JP7265566B2 - Method for evaluating construction condition of air flow passage and method for manufacturing building - Google Patents
[go: Go Back, main page]

JP7265566B2 - Method for evaluating construction condition of air flow passage and method for manufacturing building - Google Patents

Method for evaluating construction condition of air flow passage and method for manufacturing building Download PDF

Info

Publication number
JP7265566B2
JP7265566B2 JP2021009326A JP2021009326A JP7265566B2 JP 7265566 B2 JP7265566 B2 JP 7265566B2 JP 2021009326 A JP2021009326 A JP 2021009326A JP 2021009326 A JP2021009326 A JP 2021009326A JP 7265566 B2 JP7265566 B2 JP 7265566B2
Authority
JP
Japan
Prior art keywords
air
evaluating
duct
air volume
inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021009326A
Other languages
Japanese (ja)
Other versions
JP2022113241A (en
Inventor
大輔 梅本
耕一 伊吹
忠司 吉本
Original Assignee
パナソニックホームズ株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by パナソニックホームズ株式会社 filed Critical パナソニックホームズ株式会社
Priority to JP2021009326A priority Critical patent/JP7265566B2/en
Publication of JP2022113241A publication Critical patent/JP2022113241A/en
Application granted granted Critical
Publication of JP7265566B2 publication Critical patent/JP7265566B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/70Efficient control or regulation technologies, e.g. for control of refrigerant flow, motor or heating

Landscapes

  • Central Air Conditioning (AREA)
  • Air Conditioning Control Device (AREA)

Description

本発明は、送風流路の施工状態評価方法、及び、建物の製造方法に関する。 BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for evaluating the construction state of airflow passages and a method for manufacturing a building.

下記特許文献1には、ダクトを含む送風流路を備えた建物が記載されている。この送風流路には、空気を供給するためのファンが接続されており、その少なくとも一部が、天井材や床材等の建材に囲まれた閉空間内を通るように設置されている。 Patent Literature 1 listed below describes a building provided with an air flow path including a duct. A fan for supplying air is connected to the airflow passage, and at least a part of the fan is installed so as to pass through a closed space surrounded by building materials such as ceiling materials and floor materials.

特開2017-083097号公報JP 2017-083097 A

ところで、建物内にダクトを取り回す施工時においては、ダクトに想定外の曲げや潰れ等が生じることがある。これらの曲げや潰れ等は、ダクトの圧力損失を大きくし、必要な風量の確保が困難となる。そして、このような施工状態の不具合が、閉空間が建材で閉じられた後に発見された場合には、建材を一旦取り外して、ダクトの施工状態を改修する必要が生じるという問題があった。 By the way, unexpected bending, crushing, or the like may occur in the duct during construction work for arranging the duct inside the building. Such bending, crushing, or the like increases the pressure loss of the duct, making it difficult to secure the required air volume. If such a defect in the construction state is discovered after the closed space is closed with building materials, there is a problem that the building materials need to be temporarily removed and the construction state of the duct needs to be repaired.

本発明は、以上のような実状に鑑み案出されたもので、閉空間が建材で閉じられる前に、ダクトの施工状態を評価することが可能な方法を提供することを主たる目的としている。 The present invention has been devised in view of the actual situation as described above, and its main object is to provide a method capable of evaluating the construction state of a duct before a closed space is closed with building materials.

本発明は、建物を製造する過程で、前記建物内を延びるダクトを含む送風流路の施工状態を評価するための方法であって、前記送風流路は、入口と、出口とを有し、かつ、第1のファンから供給される空気を前記入口から前記出口に搬送することが予定されており、かつ、前記ダクトの少なくとも一部が建材で囲まれた閉空間内を通るように設置されるものであり、前記方法は、前記閉空間が前記建材で閉じられる前に、前記第1のファンよりも風量が小さい第2のファンを用いて、前記送風流路の前記入口に予め定められた風量で空気を供給する工程と、前記送風流路の前記入口又は前記出口での風量を測定する工程と、測定された前記風量と、前記風量に対する予め定められた閾値とに基づいて、前記ダクトの施工状態を評価する工程とを実行することを特徴とする。 The present invention is a method for evaluating the construction status of a ventilation channel including a duct extending through the building during the process of manufacturing a building, wherein the ventilation channel has an inlet and an outlet, Further, the air supplied from the first fan is planned to be conveyed from the inlet to the outlet, and at least part of the duct is installed so as to pass through a closed space surrounded by building materials. The method uses a second fan having a smaller air volume than the first fan to pre-determine at the inlet of the air flow path before the closed space is closed with the building material. measuring the air volume at the inlet or the outlet of the air flow path; based on the measured air volume and a predetermined threshold value for the air volume, the and a step of evaluating the construction state of the duct.

本発明に係る前記送風流路の施工状態評価方法において、前記評価する工程は、前記入口又は前記出口での風量が前記閾値以上である場合に、前記ダクトの施工状態が良好であると評価してもよい。 In the method for evaluating the construction state of the air flow passage according to the present invention, the evaluating step evaluates that the construction state of the duct is good when the air volume at the inlet or the outlet is equal to or greater than the threshold value. may

本発明に係る前記送風流路の施工状態評価方法において、前記入口又は前記出口での風量が前記閾値以上である場合に、前記閉空間を前記建材で閉じる工程をさらに含んでもよい。 The method for evaluating the construction state of the air flow passage according to the present invention may further include closing the closed space with the building material when the air volume at the inlet or the outlet is equal to or greater than the threshold value.

本発明に係る前記送風流路の施工状態評価方法において、前記評価する工程は、前記入口又は前記出口での風量が前記閾値未満である場合に、前記ダクトの施工状態が良好でないと評価してもよい。 In the method for evaluating the construction state of the air flow passage according to the present invention, the evaluating step evaluates that the construction state of the duct is not good when the air volume at the inlet or the outlet is less than the threshold value. good too.

本発明に係る前記送風流路の施工状態評価方法において、前記入口又は前記出口での風量が前記閾値未満である場合に、前記入口又は前記出口での風量が前記閾値以上になるように、前記ダクトの施工状態を改修する工程をさらに含んでもよい。 In the method for evaluating the construction state of the air flow passage according to the present invention, when the air volume at the entrance or the exit is less than the threshold, the air volume at the entrance or the exit is equal to or greater than the threshold. A step of refurbishing the construction condition of the duct may be further included.

本発明に係る前記送風流路の施工状態評価方法において、前記評価する工程に先立ち、前記閾値を決定する工程をさらに含み、前記閾値を決定する工程は、前記第2のファンの静圧と風量との関係を示す第1曲線と、前記送風流路の圧力損失と風量との関係を示す第2曲線との交点での風量に基づいて、前記閾値を決定してもよい。 The method for evaluating the construction state of the air flow path according to the present invention further includes the step of determining the threshold value prior to the evaluating step, wherein the step of determining the threshold value is based on the static pressure and the air volume of the second fan. and a second curve representing the relationship between the pressure loss of the air flow path and the air volume.

本発明は、建物を製造する過程で、前記建物内を延びるダクトを含む送風流路の施工状態を評価するための方法であって、前記送風流路は、入口と、出口とを有し、かつ、第1のファンから供給される空気を前記入口から前記出口に搬送することが予定されており、かつ、前記ダクトの少なくとも一部が建材で囲まれた閉空間内を通るように設置されるものであり、前記方法は、前記閉空間が前記建材で閉じられる前に、定風量の第2のファンを用いて、前記送風流路の前記入口に予め定められた風量で空気を供給する工程と、前記第2のファンの回転数を測定する工程と、測定された前記回転数と、前記回転数に対する予め定められた閾値とに基づいて、前記ダクトの施工状態を評価する工程とを実行することを特徴とする。 The present invention is a method for evaluating the construction status of a ventilation channel including a duct extending through the building during the process of manufacturing a building, wherein the ventilation channel has an inlet and an outlet, Further, the air supplied from the first fan is planned to be conveyed from the inlet to the outlet, and at least part of the duct is installed so as to pass through a closed space surrounded by building materials. wherein, before the closed space is closed with the building material, a second fan with a constant air volume is used to supply air at a predetermined air volume to the inlet of the air flow path. measuring the number of revolutions of the second fan; and evaluating the construction state of the duct based on the measured number of revolutions and a predetermined threshold for the number of revolutions. characterized by executing

本発明に係る前記送風流路の施工状態評価方法において、前記評価する工程は、前記測定された回転数が前記閾値未満である場合に、前記ダクトの施工状態が良好であると評価してもよい。 In the method for evaluating the construction state of the air flow passage according to the present invention, the evaluating step includes evaluating that the construction state of the duct is good when the measured rotational speed is less than the threshold value. good.

本発明に係る前記送風流路の施工状態評価方法において、前記評価する工程は、前記測定された回転数が前記閾値以上である場合に、前記ダクトの施工状態が良好でないと評価してもよい。 In the method for evaluating the construction state of the air flow passage according to the present invention, the evaluating step may evaluate that the construction state of the duct is not good when the measured rotational speed is equal to or greater than the threshold value. .

本発明は、建物内を延びるダクトを含む送風流路を備えた建物と製造方法であって、上記の送風流路の施工状態評価方法を含むことを特徴とする。 The present invention provides a building and a manufacturing method having an air flow path including a duct extending inside the building, and is characterized by including the above-described method for evaluating the construction state of the air flow path.

本発明の送風流路の施工状態評価方法は、上記の工程を採用することにより、閉空間が建材で閉じられる前に、ダクトの施工状態を評価することが可能となる。 By adopting the above-described steps, the method for evaluating the construction state of the air flow path of the present invention makes it possible to evaluate the construction state of the duct before the closed space is closed with building materials.

