JP6466814B2 - How to improve soft ground - Google Patents
How to improve soft ground Download PDFInfo
- Publication number
- JP6466814B2 JP6466814B2 JP2015210950A JP2015210950A JP6466814B2 JP 6466814 B2 JP6466814 B2 JP 6466814B2 JP 2015210950 A JP2015210950 A JP 2015210950A JP 2015210950 A JP2015210950 A JP 2015210950A JP 6466814 B2 JP6466814 B2 JP 6466814B2
- Authority
- JP
- Japan
- Prior art keywords
- time
- creation
- penetration
- soft ground
- sand
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Description
本発明は、造成工程における時間を制御した軟弱地盤の改良方法に関するものである。 The present invention relates to a method for improving soft ground in which the time in the creation process is controlled.
軟弱地盤の液状化対策として、中空管を圧入して砂材料を地中に供給しながら締固め砂杭を造成し周辺地盤を締固めるサンドコンパクションパイル工法(以下、単に「SCP工法」とも言う。)が知られている。SCP工法で締固めた砂杭を軟弱地盤中に所定の間隔で多数造成すると、周辺地盤のN値が大きくなり、軟弱地盤の液状化に対する抵抗性が増大する。 As a countermeasure against liquefaction of soft ground, sand compaction pile method (hereinafter also referred to simply as “SCP method”) is a method of compacting sand piles by press-fitting a hollow tube and supplying sand material into the ground to compact the surrounding ground. .)It has been known. When a large number of sand piles compacted by the SCP method are formed at a predetermined interval in the soft ground, the N value of the surrounding ground increases, and the resistance to liquefaction of the soft ground increases.
SCP工法においては、予め現場データをもとに、打設砂杭の置換率(改良率)で改良効果を予測する設計を行う。この際、施工の対象となる軟弱地盤に、隣接する等ピッチ間隔の3本又は4本の造成予定の砂杭で区画される小区画を多数形成する。すなわち、軟弱地盤に対して、砂杭は等間隔で多数形成することになる。このように、設計段階において砂杭間隔(パイル間隔)が決定されるが、現場によっては締固め砂杭による地盤変位が既設構造物に影響するため、SCP工法の適用を断念することがある。従って、砂杭間隔を従来設計の砂杭間隔より大きく採っても、目標とするN値が得られるSCP工法が開発されれば、周辺に与える地盤変位を抑制でき、SCP工法の適用範囲が広まる。 In the SCP method, a design for predicting the improvement effect by the replacement rate (improvement rate) of the cast sand pile is performed based on the field data in advance. At this time, a large number of small sections partitioned by adjacent three or four sand piles to be constructed are formed on the soft ground to be constructed. That is, many sand piles are formed at equal intervals with respect to the soft ground. As described above, the sand pile interval (pile interval) is determined at the design stage. However, depending on the site, the ground displacement due to the compacted sand pile affects the existing structure, so the application of the SCP method may be abandoned. Therefore, if an SCP method is developed that can achieve the target N value even if the sand pile interval is larger than the conventionally designed sand pile interval, the ground displacement applied to the periphery can be suppressed, and the application range of the SCP method is expanded. .
従来、特開2003−147756号公報などSCP工法に関する改良技術が種々提案されているものの、従来設計の施工で得られるN値はせいぜい30〜40程度であり、N値が50を超える技術は未だ知られていない。 Conventionally, various improvement techniques related to the SCP method such as Japanese Patent Application Laid-Open No. 2003-147756 have been proposed, but the N value obtained by the construction of the conventional design is about 30 to 40 at most, and the technology with an N value exceeding 50 is still not available. unknown.
従って、本発明の目的は、効率的な改良効果が得られる軟弱地盤の改良方法を提供することにある。 Accordingly, an object of the present invention is to provide a soft ground improving method capable of obtaining an efficient improving effect.
このような状況下、本発明者らは、鋭意検討を行ったところ、貫入工程より造成工程に時間をかけるなど造成工程で緩やかな締め固めを行えば、周辺地盤では締固めに寄与する応力が伝わり易く、密度上昇となることを見出し、本発明を完成するに至った。 Under such circumstances, the present inventors have conducted intensive studies and found that stress that contributes to compaction is generated in the surrounding ground if gentle compaction is performed in the creation process, such as taking time from the penetration process to the creation process. It was found that the density was easily increased and the present invention was completed.
