JP6826864B2 - Restoration method of existing foundation and restoration structure of existing foundation - Google Patents
Restoration method of existing foundation and restoration structure of existing foundation Download PDFInfo
- Publication number
- JP6826864B2 JP6826864B2 JP2016216257A JP2016216257A JP6826864B2 JP 6826864 B2 JP6826864 B2 JP 6826864B2 JP 2016216257 A JP2016216257 A JP 2016216257A JP 2016216257 A JP2016216257 A JP 2016216257A JP 6826864 B2 JP6826864 B2 JP 6826864B2
- Authority
- JP
- Japan
- Prior art keywords
- existing
- foundation
- improvement body
- ground improvement
- existing foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
本発明は、既存基礎の復元方法及び既存基礎の復元構造に関する。 The present invention relates to a method for restoring an existing foundation and a structure for restoring an existing foundation.
特許文献1には、薬液注入によって改良した改良部の外周部の下に、高圧噴射攪拌によって改良部を形成する工法が開示されている。 Patent Document 1 discloses a method of forming an improved portion by high-pressure jet stirring under the outer peripheral portion of the improved portion improved by injecting a chemical solution.
特許文献2には、深層混合処理工法によって第1地盤改良体を構築した後、鉛直ジェットグラウト工法によって第1地盤改良体の下に追加地盤改良体を構築する工法が開示されている。 Patent Document 2 discloses a method of constructing a first ground improvement body by a deep mixing treatment method and then constructing an additional ground improvement body under the first ground improvement body by a vertical jet grout method.
ここで、液状化等によって沈下した基礎梁等の既存基礎とその下の既存地盤改良体との間にモルタルを注入することで、既存基礎を押し上げ、沈下した既存基礎を復元する技術が知られている。 Here, a technique is known in which mortar is injected between an existing foundation such as a foundation beam that has subsided due to liquefaction and an existing ground improvement body underneath to push up the existing foundation and restore the subsided existing foundation. ing.
しかし、この工法では、既存基礎の下にある既存地盤改良体が、モルタルの注入圧によって、沈下すると、既存基礎の復元が困難になる。 However, in this construction method, if the existing ground improvement body under the existing foundation sinks due to the injection pressure of mortar, it becomes difficult to restore the existing foundation.
本発明は、上記事実に鑑み、既存地盤改良体の沈下を抑制し、その上の沈下した既存基礎を押し上げて復元することが目的である。 In view of the above facts, it is an object of the present invention to suppress the subsidence of the existing ground improvement body and to push up and restore the subsided existing foundation on the existing ground improvement body.
第一態様は、沈下した既存基礎の下に構築された既存地盤改良体の直下に、新設地盤改良体を構築する工程と、前記既存基礎と前記既存地盤改良体との間に注入材を注入し、前記既存基礎を押し上げて復元する工程と、を備える既存基礎の復元方法である。 The first aspect is a step of constructing a new ground improvement body directly under the existing ground improvement body constructed under the subsided existing foundation, and injecting an injection material between the existing foundation and the existing ground improvement body. It is a method of restoring an existing foundation, which comprises a step of pushing up and restoring the existing foundation.
第一態様の復元方法では、既存基礎の下に構築された既存地盤改良体の直下に新設地盤改良体を構築し、地盤が補強されている。よって、既存基礎と既存地盤改良体との間に注入材を注入したときの注入圧による、既存地盤改良体の沈下が抑制される。したがって、注入圧による既存地盤改良体の沈下を抑制し、その上の沈下した既存基礎を押し上げて復元することができる。 In the restoration method of the first aspect , a new ground improvement body is constructed directly under the existing ground improvement body constructed under the existing foundation, and the ground is reinforced. Therefore, the subsidence of the existing ground improvement body due to the injection pressure when the injection material is injected between the existing foundation and the existing ground improvement body is suppressed. Therefore, it is possible to suppress the subsidence of the existing ground improvement body due to the injection pressure and push up the existing subsidence foundation on it to restore it.
第二態様は、前記新設地盤改良体は、高圧噴射撹拌工法によって地盤改良して構築する、第一態様に記載の既存基礎の復元方法である。 The second aspect is the method for restoring the existing foundation according to the first aspect , wherein the newly constructed ground improvement body is constructed by improving the ground by a high-pressure injection stirring method.
第二態様の復元方法では、高圧噴射撹拌工法を用いることで、既存地盤改良体の直下を容易に地盤改良して新設地盤改良体を構築することができる。 In the restoration method of the second aspect, by using the high-pressure injection stirring method, it is possible to easily improve the ground directly under the existing ground improvement body to construct a new ground improvement body.
第三態様は、既存基礎と、前記既存基礎の下に構築された既存地盤改良体と、前記既存基礎の直下に構築された新設地盤改良体と、前記既存基礎と前記既存地盤改良体との間に注入された注入材と、を備える既存基礎の復元構造である。 The third aspect is the existing foundation, the existing ground improvement body constructed under the existing foundation, the new ground improvement body constructed directly under the existing foundation, and the existing foundation and the existing ground improvement body. It is a restored structure of an existing foundation with an injection material injected in between.
第三態様の復元構造では、既存基礎の下に構築された既存地盤改良体の直下に新設地盤改良体が構築され、地盤が補強されている。よって、既存基礎と既存地盤改良体との間に注入材を注入したときの注入圧による、既存地盤改良体の沈下が抑制されている。したがって、沈下した既存基礎が、注入圧によって押し上げられ復元される。 In the restoration structure of the third aspect , a new ground improvement body is constructed directly under the existing ground improvement body constructed under the existing foundation, and the ground is reinforced. Therefore, the subsidence of the existing ground improvement body due to the injection pressure when the injection material is injected between the existing foundation and the existing ground improvement body is suppressed. Therefore, the existing subsided foundation is pushed up and restored by the injection pressure.
本発明によれば、既存地盤改良体の沈下を抑制し、その上の沈下した既存基礎を押し上げて復元することができる。 According to the present invention, it is possible to suppress the subsidence of the existing ground improvement body and push up the subsided existing foundation on the existing ground improvement body to restore it.
<実施形態>
本発明の一実施形態の既存基礎の復元構造及び既存基礎の復元方法について説明する。
<Embodiment>
The restoration structure of the existing foundation and the restoration method of the existing foundation according to the embodiment of the present invention will be described.
[復元構造]
まず、地盤の液状化等によって沈下した既存基礎が復元された状態(復元構造)について説明する。
[Restoration structure]
First, a state (restoration structure) in which an existing foundation that has subsided due to liquefaction of the ground has been restored will be described.
図1に示すように、地盤10に構築された既存基礎の一例としての基礎30の下には、既存の地盤改良体40(以降「既存地盤改良体40」と記す)が構築されている。基礎30には、一階のスラブ12及び柱16が接合され支持されている。また、柱16には、二階のスラブ18を支持する梁20が接合されている。なお、本実施形態では、基礎30は鉄筋コンクリート造で、柱16及び梁20は鉄骨造であるが、これらに限定されるものではない。 As shown in FIG. 1, an existing ground improvement body 40 (hereinafter referred to as “existing ground improvement body 40”) is constructed under the foundation 30 as an example of the existing foundation constructed on the ground 10. A slab 12 and a pillar 16 on the first floor are joined and supported on the foundation 30. Further, a beam 20 for supporting the slab 18 on the second floor is joined to the pillar 16. In the present embodiment, the foundation 30 is made of reinforced concrete, and the columns 16 and beams 20 are made of steel, but the present invention is not limited thereto.
想定以上の大地震等により地盤10における既存地盤改良体40の下部が液状化し、基礎30及び既存地盤改良体40が沈下している。沈下した状態の既存地盤改良体40の直下には、新設の地盤改良体50(以降「新設地盤改良体50」と記す)が構築されている。 The lower part of the existing ground improvement body 40 in the ground 10 is liquefied due to a large earthquake or the like larger than expected, and the foundation 30 and the existing ground improvement body 40 are subsided. A new ground improvement body 50 (hereinafter referred to as "new ground improvement body 50") is constructed directly under the existing ground improvement body 40 in the subsided state.
そして、基礎30と既存地盤改良体40との間には、注入材の一例としてのモルタル60が注入され、注入圧によって基礎30が押し上げられ、設計GLに復元されている。 Then, a mortar 60 as an example of the injection material is injected between the foundation 30 and the existing ground improvement body 40, and the foundation 30 is pushed up by the injection pressure and restored to the design GL.
図1及び図2に示すように、基礎30には、モルタル60を注入する注入孔32があけられている。また、既存地盤改良体40は、互いにラップ若しくは接した複数の円柱状改良体42で構成されている。なお、図2は、断面を表す斜線(ハッチング)の図示を省略している。 As shown in FIGS. 1 and 2, the foundation 30 is provided with an injection hole 32 for injecting the mortar 60. Further, the existing ground improvement body 40 is composed of a plurality of columnar improvement bodies 42 that are wrapped or in contact with each other. Note that FIG. 2 omits the illustration of diagonal lines (hatching) representing the cross section.
また、図4に示すように、新設地盤改良体50は、互いにラップした複数の平面視扇状の扇状改良体52(図3も参照)で構成されている。 Further, as shown in FIG. 4, the newly constructed ground improvement body 50 is composed of a plurality of fan-shaped improvement bodies 52 (see also FIG. 3) that are wrapped around each other.
[復元方法]
つぎに、地盤10の液状化等によって沈下した基礎30を復元させる復元方法の一例について説明する。
[Restoration method]
Next, an example of a restoration method for restoring the foundation 30 that has subsided due to liquefaction of the ground 10 or the like will be described.
図5(A)に示すように、基礎30及び既存地盤改良体40が地盤10に構築されている。基礎30には、一階のスラブ12及び柱16が接合され支持されている。また、柱16には、二階のスラブ18を支持する梁20が接合されている。 As shown in FIG. 5A, the foundation 30 and the existing ground improvement body 40 are constructed on the ground 10. A slab 12 and a pillar 16 on the first floor are joined and supported on the foundation 30. Further, a beam 20 for supporting the slab 18 on the second floor is joined to the pillar 16.
そして、想定以上の大地震等により地盤10における既存地盤改良体40の下部が液状化し、基礎30及び既存地盤改良体40が不同沈下している。よって、一階のスラブ12は1FL(設計GL)よりも下側に位置し、また二階のスラブ18は2FLよりも下側に位置している。 Then, the lower part of the existing ground improvement body 40 in the ground 10 is liquefied due to a larger earthquake or the like than expected, and the foundation 30 and the existing ground improvement body 40 are subsided unevenly. Therefore, the slab 12 on the first floor is located below 1FL (design GL), and the slab 18 on the second floor is located below 2FL.
図5(B)に示すように、沈下した状態の既存地盤改良体40の直下に新設地盤改良体50を構築する。本実施形態では、新設地盤改良体50は、高圧噴射撹拌工法によって地盤改良して構築している。なお、高圧噴射撹拌工法については後述する。 As shown in FIG. 5 (B), the new ground improvement body 50 is constructed directly under the existing ground improvement body 40 in the subsided state. In the present embodiment, the newly constructed ground improvement body 50 is constructed by improving the ground by a high-pressure injection stirring method. The high-pressure injection stirring method will be described later.
図6(A)に示すように、JOG(ジャッキング オフ グラウト)工法によって、基礎30を復元する。 As shown in FIG. 6A, the foundation 30 is restored by the JOG (jacking off grout) method.
具体的には、基礎30にモルタル60を注入する注入孔32をあける(図2も参照)。この注入孔32から図示していない注入管を差し込んで基礎30と既存地盤改良体40との間にモルタル60を注入する。そして、モルタル60の注入圧によって基礎30を押し上げ、一階のスラブ12を1FL(設計GL)に復元し、また二階のスラブ18を2FLに復元する。 Specifically, an injection hole 32 for injecting the mortar 60 is formed in the foundation 30 (see also FIG. 2). An injection pipe (not shown) is inserted through the injection hole 32 to inject the mortar 60 between the foundation 30 and the existing ground improvement body 40. Then, the foundation 30 is pushed up by the injection pressure of the mortar 60, the slab 12 on the first floor is restored to 1FL (design GL), and the slab 18 on the second floor is restored to 2FL.
このとき、既存地盤改良体40の直下に新設地盤改良体50を構築し、地盤10を補強しているので、注入圧による既存地盤改良体40の沈下が抑制される。 At this time, since the new ground improvement body 50 is constructed directly under the existing ground improvement body 40 to reinforce the ground 10, the subsidence of the existing ground improvement body 40 due to the injection pressure is suppressed.
なお、本実施形態では、沈下した地盤10と一階のスラブ12との間には、隙間11ができる。また、図1は、この図6(A)の状態を図示している。 In the present embodiment, a gap 11 is formed between the subsided ground 10 and the slab 12 on the first floor. Further, FIG. 1 illustrates the state of FIG. 6 (A).
図6(B)に示すように、注入孔32を埋める。また、基礎30と柱16との接合部位17を補修する。補修内容は、基礎30と柱16と接合部位が不同沈下によって生じたひび割れ等への補修材の圧入や基礎30の鉄筋が露出する等の被害が大きい部分を斫つり取って新たに型枠を設けての断面の修復等である。 As shown in FIG. 6B, the injection hole 32 is filled. In addition, the joint portion 17 between the foundation 30 and the pillar 16 is repaired. The repair content is to scrape off the parts that are heavily damaged, such as press-fitting the repair material into cracks caused by uneven settlement of the foundation 30 and the pillar 16 and the joints, and exposing the reinforcing bars of the foundation 30, and newly forming the formwork. Repair of the provided cross section, etc.
図7(A)に示すように、一階のスラブ12を補修する。補修方法は、一例として一階のスラブ12と地盤10との隙間11に、硬質ウレタン樹脂等の膨張材70を充填し、充填後、膨張材70が膨張することで、スラブ12と地盤10との隙間を埋めると共にスラブ12を押し上げ平らにする。 As shown in FIG. 7A, the slab 12 on the first floor is repaired. As an example, the repair method is to fill the gap 11 between the slab 12 and the ground 10 on the first floor with an expansion material 70 such as hard urethane resin, and after filling, the expansion material 70 expands to form the slab 12 and the ground 10. Fill the gap and push up the slab 12 to flatten it.
図7(B)に示すように、梁20に補修梁22を接合し、梁20を補修及び補強する。 As shown in FIG. 7B, the repair beam 22 is joined to the beam 20 to repair and reinforce the beam 20.
なお、図6(B)以降の工程は、破損などの状況によっては不要な工程がある。また、破損などの状況によっては、これら以外の工程が必要な場合がある。 The steps after FIG. 6B may be unnecessary depending on the situation such as breakage. In addition, depending on the situation such as damage, steps other than these may be required.
(高圧噴射撹拌工法)
次に、既存地盤改良体40の直下に新設地盤改良体50の高圧噴射撹拌工法による構築について説明する。
(High pressure injection stirring method)
Next, the construction of the new ground improvement body 50 directly under the existing ground improvement body 40 by the high-pressure injection stirring method will be described.
図5(B)及び図4に示すように、既存地盤改良体40の外側の地盤10に挿入した噴出菅100から、図3に示すように、左右に揺動(図3の矢印R)且つ上方に移動(図3の矢印T)しながら、固化材を高圧で噴射(図3の矢印F)する。これにより、地盤10を切削しながら混合・撹拌して地盤改良し、扇状改良体52を構築する。 As shown in FIGS. 5B and 4, the ejection tube 100 inserted into the ground 10 outside the existing ground improvement body 40 swings left and right (arrow R in FIG. 3) as shown in FIG. While moving upward (arrow T in FIG. 3), the solidifying material is injected at high pressure (arrow F in FIG. 3). As a result, the ground 10 is mixed and agitated while being cut to improve the ground, and the fan-shaped improved body 52 is constructed.
そして、図4に示すように、四つの扇状改良体52をラップするように構築することで、新設地盤改良体50を構築する。 Then, as shown in FIG. 4, the new ground improvement body 50 is constructed by constructing the four fan-shaped improvement bodies 52 so as to wrap them.
<作用及び効果>
次に、本実施形態の作用及び効果について説明する。
<Action and effect>
Next, the operation and effect of this embodiment will be described.
基礎30の下の既存地盤改良体40の直下に新設地盤改良体50を構築し、地盤10を補強している。よって、基礎30と既存地盤改良体40との間にモルタル60を注入したときの注入圧による、既存地盤改良体40の沈下が抑制されるので、沈下した基礎30を押し上げて設計GLレベルに容易に復元することができる。 A new ground improvement body 50 is constructed directly under the existing ground improvement body 40 under the foundation 30 to reinforce the ground 10. Therefore, the subsidence of the existing ground improvement body 40 due to the injection pressure when the mortar 60 is injected between the foundation 30 and the existing ground improvement body 40 is suppressed, so that the subsidence foundation 30 is easily pushed up to the design GL level. Can be restored to.
別の観点から説明すると、基礎30の下にある既存地盤改良体40がモルタル60の注入圧により沈下することにより、基礎30の復元が困難になること又は復元できなくなることが防止される。 From another point of view, it is prevented that the existing ground improvement body 40 under the foundation 30 is subsided by the injection pressure of the mortar 60, which makes it difficult or impossible to restore the foundation 30.
また、本実施形態では、高圧噴射撹拌工法を用いているので、既存地盤改良体40の直下を、容易に地盤改良して新設地盤改良体50を構築することができる。 Further, in the present embodiment, since the high-pressure injection stirring method is used, it is possible to easily improve the ground directly under the existing ground improvement body 40 to construct the new ground improvement body 50.
<その他>
尚、本発明は上記実施形態に限定されない。
<Others>
The present invention is not limited to the above embodiment.
例えば、上記実施形態では、基礎30と既存地盤改良体40との間にモルタル60を注入したが、これに限定されない。モルタル60以外の注入材、例えば、流動化コンクリートや高流動コンクリート等を注入してもよい。 For example, in the above embodiment, the mortar 60 is injected between the foundation 30 and the existing ground improvement body 40, but the present invention is not limited to this. An injection material other than the mortar 60, for example, fluidized concrete, high fluidized concrete, or the like may be injected.
また、例えば、上記実施形態では、新設地盤改良体50は、高圧噴射撹拌工法で構築したが、これに限定されない。高圧噴射撹拌工法以外の他の工法で、新設地盤改良体50を構築してもよい。 Further, for example, in the above embodiment, the new ground improvement body 50 is constructed by the high pressure injection stirring method, but the present invention is not limited to this. The new ground improvement body 50 may be constructed by a method other than the high-pressure injection stirring method.
また、例えば、上記実施形態では、既存基礎は、基礎30であったが、これに限定されない。例えば、ベタ基礎、連続(布)基礎及び複合基礎等であってもよい。 Further, for example, in the above embodiment, the existing foundation is the foundation 30, but the foundation is not limited to this. For example, it may be a solid foundation, a continuous (cloth) foundation, a composite foundation, or the like.
更に、本発明の要旨を逸脱しない範囲において種々なる態様で実施し得ることは言うまでもない Furthermore, it goes without saying that it can be carried out in various embodiments without departing from the gist of the present invention.
30 基礎(既存基礎の一例)
40 既存地盤改良体
50 新設地盤改良体
60 モルタル(注入材の一例)
30 foundations (an example of existing foundations)
40 Existing ground improvement body 50 New ground improvement body 60 Mortar (an example of injection material)
Claims (5)
前記既存基礎と前記既存地盤改良体との間に注入材を注入し、前記既存基礎を押し上げて復元する工程と、
を備える既存基礎の復元方法。 The process of constructing a new ground improvement body directly under the existing ground improvement body built under the subsided existing foundation,
A step of injecting an injection material between the existing foundation and the existing ground improvement body and pushing up the existing foundation to restore it.
How to restore an existing foundation with.
請求項1に記載の既存基礎の復元方法。 The newly constructed ground improvement body is constructed by improving the ground by a high-pressure injection stirring method.
The method for restoring an existing foundation according to claim 1.
請求項1又は請求項2に記載の既存基礎の復元方法。 The method for restoring an existing foundation according to claim 1 or 2.
前記既存基礎の下に構築された既存地盤改良体と、 The existing ground improvement body constructed under the existing foundation and
前記既存基礎の直下に構築された新設地盤改良体と、 A new ground improvement body constructed directly under the existing foundation,
前記既存基礎と前記既存地盤改良体との間に注入された注入材と、 The injection material injected between the existing foundation and the existing ground improvement body,
を備える既存基礎の復元構造。 Restoration structure of the existing foundation with.
請求項4に記載の既存基礎の復元構造。 The restoration structure of the existing foundation according to claim 4.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2016216257A JP6826864B2 (en) | 2016-11-04 | 2016-11-04 | Restoration method of existing foundation and restoration structure of existing foundation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2016216257A JP6826864B2 (en) | 2016-11-04 | 2016-11-04 | Restoration method of existing foundation and restoration structure of existing foundation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2018071308A JP2018071308A (en) | 2018-05-10 |
| JP6826864B2 true JP6826864B2 (en) | 2021-02-10 |
Family
ID=62114662
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2016216257A Expired - Fee Related JP6826864B2 (en) | 2016-11-04 | 2016-11-04 | Restoration method of existing foundation and restoration structure of existing foundation |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP6826864B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7267890B2 (en) * | 2019-09-26 | 2023-05-02 | ケミカルグラウト株式会社 | Structure foundation reinforcement method |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FI823299A7 (en) * | 1982-09-27 | 1984-03-28 | Uretaanitekniikka Oy | Method for raising floor depressions. |
| JPH0739669B2 (en) * | 1986-07-23 | 1995-05-01 | 株式会社竹中工務店 | Structures such as foundation slabs that can be easily repaired by subsidence |
| DE19623305A1 (en) * | 1996-06-11 | 1997-12-18 | Keller Grundbau Gmbh | Ground hardening equipment to prevent subsidence of railway line |
| JP4080421B2 (en) * | 2003-12-25 | 2008-04-23 | 株式会社設計室ソイル | How to adjust the height of the structure |
| JP5294117B2 (en) * | 2009-02-25 | 2013-09-18 | 清水建設株式会社 | Dirt floor |
| JP5348781B2 (en) * | 2009-12-04 | 2013-11-20 | 株式会社不動テトラ | Repair method of substructure |
-
2016
- 2016-11-04 JP JP2016216257A patent/JP6826864B2/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| JP2018071308A (en) | 2018-05-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101410471B1 (en) | Method for buttom-up removal of underground retaining wall by using h-piles remained in earth retaining work of existed building | |
| KR101542126B1 (en) | PHC pile for Prestressed Concrete Member, Manufacturing method of PHC pile amd Construction method of retaining wall using PHC pile | |
| JP2009161974A (en) | Reinforced concrete beam construction method | |
| JP2015031119A (en) | Ground reinforcement structure | |
| JP6826864B2 (en) | Restoration method of existing foundation and restoration structure of existing foundation | |
| JP5976373B2 (en) | Pile foundation reinforcement structure and reinforcement method | |
| JP7085464B2 (en) | How to build a retaining wall structure in the reverse striking method | |
| JP7082515B2 (en) | Durable block press-fit foundation construction method for foundation repair | |
| JP6918469B2 (en) | Construction method of precast member, erection structure of precast member, erection structure of precast member | |
| JP6855665B2 (en) | Pile foundation structure and how to reinforce existing piles | |
| US20120163923A1 (en) | Structure supporting system | |
| JP2013002077A (en) | Ground improvement body, and piled raft foundation equipped therewith | |
| JP6345328B1 (en) | Original position building method and original position structure | |
| JP3648664B2 (en) | Building renovation method and building | |
| JP5032012B2 (en) | Sheet pile combined direct foundation and its construction method | |
| KR102364887B1 (en) | Non-open cut construction method for a tunnel and temporary structure | |
| JP5149822B2 (en) | Reinforcement method for foundation of existing structure | |
| JP3353166B2 (en) | Method of rebuilding building structure and basic structure used for it | |
| JP5165546B2 (en) | Installation method of bridge support | |
| JP2009068276A (en) | Widening method of shield tunnel | |
| RU2619964C1 (en) | Method for increasing bearing capacity of pile pier | |
| JP2015113589A (en) | Ps post-introduction method of rc building and structure thereof | |
| JP4714928B2 (en) | Tunnel excavation method | |
| JP7510328B2 (en) | Construction Method | |
| KR100479500B1 (en) | The slope tree-planting structure using socket type steel pipe, and his construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20190925 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20200731 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20200804 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20200825 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20210112 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20210118 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 6826864 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| LAPS | Cancellation because of no payment of annual fees |