建物の一例を示す概念図である。1 is a conceptual diagram showing an example of a building; FIG. 送風流路の施工状態評価方法の処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of the processing procedure of the construction state evaluation method of an air flow path. 送風流路の施工状態評価方法の一例を説明するための概念図である。It is a conceptual diagram for demonstrating an example of the construction state evaluation method of an air flow path. 第1曲線及び第2曲線の一例を示すグラフである。It is a graph which shows an example of a 1st curve and a 2nd curve. 本発明の他の実施形態の送風流路の施工状態評価方法の処理手順の一例を示すフローチャートである。It is a flowchart which shows an example of the processing procedure of the construction state evaluation method of the ventilation flow path of other embodiment of this invention. (a)は、第2曲線の一例を示すグラフ、(b)は、第2のファンの静圧と回転数との関係を示すグラフである。(a) is a graph showing an example of a second curve, and (b) is a graph showing the relationship between the static pressure and rotation speed of a second fan.

以下、本発明の実施形態が図面に基づき説明される。図面は、発明の内容の理解を助けるために、誇張表現や、実際の構造の寸法比とは異なる表現が含まれることが理解されなければならない。また、各実施形態を通して、同一又は共通する要素については同一の符号が付されており、重複する説明が省略される。さらに、実施形態及び図面に表された具体的な構成は、本発明の内容理解のためのものであって、本発明は、図示されている具体的な構成に限定されるものではない。 BEST MODE FOR CARRYING OUT THE INVENTION Hereinafter, embodiments of the present invention will be described based on the drawings. It should be understood that the drawings include exaggerated representations and representations that differ from the dimensional ratios of the actual structures in order to facilitate understanding of the content of the invention. In addition, throughout each embodiment, the same or common elements are denoted by the same reference numerals, and overlapping descriptions are omitted. Furthermore, the specific configurations shown in the embodiments and drawings are for understanding the content of the present invention, and the present invention is not limited to the illustrated specific configurations.

本実施形態の送風流路の施工状態評価方法(以下、単に「評価方法」ということがある。)では、建物を製造する過程で、建物内を延びるダクトを含む送風流路の施工状態が評価される。図1は、建物2の一例を示す概念図である。 In the method for evaluating the construction state of the air flow passage of the present embodiment (hereinafter, sometimes simply referred to as the "evaluation method"), the construction state of the air flow passage including the duct extending inside the building is evaluated in the process of manufacturing the building. be done. FIG. 1 is a conceptual diagram showing an example of a building 2. As shown in FIG.

[建物]
本実施形態の建物2は、住宅である場合が例示されているが、ビル等であってもよい。本実施形態の建物2は、床下空間3と、床上空間4とを含んで構成されている。
[building]
The building 2 in this embodiment is illustrated as a house, but may be a building or the like. The building 2 of this embodiment includes an underfloor space 3 and an abovefloor space 4 .

[床下空間]
床下空間3は、基礎5と地面と1階の床6(床材6a)とで囲まれた空間である。基礎5には、外気A1を取り入れるための開口部7が設けられている。外気A1は、開口部7から取り入れられた後に、1年を通じて温度変化の少ない地中の熱と、地面を介して熱交換される。これにより、床下空間3には、外気に比べて、夏期は比較的涼しく、冬期は比較的暖かい空気(以下、単に「床下空気」ということがある。)を蓄えることができる。
[Underfloor space]
The underfloor space 3 is a space surrounded by the foundation 5, the ground, and the first floor floor 6 (floor material 6a). The foundation 5 is provided with an opening 7 for taking in outside air A1. After the outside air A1 is taken in from the opening 7, it is heat-exchanged via the ground with underground heat whose temperature changes little throughout the year. As a result, the underfloor space 3 can store air that is relatively cooler in summer and relatively warmer in winter than the outside air (hereinafter sometimes simply referred to as "underfloor air").

[床上空間]
床上空間4は、床下空間3の上方に設けられた空間である。本実施形態の床上空間4は、居室10と、小屋裏8とを含んで構成されている。
[Floor space]
The floor space 4 is a space provided above the underfloor space 3 . The above-floor space 4 of this embodiment includes a living room 10 and an attic 8 .

[居室]
本実施形態の居室10は、建物2の1階に設けられているが、2階以上にも設けられてもよい。居室10は、例えば、外壁11、間仕切り壁12及び扉13などで区切られている。本実施形態の居室10は、第1居室10A及び第2居室10Bを含んでいるが、いずれか一方のみでもよいし、他の居室がさらに設けられてもよい。
[room]
The living room 10 of the present embodiment is provided on the first floor of the building 2, but may be provided on the second floor or higher. The living room 10 is partitioned by, for example, an outer wall 11, a partition wall 12, a door 13, and the like. The living room 10 of this embodiment includes the first living room 10A and the second living room 10B, but only one of them may be provided, or another living room may be further provided.

[小屋裏]
小屋裏8は、天井14と屋根15とで囲まれた空間である。天井14(天井形成材14a)は、例えば、梁に支持された野縁(図示省略)に固定される。
[Attic]
The attic 8 is a space surrounded by a ceiling 14 and a roof 15. - 特許庁The ceiling 14 (ceiling forming member 14a) is fixed to, for example, joists (not shown) supported by beams.

[送風流路]
本実施形態では、建物2内を延びるダクト16を含む送風流路17が設置されている。本実施形態の送風流路17は、建物2内を換気及び空調するための空調ユニット18に接続されているが、このような態様に限定されない。
[Blower flow path]
In this embodiment, an air flow path 17 including a duct 16 extending inside the building 2 is installed. The air flow path 17 of the present embodiment is connected to an air conditioning unit 18 for ventilating and air conditioning the inside of the building 2, but is not limited to such a mode.

本実施形態の送風流路17は、入口17iと、出口17oとを有している。送風流路17には、入口17i及び出口17oに取り付けられる末端換気口(ベントキャップ)や、エルボ等が設けられてもよい。本実施形態のダクト16は、可撓性を有するフレキシブルダクトである場合が例示されるが、空気を搬送可能なものであれば、特に限定されない。 The air flow path 17 of this embodiment has an inlet 17i and an outlet 17o. The air flow path 17 may be provided with a terminal ventilation port (vent cap) attached to the inlet 17i and the outlet 17o, an elbow, or the like. The duct 16 of the present embodiment is exemplified by a flexible duct, but is not particularly limited as long as it can convey air.

本実施形態の送風流路17の入口17iには、空気を供給可能な第1のファン21が接続されている。これにより、送風流路17は、第1のファン21から供給される空気が、入口17iから出口17oに搬送される。本明細書において、「ファン」は、空気を圧送するための機械である。したがって、ファンは、空気を圧送可能なものであれば、特に限定されない。 A first fan 21 capable of supplying air is connected to the inlet 17i of the airflow path 17 of the present embodiment. As a result, the air supplied from the first fan 21 is conveyed from the inlet 17i to the outlet 17o in the airflow path 17 . As used herein, a "fan" is a machine for pumping air. Therefore, the fan is not particularly limited as long as it can pump air.

本実施形態の送風流路17は、第1送風流路17A、第2送風流路17B及び第3送風流路17Cを含んで構成されている。なお、送風流路17は、例えば、居室10の個数等に応じて、第1送風流路17A~第3送風流路17Cの何れか1つが設けられてもよいし、他の送風流路(図示省略)がさらに設けられてもよい。 The air flow path 17 of this embodiment includes a first air flow path 17A, a second air flow path 17B, and a third air flow path 17C. Note that the air flow path 17 may be provided with any one of the first air flow path 17A to the third air flow path 17C, for example, depending on the number of living rooms 10, or another air flow path ( (illustration omitted) may be further provided.

本実施形態の送風流路17は、ダクト16の少なくとも一部が、建材23で囲まれた閉空間24内を通るように設置されている。本実施形態の閉空間24とは、その内部が、外部から見えにくくされている空間であり、建材23で完全に閉じられた空間に限定されない。 The air flow path 17 of this embodiment is installed such that at least part of the duct 16 passes through a closed space 24 surrounded by building materials 23 . The closed space 24 of the present embodiment is a space whose interior is difficult to see from the outside, and is not limited to a space completely closed with the building materials 23 .

本実施形態の第1送風流路17Aは、そのダクト16の少なくとも一部が、床6と基礎5とで囲まれる床下空間3(閉空間24)内を通るように設置されている。第2送風流路17B及び第3送風流路17Cは、それらのダクト16の少なくとも一部が、天井14と屋根15とで囲まれる小屋裏8(閉空間24)内を通るように設置されている。なお、これらの第1送風流路17A~第3送風流路17Cは、それらのダクト16の少なくとも一部が、例えば、1階の天井と2階の床の間の階間(図示省略)や、間仕切り壁12等で閉じられる空間(図示省略)を含む閉空間内を通るように設置されてもよい。 17 A of 1st air flow paths of this embodiment are installed so that at least one part of the duct 16 may pass through the underfloor space 3 (closed space 24) enclosed by the floor 6 and the foundation 5. As shown in FIG. The second air flow path 17B and the third air flow path 17C are installed such that at least part of the duct 16 passes through the attic 8 (closed space 24) surrounded by the ceiling 14 and the roof 15. there is At least a part of these ducts 16 of the first air flow path 17A to the third air flow path 17C is, for example, between floors (not shown) between the ceiling of the first floor and the floor of the second floor, or a partition It may be installed so as to pass through a closed space including a space (not shown) closed by a wall 12 or the like.

本実施形態の送風流路17(第1送風流路17A~第3送風流路17C)には、曲がり等の局部25が設けられている。このような局部25は、ダクト16を屈曲させる(撓ませる)ことによって形成されてもよいし、図示しないエルボ等にダクト16が接続されることによって形成されてもよい。 A local portion 25 such as a bend is provided in the air flow path 17 (the first air flow path 17A to the third air flow path 17C) of the present embodiment. Such a local portion 25 may be formed by bending (flexing) the duct 16, or may be formed by connecting the duct 16 to an elbow (not shown) or the like.

[第1送風流路]
本実施形態の第1送風流路17Aは、建物2内の換気に用いられる外気(床下空気)A1を、空調ユニット18に搬送するためのものである。第1送風流路17Aの入口17iは、床下空間3に配されている。この入口17iには、第1のファン21によって、外気(床下空気)A1が供給される。一方、第1送風流路17Aの出口17oは、空調ユニット18に接続されている。これにより、第1送風流路17Aは、外気(床下空気)A1を、入口17iから出口17oに搬送して、空調ユニット18に供給することができる。
[First air flow path]
17 A of 1st ventilation flow paths of this embodiment are for conveying outside air (underfloor air) A1 used for the ventilation in the building 2 to the air conditioning unit 18. As shown in FIG. An inlet 17i of the first airflow path 17A is arranged in the underfloor space 3 . Outside air (underfloor air) A1 is supplied to the inlet 17i by the first fan 21 . On the other hand, the outlet 17o of the first air flow path 17A is connected to the air conditioning unit 18. As shown in FIG. Thereby, the first air flow path 17A can convey outside air (underfloor air) A1 from the inlet 17i to the outlet 17o and supply the air conditioning unit 18 with the air.

[第2送風流路]
本実施形態の第2送風流路17Bは、空調ユニット18で生成される換気・空調空気A2を、第1居室10Aに搬送するためのものである。第2送風流路17Bの入口17iは、空調ユニット18に接続されている。この入口17iには、第1のファン21によって、換気・空調空気A2が供給される。一方、第2送風流路17Bの出口17oは、第1居室10Aに接続されている。これにより、第2送風流路17Bは、換気・空調空気A2を、入口17iから出口17oに搬送して、第1居室10Aに供給することができる。
[Second air flow path]
The second airflow path 17B of the present embodiment is for conveying the ventilation/air-conditioning air A2 generated by the air conditioning unit 18 to the first living room 10A. An inlet 17i of the second airflow path 17B is connected to the air conditioning unit 18 . Ventilation/conditioning air A2 is supplied to this inlet 17i by a first fan 21 . On the other hand, the outlet 17o of the second air flow path 17B is connected to the first living room 10A. Thereby, the second ventilation flow path 17B can convey the ventilation/air-conditioning air A2 from the inlet 17i to the outlet 17o and supply it to the first living room 10A.

[第3送風流路]
本実施形態の第3送風流路17Cは、空調ユニット18で生成される換気・空調空気A2を、第2居室10Bに搬送するためのものである。第3送風流路17Cの入口17iは、空調ユニット18に接続されている。この入口17iには、第1のファン21によって、換気・空調空気A2が供給される。一方、第3送風流路17Cの出口17oは、第2居室10Bに接続されている。これにより、第3送風流路17Cは、換気・空調空気A2を、入口17iから出口17oに搬送して、第2居室10Bに供給することができる。
[Third air flow path]
17 C of 3rd ventilation flow paths of this embodiment are for conveying ventilation / air-conditioning air A2 produced|generated by the air conditioning unit 18 to the 2nd living room 10B. An inlet 17i of the third air flow path 17C is connected to the air conditioning unit 18. As shown in FIG. Ventilation/conditioning air A2 is supplied to this inlet 17i by a first fan 21 . On the other hand, the outlet 17o of the third air flow path 17C is connected to the second living room 10B. Thereby, 17 C of 3rd ventilation flow paths can convey ventilation / air conditioning air A2 from the inlet 17i to the outlet 17o, and can supply it to the 2nd living room 10B.

[空調ユニット]
空調ユニット18は、換気・空調空気A2を生成するためのものである。本実施形態の空調ユニット18は、チャンバー26と、チャンバー26の内部に設けられた室内空調機27とを含んで構成されている。
[Air conditioning unit]
The air conditioning unit 18 is for generating ventilation and conditioning air A2. The air conditioning unit 18 of this embodiment includes a chamber 26 and an indoor air conditioner 27 provided inside the chamber 26 .

[チャンバー]
本実施形態のチャンバー26は、その内部に空間(スペース)を有する箱状に形成されている。空間を区画する壁部には、断熱材(図示省略)が配されていてもよい。
[Chamber]
The chamber 26 of this embodiment is formed in a box shape having a space inside. A heat insulating material (not shown) may be arranged on the wall portion that divides the space.

本実施形態のチャンバー26は、外気(床下空気)A1が供給されるように、第1送風流路17Aの出口17oが接続されている。さらに、チャンバー26には、居室10の少なくとも一部の空気(リターン)A3を取り込むための空気導入口28が設けられている。 The chamber 26 of the present embodiment is connected to the outlet 17o of the first air flow passage 17A so as to be supplied with the outside air (underfloor air) A1. Furthermore, the chamber 26 is provided with an air inlet 28 for taking in at least part of the air (return) A3 of the living room 10 .

[室内空調機]
本実施形態の室内空調機27は、一般的な家庭用のセパレート型エアコンである場合が例示される。室内空調機27は、建物2の外部に設置される室外機(図示省略)とセットとして構成されている。本実施形態の室内空調機27は、吸込口27aと吹出口27bとを有している。
[Indoor air conditioner]
The indoor air conditioner 27 of the present embodiment is exemplified by a general household separate air conditioner. The indoor air conditioner 27 is configured as a set with an outdoor unit (not shown) installed outside the building 2 . The indoor air conditioner 27 of this embodiment has an inlet 27a and an outlet 27b.

吸込口27aは、チャンバー26の空気導入口28と、第1送風流路17Aの出口17oとに隣接して設けられている。これにより、吸込口27aには、居室10の空気(リターン空気)A3と、外気(床下空気)A1とが供給されうる。 The suction port 27a is provided adjacent to the air introduction port 28 of the chamber 26 and the outlet 17o of the first air flow path 17A. As a result, air (return air) A3 in living room 10 and outside air (underfloor air) A1 can be supplied to suction port 27a.

吹出口27bからは、これらの混合気(居室10の空気A3及び外気A1)を熱交換した換気・空調空気A2が吐出される。吹出口27bの下流側には、第2送風流路17Bの入口17i、及び、第3送風流路17Cの入口17iが設けられている。これにより、空調ユニット18は、第2送風流路17B及び第3送風流路17Cを介して、換気・空調空気A2を居室10(本例では、第1居室10A及び第2居室10B)に供給することができる。 Ventilation/air-conditioning air A2 obtained by heat-exchanging the mixed gas (the air A3 in the living room 10 and the outside air A1) is discharged from the outlet 27b. An inlet 17i of the second air flow path 17B and an inlet 17i of the third air flow path 17C are provided downstream of the blow-out port 27b. As a result, the air conditioning unit 18 supplies the ventilation/conditioned air A2 to the living room 10 (in this example, the first living room 10A and the second living room 10B) through the second air flow path 17B and the third air flow path 17C. can do.

このように、本実施形態の建物2は、送風流路17(第1送風流路17A~第3送風流路17C)により、外気(床下空気)A1を空調ユニット18に供給しつつ、換気・空調空気A2を居室10に供給することができる。したがって、建物2は、居室10を、換気及び空調することができる。このような換気及び空調を効率よく行うには、送風流路17(第1送風流路17A~第3送風流路17C)において、換気及び空調に必要な風量が確保されているのが重要である。 In this way, the building 2 of the present embodiment supplies outside air (underfloor air) A1 to the air conditioning unit 18 through the air flow paths 17 (first air flow path 17A to third air flow path 17C), Conditioned air A2 can be supplied to the living room 10 . Therefore, the building 2 can ventilate and air-condition the living room 10 . In order to efficiently perform such ventilation and air conditioning, it is important that the air volume necessary for ventilation and air conditioning is secured in the air flow passages 17 (first air flow passage 17A to third air flow passage 17C). be.

[建物の製造方法]
次に、本実施形態の建物2の製造方法(以下、単に「製造方法」ということがある。)が説明される。本実施形態の製造方法では、後述の評価方法を含んでいる点を除き、従来の製造方法と同様の手順に基づいて、建物2が製造される。
[Building manufacturing method]
Next, a method for manufacturing the building 2 of the present embodiment (hereinafter sometimes simply referred to as "manufacturing method") will be described. In the manufacturing method of the present embodiment, the building 2 is manufactured based on the same procedure as the conventional manufacturing method, except that the evaluation method described below is included.

本実施形態の製造方法では、先ず、基礎5、柱や梁などの架構体(図示省略)、及び、外壁11等の施工が行われた後に、ダクト16を含む送風流路17(本例では、第1送風流路17A~第3送風流路17C)を取り回す施工が行われる。その後、本実施形態の製造方法では、ダクト16が通る閉空間24(本例では、床下空間3及び小屋裏8等)が、建材23(本例では、天井形成材14aや床材6a等)で閉じられ、空調ユニット18等が設置される。 In the manufacturing method of the present embodiment, first, after the construction of the foundation 5, the framework (not shown) such as columns and beams, and the outer wall 11, etc., the air flow path 17 including the duct 16 (in this example, , the first air flow path 17A to the third air flow path 17C). After that, in the manufacturing method of the present embodiment, the closed space 24 (in this example, the underfloor space 3, the attic 8, etc.) through which the duct 16 passes is replaced by the building materials 23 (in this example, the ceiling forming material 14a, the flooring material 6a, etc.). , and the air conditioning unit 18 and the like are installed.

ところで、建物2内にダクト16を取り回す施工時においては、ダクト16に想定外の曲げや潰れ等が生じることがある。これらの曲げや潰れ等は、ダクト16の圧力損失を大きくし、換気及び空調に必要な風量の確保が困難となる。このような施工状態の不具合が、建材23(本例では、天井形成材14aや床材6a等)で、閉空間24(本例では、床下空間3及び小屋裏8等)が閉じられた後に発見された場合には、建材23を一旦取り外して、ダクト16の施工状態を改修する必要が生じる。 By the way, when the duct 16 is routed inside the building 2, the duct 16 may be bent or crushed unexpectedly. These bends, crushes, and the like increase the pressure loss of the duct 16, making it difficult to secure the air volume required for ventilation and air conditioning. After the closed space 24 (in this example, the underfloor space 3, the attic 8, etc.) is closed with the building materials 23 (in this example, the ceiling forming material 14a, the flooring 6a, etc.) If found, it is necessary to temporarily remove the building material 23 and repair the construction state of the duct 16 .

[送風流路の施工状態評価方法(第1実施形態)]
本実施形態では、建物2を製造する過程で、建物2内を延びるダクト16を含む送風流路17の施工状態が評価される。本実施形態の評価方法は、閉空間24(本例では、床下空間3及び小屋裏8等)が、建材23(本例では、天井形成材14aや床材6a等)で閉じられる前に実行される。
[Method for Evaluating Construction State of Blower Channel (First Embodiment)]
In this embodiment, in the process of manufacturing the building 2, the construction state of the air flow path 17 including the duct 16 extending inside the building 2 is evaluated. The evaluation method of the present embodiment is executed before the closed space 24 (in this example, the underfloor space 3, the attic 8, etc.) is closed with the building materials 23 (in this example, the ceiling forming material 14a, the flooring material 6a, etc.). be done.

本実施形態では、第1送風流路17A~第3送風流路17Cの施工状態が評価されるが、施工状態(ダクト16の取り回し)に応じて、それらの一部のみが評価されてもよい。また、評価方法の実施には、コンピュータ等が用いられてもよい。図2は、送風流路の施工状態評価方法の処理手順の一例を示すフローチャートである。図3は、送風流路の施工状態評価方法の一例を説明するための概念図である。図3では、第1送風流路17Aの施工状態の評価方法の一例が、簡略化して示されている。 In the present embodiment, the construction state of the first air flow path 17A to the third air flow path 17C is evaluated, but only some of them may be evaluated according to the construction state (routing of the duct 16). . Moreover, a computer etc. may be used for implementation of the evaluation method. FIG. 2 is a flow chart showing an example of a processing procedure of a method for evaluating the construction state of the air flow path. FIG. 3 is a conceptual diagram for explaining an example of a method for evaluating the construction state of air flow passages. FIG. 3 simplifies and shows an example of the evaluation method of the construction state of 17 A of 1st air flow paths.

[空気を供給]
本実施形態の評価方法では、先ず、図3に示されるように、第1のファン21(図1に示す)よりも風量が小さい第2のファン22を用いて、送風流路17の入口17iに予め定められた風量で空気A4が供給される(工程S1)。第2のファン22は、第1のファン21よりも風量が小さければ、特に限定されない。第2のファン22は、第1のファン21よりも消費電力(風量)が小さいため、例えば、仮設された電力供給装置(電源や蓄電池等)29からの電力供給で運転することができる。これにより、本実施形態の評価方法では、例えば、第1のファン21の設置工事や、第1のファン21の運転に必要な電気工事が実施される前に、送風流路17の入口17iに、空気A4を供給することができる。したがって、本実施形態の評価方法は、ダクト16の施工状態を早期に評価することが可能となる。
[Supply air]
In the evaluation method of this embodiment, first, as shown in FIG. is supplied with air A4 at a predetermined air volume (step S1). The second fan 22 is not particularly limited as long as the air volume is smaller than that of the first fan 21 . Since the second fan 22 consumes less power (air volume) than the first fan 21 , it can be operated with power supplied from a temporarily installed power supply device (power supply, storage battery, etc.) 29 . As a result, in the evaluation method of the present embodiment, for example, before the installation work of the first fan 21 and the electrical work necessary for the operation of the first fan 21 are performed, the inlet 17i of the air flow path 17 , air A4. Therefore, the evaluation method of the present embodiment enables early evaluation of the construction state of the duct 16 .

本実施形態の工程S1では、先ず、送風流路17の入口17iに、第2のファン22が設置される。入口17iと第2のファン22との間には、それらの間の隙間を防ぐためのアダプター31が設けられてもよい。本実施形態の第2のファン22には、仮設された電力供給装置(電源や蓄電池等)29から電力が供給される。次に、本実施形態の工程S1では、第2のファン22の運転が開始され、送風流路17の入口17iに予め定められた風量で、空気A4が供給される。 In step S<b>1 of the present embodiment, first, the second fan 22 is installed at the inlet 17 i of the airflow passage 17 . An adapter 31 may be provided between the inlet 17i and the second fan 22 to prevent gaps between them. Power is supplied to the second fan 22 of the present embodiment from a temporary power supply device (power supply, storage battery, etc.) 29 . Next, in step S1 of the present embodiment, the operation of the second fan 22 is started, and air A4 is supplied to the inlet 17i of the air flow path 17 at a predetermined air volume.

風量は、次の工程S2において、送風流路17の出口17oで測定可能な風量であれば、特に限定されない。本実施形態の風量は、第2のファン22の仕様に基づいて、適宜設定される。 The air volume is not particularly limited as long as it is measurable at the outlet 17o of the airflow passage 17 in the next step S2. The air volume in this embodiment is appropriately set based on the specifications of the second fan 22 .

図1に示されるように、本実施形態の送風流路17は、建物2が製造された後において、第1のファン21から供給される空気(本例では、外気A1又は換気・空調空気A2)が、入口17iから出口17oに搬送されることが予定されている。したがって、工程S1では、図3に示されるように、送風流路17の入口17iに、第2のファン22から空気A4が供給されることにより、第1のファン21で空気が搬送される状態を、第1のファン21が設置される前に擬似的に実施することができる。 As shown in FIG. 1, the air flow path 17 of the present embodiment is designed to supply air (outside air A1 or ventilation/air-conditioning air A2 in this example) supplied from the first fan 21 after the building 2 is manufactured. ) is intended to be conveyed from the inlet 17i to the outlet 17o. Therefore, in step S1, as shown in FIG. 3, air A4 is supplied from the second fan 22 to the inlet 17i of the airflow passage 17, and the air is conveyed by the first fan 21. can be simulated before the first fan 21 is installed.

[風量を測定]
次に、本実施形態の評価方法では、送風流路17の入口17i又は出口17oでの風量が測定される(工程S2)。本実施形態の工程S2では、送風流路17の入口17iから出口17oに搬送された空気A4について、出口17oでの風量が測定される。風量は、従来の方法に基づいて、適宜測定されうる。本実施形態の工程S2では、公知の風量計32が用いられる。本実施形態の風量計32には、ベーン式風量計(例えば、株式会社テストー製の「testo417」)が採用されている。このような風量計32は、例えば、ダクト16の内径が小さく、かつ、測定位置での風速が速い場合に、風量を精度良く測定しうる。なお、風量計32は、ベーン式風量計に限定されるわけではなく、例えば、熱線式風量計が用いられてもよい。このような熱線式風量計は、例えば、ダクト16の内径が大きく、かつ、測定位置での風速が遅い場合に、風量を精度良く測定しうる。また、風量計32と出口17oとの間には、それらの間の隙間を防ぐためのアダプター33が設けられてもよい。
[Measure air volume]
Next, in the evaluation method of the present embodiment, the air volume at the inlet 17i or the outlet 17o of the airflow passage 17 is measured (step S2). In step S2 of the present embodiment, the air volume at the outlet 17o of the air A4 conveyed from the inlet 17i to the outlet 17o of the air flow path 17 is measured. The air volume can be appropriately measured based on conventional methods. A known air flow meter 32 is used in step S2 of the present embodiment. A vane-type air flow meter (for example, "testo417" manufactured by Testo Corporation) is adopted as the air flow meter 32 of the present embodiment. Such an air volume meter 32 can accurately measure the air volume, for example, when the inner diameter of the duct 16 is small and the wind speed at the measurement position is high. The air volume meter 32 is not limited to the vane type air volume meter, and for example, a hot wire type air volume meter may be used. Such a hot-wire air flow meter can accurately measure the air volume, for example, when the inner diameter of the duct 16 is large and the wind speed at the measurement position is slow. Also, an adapter 33 may be provided between the air flow meter 32 and the outlet 17o to prevent a gap therebetween.

工程S2では、送風流路17の出口17oでの風量を測定する態様に限定されるわけではなく、送風流路17の入口17iでの風量が測定されてもよい。送風流路17は、入口17iと出口17oとの間が密閉されているため、入口17iでの風量と、出口17oでの風量とは等しくなる。したがって、工程S2では、入口17iでの風量が測定されることにより、出口17oでの風量を測定した場合と同一の測定結果が得られる。 In step S2, the method is not limited to measuring the air volume at the outlet 17o of the airflow passage 17, and the air volume at the inlet 17i of the airflow passage 17 may be measured. Since the inlet 17i and the outlet 17o of the air flow path 17 are sealed, the air volume at the inlet 17i and the air volume at the outlet 17o are equal. Therefore, in step S2, by measuring the air volume at the inlet 17i, the same measurement result as when measuring the air volume at the outlet 17o is obtained.

送風流路17の入口17iでの風量が測定される場合には、工程S1での空気A4の供給、及び、工程S2での風量の測定を、入口17iにおいて実施することができる。これにより、評価方法では、例えば、入口17iで空気A4を供給するためのオペレータと、出口17oで風量を測定するためのオペレータとをそれぞれ配置する必要がないため、ダクトの施工状態を容易に評価することが可能となる。 When the air volume at the inlet 17i of the air flow path 17 is measured, the supply of the air A4 in step S1 and the measurement of the air volume in step S2 can be performed at the inlet 17i. Thus, in the evaluation method, for example, it is not necessary to arrange an operator for supplying the air A4 at the inlet 17i and an operator for measuring the air volume at the outlet 17o, so the construction state of the duct can be easily evaluated. It becomes possible to

送風流路17の入口17iでの風量が測定される場合には、第2のファン22と入口17iとの間に風量計32が配置されてもよいし、第2のファン22の吸込口に、風量計32が配置されてもよい。風量の測定結果は、例えば、コンピュータ(図示省略)などに記録される。 When the air volume at the inlet 17i of the air flow path 17 is measured, an air volume meter 32 may be arranged between the second fan 22 and the inlet 17i, or may be placed at the suction port of the second fan 22. , an air flow meter 32 may be arranged. The measurement result of the air volume is recorded, for example, in a computer (not shown).

[風量に対する閾値を決定]
次に、本実施形態の評価方法では、風量に対する予め定められた閾値が決定される(工程S3)。本実施形態の工程S3は、後述の施工状態を評価する工程S4に先立って実行される。なお、工程S3は、施工状態を評価する工程S4が実行される前であれば、適宜実行(例えば、工程S1及び工程S2の前に実行)されてもよい。
[Determine threshold for air volume]
Next, in the evaluation method of the present embodiment, a predetermined threshold for air volume is determined (step S3). Step S3 of the present embodiment is performed prior to step S4 of evaluating the construction state, which will be described later. Note that step S3 may be performed as appropriate (for example, before step S1 and step S2) as long as it is before step S4 of evaluating the construction state is performed.

本実施形態の工程S3では、先ず、第2のファン22の静圧と風量との関係を示す第1曲線と、送風流路17の圧力損失と風量との関係を示す第2曲線とが取得される。図4は、第1曲線C1及び第2曲線C2の一例を示すグラフである。 In step S3 of the present embodiment, first, a first curve indicating the relationship between the static pressure of the second fan 22 and the air volume, and a second curve indicating the relationship between the pressure loss and the air volume in the air flow path 17 are obtained. be done. FIG. 4 is a graph showing an example of the first curve C1 and the second curve C2.

第1曲線C1は、例えば、第2のファン22(図3に示す)のメーカー等が公表している「風量-静圧特性」が用いられる。このような第1曲線C1では、第2のファン22が設置される装置(ダクトなど)の圧力損失(静圧)に対して、第2のファン22で供給される風量が特定されうる。 For the first curve C1, for example, the "air volume-static pressure characteristic" published by the manufacturer of the second fan 22 (shown in FIG. 3) is used. With such a first curve C1, the air volume supplied by the second fan 22 can be specified with respect to the pressure loss (static pressure) of the device (such as a duct) in which the second fan 22 is installed.

第2曲線C2は、例えば、図3に示した送風流路17の設計因子(例えば、ダクト16の内径、ダクト16の摩擦係数、局部25の圧力損失係数等)に基づいて、公知の方法にしたがって適宜求められる。本実施形態では、例えば、送風流路17の設計因子に基づいて、例えば、ダクトの圧力損失計算の詳細法(A式)の変数が代入されることにより、第2曲線が取得されうる。なお、詳細法(A式)の詳細は、例えば、文献(国土交通省住宅局等著、「改正建築基準法に対応した建築物のシックハウス対策マニュアル」、工学図書、2003年11月、p.248-249)に記載のとおりである。 The second curve C2 is obtained by a known method, for example, based on the design factors of the airflow passage 17 shown in FIG. Therefore, it is required as appropriate. In the present embodiment, for example, the second curve can be obtained by substituting the variables of the detailed method (formula A) for calculating the pressure loss of the duct based on the design factors of the air flow path 17 . For details of the detailed method (formula A), see, for example, a document (Ministry of Land, Infrastructure, Transport and Tourism, Housing Bureau, etc., "Manual for Building Sick House Countermeasures Corresponding to the Revised Building Standards Law", Kogaku Tosho, November 2003, p. 248-249).

本実施形態の評価方法が実行される時点において、送風流路17に、例えば、外部端末換気口(図示省略)や、室内端末換気口(図示省略)が設けられていない場合には、詳細法(A式)のうち、これらに関する変数への代入は省略されうる。これにより、本実施形態の評価方法では、第2曲線C2が容易に取得されうる。 When the evaluation method of this embodiment is executed, for example, if the air flow path 17 is not provided with an external terminal ventilation opening (not shown) or an indoor terminal ventilation opening (not shown), the detailed method In (A formula), assignments to variables related to these can be omitted. Thereby, the second curve C2 can be easily obtained in the evaluation method of the present embodiment.

このような第2曲線C2は、送風流路17が設計因子のとおりに設置された(すなわち、ダクト16の施工状態に不具合がない)場合において、送風流路17に供給された空気の風量に対して、送風流路17に発生する圧力損失が特定されうる。第2曲線C2は、風量が大きくなるほど、圧力損失が大きくなることを示している。 Such a second curve C2 corresponds to the amount of air supplied to the air flow path 17 when the air flow path 17 is installed according to the design factors (that is, the duct 16 is not defective in construction). On the other hand, the pressure loss occurring in the air flow path 17 can be identified. The second curve C2 indicates that the pressure loss increases as the air volume increases.

次に、本実施形態の工程S3では、第1曲線C1と、第2曲線C2との交点Pでの風量Wに基づいて、第2のファン22の風量に対する閾値が決定される。交点Pでの風量Wは、ダクト16の施工状態に不具合(例えば、想定外の曲げや潰れ等)がない送風流路17の入口17iに、第2のファン22から空気A4が供給された場合に、出口17oから吐出されると予測された風量を示している。したがって、工程S2において測定された入口17i又は出口17oでの風量が、交点Pでの風量W未満である場合には、ダクト16の施工状態に不具合がある可能性が高いと判断しうる。このような交点Pでの風量Wに基づいて、第2のファン22の風量に対する閾値が設定されることにより、ダクト16の施工状態を適切に評価することが可能となる。 Next, in step S3 of the present embodiment, a threshold for the air volume of the second fan 22 is determined based on the air volume W at the intersection point P between the first curve C1 and the second curve C2. The air volume W at the intersection point P is obtained when air A4 is supplied from the second fan 22 to the inlet 17i of the air flow path 17 where there is no problem in the construction state of the duct 16 (for example, unexpected bending or collapse). shows the amount of wind predicted to be discharged from the outlet 17o. Therefore, if the air volume at the inlet 17i or the outlet 17o measured in step S2 is less than the air volume W at the intersection point P, it can be determined that there is a high possibility that the duct 16 is defective in construction. By setting the threshold for the air volume of the second fan 22 based on the air volume W at the intersection point P, it is possible to appropriately evaluate the construction state of the duct 16 .

閾値には、交点Pでの風量Wがそのまま採用されてもよい。なお、閾値は、例えば、第2のファン22の風量の誤差や、入口17i又は出口17oでの風量の測定誤差等の影響を考慮して、適宜決定(すなわち、交点Pでの風量Wよりも小さい値や、交点Pでの風量Wよりも大きな値に決定)されてもよい。閾値は、例えば、コンピュータなどに記録される。 As the threshold value, the air volume W at the intersection P may be used as it is. Note that the threshold is determined as appropriate in consideration of, for example, an error in the air volume of the second fan 22 and an error in measuring the air volume at the inlet 17i or the outlet 17o (that is, the air volume W at the intersection point P is A smaller value or a value larger than the air volume W at the intersection point P may be determined). The threshold is recorded, for example, in a computer or the like.

[ダクトの施工状態を評価]
次に、本実施形態の評価方法では、測定された風量と、風量に対する予め定められた閾値(例えば、図4の交点Pでの風量W)とに基づいて、ダクト16の施工状態が評価される(工程S4)。本実施形態の工程S4では、測定された入口17i又は出口17oでの風量が、閾値以上であるか否かが判断される。
[Evaluate the construction status of the duct]
Next, in the evaluation method of the present embodiment, the construction state of the duct 16 is evaluated based on the measured air volume and a predetermined threshold for the air volume (for example, the air volume W at the intersection point P in FIG. 4). (step S4). In step S4 of the present embodiment, it is determined whether or not the measured air volume at the inlet 17i or the outlet 17o is equal to or greater than a threshold value.

工程S4において、入口17i又は出口17oでの風量が閾値以上である場合(工程S4において、「Yes」)、ダクト16の施工状態に不具合(例えば、想定外の曲げや潰れ等)がない可能性が高い。この場合、工程S4では、ダクト16の施工状態が良好であると評価される。 In step S4, if the air volume at the inlet 17i or the outlet 17o is equal to or greater than the threshold value ("Yes" in step S4), there is a possibility that there is no defect in the construction state of the duct 16 (for example, unexpected bending, crushing, etc.). is high. In this case, in step S4, the construction state of the duct 16 is evaluated as good.

一方、工程S4において、入口17i又は出口17oでの風量が閾値未満である場合(工程S4において、「No」)、ダクト16の施工状態に不具合(例えば、想定外の曲げや潰れ等)がある可能性が高い。この場合、工程S4では、ダクト16の施工状態が良好でないと評価される。 On the other hand, in step S4, if the air volume at the inlet 17i or the outlet 17o is less than the threshold value ("No" in step S4), there is a problem in the construction state of the duct 16 (for example, unexpected bending, crushing, etc.). Probability is high. In this case, in step S4, it is evaluated that the construction state of the duct 16 is not good.

このように、本実施形態の評価方法は、閉空間24が建材23(図1に示す)で閉じられる前に、ダクト16の施工状態の良否を簡易に評価することができる。したがって、本実施形態の評価方法は、例えば、ダクト16の施工状態が良好でない場合に、その施工状態を改修するために、閉空間24を閉じた建材23を一旦取り外す必要がないため、建物2の製造コストの増大を抑制することができる。 Thus, the evaluation method of the present embodiment can easily evaluate whether the construction state of the duct 16 is good or bad before the closed space 24 is closed with the building material 23 (shown in FIG. 1). Therefore, in the evaluation method of this embodiment, for example, when the construction state of the duct 16 is not good, there is no need to once remove the building material 23 that closed the closed space 24 in order to repair the construction state. It is possible to suppress an increase in the manufacturing cost of

本実施形態の評価方法は、送風流路17の入口17iから出口17oに搬送することが予定されている第1のファン21(図1に示す)よりも、風量の小さい第2のファン22(図3に示す)が用いられる。このため、本実施形態の評価方法は、第1のファン21が設置される前に、ダクト16の施工状態が早期に評価されうる。さらに、本実施形態の評価方法は、例えば、第1のファン21の設置に必要な電気工事を必要としない。このため、本実施形態の評価方法は、ダクト16の施工状態を早期に評価することができる。 In the evaluation method of the present embodiment, the second fan 22 ( 3) is used. Therefore, according to the evaluation method of the present embodiment, the construction state of the duct 16 can be evaluated early before the first fan 21 is installed. Furthermore, the evaluation method of the present embodiment does not require electrical work required for installing the first fan 21, for example. Therefore, the evaluation method of this embodiment can evaluate the construction state of the duct 16 at an early stage.

[閉空間を閉じる]
本実施形態の評価方法(製造方法)では、入口17i又は出口17oでの風量が閾値以上である場合に(工程S4で「Yes」)、図1に示されるように、閉空間24が建材23で閉じられる(工程S5)。これにより、本実施形態の評価方法(製造方法)では、ダクト16の施工状態に不具合(例えば、想定外の曲げや潰れ等)がない状態で、閉空間24が建材23で閉じられるため、換気及び空調を効率よく行うことが可能な建物2を、確実に製造することができる。
[Close Closed Space]
In the evaluation method (manufacturing method) of the present embodiment, when the air volume at the inlet 17i or the outlet 17o is equal to or greater than the threshold value (“Yes” in step S4), as shown in FIG. is closed (step S5). As a result, in the evaluation method (manufacturing method) of the present embodiment, the closed space 24 is closed with the building material 23 in a state in which there is no defect in the construction state of the duct 16 (for example, unexpected bending, crushing, etc.). And the building 2 that can be efficiently air-conditioned can be reliably manufactured.

[ダクトの施工状態を改修]
本実施形態の評価方法(製造方法)では、入口17i又は出口17oでの風量が閾値未満である場合に(工程S4で「No」)、入口17i又は出口17oでの風量が閾値以上になるように、ダクト16の施工状態が改修される(工程S6)。本実施形態の工程S6では、ダクト16の施工状態の不具合(例えば、想定外の曲げや潰れ等)が特定され、その不具合が補修される。本実施形態では、建材23を取り外すことなく、ダクト16の施工状態を迅速に改修することができるため、建物2の製造コストの増大が抑制されうる。
[Renovation of duct construction status]
In the evaluation method (manufacturing method) of the present embodiment, when the air volume at the inlet 17i or the outlet 17o is less than the threshold ("No" in step S4), the air volume at the inlet 17i or the outlet 17o is set to be equal to or greater than the threshold. Then, the construction state of the duct 16 is repaired (step S6). In step S6 of the present embodiment, defects in the construction state of the duct 16 (for example, unexpected bending, crushing, etc.) are identified, and the defects are repaired. In this embodiment, the construction state of the duct 16 can be quickly repaired without removing the building material 23, so an increase in manufacturing cost of the building 2 can be suppressed.

本実施形態の評価方法では、ダクト16の施工状態が改修された後に(工程S6の実行された後に)、工程S1~工程S4が再度実施されるのが望ましい。これにより、本実施形態の評価方法(製造方法)では、入口17i又は出口17oでの風量が閾値以上になるまで、ダクト16の施工状態が確実に改修されるため、換気及び空調を効率よく行うことが可能な建物2を、確実に製造することができる。なお、送風流路17の設計因子に変更がない場合には、風量に対する閾値も変更されないため、閾値を決定する工程S3が省略されてもよい。 In the evaluation method of the present embodiment, it is desirable that steps S1 to S4 are performed again after the construction state of the duct 16 is repaired (after step S6 is performed). As a result, in the evaluation method (manufacturing method) of the present embodiment, the construction state of the duct 16 is reliably repaired until the air volume at the entrance 17i or the exit 17o reaches a threshold value or more, so ventilation and air conditioning are performed efficiently. The building 2 capable of doing so can be reliably manufactured. If there is no change in the design factor of the air flow path 17, the threshold for the air volume is also not changed, so the step S3 of determining the threshold may be omitted.

[送風流路の施工状態評価方法(第2実施形態)]
本実施形態の評価方法では、閾値を決定する工程S3が実施されたが、このような態様に限定されない。例えば、建物2に設置される送風流路17の設計因子と、以前に製造された他の建物(図示省略)に設置された送風流路17の設計因子とが共通する場合には、他の建物の製造時に取得された閾値が用いられてもよい。これにより、この実施形態の評価方法では、閾値を決定する工程S3が省略されるため、ダクト16の施工状態を、より迅速に評価することが可能となる。
[Method for Evaluating Construction Condition of Blower Channel (Second Embodiment)]
In the evaluation method of the present embodiment, the step S3 of determining the threshold is performed, but the present invention is not limited to such a mode. For example, when the design factor of the air flow path 17 installed in the building 2 and the design factor of the air flow path 17 installed in another previously manufactured building (not shown) are common, other Thresholds obtained during building manufacture may be used. Accordingly, in the evaluation method of this embodiment, the step S3 of determining the threshold value is omitted, so the construction state of the duct 16 can be evaluated more quickly.

[送風流路の施工状態評価方法(第3実施形態)]
これまでの実施形態では、送風流路17の入口17i又は出口17oでの風量を測定して、測定された風量と、風量に対する閾値とに基づいて、ダクトの施工状態が評価されたが、このような態様に限定されない。図5は、本発明の他の実施形態の送風流路の施工状態評価方法の処理手順の一例を示すフローチャートである。この実施形態において、これまでの実施形態と同一の構成については、同一の符号を付し、説明を省略することがある。
[Method for Evaluating Construction Condition of Blower Channel (Third Embodiment)]
In the previous embodiments, the air volume at the inlet 17i or the outlet 17o of the airflow passage 17 was measured, and the installation state of the duct was evaluated based on the measured air volume and the threshold for the air volume. It is not limited to such an aspect. FIG. 5 is a flow chart showing an example of a processing procedure of a method for evaluating the construction state of a ventilation passage according to another embodiment of the present invention. In this embodiment, the same reference numerals are assigned to the same configurations as in the previous embodiments, and the description may be omitted.

[空気を供給]
この実施形態の評価方法では、先ず、定風量の第2のファン22を用いて、送風流路17の入口17iに予め定められた風量で空気が供給される(工程S7)。定風量の第2のファン22は、一定の風量となるように、回転数が制御されるものである。したがって、第2のファン22は、送風流路17に発生する圧力損失が大きくなるほど、その回転数が大きくなる。なお、第2のファン22の風量は、特に限定されるわけではなく、第2のファン22の仕様に基づいて、適宜設定される。また、第2のファン22の設置等は、これまでの実施形態と同様の手順に基づいて実施されうる。
[Supply air]
In the evaluation method of this embodiment, first, air is supplied at a predetermined air volume to the inlet 17i of the airflow passage 17 using the second fan 22 with a constant air volume (step S7). The constant air volume second fan 22 is controlled in rotation speed so as to maintain a constant air volume. Therefore, the rotation speed of the second fan 22 increases as the pressure loss generated in the air flow path 17 increases. Note that the air volume of the second fan 22 is not particularly limited, and is appropriately set based on the specifications of the second fan 22 . Also, the installation of the second fan 22 and the like can be performed based on the same procedure as in the previous embodiments.

[第2ファンの回転数を測定]
次に、この実施形態の評価方法では、第2のファン22の回転数が測定される(工程S8)。第2のファン22の回転数は、適宜測定されうる。この実施形態の工程S8では、例えば、第2のファン22を制御する制御装置(図示省略)で測定される回転数の読み込みや、公知の回転計(例えば、株式会社テストー製の「testo460」)を用いた測定によって、第2のファン22の回転数が測定されうる。風量の測定結果は、例えば、コンピュータ(図示省略)などに記録される。
[Measure the rotation speed of the second fan]
Next, in the evaluation method of this embodiment, the rotation speed of the second fan 22 is measured (step S8). The rotation speed of the second fan 22 can be measured as appropriate. In step S8 of this embodiment, for example, the number of revolutions measured by a control device (not shown) that controls the second fan 22 is read, or a known tachometer (eg, "testo460" manufactured by Testo Co., Ltd.) can measure the rotation speed of the second fan 22 . The measurement result of the air volume is recorded, for example, in a computer (not shown).

[回転数に対する閾値を測定]
次に、この実施形態の評価方法では、回転数に対する予め定められた閾値が決定される(工程S9)。この実施形態の工程S9は、後述の施工状態を評価する工程S10に先立って実行される。なお、工程S9は、施工状態を評価する工程S10が実行される前であれば、適宜実行(例えば、工程S7及び工程S8の前に実行)されてもよい。
[Measure the threshold for the number of revolutions]
Next, in the evaluation method of this embodiment, a predetermined threshold for the number of revolutions is determined (step S9). Step S9 of this embodiment is performed prior to step S10 of evaluating the construction state, which will be described later. Note that step S9 may be appropriately performed (for example, performed before steps S7 and S8) before step S10 for evaluating the construction state is performed.

この実施形態の工程S9では、先ず、これまでの実施形態の手順に基づいて、送風流路17の圧力損失と風量との関係を示す第2曲線とが取得される。図6(a)は、第2曲線C2の一例を示すグラフである。 In step S9 of this embodiment, first, a second curve representing the relationship between the pressure loss of the air flow path 17 and the air volume is acquired based on the procedure of the previous embodiments. FIG. 6(a) is a graph showing an example of the second curve C2.

次に、この実施形態の工程S9では、図6(a)に示されるように、第2曲線C2において、風量(第2のファン22の定風量)Xの空気が、送風流路17に供給されたときの圧力損失が求められる。この圧力損失は、ダクト16の施工状態に不具合(例えば、想定外の曲げや潰れ等)がない送風流路17の入口17iに、第2のファン22から定風量Xの空気A4が供給された場合における第2のファン22の静圧Yを示している。 Next, in step S9 of this embodiment, as shown in FIG. 6A, air with an air volume (constant air volume of the second fan 22) X is supplied to the air flow path 17 on the second curve C2. The pressure loss when the This pressure loss is due to the fact that air A4 with a constant air volume X is supplied from the second fan 22 to the inlet 17i of the airflow passage 17 where there is no problem in the construction state of the duct 16 (for example, unexpected bending or collapse). 2 shows the static pressure Y of the second fan 22 in this case.

次に、この実施形態の工程S9では、第2のファン22の静圧と回転数との関係が取得される。第2のファン22の静圧と回転数との関係は、例えば、第2のファン22のメーカー等が公表している技術資料等から取得される。図6(b)は、第2のファン22の静圧と回転数との関係を示すグラフである。 Next, in step S9 of this embodiment, the relationship between the static pressure and the rotational speed of the second fan 22 is obtained. The relationship between the static pressure and the number of rotations of the second fan 22 is obtained, for example, from technical data published by the manufacturer of the second fan 22 or the like. FIG. 6B is a graph showing the relationship between the static pressure of the second fan 22 and the rotation speed.

次に、この実施形態の工程S9では、図6(b)に示されるように、第2のファン22の静圧と回転数との関係(曲線C3)に基づいて、静圧Yでの第2のファン22の回転数Zが特定される。そして、工程S9では、回転数Zに基づいて、第2のファン22の回転数に対する閾値が決定される。 Next, in step S9 of this embodiment, as shown in FIG. 2, the rotation speed Z of the fan 22 is specified. Then, in step S9, based on the rotation speed Z, a threshold for the rotation speed of the second fan 22 is determined.

静圧Yでの第2のファン22の回転数Zは、ダクト16の施工状態に不具合がない送風流路17の入口17iに、第2のファン22から定風量Xの空気A4が供給された場合における第2のファン22の回転数を示している。したがって、工程S8で測定された第2のファン22の回転数が、回転数Z以上である場合には、送風流路17での圧力損失によって第2のファン22の回転数が大きくなっており、ダクト16の施工状態に不具合がある可能性が高いと判断しうる。このような回転数Zに基づいて、第2のファン22の回転数に対する閾値が設定されることにより、ダクト16の施工状態を適切に評価することが可能となる。 The number of rotations Z of the second fan 22 at the static pressure Y is determined by supplying air A4 with a constant air volume X from the second fan 22 to the inlet 17i of the air flow path 17 where the duct 16 is not defective in the construction state. It shows the rotation speed of the second fan 22 in the case. Therefore, when the rotation speed of the second fan 22 measured in step S8 is equal to or higher than the rotation speed Z, the rotation speed of the second fan 22 is increased due to the pressure loss in the air flow path 17. , it can be determined that there is a high possibility that the construction state of the duct 16 is defective. By setting the threshold value for the rotation speed of the second fan 22 based on such rotation speed Z, it becomes possible to appropriately evaluate the construction state of the duct 16 .

閾値には、静圧Yでの回転数Zがそのまま採用されてもよい。なお、閾値は、例えば、第2のファン22の定風量の誤差や、回転数の測定誤差等の影響を考慮して、適宜決定(すなわち、回転数Zよりも小さい値や、回転数Zよりも大きな値に決定)されてもよい。閾値は、例えば、コンピュータなどに記録される。 The rotation speed Z at the static pressure Y may be used as it is for the threshold value. Note that the threshold is determined as appropriate (that is, a value smaller than the number of revolutions Z, or a value smaller than the number of revolutions Z or is also determined to be a large value). The threshold is recorded, for example, in a computer or the like.

[ダクトの施工状態を評価]
次に、この実施形態の評価方法では、測定された回転数と、回転数に対する予め定められた閾値とに基づいて、ダクト16の施工状態が評価される(工程S10)。この実施形態の工程S10では、測定された回転数が、閾値以上であるか否かが判断される。
[Evaluate the construction status of the duct]
Next, in the evaluation method of this embodiment, the construction state of the duct 16 is evaluated based on the measured number of revolutions and a predetermined threshold for the number of revolutions (step S10). In step S10 of this embodiment, it is determined whether the measured number of rotations is equal to or greater than a threshold value.

工程S10において、測定された回転数が閾値未満である場合(工程S10において、「Yes」)、ダクト16の施工状態に不具合(例えば、想定外の曲げや潰れ等)がない可能性が高い。この場合、工程S10では、ダクト16の施工状態が良好であると評価される。 In step S10, if the measured number of revolutions is less than the threshold value ("Yes" in step S10), there is a high possibility that the duct 16 has no defects (for example, unexpected bending or crushing). In this case, in step S10, the construction state of the duct 16 is evaluated as good.

一方、工程S10において、測定された回転数が閾値以上である場合(工程S10において、「No」)、ダクト16の施工状態に不具合(例えば、想定外の曲げや潰れ等)がある可能性が高い。この場合、工程S10では、ダクト16の施工状態が良好でないと評価される。 On the other hand, in step S10, if the measured number of rotations is equal to or greater than the threshold value (“No” in step S10), there is a possibility that the duct 16 has a defect (for example, unexpected bending, crushing, etc.). expensive. In this case, in step S10, the construction state of the duct 16 is evaluated as not good.

このように、この実施形態の評価方法は、これまでの実施形態の評価方法と同様に、閉空間24が建材23(図1に示す)で閉じられる前に、ダクト16の施工状態の良否を簡易に評価することができる。したがって、この実施形態の評価方法は、例えば、ダクト16の施工状態が良好でない場合に、その施工状態を改修するために、閉空間24を閉じた建材23を一旦取り外す必要がないため、建物2の製造コストの増大を抑制することができる。 As described above, the evaluation method of this embodiment is similar to the evaluation methods of the previous embodiments, and before the closed space 24 is closed with the building material 23 (shown in FIG. 1), the quality of the construction state of the duct 16 is evaluated. can be easily evaluated. Therefore, in the evaluation method of this embodiment, for example, when the construction state of the duct 16 is not good, there is no need to temporarily remove the building material 23 that closed the closed space 24 in order to repair the construction state. It is possible to suppress an increase in the manufacturing cost of

以上、本発明の特に好ましい実施形態について詳述したが、本発明は図示の実施形態に限定されることなく、種々の態様に変形して実施しうる。 Although the particularly preferred embodiments of the present invention have been described in detail above, the present invention is not limited to the illustrated embodiments and can be modified in various ways.

S1 送風流路の入口に空気を供給する工程
S2 送風流路の入口又は出口での風量を測定する工程
S4 ダクトの施工状態を評価する工程
S1 Step of supplying air to the inlet of the airflow channel S2 Step of measuring the air volume at the inlet or outlet of the airflow channel S4 Step of evaluating the construction state of the duct

Claims (10)

建物を製造する過程で、前記建物内を延びるダクトを含む送風流路の施工状態を評価するための方法であって、
前記送風流路は、入口と、出口とを有し、かつ、第1のファンから供給される空気を前記入口から前記出口に搬送することが予定されており、かつ、前記ダクトの少なくとも一部が建材で囲まれた閉空間内を通るように設置されるものであり、
前記方法は、前記閉空間が前記建材で閉じられる前に、
前記第1のファンよりも風量が小さい第2のファンを用いて、前記送風流路の前記入口に予め定められた風量で空気を供給する工程と、
前記送風流路の前記入口又は前記出口での風量を測定する工程と、
測定された前記風量と、前記風量に対する予め定められた閾値とに基づいて、前記ダクトの施工状態を評価する工程とを実行する、
送風流路の施工状態評価方法。
A method for evaluating the construction state of a ventilation channel including a duct extending through the building in the process of manufacturing a building, comprising:
The blowing channel has an inlet and an outlet and is destined to convey air supplied by the first fan from the inlet to the outlet, and at least part of the duct is installed so as to pass through a closed space surrounded by building materials,
Before the closed space is closed with the building material, the method includes:
a step of supplying air at a predetermined air volume to the inlet of the air flow path using a second fan having an air volume smaller than that of the first fan;
measuring the air volume at the inlet or the outlet of the airflow channel;
evaluating the construction state of the duct based on the measured air volume and a predetermined threshold for the air volume;
A method for evaluating the construction state of air flow passages.
前記評価する工程は、前記入口又は前記出口での風量が前記閾値以上である場合に、前記ダクトの施工状態が良好であると評価する、請求項1に記載の送風流路の施工状態評価方法。 2. The method for evaluating a construction state of a blast passage according to claim 1, wherein said step of evaluating evaluates that the construction state of said duct is good when the air volume at said inlet or said outlet is equal to or greater than said threshold value. . 前記入口又は前記出口での風量が前記閾値以上である場合に、前記閉空間を前記建材で閉じる工程をさらに含む、請求項1又は2に記載の送風流路の施工状態評価方法。 3. The method for evaluating construction status of a ventilation passage according to claim 1, further comprising closing said closed space with said building material when the air volume at said inlet or said outlet is equal to or greater than said threshold value. 前記評価する工程は、前記入口又は前記出口での風量が前記閾値未満である場合に、前記ダクトの施工状態が良好でないと評価する、請求項1ないし3のいずれか1項に記載の送風流路の施工状態評価方法。 4. The blast flow according to any one of claims 1 to 3, wherein the evaluating step evaluates that the construction state of the duct is not good when the air volume at the inlet or the outlet is less than the threshold value. Road construction condition evaluation method. 前記入口又は前記出口での風量が前記閾値未満である場合に、前記入口又は前記出口での風量が前記閾値以上になるように、前記ダクトの施工状態を改修する工程をさらに含む、請求項1ないし4のいずれか1項に記載の送風流路の施工状態評価方法。 2. The method of claim 1, further comprising, when the air volume at the entrance or the exit is less than the threshold value, modifying the construction state of the duct so that the air volume at the entrance or the exit becomes equal to or greater than the threshold value. 5. The method for evaluating the construction state of the air flow path according to any one of items 1 to 4. 前記評価する工程に先立ち、前記閾値を決定する工程をさらに含み、
前記閾値を決定する工程は、前記第2のファンの静圧と風量との関係を示す第1曲線と、前記送風流路の圧力損失と風量との関係を示す第2曲線との交点での風量に基づいて、前記閾値を決定する、請求項1ないし5のいずれか1項に記載の送風流路の施工状態評価方法。
Prior to the evaluating step, further comprising determining the threshold;
The step of determining the threshold is performed at the intersection of a first curve showing the relationship between the static pressure of the second fan and the air volume and a second curve showing the relationship between the pressure loss and the air volume of the airflow passage. 6. The method for evaluating the construction state of the airflow path according to claim 1, wherein the threshold value is determined based on air volume.
建物を製造する過程で、前記建物内を延びるダクトを含む送風流路の施工状態を評価するための方法であって、
前記送風流路は、入口と、出口とを有し、かつ、第1のファンから供給される空気を前記入口から前記出口に搬送することが予定されており、かつ、前記ダクトの少なくとも一部が建材で囲まれた閉空間内を通るように設置されるものであり、
前記方法は、前記閉空間が前記建材で閉じられる前に、
定風量の第2のファンを用いて、前記送風流路の前記入口に予め定められた風量で空気を供給する工程と、
前記第2のファンの回転数を測定する工程と、
測定された前記回転数と、前記回転数に対する予め定められた閾値とに基づいて、前記ダクトの施工状態を評価する工程とを実行する、
送風流路の施工状態評価方法。
A method for evaluating the construction state of a ventilation channel including a duct extending through the building in the process of manufacturing a building, comprising:
The blowing channel has an inlet and an outlet and is destined to convey air supplied by the first fan from the inlet to the outlet, and at least part of the duct is installed so as to pass through a closed space surrounded by building materials,
Before the closed space is closed with the building material, the method includes:
using a second fan with a constant air volume to supply air at a predetermined air volume to the inlet of the air flow path;
measuring the rotation speed of the second fan;
Evaluating the construction state of the duct based on the measured number of rotations and a predetermined threshold for the number of rotations.
A method for evaluating the construction state of air flow passages.
前記評価する工程は、前記測定された回転数が前記閾値未満である場合に、前記ダクトの施工状態が良好であると評価する、請求項7に記載の送風流路の施工状態評価方法。 8. The method for evaluating construction condition of a blast passage according to claim 7, wherein said step of evaluating evaluates that the construction condition of said duct is good when said measured number of rotations is less than said threshold value. 前記評価する工程は、前記測定された回転数が前記閾値以上である場合に、前記ダクトの施工状態が良好でないと評価する、請求項7又は8に記載の送風流路の施工状態評価方法。 9. The method for evaluating construction condition of a ventilation passage according to claim 7 or 8, wherein said step of evaluating evaluates that said duct construction condition is not good when said measured number of revolutions is equal to or greater than said threshold value. 建物内を延びるダクトを含む送風流路を備えた建物製造方法であって、
請求項1ないし9のいずれかに記載された送風流路の施工状態評価方法を含む、建物の製造方法。
A method for manufacturing a building having an airflow passage including a duct extending through the building,
A method for manufacturing a building, comprising the method for evaluating the construction state of a ventilation passage according to any one of claims 1 to 9.
JP2021009326A 2021-01-25 2021-01-25 Method for evaluating construction condition of air flow passage and method for manufacturing building Active JP7265566B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021009326A JP7265566B2 (en) 2021-01-25 2021-01-25 Method for evaluating construction condition of air flow passage and method for manufacturing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021009326A JP7265566B2 (en) 2021-01-25 2021-01-25 Method for evaluating construction condition of air flow passage and method for manufacturing building

Publications (2)

Publication Number Publication Date
JP2022113241A JP2022113241A (en) 2022-08-04
JP7265566B2 true JP7265566B2 (en) 2023-04-26

Family

ID=82657943

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021009326A Active JP7265566B2 (en) 2021-01-25 2021-01-25 Method for evaluating construction condition of air flow passage and method for manufacturing building

Country Status (1)

Country Link
JP (1) JP7265566B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005069590A (en) 2003-08-26 2005-03-17 Masahiro Mikami Ventilation system of high air-tight and high heat insulating residence
JP2016102629A (en) 2014-11-28 2016-06-02 協立エアテック株式会社 Air conditioning system and air conditioning system construction method
WO2020095406A1 (en) 2018-11-08 2020-05-14 三菱電機株式会社 Air conditioner
CN210603782U (en) 2019-09-22 2020-05-22 厦门优尼柯机电工程有限公司 A central air-conditioning air duct air leakage detection device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005069590A (en) 2003-08-26 2005-03-17 Masahiro Mikami Ventilation system of high air-tight and high heat insulating residence
JP2016102629A (en) 2014-11-28 2016-06-02 協立エアテック株式会社 Air conditioning system and air conditioning system construction method
WO2020095406A1 (en) 2018-11-08 2020-05-14 三菱電機株式会社 Air conditioner
CN210603782U (en) 2019-09-22 2020-05-22 厦门优尼柯机电工程有限公司 A central air-conditioning air duct air leakage detection device

Also Published As

Publication number Publication date
JP2022113241A (en) 2022-08-04

Similar Documents

Publication Publication Date Title
US8738185B2 (en) Altitude adjustment for heating, ventilating and air conditioning systems
KR101691881B1 (en) The ventilation and air conditioning systems for environment test equipment
JP2021101140A (en) Air conditioning system
CA2836461A1 (en) Methods and apparatus for differential energy based airside economizer changeover
JP6572628B2 (en) Air conditioning ventilation system
JP6856154B2 (en) Air conditioning system
JP7002918B2 (en) Ventilation system, air conditioning system, ventilation method and program
JP7181477B2 (en) air conditioning system
JP7265566B2 (en) Method for evaluating construction condition of air flow passage and method for manufacturing building
Kwag et al. Evaluation of the impact of installation environment for a condensing unit of a split-type air conditioner in a plant room of Korean apartment dwellings
WO2020213216A1 (en) Air conditioning system
CN116209860A (en) Method for selecting additional ventilation device, method for selecting air conditioner, and air conditioning ventilation system
JP7633896B2 (en) Central air conditioning system and its performance evaluation method
Khan et al. Method identifying oversizing of mechanical ventilation systems in office buildings using airflow and electrical power measurements
JP6431387B2 (en) Ventilation air conditioning system and building
JP6942262B2 (en) Air conditioning system
JP7817803B2 (en) Central air conditioning system and its inspection method
CN112528380A (en) Method and system for optimizing ventilation environment of electric room
JP2021004682A (en) Trouble detection method and device of air conditioning system
Hall Test, Adjust and Balance: Lessons Learned for Engineers, Cx and Energy Providers.
JP2004309160A (en) Test method for airtightness of clean room
WO2005071323A1 (en) Ceiling-hanged air conditioner
Howard Performance-Based Specifications for AHUs
Browning Case Studies of Commissioning HVAC Systems
WO2026013886A1 (en) Hot air flow analysis device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210830

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20221101

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20221213

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230411

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230414

R150 Certificate of patent or registration of utility model

Ref document number: 7265566

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150