設柱2と高強度モルタル4とが、所定の強度に達した後、前記PC鋼棒7をジャッキで引張り、所定の張力を導入する。これによりPCaブラケット3a,3bと増設柱2との摩擦力で、上部架構の軸力が支持可能となる。その後、前記PCaブラケット3aの上に油圧ジャッキ9を必要数設置する。   After the extension pillar 2 and the high strength mortar 4 reach a predetermined strength, the PC steel rod 7 is pulled with a jack and a predetermined tension is introduced. As a result, the axial force of the upper frame can be supported by the frictional force between the PCa brackets 3a and 3b and the extension column 2. Thereafter, a necessary number of hydraulic jacks 9 are installed on the PCa bracket 3a.

前記油圧ジャッキ9を稼動させてジャッキアップし、建物の上部架構の長期軸力を、前記PCaブラケット3a,3bを介して、増設柱2と既存柱2aに支持させる。その後、増設柱2から上部に露出している既存柱2aをワイヤーソーで切断する。   The hydraulic jack 9 is operated to jack up, and the long-term axial force of the upper frame of the building is supported by the extension pillar 2 and the existing pillar 2a via the PCa brackets 3a and 3b. Then, the existing pillar 2a exposed to the upper part from the additional pillar 2 is cut with a wire saw.

前記既存柱2aの切断箇所に、新しい免震装置10を所定の位置に設置する。更に、免震装置10の上下に、補強部を設け、該補強部に補強コンクリート2b,2cを打設する。このコンクリートが硬化した後に、隙間部にグラウトを注入する。   A new seismic isolation device 10 is installed at a predetermined position at the cutting position of the existing pillar 2a. Furthermore, a reinforcement part is provided in the upper and lower sides of the seismic isolation apparatus 10, and reinforced concrete 2b and 2c are laid in this reinforcement part. After this concrete has hardened, grout is poured into the gap.

前記補強部の補強コンクリート2b,2cと、隙間部のグラウトとが所定の強度に達した後、油圧ジャッキ9のジャッキダウンを行う。これにより、建物の上部架構の長期軸力が免震装置10に移行する。   After the reinforced concrete 2b, 2c of the reinforcing portion and the grout of the gap portion reach a predetermined strength, the hydraulic jack 9 is jacked down. Thereby, the long-term axial force of the upper frame of the building is transferred to the seismic isolation device 10.

次に、PC鋼棒6,7の定着ナット6b,7bを弛緩して外し、PCaブラケット3a,3bを増設柱2から撤去する。PC鋼棒7を撤去した後の増設柱2,既存柱2aにおける孔に、グラウトを充填する。このようにして、上記の仮受け構造1による鉛直荷重の仮受け方法が完了する。   Next, the fixing nuts 6 b and 7 b of the PC steel bars 6 and 7 are loosened and removed, and the PCa brackets 3 a and 3 b are removed from the additional pillar 2. The grout is filled in the holes in the additional pillar 2 and the existing pillar 2a after the PC steel rod 7 is removed. In this way, the method for temporarily receiving the vertical load by the temporary support structure 1 is completed.

鉛直荷重の仮受け構造1の他の実施例として、図3に示すように、垂直方向に分割面3eで分割したPCaブラケット3dを用いた構造がある。このような垂直方向に分割して小型化、軽量化を図ることで、免震装置10の設置が容易となるものである。   As another example of the vertical load temporary receiving structure 1, as shown in FIG. 3, there is a structure using a PCa bracket 3d divided by a dividing surface 3e in the vertical direction. The seismic isolation device 10 can be easily installed by reducing the size and weight by dividing in such a vertical direction.