すなわち、本発明は、中空管を所定の深度まで貫入する貫入工程と、
該貫入工程後、中空管を適宜の長さ引き抜き、該引き抜き跡に中空管内の砂杭材料を排出する引き抜きと、中空管の打ち戻しを順次、地表に至るまで繰り返す造成工程とを行い軟弱地盤中に複数の締固め砂杭を打設する工法において、
1本の砂杭の打設において、造成工程に要する時間(T2)が、貫入工程に要する時間(T1)の3倍以上となるように、貫入工程と造成工程を行うことを特徴とする軟弱地盤の改良方法を提供するものである。
That is, the present invention includes a penetration step of penetrating the hollow tube to a predetermined depth;
After the penetration step, the hollow tube is drawn out to an appropriate length, and a drawing step of discharging sand pile material in the hollow tube to the drawing trace and a creation step of repeating the hollow pipe back-up to the ground surface in order. In the method of placing multiple compacted sand piles in soft ground,
In placing one sand pile, the penetration process and the creation process are performed so that the time required for the creation process (T2) is more than three times the time required for the penetration process (T1). The ground improvement method is provided.
また、本発明は、造成工程に要する時間(T2)が、貫入工程に要する時間(T1)の4倍以上となるように、貫入工程と造成工程を行うことを特徴とする前記軟弱地盤の改良方法を提供するものである。 Moreover, this invention improves the said soft ground characterized by performing a penetration process and a creation process so that the time (T2) required for a creation process may be 4 times or more of the time (T1) required for a penetration process. A method is provided.
また、本発明は、更に、引き抜きと打ち戻しの1サイクル中、打ち戻し時間(T4)が、引き抜き時間(T3)より大となるように造成工程を行うことを特徴とする前記軟弱地盤の改良方法を提供するものである。 Further, the present invention further provides the improvement of the soft ground characterized in that the creation step is performed so that the withdrawal time (T4) is longer than the withdrawal time (T3) during one cycle of withdrawal and withdrawal. A method is provided.
また、本発明は、打ち戻し長を、引き抜き長の70%〜90%として造成工程を行うことを特徴とする前記軟弱地盤の改良方法を提供するものである。 Moreover, this invention provides the improvement method of the said soft ground characterized by performing a creation process by setting back-up length as 70%-90% of drawing-out length.
本発明によれば、測定点(以下、「周辺地盤」とも言う。)のN値は50を超える高い改良効果が得られた。従来のSCP工法では、改良率が20%と高いものでも、N値はせいぜい30〜40程度であり、顕著な改良効果であった。これは、貫入工程より造成工程に時間をかけるなどの方法を採ったため、貫入工程に比べて造成工程の最大過剰間隙水圧が小となり、締固めに寄与する応力が伝わり易く、密度上昇につながったものである。このため、従来より広いパイル間隔で施工しても従来と同等の改良効果が得られる。また、パイル間隔を大きく採れるため、周辺に与える地盤変位を抑制することができ、従来施工が困難であった場所でも施工が可能となる。また、従来と同等のパイル間隔で施工した場合、より高い改良効果が得られるため、改良の要求が厳しい条件においても対応が可能となる。 According to the present invention, a high improvement effect in which the N value of the measurement point (hereinafter also referred to as “periphery ground”) exceeds 50 was obtained. In the conventional SCP method, even if the improvement rate is as high as 20%, the N value is at most about 30 to 40, which is a remarkable improvement effect. This is because it took a longer time for the creation process than the penetration process, so the maximum excess pore water pressure in the creation process was smaller than in the penetration process, and the stress contributing to compaction was easily transmitted, leading to an increase in density. Is. For this reason, even if it constructs with a wider pile interval than before, the same improvement effect as before can be obtained. Moreover, since a pile interval can be taken large, the ground displacement given to the periphery can be suppressed and construction can be performed even in a place where conventional construction is difficult. In addition, when the construction is performed at the same pile interval as that of the prior art, a higher improvement effect can be obtained, so that it is possible to cope even under severe conditions for improvement.
次に、本発明の実施の形態における軟弱地盤の改良方法について、図1及び図2を参照して説明する。図1は、軟弱地盤10に対して、正四角形a、c、i、gで形成される改良予定区域Xに、等ピッチpで砂杭1を9本打設しようとするものである。 Next, a method for improving soft ground in the embodiment of the present invention will be described with reference to FIGS. FIG. 1 shows an attempt to drive nine sand piles 1 at an equal pitch p in a planned improvement area X formed by regular squares a, c, i, and g on a soft ground 10.
本発明の軟弱地盤の改良方法において、先ず、中空管11を所定の深度まで貫入する貫入工程(I)を行う(図2(a)〜(c))。具体的には、中空管11を所定の位置(例えば、図1中の符号aの位置)に据え、一定量の砂杭材料が投入される。次いで、中空管を回転させながら地中に所定の深度貫入する。従って、貫入工程の開始時間は、図2(a)に示すように、中空管11が地面に押し込まれたスタート時であり、貫入工程の終了時間は、図2(c)に示すように、中空管11が所定の深さD(最下位置)に到達した時間である。砂杭材料としては、砂、砕石などが挙げられる。 In the method for improving soft ground according to the present invention, first, a penetration step (I) for penetrating the hollow tube 11 to a predetermined depth is performed (FIGS. 2A to 2C). Specifically, the hollow tube 11 is placed at a predetermined position (for example, the position indicated by symbol a in FIG. 1), and a certain amount of sand pile material is charged. Next, the hollow tube is rotated to penetrate a predetermined depth into the ground. Therefore, the start time of the penetration process is the start time when the hollow tube 11 is pushed into the ground as shown in FIG. 2 (a), and the end time of the penetration process is as shown in FIG. 2 (c). The time when the hollow tube 11 reaches the predetermined depth D (the lowest position). Examples of the sand pile material include sand and crushed stone.
