JP6981606B2 - Pile driving method on bedrock - Google Patents
[go: Go Back, main page]

JP6981606B2 - Pile driving method on bedrock - Google Patents

Pile driving method on bedrock Download PDF

Info

Publication number
JP6981606B2
JP6981606B2 JP2017074143A JP2017074143A JP6981606B2 JP 6981606 B2 JP6981606 B2 JP 6981606B2 JP 2017074143 A JP2017074143 A JP 2017074143A JP 2017074143 A JP2017074143 A JP 2017074143A JP 6981606 B2 JP6981606 B2 JP 6981606B2
Authority
JP
Japan
Prior art keywords
pile
bedrock
protrusion
outer peripheral
tip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017074143A
Other languages
Japanese (ja)
Other versions
JP2018178382A (en
Inventor
博文 田口
洋一 嶋田
一訓 稲積
夕一 辰見
通宏 中島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GANKEN CO., LTD.
JFE Steel Corp
Obayashi Corp
Toa Corp
Original Assignee
GANKEN CO., LTD.
JFE Steel Corp
Obayashi Corp
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GANKEN CO., LTD., JFE Steel Corp, Obayashi Corp, Toa Corp filed Critical GANKEN CO., LTD.
Priority to JP2017074143A priority Critical patent/JP6981606B2/en
Publication of JP2018178382A publication Critical patent/JP2018178382A/en
Application granted granted Critical
Publication of JP6981606B2 publication Critical patent/JP6981606B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

本発明は、岩盤への杭打設工法に関し、さらに詳しくは、ガンパイル工法により岩盤に打設された杭を、長期に渡り安定的に岩盤に固定することができる岩盤への杭打設工法に関するものである。 The present invention relates to a pile driving method for rock, and more particularly to a pile driving method for rock that can stably fix a pile placed in rock by a gun pile method to rock for a long period of time. It is a thing.

従来、岩盤に対して鋼矢板や鋼管矢板などの杭を打設する施工が行われている。この施工において杭をバイブロハンマー等で打設すると杭で破砕された破砕岩が杭の先端と岩盤の間でクッション材となり、打撃エネルギーが岩盤に十分に伝わらない。これに起因して、岩盤を容易に破砕することができず、杭の打設に要する時間が長くなるという問題があった。そこで、打設する杭に、高水圧ポンプに接続された注水パイプを設け、杭によって破砕された岩石を注水パイプの先端ノズルから噴射する噴射水により除去しつつ、杭を岩盤に打ち込むいわゆるガンパイル工法が開発されている(例えば、特許文献1参照)。 Conventionally, piles such as steel sheet piles and steel pipe sheet piles have been placed on the bedrock. In this construction, when the pile is driven with a vibro hammer or the like, the crushed rock crushed by the pile becomes a cushioning material between the tip of the pile and the bedrock, and the striking energy is not sufficiently transmitted to the bedrock. Due to this, there is a problem that the bedrock cannot be easily crushed and the time required for driving the piles becomes long. Therefore, a so-called gunpile method is used in which a water injection pipe connected to a high water pressure pump is provided on the pile to be driven, and the rock crushed by the pile is removed by the jet water jetted from the tip nozzle of the water injection pipe, while the pile is driven into the bedrock. Has been developed (see, for example, Patent Document 1).

ガンパイル工法により杭を打設した場合には、打設された杭と岩盤との間には、ある程度のすき間が生じる。このすき間が大きい程、杭と岩盤との摩擦力が小さくなるため、杭を岩盤に対して長期間に渡って安定して固定するには不利になる。現状では、ガンパイル工法によって岩盤に打設された杭は、いわゆる仮設杭として短期的に使用されているので、長期的な安定した固定強度は必要とされていない。 When piles are driven by the gun pile method, a certain amount of gap is created between the piles and the bedrock. The larger the gap, the smaller the frictional force between the pile and the bedrock, which is disadvantageous for stably fixing the pile to the bedrock for a long period of time. At present, the piles placed on the bedrock by the gun pile method are used as so-called temporary piles in the short term, so long-term stable fixing strength is not required.

しかしながら、ガンパイル工法によって岩盤に打設された杭を、いわゆる本設杭として長期的に使用することができれば、打設した杭を、様々な構造物を構成する一部材として利用できるので有益である。そのためには、ガンパイル工法により打設された杭を岩盤に対して長期的に安定して固定させる工夫が必要になる。 However, if the piles driven into the bedrock by the gun pile method can be used for a long period of time as so-called main piles, it is advantageous because the piles placed can be used as one member constituting various structures. .. For that purpose, it is necessary to devise a method to stably fix the piles driven by the gun pile method to the bedrock for a long period of time.

特開2004−124505号公報Japanese Unexamined Patent Publication No. 2004-124505

本発明の目的は、ガンパイル工法により岩盤に打設された杭を、長期に渡り安定的に岩盤に固定することができる岩盤への杭打設工法を提供することにある。 An object of the present invention is to provide a pile driving method for rock that can stably fix a pile driven to rock by a gun pile method to rock for a long period of time.

上記目的を達成するため本発明の岩盤への杭打設工法は、振動杭打設機によって、杭の先端を岩盤に打ち付けて岩盤を破砕しつつ、破砕した岩石を、前記杭に隣接配置されている注水パイプの先端ノズルから噴射する水で前記杭の先端領域から排除しながら前記岩盤に前記杭を打ち込む岩盤への杭打設工法において、前記杭の先端部の外周面が他の部位よりも外周側に突出した厚肉の突出部を有するとともに、前記突出部以外の前記杭の少なくとも先端側の外周面の表面にその外周面からの突出量が前記突出部の最大突出量以下の凸部が設けられていて、前記杭が管状であり、前記突出部が、前記杭の最先端部で前記杭の
周方向全長に連続する一方の環状突出部と、前記一方の環状突出部の後端に連接されていて前記杭の周方向全長に連続する他方の環状突出部とで構成され、前記一方の環状突出部の外周面よりも前記他方の環状突出部の外周面が前記杭の外周側に突出している2段構造であり、前記凸部が、前記他方の環状突出部の後端から前記杭の長手方向に延在していて、前記杭を前記岩盤に所定深さ打込んだ後、前記杭と前記岩盤とのすき間にセメントミルクを充填し、このセメントミルクが固化することにより、固化したセメントミルクを介して前記杭を前記岩盤に固定させることを特徴とする。
本発明の別の岩盤への杭打設工法は、振動杭打設機によって、杭の先端を岩盤に打ち付けて岩盤を破砕しつつ、破砕した岩石を、前記杭に隣接配置されている注水パイプの先端ノズルから噴射する水で前記杭の先端領域から排除しながら前記岩盤に前記杭を打ち込む岩盤への杭打設工法において、前記杭の先端部の外周面が他の部位よりも外周側に突出した厚肉の突出部を有するとともに、前記突出部以外の前記杭の少なくとも先端側の外周面の表面にその外周面からの突出量が前記突出部の最大突出量以下の凸部が設けられていて、前記杭が管状であり、前記突出部が、前記杭の最先端部で前記杭の周方向全長に連続する環状突出部と、前記環状突出部の外周面に前記杭の周方向に間隔をあけて配置された複数の離間する突出部とで構成されていて、前記凸部が、それぞれの前記複数の離間する突出部の後端から前記杭の長手方向に延在して、それぞれの前記複数の離間する突出部は、前記凸部が存在する周方向位置にのみ配置されていて、前記杭を前記岩盤に所定深さ打込んだ後、前記杭と前記岩盤とのすき間にセメントミルクを充填し、このセメントミルクが固化することにより、固化したセメントミルクを介して前記杭を前記岩盤に固定させることを特徴とする。
In order to achieve the above object, in the pile driving method on the bedrock of the present invention, the crushed rock is placed adjacent to the pile while the tip of the pile is struck against the bedrock by a vibrating pile driving machine to crush the bedrock. In the pile driving method of driving the pile into the bedrock while removing it from the tip area of the pile with the water jetted from the tip nozzle of the water injection pipe, the outer peripheral surface of the tip of the pile is from another part. Also has a thick protruding portion protruding to the outer peripheral side, and the amount of protrusion from the outer peripheral surface is convex to the surface of the outer peripheral surface of at least the tip side of the pile other than the protruding portion. A portion is provided, the pile is tubular, and the protrusion is the tip of the pile, one annular protrusion continuous with the entire circumferential length of the pile, and the rear of the one annular protrusion. It is composed of the other annular protrusion that is connected to the end and is continuous with the total length in the circumferential direction of the pile, and the outer peripheral surface of the other annular protrusion is the outer circumference of the pile rather than the outer peripheral surface of the one annular protrusion. It has a two-stage structure protruding to the side, and the convex portion extends in the longitudinal direction of the pile from the rear end of the other annular protrusion, and the pile is driven into the bedrock to a predetermined depth. Later, cement milk is filled in the gap between the pile and the bedrock, and the cement milk solidifies to fix the pile to the bedrock through the solidified cement milk.
In another method of driving a pile into a bedrock of the present invention, a vibration pile driving machine is used to drive the tip of a pile into the bedrock to crush the bedrock, and the crushed rock is placed adjacent to the pile. In the pile driving method of driving the pile into the bedrock while removing the pile from the tip area of the pile with water sprayed from the tip nozzle of the pile, the outer peripheral surface of the tip of the pile is on the outer peripheral side of other parts. It has a protruding thick-walled protrusion, and a protrusion other than the protruding portion is provided on the surface of the outer peripheral surface of the pile at least on the tip end side so that the amount of protrusion from the outer peripheral surface is equal to or less than the maximum protrusion amount of the protruding portion. The pile is tubular, and the projecting portion is an annular projecting portion continuous with the entire circumferential direction of the pile at the tip end portion of the pile, and the outer peripheral surface of the annular projecting portion in the circumferential direction of the pile. It is composed of a plurality of separated protrusions arranged at intervals, and the convex portion extends from the rear end of each of the plurality of separated protrusions in the longitudinal direction of the pile, respectively. The plurality of separated protrusions of the above are arranged only in the circumferential position where the convex portion exists, and after the pile is driven into the bedrock to a predetermined depth, cement is provided in the gap between the pile and the bedrock. It is characterized in that the pile is fixed to the bedrock through the solidified cement milk by filling the milk and solidifying the cement milk .

本発明によれば、杭の先端部に外周面が他の部位よりも外周側に突出した突出部を有しているので、打設している杭の外周面と岩盤との摩擦抵抗が小さくなり、杭を円滑に打設することができる。また、打設した杭の外周面と岩盤との間に適度なすき間が確保されるので、このすき間に必要な量のセメントミルクを充填することができる。 According to the present invention, since the outer peripheral surface of the pile has a protruding portion protruding toward the outer peripheral side from other parts, the frictional resistance between the outer peripheral surface of the pile to be driven and the bedrock is small. Therefore, the pile can be driven smoothly. In addition, since an appropriate gap is secured between the outer peripheral surface of the placed pile and the bedrock, a required amount of cement milk can be filled in this gap.

そして、岩盤に対して所定深さ打ち込んだ杭と岩盤とのすき間に充填したセメントミルクが固化することにより、固化したセメントミルクを介して杭が岩盤に固定される。杭の先端側の外周面に設けられている凸部の突出量は突出部の最大突出量以下なので、杭の打設の際には凸部は突出部に保護されて損傷し難くなっている。そして、この凸部の存在によってセメントミルクと接合する杭の外周面の面積が増大する。そのため、杭を岩盤に一段と強固に固定するに有利になっている。 Then, the cement milk filled in the gap between the pile driven into the bedrock to a predetermined depth and the bedrock solidifies, and the pile is fixed to the bedrock through the solidified cement milk. Since the amount of protrusion of the protrusion provided on the outer peripheral surface on the tip side of the pile is less than the maximum amount of protrusion of the protrusion, the protrusion is protected by the protrusion and is not easily damaged when the pile is placed. .. The presence of this convex portion increases the area of the outer peripheral surface of the pile to be joined to the cement milk. Therefore, it is advantageous to fix the pile to the bedrock more firmly.

本発明の岩盤への杭打設工法において、杭を岩盤に打ち込んでいる工程を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the process of driving a pile into the bedrock in the vertical cross-sectional view in the pile driving method to the bedrock of this invention. 図1の杭の先端部周辺を拡大して例示する説明図である。It is explanatory drawing which enlarges and exemplifies the periphery of the tip portion of the pile of FIG. 杭の突出部を拡大して縦断面視で例示する説明図である。It is explanatory drawing which enlarges and exemplifies the protrusion of the pile in the vertical cross-sectional view. 杭の先端側の外周面を例示する説明図である。It is explanatory drawing which illustrates the outer peripheral surface on the tip end side of a pile. 岩盤に所定深さ打込んだ杭と岩盤とのすき間にセメントミルクを充填する工程を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the process of filling cement milk in the gap between the pile which was driven into the bedrock to a predetermined depth, and the bedrock in the vertical cross-sectional view. 図5のセメントミルクが固化して、このセメントミルクを介して杭が岩盤に固定されている状態を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the state in which the cement milk of FIG. 5 is solidified and the pile is fixed to the bedrock through this cement milk in the vertical cross-sectional view. 図6のA−A断面図である。FIG. 6 is a cross-sectional view taken along the line AA of FIG. 突出部の変形例を示す杭の縦断面図である。It is a vertical sectional view of a pile which shows the deformation example of a protrusion. 突出部の別の変形例を示す杭の縦断面図である。It is a vertical sectional view of a pile which shows another deformation example of a protrusion. 凸部の変形例を示す杭の正面図である。It is a front view of the pile which shows the deformation example of a convex part. 凸部の別の変形例を示す杭の正面図である。It is a front view of the pile which shows another deformation example of a convex part. 図11のB−B断面図である。11 is a cross-sectional view taken along the line BB of FIG. 突出部を2段構造にした変形例を杭の右半分の縦断面視で例示する説明図である。It is explanatory drawing which illustrates the modification which made the protrusion into a two-step structure in the vertical cross-sectional view of the right half of a pile. 突出部の別の変形例を杭の右半分の縦断面視で例示する説明図である。It is explanatory drawing which illustrates another deformation example of the protrusion in the vertical cross-sectional view of the right half of a pile. 図14のC−C断面視で杭を例示する説明図である。It is explanatory drawing which illustrates the pile in the CC cross-sectional view of FIG. 隅肉溶接の状態を杭の正面視で例示し、図16(A)は異形鉄筋の長手方向に連続して施工した場合、図16(B)は断続的に施工した場合を示す。The state of fillet welding is illustrated from the front view of the pile, FIG. 16 (A) shows the case where the deformed reinforcing bar is continuously constructed in the longitudinal direction, and FIG. 16 (B) shows the case where the pile is constructed intermittently. 凸部の別の変形例を示す杭の正面図である。It is a front view of the pile which shows another deformation example of a convex part. 凸部の別の変形例を示す杭の正面図である。It is a front view of the pile which shows another deformation example of a convex part. 岩盤に所定深さ打込んだ杭を上方移動させた状態でセメントミルクを充填する工程を縦断面視で例示する説明図である。It is explanatory drawing which illustrates the process of filling cement milk with the pile driven into the bedrock to a predetermined depth moved upward in the vertical cross-sectional view.

以下、本発明の岩盤への杭打設方法を図に示した実施形態に基づいて説明する。 Hereinafter, the method of driving piles on the bedrock of the present invention will be described based on the embodiment shown in the figure.

図1、図2に例示する杭2の打設現場は、岩盤Rの上に土砂層Sが堆積した地盤である。この地盤にガンパイル工法によって杭2を打設するには、バイブロハンマー等の振動杭打設機1が発振する振動を利用する。杭2としては例えば、H型鋼や鋼矢板など様々なタイプを用いることができるが、この実施形態では鋼管杭を用いている。 The driving site of the pile 2 exemplified in FIGS. 1 and 2 is the ground where the earth and sand layer S is deposited on the bedrock R. In order to drive the pile 2 on this ground by the gun pile method, the vibration oscillated by the vibration pile driving machine 1 such as a vibro hammer is used. As the pile 2, various types such as H-shaped steel and steel sheet pile can be used, but in this embodiment, a steel pipe pile is used.

図3、図4に例示するように、杭2の先端部は外周面が他の部位よりも外周側に所定の突出量t1だけ突出した突出部2aを有している。突出量t1は一定になっているので、この突出量t1が最大突出量となる。突出部2aは杭2の周方向に連続した筒状になっている。即ち、本発明では、先端部に他の部位に比して相対的に厚肉の突出部2aを有する杭2を使用する。この実施形態では、突出部2aが予め一体的に形成されている杭2を使用している。 As illustrated in FIGS. 3 and 4, the tip portion of the pile 2 has a protruding portion 2a whose outer peripheral surface protrudes toward the outer peripheral side from other portions by a predetermined protrusion amount t1. Since the protrusion amount t1 is constant, this protrusion amount t1 is the maximum protrusion amount. The protruding portion 2a has a cylindrical shape continuous in the circumferential direction of the pile 2. That is, in the present invention, a pile 2 having a protruding portion 2a having a relatively thick wall at the tip portion as compared with other portions is used. In this embodiment, a pile 2 in which the protrusion 2a is integrally formed in advance is used.

突出部2aの最大突出量t1は例えば、6mm以上35mm以下にすることが好ましく、9mm以上12mm以下にすることがより好ましい。この突出部2aの杭2の長手方向寸法Lは、例えば20mm以上300mm以下が好ましい。 The maximum protrusion amount t1 of the protrusion 2a is preferably, for example, 6 mm or more and 35 mm or less, and more preferably 9 mm or more and 12 mm or less. The longitudinal dimension L of the pile 2 of the protrusion 2a is preferably, for example, 20 mm or more and 300 mm or less.

突出部2aは、他の部位に比して高強度および高硬度であることが望ましい。突出部2aの強度は例えば、引張強さが1000N/mm2以上に設定される。 It is desirable that the protruding portion 2a has higher strength and higher hardness than other portions. The strength of the protrusion 2a is set, for example, to have a tensile strength of 1000 N / mm 2 or more.

突出部2a以外のこの杭2の先端側の外周面の表面には、その表面から外周側に所定の突出量t2だけ突出した凸部2bが設けられている。凸部2bの突出量t2は突出部2の最大突出量t1以下になっている。突出量t2は1mm以上で、かつ、最大突出量t1よりも小さいことが好ましい。凸部2bの突出量t2が1mm未満では、杭2の外周面とセメントミルクCの付着強度を向上させる効果が過小になる。凸部2bの突出量t2を最大突出量t1よりも大きくすると、杭2を打設する際に岩盤Rに接触したり、打設の際に発生する岩粉が衝突して凸部2bが損耗し易くなる。 On the surface of the outer peripheral surface of the pile 2 on the tip end side other than the protruding portion 2a, a convex portion 2b protruding from the surface to the outer peripheral side by a predetermined protrusion amount t2 is provided. The protrusion amount t2 of the protrusion 2b is equal to or less than the maximum protrusion amount t1 of the protrusion 2. It is preferable that the protrusion amount t2 is 1 mm or more and smaller than the maximum protrusion amount t1. If the protrusion amount t2 of the convex portion 2b is less than 1 mm, the effect of improving the adhesion strength between the outer peripheral surface of the pile 2 and the cement milk C becomes too small. When the protrusion amount t2 of the convex portion 2b is made larger than the maximum protrusion amount t1, the convex portion 2b is worn out due to contact with the bedrock R when the pile 2 is driven or the rock powder generated during the driving collides with the rock mass. It becomes easier to do.

この凸部2bは、概ね、杭2が岩盤Rに埋設される範囲に配置される。例えば、凸部2bを設ける範囲は、杭2の先端から後端に向かって2m〜10mまでの範囲(凸部2bを設ける範囲の後端位置を杭2の先端から2m〜10mの位置にする)、或いは、杭2の先端から後端に向かって杭2の外径の100%〜500%の長さまでの範囲(凸部2bを設ける範囲の後端位置を杭2の先端から杭2の外径の100%〜500%の長さの位置にする)。尚、突出部2aには凸部2bを設けない。 The convex portion 2b is generally arranged in a range where the pile 2 is buried in the bedrock R. For example, the range in which the convex portion 2b is provided is a range from the tip of the pile 2 to the rear end of 2 m to 10 m (the rear end position of the range in which the convex portion 2b is provided is set to a position of 2 m to 10 m from the tip of the pile 2). ) Or, the range from the tip of the pile 2 to the rear end to a length of 100% to 500% of the outer diameter of the pile 2 (the rear end position of the range where the convex portion 2b is provided is set from the tip of the pile 2 to the pile 2). Positioned at a length of 100% to 500% of the outer diameter). The protruding portion 2a is not provided with the convex portion 2b.

この実施形態では、凸部2bは杭2の外周面で周方向に延在する環状凸部になっていて、複数の環状凸部が杭2の長手方向に間隔をあけて配置されている。それぞれの環状凸部は杭2の長手方向に対して直交した向きに配置されている。 In this embodiment, the convex portion 2b is an annular convex portion extending in the circumferential direction on the outer peripheral surface of the pile 2, and a plurality of annular convex portions are arranged at intervals in the longitudinal direction of the pile 2. Each annular convex portion is arranged in a direction orthogonal to the longitudinal direction of the pile 2.

杭2には注水パイプ4が着脱自在に隣接配置されている。この実施形態では、注水パイプ4が杭2の内周面に沿って杭2の長手方向に延在している。1本の杭2に対して、単数または複数の注水パイプ4が配置される。注水パイプ4の後端には直接、または別の配管3aを介して、地盤上に配置された水タンク3が接続される。注水パイプ4の先端は、水タンク3から供給された水Wを噴射する先端ノズル4aになっている。杭2には、打設中の注入パイプ4の振れを抑制するための振れ留め金具が適宜設けられる。先端ノズル4aは、杭2の先端から突出しない位置に配置される。 A water injection pipe 4 is detachably arranged adjacent to the pile 2. In this embodiment, the water injection pipe 4 extends in the longitudinal direction of the pile 2 along the inner peripheral surface of the pile 2. A single or a plurality of water injection pipes 4 are arranged for one pile 2. A water tank 3 arranged on the ground is connected to the rear end of the water injection pipe 4 directly or via another pipe 3a. The tip of the water injection pipe 4 is a tip nozzle 4a for injecting water W supplied from the water tank 3. The pile 2 is appropriately provided with a steady rest fitting for suppressing the runout of the injection pipe 4 during driving. The tip nozzle 4a is arranged at a position that does not protrude from the tip of the pile 2.

この杭2を打設するには、クレーン等によって吊り下げられた振動杭打設機1により杭2を保持する。次いで、振動杭打設機1により杭2を振動させながら、杭2の先端を土砂層Sに打ち込んでゆく。杭2の先端が土砂層Sの範囲内に位置していて、岩盤Rまで達していない段階では、先端ノズル4aから水Wを噴射する必要はない。 In order to drive the pile 2, the pile 2 is held by a vibrating pile driving machine 1 suspended by a crane or the like. Next, the tip of the pile 2 is driven into the earth and sand layer S while the pile 2 is vibrated by the vibrating pile driving machine 1. When the tip of the pile 2 is located within the range of the earth and sand layer S and has not reached the bedrock R, it is not necessary to inject water W from the tip nozzle 4a.

図1、2に例示するように、杭2の先端が岩盤Rに達すると、水タンク3に収容されている水Wを高圧ポンプによって注水パイプ4に供給して、先端ノズル4aから噴射させる。即ち、振動杭打設機1により杭2を振動させるとともに、先端ノズル4aから水Wを噴射しながら杭2を岩盤Rに打ち込む。即ち、打設している杭2の先端が岩盤Rに到達した時点で先端ノズル4aから水の噴射を開始するとよい。これにより、噴射した水Wによって土砂層Sを不必要に緩めることがなくなり、かつ、土砂層Sと杭2との間に実質的にすき間が形成されなくなるので、後工程で使用するセメントミルクCの量を抑制するには有利になる。 As illustrated in FIGS. 1 and 2, when the tip of the pile 2 reaches the bedrock R, the water W contained in the water tank 3 is supplied to the water injection pipe 4 by a high-pressure pump and injected from the tip nozzle 4a. That is, the pile 2 is vibrated by the vibrating pile driving machine 1, and the pile 2 is driven into the bedrock R while injecting water W from the tip nozzle 4a. That is, it is preferable to start spraying water from the tip nozzle 4a when the tip of the pile 2 to be driven reaches the bedrock R. As a result, the jetted water W does not unnecessarily loosen the sediment layer S, and a gap is substantially not formed between the sediment layer S and the pile 2, so that the cement milk C used in the subsequent process is not formed. It is advantageous to suppress the amount of.

振動する杭2の打撃を受けることにより、杭2の先端に衝突した岩盤Rの部分が破砕される。岩盤Rが破砕されて発生した岩石Rcは、杭2の先端と岩盤Rとの間に存在するが、杭2の先端が打撃の反力により上方移動して岩盤Rから離反した際に、先端ノズル4aから噴射されている水Wにより杭2の先端領域から排除される。杭2が続いて岩盤Rを打撃する時には杭2の先端と岩盤Rとの間には緩衝作用を及ぼす岩石Rcがない状態になる。そのため、杭2による打撃エネルギーが岩石Rcによって減殺されることなく岩盤Rに作用して岩盤Rを容易に破砕することができる。杭2の打撃による岩盤Rの破砕と、先端ノズル4aから噴射される水Wによる岩石Rcの排除を繰り返して、岩盤Rへの杭2の打込みを進める。杭2は先端部に相対的に厚肉の突出部2aを有しているので他の部位に比して、岩盤Rに衝突しても変形し難いというメリットがある。 By being hit by the vibrating pile 2, the portion of the bedrock R that collides with the tip of the pile 2 is crushed. The rock Rc generated by crushing the bedrock R exists between the tip of the pile 2 and the bedrock R, but when the tip of the pile 2 moves upward due to the reaction force of the impact and separates from the bedrock R, the tip The water W ejected from the nozzle 4a removes the pile 2 from the tip region. When the pile 2 subsequently hits the bedrock R, there is no rock Rc exerting a buffering action between the tip of the pile 2 and the bedrock R. Therefore, the impact energy of the pile 2 acts on the rock R without being attenuated by the rock Rc, and the rock R can be easily crushed. The crushing of the bedrock R by the impact of the pile 2 and the removal of the rock Rc by the water W ejected from the tip nozzle 4a are repeated, and the pile 2 is driven into the bedrock R. Since the pile 2 has a relatively thick protruding portion 2a at the tip portion, there is an advantage that the pile 2 is less likely to be deformed even if it collides with the bedrock R as compared with other portions.

杭2を岩盤Rに対して所定深さまで打込むと、打ち込んだ杭2と岩盤Rとの間には、ある程度のすき間gが生じる。このすき間gは例えば20mm〜100mm程度である。そこで、図5に例示するように、杭2と岩盤Rとのすき間gにセメントミルクC(セメントと水の混合材)を充填する。すき間gに充填する前のセメントミルクCには、セメントミルクCを充填する際の流動性に支障が生じない範囲で所定量の増粘材Bや膨張材Dを予め配合しておくとよい。増粘材Bおよび膨張材Dの詳細については後述する。尚、土砂層Sはその土圧によって締め固まるので、杭2と土砂層Sとの間には実質的にすき間は生じない。したがって、杭2には土砂層Sが密着して杭2は土砂層Sに固定されることになる。 When the pile 2 is driven to a predetermined depth with respect to the bedrock R, a certain gap g is generated between the driven pile 2 and the bedrock R. This gap g is, for example, about 20 mm to 100 mm. Therefore, as illustrated in FIG. 5, the gap g between the pile 2 and the bedrock R is filled with cement milk C (a mixed material of cement and water). It is advisable to preliminarily add a predetermined amount of the thickener B and the expanding material D to the cement milk C before filling the gap g within a range that does not hinder the fluidity when the cement milk C is filled. Details of the thickener B and the expansion material D will be described later. Since the earth and sand layer S is compacted by the earth pressure, there is substantially no gap between the pile 2 and the earth and sand layer S. Therefore, the earth and sand layer S is in close contact with the pile 2, and the pile 2 is fixed to the earth and sand layer S.

セメントミルクCは、地盤上に配置された収容タンク5から充填用パイプ6を通じてすき間gに供給される。一般的には、このすき間gには地下水が存在しているが、セメントミルクCを充填することにより、地下水とセメントミルクCが置き換わることになる。充填用パイプ6は1本に限らず、複数本にすることもできる。 The cement milk C is supplied from the storage tank 5 arranged on the ground to the gap g through the filling pipe 6. Generally, groundwater exists in this gap g, but by filling the cement milk C, the groundwater and the cement milk C are replaced. The number of filling pipes 6 is not limited to one, and may be multiple.

すき間gの大部分の範囲にセメントミルクCを充填した後は、所定時間、養生することによりセメントミルクCを固化させる。図6、7に例示するように、すき間gに介在して固化したセメントミルクCは、杭2によって削られた岩盤Rの表面および杭2の表面(周面)に強固に付着する。固化したセメントミルクCの一軸圧縮強度は例えば、5N/mm2以上にする。 After filling the majority of the gap g with the cement milk C, the cement milk C is solidified by curing for a predetermined time. As illustrated in FIGS. 6 and 7, the cement milk C solidified via the gap g firmly adheres to the surface of the bedrock R carved by the pile 2 and the surface (peripheral surface) of the pile 2. The uniaxial compressive strength of the solidified cement milk C is, for example, 5 N / mm 2 or more.

本発明では杭2の凸部2bを設けているので、凸部2bを設けていない場合に比して、セメントミルクCと接合する杭2の外周面の面積が増大する。それ故、固化したセメントミルクCを介して杭2を岩盤Rに対して一段と強固に固定することができる。即ち、本発明では、凸部2bを設けることで、岩盤Rと杭2の周面との間の摩擦力(固定力)を大幅に増大させることができる。 In the present invention, since the convex portion 2b of the pile 2 is provided, the area of the outer peripheral surface of the pile 2 to be joined to the cement milk C is increased as compared with the case where the convex portion 2b is not provided. Therefore, the pile 2 can be more firmly fixed to the bedrock R via the solidified cement milk C. That is, in the present invention, by providing the convex portion 2b, the frictional force (fixing force) between the bedrock R and the peripheral surface of the pile 2 can be significantly increased.

詳述すると、杭2と岩盤Rとの間のすき間gにセメントミルクCを充填した場合、杭の周面とセメントミルクCとの境界面、セメントミルクCと岩盤Rとの境界面が形成される。セメントミルクCと岩盤Rとの境界面では、岩盤Rの凹凸の影響によって互いの付着強度は比較的高くなる。一方、杭2の周面が滑らかであると、セメントミルクCとの境界面では互いの付着強度は比較的低くなる。 More specifically, when the gap g between the pile 2 and the bedrock R is filled with cement milk C, the boundary surface between the peripheral surface of the pile and the cement milk C and the boundary surface between the cement milk C and the bedrock R are formed. To. At the boundary surface between the cement milk C and the bedrock R, the mutual adhesion strength becomes relatively high due to the influence of the unevenness of the bedrock R. On the other hand, if the peripheral surface of the pile 2 is smooth, the adhesive strength between the piles 2 and the cement milk C is relatively low.

ここで、杭2の周面摩擦力度を考えると、杭2の周面が滑らかな仕様では、例えば杭2に引き抜き力を作用させた場合、杭2の周面とセメントミルクCの付着強度程度に達すると、セメントミルクCと岩盤Rとの境界面に先行して杭の周面とセメントミルクCとの境界ですべりが発生する。そのため、セメントミルクCと岩盤Rとの付着によって発現される周面摩擦力度よりも低い摩擦力度しか得られない。 Here, considering the degree of frictional force on the peripheral surface of the pile 2, if the peripheral surface of the pile 2 is smooth, for example, when a pulling force is applied to the pile 2, the adhesive strength between the peripheral surface of the pile 2 and the cement milk C is about. When it reaches, slip occurs at the boundary between the peripheral surface of the pile and the cement milk C prior to the boundary surface between the cement milk C and the bedrock R. Therefore, a frictional force lower than the peripheral frictional force developed by the adhesion between the cement milk C and the bedrock R can be obtained.

ところが、本発明では杭2の外周面に凸部2bを設けているので、杭2の外周面とセメントミルクCの付着強度が向上して、セメントミルクCと岩盤Rの付着強度と同等程度にすることが可能になっている。即ち、セメントミルクCと岩盤Rとの付着によって発現される周面摩擦力度と、杭2の周面とセメントミルクCとの付着によって発現される周面摩擦力度とを同等にすることができるので、岩盤Rと杭2の周面との摩擦力の向上にセメントミルクCが無駄なく効率的に使用されている。 However, in the present invention, since the convex portion 2b is provided on the outer peripheral surface of the pile 2, the adhesion strength between the outer peripheral surface of the pile 2 and the cement milk C is improved to the same level as the adhesion strength between the cement milk C and the bedrock R. It is possible to do. That is, the peripheral frictional force developed by the adhesion between the cement milk C and the bedrock R can be made equal to the peripheral frictional force developed by the adhesion between the peripheral surface of the pile 2 and the cement milk C. , Cement milk C is efficiently used to improve the frictional force between the bedrock R and the peripheral surface of the pile 2.

しかも、凸部2bの突出量t2は突出部2aの最大突出量t1以下なので、杭2を打設する際には凸部2bは突出部2aに保護されて、岩盤Rとの接触や破砕された岩粉との接触によって損傷、摩耗する不具合を防止し易い仕様になっている。そのため、杭2の打設後も凸部2bを健全な状態に維持することができる。 Moreover, since the protrusion amount t2 of the protrusion 2b is equal to or less than the maximum protrusion amount t1 of the protrusion 2a, the protrusion 2b is protected by the protrusion 2a when the pile 2 is driven, and is contacted with or crushed by the bedrock R. The specifications are such that it is easy to prevent problems such as damage and wear due to contact with rock powder. Therefore, the convex portion 2b can be maintained in a sound state even after the pile 2 is driven.

加えて、杭2は先端部に上述した仕様の突出部2aを有しているので、杭2と岩盤Rとのすき間gが適切な大きさになる。このすき間gが過小にならないので、打設している杭2の周面に作用する地盤(土砂層Sおよび岩盤R)からの摩擦が低減して円滑に打設することができる。一方、このすき間gを過大にしないために突出部2aの最大突出量t1は、35mm以下、より好ましくは12mm以下にする。これにより、打設後の杭2の周面に作用する地盤(土砂層Sおよび岩盤R)からの摩擦支持力が低下することを回避できる。 In addition, since the pile 2 has the protruding portion 2a of the above-mentioned specifications at the tip portion, the gap g between the pile 2 and the bedrock R becomes an appropriate size. Since this gap g is not too small, friction from the ground (earth and sand layer S and bedrock R) acting on the peripheral surface of the pile 2 being driven is reduced, and the pile 2 can be smoothly driven. On the other hand, in order not to make the gap g excessive, the maximum protrusion amount t1 of the protrusion 2a is set to 35 mm or less, more preferably 12 mm or less. As a result, it is possible to avoid a decrease in the frictional bearing capacity from the ground (earth and sand layer S and bedrock R) acting on the peripheral surface of the pile 2 after placing.

上記のとおり本発明によれば、杭2を長期に渡って安定的に岩盤Rに固定することが可能になる。特に、杭2の引抜き抵抗力の大幅な向上が期待できるので、構造物を構成する一部材としてこの杭2を使用しても、十分な耐震性を確保することが可能になる。それ故、ガンパイル工法により打設した杭2を、仮設杭としてだけでなく本設杭として用いることができる。 As described above, according to the present invention, the pile 2 can be stably fixed to the bedrock R for a long period of time. In particular, since the pull-out resistance of the pile 2 can be expected to be significantly improved, sufficient seismic resistance can be ensured even if the pile 2 is used as one member constituting the structure. Therefore, the pile 2 driven by the gun pile method can be used not only as a temporary pile but also as a main pile.

突出部2aが予め一体的に形成されている杭2を使用すると、突出部2aが後付けされた杭2よりも、突出部2a(杭2)の長期間の安定した耐久性を確保するには有利になる。それ故、本設杭として用いるためには、突出部2aが予め一体的に形成されている杭2にするとよい。 When the pile 2 in which the protrusion 2a is integrally formed in advance is used, the long-term stable durability of the protrusion 2a (pile 2) can be ensured as compared with the pile 2 to which the protrusion 2a is retrofitted. It will be advantageous. Therefore, in order to use it as a permanent pile, it is preferable to use a pile 2 in which the protruding portion 2a is integrally formed in advance.

セメントミルクCに予め配合する増粘材Bとしては、例えばベントナイト、セルロースエーテル、炭酸カルシウム等の様々なコンクリート増粘材を用いることができる。膨張材Dとしては、例えば、石灰、石膏、ボーキサイトを主成分とする焼成化合物等の様々なコンクリート膨張材を用いることができる。 As the thickener B to be blended in advance with the cement milk C, various concrete thickeners such as bentonite, cellulose ether, and calcium carbonate can be used. As the expansion material D, for example, various concrete expansion materials such as lime, gypsum, and a calcined compound containing bauxite as a main component can be used.

増粘材Bを配合することにより、セメントミルクC成分中のセメントと水とが分離し難くなる。セメントと水との分離が生じると、岩盤Rに対する杭2の固定力が低下するので、増粘材Bを配合することにより、杭2の固定力を長期に渡って安定して維持するには有利になる。ただし、増粘材Bの配合割合が過大になると、すき間gに充填する際のセメントミルクCの流動性が悪化して、すき間gに密に充填させることが困難になる。一方、増粘材Bの配合割合が過小であると、期待する分離抵抗性(セメントと水との分離を抑制する作用効果)を発揮することができない。そのため、増粘材Bの配合量はセメントミルクCに含有されるセメントに対して3重量%以上12重量%以下にすることが好ましく、5重量%以上8重量%以下がより好ましい。 By blending the thickener B, it becomes difficult to separate the cement and water in the cement milk C component. When the cement and water are separated, the fixing force of the pile 2 to the bedrock R decreases. Therefore, by blending the thickener B, the fixing force of the pile 2 can be stably maintained for a long period of time. It will be advantageous. However, if the blending ratio of the thickener B becomes excessive, the fluidity of the cement milk C when filling the gap g deteriorates, and it becomes difficult to fill the gap g densely. On the other hand, if the blending ratio of the thickener B is too small, the expected separation resistance (action and effect of suppressing the separation between cement and water) cannot be exhibited. Therefore, the blending amount of the thickener B is preferably 3% by weight or more and 12% by weight or less with respect to the cement contained in the cement milk C, and more preferably 5% by weight or more and 8% by weight or less.

セメントミルクCに膨張材Dを配合することで、セメントミルクCが膨張して周辺に対する圧力が上昇する結果、杭2とセメントミルクCとの付着性が向上する。相応の効果を期待できる膨張材Dの配合量は、セメントミルクCに含有されるセメントに対して10重量%程度(例えば5重量%以上15重量%以下)である。 By blending the expansion material D with the cement milk C, the cement milk C expands and the pressure on the periphery increases, and as a result, the adhesiveness between the pile 2 and the cement milk C is improved. The blending amount of the expanding material D that can be expected to have a corresponding effect is about 10% by weight (for example, 5% by weight or more and 15% by weight or less) with respect to the cement contained in the cement milk C.

打設した杭2と土砂層Sとの間では、十分な摩擦力が確保できるので、両者のすき間にセメントミルクCを敢えて充填する必要はない。即ち、セメントミルクCの使用量を抑えつつ、杭2の固定強度を十分に確保するには、実質的に杭2と岩盤Rとのすき間gのみにセメントミルクCを充填して固化させればよい。 Since a sufficient frictional force can be secured between the placed pile 2 and the earth and sand layer S, it is not necessary to dare to fill the gap between the two with cement milk C. That is, in order to sufficiently secure the fixing strength of the pile 2 while suppressing the amount of cement milk C used, the cement milk C should be substantially filled and solidified only in the gap g between the pile 2 and the bedrock R. good.

それ故、セメントミルクCをすき間gに充填する際には、岩盤Rの深さ位置(範囲)を予め把握しておくとよい。そして、セメントミルクCの供給量、供給位置を適切に調整してセメントミルクCをすき間gに供給することにより、岩盤Rが存在している深さ位置(範囲)のみにセメントミルクCを充填するとよい。 Therefore, when filling the gap g with the cement milk C, it is preferable to know the depth position (range) of the bedrock R in advance. Then, by appropriately adjusting the supply amount and supply position of the cement milk C and supplying the cement milk C to the gap g, the cement milk C is filled only in the depth position (range) where the bedrock R exists. good.

セメントミルクCは、すき間gの上方側から充填することも、すき間gの下方側から充填することもできる。すき間gの下方側からセメントミルクCを充填すると、すき間gに存在している地下水をすき間gから排除してセメントミルクCを密に充填し易くなる。したがって、例えば、充填用パイプ6をすき間gの下端近傍まで延ばした状態にして収容タンク5からセメントミルクCを供給する。 The cement milk C can be filled from the upper side of the gap g or from the lower side of the gap g. When the cement milk C is filled from the lower side of the gap g, the groundwater existing in the gap g is removed from the gap g and the cement milk C can be easily filled tightly. Therefore, for example, the cement milk C is supplied from the storage tank 5 in a state where the filling pipe 6 is extended to the vicinity of the lower end of the gap g.

杭2が鋼管杭の場合は、管内周側と管外周側にそれぞれ充填用パイプ6を杭2の長手方向に延在させて、岩盤Rの杭2の外周面とのすき間g、岩盤Rと杭2の内周面とのすき間gにそれぞれ、セメントミルクCを充填するとよい。これにより、すき間gの全体範囲に十分、かつ、迅速にセメントミルクCを密に充填し易くなる。鋼管杭ではない他のタイプの杭2の場合も、複数本の充填用パイプ6を用いて、複数系統でセメントミルクCを充填することがより好ましいが、1本の充填用パイプ6を用いてセメントミルクCを充填することもできる。 When the pile 2 is a steel pipe pile, filling pipes 6 are extended in the longitudinal direction of the pile 2 on the inner peripheral side of the pipe and the outer peripheral side of the pipe, respectively. It is advisable to fill the gap g with the inner peripheral surface of the pile 2 with cement milk C, respectively. This makes it easy to fill the entire range of the gap g sufficiently and quickly with the cement milk C. In the case of other types of piles 2 that are not steel pipe piles, it is more preferable to fill the cement milk C in a plurality of systems using a plurality of filling pipes 6, but it is more preferable to use one filling pipe 6. Cement milk C can also be filled.

この実施形態では、突出部2aは杭2と一体的に形成されているが、図8に例示するように、厚さt1のリングを杭2の先端部に溶接等で接合して突出部2aを設けることもできる。また、図9に例示するように、突出部2は、杭2の外周側だけでなく内周側にも突出した形状にすることもできる。 In this embodiment, the protrusion 2a is integrally formed with the pile 2, but as illustrated in FIG. 8, a ring having a thickness t1 is joined to the tip of the pile 2 by welding or the like to join the protrusion 2a. Can also be provided. Further, as illustrated in FIG. 9, the protruding portion 2 may have a shape protruding not only on the outer peripheral side of the pile 2 but also on the inner peripheral side.

この実施形態では、凸部2bとなる環状凸部が杭2の長手方向に対して直交した向きに配置されているが、図10に例示するように、環状凸部を杭2の長手方向に対して傾斜させた向きに配置することもできる。 In this embodiment, the annular convex portion to be the convex portion 2b is arranged in a direction orthogonal to the longitudinal direction of the pile 2, but as illustrated in FIG. 10, the annular convex portion is arranged in the longitudinal direction of the pile 2. On the other hand, it can be arranged in an inclined direction.

図11、図12に例示する凸部2bは、杭2の長手方向に延在する異形鉄筋により形成されている。凸部2bとなる複数本の異形鉄筋は、杭2の周方向に等間隔で配置することが好ましい。尚、この等間隔とは完全な等間隔だけを意味するのではなく、若干のずれ(例えば杭2の軸心を中心にした周方向に±3°程度)を許容することを含んでいて、概ね等間隔を意味する。配置する異形鉄筋の数は、杭2の外径の大きさにも依存するが4本以上にして、岩盤RとセメントミルクCとの付着強度に応じて、杭2とセメントミルクCとの十分な付着強度が確保できる本数にすることが望ましい。 The convex portion 2b exemplified in FIGS. 11 and 12 is formed by a deformed reinforcing bar extending in the longitudinal direction of the pile 2. It is preferable that the plurality of deformed reinforcing bars forming the convex portions 2b are arranged at equal intervals in the circumferential direction of the pile 2. It should be noted that this equidistant interval does not mean only a perfect equidistant interval, but also includes allowing a slight deviation (for example, about ± 3 ° in the circumferential direction about the axis of the pile 2). It means approximately equal intervals. The number of deformed reinforcing bars to be arranged depends on the size of the outer diameter of the pile 2, but it should be 4 or more, and the pile 2 and the cement milk C should be sufficiently attached according to the adhesion strength between the bedrock R and the cement milk C. It is desirable to use a number that can secure a sufficient adhesion strength.

図11、図12では、異形鉄筋(凸部2b)の突出量t2よりも大きな最大突出量t1の突出部2aが杭2の周方向全長に連続して形成されている。突出部2aはその他に図13に例示するように2段構造にすることができる。図13では、異形鉄筋(凸部2b)の突出量t2よりも小さな突出量t3の周方向に連続する環状の突出部2a1と、この突出部2a1に連続して杭2の外周面に突出量t2よりも大きな突出量t4の環状の突出部2a2とが設けられている。突出部2a1と突出部2a2とにより突出部2aが形成されている。したがって、突出部2aの最大突出量t1(=t4)は凸部2bの突出量t2よりも大きく設定されている。 In FIGS. 11 and 12, a protruding portion 2a having a maximum protruding amount t1 larger than the protruding amount t2 of the deformed reinforcing bar (convex portion 2b) is continuously formed over the entire length in the circumferential direction of the pile 2. The protrusion 2a may also have a two-stage structure as illustrated in FIG. In FIG. 13, an annular protrusion 2a 1 continuous in the circumferential direction with a protrusion amount t3 smaller than the protrusion amount t2 of the deformed reinforcing bar (convex portion 2b) and the protrusion 2a 1 continuously on the outer peripheral surface of the pile 2. An annular protrusion 2a 2 having a protrusion amount t4 larger than the protrusion amount t2 is provided. The protrusion 2a 1 is formed by the protrusion 2a 1 and the protrusion 2a 2. Therefore, the maximum protrusion amount t1 (= t4) of the protrusion 2a is set to be larger than the protrusion amount t2 of the protrusion 2b.

図14、図15に例示するように、突出部2a2は、突出部2a1の外周面に設けて異形鉄筋(凸部2b)の存在する位置にのみに配置した構造にすることもできる。この構造では、環状の突出部2a1の外周面に周方向に間隔をあけて突出部2a2が配置される。尚、図13に例示した突出部2a2も同様に周方向に間隔をあけて配置することができる。 As illustrated in FIGS. 14 and 15, the projecting portion 2a 2 may be provided on the outer peripheral surface of the projecting portion 2a 1 and may be arranged only at the position where the deformed reinforcing bar (convex portion 2b) is present. In this structure, the protrusions 2a 2 are arranged on the outer peripheral surface of the annular protrusion 2a 1 at intervals in the circumferential direction. The protrusions 2a 2 illustrated in FIG. 13 can also be arranged at intervals in the circumferential direction in the same manner.

凸部2bとなる異形鉄筋は例えば、杭2の外周面に隅肉溶接によって取り付ける。図16(A)に例示するように隅肉溶接部Uは、異形鉄筋の長手方向に継ぎ目なく連続させることもできるが、図16(B)に例示するように長手方向に間隔をあけた状態にすることもできる。図16(B)のように隅肉溶接部Uを形成すると、長手方向に隣り合う隅肉溶接部U(肉盛りされた部分)の間の隅肉溶接していない部分に入り込んだセメントミルクCと隅肉溶接部Uとが係合した状態になる。そのため、隅肉溶接部UとセメントミルクCとのずれ止め効果によって一段と高い付着耐力が期待できる。 The deformed reinforcing bar that becomes the convex portion 2b is attached to the outer peripheral surface of the pile 2 by fillet welding, for example. The fillet welded portion U can be seamlessly continuous in the longitudinal direction of the deformed reinforcing bar as illustrated in FIG. 16 (A), but is in a state of being spaced in the longitudinal direction as illustrated in FIG. 16 (B). It can also be. When the fillet welded portion U is formed as shown in FIG. 16B, the cement milk C that has entered the portion not fillet welded between the fillet welded portions U (the built-up portions) adjacent to each other in the longitudinal direction. And the fillet welded portion U are engaged with each other. Therefore, a higher adhesion strength can be expected due to the slip-preventing effect between the fillet welded portion U and the cement milk C.

さらには、隅肉溶接部Uは杭2の外周面と異形鉄筋の外周面との接触部分の近傍に形成されるので、杭2を打設する際に、岩盤Rとは接触し難い位置に存在することになる。そのため、隅肉溶接部Uは、杭2の打設後にも損耗が最小限になり、健全な状態で維持するには有利になっている。 Further, since the fillet welded portion U is formed in the vicinity of the contact portion between the outer peripheral surface of the pile 2 and the outer peripheral surface of the deformed reinforcing bar, it is located at a position where it is difficult to contact the bedrock R when the pile 2 is placed. Will exist. Therefore, the fillet welded portion U has minimal wear even after the pile 2 is driven, which is advantageous for maintaining a sound state.

異形鉄筋は入手し易いメリットの他に、表面が凹凸になっているのでセメントミルクCとの接合面積を増大するには益々有利になる。凸部2bが杭2の長手方向に延在していると、杭2を打設する際に、土砂層Sおよび岩盤Rと杭2との摩擦抵抗が増大することを回避できる。また、セメントミルクCが凸部2bに沿って下方に円滑に流動するので、すき間gに密実に充填し易くなる。 In addition to the merit that the deformed reinforcing bar is easily available, since the surface is uneven, it is more advantageous to increase the bonding area with the cement milk C. When the convex portion 2b extends in the longitudinal direction of the pile 2, it is possible to avoid an increase in frictional resistance between the sediment layer S and the bedrock R and the pile 2 when the pile 2 is driven. Further, since the cement milk C smoothly flows downward along the convex portion 2b, it becomes easy to fill the gap g densely and steadily.

図17に例示するように凸部2bは、杭2の外周面で周方向に螺旋状に延在する螺旋状凸部にすることもできる。凸部2bをこの形状にすると、上方から充填したセメントミルクCを螺旋状凸部に沿って円滑に下方に流動させ易くなる。 As illustrated in FIG. 17, the convex portion 2b may be a spiral convex portion extending spirally in the circumferential direction on the outer peripheral surface of the pile 2. When the convex portion 2b has this shape, the cement milk C filled from above can be smoothly flowed downward along the spiral convex portion.

図18に例示するように、杭2の長手方向に延在する凸部2bと周方向に延在する凸部2bとを組み合わせてもよい。または、これら凸部2bの少なくとも一方と、杭2の長手方向に対して傾斜して延在する凸部2bとを組み合わせてもよい。或いは、杭2の先端部の外周面に巻き付けて網状体を凸部2bにすることもできる。 As illustrated in FIG. 18, a convex portion 2b extending in the longitudinal direction of the pile 2 and a convex portion 2b extending in the circumferential direction may be combined. Alternatively, at least one of these convex portions 2b may be combined with the convex portion 2b extending so as to be inclined with respect to the longitudinal direction of the pile 2. Alternatively, the net-like body can be formed into a convex portion 2b by winding it around the outer peripheral surface of the tip portion of the pile 2.

セメントミルクCの充填手順は、図19に例示する実施形態のようにすることもできる。この実施形態では、杭2を岩盤Rに所定深さ打込んだ後、杭2を上方移動させて、岩盤Rよりも上方位置に維持する。岩盤Rには杭2を所定深さまで打ち込んだことによって筒状のすき間g1が形成されている。 The filling procedure of cement milk C can also be as in the embodiment illustrated in FIG. In this embodiment, after the pile 2 is driven into the bedrock R to a predetermined depth, the pile 2 is moved upward and maintained at a position above the bedrock R. A cylindrical gap g1 is formed in the bedrock R by driving the pile 2 to a predetermined depth.

この状態で、筒状のすき間g1に所定量のセメントミルクCを充填する。次いで、杭2を所定深さに再度打込む。セメントミルクCは杭2に押されて、杭2と岩盤Rとのすき間gに入り込む。その後、所定時間、養生することによりセメントミルクCを固化させて図6、図7に例示した状態にする。 In this state, a predetermined amount of cement milk C is filled in the tubular gap g1. Then, the pile 2 is driven again to a predetermined depth. The cement milk C is pushed by the pile 2 and enters the gap g between the pile 2 and the bedrock R. After that, the cement milk C is solidified by curing for a predetermined time to bring it into the state illustrated in FIGS. 6 and 7.

この実施形態では、岩盤Rに杭2が存在しない状態でセメントミルクCを充填するので迅速に充填を行うことができ、作業時間の短縮が可能になる。また、充填されたセメントミルクCの中に杭2を押し込むので、杭2と岩盤Rとのすき間gにセメントミルクCを密実に充填させるには有利である。 In this embodiment, since the cement milk C is filled in the state where the pile 2 does not exist in the bedrock R, the filling can be performed quickly and the working time can be shortened. Further, since the pile 2 is pushed into the filled cement milk C, it is advantageous for the cement milk C to be densely filled in the gap g between the pile 2 and the bedrock R.

上述したそれぞれの実施形態では、岩盤Rの上に土砂層Sが堆積した地盤に杭2を打設する場合を例にして説明したが、土砂層Sが存在せずに岩盤Rのみの地盤に杭2を打設することもできる。この場合も、岩盤Rに対して杭2を所定深さまで打ち込み、その後、すき間gまたはすき間g1にセメントミルクCを充填して固化させる手順は、上述したそれぞれの実施形態と同様である。 In each of the above-described embodiments, the case where the pile 2 is placed on the ground where the sediment layer S is deposited on the bedrock R has been described as an example, but the ground has only the bedrock R without the sediment layer S. Pile 2 can also be driven. In this case as well, the procedure in which the pile 2 is driven into the bedrock R to a predetermined depth and then the gap g or the gap g1 is filled with cement milk C and solidified is the same as in each of the above-described embodiments.

1 振動杭打設機
2 杭
2a、2a1、2a2 突出部
2b 凸部
3 水タンク
3a 配管
4 注水パイプ
4a 先端ノズル
5 収容タンク
6 充填用パイプ
B 増粘材
C セメントミルク
D 膨張材
S 土砂層
R 岩盤
U 隅肉溶接部
W 水
1 Vibration pile driving machine 2 Pile 2a, 2a 1 , 2a 2 Protruding part 2b Convex part 3 Water tank 3a Piping 4 Water injection pipe 4a Tip nozzle 5 Storage tank 6 Filling pipe B Thickening material C Cement milk D Expansion material S Sediment Layer R Bedrock U Fillet weld W Water

Claims (5)

振動杭打設機によって、杭の先端を岩盤に打ち付けて岩盤を破砕しつつ、破砕した岩石を、前記杭に隣接配置されている注水パイプの先端ノズルから噴射する水で前記杭の先端領域から排除しながら前記岩盤に前記杭を打ち込む岩盤への杭打設工法において、前記杭の先端部の外周面が他の部位よりも外周側に突出した厚肉の突出部を有するとともに、前記突出部以外の前記杭の少なくとも先端側の外周面の表面にその外周面からの突出量が前記突出部の最大突出量以下の凸部が設けられていて、前記杭が管状であり、前記突出部が、前記杭の最先端部で前記杭の周方向全長に連続する一方の環状突出部と、前記一方の環
状突出部の後端に連接されていて前記杭の周方向全長に連続する他方の環状突出部とで構成され、前記一方の環状突出部の外周面よりも前記他方の環状突出部の外周面が前記杭の外周側に突出している2段構造であり、前記凸部が、前記他方の環状突出部の後端から前記杭の長手方向に延在していて、前記杭を前記岩盤に所定深さ打込んだ後、前記杭と前記岩盤とのすき間にセメントミルクを充填し、このセメントミルクが固化することにより、固化したセメントミルクを介して前記杭を前記岩盤に固定させることを特徴とする岩盤への杭打設工法。
While the tip of the pile is struck against the bedrock by a vibrating pile driving machine to crush the bedrock, the crushed rock is ejected from the tip nozzle of the water injection pipe arranged adjacent to the pile from the tip area of the pile. In the pile driving method for driving the pile into the bedrock while eliminating the pile, the outer peripheral surface of the tip of the pile has a thick protruding portion protruding toward the outer peripheral side from other parts, and the protruding portion. A convex portion having a protrusion amount from the outer peripheral surface equal to or less than the maximum protrusion amount of the protrusion is provided on the surface of the outer peripheral surface at least on the tip end side of the pile other than the above, and the pile is tubular and the protrusion is formed. , One annular protrusion that is continuous with the circumferential length of the pile at the tip of the pile and the other annular that is connected to the rear end of the one annular protrusion and is continuous with the circumferential length of the pile. It has a two-stage structure in which the outer peripheral surface of the other annular protrusion protrudes toward the outer peripheral side of the pile from the outer peripheral surface of the one annular protrusion, and the convex portion is the other. The pile extends in the longitudinal direction of the pile from the rear end of the annular protrusion of the pile, and after the pile is driven into the bedrock to a predetermined depth, cement milk is filled in the gap between the pile and the bedrock. A method for placing piles in a bedrock, characterized in that the piles are fixed to the bedrock through the solidified cement milk by solidifying the cement milk.
振動杭打設機によって、杭の先端を岩盤に打ち付けて岩盤を破砕しつつ、破砕した岩石を、前記杭に隣接配置されている注水パイプの先端ノズルから噴射する水で前記杭の先端領域から排除しながら前記岩盤に前記杭を打ち込む岩盤への杭打設工法において、前記杭の先端部の外周面が他の部位よりも外周側に突出した厚肉の突出部を有するとともに、前記突出部以外の前記杭の少なくとも先端側の外周面の表面にその外周面からの突出量が前記突出部の最大突出量以下の凸部が設けられていて、前記杭が管状であり、前記突出部が、前記杭の最先端部で前記杭の周方向全長に連続する環状突出部と、前記環状突出部の外
周面に前記杭の周方向に間隔をあけて配置された複数の離間する突出部とで構成されていて、前記凸部が、それぞれの前記複数の離間する突出部の後端から前記杭の長手方向に延在して、それぞれの前記複数の離間する突出部は、前記凸部が存在する周方向位置にのみ配置されていて、前記杭を前記岩盤に所定深さ打込んだ後、前記杭と前記岩盤とのすき間にセメントミルクを充填し、このセメントミルクが固化することにより、固化したセメントミルクを介して前記杭を前記岩盤に固定させることを特徴とする岩盤への杭打設工法。
While the tip of the pile is struck against the bedrock by a vibrating pile driving machine to crush the bedrock, the crushed rock is ejected from the tip nozzle of the water injection pipe arranged adjacent to the pile from the tip area of the pile. In the pile driving method for driving the pile into the bedrock while eliminating the pile, the outer peripheral surface of the tip of the pile has a thick protruding portion protruding toward the outer peripheral side from other parts, and the protruding portion. A convex portion having a protrusion amount from the outer peripheral surface equal to or less than the maximum protrusion amount of the protrusion is provided on the surface of the outer peripheral surface at least on the tip end side of the pile other than the above, and the pile is tubular and the protrusion is formed. An annular protrusion that is continuous with the entire circumferential length of the pile at the tip of the pile, and a plurality of separated protrusions that are arranged at intervals in the circumferential direction of the pile on the outer peripheral surface of the annular protrusion. The convex portion extends from the rear end of each of the plurality of separated protrusions in the longitudinal direction of the pile, and each of the plurality of separated protrusions has the convex portion. It is arranged only in the existing circumferential position, and after driving the pile into the bedrock to a predetermined depth, cement milk is filled in the gap between the pile and the bedrock, and the cement milk solidifies. A method for placing piles on a bedrock, which comprises fixing the piles to the bedrock via solidified cement milk.
前記杭を前記岩盤に所定深さ打込んだ後、前記杭を前記岩盤よりも上方位置に移動させた状態にして、前記杭を打込むことで前記岩盤に形成されていて、セメントミルクがまだ供給されていない打込み痕に所定量の前記セメントミルクを充填し、次いで前記杭を前記振動杭打設機によって前記所定深さに再度打込む請求項1または2に記載の岩盤への杭打設工法。 After the pile is driven into the bedrock to a predetermined depth, the pile is moved to a position higher than the bedrock, and the pile is driven into the bedrock to form cement milk. The pile driving into the bedrock according to claim 1 or 2 , wherein the unsupplied driving marks are filled with the cement milk in a predetermined amount, and then the piles are again driven to the predetermined depth by the vibration pile driving machine. Construction method. 前記突出部の前記最大突出量が6mm以上35mm以下であり、前記凸部の前記突出量が1mm以上である請求項1〜3のいずれかに記載の岩盤への杭打設工法。 The pile driving method according to any one of claims 1 to 3 , wherein the maximum protrusion amount of the protrusion is 6 mm or more and 35 mm or less, and the protrusion amount of the protrusion is 1 mm or more. 前記凸部が異形鉄筋である請求項1〜4のいずれかに記載の岩盤への杭打設工法。 The pile driving method for rock according to any one of claims 1 to 4 , wherein the convex portion is a deformed reinforcing bar.
JP2017074143A 2017-04-04 2017-04-04 Pile driving method on bedrock Active JP6981606B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017074143A JP6981606B2 (en) 2017-04-04 2017-04-04 Pile driving method on bedrock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017074143A JP6981606B2 (en) 2017-04-04 2017-04-04 Pile driving method on bedrock

Publications (2)

Publication Number Publication Date
JP2018178382A JP2018178382A (en) 2018-11-15
JP6981606B2 true JP6981606B2 (en) 2021-12-15

Family

ID=64281351

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017074143A Active JP6981606B2 (en) 2017-04-04 2017-04-04 Pile driving method on bedrock

Country Status (1)

Country Link
JP (1) JP6981606B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112081101B (en) * 2020-09-14 2021-10-19 重庆大学 Steel pipe temporary support restraint system
JP7609372B2 (en) * 2021-03-30 2025-01-07 株式会社大林組 Load test method and analysis system

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3706204A (en) * 1971-02-10 1972-12-19 Erwin L Long Method and apparatus for improving bearing strength of piles in permafrost
JPS5724724A (en) * 1980-07-18 1982-02-09 Toa Harbor Works Co Ltd Method for driving structure material into rock bed
JPH02243819A (en) * 1989-03-16 1990-09-27 Kawasaki Steel Corp Rotary press-in steel pipe pile
JPH09291529A (en) * 1996-04-26 1997-11-11 Yoshio Tanaka Rotary press-in pile
JPH10266196A (en) * 1997-03-28 1998-10-06 Tenox Corp Installation method for pipe and steel pipe pile, and steel pipe pile
JP3735225B2 (en) * 1999-12-15 2006-01-18 新日本製鐵株式会社 Method of driving steel pipe piles into bedrock
JP4476230B2 (en) * 2006-03-07 2010-06-09 東日本旅客鉄道株式会社 Steel pipe pile rooting method
JP2007262811A (en) * 2006-03-29 2007-10-11 Nippon Hume Corp Pile structure and its pile embedding method
JP5407266B2 (en) * 2007-10-17 2014-02-05 Jfeスチール株式会社 Friction pile
JP5577528B2 (en) * 2011-02-28 2014-08-27 Jfeスチール株式会社 Synthetic friction pile
KR101245609B1 (en) * 2011-04-22 2013-03-20 한국건설기술연구원 Constructing Method of Steel Pile in Sea Ground
WO2014203858A1 (en) * 2013-06-19 2014-12-24 新日鐵住金株式会社 Steel-pipe pile and steel-pipe pile construction method
JP6479584B2 (en) * 2015-06-09 2019-03-06 東亜建設工業株式会社 Pile driving device and method for bedrock
JP5932124B1 (en) * 2015-11-18 2016-06-08 株式会社オーク Steel pipe pile construction method

Also Published As

Publication number Publication date
JP2018178382A (en) 2018-11-15

Similar Documents

Publication Publication Date Title
AU2014282262B2 (en) Steel-pipe pile and steel-pipe pile construction method
JP5867301B2 (en) Pipe pile and its construction method
JP2016089404A (en) Grouting method for cast-in-place concrete piles
JP2016030925A (en) Pile placement method and pile
JP6395524B2 (en) Steel pipe for ground reinforcement and method for manufacturing the same
JP6981606B2 (en) Pile driving method on bedrock
JP6343445B2 (en) Construction method of earth retaining wall
JP2004270157A (en) Steel pile and its construction method
JP5783894B2 (en) Tip-expanded pile
JP2013104215A (en) Liquefaction prevention method
JP2001172970A (en) Driving method of steel pipe pile into rock
EP1992742A2 (en) Laying a foundation by vibrating and fluidizing
JP6630560B2 (en) Piling method for bedrock
JP5890677B2 (en) Steel pile construction method
JP2016037787A (en) Shear reinforcement method
JP5026829B2 (en) Seismic reinforcement facilities and methods for seismic reinforcement of masonry walls
JP6344244B2 (en) Steel pipe pile and its construction method
JP4530378B2 (en) Seismic reinforcement method for masonry wall and masonry wall reinforcement used therefor
JP6054334B2 (en) Retaining method of retaining wall
JP6068285B2 (en) Post-installation anchor fixing method
JP2014134008A (en) Creating method for solidified body and burying method for steel pipe pile using the same
JP6319942B2 (en) Steel pipe sheet pile press-in method and pipes
JP2012255318A (en) Expansion-type lock bolt having protrusion
JPH1171758A (en) Driving method of pile into rock
JP2017179904A (en) Support structure of structure and reinforcement method of pile foundation structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20191220

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20201014

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20201201

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210125

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210615

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210726

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211019

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211108

R150 Certificate of patent or registration of utility model

Ref document number: 6981606

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150