このほか、鉛直荷重の仮受け方法の他の実施例として、仮受け部材が上下に分割したPCaブラケット3a,3bである場合に、当該上下のPCaブラケット3a,3bを、水平方向の圧着材であるPC鋼棒7のみで増設柱2,既存柱2aに設置する。即ち、PCaブラケット3a,3b同士を上下方向に圧着するPC鋼棒6を省く方法である。   In addition, as another embodiment of the vertical load temporary receiving method, when the temporary receiving member is the PCa brackets 3a and 3b divided into upper and lower parts, the upper and lower PCa brackets 3a and 3b are made of a horizontal pressure bonding material. Installed on the extension pillar 2 and the existing pillar 2a only with a certain PC steel rod 7. That is, it is a method of omitting the PC steel bar 6 that presses the PCa brackets 3a and 3b in the vertical direction.

図2において、PC鋼棒6は、水平方向のPC鋼棒7によって張力が導入されると、実質的に不要となる。従って、PC鋼棒6が不要となって材料費が低減され、取付、引張等の施工が不要となって、工期も短縮される。   In FIG. 2, the PC steel bar 6 becomes substantially unnecessary when tension is introduced by the horizontal PC steel bar 7. Accordingly, the PC steel bar 6 is not required, the material cost is reduced, installation such as attachment and tension is not required, and the work period is shortened.

本発明に係る免震レトロフィット工事における鉛直荷重の仮受け方法とその仮受け構造によれば、仮受け部材のPCaブラケットを分割して小型化して施工できるので、建物の中間層の既存柱、若しくは基礎に対して免震装置を新たに設置する場合に限らず、新旧の免震装置を交換する場合にも適用できるものである。   According to the provisional receiving method of vertical load and its provisional receiving structure in the seismic isolation retrofit construction according to the present invention, the PCa bracket of the provisional receiving member can be divided and reduced in size, so that the existing pillars in the intermediate layer of the building, Or it is applicable not only when newly installing a seismic isolation device with respect to a foundation but also when exchanging old and new seismic isolation devices.

1 仮受け構造、
2 増設柱、 2a 既存柱、
3a,3b 水平方向に分割したPCaブラケット、
3c 分割面、
3d 垂直方向に分割したPCaブラケット、
3e 分割面、
4 高強度モルタル、
5 シアキー、
6 PC鋼棒、
7 PC鋼棒、
8 仮想線、
9 油圧ジャッキ、
10 免震装置、
11 キャピタル。
1 temporary support structure,
2 additional pillars, 2a existing pillars,
3a, 3b PCa brackets divided horizontally,
3c dividing plane,
3d PCa bracket divided vertically,
3e Dividing surface,
4 high strength mortar,
5 Shea key,
6 PC steel bar,
7 PC steel bar,
8 virtual lines,
9 Hydraulic jack,
10 Seismic isolation device,
11 Capital.

Claims (6)

建物の既存柱の一部を切断した箇所に免震装置を設置する際に、
前記建物の軸力を仮受けする仮受け部材を当該既存柱に貫通させた圧着部材で圧着し、
前記既存柱に掛かる軸力を前記仮受け部材および該仮受け部材に載置したジャッキで一旦仮受けする仮受け方法において、
前記仮受け部材が上下に分割したプレキャストコンクリートブラケットである場合に、そのブラケットの水平方向の分割面は、前記既存柱に上下のプレキャストコンクリートブラケットを設置した状態でこれらを側面視して、上側のプレキャストコンクリートブラケットの上面で軸力の掛かる位置と下側のプレキャストコンクリートブラケットの下部の内側角部を結んだ仮想線に対して直交する傾斜面となっていること、
を特徴とする免震レトロフィット工事における鉛直荷重の仮受け方法。
When installing a seismic isolation device at a location where a part of an existing pillar of a building was cut,
Crimp with a crimping member that penetrates the existing pillar a temporary receiving member that temporarily receives the axial force of the building,
In the temporary receiving method of temporarily receiving the axial force applied to the existing pillar with the temporary receiving member and the jack placed on the temporary receiving member,
When the temporary support member is a precast concrete bracket that is divided into upper and lower parts, the horizontal dividing surface of the bracket is viewed from the side with the upper and lower precast concrete brackets installed on the existing pillar, and It is an inclined surface perpendicular to the imaginary line connecting the position where the axial force is applied on the upper surface of the precast concrete bracket and the lower inner corner of the lower precast concrete bracket,
A method for temporarily receiving vertical loads in seismic isolation retrofit construction.
プレキャストコンクリートブラケットにおける既存柱との接合面には、該接合面と対向した既存柱の接合面との間に介在する高強度モルタルに突出するシアキーが突設されていること、
を特徴とする請求項1に記載の免震レトロフィット工事における鉛直荷重の仮受け方法。
The joint surface with the existing pillar in the precast concrete bracket is provided with a shear key projecting into the high-strength mortar interposed between the joint surface and the joint surface of the existing pillar facing the joint surface,
The provisional receiving method of the vertical load in the seismic isolation retrofit construction of Claim 1 characterized by these.
仮受け部材が上下に分割したプレキャストコンクリートブラケットである場合に、分割された上下のプレキャストコンクリートブラケットを、水平方向の圧着材のみで既存柱に設置すること、
を特徴とする請求項1または2に記載の免震レトロフィット工事における鉛直荷重の仮受け方法。
When the temporary receiving member is a precast concrete bracket divided into upper and lower parts, installing the divided upper and lower precast concrete brackets on the existing pillar only with the horizontal pressure bonding material,
The provisional receiving method of the vertical load in the seismic isolation retrofit construction of Claim 1 or 2 characterized by these.
建物の既存柱の一部を切断した箇所に免震装置を設置する際に、
前記建物の軸力を仮受けする仮受け部材を当該既存柱に貫通させた圧着部材で圧着し、
前記既存柱に掛かる軸力を前記仮受け部材および該仮受け部材に載置したジャッキで一旦仮受けする仮受け構造において、
前記仮受け部材が上下に分割したプレキャストコンクリートブラケットである場合に、そのブラケットの水平方向の分割面は、前記既存柱に上下のプレキャストコンクリートブラケットを設置した状態でこれらを側面視して、上側のプレキャストコンクリートブラケットの上面で軸力の掛かる位置と下側のプレキャストコンクリートブラケットの下部の内側角部を結んだ仮想線に対して直交する傾斜面となっていること、
を特徴とする免震レトロフィット工事における鉛直荷重の仮受け構造。
When installing a seismic isolation device at a location where a part of an existing pillar of a building was cut,
Crimp with a crimping member that penetrates the existing pillar a temporary receiving member that temporarily receives the axial force of the building,
In the temporary receiving structure that temporarily receives the axial force applied to the existing pillar with the temporary receiving member and the jack placed on the temporary receiving member,
When the temporary support member is a precast concrete bracket that is divided into upper and lower parts, the horizontal dividing surface of the bracket is viewed from the side with the upper and lower precast concrete brackets installed on the existing pillar, and It is an inclined surface perpendicular to the imaginary line connecting the position where the axial force is applied on the upper surface of the precast concrete bracket and the lower inner corner of the lower precast concrete bracket,
A vertical load temporary support structure for seismic isolation retrofit construction.
プレキャストコンクリートブラケットにおける既存柱との接合面には、該接合面と対向した既存柱の接合面との間に介在する高強度モルタルに突出するシアキーが突設されていること、
を特徴とする請求項4に記載の免震レトロフィット工事における鉛直荷重の仮受け構造。
The joint surface with the existing pillar in the precast concrete bracket is provided with a shear key projecting into the high-strength mortar interposed between the joint surface and the joint surface of the existing pillar facing the joint surface,
The temporary receiving structure of the vertical load in the seismic isolation retrofit construction of Claim 4 characterized by these.
仮受け部材が上下に分割したプレキャストコンクリートブラケットである場合に、分割された上下のプレキャストコンクリートブラケットが、水平方向の圧着材のみで既存柱に設置されていること、
を特徴とする請求項4または5に記載の免震レトロフィット工事における鉛直荷重の仮受け構造。
In the case where the temporary support member is a precast concrete bracket divided into upper and lower parts, the divided upper and lower precast concrete brackets are installed on existing pillars only with a horizontal pressure bonding material,
The temporary receiving structure of the vertical load in the seismic isolation retrofit construction of Claim 4 or 5 characterized by these.
JP2014002287A 2014-01-09 2014-01-09 Temporary receiving method and structure of vertical load in seismic isolation retrofit work Active JP6289912B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014002287A JP6289912B2 (en) 2014-01-09 2014-01-09 Temporary receiving method and structure of vertical load in seismic isolation retrofit work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014002287A JP6289912B2 (en) 2014-01-09 2014-01-09 Temporary receiving method and structure of vertical load in seismic isolation retrofit work

