Power supply system, power supply method, and server Download PDF

Info

Publication number
JP6430892B2
JP6430892B2 JP2015099236A JP2015099236A JP6430892B2 JP 6430892 B2 JP6430892 B2 JP 6430892B2 JP 2015099236 A JP2015099236 A JP 2015099236A JP 2015099236 A JP2015099236 A JP 2015099236A JP 6430892 B2 JP6430892 B2 JP 6430892B2
Authority
JP
Japan
Prior art keywords
load
power supply
information
reduction
ict
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2015099236A
Other languages
Japanese (ja)
Other versions
JP2016220291A (en
Inventor
暁 松本
暁 松本
武田 隆
隆 武田
三野 正人
正人 三野
英昭 石川
英昭 石川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NTT Facilities Inc
Original Assignee
NTT Facilities Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NTT Facilities Inc filed Critical NTT Facilities Inc
Priority to JP2015099236A priority Critical patent/JP6430892B2/en
Publication of JP2016220291A publication Critical patent/JP2016220291A/en
Application granted granted Critical
Publication of JP6430892B2 publication Critical patent/JP6430892B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/221General power management systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/242Home appliances
    • Y04S20/244Home appliances the home appliances being or involving heating ventilating and air conditioning [HVAC] units

Landscapes

  • Air Conditioning Control Device (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Description

本発明は、負荷に対して電力を供給する給電システム、給電方法およびサーバに関する。   The present invention relates to a power supply system that supplies power to a load, a power supply method, and a server.

複数のICT機器や空調機器などの負荷装置、および、この負荷装置に電力を供給する給電装置を備えた給電システムにおいて、現状では、ICT機器などの負荷装置の動作状況に無関係に給電が行われている。近年の消費電力低減の要望の高まりに伴い、上述の給電システムを構成する給電装置等においても、消費電力の低減を図る種々の技術が提案されている(例えば、特許文献1参照。)。   In a power supply system including a plurality of load devices such as ICT devices and air conditioners, and a power supply device that supplies power to the load devices, power is currently supplied regardless of the operation status of the load devices such as ICT devices. ing. With the recent increase in demand for power consumption reduction, various techniques for reducing power consumption have been proposed in the power supply apparatus and the like that constitute the above-described power supply system (see, for example, Patent Document 1).

特許文献1には、効率の悪い軽負荷状態で給電装置が運転されると、給電装置における損失が大きくなり消費電力の増大を招くため、効率の良い高負荷状態で給電装置が運転されるように制御する技術が開示されている。   In Patent Document 1, when the power supply apparatus is operated in a light load state with low efficiency, loss in the power supply apparatus increases and power consumption is increased. Therefore, the power supply apparatus is operated in an efficient high load state. Techniques for controlling are disclosed.

特開2010−154613号公報JP 2010-154613 A

上述の特許文献1に記載の技術では、給電装置における電力損失の低減を図ることはできても、給電システムを構成する他の要素、例えばICT機器や、ICT装置の冷却に用いられる空調装置などの負荷装置に対しては、電力損失の低減を図ることができないという問題があった。   In the technique described in Patent Document 1 described above, although power loss in the power supply apparatus can be reduced, other elements constituting the power supply system, such as ICT equipment and air conditioners used for cooling the ICT apparatus, etc. However, there is a problem that the power loss cannot be reduced.

その一方で、近年の情報処理技術の進歩に伴い、仮想化技術を用いて情報処理を行うICT機器の台数を削減する技術が、ICT機器における消費電力を削減する方法として着目されつつある。この場合、空調装置、ICT装置および給電装置のそれぞれに対して個別に消費電力を削減する制御を行う方法も考えられる。しかしながら個別の消費電力削減制御では、十分な消費電力の削減を望みにくいという問題があった。   On the other hand, with the recent progress of information processing technology, a technology for reducing the number of ICT devices that perform information processing using a virtualization technology is drawing attention as a method for reducing power consumption in ICT devices. In this case, a method of performing control to reduce power consumption individually for each of the air conditioner, the ICT device, and the power feeding device is also conceivable. However, the individual power consumption reduction control has a problem that it is difficult to expect a sufficient power consumption reduction.

また、従来のサーバは負荷の大小に関わらず、ほぼ一定の電力を消費していたが、昨今のサーバにおいては、エネルギーマネージメント機能の向上により、負荷の大小に依存して消費電力がダイナミックに変動する機器が増加している。そのため、サーバルームにおける機器からの発熱量の変化が従来に比べて大きくなっている。   Also, conventional servers consumed almost constant power regardless of the load, but recent servers have dynamically improved power consumption depending on the load due to improved energy management functions. The number of devices to be increased. Therefore, the change in the amount of heat generated from the equipment in the server room is larger than in the past.

その一方で、信頼度向上のために空調機の台数は必要台数に加えて予備機を加えた運用となるために、サーバの負荷が小さい時間帯などにおいては空調機の冷却能力が過剰な運用状態が生まれている。このような状況下では、空調機における冷却のオン・オフの繰り返しによる運転効率の低下や軽負荷時の低効率(低COP)な運転機会の増加が顕在化しており、ICT装置の運転状態を考慮した全体制御技術が望まれていた。   On the other hand, in order to improve reliability, the number of air conditioners will be increased by adding spare units in addition to the required number, so the cooling capacity of the air conditioners will be excessively operated during times when the server load is low. A state is born. Under such circumstances, the decrease in operation efficiency due to repeated cooling on and off in air conditioners and the increase in low-efficiency (low-COP) operation opportunities at light loads have become apparent, and the operating state of the ICT device has become apparent. The whole control technology that considered it was desired.

本発明は、上記の課題を解決するためになされたものであって、電力損失の低減を図ることができる給電システム、給電方法およびサーバを提供することを目的とする。   SUMMARY An advantage of some aspects of the invention is that it provides a power feeding system, a power feeding method, and a server that can reduce power loss.

上記目的を達成するために、本発明は、以下の手段を提供する。
本発明の第1の態様に係る給電システムは、所定電流を出力する複数の給電機器を有する給電装置と、前記給電装置から給電されて作動負荷の処理を行う複数の負荷装置、および、前記複数の負荷装置を冷却する複数の空調装置を少なくとも制御する制御部と、を備えた給電システムであって、前記制御部には、前記複数の負荷装置における作動負荷量に関するパラメータを取得する取得部と、前記取得部により取得した前記パラメータに基づいて、一部の負荷装置(以下、「移行元の負荷装置」と表記する。)において処理される前記作動負荷を残りの負荷装置の少なくとも一部(以下、「移行先の負荷装置」と表記する。)で処理することによる消費電力の削減(以下、「負荷装置による削減」と表記する。)、および、前記空調装置の冷房能力を制御することによる消費電力の削減(以下、「空調装置による削減」と表記する。)のいずれを優先するか優先順位を求める処理部と、が設けられていることを特徴とする。
In order to achieve the above object, the present invention provides the following means.
A power supply system according to a first aspect of the present invention includes a power supply device having a plurality of power supply devices that output a predetermined current, a plurality of load devices that are fed from the power supply device and process an operating load, and the plurality A power supply system including at least a control unit that controls a plurality of air conditioners that cool the load device, and the control unit includes an acquisition unit that acquires a parameter relating to an operating load amount in the plurality of load devices; Based on the parameters acquired by the acquisition unit, the operating load processed in a part of load devices (hereinafter referred to as “migration source load device”) is at least a part of the remaining load devices ( (Hereinafter referred to as “the load device at the transfer destination”), the reduction of power consumption by processing (hereinafter referred to as “the reduction by the load device”), and the air conditioner Reduction in power consumption by controlling the tufts ability, characterized in that a processing unit for determining whether priority to prioritize either (hereinafter referred to as "reduced by the air conditioner."), Is provided.

本発明の第2の態様に係る給電方法は、所定電流を出力する複数の給電機器を有する給電装置と、前記給電装置から給電されて作動負荷の処理を行う複数の負荷装置、および、前記複数の負荷装置を冷却する複数の空調装置を少なくとも制御する制御部と、を備えた給電システムにおける給電方法であって、前記複数の負荷装置における作動負荷量に関するパラメータを取得する取得ステップと、取得した前記パラメータに基づいて、一部の負荷装置(以下、「移行元の負荷装置」と表記する。)において処理される前記作動負荷を残りの負荷装置の少なくとも一部(以下、「移行先の負荷装置」と表記する。)で処理することによる消費電力の削減(以下、「負荷装置による削減」と表記する。)、および、前記空調装置の冷房能力を制御することによる消費電力の削減(以下、「空調装置による削減」と表記する。)のいずれを優先するか優先順位を求める優先処理ステップと、を有することを特徴とする。   A power feeding method according to a second aspect of the present invention includes a power feeding device having a plurality of power feeding devices that output a predetermined current, a plurality of load devices that are fed from the power feeding device and process an operating load, and the plurality of power feeding devices. A control unit that controls at least a plurality of air conditioners that cool the load device, and an acquisition step of acquiring a parameter related to an operating load amount in the plurality of load devices; Based on the parameter, the operating load processed in a part of load devices (hereinafter referred to as “migration source load device”) is converted into at least a part of the remaining load devices (hereinafter referred to as “migration destination load”). (Hereinafter referred to as “reduction by load device”), and the cooling capacity of the air conditioner is controlled. Reduction in power consumption by Rukoto and having a priority processing step of determining whether priority (hereinafter, referred to as "reduced by the air conditioning system".) To give priority to any of the.

本発明の第3の態様に係るサーバは、所定電流を出力する複数の給電機器を有する給電装置から給電されて作動負荷の処理を行う複数の負荷装置、および、前記複数の負荷装置を冷却する複数の空調装置を少なくとも制御する制御部を備えたサーバであって、前記制御部には、前記複数の負荷装置における作動負荷量に関するパラメータを取得する取得部と、前記取得部により取得した前記パラメータに基づいて、一部の負荷装置(以下、「移行元の負荷装置」と表記する。)において処理される前記作動負荷を残りの負荷装置の少なくとも一部(以下、「移行先の負荷装置」と表記する。)で処理することによる消費電力の削減(以下、「負荷装置による削減」と表記する。)、および、前記空調装置の冷房能力を制御することによる消費電力の削減(以下、「空調装置による削減」と表記する。)のいずれを優先するか優先順位を求める処理部と、が設けられていることを特徴とする。   A server according to a third aspect of the present invention cools a plurality of load devices that are supplied with power from a power supply device that has a plurality of power supply devices that output a predetermined current and process an operating load, and the plurality of load devices. A server including a control unit that controls at least a plurality of air conditioners, wherein the control unit includes an acquisition unit that acquires a parameter relating to an operating load amount in the plurality of load devices, and the parameter acquired by the acquisition unit. Based on the above, the operating load processed in some load devices (hereinafter referred to as “migration source load device”) is treated as at least a part of the remaining load devices (hereinafter referred to as “migration destination load device”). (Referred to as “reduction by load device”), and consumption by controlling the cooling capacity of the air conditioner. Reduction of the force, characterized in that a processing unit for determining whether priority to prioritize either (hereinafter referred to as "reduced by the air conditioner."), Is provided.

本発明の第1の態様に係る給電システム、第2の態様に係る給電方法、および、第3の態様に係るサーバによれば、取得したパラメータに基づいて負荷装置における作動負荷量を推定し、推定した作動負荷量に応じて負荷装置による電力消費量の削減、および、空調装置による電力消費量の削減の優先順位を定めて全体の消費電力の削減を図ることができる。そのため、例えば、負荷装置による削減と、空調装置による削減の優先順位を定めず、それぞれが連係を取らずに消費電力の削減を図る場合と比較して消費電力の削減量を確保しやすくなる。または、負荷装置における作動負荷の処理に与える影響を抑制しつつ、消費電力の削減を図りやすくなる。   According to the power supply system according to the first aspect of the present invention, the power supply method according to the second aspect, and the server according to the third aspect, the operating load amount in the load device is estimated based on the acquired parameter, According to the estimated operating load amount, it is possible to reduce power consumption by the load device and prioritize reduction of power consumption by the air conditioner to reduce the overall power consumption. Therefore, for example, it becomes easier to secure a reduction amount of power consumption compared to a case in which priority is not given to reduction by the load device and reduction by the air conditioner, and the power consumption is reduced without cooperation. Or it becomes easy to aim at reduction of power consumption, suppressing the influence which it has on the process of the working load in a load apparatus.

上記発明の第1の態様において前記処理部は、前記パラメータに基づいて前記複数の負荷装置における前記作動負荷量が少なく、所定の下限値よりも小さな空調能力で運転している前記空調装置が存在すると判定される場合には、前記空調装置による削減を優先し、前記所定の下限値よりも値の大きな所定の適正範囲内の前記空調能力で運転している前記空調装置が存在すると判定されている場合には、前記負荷装置による削減を優先する処理を行うことが好ましい。   In the first aspect of the present invention, the processing unit includes the air conditioner that is operating with an air conditioning capacity that is less than a predetermined lower limit value, with the operating load amount in the plurality of load devices being small based on the parameter. If it is determined, it is determined that there is an air conditioner that operates with the air conditioning capability within a predetermined appropriate range having a value larger than the predetermined lower limit, giving priority to reduction by the air conditioner. If there is, it is preferable to perform processing giving priority to reduction by the load device.

上記発明の第2の態様において前記優先処理ステップでは、前記パラメータに基づいて前記複数の負荷装置における前記作動負荷量が少なく、所定の下限値よりも小さな空調能力で運転している前記空調装置が存在すると判定される場合には、前記空調装置による削減を優先し、前記所定の下限値よりも値の大きな所定の適正範囲内の前記空調能力で運転している前記空調装置が存在すると判定されている場合には、前記負荷装置による削減を優先する処理を行うことが好ましい。   In the second aspect of the present invention, in the priority processing step, the air conditioner that is operating with an air conditioning capacity that is less than a predetermined lower limit value and that has a small operating load amount in the plurality of load devices based on the parameter. If it is determined that there is an air conditioner, it is determined that there is an air conditioner that is operating with the air conditioning capability within a predetermined appropriate range having a value larger than the predetermined lower limit value, giving priority to reduction by the air conditioner. In such a case, it is preferable to perform processing that prioritizes reduction by the load device.

上記発明の第3の態様において前記処理部は、前記パラメータに基づいて前記複数の負荷装置における前記作動負荷量が少なく、所定の下限値よりも小さな空調能力で運転している前記空調装置が存在すると判定される場合には、前記空調装置による削減を優先し、前記所定の下限値よりも値の大きな所定の適正範囲内の前記空調能力で運転している前記空調装置が存在すると判定されている場合には、前記負荷装置による削減を優先する処理を行うことが好ましい。   In the third aspect of the present invention, the processing unit includes the air conditioner that is operated with an air conditioning capability that is less than a predetermined lower limit value, with the operating load amount in the plurality of load devices being small based on the parameter. If it is determined, it is determined that there is an air conditioner that operates with the air conditioning capability within a predetermined appropriate range having a value larger than the predetermined lower limit, giving priority to reduction by the air conditioner. If there is, it is preferable to perform processing giving priority to reduction by the load device.

上記発明の第1の態様、第2の態様および第3の態様によれば、空調装置による削減の優先順位を負荷装置による削減よりも上位とすることにより、消費電力の削減量を確保しやすくなる。つまり、情報通信設備の中でICT装置に次いで消費電力が多い空調装置に注目し、より効率的な運転による削減判断処理を負荷装置による削減判断より優先することにより、消費電力の削減量を確保しやすくなる。   According to the first aspect, the second aspect, and the third aspect of the invention, it is easy to secure a reduction in power consumption by placing the priority of reduction by the air conditioner higher than the reduction by the load device. Become. In other words, focusing on air conditioners with the highest power consumption after ICT equipment in information and communication facilities, priority is given to reduction judgment processing by more efficient operation than reduction judgment by load equipment, ensuring a reduction in power consumption. It becomes easy to do.

なお、所定の下限値としては、次のものを挙げることができる。1つ目は、作動負荷量が少なくて空調装置(特に、空調装置の圧縮機)がサーマルオン・オフを繰り返すか否かの閾値が挙げられる。言い換えると、過冷却状態と温度上昇を繰り返すか否かの閾値が挙げられる。2つ目は、空調装置の効率(COP)が定格値の3割となる閾値が挙げられる。言い換えると、定格値のCOPの値が5〜6である場合、定格値の3割は2以下(COP≦2)となることから、発熱量となる電力の半分を空調装置が消費することになる閾値が挙げられる。   In addition, as a predetermined | prescribed lower limit, the following can be mentioned. The first is a threshold value indicating whether or not the operating load is small and the air conditioner (particularly the compressor of the air conditioner) repeats thermal on / off. In other words, there is a threshold value as to whether or not the supercooling state and the temperature increase are repeated. The second is a threshold at which the efficiency (COP) of the air conditioner is 30% of the rated value. In other words, when the COP value of the rated value is 5 to 6, 30% of the rated value is 2 or less (COP ≦ 2), so that the air conditioner consumes half of the electric power that is the amount of heat generation. The threshold which becomes is mentioned.

上記発明の第1の態様において前記制御部は、さらに、前記複数の給電機器の稼働数を制御することにより前記給電装置における消費電力を制御するものであり、前記処理部は、前記給電装置における消費電力の削減よりも、前記空調装置による削減および前記負荷装置による削減を優先する処理を行うことが好ましい。   In the first aspect of the present invention, the control unit further controls power consumption in the power feeding device by controlling the number of operating the plurality of power feeding devices, and the processing unit is in the power feeding device. It is preferable to perform processing that prioritizes reduction by the air conditioner and reduction by the load device over reduction of power consumption.

上記発明の第2の態様において前記優先処理ステップでは、前記複数の給電機器の稼働数を制御することによる前記給電装置における消費電力の削減よりも、前記空調装置による削減および前記負荷装置による削減を優先する処理を行うことが好ましい。   In the second aspect of the present invention, in the priority processing step, the reduction by the air conditioner and the reduction by the load device are less than the reduction of power consumption in the power supply device by controlling the number of operations of the plurality of power supply devices. It is preferable to perform priority processing.

上記発明の第3の態様において前記制御部は、さらに、前記複数の給電機器の稼働数を制御することにより前記給電装置における消費電力を制御するものであり、前記処理部は、前記給電装置における消費電力の削減よりも、前記空調装置による削減および前記負荷装置による削減を優先する処理を行うことが好ましい。   In the third aspect of the present invention, the control unit further controls power consumption in the power feeding device by controlling the number of operating the plurality of power feeding devices, and the processing unit is in the power feeding device. It is preferable to perform processing that prioritizes reduction by the air conditioner and reduction by the load device over reduction of power consumption.

上記発明の第1の態様、第2の態様および第3の態様によれば、給電装置における消費電力の削減を更に行うことにより、負荷装置による削減、および、空調装置による削減のみを行う場合と比較して、消費電力の削減量を増やしやすくなる。   According to the first aspect, the second aspect, and the third aspect of the invention, by further reducing the power consumption in the power feeding device, the reduction by the load device and the reduction by the air conditioner only are performed. In comparison, it becomes easier to increase the amount of power consumption reduction.

さらに、空調装置による削減および負荷装置による削減の優先順位を、給電装置における削減よりも上位とすることにより、消費電力の削減量を確保しやすくなる。つまり、空調装置における消費電力量および負荷装置における消費電力量と、給電装置における消費電力量とを比較すると、一般的に、空調装置における消費電力量および負荷装置における消費電力量の方が大きくなる傾向にある。そこで、空調装置による削減および負荷装置による削減を優先することにより、消費電力の削減量を確保しやすくなる。   Furthermore, it is easy to ensure a reduction in power consumption by placing the priority of reduction by the air conditioner and reduction by the load device higher than the reduction by the power supply device. That is, when the power consumption in the air conditioner and the power consumption in the load device are compared with the power consumption in the power supply device, the power consumption in the air conditioner and the power consumption in the load device are generally larger. There is a tendency. Therefore, priority is given to the reduction by the air conditioner and the reduction by the load device, thereby making it easy to secure a reduction in power consumption.

上記発明の第1の態様、第2の態様および第3の態様において前記パラメータは、前記負荷装置の利用者に関するスケジュール情報、および、カレンダ情報の少なくとも一方であることが好ましい。   In the first aspect, the second aspect, and the third aspect of the invention, it is preferable that the parameter is at least one of schedule information and calendar information related to a user of the load device.

上記発明によれば、パラメータをスケジュール情報やカレンダ情報とすることにより、負荷装置における作業負荷量を推定しやすくなる。例えば、負荷装置の利用者は、平日に負荷装置を利用し、休日や祭日には負荷装置を利用しない傾向にある場合があり、さらに、利用者が所属する組織のスケジュールに応じて負荷装置の利用頻度が変動する場合がある。このような事情に基づくことにより、負荷装置における作業負荷量を推定しやすくなる。   According to the said invention, it becomes easy to estimate the workload amount in a load apparatus by using a parameter as schedule information or calendar information. For example, a user of a load device may tend to use the load device on weekdays and not to use the load device on holidays or holidays, and in addition, according to the schedule of the organization to which the user belongs, Usage frequency may vary. Based on such circumstances, it becomes easy to estimate the work load amount in the load device.

上記発明の第1の態様、第2の態様および第3の態様において前記パラメータは、気象情報、および、交通情報の少なくとも一方であることが好ましい。
上記発明によれば、パラメータを気象情報や交通情報とすることにより、負荷装置における作業負荷量を推定しやすくなる。例えば、特別警報が発表されるような悪天候の場合や、鉄道が運休している場合などには、負荷装置の利用者の出勤が困難であることが予想され、負荷装置における作業負荷量が減少することが推定される。
In the first aspect, the second aspect, and the third aspect of the present invention, the parameter is preferably at least one of weather information and traffic information.
According to the said invention, it becomes easy to estimate the workload amount in a load apparatus by making a parameter into weather information or traffic information. For example, it is expected that it will be difficult for users of the load device to go to work in the case of bad weather, such as when a special warning is announced, or when the railway is closed, reducing the workload on the load device. It is estimated that

上記発明の第1の態様、第2の態様および第3の態様において前記パラメータは、前記負荷装置の利用者の位置情報、および、前記利用者の座席位置情報であることが好ましい。   In the first aspect, the second aspect, and the third aspect of the invention, the parameters are preferably position information of a user of the load device and seat position information of the user.

上記発明によれば、パラメータを利用者の位置情報および座席位置情報とすることにより、負荷装置における作業負荷量を推定しやすくなる。例えば、利用者の位置が、負荷装置の利用端末が配置された座席位置の近傍である場合には、当該利用者が負荷装置を利用する可能性が高いと考えられる。そのため、これら情報に基づくことにより、負荷装置における作業負荷量を推定しやすくなる。   According to the said invention, it becomes easy to estimate the workload amount in a load apparatus by setting a parameter as a user's positional information and seat positional information. For example, when the position of the user is in the vicinity of the seat position where the use terminal of the load device is arranged, it is considered that the user is highly likely to use the load device. Therefore, based on these information, it becomes easy to estimate the work load amount in the load device.

上記発明の第1の態様、第2の態様、および、第3の態様において前記パラメータは、前記負荷装置の利用者の入退情報、および、前記利用者が利用する前記負荷装置の情報の少なくとも一方であることが好ましい。   In the first aspect, the second aspect, and the third aspect of the invention described above, the parameter is at least one of user load / unload information of the load device and information of the load device used by the user. On the other hand, it is preferable.

上記発明によれば、パラメータを利用者の入退情報や負荷装置の情報とすることにより、負荷装置における作業負荷量を推定しやすくなる。例えば、利用者が負荷装置の利用端末が配置された建物に入館している場合には、当該利用者が負荷装置を利用する可能性が高いと考えられる。そのため、これら情報に基づくことにより、負荷装置における作業負荷量を推定しやすくなる。また、利用者による負荷装置の利用状況が同じであっても、負荷装置の種類や他の作業負荷量の状況に応じて、負荷装置における作業負荷量が異なると考えられる。そのため、これら情報に基づくことにより、負荷装置における作業負荷量を推定しやすくなる。   According to the said invention, it becomes easy to estimate the workload amount in a load apparatus by making a parameter into a user's entrance / exit information and information of a load apparatus. For example, when a user enters a building where a load device use terminal is arranged, it is considered that the user is likely to use the load device. Therefore, based on these information, it becomes easy to estimate the work load amount in the load device. Further, even if the usage status of the load device by the user is the same, it is considered that the work load amount in the load device varies depending on the type of the load device and other work load status. Therefore, based on these information, it becomes easy to estimate the work load amount in the load device.

本発明の給電システム、給電方法およびサーバによれば、取得したパラメータに基づいて負荷装置における作動負荷量を推定し、推定した作動負荷量に応じて負荷装置による削減、および、空調装置による削減の優先順位を定めるため、電力損失の低減を図ることができるという効果を奏する。   According to the power supply system, the power supply method, and the server of the present invention, the operating load amount in the load device is estimated based on the acquired parameters, the reduction by the load device according to the estimated operating load amount, and the reduction by the air conditioner Since the priority order is determined, the power loss can be reduced.

本発明の第1の実施形態に係る給電システムの概略構成を説明する図である。It is a figure explaining the schematic structure of the electric power feeding system which concerns on the 1st Embodiment of this invention. 図1の給電システムにおいて分散運転されている状態を説明する模式図である。FIG. 2 is a schematic diagram illustrating a state in which distributed operation is performed in the power supply system of FIG. 1. 縮退運転を実行する際の制御を説明するフローチャートである。It is a flowchart explaining the control at the time of performing degenerate operation. 縮退運転を実行する際の制御を説明するフローチャートである。It is a flowchart explaining the control at the time of performing degenerate operation. 図1の給電システムにおいて縮退運転されている状態を説明する模式図である。FIG. 2 is a schematic diagram illustrating a state in which a degenerate operation is performed in the power supply system of FIG. 1. 縮退運転から分散運転へ移行する際の制御を説明するフローチャートである。It is a flowchart explaining the control at the time of transfer from degenerate operation to distributed operation. 本発明の第2の実施形態に係る給電システムにおける縮退運転を実行する際の制御処理を説明するフローチャートである。It is a flowchart explaining the control processing at the time of performing the degeneration operation in the electric power feeding system which concerns on the 2nd Embodiment of this invention. 本発明の第3の実施形態に係る給電システムにおける縮退運転を実行する際の制御処理を説明するフローチャートである。It is a flowchart explaining the control processing at the time of performing the degeneration operation in the electric power feeding system which concerns on the 3rd Embodiment of this invention. 本発明の第4の実施形態に係る給電システムにおける分散運転を継続するか否かの判断を行う際の制御処理を説明するフローチャートである。It is a flowchart explaining the control processing at the time of determining whether to continue the distributed operation in the electric power feeding system which concerns on the 4th Embodiment of this invention. 本発明の第5の実施形態に係る給電システムにおける分散運転を継続するか否かの判断を行う際の制御処理を説明するフローチャートである。It is a flowchart explaining the control processing at the time of determining whether to continue the distributed operation in the electric power feeding system which concerns on the 5th Embodiment of this invention. 本発明の第6の実施形態に係る給電システムにおける縮退運転を継続するか否かの判断を行う際の制御処理を説明するフローチャートである。It is a flowchart explaining the control processing at the time of determining whether to continue the degeneration operation in the electric power feeding system which concerns on the 6th Embodiment of this invention. 本発明の第7の実施形態に係る給電システムにおけるICT装置優先モードおよび空調優先モードのいずれを優先するか優先順位を判定する処理を説明するフローチャートである。It is a flowchart explaining the process which determines a priority which prioritizes which of the ICT apparatus priority mode and air-conditioning priority mode in the electric power feeding system which concerns on the 7th Embodiment of this invention. 制御優先順位を判定するサブルーチンの処理の詳細を説明するフローチャートである。It is a flowchart explaining the detail of the process of the subroutine which determines a control priority. 本発明の第7の実施形態に係る給電システムにおける他の優先順位判定処理を説明するフローチャートである。It is a flowchart explaining the other priority determination processing in the electric power feeding system which concerns on the 7th Embodiment of this invention.

〔第1の実施形態〕
以下、本発明の第1の実施形態に係る給電システムについて、図1から図6を参照しながら説明する。本実施形態では、本発明の給電システム1を、情報処理や情報通信などの処理を行うICT装置(負荷装置)25、および、空調装置35や照明機器45などのICT装置25に付随する周辺機器へ電力を供給するシステムである例に適用して説明する。
[First Embodiment]
Hereinafter, a power supply system according to a first embodiment of the present invention will be described with reference to FIGS. 1 to 6. In the present embodiment, the power supply system 1 of the present invention is a peripheral device associated with an ICT device (load device) 25 that performs processing such as information processing and information communication, and an ICT device 25 such as an air conditioner 35 and a lighting device 45. This will be described by applying to an example of a system for supplying power.

給電システム1は、図1に示すように、給電装置10と、電流分配装置15と、給電制御装置(サーバ)20と、ICT装置25と、ICT制御装置(サーバ)30と、空調装置35と、空調制御装置(サーバ)40と、照明機器45と、照明制御装置50と、統合制御装置(サーバ)60と、監視制御装置70と、から主に構成されている。   As shown in FIG. 1, the power supply system 1 includes a power supply device 10, a current distribution device 15, a power supply control device (server) 20, an ICT device 25, an ICT control device (server) 30, and an air conditioner 35. The air conditioning control device (server) 40, the lighting device 45, the lighting control device 50, the integrated control device (server) 60, and the monitoring control device 70 are mainly configured.

給電装置10は、ICT装置25に電力を供給するものであり、商用電力の供給を受けて直流電流(所定電流)を出力する複数の電源ユニット(給電機器)11が設けられたものである。電源ユニット11は、給電制御装置20から入力される指令(出力信号)に基づき、直流電流の出力/停止が制御されるように構成されている。また、給電装置10は、複数の電源ユニット11の運転情報を取得し、後述する給電制御装置20へ取得した情報を出力する機能を有している。   The power supply device 10 supplies power to the ICT device 25, and is provided with a plurality of power supply units (power supply devices) 11 that receive a supply of commercial power and output a direct current (predetermined current). The power supply unit 11 is configured to control output / stop of direct current based on a command (output signal) input from the power supply control device 20. The power supply apparatus 10 has a function of acquiring operation information of the plurality of power supply units 11 and outputting the acquired information to the power supply control apparatus 20 described later.

なお、電源ユニット11における商用電力を直流電流に変換する方式や、電源ユニット11における直流電流の出力/停止の具体的な制御方法や、給電装置10における複数の電源ユニット11の接続方法などについては、公知の方法を用いることができ特に限定するものではない。また、本実施形態では、電源ユニット11が交流電流である商用電力から、ICT装置25の動作に用いられる所望電圧の直流電流に変換する例に適用して説明するが、電力の供給先である負荷装置の特性に応じて直流電流の代わりに所望電圧の交流電流を供給してもよく、特に電流の態様を限定するものではない。   Note that a method for converting commercial power in the power supply unit 11 into direct current, a specific control method for outputting / stopping direct current in the power supply unit 11, a method for connecting a plurality of power supply units 11 in the power supply apparatus 10, and the like. A known method can be used and is not particularly limited. In the present embodiment, the power supply unit 11 is described as applied to an example in which commercial power, which is alternating current, is converted into direct current of a desired voltage used for the operation of the ICT device 25, but is a power supply destination. Depending on the characteristics of the load device, an alternating current of a desired voltage may be supplied instead of the direct current, and the mode of the current is not particularly limited.

電流分配装置15は、給電装置10から供給された直流電流を、ICT装置25が格納される複数のICTラック26へ分配するものである。電流分配装置15には、給電制御装置20からの指令(切替え信号)に従い、ポスト毎に直流電流の供給/非供給制御(以下、「ON/OFF制御」とも表記する。)を行うスイッチ16が搭載されている。スイッチ16は、それぞれのポストに接続されたICTラック26に格納されたICT装置25における消費電力を測定する機能も設けられている。スイッチ16で測定された消費電力は、給電制御装置20に出力される。なお、スイッチ16の形式としては、公知の形式のものを用いることができ、特に限定するものではない。   The current distribution device 15 distributes the direct current supplied from the power supply device 10 to a plurality of ICT racks 26 in which the ICT device 25 is stored. The current distribution device 15 includes a switch 16 that performs DC current supply / non-supply control (hereinafter also referred to as “ON / OFF control”) for each post in accordance with a command (switching signal) from the power supply control device 20. It is installed. The switch 16 is also provided with a function of measuring power consumption in the ICT device 25 stored in the ICT rack 26 connected to each post. The power consumption measured by the switch 16 is output to the power supply control device 20. In addition, as a form of the switch 16, a well-known thing can be used and it does not specifically limit.

さらに、電流分配装置15には、短絡事故などによる過電流を防止するためにポスト毎にヒューズやブレーカなどの保護素子(図示せず。)が搭載されている。この保護素子を搭載することにより、短絡事故が発生したICT装置25を含む系統(以下、「事故系」とも表記する。)の影響が、それ以外の通常の運転を継続するICT装置25を含む系統(以下、「健全系」とも表記する。)へ波及することを防止できる。   Further, the current distribution device 15 is provided with a protection element (not shown) such as a fuse or a breaker for each post in order to prevent an overcurrent due to a short circuit accident or the like. By mounting this protective element, the influence of the system including the ICT device 25 in which a short circuit accident has occurred (hereinafter also referred to as “accident system”) includes the ICT device 25 that continues normal operation other than that. Ripple to the system (hereinafter also referred to as “healthy system”) can be prevented.

給電制御装置20は、統合制御装置60からの指令に基づき、電流分配装置15の1ポスト毎の給電ON/OFFを制御する指令、コンセントバー27のコンセント口毎の給電ON/OFFを制御する指令、給電装置10の電源ユニット11の運転/停止を制御する指令、給電装置10の運転/停止を制御する指令を出力するものである。   The power supply control device 20 is based on a command from the integrated control device 60, a command for controlling power supply ON / OFF for each post of the current distribution device 15, and a command for controlling power supply ON / OFF for each outlet port of the outlet bar 27. A command for controlling the operation / stop of the power supply unit 11 of the power supply apparatus 10 and a command for controlling the operation / stop of the power supply apparatus 10 are output.

給電制御装置20は、CPU(中央演算処理ユニット)、ROM、RAM、ハードディスク、入出力インタフェース等を有するコンピュータシステムである。ROM等に記憶されている制御プログラムは、CPUを少なくとも演算処理部(制御部)21として機能させるものであり、入出力インタフェース等を少なくとも取得部22として機能させるものである。   The power supply control device 20 is a computer system having a CPU (Central Processing Unit), ROM, RAM, hard disk, input / output interface, and the like. The control program stored in the ROM or the like causes the CPU to function as at least the arithmetic processing unit (control unit) 21 and causes the input / output interface or the like to function as at least the acquisition unit 22.

演算処理部21は、給電装置10、並びに、電流分配装置15のスイッチ16およびコンセントバー27内部に設けられたスイッチ27Aの動作を制御する演算処理を行うと共に、当該動作を制御する指令を生成するものでもある。演算処理部21における演算処理等の詳細については後述する。   The arithmetic processing unit 21 performs arithmetic processing for controlling operations of the power supply device 10 and the switch 16A of the current distribution device 15 and the switch 27A provided in the outlet bar 27, and generates a command for controlling the operation. It is also a thing. Details of the arithmetic processing in the arithmetic processing unit 21 will be described later.

取得部22は、給電装置10から出力される複数の電源ユニット11の運転情報、および、電流分配装置15から出力される1ポスト毎の消費電力情報、および、コンセントバー27の1口毎の消費電力情報が入力されるインタフェースである。また、取得部22は、演算処理部21において生成された各種の指令を出力するインタフェースでもある。   The acquisition unit 22 includes operation information of the plurality of power supply units 11 output from the power supply device 10, power consumption information for each post output from the current distribution device 15, and consumption for each outlet of the outlet bar 27. An interface to which power information is input. The acquisition unit 22 is also an interface that outputs various commands generated by the arithmetic processing unit 21.

ICT装置25は、演算等の情報処理や、情報の受信/送信などの通信処理等を行うものである。ICT装置25における処理などの動作は、ICT制御装置30から入力される指令に基づいて制御される。ICT装置25は、ICTラック26に1台以上が搭載され、ICTラック26に設けられたコンセントバー27から直流電流が給電されている。なお、上述の情報処理や通信処理などが特許請求の範囲における作業負荷に相当するものである。   The ICT device 25 performs information processing such as calculation and communication processing such as information reception / transmission. Operations such as processing in the ICT device 25 are controlled based on a command input from the ICT control device 30. One or more ICT devices 25 are mounted on the ICT rack 26, and a direct current is supplied from an outlet bar 27 provided on the ICT rack 26. The information processing and communication processing described above correspond to the workload in the claims.

コンセントバー27は、電流分配装置15にて分配された配線が接続されたものである。コンセントバー27内部のスイッチ27Aには、給電制御装置20から入力される指令に基づいて、コンセント口毎にICT装置25への給電のON/OFFを制御する機能が搭載されている。さらに、コンセント口毎に消費電流・電力を計測する機能が搭載され、計測された消費電流・電力の情報は、給電制御装置20へ出力されている。このように、コンセントバー27は、いわゆるインテリジェントコンセントとして機能するものを用いている。   The outlet bar 27 is connected to the wiring distributed by the current distribution device 15. The switch 27A in the outlet bar 27 is equipped with a function for controlling ON / OFF of power supply to the ICT device 25 for each outlet port based on a command input from the power supply control device 20. Further, a function for measuring current consumption / power is installed for each outlet, and information on the measured current consumption / power is output to the power supply control device 20. Thus, the outlet bar 27 uses what functions as a so-called intelligent outlet.

図2に示すように、複数のICTラック26は、一列に配置されることにより架列28A,28B,28C,28D,28E,28Fのそれぞれを構成する。さらに、これら架列28A,28B,28C,28D,28E,28Fは並列に並んで配置される。   As shown in FIG. 2, the plurality of ICT racks 26 are arranged in a line to constitute the racks 28A, 28B, 28C, 28D, 28E, and 28F. Further, these racks 28A, 28B, 28C, 28D, 28E, 28F are arranged in parallel.

ICT制御装置30は、統合制御装置60からの指令に基づき、ICT装置25へ集約運転を指示する縮退指令、分散運転を指示する復元指令、ICT装置25の停止を指示する停止指令、ICT装置25の起動を指示する起動指令を出力するものである。   The ICT control device 30 is based on a command from the integrated control device 60, a degeneration command for instructing the ICT device 25 to perform aggregate operation, a restoration command for instructing distributed operation, a stop command for instructing the ICT device 25 to stop, and an ICT device 25. A start command for instructing start-up is output.

ICT制御装置30は、図1に示すように、CPU(中央演算処理ユニット)、ROM、RAM、ハードディスク、入出力インタフェース等を有するコンピュータシステムである。ROM等に記憶されている制御プログラムは、CPUを少なくとも演算処理部(制御部)31として機能させるものであり、入出力インタフェース等を少なくとも取得部32として機能させるものである。   As shown in FIG. 1, the ICT control device 30 is a computer system having a CPU (Central Processing Unit), ROM, RAM, hard disk, input / output interface, and the like. The control program stored in the ROM or the like causes the CPU to function as at least the arithmetic processing unit (control unit) 31 and causes the input / output interface or the like to function as at least the acquisition unit 32.

演算処理部31は、ICT装置25の動作を制御する演算処理を行うと共に、当該動作を制御する指令を生成するものでもある。演算処理部31における演算処理等の詳細については後述する。   The arithmetic processing unit 31 performs arithmetic processing for controlling the operation of the ICT device 25 and also generates a command for controlling the operation. Details of the arithmetic processing in the arithmetic processing unit 31 will be described later.

取得部32は、コンセントバー27から出力されるコンセント口毎の消費電流・電力情報、ICT装置25から出力される業務処理量や、装置内部温度や、消費電力などの運転情報が入力されるインタフェースである。また、取得部32は、演算処理部31において生成された各種の指令を出力するインタフェースでもある。   The acquisition unit 32 is an interface through which operation information such as current consumption / power information for each outlet port output from the outlet bar 27, business processing amount output from the ICT device 25, device internal temperature, and power consumption is input. It is. The acquisition unit 32 is also an interface that outputs various commands generated by the arithmetic processing unit 31.

空調装置35は、図2に示すように、ICT装置25が配置されたサーバルームSRの室内空気を介してICT装置25を冷却するものである。つまり、ICT装置25において発生した熱は、ICT装置25の内部を通過するサーバルームSRの室内空気に放出され、サーバルームSRの室内空気の温度が上昇する。空調装置35は、この温度が上昇した室内空気を吸入して熱を奪い、所望の温度に冷却した後にサーバルームSR内に送り出すものである。室内空気から奪った熱は、サーバルームSRの外側に配置された室外機(図示せず。)において、外部へ放出される。この空調装置35における動作は、空調制御装置40から出力される指令(動作信号)に基づいて制御されている。   As shown in FIG. 2, the air conditioner 35 cools the ICT device 25 through the indoor air of the server room SR in which the ICT device 25 is arranged. That is, the heat generated in the ICT device 25 is released to the indoor air of the server room SR that passes through the inside of the ICT device 25, and the temperature of the indoor air of the server room SR rises. The air conditioner 35 takes in the indoor air whose temperature has increased, takes heat away, cools it to a desired temperature, and sends it out into the server room SR. The heat taken from the room air is released to the outside in an outdoor unit (not shown) arranged outside the server room SR. The operation of the air conditioner 35 is controlled based on a command (operation signal) output from the air conditioner control device 40.

本実施形態では、中央に架列28A,28B,28C,28D,28E,28Fが並列に並んで配置されているサーバルームSRにおいて、架列28A,28B,28C,28D,28E,28Fの端部近傍に、空調装置35が並んで配置されている例に適用して説明する。また、空調装置35における室内空気を冷却する形式や、冷却した空気をサーバルームSR内へ送り出す形式としては、公知の形式を用いることができ、特に限定するものではない。   In the present embodiment, in the server room SR in which the racks 28A, 28B, 28C, 28D, 28E, and 28F are arranged in parallel at the center, the ends of the racks 28A, 28B, 28C, 28D, 28E, and 28F This will be described by applying to an example in which the air conditioners 35 are arranged in the vicinity. Moreover, a well-known format can be used as a format which cools the indoor air in the air conditioner 35, and a format which sends out the cooled air in the server room SR, and it does not specifically limit it.

さらに、本実施形態では、サーバルームSR内に配置される複数の空調装置35に対して、屋外に配置され熱を外気に放出する手段である室外機等が一対一に対応して設けられる個別方式空調である例に適用して説明するが、複数の空調機35に対して、熱を外気に放出する手段である冷却塔等が一つ設けられた中央熱源方式空調であってもよく、特に限定するものではない。   Furthermore, in this embodiment, with respect to the several air conditioner 35 arrange | positioned in the server room SR, the outdoor unit etc. which are arrange | positioned outdoors and are a means to discharge | release heat to external air are provided corresponding to one to one. Although applied to an example of a system air conditioning, a central heat source system air conditioning in which one cooling tower or the like, which is a means for releasing heat to the outside air, is provided for the plurality of air conditioners 35, There is no particular limitation.

空調制御装置40は、統合制御装置60からの指令に基づき、空調装置35の起動を制御する指令、空調装置35の停止を制御する指令、空調装置35の運転条件を制御する指令を出力するものである。   The air conditioning control device 40 outputs a command for controlling the start of the air conditioning device 35, a command for controlling the stop of the air conditioning device 35, and a command for controlling the operating conditions of the air conditioning device 35 based on the commands from the integrated control device 60. It is.

空調制御装置40は、図1に示すように、CPU(中央演算処理ユニット)、ROM、RAM、ハードディスク、入出力インタフェース等を有するコンピュータシステムである。ROM等に記憶されている制御プログラムは、CPUを少なくとも演算処理部(制御部)41として機能させるものであり、入出力インタフェース等を少なくとも取得部42として機能させるものである。   As shown in FIG. 1, the air conditioning control device 40 is a computer system having a CPU (Central Processing Unit), ROM, RAM, hard disk, input / output interface, and the like. The control program stored in the ROM or the like causes the CPU to function as at least the arithmetic processing unit (control unit) 41, and causes the input / output interface or the like to function as at least the acquisition unit.

演算処理部41は、空調装置35の動作を制御する演算処理を行うと共に、当該動作を制御する指令を生成するものでもある。演算処理部41における演算処理等の詳細については後述する。取得部42は、空調装置35から出力される運転状況を示す運転情報が入力されるインタフェースである。   The arithmetic processing unit 41 performs arithmetic processing for controlling the operation of the air conditioner 35 and also generates a command for controlling the operation. Details of the arithmetic processing in the arithmetic processing unit 41 will be described later. The acquisition unit 42 is an interface through which operation information indicating the operation status output from the air conditioner 35 is input.

照明機器45は、ICT装置25などが配置されたサーバルームSR等における照明を行うものである。照明機器45には、人の存在を感知する人感センサ(図示せず。)が設けられている。サーバルームSRに人が立ち入った場合のように、人感センサが人を感知した際に照明機器45は照明を行う。また、空調装置35における照明/非照明の制御は、空調制御装置40から出力される指令(動作信号)に基づいても行われる。なお、照明機器45としては、公知の機器を用いることができ、特に限定するものではない。   The illumination device 45 performs illumination in the server room SR in which the ICT device 25 and the like are arranged. The lighting device 45 is provided with a human sensor (not shown) that senses the presence of a person. The illumination device 45 performs illumination when the human sensor detects a person, such as when a person enters the server room SR. The illumination / non-illumination control in the air conditioner 35 is also performed based on a command (operation signal) output from the air conditioner controller 40. Note that a known device can be used as the lighting device 45, and is not particularly limited.

照明制御装置50は、統合制御装置60からの指令に基づき、照明機器45における点灯・消灯を制御する指令、照明機器45の運転条件を制御する指令を出力するものである。   The lighting control device 50 outputs a command for controlling lighting / extinguishing in the lighting device 45 and a command for controlling the operating condition of the lighting device 45 based on a command from the integrated control device 60.

照明制御装置50は、CPU(中央演算処理ユニット)、ROM、RAM、ハードディスク、入出力インタフェース等を有するコンピュータシステムである。ROM等に記憶されている制御プログラムは、CPUを少なくとも演算処理部51として機能させるものであり、入出力インタフェース等を少なくとも取得部52として機能させるものである。   The illumination control device 50 is a computer system having a CPU (Central Processing Unit), ROM, RAM, hard disk, input / output interface, and the like. The control program stored in the ROM or the like causes the CPU to function as at least the arithmetic processing unit 51, and causes the input / output interface or the like to function as at least the acquisition unit 52.

演算処理部51は、照明機器45の動作を制御する演算処理を行うと共に、当該動作を制御する指令を生成するものでもある。演算処理部51における演算処理等の詳細については後述する。取得部52は、照明機器45から出力される動作状況を示す運転情報が入力されるインタフェースであり、さらに、照明機器45に付随する人感センサの測定情報などが入力されるインタフェースでもある。   The arithmetic processing unit 51 performs arithmetic processing for controlling the operation of the lighting device 45 and also generates a command for controlling the operation. Details of the arithmetic processing in the arithmetic processing unit 51 will be described later. The acquisition unit 52 is an interface to which driving information indicating the operation status output from the lighting device 45 is input, and is also an interface to which measurement information of a human sensor attached to the lighting device 45 is input.

上述の給電制御装置20、ICT制御装置30、空調制御装置40、および照明制御装置50は、統合制御装置60との間の通信が途絶えて指令が入力されない場合や、統合制御装置60から出力された指令が異常値である場合には、統合制御装置60が故障したと判断し、それぞれの制御装置が自立した運転状態に遷移する。   The power supply control device 20, the ICT control device 30, the air conditioning control device 40, and the lighting control device 50 described above are output from the integrated control device 60 when communication with the integrated control device 60 is interrupted and no command is input. If the command is an abnormal value, it is determined that the integrated control device 60 has failed, and each control device transitions to an independent operating state.

統合制御装置60は、監視制御装置70から入力される故障情報や運転異常情報、BEMSやBASなどの外部EMS(エネルギ・マネジメント・システム)、DCIM(データセンタ・インフラストラクチャ・マネジメント)などから入力される情報や指令に基づいて、給電制御装置20、ICT制御装置30、空調制御装置40、および照明制御装置50に対する制御内容を判断する処理や、出力する指令を生成する処理を行うものである。   The integrated control device 60 is input from failure information and operational abnormality information input from the monitoring control device 70, external EMS (energy management system) such as BEMS and BAS, DCIM (data center infrastructure management), and the like. Based on the information and command to be processed, processing for determining the control content for the power supply control device 20, the ICT control device 30, the air conditioning control device 40, and the lighting control device 50 and processing for generating a command to be output are performed.

統合制御装置60は、CPU(中央演算処理ユニット)、ROM、RAM、ハードディスク、入出力インタフェース等を有するコンピュータシステムである。ROM等に記憶されている制御プログラムは、CPUを少なくとも演算処理部(処理部)61、学習処理部(処理部)62、および、予測処理部(処理部)63として機能させるものであり、入出力インタフェース等を少なくとも取得部64として機能させるものである。   The integrated control device 60 is a computer system having a CPU (Central Processing Unit), ROM, RAM, hard disk, input / output interface, and the like. The control program stored in the ROM or the like causes the CPU to function as at least the arithmetic processing unit (processing unit) 61, the learning processing unit (processing unit) 62, and the prediction processing unit (processing unit) 63. An output interface or the like is caused to function as at least the acquisition unit 64.

取得部64は、入退管理装置65、社員位置情報が記憶された記憶部66、社員スケジュールが記憶された記憶部67、および、交通情報や気象情報などの市中情報が記憶された記憶部68からそれぞれの情報を取得するインタフェースである。   The acquisition unit 64 includes an entrance / exit management device 65, a storage unit 66 that stores employee location information, a storage unit 67 that stores employee schedules, and a storage unit that stores city information such as traffic information and weather information. 68 is an interface for acquiring each information from 68.

また取得部64は、給電制御装置20、ICT制御装置30、空調制御装置40、照明制御装置50、および、統合制御装置60から出力される情報、ICTラック26の配置位置およびICTラック26におけるICT装置の搭載位置の情報、並びに、外部から入力される指令情報を取得するインタフェースである。取得部64は、さらに、外部EMSシステム、DCIMなどへ情報や指令を出すことができる外部とのインタフェースでもある。   The acquisition unit 64 also includes information output from the power supply control device 20, the ICT control device 30, the air conditioning control device 40, the lighting control device 50, and the integrated control device 60, the arrangement position of the ICT rack 26, and the ICT in the ICT rack 26. It is an interface for acquiring information on the mounting position of the apparatus and command information input from the outside. The acquisition unit 64 is also an interface with the outside that can send information and commands to an external EMS system, DCIM, and the like.

入退管理装置65は、ICT装置25を利用する社員(利用者)の入退管理を行い、社員の入退情報を取得するものである。入退情報は、ICT装置25に接続される端末が設置された部屋に対する入室および退室を表す情報であってもよいし、上述の端末が設置された建物に対する入館および退館を表す情報であってもよい。   The entrance / exit management device 65 manages entrance / exit of employees (users) who use the ICT device 25 and acquires employee entrance / exit information. The entry / exit information may be information representing entry and exit from a room in which a terminal connected to the ICT device 25 is installed, or information representing entry into and exit from a building in which the terminal is installed. May be.

また、社員の入退情報を取得する方法としては、出入口に設置されたセンサにより上述の社員の入室および退室等を検出して取得してもよいし、社員が所持する携帯端末から取得した社員の位置情報に基づいて推定してもよく、入退情報を取得する方法を特に限定するものではない。   In addition, as a method of acquiring employee entry / exit information, the above-mentioned employee entry / exit may be detected by a sensor installed at the entrance / exit, or may be obtained from a portable terminal owned by the employee. The position information may be estimated based on the position information, and the method for acquiring the entry / exit information is not particularly limited.

記憶部66は、取得された社員の位置情報を記憶するものであり、統合制御装置60から入力される制御信号に基づいて、記憶している位置情報を統合制御装置60へ出力するものである。社員の位置情報は、位置情報取得部(図示せず。)により繰り返し取得されたものである。位置情報取得部としては、建物の中の各部屋に設置されたビーコンおよび社員が所持する携帯端末を利用したものや、携帯端末の位置検出機能を利用したものなど、公知の方法を用いることができる。なお、記憶部66には、社員の位置情報の他に、社員の座席位置情報が記憶されていてもよい。   The storage unit 66 stores the acquired employee position information, and outputs the stored position information to the integrated control apparatus 60 based on a control signal input from the integrated control apparatus 60. . The employee position information is repeatedly acquired by a position information acquisition unit (not shown). As the position information acquisition unit, a known method such as a beacon installed in each room in the building and a portable terminal owned by an employee or a position detecting function of the portable terminal may be used. it can. The storage unit 66 may store employee seat position information in addition to the employee position information.

記憶部67は、社員のスケジュール情報を記憶するものであり、統合制御装置60から入力される制御信号に基づいて、記憶しているスケジュール情報を統合制御装置60へ出力するものである。なお、記憶部67にはスケジュール情報の他に、平日、休日、祝祭日などの情報を含むカレンダ情報が記憶されていてもよい。   The storage unit 67 stores employee schedule information, and outputs the stored schedule information to the integrated control device 60 based on a control signal input from the integrated control device 60. In addition to the schedule information, the storage unit 67 may store calendar information including information such as weekdays, holidays, and holidays.

記憶部68は、市中情報を記憶するものであり、統合制御装置60から入力される制御信号に基づいて、記憶している市中情報を統合制御装置60へ出力するものである。市中情報は交通情報および気象情報を含むものであり、例えば、鉄道などの公共交通機関の運行情報や、気象庁から発表される特別警報を含む各種の警報を例示することができる。市中情報を収集する方法としては、公知の方法を用いることができ、特に限定するものではない。   The storage unit 68 stores city information, and outputs the stored city information to the integrated control device 60 based on a control signal input from the integrated control device 60. The city information includes traffic information and weather information, and examples thereof include various types of alarms including operation information of public transportation such as railways and special alarms announced by the Japan Meteorological Agency. A publicly known method can be used as a method for collecting the city information, and is not particularly limited.

ここで、入退管理装置65から取得される社員の入退情報、記憶部66に記憶されている社員の位置情報、記憶部67に記憶されている社員のスケジュール情報、並びに、記憶部68に記憶されている交通情報および気象情報は、特許請求の範囲におけるパラメータに相当する。   Here, the employee entry / exit information acquired from the entry / exit management device 65, the employee location information stored in the storage unit 66, the employee schedule information stored in the storage unit 67, and the storage unit 68 The stored traffic information and weather information correspond to parameters in the claims.

演算処理部61は、取得部64で取得した情報をROM等に蓄積する処理、蓄積した情報等の集計処理、および、集計処理した情報等の分析処理を行うものである。さらに演算処理部61は、分析処理の結果に基づき、外部へ出力する情報や指令を生成するものである。   The arithmetic processing unit 61 performs processing for accumulating information acquired by the acquisition unit 64 in a ROM, tabulation processing for the stored information, and analysis processing for the tabulated information. Further, the arithmetic processing unit 61 generates information and instructions to be output to the outside based on the result of the analysis processing.

予測処理部63は、ROM等に蓄積した情報等に基づいて、ICT装置25における演算等の情報処理量を予測するものである。予測処理部63における予測方法の詳細については後述する。   The prediction processing unit 63 predicts an information processing amount such as calculation in the ICT device 25 based on information stored in a ROM or the like. Details of the prediction method in the prediction processing unit 63 will be described later.

学習処理部62は、学習により予測処理部63により予測された演算等の情報処理量と、実際の演算等の情報処理量と差を縮小させる処理を行うものである。差を縮小させる処理としては、公知の処理を用いることができ、特に限定するものではない。   The learning processing unit 62 performs processing to reduce the difference between the information processing amount such as the calculation predicted by the prediction processing unit 63 by learning and the information processing amount such as the actual calculation. A known process can be used as the process for reducing the difference, and is not particularly limited.

監視制御装置70は、CPU(中央演算処理ユニット)、ROM、RAM、ハードディスク、入出力インタフェース等を有するコンピュータシステムである。ROM等に記憶されている制御プログラムは、CPUを少なくとも演算処理部71として機能させるものであり、入出力インタフェース等を少なくとも取得部72として機能させるものである。   The monitoring control device 70 is a computer system having a CPU (Central Processing Unit), ROM, RAM, hard disk, input / output interface, and the like. The control program stored in the ROM or the like causes the CPU to function as at least the arithmetic processing unit 71, and causes the input / output interface or the like to function as at least the acquisition unit 72.

取得部72は、給電装置10、電流分配装置15、ICT装置25、および、空調制御装置40などの給電システム1を構成する機器から出力される故障状態や、運転異常に関する情報を取得するインタフェースである。演算処理部71は、取得部72により取得された故障状態や運転異常に関する情報に基づいて、給電システム1を構成する装置の故障状態・運転異常を監視するものである。   The acquisition unit 72 is an interface that acquires information on failure states and operational abnormalities output from devices constituting the power supply system 1 such as the power supply device 10, the current distribution device 15, the ICT device 25, and the air conditioning control device 40. is there. The arithmetic processing unit 71 monitors the failure state / operation abnormality of the devices constituting the power supply system 1 based on the information regarding the failure state and the operation abnormality acquired by the acquisition unit 72.

次に、上記の構成からなる給電システム1における制御について説明する。まず、社員の入退情報や、ICT装置25等の情報に基づく給電システム1の運用について説明する。   Next, control in the power feeding system 1 having the above configuration will be described. First, the operation of the power supply system 1 based on employee entry / exit information and information on the ICT device 25 and the like will be described.

最初に、ICT装置25が分散運転されている通常の運用状態について、図2を参照しながら説明する。分散運転とは、給電システム1における全てのICT装置25、または、大半のICT装置25において情報処理などの演算処理が行われる状態のことである。   First, a normal operation state in which the ICT device 25 is in a distributed operation will be described with reference to FIG. The distributed operation is a state in which arithmetic processing such as information processing is performed in all ICT devices 25 or most ICT devices 25 in the power feeding system 1.

図2においてICT装置25(ICTラック26)に記載されたパーセントは、該当するICT装置の負荷率を示している。また、サーバルームSRにおけるハッチングは、サーバルームSRの室内空気の温度を示すものであり、ハッチングが濃くなるに伴い温度が高くなっていることを示している。   In FIG. 2, the percentage described in the ICT device 25 (ICT rack 26) indicates the load factor of the corresponding ICT device. The hatching in the server room SR indicates the temperature of the indoor air in the server room SR, and indicates that the temperature increases as the hatching becomes darker.

サーバルームSR内には、給電装置10、空調装置35およびICT装置25が配置されている。また、消費電力ベースに基づくICT装置25における構成の内訳は、サーバ系の機器が8割、スイッチ、ルータなどのネットワーク系機器が2割となる。本実施形態では、ICT装置25の最大消費電力の合計が300kWである例に適用して説明する。   In the server room SR, a power feeding device 10, an air conditioner 35, and an ICT device 25 are arranged. The breakdown of the configuration of the ICT device 25 based on the power consumption base is 80% for server equipment and 20% for network equipment such as switches and routers. In the present embodiment, description will be made by applying to an example in which the total maximum power consumption of the ICT device 25 is 300 kW.

次に、上記の構成からなる給電システム1に対して本発明に関する統合連係制御を実施した場合の説明を行う。本説明において統合制御装置60は、ICT装置25の端末が設置された建物に在館する社員数が所定の一定数よりも少ない場合に、ICT装置25における負荷を集約する縮退運転を行う指令を出力する。縮退運転を行っている最中にICT装置25の負荷が増加すると、統合制御装置60は事前に縮退運転を解放する指令を出力し、その後に通常の分散運転に戻す指令を出力する。   Next, a description will be given of the case where the integrated linkage control according to the present invention is performed on the power supply system 1 having the above-described configuration. In this description, the integrated control device 60 issues a command to perform a degenerate operation that aggregates loads in the ICT device 25 when the number of employees in the building where the terminal of the ICT device 25 is installed is smaller than a predetermined number. Output. If the load on the ICT device 25 increases during the degenerate operation, the integrated control device 60 outputs a command to release the degenerate operation in advance, and then outputs a command to return to normal distributed operation.

ここで、縮退運転を実行する際の制御処理について図3のフローチャートを参照しながら説明する。はじめに統合制御装置60の取得部64は、入退管理装置65から入退情報を取得する処理を実行する(S11:取得ステップ)。   Here, the control process when executing the degenerate operation will be described with reference to the flowchart of FIG. First, the acquisition unit 64 of the integrated control device 60 executes processing for acquiring entrance / exit information from the entrance / exit management device 65 (S11: acquisition step).

入退情報が取得されると、統合制御装置60の演算処理部61は、ICT装置25の端末が設けられた建物に在館する社員数が、予め定められた所定の一定数未満であるか否かを判定する処理を行う(S12:優先処理ステップ)。具体的には、入退情報に基づき在館する社員数を求める演算処理と、統合制御装置60のハードディスク等に予め記憶された所定の一定数を取得する処理と、在館する社員数および所定の一定数を比較する処理を行う。   When the entry / exit information is acquired, the arithmetic processing unit 61 of the integrated control device 60 determines whether the number of employees in the building where the terminal of the ICT device 25 is provided is less than a predetermined fixed number. Processing to determine whether or not is performed (S12: priority processing step). Specifically, a calculation process for obtaining the number of employees in the building based on the entrance / exit information, a process for obtaining a predetermined constant stored in advance in the hard disk of the integrated control device 60, the number of employees in the building and the predetermined number A process of comparing a certain number of.

S12の判定処理において、在館する社員数が所定の一定数以上と判定された場合(NOの場合)には、演算処理部61は縮退運転の可否を判断する処理を中止する。
その一方で、在館する社員数が所定の一定数未満と判定された場合(YESの場合)には、統合制御装置60の取得部64はICTリソース情報を取得する処理を行う(S13:優先処理ステップ)。具体的には、取得処理を行う時点で最も新しいICT装置25および空調装置35の稼働に関する情報などを取得する処理を行う。
In the determination process of S12, when it is determined that the number of employees in the building is equal to or larger than a predetermined number (in the case of NO), the arithmetic processing unit 61 stops the process of determining whether or not the degenerate operation is possible.
On the other hand, when it is determined that the number of employees in the building is less than a predetermined number (in the case of YES), the acquisition unit 64 of the integrated control device 60 performs processing for acquiring ICT resource information (S13: priority). Processing steps). Specifically, a process of acquiring information related to the operation of the latest ICT device 25 and air conditioner 35 at the time of performing the acquisition process is performed.

リソース情報を取得すると演算処理部61は制御の優先順位を判定する処理を行う(S14:優先処理ステップ)。本実施形態では、ICT装置25の稼働状況を制御して消費電力を削減させる制御(以下、「ICT装置25による削減制御」とも表記する。)と、空調装置35の稼働状況を制御して消費電力を削減させる制御(以下、「空調装置35による削減制御」とも表記する。)との間の優先順位を判定する処理が行われる。具体的には、ICT装置25による削減制御が、空調装置35による削減制御よりも優先されるか否かを判定する処理を行う。   When the resource information is acquired, the arithmetic processing unit 61 performs processing for determining the priority of control (S14: priority processing step). In the present embodiment, control for reducing the power consumption by controlling the operating status of the ICT device 25 (hereinafter also referred to as “reduction control by the ICT device 25”) and the operating status of the air conditioner 35 are controlled and consumed. Processing for determining the priority order with respect to control for reducing power (hereinafter also referred to as “reduction control by the air conditioner 35”) is performed. Specifically, a process for determining whether or not the reduction control by the ICT device 25 has priority over the reduction control by the air conditioner 35 is performed.

予測処理部63は、在館する社員数および取得したリソース情報に基づいてICT装置25における演算等の情報処理量を推定する演算処理を行う。推定された演算等の情報処理量が増加する場合には、演算処理部61はICT装置25による削減制御を優先するとの判定を行う(YES)。その一方で、推定された演算等の情報処理量が増加しない場合には、空調装置35による削減制御を優先するとの判定を行う(NO)。   The prediction processing unit 63 performs a calculation process for estimating an information processing amount such as a calculation in the ICT device 25 based on the number of employees in the building and the acquired resource information. When the amount of information processing such as the estimated calculation increases, the calculation processing unit 61 determines that priority is given to reduction control by the ICT device 25 (YES). On the other hand, if the amount of information processing such as the estimated calculation does not increase, it is determined that priority is given to reduction control by the air conditioner 35 (NO).