貫入工程後、中空管11を適宜の長さ(図2中、符号l1)引き抜き、該引き抜き跡に中空管内の砂杭材料を排出する引き抜きと、中空管11の打ち戻し(図2中、打ち戻し長さは符号l2)を順次、地表に至るまで繰り返し、締固め砂杭1を造成する。引き抜き工程は、図2中、(c)〜(d)の工程(符号II1)であり、図2の符号II1は、最初の引き抜きである。打ち戻し工程は、図2中、(d)〜(e)の工程(符号II2)であり、図2の符号II2は、最初の打ち戻しである。図2中、符号II3は、引き抜きと打ち戻しを1サイクルとして、2サイクル以降の工程である。すなわち、造成工程の開始は、貫入工程後、最初の引く抜きの引き始めであり、造成工程の終了は、造成工程の最後の打ち戻しが終わり中空管が引き抜かれて地表の面と同一となる時点である。 After penetration step, an appropriate length of hollow tube 11 (in FIG. 2, reference numeral l 1) withdrawal, and withdrawal for discharging Sunakui material of the hollow tube to the pull-out trace, the hollow tube 11 out return (Figure 2 In the middle, the backlash length is the code l 2 ) in order until the ground surface is reached, and the compacted sand pile 1 is formed. The drawing process is a process (reference numeral II 1 ) of (c) to (d) in FIG. 2, and reference numeral II 1 in FIG. 2 is the first extraction. 2 is a process (reference numeral II 2 ) of (d) to (e) in FIG. 2, and reference numeral II 2 in FIG. 2 is an initial return. In FIG. 2, reference numeral II 3 is a process after two cycles, with one cycle of drawing and strike back. That is, the start of the creation process is the start of the first drawing after the intrusion process, and the end of the creation process is the same as the surface of the ground surface after the last backlash of the creation process is finished and the hollow tube is pulled out. It is time to become.
本発明において、1本の砂杭の打設において、造成工程に要する時間(T2)が、貫入工程に要する時間(T1)の3倍以上、好ましくは(T1)の4倍以上となるように、貫入工程と造成工程を行う(以下、「時間差造成方法1」とも言う。)。(T2)>(T1)×3とする方法としては、引き抜き時間を長くする方法、打ち戻し時間を長くする方法、造成工程中、待ち時間を長く採る方法及引き抜きと打ち戻しを1サイクルとするサイクル数を増加させる方法等が挙げられる。また、1本の砂杭の打設において、造成工程に要する時間(T2)が、貫入工程に要する時間(T1)の3倍より大とし、更に、引き抜きと打ち戻しの1サイクル中、打ち戻し時間(T4)が、引き抜き時間(T3)より大となるように行う方法(以下、「時間差造成方法2」とも言う。)、打ち戻し長を、引き抜き長の70%〜90%として造成工程を行う方法(以下、「サイクル数増加方法1」とも言う。)及び引き抜きと打ち戻しを1サイクルとするサイクル数を増加させて、造成工程を行う方法(以下、「サイクル数増加方法2」とも言う。)であってもよい。以下に詳細に説明する。 In the present invention, in placing a single sand pile, the time required for the creation process (T2) is not less than 3 times the time required for the penetration process (T1), preferably not less than 4 times (T1). The penetration process and the creation process are performed (hereinafter also referred to as “time difference creation method 1”). As a method of (T2)> (T1) × 3, a method of extending the extraction time, a method of extending the retraction time, a method of taking a long waiting time during the creation process, and a cycle of extraction and retraction are set as one cycle. A method for increasing the number of cycles is exemplified. In addition, the time required for the creation process (T2) is longer than three times the time required for the penetration process (T1) in the placement of a single sand pile. A method in which the time (T4) is made longer than the drawing time (T3) (hereinafter also referred to as “time difference forming method 2”), and the back-up length is set to 70% to 90% of the drawing length. A method of performing a creation step by increasing the number of cycles (hereinafter also referred to as “cycle number increasing method 1”) and the number of cycles in which extraction and retraction are one cycle (hereinafter also referred to as “cycle number increasing method 2”). .). This will be described in detail below.
時間差造成方法1は、1本の砂杭の打設において、造成工程に要する時間(T2)が、貫入工程に要する時間(T1)の3倍以上、好ましくは4×(T1)時間以上、9×(T1)時間以下となるように行うことが好ましい。余り長い時間を採っても、改良効果の割に施工時間が長くなり、却って施工コストを上昇させる。造成工程に要する時間(T2)には、次のサイクルに移る待ち時間や引き抜きから打ち戻しに移る待ち時間も含まれる。待ち時間であっても、周辺地盤への締固めに寄与する応力は伝わるからである。 In the time difference creation method 1, the time required for the creation process (T2) is 3 times or more of the time required for the penetration process (T1), preferably 4 × (T1) time or more, when placing one sand pile. X (T1) It is preferable to carry out so that it may be less than time. Even if too much time is taken, the construction time becomes longer for the improvement effect, and on the contrary, the construction cost is increased. The time (T2) required for the creation process includes a waiting time for moving to the next cycle and a waiting time for moving from drawing to strike back. This is because the stress that contributes to compaction to the surrounding ground is transmitted even during the waiting time.
時間差造成方法2は、時間差造成方法1に加えて、更に、引き抜きと打ち戻しの1サイクル中、打ち戻し時間(T4)が、引き抜き時間(T3)より大となるように行う方法である。1サイクル中、打ち戻し時間(T4)は、好ましくは2×(T3)時間以上、特に3×(T3)時間以上、8×(T1)時間以下となるように行うことが好ましい。余り長い時間を採っても、改良効果の割に施工時間が長くなり、却って施工コストを上昇させる。時間差造成方法2は、造成工程に要する時間を長くする点では時間差造成方法1と同様であり、打ち戻し時間(T4)が引き抜き時間(T3)より大となる条件は、全サイクルに実施する必要はなく、一部のサイクルで満たせばよい。 In addition to the time difference generation method 1, the time difference generation method 2 is a method in which the retraction time (T4) is longer than the extraction time (T3) during one cycle of drawing and retraction. During one cycle, it is preferable that the time to return (T4) is preferably 2 × (T3) or more, particularly 3 × (T3) or more and 8 × (T1) or less. Even if too much time is taken, the construction time becomes longer for the improvement effect, and on the contrary, the construction cost is increased. The time difference creation method 2 is the same as the time difference creation method 1 in that the time required for the creation process is lengthened, and the condition that the return time (T4) is longer than the drawing time (T3) needs to be implemented in all cycles. It is not necessary to fill in some cycles.
サイクル数増加方法1は、打ち戻し長を、引き抜き長の70%〜90%として造成工程を行う方法である。具体的には、引き抜き長が50cmの場合、打ち戻し長を35cm〜45cmとして造成する。打ち戻し長と引き抜き長を上記条件とし、引き抜き速度や打ち戻し速度など他の条件を従来通りとすれば、当然に造成工程におけるサイクル数は増加する。従来のSCP工法は、打ち戻し長を、引き抜き長の60%として造成するのが一般的である。 The number-of-cycles increasing method 1 is a method in which the creation process is performed with the strike back length being 70% to 90% of the drawing length. Specifically, when the drawing length is 50 cm, the strike back length is set to 35 cm to 45 cm. If the retraction length and the drawing length are set as the above conditions and other conditions such as the drawing speed and the pulling speed are set as usual, the number of cycles in the creation process naturally increases. In the conventional SCP method, the strike back length is generally set to 60% of the drawing length.
サイクル数増加方法2は、引き抜きと打ち戻しを1サイクルとするサイクル数を増加させて、造成工程を行う方法である。具体的なサイクル数は、砂杭長や打ち戻し長により異なるため、一概には言えないが、10mの砂杭長で、70サイクル以上、特に100サイクル以上、200サイクル以下が好ましく、16mの砂杭長で、128サイクル以上、特に160サイクル以上、320サイクル以下が好ましい。従来のSCP工法は、16mの砂杭長で、80サイクルで造成するのが一般的である。 The cycle number increasing method 2 is a method in which the creation step is performed by increasing the number of cycles in which extraction and retraction are one cycle. Since the specific number of cycles varies depending on the sand pile length and backlash length, it cannot be generally stated. However, a sand pile length of 10 m is preferably 70 cycles or more, particularly 100 cycles or more and 200 cycles or less, and 16 m sand. The pile length is preferably 128 cycles or more, particularly 160 cycles or more and 320 cycles or less. The conventional SCP method is generally constructed in 80 cycles with a sand pile length of 16 m.
貫入工程と造成工程を上記の条件で施工する方法によれば、造成工程にかかる時間が長くなるので、貫入工程に比べて造成工程の最大過剰間隙水圧が小となる。すなわち、造成工程では、締固めに寄与する応力が伝わり易く、密度上昇につながる。 According to the method of constructing the penetration process and the creation process under the above conditions, the time required for the creation process becomes longer, so that the maximum excess pore water pressure in the creation process becomes smaller than that in the penetration process. That is, in the creation process, stress contributing to compaction is easily transmitted, leading to an increase in density.
本発明の軟弱地盤の改良方法において、改良効果を確認する測定点は、打設しようとする砂杭の周辺地盤であり、例えば、測定対象となる砂杭から10m以内である。測定点4は、例えば、打設しようとする砂杭が2本の場合、その中間点又は砂杭2本からの当距離で改良が期待される位置であり、打設しようとする砂杭が3本又は4本の場合、その砂杭を結んで区画される領域の中心及び中心近傍である。本例における測定点4は、図1に示すように、打設位置a、b、d及びeに砂杭を打設する場合、四角形の小区画31の中心及び中心近傍である。また、打設位置b、e、c及びfに砂杭を打設する場合、四角形の小区画32の中心及び中心近傍である。また、打設位置d、e、g及びhに砂杭を打設する場合、四角形の小区画33の中心及び中心近傍である。また、打設位置e、f、h及びiに砂杭を打設する場合、四角形の小区画34の中心及び中心近傍である。測定点は、概ね適宜定めるような地点で良い理由は、1本の砂杭打設における貫入工程時の所要時間と造成工程時の所要時間だからである。 In the soft ground improvement method of the present invention, the measurement point for confirming the improvement effect is the surrounding ground of the sand pile to be placed, for example, within 10 m from the sand pile to be measured. For example, when there are two sand piles to be placed, the measurement point 4 is a position where improvement is expected at the intermediate point or the distance from the two sand piles. In the case of three or four, it is the center of the area | region divided by connecting the sand pile, and the center vicinity. As shown in FIG. 1, the measurement point 4 in this example is the center and the vicinity of the center of the rectangular small section 31 when sand piles are placed at the placement positions a, b, d, and e. Further, when sand piles are placed at the placement positions b, e, c, and f, they are at the center and the vicinity of the center of the rectangular small section 32. Further, when sand piles are placed at the placement positions d, e, g, and h, they are at the center and the vicinity of the center of the rectangular small section 33. Further, when sand piles are placed at the placement positions e, f, h, and i, they are at the center and the vicinity of the center of the rectangular small section 34. The reason why the measurement points may be determined as appropriate is that the time required for the penetration process and the time required for the creation process in a single sand pile driving operation.
測定点は、隣接する造成予定の砂杭又は造成砂杭で区画される領域の中心に限定されず、例えば図1中、位置g又は位置hで砂杭を打設する際、符号4aで示す位置であってもよい。また、測定点は、図3に示すように、隣接する3本の造成予定の砂杭又は造成砂杭で区画される領域の中心であってもよい。すなわち、符号a、b及びeの位置で砂杭を打設する際の符号4bの地点であり、符号b、e及びfの位置で砂杭を打設する際の符号4cの地点であり、符号f、g及びjの位置で砂杭を打設する際の符号4dの地点である。また、測定点は、隣接する2本の造成予定の砂杭間又は造成予定の砂杭と造成砂杭間であってもよい。 The measurement point is not limited to the center of the area defined by the adjacent sand pile to be created or the created sand pile. For example, when placing the sand pile at the position g or h in FIG. It may be a position. Further, as shown in FIG. 3, the measurement point may be the center of a region partitioned by three adjacent sand piles to be created or created sand piles. That is, it is a point of 4b when placing a sand pile at the positions of symbols a, b and e, and a point of 4c when placing a sand pile at the positions of symbols b, e and f, This is the point 4d when the sand pile is driven at the positions of symbols f, g and j. The measurement point may be between two adjacent sand piles to be created or between a sand pile to be created and a created sand pile.
本発明において使用される締固め砂杭造成装置としては、公知のものが使用できる。すなわち、中空管の外周面には螺旋羽根があってもよく、中空管の先端には掘削ビットが設けられていてもよい。また、中空管昇降装置としては、特に制限されず、例えば、ラックとピニオンによるもの、チェーンとスプロケットによるもの、ワイヤロープの牽引によるものなど貫入時と引き抜き時にリーダーからの反力が得られるもの、あるいは、バイブロハンマーによるものなどが挙げられる。 A well-known thing can be used as a compacting sand pile production apparatus used in this invention. That is, a spiral blade may be provided on the outer peripheral surface of the hollow tube, and a drilling bit may be provided at the tip of the hollow tube. The hollow tube lifting device is not particularly limited. For example, a device using a rack and pinion, a device using a chain and a sprocket, a device using a wire rope towing, or the like, which can obtain a reaction force from the leader at the time of penetration and withdrawal. Or by vibro hammer.
本発明において、周辺地盤、すなわち、測定点のN値は、従来の1.1倍以上、特に1.2倍以上、更に1.3倍以上の値を示す。また、深さ方向の特定の位置では、N値が50以上となってもよい。従来のSCP工法では、改良率が20%と高いものでも、N値はせいぜい30程度であり、N値50は、顕著に高いものである。 In the present invention, the N value of the surrounding ground, that is, the measurement point, is 1.1 times or more, particularly 1.2 times or more, and further 1.3 times or more than the conventional value. Further, the N value may be 50 or more at a specific position in the depth direction. In the conventional SCP method, even if the improvement rate is as high as 20%, the N value is at most about 30, and the N value 50 is remarkably high.
次に、実施例を挙げて本発明を詳細に説明するが、これは単に例示であって、本発明を制限するものではない。 EXAMPLES Next, although an Example is given and this invention is demonstrated in detail, this is only an illustration and does not restrict | limit this invention.
(実施例1)
外周面には螺旋羽根が付設されておらず、先端には掘削ビットが付設された中空管を使用した。中空管昇降装置は、ラックとピニオンによるものであった。改良地盤は、図1のようなA地盤であった。図1中、砂杭間隔は2m、砂杭径は700mmで改良率は10%であった。また、砂杭長は13mであった。貫入工程は、回転圧入であり、従来の標準条件である1本当たり平均貫入時間10分とした。また、造成工程は、貫入工程よりも長くとり、1本当たり平均造成時間55分(平均貫入時間の5.5倍)とした。また、図1中の符号4の位置でN値を測定した。その結果を表1及び図4の符号x3に示す。表1中、砂杭番号(1)〜(7)は、図5中の符号a〜gにそれぞれ対応する。表1では、「造成工程所要時間/貫入工程所要時間」で表した。なお、図4中、符号X1は施工前の地盤のN値であり、符号X2は改良後の予測された平均N値である。なお、予測されたN値とは、周知の設計値であり、圧入された補給砂の体積と同量だけ地盤が締まると仮定を置き、これと相対密度とN値の経験的な関係を用いて、圧入後のN値を決定するものであり、一般的には、SCP工法の標準的な施工時のN値のデータに基づいた予測式から算出されるものである。図4より、改良後の平均N値は28.2であった。この改良後の平均N値28.2は、図4の符号X2で示される予測平均N値23.8の1.18倍であった。
Example 1
The outer peripheral surface was not provided with a spiral blade, and a hollow tube provided with a drilling bit at the tip was used. The hollow tube lifting device was based on a rack and a pinion. The improved ground was A ground as shown in FIG. In FIG. 1, the sand pile interval was 2 m, the sand pile diameter was 700 mm, and the improvement rate was 10%. Moreover, the sand pile length was 13 m. The penetration process was rotary press-fitting, and the average penetration time was 10 minutes per piece, which is a conventional standard condition. The creation process was longer than the penetration process, and the average creation time per bottle was 55 minutes (5.5 times the average penetration time). Further, the N value was measured at the position of reference numeral 4 in FIG. The results are shown in Table 1 and symbol x3 in FIG. In Table 1, sand pile numbers (1) to (7) respectively correspond to symbols a to g in FIG. In Table 1, it was expressed as “required process time / intrusion process time”. In addition, in FIG. 4, the code | symbol X1 is the N value of the ground before construction, and the code | symbol X2 is the estimated average N value after improvement. The predicted N value is a well-known design value, and it is assumed that the ground is tightened by the same amount as the volume of the supplied replenishment sand, and this is used as an empirical relationship between the relative density and the N value. The N value after press-fitting is determined, and is generally calculated from a prediction formula based on N-value data at the time of standard construction of the SCP method. From FIG. 4, the average N value after improvement was 28.2. The average N value 28.2 after this improvement was 1.18 times the predicted average N value 23.8 indicated by the symbol X2 in FIG.
(実施例2)
砂杭間隔2.0mに代えて1.4mとし、改良率10%に代えて20%とし、且つ下記の貫入時間及び造成時間とした以外は、実施例1と同様の方法で行った。すなわち、実施例2の平均貫入時間は10分、平均造成時間は73分(7.3倍)であった。その結果を表2及び図5の符号Y3に示す。なお、図5中、符号Y1は施工前の地盤のN値であり、符号Y2は改良後の予測された平均N値である。その結果、改良後の平均N値は42.7であり、予測平均N値29.6の1.44倍であった。
(Example 2)
The procedure was the same as in Example 1 except that the distance between sand piles was set to 1.4 m, the improvement rate was changed to 10%, 20%, and the following penetration time and creation time were set. That is, the average penetration time of Example 2 was 10 minutes, and the average creation time was 73 minutes (7.3 times). The results are shown in Table 2 and symbol Y3 in FIG. In addition, in FIG. 5, the code | symbol Y1 is the N value of the ground before construction, and the code | symbol Y2 is the estimated average N value after improvement. As a result, the improved average N value was 42.7, which was 1.44 times the predicted average N value of 29.6.
(実施例3)
A地盤に代えてB地盤とし、砂杭間隔2.0mに代えて1.4mとし、改良率10%に代えて20%とし、砂杭長13mに代えて14mとし、測定対象砂杭(1)〜(7)に代えて砂杭(1)、(2)及び(4)とし、且つ平均造成時間55分に代えて45分とした以外は、実施例1と同様の方法で行った。すなわち、実施例3は、造成工程に要する平均時間を貫入工程に要する平均時間より4.5倍大としたものである。なお、本例では、砂杭の測定点4は、小四角形31の中心とした。測定点4のN値の結果を図6中の符号Z3で示した。なお、Z1は施工前の地盤のN値であり、符号Z2は改良後の予測された平均N値である。
(Example 3)
B ground instead of A ground, 1.4 m instead of 2.0 m between sand piles, 20% instead of 10% improvement rate, 14 m instead of sand pile length 13 m, ) To (7), except that the sand piles (1), (2) and (4) were changed to 45 minutes instead of the average creation time of 55 minutes. That is, in Example 3, the average time required for the creation process is 4.5 times longer than the average time required for the penetration process. In this example, the measurement point 4 of the sand pile is the center of the small square 31. The result of the N value at the measurement point 4 is indicated by the symbol Z3 in FIG. Z1 is the N value of the ground before construction, and Z2 is the predicted average N value after the improvement.
実施例3の平均N値は40であり、図6の符号Z2で示される予測平均N値35の1.14倍であった。また、実施例3は、図6のZ3に示すように、深度8mにおけるN値は、50を超えるものであった。 The average N value in Example 3 was 40, which was 1.14 times the predicted average N value 35 indicated by the symbol Z2 in FIG. In Example 3, the N value at a depth of 8 m exceeded 50 as indicated by Z3 in FIG.
(比較例1)
造成工程における所要時間45分に代えて15分とした以外は、実施例3と同様の方向で行った。すなわち、比較例1の平均造成工程の所要時間は実施例3の1/3であり、貫入工程で要する時間の2.0倍である。その結果を表3に示した。測定点4のN値の結果は、図6の符号Z21のものである。3本の打設砂杭の測定点のN値は34であり、予測平均N値の0.97倍と高くなかった。
(Comparative Example 1)
The test was performed in the same direction as Example 3 except that the required time in the creation process was changed to 45 minutes instead of 45 minutes. That is, the time required for the average creation process of Comparative Example 1 is 1/3 that of Example 3, which is 2.0 times the time required for the penetration process. The results are shown in Table 3. The result of the N value at the measurement point 4 is that of the symbol Z21 in FIG. The N value of the measurement points of the three cast sand piles was 34, which was not as high as 0.97 times the predicted average N value.
(比較例2)
平均造成工程の所要時間45分に代えて6分とした以外は、実施例3と同様の方法で行った。すなわち、比較例1の平均造成工程の所要時間は実施例3の0.13倍である。その結果、測定点4のN値の結果は、図6の符号Z22のものである。図6の結果から、比較例1の平均N値は32であり、予測平均N値の0.91倍と高くなかった。
(Comparative Example 2)
The same procedure as in Example 3 was performed except that the time required for the average creation process was changed to 6 minutes instead of 45 minutes. That is, the time required for the average creation process of Comparative Example 1 is 0.13 times that of Example 3. As a result, the result of the N value at the measurement point 4 is that of the symbol Z22 in FIG. From the results of FIG. 6, the average N value of Comparative Example 1 was 32, which was not as high as 0.91 times the predicted average N value.
なお、実施例1〜3及び比較例1、2の結果を図7にまとめて示した。図7は、A地盤とB地盤について、横軸を「造成時間/貫入時間」とし、縦軸を「予測平均N値を1とした時の平均N値の比」としものである。この結果から、造成時間/貫入時間が3以上、好ましくは4以上で、顕著な改良効果が得られていることが判る。 In addition, the result of Examples 1-3 and Comparative Examples 1 and 2 was put together in FIG. In FIG. 7, the horizontal axis is “creation time / penetration time” and the vertical axis is “ratio of average N values when the predicted average N value is 1” for the A and B grounds. From this result, it can be seen that the formation time / penetration time is 3 or more, preferably 4 or more, and a remarkable improvement effect is obtained.
本発明によれば、パイル間隔を大きく採れるため、周辺に与える地盤変位を抑制することができ、従来施工が困難であった場所でも施工が可能となる。また、従来と同等のパイル間隔で施工した場合、より高い改良効果が得られるため、改良の要求が厳しい条件においても対応が可能となる。 According to the present invention, since a pile interval can be taken large, ground displacement given to the periphery can be suppressed, and construction can be performed even in a place where conventional construction is difficult. In addition, when the construction is performed at the same pile interval as that of the prior art, a higher improvement effect can be obtained, so that it is possible to cope even under severe conditions for improvement.
1 砂杭
4、4a〜4f 改良目標地点
11 中空管
X 改良区画領域
a〜j 砂杭打設予定地
DESCRIPTION OF SYMBOLS 1 Sand pile 4, 4a-4f Improvement target point 11 Hollow pipe X Improvement division area aj Sand pile placing planned site
Claims (4)
該貫入工程後、中空管を適宜の長さ引き抜き、該引き抜き跡に中空管内の砂杭材料を排出する引き抜きと、中空管の打ち戻しを順次、地表に至るまで繰り返す造成工程とを行い軟弱地盤中に複数の締固め砂杭を打設する工法において、
1本の砂杭の打設において、造成工程に要する時間(T2)が、貫入工程に要する時間(T1)の3倍以上となるように、貫入工程と造成工程を行うものであり、
該造成工程は、貫入工程に比べて最大間隙水圧が小となり、締固めに寄与する応力が伝わり易く、密度上昇となることを特徴とする軟弱地盤の改良方法。 An intrusion process for penetrating the hollow tube to a predetermined depth;
After the penetration step, the hollow tube is drawn out to an appropriate length, and a drawing step of discharging sand pile material in the hollow tube to the drawing trace and a creation step of repeating the hollow pipe back-up to the ground surface in order. In the method of placing multiple compacted sand piles in soft ground,
In the placement of one sand pile, the penetration process and the creation process are performed so that the time required for the creation process (T2) is more than three times the time required for the penetration process (T1) .
The method for improving soft ground is characterized in that the creation step has a smaller maximum pore water pressure than the intrusion step, facilitates transmission of stress contributing to compaction, and increases density .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2015210950A JP6466814B2 (en) | 2015-10-27 | 2015-10-27 | How to improve soft ground |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2015210950A JP6466814B2 (en) | 2015-10-27 | 2015-10-27 | How to improve soft ground |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2017082468A JP2017082468A (en) | 2017-05-18 |
| JP6466814B2 true JP6466814B2 (en) | 2019-02-06 |
Family
ID=58712972
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2015210950A Active JP6466814B2 (en) | 2015-10-27 | 2015-10-27 | How to improve soft ground |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP6466814B2 (en) |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS53145310A (en) * | 1977-05-23 | 1978-12-18 | Fudo Construction Co | Method of placing sand pile |
| JP2681821B2 (en) * | 1989-03-04 | 1997-11-26 | 不動建設株式会社 | Construction management system for ground improvement method |
| KR100479563B1 (en) * | 2004-12-29 | 2005-04-06 | (주)초석건설 | Marine large crusher-stone compaction pile method and equipment of, using the auto pressurize device |
| JP5426321B2 (en) * | 2009-10-29 | 2014-02-26 | 五洋建設株式会社 | Sand pile construction method and improved ground in floating sand compaction pile method |
| JP6150289B2 (en) * | 2013-09-24 | 2017-06-21 | 株式会社不動テトラ | Construction management method in compacted sand pile method |
-
2015
- 2015-10-27 JP JP2015210950A patent/JP6466814B2/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| JP2017082468A (en) | 2017-05-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104912076B (en) | A static pile press complete machine is planted in a kind of reaming | |
| JP5932124B1 (en) | Steel pipe pile construction method | |
| CN102677658A (en) | Pile construction method and pile casings | |
| JP2023105455A (en) | Compaction soil improvement method | |
| CN206681671U (en) | A kind of jackstone stratigraphical drilling device | |
| JP2008175012A (en) | Cast-in-place pile construction method and construction apparatus | |
| JP6466814B2 (en) | How to improve soft ground | |
| JP4430975B2 (en) | Grounding device construction method | |
| CN102777146A (en) | Downhole junk overshot | |
| JP7139277B2 (en) | Compaction soil improvement method | |
| RU2014117507A (en) | DRILLING PILES IN A BROKEN WELL WITH AN EXTENDED BASE | |
| JP2018076663A (en) | Displacement-reduced compacted sand pile hollow tube and compacted sand pile construction method | |
| CN105297732A (en) | Slagging promoting device for ultra-thick clay layer positive-cycle cast-in-place pile and construction method of slagging promoting device | |
| JP6432987B2 (en) | How to improve soft ground | |
| CN105133568A (en) | Improved dynamic compaction hammer | |
| KR102521610B1 (en) | Multi casing perforation device | |
| RU2551590C1 (en) | Method to produce root piles | |
| CN102644285A (en) | Anti-collapse hole construction method for anchor drilling | |
| EP1719841A1 (en) | Method and equipment for constructing micropiles in soil | |
| CN104278680A (en) | Envelope structure combining five (six) shaft mixing piles with press grouting piles and construction method | |
| CN106812464A (en) | A kind of rotary digging static pressure bar | |
| CN107386263B (en) | A kind of construction method of collapsible loess large-diameter compaction pile | |
| CN106192980A (en) | A kind of method of dither closely knit sandstone ground | |
| CN203487527U (en) | Novel visual intelligent extra-liquid concrete cast-in-place pile device | |
| JP2018059285A (en) | Hollow tube for displacement-reduced type compacting sand-pile creation and compacting sand-pile creating method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| RD02 | Notification of acceptance of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7422 Effective date: 20170612 |
|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20180208 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20181019 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20181031 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20181217 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20190108 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20190110 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 6466814 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |