JP6327092B2 - Transformer connection phase determination program, transformer connection phase determination method, and transformer connection phase determination device - Google Patents
Transformer connection phase determination program, transformer connection phase determination method, and transformer connection phase determination device Download PDFInfo
- Publication number
- JP6327092B2 JP6327092B2 JP2014202249A JP2014202249A JP6327092B2 JP 6327092 B2 JP6327092 B2 JP 6327092B2 JP 2014202249 A JP2014202249 A JP 2014202249A JP 2014202249 A JP2014202249 A JP 2014202249A JP 6327092 B2 JP6327092 B2 JP 6327092B2
- Authority
- JP
- Japan
- Prior art keywords
- value
- power
- time zone
- transformer
- correlation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/242—Home appliances
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Description
本発明は、トランス接続相判定プログラム、トランス接続相判定方法、およびトランス接続相判定装置に関する。 The present invention relates to a transformer connection phase determination program, a transformer connection phase determination method, and a transformer connection phase determination device.
近年、太陽光発電(Photovoltaics、PV)システムを代表とする分散型電源が一般家庭にも普及してきている。また、新しい電圧管理方式の検討を行う場合などに、配電網内の3以上の配電線のいずれか2つの配電線に接続されたトランスの接続相の判定が行われる場合がある。 2. Description of the Related Art In recent years, a distributed power source represented by a photovoltaic power generation (PV) system has become popular in general households. Moreover, when examining a new voltage management system, the connection phase of the transformer connected to any two of the three or more distribution lines in the distribution network may be determined.
先行技術としては、例えば、既存の電力系統に連系される系統連系インバータ装置がある。この系統連系インバータ装置では、商用電力系統が断になると、変圧器が連系点の交流出力を取り出し、位相比較回路が変圧器からの交流出力と商用電力系統が断になる前の電圧制御発振回路からの交流出力との位相差を検出する。また、位相比較回路での比較結果が所定値をこえると検出回路が制御信号を発生して、変換部が検出回路からの制御信号により直流出力の変換を停止する。 As a prior art, for example, there is a grid interconnection inverter device linked to an existing power system. In this grid-connected inverter device, when the commercial power system is cut off, the transformer takes out the AC output at the linkage point, and the phase comparison circuit controls the voltage before the AC output from the transformer and the commercial power system are cut off. The phase difference with the AC output from the oscillation circuit is detected. Further, when the comparison result in the phase comparison circuit exceeds a predetermined value, the detection circuit generates a control signal, and the conversion unit stops the conversion of the DC output by the control signal from the detection circuit.
しかしながら、従来技術では、配電網内のトランス配下の需要家に太陽光発電システムを導入した需要家が含まれていると、トランスの接続相の判定精度が低下してしまう場合がある。 However, in the related art, when a customer who has introduced a solar power generation system is included in a customer under a transformer in the distribution network, the determination accuracy of the connection phase of the transformer may be lowered.
一つの側面では、本発明は、トランスの接続相の判定精度の向上を図るトランス接続相判定プログラム、トランス接続相判定方法、およびトランス接続相判定装置を提供することを目的とする。 In one aspect, an object of the present invention is to provide a transformer connection phase determination program, a transformer connection phase determination method, and a transformer connection phase determination apparatus that improve the determination accuracy of a connection phase of a transformer.
本発明の一側面によれば、3以上の配電線のいずれか2つの配電線に接続されたトランスに接続された需要家で消費された計測期間内の各時間帯の電力値のうち、太陽光発電が導入された需要家で消費された特定の時間帯の電力値を除く前記各時間帯の電力値を取得し、前記3以上の配電線の各々の配電線について、取得した前記各時間帯の電力値と、前記各々の配電線に流れた前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出し、算出した前記各々の配電線の相関値に基づいて、前記3以上の配電線のうちの前記トランスに接続された2つの配電線を判定するトランス接続相判定プログラム、トランス接続相判定方法、およびトランス接続相判定装置が提案される。 According to one aspect of the present invention, among the power values in each time zone within a measurement period consumed by a consumer connected to a transformer connected to any two of the three or more distribution lines, the solar power Obtaining the power value of each time zone excluding the power value of the specific time zone consumed by the consumer in which photovoltaic power generation was introduced, and obtaining each time for each distribution line of the three or more distribution lines Based on the power value of the band and the current value of each time zone flowing through each of the distribution lines, a correlation value indicating the correlation between power and current is calculated, and the calculated correlation value of each distribution line Based on the above, a transformer connection phase determination program, a transformer connection phase determination method, and a transformer connection phase determination device for determining two distribution lines connected to the transformer among the three or more distribution lines are proposed.
本発明の一態様によれば、トランスの接続相の判定精度の向上を図ることができるという効果を奏する。 According to one aspect of the present invention, it is possible to improve the determination accuracy of the connection phase of the transformer.
以下に図面を参照して、本発明にかかるトランス接続相判定プログラム、トランス接続相判定方法、およびトランス接続相判定装置の実施の形態を詳細に説明する。 Exemplary embodiments of a transformer connection phase determination program, a transformer connection phase determination method, and a transformer connection phase determination device according to the present invention will be described below in detail with reference to the drawings.
(トランス接続相判定方法の一実施例)
図1は、実施の形態にかかるトランス接続相判定方法の一実施例を示す説明図である。図1において、トランス接続相判定装置101は、柱上トランスの接続相を判定するコンピュータである。柱上トランスは、電磁誘導の作用によって交流電流の電圧を変える変圧器である。以下の説明では、柱上トランスを、単に「トランス」と表記する。
(One Example of Transformer Connection Phase Determination Method)
FIG. 1 is an explanatory diagram of an example of the transformer connection phase determination method according to the embodiment. In FIG. 1, a transformer connection
トランスの接続相とは、配電網内の複数の配電線のうちトランスに接続された2つの配電線の組み合わせである。例えば、配電方式が三相3線式の配電網においては、三種類ある配電線のうちのトランスに接続された2つの配電線の組み合わせが、当該トランスの接続相となる。配電方式としては、三相3線式のほかに、例えば、三相4線式がある。 The connection phase of the transformer is a combination of two distribution lines connected to the transformer among a plurality of distribution lines in the distribution network. For example, in a distribution network with a three-phase three-wire distribution system, a combination of two distribution lines connected to a transformer among three types of distribution lines is a connection phase of the transformer. In addition to the three-phase three-wire system, for example, there is a three-phase four-wire system.
ここで、太陽光発電システムは、環境に優しい発電システムであるが、電力会社が供給する電力の品質に悪影響を及ぼすというデメリットがある。例えば、電気事業法により、電力会社は、100V供給の場合に、95V〜107Vの規定電圧を維持することが定められている。ところが、分散型電源の配電網においては、売電のための逆潮流が発生して電圧が上昇し、配電網の電圧が規定電圧から逸脱してしまう場合がある。 Here, the solar power generation system is an environmentally friendly power generation system, but has a demerit that it adversely affects the quality of power supplied by the power company. For example, the Electricity Business Law stipulates that electric power companies maintain a specified voltage of 95V to 107V when supplying 100V. However, in the distribution network of the distributed power source, there is a case where a reverse power flow for power sale occurs and the voltage rises, and the voltage of the distribution network deviates from the specified voltage.
電圧の制御方法としては、例えば、配電変電所の送り出し電圧の変更、電線の太線化、変圧器タップの見直しなどの様々な方法が考えられる。しかし、どこをどのように変更するかを判断するためには、現状の配電網の電圧分布を知る必要がある。このため、潮流計算と呼ばれる回路計算で電圧を求めることが考えられる。 As a method for controlling the voltage, for example, various methods such as changing the sending voltage of the distribution substation, thickening the electric wire, and reviewing the transformer tap can be considered. However, in order to determine where and how to change, it is necessary to know the current voltage distribution of the distribution network. For this reason, it is conceivable to obtain the voltage by circuit calculation called power flow calculation.
潮流計算には、配電系統の様々な情報の入力を必要とするが、その中でも、トランスの接続相については管理が難しい。例えば、三相3線式の配電網においては、需要家との接点にあるトランスが、三種類ある配電線の組み合わせのうち、どの相で高圧側と接続されているかを管理することは難しい。 Power flow calculation requires input of various information on the power distribution system, but it is difficult to manage the connection phase of the transformer. For example, in a three-phase three-wire distribution network, it is difficult to manage which phase is connected to the high-voltage side of a combination of three types of distribution lines for a transformer at a contact point with a customer.
この問題は、三相3線式でだけでなく、三相4線式といった3以上の電線を用いた配電網で起こり得る。このため、管理値として誤った接続相が用いられている可能性があり、潮流計算を行う場合には、トランスの接続相の現状調査を行うことになる。ところが、人手による確認にはコストがかかるため、トランスの接続相を自動で判定することが求められる。 This problem can occur not only in a three-phase three-wire system but also in a distribution network using three or more wires such as a three-phase four-wire system. For this reason, there is a possibility that an incorrect connection phase is used as the management value, and when performing the power flow calculation, the current state of the connection phase of the transformer will be investigated. However, since manual confirmation is costly, it is required to automatically determine the connection phase of the transformer.
トランスの接続相を判定する手法としては、例えば、三相3線の各線の電流を計測可能なセンサが計測した電流値と、トランス配下に設置されたスマートメータの電力値との相関の違いによって接続相を判定するものがある。ところが、三相3線の各線の電流値とトランス配下に設置されたスマートメータの電力値は、例えば、冬の場合は、朝方と夕方に大きな値をとるという共通の傾向を有することが多く、相関の違いを上手く抽出できない場合がある。 As a method for determining the connection phase of the transformer, for example, depending on the difference in correlation between the current value measured by the sensor capable of measuring the current of each of the three-phase three-wires and the power value of the smart meter installed under the transformer Some determine the connection phase. However, the current value of each line of the three-phase three-wire and the power value of the smart meter installed under the transformer often have a common tendency to take a large value in the morning and evening, for example, in winter, In some cases, the correlation difference cannot be extracted well.
このため、例えば、三相3線の各線の電流値とトランス配下に設置されたスマートメータの電力値に対してデジタルフィルタを適用して、共通の成分を除去することが考えられる。デジタルフィルタとしては、例えば、低周波成分を減衰させ、高周波成分を通過させるハイパスフィルタを用いることができる。 For this reason, for example, it is conceivable to apply a digital filter to the current value of each of the three-phase three-wires and the power value of the smart meter installed under the transformer to remove common components. As the digital filter, for example, a high-pass filter that attenuates a low-frequency component and passes a high-frequency component can be used.
しかし、トランス配下の需要家に太陽光発電システム(以下、単に「太陽光発電」という)が導入されていると、たとえデジタルフィルタを適用したとしても、トランスの接続相の判定精度が低下してしまう場合がある。例えば、太陽光発電の発電量は、『α×太陽光パネルの面積×日射量』で近似することができる(αは定数)。また、同じ地域の日射量は、ほぼ同じものとなることが多い。このため、同一のトランス配下の太陽光発電の推移は、高周波成分も低周波成分も全ての需要家でほぼ共通となり、デジタルフィルタによる共通成分の除去が困難なものとなる。 However, if a solar power generation system (hereinafter simply referred to as “solar power generation”) is installed in a customer under the transformer, even if a digital filter is applied, the determination accuracy of the connection phase of the transformer is reduced. May end up. For example, the power generation amount of solar power generation can be approximated by “α × area of solar panel × amount of solar radiation” (α is a constant). In addition, the amount of solar radiation in the same region is often almost the same. For this reason, the transition of photovoltaic power generation under the same transformer is almost common for all consumers for both high-frequency components and low-frequency components, making it difficult to remove common components using a digital filter.
そこで、本実施の形態では、トランス配下の需要家に太陽光発電を導入した需要家が含まれる場合であっても、トランスの接続相を精度良く判定するためのトランス接続相判定方法について説明する。以下、図1を用いて、トランス接続相判定装置101の処理例について説明する。
Therefore, in the present embodiment, a transformer connection phase determination method for accurately determining the connection phase of a transformer even when a customer who has introduced solar power generation is included in the consumers under the transformer will be described. . Hereinafter, a processing example of the transformer connection
ただし、本実施の形態では、配電網の配線方式として「三相3線式」を例に挙げて説明する。また、三種類ある配電線をそれぞれ「a線」、「b線」、「c線」と表記する場合がある。また、a線とb線との組み合わせを「ab相」と表記し、b線とc線との組み合わせを「bc相」と表記し、c線とa線との組み合わせを「ca相」と表記する場合がある。 However, in the present embodiment, the “three-phase three-wire system” will be described as an example of the distribution network wiring method. In addition, the three types of distribution lines may be referred to as “a line”, “b line”, and “c line”, respectively. Also, the combination of a line and b line is expressed as “ab phase”, the combination of b line and c line is expressed as “bc phase”, and the combination of c line and a line is expressed as “ca phase”. May be written.
図1の例では、三相3線式の配電網として、配電網ENを示す。配電網ENは、電力の流れを制御する変電所SUと、センサSEと、複数のトランスTの1つとしてトランスT1と、を含む。センサSEは、a線、b線、c線に流れる線電流の値(電流値)それぞれを計測する。 In the example of FIG. 1, a power distribution network EN is shown as a three-phase three-wire power distribution network. The distribution network EN includes a substation SU that controls the flow of electric power, a sensor SE, and a transformer T1 as one of a plurality of transformers T. The sensor SE measures each value (current value) of a line current flowing through the a line, the b line, and the c line.
トランスT1には、需要家C11,C12が接続されている。需要家Cとは、電力を消費する電力消費源であり、例えば、一般家庭や企業などである。また、需要家C11,C12には、スマートメータSM11,SM12がそれぞれ導入されている。スマートメータSMは、通信機能を備えた電力計であり、需要家Cで消費された電力の値(電力値)を計測する。 Consumers C 11 and C 12 are connected to the transformer T1. The consumer C is a power consumption source that consumes power, and is, for example, a general household or a company. In addition, smart meters SM 11 and SM 12 are respectively introduced to the consumers C 11 and C 12 . The smart meter SM is a power meter having a communication function, and measures the value of power consumed by the customer C (power value).