S14の判定においてICT装置25による削減制御を優先すると判定された場合(YESの場合)、演算処理部61は、ICT装置25等に障害が発生していないか否か、または運用に支障が出るか否かを判定する処理を行う(S15)。具体的には、監視制御装置70が、演算処理の移行元であるICT装置25(以後、「縮退元ICT装置25」と表記する。)および演算処理の移行先であるICT装置25(以後、「縮退先ICT装置25」と表記する。)や、空調装置35や、給電装置10において異常が発生したことを示す情報を受け取っているか否かに基づいて、上述の判定処理を行う。障害が発生している、あるいは運用に支障が出ると判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。なお、縮退元ICT装置25は、特許請求の範囲における移行元の負荷装置に相当し、縮退先ICT装置25は、特許請求の範囲における移行先の負荷装置に相当する。   When it is determined in S14 that priority is given to the reduction control by the ICT device 25 (in the case of YES), the arithmetic processing unit 61 determines whether or not a failure has occurred in the ICT device 25 or the like, or hinders operation. The process which determines whether or not is performed (S15). Specifically, the supervisory control device 70 includes the ICT device 25 (hereinafter referred to as “degenerate source ICT device 25”) that is the operation processing transfer source and the ICT device 25 (hereinafter referred to as “degeneration source ICT device 25”). The above-described determination processing is performed based on whether or not information indicating that an abnormality has occurred in the air conditioner 35 or the power supply device 10 is received. If it is determined that a failure has occurred or that the operation will be hindered (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped. The degeneration source ICT device 25 corresponds to the load source load device in the claims, and the degeneration destination ICT device 25 corresponds to the transfer destination load device in the claims.

障害が発生していないと判定された場合(YESの場合)、演算処理部61は、ICT装置25のリソースに余裕があるか否かを判定する処理を行う(S16)。つまり、演算処理部61は、縮退先ICT装置25のリソースに余裕があるか否かを判定する。より具体的には、縮退元ICT装置25の演算処理を縮退先ICT装置25に移行させても、縮退先ICT装置25におけるCPU使用率が所定値(例えば80%)未満であること、メモリの使用率が所定値(例えば80%)未満であること、ハードディスク(HDD)の使用率が所定値(例えば80%)未満であること、の全てを満たすか否かを判定する。リソースに余裕がないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。   When it is determined that no failure has occurred (in the case of YES), the arithmetic processing unit 61 performs a process of determining whether or not the resources of the ICT device 25 have room (S16). That is, the arithmetic processing unit 61 determines whether or not the resources of the degeneration destination ICT device 25 have room. More specifically, even if the arithmetic processing of the degeneration source ICT device 25 is transferred to the degeneration destination ICT device 25, the CPU usage rate in the degeneration destination ICT device 25 is less than a predetermined value (for example, 80%), It is determined whether or not the usage rate is less than a predetermined value (for example, 80%) and the usage rate of the hard disk (HDD) is less than the predetermined value (for example, 80%). When it is determined that there is no room for resources (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped.

リソースに余裕があると判定された場合(YESの場合)、演算処理部61は、給電装置10やスイッチ16やスイッチ27Aの容量に余裕があるか否かを判定する処理を行う(S17)。つまり、縮退先ICT装置25に直流電流を供給する給電装置10やスイッチ16やスイッチ27Aなどの容量に余裕があるか否かを判定する処理を行う。より具体的には、縮退元ICT装置25の演算処理を縮退先ICT装置25に移行させても、給電装置10の出力が定格容量の所定値(例えば80%)未満であること、スイッチ16およびやスイッチ27Aの電流が定格容量の所定値(80%)未満であること、の全てを満たすか否かを判定する。容量に余裕がないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。   When it is determined that there is a margin in resources (in the case of YES), the arithmetic processing unit 61 performs a process of determining whether or not there is a margin in the capacity of the power supply apparatus 10, the switch 16, or the switch 27A (S17). That is, a process of determining whether or not there is a margin in the capacity of the power supply apparatus 10 that supplies a direct current to the degeneration destination ICT apparatus 25, the switch 16, the switch 27A, or the like is performed. More specifically, even if the arithmetic processing of the degeneration source ICT device 25 is shifted to the degeneration destination ICT device 25, the output of the power supply device 10 is less than a predetermined value (for example, 80%) of the rated capacity, the switch 16 and Or whether the current of the switch 27A is less than a predetermined value (80%) of the rated capacity. When it is determined that there is no capacity (NO), the process for determining whether or not the degenerate operation is possible is stopped.

容量に余裕があると判定された場合(YESの場合)、演算処理部61は、空調能力に余裕があるか否かを判定する処理を行う(S18)。つまり、縮退先ICT装置25の冷却を行う空調装置35の冷房能力に余裕があるか否かを判定する処理を行う。より具体的には、縮退元ICT装置25の演算処理を縮退先ICT装置25に移行させても、空調装置35の定格冷房能力の所定値(例えば80%)未満であることを満たすか否かを判定する。空調能力に余裕がないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。   When it is determined that there is a sufficient capacity (in the case of YES), the arithmetic processing unit 61 performs a process of determining whether there is a sufficient air conditioning capacity (S18). That is, a process for determining whether or not there is a margin in the cooling capacity of the air conditioner 35 that cools the degeneration destination ICT device 25 is performed. More specifically, whether or not the arithmetic processing of the degeneration source ICT device 25 is less than a predetermined value (for example, 80%) of the rated cooling capacity of the air conditioner 35 even if the arithmetic processing of the degeneration source ICT device 25 is shifted to the degeneration destination ICT device 25. Determine. When it is determined that there is no room for air conditioning capability (in the case of NO), the process of determining whether or not the degenerate operation is possible is stopped.

空調能力に余裕があると判定された場合(YESの場合)、統合制御装置60は、ICT制御装置30へ集約処理を行う指令を出力する。ICT制御装置30は対象となるICT装置25へ縮退運転に移行するための集約処理を実行する指令を出力する(S21)。集約処理が仮想化による場合には、縮退元ICT装置25は、縮退先ICT装置25へのライブマイグレーションを実行する。移行が完了した後、縮退元ICT装置25は休止状態へ移行する。集約処理が余剰ICT装置25の運転休止である場合には対象装置を休止状態へ移行する。   When it is determined that the air conditioning capacity has a margin (in the case of YES), the integrated control device 60 outputs a command to perform the aggregation process to the ICT control device 30. The ICT control device 30 outputs a command to execute an aggregation process for shifting to the degenerate operation to the target ICT device 25 (S21). When the aggregation process is based on virtualization, the degeneration source ICT device 25 performs live migration to the degeneration destination ICT device 25. After the transfer is completed, the degeneration source ICT device 25 shifts to a dormant state. When the aggregation process is operation suspension of the surplus ICT device 25, the target device is shifted to the suspension state.

本実施形態では、図5に示すように、架列28A,28B,28E,28Fに搭載されたICT装置25を縮退元ICT装置25とし、架列28C,28Dに搭載されたICT装置25を縮退先ICT装置25とした例に適用して説明する。   In this embodiment, as shown in FIG. 5, the ICT device 25 mounted on the racks 28A, 28B, 28E, and 28F is the degeneration source ICT device 25, and the ICT device 25 mounted on the racks 28C and 28D is degenerated. Description will be made by applying to the example in which the previous ICT device 25 is used.

次いで、図3のフローチャートに戻り、ICTリソースの移動(Guestマシンの移動)が成功したか否かを判定する処理を行う(S22)。具体的には、次の5条件が満たされるか否かに基づいて判定が行われる。1つ目が、縮退先ICT装置25でハードウエア障害(以下「H/W障害」と表記する。)が発生していないこと。2つ目が、縮退元ICT装置25でH/W障害が発生していないこと。3つ目が、仮想化管理ソフト上で、縮退元の仮想Guestマシンが正常であること。4つ目が縮退元の仮想化ソフト上で、移動対象となる仮想Guestマシンが正常であること。5つ目が、縮退先のICTリソースに余裕があること。より具体的には、縮退元ICT装置25の演算処理を縮退先ICT装置25に移行させても、縮退先ICT装置25におけるCPU使用率が所定値(例えば80%)未満であること、メモリの使用率が所定値(例えば最大容量の80%)未満であること、ハードディスク(HDD)の使用率が所定値(例えば最大容量の80%)未満であることを満たすこと。   Next, returning to the flowchart of FIG. 3, a process for determining whether or not the ICT resource movement (Guest machine movement) is successful is performed (S22). Specifically, the determination is performed based on whether or not the following five conditions are satisfied. The first is that no hardware failure (hereinafter referred to as “H / W failure”) has occurred in the degeneration destination ICT device 25. Second, there is no H / W failure in the degeneration source ICT device 25. Third, the virtual guest machine of the degeneration source is normal on the virtualization management software. The fourth is that the virtual guest machine to be moved is normal on the degeneration-source virtualization software. The fifth is that there is room in the degenerate destination ICT resource. More specifically, even if the arithmetic processing of the degeneration source ICT device 25 is transferred to the degeneration destination ICT device 25, the CPU usage rate in the degeneration destination ICT device 25 is less than a predetermined value (for example, 80%), The usage rate is less than a predetermined value (for example, 80% of the maximum capacity) and the usage rate of the hard disk (HDD) is less than a predetermined value (for example, 80% of the maximum capacity).

ICTリソースの移動が失敗したと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。ICTリソースの移動が成功したと判定された場合(YESの場合)、統合制御装置60は、ICT制御装置30へ縮退元のICT装置25へ対して休止指示を出し、当該ICT装置25への休止処理が成功したか否かを判定する処理を行う(S23)。具体的には、次の4条件が満たされるか否かに基づいて判定が行われる。1つ目が、休止対象ICT装置25においてCPU使用率が所定値(例えば5%)以下であり、かつ、メモリ使用率が所定値(例えば5%)以下であること。2つ目が、仮想化管理ソフト上で、休止対象ICT装置25上に仮想Guestマシンが存在しないこと。3つ目が、休止対象ICT装置25の仮想化ソフト上で、仮想Guestマシンが存在しないこと。4つ目が、休止対象ICT装置25と接続しているスイッチ16およびスイッチ27Aのアウトレット(Outlet)の消費電流が所定値(例えば定格電流の3割)以下であること。   When it is determined that the movement of the ICT resource has failed (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped. When it is determined that the ICT resource has been successfully moved (in the case of YES), the integrated control device 60 issues a pause instruction to the ICT control device 30 to the ICT device 25 that is the degeneration source, and pauses to the ICT device 25. A process of determining whether or not the process is successful is performed (S23). Specifically, the determination is performed based on whether or not the following four conditions are satisfied. First, the CPU usage rate is less than or equal to a predetermined value (for example, 5%) and the memory usage rate is less than or equal to a predetermined value (for example, 5%) in the suspension target ICT device 25. Second, there is no virtual guest machine on the suspension target ICT device 25 on the virtualization management software. Third, there is no virtual guest machine on the virtualization software of the suspension target ICT device 25. Fourth, the current consumption of the outlets of the switch 16 and the switch 27A connected to the suspension target ICT device 25 is not more than a predetermined value (for example, 30% of the rated current).

ICT装置25の休止が失敗したと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。ICT装置25の休止が成功したと判定された場合(YESの場合)、統合制御装置60は、ICT制御装置30から出力されるICT装置25の休止状態情報を確認する。確認後に、ICT制御装置30に対して、休止済みのICT装置25に対して停止(シャットダウン)指令を出す。統合制御装置60はICT装置25の停止を確認した後、給電制御装置20に対し給電ルート上にあるコンセントバー27、または電流分配装置15のスイッチ16またはスイッチ27Aに対して給電OFFとする指令を出力する(S31)。   When it is determined that the pause of the ICT device 25 has failed (in the case of NO), the process of determining whether or not the degenerate operation is possible is stopped. When it is determined that the suspension of the ICT device 25 is successful (in the case of YES), the integrated control device 60 confirms the suspension state information of the ICT device 25 output from the ICT control device 30. After the confirmation, a stop (shutdown) command is issued to the ICT device 25 that has been stopped. After confirming that the ICT device 25 is stopped, the integrated control device 60 instructs the power supply control device 20 to turn off power to the outlet bar 27 on the power supply route, or to the switch 16 or the switch 27A of the current distribution device 15. Output (S31).

次いで、停止済みのICT装置25に対応するスイッチ16またはスイッチ27Aにおいて給電OFFされているか否かを判定する処理を行う(S32)。具体的には、次の2条件が満たされているか否かを判定する処理を行う。1つ目は、接続しているICT装置25が停止していること。より具体的に説明すると次の3つの内容が満たされていること。対象のICT装置25にピン(Ping)接続しても応答がないこと、対象のICT装置25の仮想化ソフトに接続できないこと、対象のICT装置25に管理用ネットワーク(NW)で接続し、電源がオフ(OFF)となっていること。2つ目は、対象のICT装置25に接続しているスイッチ16またはスイッチ27Aのアウトレット(Outlet)の消費電流値が所定値(例えば定格電流の1割)以下であること。   Next, a process of determining whether or not the power supply is turned off in the switch 16 or the switch 27A corresponding to the stopped ICT device 25 is performed (S32). Specifically, processing for determining whether or not the following two conditions are satisfied is performed. First, the connected ICT device 25 is stopped. More specifically, the following three contents are satisfied. Even if a pin (Ping) connection is made to the target ICT device 25, there is no response, connection to the virtualization software of the target ICT device 25 is not possible, connection to the target ICT device 25 via a management network (NW), and power supply Is turned off. Second, the current consumption value of the outlet of the switch 16 or the switch 27A connected to the target ICT device 25 is not more than a predetermined value (for example, 10% of the rated current).

給電OFFされていないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。
次いで、給電OFFされていると判定された場合(YESの場合)、統合制御装置60は、停止済みのICT装置25の温度が低下する余裕をもって、停止済みのICT装置25に対応する空調装置35を停止させる指令を空調制御装置40に出力する(S41)。空調制御装置40は停止済みのICT装置25に対応する空調装置35を停止させる指令を当該空調装置35に出力する。
When it is determined that the power supply is not turned off (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped.
Next, when it is determined that the power supply is turned off (in the case of YES), the integrated control device 60 has an allowance for the temperature of the stopped ICT device 25 to fall, and the air conditioner 35 corresponding to the stopped ICT device 25. The command which stops is output to the air-conditioning control apparatus 40 (S41). The air conditioning control device 40 outputs to the air conditioning device 35 a command to stop the air conditioning device 35 corresponding to the stopped ICT device 25.

本実施形態では、図5に示すように、架列28A,28B,28E,28Fに対応する空調装置35が停止されている例に適用して説明する。図5では、対応する空調装置35に斜線を入れることにより、給電OFFを表している。   In the present embodiment, as shown in FIG. 5, description will be made by applying to an example in which the air conditioners 35 corresponding to the racks 28A, 28B, 28E, and 28F are stopped. In FIG. 5, feeding OFF is indicated by putting a diagonal line in the corresponding air conditioner 35.

なお、停止済みのICT装置25に対応する空調装置35を停止したことにより、縮退先のICT装置25が属する空調ゾーンの温度が上昇した場合、空調制御装置40は、必要に応じて停止した空調装置35の運転を再開する指令を出力してもよい。   If the temperature of the air-conditioning zone to which the degeneration destination ICT device 25 belongs increases due to the stop of the air-conditioning device 35 corresponding to the stopped ICT device 25, the air-conditioning control device 40 stops the air-conditioning that has been stopped as necessary. A command for resuming the operation of the device 35 may be output.

次いで、図3のフローチャートに戻り、休止済みのICT装置25に対応する空調装置35が停止しているか否かを判定する処理を行う(S42)。具体的には、次の4条件が満たされているか否かを判定する処理を行う。1つ目は、停止対象以外のICT装置25に対応する空調装置35が正常であること(言い換えると、障害が発生していないこと。)。2つ目は、停止対象以外のICT装置25に対応する空調装置35において冷房能力に余裕があり、定格能力の所定値(90%)未満であること。3つ目は、停止対象以外の空調装置35が管轄するICT装置25の吸込み部付近(または、架列の間の一部であるコールドアイル(Cold Aisle))の温度が所定温度以下であること。4つ目は、停止対象となる空調装置35が管轄するICT装置25は稼働していないこと。より具体的には、ICT装置25が停止していること、かつ、ICT装置25と接続しているスイッチ16またはスイッチ27AのアウトレットがOFFとなっていること。   Next, returning to the flowchart of FIG. 3, processing for determining whether or not the air conditioner 35 corresponding to the suspended ICT device 25 is stopped is performed (S <b> 42). Specifically, processing for determining whether or not the following four conditions are satisfied is performed. The first is that the air conditioner 35 corresponding to the ICT device 25 other than the stop target is normal (in other words, no failure has occurred). The second is that the air conditioning device 35 corresponding to the ICT device 25 other than the stop target has a sufficient cooling capacity and is less than a predetermined value (90%) of the rated capacity. Third, the temperature in the vicinity of the suction portion of the ICT device 25 (or Cold Aisle) that is under the jurisdiction of the air conditioner 35 other than the stop target is equal to or lower than the predetermined temperature. . Fourth, the ICT device 25 under the jurisdiction of the air conditioner 35 to be stopped is not operating. More specifically, the ICT device 25 is stopped and the outlet of the switch 16 or the switch 27A connected to the ICT device 25 is OFF.

空調装置35が停止していないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。
次いで、空調装置35が停止されていると判定された場合(YESの場合)、統合制御装置60は、停止済みのICT装置25に対応する電源ユニット11を停止させる指令を出力する(S51)。言い換えると、ICT装置25の停止に伴い給電装置10の運転負荷率が低下するため、余剰となった電源ユニット11を停止させる指令を給電制御装置20に出力する。
When it is determined that the air conditioner 35 has not stopped (in the case of NO), the process of determining whether or not the degenerate operation is possible is stopped.
Next, when it is determined that the air conditioner 35 is stopped (in the case of YES), the integrated control device 60 outputs a command to stop the power supply unit 11 corresponding to the stopped ICT device 25 (S51). In other words, since the operating load factor of the power supply device 10 decreases with the stop of the ICT device 25, a command to stop the surplus power supply unit 11 is output to the power supply control device 20.

具体的には、給電装置10に搭載されている電源ユニット11の台数と、出力電流値とを比較し、以下の式で求められる台数の電源ユニット11を停止する指令を出力する。なお、停止する電源ユニット11の台数は、電源ユニット11の故障や負荷急増時の対応等を考慮して、必要な電源ユニット11の台数に冗長分を考慮した台数としてもよい。   Specifically, the number of power supply units 11 mounted on the power supply apparatus 10 is compared with the output current value, and a command to stop the number of power supply units 11 obtained by the following equation is output. Note that the number of power supply units 11 to be stopped may be a number that takes redundancy into consideration for the necessary number of power supply units 11 in consideration of a failure of the power supply unit 11 or a response to a sudden increase in load.

[(給電装置10に搭載された電源ユニット11の台数)×(電源ユニット11単体の容量)−{(出力電流)+(電源ユニット11単体の容量)}]÷(電源ユニット11単体の容量)≧停止可能な電源ユニット11の台数
次いで、停止済みのICT装置25に対応する電源ユニット11が停止しているか否かを判定する処理を行う(S52)。電源ユニット11が停止していないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。
[(The number of power supply units 11 mounted on the power supply apparatus 10) × (capacity of the power supply unit 11 alone) − {(output current) + (capacity of the power supply unit 11 alone)}] / (capacity of the power supply unit 11 alone) ≧ Number of power supply units 11 that can be stopped Next, it is determined whether or not the power supply unit 11 corresponding to the stopped ICT device 25 is stopped (S52). When it is determined that the power supply unit 11 is not stopped (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped.

電源ユニット11が停止していると判定された場合(YESの場合)、統合制御装置60は、照明機器45を消灯する指令を出力する処理を行う(S61)。言い換えると、不要となった照明機器45を消灯するため、照明制御装置50へ消灯指令を出力する。照明制御装置50は、必要に応じて作業者の不在を確認した後、該当部分の消灯を実行する。   When it determines with the power supply unit 11 having stopped (in the case of YES), the integrated control apparatus 60 performs the process which outputs the instruction | command which turns off the illuminating device 45 (S61). In other words, a turn-off command is output to the lighting control device 50 in order to turn off the lighting device 45 that is no longer needed. After confirming the absence of the worker as necessary, the lighting control device 50 turns off the corresponding part.

次いで、照明機器45が消灯されたか否かを判定する処理を行う(S62)。具体的には、次の3条件を満たすか否かを判定する処理を行う。1つ目は、ICT装置25が正常に停止したこと。2つ目は、対応するスイッチ16またはスイッチ27Aが全てOFFになっていること。3つ目は、対応する空調装置35が停止していること。   Subsequently, the process which determines whether the illuminating device 45 was light-extinguished is performed (S62). Specifically, a process for determining whether or not the following three conditions are satisfied is performed. The first is that the ICT device 25 has stopped normally. Second, all the corresponding switches 16 or 27A are OFF. Third, the corresponding air conditioner 35 is stopped.

照明機器45が消灯されていないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。また、照明機器45が消灯されていると判定された場合(YESの場合)、縮退運転の可否を判断する処理を終了する。   When it is determined that the lighting device 45 is not turned off (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped. Moreover, when it determines with the illuminating device 45 having been extinguished (in the case of YES), the process which determines the propriety of degeneration operation is complete | finished.

なお、上述のように縮退運転への移行処理を実行するにあたり、必要に応じてSDN(software defined network)技術、NFV(Network Function Virtualization)技術やロードバランサーなどのネットワーク制御、負荷制御を行う場合もある。   In addition, when executing the transition process to the degenerate operation as described above, network control and load control such as SDN (software defined network) technology, NFV (Network Function Virtualization) technology, load balancer, etc. may be performed as necessary. .

S14の判定において空調装置35による削減制御を優先すると判定された場合(NOの場合)、図4のフローチャートに移動し、演算処理部61は、ICT装置25等に障害が発生していないか否か、または運用に支障が出るか否かを判定する処理を行う(S115)。障害が発生している、あるいは運用に支障が出ると判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。なお、この判定における具体的な処理内容は、S15における判定と同様であるため、その説明を省略する。   If it is determined in S14 that priority is given to the reduction control by the air conditioner 35 (in the case of NO), the process moves to the flowchart of FIG. 4 and the arithmetic processing unit 61 determines whether or not a failure has occurred in the ICT device 25 or the like. Or processing for determining whether or not the operation will be hindered (S115). If it is determined that a failure has occurred or that the operation will be hindered (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped. In addition, since the specific processing content in this determination is the same as the determination in S15, the description is abbreviate | omitted.

障害が発生していないと判定された場合(YESの場合)、演算処理部61は、ICT装置25のリソースに余裕があるか否かを判定する処理を行う(S116)。リソースに余裕がないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。なお、この判定における具体的な処理内容は、S16における判定と同様であるため、その説明を省略する。   When it is determined that no failure has occurred (in the case of YES), the arithmetic processing unit 61 performs a process of determining whether or not the resources of the ICT device 25 have room (S116). When it is determined that there is no room for resources (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped. In addition, since the specific processing content in this determination is the same as the determination in S16, the description is abbreviate | omitted.

リソースに余裕があると判定された場合(YESの場合)、演算処理部61は、給電装置10やスイッチ16やスイッチ27Aの容量に余裕があるか否かを判定する処理を行う(S117)。容量に余裕がないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。なお、この判定における具体的な処理内容は、S17における判定と同様であるため、その説明を省略する。   When it is determined that there is a margin in resources (in the case of YES), the arithmetic processing unit 61 performs a process of determining whether or not there is a margin in the capacity of the power supply apparatus 10, the switch 16, or the switch 27A (S117). When it is determined that there is no capacity (NO), the process for determining whether or not the degenerate operation is possible is stopped. In addition, since the specific processing content in this determination is the same as the determination in S17, the description is abbreviate | omitted.

容量に余裕があると判定された場合(YESの場合)、演算処理部61は、空調能力に余裕があるか否かを判定する処理を行う(S118)。空調能力に余裕がないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。なお、この判定における具体的な処理内容は、S18における判定と同様であるため、その説明を省略する。   When it is determined that there is a sufficient capacity (in the case of YES), the arithmetic processing unit 61 performs a process of determining whether there is a sufficient air conditioning capacity (S118). When it is determined that there is no room for air conditioning capability (in the case of NO), the process of determining whether or not the degenerate operation is possible is stopped. In addition, since the specific processing content in this determination is the same as the determination in S18, the description thereof is omitted.

空調能力に余裕があると判定された場合(YESの場合)、統合制御装置60は、冷房能力が過剰になると推定される空調装置35を停止させる指令を空調制御装置40に出力する(S141)。なお、本実施形態では、冷房能力が過剰になると推定される空調装置35を停止させる例に適用して説明するが、停止に限定されず、空調装置35で消費される電力が削減される制御を行ってもよい。また、冷房能力が過剰になるとの推定方法としては、公知の方法を用いることができ、特に限定するものではない。   If it is determined that the air conditioning capacity is sufficient (in the case of YES), the integrated control device 60 outputs to the air conditioning control device 40 a command to stop the air conditioning device 35 that is estimated to have an excessive cooling capacity (S141). . In this embodiment, the description will be made by applying the present invention to an example in which the air conditioner 35 estimated to have an excessive cooling capacity is stopped. However, the present invention is not limited to the stop, and the control for reducing the power consumed by the air conditioner 35 is described. May be performed. Moreover, as a method for estimating that the cooling capacity is excessive, a known method can be used, and it is not particularly limited.

次いで、停止させる指令の対象になった空調装置35が停止しているか否かを判定する処理を行う(S142)。対象になった空調装置35が停止していないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。なお、この判定における具体的な処理内容は、S42における判定と同様であるため、その説明を省略する。   Next, a process of determining whether or not the air conditioner 35 that is the target of the stop command is stopped is performed (S142). When it is determined that the target air conditioner 35 is not stopped (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped. In addition, since the specific processing content in this determination is the same as the determination in S42, the description thereof is omitted.

次いで、空調装置35が停止されていると判定された場合(YESの場合)、統合制御装置60は、ICT制御装置30へ集約処理を行う指令を出力する。ICT制御装置30は対象となるICT装置25へ縮退運転に移行するための集約処理を実行する指令を出力する(S121)。ここで、対象となるICT装置25としては、S141の処理において、停止させる指令の対象になった空調装置35による冷房ゾーンに配置されているICT装置25を例示することができる。なお、集約処理の内容についてはS21における処理内容と同様であるため、その説明を省略する。   Next, when it is determined that the air conditioner 35 is stopped (in the case of YES), the integrated control device 60 outputs a command to perform the aggregation process to the ICT control device 30. The ICT control device 30 outputs a command to execute an aggregation process for shifting to the degenerate operation to the target ICT device 25 (S121). Here, as the target ICT device 25, the ICT device 25 arranged in the cooling zone by the air conditioner 35 that is the target of the command to be stopped in the process of S141 can be exemplified. The contents of the aggregation process are the same as the contents of the process in S21, and thus the description thereof is omitted.

次いで、統合制御装置60は、ICTリソースの移動(Guestマシンの移動)が成功したか否かを判定する処理を行う(S122)。ICTリソースの移動が失敗したと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。なお、この判定における具体的な処理内容は、S22における判定と同様であるため、その説明を省略する。   Next, the integrated control device 60 performs a process of determining whether or not the ICT resource movement (Guest machine movement) is successful (S122). When it is determined that the movement of the ICT resource has failed (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped. In addition, since the specific processing content in this determination is the same as the determination in S22, the description is abbreviate | omitted.

ICTリソースの移動が成功したと判定された場合(YESの場合)、統合制御装置60は、ICT制御装置30へ縮退元のICT装置25へ対して休止指示を出し、当該ICT装置25への休止処理が成功したか否かを判定する処理を行う(S123)。ICT装置25の休止が失敗したと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。なお、この判定における具体的な処理内容は、S23における判定と同様であるため、その説明を省略する。   When it is determined that the ICT resource has been successfully moved (in the case of YES), the integrated control device 60 issues a pause instruction to the ICT control device 30 to the ICT device 25 that is the degeneration source, and pauses to the ICT device 25. A process of determining whether or not the process is successful is performed (S123). When it is determined that the pause of the ICT device 25 has failed (in the case of NO), the process of determining whether or not the degenerate operation is possible is stopped. In addition, since the specific processing content in this determination is the same as the determination in S23, the description thereof is omitted.

ICT装置25の休止が成功したと判定された場合(YESの場合)、統合制御装置60は、ICT制御装置30から出力されるICT装置25の休止状態情報を確認する。確認後に、ICT制御装置30に対して、休止済みのICT装置25に対して停止(シャットダウン)指令を出す。統合制御装置60はICT装置25の停止を確認した後、給電制御装置20に対し給電ルート上にあるコンセントバー27、または電流分配装置15のスイッチ16またはスイッチ27Aに対して給電OFFとする指令を出力する(S31)。   When it is determined that the suspension of the ICT device 25 is successful (in the case of YES), the integrated control device 60 confirms the suspension state information of the ICT device 25 output from the ICT control device 30. After the confirmation, a stop (shutdown) command is issued to the ICT device 25 that has been stopped. After confirming that the ICT device 25 is stopped, the integrated control device 60 instructs the power supply control device 20 to turn off power to the outlet bar 27 on the power supply route, or to the switch 16 or the switch 27A of the current distribution device 15. Output (S31).

次いで、停止済みのICT装置25に対応するスイッチ16またはスイッチ27Aにおいて給電OFFされているか否かを判定する処理を行う(S32)。給電OFFされていないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。   Next, a process of determining whether or not the power supply is turned off in the switch 16 or the switch 27A corresponding to the stopped ICT device 25 is performed (S32). When it is determined that the power supply is not turned off (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped.

次いで、給電OFFされていると判定された場合(YESの場合)、統合制御装置60は、停止済みのICT装置25に対応する電源ユニット11を停止させる指令を出力する(S51)。   Next, when it is determined that the power supply is turned off (in the case of YES), the integrated control device 60 outputs a command to stop the power supply unit 11 corresponding to the stopped ICT device 25 (S51).

次いで、停止済みのICT装置25に対応する電源ユニット11が停止しているか否かを判定する処理を行う(S52)。電源ユニット11が停止していないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。   Next, a process of determining whether or not the power supply unit 11 corresponding to the stopped ICT device 25 is stopped is performed (S52). When it is determined that the power supply unit 11 is not stopped (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped.

電源ユニット11が停止していると判定された場合(YESの場合)、統合制御装置60は、照明機器45を消灯する指令を出力する処理を行う(S61)。次いで、照明機器45が消灯されたか否かを判定する処理を行う(S62)。   When it determines with the power supply unit 11 having stopped (in the case of YES), the integrated control apparatus 60 performs the process which outputs the instruction | command which turns off the illuminating device 45 (S61). Subsequently, the process which determines whether the illuminating device 45 was light-extinguished is performed (S62).

照明機器45が消灯されていないと判定された場合(NOの場合)には、縮退運転の可否を判断する処理を中止する。また、照明機器45が消灯されていると判定された場合(YESの場合)、縮退運転の可否を判断する処理を終了する。   When it is determined that the lighting device 45 is not turned off (in the case of NO), the process for determining whether or not the degenerate operation is possible is stopped. Moreover, when it determines with the illuminating device 45 having been extinguished (in the case of YES), the process which determines the propriety of degeneration operation is complete | finished.

次いで、縮退運転から分散運転への復元を実行する際の制御処理について図6のフローチャートを参照しながら説明する。はじめに統合制御装置60の取得部64は、入退管理装置65から入退情報を取得する処理を実行する(S211)。   Next, a control process for executing restoration from the degenerate operation to the distributed operation will be described with reference to the flowchart of FIG. First, the acquisition unit 64 of the integrated control device 60 executes processing for acquiring entry / exit information from the entry / exit management device 65 (S211).

入退情報が取得されると、統合制御装置60の演算処理部61は、ICT装置25の端末が設けられた建物に在館する社員数が、予め定められた所定の一定数以上であるか否かを判定する処理を行う(S212)。S212の判定処理において、在館する社員数が所定の一定数未満と判定された場合(NOの場合)には、演算処理部61は分散運転の可否を判断する処理を中止する。なお、S212における判定の内容は、S12における処理内容と同様であるため、その説明を省略する。   When the entry / exit information is acquired, the arithmetic processing unit 61 of the integrated control device 60 determines whether the number of employees in the building in which the terminal of the ICT device 25 is provided is equal to or greater than a predetermined constant. Processing to determine whether or not is performed (S212). In the determination process of S212, when it is determined that the number of employees in the building is less than a predetermined number (in the case of NO), the arithmetic processing unit 61 stops the process of determining whether or not the distributed operation is possible. Note that the content of the determination in S212 is the same as the content of the process in S12, and thus the description thereof is omitted.

その一方で、在館する社員数が所定の一定数以上と判定された場合(YESの場合)には、統合制御装置60は、ICT装置25等に障害が発生していないか否か、または運用に支障が出るか否かを判定する処理を行う(S213)。具体的には、監視制御装置70が、分散元ICT装置25および分散先ICT装置25や、空調装置35や、給電装置10において異常が発生したことを示す情報を受け取っているか否かに基づいて、上述の判定処理を行う。   On the other hand, when it is determined that the number of employees in the building is equal to or larger than a predetermined number (in the case of YES), the integrated control device 60 determines whether or not a failure has occurred in the ICT device 25 or the like. A process of determining whether or not the operation is hindered is performed (S213). Specifically, based on whether the monitoring control device 70 has received information indicating that an abnormality has occurred in the distribution source ICT device 25 and the distribution destination ICT device 25, the air conditioner 35, or the power supply device 10. The above-described determination process is performed.

障害が発生している、あるいは運用に支障がでると判定された場合(NOの場合)には、移行の可否を判断する処理を中止する。なお、分散元ICT装置25は上述の縮退先ICT装置25であり、分散先ICT装置25は上述の縮退元ICT装置25である。   When it is determined that a failure has occurred or that the operation is hindered (in the case of NO), the process for determining whether or not to migrate is stopped. The distribution source ICT device 25 is the above-described degeneration destination ICT device 25, and the distribution destination ICT device 25 is the above-described degeneration source ICT device 25.

障害が発生していないと判定された場合(YESの場合)、統合制御装置60は、起動対象に関する空調装置35を起動させる指令を出力する処理を行う(S221)。言い換えると、運転を再開するICT装置25の空調ゾーンの空調装置35を制御する空調制御装置40に対して、予冷のための運転を開始する指令を出力する。空調制御装置40は、該当する空調装置35に対して起動指令を出力する。   When it is determined that no failure has occurred (in the case of YES), the integrated control device 60 performs a process of outputting a command for starting the air conditioner 35 related to the start target (S221). In other words, a command to start the operation for pre-cooling is output to the air-conditioning control device 40 that controls the air-conditioning device 35 in the air-conditioning zone of the ICT device 25 that resumes operation. The air conditioning control device 40 outputs a start command to the corresponding air conditioning device 35.

次いで、起動対象に関する空調装置35が起動したか否かを判定する処理を行う(S222)。起動対象に関する空調装置35が起動していないと判定された場合(NOの場合)には、移行の可否を判断する処理を中止する。   Next, a process of determining whether or not the air conditioner 35 related to the activation target has been activated is performed (S222). When it is determined that the air conditioner 35 related to the activation target is not activated (in the case of NO), the process for determining whether or not to move is stopped.

起動対象に関する空調装置35が起動したと判定された場合(YESの場合)には、統合制御装置60は、ICT装置25の周辺の温度が所定温度以下であるか否かを判定する処理を行う(S223)。ICT装置25の周辺の温度としては、例えば、ICT装置25の周辺の空気温度、または、空調装置35における吸込み空気温度を例示することができる。この判定では、具体的には次の2条件が満たされているか否かが判定される。1つ目は、起動した空調装置35に異常が発生していないこと。2つ目は、起動した空調装置35が管轄するICT装置25の吸込み部付近(または、架列の間の一部であるコールドアイル(Cold Aisle))の温度が、所定温度以下となっていること。   When it is determined that the air conditioner 35 related to the activation target is activated (in the case of YES), the integrated control device 60 performs a process of determining whether or not the temperature around the ICT device 25 is equal to or lower than a predetermined temperature. (S223). Examples of the temperature around the ICT device 25 include the air temperature around the ICT device 25 or the intake air temperature in the air conditioner 35. In this determination, specifically, it is determined whether or not the following two conditions are satisfied. The first is that no abnormality has occurred in the activated air conditioner 35. Second, the temperature in the vicinity of the suction portion of the ICT device 25 (or cold aisle) that is controlled by the activated air conditioner 35 is equal to or lower than a predetermined temperature. about.

ICT装置25の周辺の温度が所定温度以下になっていないと判定された場合(NOの場合)には、再びS223の判定が行われる。ICT装置25の周辺の温度が所定温度以下になっていると判定された場合(YESの場合)、統合制御装置60は、運転を再開するICT装置25へ電力を供給する電源ユニット11を起動する指令を出力する処理を行う(S231)。具体的には、給電制御装置20へ電源ユニット11を起動する指令を出力する。給電制御装置20は、当該電源ユニット11を起動させる。   When it is determined that the temperature around the ICT device 25 is not lower than the predetermined temperature (in the case of NO), the determination in S223 is performed again. When it is determined that the temperature around the ICT device 25 is equal to or lower than the predetermined temperature (in the case of YES), the integrated control device 60 activates the power supply unit 11 that supplies power to the ICT device 25 that resumes operation. Processing to output a command is performed (S231). Specifically, a command for starting the power supply unit 11 is output to the power supply control device 20. The power supply control device 20 activates the power supply unit 11.

次いで、統合制御装置60は、電源ユニット11が起動したか否かを判定する処理を行う(S232)。判定は次の3条件を満たすか否かにより行われる。1つ目は、給電装置10に異常が発生していないこと。2つ目は、電源ユニット11が正常に起動していること。3つ目は、起動後も電源ユニット11に異常が発生していないこと。電源ユニット11が起動していないと判定された場合(NOの場合)には、アラートを出力する処理が行われる。   Next, the integrated control device 60 performs processing for determining whether or not the power supply unit 11 has been activated (S232). The determination is made based on whether or not the following three conditions are satisfied. The first is that no abnormality has occurred in the power supply apparatus 10. Secondly, the power supply unit 11 has started up normally. Third, no abnormality has occurred in the power supply unit 11 even after startup. When it is determined that the power supply unit 11 is not activated (in the case of NO), processing for outputting an alert is performed.

電源ユニット11が起動していると判定された場合(YESの場合)には、スイッチ16およびスイッチ27AをON状態にする指令を出力する処理が行われる(S241)。具体的には、給電制御装置20へ運転を再開するICT装置25への給電経路上に位置するスイッチ16およびスイッチ27Aに対して、OFF状態からON状態へ移行させる指令を出力する。   When it is determined that the power supply unit 11 is activated (in the case of YES), a process of outputting a command to turn on the switch 16 and the switch 27A is performed (S241). Specifically, a command to shift from the OFF state to the ON state is output to the switch 16 and the switch 27A located on the power supply path to the ICT device 25 that resumes operation to the power supply control device 20.

次いで、統合制御装置60は、スイッチ16およびスイッチ27AがON状態へ移行したか否かを判定する処理を行う(S242)。判定は次の3条件を満たしているか否かにより行われる。1つ目は、スイッチ16およびスイッチ27Aに異常が発生していないこと。2つ目は、スイッチ16およびスイッチ27Aのアウトレットが正常に電源ONになっていること。アウトレットがONになった後も異常が発生していないこと。スイッチ16またはスイッチ27AがOFF状態のままと判定された場合(NOの場合)には、アラートを出力する処理が行われる。   Next, the integrated control device 60 performs a process of determining whether or not the switch 16 and the switch 27A have shifted to the ON state (S242). The determination is made based on whether or not the following three conditions are satisfied. The first is that no abnormality has occurred in the switch 16 and the switch 27A. Second, the outlets of the switch 16 and the switch 27A are normally turned on. No abnormality has occurred after the outlet is turned on. When it is determined that the switch 16 or the switch 27A remains in the OFF state (in the case of NO), processing for outputting an alert is performed.

スイッチ16およびスイッチ27AがON状態へ移行したと判定された場合(YESの場合)、統合制御装置60は、ICT装置25への起動指令を出力する処理を行う(S251)。指令が入力されたICT制御装置30は、ICT装置25の仕様に合わせた起動手順を踏んでICT装置25を起動させる処理を行う。統合制御装置60は、引き続き、縮退運転から分散運転へ移行させるためにICT制御装置30に対して復元処理の開始指示を出力する。ICT制御装置30は、縮退運転から分散運転に必要な手順を踏んで分散運転状態へ移行させる処理を行う。   When it is determined that the switch 16 and the switch 27A have shifted to the ON state (in the case of YES), the integrated control device 60 performs a process of outputting a start command to the ICT device 25 (S251). The ICT control device 30 to which the command has been input performs a process of starting the ICT device 25 according to a startup procedure that matches the specifications of the ICT device 25. The integrated control device 60 continues to output a restoration process start instruction to the ICT control device 30 in order to shift from the degenerate operation to the distributed operation. The ICT control device 30 performs a process of shifting from the degenerate operation to the distributed operation state by following a procedure necessary for the distributed operation.

次いで、統合制御装置60は、ICT装置25(Hostマシン)が起動したか否かを判定する処理を行う(S252)。判定は次の3条件が満たされているか否かにより行われる。1つ目は、対象のICT装置25に管理用NWで接続でき、異常が発生していないこと。2つ目は、対象ICT装置25に管理用NWで接続でき、電源投入が行えること。3つ目は、電源がONされた後も異常が発生することなく起動すること。ICT装置25が起動していないと判定された場合(NOの場合)には、アラートを出力する処理が行われる。   Next, the integrated control device 60 performs processing for determining whether or not the ICT device 25 (Host machine) has been started (S252). The determination is made based on whether or not the following three conditions are satisfied. First, it is possible to connect to the target ICT device 25 using the management NW, and no abnormality has occurred. Second, it can be connected to the target ICT device 25 by a management NW and can be turned on. The third is to start up without any abnormality even after the power is turned on. When it is determined that the ICT device 25 is not activated (in the case of NO), processing for outputting an alert is performed.

ICT装置25が起動していると判定された場合(YESの場合)、統合制御装置60は、ICTリソースの移動(Guestマシンの移動)が行われたか否かを判定する処理を行う(S253)。判定は次の5条件を満たすか否かにより行われる。1つ目は、切替(移動)先のICT装置25である分散先ICT装置25でH/W障害が発生していないこと。2つ目は、切替(移動)元のICT装置25である分散元ICT装置25でH/W障害が発生していないこと。3つ目は、仮想化管理ソフト上で、分散元の仮想Guestマシンが正常であること。4つ目は、分散元の仮想化ソフト上で、移動対象となる仮想Guestマシンが正常であること。5つ目は、分散先のICTリソースに余裕があること。具体的には、CPU使用率が所定値(例えば80%)未満であること、メモリ使用率が所定値(例えば80%)未満であること、および、ハードディスク(HDD)の使用率が所定値(例えば80%)未満であること。   When it is determined that the ICT device 25 is activated (in the case of YES), the integrated control device 60 performs a process of determining whether or not the ICT resource movement (Guest machine movement) has been performed (S253). . The determination is made based on whether or not the following five conditions are satisfied. The first is that no H / W failure has occurred in the distributed ICT device 25 that is the switching (moving) ICT device 25. Second, there is no H / W failure in the distribution source ICT device 25 which is the switching (movement) source ICT device 25. Third, the virtual guest machine of the distribution source is normal on the virtualization management software. Fourth, the virtual guest machine to be moved is normal on the distribution source virtualization software. The fifth is that the ICT resource at the distribution destination has a margin. Specifically, the CPU usage rate is less than a predetermined value (for example, 80%), the memory usage rate is less than a predetermined value (for example, 80%), and the usage rate of the hard disk (HDD) is a predetermined value ( For example, less than 80%).

ICTリソースの移動が行われていないと判定された場合(NOの場合)には、アラートを出力する処理が行われる。ICTリソースの移動が行われていると判定された場合(YESの場合)、統合制御装置60は、照明機器45を点灯させる指令を出力する処理を行う(S261)。   When it is determined that the ICT resource has not been moved (in the case of NO), processing for outputting an alert is performed. When it is determined that the ICT resource has been moved (in the case of YES), the integrated control device 60 performs a process of outputting a command to turn on the lighting device 45 (S261).

次いで、統合制御装置60は、照明機器45が点灯されたか否かを判定する処理を行う(S262)。判定は、給電装置10、ICT装置25、および空調装置35が正常に起動し、異常が発生していないか否かにより行われる。   Next, the integrated control device 60 performs a process of determining whether or not the lighting device 45 is turned on (S262). The determination is made based on whether or not the power supply device 10, the ICT device 25, and the air conditioner 35 are normally activated and no abnormality has occurred.

照明機器45が点灯されていないと判定された場合(NOの場合)には、アラートを出力する処理が行われる。照明機器45が点灯されていると判定された場合(YESの場合)、縮退運転から分散運転への復元を実行する処理は終了される。   When it is determined that the lighting device 45 is not turned on (in the case of NO), processing for outputting an alert is performed. When it is determined that the lighting device 45 is turned on (in the case of YES), the process for executing restoration from the degenerate operation to the distributed operation is ended.

なお、縮退運転から分散運転へ移行する復元処理においては、必要に応じてSDN(software defined network)技術、NFV(Network Function Virtualization)技術やロードバランサーなどのネットワーク制御、負荷制御を行う場合もある。また、移行プロセス途中において、不要な警報が発生する場合には、警報を一時的にマスクする措置を講ずることも可能である。   In the restoration process for shifting from the degenerate operation to the distributed operation, network control and load control such as SDN (software defined network) technology, NFV (Network Function Virtualization) technology, load balancer, and the like may be performed as necessary. Also, if an unnecessary alarm occurs during the transition process, it is possible to take measures to temporarily mask the alarm.

上記の構成の給電システム1によれば、取得した社員の入退情報や、ICT装置25等の情報に基づいてICT装置25における演算等の情報処理量を推定し、推定した演算等の情報処理量に応じてICT装置25による電力消費量の削減、および、空調装置35による電力消費量の削減の優先順位を定めて全体の消費電力の削減を図ることができる。そのため、例えば、ICT装置25による削減と、空調装置35による削減の優先順位を定めず、それぞれが連係を取らずに消費電力の削減を図る場合と比較して消費電力の削減量を確保しやすくなる。または、ICT装置25における演算等の情報処理に与える影響を抑制しつつ、消費電力の削減を図りやすくなる。   According to the power supply system 1 having the above-described configuration, the information processing amount such as calculation in the ICT device 25 is estimated based on the acquired employee entry / exit information and information such as the ICT device 25, and information processing such as the estimated calculation is performed. According to the amount, the power consumption by the ICT device 25 and the power consumption by the air conditioner 35 can be prioritized to reduce the overall power consumption. Therefore, for example, priority is not given to reduction by the ICT device 25 and reduction by the air conditioner 35, and it is easy to secure a reduction amount of power consumption compared to a case where each reduces power consumption without being linked. Become. Or it becomes easy to aim at reduction of power consumption, suppressing the influence which it has on information processing, such as calculation in the ICT apparatus 25. FIG.

ICT装置25による削減の優先順位を空調装置35による削減よりも上位とすることにより、ICT装置25における演算等の情報処理に与える影響を抑制しつつ、消費電力の削減を図ることができる。一般的に、ICT装置25における消費電力量は、ICT装置25における演算等の情報処理との間に関連性が存在する。そこで、ICT装置25による削減を優先することにより、ICT装置25における演算等の情報処理に与える影響と、消費電力の削減との間のバランスを図り易くなる。   By making the priority of reduction by the ICT device 25 higher than the reduction by the air conditioner 35, it is possible to reduce power consumption while suppressing the influence on the information processing such as calculation in the ICT device 25. In general, the power consumption in the ICT device 25 is related to information processing such as computation in the ICT device 25. Therefore, by giving priority to the reduction by the ICT device 25, it becomes easy to achieve a balance between the influence on the information processing such as calculation in the ICT device 25 and the reduction of power consumption.

給電装置10における消費電力の削減を更に行うことにより、ICT装置25による削減、および、空調装置35による削減のみを行う場合と比較して、消費電力の削減量を増やしやすくなる。   By further reducing the power consumption in the power supply apparatus 10, it becomes easier to increase the amount of power consumption compared to the case where only the reduction by the ICT apparatus 25 and the reduction by the air conditioner 35 are performed.

さらに、空調装置35による削減およびICT装置25による削減の優先順位を、給電装置10における削減よりも上位とすることにより、消費電力の削減量を確保しやすくなる。つまり、情報通信設備の中でICT装置25に次いで消費電力が多い空調装置35に注目し、より効率的な運転による削減判断処理をICT装置25による削減判断より優先することにより、消費電力の削減量を確保しやすくなる。   Furthermore, the priority of reduction by the air conditioner 35 and reduction by the ICT device 25 is set higher than the reduction in the power supply device 10, so that it becomes easy to secure a reduction in power consumption. That is, in the information communication equipment, paying attention to the air conditioner 35 that consumes the second most power after the ICT device 25, and prioritizing the reduction judgment process by more efficient operation over the reduction judgment by the ICT device 25, the power consumption can be reduced. It becomes easy to secure the amount.

パラメータに社員の入退情報やICT装置25の情報を含めることにより、ICT装置25における演算等の情報処理量を推定しやすくなる。例えば、社員がICT装置25の利用端末が配置された建物に入館している場合には、当該社員がICT装置25を利用する可能性が高いと考えられる。そのため、これら情報に基づくことにより、ICT装置25における演算等の情報処理量を推定しやすくなる。また、社員によるICT装置25の利用状況が同じであっても、ICT装置25の種類や他の演算等の情報処理量の状況に応じて、ICT装置25における演算等の情報処理量が異なると考えられる。そのため、これら情報に基づくことにより、ICT装置25における演算等の情報処理量を推定しやすくなる。   By including employee entry / exit information and information of the ICT device 25 in the parameters, it becomes easy to estimate the amount of information processing such as computation in the ICT device 25. For example, when an employee enters a building where a terminal for using the ICT device 25 is placed, it is considered that the employee is likely to use the ICT device 25. Therefore, based on these pieces of information, it becomes easy to estimate the amount of information processing such as computation in the ICT device 25. Further, even if the use status of the ICT device 25 by the employee is the same, the amount of information processing such as computation in the ICT device 25 differs depending on the type of the ICT device 25 and the status of information processing amount such as other computations. Conceivable. Therefore, based on these pieces of information, it becomes easy to estimate the amount of information processing such as computation in the ICT device 25.

〔第2の実施形態〕
次に、本発明の第2の実施形態について図7を参照して説明する。本実施形態の給電システムの基本構成は、第1の実施形態と同様であるが、第1の実施形態とは、給電システムにおける制御が異なっている。よって、本実施形態においては、図7を用いて異なる制御について説明し、給電システムの構成等の説明を省略する。
[Second Embodiment]
Next, a second embodiment of the present invention will be described with reference to FIG. The basic configuration of the power supply system of this embodiment is the same as that of the first embodiment, but the control in the power supply system is different from that of the first embodiment. Therefore, in this embodiment, different control will be described using FIG. 7, and description of the configuration of the power feeding system and the like will be omitted.

本実施形態の給電システム1における制御について説明する。本実施形態では、社員の位置情報、社員のスケジュール情報、社員の座席情報およびICT装置25等の情報に基づく給電システム1の統合連係制御について説明する。   Control in the power supply system 1 of the present embodiment will be described. In the present embodiment, a description will be given of the integrated linkage control of the power feeding system 1 based on information on employee position information, employee schedule information, employee seat information, ICT device 25, and the like.

具体的には、縮退運転を実行する際の制御処理について図7のフローチャートを参照しながら説明する。はじめに統合制御装置60の取得部64は、記憶部66から社員の位置情報を取得する処理を実行する(S311:取得ステップ)。次いで、追加情報を取得する処理を実行する(S312:取得ステップ)。ここで、追加情報は、記憶部67に記憶された社員のスケジュール情報、社員の座席情報、および、ICTリソース情報を例示することができる。   Specifically, the control process when executing the degenerate operation will be described with reference to the flowchart of FIG. First, the acquisition unit 64 of the integrated control device 60 executes a process of acquiring employee position information from the storage unit 66 (S311: acquisition step). Subsequently, the process which acquires additional information is performed (S312: acquisition step). Here, the additional information can exemplify employee schedule information, employee seat information, and ICT resource information stored in the storage unit 67.

これらの情報を取得すると、統合制御装置60は、縮退運転を実行した場合に消費電力の削減効果があるか否かを判定する処理を行う(S313)。消費電力の削減効果がないと判定された場合(NOの場合)には、演算処理部61は縮退運転の可否を判断する処理を中止する。   Upon acquiring these pieces of information, the integrated control device 60 performs a process of determining whether or not there is an effect of reducing power consumption when the degenerate operation is executed (S313). When it is determined that there is no power consumption reduction effect (in the case of NO), the arithmetic processing unit 61 stops the process of determining whether or not the degenerate operation is possible.

なお、消費電力の削減効果の判定には、上述の社員の位置情報、社員のスケジュール情報、社員の座席情報、および、ICTリソース情報に基づいて行われる。例えば、社員の位置情報および社員の座席情報に基づいて、社員が座席に着席しているか否かの推定が行われ、社員が着席している場合にはICT装置25において演算等の情報処理が要求される可能性が高いと推定することができる。   Note that the effect of reducing the power consumption is determined based on the above-described employee position information, employee schedule information, employee seat information, and ICT resource information. For example, based on the position information of the employee and the seat information of the employee, it is estimated whether or not the employee is seated. When the employee is seated, the ICT device 25 performs information processing such as calculation. It can be estimated that there is a high possibility of being required.

また、社員のスケジュール情報に基づくと、当該社員がその時間帯にICT装置25を利用するか否か、ICT装置25を利用する場合には演算等の情報処理量を推定することができる。これらの推定した演算等の情報処理量とICTリソース情報とに基づくことにより、ICT装置25の稼働率などを推定することもできる。このような推定に基づいて、縮退運転を実行した場合に消費電力の削減効果があるか否かを求めることができる。   Further, based on the schedule information of the employee, it is possible to estimate whether the employee uses the ICT device 25 during the time period, and when the ICT device 25 is used, the amount of information processing such as calculation can be estimated. Based on the information processing amount such as the estimated calculation and the ICT resource information, the operating rate of the ICT device 25 can be estimated. Based on such estimation, it can be determined whether or not there is an effect of reducing power consumption when the degenerate operation is executed.

消費電力の削減効果があると判定された場合(YESの場合)には、演算処理部61は制御の優先順位を判定する処理を行う(S314:優先処理ステップ)。本実施形態では、ICT装置25による削減制御と、空調装置35による削減制御との間の優先順位を判定する処理が行われる。具体的には、ICT装置25による削減制御が、空調装置35による削減制御よりも優先されるか否かを判定する処理を行う。   When it is determined that there is an effect of reducing power consumption (in the case of YES), the arithmetic processing unit 61 performs processing for determining the priority of control (S314: priority processing step). In the present embodiment, processing for determining the priority between the reduction control by the ICT device 25 and the reduction control by the air conditioner 35 is performed. Specifically, a process for determining whether or not the reduction control by the ICT device 25 has priority over the reduction control by the air conditioner 35 is performed.

予測処理部63は、社員の位置情報、社員のスケジュール情報、社員の座席情報、および、ICTリソース情報に基づいてICT装置25における演算等の情報処理量を推定する演算処理を行う。推定された演算等の情報処理量が増加する場合には、演算処理部61はICT装置25による削減制御を優先するとの判定を行う(YES)。その一方で、推定された演算等の情報処理量が増加しない場合には、空調装置35による削減制御を優先するとの判定を行う(NO)。   The prediction processing unit 63 performs calculation processing for estimating an information processing amount such as calculation in the ICT device 25 based on employee position information, employee schedule information, employee seat information, and ICT resource information. When the amount of information processing such as the estimated calculation increases, the calculation processing unit 61 determines that priority is given to reduction control by the ICT device 25 (YES). On the other hand, if the amount of information processing such as the estimated calculation does not increase, it is determined that priority is given to reduction control by the air conditioner 35 (NO).

S314の判定においてICT装置25による削減制御を優先すると判定された場合(YESの場合)、演算処理部61は、ICT装置25等に障害が発生していないか否か、または運用に支障が出るか否かを判定する処理を行う(S15)。以降の制御は第1の実施形態と同様であるため、図7のフローチャートに図示を行い、その説明を省略する。また、S314の判定において空調装置35による削減制御を優先するとの判定と判定された場合(NOの場合)におけるその後の制御についても、第1の実施形態と同様であるため、その説明を省略する。   If it is determined in S314 that priority is given to the reduction control by the ICT device 25 (in the case of YES), the arithmetic processing unit 61 determines whether or not a failure has occurred in the ICT device 25 or the like, or hinders operation. The process which determines whether or not is performed (S15). Since the subsequent control is the same as that of the first embodiment, the flowchart is shown in FIG. 7 and the description thereof is omitted. Moreover, since it is the same as that of 1st Embodiment also about the subsequent control in the case of determining with priority to the reduction control by the air conditioner 35 in determination of S314 (in the case of NO), the description is abbreviate | omitted. .

上記の構成の給電システム1によれば、パラメータとしてスケジュール情報やカレンダ情報を含めることにより、ICT装置25における演算等の情報処理量を推定しやすくなる。例えば、ICT装置25の社員は、平日にICT装置25を利用し、休日や祭日にはICT装置25を利用しない傾向にある場合があり、さらに、社員が所属する組織のスケジュールに応じてICT装置25の利用頻度が変動する場合がある。このような事情に基づくことにより、ICT装置25における演算等の情報処理量を推定しやすくなる。   According to the power supply system 1 having the above configuration, it is easy to estimate the amount of information processing such as computation in the ICT device 25 by including schedule information and calendar information as parameters. For example, the employee of the ICT device 25 may tend to use the ICT device 25 on weekdays and not to use the ICT device 25 on holidays or holidays. Further, the ICT device 25 may be used according to the schedule of the organization to which the employee belongs. The usage frequency of 25 may vary. Based on such circumstances, it becomes easy to estimate the amount of information processing such as computation in the ICT device 25.

パラメータを社員の位置情報および座席位置情報とすることにより、ICT装置25における演算等の情報処理量を推定しやすくなる。例えば、社員の位置が、ICT装置25の利用端末が配置された座席位置の近傍である場合には、当該社員がICT装置25を利用する可能性が高いと考えられる。そのため、これら情報に基づくことにより、ICT装置25における作業負荷量を推定しやすくなる。   By making the parameters position information and seat position information of the employee, it becomes easy to estimate the amount of information processing such as calculation in the ICT device 25. For example, when the position of the employee is in the vicinity of the seat position where the use terminal of the ICT device 25 is arranged, it is considered that the employee is likely to use the ICT device 25. Therefore, based on these pieces of information, the workload amount in the ICT device 25 can be easily estimated.

〔第3の実施形態〕
次に、本発明の第3の実施形態について図8を参照して説明する。本実施形態の給電システムの基本構成は、第1の実施形態と同様であるが、第1の実施形態とは、給電システムにおける制御が異なっている。よって、本実施形態においては、図8を用いて異なる制御について説明し、給電システムの構成等の説明を省略する。
[Third Embodiment]
Next, a third embodiment of the present invention will be described with reference to FIG. The basic configuration of the power supply system of the present embodiment is the same as that of the first embodiment, but the control in the power supply system is different from that of the first embodiment. Therefore, in the present embodiment, different control will be described using FIG. 8 and description of the configuration of the power feeding system and the like will be omitted.

本実施形態の給電システム1における制御について説明する。本実施形態では、交通情報、社員のスケジュール情報、入退情報およびICT装置25等の情報に基づく給電システム1の統合連係制御について説明する。   Control in the power supply system 1 of the present embodiment will be described. In the present embodiment, the integrated linkage control of the power feeding system 1 based on information such as traffic information, employee schedule information, entry / exit information, and the ICT device 25 will be described.

具体的には、縮退運転を実行する際の制御処理について図8のフローチャートを参照しながら説明する。はじめに統合制御装置60の取得部64は、記憶部68から交通情報を取得する処理を実行する(S411)。ここで取得する交通情報として鉄道会社やバス会社などの公共交通機関から発表される遅延情報を例示することができる。   Specifically, the control process when executing the degenerate operation will be described with reference to the flowchart of FIG. First, the acquisition unit 64 of the integrated control device 60 executes a process of acquiring traffic information from the storage unit 68 (S411). Examples of the traffic information acquired here include delay information announced by public transportation such as a railway company and a bus company.

次いで取得部64は、記憶部67から社員のスケジュール情報を取得する処理を実行する(S412)。さらに、入退管理装置65から社員の入退情報を取得する処理を実行し(S413)、ICTリソース情報を取得する処理を実行する(S414)。   Next, the acquisition unit 64 executes a process of acquiring employee schedule information from the storage unit 67 (S412). Further, a process of acquiring employee entry / exit information from the entry / exit management device 65 is executed (S413), and a process of acquiring ICT resource information is executed (S414).

これらの情報を取得すると、統合制御装置60の演算処理部61は、縮退運転を実行した場合に消費電力の削減効果があるか否かを判定する処理を行う(S415)。消費電力の削減効果がないと判定された場合(NOの場合)には、演算処理部61は縮退運転の可否を判断する処理を中止する。消費電力の削減効果があると判定された場合(YESの場合)には、演算処理部61は縮退運転を実行する制御処理を継続する(S416)。   When these pieces of information are acquired, the arithmetic processing unit 61 of the integrated control device 60 performs processing for determining whether or not there is an effect of reducing power consumption when the degenerate operation is executed (S415). When it is determined that there is no power consumption reduction effect (in the case of NO), the arithmetic processing unit 61 stops the process of determining whether or not the degenerate operation is possible. When it is determined that there is an effect of reducing power consumption (in the case of YES), the arithmetic processing unit 61 continues the control process for executing the degenerate operation (S416).

なお、消費電力の削減効果の判定には、上述の交通情報(例えば遅延情報)、社員のスケジュール情報、入退情報およびICT装置25等の情報に基づいて行われる。例えば、遅延情報に基づいて、社員が始業時間に出勤しているか否かの推定が行われ、社員が始業時間に出勤している場合にはICT装置25において演算等の情報処理が要求される可能性が高いと推定することができる。また、社員のスケジュール情報に基づくと、当該社員の始業時間が不規則な場合であっても、ICT装置25において演算等の情報処理が要求される可能性の推定精度が悪化することが抑制できる。これらの推定した演算等の情報処理量とICTリソース情報とに基づくことにより、ICT装置25の稼働率などを推定することもできる。このような推定に基づいて、縮退運転を実行した場合に消費電力の削減効果があるか否かを求めることができる。   The power consumption reduction effect is determined based on the above-described traffic information (for example, delay information), employee schedule information, entry / exit information, ICT device 25, and the like. For example, based on the delay information, it is estimated whether or not the employee is working at the start time. When the employee is at the start time, information processing such as calculation is required in the ICT device 25. It can be estimated that the possibility is high. Further, based on the schedule information of the employee, even if the start time of the employee is irregular, it can be suppressed that the estimation accuracy of the possibility that information processing such as calculation is required in the ICT device 25 is deteriorated. . Based on the information processing amount such as the estimated calculation and the ICT resource information, the operating rate of the ICT device 25 can be estimated. Based on such estimation, it can be determined whether or not there is an effect of reducing power consumption when the degenerate operation is executed.

上記の構成の給電システム1によれば、パラメータを交通情報とすることにより、ICT装置25における演算等の情報処理量を推定しやすくなる。例えば、遅延などにより交通手段の確保が困難な場合などには、ICT装置25の利用者の出勤が困難であることが予想され、ICT装置25における演算等の情報処理量が減少することが推定される。   According to the power supply system 1 having the above-described configuration, the information processing amount such as the calculation in the ICT device 25 can be easily estimated by using the parameter as traffic information. For example, when it is difficult to secure transportation means due to a delay or the like, it is predicted that it is difficult for the user of the ICT device 25 to go to work, and it is estimated that the amount of information processing such as computation in the ICT device 25 decreases. Is done.

〔第4の実施形態〕
次に、本発明の第4の実施形態について図9を参照して説明する。本実施形態の給電システムの基本構成は、第1の実施形態と同様であるが、第1の実施形態とは、給電システムにおける制御が異なっている。よって、本実施形態においては、図9を用いて異なる制御について説明し、給電システムの構成等の説明を省略する。
[Fourth Embodiment]
Next, a fourth embodiment of the present invention will be described with reference to FIG. The basic configuration of the power supply system of this embodiment is the same as that of the first embodiment, but the control in the power supply system is different from that of the first embodiment. Therefore, in the present embodiment, different control will be described using FIG. 9 and description of the configuration of the power feeding system and the like will be omitted.

本実施形態の給電システム1における制御について説明する。本実施形態では、気象情報およびICT装置25等の情報に基づく給電システム1の統合連係制御に関して、分散運転を継続するか否かの判断がさらに行われる。   Control in the power supply system 1 of the present embodiment will be described. In this embodiment, regarding the integrated linkage control of the power feeding system 1 based on weather information and information such as the ICT device 25, it is further determined whether to continue the distributed operation.

具体的には、分散運転を継続するか否かの判断を行う際の制御処理について図9のフローチャートを参照しながら説明する。はじめに統合制御装置60の取得部64は、記憶部68から気象情報を取得する処理を実行する(S511)。ここで取得する気象情報としては、気象庁から発表される各種の特別警報を例示することができる。次いで、取得部64は、ICTリソース情報および警報情報を取得する処理を実行する(S512)。   Specifically, a control process for determining whether to continue the distributed operation will be described with reference to the flowchart of FIG. First, the acquisition unit 64 of the integrated control device 60 executes a process of acquiring weather information from the storage unit 68 (S511). Examples of the weather information acquired here include various special warnings announced by the Japan Meteorological Agency. Next, the acquisition unit 64 executes processing for acquiring ICT resource information and alarm information (S512).

これらの情報を取得すると、統合制御装置60の演算処理部61は、分散運転を継続した場合に問題がないか否かを判定する処理を行う(S513)。S513における判定の処理を行う際に用いられる演算等の情報処理量を推定する際に、取得した気象情報およびICT装置25等の情報が用いられる。なお、問題がないか否かの判定としては、例えば、第1の実施形態におけるS14からS18までの一連の判定などを挙げることができる。   When these pieces of information are acquired, the arithmetic processing unit 61 of the integrated control device 60 performs a process of determining whether there is no problem when the distributed operation is continued (S513). The acquired weather information and information such as the ICT device 25 are used when estimating the information processing amount such as the calculation used when performing the determination process in S513. In addition, as determination of whether there is no problem, for example, a series of determinations from S14 to S18 in the first embodiment can be cited.

S513における判定において問題があると判定された場合(NOの場合)には、演算処理部61は分散運転継続の可否を判断する処理を中止する。問題がないと判定された場合(YESの場合)には、演算処理部61は分散運転を継続する制御処理を継続する(S514)。   When it is determined that there is a problem in the determination in S513 (in the case of NO), the arithmetic processing unit 61 stops the process of determining whether or not to continue the distributed operation. When it is determined that there is no problem (in the case of YES), the arithmetic processing unit 61 continues the control process for continuing the distributed operation (S514).

〔第5の実施形態〕
次に、本発明の第5の実施形態について図10を参照して説明する。本実施形態の給電システムの基本構成は、第1の実施形態と同様であるが、第1の実施形態とは、給電システムにおける制御が異なっている。よって、本実施形態においては、図10を用いて異なる制御について説明し、給電システムの構成等の説明を省略する。
[Fifth Embodiment]
Next, a fifth embodiment of the present invention will be described with reference to FIG. The basic configuration of the power supply system of the present embodiment is the same as that of the first embodiment, but the control in the power supply system is different from that of the first embodiment. Therefore, in the present embodiment, different control will be described using FIG. 10 and description of the configuration of the power feeding system and the like will be omitted.

本実施形態の給電システム1における制御について説明する。本実施形態では、気象情報、社員のスケジュール情報、入退情報およびICT装置25等の情報に基づく給電システム1の統合連係制御に関して、分散運転を継続するか否かの判断がさらに行われる。   Control in the power supply system 1 of the present embodiment will be described. In the present embodiment, regarding the integrated linkage control of the power supply system 1 based on information such as weather information, employee schedule information, entrance / exit information, and the ICT device 25, it is further determined whether to continue the distributed operation.

具体的には、分散運転を継続するか否かの判断を行う際の制御処理について図10のフローチャートを参照しながら説明する。はじめに統合制御装置60の取得部64は、記憶部68から気象情報として大規模地震情報を取得する処理を実行する(S611)。   Specifically, the control process for determining whether to continue the distributed operation will be described with reference to the flowchart of FIG. First, the acquisition unit 64 of the integrated control device 60 executes a process of acquiring large-scale earthquake information as weather information from the storage unit 68 (S611).

次いで取得部64は、記憶部67から社員のスケジュール情報を取得する処理を実行する(S612)。さらに、入退管理装置65から社員の入退情報を取得する処理を実行し(S613)、ICTリソース情報を取得する処理を実行する(S614)。   Next, the acquisition unit 64 executes processing for acquiring employee schedule information from the storage unit 67 (S612). Furthermore, a process of acquiring employee entry / exit information from the entry / exit management device 65 is executed (S613), and a process of acquiring ICT resource information is executed (S614).

これらの情報を取得すると、統合制御装置60の演算処理部61は、分散運転を継続して問題がないか否かを判定する処理を行う(S615)。分散運転を継続して問題があると判定された場合(NOの場合)には、演算処理部61は分散運転の継続を判断する処理を中止する。分散運転を継続して問題がないと判定された場合(YESの場合)には、演算処理部61は縮退運転を実行する制御処理を継続する(S616)。   When these pieces of information are acquired, the arithmetic processing unit 61 of the integrated control device 60 performs a process of determining whether there is no problem by continuing the distributed operation (S615). When it is determined that there is a problem by continuing the distributed operation (in the case of NO), the arithmetic processing unit 61 stops the process for determining the continuation of the distributed operation. When it is determined that there is no problem by continuing the distributed operation (in the case of YES), the arithmetic processing unit 61 continues the control process for executing the degenerate operation (S616).

上記の構成の給電システム1によれば、パラメータとして気象情報を含めることにより、ICT装置25における演算等の情報処理量を推定しやすくなる。例えば、特別警報が発表されるような悪天候の場合などには、ICT装置25を利用する社員の出勤が困難であることが予想され、ICT装置25における演算等の情報処理量が減少することが推定される。   According to the power feeding system 1 having the above configuration, it is easy to estimate the amount of information processing such as computation in the ICT device 25 by including weather information as a parameter. For example, in the case of bad weather such as when a special warning is announced, it is predicted that it is difficult for employees who use the ICT device 25 to go to work, and the amount of information processing such as calculations in the ICT device 25 may decrease. Presumed.

〔第6の実施形態〕
次に、本発明の第6の実施形態について図11を参照して説明する。本実施形態の給電システムの基本構成は、第1の実施形態と同様であるが、第1の実施形態とは、給電システムにおける制御が異なっている。よって、本実施形態においては、図11を用いて異なる制御について説明し、給電システムの構成等の説明を省略する。
[Sixth Embodiment]
Next, a sixth embodiment of the present invention will be described with reference to FIG. The basic configuration of the power supply system of the present embodiment is the same as that of the first embodiment, but the control in the power supply system is different from that of the first embodiment. Therefore, in the present embodiment, different control will be described using FIG. 11 and description of the configuration of the power feeding system and the like will be omitted.

本実施形態の給電システム1における制御について説明する。本実施形態では、気象情報、交通情報、社員のスケジュール情報、入退情報およびICT装置25等の情報に基づく給電システム1の統合連係制御に関して、縮退運転を継続するか否かの判断がさらに行われる。   Control in the power supply system 1 of the present embodiment will be described. In the present embodiment, regarding the integrated linkage control of the power feeding system 1 based on weather information, traffic information, employee schedule information, entrance / exit information, and information such as the ICT device 25, it is further determined whether or not to continue the reduced operation. Is called.

具体的には、縮退運転を継続するか否かの判断を行う際の制御処理について図11のフローチャートを参照しながら説明する。はじめに統合制御装置60の取得部64は、記憶部68から気象情報を取得する処理を実行する(S711)。ここで取得する気象情報としては、気象庁から発表される各種の特別警報を例示することができる。   Specifically, a control process for determining whether to continue the degenerate operation will be described with reference to the flowchart of FIG. First, the acquisition unit 64 of the integrated control device 60 executes a process of acquiring weather information from the storage unit 68 (S711). Examples of the weather information acquired here include various special warnings announced by the Japan Meteorological Agency.

次いで、記憶部68から交通情報を取得する処理を実行する(S712)。ここで取得する交通情報として鉄道会社やバス会社などの公共交通機関から発表される遅延情報を例示することができる。   Subsequently, the process which acquires traffic information from the memory | storage part 68 is performed (S712). Examples of the traffic information acquired here include delay information announced by public transportation such as a railway company and a bus company.

その後、取得部64は、記憶部67から社員のスケジュール情報を取得する処理を実行する(S713)。さらに、入退管理装置65から社員の入退情報を取得する処理を実行し(S714)、ICTリソース情報および警報情報を取得する処理を実行する(S715)。   Thereafter, the acquisition unit 64 executes a process of acquiring employee schedule information from the storage unit 67 (S713). Furthermore, the process which acquires the employee's entrance / exit information from the entrance / exit management apparatus 65 is performed (S714), and the process which acquires ICT resource information and alarm information is performed (S715).

これらの情報を取得すると、統合制御装置60の演算処理部61は、縮退運転を実行した場合に問題がないか否かを判定する処理を行う(S716)。S716における判定の処理を行う際に用いられる演算等の情報処理量を推定する際に、取得した気象情報、交通情報、社員のスケジュール情報、入退情報およびICT装置25等の情報が用いられる。なお、問題がないか否かの判定としては、例えば、第1の実施形態におけるS14からS18までの一連の判定などを挙げることができる。   When these pieces of information are acquired, the arithmetic processing unit 61 of the integrated control device 60 performs a process of determining whether or not there is a problem when the degenerate operation is executed (S716). Information such as the acquired weather information, traffic information, employee schedule information, entrance / exit information, and the ICT device 25 is used when estimating the amount of information processing such as computation used when performing the determination process in S716. In addition, as determination of whether there is no problem, for example, a series of determinations from S14 to S18 in the first embodiment can be cited.

S716における判定において問題があると判定された場合(NOの場合)には、演算処理部61は縮退運転の可否を判断する処理を中止する。問題がないと判定された場合(YESの場合)には、演算処理部61は縮退運転を実行する制御処理を継続する(S717)。   When it is determined that there is a problem in the determination in S716 (in the case of NO), the arithmetic processing unit 61 stops the process of determining whether or not the degenerate operation is possible. When it is determined that there is no problem (in the case of YES), the arithmetic processing unit 61 continues the control process for executing the degenerate operation (S717).

〔第7の実施形態〕
次に、本発明の第7の実施形態について図12から図14を参照して説明する。本実施形態の給電システムの基本構成は、第1の実施形態と同様であるが、第1の実施形態とは、給電システムにおける制御が異なっている。よって、本実施形態においては、図12および図13を用いて異なる制御について説明し、給電システムの構成等の説明を省略する。
[Seventh Embodiment]
Next, a seventh embodiment of the present invention will be described with reference to FIGS. The basic configuration of the power supply system of this embodiment is the same as that of the first embodiment, but the control in the power supply system is different from that of the first embodiment. Therefore, in this embodiment, different control is demonstrated using FIG. 12 and FIG. 13, and description, such as a structure of an electric power feeding system, is abbreviate | omitted.

ここでは、本実施形態の給電システム1の特徴である制御について説明する。本実施形態では、ICT装置優先モードおよび空調優先モードのいずれを優先するか優先順位を判定する処理がさらに行われることが上述の他の実施形態と異なっている。   Here, the control which is the characteristic of the electric power feeding system 1 of this embodiment is demonstrated. The present embodiment is different from the other embodiments described above in that a process for determining the priority order of which one of the ICT device priority mode and the air conditioning priority mode is prioritized is further performed.

まず、縮退運転を実行する際の制御処理について、図12を参照しながら説明する。制御処理が開始されると、統合制御装置60は制御優先順位を判定する処理を行う(S800)。具体的には、ICT装置25による削減制御を優先するICT装置優先モード、および、空調装置35による削減制御を優先する空調優先モードのいずれかを選択するか判定する図13に示すサブルーチンの処理が行わる。   First, the control process when executing the degenerate operation will be described with reference to FIG. When the control process is started, the integrated control device 60 performs a process of determining the control priority (S800). Specifically, the subroutine processing shown in FIG. 13 determines whether to select either the ICT device priority mode that prioritizes the reduction control by the ICT device 25 or the air conditioning priority mode that prioritizes the reduction control by the air conditioning device 35. To do.

制御優先順位を判定するサブルーチンの処理の詳細について、図13を参照しながら説明する。上記サブルーチンの処理が開始されると、統合制御装置60の取得部64は、情報を取得する処理を行う(S801)。ここで取得される情報は、ICT装置25の負荷率情報、電力消費情報および位置情報、並びに、空調装置35の運転情報などが挙げられる。   Details of the subroutine processing for determining the control priority will be described with reference to FIG. When the processing of the subroutine is started, the acquisition unit 64 of the integrated control device 60 performs processing for acquiring information (S801). Examples of the information acquired here include load factor information of the ICT device 25, power consumption information and position information, and operation information of the air conditioner 35.

情報の取得が行われると、演算処理部61は空調ゾーンごとの負荷率を算出する処理を行う(S802)。空調ゾーンとは、空調装置35によって室温の調整が行われる領域のことである。空調ゾーンは、空調装置35やICT装置25の配置や、空調装置35から吹出される空気の風速、風量、向きなどに応じて変化するものである。本実施形態では、それぞれの空調装置35について測定を行い、空調ゾーンを予め把握している例に適用して説明する。   When the information is acquired, the arithmetic processing unit 61 performs a process of calculating a load factor for each air conditioning zone (S802). The air conditioning zone is an area where the room temperature is adjusted by the air conditioner 35. The air conditioning zone changes according to the arrangement of the air conditioner 35 and the ICT device 25, the wind speed, the air volume, the direction of the air blown from the air conditioner 35, and the like. In the present embodiment, description will be made by applying to an example in which each air conditioner 35 is measured and the air conditioning zone is grasped in advance.

本実施形態では、負荷率を算出する方法を次に記載する例に適用して説明する。つまり、空調ゾーンごとの負荷率は、位置情報に基づいてICT装置25を空調ゾーン毎に紐付けし、それぞれの空調ゾーンに紐付けされたICT装置25の負荷率情報に基づいて算出される。空調ゾーンごとの負荷率は、空調ゾーンに紐付けされた複数のICT装置25の負荷率情報に基づく平均値であってもよいし、中央値、最頻値、最大値、最小値などの他の値であってもよく、特に限定するものではない。   In the present embodiment, a method for calculating a load factor will be described by applying it to an example described below. That is, the load factor for each air conditioning zone is calculated based on the load factor information of the ICT device 25 associated with each air conditioning zone by associating the ICT device 25 with each air conditioning zone based on the position information. The load factor for each air conditioning zone may be an average value based on the load factor information of a plurality of ICT devices 25 linked to the air conditioning zone, or may be other than the median value, mode value, maximum value, minimum value, etc. It may be a value of and is not particularly limited.

空調ゾーンごとの負荷率が算出されると、演算処理部61は、低負荷ゾーンが存在するか否かを判定する処理を行う(S803)。本実施形態では、予め定められた負荷率の閾値と、空調ゾーンごとの負荷率とを比較することにより、低負荷ゾーンが存在するか否かが判定される例に適用して説明する。   When the load factor for each air conditioning zone is calculated, the arithmetic processing unit 61 performs a process of determining whether or not a low load zone exists (S803). In the present embodiment, description will be made by applying to an example in which it is determined whether or not a low load zone exists by comparing a threshold value of a predetermined load factor with a load factor for each air conditioning zone.

S803の判定処理において低負荷ゾーンが存在しないと判定された場合(NOの場合)には、演算処理部61は、設定をICT装置優先モードとする処理を行う(S804)。その後、演算処理部61によるサブルーチンの処理が終了し、処理は図12のフローチャートに移行する。   If it is determined in the determination process of S803 that there is no low load zone (in the case of NO), the arithmetic processing unit 61 performs a process of setting the ICT device priority mode (S804). Thereafter, the subroutine processing by the arithmetic processing unit 61 ends, and the processing shifts to the flowchart of FIG.

S803の判定処理において低負荷ゾーンが存在すると判定された場合(YESの場合)には、演算処理部61は、低負荷ゾーンのICT装置25からその他のゾーンのICT装置25に負荷の処理の移行が可能か否かを判定する処理を行う(S805)。   When it is determined in the determination process of S803 that a low load zone exists (in the case of YES), the arithmetic processing unit 61 transfers the load process from the ICT device 25 in the low load zone to the ICT device 25 in the other zone. Processing for determining whether or not is possible is performed (S805).

ここで行う判定処理の具体的な内容は、第1の実施形態におけるS15のICT装置25等に障害が発生していないか否か、または運用に支障が出るか否かの判定処理、S16のICT装置25のリソースに余裕があるか否かの判定処理、S17の給電装置10やスイッチ16やスイッチ27Aの容量に余裕があるか否かの判定処理、S18の空調能力に余裕があるか否かの判定処理等と同様であるため、その説明を省略する。   The specific contents of the determination processing performed here are determination processing for determining whether or not a failure has occurred in the ICT device 25 or the like of S15 in the first embodiment, or whether or not the operation will be hindered, Processing for determining whether or not the resources of the ICT device 25 have a margin, processing for determining whether or not the capacity of the power supply device 10, the switch 16, and the switch 27A in S17 is sufficient, and whether or not the air conditioning capability in S18 has margin Since this is the same as the determination processing, the description thereof is omitted.

S805の判定処理において、負荷の処理の移行が可能と判定された場合(YESの場合)には、演算処理部61は、この移行により消費電力が減少するか否かを判定する処理を行う(S806)。具体的には、低負荷ゾーンに位置するICT装置25で負荷の処理を続けた場合に消費される電力と、その他のゾーンに位置するICT装置25に負荷の処理を移行し、当該負荷の処理を行った場合に消費される電力と、をそれぞれ演算により求め、両電力の値を比較することにより判定が行われる。   In the determination process of S805, when it is determined that the shift of the load process is possible (in the case of YES), the arithmetic processing unit 61 performs a process of determining whether or not the power consumption is reduced by this shift ( S806). Specifically, the power consumed when the load processing is continued in the ICT device 25 located in the low load zone and the load processing are transferred to the ICT device 25 located in the other zone, and the load processing is performed. The determination is performed by calculating the power consumed when performing the above and comparing the values of both powers.

S806の判定処理において、消費電力が減少すると判定された場合(YESの場合)には、演算処理部61は、設定を空調優先モードとする処理を行う(S807)。その後、演算処理部61によるサブルーチンの処理が終了し、処理は図12のフローチャートに移行する。   In the determination process of S806, when it is determined that the power consumption is reduced (in the case of YES), the arithmetic processing unit 61 performs a process of setting the air conditioning priority mode (S807). Thereafter, the subroutine processing by the arithmetic processing unit 61 ends, and the processing shifts to the flowchart of FIG.

S805の判定処理において、負荷の処理の移行が不可能と判定された場合(NOの場合)、または、S806における判定処理において、消費電力が減少しないと判定された場合(NOの場合)には、演算処理部61は、上述の他のゾーンのICT装置25から低負荷ゾーンのICT装置25へ負荷の処理が移行可能か否かを判定する処理を行う(S808)。   In the determination process of S805, when it is determined that the load process cannot be shifted (in the case of NO), or in the determination process in S806, it is determined that the power consumption does not decrease (in the case of NO). The arithmetic processing unit 61 performs processing to determine whether or not load processing can be transferred from the ICT device 25 in the other zone described above to the ICT device 25 in the low load zone (S808).

S808の判定処理において負荷の移行が可能と判定された場合(YESの場合)には、演算処理部61は、移行後の消費電力が減少するか否かを判定する処理を行う(S809)。具体的には、他のゾーンに位置するICT装置25で負荷の処理を続けた場合に消費される電力と、低負荷ゾーンに位置するICT装置25に負荷の処理を移行し、当該負荷の処理を行った場合に消費される電力と、をそれぞれ演算により求め、両電力の値を比較することにより判定が行われる。   When it is determined in the determination process of S808 that the load can be shifted (in the case of YES), the arithmetic processing unit 61 performs a process of determining whether or not the power consumption after the shift is reduced (S809). Specifically, the power consumed when the load processing is continued in the ICT device 25 located in another zone and the load processing are transferred to the ICT device 25 located in the low load zone, and the load processing is performed. The determination is performed by calculating the power consumed when performing the above and comparing the values of both powers.

S809の判定処理において、移行後の消費電力が減少すると判定された場合(YESの場合)には、演算処理部61は、他のゾーンのICT装置25から低負荷ゾーンのICT装置25へ、負荷の処理を移行させる処理を行い(S810)、設定を空調優先モードとする処理を行う(S807)。その後、演算処理部61によるサブルーチンの処理が終了し、処理は図12のフローチャートに移行する。   In the determination process of S809, when it is determined that the power consumption after the transition decreases (in the case of YES), the arithmetic processing unit 61 loads the load from the ICT device 25 in the other zone to the ICT device 25 in the low load zone. (S810) and a process for setting the air conditioning priority mode (S807). Thereafter, the subroutine processing by the arithmetic processing unit 61 ends, and the processing shifts to the flowchart of FIG.

S808における判定処理で、負荷の処理の移行が不可能と判定された場合(NOの場合)、または、S809における判定処理で、移行後の消費電力が減少しないと判定された場合(NOの場合)には、演算処理部61は、設定をICT装置優先モードとする処理を行う(S804)。その後、演算処理部61によるサブルーチンの処理が終了し、処理は図12のフローチャートに移行する。   When it is determined in the determination process in S808 that the load process cannot be shifted (in the case of NO), or in the determination process in S809, it is determined that the power consumption after the shift does not decrease (in the case of NO) ), The arithmetic processing unit 61 performs processing for setting the ICT device priority mode (S804). Thereafter, the subroutine processing by the arithmetic processing unit 61 ends, and the processing shifts to the flowchart of FIG.

サブルーチンの処理が終了して、処理が図12のフローチャートに戻ると、演算処理部61は、サブルーチンにおいて設定されたモードがICT装置優先モードであるか否かを判定する処理を行う(S821)。設定がICT装置優先モードであると判定された場合(YESの場合)には、演算処理部61における処理はS11の処理に移行し、その後、第1の実施形態と同様な処理を行う。   When the subroutine processing is completed and the processing returns to the flowchart of FIG. 12, the arithmetic processing unit 61 performs processing to determine whether or not the mode set in the subroutine is the ICT device priority mode (S821). When it is determined that the setting is the ICT device priority mode (in the case of YES), the processing in the arithmetic processing unit 61 proceeds to the processing of S11, and thereafter, the same processing as in the first embodiment is performed.

S821の判定処理において設定がICT装置優先モードでないと判定された場合(NOの場合)には、演算処理部61は、サブルーチンにおいて設定されたモードが空調優先モードであるか否かを判定する処理を行う(S822)。設定が空調優先モードであると判定された場合(YESの場合)には、演算処理部61の処理はS115の処理に移行し、その後、第1の実施形態と同様な処理を行う。   When it is determined in the determination process of S821 that the setting is not the ICT device priority mode (in the case of NO), the arithmetic processing unit 61 determines whether or not the mode set in the subroutine is the air conditioning priority mode. (S822). When it is determined that the setting is the air conditioning priority mode (in the case of YES), the processing of the arithmetic processing unit 61 proceeds to the processing of S115, and thereafter, the same processing as that of the first embodiment is performed.

設定が空調優先モードでないと判定された場合(NOの場合)には、演算処理部61は、縮退運転の可否を判定する処理を中止する。
なお、上述の実施形態のように、制御処理が開始された後に制御優先順位を判定する処理(S800)を行ってもよいし、図14に示すように、入退情報を取得する処理(S11)を行い、社員数が予め定められた所定の一定数未満であると判定された(S12のYES)後に、制御優先順位を判定する処理(S800)を行ってもよい。この場合、S821の判定処理において設定がICT装置優先モードと判定された(YES)とき、演算処理部61における処理はS15の処理に移行し、その後、第1の実施形態と同様な処理を行う。
When it is determined that the setting is not the air conditioning priority mode (in the case of NO), the arithmetic processing unit 61 stops the process of determining whether or not the degenerate operation is possible.
In addition, like the above-mentioned embodiment, you may perform the process (S800) which determines a control priority after a control process is started, or as shown in FIG. 14, the process (S11 which acquires entrance / exit information) ) And the process of determining the control priority (S800) may be performed after it is determined that the number of employees is less than a predetermined fixed number (YES in S12). In this case, when the setting is determined to be the ICT device priority mode in the determination process of S821 (YES), the process in the arithmetic processing unit 61 proceeds to the process of S15, and thereafter, the same process as in the first embodiment is performed. .

上記の構成の給電システム1によれば、ICT装置優先モードおよび空調優先モードのいずれを優先するかの判定結果に基づいて制御が行われるため、消費電力の削減を図り易くなる。例えば、ICT装置25の負荷率が低いICT装置25が存在する場合、空調装置35は低負荷状態で運転されたり、送風運転と冷房運転を繰り返したりすることとなり、消費電力の削減を行いにくい状況となる。この場合、空調優先モードを採用することにより、ICT装置優先モードを採用する場合と比較して、消費電力の削減を行いやすくなる。   According to the power supply system 1 having the above-described configuration, control is performed based on the determination result as to which of the ICT device priority mode and the air conditioning priority mode is prioritized, so that power consumption can be easily reduced. For example, when there is an ICT device 25 with a low load factor of the ICT device 25, the air conditioner 35 is operated in a low load state or the air blowing operation and the cooling operation are repeated, so that it is difficult to reduce power consumption. It becomes. In this case, by adopting the air conditioning priority mode, it becomes easier to reduce the power consumption than when the ICT device priority mode is adopted.

なお、本発明の技術範囲は上記実施形態に限定されるものではなく、本発明の趣旨を逸脱しない範囲において種々の変更を加えることが可能である。例えば、上記の実施形態では、給電制御装置20と、ICT制御装置30と、空調制御装置40と、照明制御装置50と、統合制御装置60と、がそれぞれ設けられている例に適用して説明しているが、一部の制御装置が1つの制御装置(サーバ)にまとめられていてもよいし、全ての制御装置が1つの制御装置(サーバ)にまとめられていてもよく、特に限定するものではない。   The technical scope of the present invention is not limited to the above embodiment, and various modifications can be made without departing from the spirit of the present invention. For example, in the above embodiment, the description is applied to an example in which the power supply control device 20, the ICT control device 30, the air conditioning control device 40, the lighting control device 50, and the integrated control device 60 are provided. However, some control devices may be combined into one control device (server), or all control devices may be combined into one control device (server), which is particularly limited. It is not a thing.

1…給電システム、10…給電装置、11…電源ユニット(給電機器)、20…給電制御装置(サーバ)、21…演算処理部(制御部)、25…ICT装置(負荷装置)、30…ICT制御装置(サーバ)、31…演算処理部(制御部)、35…空調装置、40…空調制御装置(サーバ)、41…演算処理部(制御部)、60…統合制御装置(制御部、サーバ)、61…演算処理部(処理部)、62…学習処理部(処理部)、63…予測処理部(処理部)、64…取得部、S11,S311,S312,S411,S412,S413,S414…取得ステップ、S12,S13,S14,S314…優先処理ステップ   DESCRIPTION OF SYMBOLS 1 ... Power feeding system, 10 ... Power feeding apparatus, 11 ... Power supply unit (power feeding apparatus), 20 ... Power feeding control apparatus (server), 21 ... Arithmetic processing part (control part), 25 ... ICT apparatus (load apparatus), 30 ... ICT Control device (server), 31 ... arithmetic processing unit (control unit), 35 ... air conditioning device, 40 ... air conditioning control device (server), 41 ... arithmetic processing unit (control unit), 60 ... integrated control device (control unit, server) , 61... Arithmetic processing unit (processing unit), 62... Learning processing unit (processing unit), 63 .. prediction processing unit (processing unit), 64... Acquisition unit, S 11, S 311, S 312, S 411, S 412, S 413, S 414 ... Acquisition step, S12, S13, S14, S314 ... Priority processing step

Claims (21)

所定電流を出力する複数の給電機器を有する給電装置と、
前記給電装置から給電されて作動負荷の処理を行う複数の負荷装置、および、前記複数の負荷装置を冷却する複数の空調装置を少なくとも制御する制御部と、を備えた給電システムであって、
前記制御部には、前記複数の負荷装置における作動負荷量に関するパラメータを取得する取得部と、
前記取得部により取得した前記パラメータに基づいて、一部の負荷装置(以下、「移行元の負荷装置」と表記する。)において処理される前記作動負荷を残りの負荷装置の少なくとも一部(以下、「移行先の負荷装置」と表記する。)で処理することによる消費電力の削減(以下、「負荷装置による削減」と表記する。)、および、前記空調装置の冷房能力を制御することによる消費電力の削減(以下、「空調装置による削減」と表記する。)のいずれを優先するか優先順位を求める処理部と、
が設けられていることを特徴とする給電システム。
A power supply apparatus having a plurality of power supply devices that output a predetermined current;
A power supply system comprising: a plurality of load devices that are fed from the power supply device to process an operating load; and a control unit that controls at least a plurality of air conditioners that cool the plurality of load devices,
In the control unit, an acquisition unit that acquires a parameter related to an operation load amount in the plurality of load devices;
Based on the parameter acquired by the acquisition unit, the operating load processed in a part of load devices (hereinafter referred to as “migration source load device”) is at least a part of the remaining load devices (hereinafter referred to as “load source device”). , "Represented as" destination load device "), by reducing power consumption by processing (hereinafter referred to as" reduction by load device "), and by controlling the cooling capacity of the air conditioner A processing unit for obtaining a priority order to prioritize which of power consumption reduction (hereinafter referred to as “reduction by an air conditioner”);
A power supply system characterized in that is provided.
前記処理部は、前記パラメータに基づいて前記複数の負荷装置における前記作動負荷量が少なく、所定の下限値よりも小さな空調能力で運転している前記空調装置が存在すると判定される場合には、前記空調装置による削減を優先し、前記所定の下限値よりも値の大きな所定の適正範囲内の前記空調能力で運転している前記空調装置が存在すると判定されている場合には、前記負荷装置による削減を優先する処理を行うことを特徴とする請求項1に記載の給電システム。   In the case where it is determined that the processing unit is based on the parameter, the operating load amount in the plurality of load devices is small, and there is the air conditioner operating with an air conditioning capability smaller than a predetermined lower limit value. If it is determined that there exists the air conditioner operating in the air conditioning capacity within a predetermined appropriate range having a value larger than the predetermined lower limit value, giving priority to reduction by the air conditioner, the load device The power feeding system according to claim 1, wherein processing that prioritizes reduction by the power is performed. 前記制御部は、さらに、前記複数の給電機器の稼働数を制御することにより前記給電装置における消費電力を制御するものであり、
前記処理部は、前記給電装置における消費電力の削減よりも、前記空調装置による削減および前記負荷装置による削減を優先する処理を行うことを特徴とする請求項1または2記載の給電システム。
The control unit further controls power consumption in the power supply apparatus by controlling the number of operating the plurality of power supply devices.
The power supply system according to claim 1, wherein the processing unit performs processing that prioritizes reduction by the air conditioner and reduction by the load device over reduction of power consumption in the power supply device.
前記パラメータは、前記負荷装置の利用者に関するスケジュール情報、および、カレンダ情報の少なくとも一方であることを特徴とする請求項1から3のいずれか1項に記載の給電システム。   The power supply system according to any one of claims 1 to 3, wherein the parameter is at least one of schedule information related to a user of the load device and calendar information. 前記パラメータは、気象情報、および、交通情報の少なくとも一方であることを特徴する請求項1から3のいずれか1項に記載の給電システム。   The power feeding system according to any one of claims 1 to 3, wherein the parameter is at least one of weather information and traffic information. 前記パラメータは、前記負荷装置の利用者の位置情報、および、前記利用者の座席位置情報であることを特徴とする請求項1から3のいずれか1項に記載の給電システム。   The power supply system according to any one of claims 1 to 3, wherein the parameters are position information of a user of the load device and seat position information of the user. 前記パラメータは、前記負荷装置の利用者の入退情報、および、前記利用者が利用する前記負荷装置の情報の少なくとも一方であることを特徴とする請求項1から3のいずれか1項に記載の給電システム。   The said parameter is at least one of the user's entrance / exit information of the said load apparatus, and the information of the said load apparatus which the said user uses, The any one of Claim 1 to 3 characterized by the above-mentioned. Power supply system. 所定電流を出力する複数の給電機器を有する給電装置と、
前記給電装置から給電されて作動負荷の処理を行う複数の負荷装置、および、前記複数の負荷装置を冷却する複数の空調装置を少なくとも制御する制御部と、を備えた給電システムにおける給電方法であって、
前記複数の負荷装置における作動負荷量に関するパラメータを取得する取得ステップと、
取得した前記パラメータに基づいて、一部の負荷装置(以下、「移行元の負荷装置」と表記する。)において処理される前記作動負荷を残りの負荷装置の少なくとも一部(以下、「移行先の負荷装置」と表記する。)で処理することによる消費電力の削減(以下、「負荷装置による削減」と表記する。)、および、前記空調装置の冷房能力を制御することによる消費電力の削減(以下、「空調装置による削減」と表記する。)のいずれを優先するか優先順位を求める優先処理ステップと、
を有することを特徴とする給電方法。
A power supply apparatus having a plurality of power supply devices that output a predetermined current;
A power supply method in a power supply system, comprising: a plurality of load devices that are supplied with power from the power supply device to process an operating load; and a control unit that controls at least a plurality of air conditioners that cool the plurality of load devices. And
An obtaining step for obtaining a parameter relating to an operating load amount in the plurality of load devices;
Based on the acquired parameter, the operating load processed in a part of load devices (hereinafter referred to as “migration source load device”) is changed to at least a part of the remaining load devices (hereinafter referred to as “migration destination”). Reduction of power consumption by processing in (hereinafter referred to as “reduction by load device”), and reduction of power consumption by controlling the cooling capacity of the air conditioner. (Hereinafter referred to as “reduction by air conditioner”) priority processing step for determining which priority is given,
A power supply method characterized by comprising:
前記優先処理ステップでは、前記パラメータに基づいて前記複数の負荷装置における前記作動負荷量が少なく、所定の下限値よりも小さな空調能力で運転している前記空調装置が存在すると判定される場合には、前記空調装置による削減を優先し、前記所定の下限値よりも値の大きな所定の適正範囲内の前記空調能力で運転している前記空調装置が存在すると判定されている場合には、前記負荷装置による削減を優先する処理を行うことを特徴とする請求項8に記載の給電方法。   In the priority processing step, when it is determined that there is an air conditioner that is operating with an air conditioning capacity that is smaller than a predetermined lower limit value based on the parameter and the operating load amount in the plurality of load devices is small. If it is determined that the air conditioner operating in the air conditioning capacity within a predetermined appropriate range having a value larger than the predetermined lower limit value is prioritized for reduction by the air conditioner, the load The power feeding method according to claim 8, wherein processing that prioritizes reduction by the apparatus is performed. 前記優先処理ステップでは、前記複数の給電機器の稼働数を制御することによる前記給電装置における消費電力の削減よりも、前記空調装置による削減および前記負荷装置による削減を優先する処理を行うことを特徴とする請求項8または9記載の給電方法。   In the priority processing step, processing that prioritizes reduction by the air conditioning device and reduction by the load device is performed over reduction of power consumption in the power feeding device by controlling the number of operations of the plurality of power feeding devices. The power feeding method according to claim 8 or 9. 前記パラメータは、前記負荷装置の利用者に関するスケジュール情報、および、カレンダ情報の少なくとも一方であることを特徴とする請求項8から10のいずれか1項に記載の給電方法。   The power supply method according to claim 8, wherein the parameter is at least one of schedule information and calendar information related to a user of the load device. 前記パラメータは、気象情報、および、交通情報の少なくとも一方であることを特徴する請求項8から10のいずれか1項に記載の給電方法。   The power feeding method according to claim 8, wherein the parameter is at least one of weather information and traffic information. 前記パラメータは、前記負荷装置の利用者の位置情報、および、前記利用者の座席位置情報であることを特徴とする請求項8から10のいずれか1項に記載の給電方法。   The power feeding method according to any one of claims 8 to 10, wherein the parameters are position information of a user of the load device and seat position information of the user. 前記パラメータは、前記負荷装置の利用者の入退情報、および、前記利用者が利用する前記負荷装置の情報の少なくとも一方であることを特徴とする請求項8から10のいずれか1項に記載の給電方法。   The said parameter is at least one of the user's entrance / exit information of the said load apparatus, and the information of the said load apparatus which the said user uses, The any one of Claim 8 to 10 characterized by the above-mentioned. Power supply method. 所定電流を出力する複数の給電機器を有する給電装置から給電されて作動負荷の処理を行う複数の負荷装置、および、前記複数の負荷装置を冷却する複数の空調装置を少なくとも制御する制御部を備えたサーバであって、
前記制御部には、前記複数の負荷装置における作動負荷量に関するパラメータを取得する取得部と、
前記取得部により取得した前記パラメータに基づいて、一部の負荷装置(以下、「移行元の負荷装置」と表記する。)において処理される前記作動負荷を残りの負荷装置の少なくとも一部(以下、「移行先の負荷装置」と表記する。)で処理することによる消費電力の削減(以下、「負荷装置による削減」と表記する。)、および、前記空調装置の冷房能力を制御することによる消費電力の削減(以下、「空調装置による削減」と表記する。)のいずれを優先するか優先順位を求める処理部と、
が設けられていることを特徴とするサーバ。
Provided with a plurality of load devices that are supplied with power from a power supply device having a plurality of power supply devices that output a predetermined current and process an operating load, and a control unit that controls at least a plurality of air conditioners that cool the plurality of load devices Server,
In the control unit, an acquisition unit that acquires a parameter related to an operation load amount in the plurality of load devices;
Based on the parameter acquired by the acquisition unit, the operating load processed in a part of load devices (hereinafter referred to as “migration source load device”) is at least a part of the remaining load devices (hereinafter referred to as “load source device”). , "Represented as" destination load device "), by reducing power consumption by processing (hereinafter referred to as" reduction by load device "), and by controlling the cooling capacity of the air conditioner A processing unit for obtaining a priority order to prioritize which of power consumption reduction (hereinafter referred to as “reduction by an air conditioner”);
A server characterized in that is provided.
前記処理部は、前記パラメータに基づいて前記複数の負荷装置における前記作動負荷量が少なく、所定の下限値よりも小さな空調能力で運転している前記空調装置が存在すると判定される場合には、前記空調装置による削減を優先し、前記所定の下限値よりも値の大きな所定の適正範囲内の前記空調能力で運転している前記空調装置が存在すると判定されている場合には、前記負荷装置による削減を優先する処理を行うことを特徴とする請求項15に記載のサーバ。   In the case where it is determined that the processing unit is based on the parameter, the operating load amount in the plurality of load devices is small, and there is the air conditioner operating with an air conditioning capability smaller than a predetermined lower limit value. If it is determined that there exists the air conditioner operating in the air conditioning capacity within a predetermined appropriate range having a value larger than the predetermined lower limit value, giving priority to reduction by the air conditioner, the load device The server according to claim 15, wherein a process that prioritizes reduction by the server is performed. 前記制御部は、さらに、前記複数の給電機器の稼働数を制御することにより前記給電装置における消費電力を制御するものであり、
前記処理部は、前記給電装置における消費電力の削減よりも、前記空調装置による削減および前記負荷装置による削減を優先する処理を行うことを特徴とする請求項15または16記載のサーバ。
The control unit further controls power consumption in the power supply apparatus by controlling the number of operating the plurality of power supply devices.
The server according to claim 15 or 16, wherein the processing unit performs processing that prioritizes reduction by the air conditioner and reduction by the load device over reduction of power consumption in the power supply device.
前記パラメータは、前記負荷装置の利用者に関するスケジュール情報、および、カレンダ情報の少なくとも一方であることを特徴とする請求項15から17のいずれか1項に記載のサーバ。   The server according to any one of claims 15 to 17, wherein the parameter is at least one of schedule information and calendar information related to a user of the load device. 前記パラメータは、気象情報、および、交通情報の少なくとも一方であることを特徴する請求項15から17のいずれか1項に記載のサーバ。   The server according to any one of claims 15 to 17, wherein the parameter is at least one of weather information and traffic information. 前記パラメータは、前記負荷装置の利用者の位置情報、および、前記利用者の座席位置情報であることを特徴とする請求項15から17のいずれか1項に記載のサーバ。   The server according to any one of claims 15 to 17, wherein the parameters are position information of a user of the load device and seat position information of the user. 前記パラメータは、前記負荷装置の利用者の入退情報、および、前記利用者が利用する前記負荷装置の情報の少なくとも一方であることを特徴とする請求項15から17のいずれか1項に記載のサーバ。   The said parameter is at least one of the user's entrance / exit information of the said load apparatus, and the information of the said load apparatus which the said user uses, The any one of Claim 15 to 17 characterized by the above-mentioned. Server.
JP2015099236A 2015-05-14 2015-05-14 Power supply system, power supply method, and server Expired - Fee Related JP6430892B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015099236A JP6430892B2 (en) 2015-05-14 2015-05-14 Power supply system, power supply method, and server

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015099236A JP6430892B2 (en) 2015-05-14 2015-05-14 Power supply system, power supply method, and server

Publications (2)

Publication Number Publication Date
JP2016220291A JP2016220291A (en) 2016-12-22
JP6430892B2 true JP6430892B2 (en) 2018-11-28

Family

ID=57581806

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015099236A Expired - Fee Related JP6430892B2 (en) 2015-05-14 2015-05-14 Power supply system, power supply method, and server

Country Status (1)

Country Link
JP (1) JP6430892B2 (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4895266B2 (en) * 2005-12-28 2012-03-14 富士通株式会社 Management system, management program, and management method
JP5054590B2 (en) * 2008-03-26 2012-10-24 パナソニック株式会社 Demand control system and demand control method
JP5435399B2 (en) * 2009-10-07 2014-03-05 日本電気株式会社 Power saving system, power saving method, and power saving program
JP5378946B2 (en) * 2009-10-26 2013-12-25 株式会社日立製作所 Server management apparatus and server management method
JP5614162B2 (en) * 2010-08-12 2014-10-29 富士ゼロックス株式会社 Information processing apparatus and information processing program

Also Published As

Publication number Publication date
JP2016220291A (en) 2016-12-22

Similar Documents

Publication Publication Date Title
US7865272B2 (en) Method and apparatus for preventing overloads of power distribution networks
JP5813904B1 (en) Power supply control device
CN106100101B (en) UPS operation with high converter efficiency
JP5737969B2 (en) Ship power control method and ship power control system
JP5826714B2 (en) Power control system and power monitoring device
KR101566621B1 (en) system for operation control of inverter in emergency situation
JP2007195392A (en) Demand supervisory equipment
JP2015195696A (en) Power management system, power management method and server
JP6430892B2 (en) Power supply system, power supply method, and server
JP2009096582A (en) Elevator electric power adjusting device
JP2013169039A (en) Demand power amount control system, demand power amount control method, and program
JP2013025343A (en) Network apparatus
JP2015231290A (en) Power storage device and control program
JP2017042021A (en) Power storage control device, power conversion device, power storage system, power storage control method and program
KR101157651B1 (en) Demand controller switchable to electric generator in peak and method for controlling the same
JP2015231316A (en) Power storage system
JP2017146795A (en) Controller for information processor, control method for information processor, and program
JP6454929B2 (en) Storage battery control system, storage battery control method, and program
JP6639929B2 (en) Control device, control method, and program for information processing device
CN115709691A (en) Power-on method and device of automatic driving controller, storage medium and vehicle
RU2478046C1 (en) Device for electric locomotive continuous temperature control and automatic adjustment of electric power equipment load
KR101119613B1 (en) Sub Power Supply Management System and Method therefor
JP2016033813A (en) Power supply system, power supply method and server
JP2008094508A (en) Car interior ventilation system of elevator
JP7499958B2 (en) Power Supply System

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180201

TRDD Decision of grant or rejection written
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20181024

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181030

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20181101

R150 Certificate of patent or registration of utility model

Ref document number: 6430892

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees