JP6635591B2 - Post foundation - Google Patents
Post foundation Download PDFInfo
- Publication number
- JP6635591B2 JP6635591B2 JP2016013312A JP2016013312A JP6635591B2 JP 6635591 B2 JP6635591 B2 JP 6635591B2 JP 2016013312 A JP2016013312 A JP 2016013312A JP 2016013312 A JP2016013312 A JP 2016013312A JP 6635591 B2 JP6635591 B2 JP 6635591B2
- Authority
- JP
- Japan
- Prior art keywords
- core member
- final
- shape
- core
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Foundations (AREA)
Description
本発明は、例えば列車あるいは電車の線路の脇において敷設される信号機柱などの支柱を支持する基礎であって、特に現場にて、基礎用ブロック搬入後、組立て可能に構成された支柱用組立基礎に関するものである。
The present invention relates to a foundation for supporting a pillar such as a signal pole laid on the side of a train or a train track, for example, and particularly to a pillar assembling base that can be assembled after loading a foundation block at a site. It is about.
従来、例えば、高架化区間において信号機柱などを立設する際は、前記信号機を立設する構築場所の例えば、コンクリート床版を削り、削った箇所にコンクリートを流し込み、これを前記信号機用の基礎と使用していた。 Conventionally, for example, when erecting a signal pillar or the like in an elevated section, for example, a concrete floor slab of a construction place where the signal is to be erected is cut, concrete is poured into the shaved portion, and this is used as a base for the signal. And had used.
しかしながらこの様な基礎の現場施工であると、前記コンクリートの養生、固化のための一定の期間が必要となる。
しかも、前記基礎の現場構築作業は土木工事となり、通常は土木担当箇所に施工の委託を行い、この基礎の現場構築をし、その後、信号機立設担当箇所が別途信号機柱などの立設作業を行わなければならなかった。
However, such an on-site construction of a foundation requires a certain period for curing and solidifying the concrete.
Moreover, the site construction work of the foundation is civil engineering work, and the construction is usually entrusted to a site in charge of civil engineering, and the site construction of this foundation is performed. Had to do.
そのため、委託・施工などの調整に時間を要すると共に、例えば、信号機柱など1柱あたりにかかる基礎の単価も高くなってしまうとの課題があった。
For this reason, there is a problem that it takes time for adjustment such as commissioning and construction, and that the unit price of the foundation per pillar, such as a signal pole, becomes high.
かくして、本発明は前記従来からの課題を解決するために創案されたものであり、前記基礎の現場施工を行わないものとし、もってコンクリートの養生、固化のための一定の期間を必要とせず、前記基礎の現場構築作業が信号機立設担当箇所で行え、そのため、委託・施工などの調整に時間を要せず、信号機柱など1柱あたりにかかる基礎の単価を安価にしうる支柱用組立基礎を提供することを目的とするものである。
Thus, the present invention has been devised to solve the above-mentioned conventional problems, and does not perform the on-site construction of the foundation, so that curing of concrete does not require a certain period for solidification, The site construction work of the foundation can be performed at the signal signal erecting place, and therefore, it does not require time for adjustment such as consignment and construction, and a pillar assembling foundation that can reduce the unit price of the foundation per pillar such as a signal pillar. It is intended to provide.
