JP7022025B2 - Suction foundation and its installation method - Google Patents
[go: Go Back, main page]

JP7022025B2 - Suction foundation and its installation method - Google Patents

Suction foundation and its installation method Download PDF

Info

Publication number
JP7022025B2
JP7022025B2 JP2018139382A JP2018139382A JP7022025B2 JP 7022025 B2 JP7022025 B2 JP 7022025B2 JP 2018139382 A JP2018139382 A JP 2018139382A JP 2018139382 A JP2018139382 A JP 2018139382A JP 7022025 B2 JP7022025 B2 JP 7022025B2
Authority
JP
Japan
Prior art keywords
partition wall
suction foundation
suction
valve
water pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018139382A
Other languages
Japanese (ja)
Other versions
JP2020016073A (en
Inventor
雄一郎 木村
泰明 小野
武人 矢幡
武俊 岡村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kanadevia Corp
Original Assignee
Hitachi Zosen Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Zosen Corp filed Critical Hitachi Zosen Corp
Priority to JP2018139382A priority Critical patent/JP7022025B2/en
Publication of JP2020016073A publication Critical patent/JP2020016073A/en
Application granted granted Critical
Publication of JP7022025B2 publication Critical patent/JP7022025B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/10Energy storage using batteries

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Foundations (AREA)

Description

ここに開示された技術は、サクション基礎及びその設置方法に関する。 The techniques disclosed herein relate to suction foundations and their installation methods.

従来より、水中の地盤に設置されるサクション基礎が知られている。例えば、特許文献1には、天井部と周壁部とを有して底が開放された隔壁を備えたサクション基礎が開示されている。周壁部が水底地盤中に貫入されることにより、隔壁が地盤に支持される。隔壁には、躯体等の構造体が設置される。 Conventionally, suction foundations installed in underwater ground have been known. For example, Patent Document 1 discloses a suction foundation having a ceiling portion and a peripheral wall portion and having a partition wall having an open bottom. The partition wall is supported by the ground by penetrating the peripheral wall into the bottom ground. A structure such as a skeleton is installed on the partition wall.

特開2005-23730号公報Japanese Unexamined Patent Publication No. 2005-23730

前述のサクション基礎は、周壁部が貫入された地盤によって支持されている。この地盤が緩むと、地盤の支持力が低下し、サクション基礎の安定性も低下してしまう。 The above-mentioned suction foundation is supported by the ground in which the peripheral wall is intruded. When this ground becomes loose, the bearing capacity of the ground decreases and the stability of the suction foundation also decreases.

ここに開示された技術は、かかる点に鑑みてなされたものであり、その目的とするところは、サクション基礎の安定性を向上させることにある。 The technique disclosed herein has been made in view of this point, and its purpose is to improve the stability of the suction foundation.

ここに開示されたサクション基礎は、天井部と前記天井部に接続された周壁部とを有して底が開放されるように形成され、前記周壁部が水中の地盤に貫入される隔壁と、前記隔壁を貫通して前記隔壁の内部と外部とを連通させ、前記隔壁の内部の土粒子間の間隙水圧を解放する解放部とを備える。 The suction foundation disclosed herein has a ceiling portion and a peripheral wall portion connected to the ceiling portion, and is formed so that the bottom is open. It is provided with a release portion that penetrates the partition wall to communicate the inside and the outside of the partition wall and releases the pore water pressure between the soil particles inside the partition wall.

前記サクション基礎によれば、サクション基礎の安定性を向上させることができる。 According to the suction foundation, the stability of the suction foundation can be improved.

図1は、サクション基礎の模式図である。FIG. 1 is a schematic diagram of a suction foundation. 図2は、サクション基礎の底面図である。FIG. 2 is a bottom view of the suction foundation. 図3は、サクション基礎の設置方法の手順を示すフローチャートである。FIG. 3 is a flowchart showing the procedure of how to install the suction foundation. 図4は、ステップS1においてサクション基礎を沈設する前の状態を示す説明図である。FIG. 4 is an explanatory diagram showing a state before the suction foundation is sunk in step S1. 図5は、ステップS1においてサクション基礎を沈設した後の状態を示す説明図である。FIG. 5 is an explanatory diagram showing a state after the suction foundation is sunk in step S1. 図6は、変形例1に係るサクション基礎の模式図である。FIG. 6 is a schematic diagram of the suction foundation according to the modified example 1. 図7は、変形例2に係るサクション基礎の模式図である。FIG. 7 is a schematic diagram of the suction foundation according to the modified example 2. 図8は、変形例3に係るサクション基礎の模式図である。FIG. 8 is a schematic diagram of the suction foundation according to the modified example 3. 図9は、変形例4に係るサクション基礎の模式図である。FIG. 9 is a schematic diagram of the suction foundation according to the modified example 4.

以下、例示的な実施形態を図面に基づいて詳細に説明する。 Hereinafter, exemplary embodiments will be described in detail with reference to the drawings.

図1は、サクション基礎100の模式図である。図2は、サクション基礎100の底面図である。 FIG. 1 is a schematic diagram of a suction foundation 100. FIG. 2 is a bottom view of the suction foundation 100.

サクション基礎100は、水上又は水中に構造体を設置するための基礎であり、水中の地盤Gに沈設される。図1の例では、サクション基礎100は、風車40を洋上に設置するための基礎である。サクション基礎100は、風車40が設置される隔壁10と、隔壁10の内部の土粒子間の間隙水圧を解放する解放部30とを備えている。 The suction foundation 100 is a foundation for installing a structure on or under water, and is sunk in the ground G underwater. In the example of FIG. 1, the suction foundation 100 is a foundation for installing the wind turbine 40 at sea. The suction foundation 100 includes a partition wall 10 on which the wind turbine 40 is installed, and a release portion 30 that releases the pore water pressure between the soil particles inside the partition wall 10.

隔壁10は、天井が閉塞され且つ底が開放された容器状に形成されている。具体的には、隔壁10は、略円盤状の天井部11と、天井部11の周縁に接続された略円筒状の周壁部12とを有している。天井部11には、支柱15が設けられている。支柱15は、天井部11の中心Xに配置され、鉛直方向の上方に延びている。支柱15の上端は、隔壁10が地盤Gに沈設された状態において、水面よりも上方に位置している。支柱15に、風車40が設置されている。 The partition wall 10 is formed in the shape of a container in which the ceiling is closed and the bottom is open. Specifically, the partition wall 10 has a substantially disk-shaped ceiling portion 11 and a substantially cylindrical peripheral wall portion 12 connected to the peripheral edge of the ceiling portion 11. A support column 15 is provided on the ceiling portion 11. The support column 15 is arranged at the center X of the ceiling portion 11 and extends upward in the vertical direction. The upper end of the support column 15 is located above the water surface when the partition wall 10 is submerged in the ground G. A wind turbine 40 is installed on the support column 15.

隔壁10の内部、即ち、天井部11と周壁部12とによって囲まれた空間は、図2に示すように、3つの仕切壁部13によって3つの空間Pに区画されている。仕切壁部13は、天井部11の中心Xから半径方向に延びている。3つの仕切壁部13は、中心X周りの周方向に等間隔に配置されている。隔壁10(詳しくは、天井部11、周壁部12及び仕切壁部13)は、鋼板で形成されている。 As shown in FIG. 2, the space inside the partition wall 10, that is, the space surrounded by the ceiling portion 11 and the peripheral wall portion 12, is divided into three spaces P by the three partition wall portions 13. The partition wall portion 13 extends in the radial direction from the center X of the ceiling portion 11. The three partition wall portions 13 are arranged at equal intervals in the circumferential direction around the center X. The partition wall 10 (specifically, the ceiling portion 11, the peripheral wall portion 12, and the partition wall portion 13) is made of a steel plate.

周壁部12及び仕切壁部13は、地盤Gに貫入している。このとき、隔壁10の内部、即ち、空間Pには地盤Gを構成する土粒子が充填されている。ここで、「充填」とは、空間Pが土粒子で完全に満たされた状態だけでなく、空間Pにおいて土粒子の上方に水が残留した状態も含む意味である。地盤Gに設置されたサクション基礎100においては、周壁部12及び仕切壁部13に摩擦力が作用する。これにより、サクション基礎100は、地盤Gに強固に固定されている。それに加えて、サクション基礎100に外力が作用した場合には、隔壁10の内部に負圧が発生し、引き抜き抵抗が増加する。これにより、サクション基礎100の安定性が確保される。 The peripheral wall portion 12 and the partition wall portion 13 penetrate into the ground G. At this time, the inside of the partition wall 10, that is, the space P is filled with soil particles constituting the ground G. Here, "filling" means not only a state in which the space P is completely filled with soil particles, but also a state in which water remains above the soil particles in the space P. In the suction foundation 100 installed on the ground G, a frictional force acts on the peripheral wall portion 12 and the partition wall portion 13. As a result, the suction foundation 100 is firmly fixed to the ground G. In addition, when an external force acts on the suction foundation 100, a negative pressure is generated inside the partition wall 10, and the pull-out resistance increases. This ensures the stability of the suction foundation 100.

解放部30は、3本の排水管31と、各排水管31に設けられたバルブ32とを有している。解放部30は、空間Pに充填された土粒子間の間隙水圧を解放する。 The release unit 30 has three drain pipes 31 and a valve 32 provided in each drain pipe 31. The release unit 30 releases the pore water pressure between the soil particles filled in the space P.

排水管31は、隔壁10を貫通して隔壁10の内部と外部とを連通させる。詳しくは、排水管31は、空間Pを水面より上方の大気に連通させる。排水管31は、一端が隔壁10の内部、即ち、空間Pに開口し、他端が隔壁10の外部であって且つ水面より上方において開口する。排水管31は、3つの空間Pのそれぞれに設けられている。つまり、それぞれの空間Pは、個別の排水管31によって大気に開放される。排水管31は、支柱15に沿って設けられ、支柱15に支持されている。排水管31は、解放部の管の一例である。 The drainage pipe 31 penetrates the partition wall 10 to communicate the inside and the outside of the partition wall 10. Specifically, the drainage pipe 31 communicates the space P with the atmosphere above the water surface. One end of the drainage pipe 31 opens inside the partition wall 10, that is, the space P, and the other end opens outside the partition wall 10 and above the water surface. The drainage pipe 31 is provided in each of the three spaces P. That is, each space P is opened to the atmosphere by a separate drain pipe 31. The drainage pipe 31 is provided along the support column 15 and is supported by the support column 15. The drainage pipe 31 is an example of a pipe of the opening portion.

バルブ32は、隔壁10の内部と外部との連通及び遮断、即ち、排水管31の開通及び遮断を切り替える。バルブ32は、排水管31のうち水面よりも上方の部分に設置されている。 The valve 32 switches communication and shutoff between the inside and the outside of the partition wall 10, that is, opening and shutting off the drain pipe 31. The valve 32 is installed in a portion of the drain pipe 31 above the water surface.

尚、サクション基礎100は、図示を省略するが、隔壁10を沈設する際に隔壁10内の水を排水する排水機構をさらに有していてもよい。この排水機構は、3つの空間Pのそれぞれに連通する3本の排水管と、各排水管に設けられた排水ポンプとを有している。排水ポンプを作動させて、排水管を介して空間P内の水を排水することによって隔壁10の地盤Gへの貫入が促進される。 Although not shown, the suction foundation 100 may further have a drainage mechanism for draining the water in the partition wall 10 when the partition wall 10 is sunk. This drainage mechanism has three drainage pipes communicating with each of the three spaces P and a drainage pump provided in each drainage pipe. By operating the drainage pump and draining the water in the space P through the drainage pipe, the penetration of the partition wall 10 into the ground G is promoted.

風車40は、サクション基礎100に設置される構造体の一例である。風車40は、タワー41と、タワー41に設けられたロータ42とを有している。タワー41は、隔壁10の支柱15に設置されている。ロータ42は、タワー41の先端部に回転自在に設けられている。 The wind turbine 40 is an example of a structure installed on the suction foundation 100. The wind turbine 40 has a tower 41 and a rotor 42 provided in the tower 41. The tower 41 is installed on the support column 15 of the partition wall 10. The rotor 42 is rotatably provided at the tip of the tower 41.

続いて、サクション基礎100の設置方法について説明する。図3は、サクション基礎100の設置方法の手順を示すフローチャートである。図4は、ステップS1においてサクション基礎100を沈設する前の状態を示す説明図である。図5は、ステップS1においてサクション基礎100を沈設した後の状態を示す説明図である。 Subsequently, a method of installing the suction foundation 100 will be described. FIG. 3 is a flowchart showing the procedure of the installation method of the suction foundation 100. FIG. 4 is an explanatory diagram showing a state before the suction foundation 100 is sunk in step S1. FIG. 5 is an explanatory diagram showing a state after the suction foundation 100 is sunk in step S1.

まず、ステップS1において、図4に示すように、風車40が設置されていない状態のサクション基礎100が設置現場まで曳航される。その後、サクション基礎100の地盤Gへの沈設が開始される。詳しくは、サクション基礎100は、自重又はバラスト荷重によって海底に沈んでいく。周壁部12及び仕切壁部13の下端部は、サクション基礎100の自重又はバラスト荷重によって地盤Gに或る程度貫入する。このとき、バルブ32は、閉じている。 First, in step S1, as shown in FIG. 4, the suction foundation 100 in a state where the wind turbine 40 is not installed is towed to the installation site. After that, the subduction of the suction foundation 100 to the ground G is started. Specifically, the suction foundation 100 sinks to the seabed due to its own weight or ballast load. The lower end portions of the peripheral wall portion 12 and the partition wall portion 13 penetrate into the ground G to some extent by the own weight of the suction foundation 100 or the ballast load. At this time, the valve 32 is closed.

その後、排水機構の排水ポンプを作動させ、隔壁10の内側(空間P)の水が排水される。これにより、隔壁10にサクション荷重が作用し、周壁部12は、地盤Gにさらに貫入していく。図5に示すように、周壁部12が所定の深さ(例えば、天井部11が地盤Gに接する深さ)まで地盤Gに貫入すると、排水ポンプによる排水が停止される。ステップS1は、周壁部を水中の地盤に貫入させる工程の一例である。 After that, the drainage pump of the drainage mechanism is operated, and the water inside the partition wall 10 (space P) is drained. As a result, a suction load acts on the partition wall 10, and the peripheral wall portion 12 further penetrates into the ground G. As shown in FIG. 5, when the peripheral wall portion 12 penetrates into the ground G to a predetermined depth (for example, the depth at which the ceiling portion 11 is in contact with the ground G), drainage by the drainage pump is stopped. Step S1 is an example of a step of penetrating the peripheral wall portion into the underwater ground.

このように周壁部12及び仕切壁部13が地盤Gに貫入していくのに従って、隔壁10の内部、即ち、空間Pは、地盤Gを構成する土粒子によって下方から満たされていく。このとき、地盤Gより上方の水や土粒子間の間隙水は、排水ポンプによって排出されたり、隔壁10の下端から隔壁10の外部へ排出されていく。 As the peripheral wall portion 12 and the partition wall portion 13 penetrate into the ground G in this way, the inside of the partition wall 10, that is, the space P is filled from below by the soil particles constituting the ground G. At this time, the water above the ground G and the interstitial water between the soil particles are discharged by the drainage pump or discharged from the lower end of the partition wall 10 to the outside of the partition wall 10.

次に、ステップS2において、隔壁10に風車40が設置される。詳しくは、支柱15に風車40が設置される。ステップS2は、周壁部の貫入後の隔壁に構造体を設置する工程の一例である。 Next, in step S2, the wind turbine 40 is installed on the partition wall 10. Specifically, the wind turbine 40 is installed on the support column 15. Step S2 is an example of a step of installing the structure on the partition wall after the penetration of the peripheral wall portion.

風車40が設置されると、風車40を含む隔壁10の重量が大きくなる。これにより、隔壁10の内部の圧力は高くなり、隔壁10の内部の土粒子間の間隙水圧が高くなる。間隙水圧が高くなると、土粒子同士の摩擦力が低減し、地盤Gが緩んでしまう。その結果、地盤Gによる隔壁10の支持力が低下してしまう。ただし、隔壁10の内部において土粒子間の間隙水は、隔壁10の底、即ち、周壁部12の下端から排出され得る。そのため、隔壁10の内部の過剰間隙水圧(同じ水深における隔壁10の外部の土粒子間の間隙水圧からの増大分の水圧)はやがて低減される。しかしながら、地盤Gには、砂質土等からなる透水層Sだけでなく、粘性土等からなる不透水層Cが存在する場合がある。ステップS1において、周壁部12を地盤Gのうち不透水層Cに貫入させる場合がある。周壁部12が不透水層Cに貫入している場合には、不透水層Cよりも上方の部分の間隙水の排出が不透水層Cにより妨げられる。不透水層Cよりも上方の部分の間隙水は不透水層Cに浸透して、隔壁10の底から少しずつ排水される場合もあるが、隔壁10の内部の間隙水圧が高い状態が長い間継続することになる。 When the wind turbine 40 is installed, the weight of the partition wall 10 including the wind turbine 40 becomes large. As a result, the pressure inside the partition wall 10 becomes high, and the pore water pressure between the soil particles inside the partition wall 10 becomes high. When the pore water pressure becomes high, the frictional force between the soil particles decreases, and the ground G loosens. As a result, the bearing capacity of the partition wall 10 due to the ground G is reduced. However, the interstitial water between the soil particles inside the partition wall 10 can be discharged from the bottom of the partition wall 10, that is, the lower end of the peripheral wall portion 12. Therefore, the excess pore water pressure inside the partition wall 10 (the water pressure increased from the pore water pressure between the soil particles outside the partition wall 10 at the same water depth) is eventually reduced. However, in the ground G, not only the permeable layer S made of sandy soil or the like but also the impermeable layer C made of cohesive soil or the like may be present. In step S1, the peripheral wall portion 12 may penetrate into the impermeable layer C in the ground G. When the peripheral wall portion 12 penetrates into the impermeable layer C, the impermeable layer C hinders the discharge of the pore water in the portion above the impermeable layer C. Pore water in the portion above the impermeable layer C may permeate into the impermeable layer C and be gradually drained from the bottom of the partition wall 10, but the pore water pressure inside the partition wall 10 remains high for a long time. Will continue.

そこで、風車40の設置後に、ステップS3において、過剰間隙水圧の解放が実行される。ステップS3は、構造体の設置に起因して増大する、隔壁の内部の土粒子間の間隙水圧を解放する工程の一例である。 Therefore, after the installation of the wind turbine 40, the release of the excess pore water pressure is executed in step S3. Step S3 is an example of a step of releasing the pore water pressure between the soil particles inside the partition wall, which increases due to the installation of the structure.

詳しくは、作業者は、風車40の設置後にバルブ32を開ける。風車40の搭載により増加した過剰間隙水圧によって、空間Pの水が排水管31を介して成り行きで排出される。これにより、同じ水深における隔壁10の外部の間隙水圧と隔壁10の内部の間隙水圧との差が低減していく。やがて、排水管31のうち水面よりも上方に突出している部分の水頭と空間Pの土粒子の間隙水圧とのバランスが取れるところで、排水管31からの排水が停止される。作業者は、排水が停止した後、バルブ32を閉じる。これにより、サクション基礎100は図1に示すように設置され、サクション基礎100の設置が完了する。 Specifically, the operator opens the valve 32 after installing the wind turbine 40. Due to the excess pore water pressure increased by the mounting of the wind turbine 40, the water in the space P is discharged through the drain pipe 31 as a matter of course. As a result, the difference between the pore water pressure outside the partition wall 10 and the pore water pressure inside the partition wall 10 at the same water depth is reduced. Eventually, drainage from the drainage pipe 31 is stopped at a point where the water head of the portion of the drainage pipe 31 protruding above the water surface and the pore water pressure of the soil particles in the space P are balanced. The operator closes the valve 32 after the drainage is stopped. As a result, the suction foundation 100 is installed as shown in FIG. 1, and the installation of the suction foundation 100 is completed.

これにより、隔壁10の内部の土粒子間の過剰間隙水圧が早期に低減され、地盤Gによる隔壁10の支持力が早期に向上する。尚、周壁部12が不透水層Cに貫入していない場合であっても、隔壁10の内部の水が隔壁10の底からだけではなく解放部30を介しても排出されるので、隔壁10の内部の過剰間隙水圧が早期に低減され、地盤Gによる隔壁10の支持力が早期に向上する。 As a result, the excess pore water pressure between the soil particles inside the partition wall 10 is reduced at an early stage, and the bearing capacity of the partition wall 10 by the ground G is improved at an early stage. Even when the peripheral wall portion 12 does not penetrate into the impermeable layer C, the water inside the partition wall 10 is discharged not only from the bottom of the partition wall 10 but also through the release portion 30, so that the partition wall 10 is discharged. The excess pore water pressure inside the wall is reduced at an early stage, and the bearing capacity of the partition wall 10 by the ground G is improved at an early stage.

また、隔壁10の内部の過剰間隙水圧が低減した後にバルブ32を閉じることによって排水管31を介した隔壁10の内部と外部との連通が遮断される。前述の如く、サクション基礎100は、隔壁10の内部に発生する負圧によって外力に対する引き抜き抵抗を増加させる。排水管31を開通させたままにしておくと、負圧を発生させる機能が多少なりとも弱まってしまう。バルブ32を閉じることによって、隔壁10の閉塞性を高め、負圧の発生機能の低下を抑制することができる。ここでいう「閉塞性」とは、隔壁10の底が開放していることを踏まえた上での閉塞性であり、天井部11及び周壁部12による閉塞性である。 Further, by closing the valve 32 after the excess pore water pressure inside the partition wall 10 is reduced, the communication between the inside and the outside of the partition wall 10 via the drain pipe 31 is cut off. As described above, the suction foundation 100 increases the pull-out resistance against an external force due to the negative pressure generated inside the partition wall 10. If the drain pipe 31 is left open, the function of generating negative pressure is weakened to some extent. By closing the valve 32, the closing property of the partition wall 10 can be enhanced and the deterioration of the negative pressure generation function can be suppressed. The "obstructiveness" referred to here is the obstructiveness based on the fact that the bottom of the partition wall 10 is open, and is the obstructiveness due to the ceiling portion 11 and the peripheral wall portion 12.

尚、ステップS2とステップS3とは並行して行われてもよい。つまり、バルブ32を開けた状態で風車40を設置してもよい。風車40の設置により隔壁10の内部の間隙水圧が増大すると、その増加に応じて隔壁10内の水が排水管31を介して排出される。風車40の設置後にバルブ32が閉じられる。尚、バルブ32は、風車40の設置を開始するときよりも前、例えば、ステップS1の隔壁10の貫入時から開いていてもよい。 In addition, step S2 and step S3 may be performed in parallel. That is, the wind turbine 40 may be installed with the valve 32 open. When the pore water pressure inside the partition wall 10 increases due to the installation of the wind turbine 40, the water in the partition wall 10 is discharged through the drain pipe 31 according to the increase. The valve 32 is closed after the wind turbine 40 is installed. The valve 32 may be opened before the installation of the wind turbine 40 is started, for example, from the time when the partition wall 10 of step S1 is penetrated.

また、隔壁10の内部の過剰間隙水圧を解放した後にバルブ32を閉じず、排水管31を開通させたままにしておいてもよい。排水管31を開通させておくことによって、潮汐や地盤Gの圧密状態の経年変化等に起因する、隔壁10の内部の間隙水圧の増大を緩和することができる。例えば、潮位が低下した際には、隔壁10の内部の間隙水圧に比べて隔壁10の外部の間隙水圧が低くなる。その結果、隔壁10の内部の水が排水管31から排出され、隔壁10の内部と外部とでの間隙水圧の差が低減される。逆に、潮位が上昇した際には、隔壁10の内部の間隙水圧に比べて隔壁10の外部の間隙水圧が高くなる。その結果、排水管31内の水位が低下し、隔壁10の内部と外部とでの間隙水圧の差が低減される。尚、排水管31が開通していると、隔壁10の閉塞性が低下することになるが、排水管31の断面積は空間Pの断面積に比べて小さいので、隔壁10の閉塞性の低下はわずかである。つまり、排水管31が開通していることによる、隔壁10の負圧の発生機能の低下はそれほど大きくはない。 Further, the valve 32 may not be closed after the excess pore water pressure inside the partition wall 10 is released, and the drain pipe 31 may be left open. By opening the drainage pipe 31, it is possible to alleviate an increase in pore water pressure inside the partition wall 10 due to tides, secular changes in the consolidation state of the ground G, and the like. For example, when the tide level drops, the pore water pressure outside the partition wall 10 becomes lower than the pore water pressure inside the partition wall 10. As a result, the water inside the partition wall 10 is discharged from the drain pipe 31, and the difference in pore water pressure between the inside and the outside of the partition wall 10 is reduced. On the contrary, when the tide level rises, the pore water pressure outside the partition wall 10 becomes higher than the pore water pressure inside the partition wall 10. As a result, the water level in the drain pipe 31 is lowered, and the difference in pore water pressure between the inside and the outside of the partition wall 10 is reduced. If the drainage pipe 31 is open, the blockage of the partition wall 10 is lowered, but since the cross-sectional area of the drainage pipe 31 is smaller than the cross-sectional area of the space P, the blockage of the partition wall 10 is lowered. Is few. That is, the decrease in the negative pressure generation function of the partition wall 10 due to the opening of the drainage pipe 31 is not so large.

以上のように、サクション基礎100は、天井部11と天井部11に接続された周壁部12とを有して底が開放されるように形成され、周壁部12が水中の地盤Gに貫入される隔壁10と、隔壁10を貫通して隔壁10の内部と外部とを連通させ、隔壁10の内部の土粒子間の間隙水圧を解放する解放部30とを備える。 As described above, the suction foundation 100 is formed so as to have a ceiling portion 11 and a peripheral wall portion 12 connected to the ceiling portion 11 so that the bottom is opened, and the peripheral wall portion 12 penetrates into the underwater ground G. The partition wall 10 is provided with a partition wall 10 and a release portion 30 that penetrates the partition wall 10 to communicate the inside and the outside of the partition wall 10 and releases the pore water pressure between the soil particles inside the partition wall 10.

この構成によれば、隔壁10に風車40等の構造体が設置されることによって隔壁10の内部の間隙水圧が増大したとしても、増大した間隙水圧が解放部30によって早期に低減される。その結果、過剰間隙水圧による地盤Gの支持力の低下を早期に解消でき、サクション基礎100の安定性を早期に向上させることができる。 According to this configuration, even if the pore water pressure inside the partition wall 10 increases due to the installation of the structure such as the wind turbine 40 on the partition wall 10, the increased pore water pressure is reduced at an early stage by the release portion 30. As a result, the decrease in the bearing capacity of the ground G due to the excessive pore water pressure can be eliminated at an early stage, and the stability of the suction foundation 100 can be improved at an early stage.

また、解放部30は、隔壁10の内部と外部との連通及び遮断を切り替え可能なバルブ32を有する。 Further, the release portion 30 has a valve 32 capable of switching communication and disconnection between the inside and the outside of the partition wall 10.

この構成によれば、隔壁10の内部と外部との連通及び遮断をバルブ32によって切り替えることができる。バルブ32を開いて隔壁10の内部と外部とを解放部30を介して連通させると、潮汐等による隔壁10の内部の間隙水圧の増大を緩和することができるという利点がある。一方、バルブ32を閉じて隔壁10の内部と外部との解放部30を介した連通を遮断すると、隔壁10の閉塞性を向上させるという利点がある。バルブ32を設けることによって、いずれの利点を優先するかを選択することができるようになる。 According to this configuration, the communication and disconnection between the inside and the outside of the partition wall 10 can be switched by the valve 32. When the valve 32 is opened to allow the inside and the outside of the partition wall 10 to communicate with each other through the release portion 30, there is an advantage that the increase in the pore water pressure inside the partition wall 10 due to tide or the like can be alleviated. On the other hand, closing the valve 32 to block communication between the inside and the outside of the partition wall 10 via the release portion 30 has an advantage of improving the blockage property of the partition wall 10. By providing the valve 32, it becomes possible to select which advantage is prioritized.

さらに、解放部30は、一端が隔壁10の内部に開口し、他端が隔壁10の外部であって且つ水面より上方において開口する排水管31(管)を有し、バルブ32は、排水管31のうち水面よりも上方の部分に設けられている。 Further, the release portion 30 has a drainage pipe 31 (pipe) having one end opened inside the partition wall 10 and the other end open outside the partition wall 10 and above the water surface, and the valve 32 is a drainage pipe. It is provided in the portion of 31 above the water surface.

この構成によれば、バルブ32は、水面よりも上方の位置に設けられている。そのため、バルブ32の開閉を手動で行う場合に、その作業を水中で行う必要がないので、バルブ32の開閉の作業性が向上する。 According to this configuration, the valve 32 is provided at a position above the water surface. Therefore, when the valve 32 is manually opened and closed, it is not necessary to perform the work underwater, so that the workability of opening and closing the valve 32 is improved.

また、解放部30は、隔壁10に風車40(構造体)が設置されることに起因して隔壁10の内部に発生する過剰間隙水圧を解放する。 Further, the release portion 30 releases the excess pore water pressure generated inside the partition wall 10 due to the installation of the wind turbine 40 (structure) on the partition wall 10.

この構成によれば、解放部30は、隔壁10に風車40等の構造体を設置した後に隔壁10の内部に発生する過剰間隙水圧を解放することができる。つまり、隔壁10に風車40等の構造体を設置した後の地盤Gの支持力の低下を抑制することができる。 According to this configuration, the release portion 30 can release the excess pore water pressure generated inside the partition wall 10 after installing a structure such as a wind turbine 40 on the partition wall 10. That is, it is possible to suppress a decrease in the bearing capacity of the ground G after installing a structure such as a wind turbine 40 on the partition wall 10.

また、周壁部12は、地盤Gのうち不透水層Cに貫入する。 Further, the peripheral wall portion 12 penetrates into the impermeable layer C in the ground G.

この構成によれば、隔壁10の内部の水が隔壁10の底から排出されることが妨げられるので、解放部30によって隔壁10の内部の過剰間隙水圧を解放することが特に有効となる。 According to this configuration, since the water inside the partition wall 10 is prevented from being discharged from the bottom of the partition wall 10, it is particularly effective to release the excess pore water pressure inside the partition wall 10 by the release portion 30.

また、天井部11と天井部11に接続された周壁部12とを有して底が開放されるように形成された隔壁10を備えたサクション基礎100の設置方法は、周壁部12を水中の地盤Gに貫入させる工程と、周壁部12の貫入後の隔壁10に風車40(構造体)を設置する工程と、風車40の設置に起因して増大する、隔壁10の内部の土粒子間の間隙水圧を解放する工程とを含む。 Further, in a method of installing a suction foundation 100 having a ceiling portion 11 and a peripheral wall portion 12 connected to the ceiling portion 11 and having a partition wall 10 formed so that the bottom is open, the peripheral wall portion 12 is placed in water. Between the step of penetrating into the ground G, the step of installing the windmill 40 (structure) in the partition wall 10 after the penetration of the peripheral wall portion 12, and the soil particles inside the partition wall 10 that increase due to the installation of the windmill 40. It includes a step of releasing the pore water pressure.

この構成によれば、解放部30は、風車40等の構造体の設置に起因して隔壁10の内部に発生する過剰間隙水圧を早期に低減することができる。その結果、過剰間隙水圧による地盤Gの支持力の低下を早期に抑制でき、サクション基礎100の安定性を早期に向上させることができる。 According to this configuration, the release portion 30 can reduce the excess pore water pressure generated inside the partition wall 10 due to the installation of the structure such as the wind turbine 40 at an early stage. As a result, the decrease in the bearing capacity of the ground G due to the excessive pore water pressure can be suppressed at an early stage, and the stability of the suction foundation 100 can be improved at an early stage.

また、周壁部12を貫入させる工程では、周壁部12を地盤Gのうち不透水層Cに貫入させる。 Further, in the step of penetrating the peripheral wall portion 12, the peripheral wall portion 12 is penetrated into the impermeable layer C of the ground G.

この構成によれば、隔壁10の内部の水が隔壁10の底から排出されることが妨げられるので、解放部30によって隔壁10の内部の過剰間隙水圧を解放することが特に有効となる。 According to this configuration, since the water inside the partition wall 10 is prevented from being discharged from the bottom of the partition wall 10, it is particularly effective to release the excess pore water pressure inside the partition wall 10 by the release portion 30.

続いて、サクション基礎100の変形例について説明する。以下の説明では、サクション基礎100と同様の構成については同様の符号を付して説明を省略し、異なる部分を中心に説明する。 Subsequently, a modification of the suction foundation 100 will be described. In the following description, the same configuration as the suction basic 100 will be described with the same reference numerals, the description thereof will be omitted, and different parts will be mainly described.

〈変形例1〉
変形例1に係るサクション基礎200について説明する。図6は、変形例1に係るサクション基礎200の模式図である。サクション基礎200は、バルブ32の開閉を自動制御する点で、サクション基礎100と異なる。
<Modification example 1>
The suction foundation 200 according to the first modification will be described. FIG. 6 is a schematic diagram of the suction foundation 200 according to the modified example 1. The suction foundation 200 is different from the suction foundation 100 in that the opening and closing of the valve 32 is automatically controlled.

サクション基礎200の解放部230は、排水管31及びバルブ32に加えて、バルブ32を制御する制御部35をさらに有している。制御部35は、サクション基礎200の設置時にバルブ32の開閉を制御する。 The release unit 230 of the suction foundation 200 further has a control unit 35 for controlling the valve 32 in addition to the drain pipe 31 and the valve 32. The control unit 35 controls the opening and closing of the valve 32 when the suction foundation 200 is installed.

サクション基礎200は、前述の図3のフローチャートの手順で設置される。ステップS1,S2までの処理は、サクション基礎100の場合と同様である。 The suction foundation 200 is installed according to the procedure shown in the flowchart of FIG. 3 described above. The processes up to steps S1 and S2 are the same as in the case of the suction basis 100.

作業者は、ステップS3において、風車40の設置後に制御部35を作動させる。制御部35は、バルブ32を開ける。風車40の設置により増加した過剰間隙水圧によって、空間Pの水が排水管31を介して成り行きで排出される。これにより、同じ水深における隔壁10の外部の間隙水圧と隔壁10の内部の間隙水圧との差が低減していく。やがて、排水管31のうち水面よりも上方に突出している部分の水頭と空間Pの土粒子の間隙水圧とのバランスが取れるところで、排水管31からの排水が停止される。制御部35は、この水頭と間隙水圧とがバランスすると想定される時間だけ待機した後、バルブ32を閉じる。制御部35は、3つのバルブ32を同様に且つ並行して制御する。 In step S3, the operator operates the control unit 35 after installing the wind turbine 40. The control unit 35 opens the valve 32. Due to the excess pore water pressure increased by the installation of the wind turbine 40, the water in the space P is discharged through the drain pipe 31 as a matter of course. As a result, the difference between the pore water pressure outside the partition wall 10 and the pore water pressure inside the partition wall 10 at the same water depth is reduced. Eventually, drainage from the drainage pipe 31 is stopped at a point where the water head of the portion of the drainage pipe 31 protruding above the water surface and the pore water pressure of the soil particles in the space P are balanced. The control unit 35 waits for a time expected to balance the head and the pore water pressure, and then closes the valve 32. The control unit 35 controls the three valves 32 in the same manner and in parallel.

これにより、隔壁10の内部の土粒子間の過剰間隙水圧が早期に低減され、地盤Gによる隔壁10の支持力が早期に向上する。また、隔壁10の内部の過剰間隙水圧が低減した後にバルブ32を閉じることによって隔壁10の閉塞性を高め、負圧の発生機能の低下を抑制することができる。 As a result, the excess pore water pressure between the soil particles inside the partition wall 10 is reduced at an early stage, and the bearing capacity of the partition wall 10 by the ground G is improved at an early stage. Further, by closing the valve 32 after the excess pore water pressure inside the partition wall 10 is reduced, the closing property of the partition wall 10 can be enhanced and the deterioration of the negative pressure generation function can be suppressed.

尚、ステップS2とステップS3とは並行して行われてもよい。つまり、バルブ32を開けた状態で風車40を設置してもよい。尚、バルブ32は、風車40の設置を開始するときよりも前、例えば、ステップS1の隔壁10の貫入時から開いていてもよい。 In addition, step S2 and step S3 may be performed in parallel. That is, the wind turbine 40 may be installed with the valve 32 open. The valve 32 may be opened before the installation of the wind turbine 40 is started, for example, from the time when the partition wall 10 of step S1 is penetrated.

〈変形例2〉
図7は、変形例2に係るサクション基礎300の模式図である。サクション基礎300は、バルブ32の制御内容が、変形例1に係るサクション基礎200と異なる。
<Modification 2>
FIG. 7 is a schematic diagram of the suction foundation 300 according to the modified example 2. The control content of the valve 32 of the suction foundation 300 is different from that of the suction foundation 200 according to the first modification.

サクション基礎300の解放部330は、排水管31、バルブ32及び制御部35に加えて、波高を検出する波高センサ36と、風速を検出する風速センサ37とをさらに有している。制御部35には、波高センサ36及び風速センサ37の検出結果が入力されている。制御部35は、サクション基礎300の設置時にバルブ32の開閉を制御すると共に、サクション基礎300の設置後においても外部環境の変化に応じてバルブ32の開閉を制御する。 The release unit 330 of the suction foundation 300 further includes a wave height sensor 36 for detecting the wave height and a wind speed sensor 37 for detecting the wind speed, in addition to the drain pipe 31, the valve 32, and the control unit 35. The detection results of the wave height sensor 36 and the wind speed sensor 37 are input to the control unit 35. The control unit 35 controls the opening and closing of the valve 32 when the suction foundation 300 is installed, and also controls the opening and closing of the valve 32 according to changes in the external environment even after the suction foundation 300 is installed.

サクション基礎300は、前述の図3のフローチャートの手順で設置される。ステップS1,S2までの処理は、サクション基礎100の場合と同様である。 The suction foundation 300 is installed according to the procedure shown in the flowchart of FIG. 3 described above. The processes up to steps S1 and S2 are the same as in the case of the suction basis 100.

制御部35は、変形例2と同様に、ステップS3において風車40の設置後にバルブ32を開ける。ただし、隔壁10の内部の過剰間隙水圧を解放した後は、制御部35は、波高センサ36及び風速センサ37の検出結果に基づいてバルブ32の開閉を制御する。詳しくは、制御部35は、波高センサ36により検出される波高が所定の波高閾値よりも高い場合、又は、風速センサ37により検出される風速が所定の風速閾値よりも大きい場合には、バルブ32を閉じる。一方、制御部35は、波高センサ36により検出される波高が所定の波高閾値以下で且つ、風速センサ37により検出される風速が所定の風速閾値以下の場合には、バルブ32を開いたままにする。制御部35は、3つのバルブ32を同様に且つ並行して制御する。 The control unit 35 opens the valve 32 after installing the wind turbine 40 in step S3, as in the modification 2. However, after releasing the excess pore water pressure inside the partition wall 10, the control unit 35 controls the opening and closing of the valve 32 based on the detection results of the wave height sensor 36 and the wind speed sensor 37. Specifically, the control unit 35 controls the valve 32 when the wave height detected by the wave height sensor 36 is higher than the predetermined wave height threshold value or when the wind speed detected by the wind speed sensor 37 is larger than the predetermined wind speed threshold value. Close. On the other hand, when the wave height detected by the wave height sensor 36 is equal to or less than the predetermined wave height threshold value and the wind speed detected by the wind speed sensor 37 is equal to or less than the predetermined wind speed threshold value, the control unit 35 keeps the valve 32 open. do. The control unit 35 controls the three valves 32 in the same manner and in parallel.

波高又は風速が大きい場合には、サクション基礎300に作用する外力が大きくなる。そのような場合には、制御部35はバルブ32を閉じることによって、隔壁10の内部と外部との解放部330を介した連通を遮断する。これにより隔壁10の閉塞性を高め、外力へのサクション基礎300の耐性を向上させることができる。一方、波高及び風速が小さい場合には、サクション基礎300に作用する外力が小さいので、バルブ32を開けておくことによって、潮汐や地盤Gの圧密状態の経年変化等に起因する、隔壁10の内部の間隙水圧の増大を緩和することができる。 When the wave height or the wind speed is large, the external force acting on the suction foundation 300 becomes large. In such a case, the control unit 35 closes the valve 32 to block communication between the inside and the outside of the partition wall 10 via the release unit 330. As a result, the blockage of the partition wall 10 can be enhanced, and the resistance of the suction foundation 300 to an external force can be improved. On the other hand, when the wave height and the wind speed are small, the external force acting on the suction foundation 300 is small. Therefore, by opening the valve 32, the inside of the partition wall 10 is caused by the tide and the secular change of the consolidation state of the ground G. The increase in pore water pressure can be alleviated.

尚、ステップS2とステップS3とは並行して行われてもよい。つまり、バルブ32を開けた状態で風車40を設置してもよい。尚、バルブ32は、風車40の設置を開始するときよりも前、例えば、ステップS1の隔壁10の貫入時から開いていてもよい。 In addition, step S2 and step S3 may be performed in parallel. That is, the wind turbine 40 may be installed with the valve 32 open. The valve 32 may be opened before the installation of the wind turbine 40 is started, for example, from the time when the partition wall 10 of step S1 is penetrated.

〈変形例3〉
図8は、変形例3に係るサクション基礎400の模式図である。サクション基礎400は、バルブ32を有していない点で、サクション基礎100と異なる。
<Modification 3>
FIG. 8 is a schematic diagram of the suction foundation 400 according to the modified example 3. The suction foundation 400 differs from the suction foundation 100 in that it does not have a valve 32.

解放部430は、排水管31を有し、バルブ32を有していない。つまり、解放部430の排水管31は、常時、開放されている。 The release portion 430 has a drain pipe 31 and does not have a valve 32. That is, the drain pipe 31 of the release portion 430 is always open.

サクション基礎400は、前述の図3のフローチャートの手順で設置される。ステップS1の処理は、サクション基礎100の場合と同様である。 The suction foundation 400 is installed according to the procedure shown in the flowchart of FIG. 3 described above. The processing in step S1 is the same as in the case of the suction basis 100.

そして、ステップS2の風車40の設置とステップS3の過剰間隙水圧の解放とが常に並行して行われる。さらに、風車40の設置後においては、排水管31は開放されたままである。排水管31を開通させておくことによって、潮汐や地盤Gの圧密状態の経年変化等に起因する、隔壁10の内部の間隙水圧の増大を緩和することができる。 Then, the installation of the wind turbine 40 in step S2 and the release of the excess pore water pressure in step S3 are always performed in parallel. Further, after the installation of the wind turbine 40, the drain pipe 31 remains open. By opening the drainage pipe 31, it is possible to alleviate an increase in pore water pressure inside the partition wall 10 due to tides, secular changes in the consolidation state of the ground G, and the like.

〈変形例4〉
図9は、変形例4に係るサクション基礎500の模式図である。サクション基礎500は、解放部530が排水ポンプ33を有する点で、サクション基礎100と異なる。ここでは、サクション基礎300から変形した構成について説明する。しかし、変形例4のベースとなる構成は、サクション基礎300に限られず、サクション基礎100,200,400等であってもよい。
<Modification example 4>
FIG. 9 is a schematic diagram of the suction foundation 500 according to the modified example 4. The suction foundation 500 differs from the suction foundation 100 in that the release portion 530 has a drainage pump 33. Here, a configuration modified from the suction foundation 300 will be described. However, the configuration that is the base of the modified example 4 is not limited to the suction foundation 300, and may be the suction foundation 100, 200, 400, or the like.

サクション基礎500の解放部530は、排水管31、バルブ32、制御部35、波高センサ36及び風速センサ37に加えて、隔壁10の内部の間隙水を排出する排水ポンプ33と、各排水管31に設けられた圧力センサ34と、隔壁10の傾きを検出する傾きセンサ38とをさらに有している。制御部35には、圧力センサ34、傾きセンサ38、波高センサ36及び風速センサ37の検出結果が入力されている。排水ポンプ33は、空間Pの水を排水管31を介して排水する。排水ポンプ33は、排水管31のうち水面よりも上方の部分に設置されている。圧力センサ34は、排水管31内の水圧を検出する。 The release portion 530 of the suction foundation 500 includes a drain pipe 31, a valve 32, a control unit 35, a wave height sensor 36, and a wind speed sensor 37, as well as a drain pump 33 for discharging the pore water inside the partition wall 10, and each drain pipe 31. Further has a pressure sensor 34 provided in the above and an inclination sensor 38 for detecting the inclination of the partition wall 10. The detection results of the pressure sensor 34, the tilt sensor 38, the wave height sensor 36, and the wind speed sensor 37 are input to the control unit 35. The drainage pump 33 drains the water in the space P through the drainage pipe 31. The drainage pump 33 is installed in a portion of the drainage pipe 31 above the water surface. The pressure sensor 34 detects the water pressure in the drain pipe 31.

サクション基礎500は、前述の図3のフローチャートの手順で設置される。ステップS1,S2までの処理は、サクション基礎100の場合と同様である。 The suction foundation 500 is installed according to the procedure shown in the flowchart of FIG. 3 described above. The processes up to steps S1 and S2 are the same as in the case of the suction basis 100.

制御部35は、ステップS3においてバルブ32を開けると共に圧力センサ34の検出結果に基づいて排水ポンプ33を作動させることによって、空間Pの水を排出する。制御部35は、同じ水深における隔壁10の外部の間隙水圧と隔壁10の内部の間隙水圧との差が低減するように水を排出する。具体的には、圧力センサ34の検出圧力と、圧力センサ34と隔壁10(例えば、排水管31の下端)との高低差とから、隔壁10の内部の間隙水圧がわかる。圧力センサ34の検出圧力が目標の間隙水圧の範囲に対応する圧力範囲内に入るように、制御部35は、排水ポンプ33を制御する。圧力センサ34の検出圧力が目標の圧力範囲内に入ると、制御部35は、排水ポンプ33を停止すると共にバルブ32を閉じる。制御部35は、3組のバルブ32及び排水ポンプ33に対するこのような制御を並行して行う。 The control unit 35 discharges the water in the space P by opening the valve 32 in step S3 and operating the drainage pump 33 based on the detection result of the pressure sensor 34. The control unit 35 discharges water so that the difference between the pore water pressure outside the partition wall 10 and the pore water pressure inside the partition wall 10 at the same water depth is reduced. Specifically, the pore water pressure inside the partition wall 10 can be known from the detected pressure of the pressure sensor 34 and the height difference between the pressure sensor 34 and the partition wall 10 (for example, the lower end of the drain pipe 31). The control unit 35 controls the drainage pump 33 so that the detected pressure of the pressure sensor 34 falls within the pressure range corresponding to the range of the target pore water pressure. When the detected pressure of the pressure sensor 34 falls within the target pressure range, the control unit 35 stops the drainage pump 33 and closes the valve 32. The control unit 35 performs such control for the three sets of valves 32 and the drainage pump 33 in parallel.

サクション基礎500は、隔壁10の内部の水を排水ポンプ33によって強制的に排出するので、隔壁10の内部の水を成り行きで排出する場合と比較して、隔壁10の内部の過剰間隙水圧を早期に低減することができる。 Since the suction foundation 500 forcibly discharges the water inside the partition wall 10 by the drainage pump 33, the excess pore water pressure inside the partition wall 10 is set earlier than in the case where the water inside the partition wall 10 is discharged as it is. Can be reduced to.

尚、ステップS2とステップS3とは並行して行われてもよい。つまり、バルブ32を開け且つ排水ポンプ33で排水を行いつつ風車40を設置してもよい。尚、バルブ32は、風車40の設置を開始するときよりも前、例えば、ステップS1の隔壁10の貫入時から開いていてもよい。 In addition, step S2 and step S3 may be performed in parallel. That is, the wind turbine 40 may be installed while opening the valve 32 and draining water with the drainage pump 33. The valve 32 may be opened before the installation of the wind turbine 40 is started, for example, from the time when the partition wall 10 of step S1 is penetrated.

それに加えて、制御部35は、過剰間隙水圧を解放する際に、隔壁10の傾きを調節してもよい。隔壁10の内部の水を排出すると、間隙水圧が低下するだけでなく、周壁部12が地盤Gにさらに貫入し得る。制御部35は、傾きセンサ38の検出結果に基づいて、3つの排水ポンプ33の排水量を調節する。詳しくは、制御部35は、傾きセンサ38の検出結果に基づいて、天井部11のうち相対的に高い部分に対応する空間Pの排水ポンプ33の排水量を相対的に多くする。このとき、制御部35は、3つの圧力センサ34の検出圧力が前述の圧力範囲に収まる範囲内で3つの排水ポンプ33の排水量を調節する。これにより、隔壁10の内部の過剰間隙水圧を低減しつつ、隔壁10の傾きを調節することができる。 In addition, the control unit 35 may adjust the inclination of the partition wall 10 when releasing the excess pore water pressure. When the water inside the partition wall 10 is discharged, not only the pore water pressure decreases, but also the peripheral wall portion 12 can further penetrate into the ground G. The control unit 35 adjusts the drainage amount of the three drainage pumps 33 based on the detection result of the tilt sensor 38. Specifically, the control unit 35 relatively increases the amount of drainage of the drainage pump 33 in the space P corresponding to the relatively high portion of the ceiling portion 11 based on the detection result of the tilt sensor 38. At this time, the control unit 35 adjusts the drainage amount of the three drainage pumps 33 within the range in which the detected pressures of the three pressure sensors 34 fall within the above-mentioned pressure range. Thereby, the inclination of the partition wall 10 can be adjusted while reducing the excess pore water pressure inside the partition wall 10.

さらに、制御部35は、サクション基礎500の設置後の通常の運用時に、波高センサ36及び風速センサ37の検出結果に基づいてバルブ32及び排水ポンプ33を制御してもよい。詳しくは、制御部35は、波高センサ36により検出される波高が所定の波高閾値よりも高い場合、又は、風速センサ37により検出される風速が所定の風速閾値よりも大きい場合には、バルブ32を開くと共に排水ポンプ33を作動させる。制御部35は、圧力センサ34による検出圧力が所定の圧力以下になるまで排水ポンプ33による排水を継続する。この所定の圧力は、前述の過剰間隙水圧の解放における圧力範囲よりも小さい値である。排水ポンプ33の停止後は、バルブ32が閉じられる。一方、制御部35は、波高センサ36により検出される波高が所定の波高閾値以下で且つ、風速センサ37により検出される風速が所定の風速閾値以下の場合には、バルブ32を閉じ、排水ポンプ33を停止させたままにする。制御部35は、3つのバルブ32及び排水ポンプ33を同様に且つ並行して制御する。 Further, the control unit 35 may control the valve 32 and the drainage pump 33 based on the detection results of the wave height sensor 36 and the wind speed sensor 37 during normal operation after the suction base 500 is installed. Specifically, the control unit 35 controls the valve 32 when the wave height detected by the wave height sensor 36 is higher than the predetermined wave height threshold value or when the wind speed detected by the wind speed sensor 37 is larger than the predetermined wind speed threshold value. And operate the drainage pump 33. The control unit 35 continues draining by the drainage pump 33 until the pressure detected by the pressure sensor 34 becomes equal to or lower than a predetermined pressure. This predetermined pressure is a value smaller than the pressure range in the release of the above-mentioned excess pore water pressure. After the drainage pump 33 is stopped, the valve 32 is closed. On the other hand, when the wave height detected by the wave height sensor 36 is equal to or less than the predetermined wave height threshold value and the wind speed detected by the wind speed sensor 37 is equal to or less than the predetermined wind speed threshold value, the control unit 35 closes the valve 32 and drains the pump. Keep 33 stopped. The control unit 35 controls the three valves 32 and the drainage pump 33 in the same manner and in parallel.

波高又は風速が大きい場合には、サクション基礎500に作用する外力が大きくなる。そのような場合には、制御部35はバルブ32を開け、排水ポンプ33によって隔壁10の内部の水を排出する。これによって、隔壁10の内部の間隙水圧が低下し、地盤Gの支持力が増強される。その結果、外力へのサクション基礎500の耐性を向上させることができる。一方、波高及び風速が小さい場合には、サクション基礎300に作用する外力が小さいので、バルブ32を開けておくことによって、潮汐や地盤Gの圧密状態の経年変化等に起因する、隔壁10の内部の間隙水圧の増大を緩和することができる。 When the wave height or the wind speed is large, the external force acting on the suction foundation 500 becomes large. In such a case, the control unit 35 opens the valve 32 and drains the water inside the partition wall 10 by the drainage pump 33. As a result, the pore water pressure inside the partition wall 10 is reduced, and the bearing capacity of the ground G is enhanced. As a result, the resistance of the suction foundation 500 to an external force can be improved. On the other hand, when the wave height and the wind speed are small, the external force acting on the suction foundation 300 is small. Therefore, by opening the valve 32, the inside of the partition wall 10 is caused by the tide and the secular change of the consolidation state of the ground G. The increase in pore water pressure can be alleviated.

このように、サクション基礎500の解放部530は、隔壁10の内部の間隙水を排出する排水ポンプ33を有する。 As described above, the release portion 530 of the suction foundation 500 has a drainage pump 33 for draining the interstitial water inside the partition wall 10.

この構成によれば、隔壁10の内部の水を成り行きで排水する場合と比べて、早期に排水することができる。その結果、過剰間隙水圧による地盤Gの支持力の低下をより早期に抑制でき、サクション基礎100の安定性をより早期に向上させることができる。 According to this configuration, the water inside the partition wall 10 can be drained earlier than in the case of draining the water inside. As a result, the decrease in the bearing capacity of the ground G due to the excessive pore water pressure can be suppressed earlier, and the stability of the suction foundation 100 can be improved earlier.

尚、サクション基礎500において、傾き制御及び外部環境によるバルブ32及び排水ポンプ33の制御は省略してもよい。 In the suction foundation 500, tilt control and control of the valve 32 and the drainage pump 33 by the external environment may be omitted.

また、制御部35は、圧力センサ34の検出結果に基づいて排水ポンプ33を制御しているが、これに限られない。例えば、解放部530は、目標とする隔壁10の内部の間隙水圧に対応する揚程を有する排水ポンプ33を採用し、圧力センサ34を省略してもよい。その場合、制御部35は、風車40の設置後に過剰間隙水圧を解放する際には、排水ポンプ33の排水能力で排出できるだけの水を排出させるようにしてもよい。排水ポンプ33が可能な量の水を排出したときには、隔壁10の内部の間隙水圧は、目標とする値となる。 Further, the control unit 35 controls the drainage pump 33 based on the detection result of the pressure sensor 34, but the control unit 35 is not limited to this. For example, the release portion 530 may employ a drainage pump 33 having a lift corresponding to the pore water pressure inside the target partition wall 10, and the pressure sensor 34 may be omitted. In that case, when the excess pore water pressure is released after the wind turbine 40 is installed, the control unit 35 may discharge as much water as possible by the drainage capacity of the drainage pump 33. When the drainage pump 33 discharges a possible amount of water, the pore water pressure inside the partition wall 10 becomes a target value.

《その他の実施形態》
以上のように、本出願において開示する技術の例示として、前記実施形態を説明した。しかしながら、本開示における技術は、これに限定されず、適宜、変更、置き換え、付加、省略などを行った実施の形態にも適用可能である。また、前記実施形態で説明した各構成要素を組み合わせて、新たな実施の形態とすることも可能である。また、添付図面および詳細な説明に記載された構成要素の中には、課題解決のために必須な構成要素だけでなく、前記技術を例示するために、課題解決のためには必須でない構成要素も含まれ得る。そのため、それらの必須ではない構成要素が添付図面や詳細な説明に記載されていることをもって、直ちに、それらの必須ではない構成要素が必須であるとの認定をするべきではない。
<< Other Embodiments >>
As described above, the above-described embodiment has been described as an example of the technology disclosed in the present application. However, the technique in the present disclosure is not limited to this, and can be applied to embodiments in which changes, replacements, additions, omissions, etc. are made as appropriate. It is also possible to combine the components described in the above embodiment to form a new embodiment. Further, among the components described in the attached drawings and the detailed description, not only the components essential for solving the problem but also the components not essential for solving the problem in order to exemplify the above-mentioned technology. Can also be included. Therefore, the fact that those non-essential components are described in the accompanying drawings or detailed description should not immediately determine that those non-essential components are essential.

例えば、前記実施形態について、以下のような構成としてもよい。 For example, the embodiment may have the following configuration.

隔壁10の形状は、略円筒状に限られるものではない。隔壁10は、天井部及び周壁部を有し且つ底を有さない形状であれば、任意の形状に形成することができる。例えば、隔壁10は、断面が略四角形や略五角形等の角筒状に形成されていてもよい。また、隔壁10は、天井部が湾曲したドーム状に形成されていてもよい。 The shape of the partition wall 10 is not limited to a substantially cylindrical shape. The partition wall 10 can be formed into any shape as long as it has a ceiling portion and a peripheral wall portion and does not have a bottom. For example, the partition wall 10 may be formed in the shape of a square cylinder having a substantially quadrangular cross section or a substantially pentagonal cross section. Further, the partition wall 10 may be formed in a dome shape having a curved ceiling portion.

また、隔壁10の内部は、仕切壁部13によって複数の空間に仕切られているが、仕切壁部13が省略されてもよい。すなわち、隔壁10の内部には、単一の空間が形成されていてもよい。 Further, although the inside of the partition wall 10 is partitioned into a plurality of spaces by the partition wall portion 13, the partition wall portion 13 may be omitted. That is, a single space may be formed inside the partition wall 10.

隔壁10には、支柱15が設けられていなくてもよい。 The partition wall 10 may not be provided with the support column 15.

さらに、サクション基礎100に設置される構造体は、風車40に限られるものではない。構造体は、風況観測塔又はケーソン等であってもよい。 Further, the structure installed on the suction foundation 100 is not limited to the wind turbine 40. The structure may be a wind condition observation tower, a caisson, or the like.

隔壁10の内部と外部との連通は、排水管31以外の構成で実現されてもよい。例えば、隔壁10に形成された貫通孔によって、隔壁10の内部と外部との連通が実現されてもよい。 Communication between the inside and the outside of the partition wall 10 may be realized by a configuration other than the drainage pipe 31. For example, a through hole formed in the partition wall 10 may realize communication between the inside and the outside of the partition wall 10.

排水管31は、隔壁10の内部の空間Pごとに1つ設けられているが、空間Pごとに複数設けられていてもよい。また、排水管31の上端は、水面よりも上方に位置しているが、水面よりも下方に位置していてもよい。また、排水管31は、天井部11を貫通しているが、周壁部12を貫通していてもよい。 Although one drainage pipe 31 is provided for each space P inside the partition wall 10, a plurality of drainage pipes 31 may be provided for each space P. Further, although the upper end of the drain pipe 31 is located above the water surface, it may be located below the water surface. Further, although the drainage pipe 31 penetrates the ceiling portion 11, it may penetrate the peripheral wall portion 12.

バルブ32及び/又は排水ポンプ33が設けられている場合には、バルブ32及び/又は排水ポンプ33は、排水管31のうち水面よりも下方の部分に設けられていてもよい。 When the valve 32 and / or the drainage pump 33 is provided, the valve 32 and / or the drainage pump 33 may be provided in a portion of the drainage pipe 31 below the water surface.

以上説明したように、ここに開示された技術は、サクション基礎及びその設置方法について有用である。 As described above, the techniques disclosed herein are useful for suction foundations and their installation methods.

100,200,300,400,500 サクション基礎
10 隔壁
11 天井部
12 周壁部
30,230,330,430,530 解放部
31 排水管(管)
32 バルブ
33 排水ポンプ
40 風車(構造体)
G 地盤
C 不透水層

100,200,300,400,500 Suction foundation 10 Partition 11 Ceiling part 12 Peripheral wall part 30,230,330,430,530 Release part 31 Drainage pipe (pipe)
32 Valve 33 Drainage pump 40 Wind turbine (structure)
G Ground C Impermeable layer

Claims (7)

天井部と前記天井部に接続された周壁部とを有して底が開放されるように形成され、前記周壁部が水中の地盤に貫入される隔壁と、
前記隔壁を貫通して前記隔壁の内部と外部とを連通させ、前記隔壁の内部の土粒子間の間隙水圧を解放する解放部とを備え
前記解放部は、前記周壁部の貫入後の前記隔壁に構造体が設置された後の、前記隔壁の内部の間隙水圧を解放するサクション基礎。
A partition wall having a ceiling portion and a peripheral wall portion connected to the ceiling portion and formed so that the bottom is open, and the peripheral wall portion penetrates into the underwater ground.
It is provided with a release portion that penetrates the partition wall to communicate the inside and the outside of the partition wall and releases the pore water pressure between the soil particles inside the partition wall .
The release portion is a suction foundation that releases the pore water pressure inside the partition wall after the structure is installed on the partition wall after the penetration of the peripheral wall portion .
請求項1に記載のサクション基礎において、
前記解放部は、前記隔壁の内部と外部との連通及び遮断を切り替え可能なバルブを有するサクション基礎。
In the suction basis according to claim 1,
The release portion is a suction foundation having a valve capable of switching communication and cutoff between the inside and the outside of the partition wall.
請求項2に記載のサクション基礎において、
前記解放部は、一端が前記隔壁の内部に開口し、他端が前記隔壁の外部であって且つ水面より上方において開口する管を有し、
前記バルブは、前記管のうち水面よりも上方の部分に設けられているサクション基礎。
In the suction basis according to claim 2,
The release portion has a tube having one end open inside the partition and the other end outside the partition and above the water surface.
The valve is a suction foundation provided in a portion of the pipe above the water surface.
請求項1乃至3の何れか1つに記載のサクション基礎において、
前記解放部は、前記隔壁の内部の間隙水を排出する排水ポンプを有するサクション基礎。
In the suction basis according to any one of claims 1 to 3,
The release portion is a suction foundation having a drainage pump for draining the interstitial water inside the partition wall.
請求項1乃至の何れか1つに記載のサクション基礎において、
前記周壁部は、地盤のうち不透水層に貫入するサクション基礎。
In the suction basis according to any one of claims 1 to 4 ,
The peripheral wall is a suction foundation that penetrates the impermeable layer of the ground.
天井部と前記天井部に接続された周壁部とを有して底が開放されるように形成された隔壁を備えたサクション基礎の設置方法であって、
前記周壁部を水中の地盤に貫入させる工程と、
前記周壁部の貫入後の前記隔壁に構造体を設置する工程と、
前記構造体の設置後に前記隔壁の内部の土粒子間の間隙水圧を解放する工程とを含むサクション基礎の設置方法。
It is a method of installing a suction foundation having a ceiling portion and a peripheral wall portion connected to the ceiling portion and having a partition wall formed so that the bottom is open.
The process of penetrating the peripheral wall into the underwater ground,
The step of installing the structure on the partition wall after the penetration of the peripheral wall portion, and
A method for installing a suction foundation, which comprises a step of releasing the pore water pressure between soil particles inside the partition wall after installing the structure.
請求項に記載のサクション基礎の設置方法において、
前記周壁部を貫入させる工程では、前記周壁部を地盤のうち不透水層に貫入させるサクション基礎の設置方法。
In the method of installing the suction foundation according to claim 6 ,
In the step of penetrating the peripheral wall portion, a method of installing a suction foundation that penetrates the peripheral wall portion into the impermeable layer of the ground.
JP2018139382A 2018-07-25 2018-07-25 Suction foundation and its installation method Active JP7022025B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018139382A JP7022025B2 (en) 2018-07-25 2018-07-25 Suction foundation and its installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018139382A JP7022025B2 (en) 2018-07-25 2018-07-25 Suction foundation and its installation method

Publications (2)

Publication Number Publication Date
JP2020016073A JP2020016073A (en) 2020-01-30
JP7022025B2 true JP7022025B2 (en) 2022-02-17

Family

ID=69580101

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018139382A Active JP7022025B2 (en) 2018-07-25 2018-07-25 Suction foundation and its installation method

Country Status (1)

Country Link
JP (1) JP7022025B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2024041507A (en) * 2022-09-14 2024-03-27 東洋建設株式会社 Cone penetration device and cone penetration method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000110179A (en) 1998-10-02 2000-04-18 Ohbayashi Corp Method for constructing underwater foundation
JP2000170182A (en) 1998-12-09 2000-06-20 Ohbayashi Corp Construction method of underwater foundation
JP2001311166A (en) 2000-04-26 2001-11-09 Ohbayashi Corp Construction method for underwater foundation structure
JP2015034430A (en) 2013-08-09 2015-02-19 株式会社大林組 Suction structure
JP2017020287A (en) 2015-07-14 2017-01-26 株式会社大林組 Suction anchor extraction prevention method and system

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6149029A (en) * 1984-08-13 1986-03-10 Nippon Steel Corp Underwater foundation fixer
JP3603193B2 (en) * 1997-11-28 2004-12-22 株式会社大林組 How to build an underwater foundation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000110179A (en) 1998-10-02 2000-04-18 Ohbayashi Corp Method for constructing underwater foundation
JP2000170182A (en) 1998-12-09 2000-06-20 Ohbayashi Corp Construction method of underwater foundation
JP2001311166A (en) 2000-04-26 2001-11-09 Ohbayashi Corp Construction method for underwater foundation structure
JP2015034430A (en) 2013-08-09 2015-02-19 株式会社大林組 Suction structure
JP2017020287A (en) 2015-07-14 2017-01-26 株式会社大林組 Suction anchor extraction prevention method and system

Also Published As

Publication number Publication date
JP2020016073A (en) 2020-01-30

Similar Documents

Publication Publication Date Title
KR101435219B1 (en) Foundation structure
CN111945773A (en) Pile box barrel composite foundation for offshore wind power and construction method thereof
EP4060121B1 (en) Subsea foundations
JP2006257829A (en) Automatic tide door equipment at Rikusu
KR20190031868A (en) Suction foundation using inner wall and offshare structure using thereof
JP7022025B2 (en) Suction foundation and its installation method
KR101544640B1 (en) Suction Foundation Assembly, Construction Method for Adjusting Horizontality and Offshore Wind Power System using the same
WO2023003476A1 (en) A suction anchor system
CN102900097A (en) Reverse filtering layer device for assisting in mounting suction barrel-shaped foundation applied to silt seabed and method for mounting barrel-shaped foundation
EP4423345B1 (en) Marine foundations comprising suction piles
CN211735480U (en) Negative pressure barrel-pile composite foundation structure
Dekker Achievement under pressure: suction pile jackets for the Aberdeen offshore wind farm
CN204803913U (en) Take raft board combined type marine wind power fan single pile basis
CN102561286A (en) Suction penetration control system
CN114703878A (en) Plugging and draining device for dewatering well and construction method
JP2010001619A (en) Flap gate, water channel temporary wall, and water channel connection method
CN105019471A (en) Inclined type barrel-shaped foundation mooring system and construction method thereof
CN110924420A (en) A composite foundation based on rapid precompression consolidation treatment of underwater soft soil foundation
NO332557B1 (en) Offshore foundation for installation on the seabed as well as methods for installation of the offshore foundation
JPH1037173A (en) Landslide deterrent well
KR20090102472A (en) Buoyant piled raft system with suction pile
CN211285678U (en) Composite foundation of underwater soft soil foundation based on rapid precompression consolidation
JP2010101013A (en) Base isolation structure
CN109555084B (en) Geomembrane anti-seepage covering at the bottom of the reservoir, gas collection and exhaust structure and its construction method
CN102561285A (en) Suction penetration control method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201229

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211115

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211124

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220119

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220201

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220204

R150 Certificate of patent or registration of utility model

Ref document number: 7022025

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250