Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP7077907B2 - Abutment reinforcement structure - Google Patents
[go: Go Back, main page]

JP7077907B2 - Abutment reinforcement structure - Google Patents

Abutment reinforcement structure Download PDF

Info

Publication number
JP7077907B2
JP7077907B2 JP2018194791A JP2018194791A JP7077907B2 JP 7077907 B2 JP7077907 B2 JP 7077907B2 JP 2018194791 A JP2018194791 A JP 2018194791A JP 2018194791 A JP2018194791 A JP 2018194791A JP 7077907 B2 JP7077907 B2 JP 7077907B2
Authority
JP
Japan
Prior art keywords
steel sheet
abutment
sheet pile
embankment
sheet piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018194791A
Other languages
Japanese (ja)
Other versions
JP2020063573A (en
Inventor
和秀 戸田
真治 妙中
吉郎 石濱
典佳 原田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP2018194791A priority Critical patent/JP7077907B2/en
Publication of JP2020063573A publication Critical patent/JP2020063573A/en
Application granted granted Critical
Publication of JP7077907B2 publication Critical patent/JP7077907B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Bridges Or Land Bridges (AREA)

Description

本発明は、橋台の補強構造に関し、特に、背面が盛土に隣接する橋台の補強構造に関する。 The present invention relates to an abutment reinforcing structure, and more particularly to an abutment reinforcing structure whose back surface is adjacent to an embankment.

橋台の背面が盛土に隣接する箇所では、例えば地震荷重が作用したときに、盛土の土圧によって橋台が傾斜または滑動したり、橋台の側面側に構築されたウイングが変形または崩壊したりする可能性がある。このような場合において、盛土が流出または沈下すると、盛土上に敷設された軌道または道路の輸送に障害が発生する。 Where the back of the abutment is adjacent to the embankment, for example, the earth pressure of the embankment can cause the abutment to tilt or slide, or the wings built on the side of the abutment to deform or collapse when an earthquake load is applied. There is sex. In such a case, if the embankment flows out or sinks, the transportation of the track or road laid on the embankment will be hindered.

従来、このような箇所における橋台の補強には、橋台の前面側からグラウンドアンカーを貫入させたり、盛土を地盤改良したりする工法が用いられてきた。しかしながら、グラウンドアンカーは、橋台の前面側に施工用の空間が確保できない場合には施工が困難であり、地盤改良は盛土を掘り返す等の作業を伴うため供用中の施工が困難である。 Conventionally, in order to reinforce the abutment in such a place, a method of penetrating a ground anchor from the front side of the abutment or improving the ground of the embankment has been used. However, it is difficult to construct the ground anchor when the space for construction cannot be secured on the front side of the abutment, and it is difficult to construct the ground anchor during operation because the ground improvement involves work such as digging up the embankment.

このような点に鑑み、特許文献1では、橋台の背面側に位置する盛土中に複数の柱状体からなる盛土改良体を鉛直方向に設けた橋台の補強構造が提案されている。特許文献1に記載の技術において、複数の盛土改良体は、橋軸方向に対して交差する方向に隣接させて壁状に連結された状態で、直線で形成される波線状に配列される。 In view of these points, Patent Document 1 proposes a reinforcing structure for an abutment in which an improved embankment composed of a plurality of columnar bodies is provided in the vertical direction in the embankment located on the back surface side of the abutment. In the technique described in Patent Document 1, a plurality of embankment improvement bodies are arranged in a wavy line formed by a straight line in a state of being connected in a wall shape adjacent to each other in a direction intersecting the bridge axis direction.

上記の特許文献1に記載の技術では、地震発生時の土圧の波が壁状の盛土改良体によって分断されて小さくなるため、橋台の背面に加わる土圧を分散させることができる。また、地震によって揺り動かされる盛土の振動が、盛土と盛土改良体との摩擦によって減衰されるため、地震発生時に橋台の背面に加わる盛土の土圧を低減することができる。 In the technique described in Patent Document 1 above, the earth pressure wave at the time of the occurrence of an earthquake is divided by the wall-shaped embankment improver and becomes smaller, so that the earth pressure applied to the back surface of the abutment can be dispersed. Further, since the vibration of the embankment shaken by the earthquake is dampened by the friction between the embankment and the embankment improver, the embankment pressure applied to the back surface of the abutment when the earthquake occurs can be reduced.

特開2016-148196号公報Japanese Unexamined Patent Publication No. 2016-148196

しかしながら、上記の特許文献1に記載の技術の場合、盛土改良体は、削孔撹拌ドリルで盛土を掘削しながらセメントミルクと撹拌することによって形成されるソイルセメントであるため、圧縮荷重には強いが引張荷重には弱い。また、ソイルセメントで形成される盛土改良体を橋台と一体化させることも容易ではない。従って、例えば地震発生時に盛土改良体に対して引張荷重が作用したような場合に、盛土改良体の連結構造が破断した部分や、盛土改良体と橋台との間の隙間から盛土が流出する可能性がある。 However, in the case of the technique described in Patent Document 1 above, the embankment improved body is a soil cement formed by stirring the embankment with cement milk while excavating the embankment with a drilling stirring drill, and therefore is strong against a compressive load. Is vulnerable to tensile loads. In addition, it is not easy to integrate the embankment improvement body formed of soil cement with the abutment. Therefore, for example, when a tensile load is applied to the embankment improved body at the time of an earthquake, the embankment can flow out from the part where the connecting structure of the embankment improved body is broken or from the gap between the embankment improved body and the abutment. There is sex.

そこで、本発明は、施工が容易であり、かつ引張荷重にも対抗可能な橋台の補強構造を提供することを目的とする。 Therefore, an object of the present invention is to provide a reinforcing structure for an abutment that is easy to construct and can withstand a tensile load.

本発明のある観点によれば、背面が盛土の延長方向の端部に隣接する橋台の補強構造は、盛土の延長方向に一致する幅方向の端部で互いに連結される複数の鋼矢板で構成され、少なくとも片面で盛土の土圧を支持する鋼矢板壁を備える。複数の鋼矢板のうち、橋台に隣接する鋼矢板の幅方向の一方の端部は、橋台に連結される。 According to one aspect of the invention, the abutment reinforcement structure whose back surface is adjacent to the extension end of the embankment consists of a plurality of steel sheet piles connected to each other at the widthwise end corresponding to the extension direction of the embankment. It is equipped with a steel sheet pile wall that supports the earth pressure of the embankment on at least one side. Of the plurality of steel sheet piles, one end in the width direction of the steel sheet pile adjacent to the abutment is connected to the abutment.

上記の橋台の補強構造は、複数の鋼矢板の頭部を互いに連結する連結部材をさらに備えてもよい。 The abutment reinforcement structure may further include connecting members that connect the heads of the plurality of steel sheet piles to each other.

上記の橋台の補強構造において、橋台に隣接する鋼矢板の幅方向の一方の端部は、橋台の側面または背面に連結されてもよい。 In the above abutment reinforcement structure, one end in the width direction of the steel sheet pile adjacent to the abutment may be connected to the side surface or the back surface of the abutment.

上記の橋台の補強構造において、鋼矢板壁は、盛土の延長方向に敷設される軌道または道路に対して水平方向で重複しない位置に配置されてもよい。 In the above abutment reinforcement structure, the steel sheet pile wall may be arranged at a position that does not overlap in the horizontal direction with respect to the track or road laid in the extension direction of the embankment.

上記の橋台の補強構造において、複数の鋼矢板の少なくとも一部には、幅方向に直交する方向に貫通孔が形成されてもよい。 In the reinforcement structure of the abutment, at least a part of the plurality of steel sheet piles may have through holes formed in a direction orthogonal to the width direction.

上記の橋台の補強構造において、複数の鋼矢板は、第1の深さまで打設される第1の鋼矢板と、第1の深さよりも深い第2の深さまで打設される第2の鋼矢板とを含んでもよい。 In the abutment reinforcement structure described above, the plurality of steel sheet piles are a first steel sheet pile to be driven to a first depth and a second steel to be driven to a second depth deeper than the first depth. It may include a sheet pile.

上記の橋台の補強構造は、複数の鋼矢板の少なくとも一部で打設後に地中部になる位置に接合され、鋼矢板の長手方向に直交する断面に閉合領域を形成する閉合部材をさらに備えてもよい。 The abutment reinforcement structure described above further comprises a closing member that is joined to at least a portion of the steel sheet piles at a position that will be in the ground after casting and forms a closing region in a cross section orthogonal to the longitudinal direction of the steel sheet piles. May be good.

上記の橋台の補強構造は、複数の鋼矢板の少なくとも一部で打設後に地中部になる位置に接合され、鋼矢板の長手方向に直交する断面において、鋼矢板の幅方向に略直交する方向に突出する突出部材をさらに備えてもよい。 The reinforcement structure of the above abutment is joined at a position where at least a part of a plurality of steel sheet piles becomes an underground part after being placed, and in a cross section orthogonal to the longitudinal direction of the steel sheet piles, a direction substantially orthogonal to the width direction of the steel sheet piles. A protruding member may be further provided.

上記の橋台の補強構造は、鋼矢板の打設によって施工可能であるため、例えば盛土上に敷設される軌道や道路の供用中であっても施工が容易である。また、鋼矢板は鋼材で形成されるため引張荷重に強く、また鋼矢板の継手は引張応力が作用することを前提として設計されているため、鋼矢板壁の全体としても引張荷重に十分に対抗可能である。このような鋼矢板壁を橋台に連結することによって、橋台の背面に作用する土圧を低減し、土圧による橋台の変位を抑制することができる。 Since the above-mentioned abutment reinforcement structure can be constructed by placing steel sheet piles, it is easy to construct even while the track or road laid on the embankment is in service, for example. In addition, since the steel sheet pile is made of steel, it is strong against tensile load, and since the steel sheet pile joint is designed on the assumption that tensile stress acts, the steel sheet pile wall as a whole can sufficiently withstand the tensile load. It is possible. By connecting such a steel sheet pile wall to the abutment, the earth pressure acting on the back surface of the abutment can be reduced, and the displacement of the abutment due to the earth pressure can be suppressed.

本発明の第1の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 1st Embodiment of this invention. 本発明の第1の実施形態に係る橋台の補強構造の平面図である。It is a top view of the reinforcement structure of the abutment which concerns on 1st Embodiment of this invention. 本発明の第1の実施形態における軌道の配置例を示す平面図である。It is a top view which shows the arrangement example of the orbit in 1st Embodiment of this invention. 本発明の第1の実施形態における軌道の配置例を示す平面図である。It is a top view which shows the arrangement example of the orbit in 1st Embodiment of this invention. 本発明の第2の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 2nd Embodiment of this invention. 本発明の第2の実施形態に係る橋台の補強構造の平面図である。It is a top view of the reinforcement structure of the abutment which concerns on 2nd Embodiment of this invention. 本発明の第3の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 3rd Embodiment of this invention. 本発明の第3の実施形態に係る橋台の補強構造の平面図である。It is a top view of the reinforcement structure of the abutment which concerns on 3rd Embodiment of this invention. 本発明の第4の実施形態に係る橋台の補強構造の平面図である。It is a top view of the reinforcement structure of the abutment which concerns on 4th Embodiment of this invention. 本発明の第4の実施形態に係る橋台の補強構造の平面図である。It is a top view of the reinforcement structure of the abutment which concerns on 4th Embodiment of this invention. 橋台の背面に形成されたキャビティを用いて鋼矢板を連結する構造の例を示す図である。It is a figure which shows the example of the structure which connects the steel sheet pile by using the cavity formed in the back surface of the abutment. 橋台の背面に形成されたキャビティを用いて鋼矢板を連結する構造の例を示す図である。It is a figure which shows the example of the structure which connects the steel sheet pile by using the cavity formed in the back surface of the abutment. 橋台の背面に形成されたキャビティを用いて鋼矢板を連結する構造の例を示す図である。It is a figure which shows the example of the structure which connects the steel sheet pile by using the cavity formed in the back surface of the abutment. 橋台の背面に形成されたキャビティを用いて鋼矢板を連結する構造の例を示す図である。It is a figure which shows the example of the structure which connects the steel sheet pile by using the cavity formed in the back surface of the abutment. 本発明の第5の実施形態に係る橋台の補強構造の平面図である。It is a top view of the reinforcement structure of the abutment which concerns on 5th Embodiment of this invention. 本発明の第5の実施形態に係る橋台の補強構造の平面図である。It is a top view of the reinforcement structure of the abutment which concerns on 5th Embodiment of this invention. 本発明の第6の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 6th Embodiment of this invention. 本発明の第6の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 6th Embodiment of this invention. 本発明の第6の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 6th Embodiment of this invention. 本発明の第7の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 7th Embodiment of this invention. 本発明の第7の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 7th Embodiment of this invention. 本発明の第7の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 7th Embodiment of this invention. 本発明の第7の実施形態に係る橋台の補強構造の側面図である。It is a side view of the reinforcement structure of the abutment which concerns on 7th Embodiment of this invention. 本発明の実施形態において鋼矢板に突出部材を接合する例を示す図である。It is a figure which shows the example which joins the projecting member to a steel sheet pile in embodiment of this invention.

以下に添付図面を参照しながら、本発明の好適な実施形態について詳細に説明する。なお、本明細書および図面において、実質的に同一の機能構成を有する構成要素については、同一の符号を付することにより重複説明を省略する。 Preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings. In the present specification and the drawings, components having substantially the same functional configuration are designated by the same reference numerals, and duplicate description will be omitted.

図1Aおよび図1Bは、本発明の第1の実施形態に係る橋台の補強構造の側面図および平面図である。図1Aおよび図1Bには、互いの図の関係を示すIA-IA線およびIB-IB線が示されている。なお、図1B以降の平面図では、橋桁Bおよび水面は図示を省略されている。図1Aおよび図1Bに示されるように、橋桁Bを支持し、盛土1の延長方向(図中のx方向)の端部に背面2Aが隣接する橋台2の補強構造3は、鋼矢板壁4を含む。鋼矢板壁4は、幅方向が盛土1の延長方向に一致するように配置される複数のハット形の鋼矢板5で構成される。それぞれの鋼矢板5の幅方向の端部には継手(図示せず)が形成されており、複数の鋼矢板5は継手を互いに嵌合させることによって、幅方向の端部で互いに連結される。図示された例において、それぞれの鋼矢板5は盛土1に所定の深さまで打設されており、これによって鋼矢板壁4は両面で盛土1の土圧を支持する。 1A and 1B are side views and plan views of the abutment reinforcement structure according to the first embodiment of the present invention. 1A and 1B show IA-IA and IB-IB lines showing the relationship between the figures. In the plan views after FIG. 1B, the bridge girder B and the water surface are not shown. As shown in FIGS. 1A and 1B, the reinforcing structure 3 of the abutment 2 that supports the bridge girder B and has the back surface 2A adjacent to the end in the extension direction (x direction in the figure) of the embankment 1 is a steel sheet pile wall 4. including. The steel sheet pile wall 4 is composed of a plurality of hat-shaped steel sheet piles 5 arranged so that the width direction coincides with the extension direction of the embankment 1. A joint (not shown) is formed at the widthwise end of each steel sheet pile 5, and the plurality of steel sheet piles 5 are connected to each other at the widthwise end by fitting the joint to each other. .. In the illustrated example, each steel sheet pile 5 is driven into the embankment 1 to a predetermined depth, whereby the steel sheet pile wall 4 supports the earth pressure of the embankment 1 on both sides.

なお、橋台2は、図1AではL字形の断面形状で図示されているが、この例には限定されず、例えば逆T字形の断面を有してもよい。また、橋台2は杭基礎(木杭を含む)であってもよい。また、図示された例では鋼矢板5が盛土1に打設される深さが橋台2の底面深さと略一致しているが、この例には限定されず、鋼矢板5は橋台2の底面よりも浅く打設されてもよいし、あるいは橋台2の底面よりも深く打設されてもよい。 Although the abutment 2 is shown in FIG. 1A with an L-shaped cross section, the abutment 2 is not limited to this example and may have, for example, an inverted T-shaped cross section. Further, the abutment 2 may be a pile foundation (including a wooden pile). Further, in the illustrated example, the depth at which the steel sheet pile 5 is placed on the embankment 1 substantially coincides with the bottom depth of the abutment 2, but the present invention is not limited to this, and the steel sheet pile 5 is the bottom surface of the abutment 2. It may be placed shallower than, or it may be placed deeper than the bottom surface of the abutment 2.

図1Aに示された例では、鋼矢板5に、幅方向に直交する方向に貫通孔5Bが形成される。貫通孔5Bを形成することによって、例えば盛土1の内部での透水性を確保することができる。貫通孔5Bは、一部の鋼矢板5に形成されてもよいし、全部の鋼矢板5に形成されてもよいし、例えば鉛直方向に十分な透水性が得られる場合は形成されなくてもよい。盛土1の内部での透水性を確保することによって、降雨時における盛土1の内部の水位上昇を防止し、水位上昇の後に水位が低下するときに発生する土の細粒分の流出を抑制することができる。なお、図1B以降の図では貫通孔5Bの図示が省略されているが、図1Aの例と同様に貫通孔5Bを形成することが可能である。 In the example shown in FIG. 1A, a through hole 5B is formed in the steel sheet pile 5 in a direction orthogonal to the width direction. By forming the through hole 5B, for example, water permeability inside the embankment 1 can be ensured. The through hole 5B may be formed in a part of the steel sheet piles 5, may be formed in all the steel sheet piles 5, or may not be formed, for example, if sufficient water permeability can be obtained in the vertical direction. good. By ensuring the permeability inside the embankment 1, the water level inside the embankment 1 is prevented from rising during rainfall, and the outflow of fine particles of soil that occurs when the water level drops after the water level rise is suppressed. be able to. Although the through hole 5B is not shown in the drawings after FIG. 1B, it is possible to form the through hole 5B in the same manner as in the example of FIG. 1A.

ここで、本実施形態において、鋼矢板壁4を構成する複数の鋼矢板5のうち橋台2に隣接する鋼矢板5Aの幅方向の一方の端部は、アンカー6を用いて橋台2の側面2Bに連結される。より具体的には、例えば、鋼矢板5Aの幅方向の一方の端部に形成されるアーム部分が、直接的にアンカー6を用いて橋台2の側面2Bに連結されてもよい。あるいは、アンカー6を用いて橋台2の側面2Bに継手部材が取り付けられ、鋼矢板5Aの幅方向の一方の端部に形成される継手がこの継手部材に嵌合することによって、鋼矢板5Aが橋台2の側面2Bに連結されてもよい。 Here, in the present embodiment, of the plurality of steel sheet piles 5 constituting the steel sheet pile wall 4, one end of the steel sheet pile 5A adjacent to the abutment 2 in the width direction uses an anchor 6 to form a side surface 2B of the abutment 2. Is linked to. More specifically, for example, the arm portion formed at one end of the steel sheet pile 5A in the width direction may be directly connected to the side surface 2B of the abutment 2 by using the anchor 6. Alternatively, the steel sheet pile 5A is formed by attaching a joint member to the side surface 2B of the abutment 2 using the anchor 6 and fitting the joint formed at one end of the steel sheet pile 5A in the width direction to the joint member. It may be connected to the side surface 2B of the abutment 2.

上記のように、本実施形態では、補強構造3が鋼矢板壁4を含んで構成される。鋼矢板壁4を構成する鋼矢板5は鋼材で形成されるため引張荷重に強く、また鋼矢板5の継手は引張応力が作用することを前提として設計されているため、鋼矢板壁4の全体としても幅方向(図中のx方向)の引張荷重に十分に対抗可能である。 As described above, in the present embodiment, the reinforcing structure 3 includes the steel sheet pile wall 4. Since the steel sheet pile 5 constituting the steel sheet pile wall 4 is made of a steel material, it is strong against a tensile load, and since the joint of the steel sheet pile 5 is designed on the premise that a tensile stress acts, the entire steel sheet pile wall 4 is formed. Even so, it can sufficiently withstand the tensile load in the width direction (x direction in the figure).

また、本実施形態では、鋼矢板壁4を構成し、かつ橋台2に隣接する鋼矢板5Aが、橋台2の側面2Bに連結される。これによって、橋台2の背面2Aに作用する土圧を低減し、また土圧による盛土1の延長方向(図中のx方向)における橋台2の変位を、鋼矢板5の幅方向(図中のx方向)のせん断抵抗力、および鉛直支持力によって抑制することができる。また、橋台2の背面2Aに隣接する部分の盛土1が橋台2と鋼矢板5Aとの間の隙間から流出することを防止できる。 Further, in the present embodiment, the steel sheet pile 5A constituting the steel sheet pile wall 4 and adjacent to the abutment 2 is connected to the side surface 2B of the abutment 2. As a result, the earth pressure acting on the back surface 2A of the abutment 2 is reduced, and the displacement of the abutment 2 in the extension direction (x direction in the figure) of the embankment 1 due to the earth pressure is set in the width direction of the steel sheet pile 5 (in the figure). It can be suppressed by the shear resistance in the x direction) and the vertical bearing capacity. Further, it is possible to prevent the embankment 1 in the portion adjacent to the back surface 2A of the abutment 2 from flowing out from the gap between the abutment 2 and the steel sheet pile 5A.

図2および図3は、本発明の第1の実施形態における軌道の配置例を示す平面図である。図2に示される例では、盛土1上に、盛土1の延長方向(図中のx方向)に単線の軌道Tが敷設され、図3に示される例では、同じ方向に複線の軌道T1、T2が敷設されている。これらの例において、橋台2の補強構造3を構成する鋼矢板壁4は、軌道Tまたは軌道T1、T2に対して水平方向(図中のx方向およびy方向)で重複しない位置に配置されている。これによって、例えば軌道Tまたは軌道T1、T2が既に敷設された盛土1および橋台2について補強構造3を事後的に施工する場合も、鋼矢板壁4を構築するために打設される鋼矢板5が軌道Tまたは軌道T1、T2を支障することがなく、軌道Tまたは軌道T1、T2の供用中においても容易に補強構造3を施工することができる。 2 and 3 are plan views showing an example of arrangement of trajectories according to the first embodiment of the present invention. In the example shown in FIG. 2, a single track T is laid on the embankment 1 in the extension direction of the embankment 1 (x direction in the figure), and in the example shown in FIG. 3, the double track T1 is laid in the same direction. T2 is laid. In these examples, the steel sheet pile wall 4 constituting the reinforcing structure 3 of the abutment 2 is arranged at positions that do not overlap in the horizontal direction (x direction and y direction in the figure) with respect to the track T or the tracks T1 and T2. There is. As a result, for example, even when the reinforcing structure 3 is subsequently constructed on the embankment 1 and the abutment 2 on which the track T or the tracks T1 and T2 have already been laid, the steel sheet pile 5 to be driven to construct the steel sheet pile wall 4 Does not interfere with the track T or the tracks T1 and T2, and the reinforcing structure 3 can be easily constructed even while the track T or the tracks T1 and T2 are in service.

なお、例えば軌道Tまたは軌道T1、T2がまだ敷設されていない場合であっても、鋼矢板5を打設する工程は、例えば地盤改良やグラウンドアンカーの貫入などの工程に比べると容易である。また、上記の軌道Tまたは軌道T1、T2と同様に道路が敷設されている場合も、道路の供用中における補強構造3の施工が容易になる。 Even when the track T or the tracks T1 and T2 have not been laid, the step of placing the steel sheet pile 5 is easier than, for example, a step of ground improvement or penetration of a ground anchor. Further, when the road is laid as in the above-mentioned track T or tracks T1 and T2, the construction of the reinforcing structure 3 becomes easy while the road is in service.

図4Aおよび図4Bは、本発明の第2の実施形態に係る橋台の補強構造の側面図および平面図である。図4Aおよび図4Bには、互いの図の関係を示すIVA-IVA線およびIVB-IVB線が示されている。上記の第1の実施形態との違いとして、本実施形態では、橋台2の補強構造3Aが、鋼矢板壁4を構成する複数の鋼矢板5の頭部を互いに連結するコンクリート製の連結部材7をさらに含む。なお、それ以外の点について、本実施形態の構成は第1の実施形態と同様であるため、重複した説明は省略する。 4A and 4B are side views and plan views of the abutment reinforcement structure according to the second embodiment of the present invention. 4A and 4B show the IVA-IVA and IVB-IVB lines showing the relationship between the figures. As a difference from the first embodiment described above, in the present embodiment, the reinforcing structure 3A of the abutment 2 is a concrete connecting member 7 that connects the heads of the plurality of steel sheet piles 5 constituting the steel sheet pile wall 4 to each other. Including further. Since the configuration of the present embodiment is the same as that of the first embodiment with respect to other points, duplicated description will be omitted.

連結部材7は、例えば現場打ちのコンクリートで形成される。具体的には、連結部材7はすべての鋼矢板5の盛土1への打設が完了した後に施工される。本実施形態では、連結部材7によって複数の鋼矢板5の頭部が互いに連結されることによって、例えば橋台2が前面の下端位置2Cを中心に転動または傾動しようとした場合に、鉛直方向のせん断力によって複数の鋼矢板5が互いに深さ方向に摺動するのを防止し、複数の鋼矢板5の鉛直支持力を橋台2に確実に伝達して橋台2の変位を抑制することができる。 The connecting member 7 is formed of, for example, cast-in-place concrete. Specifically, the connecting member 7 is constructed after all the steel sheet piles 5 have been placed on the embankment 1. In the present embodiment, the heads of the plurality of steel sheet piles 5 are connected to each other by the connecting member 7, for example, when the abutment 2 attempts to roll or tilt around the lower end position 2C on the front surface, in the vertical direction. It is possible to prevent the plurality of steel sheet piles 5 from sliding in the depth direction with each other due to the shearing force, and reliably transmit the vertical bearing capacity of the plurality of steel sheet piles 5 to the abutment 2 to suppress the displacement of the abutment 2. ..

図5Aおよび図5Bは、本発明の第3の実施形態に係る橋台の補強構造の側面図および平面図である。図5Aおよび図5Bには、互いの図の関係を示すVA-VA線およびVB-VB線が示されている。なお、図5Bにおいて、橋桁Bおよび水面は図示を省略されている。上記の第1の実施形態との違いとして、本実施形態では、橋台2の補強構造3Bが、鋼矢板壁4を構成する複数の鋼矢板5の頭部を互いに連結する鋼製の連結部材8をさらに含む。なお、それ以外の点について、本実施形態の構成は第1の実施形態と同様であるため、重複した説明は省略する。 5A and 5B are side views and plan views of the abutment reinforcement structure according to the third embodiment of the present invention. 5A and 5B show VA-VA and VB-VB lines showing the relationship between the figures. In FIG. 5B, the bridge girder B and the water surface are not shown. As a difference from the first embodiment described above, in the present embodiment, the reinforcing structure 3B of the abutment 2 is a steel connecting member 8 that connects the heads of a plurality of steel sheet piles 5 constituting the steel sheet pile wall 4 to each other. Including further. Since the configuration of the present embodiment is the same as that of the first embodiment with respect to other points, duplicated description will be omitted.

連結部材8は、溶接、またはボルトなどの接合部材を用いて、それぞれの鋼矢板5の頭部に連結される。例えば、連結部材8は、すべての鋼矢板5の打設が完了した後に、それぞれの鋼矢板5に接合される。連結部材8は、図示された例のような板状の部材には限られず、H形鋼、溝形鋼、T形鋼など、各種の形状の鋼材を連結部材8に用いることができる。本実施形態でも、上記の第2の実施形態と同様に、連結部材8によって複数の鋼矢板5の頭部が互いに連結されることによって、鉛直方向のせん断力によって複数の鋼矢板5が互いに深さ方向に摺動するのを防止し、複数の鋼矢板5の鉛直支持力を橋台2に確実に伝達して橋台2の変位を抑制することができる。なお、図示された例では連結部材8が盛土1の幅方向(図中のy方向)で見た場合に鋼矢板壁4の内側に配置されているが、連結部材8は鋼矢板壁4の外側に配置されてもよく、あるいは連結部材8が鋼矢板壁4の内側および外側の両方に配置されてもよい。 The connecting member 8 is connected to the head of each steel sheet pile 5 by welding or using a joining member such as a bolt. For example, the connecting member 8 is joined to each steel sheet pile 5 after all the steel sheet piles 5 have been placed. The connecting member 8 is not limited to the plate-shaped member as shown in the illustrated example, and steel materials having various shapes such as H-shaped steel, channel steel, and T-shaped steel can be used for the connecting member 8. Also in this embodiment, as in the second embodiment described above, the heads of the plurality of steel sheet piles 5 are connected to each other by the connecting member 8, so that the plurality of steel sheet piles 5 are deeply connected to each other by the shearing force in the vertical direction. It is possible to prevent sliding in the vertical direction and reliably transmit the vertical bearing capacity of the plurality of steel sheet piles 5 to the abutment 2 to suppress the displacement of the abutment 2. In the illustrated example, the connecting member 8 is arranged inside the steel sheet pile wall 4 when viewed in the width direction of the embankment 1 (y direction in the drawing), but the connecting member 8 is formed on the steel sheet pile wall 4. It may be arranged on the outside, or the connecting member 8 may be arranged on both the inside and the outside of the steel sheet pile wall 4.

図6および図7は、本発明の第4の実施形態に係る橋台の補強構造の平面図である。図6および図7は、それぞれ上記の図2および図3(第1の実施形態)に対応する。第1の実施形態との違いとして、本実施形態に係る橋台2の補強構造3Cでは、鋼矢板壁4を構成する複数の鋼矢板5のうち、橋台2に隣接する鋼矢板5Aの幅方向の一方の端部が、継手部材9を用いて橋台2の背面2Aに連結される。なお、それ以外の点について、本実施形態の構成は第1の実施形態と同様であるため、重複した説明は省略する。 6 and 7 are plan views of the abutment reinforcement structure according to the fourth embodiment of the present invention. 6 and 7 correspond to FIGS. 2 and 3 (first embodiment) described above, respectively. As a difference from the first embodiment, in the reinforcing structure 3C of the abutment 2 according to the present embodiment, among the plurality of steel sheet piles 5 constituting the steel sheet pile wall 4, the steel sheet pile 5A adjacent to the abutment 2 is in the width direction. One end is connected to the back surface 2A of the abutment 2 using the joint member 9. Since the configuration of the present embodiment is the same as that of the first embodiment with respect to other points, duplicated description will be omitted.

継手部材9は、例えば平鋼に継手部分を溶接により接合した部材であり、平鋼が橋台2の背面2Aにアンカーを用いて連結され、継手部分が鋼矢板5Aの継手部分に嵌合する(後述する図8Cに示す継手部材9Gと鋼矢板5Aとの関係も参照)。鋼矢板5Aが継手部材9を用いて橋台2の背面2Aに連結されていることによって、橋台2の背面2Aに作用する土圧を低減し、また盛土1の延長方向(図中のx方向)における橋台2の変位を抑制することができる点は、上記の第1の実施形態と同様である。 The joint member 9 is, for example, a member in which a joint portion is joined to flat steel by welding. The flat steel is connected to the back surface 2A of the abutment 2 by using an anchor, and the joint portion is fitted to the joint portion of the steel sheet pile 5A ( See also the relationship between the joint member 9G and the steel sheet pile 5A shown in FIG. 8C, which will be described later). By connecting the steel sheet pile 5A to the back surface 2A of the abutment 2 using the joint member 9, the earth pressure acting on the back surface 2A of the abutment 2 is reduced, and the extension direction of the embankment 1 (x direction in the figure). The point that the displacement of the abutment 2 in the above can be suppressed is the same as that of the first embodiment described above.

また、本実施形態では、橋台2の背面2Aに隣接する部分で、盛土1の幅方向(図中のy方向)で見た場合に鋼矢板壁4の間に挟まれた領域の盛土1が流出することが防止される。鋼矢板壁4の外側の領域の盛土1については補強構造3Cによる流出防止の効果はないが、軌道Tは鋼矢板壁4の間に挟まれた領域に位置するため、軌道Tの輸送機能を維持する点では上記の第1の実施形態と同様の効果が得られる。 Further, in the present embodiment, in the portion adjacent to the back surface 2A of the abutment 2, the embankment 1 in the region sandwiched between the steel sheet pile walls 4 when viewed in the width direction of the embankment 1 (y direction in the figure) is formed. The outflow is prevented. The embankment 1 in the outer region of the steel sheet pile wall 4 has no effect of preventing outflow by the reinforcing structure 3C, but the track T is located in the region sandwiched between the steel sheet pile walls 4, so that the track T has a transport function. In terms of maintenance, the same effect as that of the first embodiment described above can be obtained.

なお、本実施形態でも、鋼矢板壁4は、軌道Tまたは軌道T1、T2に対して水平方向(図中のx方向およびy方向)で重複しない位置に配置されている。従って、本実施形態でも、鋼矢板壁4を構築するために打設される鋼矢板5が軌道Tまたは軌道T1、T2を支障することがなく、軌道Tまたは軌道T1、T2の供用中においても容易に補強構造3Cを施工することができる。 Also in this embodiment, the steel sheet pile wall 4 is arranged at a position that does not overlap with the track T or the tracks T1 and T2 in the horizontal direction (x direction and y direction in the figure). Therefore, also in this embodiment, the steel sheet pile 5 cast to construct the steel sheet pile wall 4 does not interfere with the track T or the tracks T1 and T2, and the track T or the track T1 and T2 are in service. The reinforcing structure 3C can be easily constructed.

図8Aから図8Dは、橋台の背面に形成されたキャビティを用いて鋼矢板を連結する構造の例を示す図である。図8Aに示された例では、橋台2の背面に接続部と円形の拡大部とを含む球根状断面のキャビティ9Aが形成される。鋼矢板5Aの打設時に継手部分をキャビティ9Aに差し込み、打設後にキャビティ9Aにモルタル9Bを充填することによって鋼矢板5Aが橋台2に背面に連結される。図8Bに示された例では、図8Aの例の構成に加えてキャビティ9Aの内面にC字形断面の補強鋼板9Cを嵌め込むことによって、鋼矢板5Aに引張応力が作用したときにキャビティ9Aの接続部が変形するのを防止する。図8Cに示された例では、橋台2の背面に接続部と矩形の拡大部とを含む断面のキャビティ9Dが形成される。キャビティ9Dの内部には平鋼9Eと継手部分9Fとが溶接された継手部材9Gが配置される。鋼矢板5Aの打設時に継手部分を継手部材9Gの継手部分9Fに嵌合させ、打設後にキャビティ9Dにモルタル9Bを充填することによって鋼矢板5Aが継手部材9Gを介して橋台2の背面に連結される。図8Dに示された例では、図8Bの例と同様に球根状断面のキャビティ9Aの内面に補強鋼板9Cが嵌め込まれ、補強鋼板9Cの内側に図8Cの例と同様に平鋼9Eと継手部分9Fとが溶接された継手部材9Gが配置される。平鋼9Eは、例えば溶接などによって補強鋼板9Cに接合されてもよい。 8A to 8D are views showing an example of a structure in which steel sheet piles are connected by using a cavity formed on the back surface of the abutment. In the example shown in FIG. 8A, a cavity 9A having a bulbous cross section including a connecting portion and a circular enlarged portion is formed on the back surface of the abutment 2. The steel sheet pile 5A is connected to the abutment 2 on the back surface by inserting the joint portion into the cavity 9A at the time of placing the steel sheet pile 5A and filling the cavity 9A with the mortar 9B after the placement. In the example shown in FIG. 8B, in addition to the configuration of the example of FIG. 8A, by fitting the reinforcing steel plate 9C having a C-shaped cross section on the inner surface of the cavity 9A, the cavity 9A is formed when a tensile stress is applied to the steel sheet pile 5A. Prevents the connection from deforming. In the example shown in FIG. 8C, a cavity 9D having a cross section including a connecting portion and a rectangular enlarged portion is formed on the back surface of the abutment 2. Inside the cavity 9D, a joint member 9G to which the flat steel 9E and the joint portion 9F are welded is arranged. When the steel sheet pile 5A is placed, the joint portion is fitted to the joint portion 9F of the joint member 9G, and after the placement, the cavity 9D is filled with the mortar 9B so that the steel sheet pile 5A is placed on the back surface of the abutment 2 via the joint member 9G. Be concatenated. In the example shown in FIG. 8D, the reinforcing steel plate 9C is fitted into the inner surface of the cavity 9A having a bulbous cross section as in the example of FIG. 8B, and the flat steel 9E is joined to the inside of the reinforcing steel plate 9C as in the example of FIG. A joint member 9G welded to the portion 9F is arranged. The flat steel 9E may be joined to the reinforcing steel plate 9C by, for example, welding.

上記の例において、キャビティ9A、9Dは、橋台2の背面の上端から下端までの全長にわたって形成されていてもよい。この場合、鋼矢板5Aの打設深さに関わらず、鋼矢板5Aの継手部分を橋台2の背面に形成されたキャビティ9A、9Dに差し込むことによって鋼矢板5Aを橋台2の背面に固定することができる。あるいは、キャビティ9A、9Dは、橋台2の背面の上端側の一部に形成され、下端に達していなくてもよい。この例において、鋼矢板5Aの打設深さがキャビティ9A、9Dの長さを越える場合は、キャビティ9A、9Dの長さを超える部分で鋼矢板5Aの継手部分を切り落とすことによって、キャビティ9A、9Dが形成されない部分でも鋼矢板5Aと橋台2とが干渉することを防止できる。 In the above example, the cavities 9A and 9D may be formed over the entire length from the upper end to the lower end of the back surface of the abutment 2. In this case, regardless of the casting depth of the steel sheet pile 5A, the steel sheet pile 5A is fixed to the back surface of the abutment 2 by inserting the joint portion of the steel sheet pile 5A into the cavities 9A and 9D formed on the back surface of the abutment 2. Can be done. Alternatively, the cavities 9A and 9D may be formed in a part of the upper end side of the back surface of the abutment 2 and may not reach the lower end. In this example, when the casting depth of the steel sheet pile 5A exceeds the lengths of the cavities 9A and 9D, the joint portion of the steel sheet pile 5A is cut off at the portion exceeding the lengths of the cavities 9A and 9D. It is possible to prevent the steel sheet pile 5A and the abutment 2 from interfering with each other even in a portion where 9D is not formed.

図9および図10は、本発明の第5の実施形態に係る橋台の補強構造の平面図である。図9および図10は、それぞれ上記の図3(第1の実施形態)および図7(第4の実施形態)に対応する。第1および第4の実施形態との違いとして、本実施形態に係る橋台2の補強構造3Dは、盛土1の幅方向(図中のy方向)で見た場合に複線の軌道T1、T2の両外側に配置される鋼矢板壁4に加えて、複線の軌道T1、T2の線間に配置される鋼矢板壁4Dを含む。なお、それ以外の点について、本実施形態の構成は第1または第4の実施形態と同様であるため、重複した説明は省略する。 9 and 10 are plan views of the abutment reinforcement structure according to the fifth embodiment of the present invention. 9 and 10 correspond to FIGS. 3 (first embodiment) and 7 (fourth embodiment) described above, respectively. The difference from the first and fourth embodiments is that the reinforcing structure 3D of the abutment 2 according to the present embodiment has double-track tracks T1 and T2 when viewed in the width direction of the embankment 1 (y direction in the figure). In addition to the steel sheet pile walls 4 arranged on both outer sides, the steel sheet pile wall 4D arranged between the tracks T1 and T2 of the double track is included. Since the configuration of the present embodiment is the same as that of the first or fourth embodiment with respect to other points, duplicated description will be omitted.

鋼矢板壁4Dは、鋼矢板壁4と同様に複数の鋼矢板5で構成され、複数の鋼矢板5のうち橋台2に隣接する鋼矢板5Aの幅方向の一方の端部は、上記の第4の実施形態で説明したのと同様の継手部材9を用いて橋台2の背面2Aに連結される。軌道T1、T2の両外側に配置される鋼矢板壁4は、上記の第1の実施形態と同様に橋台2の側面2Bに連結されてもよいし(図9の例)、第4の実施形態と同様に橋台2の背面2Aに連結されてもよい(図10の例)。 Like the steel sheet pile wall 4, the steel sheet pile wall 4D is composed of a plurality of steel sheet piles 5, and one end of the plurality of steel sheet piles 5 adjacent to the abutment 2 in the width direction is the above-mentioned first end. It is connected to the back surface 2A of the abutment 2 by using the same joint member 9 as described in the embodiment of 4. The steel sheet pile walls 4 arranged on both outer sides of the tracks T1 and T2 may be connected to the side surface 2B of the abutment 2 in the same manner as in the first embodiment described above (example of FIG. 9), or the fourth embodiment. It may be connected to the back surface 2A of the abutment 2 in the same manner as the form (example of FIG. 10).

本実施形態では、軌道T1、T2の両外側の鋼矢板壁4に加えて、軌道T1、T2の線間に鋼矢板壁4Dが配置され、鋼矢板壁4および鋼矢板壁4Dがいずれも橋台2に連結される。これによって、補強構造3Dが橋台2の背面2Aに作用する土圧を低減し、また盛土1の延長方向(図中のx方向)における橋台2の変位を抑制する効果が増強される。 In the present embodiment, in addition to the steel sheet pile walls 4 on both outer sides of the tracks T1 and T2, the steel sheet pile wall 4D is arranged between the lines of the tracks T1 and T2, and the steel sheet pile wall 4 and the steel sheet pile wall 4D are both bridge stands. It is connected to 2. As a result, the effect of the reinforcing structure 3D on the back surface 2A of the abutment 2 is reduced, and the effect of suppressing the displacement of the abutment 2 in the extension direction (x direction in the figure) of the embankment 1 is enhanced.

図11A~図11Cは、本発明の第6の実施形態に係る橋台の補強構造の側面図である。本実施形態に係る補強構造3Eでは、鋼矢板壁4を形成する複数の鋼矢板5が、第1の深さd1まで打設される第1の鋼矢板5Cと、第1の深さd1よりも深い第2の深さd2まで打設される第2の鋼矢板5Dとを含む。図11A~図11Cに示された例では、複数の鋼矢板5の打設される深さが異なることによって、鋼矢板壁4の深さが階段状に変化している。なお、それ以外の点について、本実施形態の構成は上述した第1~第5のいずれかの実施形態と同様であるため、重複した説明は省略する。 11A to 11C are side views of the abutment reinforcement structure according to the sixth embodiment of the present invention. In the reinforcing structure 3E according to the present embodiment, the plurality of steel sheet piles 5 forming the steel sheet pile wall 4 are driven from the first steel sheet pile 5C to the first depth d1 and the first depth d1. Also includes a second steel sheet pile 5D that is driven to a deep second depth d2. In the examples shown in FIGS. 11A to 11C, the depth of the steel sheet pile wall 4 changes stepwise due to the difference in the driving depth of the plurality of steel sheet piles 5. Since the configuration of the present embodiment is the same as that of any of the first to fifth embodiments described above with respect to other points, duplicated description will be omitted.

図11Aに示された例では、鋼矢板壁4の深さが、橋台2に隣接する鋼矢板5Aから階段状に深くなっている。図11Bに示された例では、鋼矢板壁4の深さが、鋼矢板5Aから何枚かの鋼矢板5では一定であり、そこから階段状に深くなっている。例えば、橋台2が前面の下端位置2Cを中心に転動または傾動しようとした場合には、橋台2から離れた鋼矢板5により大きな引き抜き力がかかる。上記のように鋼矢板壁4の深さを橋台2から離れるにつれて深くすることによって、より大きな引き抜き力がかかる鋼矢板5ではより大きな鉛直支持力を得ることができる。 In the example shown in FIG. 11A, the depth of the steel sheet pile wall 4 is stepwise deeper than the steel sheet pile 5A adjacent to the abutment 2. In the example shown in FIG. 11B, the depth of the steel sheet pile wall 4 is constant from the steel sheet pile 5A to some steel sheet piles 5, and is deepened stepwise from there. For example, when the abutment 2 attempts to roll or tilt around the lower end position 2C on the front surface, a large pulling force is applied to the steel sheet pile 5 away from the abutment 2. By increasing the depth of the steel sheet pile wall 4 as the distance from the abutment 2 increases as described above, the steel sheet pile 5 to which a larger pulling force is applied can obtain a larger vertical bearing capacity.

一方、図11Cに示された例では、鋼矢板壁4の深さが、橋台2に隣接する鋼矢板5Aから階段状に浅くなっている。例えば、盛土1の延長方向(図中のx方向)への橋台2の滑動(水平移動)の抑制が主な目的である場合は、橋台2に近い鋼矢板5で鋼矢板5の幅方向(図中のx方向)のせん断抵抗力を得ることができるため、橋台2から離れた鋼矢板5は補助的なせん断抵抗力を発揮できる程度に浅く打設して、鋼矢板5の材料を節約してもよい。 On the other hand, in the example shown in FIG. 11C, the depth of the steel sheet pile wall 4 is stepwise shallower than the steel sheet pile 5A adjacent to the abutment 2. For example, when the main purpose is to suppress the sliding (horizontal movement) of the abutment 2 in the extension direction (x direction in the figure) of the embankment 1, the steel sheet pile 5 near the abutment 2 is used in the width direction of the steel sheet pile 5. Since the shear resistance force in the x direction in the figure can be obtained, the steel sheet pile 5 away from the abutment 2 is cast shallow enough to exert an auxiliary shear resistance force, and the material of the steel sheet pile 5 is saved. You may.

図12A~図12Dは、本発明の第7の実施形態に係る橋台の補強構造の側面図である。本実施形態では、補強構造3Fが、鋼矢板壁4を形成する複数の鋼矢板5のうちの少なくとも一部で打設後に地中部になる位置に接合され、鋼矢板5の長手方向に直交する断面に閉合領域を形成する閉合部材10をさらに含む。なお、閉合部材10を用いて鋼矢板の断面に閉合領域を形成する方法については、例えば特許第4916932号公報などに記載されている。閉合部材10を用いて閉合領域を形成することによって、鋼矢板5の鉛直支持力を増大させることができる。それ以外の点について、本実施形態の構成は上述した第1~第6のいずれかの実施形態と同様であるため、重複した説明は省略する。 12A to 12D are side views of the abutment reinforcement structure according to the seventh embodiment of the present invention. In the present embodiment, the reinforcing structure 3F is joined to a position where at least a part of the plurality of steel sheet piles 5 forming the steel sheet pile wall 4 becomes the underground portion after casting, and is orthogonal to the longitudinal direction of the steel sheet pile 5. Further includes a closing member 10 that forms a closing region in the cross section. A method of forming a closed region in a cross section of a steel sheet pile using the closing member 10 is described in, for example, Japanese Patent No. 4916932. By forming the closed region by using the closed member 10, the vertical bearing capacity of the steel sheet pile 5 can be increased. Other than that, the configuration of the present embodiment is the same as that of any of the first to sixth embodiments described above, and therefore duplicate description will be omitted.

図12Aに示された例では、複数の鋼矢板5のうち、橋台2から最も離れた鋼矢板5の下端部に閉合部材10が接合されている。上述のように、例えば橋台2が前面の下端位置2Cを中心に転動または傾動しようとした場合には、橋台2から離れた鋼矢板5により大きな引き抜き力がかかる。従って、閉合部材10を用いて閉合領域を形成することによって橋台2から離れた鋼矢板5の鉛直支持力を増大させれば、鋼矢板壁4が全体として橋台2の転動または傾動を抑制する効果が増強される。 In the example shown in FIG. 12A, the closing member 10 is joined to the lower end portion of the steel sheet pile 5 farthest from the abutment 2 among the plurality of steel sheet piles 5. As described above, for example, when the abutment 2 tries to roll or tilt around the lower end position 2C on the front surface, a large pulling force is applied to the steel sheet pile 5 away from the abutment 2. Therefore, if the vertical bearing capacity of the steel sheet pile 5 separated from the abutment 2 is increased by forming the closed region using the closing member 10, the steel sheet pile wall 4 suppresses the rolling or tilting of the abutment 2 as a whole. The effect is enhanced.

同様の効果を得るために、図12Bに示された例のように、本実施形態と上記の第6の実施形態とを組み合わせ、鋼矢板壁4の深さを階段状に深くするとともに、橋台2から最も離れた鋼矢板5の下端部に閉合部材10を接合してもよい。また、図12Cに示された例のように、橋台2から最も離れた鋼矢板5を含む数本の鋼矢板5の打設される深さを他の鋼矢板5よりも深くし、それらの鋼矢板5の下端部に閉合部材10を接合してもよい。 In order to obtain the same effect, as in the example shown in FIG. 12B, the present embodiment and the above-mentioned sixth embodiment are combined to deepen the depth of the steel sheet pile wall 4 in a stepped manner and abutment. The closing member 10 may be joined to the lower end portion of the steel sheet pile 5 farthest from 2. Further, as in the example shown in FIG. 12C, the depth of several steel sheet piles 5 including the steel sheet pile 5 farthest from the abutment 2 is set to be deeper than that of the other steel sheet piles 5, and they are used. The closing member 10 may be joined to the lower end of the steel sheet pile 5.

図12Dに示された例では、複数の鋼矢板5のうち、橋台2から最も離れた鋼矢板5と、橋台2に隣接する鋼矢板5A、およびその隣の鋼矢板5に閉合部材10が接合されている。橋台2に隣接する鋼矢板5には、橋台2が前面の下端位置2Cを中心に転動または傾動しようとした場合に押し込みの力がかかる可能性があるため、橋台2に隣接する鋼矢板5Aおよびその隣の鋼矢板5についても閉合部材10を接合して鉛直支持力を増大させることによって、鋼矢板壁4が全体として橋台2の転動または傾動を抑制する効果が増強される。 In the example shown in FIG. 12D, the closing member 10 is joined to the steel sheet pile 5 farthest from the abutment 2, the steel sheet pile 5A adjacent to the abutment 2, and the steel sheet pile 5 adjacent to the steel sheet pile 5 among the plurality of steel sheet piles 5. Has been done. Since the steel sheet pile 5 adjacent to the abutment 2 may be subjected to a pushing force when the abutment 2 attempts to roll or tilt around the lower end position 2C on the front surface, the steel sheet pile 5A adjacent to the abutment 2 may be applied. By joining the closing member 10 to the steel sheet pile 5 adjacent to the steel sheet pile 5 and increasing the vertical bearing capacity, the effect of the steel sheet pile wall 4 as a whole to suppress the rolling or tilting of the abutment 2 is enhanced.

図13は、本発明の実施形態において鋼矢板に突出部材を接合する例を示す図である。図13に示されるように、上述したような本発明の実施形態において、鋼矢板5の少なくとも一部で、打設後に地中部になる位置に、突出部材11を接合してもよい。突出部材11は、鋼矢板5の長手方向(図中のz方向)に直交する断面において、鋼矢板5の幅方向(図中のx方向)に略直交する方向に突出する。このような突出部材11を接合することによって、鋼矢板5の幅方向のせん断抵抗力を増大させることができる。突出部材11は、図示された例のような板状の部材には限られず、H形鋼、溝形鋼、T形鋼など、各種の形状の鋼材を突出部材11に用いることができる。 FIG. 13 is a diagram showing an example of joining a protruding member to a steel sheet pile in the embodiment of the present invention. As shown in FIG. 13, in the embodiment of the present invention as described above, the projecting member 11 may be joined to at least a part of the steel sheet pile 5 at a position where it becomes an underground portion after casting. The projecting member 11 projects in a direction substantially orthogonal to the width direction (x direction in the drawing) of the steel sheet pile 5 in a cross section orthogonal to the longitudinal direction (z direction in the drawing) of the steel sheet pile 5. By joining such protruding members 11, the shear resistance force in the width direction of the steel sheet pile 5 can be increased. The projecting member 11 is not limited to the plate-shaped member as shown in the illustrated example, and steel materials having various shapes such as H-shaped steel, channel steel, and T-shaped steel can be used for the projecting member 11.

なお、上記の実施形態では補強構造3において鋼矢板壁4を構成する鋼矢板5がハット形の鋼矢板である例について説明したが、例えばU形鋼矢板や直線鋼矢板など、各種の形状の鋼矢板で鋼矢板壁を構成することが可能である。また、上記の実施形態では鋼矢板5を盛土1に打設することによって鋼矢板壁4が両面で盛土1の土圧を支持したが、鋼矢板5を予め地盤に打設して鋼矢板壁4を構築した上で、鋼矢板壁4の内側に盛土1を形成してもよい。あるいは、既存の盛土1に鋼矢板5を打設して鋼矢板壁4を構築した上で、鋼矢板壁4よりも外側の盛土1を撤去してもよい。これらの場合、鋼矢板壁4は、橋台2の補強構造3を構成するとともに、片面で盛土1の土圧を支持する擁壁としても機能する。 In the above embodiment, an example in which the steel sheet pile 5 constituting the steel sheet pile wall 4 in the reinforcing structure 3 is a hat-shaped steel sheet pile has been described, but various shapes such as a U-shaped steel sheet pile and a straight steel sheet pile have been described. It is possible to construct a steel sheet pile wall with steel sheet piles. Further, in the above embodiment, the steel sheet pile wall 4 supports the soil pressure of the embankment 1 on both sides by driving the steel sheet pile 5 into the embankment 1, but the steel sheet pile 5 is placed in the ground in advance to support the steel sheet pile wall. After constructing 4, the embankment 1 may be formed inside the steel sheet pile wall 4. Alternatively, the steel sheet pile 5 may be placed on the existing embankment 1 to construct the steel sheet pile wall 4, and then the embankment 1 outside the steel sheet pile wall 4 may be removed. In these cases, the steel sheet pile wall 4 constitutes the reinforcing structure 3 of the abutment 2 and also functions as a retaining wall that supports the earth pressure of the embankment 1 on one side.

以上、添付図面を参照しながら本発明の好適な実施形態について詳細に説明したが、本発明はかかる例に限定されない。本発明の属する技術の分野における通常の知識を有する者であれば、特許請求の範囲に記載された技術的思想の範疇内において、各種の変更例または修正例に想到し得ることは明らかであり、これらについても、当然に本発明の技術的範囲に属するものと了解される。 Although the preferred embodiments of the present invention have been described in detail with reference to the accompanying drawings, the present invention is not limited to these examples. It is clear that a person having ordinary knowledge in the field of the art to which the present invention belongs can come up with various modifications or modifications within the scope of the technical idea described in the claims. , These are also naturally understood to belong to the technical scope of the present invention.

1…盛土、2…橋台、2A…背面、2B…側面、2C…下端位置、3、3A、3B、3C、3D、3E、3F…補強構造、4、4D…鋼矢板壁、5、5A…鋼矢板、5B…貫通孔、5C…第1の鋼矢板、5D…第2の鋼矢板、6…アンカー、7、8…連結部材、9…継手部材、10…閉合部材、11…突出部材。 1 ... embankment, 2 ... abutment, 2A ... back, 2B ... side, 2C ... bottom position, 3, 3A, 3B, 3C, 3D, 3E, 3F ... reinforcement structure, 4, 4D ... steel sheet pile wall, 5, 5A ... Steel sheet pile, 5B ... Through hole, 5C ... First steel sheet pile, 5D ... Second steel sheet pile, 6 ... Anchor, 7, 8 ... Connecting member, 9 ... Joint member, 10 ... Closing member, 11 ... Protruding member.

Claims (8)

背面が盛土の延長方向の端部に隣接する橋台の補強構造であって、
前記盛土の延長方向に一致する幅方向の端部で互いに連結される複数の鋼矢板で構成され、少なくとも片面で前記盛土の土圧を支持する鋼矢板壁を備え、
前記複数の鋼矢板のうち、前記橋台に隣接する鋼矢板の幅方向の一方の端部は、前記橋台に連結される、橋台の補強構造。
The back is a reinforcement structure of the abutment adjacent to the end of the embankment in the extension direction.
It consists of a plurality of steel sheet piles connected to each other at the widthwise ends that coincide with the extension direction of the embankment, and has a steel sheet pile wall that supports the earth pressure of the embankment on at least one side.
Of the plurality of steel sheet piles, one end in the width direction of the steel sheet pile adjacent to the abutment is a reinforcing structure of the abutment connected to the abutment.
前記複数の鋼矢板の頭部を互いに連結する連結部材をさらに備える、請求項1に記載の橋台の補強構造。 The reinforcing structure for an abutment according to claim 1, further comprising a connecting member for connecting the heads of the plurality of steel sheet piles to each other. 前記橋台に隣接する鋼矢板の幅方向の一方の端部は、前記橋台の側面または背面に連結される、請求項1または請求項2に記載の橋台の補強構造。 The reinforcing structure of the abutment according to claim 1 or 2, wherein one end in the width direction of the steel sheet pile adjacent to the abutment is connected to the side surface or the back surface of the abutment. 前記鋼矢板壁は、前記盛土の延長方向に敷設される軌道または道路に対して水平方向で重複しない位置に配置される、請求項1から請求項3のいずれか1項に記載の橋台の補強構造。 The abutment according to any one of claims 1 to 3, wherein the steel sheet pile wall is arranged at a position that does not overlap in the horizontal direction with respect to the track or road laid in the extension direction of the embankment. structure. 前記複数の鋼矢板の少なくとも一部には、前記幅方向に直交する方向に貫通孔が形成される、請求項1から請求項4のいずれか1項に記載の橋台の補強構造。 The reinforcing structure for an abutment according to any one of claims 1 to 4, wherein through holes are formed in at least a part of the plurality of steel sheet piles in a direction orthogonal to the width direction. 前記複数の鋼矢板は、第1の深さまで打設される第1の鋼矢板と、前記第1の深さよりも深い第2の深さまで打設される第2の鋼矢板とを含む、請求項1から請求項5のいずれか1項に記載の橋台の補強構造。 The plurality of steel sheet piles include a first steel sheet pile to be driven to a first depth and a second steel sheet pile to be driven to a second depth deeper than the first depth. The abutment reinforcement structure according to any one of claims 1 to 5. 前記複数の鋼矢板の少なくとも一部で打設後に地中部になる位置に接合され、前記鋼矢板の長手方向に直交する断面に閉合領域を形成する閉合部材をさらに備える、請求項1から請求項6のいずれか1項に記載の橋台の補強構造。 Claim 1 to claim 1, further comprising a closing member which is joined at a position where at least a part of the plurality of steel sheet piles becomes an underground portion after casting and forms a closing region in a cross section orthogonal to the longitudinal direction of the steel sheet piles. Reinforcement structure of the abutment according to any one of 6. 前記複数の鋼矢板の少なくとも一部で打設後に地中部になる位置に接合され、前記鋼矢板の長手方向に略直交する断面において、前記鋼矢板の幅方向に直交する方向に突出する突出部材をさらに備える、請求項1から請求項7のいずれか1項に記載の橋台の補強構造。 A protruding member that is joined at least a part of the plurality of steel sheet piles to be in the ground after being placed and projects in a direction orthogonal to the width direction of the steel sheet piles in a cross section substantially orthogonal to the longitudinal direction of the steel sheet piles. The abutment reinforcing structure according to any one of claims 1 to 7, further comprising.
JP2018194791A 2018-10-16 2018-10-16 Abutment reinforcement structure Active JP7077907B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018194791A JP7077907B2 (en) 2018-10-16 2018-10-16 Abutment reinforcement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018194791A JP7077907B2 (en) 2018-10-16 2018-10-16 Abutment reinforcement structure

Publications (2)

Publication Number Publication Date
JP2020063573A JP2020063573A (en) 2020-04-23
JP7077907B2 true JP7077907B2 (en) 2022-05-31

Family

ID=70386991

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018194791A Active JP7077907B2 (en) 2018-10-16 2018-10-16 Abutment reinforcement structure

Country Status (1)

Country Link
JP (1) JP7077907B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115094787B (en) * 2022-06-23 2025-09-05 湖南省交通规划勘察设计院有限公司 A construction method for widening and strengthening a bridge by using a front-mounted lightweight composite column platform

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003336252A (en) 2002-05-22 2003-11-28 Sumitomo Metal Ind Ltd Permeable steel sheet pile wall
JP2005146756A (en) 2003-11-19 2005-06-09 Okumura Corp Earth retaining wall construction method and earth retaining wall formed thereby
JP2006112030A (en) 2004-10-12 2006-04-27 Taisei Corp Continuous underground wall
JP2010209548A (en) 2009-03-09 2010-09-24 Nippon Steel Corp Steel sheet pile foundation structure and method for reinforcing foundation
JP2011157781A (en) 2010-02-03 2011-08-18 Nippon Steel Corp Steel sheet pile retaining wall and method for designing the same
JP4916932B2 (en) 2007-03-29 2012-04-18 新日本製鐵株式会社 Steel sheet pile and steel sheet pile foundation structure
JP2013514472A (en) 2010-02-20 2013-04-25 ホオ パク、ガン Reinforced self-supporting earth retaining structure using arching effect and underground excavation method using it
JP2016148196A (en) 2015-02-12 2016-08-18 公益財団法人鉄道総合技術研究所 Structure and method for reinforcing abutment

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0457525U (en) * 1990-09-20 1992-05-18
JP2012007325A (en) * 2010-06-23 2012-01-12 Sumitomo Metal Ind Ltd Steel pipe sheet pile wall structure
JP2015031119A (en) * 2013-08-06 2015-02-16 東日本旅客鉄道株式会社 Ground reinforcement structure
JP6219644B2 (en) * 2013-09-11 2017-10-25 公益財団法人鉄道総合技術研究所 Seismic reinforcement method for abutments by reducing earth pressure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003336252A (en) 2002-05-22 2003-11-28 Sumitomo Metal Ind Ltd Permeable steel sheet pile wall
JP2005146756A (en) 2003-11-19 2005-06-09 Okumura Corp Earth retaining wall construction method and earth retaining wall formed thereby
JP2006112030A (en) 2004-10-12 2006-04-27 Taisei Corp Continuous underground wall
JP4916932B2 (en) 2007-03-29 2012-04-18 新日本製鐵株式会社 Steel sheet pile and steel sheet pile foundation structure
JP2010209548A (en) 2009-03-09 2010-09-24 Nippon Steel Corp Steel sheet pile foundation structure and method for reinforcing foundation
JP2011157781A (en) 2010-02-03 2011-08-18 Nippon Steel Corp Steel sheet pile retaining wall and method for designing the same
JP2013514472A (en) 2010-02-20 2013-04-25 ホオ パク、ガン Reinforced self-supporting earth retaining structure using arching effect and underground excavation method using it
JP2016148196A (en) 2015-02-12 2016-08-18 公益財団法人鉄道総合技術研究所 Structure and method for reinforcing abutment

Also Published As

Publication number Publication date
JP2020063573A (en) 2020-04-23

Similar Documents

Publication Publication Date Title
CN104404915B (en) The cross section defining method of coupling member
JP5464370B2 (en) Filling reinforcement structure
KR20100068597A (en) A shoring method using arch plate pile and h-pile
JP6632028B2 (en) Concrete assembly retaining wall
EP2848739A1 (en) Steel wall
KR100633796B1 (en) Central Reinforced Connection Structure of Temporary Temporary Construction
JP6650257B2 (en) Mountain retaining structure and construction method thereof
JP7077907B2 (en) Abutment reinforcement structure
JP7506964B2 (en) Ground improvement composite pile foundation, ground improvement composite pile combined independent footing foundation, and design method for ground improvement composite pile combined independent footing foundation
JP5471381B2 (en) Filling reinforcement method
JP2005171488A (en) Connection structure between steel wall and reinforced concrete plate
JP4851881B2 (en) Embankment structure and method for reinforcing embankment structure
JP2007146399A (en) Construction method of soil cement pile, soil cement pile
KR102252011B1 (en) Composite Pile Using Angled Channel With Different Strength Steels
JP6292028B2 (en) Embankment reinforcement structure
JP4705513B2 (en) Foundation structure
JP6774774B2 (en) Pile foundation structure
JP4830589B2 (en) Core material, soil cement wall, soil cement wall pile, method of building soil cement wall
KR20230153660A (en) Steel Assembly Pile
JP2004132124A (en) Pneumatic caisson and pneumatic caisson method
JP3832845B2 (en) Steel sheet pile combined direct foundation and construction method of steel sheet pile combined direct foundation
JP4466418B2 (en) Soil cement wall pile, soil cement structure
KR102603493B1 (en) Cap module-based column wall for building foundation
KR101253051B1 (en) Arching pile
KR102587240B1 (en) Steel Assembly Pile

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210603

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20220318

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220419

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220502

R151 Written notification of patent or utility model registration

Ref document number: 7077907

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R151