Publications (2)

Publication Number Publication Date
JP2015129425A JP2015129425A (en) 2015-07-16
JP6289912B2 true JP6289912B2 (en) 2018-03-07

Family

ID=53760330

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014002287A Active JP6289912B2 (en) 2014-01-09 2014-01-09 Temporary receiving method and structure of vertical load in seismic isolation retrofit work

Country Status (1)

Country Link
JP (1) JP6289912B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6872384B2 (en) * 2017-02-16 2021-05-19 株式会社奥村組 Reinforcement structure and construction method of existing skeleton

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000291134A (en) * 1999-04-01 2000-10-17 Shimizu Corp Precast member joint structure
JP2001049873A (en) * 1999-08-13 2001-02-20 Taisei Corp Existing building seismic isolation method
US6324795B1 (en) * 1999-11-24 2001-12-04 Ever-Level Foundation Systems, Inc. Seismic isolation system between floor and foundation comprising a ball and socket joint and elastic or elastomeric element
JP3725818B2 (en) * 2001-11-26 2005-12-14 ドーピー建設工業株式会社 How to install seismic isolation devices on existing pillars
JP4255423B2 (en) * 2004-09-14 2009-04-15 株式会社竹中工務店 How to install the temporary extension member

Also Published As

Publication number Publication date
JP2015129425A (en) 2015-07-16

Similar Documents

Publication Publication Date Title
JP6022631B1 (en) Seismic isolation device replacement method and seismic isolation structure
JP5437113B2 (en) Load receiving method and device for seismic isolation device
JP5865567B2 (en) Connecting slab and its construction method
JP6289912B2 (en) Temporary receiving method and structure of vertical load in seismic isolation retrofit work
JP6208090B2 (en) Temporary support structure for seismic isolation work and seismic isolation method for existing buildings
JP6543077B2 (en) Construction method of structure
JP5989597B2 (en) Temporary seismic structure and its construction method during construction of seismic isolation for existing frame
JP2013032684A (en) Foundation form changing method for existing building
JP5749620B2 (en) Seismic isolation method for existing buildings
JP5368040B2 (en) Horizontal force restraint method in seismic isolation work
JP5378896B2 (en) Seismic isolation method for existing buildings
JP6302222B2 (en) Horizontal force support structure and method for constructing horizontal force support structure
JP6031626B1 (en) Replacing the seismic isolation device in the pile head seismic isolation structure
JP2013181322A (en) Reconstruction method of pile foundation and pile foundation structure
JP6138719B2 (en) Construction method of seismic reinforcement structure
JP5980697B2 (en) Reinforcement structure of existing pile foundation and reinforcement method of existing pile foundation
JP5123967B2 (en) Seismic isolation method
JP5645548B2 (en) Dismantling method, jack structure
JP6190292B2 (en) Seismic isolation method for existing structures
JP2018096050A (en) Horizontal force restraint structure and seismic isolation method
JP6114071B2 (en) Seismic isolation method for existing buildings and temporary structure under construction
JP4439938B2 (en) Wall type reinforced concrete structure and its construction method
JP6000414B2 (en) Pile foundation reconstruction method and pile foundation structure
JP2016153559A (en) Construction method of wooden building and foundation member used for construction method
JP6359349B2 (en) Mounting structure and mounting method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160930

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170614

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170620

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170807

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180109

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180207

R150 Certificate of patent or registration of utility model

Ref document number: 6289912

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250