JP6932544B2 - Construction method of support pile - Google Patents
[go: Go Back, main page]

JP6932544B2 - Construction method of support pile - Google Patents

Construction method of support pile Download PDF

Info

Publication number
JP6932544B2
JP6932544B2 JP2017095797A JP2017095797A JP6932544B2 JP 6932544 B2 JP6932544 B2 JP 6932544B2 JP 2017095797 A JP2017095797 A JP 2017095797A JP 2017095797 A JP2017095797 A JP 2017095797A JP 6932544 B2 JP6932544 B2 JP 6932544B2
Authority
JP
Japan
Prior art keywords
support pile
steel pipe
pressurizing
solidifying material
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017095797A
Other languages
Japanese (ja)
Other versions
JP2018193686A (en
Inventor
北村 精男
北村  精男
田内 宏明
田内  宏明
将吾 中村
将吾 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Giken Ltd
Original Assignee
Giken Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Giken Ltd filed Critical Giken Ltd
Priority to JP2017095797A priority Critical patent/JP6932544B2/en
Publication of JP2018193686A publication Critical patent/JP2018193686A/en
Application granted granted Critical
Publication of JP6932544B2 publication Critical patent/JP6932544B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Description

本発明は、例えば構造物の基礎等に用いられる地盤食い込み型の支持杭の施工方法に関する。 The present invention relates to a method for constructing a ground-cutting type support pile used for, for example, the foundation of a structure.

従来、基礎構造物用の杭基礎として支持杭が用いられている。支持杭は先端を支持層に到達させ、主として杭の先端に働く先端支持力によって荷重を支えている。
例えば特許文献1に記載された支持杭は、地盤中に鋼管製やコンクリート製の支持杭を埋設施工するに際し、支持杭の下端部の外周に拡径部を形成したものを支持層の立孔に挿入して根固め部に埋設させ、根固め部に根固め液を注入固化して固定している。そして、支持杭の内部にコンクリートを充填して固化させている。
Conventionally, support piles have been used as pile foundations for foundation structures. The tip of the support pile reaches the support layer, and the load is supported mainly by the tip bearing force acting on the tip of the pile.
For example, the support pile described in Patent Document 1 has a diameter-expanded portion formed on the outer periphery of the lower end portion of the support pile when the support pile made of steel pipe or concrete is buried in the ground. It is inserted into the root-consolidating part and embedded in the root-consolidating part, and the root-consolidating liquid is injected into the root-consolidating part to solidify and fix it. Then, the inside of the support pile is filled with concrete and solidified.

また、特許文献2に記載された支持杭の施工方法では、打設や圧入、或いは回転工法等により鋼管を所定深度まで埋設し、鋼管内の土を所定深さまで排土する。そして、上端の開口から鋼管内に拡径装置を挿入し、鋼管を内部から拡径して外周に膨らむ突起部を多段に形成し、この突起部を地山面に圧着または貫入している。 Further, in the method of constructing the support pile described in Patent Document 2, the steel pipe is buried to a predetermined depth by driving, press-fitting, rotary construction, or the like, and the soil in the steel pipe is discharged to a predetermined depth. Then, a diameter-expanding device is inserted into the steel pipe through the opening at the upper end, the diameter of the steel pipe is expanded from the inside to form a multi-stage protrusion that bulges to the outer circumference, and this protrusion is crimped or penetrated into the ground surface.

特許第3664361号公報Japanese Patent No. 3664361 特開2000−120066号公報Japanese Unexamined Patent Publication No. 2000-120066

しかしながら、特許文献1に記載された支持杭の施工方法では、掘削装置で予め立孔を形成して地盤の支持層に大径の根固め部を形成する上に立孔内に根固め液や周囲固め液を注入した後に、下端部に拡径部を形成した支持杭を挿入する為、挿入する支持杭の体積分の根固め液や周囲固め液が地上部に出ないと杭は入らない。また、支持杭自体を囲うのは根固め液や周囲固め液であり、直接地盤と接するのは支持杭ではない。つまり、支持部に多段の拡径部を設けても地盤との間の摩擦の向上になっていなかった。
また、特許文献2に記載された支持杭の施工方法は、圧入した鋼管の長手方向に所定間隔で複数の拡径部を形成するため、地盤強度と杭強度と引き抜き抵抗を強化するためには鋼管の長手方向に所定間隔で多段の拡径部を形成している。しかしながら、この施工方法は杭の周面摩擦を増して支持力を得る方法であり、大抵の地盤では途中が柔らかく下方に支持層がある場合が多いので、十分に支持力を得ることはできないという問題がある。
However, in the method of constructing a support pile described in Patent Document 1, a standing hole is formed in advance by an excavator to form a large-diameter rooting portion in the support layer of the ground, and a rooting liquid or a rooting liquid is formed in the standing hole. After injecting the surrounding solidifying liquid, the support pile with the enlarged diameter formed at the lower end is inserted, so the pile will not enter unless the root hardening liquid and the surrounding solidifying liquid for the volume of the supporting pile to be inserted come out to the ground part. .. Further, it is the root hardening liquid and the surrounding hardening liquid that surround the support pile itself, and it is not the support pile that is in direct contact with the ground. That is, even if the support portion is provided with a multi-stage enlarged diameter portion, the friction with the ground is not improved.
Further, in the method of constructing a support pile described in Patent Document 2, since a plurality of enlarged diameter portions are formed at predetermined intervals in the longitudinal direction of the press-fitted steel pipe, in order to strengthen the ground strength, pile strength and pull-out resistance, Multi-stage enlarged diameter portions are formed at predetermined intervals in the longitudinal direction of the steel pipe. However, this construction method is a method of increasing the peripheral friction of the pile to obtain bearing capacity, and in most grounds, the middle is soft and there is often a support layer below, so it is said that sufficient bearing capacity cannot be obtained. There's a problem.

本発明は、上述した事情に鑑みてなされたものであって、簡単な施工で杭強度と引き抜き抵抗を増大できるようにした支持杭の施工方法を提供することを目的とする。 The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a method for constructing a support pile so that pile strength and pull-out resistance can be increased by simple construction.

すなわち、本発明に係る支持杭の施工方法は、鋼管を打設する鋼管打設工程と、鋼管を打設しながらまたは打設した後に鋼管内を掘削する掘削工程と、鋼管の内壁を拡径して凹部を形成する凹部形成工程と、鋼管内の凹部を含む範囲に固化材料を充填する固化材料充填工程と、充填した固化材料を加圧する加圧工程と、を備えたことを特徴とする。
本発明によれば、支持杭の内部に内壁を拡径した凹部の領域を含めて固化材料を充填した後に固化材料を加圧固化したために、凹部によって鋼管と固化材料との一体性が高く高強度で引き抜き抵抗を増大できる上に、鋼管にスリットを形成しないので応力集中も発生しない。
That is, the method for constructing the support pile according to the present invention includes a steel pipe driving process for driving a steel pipe, an excavation process for excavating the inside of the steel pipe while driving or after driving the steel pipe, and expanding the diameter of the inner wall of the steel pipe. It is characterized by including a recess forming step of forming a recess, a solidifying material filling step of filling a solidified material in a range including the recess in the steel pipe, and a pressurizing step of pressurizing the filled solidified material. ..
According to the present invention, since the solidifying material is pressure-solidified after filling the solidifying material including the region of the recess in which the inner wall is enlarged in diameter inside the support pile, the solidification is highly integrated between the steel pipe and the solidifying material due to the recess. In addition to being able to increase pull-out resistance with strength, stress concentration does not occur because slits are not formed in the steel pipe.

また、加圧工程において、支持杭の下端部から固化材料を突出させて鋼管の径よりも拡径された固化材料の拡径部を形成することが好ましい。
支持杭の下端部に鋼管の径よりも拡径された固化材料の拡径部を形成することで支持杭の強度と引き抜き抵抗を一層向上できる。
なお、拡径部を掘削で広げる方法であると地下水や掘削面の土の強度により周面地盤は元の状態より崩壊方向に強度低下する傾向があるのに対して、本発明によれば、加圧工程で周面地盤を圧密するため周面地盤を強固にすることができる。
Further, in the pressurizing step, it is preferable to project the solidifying material from the lower end of the support pile to form an enlarged diameter portion of the solidifying material whose diameter is larger than the diameter of the steel pipe.
The strength and pull-out resistance of the support pile can be further improved by forming an enlarged diameter portion of the solidifying material whose diameter is larger than that of the steel pipe at the lower end portion of the support pile.
In addition, in the method of expanding the enlarged diameter portion by excavation, the strength of the peripheral ground tends to decrease in the collapse direction from the original state due to the strength of the groundwater and the soil on the excavated surface, whereas according to the present invention. Since the peripheral ground is compacted in the pressurizing process, the peripheral ground can be strengthened.

また、加圧工程において、鋼管の下端部から突出する固化材料を支持地盤に食い込ませることが好ましい。
支持杭の下端部から突出する加圧した固化材料を支持地盤に食い込ませたことで、拡径部を形成しなくても支持杭の強度と引き抜き抵抗を一層向上できる。
Further, in the pressurizing step, it is preferable that the solidifying material protruding from the lower end of the steel pipe bites into the supporting ground.
By allowing the pressurized solidifying material protruding from the lower end of the support pile to bite into the support ground, the strength and pull-out resistance of the support pile can be further improved without forming a diameter-expanded portion.

また、加圧工程において、加圧装置によって固化材料を加圧するようにしてもよい。
具体的には、加圧装置は、圧入機によって固化材料を加圧することができる。
支持杭の圧入に用いる圧入機で蓋部を介して鋼管内の固化材料を加圧することで、別個の設備を用いないで効率的に固化材料の加圧ができる。しかも、押す際の抵抗は支持杭内面と固化材料との摩擦抵抗のみであり、固化材料の加圧が容易である。
Further, in the pressurizing step, the solidifying material may be pressurized by a pressurizing device.
Specifically, the pressurizing device can pressurize the solidified material by a press-fitting machine.
By pressurizing the solidifying material in the steel pipe through the lid with a press-fitting machine used for press-fitting the support pile, the solidifying material can be efficiently pressurized without using separate equipment. Moreover, the resistance at the time of pushing is only the frictional resistance between the inner surface of the support pile and the solidifying material, and the solidifying material can be easily pressurized.

また、加圧装置は、鋼管内に蓋部を固定し、圧入機で鋼管を押すことで固化材料を加圧するようにしてもよい。
蓋部は支持杭内で固化材料の上面に固定したため、圧入機で鋼管を押すことで蓋部も押されて固化材料の加圧を行える。
Further, the pressurizing device may press the solidified material by fixing the lid portion in the steel pipe and pushing the steel pipe with a press-fitting machine.
Since the lid is fixed to the upper surface of the solidifying material in the support pile, the lid can be pressed by pushing the steel pipe with the press-fitting machine to pressurize the solidifying material.

また、加圧装置は、鋼管内にシリンダ装置を固定し、該シリンダ装置で固化材料を加圧するようにしてもよい。
支持杭内に固定したシリンダ装置により蓋部を介して固化材料を押すことで固化材料を加圧でき、押す際の抵抗は支持杭内面と固化材料との摩擦抵抗のみであり、固化材料の加圧が容易である。
Further, the pressurizing device may fix the cylinder device in the steel pipe and pressurize the solidified material with the cylinder device.
The solidifying material can be pressurized by pushing the solidifying material through the lid with a cylinder device fixed in the support pile, and the resistance at the time of pushing is only the frictional resistance between the inner surface of the support pile and the solidifying material, and the solidifying material is added. The pressure is easy.

本発明に係る支持杭の施工方法によれば、支持杭の内部に形成した凹部に固化材料を充填した後に加圧し固化したために、支持杭と固化材料との一体性が高くなる上に支持杭が高強度で引き抜き抵抗を増大できる。
しかも、支持杭に所定間隔で多段の突起部を形成しなくてもよいため、施工工数とコストを削減できる。
According to the method for constructing a support pile according to the present invention, since the recess formed inside the support pile is filled with the solidifying material and then pressurized and solidified, the unity between the support pile and the solidifying material is improved and the support pile is solidified. Is high strength and can increase pull-out resistance.
Moreover, since it is not necessary to form multi-step protrusions on the support piles at predetermined intervals, the construction man-hours and costs can be reduced.

本発明の第一実施形態による支持杭の掘削工程を示す図である。It is a figure which shows the excavation process of the support pile by 1st Embodiment of this invention. 支持杭内部の排土工程を示す図である。It is a figure which shows the earth removal process in the support pile. 支持杭に突起部を形成する拡径工程と突起部の図である。It is a figure of the diameter expansion process which forms a protrusion on a support pile, and the protrusion. 支持杭にコンクリートを充填する工程の図である。It is a figure of the process of filling concrete in a support pile. 支持杭内のコンクリートを加圧する工程の図である。It is a figure of the process of pressurizing concrete in a support pile. 本実施形態によって施工された支持杭の説明図である。It is explanatory drawing of the support pile constructed by this embodiment. コンクリートを加圧する他の方法を示す図であり、(a)はジャッキで蓋部を固定して支持杭を圧入する加圧方法の図、(b)は圧入シリンダでコンクリートを加圧する加圧方法の図である。It is a figure which shows the other method of pressurizing concrete, (a) is the figure of the pressurizing method which fixes the lid part with a jack and press-fits a support pile, (b) is the figure of a pressurizing method which presses concrete with a press-fitting cylinder. It is a figure of. 本発明の第二実施形態による支持杭の施工方法を示すもので、排土工程を示す図である。It shows the construction method of the support pile by the 2nd Embodiment of this invention, and is the figure which shows the earth removal process. 本第二実施形態によって施工された支持杭の説明図である。It is explanatory drawing of the support pile constructed by this 2nd Embodiment. 加圧された支持杭の説明図である。It is explanatory drawing of the pressure | pressure support pile.

以下、本発明の各実施形態による支持杭の施工方法について添付図面により説明する。
図1乃至図7は本発明の第一実施形態による支持杭の施工方法を示す図である。
本実施形態による支持杭1の施工方法は、例えば地盤2に圧入機3を用いて圧入または回転圧入する方法である。支持杭1は、例えば防波堤等の構造物を地盤2に定着させるために打設する。支持杭1は図1に示すように鋼管の杭からなり、下端部に掘削歯1aが形成されている。圧入機3はクランプ4を反力ウェイト5または既設の支持杭1に設置して反力をとり、鋼管を支持杭1として打設するものである。
Hereinafter, a method of constructing a support pile according to each embodiment of the present invention will be described with reference to the accompanying drawings.
1 to 7 are views showing a method of constructing a support pile according to the first embodiment of the present invention.
The construction method of the support pile 1 according to the present embodiment is, for example, a method of press-fitting or rotating press-fitting into the ground 2 using a press-fitting machine 3. The support pile 1 is driven to fix a structure such as a breakwater to the ground 2. As shown in FIG. 1, the support pile 1 is made of a steel pipe pile, and excavation teeth 1a are formed at the lower end portion. The press-fitting machine 3 installs the clamp 4 on the reaction force weight 5 or the existing support pile 1 to take the reaction force, and drives the steel pipe as the support pile 1.

以下、鋼管を用いて支持杭1を施工する方法について説明する。
図1に示す鋼管打設工程において、鋼管を圧入機3を用いて所定の施工位置に支持杭1として埋設する。支持杭1の埋設は圧入または回転圧入によって行われる。圧入に際して、図2に示すように支持杭1は地盤2中をより硬い支持地盤7に到達するまで掘削する。その後、コンクリートによる拡径球根を形成するための所定のストロークa分、支持杭1を引き上げる(図4参照)。この場合、支持杭1の下端部と支持地盤7との間に鋼管の無い部分が形成されるが、コンクリートが入っているため地盤2が崩壊することはない。支持杭1が支持地盤7に到達することで圧入時に圧入機3の圧力により支持地盤7の強度を確認できる。
Hereinafter, a method of constructing the support pile 1 using a steel pipe will be described.
In the steel pipe driving process shown in FIG. 1, the steel pipe is buried as a support pile 1 at a predetermined construction position using a press-fitting machine 3. The support pile 1 is buried by press-fitting or rotary press-fitting. Upon press-fitting, as shown in FIG. 2, the support pile 1 excavates the ground 2 until it reaches the harder support ground 7. After that, the support pile 1 is pulled up by a predetermined stroke a for forming the enlarged diameter bulb made of concrete (see FIG. 4). In this case, a portion without a steel pipe is formed between the lower end of the support pile 1 and the support ground 7, but the ground 2 does not collapse because concrete is contained. When the support pile 1 reaches the support ground 7, the strength of the support ground 7 can be confirmed by the pressure of the press-fitting machine 3 at the time of press-fitting.

次に、図2に示す支持杭1内の排土工程において、掘削機9によって支持杭1の内部を掘削して排土する。支持杭1の内部の掘削は鋼管の圧入終了後でもよいし、圧入しながら掘削して排土してもよい。
支持杭1内の排土が終了した後、拡径工程に移行する。図3に示すように、鋼管の内径を拡径するための拡径装置11を支持杭1内に挿入する。ここで、拡径装置11は、装置本体12に設けられていて鋼管の内壁方向即ち径方向に進退可能な押圧部13と押圧部13を進退させるジャッキ部14とを有している。しかも、装置本体12には、その姿勢を安定させると共に上下方向に昇降させるワイヤや拡径装置作動用の油圧ホースを含む懸垂部15が連結されている。
Next, in the soil removal step in the support pile 1 shown in FIG. 2, the inside of the support pile 1 is excavated by the excavator 9 to discharge the soil. The inside of the support pile 1 may be excavated after the press-fitting of the steel pipe is completed, or the excavation may be performed while press-fitting and the soil may be discharged.
After the soil removal in the support pile 1 is completed, the process shifts to the diameter expansion process. As shown in FIG. 3, a diameter expanding device 11 for increasing the inner diameter of the steel pipe is inserted into the support pile 1. Here, the diameter expanding device 11 has a pressing portion 13 that is provided in the apparatus main body 12 and is capable of advancing and retreating in the inner wall direction of the steel pipe, that is, in the radial direction, and a jack portion 14 that advances and retreats the pressing portion 13. Moreover, a suspension portion 15 including a wire for stabilizing the posture and raising and lowering in the vertical direction and a hydraulic hose for operating the diameter-expanding device is connected to the device main body 12.

押圧部13は例えば先細の円錐形状や多角錐形状等の適宜の爪先部を採用できる。押圧部13の先端は、拡径時に鋼管に外部に連通する切欠孔が形成されないように丸面取り等を形成することが好ましい。
支持杭1に切欠孔等が形成されると応力集中して杭強度を低下させる上に、周囲の地盤2の水や土砂等が支持杭1内に流入して充填されるコンクリートの品質を劣化させるおそれがある。また、支持杭1の下端部が硬質地盤である支持地盤7に至ると掘削歯1aに大きな抵抗が加わって切欠孔に応力集中が生じて杭強度が低下する。また、その加工工程が必要である。その点、本実施形態では、鋼管に切欠孔が形成されないノーマル状態の鋼管を使用できるようにしたため、杭強度の低下を抑制し、周囲の地盤2の水や土砂が流入することを防止できてコストも安くなる。
As the pressing portion 13, an appropriate toe portion such as a tapered conical shape or a polygonal pyramid shape can be adopted. It is preferable that the tip of the pressing portion 13 has a round chamfer or the like so that a notch hole communicating with the outside is not formed in the steel pipe when the diameter is expanded.
When a notch hole or the like is formed in the support pile 1, stress is concentrated to reduce the pile strength, and water, earth and sand, etc. from the surrounding ground 2 flow into the support pile 1 to deteriorate the quality of the filled concrete. There is a risk of causing it. Further, when the lower end of the support pile 1 reaches the support ground 7, which is a hard ground, a large resistance is applied to the excavated teeth 1a, stress concentration occurs in the notch hole, and the pile strength decreases. Moreover, the processing process is necessary. In that respect, in the present embodiment, since the steel pipe in the normal state in which the notch hole is not formed in the steel pipe can be used, it is possible to suppress the decrease in pile strength and prevent the inflow of water and earth and sand from the surrounding ground 2. The cost is also cheaper.

押圧部13とジャッキ部14の数は適宜設定できるが、鋼管の塑性加工時に反力をとれるように一対対向配置させることが好ましい。また、支持杭1に形成される突起部17及び凹部17aは断面略三角形状であるが、このような形状に限定されることなく適宜形状のものを採用できる。また、突起部17同士が連続する形状でもよい。
支持杭1の内面に凹部17aを形成することで、支持杭1内にコンクリートを充填して固化した際に高い一体性を確保できればよい。
Although the number of the pressing portion 13 and the jack portion 14 can be appropriately set, it is preferable to arrange them in pairs so as to take a reaction force during plastic working of the steel pipe. Further, the protrusion 17 and the recess 17a formed on the support pile 1 have a substantially triangular cross section, but the shape is not limited to such a shape, and an appropriate shape can be adopted. Further, the protrusions 17 may have a continuous shape.
By forming the recess 17a on the inner surface of the support pile 1, it is sufficient that high integrity can be ensured when the support pile 1 is filled with concrete and solidified.

図3に示す拡径工程(凹部形成工程)において、支持杭1内で懸垂部15を降下させることで拡径装置11を支持杭1内の長さ方向任意の位置に移動できる。当該位置でジャッキ部14を作動させることで押圧部13によって鋼管の内面を押圧して鋼管を塑性変形させて、支持杭1の内面に凹部17aを拡径して形成できる。本実施形態では、支持杭1の周方向に所定間隔で6カ所の突起部17を形成した。
そして、拡径装置11を支持杭1内から引き上げた後で、図4に示す固化材料充填工程で、固化材料としてコンクリートCを充填する。コンクリートCの充填量は、次の工程でコンクリートCを加圧した後も凹部17aの上側にコンクリート面C1が位置するように設定するものとする。なお、崩壊性のない地盤の場合は、杭を引き上げた後にコンクリートを充填してもよい。
In the diameter-expanding step (recess forming step) shown in FIG. 3, the diameter-expanding device 11 can be moved to an arbitrary position in the support pile 1 in the length direction by lowering the suspension portion 15 in the support pile 1. By operating the jack portion 14 at that position, the inner surface of the steel pipe is pressed by the pressing portion 13 to plastically deform the steel pipe, and the recess 17a can be formed by expanding the diameter on the inner surface of the support pile 1. In the present embodiment, six protrusions 17 are formed at predetermined intervals in the circumferential direction of the support pile 1.
Then, after the diameter expanding device 11 is pulled up from the inside of the support pile 1, concrete C is filled as the solidifying material in the solidifying material filling step shown in FIG. The filling amount of the concrete C shall be set so that the concrete surface C1 is located above the recess 17a even after the concrete C is pressurized in the next step. In the case of non-collapsed ground, concrete may be filled after the pile is pulled up.

図5に示す加圧工程で、支持杭1内に充填されたコンクリートCを固化前に加圧する。コンクリートCの加圧手段は適宜の装置を採用できる。例えば、図5に示す加圧装置19は支持杭1内のコンクリート面C1に設置した蓋部20と、蓋部20に連結されていて支持杭1の上端部開口よりも上方に延びる支持部材としての例えば内管21とを備えている。内管21は支持杭1を圧入するための圧入機3の把持部で支持され、内管21で蓋部20を押圧することができる。蓋部20は支持杭1の内径と略同一外径の円板形状を有する金属製等の板材を採用できる。 In the pressurizing step shown in FIG. 5, the concrete C filled in the support pile 1 is pressurized before solidification. As the pressurizing means of the concrete C, an appropriate device can be adopted. For example, the pressurizing device 19 shown in FIG. 5 has a lid portion 20 installed on the concrete surface C1 in the support pile 1 and a support member connected to the lid portion 20 and extending upward from the opening of the upper end portion of the support pile 1. For example, the inner tube 21 is provided. The inner pipe 21 is supported by the grip portion of the press-fitting machine 3 for press-fitting the support pile 1, and the lid portion 20 can be pressed by the inner pipe 21. For the lid portion 20, a plate material such as metal having a disk shape having substantially the same outer diameter as the inner diameter of the support pile 1 can be adopted.

加圧工程においては、圧入機3によって内管21を介して蓋部20を押圧することで静止状態の支持杭1内でコンクリートCが加圧される。支持杭1の下端開口から突出する加圧コンクリートCは周囲の地盤2の圧力より高圧であるため、空間b内に流動して地盤2を押し広げて膨張し球根状に拡径されて体積が増大する。また、コンクリート面C1は高さeだけ下がる。支持杭1の下端側では、図6に示すように支持地盤7との間でコンクリートCが支持杭1の径より拡径された圧密の拡径球根23が径方向に幅Eだけ拡径して形成される。この場合にはコンクリートCの杭内にコンクリートが接する摩擦抵抗のみで加圧できる。
しかも、支持杭1の内部のコンクリートCを加圧装置19で押圧することでコンクリート内部の水分を押し出してコンクリートの容積を圧縮させる。これによってコンクリートCの強度が強くなって支持杭1と内部のコンクリートCをより密着させることができ、凹部17aとの密着強度を向上できる。更に支持杭1の先端開口から突出する加圧コンクリートCの拡径球根23の圧力で周囲の地盤2の土圧が増大して互いにバランスする。つまり、周辺地盤の改良にもなる。
In the pressurizing step, the concrete C is pressurized in the stationary support pile 1 by pressing the lid portion 20 through the inner pipe 21 by the press-fitting machine 3. Since the pressure concrete C protruding from the lower end opening of the support pile 1 has a pressure higher than the pressure of the surrounding ground 2, it flows into the space b, expands the ground 2 and expands, and the volume is expanded like a bulb. Increase. Further, the concrete surface C1 is lowered by the height e. On the lower end side of the support pile 1, as shown in FIG. 6, the diameter of the compacted enlarged diameter sphere 23 in which the concrete C is expanded from the diameter of the support pile 1 with the support ground 7 is expanded by the width E in the radial direction. Is formed. In this case, pressurization can be performed only by the frictional resistance that the concrete contacts in the pile of the concrete C.
Moreover, by pressing the concrete C inside the support pile 1 with the pressurizing device 19, the moisture inside the concrete is pushed out and the volume of the concrete is compressed. As a result, the strength of the concrete C becomes stronger, the support pile 1 and the concrete C inside can be brought into close contact with each other, and the adhesive strength with the recess 17a can be improved. Further, the earth pressure of the surrounding ground 2 is increased by the pressure of the enlarged bulb 23 of the pressurized concrete C protruding from the tip opening of the support pile 1 to balance each other. In other words, it also improves the surrounding ground.

本実施形態による支持杭1の施工方法によれば、図6に示すように、支持杭1の先端に支持杭1より拡径された加圧コンクリートの拡径球根23を形成でき、しかも支持杭1内のコンクリートCと拡径球根23を圧密した。更に、支持杭1の凹部17aと加圧コンクリートCとの圧密強度を向上できる。そのため、支持杭1に設置した既設構造物としての例えば鉄塔等に大きな引き抜き力が働いても増大した引き抜き抵抗で引き受けることができる。 According to the construction method of the support pile 1 according to the present embodiment, as shown in FIG. 6, a diameter-expanded bulb 23 of pressure concrete having a diameter larger than that of the support pile 1 can be formed at the tip of the support pile 1, and the support pile can be formed. The concrete C and the enlarged diameter stake 23 in 1 were compacted. Further, the consolidation strength between the recess 17a of the support pile 1 and the pressure concrete C can be improved. Therefore, even if a large pulling force acts on, for example, a steel tower as an existing structure installed on the support pile 1, it can be undertaken by the increased pulling resistance.

さらに、突起部17にスリット等の切欠部を形成しないから、外部の地盤2から水や土砂等が流入してコンクリートCの品質を低下させることがなく支持杭1の強度を向上できる。また、切欠部による応力集中も発生しないため杭強度が高い。
コンクリートCの加圧によって拡径球根23で周囲の地盤2を圧縮してコンクリート強度と釣り合うと共に、加圧コンクリートCの強度を増大させることができる。そのため、支持杭1の強度とコンクリートCの引き抜き抵抗を向上できる。
Further, since the protrusion 17 does not form a notch such as a slit, the strength of the support pile 1 can be improved without inflowing water, earth and sand, etc. from the external ground 2 and deteriorating the quality of the concrete C. In addition, the pile strength is high because stress concentration does not occur due to the notch.
By pressurizing the concrete C, the surrounding ground 2 can be compressed by the enlarged bulb 23 to balance with the concrete strength, and the strength of the pressurized concrete C can be increased. Therefore, the strength of the support pile 1 and the pull-out resistance of the concrete C can be improved.

上述したように本実施形態による支持杭1の施工方法によれば、支持杭1の凹部17aに加圧コンクリートCを圧密させたため、コンクリートCの鋼管への密着度が高くなりコンクリート強度が増大するため杭強度と引き抜き抵抗を向上できる。
しかも、コンクリートCを加圧して支持杭1の下端部に拡径球根23を形成することで凹部17aと共に支持杭1による支持力と引き抜き抵抗を一層増大できる。
また、支持杭1の施工方法に圧入機3を用いたため、コンクリートの圧入ストロークを管理することで拡径球根23の拡径量Eをコントロールでき、コンクリートの加圧力を管理することでコンクリートの圧密強度をコントロールできる。
As described above, according to the construction method of the support pile 1 according to the present embodiment, since the pressurized concrete C is compacted in the recess 17a of the support pile 1, the degree of adhesion of the concrete C to the steel pipe is increased and the concrete strength is increased. Therefore, pile strength and pull-out resistance can be improved.
Moreover, by pressurizing the concrete C to form the enlarged bulb 23 at the lower end of the support pile 1, the support force and the pull-out resistance of the support pile 1 can be further increased together with the recess 17a.
Further, since the press-fitting machine 3 is used as the construction method of the support pile 1, the diameter-expanding amount E of the enlarged-diameter bulb 23 can be controlled by controlling the press-fitting stroke of the concrete, and the concrete is compacted by controlling the pressing force of the concrete. You can control the strength.

なお、本発明による支持杭1の施工方法は、上述の実施形態に限定されるものではなく、その要旨を逸脱しない範囲で種々の変更や置換等が可能であり、これらの場合も本発明の技術的範囲に含まれる。以下に本発明の他の実施形態や変形例について上述した実施形態と同一または同様な部分、部材には同一の符号を用いて説明する。 The method of constructing the support pile 1 according to the present invention is not limited to the above-described embodiment, and various changes and replacements can be made without departing from the gist thereof. Included in the technical scope. Hereinafter, other embodiments and modifications of the present invention will be described with reference to the same or similar parts and members as those in the above-described embodiment.

本発明では、圧入機3を用いた加圧装置19とは別の加圧装置を採用してもよく、これについて図7により説明する。
図7(a)に示す加圧装置25は支持杭1を所定ストローク引き上げて使用する。加圧装置25において、蓋部20を支持杭1内に充填したコンクリート面C1上に設置し、その蓋部20の上面にジャッキ部26と支持杭1の内壁方向に進退可能な一対の押圧部材27とを備えた押圧装置28を設置している。押圧部材27は表面に凸部からなる複数の係合爪を備えており、ジャッキ部26によって押圧部材27を径方向外側に進出させて支持杭1の内壁に係止させることで連結させる。
In the present invention, a pressurizing device different from the pressurizing device 19 using the press-fitting machine 3 may be adopted, and this will be described with reference to FIG.
The pressurizing device 25 shown in FIG. 7A is used by pulling up the support pile 1 by a predetermined stroke. In the pressurizing device 25, the lid portion 20 is installed on the concrete surface C1 filled in the support pile 1, and a pair of pressing members capable of advancing and retreating in the direction of the inner wall of the jack portion 26 and the support pile 1 on the upper surface of the lid portion 20. A pressing device 28 provided with 27 is installed. The pressing member 27 is provided with a plurality of engaging claws consisting concave protrusions on the surface, it is linked by engaged to the inner wall of the supporting piles 1 by advancing the pressing member 27 radially outward by the jack unit 26.

また、圧入機3の把持部に打ち下げ部材30を把持させる。この打ち下げ部材30は鋼管径より大径の円柱部30aとその先端面から突出させた鋼管径より小径の貫入部30bとを有していて、支持杭1の上端部開口に円柱部30aの先端面を着座させ、貫入部30bを先端部開口から支持杭1内に嵌入させる。
そして、加圧工程において、圧入機3で打ち下げ部材30を押し下げて支持杭1を地盤2内に押し込む。すると、支持杭1と一体に押圧装置28も降下するため蓋部20を介してコンクリートCを加圧できる。この場合、支持杭1の全長に亘る地盤2との周囲摩擦抵抗が圧入力に加わる。支持杭1の圧入力と引き抜き力(杭の周面摩擦抵抗)との差でコンクリートCの加圧力が設定される。支持杭1は引き上げた所定ストローク分押し下げることが好ましい。
Further, the downhill member 30 is gripped by the gripping portion of the press-fitting machine 3. The downhill member 30 has a columnar portion 30a having a diameter larger than the steel pipe diameter and an intrusion portion 30b having a diameter smaller than the steel pipe diameter protruding from the tip surface thereof, and the columnar portion 30a opens at the upper end of the support pile 1. The tip surface is seated, and the penetration portion 30b is fitted into the support pile 1 through the tip opening.
Then, in the pressurizing step, the press-fitting machine 3 pushes down the down member 30 to push the support pile 1 into the ground 2. Then, since the pressing device 28 also descends integrally with the support pile 1, the concrete C can be pressurized through the lid portion 20. In this case, the peripheral frictional resistance with the ground 2 over the entire length of the support pile 1 is applied to the pressure input. The pressing force of the concrete C is set by the difference between the pressure input of the support pile 1 and the pulling force (friction resistance of the peripheral surface of the pile). It is preferable that the support pile 1 is pushed down by a predetermined stroke that is pulled up.

また、図7(b)に示す加圧装置32は、上述した押圧装置28におけるジャッキ部26にシリンダ装置33を固定し、シリンダ装置33に設けたロッド34の先端に蓋部20を連結している。しかもジャッキ部26には支持杭1の上端部開口から外部に延びる油圧チューブを介して油圧を供給可能とした。
そのため、押圧装置28の押圧部材27をジャッキ部26で支持杭1の内面に押圧して係止させた状態で、シリンダ装置33からロッド34を押し下げて蓋部20でコンクリートCを押圧することで加圧できる。この場合にはコンクリートCの摩擦抵抗のみでコンクリートCを加圧できる。
Further, in the pressurizing device 32 shown in FIG. 7B, the cylinder device 33 is fixed to the jack portion 26 in the pressing device 28 described above, and the lid portion 20 is connected to the tip of the rod 34 provided in the cylinder device 33. There is. Moreover, the jack portion 26 can be supplied with flood control via a hydraulic tube extending outward from the opening at the upper end of the support pile 1.
Therefore, in a state where the pressing member 27 of the pressing device 28 is pressed against the inner surface of the support pile 1 by the jack portion 26 to be locked, the rod 34 is pushed down from the cylinder device 33 and the concrete C is pressed by the lid portion 20. Can be pressurized. In this case, the concrete C can be pressurized only by the frictional resistance of the concrete C.

次に、本発明の第二実施形態による支持杭1Aの施工方法について、図8〜図10により説明する。
本第二実施形態による支持杭1Aの施工方法は、例えば非常に硬い地盤2で拡径しなくとも支持力を得られそうな場合の施工方法に関する。支持杭1Aは第一実施形態と同様に図1に示す鋼管からなり、鋼管を支持杭1Aとして圧入機3を用いて圧入または回転圧入によって所定の施工位置に圧入する。掘削工程において、図8に示すように圧入機3によって支持杭1Aを地盤2中に掘削し、硬質地盤の支持地盤7まで掘削する。支持杭1Aは先端が支持地盤7に食い込んだ状態で停止させ、地盤2の崩壊の可能性があるため支持地盤7との間に空間bは形成しない。
Next, the construction method of the support pile 1A according to the second embodiment of the present invention will be described with reference to FIGS. 8 to 10.
The construction method of the support pile 1A according to the second embodiment relates to, for example, a construction method in a case where a bearing capacity can be obtained without expanding the diameter of the very hard ground 2. The support pile 1A is made of the steel pipe shown in FIG. 1 as in the first embodiment, and the steel pipe is press-fitted into a predetermined construction position by press-fitting or rotary press-fitting using the press-fitting machine 3 as the support pile 1A. In the excavation process, as shown in FIG. 8, the support pile 1A is excavated in the ground 2 by the press-fitting machine 3, and the support ground 7 of the hard ground is excavated. The support pile 1A is stopped in a state where the tip bites into the support ground 7, and the space b is not formed between the support pile 1A and the support ground 7 because the ground 2 may collapse.

次に、支持杭1A内部の排土工程において、掘削機9によって支持杭1Aの内部を掘削して排土する。支持杭1Aの内部の掘削は鋼管の圧入終了後でもよいし、圧入しながら掘削して排土してもよい。
支持杭1A内の排土が終了した後、支持地盤と一体化させるよう支持地盤を掘削する。次に拡径工程に移行する。第一実施形態と同様に、鋼管の内径を拡径するための拡径装置11を支持杭1A内の適宜の高さ位置まで挿入し、ジャッキ部14を作動させて押圧部13を外側に進出させ、支持杭1Aの内面を押圧して支持杭1Aを塑性変形させて支持杭1Aの内面に凹部17aを形成できる。
Next, in the soil removal step inside the support pile 1A, the inside of the support pile 1A is excavated by the excavator 9 to discharge the soil. The inside of the support pile 1A may be excavated after the press-fitting of the steel pipe is completed, or the excavation may be performed while press-fitting and the soil may be discharged.
After the soil removal in the support pile 1A is completed, the support ground is excavated so as to be integrated with the support ground. Next, the process shifts to the diameter expansion process. Similar to the first embodiment, the diameter expanding device 11 for expanding the inner diameter of the steel pipe is inserted to an appropriate height position in the support pile 1A, and the jack portion 14 is operated to advance the pressing portion 13 to the outside. The inner surface of the support pile 1A can be pressed to plastically deform the support pile 1A to form a recess 17a on the inner surface of the support pile 1A.

拡径装置11を支持杭1A内から引き上げた後で、図9に示す固化材料充填工程で、固化材料としてコンクリートCを充填する。コンクリートCの充填量は、次の拡径工程でコンクリートCを加圧した後も凹部17aの上側にコンクリート面C1が位置するように設定する。
次に加圧工程において、図5に示す例えば加圧装置19(または加圧装置25,32)を用いて支持杭1A内のコンクリートCを加圧する。加圧によってコンクリートC中の水分を脱水することで強度が高くなって鋼管の強度に近くなり、凹部17aでもコンクリートCが圧密することで支持杭1Aとより強固に一体化する。支持杭1Aの下端部では支持地盤7に加圧コンクリートCの下端部が食い付いて強固に接合されると共に、支持地盤7の改良もなされる。
After the diameter expanding device 11 is pulled up from the inside of the support pile 1A, concrete C is filled as the solidifying material in the solidifying material filling step shown in FIG. The filling amount of the concrete C is set so that the concrete surface C1 is located above the recess 17a even after the concrete C is pressurized in the next diameter expansion step.
Next, in the pressurizing step, the concrete C in the support pile 1A is pressurized using, for example, the pressurizing device 19 (or the pressurizing devices 25 and 32) shown in FIG. By dehydrating the water in the concrete C by pressurization, the strength becomes high and becomes close to the strength of the steel pipe, and the concrete C is compacted even in the recess 17a to be more firmly integrated with the support pile 1A. At the lower end of the support pile 1A, the lower end of the pressure concrete C bites into the support ground 7 and is firmly joined, and the support ground 7 is also improved.

こうして、支持杭1A内のコンクリートCを加圧することで、図10に示すように強度の高い支持杭1Aを施工できる。本第二実施形態による支持杭1Aの施工方法では、支持杭1Aの下端部に拡径球根23を形成しないが、支持杭1Aの下端部を支持地盤7に食い込ませてコンクリートCを加圧し凹部17aに密着させたため、第一実施形態と同様に高強度で引き抜き抵抗を向上させることができる。 By pressurizing the concrete C in the support pile 1A in this way, the support pile 1A having high strength can be constructed as shown in FIG. In the construction method of the support pile 1A according to the second embodiment, the enlarged bulb 23 is not formed at the lower end of the support pile 1A, but the lower end of the support pile 1A is made to bite into the support ground 7 to pressurize the concrete C and make a recess. Since it is brought into close contact with 17a, it is possible to improve the pull-out resistance with high strength as in the first embodiment.

なお、上述した各実施形態では、支持杭1,1Aに1段の凹部17aを形成したが、支持杭1の長手方向に複数段の凹部17aを形成してもよい。この場合にはより一層支持杭1,1Aが高強度になり引き抜き抵抗を増大できる。
また、本発明の第一実施形態では支持杭1の下端部に拡径部として拡径球根23を形成したが、必ずしも拡径球根23は設けなくてもよい。同様に、本発明の第二実施形態では支持杭1Aの下端部を支持地盤7に食い込ませたが、引抜力を考慮しない設計であれば、必ずしも支持地盤7に先端部が喰い込んでいなくてもよい。これらの場合でも、地盤2に圧入した支持杭1、1Aの突起部17の凹部17aに加圧コンクリートCを充填したことで、高い強度と引き抜き抵抗を得られる。
なお、支持地盤7は既設の地下構造物でもよい。また、凹部17aは支持地盤7や既設構造物に入っていてもよい。
In each of the above-described embodiments, one-stage recesses 17a are formed in the support piles 1 and 1A, but a plurality of-stage recesses 17a may be formed in the longitudinal direction of the support piles 1. In this case, the support piles 1 and 1A have higher strength and the pull-out resistance can be increased.
Further, in the first embodiment of the present invention, the enlarged diameter bulb 23 is formed as the enlarged diameter portion at the lower end portion of the support pile 1, but the enlarged diameter bulb 23 does not necessarily have to be provided. Similarly, in the second embodiment of the present invention, the lower end portion of the support pile 1A is made to bite into the support ground 7, but if the design does not consider the pulling force, the tip portion does not necessarily bite into the support ground 7. You may. Even in these cases, high strength and pull-out resistance can be obtained by filling the recesses 17a of the protrusions 17 of the support piles 1 and 1A press-fitted into the ground 2 with the pressure concrete C.
The supporting ground 7 may be an existing underground structure. Further, the recess 17a may be contained in the supporting ground 7 or the existing structure.

1 、1A 支持杭
2 地盤
3 圧入機
7 支持地盤
9 掘削機
11 拡径装置
13 押圧部
14、26 ジャッキ部
17 突起部
17a 凹部
19,25,32 加圧装置
20 蓋部
23 拡径球根
33 シリンダ装置
C コンクリート
b 空間
1, 1A Support pile 2 Ground
3 Press-fitting machine 7 Supporting ground 9 Excavator 11 Diameter-expanding device 13 Pressing part 14, 26 Jack part 17 Protruding part 17a Recession 19, 25, 32 Pressurizing device 20 Lid part 23 Diameter-expanding bulb 33 Cylinder device C Concrete b Space

Claims (5)

鋼管を打設する鋼管打設工程と、
前記鋼管を打設しながらまたは打設した後に前記鋼管内を掘削する掘削工程と、
前記鋼管の内壁を拡径して凹部を形成する凹部形成工程と、
前記鋼管内の前記凹部を含む範囲に固化材料を充填する固化材料充填工程と、
充填した前記固化材料を加圧する加圧工程と、
を備え
前記加圧工程において、加圧装置によって前記固化材料を加圧するようにし、
前記加圧装置は、圧入機によって前記固化材料を加圧するものであることを特徴とする支持杭の施工方法。
The steel pipe placing process for placing steel pipes and
An excavation process in which the inside of the steel pipe is excavated while or after the steel pipe is driven.
A recess forming step of expanding the diameter of the inner wall of the steel pipe to form a recess,
A solidifying material filling step of filling a range including the recess in the steel pipe with a solidifying material,
A pressurizing step of pressurizing the filled solidified material and
Equipped with a,
In the pressurizing step, the solidifying material is pressurized by a pressurizing device.
A method for constructing a support pile, wherein the pressurizing device pressurizes the solidifying material with a press-fitting machine.
前記加圧装置は、前記鋼管内に蓋部を固定し、圧入機で前記鋼管を押すことで前記固化材料を加圧するようにした請求項に記載された支持杭の施工方法。 The method for constructing a support pile according to claim 1 , wherein the pressurizing device has a lid fixed in the steel pipe and presses the steel pipe with a press-fitting machine to pressurize the solidifying material. 鋼管を打設する鋼管打設工程と、
前記鋼管を打設しながらまたは打設した後に前記鋼管内を掘削する掘削工程と、
前記鋼管の内壁を拡径して凹部を形成する凹部形成工程と、
前記鋼管内の前記凹部を含む範囲に固化材料を充填する固化材料充填工程と、
充填した前記固化材料を加圧する加圧工程と、
を備え
前記加圧工程において、加圧装置によって前記固化材料を加圧するようにし、
前記加圧装置は、前記鋼管内にシリンダ装置を固定し、該シリンダ装置で前記固化材料を加圧するようにしたことを特徴とする支持杭の施工方法。
The steel pipe placing process for placing steel pipes and
An excavation process in which the inside of the steel pipe is excavated while or after the steel pipe is driven.
A recess forming step of expanding the diameter of the inner wall of the steel pipe to form a recess,
A solidifying material filling step of filling a range including the recess in the steel pipe with a solidifying material,
A pressurizing step of pressurizing the filled solidified material and
Equipped with a,
In the pressurizing step, the solidifying material is pressurized by a pressurizing device.
The pressurizing device is a method for constructing a support pile, characterized in that a cylinder device is fixed in the steel pipe and the solidifying material is pressurized by the cylinder device.
前記加圧工程において、前記鋼管の下端部から前記固化材料を突出させて前記鋼管の径よりも拡径された固化材料の拡径部を形成した請求項1または3に記載された支持杭の施工方法。 The support pile according to claim 1 or 3 , wherein in the pressurizing step, the solidifying material is projected from the lower end of the steel pipe to form an enlarged diameter portion of the solidifying material whose diameter is larger than the diameter of the steel pipe. Construction method. 前記加圧工程において、前記鋼管の下端部から突出する前記固化材料を支持地盤に食い込ませた請求項1または3に記載された支持杭の施工方法。 The method for constructing a support pile according to claim 1 or 3 , wherein in the pressurizing step, the solidifying material protruding from the lower end of the steel pipe bites into the support ground.
JP2017095797A 2017-05-12 2017-05-12 Construction method of support pile Active JP6932544B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017095797A JP6932544B2 (en) 2017-05-12 2017-05-12 Construction method of support pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017095797A JP6932544B2 (en) 2017-05-12 2017-05-12 Construction method of support pile

Publications (2)

Publication Number Publication Date
JP2018193686A JP2018193686A (en) 2018-12-06
JP6932544B2 true JP6932544B2 (en) 2021-09-08

Family

ID=64569178

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017095797A Active JP6932544B2 (en) 2017-05-12 2017-05-12 Construction method of support pile

Country Status (1)

Country Link
JP (1) JP6932544B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102099282B1 (en) * 2019-05-30 2020-04-22 삼호엔지니어링 주식회사 Partially enlarging apparatus for underground pipe and composite cast in place pile method using the same
KR102037274B1 (en) * 2019-05-30 2019-10-28 삼호엔지니어링 주식회사 Partial extension apparatus for underground pipe and composite cast in place pile method using the same
KR102037275B1 (en) * 2019-05-30 2019-10-28 삼호엔지니어링 주식회사 Partially expanding apparatus for underground pipe and composite cast in place pile method using the same
KR102224524B1 (en) * 2019-08-12 2021-03-08 삼호엔지니어링 주식회사 Composite cast in place pile method using partially expanding apparatus for underground pipe
KR102224526B1 (en) * 2019-08-15 2021-03-08 삼호엔지니어링 주식회사 Partial extension apparatus for underground pipe and composite cast in place pile method using the same
JP7295436B2 (en) * 2020-01-29 2023-06-21 日本製鉄株式会社 METHOD FOR MANUFACTURING STEEL PIPE PILE WITH INTERNAL PROJECTS, CONSTRUCTION METHOD OF STEEL PIPE PILE, AND STEEL PIPE PILE WITH INNER PROJECTIONS
JP7288199B2 (en) * 2020-01-29 2023-06-07 日本製鉄株式会社 METHOD FOR MANUFACTURING STEEL PIPE PILE WITH INTERNAL PROJECTS, CONSTRUCTION METHOD OF STEEL PIPE PILE, AND STEEL PIPE PILE WITH INNER PROJECTIONS
CN114851376B (en) * 2022-05-09 2023-12-29 新疆博泷建设工程有限公司 Prefabrication device and prefabrication method for engineering building foundation piles

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57174527A (en) * 1981-04-20 1982-10-27 Kubota Ltd Construction of underground pile
JP2641137B2 (en) * 1995-05-01 1997-08-13 株式会社技研製作所 Pressing device for cylindrical structure and method of driving cylindrical structure
JP3880161B2 (en) * 1997-07-02 2007-02-14 株式会社技研製作所 Steel pipe pile support structure and construction equipment
JP2000001849A (en) * 1998-06-12 2000-01-07 Geotop Corp Cast-in-place pile
JP3749868B2 (en) * 2002-03-12 2006-03-01 株式会社藤井組 Steel pipe pile construction method
US20050019104A1 (en) * 2003-07-23 2005-01-27 Derald Christians Soil stabilization and pile formation method

Also Published As

Publication number Publication date
JP2018193686A (en) 2018-12-06

Similar Documents

Publication Publication Date Title
JP6932544B2 (en) Construction method of support pile
JP5199166B2 (en) Foundation pile structure by site construction and construction method of foundation pile
CN104234055B (en) A kind of prefabricated pile post-grouting device and technique thereof
KR101332848B1 (en) Method for constructing micro pile using deformed or screw steel pipe and pressure grouting
JP4901593B2 (en) Underground bite type anchor and its anchor method
KR101236765B1 (en) Method for placing adhesive filling into the expanded drill hole to increase bearing capacity of piles and tention members and apparatus therefor
JP2008248524A (en) Steel pipe pile construction method
JP6110156B2 (en) Construction method of high bearing capacity pile
KR101698457B1 (en) Multi pile construction method for strengthening weak soil
JP5777435B2 (en) Reinforcement method for foundations for small buildings
KR101119829B1 (en) Method for cast-in-place pile construction using punctured couplers
JP2007255107A (en) Casting concrete pile construction method
CN103741682B (en) The construction method of a kind of carbon fiber cloth bag cast-in-place antiarch surface composition shaped pile
JP3664361B2 (en) Method of burying steel pipe support piles
JP5551750B2 (en) Ground bite type support pile
JP4499001B2 (en) Filling reinforcement method and filling
US20120163923A1 (en) Structure supporting system
KR101951684B1 (en) Expandable cast-in-place pile construction method
JPH06108462A (en) Foundation pile method and its equipment
JP6319942B2 (en) Steel pipe sheet pile press-in method and pipes
KR102037275B1 (en) Partially expanding apparatus for underground pipe and composite cast in place pile method using the same
JP2011246981A (en) Foundation reinforcement method of structure
JP2884268B2 (en) Construction method of cast-in-place concrete pile
JP2000120066A (en) Construction method of steel pipe pile
JP2015187379A (en) Steel pipe pile and its construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200403

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210218

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210323

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210524

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210720

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210818

R150 Certificate of patent or registration of utility model

Ref document number: 6932544

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250