需要家C11は、太陽光発電が導入されていない需要家Cである。また、需要家C12は、太陽光発電が導入された需要家Cである。ここでは、トランスT1の接続相が不明であることを想定して、トランス接続相判定装置101がトランスT1の接続相を判定する場合について説明する。
The customer C 11 is a customer C into which no photovoltaic power generation is introduced. The consumer C 12 is a consumer C into which solar power generation has been introduced. Here, a case where the transformer connection
(1)トランス接続相判定装置101は、トランスTに接続された需要家Cで消費された計測期間MP内の各時間帯の電力値のうち、太陽光発電が導入された需要家Cで消費された特定の時間帯の電力値を除く各時間帯の電力値を取得する。
(1) The transformer connection
ここで、計測期間MPは、需要家Cで消費された電力値が計測された期間であり、任意に設定可能である。計測期間MPとしては、例えば、数ヶ月〜数年程度の期間が設定される。計測期間MP内の各時間帯は、例えば、計測期間を30分や1時間などの時間間隔で区切って分割された区間である。 Here, the measurement period MP is a period in which the power value consumed by the customer C is measured, and can be arbitrarily set. As the measurement period MP, for example, a period of several months to several years is set. Each time zone in the measurement period MP is a section divided by dividing the measurement period by a time interval such as 30 minutes or 1 hour, for example.
特定の時間帯は、需要家Cに導入された太陽光発電の発電量が「0(ゼロ)」であると見なせない時間帯である。換言すれば、特定の時間帯は、需要家Cを含む地域の日射量が無視できない程度発生する時間帯である。日射量は、太陽からの放射エネルギー量を測定したものである。 The specific time zone is a time zone in which the power generation amount of the photovoltaic power generation introduced to the customer C cannot be regarded as “0 (zero)”. In other words, the specific time zone is a time zone in which the amount of solar radiation in the region including the customer C cannot be ignored. The amount of solar radiation is a measure of the amount of radiant energy from the sun.
例えば、日の出から日の入りまでの明るい間は、需要家Cを含む地域の日射量が無視できない程度発生する可能性が高い。このため、特定の時間帯は、例えば、日の出から日の入りまでの時間帯を考慮して設定される。図1の例では、特定の時間帯が、6時00分から18時00分までの時間帯に設定されている場合を想定する。また、各時間帯を30分間隔で区切った区間とする。 For example, during the bright period from sunrise to sunset, there is a high possibility that the amount of solar radiation in the area including the customer C will not be ignored. For this reason, the specific time zone is set in consideration of the time zone from sunrise to sunset, for example. In the example of FIG. 1, it is assumed that the specific time zone is set to a time zone from 6:00 to 18:00. Moreover, it is set as the area which divided each time slot | zone at intervals of 30 minutes.
この場合、トランス接続相判定装置101は、トランスT1に接続された需要家C11,C12で消費された計測期間MP内の各時間帯の電力値のうち、需要家C12で消費された6時00分から18時00分までの各時間帯の電力値を除く各時間帯の電力値を取得する。需要家C12は、太陽光発電が導入された需要家Cである。
In this case, the transformer connected
需要家C11,C12で消費された計測期間MP内の各時間帯の電力値は、需要家C11,C12に導入されたスマートメータSM11,SM12によりそれぞれ計測された電力値である。なお、太陽光発電が導入されていない需要家C11については、スマートメータSM11の計測値として、需要家C11の消費電力Pcsptそのものが得られる。 Power value of each time zone in the customer C 11, C 12 measurement period spent in the MP, the power value measured respectively by customer C 11, a smart meter SM 11, SM 12, which is introduced into the C 12 is there. For the consumer C 11 into which solar power generation has not been introduced, the power consumption P cspt itself of the consumer C 11 is obtained as the measured value of the smart meter SM 11 .
一方、太陽光発電が導入された需要家C12については、スマートメータSM12の計測値として、需要家C12の消費電力Pcsptと太陽光発電による発電電力Psunとの和が得られる(消費電力Pcsptはプラスの値をとり、発電電力Psunはマイナスの値をとる)。このため、太陽光発電による発電電力Psunが消費電力Pcsptよりも大きければ、スマートメータSM12には余剰発電分の電力が電力値(マイナスの値)として記録される。ただし、スマートメータSM12では、消費電力Pcsptと発電電力Psunそれぞれの値は得られない。 On the other hand, for the customer C 12 into which solar power generation has been introduced, the sum of the power consumption P cspt of the customer C 12 and the power generation power P sun generated by solar power generation is obtained as the measured value of the smart meter SM 12 ( The power consumption P cspt takes a positive value and the generated power P sun takes a negative value). For this reason, if the electric power P sun generated by solar power generation is larger than the electric power consumption P cspt , the electric power for surplus power generation is recorded as a power value (negative value) in the smart meter SM 12 . However, the smart meter SM 12, the power consumption P CSPT the generated power P sun respective values can not be obtained.
一例として、計測期間MP内の各時間帯を、計測期間MPを30分間隔で区切った区間とすると、取得される各時間帯の電力値は、例えば、以下の通りである。 As an example, assuming that each time zone in the measurement period MP is a section obtained by dividing the measurement period MP at 30-minute intervals, the acquired power values in each time zone are as follows, for example.
6時00分から18時00分までの各時間帯の電力値
⇒需要家C11で消費された電力値
18時00分から6時00分までの各時間帯の電力値
⇒需要家C11,C12で消費された電力値の合計
Power value of each time zone from 6:00 to 18:00 ⇒ Power value consumed by customer C 11 Power value of each time zone from 18:00 to 6:00 ⇒ Consumer C 11 , C Total power consumed in 12
(2)トランス接続相判定装置101は、a線〜c線の各々の配電線について、取得した各時間帯の電力値と、各々の配電線に流れた各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出する。計測期間MP内の各時間帯にa線〜c線の各々の配電線に流れた電流値は、センサSEにより計測された電流値である。なお、相関値の具体的な算出例については、図7を用いて後述する。
(2) The transformer connection
(3)トランス接続相判定装置101は、算出した各々の配電線の相関値に基づいて、a線〜c線のうちのトランスTに接続された2つの配電線を判定する。具体的には、例えば、トランス接続相判定装置101は、算出した各々の配電線の相関値のうちの相関が最も小さい値から、トランスTの接続相を判定する。
(3) The transformer connection
図1の例では、a線の相関値を「ρa」とし、b線の相関値を「ρb」とし、c線の相関値を「ρc」とする。また、相関値ρa〜ρcの大小関係を「ρc<ρa,ρb」とする。この場合、トランス接続相判定装置101は、トランスT1の接続相をab相(a線とb線との組み合わせ)と判定する。
In the example of FIG. 1, the correlation value of the a line is “ρ a ”, the correlation value of the b line is “ρ b ”, and the correlation value of the c line is “ρ c ”. Further, the size relationship of the correlation values ρ a ~ρ c and "ρ c <ρ a, ρ b". In this case, the transformer connection
このように、トランス接続相判定装置101によれば、トランス配下の需要家Cで消費された各時間帯の電力値のうち、太陽光発電を導入済みの需要家Cで消費された特定の時間帯の電力値を除外して、電力と電流との相関を示す相関値を算出することができる。これにより、太陽光発電の影響により相関分析に不要となる共通の成分を含んだ情報を除去して相関分析を行うことができ、トランスTの接続相の判定精度を向上させることができる。
Thus, according to the transformer connection
(トランス接続相判定システムのシステム構成例)
つぎに、トランス接続相判定装置101を、配電網EN上に存在するトランスTの接続相を判定するトランス接続相判定システムに適用した場合について説明する。
(System configuration example of transformer connection phase judgment system)
Next, a case where the transformer connection
図2は、トランス接続相判定システム200のシステム構成例を示す説明図である。図2において、トランス接続相判定システム200は、配電網EN上に存在するトランスTの接続相を判定するシステムである。トランス接続相判定システム200は、配電網ENと、トランス接続相判定装置101とを有する。
FIG. 2 is an explanatory diagram showing a system configuration example of the transformer connection
配電網ENは、変電所SUと、センサSEと、トランスT1〜Tnと、需要家C(例えば、需要家C11,C12,Cn1)とを含む。各需要家Cには、スマートメータSM(例えば、スマートメータSM11,SM12,SMn1)が導入されている。ただし、需要家Cの中には、スマートメータSMを導入していない需要家Cが含まれていてもよい。 Grid EN includes a substation SU, and sensor SE, and the transformer Tl to Tn, and a customer C (e.g., customer C 11, C 12, C n1 ). Each customer C is installed with a smart meter SM (for example, smart meters SM 11 , SM 12 , SM n1 ). However, the customer C which has not introduced the smart meter SM may be included in the customer C.
変電所SUは、電力の流れを制御して、電力を需要家Cに送り出す。トランスT1〜Tnは、電磁誘導の作用によって交流電流の電圧を変える変圧器である。以下の説明では、配電網ENのうちの変電所SUからトランスT1〜Tnを、「高圧配電網」と表記する場合がある。また、配電網ENのうちのトランスT1〜TnからトランスT1〜Tnのそれぞれに接続する需要家Cまでの部分を「低圧配電網」と表記する場合がある。 The substation SU controls the flow of electric power and sends out electric power to the consumer C. The transformers T1 to Tn are transformers that change the voltage of the alternating current by the action of electromagnetic induction. In the following description, the transformers T1 to Tn from the substation SU in the distribution network EN may be referred to as “high voltage distribution network”. Further, the portion from the transformers T1 to Tn to the customer C connected to each of the transformers T1 to Tn in the distribution network EN may be referred to as a “low voltage distribution network”.
センサSEは、トランスT1〜Tnよりも変電所SU寄りに設置されており、高圧配電網の電流を計測する。ここで、高圧配電網は、本実施の形態では三相3線、すなわち、3本の電線で電力を送るため、センサSEは、3本の電線(a線〜c線)の電流値それぞれを計測する。 The sensor SE is installed closer to the substation SU than the transformers T1 to Tn, and measures the current of the high-voltage distribution network. Here, in the present embodiment, the high-voltage distribution network transmits power by three-phase three-wires, that is, three electric wires. Therefore, the sensor SE calculates the current values of the three electric wires (a line to c line). measure.
トランス接続相判定装置101は、トランスT1〜Tnの接続相を判定するコンピュータである。また、トランス接続相判定装置101は、a線〜c線の線電流をセンサSEが計測した値と、需要家Cが導入したスマートメータSMが計測した電力値とを取得可能である。
The transformer connection
(トランス接続相判定装置101のハードウェア構成例)
図3は、トランス接続相判定装置101のハードウェア構成例を示すブロック図である。図3において、トランス接続相判定装置101は、CPU(Central Processing Unit)301と、メモリ302と、ディスクドライブ303と、ディスク304と、I/F(Interface)305と、ディスプレイ306と、入力装置307と、を有する。また、各構成部はバス300によってそれぞれ接続される。
(Hardware configuration example of transformer connection phase determination apparatus 101)
FIG. 3 is a block diagram illustrating a hardware configuration example of the transformer connection
ここで、CPU301は、トランス接続相判定装置101の全体の制御を司る。メモリ302は、例えば、ROM(Read−Only Memory)、RAM(Random Access Memory)およびフラッシュROMなどを有する。具体的には、例えば、フラッシュROMやROMが各種プログラムを記憶し、RAMがCPU301のワークエリアとして使用される。メモリ302に記憶されるプログラムは、CPU301にロードされることで、コーディングされている処理をCPU301に実行させる。
Here, the
ディスクドライブ303は、CPU301の制御に従ってディスク304に対するデータのリード/ライトを制御する。ディスク304は、ディスクドライブ303の制御で書き込まれたデータを記憶する。ディスク304としては、例えば、磁気ディスク、光ディスクなどが挙げられる。
The
I/F305は、通信回線を通じてネットワーク310に接続され、ネットワーク310を介して他の装置に接続される。そして、I/F305は、ネットワーク310と内部のインターフェースを司り、他の装置からのデータの入出力を制御する。ネットワーク310は、例えば、LAN(Local Area Network)、WAN(Wide Area Network)、インターネットなどである。
The I /
ディスプレイ306は、カーソル、アイコンあるいはツールボックスをはじめ、文書、画像、機能情報などのデータを表示する。ディスプレイ306は、例えば、CRT(Cathode Ray Tube)、液晶ディスプレイ、プラズマディスプレイなどを採用することができる。
A
入力装置307は、文字、数字、各種指示などの入力のためのキーを有し、データの入力を行う。入力装置307は、キーボードやマウスなどであってもよく、また、タッチパネル式の入力パッドやテンキーなどであってもよい。
The
なお、トランス接続相判定装置101は、上述した構成部のうち、例えば、ディスプレイ306や入力装置307を有さないことにしてもよい。また、トランス接続相判定装置101は、上述した構成部のほか、例えば、SSD(Solid State Drive)、スキャナ、プリンタなどを有することにしてもよい。
Note that the transformer connection
(センサ線電流データ400の具体例)
つぎに、センサ線電流データ400の具体例について説明する。センサ線電流データ400は、配電網EN内のセンサSEにより計測された各線(a線〜c線)の電流値を示す時系列データである。
(Specific example of sensor line current data 400)
Next, a specific example of the sensor line
図4は、センサ線電流データ400の具体例を示す説明図である。図4において、センサ線電流データ400は、計測期間MP内の各時間帯に各線(a線〜c線)に流れた電流値を示す。ここでは、計測期間MPを、20XX年の1月1日〜12月31日の1年間とする。また、計測期間MP内の各時間帯を、計測期間MPを30分間隔で区切った区間とする。
FIG. 4 is an explanatory diagram showing a specific example of the sensor line
ここで、時刻t1〜t17520は、計測期間MP内の各時間帯に対応している。例えば、時刻t1は、1月1日の0時00分から0時30分までの時間帯を示す。このため、電流値Ia(1)は、1月1日の0時00分から0時30分までの時間帯にa線に流れた電流値を示す。 Here, the times t1 to t17520 correspond to the respective time zones in the measurement period MP. For example, time t1 indicates a time period from 0:00 to 0:30 on January 1. Therefore, the current value I a (1) indicates the current value that flows through the a line during the time period from 0:00 to 0:30 on January 1.
また、電流値Ib(1)は、1月1日の0時00分から0時30分までの時間帯にb線に流れた電流値を示す。また、電流値Ic(1)は、1月1日の0時00分から0時30分までの時間帯にc線に流れた電流値を示す。すなわち、センサ線電流データ400は、各線(a線〜c線)に流れた電流値が、1日に48ポイント計測され、1年で17520ポイント計測された場合の例である。
The current value I b (1) indicates a current value that flows through the b line during the time period from 0:00 to 0:30 on January 1. Further, the current value I c (1) indicates a current value that flows through the c-line in the time zone from 0:00 to 0:30 on January 1. That is, the sensor line
(需要家電力データ500の具体例)
つぎに、需要家電力データ500の具体例について説明する。需要家電力データ500は、配電網EN内のトランスTに接続された需要家Cに導入されたスマートメータSMにより計測された電力値、すなわち、需要家Cで消費された電力値を示す時系列データである。ここでは一例として、配電網EN内のトランスT1に接続された需要家C11で消費された電力値を例に挙げて説明する。
(Specific example of customer power data 500)
Next, a specific example of
図5は、需要家電力データ500の具体例を示す説明図である。図5において、需要家電力データ500は、計測期間MP内の各時間帯に需要家C11で消費された電力値を示す。ここでは、計測期間MPを、20XX年の1月1日〜12月31日の1年間とする。また、計測期間MP内の各時間帯を、計測期間MPを30分間隔で区切った区間とする。
FIG. 5 is an explanatory diagram showing a specific example of
ここで、時刻t1〜t17520は、計測期間MP内の各時間帯に対応している。例えば、時刻t1は、1月1日の0時00分から0時30分までの時間帯を示す。このため、電力値P11(1)は、1月1日の0時00分から0時30分までの時間帯に需要家C11で消費された電力値を示す。 Here, the times t1 to t17520 correspond to the respective time zones in the measurement period MP. For example, time t1 indicates a time period from 0:00 to 0:30 on January 1. Therefore, the power value P 11 (1) indicates the power value consumed by the consumer C 11 during the time period from 0:00 to 0:30 on January 1.
また、電力値P11(2)は、1月1日の0時30分から1時00分までの時間帯に需要家C11で消費された電力値を示す。すなわち、需要家電力データ500は、需要家C11で消費された電力値が、1日に48ポイント計測され、1年で17520ポイント計測された場合の例である。
The power value P 11 (2) indicates the power value consumed by the customer C 11 during the time period from 0:30 to 1:00 on January 1st. That is, the
(配電網設備データ600の具体例)
図6は、配電網設備データ600の具体例を示す説明図である。図6において、配電網設備データ600は、配電網EN内の設備に関する情報である。配電網設備データ600は、トランスID、接続相、スマートメータ導入済み需要家IDおよび太陽光発電導入済み需要家IDのフィールドを有し、各フィールドに情報を設定することで、配電網設備情報600−1〜600−nをレコードとして記憶する。
(Specific example of distribution network equipment data 600)
FIG. 6 is an explanatory diagram showing a specific example of the power distribution
ここで、トランスIDは、トランスTを識別する識別子である。接続相は、トランスTの接続相(ab相またはbc相またはca相)を示す。ただし、トランスTの接続相が未判定の場合は、接続相フィールドに「未」が設定される。スマートメータ導入済み需要家IDは、トランス配下のスマートメータ導入済みの需要家Cを識別する識別子である。 Here, the transformer ID is an identifier for identifying the transformer T. The connection phase indicates a connection phase (ab phase, bc phase, or ca phase) of the transformer T. However, when the connection phase of the transformer T has not been determined, “not yet” is set in the connection phase field. The smart meter installed customer ID is an identifier for identifying the customer C installed with the smart meter under the transformer.
太陽光発電導入済み需要家IDは、トランス配下のスマートメータ導入済みかつ太陽光発電導入済みの需要家Cを識別する識別子である。例えば、配電網設備情報600−1は、配電網EN内のトランスT1に接続されたスマートメータ導入済みの需要家C11,C12と、太陽光発電導入済みの需要家C12を示す。 The customer ID already introduced with photovoltaic power generation is an identifier for identifying the customer C who has introduced the smart meter under the transformer and has already introduced photovoltaic power generation. For example, the distribution network facility information 600-1 indicates the customers C 11 and C 12 that have been introduced to the smart meter and are connected to the transformer T1 in the distribution network EN, and the customer C 12 that has already been introduced with solar power generation.
(トランス接続相判定装置101の機能的構成例)
図7は、トランス接続相判定装置101の機能的構成例を示すブロック図である。図7において、トランス接続相判定装置101は、制御部701と、記憶部702と、を有する。制御部701は、取得部711と、データ分類部712と、フィルタ適用部713と、相関分析部714と、接続相判定部715と、出力部716と、を含む構成である。制御部701は、例えば、図3に示したメモリ302、ディスク304などの記憶装置に記憶されたプログラムをCPU301に実行させることにより、または、I/F305により、その機能を実現する。各機能部の処理結果は、例えば、CPU301が有するレジスタやメモリ302などに記憶される。また、記憶部702は、メモリ302、ディスク304などの記憶装置により実現される。
(Functional configuration example of transformer connection phase determination apparatus 101)
FIG. 7 is a block diagram illustrating a functional configuration example of the transformer connection
取得部711は、配電網EN内のセンサSEにより計測された各線(a線〜c線)の電流値を示すセンサ線電流データ400(例えば、図4参照)を取得する。具体的には、例えば、取得部711は、配電網EN内のセンサSEからセンサ線電流データ400を取得する。また、例えば、取得部711は、図3に示した入力装置307を用いたユーザの操作入力により、センサ線電流データ400を取得することにしてもよい。
The
また、取得部711は、配電網EN内のトランスTに接続された需要家Cに導入されたスマートメータSMにより計測された電力値を示す需要家電力データ500(例えば、図5参照)を取得する。具体的には、例えば、取得部711は、配電網EN内の各スマートメータSMから需要家電力データ500を取得する。また、例えば、取得部711は、入力装置307を用いたユーザの操作入力により、需要家電力データ500を取得することにしてもよい。
In addition, the
また、取得部711は、配電網EN内の設備に関する配電網設備データ600を取得する。具体的には、例えば、取得部711は、入力装置307を用いたユーザの操作入力により、配電網設備データ600を取得することにしてもよい。取得された配電網設備データ600は、例えば、記憶部702に記憶される。
In addition, the
データ分類部712は、取得されたセンサ線電流データ400を参照して、各線(a線〜c線)の電流値を、特定の時間帯の電流値と、特定の時間帯とは異なる他の時間帯の電流値とに分類する。上述したように、特定の時間帯は、需要家Cに導入された太陽光発電の発電量が「0(ゼロ)」であると見なせない時間帯である。
The
以下の説明では、1日のうちの特定の時間帯を「昼の時間帯」と表記し、1日のうちの特定の時間帯とは異なる他の時間帯を「夜の時間帯」と表記する場合がある。また、昼の時間帯として、「6時00分から18時00分までの時間帯」が設定されている場合を例に挙げて説明する。 In the following explanation, a specific time zone in one day is expressed as “day time zone”, and another time zone different from the specific time zone in one day is expressed as “night time zone”. There is a case. Further, a case where “time zone from 6:00 to 18:00” is set as the daytime time zone will be described as an example.
この場合、データ分類部712は、センサ線電流データ400を参照して、各線(a線〜c線)の電流値を、昼の時間帯(6時00分〜18時00分)の電流値と、夜の時間帯(18時00分〜6時00分)の電流値とに分類する。
In this case, the
例えば、時刻t13は、6時00分から6時30分までの時間帯を示す。すなわち、電流値Ia(13)は、6時00分から6時30分までの時間帯にa線に流れた電流値を示す。このため、データ分類部712は、電流値Ia(13)を、昼の時間帯の電流値として分類する。
For example, time t13 indicates a time zone from 6:00 to 6:30. That is, the current value I a (13) indicates the current value that flows through the a line during the time period from 6:00 to 6:30. Therefore, the
昼の時間帯に分類された各線(a線〜c線)の電流値は、例えば、後述の図8に示す昼データDB(データベース)800に記憶される。 The current value of each line (line a to line c) classified in the daytime time zone is stored, for example, in a daytime data DB (database) 800 shown in FIG.
また、例えば、時刻t12は、5時30分から6時00分までの時間帯を示す。すなわち、電流値Ia(12)は、5時30分から6時00分までの時間帯にa線に流れた電流値を示す。このため、データ分類部712は、電流値Ia(12)を、夜の時間帯の電流値として分類する。
Further, for example, time t12 indicates a time zone from 5:30 to 6:00. That is, the current value I a (12) indicates the current value that flows through the a line during the time period from 5:30 to 6:00. Therefore, the
夜の時間帯に分類された各線(a線〜c線)の電流値は、例えば、後述の図9に示す夜データDB900に記憶される。
The current value of each line (a line to c line) classified in the night time zone is stored in, for example, the
ただし、昼の長さは時期に応じて異なる場合がある。例えば、春夏秋冬の季節に応じて昼の長さは異なる。このため、季節に応じて異なる昼の長さを考慮して、昼の時間帯を季節ごとに設定することにしてもよい。例えば、夏(6月、7月、8月)は、他の季節に比べて昼が長いため、昼の時間帯を他の季節よりも長い期間に設定することにしてもよい。 However, the length of the day may vary depending on the time. For example, the length of the day varies depending on the season of spring, summer, autumn and winter. For this reason, the daytime period may be set for each season in consideration of a different daytime length depending on the season. For example, in summer (June, July, and August), the daytime is longer than in other seasons, so the time zone of the day may be set to a longer period than in other seasons.
また、データ分類部712は、取得された需要家電力データ500を参照して、各需要家Cの電力値を、昼の時間帯の電力値と、夜の時間帯の電力値とに分類する。
In addition, the
例えば、電力値P11(13)は、6時00分から6時30分までの時間帯に、需要家C11で消費された電力値を示す。このため、データ分類部712は、電力値P11(13)を、昼の時間帯の電力値として分類する。昼の時間帯に分類された各需要家Cの電力値は、例えば、後述の図8に示す昼データDB800に記憶される。
For example, the power value P 11 (13) indicates the power value consumed by the customer C 11 during the time period from 6:00 to 6:30. Therefore, the
また、例えば、電力値P11(12)は、5時30分から6時00分までの時間帯に、需要家C11で消費された電力値を示す。このため、データ分類部712は、電力値P11(12)を、夜の時間帯の電力値として分類する。夜の時間帯に分類された各線(a線〜c線)の電流値は、例えば、後述の図9に示す夜データDB900に記憶される。
Further, for example, the power value P 11 (12) indicates the power value consumed by the customer C 11 in the time zone from 5:30 to 6:00. Therefore, the
ここで、昼データDB800および夜データDB900の記憶内容について説明する。昼データDB800および夜データDB900は、例えば、記憶部702に記憶される。ここでは、配電網EN内のトランスTに接続された需要家Cとして、トランスT1に接続された需要家C11,C12、トランスT2に接続された需要家C21,C22およびトランスT3に接続された需要家C31,C32を例に挙げて説明する。
Here, the contents stored in the
図8は、昼データDB800の記憶内容の一例を示す説明図(その1)である。図8において、昼データDB800は、各線(a線〜c線)の昼の時間帯(6時00分〜18時00分)の電流値を記憶している。また、昼データDB800は、各需要家C11,C12,C21,C22,C31,C32の昼の時間帯(6時00分〜18時00分)の電力値を記憶している。
FIG. 8 is an explanatory diagram (part 1) illustrating an example of the contents stored in the
なお、図8では、各線の電流値と各需要家Cの電力値が昼の時間帯のものであることを識別するために、各線の電流値と各需要家Cの電力値の末尾に「_昼」を付加している。 In FIG. 8, in order to identify that the current value of each line and the power value of each customer C are in the daytime period, “ _Day "is added.
図9は、夜データDB900の記憶内容の一例を示す説明図(その1)である。図9において、夜データDB900は、各線(a線〜c線)の夜の時間帯(18時00分〜6時00分)の電流値を記憶している。また、夜データDB900は、各需要家C11,C12,C21,C22,C31,C32の夜の時間帯(18時00分〜6時00分)の電力値を記憶している。
FIG. 9 is an explanatory diagram (part 1) illustrating an example of the contents stored in the
なお、図9では、各線の電流値と各需要家Cの電力値が夜の時間帯のものであることを識別するために、各線の電流値と各需要家Cの電力値の末尾に「_夜」を付加している。 In FIG. 9, in order to identify that the current value of each line and the power value of each customer C are in the night time zone, the current value of each line and the power value of each customer C are suffixed with “ _Night "is added.
図7の説明に戻り、フィルタ適用部713は、各線の電流値と各需要家Cの電力値とに対して、低周波成分を減衰させるフィルタを適用する。フィルタとしては、低周波成分を減衰させ、高周波成分を通過させるハイパスフィルタ(例えば、FIR(Finite Impulse Response)フィルタ)を用いることができる。
Returning to the description of FIG. 7, the
具体的には、例えば、フィルタ適用部713は、昼データDB800を参照して、予め記録されたフィルタ係数により定まるフィルタを、各線(a線〜c線)の昼の時間帯(6時00分〜18時00分)の電流値に適用する。また、フィルタ適用部713は、昼データDB800を参照して、同様のフィルタを、各需要家C11,C12,C21,C22,C31,C32の昼の時間帯(6時00分〜18時00分)の電力値に適用する。
Specifically, for example, the
また、フィルタ適用部713は、夜データDB900を参照して、同様のフィルタを、各線(a線〜c線)の夜の時間帯(18時00分〜6時00分)の電流値に適用する。また、フィルタ適用部713は、夜データDB900を参照して、同様のフィルタを、各需要家C11,C12,C21,C22,C31,C32の夜の時間帯(18時00分〜6時00分)の電力値に適用する。
The
より詳細に説明すると、例えば、フィルタ適用部713は、下記式(1)を用いて、フィルタ適用後の各線(a線〜c線)の昼の時間帯の電流値を求めることができる。ただし、IX昼_filter(t)は、フィルタ適用後の各線(a線〜c線)の昼の時間帯の電流値である(X=a,b,c)。
More specifically, for example, the
IX昼_filter(t)=−1/3×IX(t−1)_昼+2/3×IX(t)_昼
−1/3×IX(t+1)_昼 ・・・(1)
I X noon _filter (t) = - 1/ 3 × I X (t-1) _ day + 2/3 × I X ( t) _ day
−1 / 3 × I X (t + 1) _daytime (1)
フィルタ適用後の各線(a線〜c線)の昼の時間帯の電流値は、例えば、昼データDB800に記憶される。
The current value of the daytime time zone of each line (a line to c line) after the filter application is stored in, for example, the
また、例えば、フィルタ適用部713は、下記式(2)を用いて、フィルタ適用後の各需要家C11,C12,C21,C22,C31,C32の昼の時間帯の電力値を求めることができる。ただし、PXX昼_filter(t)は、フィルタ適用後の各需要家C11,C12,C21,C22,C31,C32の昼の時間帯の電力値である(XX=11,12,21,22,31,32)。
Further, for example, the
PXX昼_filter(t)=−1/3×PXX(t−1)_昼+2/3×PXX(t)_昼
−1/3×PXX(t+1)_昼 ・・・(2)
P XX noon _filter (t) = - 1/ 3 × P XX (t-1) _ daytime + 2/3 × P XX ( t) _ noon
−1 / 3 × P XX (t + 1) _Daytime (2)
フィルタ適用後の各需要家C11,C12,C21,C22,C31,C32の昼の時間帯の電力値は、例えば、昼データDB800に記憶される。
The electric power values in the daytime hours of the customers C 11 , C 12 , C 21 , C 22 , C 31 , C 32 after applying the filter are stored in, for example, the
また、例えば、フィルタ適用部713は、下記式(3)を用いて、フィルタ適用後の各線(a線〜c線)の夜の時間帯の電流値を求めることができる。ただし、IX夜_filter(t)は、フィルタ適用後の各線(a線〜c線)の夜の時間帯の電流値である(X=a,b,c)。
In addition, for example, the
IX夜_filter(t)=−1/3×IX(t−1)_夜+2/3×IX(t)_夜
−1/3×IX(t+1)_夜 ・・・(3)
I X night _filter (t) = - 1/ 3 × I X (t-1) _ night + 2/3 × I X ( t) _ night
−1 / 3 × I X (t + 1) _night (3)
フィルタ適用後の各線(a線〜c線)の夜の時間帯の電流値は、例えば、夜データDB900に記憶される。
The current value in the night time zone of each line (a line to c line) after applying the filter is stored in the
また、例えば、フィルタ適用部713は、下記式(4)を用いて、フィルタ適用後の各需要家C11,C12,C21,C22,C31,C32の夜の時間帯の電力値を求めることができる。ただし、PXX夜_filter(t)は、フィルタ適用後の各需要家C11,C12,C21,C22,C31,C32の夜の時間帯の電力値である(XX=11,12,21,22,31,32)。
In addition, for example, the
PXX夜_filter(t)=−1/3×PXX(t−1)_夜+2/3×PXX(t)_夜
−1/3×PXX(t+1)_夜 ・・・(4)
P XX night _filter (t) = - 1/ 3 × P XX (t-1) _ night + 2/3 × P XX ( t) _ night
−1 / 3 × P XX (t + 1) _night ... (4)
フィルタ適用後の各需要家C11,C12,C21,C22,C31,C32の夜の時間帯の電力値は、例えば、夜データDB900に記憶される。
The power values in the night time zone of the consumers C 11 , C 12 , C 21 , C 22 , C 31 , C 32 after applying the filter are stored in the
ここで、フィルタ適用後の各線(a線〜c線)の昼の時間帯の電流値を記憶する昼データDB800の記憶内容について説明する。ただし、時刻t#の「#」は、「#=1,2,3,…」となるように振り直している。
Here, the contents stored in the
図10は、昼データDB800の記憶内容の一例を示す説明図(その2)である。図10において、昼データDB800は、フィルタ適用後の各線(a線〜c線)の昼の時間帯(6時00分〜18時00分)の電流値を記憶している。また、昼データDB800は、フィルタ適用後の各需要家C11,C12,C21,C22,C31,C32の昼の時間帯(6時00分〜18時00分)の電力値を記憶している。
FIG. 10 is an explanatory diagram (part 2) of an example of the contents stored in the
つぎに、フィルタ適用後の各線(a線〜c線)の夜の時間帯の電流値を記憶する夜データDB900の記憶内容について説明する。ただし、時刻t#の「#」は、「#=1,2,3,…」となるように振り直している。
Next, the contents stored in the
図11は、夜データDB900の記憶内容の一例を示す説明図(その2)である。図11において、夜データDB900は、フィルタ適用後の各線(a線〜c線)の夜の時間帯(18時00分〜6時00分)の電流値を記憶している。また、夜データDB900は、フィルタ適用後の各需要家C11,C12,C21,C22,C31,C32の夜の時間帯(18時00分〜6時00分)の電力値を記憶している。
FIG. 11 is an explanatory diagram (part 2) illustrating an example of the contents stored in the
図7の説明に戻り、相関分析部714は、各線(a線〜c線)について、電力と電流との相関を示す相関値ρ(IX,P)を算出する(ただし、X=a,b,c)。以下の説明では、配電網EN内のトランスT1〜Tnのうちの任意のトランスTを「トランスTi」と表記する場合がある(i=1,2,…,n)。また、トランスTiに接続された任意の需要家Cを「需要家Cij」と表記する場合がある(j:1以上の自然数)。
Returning to the description of FIG. 7, the
具体的には、例えば、まず、相関分析部714は、図6に示した配電網設備データ600を参照して、トランスTiに接続された全需要家C(スマートメータSMを導入済みの需要家C)を特定する。一例として、トランスT1を例に挙げると、トランスT1に接続された需要家C11,C12が特定される。
Specifically, for example, first, the
また、相関分析部714は、配電網設備データ600を参照して、特定したトランスTiに接続された全需要家Cのうち、太陽光発電を導入済みの需要家Cを特定する。一例として、トランスT1を例に挙げると、トランスT1に接続された需要家C11,C12のうち太陽光発電を導入済みの需要家C12が特定される。
In addition, the
つぎに、相関分析部714は、下記式(5)を用いて、特定したトランスTiに接続された需要家Cのうち、太陽光発電が未導入の需要家Cの昼の時間帯の各時刻tの合計電力値を算出する。トランスTiに接続された需要家Cijの昼の時間帯の各時刻tの電力値は、例えば、図10に示した昼データDB800から特定される。
Next, the
ただし、Pi_昼_filter(t)は、トランスTiに接続された需要家Cのうち、太陽光発電が未導入の需要家Cの昼の時間帯の各時刻tの合計電力値である。zij(t)は、需要家Cijが太陽光発電を導入済みの場合は「zij(t)=0」となり、需要家Cijが太陽光発電を未導入の場合は「zij(t)=1」となる。 However, Pi_daytime_filter (t) is a total electric power value of each time t of the daytime time zone of the consumer C which has not yet introduced solar power generation among the consumers C connected to the transformer Ti. z ij (t) is, in the case if the customer C ij is already introducing solar power "z ij (t) = 0", and the customer C ij of the non-introduction of the solar power "z ij ( t) = 1 ".
Pi_昼_filter(t)=Σj{zij(t)Pij昼_filter(t)}・・・(5) P i —daytime_filter (t) = Σ j {z ij (t) P ij daytime_filter (t)} (5)
一例として、トランスT1に接続された太陽光発電が未導入の需要家Cの昼の時間帯の時刻t1の合計電力値P1_昼_filter(1)を例に挙げると、「P1_昼_filter(1)=P11昼_filter(1)」となる。算出された合計電力値Pi_昼_filter(t)は、例えば、図12に示す昼合計電力テーブル1200に記憶される。 As an example, when the total power value P 1_day_filter (1) at time t1 in the daytime time period of a customer C that has not yet been introduced with photovoltaic power generation connected to the transformer T1 is taken as an example, “P 1_day_filter ( 1) = P 11 daytime_filter (1) ”. The calculated total power value P i_daytime_filter (t) is stored in, for example, the daytime total power table 1200 shown in FIG.
ここで、昼合計電力テーブル1200の記憶内容について説明する。昼合計電力テーブル1200は、例えば、記憶部702に記憶される。
Here, the contents stored in the daytime total power table 1200 will be described. The daytime total power table 1200 is stored in the
図12は、昼合計電力テーブル1200の記憶内容の一例を示す説明図である。図12において、昼合計電力テーブル1200は、各トランスTiに接続された需要家Cのうち、太陽光発電が未導入の需要家Cの昼の時間帯(6時00分〜18時00分)の各時刻tの合計電力値Pi_昼_filter(t)を記憶している。 FIG. 12 is an explanatory diagram showing an example of the stored contents of the daytime total power table 1200. In FIG. 12, the daytime total power table 1200 shows the daytime hours of customers C who have not yet introduced solar power generation among the customers C connected to each transformer Ti (6:00 to 18:00). The total power value P i_daytime_filter (t) at each time t is stored.
図7の説明に戻り、また、相関分析部714は、下記式(6)を用いて、トランスTiに接続された全需要家Cの夜の時間帯の各時刻tの合計電力値を算出する。トランスTiに接続された需要家Cijの夜の時間帯の各時刻tの電力値は、例えば、図11に示した夜データDB900から特定される。ただし、Pi_夜_filter(t)は、トランスTiに接続された全需要家Cの夜の時間帯の各時刻tの合計電力値である。
Returning to the description of FIG. 7, the
Pi_夜_filter(t)=Σj{Pij夜_filter(t)}・・・(6) P i — night — filter (t) = Σ j {P ij night — filter (t)} (6)
一例として、トランスT1に接続された全需要家Cの夜の時間帯の時刻t1の合計電力値P1_夜_filter(1)を例に挙げると、「P1_夜_filter(1)=P11夜_filter(1)+P12夜_filter(1)」となる。算出された合計電力値Pi_夜_filter(t)は、例えば、図13に示す夜合計電力テーブル1300に記憶される。 As an example, if the total power value P 1_night_filter (1) at time t1 of the night time zone of all the consumers C connected to the transformer T1 is taken as an example, “P 1_night_filter (1) = P 11 night _Filter (1) + P 12 night _filter (1) ". The calculated total power value P i_night_filter (t) is stored in, for example, the night total power table 1300 illustrated in FIG.
ここで、夜合計電力テーブル1300の記憶内容について説明する。夜合計電力テーブル1300は、例えば、記憶部702に記憶される。
Here, the contents stored in the night total power table 1300 will be described. The night total power table 1300 is stored in the
図13は、夜合計電力テーブル1300の記憶内容の一例を示す説明図である。図13において、夜合計電力テーブル1300は、各トランスTiに接続された全需要家Cの夜の時間帯(18時00分〜6時00分)の各時刻tの合計電力値Pi_夜_filter(t)を記憶している。 FIG. 13 is an explanatory diagram showing an example of the contents stored in the night total power table 1300. In FIG. 13, the total night power table 1300 includes a total power value P i_night_filter at each time t in the night time zone (18:00 to 6:00) of all the consumers C connected to each transformer Ti. (T) is stored.
なお、上述した説明では、各時刻tの合計電力値をフィルタ適用後の電力値を用いて求める場合を例に挙げて説明したが、これに限らない。例えば、相関分析部714は、各時刻tの合計電力値をフィルタ適用前の電力値を用いて求めることにしてもよい。
In the above description, the case where the total power value at each time t is obtained using the power value after applying the filter has been described as an example, but the present invention is not limited to this. For example, the
図7の説明に戻り、つぎに、相関分析部714は、各線(a線〜c線)について、トランスTiに接続された太陽光発電が未導入の需要家Cの昼の時間帯の各時刻tの合計電力値と、各線(a線〜c線)の昼の時間帯の各時刻tの電流値とに基づいて、電力と電流との相関を示す第1の相関値ρ昼(IX,Pi)を算出する。
Returning to the description of FIG. 7, the
具体的には、例えば、相関分析部714は、下記式(7)および下記式(8)を用いて、第1の相関値ρ昼(IX,Pi)を算出することができる(X=a,b,c)。ただし、ρ(x,y)は、xとyの相関の強さを表す。また、時刻tを「t=1,2,…,T」とする。また、x(t)を「x(t)=IX昼_filter(1),IX昼_filter(2),…,IX昼_filter(T)」とする。x(t)は、例えば、図10に示した昼データDB800から特定される。また、y(t)を「y(t)=Pi_昼_filter(1),Pi_昼_filter(2),…,Pi_昼_filter(T)」とする。y(t)は、例えば、図12に示した昼合計電力テーブル1200から特定される。
Specifically, for example, the
これにより、各線(a線〜c線)についての第1の相関値ρ昼(Ia,Pi),ρ昼(Ib,Pi),ρ昼(Ic,Pi)を算出することができる。算出された第1の相関値ρ昼(IX,Pi)は、例えば、後述の図14に示す相関値テーブル1400に記憶される。 Thus, the first correlation values ρ daytime (I a , P i ), ρ daytime (I b , P i ), and ρ daytime (I c , P i ) for each line (line a to line c) are calculated. be able to. The calculated first correlation value ρ daytime (I X , P i ) is stored in, for example, a correlation value table 1400 shown in FIG.
なお、上述した説明では、昼の時間帯の各時刻tのフィルタ適用後の合計電力値と電流値とを用いて第1の相関値ρ昼(IX,Pi)を求める場合を例に挙げて説明したが、これに限らない。例えば、相関分析部714は、昼の時間帯の各時刻tのフィルタ適用前の合計電力値と電流値とを用いて第1の相関値ρ昼(IX,Pi)を求めることにしてもよい。
In the above description, the case where the first correlation value ρ noon (I X , P i ) is obtained by using the total power value and the current value after applying the filter at each time t in the daytime period is taken as an example. Although it has been described, it is not limited to this. For example, the
また、相関分析部714は、各線(a線〜c線)について、トランスTiに接続された全需要家Cの夜の時間帯の各時刻tの合計電力値と、各線(a線〜c線)の夜の時間帯の各時刻tの電流値とに基づいて、電力と電流との相関を示す第2の相関値ρ夜(IX,Pi)を算出する。
In addition, the
具体的には、例えば、相関分析部714は、上記式(7)および上記式(8)を用いて、第2の相関値ρ夜(IX,Pi)を算出することができる(X=a,b,c)。ただし、x(t)を「x(t)=IX夜_filter(1),IX夜_filter(2),…,IX夜_filter(T)」とする。x(t)は、例えば、図11に示した夜データDB900から特定される。また、y(t)を「y(t)=Pi_夜_filter(1),Pi_夜_filter(2),…,Pi_夜_filter(T)」とする。y(t)は、例えば、図13に示した夜合計電力テーブル1300から特定される。
Specifically, for example, the
これにより、各線(a線〜c線)についての第2の相関値ρ夜(Ia,Pi),ρ夜(Ib,Pi),ρ夜(Ic,Pi)を算出することができる。算出された第2の相関値ρ夜(IX,Pi)は、例えば、図14に示す相関値テーブル1400に記憶される。 Accordingly, the second correlation values ρ night (I a , P i ), ρ night (I b , P i ), and ρ night (I c , P i ) for each line (line a to line c) are calculated. be able to. The calculated second correlation value ρ night (I X , P i ) is stored in, for example, the correlation value table 1400 shown in FIG.
なお、上述した説明では、夜の時間帯の各時刻tのフィルタ適用後の合計電力値と電流値とを用いて第2の相関値ρ夜(IX,Pi)を求める場合を例に挙げて説明したが、これに限らない。例えば、相関分析部714は、夜の時間帯の各時刻tのフィルタ適用前の合計電力値と電流値とを用いて第2の相関値ρ夜(IX,Pi)を求めることにしてもよい。
In the above description, the case where the second correlation value ρ night (I X , P i ) is obtained by using the total power value and current value after applying the filter at each time t in the night time zone is taken as an example. Although it has been described, it is not limited to this. For example, the
ここで、相関値テーブル1400の記憶内容について説明する。相関値テーブル1400は、例えば、記憶部702に記憶される。
Here, the contents stored in the correlation value table 1400 will be described. The correlation value table 1400 is stored in the
図14は、相関値テーブル1400の記憶内容の一例を示す説明図である。図14において、相関値テーブル1400は、トランスTiごとに、第1の相関値ρ昼(IX,Pi)、第2の相関値ρ夜(IX,Pi)および相関値ρ(IX,Pi)を記憶する(X=a,b,c)。 FIG. 14 is an explanatory diagram showing an example of the contents stored in the correlation value table 1400. 14, the correlation value table 1400, for each transformer Ti, the first correlation value [rho noon (I X, P i), the second correlation value [rho night (I X, P i) and the correlation value [rho (I X , P i ) is stored (X = a, b, c).
図14に示す(14−1)の例では、相関値テーブル1400は、トランスT1〜Tnの第1の相関値ρ昼(IX,P1)〜ρ昼(IX,Pn)を記憶している。また、相関値テーブル1400は、トランスT1〜Tnの第2の相関値ρ夜(IX,P1)〜ρ夜(IX,Pn)を記憶している。 In the example of (14-1) illustrated in FIG. 14, the correlation value table 1400 stores the first correlation values ρ day (I X , P 1 ) to ρ day (I X , P n ) of the transformers T1 to Tn. doing. The correlation value table 1400 stores the second correlation values ρ night (I X , P 1 ) to ρ night (I X , P n ) of the transformers T1 to Tn.
図7の説明に戻り、相関分析部714は、算出した第1の相関値ρ昼(IX,Pi)と第2の相関値ρ夜(IX,Pi)との重み付け平均を求めることにより、相関値ρ(IX,Pi)を算出する(X=a,b,c)。具体的には、例えば、相関分析部714は、下記式(9)を用いて、相関値ρ(IX,Pi)を算出することができる。ただし、k昼は、第1の相関値ρ昼(IX,Pi)にかける重みである。また、k夜は、第2の相関値ρ夜(IX,Pi)にかける重みである。また、「k昼+k夜=1」とする。
Referring back to FIG. 7,
ρ(IX,Pi)=k昼×ρ昼(IX,Pi)+k夜×ρ夜(IX,Pi)・・・(9) ρ (I X , P i ) = k day × ρ day (I X , P i ) + k night × ρ night (I X , P i ) (9)
算出された相関値ρ(IX,Pi)は、例えば、図14に示した相関値テーブル1400に記憶される。図14に示す(14−2)の例では、相関値テーブル1400は、トランスT1〜Tnの相関値ρ(IX,P1)〜ρ(IX,Pn)を記憶している(ただし、X=a,b,c)。 The calculated correlation value ρ (I X , P i ) is stored in, for example, the correlation value table 1400 shown in FIG. In the example of (14-2) shown in FIG. 14, the correlation value table 1400 stores the correlation values ρ (I X , P 1 ) to ρ (I X , P n ) of the transformers T1 to Tn (however, X = a, b, c).
また、相関分析部714は、昼の時間帯に含まれる需要家Cの電力または各線(a線〜c線)の電流の計測点の数N昼と、夜の時間帯に含まれる需要家Cの電力または各線(a線〜c線)の電流の計測点の数N夜とに基づいて、重みk昼,k夜を決定することにしてもよい。
Also,
例えば、相関分析部714は、図8に示した昼データDB800の時刻tの数を計数することにより、計測点の数N昼を求めることができる。また、例えば、相関分析部714は、図9に示した夜データDB900の時刻tの数を計数することにより、計測点の数N夜を求めることができる。
For example,
ここで、計測点の数N昼,N夜は、スマートメータSMにより計測される需要家Cの電力値や、センサSEにより計測される各線(a線〜c線)の電流値のデータ数に相当する。また、トランスTiの接続相の判定に用いるデータ数が多いほど、トランスTiの接続相の判定精度が向上とするといえる。このため、相関分析部714は、例えば、「N昼/N夜」の値が大きいほど、重みk昼が大きくなるように、重みk昼,k夜を決定することにしてもよい。
Here, the number N day of measurement points, N night, and the power value of the consumer C as measured by the smart meter SM, the number of data of the current value of each line to be measured by the sensor SE (a line ~c line) Equivalent to. In addition, it can be said that the determination accuracy of the connection phase of the transformer Ti improves as the number of data used for the determination of the connection phase of the transformer Ti increases. Therefore, the
また、相関分析部714は、昼の時間帯の電力値の平均値Pi_昼_aveと、夜の時間帯の電力値の平均値Pi_夜_aveとに基づいて、重みk昼,k夜を決定することにしてもよい。ここで、平均値Pi_昼_aveは、トランスTiに接続された需要家Cのうち太陽光発電が未導入の需要家Cの昼の時間帯の各時刻tの合計電力値の平均である。また、平均値Pi_夜_aveは、トランスTiに接続された全需要家Cの夜の時間帯の各時刻tの合計電力値の平均である。
Further, the
例えば、相関分析部714は、図12に示した昼合計電力テーブル1200を参照して、合計電力値Pi_昼_filter(t)の平均を求めることにより、平均値Pi_昼_aveを算出することができる。また、例えば、相関分析部714は、図13に示した夜合計電力テーブル1300を参照して、合計電力値Pi_夜_filter(t)の平均を求めることにより、平均値Pi_夜_aveを算出することができる。
For example, the
ここで、平均値Pi_昼_aveや平均値Pi_夜_aveが大きいほど、平均値Pi_昼_aveや平均値Pi_夜_aveが、トランス配下の総需要を良く特徴付けているといえる。このため、相関分析部714は、例えば、「Pi_昼_ave/Pi_夜_ave」の値が大きいほど、重みk昼が大きくなるように、重みk昼,k夜を決定することにしてもよい。
Here, it can be said that as the average value P i_day_ave and the average value P i_night_ave are larger, the average value P i_day_ave and the average value P i_night_ave better characterize the total demand under the transformer. Therefore, the
また、相関分析部714は、昼の時間帯の各線(a線〜c線)の電流値の平均値I昼_aveに対する平均値Pi_昼_aveの割合R1と、夜の時間帯の各線(a線〜c線)の電流値の平均値I夜_aveに対する平均値Pi_夜_aveの割合R2とに基づいて、重みk昼,k夜を決定することにしてもよい。
The
例えば、相関分析部714は、図10に示した昼データDB800を参照して、各線(a線〜c線)の電流値IX昼_filter(t)の平均を求めることにより(X=a,b,c)、平均値I昼_aveを算出することができる。また、例えば、相関分析部714は、図11に示した夜データDB900を参照して、各線(a線〜c線)の電流値IX夜_filter(t)の平均を求めることにより(X=a,b,c)、平均値I夜_aveを算出することができる。
For example, the
ここで、割合R1や割合R2が大きいほど、「センサデータから抽出したいトランス配下の電力の特徴/ノイズの量」の値が大きくなり、トランスTiの接続相の判定精度が向上するといえる。このため、相関分析部714は、例えば、「R1/R2」の値が大きいほど、重みk昼が大きくなるように、重みk昼,k夜を決定することにしてもよい。
Here, it can be said that as the ratio R1 and the ratio R2 are larger, the value of “feature of power under the transformer / amount of noise to be extracted from sensor data” is larger, and the determination accuracy of the connection phase of the transformer Ti is improved. Therefore, the
ただし、重みk昼,k夜は、予め設定されて記憶されていてもよい。例えば、トランスTiの接続相の判定に昼の時間帯のデータを用いない場合は、重みk昼,k夜を「k昼=0、k夜=1」と設定していてもよい。また、トランス配下の太陽光発電を導入済みの需要家Cが多いほど、昼の時間帯のデータよりも夜の時間帯のデータのほうが信頼できると仮定して、重みk昼,k夜を設定することにしてもよい。例えば、太陽光発電を導入済みの需要家Cの数と太陽光発電を未導入の需要家Cの数の割合が「1:1」の場合は、夜の時間帯のデータのほうが2倍信頼できると仮定して、重みk昼,k夜を「k昼=1/3、k夜=2/3」と設定していてもよい。 However, the weight k day and k night may be preset and stored. For example, the case of not using the data of the daytime time zone to determine the connection phase of the transformer Ti is the weight k noon, night k may be set as "k day = 0, k Night = 1". Assuming that the more consumers C who have installed solar power under the transformer, the more reliable the data in the night time zone than the data in the day time zone, the weights k are set to day and night . You may decide to do it. For example, if the ratio of the number of consumers C that have already installed solar power generation to the number of customers C that have not yet installed solar power generation is “1: 1”, the data in the night time zone is twice as reliable. Assuming that it is possible, the weight k day and k night may be set as “k day = 1/3, k night = 2/3”.
接続相判定部715は、算出した各線(a線〜c線)の相関値ρ(Ia,Pi),ρ(Ib,Pi),ρ(Ic,Pi)に基づいて、a線〜c線のうちのトランスTiに接続された2つの配電線を判定する。具体的には、例えば、接続相判定部715は、相関値ρ(Ia,Pi),ρ(Ib,Pi),ρ(Ic,Pi)のうちの相関が最も小さい値から、トランスTiの接続相を判定する。
Based on the calculated correlation values ρ (I a , P i ), ρ (I b , P i ), ρ (I c , P i ) of each line (line a to line c), Two distribution lines connected to the transformer Ti among the a line to the c line are determined. Specifically, for example, the connection
より詳細に説明すると、接続相判定部715は、下記式(10)〜(12)のうち、条件を満たす式に対応する相を接続相として判定する。
If it demonstrates in detail, the connection
ρ(Ic,Pi)≦ρ(Ia,Pi),ρ(Ib,Pi) ・・・(10)
ρ(Ia,Pi)≦ρ(Ib,Pi),ρ(Ic,Pi) ・・・(11)
ρ(Ib,Pi)≦ρ(Ic,Pi),ρ(Ia,Pi) ・・・(12)
ρ (I c , P i ) ≦ ρ (I a , P i ), ρ (I b , P i ) (10)
ρ (I a , P i ) ≦ ρ (I b , P i ), ρ (I c , P i ) (11)
ρ (I b , P i ) ≦ ρ (I c , P i ), ρ (I a , P i ) (12)
例えば、上記式(10)を満たす場合、接続相判定部715は、トランスTiの接続相をab相として判定する。また、上記式(11)を満たす場合、接続相判定部715は、トランスTiの接続相をbc相として判定する。また、上記式(12)を満たす場合、接続相判定部715は、トランスTiの接続相をca相として判定する。
For example, when the above formula (10) is satisfied, the connection
判定されたトランスTiの接続相は、例えば、図6に示した配電網設備データ600の接続相フィールドに設定される。例えば、トランスT1の接続相がab相と判定された場合、配電網設備情報600−1の接続相フィールドに「ab相」が設定される。
The determined connection phase of the transformer Ti is set, for example, in the connection phase field of the distribution
出力部716は、判定されたトランスTiの接続相を示す情報を出力する。具体的には、例えば、出力部716は、配電網設備データ600を参照して、各トランスT1〜Tnの接続相を示す情報を出力することにしてもよい。出力部716の出力形式としては、例えば、メモリ302、ディスク304などの記憶装置への記憶、ディスプレイ306への表示、不図示のプリンタへの印刷出力、I/F305による外部装置への送信がある。
The
なお、上述した説明では、第1の相関値ρ昼(IX,Pi)と第2の相関値ρ夜(IX,Pi)との重み付け平均を求めることにより、相関値ρ(IX,Pi)を算出することにしたが、これに限らない。例えば、相関分析部714は、昼の時間帯の各時刻tの合計電力値Pi昼_filter(t)および夜の時間帯の各時刻tの合計電力値Pi夜_filter(t)に基づいて、相関値ρ(IX,Pi)を直接算出することにしてもよい。
Incidentally, in the above description, the first correlation value [rho noon (I X, P i) and the second correlation value [rho night (I X, P i) by obtaining a weighted average of the correlation values [rho (I X , P i ) is calculated, but the present invention is not limited to this. For example,
(トランス接続相判定装置101のトランス接続相判定処理手順)
つぎに、トランス接続相判定装置101のトランス接続相判定処理手順について説明する。
(Transformer connection phase determination processing procedure of the transformer connection phase determination device 101)
Next, the transformer connection phase determination processing procedure of the transformer connection
図15は、トランス接続相判定装置101のトランス接続相判定処理手順の一例を示すフローチャートである。図15のフローチャートにおいて、まず、トランス接続相判定装置101は、配電網EN内の各スマートメータSMにより計測された電力値を示す需要家電力データ500を取得する(ステップS1501)。
FIG. 15 is a flowchart illustrating an example of the transformer connection phase determination processing procedure of the transformer connection
つぎに、トランス接続相判定装置101は、配電網EN内のセンサSEにより計測された各線(a線〜c線)の電流値を示すセンサ線電流データ400を取得する(ステップS1502)。そして、トランス接続相判定装置101は、取得したセンサ線電流データ400を参照して、各線(a線〜c線)の電流値を、昼の時間帯の電流値と夜の時間帯の電流値とに分類する(ステップS1503)。
Next, the transformer connection
つぎに、トランス接続相判定装置101は、分類した昼の時間帯の電流値と夜の時間帯の電流値とに、低周波成分を減衰させるフィルタを適用する(ステップS1504)。そして、トランス接続相判定装置101は、昼の時間帯に含まれる計測点の数N昼と、夜の時間帯に含まれる計測点の数N夜とに基づいて、重みk昼,k夜を決定する(ステップS1505)。
Next, the transformer connection
つぎに、トランス接続相判定装置101は、トランスTiの「i」を「i=1」とする(ステップS1506)。そして、トランス接続相判定装置101は、配電網設備データ600を参照して、配電網EN内のトランスTiを選択する(ステップS1507)。
Next, the transformer connection
つぎに、トランス接続相判定装置101は、選択したトランスTiの接続相を判定する接続相判定処理を実行する(ステップS1508)。なお、接続相判定処理の具体的な処理手順については、図16を用いて後述する。
Next, the transformer connection
つぎに、トランス接続相判定装置101は、トランスTiの「i」をインクリメントして(ステップS1509)、「i」が「n」より大きくなったか否かを判断する(ステップS1510)。ここで、トランスTiの「i」が「n」以下の場合(ステップS1510:No)、トランス接続相判定装置101は、ステップS1507に戻る。
Next, the transformer connection
一方、「i」が「n」より大きい場合(ステップS1510:Yes)、トランス接続相判定装置101は、配電網EN内の各トランスT1〜Tnの接続相を示す情報を出力して(ステップS1511)、本フローチャートによる一連の処理を終了する。
On the other hand, when “i” is larger than “n” (step S1510: Yes), the transformer connection
これにより、配電網EN内の各トランスT1〜Tnの接続相を自動判定することができる。 Thereby, the connection phase of each transformer T1-Tn in the power distribution network EN can be automatically determined.
つぎに、図15に示したステップS1508の接続相判定処理の具体的な処理手順について説明する。 Next, a specific processing procedure of the connection phase determination processing in step S1508 shown in FIG. 15 will be described.
図16は、接続相判定処理の具体的処理手順の一例を示すフローチャートである。図16のフローチャートにおいて、まず、トランス接続相判定装置101は、配電網設備データ600を参照して、トランスTi配下のスマートメータ導入済みの需要家Cを特定する(ステップS1601)。つぎに、トランス接続相判定装置101は、配電網設備データ600を参照して、特定したスマートメータ導入済みの需要家Cのうち、太陽光発電導入済みの需要家Cを特定する(ステップS1602)。
FIG. 16 is a flowchart illustrating an example of a specific processing procedure of the connection phase determination process. In the flowchart of FIG. 16, first, the transformer connection
そして、トランス接続相判定装置101は、需要家電力データ500を参照して、トランスTi配下のスマートメータ導入済みの需要家Cの電力値を、昼の時間帯の電力値と夜の時間帯の電力値とに分類する(ステップS1603)。つぎに、トランス接続相判定装置101は、分類した昼の時間帯の電力値と夜の時間帯の電力値とに、低周波成分を減衰させるフィルタを適用する(ステップS1604)。
Then, the transformer connection
そして、トランス接続相判定装置101は、フィルタ適用後の昼の時間帯の各時刻tの需要家Cの電力値を参照して、トランスTiに接続された太陽光発電未導入の需要家Cの昼の時間帯の各時刻tの合計電力値Pi_昼_filter(t)を算出する(ステップS1605)。
Then, the transformer connection
つぎに、トランス接続相判定装置101は、フィルタ適用後の夜の時間帯の各時刻tの需要家Cの電力値を参照して、トランスTiに接続された全需要家Cの夜の時間帯の各時刻tの合計電力値Pi_夜_filter(t)を算出する(ステップS1606)。
Next, the transformer connection
そして、トランス接続相判定装置101は、算出した昼の時間帯の各時刻tの合計電力値Pi_昼_filter(t)と、各線(a線〜c線)の昼の時間帯の各時刻tのフィルタ適用後の電流値IX昼_filter(t)とに基づいて、第1の相関値ρ昼(IX,Pi)を算出する(ステップS1607)。ただし、Xは、a,b,cのいずれかである。
The transformer connection
つぎに、トランス接続相判定装置101は、算出した夜の時間帯の各時刻tの合計電力値Pi_夜_filter(t)と、各線(a線〜c線)の夜の時間帯の各時刻tのフィルタ適用後の電流値IX夜_filter(t)とに基づいて、第2の相関値ρ夜(IX,Pi)を算出する(ステップS1608)。ただし、Xは、a,b,cのいずれかである。
Next, the transformer connection
そして、トランス接続相判定装置101は、図15に示したステップS1505において決定した重みk昼,k夜を用いて、算出した第1の相関値ρ昼(IX,Pi)と第2の相関値ρ夜(IX,Pi)との重み付け平均を求めることにより、相関値ρ(IX,Pi)を算出する(ステップS1609)。ただし、Xは、a,b,cのいずれかである。
Then, trans-connected
つぎに、トランス接続相判定装置101は、算出した相関値ρ(IX,Pi)に基づいて、トランスTiの接続相を判定して(ステップS1610)、接続相判定処理を呼び出したステップに戻る。これにより、配電網EN内のa線〜c線のうちのトランスTiに接続された2つの配電線を判定することができる。
Next, the transformer connection
なお、上述した説明では、昼・夜の時間帯の電力値に対してフィルタを適用した後に昼・夜の時間帯の各時刻tの合計電力値を算出することにしたが、これに限らない。例えば、トランス接続相判定装置101は、昼・夜の時間帯の各時刻tの合計電力値を算出した後にフィルタを適用することにしてもよい。
In the above description, the total power value at each time t in the day / night time zone is calculated after applying the filter to the power value in the day / night time zone. However, the present invention is not limited to this. . For example, the transformer connection
(トランス接続相判定方法の効果の検証)
つぎに、図17に示す配電網1700を用いて、実施の形態にかかるトランス接続相判定方法の効果の検証について説明する。
(Verification of effects of transformer connection phase judgment method)
Next, verification of the effect of the transformer connection phase determination method according to the embodiment will be described using the
図17は、配電網1700の構成例を示す説明図である。図17において、配電網1700は、三相3線式の配電網であり、センサSEと、複数のトランスT(例えば、トランスT1〜T3)と、複数の需要家C(例えば、需要家C11,C12,C21,C22,C31,C32)とを含む。また、トランスT1の接続相はab相である。トランスT2の接続相はbc相である。トランスT3の接続相はca相である。
FIG. 17 is an explanatory diagram illustrating a configuration example of the
ここで、トランスT1〜T3配下の各需要家C11,C12,C21,C22,C31,C32の時刻tの電力値を以下のように定義する。ただし、C12,C22,C32は、太陽光発電導入済みの需要家Cである。また、Psun(t)は太陽光発電による発電電力である。また、時刻tは「t=1,2,…,17520」である。 Here, the power values at time t of the consumers C 11 , C 12 , C 21 , C 22 , C 31 , C 32 under the transformers T1 to T3 are defined as follows. However, C 12 , C 22 , and C 32 are customers C who have already introduced solar power generation. Further, P sun (t) is generated power by solar power generation. The time t is “t = 1, 2,..., 17520”.
需要家C11:P11_filter(t)=X11(t)
需要家C12:P12_filter(t)=X12(t)+Psun(t)
需要家C21:P21_filter(t)=X21(t)
需要家C22:P22_filter(t)=X22(t)+Psun(t)
需要家C31:P31_filter(t)=X31(t)
需要家C32:P32_filter(t)=X32(t)+Psun(t)
Customer C 11 : P 11 — filter (t) = X 11 (t)
Customer C 12 : P 12_filter (t) = X 12 (t) + P sun (t)
Customer C 21 : P 21_filter (t) = X 21 (t)
Customer C 22 : P 22 — filter (t) = X 22 (t) + P sun (t)
Consumer C 31: P 31_filter (t) = X 31 (t)
Customer C 32 : P 32 — filter (t) = X 32 (t) + P sun (t)
「その他」の部分について、ab相に接続されたトランス配下の需要家Cの時刻tの電力値を「Pab_filter(t)=50Xab(t)+sPsun(t)」と定義する。また、bc相に接続されたトランス配下の需要家Cの時刻tの電力値を「Pbc_filter(t)=50Xbc(t)+sPsun(t)」と定義する。 For the “other” part, the power value at time t of the customer C under the transformer connected to the ab phase is defined as “P ab_filter (t) = 50X ab (t) + sP sun (t)”. Further, the power value at time t of the customer C under the transformer connected to the bc phase is defined as “P bc_filter (t) = 50 × bc (t) + sP sun (t)”.
また、ca相に接続されたトランス配下の需要家Cの時刻tの電力値を「Pca_filter(t)=50Xca(t)+10Psun(t)」と定義する。ただし、係数sは、「その他」の部分の各相(ab相、bc相、ca相)における、太陽光発電を導入している需要家Cの割合を調整するための値である。 Further, the power value at time t of the customer C under the transformer connected to the ca phase is defined as “P ca — filter (t) = 50 × ca (t) + 10P sun (t)”. However, the coefficient s is a value for adjusting the ratio of the customer C introducing solar power generation in each phase (ab phase, bc phase, ca phase) of the “others” portion.
ここで、データの仮定として、X**(t)は、任意の時間t、任意の**について独立にU(−500,500)に従うと仮定する。ただし、U(−500,500)は、−500から500の中の値をランダムにとる確率変数であり、一様分布を表す。また、Psun(t)は昼の時刻にはU(−500,500)に従い、夜の時刻には「0」をとる値とする。また、センサSEの電流は、線路の損失がなくトランスTは全て巻線比が同一の理想変圧器であると仮定する。 Here, as an assumption of data, it is assumed that X ** (t) independently follows U (−500,500) for an arbitrary time t and an arbitrary **. However, U (−500, 500) is a random variable that randomly takes a value in the range of −500 to 500, and represents a uniform distribution. Also, P sun (t) is a value that takes U (−500,500) at daytime and takes “0” at nighttime. The current of the sensor SE is assumed to be an ideal transformer having no line loss and the transformer T having the same turn ratio.
このような仮定をした時の各電力値Pをもとに、トランスT1〜T3の接続相を判定した場合の正答率は図18のようになる。 The correct answer rate when the connected phases of the transformers T1 to T3 are determined based on the respective power values P when such an assumption is made is as shown in FIG.
図18は、トランス接続相判定結果の正答率を示す説明図である。図18において、(手法1)は、昼・夜の時間帯を区別しないでトランスT1〜T3の接続相を判定した場合の正答率を示す。すなわち、(手法1)は、単にフィルタ適用後の電力値と電流値を用いて、トランスT1〜T3の接続相を判定した場合の例である。 FIG. 18 is an explanatory diagram showing the correct answer rate of the transformer connection phase determination result. In FIG. 18, (Method 1) shows the correct answer rate when the connected phases of the transformers T1 to T3 are determined without distinguishing the day / night time zones. That is, (Method 1) is an example in which the connection phase of the transformers T1 to T3 is determined simply using the power value and the current value after applying the filter.
(手法2)は、本トランス接続相判定方法において、重みk昼,k夜を「k昼=0、k夜=1」とした場合のトランスT1〜T3の接続相を判定した場合の正答率を示す。(手法3)は、本トランス接続相判定方法において、重みk昼,k夜を「k昼=1/3、k夜=2/3」とした場合のトランスT1〜T3の接続相を判定した場合の正答率を示す。 (Method 2), in this transformer connected phase determination method, the correct answer rate in the case of determining the connection phase of the transformer T1~T3 when the weight k noon, k night and "k day = 0, k Night = 1" Indicates. In (Method 3), in this transformer connection phase determination method, the connection phases of the transformers T1 to T3 when the weight k day and k night are “k day = 1/3, k night = 2/3” are determined. The correct answer rate is shown.