本発明は、
基体部が立体状をなし、該基体部の中央には立体状の突出部を有し、側面形状が段差部を有する形状とされるコア部材と、前記コア部材の側面に密接する形状を一側面に有する最終連結用部材と、を有し
前記コア部材と最終連結用部材との間に、前記コア部材の側面に密接する形状を一側面に有し、他側面は前記コア部材の段差部を有する側面形状と同様の形状に構成された連結用部材を少なくとも1以上有する、
ことを特徴とし、
または、
前記コア部材、連結用部材及び最終連結用部材の全てが、あるいはそのうちの一部材が、あるいはそのうちの二部材がコンクリート部材で構成された、
ことを特徴とし、
または、
前記コア部材、連結用部材及び最終連結用部材は締結部材により締結され、一体化される、
ことを特徴とし、
または、
前記連結用部材及び最終連結部材は、コア部材の対向する二側面に連結され、略直方体状の形状に構成される、
ことを特徴とし、
または、
前記連結用部材及び最終連結部材はコア部材の対向する四側面に連結され、略十字状の形状に構成される、
ことを特徴とするものである。
The present invention
The base member has a three-dimensional shape, a core member having a three-dimensional protrusion at the center of the base portion, and a side member having a stepped portion, and a core member closely contacting the side surface of the core member. And a final connection member on the side surface.
Between the core member and the final connection member, one side has a shape closely contacting the side surface of the core member, and the other side surface has a shape similar to the side surface shape having a step portion of the core member. Having at least one or more connecting members,
Characterized in that
Or
All of the core member, the connection member and the final connection member, or one of them, or two of them were formed of concrete members,
Characterized in that
Or
The core member, the connecting member and the final connecting member are fastened by a fastening member and integrated,
Characterized in that
Or
The connection member and the final connection member are connected to two opposing side surfaces of the core member, and are configured in a substantially rectangular parallelepiped shape.
Characterized in that
Or
The connection member and the final connection member are connected to four opposing side surfaces of the core member, and are configured in a substantially cross shape.
It is characterized by the following.
本発明による支柱用組立基礎であれば、基礎の現場施工を行わないため、コンクリートの養生、固化のための一定の期間を必要とせず、もって前記基礎の現場構築作業が信号機立設担当箇所のみで行え、そのため、他の部署への委託・施工などの調整に時間を要せず、信号機柱など1柱あたりにかかる基礎の単価を安価にしうるとの優れた効果を奏する。
In the case of the pillar assembling foundation according to the present invention, since the on-site construction of the foundation is not performed, the curing of the concrete does not require a certain period for solidification, so that the on-site construction of the foundation is performed only at the signal signal erecting part. Therefore, there is an excellent effect that it is possible to reduce the unit cost of the foundation per one pillar such as a signal pillar without requiring time for commissioning and construction to other departments.
以下、本発明の実施例を図に基づいて説明する。 Hereinafter, embodiments of the present invention will be described with reference to the drawings.
図3、図4に本発明の構成部材である、通常はコンクリート部材よりなるコア部材1を示す。
コア部材1は、その基体部2が四角体状をなし、該基体部2の中央部には前記基体部2の形状より小さい四角体状の突出部3を有して断面略凸条の形状をなして構成されている。尚、基体部2、突出部3について、その形状は四角体形状に限定されず、立体形状であればよい。
3 and 4 show a core member 1 which is a component of the present invention and is usually made of a concrete member.
The core member 1 has a
そして、図3、図4から理解出来る様に、コア部材1の前後左右、すなわち四方向の側面形状は、階段状の段差部4が高さ方向略中間部に設けられた曲面形状とされている。
As can be understood from FIGS. 3 and 4, the front, rear, left, and right sides of the core member 1, that is, the side surfaces in the four directions are curved surfaces in which a
次に、図5、図6にコンクリート部材よりなる連結用部材5を示す。該連結用部材5は、前述したコア部材1の曲面形状をなす側面に密接する形状、すなわち第1曲面形状6を一側面に有し、他側面には、前記コア部材1の段差部4を有する側面形状と同様の形状に構成された第2曲面形状7を有して構成されている。
Next, FIGS. 5 and 6 show the connecting
さらに、図7、図8に、コンクリート部材よりなる最終連結用部材8を示す。
7 and 8 show a
ここで、最終連結用部材8は、前記コア部材1の側面に密接する形状、すなわち、第1曲面形状6を一側面に有し、他側面には第2曲面形状7を有することのない部材として構成されている。例えば、フラットな面での垂直側面として構成される。
Here, the final connecting
本発明の支柱用組立基礎は、前記コア部材1、コア部材1に1個あるいは複数個連結される連結用部材5、及びコア部材1や連結用部材5に連結される最終連結用部材8をあらかじめ工場で大量生産しておき、これらを必要な分だけ設置箇所まで運搬し、設置箇所でこれらを連結し、組み立てて構成されるものとなる。
The column assembly base of the present invention includes the core member 1, one or more connecting
図1及び図2は、コア部材1を1個、連結用部材5をコア部材1の左右方向に2個ずつ、及び最終連結用部材8を左右に1個ずつ連結して、本発明の支柱用組立基礎を組み立てた具体例である。
FIGS. 1 and 2 show a pillar of the present invention in which one core member 1, two connecting
ここで、連結用部材5は左右方向に2個ずつ設置する場合に限定されるものではなく、コア部材1の左右方向に1個ずつ設置した場合でも構わないし、左右方向に2個以上連結して設置しても構わない。
Here, the connecting
当該支柱用組立基礎の上に立設される信号機19などの大きさによって連結用部材5などの連結数を変更することが出来るものとなっている。すなわち、基礎上に立設される信号機19などが風などにより、倒れない重量の基礎にすることが大切なのである。よって、信号機19が大型化すれば、連結用部材5の連結数も増加するものとなる。
The number of the connecting
尚、図1、図2、図9及び図10において、符号9は、第2最終連結用部材であり、該第2最終連結要部材9は、図1に示すようにコア部材1の前後方向の側面段差部4上に連結するものとなる。よって、本発明による支柱用組立基礎は、図1、図2から理解出来る様に略直方体状をなすものとなる。
1, 2, 9, and 10,
尚、コア部材1の前後方向側面に、前述した左右方向に連結する連結用部材5と同様の形状をした第2連結用部材を用意し、これらを連結すれば、略十字状をなす形状の支柱用組立基礎に形成することも出来る。十字状に張り出した基礎であればその上に立設する信号機19などの支柱を、さらに倒れることなく支持することが出来るものとなる。
A second connecting member having the same shape as the connecting
次に、コア部材1、連結用部材5及び最終連結部材8、第2最終連結部材9の連結、組立につき説明する。
Next, connection and assembly of the core member 1, the connecting
前記の連結、組立については、ボルト10及びナット11等の締結具を用いて行われる。
図2に示される様に、コア部材1とその左右方向両側に連結される連結用部材5は、長尺のボルト10とナット11を用いてまず、垂直方向に向かって連結される。
The connection and assembly are performed using fasteners such as
As shown in FIG. 2, the core member 1 and the connecting
すなわち、コア部材1の左右方向段差部4には、各々雌ねじ部12がその開口を上方に向けて埋設、固着されており、該雌ねじ部12に長尺のボルト10の基端を螺合させるものとなる。
That is, the
すなわち、前記ボルト10を垂直方向に向かって設けられた連結用部材5の挿通孔13内に挿入し、貫通させた後、前記長尺のボルト10基端を前記雌ねじ部12に螺合させ、次いで、ボルト10の先端にナット11を螺合して締結し、コア部材1と連結用部材5を垂直方向に向かって連結するのである。
That is, after inserting the
そして、この連結方法は、連結用部材5と連結用部材5との連結、連結用部材5と最終連結用部材8との連結、さらにはコア部材1と第2最終連結部材9との連結に用いられている。
This connecting method is used for connecting the connecting
また、図1に示されるように、コア部材1とその左右方向両側に連結される連結用部材5は、第2ボルト14と第2雌ねじ部15によって水平方向においても連結される。
As shown in FIG. 1, the core member 1 and the connecting
すなわち、コア部材1の左右側面には、各々第2雌ねじ部15がその開口を水平方向に向け、かつ斜めに向けて埋設、固着されており、該第2雌ねじ部15に第2ボルト14の基端を螺合させて連結するものとなる。
That is, on the left and right side surfaces of the core member 1, the second
すなわち、前記第2ボルト14を水平方向に向かって設けられた連結用部材5の第2挿通孔16内に挿入し、貫通させた後、前記第2ボルト14の基端を前記第2雌ねじ部15に螺合させて締結し、コア部材1と連結用部材5を水平方向においても強固に連結するのである。
That is, after inserting and penetrating the
そして、この連結方法は、連結用部材5と連結用部材5との連結、連結用部材5と最終連結用部材8との連結に用いられる。
This connection method is used for connection between the
ところで、符号17は吊り上げ用雌ねじ部であり、コア部材1、連結用部材5、最終連結用部材8、第2最終連結用部材9の上面に、その開口を上方に向けた状態で埋設、固着されている。当該吊り上げ用雌ねじ部17は、コア部材1、連結用部材5、最終連結用部材8、第2最終連結用部材9を運搬して所定の設置箇所に移動する際に用いられる。
すなわち、高架橋上の線路脇などの設置箇所に前記のコア部材1、連結用部材5、最終連結用部材8、第2最終連結用部材9を運搬する際、前記吊り上げ用雌ねじ部17に吊り上げ部材を螺合し、連結した後、重機などで前記コア部材1などを吊り上げて運搬するのである。この様に、あらかじめ吊り上げ用雌ねじ部17を前記コア部材1、連結用部材5、最終連結用部材8、第2最終連結用部材9の上面に埋設、固着しておけば、これらを簡単に吊り上げて運搬することが出来る。
That is, when the core member 1, the connecting
次に、図2に示すように、コア部材1には先端が上方に向かって露出し突出しているアンカー部材18が埋設されている。
Next, as shown in FIG. 2, an
このアンカー部材18の先端が例えば雄ねじ状に構成されてなり、この先端部分について図11に示す信号機19のベース20を貫通させると共に、ナットなどにより締結し、コア部材1の上面に信号機19等の支柱を立設することになる。
The distal end of the
以上、現在、高架化区間において、例えば信号機柱などを建植する際は、前述した様に、土木担当箇所に施工委託を行い施工を進めている。そのため、委託・施工などの調整に時間を要すると共に、1柱あたりにかかる基礎の単価も高いものとなっていた。 As described above, at the time of, for example, building a signal pole or the like in an elevated section, as described above, the construction is entrusted to a location in charge of civil engineering, and construction is proceeding. For this reason, it takes time to make adjustments such as commissioning and construction, and the unit cost of the foundation per pillar is also high.
一方、本発明の支柱用組立基礎については、設置箇所においてのコア部材1などの各ブロックの連結、組立のみで作製でき、生コンクリートを用いての基礎の施工と比較して、非常に容易な施工が可能となった。 On the other hand, the column assembling foundation of the present invention can be manufactured only by connecting and assembling the blocks such as the core member 1 at the installation location, and is very easy to perform compared to the construction of the foundation using ready-mixed concrete. Construction is now possible.
尚、信号機柱用など支柱用組立基礎については、以下に留意する必要がある。 In addition, it is necessary to pay attention to the following regarding the assembling foundation for columns such as those for signal poles.
すなわち、信号機柱の転倒を防止するにあたり、可能な限り、アンカーを使用しないものとした。むやみにアンカーを用いると、高架中の鉄筋を傷つける恐れがあるからである。 That is, in preventing the signal pole from overturning, the anchor was not used as much as possible. If the anchor is used indiscriminately, there is a risk that the reinforcing steel on the elevated road may be damaged.
よって、高密度コンクリート等を使用し、基礎の重さで転倒防止を実現するものとした。これによらずアンカーを使用する場合は、高架中の鉄筋を傷つけないようにアンカーの本数・径を可能な限り小さくする。 Therefore, high-density concrete or the like is used, and the fall of the foundation is realized by the weight of the foundation. If an anchor is used regardless of this, the number and diameter of the anchors should be made as small as possible so as not to damage the reinforcing bars on the elevated tracks.
次に、従来と比較し、重心の高い信号機においても風圧強度を維持できるものとする。すなわち、コア部材1に連結する連結用部材5などの連結数を増加させて重量を増加させ、これにより風圧強度を高める。
Next, it is assumed that the wind pressure intensity can be maintained even at a traffic signal having a high center of gravity as compared with the related art. That is, the number of connecting
さらに、組立ブロック、すなわちコア部材1、連結用部材5、最終連結用部材8、第2最終連結用部材9などのひとつ当たりの重さ・大きさ等は、搬入が容易となる程度とすることが重要である。
Furthermore, the weight, size, and the like of each of the assembly blocks, that is, the core member 1, the connecting
また、施工後は、耐震性、腐食、風化に強い永久設備となる耐久性を持たせるものとする。 In addition, after construction, it shall have durability to be a permanent facility that is strong against earthquake, corrosion and weathering.
さらに、コア部材1、連結用部材5、最終連結用部材8、第2最終連結用部材9を連結するボルト10、第2ボルト14の引抜き強度も永久設備となる程の耐久性を持たせることが好ましい。
Further, the pull-out strength of the
1 コア部材
2 基体部
3 突出部
4 段差部
5 連結用部材
6 第1曲面形状
7 第2曲面形状
8 最終連結用部材
9 第2最終連結用部材
10 ボルト
11 ナット
12 雌ねじ部
13 挿通孔
14 第2ボルト
15 第2雌ねじ部
16 第2挿通孔
17 吊り上げ用雌ねじ部
18 アンカー部材
19 信号機
20 ベース
DESCRIPTION OF SYMBOLS 1
Claims (5)
前記コア部材と最終連結用部材との間に、前記コア部材の側面に密接する形状を一側面に有し、他側面は前記コア部材の段差部を有する側面形状と同様の形状に構成された連結用部材を少なくとも1以上有する、
ことを特徴とする支柱用組立基礎。
The base member has a three-dimensional shape, a core member having a three-dimensional protrusion at the center of the base portion, and a side member having a stepped portion, and a core member closely contacting the side surface of the core member. And a final connection member on the side surface.
Between the core member and the final connection member, one side has a shape closely contacting the side surface of the core member, and the other side surface has a shape similar to the side surface shape having a step portion of the core member. Having at least one or more connecting members,
An assembling base for a support, characterized in that:
ことを特徴とする請求項1記載の支柱用組立基礎。
All of the core member, the connection member and the final connection member, or one of them, or two of them were formed of concrete members,
The support base assembly according to claim 1, wherein:
ことを特徴とする請求項1または請求項2記載の支柱用組立基礎。
The core member, the connecting member and the final connecting member are fastened by a fastening member and integrated,
An assembly base for a column according to claim 1 or 2, wherein:
ことを特徴とする請求項1、請求項2または請求項3記載の支柱用組立基礎。
The connection member and the final connection member are connected to two opposing side surfaces of the core member, and are configured in a substantially rectangular parallelepiped shape.
The supporting base assembly according to claim 1, 2 or 3, wherein
ことを特徴とする請求項1、請求項2、請求項3または請求項4記載の支柱用組立基礎。
The connection member and the final connection member are connected to four opposing side surfaces of the core member, and are configured in a substantially cross shape.
The support base assembly according to claim 1, 2, 3, or 4, wherein:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2016013312A JP6635591B2 (en) | 2016-01-27 | 2016-01-27 | Post foundation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2016013312A JP6635591B2 (en) | 2016-01-27 | 2016-01-27 | Post foundation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2017133219A JP2017133219A (en) | 2017-08-03 |
| JP6635591B2 true JP6635591B2 (en) | 2020-01-29 |
Family
ID=59503979
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2016013312A Active JP6635591B2 (en) | 2016-01-27 | 2016-01-27 | Post foundation |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP6635591B2 (en) |
Family Cites Families (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS496168Y1 (en) * | 1970-12-09 | 1974-02-13 | ||
| JPS533562B2 (en) * | 1974-01-31 | 1978-02-08 | ||
| JPS547365Y2 (en) * | 1977-04-27 | 1979-04-06 | ||
| JP3443739B2 (en) * | 2001-07-09 | 2003-09-08 | 大成建設株式会社 | Foundation construction method, footing foundation and foundation structure of elevated traffic route |
| JP2007023642A (en) * | 2005-07-19 | 2007-02-01 | Yoshinobu Hayashi | Support block structure of column member |
| JP4229976B1 (en) * | 2008-03-19 | 2009-02-25 | アオイネオン株式会社 | Foundation structure |
| JP5140475B2 (en) * | 2008-03-28 | 2013-02-06 | 積水樹脂株式会社 | Block for foundation |
| ES2448769T3 (en) * | 2008-11-03 | 2014-03-17 | Siemens Aktiengesellschaft | Foundation, particularly for a wind turbine, and wind turbine |
| JP2011179213A (en) * | 2010-03-01 | 2011-09-15 | Koken Sangyo Kk | Foundation structure using concrete block |
| MX357895B (en) * | 2012-08-03 | 2018-07-27 | Wind Tower Tech Llc | Precast concrete post tensioned segmented wind turbine tower. |
| JP2014169551A (en) * | 2013-03-01 | 2014-09-18 | Chugoku Electric Power Co Inc:The | Block for foundation construction of structure |
-
2016
- 2016-01-27 JP JP2016013312A patent/JP6635591B2/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| JP2017133219A (en) | 2017-08-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR20170072080A (en) | Cantilever part for bridge and constructing method thereof | |
| CN210239246U (en) | A wide flat beam type prefabricated railway platform concrete canopy | |
| CN103572706A (en) | Assembled type reinforced concrete bridge construction technology | |
| KR101601675B1 (en) | The construction method of multicomposite Rahmen bridge | |
| KR20230014578A (en) | Insirt Anchor System for the reduction of the upper floor's life noises and upper re-bar supporter with levelling function | |
| KR101036177B1 (en) | Construction method of building structure using PPC composite method | |
| JP6283906B2 (en) | Prop foundation | |
| JP6635591B2 (en) | Post foundation | |
| CN103967332A (en) | Construction method of building site barrier | |
| JPH07247557A (en) | Foundation, column mold, and underground beam made of precast reinforced concrete | |
| CN216108042U (en) | Concrete track bridge pillar system | |
| CN218263963U (en) | A prefabricated foundation for transmission lines | |
| CN211421937U (en) | Column bearing type viewing platform | |
| US9051708B2 (en) | Tower foundation | |
| CN211646965U (en) | Reinforced column base of viewing platform | |
| CN202227281U (en) | Triangular bracket for constructing zero block by box girder cantilever | |
| KR101189041B1 (en) | Soundproofing walls using piles for constructing foundation and supporting posts and construction method the same | |
| KR101103680B1 (en) | Architectural Slab with Arch Support Ribs | |
| KR100955612B1 (en) | Construction for underground parking lot and constructing method thereof | |
| JPH0371537B2 (en) | ||
| CN114411974A (en) | Building shock insulation support connecting node and construction method thereof | |
| KR101594781B1 (en) | H Steel pole for traffic facility with type prop | |
| CN207331470U (en) | A kind of embedded box anchors assembled bracket | |
| CN219548588U (en) | Artistic cement enclosure column | |
| CN205088700U (en) | Assembled concrete foundation system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20181219 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20191007 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20191105 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20191129 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20191216 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20191216 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 6635591 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
| R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |