JP6983533B2 - Construction method of steel-concrete composite structure and steel-concrete composite structure - Google Patents
[go: Go Back, main page]

JP6983533B2 - Construction method of steel-concrete composite structure and steel-concrete composite structure - Google Patents

Construction method of steel-concrete composite structure and steel-concrete composite structure Download PDF

Info

Publication number
JP6983533B2
JP6983533B2 JP2017091390A JP2017091390A JP6983533B2 JP 6983533 B2 JP6983533 B2 JP 6983533B2 JP 2017091390 A JP2017091390 A JP 2017091390A JP 2017091390 A JP2017091390 A JP 2017091390A JP 6983533 B2 JP6983533 B2 JP 6983533B2
Authority
JP
Japan
Prior art keywords
concrete
plate
steel material
steel
joined
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017091390A
Other languages
Japanese (ja)
Other versions
JP2018188851A (en
Inventor
雅徳 土屋
尚幸 荒木
寛 齋藤
友李 吉村
智明 大木
謙二 吉武
博一 田中
大輔 林
郁夫 中谷
直人 小山
大輔 竹内
修史 関口
卓弥 松尾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2017091390A priority Critical patent/JP6983533B2/en
Publication of JP2018188851A publication Critical patent/JP2018188851A/en
Application granted granted Critical
Publication of JP6983533B2 publication Critical patent/JP6983533B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Description

本発明は、鋼コンクリート複合構造および鋼コンクリート複合構造の施工方法に関する。 The present invention relates to a steel-concrete composite structure and a method for constructing a steel-concrete composite structure.

鉄筋コンクリート構造などの鉄筋を有する鋼コンクリート複合構造では、せん断破壊を防止するために、主鉄筋を取り囲むようにせん断補強筋が配置されている。
また、せん断補強筋に代わって鋼板を設置し、鋼板に主鉄筋や配力筋を接続した鋼コンクリート複合構造が知られている(例えば、特許文献1参照)。
In a steel-concrete composite structure having reinforcing bars such as a reinforced concrete structure, shear reinforcing bars are arranged so as to surround the main reinforcing bars in order to prevent shear failure.
Further, a steel-concrete composite structure in which a steel plate is installed instead of a shear reinforcing bar and a main reinforcing bar and a force distribution bar are connected to the steel plate is known (see, for example, Patent Document 1).

特開平8−232337号公報Japanese Unexamined Patent Publication No. 8-232337

せん断補強筋は、主鉄筋が配置された後に配筋されるため、主鉄筋の配筋工程とは別にせん断補強筋の配筋工程が必要となり、労力や工期がかかるという問題がある。特に、鋼コンクリート複合構造において、要求される耐荷重が大きい場合では、より多くのせん断補強筋を配置する必要があるため、せん断補強筋の配筋工程により労力や工期がかかるという問題がある。
また、せん断補強筋に代わって鋼板を設置する場合でも、鋼板に主鉄筋や配力筋を接合する工程に労力や工期がかかるという問題がある。
このため、せん断耐力を確保しつつ容易に施工できる鋼コンクリート複合構造が望まれている。
Since the shear reinforcing bars are arranged after the main reinforcing bars are arranged, there is a problem that a shear reinforcing bar arrangement process is required separately from the main reinforcement reinforcement process, which requires labor and construction period. In particular, in a steel-concrete composite structure, when the required load capacity is large, it is necessary to arrange more shear reinforcing bars, so that there is a problem that labor and construction period are required due to the reinforcement process of the shear reinforcing bars.
Further, even when the steel plate is installed instead of the shear reinforcing bar, there is a problem that the process of joining the main reinforcing bar and the distribution bar to the steel plate requires labor and construction period.
Therefore, a steel-concrete composite structure that can be easily constructed while ensuring the shear strength is desired.

そこで、本発明は、上述する問題点に鑑みてなされたもので、せん断耐力を確保しつつ容易に施工できる鋼コンクリート複合構造および鋼コンクリート複合構造の施工方法を提供することを目的とする。 Therefore, the present invention has been made in view of the above-mentioned problems, and an object of the present invention is to provide a steel-concrete composite structure and a method for constructing a steel-concrete composite structure that can be easily constructed while ensuring a shear strength.

上記目的を達成するため、本発明に係る鋼コンクリート複合構造は、プレキャストコンクリート部と、前記プレキャストコンクリート部と接合される現場打ちコンクリート部と、を有する鋼コンクリート複合構造において、前記プレキャストコンクリート部は、複数の主鉄筋と、前記複数の主鉄筋と交差する複数の配力筋と、前記複数の配力筋がそれぞれ挿通される複数の第1孔部が形成された孔あき鋼材と、前記主鉄筋、前記配力筋および前記孔あき鋼材を一体に埋設するコンクリート部と、を有し、前記孔あき鋼材は、前記複数の第1孔部が形成されて前記コンクリート部に埋設される第1板部と、前記第1板部と一体に形成され前記コンクリート部の外部に突出し前記現場打ちコンクリート部に埋設される第2板部と、を有し、一対の前記プレキャストコンクリート部が互いの前記第2板部が突出している側を対向させるように配置され、一対の前記プレキャストコンクリート部それぞれの前記第2板部が接合鋼板を介して接合されていて、前記接合鋼板は、対向する前記第2板部それぞれの前記コンクリート部から突出する側の端部全体と接合され、一対の前記プレキャストコンクリート部それぞれのコンクリート部の間に前記現場打ちコンクリート部が打設され、前記接合鋼板は、前記現場打ちコンクリート部に埋設されていることを特徴とする。 In order to achieve the above object, the steel-concrete composite structure according to the present invention is a steel-concrete composite structure having a precast concrete portion and a cast-in-place concrete portion joined to the precast concrete portion. A plurality of main reinforcing bars, a plurality of force distribution bars intersecting the plurality of main reinforcing bars, a perforated steel material in which a plurality of first holes through which the plurality of force distribution bars are inserted are formed, and the main reinforcing bar. The perforated steel material has a concrete portion in which the force distribution bar and the perforated steel material are integrally embedded, and the perforated steel material is a first plate in which the plurality of first hole portions are formed and embedded in the concrete portion. parts and, have a, a second plate portion which is embedded in the outside projecting the poured concrete part of the formed integrally with the first plate portion the concrete section, the pair of the precast concrete part to each other the The two plate portions are arranged so as to face each other on the protruding side, the second plate portion of each of the pair of precast concrete portions is joined via a joined steel plate, and the joined steel plate is opposed to the second plate portion. The cast-in-place concrete portion is placed between the concrete portions of each of the pair of precast concrete portions, and the joined steel plate is cast in the cast-in-place manner. It is characterized by being buried in a concrete part.

また、本発明に係る鋼コンクリート複合構造の施工方法は、間をあけて対向して配置される一対のプレキャストコンクリート部と、前記一対のプレキャストコンクリートの間に設けられ前記一対のプレキャストコンクリート部と接合される現場打ちコンクリート部と、を有する鋼コンクリート複合構造の構造体を構築するための鋼コンクリート複合構造の施工方法において、前記一対のプレキャストコンクリート部を製作するプレキャストコンクリート部製作工程と、前記プレキャストコンクリート部製作工程で製作された前記一対のプレキャストコンクリート部を前記構造体を構築する位置に設置するプレキャストコンクリート部設置工程と、前記現場打ちコンクリート部を構築する現場打ちコンクリート部構築工程と、を有し、前記プレキャストコンクリート部製作工程は、複数の主鉄筋を設置する主鉄筋設置工程と、第1孔部が複数形成された孔あき鋼材を設置する孔あき鋼材設置工程と、複数の配力筋をそれぞれ前記第1孔部に挿通して前記複数の主鉄筋と交差するように設置する配力筋設置工程と、前記プレキャストコンクリート部のコンクリート部を打設し、前記主鉄筋、前記配力筋および前記孔あき鋼材を一体に埋設するコンクリート部打設工程と、を有し、前記コンクリート部打設工程では、前記孔あき鋼材のうちの前記第1孔部が形成された側の第1板部を前記コンクリート部に埋設し、前記孔あき鋼材のうちの前記第1孔部が形成されていない側の第2板部を前記コンクリート部から突出させ、前記プレキャストコンクリート部設置工程では、前記一対のプレキャストコンクリート部をそれぞれの前記第2板部が突出する側が互いに間をあけて対向し前記現場打ちコンクリート部が構築される側に向くように配置し、対向する前記第2板部それぞれの前記コンクリート部から突出する側の端部全体に接合鋼板を接合し、前記接合鋼板を介して対向する前記第2板部どうしを接合し、前記現場打ちコンクリート部構築工程では、前記第2板部および前記接合鋼板を前記現場打ちコンクリート部に埋設することを特徴とする。 Further, in the construction method of the steel-concrete composite structure according to the present invention, a pair of precast concrete portions arranged facing each other with a gap and a pair of precast concrete portions provided between the pair of precast concretes and joined to the pair of precast concrete portions. In the construction method of the steel-concrete composite structure for constructing the structure of the steel-concrete composite structure having the cast-in-place concrete portion, the precast concrete portion manufacturing process for manufacturing the pair of precast concrete portions and the precast concrete portion. It has a precast concrete part installation step of installing the pair of precast concrete parts manufactured in the part manufacturing process at a position where the structure is to be constructed, and a cast-in-place concrete part construction step of constructing the cast-in-place concrete part. In the precast concrete part manufacturing process, a main reinforcing bar installation process for installing a plurality of main reinforcing bars, a perforated steel material installing process for installing a perforated steel material having a plurality of first hole portions, and a plurality of force distribution bars are performed. A force distribution bar installation step of inserting the first hole portion and installing the force distribution bar so as to intersect the plurality of main reinforcing bars, and placing the concrete portion of the precast concrete portion, the main reinforcement bar, the force distribution bar, and the like. It has a concrete portion placing step of integrally burying the perforated steel material, and in the concrete portion placing step, the first plate portion of the perforated steel material on the side where the first hole portion is formed. Is embedded in the concrete portion, and the second plate portion of the perforated steel material on the side where the first hole portion is not formed is projected from the concrete portion . The precast concrete portion is arranged so that the side on which the second plate portion protrudes faces each other with a gap between them and faces the side on which the cast-in-place concrete portion is constructed, and the concrete of each of the second plate portions facing each other. the bonding steel plate joined to the entire end portion of the side projecting from parts, via the bonding steel to bond the second plate portion each other facing, in the poured concrete part building process, the second plate portion and the It is characterized in that the joined steel plate is embedded in the cast-in-place concrete portion.

本発明では、配力筋を孔あき鋼材の第1孔部に挿通させて主鉄筋と結束することにより、主鉄筋と配力筋とを容易に格子状に配置することができるとともに、主鉄筋および配力筋と孔あき鋼材とを容易に接合することができる。これにより、鋼コンクリート複合構造を容易に施工することができる。その結果、鋼コンクリート複合構造の施工にかかる労力の軽減や工期の短縮を図ることができる。
また、主鉄筋に作用するせん断力が、配力筋を介して孔あき鋼材に伝達されるため、孔あき鋼材がせん断力を負担することができ、せん断耐力を確保することができる。
また、孔あき鋼材の第2板部がコンクリート部の外部に突出して現場打ちコンクリート部に埋設されるため、第2板部がジベルとなってプレキャストコンクリート部と現場打ちコンクリート部とを強固に接合することができ、せん断耐力を確保することができる。
In the present invention, the main reinforcing bars and the force distribution bars can be easily arranged in a grid pattern by inserting the force distribution bars into the first hole portion of the perforated steel material and binding them to the main reinforcing bars. And the force distribution bar and the perforated steel material can be easily joined. This makes it possible to easily construct a steel-concrete composite structure. As a result, it is possible to reduce the labor required for the construction of the steel-concrete composite structure and shorten the construction period.
Further, since the shearing force acting on the main reinforcing bar is transmitted to the perforated steel material via the force distribution bar, the perforated steel material can bear the shearing force and can secure the shearing resistance.
In addition, since the second plate part of the perforated steel material protrudes to the outside of the concrete part and is buried in the cast-in-place concrete part, the second plate part becomes a gibber and firmly joins the precast concrete part and the cast-in-place concrete part. It is possible to secure the shear strength.

また、本発明に係る鋼コンクリート複合構造では、一対の前記プレキャストコンクリート部が互いの前記第2板部が突出している側を対向させるように配置され、一対の前記プレキャストコンクリート部それぞれの前記第2板部が接合鋼板を介して接合されていて、一対の前記プレキャストコンクリート部それぞれのコンクリート部の間に前記現場打ちコンクリート部が打設され、前記接合鋼板は、前記現場打ちコンクリート部に埋設されている。
このような構成とすることにより、一対のプレキャストコンクリート部を接合することができ、せん断耐力を向上させることができる。
Further, in the steel-concrete composite structure according to the present invention, the pair of precast concrete portions are arranged so as to face each other so that the side on which the second plate portion protrudes is opposed to each other, and the second of the pair of precast concrete portions is provided. The plate portion is joined via a joined steel plate, the cast-in-place concrete portion is placed between the concrete portions of each of the pair of precast concrete portions, and the joined steel plate is embedded in the cast-in-place concrete portion. To.
With such a configuration, a pair of precast concrete portions can be joined, and the shear strength can be improved.

また、本発明に係る鋼コンクリート複合構造では、前記第2板部には、前記現場打ちコンクリート部の鉄筋が挿通される第2孔部が形成されていてもよい。
このような構成とすることにより、第2孔部に鉄筋を挿通させることで、現場打ちコンクリート部の配筋を容易に行うことができる。
Further, in the steel-concrete composite structure according to the present invention, a second hole portion through which the reinforcing bar of the cast-in-place concrete portion is inserted may be formed in the second plate portion.
With such a configuration, the reinforcing bars can be easily arranged in the cast-in-place concrete portion by inserting the reinforcing bars into the second hole portion.

また、本発明に係る鋼コンクリート複合構造では、前記孔あき鋼材は、前記第1板部の端部に直交するように接合されたフランジを有し、互いに接合された前記第1板部および前記フランジ全体の断面がT字形状であってもよい。
孔あき鋼材にフランジが設けられている場合では、孔あき鋼材にフランジが設けられていない場合と比べて第1孔部から孔あき鋼材の端部までの距離が長くなるため、万が一、第1孔部の周縁部から亀裂が生じたとしても亀裂が孔あき鋼材の端部にまで達しにくく、亀裂によって孔あき鋼材が破断することを防止できる。
Further, in the steel-concrete composite structure according to the present invention, the perforated steel material has a flange joined so as to be orthogonal to the end portion of the first plate portion, and the first plate portion and the said one joined to each other. The entire cross section of the flange may be T-shaped.
When the perforated steel material is provided with a flange, the distance from the first hole to the end of the perforated steel material is longer than when the perforated steel material is not provided with a flange. Even if a crack is generated from the peripheral edge of the hole, the crack does not easily reach the end of the perforated steel material, and the crack can prevent the perforated steel material from breaking.

また、本発明に係る鋼コンクリート複合構造では、前記孔あき鋼材は、前記第1板部の端部に直交するように接合されたフランジを有し、互いに接合された前記第1板部および前記フランジ全体の断面がL字形状であってもよい。
孔あき鋼材にフランジが設けられている場合では、孔あき鋼材にフランジが設けられていない場合と比べて第1孔部から孔あき鋼材の端部までの距離が長くなるため、万が一、第1孔部の周縁部から亀裂が生じたとしても亀裂が孔あき鋼材の端部にまで達しにくく、亀裂によって孔あき鋼材が破断することを防止できる。
Further, in the steel-concrete composite structure according to the present invention, the perforated steel material has a flange joined so as to be orthogonal to the end portion of the first plate portion, and the first plate portion and the said one joined to each other. The entire cross section of the flange may be L-shaped.
When the perforated steel material is provided with a flange, the distance from the first hole to the end of the perforated steel material is longer than when the perforated steel material is not provided with a flange. Even if a crack is generated from the peripheral edge of the hole, the crack does not easily reach the end of the perforated steel material, and the crack can prevent the perforated steel material from breaking.

また、本発明に係る鋼コンクリート複合構造では、前記孔あき鋼材は、前記第1孔部の縁周の少なくとも一部を囲むように前記孔あき鋼材の第1孔部近傍を補強することができるため、第1孔部が変形したり、第1孔部の周縁部から亀裂が生じたりすることを確実に防止することができる。 Further, in the steel-concrete composite structure according to the present invention, the perforated steel material can reinforce the vicinity of the first hole portion of the perforated steel material so as to surround at least a part of the peripheral edge of the first hole portion. Therefore, it is possible to surely prevent the first hole portion from being deformed or the peripheral portion of the first hole portion from being cracked.

本発明によれば、せん断耐力を確保しつつ容易に施工できる。 According to the present invention, construction can be easily performed while ensuring shear strength.

本発明の第1実施形態による鋼コンクリート複合構造の一例を示す斜視図である。It is a perspective view which shows an example of the steel-concrete composite structure by 1st Embodiment of this invention. 本発明の第1実施形態による鋼コンクリート複合構造の一例を示す平面図である。It is a top view which shows an example of the steel-concrete composite structure by 1st Embodiment of this invention. 本発明の第1実施形態による鋼コンクリート複合構造の一例を示す幅方向から見た図で、下部側を省略した図である。It is a figure seen from the width direction which shows an example of the steel-concrete composite structure by 1st Embodiment of this invention, and is the figure which omitted the lower side. 本発明の第1実施形態による鋼コンクリート複合構造の一例を示す厚さ方向から見た図で、下部側を省略した図である。It is a figure seen from the thickness direction which shows an example of the steel-concrete composite structure by 1st Embodiment of this invention, and is the figure which omitted the lower side. 図2のA−A線断面図である。FIG. 2 is a cross-sectional view taken along the line AA of FIG. 本発明の第2実施形態による鋼コンクリート複合構造の一例を示す斜視図である。It is a perspective view which shows an example of the steel-concrete composite structure by 2nd Embodiment of this invention. 本発明の第3実施形態による鋼コンクリート複合構造の一例を示す斜視図である。It is a perspective view which shows an example of the steel-concrete composite structure by the 3rd Embodiment of this invention. 本発明の第4実施形態による鋼コンクリート複合構造の一例を示す斜視図である。It is a perspective view which shows an example of the steel-concrete composite structure by 4th Embodiment of this invention. 本発明の第5実施形態による鋼コンクリート複合構造の一例を示す斜視図である。It is a perspective view which shows an example of the steel-concrete composite structure by 5th Embodiment of this invention. 本発明の第6実施形態による鋼コンクリート複合構造の一例を示す斜視図である。It is a perspective view which shows an example of the steel-concrete composite structure by the 6th Embodiment of this invention. 本発明の第6実施形態による鋼コンクリート複合構造の一例を示す幅方向から見た図である。It is a figure seen from the width direction which shows an example of the steel-concrete composite structure by the 6th Embodiment of this invention.

(第1実施形態)
以下、本発明の第1実施形態による鋼コンクリート複合構造および鋼コンクリート複合構造の施工方法について、図1乃至図5に基づいて説明する。
第1実施形態による鋼コンクリート複合構造は、構造物の躯体となる図1に示す壁部1Aに採用されている。壁部1Aは、複数配列されて構造物の壁を構築するように構成されている。
壁部1Aは、厚さ方向の両側にそれぞれ配置される一対のプレキャストコンクリート部2,2と、一対のプレキャストコンクリート部2,2の間に配置される現場打ちコンクリート部3と、一対のプレキャストコンクリート部2,2を接合する接合鋼板4と、を有している。図1では、現場打ちコンクリート部3を仮想線で示している。
(First Embodiment)
Hereinafter, the steel-concrete composite structure and the construction method of the steel-concrete composite structure according to the first embodiment of the present invention will be described with reference to FIGS. 1 to 5.
The steel-concrete composite structure according to the first embodiment is adopted for the wall portion 1A shown in FIG. 1, which is the frame of the structure. A plurality of wall portions 1A are arranged so as to construct a wall of a structure.
The wall portion 1A includes a pair of precast concrete portions 2 and 2 arranged on both sides in the thickness direction, a cast-in-place concrete portion 3 arranged between the pair of precast concrete portions 2 and 2, and a pair of precast concrete portions. It has a joined steel plate 4 for joining portions 2 and 2. In FIG. 1, the cast-in-place concrete portion 3 is shown by a virtual line.

一対のプレキャストコンクリート部2,2は、それぞれ工場などで製作され、壁部を構築する現場に搬入されるように構成されている。現場打ちコンクリート部3は、壁部1Aを構築する現場にて打設された現場打ちコンクリートで構成されている。
壁部1Aは、鉛直に立設しているものとし、上下を結ぶ鉛直方向を上下方向とし、上下方向および厚さ方向に直交する水平方向を幅方向とする。
The pair of precast concrete portions 2 and 2 are each manufactured in a factory or the like, and are configured to be carried to the site where the wall portion is constructed. The cast-in-place concrete portion 3 is composed of cast-in-place concrete cast at the site where the wall portion 1A is constructed.
The wall portion 1A is assumed to be vertically erected, the vertical direction connecting the top and bottom is the vertical direction, and the horizontal direction orthogonal to the vertical direction and the thickness direction is the width direction.

図1乃至図5に示すように、一対のプレキャストコンクリート部2,2は、略同じ形態に形成され、互いに向き合うように配置されている。
プレキャストコンクリート部2は、主鉄筋5と、配力筋6と、配力筋6が挿通される第1孔部74が形成された孔あき鋼材7と、主鉄筋5、配力筋6、孔あき鋼材7を埋設するコンクリート部8と、を有している。図面では、コンクリート部8を仮想線で示している。
As shown in FIGS. 1 to 5, the pair of precast concrete portions 2 and 2 are formed in substantially the same shape and are arranged so as to face each other.
The precast concrete portion 2 includes a main reinforcing bar 5, a force distribution bar 6, a perforated steel material 7 in which a first hole portion 74 through which the force distribution bar 6 is inserted is formed, a main reinforcing bar 5, a force distribution bar 6, and a hole. It has a concrete portion 8 for burying the perforated steel material 7. In the drawing, the concrete portion 8 is shown by a virtual line.

主鉄筋は5、例えば異形鉄筋などで、プレキャストコンクリート部2の高さの略全体にわたって上下方向に延びる向きで、プレキャストコンクリート部2の幅方向の略全体にわたって互いに幅方向に間隔をあけて複数配列されている。
配力筋6は、例えば丸鋼などで、プレキャストコンクリート部2の幅方向の略全体にわたって幅方向に延びる向きで、プレキャストコンクリート部2の高さの略全体にわたって互いに上下方向に間隔をあけて複数配列されている。
The main reinforcing bars are 5, for example, deformed reinforcing bars, and are arranged in a direction extending in the vertical direction over substantially the entire height of the precast concrete portion 2 and at intervals in the width direction over substantially the entire width direction of the precast concrete portion 2. Has been done.
The force distribution bars 6 are, for example, round steel, and have a direction extending in the width direction over substantially the entire width direction of the precast concrete portion 2, and a plurality of force distribution bars 6 are spaced apart from each other in the vertical direction over substantially the entire height of the precast concrete portion 2. It is arranged.

孔あき鋼材7は、長尺の平板状で、板面が長尺の長方形状に形成されている。孔あき鋼材7は、短辺方向(孔あき鋼材7の板面の短辺が延びる方向)の略中央部を境として短辺方向の一方側が第1板部71となり他方側が第2板部72となっている。第1板部71と第2板部72とは一体に形成されている。第1板部71および第2板部72を合せて鋼板部73とする。
第1板部71には、板面を貫通する第1孔部74が長辺方向(孔あき鋼材7の板面の長辺が延びる方向)に間隔をあけて複数形成されている。
第2板部72には、板面を貫通する第2孔部75が長辺方向に間隔をあけて複数形成されている。
The perforated steel material 7 has a long flat plate shape, and the plate surface is formed in a long rectangular shape. In the perforated steel material 7, one side in the short side direction is the first plate portion 71 and the other side is the second plate portion 72 with the substantially central portion in the short side direction (the direction in which the short side of the plate surface of the perforated steel material 7 extends) as a boundary. It has become. The first plate portion 71 and the second plate portion 72 are integrally formed. The first plate portion 71 and the second plate portion 72 are combined to form a steel plate portion 73.
A plurality of first hole portions 74 penetrating the plate surface are formed in the first plate portion 71 at intervals in the long side direction (direction in which the long side of the plate surface of the perforated steel material 7 extends).
A plurality of second hole portions 75 penetrating the plate surface are formed in the second plate portion 72 at intervals in the long side direction.

孔あき鋼材7は、長辺方向を上下方向とし、短辺方向を厚さ方向として、板面が幅方向を向く向きで幅方向に隣り合う主鉄筋5の間に配置されている。本実施形態では、複数の孔あき鋼材7が幅方向に間隔をあけて配置されていて、幅方向に隣り合う孔あき鋼材7の間に3本の主鉄筋5が配置されている。なお、幅方向に隣り合う孔あき鋼材7の間に配置される主鉄筋5の数は適宜設定されてよい。 The perforated steel material 7 is arranged between the main reinforcing bars 5 adjacent to each other in the width direction with the plate surface facing the width direction, with the long side direction as the vertical direction and the short side direction as the thickness direction. In the present embodiment, a plurality of perforated steel materials 7 are arranged at intervals in the width direction, and three main reinforcing bars 5 are arranged between the perforated steel materials 7 adjacent to each other in the width direction. The number of main reinforcing bars 5 arranged between the perforated steel materials 7 adjacent to each other in the width direction may be appropriately set.

配列された複数の孔あき鋼材7にそれぞれ形成された第1孔部74は、幅方向に重なるように構成されている。また、配列された複数の孔あき鋼材7にそれぞれ形成された第2孔部75は、幅方向に重なるように構成されている。
幅方向に重なるように配置された第1孔部74には、同一の配力筋6が挿通されている。 幅方向に重なるように配置された第2孔部75には、同一の現場打ちコンクリート部3の鉄筋が挿通されている。主鉄筋5は、第1孔部74に挿通された配力筋6よりも第2板部72側に配置されている。
第1孔部74に挿通された配力筋6は、主鉄筋5と結束されている。これにより、主鉄筋5と配力筋6とはメッシュを構成している。
The first hole portions 74 formed in the plurality of arranged perforated steel materials 7 are configured to overlap each other in the width direction. Further, the second hole portions 75 formed in the plurality of arranged perforated steel materials 7 are configured to overlap each other in the width direction.
The same force distribution muscle 6 is inserted through the first hole portion 74 arranged so as to overlap in the width direction. Reinforcing bars of the same cast-in-place concrete portion 3 are inserted into the second hole portion 75 arranged so as to overlap in the width direction. The main reinforcing bar 5 is arranged on the second plate portion 72 side with respect to the force distribution bar 6 inserted through the first hole portion 74.
The force distribution bar 6 inserted through the first hole portion 74 is bound to the main reinforcing bar 5. As a result, the main reinforcing bar 5 and the force distribution bar 6 form a mesh.

コンクリート部8は、平板状に形成され、板面が長方形状に形成されている。コンクリート部8は、板面が厚さ方向を向く向きに配置されている。コンクリート部8は、主鉄筋、配力筋6および孔あき鋼材7の第1板部71を埋設している。コンクリート部8のコンクリートは、第1孔部74の縁部と配力筋6との隙間にも充填されている。
孔あき鋼材7の第2板部72は、コンクリート部8に埋設されておらず、コンクリート部8から厚さ方向に突出している。
The concrete portion 8 is formed in a flat plate shape, and the plate surface is formed in a rectangular shape. The concrete portion 8 is arranged so that the plate surface faces the thickness direction. The concrete portion 8 has a main reinforcing bar, a force distribution bar 6, and a first plate portion 71 of a perforated steel material 7 embedded therein. The concrete of the concrete portion 8 is also filled in the gap between the edge portion of the first hole portion 74 and the force distribution bar 6.
The second plate portion 72 of the perforated steel material 7 is not embedded in the concrete portion 8, but protrudes from the concrete portion 8 in the thickness direction.

一対のプレキャストコンクリート部2,2は、互いの孔あき鋼材7の第2板部72が突出している側が厚さ方向に対向するように厚さ方向に間隔をあけて配置されている。一方のプレキャストコンクリート部2の複数の孔あき鋼材7と他方のプレキャストコンクリート部2の複数の孔あき鋼材7とは、厚さ方向に対向する位置に配置されている。
一方のプレキャストコンクリート部2の複数の孔あき鋼材7の一部と、他方のプレキャストコンクリート部2の複数の孔あき鋼材7の一部は、接合鋼板4で接合されている。
The pair of precast concrete portions 2 and 2 are arranged at intervals in the thickness direction so that the protruding sides of the second plate portions 72 of the perforated steel materials 7 face each other in the thickness direction. The plurality of perforated steel materials 7 of one precast concrete portion 2 and the plurality of perforated steel materials 7 of the other precast concrete portion 2 are arranged at positions facing each other in the thickness direction.
A part of the plurality of perforated steel materials 7 of one precast concrete portion 2 and a part of the plurality of perforated steel materials 7 of the other precast concrete portion 2 are joined by a joined steel plate 4.

接合鋼板4は、長尺の平板状に形成され、板面が長方形状に形成されている。接合鋼板4には、接合鋼板4の長辺方向に間隔をあけて複数の第3孔部41が形成されている。接合鋼板4は、板面が幅方向を向く向きに配置されている。接合鋼板4は、幅方向の一方の縁部が幅方向の一方側に配置されたプレキャストコンクリート部2の第2板部72の幅方向の他方側の縁部と接合され、幅方向の他方の縁部が幅方向の他方側に配置されたプレキャストコンクリート部2の第2板部72の幅方向の一方側の縁部と接合されている。
本実施形態では、幅方向に配列された複数の孔あき鋼材7のうちの1つ置きの孔あき鋼材7に対して接合鋼板4が接合されている。
The joined steel plate 4 is formed in the shape of a long flat plate, and the plate surface is formed in the shape of a rectangle. A plurality of third hole portions 41 are formed in the joined steel plate 4 at intervals in the long side direction of the joined steel plate 4. The joined steel plate 4 is arranged so that the plate surface faces the width direction. The joined steel plate 4 is joined to the other edge portion in the width direction of the second plate portion 72 of the precast concrete portion 2 in which one edge portion in the width direction is arranged on one side in the width direction, and the other edge portion in the width direction is joined. The edge portion is joined to the one side edge portion in the width direction of the second plate portion 72 of the precast concrete portion 2 arranged on the other side in the width direction.
In the present embodiment, the bonded steel plate 4 is joined to every other perforated steel material 7 among the plurality of perforated steel materials 7 arranged in the width direction.

現場打ちコンクリート部3は、一対のプレキャストコンクリート部2,2のコンクリート部8の間に打設されている。現場打ちコンクリート部3には、要求される強度に応じた形態の鉄筋が適宜配筋されている。鉄筋のうちの幅方向に延びてプレキャスト部材に隣接する鉄筋は、孔あき鋼材7の第2孔部75に挿通されている。
現場打ちコンクリート部3は、一対のプレキャストコンクリート部2,2の間に打設されると、孔あき鋼材7の第2板部72および接合鋼板4を埋設している。接合鋼板4には、第3孔部41が形成されているため、第3孔部41を通って現場打ちコンクリート部3のコンクリートが接合鋼板4の一方側および他方側の両側にいきわたるように構成されている。また、第3孔部41の内部にも現場打ちコンクリート部3のコンクリートが充填されている。
また、現場打ちコンクリート部3のコンクリートは、第2孔部75の縁部と鉄筋との隙間にも充填されている。
The cast-in-place concrete portion 3 is placed between the concrete portions 8 of the pair of precast concrete portions 2 and 2. Reinforcing bars in a form corresponding to the required strength are appropriately arranged in the cast-in-place concrete portion 3. The reinforcing bar extending in the width direction of the reinforcing bar and adjacent to the precast member is inserted into the second hole portion 75 of the perforated steel material 7.
When the cast-in-place concrete portion 3 is cast between the pair of precast concrete portions 2 and 2, the second plate portion 72 of the perforated steel material 7 and the joined steel plate 4 are embedded. Since the third hole portion 41 is formed in the joined steel plate 4, the concrete of the cast-in-place concrete portion 3 is configured to spread to both one side and the other side of the joined steel plate 4 through the third hole portion 41. Has been done. Further, the inside of the third hole portion 41 is also filled with the concrete of the cast-in-place concrete portion 3.
Further, the concrete of the cast-in-place concrete portion 3 is also filled in the gap between the edge portion of the second hole portion 75 and the reinforcing bar.

次に、第1実施形態による壁部1Aの施工方法(鋼コンクリート構造の施工方法)について説明する。
まず、一対のプレキャストコンクリート部2,2をそれぞれ製作する(プレキャストコンクリート部製作工程)。
主鉄筋5を設置する(主鉄筋設置工程)。複数の主鉄筋5をそれぞれ上下方向に延びる向きで幅方向に配列し、支持具などで所定の位置に設置する。
主鉄筋設置工程と前後して孔あき鋼材7設置する(孔あき鋼材設置工程)。複数の孔あき鋼材7を幅方向に隣り合う主鉄筋5の間に配置し、支持具などで所定の位置に設置する。
本実施形態では、幅方向に隣り合う孔あき鋼材7の間に3本の主鉄筋5が配置されるように孔あき鋼材7を設置する。なお、幅方向に隣り合う孔あき鋼材7の間に配置される主鉄筋5の数は適宜設定されてよい。
配力筋6を配置する(配力筋配置工程)。配力筋6を孔あき鋼材7の第2孔部75に挿通させて、配力筋6と主鉄筋5とを結束する。
Next, the construction method of the wall portion 1A (construction method of the steel-concrete structure) according to the first embodiment will be described.
First, a pair of precast concrete parts 2 and 2 are manufactured (precast concrete part manufacturing process).
Install the main reinforcing bar 5 (main reinforcing bar installation process). A plurality of main reinforcing bars 5 are arranged in the width direction in a direction extending in the vertical direction, and installed at a predetermined position with a support or the like.
7 perforated steel materials are installed before and after the main reinforcing bar installation process (perforated steel material installation process). A plurality of perforated steel materials 7 are arranged between the main reinforcing bars 5 adjacent to each other in the width direction, and are installed at predetermined positions with a support or the like.
In the present embodiment, the perforated steel material 7 is installed so that the three main reinforcing bars 5 are arranged between the perforated steel materials 7 adjacent to each other in the width direction. The number of main reinforcing bars 5 arranged between the perforated steel materials 7 adjacent to each other in the width direction may be appropriately set.
The force distribution muscle 6 is arranged (force distribution muscle arrangement step). The force distribution bar 6 is inserted through the second hole portion 75 of the perforated steel material 7 to bind the force distribution bar 6 and the main reinforcing bar 5.

コンクリート部8を構築する(コンクリート部打設工程)。
コンクリート部8の型枠を設置し、コンクリート部8のコンクリートを打設する。このとき、孔あき鋼材の第1板部71をコンクリート部8のコンクリートに埋設し、第2板部72をコンクリート部の8コンクリートに埋設せずにコンクリート部8から突出させる。コンクリート部8のコンクリートが硬化したら脱型する。
このようにして、一対のプレキャストコンクリート部2,2が製作される。
The concrete part 8 is constructed (concrete part placing process).
The formwork of the concrete part 8 is installed, and the concrete of the concrete part 8 is placed. At this time, the first plate portion 71 of the perforated steel material is embedded in the concrete of the concrete portion 8, and the second plate portion 72 is projected from the concrete portion 8 without being embedded in the 8 concrete of the concrete portion. When the concrete of the concrete portion 8 is hardened, it is removed from the mold.
In this way, a pair of precast concrete portions 2 and 2 are manufactured.

続いて、製作された一対のプレキャストコンクリート部2,2を壁部1Aを構築する場所に運搬して設置する(プレキャストコンクリート部設置工程)。
一対のプレキャストコンクリート部2,2を壁部1Aの厚さ方向の両端部に対応する位置にそれぞれ配置し、第2板部72が突出している側を厚さ方向に対向させる。厚さ方向に対向する第2板部72どうしを接合鋼板4で接合する。なお、本実施形態では、すべての第2板部72を接合鋼板4で接合せず、幅方向に並んだ1つ置きの第2板部72を接合鋼板4で接合する。
対向する一対のプレキャストコンクリート部2,2のコンクリート部8の間に現場打ちコンクリート部3を構築する(現場打ちコンクリート部構築工程)。
現場打ちコンクリート部3の配筋を行うとともに型枠を設置して、現場打ちコンクリート3部のコンクリートを打設する。このとき、現場打ちコンクリート部3のコンクリートで第2板部72および接合鋼板4を埋設し、接合鋼板4の第3孔部41を介して接合鋼板4の一方側および他方側に現場打ちコンクリート部3のコンクリートを充填する。現場打ちコンクリート部3のコンクリートが硬化したら脱型する。
このようにして鋼コンクリート複合構造の壁部1Aが構築される。なお、壁部1Aは、複数配列された状態に構築されるように想定されているため、壁部1Aが複数配列される場合には、複数の壁部1Aのそれぞれのプレキャストコンクリート部設置工程を行い、幅方向に隣り合うプレキャストコンクリート部2を接続した後に、複数の壁部1Aのそれぞれの現場打ちコンクリート部構築工程を一度に行い、複数の壁部1Aのそれぞれの現場打ちコンクリート部3を一体に構築する。
Subsequently, the pair of manufactured precast concrete portions 2 and 2 are transported and installed at the place where the wall portion 1A is to be constructed (precast concrete portion installation process).
A pair of precast concrete portions 2 and 2 are arranged at positions corresponding to both ends of the wall portion 1A in the thickness direction, and the side on which the second plate portion 72 protrudes is opposed to each other in the thickness direction. The second plate portions 72 facing each other in the thickness direction are joined by the joined steel plate 4. In this embodiment, not all the second plate portions 72 are joined by the joined steel plate 4, but every other second plate portion 72 arranged in the width direction is joined by the joined steel plate 4.
A cast-in-place concrete portion 3 is constructed between the concrete portions 8 of the pair of precast concrete portions 2 and 2 facing each other (cast-in-place concrete portion construction step).
Reinforcement of the cast-in-place concrete part 3 is performed, a formwork is installed, and concrete of the cast-in-place concrete part 3 is placed. At this time, the second plate portion 72 and the joined steel plate 4 are embedded in the concrete of the cast-in-place concrete portion 3, and the cast-in-place concrete portion is formed on one side and the other side of the joined steel plate 4 via the third hole portion 41 of the joined steel plate 4. Fill the concrete of 3. When the concrete of the cast-in-place concrete portion 3 is hardened, it is removed from the mold.
In this way, the wall portion 1A of the steel-concrete composite structure is constructed. Since the wall portions 1A are assumed to be constructed in a state where a plurality of wall portions 1A are arranged, when a plurality of wall portions 1A are arranged, the precast concrete portion installation process of each of the plurality of wall portions 1A is performed. After connecting the precast concrete portions 2 adjacent to each other in the width direction, the cast-in-place concrete portion construction process of each of the plurality of wall portions 1A is performed at once, and the cast-in-place concrete portions 3 of the plurality of wall portions 1A are integrated. Build on.

次に、上述した第1実施形態による鋼コンクリート複合構造および鋼コンクリート複合構造の施工方法の作用・効果について図面を用いて説明する。
第1実施形態による鋼コンクリート複合構造では、配力筋6を孔あき鋼材7の第1孔部74に挿通させて主鉄筋5と結束することにより、主鉄筋5と配力筋6とを容易に格子状に配置することができるとともに、主鉄筋5および配力筋6と孔あき鋼材7とを容易に接合することができる。これにより、鋼コンクリート複合構造を容易に施工することができる。その結果、鋼コンクリート複合構造の施工にかかる労力の軽減や工期の短縮を図ることができる。
Next, the operation and effect of the steel-concrete composite structure and the construction method of the steel-concrete composite structure according to the first embodiment described above will be described with reference to the drawings.
In the steel-concrete composite structure according to the first embodiment, the main reinforcing bar 5 and the force distribution bar 6 are easily made by inserting the force distribution bar 6 into the first hole portion 74 of the perforated steel material 7 and binding the force distribution bar 6 to the main reinforcing bar 5. The main reinforcing bars 5 and the force distribution bars 6 can be easily joined to the perforated steel material 7. This makes it possible to easily construct a steel-concrete composite structure. As a result, it is possible to reduce the labor required for the construction of the steel-concrete composite structure and shorten the construction period.

また、主鉄筋5に作用するせん断力が、配力筋6を介して孔あき鋼材7に伝達されるため、孔あき鋼材7がせん断力を負担することができ、せん断耐力を確保することができる。
また、孔あき鋼材7の第2板部72がコンクリート部8の外部に突出して現場打ちコンクリート部3に埋設されるため、第2板部72がジベルとなって一対のプレキャストコンクリート部2,2と現場打ちコンクリート部3とを強固に接合することができ、せん断耐力を確保することができる。
また、第2板部72には、現場打ちコンクリート部3の鉄筋が挿通される第2孔部75が形成されていることにより、現場打ちコンクリート部3の配筋を容易に行うことができる。
Further, since the shearing force acting on the main reinforcing bar 5 is transmitted to the perforated steel material 7 via the force distribution bar 6, the perforated steel material 7 can bear the shearing force and secure the shearing force. can.
Further, since the second plate portion 72 of the perforated steel material 7 protrudes to the outside of the concrete portion 8 and is embedded in the cast-in-place concrete portion 3, the second plate portion 72 becomes a gibber and a pair of precast concrete portions 2 and 2. And the cast-in-place concrete portion 3 can be firmly joined, and the shear strength can be secured.
Further, since the second plate portion 72 is formed with the second hole portion 75 through which the reinforcing bar of the cast-in-place concrete portion 3 is inserted, the reinforcement of the cast-in-place concrete portion 3 can be easily arranged.

(他の実施形態)
次に、他の実施形態について、添付図面に基づいて説明するが、上記の第1実施形態と同一又は同様な部材、部分には同一の符号を用いて説明を省略し、実施形態と異なる構成について説明する。
(Other embodiments)
Next, another embodiment will be described with reference to the accompanying drawings, but the same or similar members and parts as those of the first embodiment will be described by using the same reference numerals, and the description will be omitted, and the configuration will be different from that of the embodiment. Will be explained.

(第2実施形態)
図6に示すように、第2実施形態による鋼コンクリート複合構造の壁部1Bでは、プレキャストコンクリート部2Bの孔あき鋼材7Bの形態が第1実施形態の孔あき鋼材7の形態と異なっている。
第2実施形態による孔あき鋼材7Bは、第1実施形態の孔あき鋼材7の鋼板部73と同様の鋼板部73と、鋼板部73の第1板部71側の端部に接続されたフランジ76Bと、を有している。
フランジ76Bは平板状の鋼板で、孔あき鋼材7Bと直交する向き(板面が厚さ方向を向く向き)に配置されている。フランジ76Bは、幅方向の略中央部が鋼板部73と溶接などによって接合されている。このため、孔あき鋼材7Bは、断面がT字形状となっている。
(Second Embodiment)
As shown in FIG. 6, in the wall portion 1B of the steel-concrete composite structure according to the second embodiment, the form of the perforated steel material 7B of the precast concrete portion 2B is different from the form of the perforated steel material 7 of the first embodiment.
The perforated steel material 7B according to the second embodiment has a flange connected to a steel plate portion 73 similar to the steel plate portion 73 of the perforated steel material 7 of the first embodiment and an end portion of the steel plate portion 73 on the first plate portion 71 side. It has 76B and.
The flange 76B is a flat plate-shaped steel plate, and is arranged in a direction orthogonal to the perforated steel material 7B (direction in which the plate surface faces the thickness direction). The flange 76B has a substantially central portion in the width direction joined to the steel plate portion 73 by welding or the like. Therefore, the perforated steel material 7B has a T-shaped cross section.

第2実施形態による孔あき鋼材7Bでは、第1孔部74から孔あき鋼材7Bの縁部までの距離が、第1孔部74からフランジ76Bの幅方向の端部までの距離となる。これに対し、第1実施形態による孔あき鋼材7は、第1孔部74から孔あき鋼材7の縁部までの距離が、第1孔部74から鋼板部73の第1板部71側の端部までの距離となる。このように、第2実施形態による孔あき鋼材では、第1孔部74ら孔あき鋼材7Bの縁部までの距離が、第1実施形態による孔あき鋼材7よりも長くなる。
このため、万が一、孔あき鋼材7Bに負荷がかかり第1孔部74の周縁部から亀裂が生じたとしても、第2実施形態による鋼コンクリート複合構造では、亀裂が孔あき鋼材7Bの縁部にまで達しにくく、亀裂によって孔あき鋼材7Bが破断することを確実に防止できる。
In the perforated steel material 7B according to the second embodiment, the distance from the first hole portion 74 to the edge portion of the perforated steel material 7B is the distance from the first hole portion 74 to the end portion in the width direction of the flange 76B. On the other hand, in the perforated steel material 7 according to the first embodiment, the distance from the first hole portion 74 to the edge portion of the perforated steel material 7 is from the first hole portion 74 to the first plate portion 71 side of the steel plate portion 73. It is the distance to the end. As described above, in the perforated steel material according to the second embodiment, the distance from the first hole portion 74 to the edge portion of the perforated steel material 7B is longer than that of the perforated steel material 7 according to the first embodiment.
Therefore, even if a load is applied to the perforated steel material 7B and a crack is generated from the peripheral edge of the first hole portion 74, in the steel-concrete composite structure according to the second embodiment, the crack is generated at the edge of the perforated steel material 7B. It is difficult to reach the level, and it is possible to reliably prevent the perforated steel material 7B from breaking due to cracks.

(第3実施形態)
図7に示すように、第3実施形態による鋼コンクリート複合構造の壁部1Cでは、プレキャストコンクリート部2B孔あき鋼材7Cの形態が上記の実施形態の孔あき鋼材7,7Bの形態と異なっている。
第3実施形態による孔あき鋼材7Cは、上記の実施形態の孔あき鋼材7,7Bの鋼板部73と同様の鋼板部73と、鋼板部73の第1板部71側の端部に接続されたフランジ76Cと、を有している。
フランジ76Cは平板状の鋼板で、鋼板部73と直交する向き(板面が厚さ方向を向く向き)に配置されている。フランジ76Cは、幅方向の一方側の端部が鋼板部73と溶接などによって接合されている。このため、孔あき鋼材7Cは、断面がL字形状となっている。
(Third Embodiment)
As shown in FIG. 7, in the wall portion 1C of the steel-concrete composite structure according to the third embodiment, the form of the precast concrete portion 2B perforated steel material 7C is different from the form of the perforated steel materials 7 and 7B of the above-described embodiment. ..
The perforated steel material 7C according to the third embodiment is connected to a steel plate portion 73 similar to the steel plate portion 73 of the perforated steel material 7 and 7B of the above embodiment and an end portion of the steel plate portion 73 on the first plate portion 71 side. It has a flange 76C and a flange 76C.
The flange 76C is a flat plate-shaped steel plate, and is arranged in a direction orthogonal to the steel plate portion 73 (direction in which the plate surface faces the thickness direction). The flange 76C has one end in the width direction joined to the steel plate portion 73 by welding or the like. Therefore, the perforated steel material 7C has an L-shaped cross section.

第3実施形態による孔あき鋼材7Cでは、第1孔部74から孔あき鋼材7Cの縁部までの距離が、第1孔部74からフランジ76Cの幅方向の端部までの距離となる。これに対し、第1実施形態による孔あき鋼材7は、第1孔部74から孔あき鋼材7の縁部までの距離が、第1孔部74から鋼板部73の第1板部71側の端部までの距離となる。このように、第3実施形態による孔あき鋼材7Cでは、第1孔部74から孔あき鋼材7Cの縁部までの距離が、第1実施形態による孔あき鋼材7よりも長くなる。
このため、万が一、孔あき鋼材7Cに負荷がかかり第1孔部74の周縁部から亀裂が生じたとしても、第3実施形態による鋼コンクリート複合構造では、亀裂が孔あき鋼材7Cの縁部にまで達しにくく、亀裂によって孔あき鋼材7Cが破断することを確実に防止できる。
In the perforated steel material 7C according to the third embodiment, the distance from the first hole portion 74 to the edge portion of the perforated steel material 7C is the distance from the first hole portion 74 to the end portion in the width direction of the flange 76C. On the other hand, in the perforated steel material 7 according to the first embodiment, the distance from the first hole portion 74 to the edge portion of the perforated steel material 7 is from the first hole portion 74 to the first plate portion 71 side of the steel plate portion 73. It is the distance to the end. As described above, in the perforated steel material 7C according to the third embodiment, the distance from the first hole portion 74 to the edge portion of the perforated steel material 7C is longer than that of the perforated steel material 7 according to the first embodiment.
Therefore, even if a load is applied to the perforated steel material 7C and a crack is generated from the peripheral edge of the first hole portion 74, in the steel-concrete composite structure according to the third embodiment, the crack is generated at the edge of the perforated steel material 7C. It is difficult to reach the level, and it is possible to reliably prevent the perforated steel material 7C from breaking due to cracks.

(第4実施形態)
図8に示すように、第4実施形態による鋼コンクリート複合構造の壁部1Dでは、プレキャストコンクリート部2Cの孔あき鋼材7D形態が上記の実施形態の孔あき鋼材7,7B,7Cの形態と異なっている。
第4実施形態による孔あき鋼材7Dは、上記の実施形態の孔あき鋼材7,7B,7Cの鋼板部73と同様の鋼板部73と、鋼板部73に第1孔部74の縁部に沿って接合された鋼棒(補強鋼材)77と、を有している。
鋼棒77は、U字形に形成され、第1板部71側から第2板部72側に開口する向きで第1板部71に溶接などによって接合されている。鋼棒77は、孔あき鋼材7Dの第1孔部74に挿通された配力筋6を囲んでいる。
(Fourth Embodiment)
As shown in FIG. 8, in the wall portion 1D of the steel-concrete composite structure according to the fourth embodiment, the form of the perforated steel material 7D of the precast concrete portion 2C is different from the form of the perforated steel materials 7, 7B, 7C of the above embodiment. ing.
The perforated steel material 7D according to the fourth embodiment has the same steel plate portion 73 as the steel plate portion 73 of the perforated steel materials 7, 7B, 7C of the above embodiment, and the steel plate portion 73 along the edge portion of the first hole portion 74. It has a steel rod (reinforcing steel material) 77 and which are joined together.
The steel rod 77 is formed in a U shape and is joined to the first plate portion 71 by welding or the like in a direction of opening from the first plate portion 71 side to the second plate portion 72 side. The steel rod 77 surrounds the force distribution bar 6 inserted through the first hole portion 74 of the perforated steel material 7D.

第4実施形態による鋼コンクリート複合構造では、U字形状の鋼棒77が第1孔部74の縁部に沿って鋼板部73に接合されていることにより、孔あき鋼材7Dの第1孔部74の近傍の強度を向上させることができる。このため、孔あき鋼材7Dの第1孔部74が変形したり、第1孔部74の縁部から鋼板部73に亀裂が生じたりすることを防止することができる。
なお、第4実施形態による鋼棒77は、U字形状に形成されているが、U字形状に代わってリング状に形成され、第1孔部74の縁部に沿った状態で鋼板部73に接合されていてもよい。
In the steel-concrete composite structure according to the fourth embodiment, the U-shaped steel rod 77 is joined to the steel plate portion 73 along the edge portion of the first hole portion 74, so that the first hole portion of the perforated steel material 7D is formed. The strength in the vicinity of 74 can be improved. Therefore, it is possible to prevent the first hole portion 74 of the perforated steel material 7D from being deformed or the steel plate portion 73 from being cracked from the edge portion of the first hole portion 74.
Although the steel rod 77 according to the fourth embodiment is formed in a U-shape, it is formed in a ring shape instead of the U-shape, and the steel plate portion 73 is formed along the edge portion of the first hole portion 74. It may be joined to.

(第5実施形態)
図9に示すように、第5実施形態による鋼コンクリート構造の壁部1Eは、上記の実施形態のようなプレキャストコンクリート部2(図1参照)を用いずに、現場打ちコンクリートで施工されている。第5実施形態における厚さ方向が本発明の第1方向に相当している。
壁部1Eは、主鉄筋E5と、配力筋6Eと、配力筋6Eが挿通される第1孔部74Eが形成された孔あき鋼材7Eと、主鉄筋5E、配力筋6E、孔あき鋼材7Eを埋設するコンクリート部8Eと、を有している。なお、図9ではコンクリート部8Eを仮想線で示している。
(Fifth Embodiment)
As shown in FIG. 9, the wall portion 1E of the steel concrete structure according to the fifth embodiment is constructed with cast-in-place concrete without using the precast concrete portion 2 (see FIG. 1) as in the above embodiment. .. The thickness direction in the fifth embodiment corresponds to the first direction of the present invention.
The wall portion 1E includes a main reinforcing bar E5, a force distribution bar 6E, a perforated steel material 7E in which a first hole portion 74E through which the force distribution bar 6E is inserted is formed, a main reinforcing bar 5E, a force distribution bar 6E, and a hole. It has a concrete portion 8E for burying a steel material 7E. In FIG. 9, the concrete portion 8E is shown by a virtual line.

主鉄筋5Eは、例えば異形鉄筋などで、壁部1Eの高さの略全体にわたって上下方向に延びる向きに配置されている。主鉄筋5Eは、壁部1Eの厚さ方向の一方側と他方側の両側それぞれに、壁部1Eの幅方向の略全体にわたって互いに幅方向に間隔をあけて複数配列されている。配力筋6Eは、例えば丸鋼などで、壁部1Eの幅方向の略全体にわたって幅方向に延びる向きで、壁部1Eの高さの略全体にわたって互いに上下方向に間隔をあけて複数配列されている。 The main reinforcing bar 5E is, for example, a deformed reinforcing bar, and is arranged in a direction extending in the vertical direction over substantially the entire height of the wall portion 1E. A plurality of main reinforcing bars 5E are arranged on one side and both sides of the wall portion 1E in the thickness direction at intervals in the width direction over substantially the entire width direction of the wall portion 1E. The force distribution bars 6E are, for example, round steel, and are arranged in a direction extending in the width direction over substantially the entire width direction of the wall portion 1E, and a plurality of force distribution bars 6E are arranged at intervals in the vertical direction over substantially the entire height of the wall portion 1E. ing.

孔あき鋼材7Eは、長尺の平板状で、板面が長尺の長方形状に形成されている。孔あき鋼材7Eは、短辺方向(孔あき鋼材7Eの板面の短辺が延びる方向)の両縁部近傍がそれぞれ第1板部71Eとなり、2つの第1板部71Eの間が第2板部72Eとなっている。第1板部71Eと第2板部72Eとは一体に形成されている。第1板部71Eおよび第2板部72Eを合せて鋼板部73Eとする。 The perforated steel material 7E has a long flat plate shape, and the plate surface is formed in a long rectangular shape. In the perforated steel material 7E, the vicinity of both edges in the short side direction (the direction in which the short side of the plate surface of the perforated steel material 7E extends) becomes the first plate portion 71E, respectively, and the space between the two first plate portions 71E is the second. It is a plate portion 72E. The first plate portion 71E and the second plate portion 72E are integrally formed. The first plate portion 71E and the second plate portion 72E are combined to form a steel plate portion 73E.

2つの第1板部71Eには、それぞれ板面を貫通する第1孔部74Eが長辺方向(孔あき鋼材7Eの板面の長辺が延びる方向)に間隔をあけて複数形成されている。
第2板部72Eには、短辺方向の両端部(第1板部71Eがそれぞれ配置されている側の端部)近傍に、それぞれ板面を貫通する第2孔部75Eが長辺方向に間隔をあけて複数形成されている。
また、第2板部72Eには、短辺方向の略中央部に長辺方向に間隔をあけて複数の第3孔部79が形成されている。
A plurality of first hole portions 74E penetrating the plate surface are formed in the two first plate portions 71E at intervals in the long side direction (direction in which the long side of the plate surface of the perforated steel material 7E extends). ..
In the second plate portion 72E, a second hole portion 75E penetrating the plate surface is provided in the long side direction in the vicinity of both ends in the short side direction (ends on the side where the first plate portion 71E is arranged). Multiple pieces are formed at intervals.
Further, in the second plate portion 72E, a plurality of third hole portions 79 are formed at a substantially central portion in the short side direction at intervals in the long side direction.

孔あき鋼材7Eは、長辺方向を上下方向とし、短辺方向を厚さ方向として、板面が幅方向を向く向きで幅方向に隣り合う主鉄筋Eの間に配置されている。孔あき鋼材7Eは、壁部1Eの厚さ方向の一方側から他方側にわたるように配置されている。このように、本実施形態では、孔あき鋼材7Eが上記の実施形態による孔あき鋼材のように壁部の厚さ方向の一方側と他方側にそれぞれ設けられて接合鋼板で接合された構成ではないため、接合鋼板が設けられていない。 The perforated steel material 7E is arranged between the main reinforcing bars E adjacent to each other in the width direction with the plate surface facing the width direction, with the long side direction as the vertical direction and the short side direction as the thickness direction. The perforated steel material 7E is arranged so as to extend from one side to the other side in the thickness direction of the wall portion 1E. As described above, in the present embodiment, the perforated steel material 7E is provided on one side and the other side in the thickness direction of the wall portion, respectively, as in the perforated steel material according to the above embodiment, and is joined by the bonded steel plate. Therefore, no joined steel plate is provided.

本実施形態では、複数の孔あき鋼材7Eが幅方向に間隔をあけて配置されていて、幅方向に隣り合う孔あき鋼材7Eの間に主鉄筋5が厚さ方向の一方側と他方側に6本ずつ配置されている。なお、幅方向に隣り合う孔あき鋼材7Eの間に配置される主鉄筋5の数は適宜設定されてよい。 In the present embodiment, a plurality of perforated steel materials 7E are arranged at intervals in the width direction, and the main reinforcing bars 5 are arranged on one side and the other side in the thickness direction between the perforated steel materials 7E adjacent to each other in the width direction. Six are arranged. The number of main reinforcing bars 5 arranged between the perforated steel materials 7E adjacent to each other in the width direction may be appropriately set.

配列された複数の孔あき鋼材7Eにそれぞれ形成された第1孔部74Eは、幅方向に重なるように構成されている。また、配列された複数の孔あき鋼材7Eにそれぞれ形成された第2孔部75Eは、幅方向に重なるように構成されている。
幅方向に重なるように配置された第1孔部74Eには、同一の配力筋6Eが挿通されている。幅方向に重なるように配置された第2孔部75Eには、同一のコンクリート部8Eの鉄筋が挿通されている。主鉄筋5Eは、第1孔部74Eに挿通された配力筋6Eよりも第2板部72E側に配置されている。
第1孔部74Eに挿通された配力筋6Eは、主鉄筋5Eと結束されている。これにより、主鉄筋5Eと配力筋6Eとはメッシュを構成している。
The first hole portions 74E formed in the plurality of arranged perforated steel materials 7E are configured to overlap each other in the width direction. Further, the second hole portions 75E formed in the plurality of arranged perforated steel materials 7E are configured to overlap each other in the width direction.
The same force distribution muscle 6E is inserted through the first hole portion 74E arranged so as to overlap in the width direction. Reinforcing bars of the same concrete portion 8E are inserted into the second hole portion 75E arranged so as to overlap in the width direction. The main reinforcing bar 5E is arranged on the second plate portion 72E side with respect to the force distribution bar 6E inserted through the first hole portion 74E.
The force distribution bar 6E inserted through the first hole portion 74E is bound to the main reinforcing bar 5E. As a result, the main reinforcing bar 5E and the force distribution bar 6E form a mesh.

コンクリート部8Eは、主鉄筋5E、配力筋6Eおよび孔あき鋼材7Eの第1板部71Eを埋設している。コンクリート部8Eのコンクリートは、第1孔部74Eの縁部と配力筋6との隙間および第3孔部79の内部にも充填されている。 In the concrete portion 8E, the main reinforcing bar 5E, the force distribution bar 6E, and the first plate portion 71E of the perforated steel material 7E are embedded. The concrete of the concrete portion 8E is also filled in the gap between the edge portion of the first hole portion 74E and the force distribution bar 6 and the inside of the third hole portion 79.

次に、第5実施形態の壁部1Eの施工方法(鋼コンクリート構造の施工方法)について説明する。
まず、主鉄筋5を設置する(主鉄筋設置工程)。複数の主鉄筋5をそれぞれ上下方向に延びる向きで幅方向に配列し、支持具などで所定の位置に設置する。
主鉄筋設置工程と前後して孔あき鋼材7Eを設置する(孔あき鋼材設置工程)。複数の孔あき鋼材7Eを幅方向に隣り合う主鉄筋5の間に配置し、支持具などで所定の位置に設置する。
本実施形態では、幅方向に隣り合う孔あき鋼材7Eの間には6本の主鉄筋5が配置されるように孔あき鋼材7Eを設置する。なお、幅方向に隣り合う孔あき鋼材7Eの間に配置される主鉄筋5の数は適宜設定されてよい。
配力筋6を配置する(配力筋配置工程)。配力筋6を孔あき鋼材7Eの第2孔部75Eに挿通させて、配力筋6と主鉄筋5とを結束する。
Next, the construction method of the wall portion 1E (construction method of the steel-concrete structure) of the fifth embodiment will be described.
First, the main reinforcing bar 5 is installed (main reinforcing bar installation process). A plurality of main reinforcing bars 5 are arranged in the width direction in a direction extending in the vertical direction, and installed at a predetermined position with a support or the like.
Perforated steel material 7E is installed before and after the main reinforcing bar installation process (perforated steel material installation process). A plurality of perforated steel materials 7E are arranged between the main reinforcing bars 5 adjacent to each other in the width direction, and are installed at predetermined positions with a support or the like.
In the present embodiment, the perforated steel material 7E is installed so that six main reinforcing bars 5 are arranged between the perforated steel materials 7E adjacent to each other in the width direction. The number of main reinforcing bars 5 arranged between the perforated steel materials 7E adjacent to each other in the width direction may be appropriately set.
The force distribution muscle 6 is arranged (force distribution muscle arrangement step). The force distribution bar 6 is inserted through the second hole portion 75E of the perforated steel material 7E to bind the force distribution bar 6 and the main reinforcing bar 5.

コンクリート部8Eを構築する(コンクリート部構築工程)。
コンクリート部8Eの型枠を設置し、コンクリート部8Eのコンクリートを打設する。このとき、孔あき鋼材7Eの第3孔部79を介して孔あき鋼材7Eの一方側および他方側にコンクリートが充填される。現場打ちコンクリートが硬化したら脱型する。
このようにして鋼コンクリート複合構造の壁部1Eが構築される。
The concrete part 8E is constructed (concrete part construction process).
The formwork of the concrete part 8E is installed, and the concrete of the concrete part 8E is placed. At this time, concrete is filled on one side and the other side of the perforated steel material 7E via the third hole portion 79 of the perforated steel material 7E. When the cast-in-place concrete hardens, it is removed from the mold.
In this way, the wall portion 1E of the steel-concrete composite structure is constructed.

第5実施形態による鋼コンクリート複合構造および鋼コンクリート複合構造の施工方法では、配力筋6を孔あき鋼材7Eの第1孔部74Eに挿通させて主鉄筋5と結束することにより、主鉄筋5と配力筋6とを容易に格子状に配置することができるとともに、主鉄筋5および配力筋6と孔あき鋼材7Eとを容易に接合することができる。これにより、鋼コンクリート複合構造を容易に施工することができる。
また、主鉄筋5に作用するせん断力が、配力筋6を介して孔あき鋼材7Eに伝達されるため、孔あき鋼材7Eがせん断力を負担することができ、せん断耐力を確保することができる。
In the method of constructing the steel-concrete composite structure and the steel-concrete composite structure according to the fifth embodiment, the main reinforcing bar 5 is bound to the main reinforcing bar 5 by inserting the force distribution bar 6 into the first hole portion 74E of the perforated steel material 7E. And the force distribution bars 6 can be easily arranged in a grid pattern, and the main reinforcing bars 5 and the force distribution bars 6 and the perforated steel material 7E can be easily joined. This makes it possible to easily construct a steel-concrete composite structure.
Further, since the shearing force acting on the main reinforcing bar 5 is transmitted to the perforated steel material 7E via the force distribution bar 6, the perforated steel material 7E can bear the shearing force and secure the shearing force. can.

(第6実施形態)
図10および図11に示すように、第6実施形態による鋼コンクリート構造は、上記の実施形態のような壁部1A〜1Eではなく、梁部1Fに採用されている。
梁部1Fは、下側に配置されるプレキャストコンクリート部2Fと、プレキャストコンクリート部2Fの上側に配置される現場打ちコンクリート部3Fと、を有している。図面では、現場打ちコンクリート部3Fおよびプレキャストコンクリート部2Fのコンクリート部8Fを仮想線で示している。
プレキャストコンクリート部2Fは、工場などで製作されたプレキャストコンクリート部2Fで構成されている。現場打ちコンクリート部3Fは、梁部1Fを構築する現場にて打設された現場打ちコンクリートで構成されている。
梁部1Fは、水平に延びているものとし、第6実施形態では、梁が延びる方向を長さ方向、長さ方向に直交する水平方向を幅方向とする。
(Sixth Embodiment)
As shown in FIGS. 10 and 11, the steel-concrete structure according to the sixth embodiment is adopted for the beam portion 1F instead of the wall portions 1A to 1E as in the above embodiment.
The beam portion 1F has a precast concrete portion 2F arranged on the lower side and a cast-in-place concrete portion 3F arranged on the upper side of the precast concrete portion 2F. In the drawing, the concrete part 8F of the cast-in-place concrete part 3F and the precast concrete part 2F is shown by a virtual line.
The precast concrete part 2F is composed of a precast concrete part 2F manufactured in a factory or the like. The cast-in-place concrete portion 3F is composed of cast-in-place concrete cast at the site where the beam portion 1F is constructed.
It is assumed that the beam portion 1F extends horizontally, and in the sixth embodiment, the direction in which the beam extends is the length direction, and the horizontal direction orthogonal to the length direction is the width direction.

プレキャストコンクリート部2Fは、主鉄筋5Fと、配力筋6Fと、配力筋6Fが挿通される第1孔部74Fが形成された孔あき鋼材7Fと、主鉄筋5F、配力筋6F、孔あき鋼材7Fを埋設するコンクリート部8Fと、を有している。
主鉄筋5Fは、例えば異形鉄筋などで、プレキャストコンクリート部2Fの長さ方向の略全体にわたって長さ方向に延びる向きで、プレキャストコンクリート部2Fの幅方向の略全体にわたって互いに幅方向に間隔をあけて複数配列されている。
配力筋6Fは、例えば丸鋼などで、プレキャストコンクリート部2Fの幅方向の略全体にわたって幅方向に延びる向きで、プレキャストコンクリート部2Fの長さ方向の略全体にわたって互いに長さ方向に間隔をあけて複数配列されている。
The precast concrete portion 2F includes a main reinforcing bar 5F, a force distribution bar 6F, a perforated steel material 7F in which a first hole portion 74F through which the force distribution bar 6F is inserted is formed, a main reinforcing bar 5F, a force distribution bar 6F, and a hole. It has a concrete portion 8F for burying the perforated steel material 7F.
The main reinforcing bar 5F is, for example, a deformed reinforcing bar, and is oriented so as to extend in the length direction over substantially the entire length direction of the precast concrete portion 2F, and is spaced apart from each other in the width direction over substantially the entire width direction of the precast concrete portion 2F. Multiple arrangements are made.
The force distribution bars 6F are, for example, round steel, and are oriented so as to extend in the width direction over substantially the entire width direction of the precast concrete portion 2F, and are spaced apart from each other in the length direction over substantially the entire length direction of the precast concrete portion 2F. Multiple arrangements are made.

孔あき鋼材7Fは、I形鋼で構成されている。孔あき鋼材7Fは、長さ方向に延びてウェブの板面が幅方向を向く向きに配置されている。孔あき鋼材7Fは、ウェブの下部側が第1板部71Fとなり、ウェブの上部側が第2板部72Fとなっている。
第1板部71Fの下端部近傍には、板面を貫通する第1孔部74Fが長さに間隔をあけて複数形成されている。
The perforated steel material 7F is made of I-shaped steel. The perforated steel material 7F extends in the length direction and is arranged so that the plate surface of the web faces the width direction. In the perforated steel material 7F, the lower side of the web is the first plate portion 71F, and the upper side of the web is the second plate portion 72F.
A plurality of first hole portions 74F penetrating the plate surface are formed in the vicinity of the lower end portion of the first plate portion 71F at intervals of length.

孔あき鋼材7Fは、幅方向に隣り合う主鉄筋5の間に配置されている。本実施形態では、2つの孔あき鋼材7Fが幅方向に間隔をあけて配置されていて、幅方向に隣り合う孔あき鋼材7Fの間に複数の主鉄筋5Fが配置されている。なお、幅方向に隣り合う孔あき鋼材7Fの間に配置される主鉄筋5Fの数は適宜設定されてよい。 The perforated steel material 7F is arranged between the main reinforcing bars 5 adjacent to each other in the width direction. In the present embodiment, the two perforated steel materials 7F are arranged at intervals in the width direction, and a plurality of main reinforcing bars 5F are arranged between the perforated steel materials 7F adjacent to each other in the width direction. The number of main reinforcing bars 5F arranged between the perforated steel materials 7F adjacent to each other in the width direction may be appropriately set.

配列された2つの孔あき鋼材7Fにそれぞれ形成された第1孔部74Fは、幅方向に重なるように構成されている。
幅方向に重なるように配置された第1孔部74Fには、同一の配力筋6が挿通されている。主鉄筋5Fは、第1孔部74Fに挿通された配力筋6Fよりも上側に配置されている。
第1孔部74Fに挿通された配力筋6Fは、主鉄筋5Fと結束されている。これにより、主鉄筋5Fと配力筋6Fとはメッシュを構成している。
The first hole portion 74F formed in each of the two arranged perforated steel materials 7F is configured to overlap in the width direction.
The same force distribution muscle 6 is inserted through the first hole portion 74F arranged so as to overlap in the width direction. The main reinforcing bar 5F is arranged above the force distribution bar 6F inserted through the first hole portion 74F.
The force distribution bar 6F inserted through the first hole portion 74F is bound to the main reinforcing bar 5F. As a result, the main reinforcing bar 5F and the force distribution bar 6F form a mesh.

コンクリート部8Fは、平板状に形成され、板面が長方形状に形成されている。コンクリート部8Fは、板面が上下方向を向く向きに配置されている。コンクリート部8Fは、主鉄筋5F、配力筋6F、孔あき鋼材7Fの第1板部71Fおよび孔あき鋼材7Fの下側のフランジ781を埋設している。コンクリート部のコンクリートは、第1孔部74Fの縁部と配力筋6Fとの隙間にも充填されている。
孔あき鋼材7Fの第2板部72Fおよび上側のフランジ782は、コンクリート部8Fに埋設されておらず、コンクリート部8Fよりも上側に突出している。
The concrete portion 8F is formed in a flat plate shape, and the plate surface is formed in a rectangular shape. The concrete portion 8F is arranged so that the plate surface faces in the vertical direction. In the concrete portion 8F, the main reinforcing bar 5F, the force distribution bar 6F, the first plate portion 71F of the perforated steel material 7F, and the lower flange 781 of the perforated steel material 7F are embedded. The concrete of the concrete portion is also filled in the gap between the edge portion of the first hole portion 74F and the force distribution bar 6F.
The second plate portion 72F and the upper flange 782 of the perforated steel material 7F are not embedded in the concrete portion 8F and protrude upward from the concrete portion 8F.

現場打ちコンクリートは、プレキャストコンクリート部2Fのコンクリート部8Fの上側に配筋された鉄筋と、プレキャストコンクリート部2Fのコンクリート部8Fの上側に打設された現場打ちコンクリートと、を有している。
現場打ちコンクリートの鉄筋は、要求される強度に応じて適宜配筋されている。
現場打ちコンクリートは、プレキャストコンクリート部2Fの上側に打設されると、孔あき鋼材7Fの第2板部72Fおよび上側のフランジ782を埋設している。
The cast-in-place concrete has a reinforcing bar arranged on the upper side of the concrete portion 8F of the precast concrete portion 2F and a cast-in-place concrete cast on the upper side of the concrete portion 8F of the precast concrete portion 2F.
The reinforcing bars of cast-in-place concrete are appropriately arranged according to the required strength.
When the cast-in-place concrete is cast on the upper side of the precast concrete portion 2F, the second plate portion 72F of the perforated steel material 7F and the upper flange 782 are embedded.

第6実施形態による鋼コンクリート複合構造によれば、梁部1Fの構造においても第1実施形態と同様の効果を奏する。 According to the steel-concrete composite structure according to the sixth embodiment, the same effect as that of the first embodiment is obtained in the structure of the beam portion 1F.

以上、本発明による鋼コンクリート複合構造および鋼コンクリート複合構造の施工方法の実施形態について説明したが、本発明は上記の実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。
例えば、上記の実施形態では、構造物の壁部1A〜1Eおよび梁部1Fに本発明の鋼コンクリート複合構造および鋼コンクリート複合構造を採用しているが、構造物の壁部1A〜1Eおよび梁部1F以外に、構造物の柱や床などの構造体に本発明の鋼コンクリート複合構造および鋼コンクリート複合構造を採用してもよい。
Although the embodiment of the steel-concrete composite structure and the construction method of the steel-concrete composite structure according to the present invention has been described above, the present invention is not limited to the above embodiment and can be appropriately changed without departing from the spirit thereof. Is.
For example, in the above embodiment, the steel-concrete composite structure and the steel-concrete composite structure of the present invention are adopted for the wall portions 1A to 1E and the beam portion 1F of the structure, but the wall portions 1A to 1E and the beam of the structure are adopted. In addition to the portion 1F, the steel-concrete composite structure and the steel-concrete composite structure of the present invention may be adopted for structures such as columns and floors of the structure.

また、上記の第5実施形態の孔あき鋼材7Eに、第2実施形態のフランジ76Bや第3実施形態のフランジ76C、第4実施形態の鋼棒77を設けてもよい。
また、孔あき鋼材7Eに第2実施形態のフランジ76Bおよび第3実施形態のフランジ76Cのいずれか一方と、第4実施形態の鋼棒77の両方を設けてもよい。
また、フランジ76Bが設けられた孔あき鋼材、フランジ76Cが設けられた孔あき鋼材、鋼棒77が設けられた孔あき鋼材のいずれか2つ以上を混在させるように設けてもよい。
また、鋼材77に代わって鋼板などの補強鋼材を第1孔部の縁部に沿って孔あき鋼材に接合してもよい。
Further, the perforated steel material 7E of the fifth embodiment may be provided with the flange 76B of the second embodiment, the flange 76C of the third embodiment, and the steel rod 77 of the fourth embodiment.
Further, both the flange 76B of the second embodiment and the flange 76C of the third embodiment and the steel rod 77 of the fourth embodiment may be provided on the perforated steel material 7E.
Further, any two or more of the perforated steel material provided with the flange 76B, the perforated steel material provided with the flange 76C, and the perforated steel material provided with the steel rod 77 may be provided in a mixed manner.
Further, instead of the steel material 77, a reinforcing steel material such as a steel plate may be joined to the perforated steel material along the edge of the first hole portion.

1A〜1E 壁部(構造体)
1F 梁部(構造体)
2,2B〜2D,2F プレキャストコンクリート部
3,3F 現場打ちコンクリート部
4 接合鋼板
5,5E,5F 主鉄筋
6,6E,6F 配力筋
7,7B〜7F 孔あき鋼材
8,8E,8F コンクリート部
71,71E,71F 第1板部
72,72E,72F 第2板部
73,73E,73F 鋼板部
74,74E,74F 第1孔部
75,75E 第2孔部
76B,76C,781 フランジ
77 鋼棒(補強鋼材)
1A-1E Wall (structure)
1F beam part (structure)
2,2B ~ 2D, 2F Precast concrete part 3,3F Cast-in-place concrete part 4 Joined steel plate 5,5E, 5F Main reinforcing bar 6,6E, 6F Force distribution bar 7,7B ~ 7F Perforated steel material 8,8E, 8F Concrete part
71, 71E, 71F 1st plate 72, 72E, 72F 2nd plate 73, 73E, 73F Steel plate 74, 74E, 74F 1st hole 75, 75E 2nd hole 76B, 76C, 781 Flange 77 Steel bar (Reinforcing steel)

Claims (6)

プレキャストコンクリート部と、前記プレキャストコンクリート部と接合される現場打ちコンクリート部と、を有する鋼コンクリート複合構造において、
前記プレキャストコンクリート部は、複数の主鉄筋と、
前記複数の主鉄筋と交差する複数の配力筋と、
前記複数の配力筋がそれぞれ挿通される複数の第1孔部が形成された孔あき鋼材と、
前記主鉄筋、前記配力筋および前記孔あき鋼材を一体に埋設するコンクリート部と、を有し、
前記孔あき鋼材は、前記複数の第1孔部が形成されて前記コンクリート部に埋設される第1板部と、前記第1板部と一体に形成され前記コンクリート部の外部に突出し前記現場打ちコンクリート部に埋設される第2板部と、を有し、
一対の前記プレキャストコンクリート部が互いの前記第2板部が突出している側を対向させるように配置され、
一対の前記プレキャストコンクリート部それぞれの前記第2板部が接合鋼板を介して接合されていて、
前記接合鋼板は、対向する前記第2板部それぞれの前記コンクリート部から突出する側の端部全体と接合され、
一対の前記プレキャストコンクリート部それぞれのコンクリート部の間に前記現場打ちコンクリート部が打設され、
前記接合鋼板は、前記現場打ちコンクリート部に埋設されていることを特徴とする鋼コンクリート複合構造。
In a steel-concrete composite structure having a precast concrete portion and a cast-in-place concrete portion joined to the precast concrete portion.
The precast concrete part has a plurality of main reinforcing bars and
With a plurality of force distribution bars intersecting with the plurality of main reinforcing bars,
A perforated steel material having a plurality of first holes through which the plurality of force distribution bars are inserted, and a perforated steel material.
It has a main reinforcing bar, a force distribution bar, and a concrete portion for integrally burying the perforated steel material.
The perforated steel material has a first plate portion in which the plurality of first hole portions are formed and embedded in the concrete portion, and the perforated steel material is integrally formed with the first plate portion and protrudes to the outside of the concrete portion to be cast on site. a second plate portion which is embedded in the concrete section, the possess,
A pair of the precast concrete portions are arranged so as to face each other so that the side on which the second plate portion protrudes faces each other.
The second plate portion of each of the pair of precast concrete portions is joined via a joined steel plate.
The joined steel plate is joined to the entire end portion of each of the second plate portions facing each other on the side protruding from the concrete portion.
The cast-in-place concrete part is placed between the concrete parts of each of the pair of precast concrete parts.
The joined steel plate is a steel-concrete composite structure characterized in that it is embedded in the cast-in-place concrete portion.
前記第2板部には、前記現場打ちコンクリート部の鉄筋が挿通される第2孔部が形成されていることを特徴とする請求項1に記載の鋼コンクリート複合構造。 The steel-concrete composite structure according to claim 1 , wherein a second hole portion through which a reinforcing bar of the cast-in-place concrete portion is inserted is formed in the second plate portion. 前記孔あき鋼材は、前記第1板部の端部に直交するように接合されたフランジを有し、
互いに接合された前記第1板部および前記フランジの全体の断面がT字形状であることを特徴とする請求項1または2に記載の鋼コンクリート複合構造。
The perforated steel material has a flange joined so as to be orthogonal to the end portion of the first plate portion.
The steel-concrete composite structure according to claim 1 or 2 , wherein the entire cross section of the first plate portion and the flange joined to each other has a T-shape.
前記孔あき鋼材は、前記第1板部の端部に直交するように接合されたフランジを有し、
互いに接合された前記第1板部および前記フランジの全体の断面がL字形状であることを特徴とする請求項1または2に記載の鋼コンクリート複合構造。
The perforated steel material has a flange joined so as to be orthogonal to the end portion of the first plate portion.
The steel-concrete composite structure according to claim 1 or 2 , wherein the entire cross section of the first plate portion and the flange joined to each other is L-shaped.
前記孔あき鋼材は、前記第1孔部の縁周の少なくとも一部を囲むように前記第1板部に接合された補強鋼材を有することを特徴とする請求項1乃至4のいずれか一項に記載の鋼コンクリート複合構造。 The perforated steel, any one of claims 1 to 4, characterized in that it has a reinforcing steel material bonded to the first plate portion so as to surround at least a part of the edge circumference of said first hole portion The steel-concrete composite structure described in. 間をあけて対向して配置される一対のプレキャストコンクリート部と、前記一対のプレキャストコンクリートの間に設けられ前記一対のプレキャストコンクリート部と接合される現場打ちコンクリート部と、を有する鋼コンクリート複合構造の構造体を構築するための鋼コンクリート複合構造の施工方法において、
前記一対のプレキャストコンクリート部を製作するプレキャストコンクリート部製作工程と、
前記プレキャストコンクリート部製作工程で製作された前記一対のプレキャストコンクリート部を前記構造体を構築する位置に設置するプレキャストコンクリート部設置工程と、
前記現場打ちコンクリート部を構築する現場打ちコンクリート部構築工程と、を有し、
前記プレキャストコンクリート部製作工程は、複数の主鉄筋を設置する主鉄筋設置工程と、
第1孔部が複数形成された孔あき鋼材を設置する孔あき鋼材設置工程と、
複数の配力筋をそれぞれ前記第1孔部に挿通して前記複数の主鉄筋と交差するように設置する配力筋設置工程と、
前記プレキャストコンクリート部のコンクリート部を打設し、前記主鉄筋、前記配力筋および前記孔あき鋼材を一体に埋設するコンクリート部打設工程と、を有し、
前記コンクリート部打設工程では、前記孔あき鋼材のうちの前記第1孔部が形成された側の第1板部を前記コンクリート部に埋設し、前記孔あき鋼材のうちの前記第1孔部が形成されていない側の第2板部を前記コンクリート部から突出させ、
前記プレキャストコンクリート部設置工程では、前記一対のプレキャストコンクリート部をそれぞれの前記第2板部が突出する側が互いに間をあけて対向し前記現場打ちコンクリート部が構築される側に向くように配置し、
対向する前記第2板部それぞれの前記コンクリート部から突出する側の端部全体に接合鋼板を接合し、前記接合鋼板を介して対向する前記第2板部どうしを接合し、
前記現場打ちコンクリート部構築工程では、前記第2板部および前記接合鋼板を前記現場打ちコンクリート部に埋設することを特徴とする鋼コンクリート複合構造の施工方法。
A steel-concrete composite structure having a pair of precast concrete portions arranged facing each other with a gap and a cast-in-place concrete portion provided between the pair of precast concretes and joined to the pair of precast concrete portions. In the construction method of steel-concrete composite structure for constructing a structure
The precast concrete part manufacturing process for manufacturing the pair of precast concrete parts, and
The precast concrete part installation step of installing the pair of precast concrete parts manufactured in the precast concrete part manufacturing process at the position where the structure is to be constructed, and the precast concrete part installation process.
It has a cast-in-place concrete part construction process for constructing the cast-in-place concrete part.
The precast concrete part manufacturing process includes a main reinforcing bar installation process in which a plurality of main reinforcing bars are installed.
The perforated steel material installation process for installing the perforated steel material in which a plurality of first holes are formed, and the perforated steel material installation process.
A force distribution bar installation step in which a plurality of force distribution bars are inserted into the first hole and installed so as to intersect the plurality of main reinforcing bars.
It has a concrete part placing step of placing a concrete part of the precast concrete part and integrally burying the main reinforcing bar, the force distribution bar and the perforated steel material.
In the concrete portion placing step, the first plate portion of the perforated steel material on the side where the first hole portion is formed is embedded in the concrete portion, and the first hole portion of the perforated steel material is embedded. The second plate portion on the side where is not formed is projected from the concrete portion,
In the precast concrete portion installation step, the pair of precast concrete portions are arranged so that the side on which the second plate portion protrudes faces each other with a gap between them and faces the side on which the cast-in-place concrete portion is constructed.
A joined steel plate is joined to the entire end portion of each of the two facing plate portions on the side protruding from the concrete portion, and the second plate portions facing each other are joined via the joined steel plate.
A method for constructing a steel-concrete composite structure, characterized in that the second plate portion and the joined steel plate are embedded in the cast-in-place concrete portion in the cast-in-place concrete portion construction step.
JP2017091390A 2017-05-01 2017-05-01 Construction method of steel-concrete composite structure and steel-concrete composite structure Active JP6983533B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017091390A JP6983533B2 (en) 2017-05-01 2017-05-01 Construction method of steel-concrete composite structure and steel-concrete composite structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017091390A JP6983533B2 (en) 2017-05-01 2017-05-01 Construction method of steel-concrete composite structure and steel-concrete composite structure

Publications (2)

Publication Number Publication Date
JP2018188851A JP2018188851A (en) 2018-11-29
JP6983533B2 true JP6983533B2 (en) 2021-12-17

Family

ID=64478239

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017091390A Active JP6983533B2 (en) 2017-05-01 2017-05-01 Construction method of steel-concrete composite structure and steel-concrete composite structure

Country Status (1)

Country Link
JP (1) JP6983533B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102204901B1 (en) * 2019-03-06 2021-01-19 (주)한울구조안전기술사사무소 Shear wall reinforced with steel plate
CN110397064B (en) * 2019-06-28 2024-03-19 天津大学 Combined annular tube jacket foundation structure and construction method thereof
CN110219388A (en) * 2019-06-29 2019-09-10 天津大学建筑设计研究院 A kind of more limb combined shear wallboards of built-in steel plate
CN111691548A (en) * 2020-07-21 2020-09-22 承德绿建建筑节能科技有限公司 Upper and lower layer connecting structure and method of prefabricated part
CN112502317B (en) * 2020-10-29 2024-11-08 福建金启点实业有限公司 A high-strength steel structure building and construction method
CN114837331B (en) * 2022-05-30 2024-11-29 河南城建学院 High-performance combined shear wall and construction method thereof
CN119777502B (en) * 2024-12-25 2026-01-06 中国建筑第四工程局有限公司 A steel lock plate connection node, a shear wall structure, a shear wall and its installation method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5459970A (en) * 1993-11-05 1995-10-24 Kim; Chin T. Concrete structures and methods for their manufacture
JPH08232337A (en) * 1995-02-28 1996-09-10 Taisei Corp Method for constructing composite half-PC plate and wall or floor slab
JPH0960188A (en) * 1995-08-24 1997-03-04 Suzue:Kk Precast concrete slab and bar arrangement method thereof
JP2009052283A (en) * 2007-08-27 2009-03-12 Ihi Corp Method and apparatus for connecting between steel member and concrete member
JP5279549B2 (en) * 2008-11-13 2013-09-04 株式会社Ihiインフラシステム Gibber device for joining steel members to concrete member, synthetic floor slab and steel-concrete structure provided with the gibber device

Also Published As

Publication number Publication date
JP2018188851A (en) 2018-11-29

Similar Documents

Publication Publication Date Title
JP6983533B2 (en) Construction method of steel-concrete composite structure and steel-concrete composite structure
KR101556545B1 (en) Method for constructing using a double wall Precast Concrete
KR101937680B1 (en) Prefabricated Precast Structure and Construction Method Thereof
KR101708760B1 (en) Construction method for precast concrete wall
KR100932468B1 (en) Centrifugal hollow PC columns and their construction methods using cast-in-place concrete or steel columns
KR101740919B1 (en) Precast concrete wall and manufacturing method of the wall
KR100903398B1 (en) Precast Fiber Reinforced Wire Mesh Slab
KR101175503B1 (en) Concrete Wall having Vertical Connection of Precast Concrete Wall Panel and Constructing Method
CN102449247A (en) Half precast floor plank, and slab construction method using same
JP2010203139A (en) Composite beam, building, and method for constructing the composite beam
KR101112195B1 (en) Steel-concrete composite crossbeam having wire mesh and construction method using the same
KR101570938B1 (en) Method for constructing dam using steel pipe pile and precast concrete block
JP5750246B2 (en) Composite beam, building, and composite beam construction method
KR20090098641A (en) Composite structure for batch strength reinforcement between bars
JP2018059397A (en) Large span concrete slab form and construction method using the same
JP7118507B2 (en) Steel reinforced concrete wall pillar building structure
JP7694135B2 (en) Connection structure and connection method
KR20180026286A (en) Grid precast concrete structure and constructing method thereof
KR101324884B1 (en) Hybrid building construction method combining dry type and wet type
KR101752285B1 (en) Hybrid beam with wide PSC lower flange and enlarged section upper flange and structure frame using the same
KR101685632B1 (en) Shear connector to increase strength and ductility
KR102180280B1 (en) Hollow Core Slab Joint Structure Using Reinforcement Member
CN118756812A (en) An assembled integral beam-slab integrated frame structure and installation method thereof
KR100456192B1 (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JP6232190B2 (en) Joint components, concrete placement methods, concrete structures

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170601

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170622

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200414

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20201016

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20201016

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210323

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210406

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210603

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211026

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211124

R150 Certificate of patent or registration of utility model

Ref document number: 6983533

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250