図18に示すように、(手法2)、(手法3)では、係数sの値が変化しても接続相の判定精度を確保できていることがわかる。例えば、(手法1)では、「その他」の部分の各相(ab相、bc相、ca相)における、太陽光発電を導入している需要家Cの数のバランスが崩れた場合に判定精度が低下するのに対して、(手法2)、(手法3)では、高精度に判定することができている。 As shown in FIG. 18, it is understood that (Method 2) and (Method 3) can ensure the connection phase determination accuracy even if the value of the coefficient s changes. For example, in (Method 1), when the balance of the number of consumers C introducing solar power generation is lost in each phase (ab phase, bc phase, ca phase) of the “others” portion, the determination accuracy On the other hand, in (Method 2) and (Method 3), determination can be made with high accuracy.
以上説明したように、実施の形態にかかるトランス接続相判定装置101によれば、需要家電力データ500を参照して、各需要家Cの電力値を、昼の時間帯の電力値と、夜の時間帯の電力値とに分類することができる。これにより、各需要家Cの電力値を、太陽光発電の影響を考慮すべき電力値と、太陽光発電の影響を考慮しなくてもよい電力値とに分類することができる。
As described above, according to the transformer connection
また、トランス接続相判定装置101によれば、センサ線電流データ400を参照して、各線(a線〜c線)の電流値を、昼の時間帯の電流値と、夜の時間帯の電流値とに分類することができる。これにより、各線(a線〜c線)の電流値を、各需要家Cの電力値に合わせて分類することができる。
Further, according to the transformer connection
また、トランス接続相判定装置101によれば、昼・夜の時間帯の各線の電流値と各需要家Cの電力値とに対して、低周波成分を減衰させるフィルタを適用することができる。これにより、低周波成分を減衰させ、細かい変化(高周波成分)を通過させて、相関分析に不要な共通の成分を除去することができる。
Moreover, according to the transformer connection
また、トランス接続相判定装置101によれば、トランスTiに接続された需要家Cのうち、太陽光発電が未導入の需要家Cの昼の時間帯の各時刻tの合計電力値Pi_昼_filter(t)を算出することができる。これにより、トランス配下の需要家Cで消費された昼の時間帯の合計電力値として、太陽光発電の影響により相関分析に不要となる共通の成分を含む電力値を除去した合計電力値Pi_昼_filter(t)を算出することができる。
Moreover, according to the transformer connection
また、トランス接続相判定装置101によれば、トランスTiに接続された全需要家Cの夜の時間帯の各時刻tの合計電力値Pi_夜_filter(t)を算出することができる。これにより、太陽光発電の影響を受けない夜の時間帯の電力値を最大限活用することができる。
Further, according to the transformer connection
また、トランス接続相判定装置101によれば、昼の時間帯の各時刻tの合計電力値Pi昼_filter(t)と、各線(a線〜c線)の昼の時間帯の各時刻tの電流値IX昼_filter(t)とに基づいて、第1の相関値ρ昼(IX,Pi)を算出することができる(X=a,b,c)。これにより、昼の時間帯の電力と電流との相関を分析することができる。また、フィルタ適用後の合計電力値Pi_昼_filter(t)と電流値IX昼_filter(t)とを用いるため、擬似相関の発生を抑制することができる。
Moreover, according to the transformer connection
また、トランス接続相判定装置101によれば、夜の時間帯の各時刻tの合計電力値Pi_夜_filter(t)と、各線(a線〜c線)の夜の時間帯の各時刻tの電流値IX夜_filter(t)とに基づいて、第2の相関値ρ夜(IX,Pi)を算出することができる(X=a,b,c)。これにより、夜の時間帯の電力と電流との相関を分析することができる。また、フィルタ適用後の合計電力値Pi_夜_filter(t)と電流値IX夜_filter(t)とを用いるため、擬似相関の発生を抑制することができる。
Moreover, according to the transformer connection
また、トランス接続相判定装置101によれば、第1の相関値ρ昼(IX,Pi)と第2の相関値ρ夜(IX,Pi)との重み付け平均を求めることにより、相関値ρ(IX,Pi)を算出することができる(X=a,b,c)。そして、トランス接続相判定装置101によれば、相関値ρ(IX,Pi)に基づいて、トランスTiの接続相を判定することができる。
Further, according to the transformer connection
これにより、トランス配下の全需要家Cの電力値が反映されているためにトランス配下の総需要を良く特徴付けているといえる夜の時間帯のほうに大きな重みを付けて接続相判定を行うことができ、トランスTiの接続相の判定精度を向上させることができる。 As a result, since the power values of all the consumers C under the transformer are reflected, the connection phase determination is performed with a greater weight on the night time zone that can be said to characterize the total demand under the transformer well. It is possible to improve the determination accuracy of the connection phase of the transformer Ti.
また、トランス接続相判定装置101によれば、昼の時間帯の計測点の数N昼と、夜の時間帯の計測点の数N夜とに基づいて、重みk昼,k夜を決定することができる。これにより、データ数(計測点)が多い時間帯のほうに重みを付けて接続相判定を行うことができ、トランスTiの接続相の判定精度を向上させることができる。
Moreover, according to the transformer connection
また、トランス接続相判定装置101によれば、昼の時間帯の電力値の平均値Pi_昼_aveと、夜の時間帯の電力値の平均値Pi_夜_aveとに基づいて、重みk昼,k夜を決定することができる。これにより、需要家Cの合計電力値の平均値が大きいためにトランス配下の総需要を良く特徴付けているといえる時間帯のほうに重みを付けて接続相判定を行うことができ、トランスTiの接続相の判定精度を向上させることができる。
Further, according to the transformer connection
また、トランス接続相判定装置101によれば、昼の時間帯の電流値の平均値I昼_aveに対する平均値Pi_昼_aveの割合R1と、夜の時間帯の電流値の平均値I夜_aveに対する平均値Pi_夜_aveの割合R2とに基づいて、重みk昼,k夜を決定することができる。これにより、配電網全体のノイズの量に対してセンサデータから抽出したいトランス配下の電力の特徴が大きくなる時間帯のほうに重みを付けて接続相判定を行うことができ、トランスTiの接続相の判定精度を向上させることができる。
Further, according to the transformer connection
これらのことから、トランス接続相判定装置101によれば、配電網EN内のトランス配下の需要家Cに太陽光発電を導入した需要家Cが含まれる場合であっても、トランスTiの接続相を高精度に判定することができる。
Therefore, according to the transformer connection
なお、本実施の形態で説明したトランス接続相判定方法は、予め用意されたプログラムをパーソナル・コンピュータやワークステーション等のコンピュータで実行することにより実現することができる。本トランス接続相判定プログラムは、ハードディスク、フレキシブルディスク、CD−ROM、MO、DVD等のコンピュータで読み取り可能な記録媒体に記録され、コンピュータによって記録媒体から読み出されることによって実行される。また、本トランス接続相判定プログラムは、インターネット等のネットワークを介して配布してもよい。 The transformer connection phase determination method described in the present embodiment can be realized by executing a program prepared in advance on a computer such as a personal computer or a workstation. The transformer connection phase determination program is recorded on a computer-readable recording medium such as a hard disk, a flexible disk, a CD-ROM, an MO, and a DVD, and is executed by being read from the recording medium by the computer. Further, the transformer connection phase determination program may be distributed through a network such as the Internet.
上述した実施の形態に関し、さらに以下の付記を開示する。 The following additional notes are disclosed with respect to the embodiment described above.
(付記1)コンピュータに、
3以上の配電線のいずれか2つの配電線に接続されたトランスに接続された需要家で消費された計測期間内の各時間帯の電力値のうち、太陽光発電が導入された需要家で消費された特定の時間帯の電力値を除く前記各時間帯の電力値を取得し、
前記3以上の配電線の各々の配電線について、取得した前記各時間帯の電力値と、前記各々の配電線に流れた前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出し、
算出した前記各々の配電線の相関値に基づいて、前記3以上の配電線のうちの前記トランスに接続された2つの配電線を判定する、
処理を実行させることを特徴とするトランス接続相判定プログラム。
(Supplementary note 1)
Of the power values in each time zone within the measurement period consumed by the consumer connected to the transformer connected to any two of the three or more distribution lines, it is a consumer with solar power generation introduced Obtain the power value for each time period excluding the power value for the specific time period consumed,
For each distribution line of the three or more distribution lines, based on the acquired power value of each time zone and the current value of each time zone flowing through each of the distribution lines, the correlation between power and current Calculate a correlation value indicating
Based on the calculated correlation value of each distribution line, two distribution lines connected to the transformer among the three or more distribution lines are determined.
A transformer connection phase determination program characterized in that a process is executed.
(付記2)前記コンピュータに、
前記各々の配電線について、取得した前記各時間帯の電力値のうちの前記特定の時間帯の電力値と、前記各時間帯の電流値のうちの前記特定の時間帯の電流値とに基づいて、電力と電流との相関を示す第1の相関値を算出し、
前記各々の配電線について、取得した前記各時間帯の電力値のうちの前記特定の時間帯とは異なる他の時間帯の電力値と、前記各時間帯の電流値のうちの前記他の時間帯の電流値とに基づいて、電力と電流との相関を示す第2の相関値を算出する、処理を実行させ、
前記相関値を算出する処理は、
前記各々の配電線について、算出した前記第1の相関値と前記第2の相関値との重み付け平均を求めることにより、前記相関値を算出することを特徴とする付記1に記載のトランス接続相判定プログラム。
(Supplementary note 2)
For each distribution line, based on the power value of the specific time zone among the acquired power values of the time zone and the current value of the specific time zone of the current value of each time zone. Calculating a first correlation value indicating a correlation between electric power and current,
For each distribution line, the power value in another time zone different from the specific time zone among the acquired power values in each time zone, and the other time in the current value in each time zone. Calculating a second correlation value indicating a correlation between the power and the current based on the current value of the belt,
The process of calculating the correlation value includes:
The transformer connection phase according to
(付記3)前記相関値を算出する処理は、
前記特定の時間帯に含まれる電力または電流の計測点の数と、前記他の時間帯に含まれる電力または電流の計測点の数とに基づいて、前記第1の相関値と前記第2の相関値との重み付け平均を求めることにより、前記相関値を算出することを特徴とする付記2に記載のトランス接続相判定プログラム。
(Supplementary Note 3) The process of calculating the correlation value is as follows:
Based on the number of power or current measurement points included in the specific time zone and the number of power or current measurement points included in the other time zone, the first correlation value and the second The transformer connection phase determination program according to
(付記4)前記相関値を算出する処理は、
前記特定の時間帯の電力値の平均値と、前記他の時間帯の電力値の平均値とに基づいて、前記第1の相関値と前記第2の相関値との重み付け平均を求めることにより、前記相関値を算出することを特徴とする付記2に記載のトランス接続相判定プログラム。
(Supplementary Note 4) The process of calculating the correlation value is as follows:
By calculating a weighted average of the first correlation value and the second correlation value based on the average value of the power values in the specific time zone and the average value of the power values in the other time zones. The transformer connection phase determination program according to
(付記5)前記相関値を算出する処理は、
前記特定の時間帯の電流値の平均値に対する前記特定の時間帯の電力値の平均値の割合と、前記他の時間帯の電流値の平均値に対する前記他の時間帯の電力値の平均値の割合とに基づいて、前記第1の相関値と前記第2の相関値との重み付け平均を求めることにより、前記相関値を算出することを特徴とする付記2に記載のトランス接続相判定プログラム。
(Supplementary Note 5) The process of calculating the correlation value is as follows:
The ratio of the average value of the power value of the specific time zone to the average value of the current value of the specific time zone, and the average value of the power value of the other time zone to the average value of the current value of the other time zone The transformer connection phase determination program according to
(付記6)前記コンピュータに、
取得した前記各時間帯の電力値と前記各時間帯の電流値とに対して、低周波成分を減衰させるフィルタを適用する処理を実行させ、
前記相関値を算出する処理は、
前記各々の配電線について、前記フィルタを適用した前記各時間帯の電力値と前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出することを特徴とする付記1〜5のいずれか一つに記載のトランス接続相判定プログラム。
(Appendix 6)
A process of applying a filter for attenuating a low-frequency component is performed on the acquired power value of each time zone and the current value of each time zone,
The process of calculating the correlation value includes:
For each distribution line, a correlation value indicating a correlation between power and current is calculated based on a power value in each time zone to which the filter is applied and a current value in each time zone. The transformer connection phase determination program according to any one of
(付記7)コンピュータが、
3以上の配電線のいずれか2つの配電線に接続されたトランスに接続された需要家で消費された計測期間内の各時間帯の電力値のうち、太陽光発電が導入された需要家で消費された特定の時間帯の電力値を除く前記各時間帯の電力値を取得し、
前記3以上の配電線の各々の配電線について、取得した前記各時間帯の電力値と、前記各々の配電線に流れた前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出し、
算出した前記各々の配電線の相関値に基づいて、前記3以上の配電線のうちの前記トランスに接続された2つの配電線を判定する、
処理を実行することを特徴とするトランス接続相判定方法。
(Appendix 7) The computer
Of the power values in each time zone within the measurement period consumed by the consumer connected to the transformer connected to any two of the three or more distribution lines, it is a consumer with solar power generation introduced Obtain the power value for each time period excluding the power value for the specific time period consumed,
For each distribution line of the three or more distribution lines, based on the acquired power value of each time zone and the current value of each time zone flowing through each of the distribution lines, the correlation between power and current Calculate a correlation value indicating
Based on the calculated correlation value of each distribution line, two distribution lines connected to the transformer among the three or more distribution lines are determined.
A transformer connection phase determination method characterized by executing processing.
(付記8)3以上の配電線のいずれか2つの配電線に接続されたトランスに接続された需要家で消費された計測期間内の各時間帯の電力値のうち、太陽光発電が導入された需要家で消費された特定の時間帯の電力値を除く前記各時間帯の電力値を取得し、
前記3以上の配電線の各々の配電線について、取得した前記各時間帯の電力値と、前記各々の配電線に流れた前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出し、
算出した前記各々の配電線の相関値に基づいて、前記3以上の配電線のうちの前記トランスに接続された2つの配電線を判定する、
制御部を有することを特徴とするトランス接続相判定装置。
(Supplementary note 8) Of the power values in each time zone within the measurement period consumed by the consumer connected to the transformer connected to any two of the three or more distribution lines, solar power generation was introduced Obtain the power value of each time period excluding the power value of a specific time period consumed by a consumer,
For each distribution line of the three or more distribution lines, based on the acquired power value of each time zone and the current value of each time zone flowing through each of the distribution lines, the correlation between power and current Calculate a correlation value indicating
Based on the calculated correlation value of each distribution line, two distribution lines connected to the transformer among the three or more distribution lines are determined.
A transformer connection phase determination device comprising a control unit.
(付記9)コンピュータに、
3以上の配電線のいずれか2つの配電線に接続されたトランスに接続された需要家で消費された計測期間内の各時間帯の電力値のうち、太陽光発電が導入された需要家で消費された特定の時間帯の電力値を除く前記各時間帯の電力値を取得し、
前記3以上の配電線の各々の配電線について、取得した前記各時間帯の電力値と、前記各々の配電線に流れた前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出し、
算出した前記各々の配電線の相関値に基づいて、前記3以上の配電線のうちの前記トランスに接続された2つの配電線を判定する、
処理を実行させるトランス接続相判定プログラムを記録したことを特徴とする前記コンピュータに読み取り可能な記録媒体。
(Appendix 9)
Of the power values in each time zone within the measurement period consumed by the consumer connected to the transformer connected to any two of the three or more distribution lines, it is a consumer with solar power generation introduced Obtain the power value for each time period excluding the power value for the specific time period consumed,
For each distribution line of the three or more distribution lines, based on the acquired power value of each time zone and the current value of each time zone flowing through each of the distribution lines, the correlation between power and current Calculate a correlation value indicating
Based on the calculated correlation value of each distribution line, two distribution lines connected to the transformer among the three or more distribution lines are determined.
A computer-readable recording medium having a transformer connection phase determination program for executing processing recorded therein.
101 トランス接続相判定装置
200 トランス接続相判定システム
400 センサ線電流データ
500 需要家電力データ
600 配電網設備データ
701 制御部
702 記憶部
711 取得部
712 データ分類部
713 フィルタ適用部
714 相関分析部
715 接続相判定部
716 出力部
800 昼データDB
900 夜データDB
1200 昼合計電力テーブル
1300 夜合計電力テーブル
1400 相関値テーブル
1700,EN 配電網
C 需要家
SE センサ
SM スマートメータ
SU 変電所
DESCRIPTION OF
900 Night Data DB
1200 Total power table for daytime 1300 Total power table for
Claims (8)
3以上の配電線のいずれか2つの配電線に接続されたトランスに接続された需要家で消費された計測期間内の各時間帯の電力値のうち、太陽光発電が導入された需要家で消費された特定の時間帯の電力値を除く前記各時間帯の電力値を取得し、
前記3以上の配電線の各々の配電線について、取得した前記各時間帯の電力値と、前記各々の配電線に流れた前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出し、
算出した前記各々の配電線の相関値に基づいて、前記3以上の配電線のうちの前記トランスに接続された2つの配電線を判定する、
処理を実行させることを特徴とするトランス接続相判定プログラム。 On the computer,
Of the power values in each time zone within the measurement period consumed by the consumer connected to the transformer connected to any two of the three or more distribution lines, it is a consumer with solar power generation introduced Obtain the power value for each time period excluding the power value for the specific time period consumed,
For each distribution line of the three or more distribution lines, based on the acquired power value of each time zone and the current value of each time zone flowing through each of the distribution lines, the correlation between power and current Calculate a correlation value indicating
Based on the calculated correlation value of each distribution line, two distribution lines connected to the transformer among the three or more distribution lines are determined.
A transformer connection phase determination program characterized in that a process is executed.
前記各々の配電線について、取得した前記各時間帯の電力値のうちの前記特定の時間帯の電力値と、前記各時間帯の電流値のうちの前記特定の時間帯の電流値とに基づいて、電力と電流との相関を示す第1の相関値を算出し、
前記各々の配電線について、取得した前記各時間帯の電力値のうちの前記特定の時間帯とは異なる他の時間帯の電力値と、前記各時間帯の電流値のうちの前記他の時間帯の電流値とに基づいて、電力と電流との相関を示す第2の相関値を算出する、処理を実行させ、
前記相関値を算出する処理は、
前記各々の配電線について、算出した前記第1の相関値と前記第2の相関値との重み付け平均を求めることにより、前記相関値を算出することを特徴とする請求項1に記載のトランス接続相判定プログラム。 In the computer,
For each distribution line, based on the power value of the specific time zone among the acquired power values of the time zone and the current value of the specific time zone of the current value of each time zone. Calculating a first correlation value indicating a correlation between electric power and current,
For each distribution line, the power value in another time zone different from the specific time zone among the acquired power values in each time zone, and the other time in the current value in each time zone. Calculating a second correlation value indicating a correlation between the power and the current based on the current value of the belt,
The process of calculating the correlation value includes:
The transformer connection according to claim 1, wherein the correlation value is calculated by obtaining a weighted average of the calculated first correlation value and the second correlation value for each distribution line. Phase judgment program.
前記特定の時間帯に含まれる電力または電流の計測点の数と、前記他の時間帯に含まれる電力または電流の計測点の数とに基づいて、前記第1の相関値と前記第2の相関値との重み付け平均を求めることにより、前記相関値を算出することを特徴とする請求項2に記載のトランス接続相判定プログラム。 The process of calculating the correlation value includes:
Based on the number of power or current measurement points included in the specific time zone and the number of power or current measurement points included in the other time zone, the first correlation value and the second The transformer connection phase determination program according to claim 2, wherein the correlation value is calculated by calculating a weighted average with the correlation value.
前記特定の時間帯の電力値の平均値と、前記他の時間帯の電力値の平均値とに基づいて、前記第1の相関値と前記第2の相関値との重み付け平均を求めることにより、前記相関値を算出することを特徴とする請求項2に記載のトランス接続相判定プログラム。 The process of calculating the correlation value includes:
By calculating a weighted average of the first correlation value and the second correlation value based on the average value of the power values in the specific time zone and the average value of the power values in the other time zones. The transformer connection phase determination program according to claim 2, wherein the correlation value is calculated.
前記特定の時間帯の電流値の平均値に対する前記特定の時間帯の電力値の平均値の割合と、前記他の時間帯の電流値の平均値に対する前記他の時間帯の電力値の平均値の割合とに基づいて、前記第1の相関値と前記第2の相関値との重み付け平均を求めることにより、前記相関値を算出することを特徴とする請求項2に記載のトランス接続相判定プログラム。 The process of calculating the correlation value includes:
The ratio of the average value of the power value of the specific time zone to the average value of the current value of the specific time zone, and the average value of the power value of the other time zone to the average value of the current value of the other time zone The transformer connection phase determination according to claim 2, wherein the correlation value is calculated by obtaining a weighted average of the first correlation value and the second correlation value based on a ratio of the first correlation value and the second correlation value. program.
取得した前記各時間帯の電力値と前記各時間帯の電流値とに対して、低周波成分を減衰させるフィルタを適用する処理を実行させ、
前記相関値を算出する処理は、
前記各々の配電線について、前記フィルタを適用した前記各時間帯の電力値と前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出することを特徴とする請求項1〜5のいずれか一つに記載のトランス接続相判定プログラム。 In the computer,
A process of applying a filter for attenuating a low-frequency component is performed on the acquired power value of each time zone and the current value of each time zone,
The process of calculating the correlation value includes:
For each distribution line, a correlation value indicating a correlation between power and current is calculated based on a power value in each time zone to which the filter is applied and a current value in each time zone. The transformer connection phase determination program according to any one of claims 1 to 5.
3以上の配電線のいずれか2つの配電線に接続されたトランスに接続された需要家で消費された計測期間内の各時間帯の電力値のうち、太陽光発電が導入された需要家で消費された特定の時間帯の電力値を除く前記各時間帯の電力値を取得し、
前記3以上の配電線の各々の配電線について、取得した前記各時間帯の電力値と、前記各々の配電線に流れた前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出し、
算出した前記各々の配電線の相関値に基づいて、前記3以上の配電線のうちの前記トランスに接続された2つの配電線を判定する、
処理を実行することを特徴とするトランス接続相判定方法。 Computer
Of the power values in each time zone within the measurement period consumed by the consumer connected to the transformer connected to any two of the three or more distribution lines, it is a consumer with solar power generation introduced Obtain the power value for each time period excluding the power value for the specific time period consumed,
For each distribution line of the three or more distribution lines, based on the acquired power value of each time zone and the current value of each time zone flowing through each of the distribution lines, the correlation between power and current Calculate a correlation value indicating
Based on the calculated correlation value of each distribution line, two distribution lines connected to the transformer among the three or more distribution lines are determined.
A transformer connection phase determination method characterized by executing processing.
前記3以上の配電線の各々の配電線について、取得した前記各時間帯の電力値と、前記各々の配電線に流れた前記各時間帯の電流値とに基づいて、電力と電流との相関を示す相関値を算出し、
算出した前記各々の配電線の相関値に基づいて、前記3以上の配電線のうちの前記トランスに接続された2つの配電線を判定する、
制御部を有することを特徴とするトランス接続相判定装置。 Of the power values in each time zone within the measurement period consumed by the consumer connected to the transformer connected to any two of the three or more distribution lines, it is a consumer with solar power generation introduced Obtain the power value for each time period excluding the power value for the specific time period consumed,
For each distribution line of the three or more distribution lines, based on the acquired power value of each time zone and the current value of each time zone flowing through each of the distribution lines, the correlation between power and current Calculate a correlation value indicating
Based on the calculated correlation value of each distribution line, two distribution lines connected to the transformer among the three or more distribution lines are determined.
A transformer connection phase determination device comprising a control unit.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2014202249A JP6327092B2 (en) | 2014-09-30 | 2014-09-30 | Transformer connection phase determination program, transformer connection phase determination method, and transformer connection phase determination device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2014202249A JP6327092B2 (en) | 2014-09-30 | 2014-09-30 | Transformer connection phase determination program, transformer connection phase determination method, and transformer connection phase determination device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2016073136A JP2016073136A (en) | 2016-05-09 |
| JP6327092B2 true JP6327092B2 (en) | 2018-05-23 |
Family
ID=55865080
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2014202249A Active JP6327092B2 (en) | 2014-09-30 | 2014-09-30 | Transformer connection phase determination program, transformer connection phase determination method, and transformer connection phase determination device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP6327092B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7215226B2 (en) * | 2019-02-28 | 2023-01-31 | 東京電力ホールディングス株式会社 | Connected phase estimating device, connected phase estimating program, and connected phase estimating method |
| JP7615565B2 (en) * | 2020-08-20 | 2025-01-17 | 東京電力ホールディングス株式会社 | Connection phase estimation device, connection phase estimation program, and connection phase estimation method |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US8825416B2 (en) * | 2011-02-28 | 2014-09-02 | International Business Machines Corporation | Systems and methods for phase identification |
| JP5665619B2 (en) * | 2011-03-18 | 2015-02-04 | 三菱電機株式会社 | Phase discrimination device |
| US8682604B2 (en) * | 2011-08-03 | 2014-03-25 | General Electric Company | Method and system of phase identification |
| JP6209951B2 (en) * | 2013-11-14 | 2017-10-11 | 富士通株式会社 | Transformer connection phase determination device, method, and program |
| JP6331465B2 (en) * | 2014-02-26 | 2018-05-30 | 富士通株式会社 | Transformer connection phase determination device, transformer connection phase determination method, and transformer connection phase determination program |
-
2014
- 2014-09-30 JP JP2014202249A patent/JP6327092B2/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| JP2016073136A (en) | 2016-05-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| Rueda et al. | Wavelet-based analysis of power system low-frequency electromechanical oscillations | |
| CN105706325B (en) | grid frequency response | |
| JP6409286B2 (en) | Transformer connection phase determination device, method, and program | |
| CN104657788B (en) | Key industry electricity demand forecasting method based on Industrial Cycle index | |
| JP6331465B2 (en) | Transformer connection phase determination device, transformer connection phase determination method, and transformer connection phase determination program | |
| EP3084913B1 (en) | Methods and systems for power injection or extraction in a power network | |
| WO2015196133A2 (en) | Energy infrastructure sensor data rectification using regression models | |
| JP6209951B2 (en) | Transformer connection phase determination device, method, and program | |
| US9389618B2 (en) | Line drop compensation methods and systems | |
| JP2016070812A (en) | Transformer connection phase determination device, method, and program | |
| JP2017121133A (en) | Power demand prediction device and power demand prediction program | |
| Milanović et al. | Compound index for power quality evaluation and benchmarking | |
| Sankarakrishnan et al. | Effective techniques for reliability worth assessment in composite power system networks using Monte Carlo simulation | |
| Yu et al. | On statistical modeling and forecasting of energy usage in smart grid | |
| Li et al. | Transformer-customer connectivity relationship identification for low-voltage distribution system with high penetration of household PV systems | |
| JP6327092B2 (en) | Transformer connection phase determination program, transformer connection phase determination method, and transformer connection phase determination device | |
| JP6135454B2 (en) | Estimation program, estimation apparatus, and estimation method | |
| Moreno et al. | An integrated tool for assessing the demand profile flexibility | |
| Mogos et al. | Hierarchical load forecast aggregation for distribution transformers using minimum trace optimal reconciliation and AMI data | |
| Klusacek et al. | Performance of smart revenue meters under bidirectional active energy flows in energy communities | |
| Yusuf et al. | PV Hosting Capacity Estimation in Low-Voltage Secondary Networks Using Statistical Properties of AMI Data | |
| CN103544362B (en) | A kind of harmonic wave medium-and long-term forecasting method based on two-dimensional curve prediction | |
| JP2017182266A (en) | Power demand prediction device | |
| De Sousa et al. | Smart Metering Enabled by the Internet of Things for Monitoring Residential Energy Consumption and Power Quality | |
| CN120822672B (en) | Low-voltage active station area line loss rate prediction method and system based on improved GAN |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20170605 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20180309 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20180320 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20180402 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 6327092 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |