Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP7125550B2 - SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH - Google Patents
[go: Go Back, main page]

JP7125550B2 - SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH - Google Patents

SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH Download PDF

Info

Publication number
JP7125550B2
JP7125550B2 JP2021514999A JP2021514999A JP7125550B2 JP 7125550 B2 JP7125550 B2 JP 7125550B2 JP 2021514999 A JP2021514999 A JP 2021514999A JP 2021514999 A JP2021514999 A JP 2021514999A JP 7125550 B2 JP7125550 B2 JP 7125550B2
Authority
JP
Japan
Prior art keywords
layer
tunnel
primary lining
arch
steel arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021514999A
Other languages
Japanese (ja)
Other versions
JP2022500579A (en
Inventor
国強 劉
錫武 陳
躍峰 周
俊涛 王
宝春 周
勇 朱
若晨 王
華 呉
思陽 陳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
Sixth Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical Sixth Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Publication of JP2022500579A publication Critical patent/JP2022500579A/en
Application granted granted Critical
Publication of JP7125550B2 publication Critical patent/JP7125550B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

本発明は、トンネル施工の技術分野に関し、特に、逆アーチを備えた2段階高速閉鎖トンネルの支持構造及びその施工方法に関する。 TECHNICAL FIELD The present invention relates to the technical field of tunnel construction, and more particularly to a support structure and construction method for a two-stage high-speed closing tunnel with inverted arches.

トンネルは、地下に建設された建造物であり、交通、鉱山、水利及び国防などの分野に広く応用されている。現在のトンネルは、新オーストリアトンネル工法を使用するのが一般的であり、支持構造は、複合ライニング構造であり、トンネルの周方向に沿ってボールト、逆アーチ及び側壁を備え、トンネルの径方向に沿って外側の一次ライニング、内側の二次ライニング及び一次ライニングと二次ライニングの間に位置する防水層を備えている。 Tunnels are structures constructed underground and are widely used in fields such as transportation, mining, water conservancy, and national defense. Current tunnels generally use the New Austrian Tunneling Method, and the support structure is a composite lining structure, with vaults, inverted arches and sidewalls along the tunnel's circumferential direction, and radially It has an outer primary lining, an inner secondary lining along and a waterproof layer positioned between the primary and secondary linings.

中国の南西地域のトンネルと地下工学の急速な発展に伴い、山岳鉄道や超長トンネルが次第に増加し、高い地盤応力や軟弱な周囲の岩石などを通り抜けるトンネル施工区間もそれに応じて増加している。地盤応力が高く、岩石が軟弱で、トンネルの変形が大ききため、施工中の制御が困難である。施工中少しでも不注意があれば、変形や土砂災害が発生しやすくなる。しかも、トンネルの構造設計及びその後のメンテナンスなどの面においても同じく解決しにくい問題が発生する押出型軟弱岩の沈埋地帯にトンネル建設するためには、「剛よく剛を制す」と「柔よく剛を制す」の二つの方法がある。「剛よく剛を制す」とは、掘削を開始した後すぐに頑丈な剛性のあるサポートを設置することにより、地層の強大な圧搾力に抵抗することである。「柔よく剛を制す」とは、掘削を開始して、先に柔軟なサポートを設置することにより、地層のある程度の変形を許容して、地面の応力を解放してから剛性のあるサポートを再設置することである。このような二つの支持理念に対し、対応する主な技術手段として、周囲の岩石の事前補強、重い鋼製フレームの初期サポート、二次ライニングを早期に施工するなどの対応する「剛性のあるサポート」、及び、可撓性の鋼材フレームを使用して、ロックボルト、先進導坑の応力解放などの対応する「柔軟なサポート」がある。明らかに、後者が新オーストリアトンネル工法の原理に適合する。ここで言う「剛」及び「柔」は、2つの相対的な概念であり、「剛」の意味は、掘削および荷下ろし後の地層圧力に最大限に抵抗することであり、「柔」の意味は、周囲の岩石の変形を合理的に解放して、支持構造に作用する力を低減することである。ただし、「柔」は、支持構造が効力を失わないことを保証することを前題とし、一旦効力を失うと変形や土砂災害が発生する。従来技術における支持構造は、トンネル通路の表面に直接緊密に接合して剛性の一次ライニングを行う方式であるが、これによれば、トンネル通路を取り巻く岩石層による高い応力のため、常に一次ライニングのコンクリートの破裂や剥離、鋼製アーチの歪み変形などが発生する。鋼製アーチが変形してしまうと、次工程の二次ライニングのスペースに侵入してしまうので、二次ライニングを施工することができなくなる。そのため、施工済みの剛性の一次ライニングを解体しなければならず、改めて新たに剛性の一次ライニングを施工しなければならない。これにより、工程コスト及び施工リスクを大幅に増加するだけではなく、工事期間も大幅に延長されてしまう。 With the rapid development of tunnel and underground engineering in southwestern China, the number of mountain railways and ultra-long tunnels has gradually increased, and the length of tunnel construction through high ground stress and soft surrounding rocks has increased accordingly. . The ground stress is high, the rock is soft, and the deformation of the tunnel is large, making it difficult to control during construction. If there is even a little carelessness during construction, deformation and landslide disasters are likely to occur. Moreover, in order to construct a tunnel in a submerged zone of extruded soft rock, which poses the same intractable problems in terms of structural design and subsequent maintenance of the tunnel, it is necessary to ``strength overcomes stiffness'' and ``softness overcomes stiffness''. There are two methods of controlling the "Stiff and stiff" means to resist the enormous squeezing forces of the formation by setting up strong rigid supports soon after drilling begins. “Flexible and rigid” means that by starting excavation and installing flexible supports first, a certain amount of deformation of the stratum is allowed, and then rigid supports are installed after the ground stress is released. to re-install. For these two support philosophies, the main corresponding technical measures are pre-strengthening of surrounding rocks, initial support of heavy steel frames, and corresponding "rigid support" such as early application of secondary lining. ”, and corresponding “flexible supports” such as rock bolts, stress relief of advanced shafts, etc. using flexible steel frames. Clearly, the latter fits the principles of the New Austrian Tunneling Method. The terms ``rigid'' and ``soft'' here are two relative concepts. The implication is to rationally release the deformation of the surrounding rock to reduce the forces acting on the supporting structure. However, "softness" is based on ensuring that the support structure does not lose its effectiveness, and once it loses its effectiveness, deformation and landslides will occur. Support structures in the prior art consist of rigid primary linings that are directly and intimately bonded to the surface of the tunnel passage, but due to the high stresses induced by the rock formations surrounding the tunnel passage, the primary lining will always remain intact. Explosions and spalling of concrete, distortion deformation of steel arches, etc. occur. If the steel arch is deformed, it will enter the space for the secondary lining in the next process, making it impossible to construct the secondary lining. Therefore, the rigid primary lining that has already been constructed must be dismantled, and a new rigid primary lining must be constructed. This not only greatly increases the process cost and construction risk, but also greatly prolongs the construction period.

本発明の一つの目的は、逆アーチを備えた2段階高速閉鎖トンネルの支持構造を提供することである。 One object of the present invention is to provide a support structure for a two-stage high-velocity closed tunnel with inverted arches.

本発明の他の一つの目的は、逆アーチを備えた2段階高速閉鎖トンネルの支持構造の施工方法を提供することである。 Another object of the present invention is to provide a method for constructing a support structure for a two-stage high-velocity closed tunnel with inverted arches.

本発明の目的を達成するために、本発明による逆アーチを備えた2段階高速閉鎖トンネルの支持構造は、トンネルの周方向に沿って、頂部のボールト、底部の逆アーチ及び両側の側壁を備え、トンネルの径方向に沿って、外層における第一層の一次ライニング、内層における二次ライニング及び前記第一層の一次ライニングと前記二次ライニングの間に設けられた防水層を備え、前記防水層は、ジオテキスタイル及び防水パネルを備えており、前記第一層の一次ライニングは、第一層の上部ステップ一次ライニングと第一層の下部ステップ一次ライニングを備えており、前記第一層の上部ステップ一次ライニングは第一の上部ステップ鋼製アーチを備え、前記第一層の下部ステップ一次ライニングは第一の下部ステップ鋼製アーチを備え、前記第一の上部ステップ鋼製アーチと前記第一の下部ステップ鋼製アーチは、頭尾結合して閉じたリングを形成し、前記支持構造は、前記第一層の一次ライニングと前記防水層の間に設けられた第二層の一次ライニングを備え、前記第二層の一次ライニングはトンネルの径方向に沿って設けられており、前記第二層の一次ライニングは、第二層の上部ステップ一次ライニングと第二層の下部ステップ一次ライニングを備え、前記第二層の上部ステップ一次ライニングは、第二の上部ステップ鋼製アーチを備え、前記第二層の下部ステップ一次ライニングは、第二の下部ステップ鋼製アーチを備え、前記第二の上部ステップ鋼製アーチと前記第二の下部ステップ鋼製アーチは、頭尾結合して閉じたリングを形成する。 To achieve the objects of the present invention, a support structure for a two-stage fast closing tunnel with inverted arch according to the present invention comprises a vault at the top, an inverted arch at the bottom and side walls on both sides along the circumference of the tunnel. a primary lining of a first layer on the outer layer, a secondary lining on the inner layer, and a waterproof layer provided between the primary lining of the first layer and the secondary lining along the radial direction of the tunnel; comprises geotextile and waterproof panels, said first layer of primary lining comprising a first layer of upper step primary lining and a first layer of lower step primary lining, said first layer of upper step primary the lining comprising a first upper step steel arch, said first layer lower step primary lining comprising a first lower step steel arch, said first upper step steel arch and said first lower step Steel arches join head-to-tail to form a closed ring, said support structure comprises a second layer of primary lining disposed between said first layer of primary lining and said waterproof layer; Two layers of primary lining are provided along the radial direction of the tunnel, said second layer of primary lining comprising a second layer of upper step primary lining and a second layer of lower step primary lining; the upper step primary lining of the layer comprising a second upper step steel arch, said lower step primary lining of said second layer comprising a second lower step steel arch, said second upper step steel arch and said second lower step steel arch join head-to-tail to form a closed ring.

好ましくは、前記第一の上部ステップ鋼製アーチは、順に接続された第一の側壁鋼製アーチ、第一の頂部鋼製アーチ、第二の側壁鋼製アーチを備え、前記第一の下部ステップ鋼製アーチは、順に接続された第三の側壁鋼製アーチ、第四の側壁鋼製アーチ、第一の底部鋼製アーチ、第五の側壁鋼製アーチ、第六の側壁鋼製アーチを備え、前記第三の側壁鋼製アーチの第一端の端部と前記第一の側壁鋼製アーチは接続され、前記第三の側壁鋼製アーチの第二端は下向きに延在し、前記第四の側壁鋼製アーチは前記第三の側壁鋼製アーチの前記第一端の側辺に接続され、前記第六の側壁鋼製アーチの第一端の端部と前記第二の側壁鋼製アーチは接続され、前記第六の側壁鋼製アーチの第二端は下向きに延在し、前記第五の側壁鋼製アーチは前記第六の側壁鋼製アーチの前記第一端の側辺に接続される。 Preferably, said first upper step steel arch comprises a first sidewall steel arch, a first top steel arch, a second sidewall steel arch connected in sequence, and said first lower step The steel arch comprises a third sidewall steel arch, a fourth sidewall steel arch, a first bottom steel arch, a fifth sidewall steel arch, a sixth sidewall steel arch connected in sequence. , the end of the first end of the third side wall steel arch and the first side wall steel arch are connected, the second end of the third side wall steel arch extends downward; Four side wall steel arches are connected to the sides of the first end of the third side wall steel arch, connecting the ends of the first end of the sixth side wall steel arch and the second side wall steel arch. The arches are connected, the second end of the sixth side wall steel arch extending downwards, and the fifth side wall steel arch flanking the first end of the sixth side wall steel arch. Connected.

好ましくは、前記第二の上部ステップ鋼製アーチは、順に接続された第一の側壁鋼材サポート、第一の頂部鋼材サポート、第二の側壁鋼材サポートを備え、前記第二の下部ステップ鋼製アーチは、順に接続された第三の側壁鋼材サポート、第一の底部鋼材サポート、第四の側壁鋼材サポートを備え、前記第一の側壁鋼材サポートは前記第三の側壁鋼材サポートと接続し、前記第二の側壁鋼材サポートは前記第四の側壁鋼材サポートと接続する。 Preferably said second upper step steel arch comprises a first sidewall steel support, a first top steel support and a second sidewall steel support connected in sequence, said second lower step steel arch comprises a third sidewall steel support, a first bottom steel support and a fourth sidewall steel support connected in sequence, said first sidewall steel support connecting with said third sidewall steel support, said A second sidewall steel support connects with the fourth sidewall steel support.

好ましくは、前記第一層の一次ライニングと前記第二層の一次ライニングの間には第一層の一次ライニングの予備変形スペースが設けられ、前記第二層の一次ライニングと前記防水層の間には第二層の一次ライニングの予備変形スペースが設けられ、前記第一層の一次ライニングの予備変形スペースの予備変形量は、前記第二層の一次ライニングの予備変形スペースの予備変形量より大きい。 Preferably, a pre-deformation space of the first layer primary lining is provided between the first layer primary lining and the second layer primary lining, and between the second layer primary lining and the waterproof layer. is provided with a pre-deformation space for the primary lining of the second layer, and the pre-deformation amount of the pre-deformation space of the primary lining of the first layer is greater than the pre-deformation amount of the pre-deformation space of the primary lining of the second layer.

好ましくは、前記第一層の上部ステップ一次ライニングは、アーチ部ロックボルトユニットを更に備え、前記アーチ部ロックボルトユニットは、複数の排気装置付きの結合中空ロックボルトを備え、複数の前記結合中空ロックボルトは、トンネルの周方向と縦方向に沿って前記ボールトに配置される。 Preferably, said first layer upper step primary lining further comprises an arch lock bolt unit, said arch lock bolt unit comprising a plurality of coupled hollow lock bolts with exhaust devices, and a plurality of said coupled hollow locks Bolts are arranged in the vault along the circumferential and longitudinal directions of the tunnel.

好ましくは、前記支持構造は、補強ロックボルトユニットを更に備え、前記補強ロックボルトユニットは、複数のアーチ部の長尺ロックボルト、複数の上部ステップ側壁の長尺ロックボルト、複数の下部ステップ側壁の長尺ロックボルト、複数のトンネル底部の長尺ロックボルトを備え、複数の前記アーチ部の長尺ロックボルトは、トンネルの周方向と縦方向に沿って前記ボールトに配置され、複数の前記上部ステップ側壁の長尺ロックボルトは、トンネルの周方向と縦方向に沿ってトンネルの前記上部ステップ両側の側壁に配置され、複数の前記下部ステップ側壁の長尺ロックボルトは、トンネルの周方向と縦方向に沿ってトンネルの前記下部ステップ両側の側壁に配置され、複数の前記のトンネル底部の長尺ロックボルトは、トンネルの周方向と縦方向に沿ってトンネルの底部に配置される。 Preferably, the support structure further comprises a reinforcing rock bolt unit, the reinforcing rock bolt unit comprising a plurality of elongated rock bolts of the arches, a plurality of upper step side wall elongated lock bolts, and a plurality of lower step side wall elongated lock bolts. An elongated rock bolt, a plurality of tunnel bottom elongated rock bolts, a plurality of said arched elongated rock bolts disposed in said vault along the tunnel's circumferential and longitudinal directions, and a plurality of said upper steps. Elongated rock bolts on sidewalls are disposed on the sidewalls on both sides of the upper step of the tunnel along the circumferential and longitudinal directions of the tunnel, and a plurality of elongated rock bolts on the lower step sidewalls extend in the circumferential and longitudinal directions of the tunnel. and a plurality of the tunnel bottom elongated rock bolts are disposed at the bottom of the tunnel along the circumferential and longitudinal directions of the tunnel.

本発明の他の目的を達成するために、本発明による逆アーチを備えた2段階高速閉鎖トンネルの支持構造の施工方法は、上部ステップの先受けサポート及び上部ステップの先受け補強用ロックボルトを設ける工程、トンネルの上部ステップ胴部を掘削する工程、第一層の上部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、トンネルの下部ステップ胴部を掘削する工程、第一層の下部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、下部ステップ側壁の長尺ロックボルト及びトンネル底部の長尺ロックボルトを設ける工程、第二層の下部ステップ一次ライニングを設け、コンクリートを吹き付けて、トンネル底部の埋め戻しをする工程、上部ステップ側壁の長尺ロックボルト及びボールトの長尺ロックボルトを設ける工程、第二層の上部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、逆アーチの打設及び逆アーチの充填打設を行う工程、二次ライニングを打設する工程、を含む。 In order to achieve another object of the present invention, the method for constructing the support structure of the two-stage high-speed closing tunnel with inverted arch according to the present invention comprises the forward support of the upper step and the forward-reinforcing rock bolt of the upper step. step of providing, step of excavating the upper step body of the tunnel, step of providing the first layer upper step primary lining and spraying concrete, step of excavating the lower step body of the tunnel, first layer lower step primary lining and spraying concrete; installing long rock bolts on the side walls of the lower step and long rock bolts on the bottom of the tunnel; providing a second layer of primary lining on the lower step, spraying concrete, and backfilling the bottom of the tunnel installation of long rock bolts on the side walls of the upper step and long rock bolts of the vault; installation of the second layer of the upper step primary lining and spraying concrete; casting of the inverted arch and filling of the inverted arch A step of placing a placement, and a step of placing a secondary lining.

好ましくは、前記施工方法において、トンネルを掘削したか否かを判断し、貫通していない場合、前記上部ステップ側壁の長尺ロックボルト及びボールトの長尺ロックボルトを打ち込むとともに、トンネルの縦方向に沿って次々と、前記上部ステップの先受けサポート及び上部ステップの先受け補強用ロックボルトを設ける工程、前記トンネルの上部ステップ胴部を掘削する工程、前記第一層の上部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、前記トンネルの下部ステップ胴部を掘削する工程、前記第一層の下部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、前記下部ステップ側壁の長尺ロックボルト及びトンネル底部の長尺ロックボルトを設ける工程、前記第二層の下部ステップ一次ライニングを設け、コンクリートを吹き付けて、トンネル底部の埋め戻しをする工程を順次行って、短いステップを形成して環状構造に速やかに閉じて施工を循環的に前進させる。 Preferably, in the construction method, it is determined whether or not the tunnel has been excavated, and if the tunnel has not been penetrated, the long rock bolt of the side wall of the upper step and the long rock bolt of the vault are driven in, and in the vertical direction of the tunnel the step of providing a pre-receiving support of the upper step and a rock bolt for reinforcing the pre-receiving of the upper step; excavating the upper step body of the tunnel; and providing the upper step primary lining of the first layer. a step of spraying concrete; a step of excavating the lower step body of the tunnel; providing the first layer of lower step primary lining and spraying concrete; The steps of installing length rock bolts, installing the lower step primary lining of the second layer, spraying concrete, and backfilling the bottom of the tunnel are carried out in sequence to form short steps to quickly close the ring structure. Move construction forward cyclically.

好ましくは、前記上部ステップの先受けサポートは、複数の先受け注入小管を備え、複数の前記先受け注入小管は、トンネルの周方向及び縦方向に沿って配置される。 Preferably, the forward receiving support of said upper step comprises a plurality of forward receiving injection tubules, and a plurality of said forward receiving injection tubules are arranged along the circumferential direction and the longitudinal direction of the tunnel.

好ましくは、前記上部ステップ先受け補強用ロックボルトは複数の縦方向のロックボルトを有し、複数の前記縦方向のロックボルトは、トンネルの縦方向に沿ってトンネル上部ステップのトンネル切羽面に配置される。 Preferably, said upper step anticipatory reinforcing rock bolt comprises a plurality of longitudinal rock bolts, said longitudinal rock bolts being arranged on the tunnel face of the tunnel upper step along the longitudinal direction of the tunnel. be done.

本発明の逆アーチを備えた2段階高速閉鎖トンネルの支持構造によれば、第一層の一次ライニングと第二層の一次ライニングの組み合わせにより、トンネルの内周における応力分布を有効に改善し、周囲の岩石の破壊範囲の進展を低減することができ、高い地盤応力、軟岩の大変形など不利な地質条件のトンネル機械化施工方法に対する限界を有効に解決することができ、トンネル施工中の安全リスクを大幅に低減して、安全、高速、経済的かつ合理的な施工を行うことができる。逆アーチを備えた2段階高速閉鎖トンネルの支持構造において、第一の上部ステップ鋼製アーチ、第一の下部ステップ鋼製アーチ、第二の上部ステップ鋼製アーチ及び第二の下部ステップ鋼製アーチをいずれも複数の鋼製アーチに分割することができ、機械化施工の運送及び保管に便利になる。逆アーチを備えた2段階高速閉鎖トンネルの支持構造において、第一層の一次ライニングと第二層の一次ライニングの間に一つの変形スペースが予め設けられ、第二層の一次ライニングと防水層の間に第二層の一次ライニングの予備変形スペースが設けられているため、周囲の岩石の変形のために許容スペースを提供して、空間上、周囲の岩石の許容最大変形量を保証することができる。逆アーチを備えた2段階高速閉鎖トンネルの支持構造において、トンネルの周方向に複数の異なる規格のロックボルトを設置できるので、トンネルの周方向での周囲の岩石の変形を制限及び拘束することができ、ロック部分の周囲の岩石の強度を高めて、トンネルの崩壊を防止することができる。 According to the support structure of the two-stage high-speed closing tunnel with inverted arch of the present invention, the combination of the primary lining of the first layer and the primary lining of the second layer effectively improves the stress distribution in the inner circumference of the tunnel, It can reduce the extent of fracture of surrounding rocks, effectively solve the limitations of tunnel mechanization construction methods due to adverse geological conditions such as high ground stress, large deformation of soft rock, and safety risks during tunnel construction. can be greatly reduced, and safe, high-speed, economical and rational construction can be performed. A support structure for a two-stage fast closing tunnel with inverted arches comprising a first upper step steel arch, a first lower step steel arch, a second upper step steel arch and a second lower step steel arch can be divided into multiple steel arches for convenient transport and storage in mechanized construction. In the support structure of the two-stage high-speed closing tunnel with inverted arch, a deformation space is preconfigured between the primary lining of the first layer and the primary lining of the second layer, and between the primary lining of the second layer and the waterproof layer A pre-deformation space for the primary lining of the second layer is provided in between, which provides a permissible space for the deformation of the surrounding rocks to guarantee the maximum permissible deformation of the surrounding rocks in space. can. In the support structure of a two-stage fast-closing tunnel with an inverted arch, multiple rock bolts of different standards can be installed in the circumferential direction of the tunnel, thus limiting and constraining the deformation of the surrounding rock in the circumferential direction of the tunnel. It is possible to increase the strength of the rock around the lock part to prevent the tunnel from collapsing.

逆アーチを備えた2段階高速閉鎖トンネルの支持構造の施工方法によれば、二重層支持及び長短ロックボルトの組み合わせ方法を使用しているので、トンネル機械化施工設備の長所と相まって、逆アーチを備えた2段階高速施工方法を採用し、大変形するトンネルの変形量を各々の施工ステップに分解することができる。そして、段階的な制御と高速閉合方法を採用することで、周囲の岩石の合計変形量を有効に制御することができ、トンネル施工中の安全リスクを大幅に低減し、安全、高速、経済的かつ合理的なトンネル施工の目的を実現することができる。 According to the construction method of the support structure of the two-stage high-speed closing tunnel with inverted arch, the combination method of double layer support and long and short rock bolts is used. In addition, a two-step high-speed construction method is adopted, and the deformation amount of the tunnel, which undergoes large deformation, can be decomposed into each construction step. And by adopting step-by-step control and fast closing method, the total deformation amount of the surrounding rock can be effectively controlled, which greatly reduces the safety risk during tunnel construction, making it safe, fast and economical. And the purpose of reasonable tunnel construction can be realized.

本発明の実施形態による支持構造の断面を示す図である。[0013] Figure 4 illustrates a cross-section of a support structure according to an embodiment of the invention; 本発明の実施形態による第一層の一次ライニングと第二層の一次ライニングの断面を示す図である。Fig. 3 shows a cross section of a first layer primary lining and a second layer primary lining according to an embodiment of the present invention; 本発明の実施形態による施工方法のフローチャートである。4 is a flowchart of a construction method according to an embodiment of the invention; 本発明の実施形態による施工方法のステップ1、ステップ2及びステップ3を実施するときの支持構造の断面を示す図である。Fig. 3 shows a cross-section of a support structure when carrying out steps 1, 2 and 3 of a construction method according to an embodiment of the present invention; 本発明の実施形態による施工方法のステップ4、ステップ5及びステップ6を実施するときの支持構造の断面を示す図である。FIG. 4 is a cross-sectional view of a support structure when performing steps 4, 5 and 6 of the construction method according to an embodiment of the present invention; 本発明の実施形態による施工方法のステップ7を実施するときの支持構造の断面を示す図である。Fig. 3 shows a cross-section of a support structure when performing step 7 of a construction method according to an embodiment of the invention; 本発明の実施形態による施工方法のステップ8を実施するときの支持構造の断面を示す図である。Fig. 3 shows a cross-section of a support structure when performing step 8 of the construction method according to an embodiment of the invention; 本発明の実施形態による施工方法のステップ9を実施するときの支持構造の断面を示す図である。Fig. 3 shows a cross-section of a support structure when performing step 9 of the construction method according to an embodiment of the invention; 本発明の実施形態による施工方法のステップ10を実施するときの支持構造の断面を示す図である。Fig. 3 shows a cross-section of the support structure when performing step 10 of the construction method according to an embodiment of the invention; 本発明の実施形態による施工方法のステップ11を実施するときの支持構造の断面を示す図である。Fig. 3 shows a cross-section of the support structure when performing step 11 of the construction method according to an embodiment of the invention;

以下、図面及び実施形態に基づいて本発明をより詳しく説明する。 Hereinafter, the present invention will be described in more detail based on the drawings and embodiments.

〈逆アーチを備えた2段階高速閉鎖トンネルの支持構造の実施形態〉
図1~2を参照されたい。図1は、本発明の実施形態による支持構造の断面を示す図であり、図2は、本発明の実施形態による第一層の一次ライニングと第二層の一次ライニングの断面を示す図である。本実施形態の支持構造は、トンネルの周方向に沿って、頂部のボールト、底部の逆アーチ及び両側の側壁を備えている。また、トンネルの径方向に沿って、外層における第一層の一次ライニング1、内層における二次ライニング3、及び第一層の一次ライニング1と二次ライニング3の間に設けられた防水層を備えており、防水層は、ジオテキスタイル及び防水パネルを備えている。第一層の一次ライニング1は、第一層の上部ステップ一次ライニングと第一層の下部ステップ一次ライニングを備えている。第一層の上部ステップ一次ライニングと第一層の下部ステップ一次ライニングは、トンネルのステップ境界線で上下に分割されている。第一層の上部ステップ一次ライニングは、ステップ境界線の上部に設置された第一の上部ステップ鋼製アーチを備えている。第一層の下部ステップ一次ライニングは、ステップ境界線の下部に設置された第一の下部ステップ鋼製アーチを備えている。第一の上部ステップ鋼製アーチと前記第一の下部ステップ鋼製アーチは、頭尾結合して閉じたリングを形成する。
<Embodiment of Support Structure for Two-Stage High-Speed Closed Tunnel with Inverted Arch>
See Figures 1-2. 1 is a cross-sectional view of a support structure according to an embodiment of the invention, and FIG. 2 is a cross-sectional view of a first layer primary lining and a second layer primary lining according to an embodiment of the invention. . The support structure of this embodiment comprises a vault at the top, an inverted arch at the bottom and side walls on both sides along the circumference of the tunnel. In addition, along the radial direction of the tunnel, a first layer primary lining 1 in the outer layer, a secondary lining 3 in the inner layer, and a waterproof layer provided between the first layer primary lining 1 and the secondary lining 3 are provided. and the waterproof layer comprises geotextile and waterproof panels. The first layer of primary lining 1 comprises a first layer of upper step primary lining and a first layer of lower step primary lining. The upper step primary lining of the first layer and the lower step primary lining of the first layer are vertically divided at the step boundary line of the tunnel. The upper step primary lining of the first layer comprises a first upper step steel arch located above the step boundary. The lower step primary lining of the first layer comprises a first lower step steel arch located below the step boundary. The first upper step steel arch and said first lower step steel arch join head-to-tail to form a closed ring.

支持構造は、第一層の一次ライニング1と防水層の間に設けられた第二層の一次ライニングを備え、第二層の一次ライニングはトンネルの径方向に沿って設けられている。第二層の一次ライニングは、第二層の上部ステップ一次ライニングと第二層の下部ステップ一次ライニングを備え、第二層の上部ステップ一次ライニングは、ステップ境界線の上部に設置された第二の上部ステップ鋼製アーチを備え、第二層の下部ステップ一次ライニングは、ステップ境界線の下部に設置された第二の下部ステップ鋼製アーチを備え、第二の上部ステップ鋼製アーチと前記第二の下部ステップ鋼製アーチは、頭尾結合して閉じたリングを形成する。 The support structure comprises a second layer of primary lining provided between the first layer of primary lining 1 and the waterproof layer, the second layer of primary lining being provided along the radial direction of the tunnel. The second layer of primary lining comprises a second layer of upper step primary lining and a second layer of lower step primary lining, the second layer of upper step primary lining comprises a second layer of step above the step boundary. comprising an upper step steel arch, the second layer lower step primary lining comprising a second lower step steel arch located below the step boundary, the second upper step steel arch and said second The lower step steel arches of the are joined head-to-tail to form a closed ring.

第一の上部ステップ鋼製アーチは、鋼製フレームにより接続された第一の側壁鋼製アーチ11、第一の頂部鋼製アーチ12、第二の側壁鋼製アーチ13を順に備え、第一の側壁鋼製アーチ11と第二の側壁鋼製アーチ13は、第一の頂部鋼製アーチ12の左右両側に対称に設置されている。第一の下部ステップ鋼製アーチは、鋼製フレームにより接続された第三の側壁鋼製アーチ14、第四の側壁鋼製アーチ15、第一の底部鋼製アーチ16、第五の側壁鋼製アーチ17、第六の側壁鋼製アーチ18を順に備えている。第四の側壁鋼製アーチ15と第五の側壁鋼製アーチ17は、第一の底部鋼製アーチ16の左右両側に対称に設置されている。第三の側壁鋼製アーチ14の第一端の端部は第一の側壁鋼製アーチ11に接続され、第三の側壁鋼製アーチ14の第二端は下向きに延在し、第三の側壁鋼製アーチ14の第一端の側辺は、第四の側壁鋼製アーチ15における第一の底部鋼製アーチ16から離れた一端に接続されている。第六の側壁鋼製アーチ18の第一端の端部は、第二の側壁鋼製アーチ13に接続され、第六の側壁鋼製アーチ18の第二端は下向きに延在し、第六の側壁鋼製アーチ18の第一端の側辺は、第五の側壁鋼製アーチ17における第一の底部鋼製アーチ16から離れた一端に接続されている。 The first upper step steel arch comprises in sequence a first sidewall steel arch 11, a first top steel arch 12, a second sidewall steel arch 13 connected by a steel frame, a first The side wall steel arch 11 and the second side wall steel arch 13 are symmetrically installed on both left and right sides of the first top steel arch 12 . The first lower step steel arch comprises a third sidewall steel arch 14, a fourth sidewall steel arch 15, a first bottom steel arch 16, a fifth sidewall steel arch connected by a steel frame. It has an arch 17 and a sixth side wall steel arch 18 in that order. A fourth sidewall steel arch 15 and a fifth sidewall steel arch 17 are symmetrically installed on both left and right sides of the first bottom steel arch 16 . The end of the first end of the third side wall steel arch 14 is connected to the first side wall steel arch 11, the second end of the third side wall steel arch 14 extends downward, The side of the first end of the side wall steel arch 14 is connected to one end of the fourth side wall steel arch 15 remote from the first bottom steel arch 16 . The end of the first end of the sixth side wall steel arch 18 is connected to the second side wall steel arch 13, the second end of the sixth side wall steel arch 18 extends downwards and the sixth side wall steel arch 18 extends downwards. side wall steel arch 18 is connected to one end of the fifth side wall steel arch 17 remote from the first bottom steel arch 16 .

第二の上部ステップ鋼製アーチは、鋼製フレームにより順に接続された第一の側壁鋼材サポート、第一の頂部鋼材サポート、第二の側壁鋼材サポートを備え、第一の側壁鋼材サポートと第二の側壁鋼材サポートは、第一の頂部鋼材サポートの左右両側に対称に設置されている。第二の下部ステップ鋼製アーチは、鋼製フレームにより順に接続された第三の側壁鋼材サポート24、第一の底部鋼材サポート25、第四の側壁鋼材サポート26を備え、第三の側壁鋼材サポート24と第四の側壁鋼材サポート26は、第一の底部鋼材サポート25の左右両側に対称に設置されている。第一の側壁鋼材サポートは、接続鋼製フレームを通じて第三の側壁鋼材サポートと接続し、第二の側壁鋼材サポートは、接続鋼製フレームを通じて第四の側壁鋼材サポート26と接続する。
第一層の一次ライニング1と第二層の一次ライニングの間には第一層の一次ライニングの予備変形スペース4が設けられ、第二層の一次ライニングと防水層の間には第二層の一次ライニングの予備変形スペース25が設けられている。ここで、第一層の一次ライニングの予備変形スペース4の予備変形量は、第二層の一次ライニングの予備変形スペース25の予備変形量より大きい。本実施形態において、第一層の一次ライニングの予備変形スペース4の予備変形量は30cmであることが好ましく、第二層の一次ライニングの予備変形スペース25の予備変形量は15cmであることが好ましい。
The second upper step steel arch comprises a first sidewall steel support, a first top steel support, a second sidewall steel support connected in sequence by a steel frame, the first sidewall steel support and a second The side wall steel supports are placed symmetrically on both left and right sides of the first top steel support. The second lower step steel arch comprises a third sidewall steel support 24, a first bottom steel support 25, a fourth sidewall steel support 26 connected in sequence by a steel frame to form a third sidewall steel support. 24 and a fourth side wall steel support 26 are placed symmetrically on both left and right sides of the first bottom steel support 25 . A first sidewall steel support connects with a third sidewall steel support through a connecting steel frame, and a second sidewall steel support connects with a fourth sidewall steel support 26 through a connecting steel frame.
A pre-deformation space 4 for the first layer primary lining is provided between the first layer primary lining 1 and the second layer primary lining, and a second layer primary lining space 4 is provided between the second layer primary lining and the waterproof layer. A pre-deformation space 25 for the primary lining is provided. Here, the pre-deformation amount of the pre-deformation space 4 of the first layer primary lining is greater than the pre-deformation amount of the pre-deformation space 25 of the second layer primary lining. In this embodiment, the pre-deformation amount of the pre-deformation space 4 of the primary lining of the first layer is preferably 30 cm, and the pre-deformation amount of the pre-deformation space 25 of the primary lining of the second layer is preferably 15 cm. .

第一層の上部ステップ一次ライニングは、アーチ部ロックボルトユニットを更に備え、アーチ部ロックボルトユニットは、複数の排気装置付きの結合中空ロックボルト6を備え、複数の結合中空ロックボルト6は、トンネルの周方向と縦方向に沿ってボールトに配置されている。結合中空ロックボルト6は長さが3mであり、周方向に1.2mの間隔で1本の結合中空ロックボルト6を打設し、縦方向に1.0mの間隔で1本の結合中空ロックボルト6を打設している。 The upper step primary lining of the first layer further comprises an arch lock bolt unit, the arch lock bolt unit comprising a plurality of connecting hollow rock bolts 6 with exhaust devices, the plurality of connecting hollow rock bolts 6 being connected to the tunnel located in the vault along the circumference and longitudinal direction of the The coupling hollow lock bolt 6 has a length of 3 m, and one coupling hollow lock bolt 6 is driven at intervals of 1.2 m in the circumferential direction, and one coupling hollow lock bolt is driven at intervals of 1.0 m in the longitudinal direction. A bolt 6 is installed.

本実施形態による支持構造は、補強ロックボルトユニット更に備え、補強ロックボルトユニットは、複数のアーチ部の長尺ロックボルト7、複数の側壁の長尺ロックボルト8、複数のトンネル底部の長尺ロックボルト9を備えている。複数のアーチ部の長尺ロックボルト7は、トンネルの周方向と縦方向に沿ってボールトに配置されている。複数の側壁の長尺ロックボルト8は、トンネルの周方向と縦方向に沿ってトンネルの両側の側壁に配置され、両側の側壁は、ステップ境界線の上下両側に分離して設置された上部ステップ側壁と下部ステップ側壁を備え、これに対応して、側壁の長尺ロックボルト8は、上部ステップの側壁の長尺ロックボルトと下部ステップの側壁の長尺ロックボルトを備え、上部ステップの側壁の長尺ロックボルトは上部ステップ側壁に配置され、下部ステップの側壁の長尺ロックボルトは下部ステップ側壁に配置されている。複数のトンネル底部の長尺ロックボルト9は、トンネルの周方向及び縦方向に沿って、トンネル底部に配置されている。アーチ部の長尺ロックボルト7は、直径が25mmで、長さ6mの樹脂製ロックボルトであり、周方向に間隔1.2mごとに1本の樹脂製ロックボルトを打設し、縦方向に間隔1.2mごとに1本の樹脂製ロックボルトを打設している。側壁の長尺ロックボルト8とトンネル底部の長尺ロックボルト9は、いずれも直径32mmで、長さ8mの自走式ロックボルトを使用し、周方向に1.2mの間隔で1本の自走式ロックボルトを打設し、縦方向に1.0mの間隔で1本の自走式ロックボルトを打設している。 The support structure according to this embodiment further comprises a reinforcing rock bolt unit, which includes a plurality of arch elongated rock bolts 7, a plurality of side wall elongated lock bolts 8, and a plurality of tunnel bottom elongated locks. It has a bolt 9. A plurality of arched elongated rock bolts 7 are arranged in the vault along the circumferential and longitudinal directions of the tunnel. A plurality of side wall long rock bolts 8 are arranged on both side walls of the tunnel along the tunnel's circumferential direction and longitudinal direction, and both side walls are separated upper steps on both sides above and below the step boundary line. side walls and lower step side walls and correspondingly side wall long lock bolts 8 comprise upper step side wall long lock bolts and lower step side wall long lock bolts; An elongated rock bolt is located on the upper step sidewall and an elongated rock bolt on the lower step sidewall is located on the lower step sidewall. A plurality of elongated tunnel bottom rock bolts 9 are arranged in the tunnel bottom along the circumferential and longitudinal directions of the tunnel. The long lock bolt 7 of the arch portion is a resin lock bolt having a diameter of 25 mm and a length of 6 m. One resin rock bolt is installed at intervals of 1.2m. The long lock bolt 8 on the side wall and the long lock bolt 9 at the bottom of the tunnel are self-propelled lock bolts with a diameter of 32 mm and a length of 8 m. A traveling lock bolt is installed, and one self-propelled rock bolt is installed at an interval of 1.0 m in the vertical direction.

第一層の一次ライニング1は、第一の上部ステップ鋼製アーチ、第一の下部ステップ鋼製アーチ、金網、縦方向の接続鋼筋、接続鋼筋、上下部ステップのパイプ式ロックボルト10を有する吹き付けコンクリート構造により構成されている。第二層の一次ライニングは、第二の上部ステップ鋼製アーチ、第二の下部ステップ鋼製アーチ、金網、縦方向の接続鋼筋、接続鋼筋を有する吹き付けコンクリート構造により構成されている。 First layer primary lining 1 is sprayed with first upper step steel arch, first lower step steel arch, wire mesh, longitudinal connecting steel bars, connecting steel bars, pipe rock bolts 10 of upper and lower steps Constructed of concrete structure. The primary lining of the second layer consists of a shotcrete structure with second upper step steel arches, second lower step steel arches, wire mesh, longitudinal connecting steel bars, and connecting steel bars.

〈逆アーチを備えた2段階高速閉鎖トンネルの支持構造の施工方法の実施形態〉
図3乃至図10を参照すると、本発明による逆アーチを備えた2段階高速閉鎖トンネルの支持構造の施工方法は、以下ステップを含む。
<Embodiment of Construction Method for Support Structure of Two-Stage High-Speed Closing Tunnel with Inverted Arch>
3 to 10, the construction method of the support structure of the two-stage high-speed closed tunnel with inverted arch according to the present invention includes the following steps.

ステップS1では、上部ステップの先受けサポート及び上部ステップの先受け補強用ロックボルトを打設する。まず、削岩機を使用して、ボールトの掘削外周輪郭線に沿って、前方に一定の角度で直径42mm、長さ4.5mの先受けトレミー管20を打ち込む。先受け小鋼管20は縦方向上3mを一つのサイクルとして接続して施工し、両サイクルは縦方向に1.5m重なっており、先受けトレミー管20の周方向での配置間隔は40cmである。次に、所定の圧力で先受けトレミー管20内にグラウト注入して補強し、先受けトレミー管20のグラウト注入は充満させる必要がある。次に、削岩機を使用して上部ステップの切羽面に先受け補強ロックボルト30を設置する。ここで、先受け補強ロックボルト30は、ガラス繊維製のロックボルトであり、ガラス繊維製ロックボルトは、直径が22mm、長さが6mである。複数のガラス繊維製ロックボルトは、複数の水平列と複数の垂直列に分けられており、各水平列は1.5mの間隔を有し、各垂直列は1.5mの間隔を有する。操作の便宜上、上部ステップの切羽面に、水平方向の間隔1.5m、垂直方向の間隔1.5mの規格で水平方向補助線及び垂直方向補助線を描き、水平方向補助線と垂直方向補助線を交差して設置する。次に、水平方向補助線と縦方向補助線のすべての交点から、複数の交点を選んでガラス繊維製ロックボルトを設けて、隣接する二つのガラス繊維製ロックボルトの水平方向上の間隔が3.0mになり、隣接する二つのガラス繊維製ロックボルトの垂直方向上の間隔が3.0mになるようにする。ガラス繊維製ロックボルトは、縦方向上6.0mを一つのサイクルとして、接続して施工する。 In step S1, a pre-receiving support for the upper step and a pre-receiving reinforcing rock bolt for the upper step are driven. First, using a rock drill, a pre-receiving tremie tube 20 with a diameter of 42 mm and a length of 4.5 m is driven forward at a constant angle along the excavation outer contour of the vault. The pre-receiving small steel pipes 20 are constructed by connecting 3m in the vertical direction as one cycle. . Next, it is necessary to grout and reinforce the receiving tremie tube 20 at a predetermined pressure so that the grouting of the receiving tremie tube 20 is filled. Next, a rock drill is used to install a pre-receiving reinforcing rock bolt 30 on the face of the upper step. Here, the pre-receiving reinforcing rock bolt 30 is a glass fiber rock bolt, and the glass fiber rock bolt has a diameter of 22 mm and a length of 6 m. The plurality of fiberglass rock bolts are divided into a plurality of horizontal rows and a plurality of vertical rows, each horizontal row having a spacing of 1.5m and each vertical row having a spacing of 1.5m. For convenience of operation, draw horizontal and vertical auxiliary lines on the face of the upper step with a standard of 1.5m horizontal interval and 1.5m vertical interval, and horizontal and vertical auxiliary lines be placed across. Next, from all the intersections of the horizontal auxiliary lines and the vertical auxiliary lines, a plurality of intersections are selected to provide glass fiber lock bolts, and the horizontal distance between two adjacent glass fiber lock bolts is 3. 0.0 m and the vertical spacing between two adjacent fiberglass rock bolts is 3.0 m. The glass fiber rock bolts are connected and constructed in a cycle of 6.0 m above the vertical direction.

次に、ステップS2では、トンネルの上部ステップ胴部を掘削する。詳しくは、削岩機を使用して削孔作業を行い、弱い発破により上部ステップ胴部を掘削する。掘削作業中はボールトを先に掘削し、次に側壁を掘削する。各サイクルの掘削長が2つの構造体の鋼製フレーム間隔を超えないように、すなわち1.2mを超えないようにして、5回の掘削を通じて合計6mまで掘削する。側壁を掘削する前に、ボールトの両側において、それぞれ岩壁に直径42mmで、長さ4.5mのパイプ式ロックボルト10を2本打設し、そのパイプ式ロックボルト10内にグラウト注入して、ボールトの収縮やアーチの脱落を防止する。 Next, in step S2, the upper step body of the tunnel is excavated. Specifically, a rock drill is used to drill and excavate the upper step body by weak blasting. During the excavation operation, the vault is excavated first, followed by the sidewalls. The excavation length of each cycle does not exceed the steel frame spacing of the two structures, i.e., 1.2 m, for a total excavation of 6 m through five excavations. Before excavating the side wall, two pipe type rock bolts 10 with a diameter of 42 mm and a length of 4.5 m were driven into the rock wall on both sides of the vault, and grout was injected into the pipe type rock bolts 10. , to prevent vault shrinkage and arch dropout.

次に、ステップS3では、上部ステップの切羽面に続いて、第一層の上部ステップ一次ライニングを設ける。トンネルの上部ステップ胴部を掘削した後、時間内に上部ステップの岩石面に対し、厚み4cmのコンクリートを最初に吹き付ける。次に、再度削岩機又はアンカー掘削機を使用して、トンネルのアーチ部に直径22mmで長さ3mの排気装置付きの結合中空ロックボルト6を設置して、グラウト注入して充満させる。隣接する2つの結合中空ロックボルト6は、周方向に1.2mの間隔を有し、縦方向に1.0mの間隔を有する。次に、第一層の一次上部ステップ鋼製アーチを設置する。第一層の一次上部ステップ鋼製アーチを設置する前に、まず、第一の側壁鋼製アーチ11、第一の頂部鋼製アーチ12、第二の側壁鋼製アーチ13を順に接続する。第一の側壁鋼製アーチ11と第一の頂部鋼製アーチ12の間は接続鋼製フレームにより接続し、第一の頂部鋼製アーチ12と第二の側壁鋼製アーチ13の間は接続鋼製フレームにより接続する。次に、鋼製アーチ組立機を使用して第一層の上部ステップ鋼製アーチを装着する。次に、金網を設置し、金網、パイプ式ロックボルト10などをそれぞれ第一層の一次上部ステップ鋼製アーチに溶接して固定してから、再度コンクリートを吹き付けることで、第一層の上部ステップ一次ライニングの最初に吹き付けたコンクリートと再度吹き付けたコンクリートの合計厚さが27cmになるようにして、全体が均一で、緻密で、背後に空洞がないことを保証する。 Next, in step S3, a first layer of upper step primary lining is provided following the face of the upper step. After excavating the upper step body of the tunnel, the rock face of the upper step is first sprayed with concrete with a thickness of 4 cm in time. Then, again using a rock drill or anchor excavator, a joint hollow rock bolt 6 with a diameter of 22 mm and a length of 3 m with an exhaust system is installed in the arch of the tunnel and filled with grout. Two adjacent coupling hollow rock bolts 6 have a circumferential spacing of 1.2 m and a longitudinal spacing of 1.0 m. Next, the primary upper step steel arches of the first layer are installed. Before installing the primary upper step steel arch of the first layer, first connect the first side wall steel arch 11, the first top steel arch 12 and the second side wall steel arch 13 in order. A connecting steel frame connects between the first side wall steel arch 11 and the first top steel arch 12, and a connecting steel between the first top steel arch 12 and the second side wall steel arch 13. connected by a frame made of A steel arch assembler is then used to install the first layer upper step steel arch. Next, a wire mesh is installed, and the wire mesh, pipe type rock bolt 10, etc. are welded and fixed to the steel arch of the primary upper step of the first layer respectively, and then concrete is sprayed again to form the upper step of the first layer. The total thickness of the primary lining initial and recast concrete is 27 cm to ensure uniformity, compactness and no voids behind.

次に、ステップS4では、トンネルの下部ステップ胴部を掘削する。まず、削岩機を使用して削孔作業を行ってから、弱い発破により下部ステップを掘削する。各サイクルの掘削長が5つの構造体の鋼製フレーム間隔を超えないように、すなわち3mを超えないようにして、2回の掘削を通じて合計6mまで掘削する。下部ステップ胴部を掘削する際、逆アーチの両側から岩壁に、直径42mmで長さ4.5mのパイプ式ロックボルト10を2本打設して、パイプ式ロックボルト10内にグラウト注入する。 Next, in step S4, the lower step body of the tunnel is excavated. First, a rock drill is used to drill and then a weak blast is used to excavate the lower step. The excavation length of each cycle does not exceed the steel frame spacing of the five structures, i.e. not more than 3m, for a total excavation of 6m through two excavations. When excavating the body of the lower step, two pipe-type rock bolts 10 with a diameter of 42 mm and a length of 4.5 m are driven into the rock wall from both sides of the reverse arch, and grout is injected into the pipe-type rock bolts 10. .

次に、ステップS5では、下部ステップの切羽面に続いて、第一層の下部ステップ一次ライニングを設ける。トンネルの下部ステップ胴部を掘削した後、時間内に下部ステップの岩石面に対し、厚み4cmのコンクリートを最初に吹き付ける。次に、削岩機又はアンカー掘削機を使用して、トンネルの底部に長尺ロックボルト9を設置して、M20セメントペーストを注入する。トンネルの長尺ロックボルト9は直径32mmで長さ8mの自走式ロックボルトが好ましく、周方向に、間隔1.2mごとに1本の自走式ロックボルトを設置し、縦方向に、間隔1.0mごとに1本の自走式ロックボルトを設置する。次に、削岩機又はアンカー掘削機を使用して、トンネルの底に案内孔を穿設して、その案内孔に挿入したグラウト注入管40を介してグラウト注入を行う。案内孔の深さは3mであり、周方向に、間隔1.5mごとに一つの案内孔を穿設し、縦方向に、間隔2.5mごとに一つの案内孔を穿設する。次に、鋼製アーチ組立機を使用して第一層の下部ステップ一次ライニングを設置して、第一層の下部ステップ一次ライニングと第一層の上部ステップ一次ライニングにより閉ループが形成されるようにする。第一層の上部ステップ一次ライニングを設置する前に、まず接続鋼製フレームにより、第三の側壁鋼製アーチ14、第四の側壁鋼製アーチ15、第一の底部鋼製アーチ16、第五の側壁鋼製アーチ17、第六の側壁鋼製アーチ18を順に接続する。次に、金網を設置してから、金網、パイプ式ロックボルト10などをそれぞれ第一層の一次上部ステップ鋼製アーチに溶接して固定し、再度コンクリートを吹き付ける。これにより、第一層の下部ステップ一次ライニングの最初に吹き付けたコンクリートと再度吹き付けたコンクリートの合計厚さが27cmになるようにして、全体が均一で、緻密で、背後に空洞がないことを保証する。 Next, in step S5, a first layer of lower step primary lining is provided following the face of the lower step. After excavating the lower step body of the tunnel, the rock face of the lower step is first sprayed with concrete with a thickness of 4 cm in time. A rock drill or anchor excavator is then used to install long rock bolts 9 at the bottom of the tunnel and inject M20 cement paste. The long lock bolt 9 of the tunnel is preferably a self-propelled lock bolt having a diameter of 32 mm and a length of 8 m. Install one self-propelled rock bolt every 1.0 m. Next, using a rock drill or an anchor excavator, a guide hole is drilled in the bottom of the tunnel, and grouting is performed through a grouting pipe 40 inserted into the guide hole. The depth of the guide holes is 3 m, one guide hole is drilled at intervals of 1.5 m in the circumferential direction, and one guide hole is drilled at intervals of 2.5 m in the longitudinal direction. Then use the steel arch assembly machine to install the first layer lower step primary lining so that the first layer lower step primary lining and the first layer upper step primary lining form a closed loop do. Before installing the upper step primary lining of the first layer, the third side wall steel arch 14, the fourth side wall steel arch 15, the first bottom steel arch 16, the fifth side wall steel arch 17 and the sixth side wall steel arch 18 are connected in order. Then, after installing the wire mesh, the wire mesh, the pipe-type rock bolt 10, etc. are welded and fixed to the primary upper step steel arch of the first layer respectively, and the concrete is sprayed again. This ensures that the total thickness of the first and second sprayed concrete of the lower step primary lining of the first layer is 27cm, ensuring that the whole is uniform, dense and without cavities behind. do.

次に、ステップS6では、下部ステップにおける側壁の長尺ロックボルト8とトンネル底部の長尺ロックボルト9を設置する。トンネルの周方向と縦方向に沿って、下部ステップの両側の側壁に複数の側壁の長尺ロックボルト8を打設し、トンネルの周方向と縦方向に沿って、トンネルの底部に複数のトンネル底部の長尺ロックボルト9を打設する。下部ステップの側壁の長尺ロックボルト8とトンネル底部の長尺ロックボルト9は、いずれも直径32mmで長さ8mの自走式ロックボルトであり、周方向に間隔1.2mごとに1本の自走式ロックボルトを設置し、縦方向に間隔1.0mごとに1本の自走式ロックボルトを設置する。 Next, in step S6, the long lock bolt 8 on the side wall and the long lock bolt 9 on the bottom of the tunnel are installed in the lower step. A plurality of long rock bolts 8 are driven into the sidewalls on both sides of the lower step along the circumferential and longitudinal directions of the tunnel, and a plurality of tunnels are formed at the bottom of the tunnel along the circumferential and longitudinal directions of the tunnel. Drive the long lock bolt 9 at the bottom. The long lock bolt 8 on the side wall of the lower step and the long lock bolt 9 on the bottom of the tunnel are both self-propelled lock bolts with a diameter of 32 mm and a length of 8 m. Self-propelled rock bolts are installed, and one self-propelled rock bolt is installed at every 1.0m interval in the vertical direction.

次に、ステップS7では、第二層の下部ステップ一次ライニングを設置してコンクリートを吹き付けて、トンネル底部の埋め戻しをする。ここで、第二層の下部ステップ一次ライニングを設置する前に、接続鋼製フレームにより、第三の側壁鋼材サポート24、第一の底部鋼材サポート25、第四の側壁鋼材サポート26を接続する。第一層の一次ライニングが最初に安定した後、鋼製アーチ組立機を使用して、第二層の下部ステップ一次ライニングを設置する。次に、金網を設置して、金網と第二層の一次下部ステップ鋼製アーチを溶接して固定し、コンクリートを吹き付ける。これにより、第二層の下部ステップ一次ライニングのコンクリート吹き付け後の厚さが25cmになるようにして、全体が均一で、緻密で、背後に空洞がないことを保証する。すなわち、第二層の下部ステップ一次ライニングと第一層の下部ステップ一次ライニングとの隙間にコンクリートを完全に充填すべきである。ここで、コンクリートの吹き付け施工の前、第二層の一次サポートの下部ステップ鋼製アーチを設置した後に、両側の外部露出部に継手を予め残し保護措置を講じてからコンクリートを吹き付ける。すなわち、第三の側壁鋼製アーチ14と第六の側壁鋼製アーチ18の方に継手を残し、それに対し保護措置を講じてからコンクリートを吹き付ける。第二層の一次サポートの設置が完了後、洞穴中のスラグによりトンネル底部の埋め戻しをして締め固める。 Next, in step S7, a second layer of lower step primary lining is installed and concrete is sprayed to backfill the bottom of the tunnel. Here, a connecting steel frame connects the third side wall steel support 24, the first bottom steel support 25 and the fourth side wall steel support 26 before installing the second layer lower step primary lining. After the first layer of primary lining is initially stabilized, a steel arch assembler is used to install the second layer of lower step primary lining. The wire mesh is then installed, the wire mesh and the primary lower step steel arch of the second layer are welded and fixed, and the concrete is sprayed. This ensures that the bottom step primary lining of the second layer has a thickness of 25 cm after spraying concrete, ensuring that the whole is uniform, dense and without cavities behind. That is, the gap between the lower step primary lining of the second layer and the lower step primary lining of the first layer should be completely filled with concrete. Here, before the concrete is sprayed, after the lower step steel arches of the second layer of primary support are installed, joints are left on both sides of the externally exposed parts to protect them before the concrete is sprayed. That is, the third side wall steel arch 14 and the sixth side wall steel arch 18 are left with joints which are protected and then blasted with concrete. After the installation of the primary support for the second layer is completed, the slag in the cave backfills and compacts the bottom of the tunnel.

次に、ステップS8では、トンネルを掘削して貫通したか否かを判断する。貫通している場合、以下のステップS9~S12のみを実行し、貫通していない場合、前の施工区域に対しステップS9~S12を実行するとともに、後の施工区域に対しステップS1~S7を実行して、縦方向上6mを一つのサイクルとして短いステップを形成し、環状構造に速やかに閉じて施工を進める。前の施工区域と後の施工区域は隣接する二つの施工区域であり、説明を簡便にするために、前の施工区域を第一の施工区域と呼び、後の施工区域を第二の施工区域と呼ぶ。 Next, in step S8, it is determined whether or not the tunnel has been excavated and penetrated. If it penetrates, only the following steps S9 to S12 are executed, and if it does not penetrate, steps S9 to S12 are executed for the previous construction area, and steps S1 to S7 are executed for the later construction area. Then, a short step is formed with 6m above in the vertical direction as one cycle, and the construction proceeds by quickly closing to a circular structure. The front construction area and the rear construction area are two adjacent construction areas, and for the sake of convenience, the front construction area is called the first construction area, and the rear construction area is the second construction area. call.

ステップS9では、上部ステップの側壁の長尺ロックボルト8及びアーチ部の長尺ロックボルト7を設置する。トンネルの周方向と縦方向に沿って、上部ステップの両側の側壁に複数の側壁の長尺ロックボルト8を設置し、トンネルの周方向と縦方向に沿って、ボールトに複数のアーチ部の長尺ロックボルト7を設置する。上部ステップの側壁の長尺ロックボルトは、直径32mmで長さ8mの自走式ロックボルトを使用し、周方向に1.2mの間隔で1本の自走式ロックボルトを設置し、縦方向に1.0mの間隔で1本の自走式ロックボルトを設置する。アーチ部の長尺ロックボルトは、直径25mmで長さ6mの樹脂製ロックボルトを使用し、周方向に1.2mの間隔で1本の樹脂製ロックボルトを設置し、縦方向に1.2mの間隔で1本の樹脂製ロックボルトを設置する。 In step S9, the long lock bolt 8 on the side wall of the upper step and the long lock bolt 7 in the arch portion are installed. Along the tunnel's circumferential direction and longitudinal direction, a plurality of side wall long lock bolts 8 are installed on both side walls of the upper step, and along the tunnel's circumferential direction and longitudinal direction, a plurality of arched lengths are installed on the vault. A length lock bolt 7 is installed. The long rock bolts on the side walls of the upper steps use self-propelled rock bolts with a diameter of 32 mm and a length of 8 m. Install one self-propelled rock bolt at intervals of 1.0m. For the long lock bolts of the arch, resin lock bolts with a diameter of 25 mm and a length of 6 m are used, and one resin lock bolt is installed at intervals of 1.2 m in the circumferential direction, and the length is 1.2 m in the vertical direction. Install one resin rock bolt at intervals of .

破壊された周辺の岩石の完全性を更に改善するために、削岩機又はアンカー掘削機を使用して、トンネル全体に対し、アーチ部と側壁の周囲の岩石に案内孔を穿設して、その案内孔に挿入したグラウト注入管40を介してグラウト注入を行う。ここで、案内孔の深さは3mであり、掘削輪郭線の3mの範囲までグラウト注入による補強が行われている。案内孔は、周方向の間隔が1.5mであり、縦方向の間隔が2.5mである。 To further improve the integrity of the fractured surrounding rock, a rock drill or anchor excavator is used to drill guide holes in the rock surrounding the arches and sidewalls for the entire tunnel, Grout is injected through a grout injection pipe 40 inserted into the guide hole. Here, the depth of the guide hole is 3 m, and reinforcement by grout injection is performed up to a range of 3 m along the excavation contour line. The guide holes are circumferentially spaced 1.5 m apart and longitudinally spaced 2.5 m apart.

次に、ステップS10では、第一の施工区域に第二層の上部ステップ一次ライニングを設置して、コンクリートの吹き付けを行う。第二の施工区域において、上部ステップの切羽面を15~20m掘削してから、且つ第一層の一次ライニングの変形が予備変形量の1/2に収束した後、又は変形が予備変形量の1/2には達してなくてもすでに安定したときに、第二の上部ステップ一次ライニングを設置する。第二層の上部ステップ一次ライニングと第一層の上部ステップ一次ライニングの間に第一層の一次ライニングの予備変形スペースを形成しておき、この予備変形スペースの予備変形量は30cmであることが好ましい。第二層の一次ライニングはトンネルの径方向に沿って設置されており、第二層の一次ライニングは第二の上部ステップ鋼製アーチを備えている。第二の上部ステップ鋼製アーチは、順に接続された第一の側壁鋼材サポート21、第一の頂部鋼材サポート22、第二の側壁鋼材サポート23を備えている。第二層の一次ライニングの前に、先ず、第一の側壁鋼材サポート21、第一の頂部鋼材サポート22、第二の側壁鋼材サポート23を順に接続しておき、次に、鋼製アーチ組立機を使用して第二の上部ステップ鋼製アーチを設置して、第二の上部ステップ鋼製アーチと第二の下部ステップ鋼製アーチで閉じたリングが形成されるようにする。次に、金網を設置して、金網と第二層の一次下部ステップ鋼製アーチを溶接して固定してから、コンクリートの吹き付けを行う。これにより、第二層の上部ステップ一次ライニング同士のコンクリート吹き付け後の厚さが25cmになるようにして、全体が均一で、緻密で、背後に空洞がないことを保証する。すなわち、第二層の上部ステップ一次ライニングと第一層の上部ステップ一次ライニングとの隙間にコンクリートを完全に充填すべきである。 Next, in step S10, the second layer of upper step primary lining is installed in the first construction area and the concrete is sprayed. In the second construction area, after excavating the face of the upper step by 15 to 20 m, and after the deformation of the primary lining of the first layer converges to 1/2 of the preliminary deformation amount, or the deformation is less than the preliminary deformation amount Install the second upper step primary lining when it is already stable but not 1/2 full. A preliminary deformation space for the first layer primary lining is formed between the second layer upper step primary lining and the first layer upper step primary lining, and the preliminary deformation amount of this preliminary deformation space is 30 cm. preferable. A second layer of primary lining is installed along the radial direction of the tunnel, the second layer of primary lining comprising a second upper step steel arch. The second upper step steel arch comprises a first sidewall steel support 21, a first top steel support 22 and a second sidewall steel support 23 connected in sequence. Before the second layer of primary lining, the first side wall steel support 21, the first top steel support 22 and the second side wall steel support 23 are connected in order, and then the steel arch assembling machine. to install the second upper step steel arch so that the second upper step steel arch and the second lower step steel arch form a closed ring. The wire mesh is then installed and fixed by welding the wire mesh and the primary lower step steel arch of the second layer before the concrete is sprayed. This ensures a thickness of 25 cm between the upper step primary linings of the second layer after spraying concrete, ensuring that the whole is uniform, dense and without cavities behind. That is, the gap between the upper step primary lining of the second layer and the upper step primary lining of the first layer should be completely filled with concrete.

次に、ステップS11では、逆アーチの打設及び逆アーチの充填打設を行う。第一の施工区域の第二層の一次ライニングにより一定の距離で支持され、且つ第二層の一次ライニングが環状に閉じられた区域の収束変形データが安定していると評価された後、逆アーチの充填打設を行う。まず、逆アーチの型板を設置して、二重層の鋼筋を入れ、C35コンクリートを使用して逆アーチの打設を行う。基本的に逆アーチが固化した後、逆アーチの充填型板を設置して、C20コンクリートを使用して充填打設を行う。 Next, in step S11, reverse arch driving and reverse arch filling driving are performed. After the convergence deformation data of the area where the primary lining of the second layer in the first construction area is supported at a certain distance and the primary lining of the second layer is annularly closed is evaluated as stable, reverse Carry out filling and placing of the arch. First, an inverted arch template is installed, a double layer of steel bars is placed, and C35 concrete is used to cast the inverted arch. Basically, after the inverted arch has solidified, the inverted arch filling template is installed and C20 concrete is used to perform the filling and pouring.

次に、ステップS12では、二次ライニングの打設を行う。二次ライニングの打設を行う前に、第二層の上部ステップ一次ライニングに防水層を敷設する。この防水層は、ジオテキスタイル及び防水パネルを備えている。防水層と第二層の一次ライニングの間に第二層の一次ライニングの予備変形スペースを形成し、又は二次ライニングと第二層の一次ライニングの間に第二層の一次ライニングの予備変形スペースを形成する。防水層はこの第二層の一次ライニングの予備変形スペースの中に含まれる。この第二層の一次ライニングの予備変形スペースの予備変形量は、第一層の一次ライニングの予備変形スペースの予備変形量より小さく、本実施形態では、第二層の一次ライニングの予備変形量は15cmである。次に、二次ライニングの型板を設置して、二重層の鋼筋を入れ、C35コンクリートを使用して二次ライニングの打設を行うことで、二次ライニングの合計厚さが60cmになるようにする。二次ライニングの打設を一定距離完了した後、二次ライニングの変形が安定した後、両側溝の線渠型板を設置して線渠の注入施工を行う。 Next, in step S12, the secondary lining is placed. A waterproofing layer is laid on the upper step primary lining of the second layer before placing the secondary lining. This waterproof layer comprises geotextile and waterproof panels. forming a pre-deformation space of the second layer primary lining between the waterproof layer and the second layer primary lining, or forming a pre-deformation space of the second layer primary lining between the secondary lining and the second layer primary lining; to form The waterproof layer is contained within the pre-deformation space of the primary lining of this second layer. The preliminary deformation amount of the preliminary deformation space of the primary lining of the second layer is smaller than the preliminary deformation amount of the preliminary deformation space of the primary lining of the first layer. 15 cm. Next, a secondary lining template is installed, a double layer of steel bars is placed, and the secondary lining is poured using C35 concrete so that the total thickness of the secondary lining is 60 cm. to After the secondary lining has been cast for a certain distance and the deformation of the secondary lining has stabilized, the conduit template for both sides of the groove is installed and the conduit is poured.

以上、好ましい実施形態により本発明を詳細に説明したが、その目的は、当業者が、本発明の内容を理解した上で実施できるようにするためである。もちろん、本発明の保護範囲は、上記実施形態、実施例に限定されず、本発明の趣旨に基づいて変更又は改善することができ、いずれも本発明の保護範囲に含まれる。
産業上の利用性
Although the present invention has been described in detail with preferred embodiments, the purpose thereof is to enable those skilled in the art to understand and implement the present invention. Of course, the protection scope of the present invention is not limited to the above embodiments and examples, and can be modified or improved within the spirit of the present invention, and both fall within the protection scope of the present invention.
Industrial applicability

本発明は、高い地盤応力や軟弱岩のトンネル施工に応用される。本発明によれば、第一層の一次ライニングと防水層の間に、第二層の一次ライニングを設置して、第一層の一次ライニングと第二層の一次ライニングの間に第一層の一次ライニングの予備変形スペースを形成し、第二層の一次ライニングと防水層の間に第二層の一次ライニングの予備変形スペースを形成することで、第一層の一次ライニングと第二層の一次ライニングにより掘削および荷下ろし後の地層圧力に最大限に抵抗することができ、トンネル内周で発生する変形を防止し、第一層の一次ライニングの予備変形スペースと第二層の一次ライニングの予備変形スペースにより周囲の岩石の変形を効果的に解放することができ、第一層の一次ライニングと第二層の一次ライニングに加える力を減少させることができる。したがって、第一層の一次ライニングと第二層の一次ライニングの構造の障害を防止して、高い地盤応力、軟岩の大変形など不利な地質条件のトンネル機械化施工方法に対する限界を有効に解決することができ、トンネル施工中の安全リスクを大幅に低減して、安全、高速、経済的かつ合理的な施工を行うことができる。 INDUSTRIAL APPLICABILITY The present invention is applied to construction of tunnels in high ground stress and soft rock. According to the present invention, a second layer of primary lining is installed between the first layer of primary lining and the waterproof layer, and the first layer of primary lining is placed between the first layer of primary lining and the second layer of primary lining. By forming a preliminary deformation space for the primary lining and forming a preliminary deformation space for the second layer primary lining between the second layer primary lining and the waterproof layer, the first layer primary lining and the second layer primary The lining can resist the pressure of the formation after excavation and unloading to the maximum extent, prevents the deformation that occurs in the inner circumference of the tunnel, and provides a preliminary deformation space for the primary lining of the first layer and a preliminary lining of the second layer. The deformation space can effectively release the deformation of the surrounding rock and reduce the force applied to the primary lining of the first layer and the primary lining of the second layer. Therefore, it is necessary to prevent the structural failure of the primary lining of the first layer and the primary lining of the second layer, and effectively solve the limitations of tunnel mechanization construction methods due to adverse geological conditions such as high ground stress and large deformation of soft rock. It is possible to greatly reduce the safety risk during tunnel construction, and to perform safe, high-speed, economical and rational construction.

Claims (10)

逆アーチを備えた2段階高速閉鎖トンネルの支持構造であって、
トンネルの周方向に沿って、頂部のボールト、底部の逆アーチ及び両側の側壁を備え、トンネルの径方向に沿って、外層における第一層の一次ライニング、内層における二次ライニング及び前記第一層の一次ライニングと前記二次ライニングの間に設けられた防水層を備え、前記防水層は、ジオテキスタイル及び防水パネルを備えており、
前記第一層の一次ライニングは、第一層の上部ステップ一次ライニングと第一層の下部ステップ一次ライニングを含み、前記第一層の上部ステップ一次ライニングは第一の上部ステップ鋼製アーチを備え、前記第一層の下部ステップ一次ライニングは第一の下部ステップ鋼製アーチを備え、前記第一の上部ステップ鋼製アーチと前記第一の下部ステップ鋼製アーチは、頭尾結合して閉じたリングを形成し、
前記支持構造は、前記第一層の一次ライニングと前記防水層の間に設けられた第二層の一次ライニングを備え、前記第二層の一次ライニングはトンネルの径方向に沿って設けられ、前記第二層の一次ライニングは、第二層の上部ステップ一次ライニングと第二層の下部ステップ一次ライニングを備え、前記第二層の上部ステップ一次ライニングは、第二の上部ステップ鋼製アーチを備え、前記第二層の下部ステップ一次ライニングは、第二の下部ステップ鋼製アーチを備え、前記第二の上部ステップ鋼製アーチと前記第二の下部ステップ鋼製アーチは、頭尾結合して閉じたリングを形成する
ことを特徴とする逆アーチを備えた2段階高速閉鎖トンネルの支持構造。
A support structure for a two-stage rapid closing tunnel with inverted arches, comprising:
along the circumference of the tunnel, with a vault at the top, an inverted arch at the bottom and side walls on both sides; a waterproof layer provided between a primary lining and said secondary lining of said waterproof layer comprising a geotextile and a waterproof panel;
said first layer of primary lining comprising a first layer of upper step primary lining and a first layer of lower step primary lining, said first layer of upper step primary lining comprising a first upper step steel arch; said first layer of lower step primary lining comprising a first lower step steel arch, said first upper step steel arch and said first lower step steel arch forming a head-to-tail closed ring; to form
Said support structure comprises a second layer of primary lining provided between said first layer of primary lining and said waterproof layer, said second layer of primary lining provided along a radial direction of the tunnel, said a second layer of primary lining comprising a second layer of upper step primary lining and a second layer of lower step primary lining, said second layer of upper step primary lining comprising a second upper step steel arch; Said second layer lower step primary lining comprises a second lower step steel arch, said second upper step steel arch and said second lower step steel arch being closed head-to-tail. A support structure for a two-stage high-velocity closed tunnel with inverted arches, characterized in that they form a ring.
前記第一の上部ステップ鋼製アーチは、順に接続された第一の側壁鋼製アーチ、第一の頂部鋼製アーチ、第二の側壁鋼製アーチを備え、前記第一の下部ステップ鋼製アーチは、順に接続された第三の側壁鋼製アーチ、第四の側壁鋼製アーチ、第一の底部鋼製アーチ、第五の側壁鋼製アーチ、第六の側壁鋼製アーチを備え、前記第三の側壁鋼製アーチの第一端の端部と前記第一の側壁鋼製アーチは接続され、前記第三の側壁鋼製アーチの第二端は下向きに延在し、前記第四の側壁鋼製アーチは前記第三の側壁鋼製アーチの前記第一端の側辺に接続され、前記第六の側壁鋼製アーチの第一端の端部と前記第二の側壁鋼製アーチは接続され、前記第六の側壁鋼製アーチの第二端は下向きに延在し、前記第五の側壁鋼製アーチは前記第六の側壁鋼製アーチの前記第一端の側辺に接続される
ことを特徴とする請求項1に記載の支持構造。
said first upper step steel arch comprising a first sidewall steel arch, a first top steel arch and a second sidewall steel arch connected in sequence; said first lower step steel arch; comprises a third sidewall steel arch, a fourth sidewall steel arch, a first bottom steel arch, a fifth sidewall steel arch, a sixth sidewall steel arch, connected in sequence; The end of the first end of the three side wall steel arches and said first side wall steel arch are connected, the second end of said third side wall steel arch extends downwards, and said fourth side wall A steel arch is connected to the side edge of the first end of the third side wall steel arch, and the end of the first end of the sixth side wall steel arch and the second side wall steel arch are connected. and the second end of the sixth side wall steel arch extends downward, and the fifth side wall steel arch is connected to the side of the first end of the sixth side wall steel arch. 2. The support structure of claim 1, wherein:
前記第二の上部ステップ鋼製アーチは、順に接続された第一の側壁鋼材サポート、第一の頂部鋼材サポート、第二の側壁鋼材サポートを備え、前記第二の下部ステップ鋼製アーチは、順に接続された第三の側壁鋼材サポート、第一の底部鋼材サポート、第四の側壁鋼材サポートを備え、前記第一の側壁鋼材サポートは前記第三の側壁鋼材サポートと接続し、前記第二の側壁鋼材サポートは前記第四の側壁鋼材サポートと接続する
ことを特徴する請求項1に記載の支持構造。
The second upper step steel arch comprises a first sidewall steel support, a first top steel support, a second sidewall steel support connected in sequence, and the second lower step steel arch comprises in sequence a a connected third sidewall steel support, a first bottom steel support and a fourth sidewall steel support, said first sidewall steel support connecting with said third sidewall steel support and said second sidewall steel support 2. The support structure of claim 1, wherein a steel support connects with said fourth sidewall steel support.
前記第一層の一次ライニングと前記第二層の一次ライニングの間には第一層の一次ライニングの予備変形スペースが設けられ、前記第二層の一次ライニングと前記防水層の間には第二層の一次ライニングの予備変形スペースが設けられ、
前記第一層の一次ライニングの予備変形スペースの予備変形量は、前記第二層の一次ライニングの予備変形スペースの予備変形量より大きい
ことを特徴とする請求項1乃至3のいずれか一項に記載の支持構造。
A pre-deformation space of the first layer primary lining is provided between the first layer primary lining and the second layer primary lining, and a second layer primary lining is provided between the second layer primary lining and the waterproof layer. A pre-deformation space for the primary lining of the layer is provided,
The pre-deformation amount of the pre-deformation space of the primary lining of the first layer is larger than the pre-deformation amount of the pre-deformation space of the primary lining of the second layer. Support structure as described.
前記第一層の上部ステップ一次ライニングは、アーチ部ロックボルトユニットを更に備え、
前記アーチ部ロックボルトユニットは、複数の排気装置付きの結合中空ロックボルトを備え、複数の前記結合中空ロックボルトは、トンネルの周方向と縦方向に沿って前記ボールトに配置される
ことを特徴とする請求項1乃至4のいずれか一項に記載の支持構造。
the first layer upper step primary lining further comprising an arch lock bolt unit;
wherein said arch lock bolt unit comprises a plurality of combined hollow lock bolts with exhaust devices, said multiple combined hollow lock bolts being arranged in said vault along the circumferential direction and the longitudinal direction of the tunnel. The support structure according to any one of claims 1 to 4.
前記支持構造は、補強ロックボルトユニットを更に備え、
前記補強ロックボルトユニットは、複数のアーチ部の長尺ロックボルト、複数の上部ステップ側壁の長尺ロックボルト、複数の下部ステップ側壁の長尺ロックボルト、複数のトンネル底部の長尺ロックボルトを備え、
複数の前記アーチ部の長尺ロックボルトは、トンネルの周方向と縦方向に沿って前記ボールトに配置され、
複数の前記上部ステップ側壁の長尺ロックボルトは、トンネルの周方向と縦方向に沿って両側の前記上部ステップ壁に配置され、
複数の前記下部ステップ側壁の長尺ロックボルトは、トンネルの周方向と縦方向に沿って両側の前記下部ステップ壁に配置され、
複数の前記のトンネル底部の長尺ロックボルトは、トンネルの周方向と縦方向に沿ってトンネルの底部に配置される
ことを特徴とする請求項1乃至5のいずれか一項に記載の支持構造。
The support structure further comprises a reinforcing rockbolt unit,
The reinforcing rock bolt unit comprises a plurality of arch long rock bolts, a plurality of upper step sidewall long rock bolts, a plurality of lower step sidewall long rock bolts, and a plurality of tunnel bottom long rock bolts. ,
A plurality of long rock bolts of the arch portion are arranged in the vault along the circumferential direction and the longitudinal direction of the tunnel,
a plurality of elongated rock bolts of the upper step sidewall are arranged on both sides of the upper step sidewall along the circumferential and longitudinal directions of the tunnel;
a plurality of long rock bolts of the lower step sidewalls are arranged on both sides of the lower step sidewalls along the circumferential and longitudinal directions of the tunnel;
6. A support structure according to any one of claims 1 to 5, characterized in that a plurality of said tunnel bottom elongated rock bolts are arranged in the tunnel bottom along the circumferential and longitudinal directions of the tunnel. .
逆アーチを備えた2段階高速閉鎖トンネルの支持構造の施工方法であって、
上部ステップの先受けサポート及び上部ステップの先受け補強用ロックボルトを設ける工程、
トンネルの上部ステップ胴部を掘削する工程、
第一層の上部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、
トンネルの下部ステップ胴部を掘削する工程、
第一層の下部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、
下部ステップ側壁の長尺ロックボルト及びトンネル底部の長尺ロックボルトを設ける工程、
第二層の下部ステップ一次ライニングを設け、コンクリートを吹き付けて、トンネル底部の埋め戻しをする工程、
上部ステップ側壁の長尺ロックボルト及びボールトの長尺ロックボルトを設ける工程、
第二層の上部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、
逆アーチの打設及び逆アーチの充填打設を行う工程、
二次ライニングを打設する工程、を含む
ことを特徴とする逆アーチを備えた2段階高速閉鎖トンネルの支持構造の施工方法。
A method of constructing a support structure for a two-stage fast-closing tunnel with an inverted arch, comprising:
a step of providing a front support for the upper step and a rock bolt for reinforcing the front support for the upper step;
excavating the upper step body of the tunnel;
providing the upper step primary lining of the first layer and spraying concrete;
excavating the lower step body of the tunnel;
providing a lower step primary lining of the first layer and spraying concrete;
providing an elongated rock bolt on the lower step sidewall and an elongated rock bolt on the bottom of the tunnel;
providing a second layer lower step primary lining and spraying concrete to backfill the bottom of the tunnel;
providing an upper step side wall elongated lock bolt and a vault elongated lock bolt;
providing a second layer of upper step primary lining and spraying concrete;
a step of casting the reverse arch and filling the reverse arch;
placing a secondary lining.
前記施工方法において、
トンネルを掘削して貫通したか否かを判断し、貫通していない場合、前記上部ステップ側壁の長尺ロックボルト及びボールトの長尺ロックボルトを打ち込むとともに、トンネルの縦方向に沿って次々と、前記上部ステップの先受けサポート及び上部ステップの先受け補強用ロックボルトを設ける工程、前記トンネルの上部ステップ胴部を掘削する工程、前記第一層の上部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、前記トンネルの下部ステップ胴部を掘削する工程、前記第一層の下部ステップ一次ライニングを設けて、コンクリートを吹き付ける工程、前記下部ステップ側壁の長尺ロックボルト及びトンネル底部の長尺ロックボルトを設ける工程、前記第二層の下部ステップ一次ライニングを設け、コンクリートを吹き付けて、トンネル底部の埋め戻しをする工程を順次行って、短いステップを形成して環状構造に速やかに閉じて施工を循環的に前進させる
ことを特徴とする請求項7に記載の施工方法。
In the construction method,
It is determined whether or not the tunnel has been excavated and penetrated, and if it has not been penetrated, the long rock bolt of the upper step side wall and the long rock bolt of the vault are driven in, and one after another along the longitudinal direction of the tunnel, providing pre-receiving supports of the upper step and pre-reinforcing rock bolts of the upper step; excavating the body of the upper step of the tunnel; providing the primary lining of the upper step of the first layer and spraying concrete; , excavating the body of the lower step of the tunnel, providing the primary lining of the lower step of the first layer and spraying concrete, and providing long rock bolts on the side walls of the lower step and long rock bolts at the bottom of the tunnel. In the process, the lower step of the second layer is provided with the primary lining, the concrete is sprayed, and the bottom of the tunnel is backfilled. The construction method according to claim 7, characterized by advancing.
前記上部ステップの先受けサポートは、複数の先受け注入小管を備え、
複数の前記先受け注入小管は、トンネルの周方向及び縦方向に沿って配置される
ことを特徴とする請求項7又は8に記載の施工方法。
said upper step pre-receiving support comprising a plurality of pre-receiving injection canaliculi;
The construction method according to claim 7 or 8, wherein the plurality of pre-received injection small pipes are arranged along the circumferential direction and longitudinal direction of the tunnel.
前記上部ステップ先受け補強用ロックボルトは複数の縦方向のロックボルトを有し、複数の前記縦方向のロックボルトは、トンネルの縦方向に沿ってトンネル上部ステップのトンネル切羽面に配置される
ことを特徴とする請求項7乃至8のいずれか一項に記載の施工方法。
The anticipatory reinforcing rock bolt of the upper step has a plurality of longitudinal rock bolts, and the plurality of longitudinal rock bolts are arranged on the tunnel face of the tunnel upper step along the longitudinal direction of the tunnel. The construction method according to any one of claims 7 to 8, characterized in that:
JP2021514999A 2019-06-19 2019-10-17 SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH Active JP7125550B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201910532043.7A CN110130948B (en) 2019-06-19 2019-06-19 A two-step fast-closed tunnel support structure with an invert and a construction method thereof
CN201910532043.7 2019-06-19
PCT/CN2019/111619 WO2020253001A1 (en) 2019-06-19 2019-10-17 Two-step fast closed tunnel support structure having inverted arch and construction method therefor

Publications (2)

Publication Number Publication Date
JP2022500579A JP2022500579A (en) 2022-01-04
JP7125550B2 true JP7125550B2 (en) 2022-08-24

Family

ID=67578133

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021514999A Active JP7125550B2 (en) 2019-06-19 2019-10-17 SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH

Country Status (3)

Country Link
JP (1) JP7125550B2 (en)
CN (1) CN110130948B (en)
WO (1) WO2020253001A1 (en)

Families Citing this family (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130948B (en) * 2019-06-19 2025-02-07 中铁十九局集团第六工程有限公司 A two-step fast-closed tunnel support structure with an invert and a construction method thereof
CN111140251A (en) * 2020-01-19 2020-05-12 四川省交通勘察设计研究院有限公司 Supporting structure and method for limiting horizontal displacement of steep-dip phyllite tunnel
CN111594182A (en) * 2020-05-14 2020-08-28 北京交通大学 A large deformation control method for large buried deep soft rock tunnel
CN111734455A (en) * 2020-06-24 2020-10-02 高军 Rapid construction method for synchronous excavation of two step inverted arches of soft rock large deformation tunnel
CN112196582B (en) * 2020-10-15 2023-02-24 中铁二局第二工程有限公司 Method for controlling severe deformation of strong-earthquake deep-buried soft rock stratum tunnel
CN112196581B (en) * 2020-10-15 2022-10-28 中铁二局第二工程有限公司 Soft rock tunnel construction supporting time determination method
CN112854113B (en) * 2020-12-31 2022-07-15 中铁七局集团武汉工程有限公司 Inverted arch template applied to inverted siphon pipeline with three-pipe-in-one concrete structure
CN112727473A (en) * 2021-02-04 2021-04-30 中铁二院工程集团有限责任公司 Pre-anchoring rapid tunneling construction method for high-ground-stress large-deformation tunnel
CN113153308B (en) * 2021-03-09 2023-12-08 中铁八局集团有限公司 Construction method for collapse section of double-arch tunnel
CN113187514B (en) * 2021-05-25 2024-02-23 中铁九局集团第七工程有限公司 A construction method for the swallowtail section of urban railway mining method tunnel
CN115614074A (en) * 2021-07-16 2023-01-17 中铁上海设计院集团有限公司 Active advanced reinforcement underground excavation tunnel construction method
CN113586079B (en) * 2021-08-24 2024-02-13 中国电建集团中南勘测设计研究院有限公司 Tunnel cross intersection structure and construction method thereof
CN113482671B (en) * 2021-08-24 2024-03-15 兰州交通大学 Construction method for restraining tunnel primary support sinking based on step method excavation
CN113669082A (en) * 2021-09-09 2021-11-19 中铁隧道集团二处有限公司 Tunnel inverted arch filling construction method containing central ditch
CN113982639B (en) * 2021-10-16 2022-06-17 北京城建道桥建设集团有限公司 Tunnel lining full-ring dismantling and replacing construction method in unfavorable geological region
CN114483054A (en) * 2022-03-07 2022-05-13 中铁隧道局集团有限公司 Non-explosive excavation construction method for pilot tunnel in upper soft and lower hard stratum
CN114961787B (en) * 2022-05-17 2025-11-14 中铁十九局集团第六工程有限公司 Protective devices for tunnel steel arch joints and methods for protecting tunnel initial support steel arch joints.
CN114837702B (en) * 2022-05-20 2025-07-25 中交第二航务工程局有限公司 Multistage yielding steel arch frame limiter and construction method
CN115387379B (en) * 2022-07-28 2023-07-04 中铁隧道局集团有限公司 Support structure for prefabricated arc-shaped component and application thereof
CN115419435B (en) * 2022-08-02 2025-06-17 中铁第五勘察设计院集团有限公司 A grouting reinforcement method for shield tunnel section dark excavation communication channel
CN115288193A (en) * 2022-08-08 2022-11-04 中铁二局集团有限公司 Space large-span dome structure construction method based on multilayer operation platform
CN115478869B (en) * 2022-08-26 2024-05-17 中铁第一勘察设计院集团有限公司 Tunnel intersection structure and construction method
CN115478873B (en) * 2022-08-29 2025-03-21 中铁十五局集团有限公司 Construction method of a traveling primary branch segment positioning device suitable for tunnels with different inner diameters
CN115492613B (en) * 2022-08-29 2025-03-25 中铁十五局集团有限公司 A construction method for temporary supporting structure of corrugated plate for initial support of traveling tunnel
CN115306424B (en) * 2022-08-29 2023-07-21 中国建筑第二工程局有限公司 Large-section transverse channel horsehead door breaking operation platform and construction method
CN115324613A (en) * 2022-09-23 2022-11-11 中铁三局集团桥隧工程有限公司 Construction method for excavating and supporting extra-large section double-line tunnel in soft rock large-deformation section
CN116427938A (en) * 2023-05-05 2023-07-14 四川省交通建设集团有限责任公司 A construction method for a shallow buried section of a tunnel
CN116517595B (en) * 2023-06-27 2023-09-05 矿冶科技集团有限公司 Soft broken rock mass chamber reinforcing structure and method
CN118278083B (en) * 2024-04-02 2025-12-26 四川华能泸定水电有限公司 A method for optimizing core soil dimensions based on controlling pre-deformation of the tunnel face

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000303797A (en) 1999-04-19 2000-10-31 Kfc Ltd Shoring joint and shoring structure using it
JP2005344346A (en) 2004-06-02 2005-12-15 Japan Railway Construction Transport & Technology Agency Steel pipe placing method
JP2006233626A (en) 2005-02-25 2006-09-07 National Institute Of Advanced Industrial & Technology Tunnel structure
JP2010116739A (en) 2008-11-13 2010-05-27 Shimizu Corp Tunnel supporting method and tunnel supporting structure
CN101906975A (en) 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 A support structure and construction method for an extra-large section loess tunnel passing under a railway
CN102996148A (en) 2012-11-22 2013-03-27 中交第二公路勘察设计研究院有限公司 A Supporting Method for High Ground Stress Soft Rock Highway Tunnel
JP2017002720A (en) 2016-10-12 2017-01-05 フジモリ産業株式会社 Tunnel boring method
JP2018040201A (en) 2016-09-09 2018-03-15 株式会社ビーエスアイ Composite waterproofing and heat insulation sheet and waterproofing sheet for tunnel, and installation method of composite sheet
CN108180025A (en) 2018-01-31 2018-06-19 中铁二十局集团轨道交通工程有限公司 A kind of circular cross section tunnel lining construction method three times
JP2018131865A (en) 2017-02-17 2018-08-23 大成建設株式会社 Tunnel support
CN110295925A (en) 2018-03-21 2019-10-01 中铁二院(成都)建设发展有限责任公司 Red beds sand shale serious deformation paragraph construction method

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58207497A (en) * 1982-05-26 1983-12-02 財団法人鉄道総合技術研究所 Method of formation construction of inner wall of tunnel
JPH08165899A (en) * 1994-12-13 1996-06-25 Shigeki Nagatomo Tunnel lining method using timbering concurrently serving as reinforcing bar
JPH09217594A (en) * 1996-02-13 1997-08-19 Fujita Corp How to support the tunnel
CN103527219B (en) * 2013-10-18 2016-03-16 四川省交通运输厅公路规划勘察设计研究院 For the construction of the tunnel support structure on large deformation stratum
CN104533446B (en) * 2015-01-16 2017-06-06 中交一公局第一工程有限公司 Construction method and its structure that a kind of big cross section Support System in Soft Rock Tunnels bilayer pre- Geological disaster prevention of preliminary bracing occurs
CN104847374B (en) * 2015-04-24 2017-05-31 长安大学 Large-deformation tunnel in soft rock support system and its construction method
CN205503151U (en) * 2016-04-07 2016-08-24 广州市水电建设工程有限公司 Be applied to deep tunnel drainage engineering's underground structure
CN106761810B (en) * 2016-11-23 2019-06-11 长安大学 A soft rock large deformation tunnel supporting structure system and its construction method
CN108952783A (en) * 2018-08-01 2018-12-07 中铁十九局集团第六工程有限公司 A kind of dual supporting pre-embedded construction method in tunnel
CN109826632B (en) * 2019-03-26 2020-06-16 西南交通大学 A large deformation control method for single-track tunnel in soft and broken carbonaceous shale
CN110130948B (en) * 2019-06-19 2025-02-07 中铁十九局集团第六工程有限公司 A two-step fast-closed tunnel support structure with an invert and a construction method thereof
CN210178380U (en) * 2019-06-19 2020-03-24 中铁十九局集团第六工程有限公司 A two-step and inverted arch fast-closing tunnel support structure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000303797A (en) 1999-04-19 2000-10-31 Kfc Ltd Shoring joint and shoring structure using it
JP2005344346A (en) 2004-06-02 2005-12-15 Japan Railway Construction Transport & Technology Agency Steel pipe placing method
JP2006233626A (en) 2005-02-25 2006-09-07 National Institute Of Advanced Industrial & Technology Tunnel structure
JP2010116739A (en) 2008-11-13 2010-05-27 Shimizu Corp Tunnel supporting method and tunnel supporting structure
CN101906975A (en) 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 A support structure and construction method for an extra-large section loess tunnel passing under a railway
CN102996148A (en) 2012-11-22 2013-03-27 中交第二公路勘察设计研究院有限公司 A Supporting Method for High Ground Stress Soft Rock Highway Tunnel
JP2018040201A (en) 2016-09-09 2018-03-15 株式会社ビーエスアイ Composite waterproofing and heat insulation sheet and waterproofing sheet for tunnel, and installation method of composite sheet
JP2017002720A (en) 2016-10-12 2017-01-05 フジモリ産業株式会社 Tunnel boring method
JP2018131865A (en) 2017-02-17 2018-08-23 大成建設株式会社 Tunnel support
CN108180025A (en) 2018-01-31 2018-06-19 中铁二十局集团轨道交通工程有限公司 A kind of circular cross section tunnel lining construction method three times
CN110295925A (en) 2018-03-21 2019-10-01 中铁二院(成都)建设发展有限责任公司 Red beds sand shale serious deformation paragraph construction method

Also Published As

Publication number Publication date
CN110130948A (en) 2019-08-16
WO2020253001A1 (en) 2020-12-24
JP2022500579A (en) 2022-01-04
CN110130948B (en) 2025-02-07

Similar Documents

Publication Publication Date Title
JP7125550B2 (en) SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH
CN104847374B (en) Large-deformation tunnel in soft rock support system and its construction method
CN102562099B (en) Method for carrying out rapid face excavation construction of loess tunnel by double rows of small conduits
CN109736827B (en) Excavation method of high-pressure gas expansion-induced cracking in the connection channel of urban subway hard rock strata
CN107091101B (en) Superimposed joint structure of middle mine shield junction tunnel in sea area and construction method
CN111119935B (en) A multi-layer grouting reinforcement method for surrounding rock of soft and broken structure of roadway
CN108442943A (en) A kind of branch-cut bridge section tunnel and Double side heading method construction method
CN114033407B (en) A TBM construction method under adverse geological conditions
CN101806217A (en) Three-line parallel small-clear-distance shallow-buried and bias tunnel group hole-entering construction method
CN112443331B (en) Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN114412475A (en) Reverse tunnel exit construction method for shallow-buried broken surrounding rock
CN110159298A (en) A kind of first branch button arch construction method of Underground Subway Station
CN208236427U (en) Large deformation weak broken wall rock outsized section tunnel excavation supporting structure
CN102979531A (en) Construction method and structure for reinforcing large rock slope deep weak structural plane
CN106894830B (en) A double-curved arch support structure and construction method for underground engineering
CN110905536A (en) Construction method for receiving complex stratum earth pressure shield in underground excavation tunnel
CN114233300A (en) A construction method for one-way excavation of a tunnel near the entrance of the tunnel
CN113565513A (en) Upper and lower step reserved core soil excavation method for tunnel excavation
CN116397694A (en) Arch protection structure and construction method of excavation and cover-excavation of tunnel under partial pressure in shallow buried section
CN109339800A (en) A rapid construction method of tunnel in the connecting section of bridge and tunnel
CN112127910B (en) Tunnel construction extra-front supporting sheath arch structure
CN210178380U (en) A two-step and inverted arch fast-closing tunnel support structure
CN116398165A (en) A new tunnel under zero distance passing through an existing station and its construction method
CN108843339B (en) The auxiliary slip casting platform and construction method of large-scale solution cavity are passed through when existing tunnel digs

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210317

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220510

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220726

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220809

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220812

R150 Certificate of patent or registration of utility model

Ref document number: 7125550

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250