Permanent scaffold installation method and back panel Download PDF

Info

Publication number
JP7323480B2
JP7323480B2 JP2020031503A JP2020031503A JP7323480B2 JP 7323480 B2 JP7323480 B2 JP 7323480B2 JP 2020031503 A JP2020031503 A JP 2020031503A JP 2020031503 A JP2020031503 A JP 2020031503A JP 7323480 B2 JP7323480 B2 JP 7323480B2
Authority
JP
Japan
Prior art keywords
back panel
frame
installing
bridge axis
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020031503A
Other languages
Japanese (ja)
Other versions
JP2021134559A (en
Inventor
真路 吉川
善彦 中村
雄一 井合
保 村田
純 浅野
真司 大口
重行 箭内
大輝 赤松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Infrastructure Systems Co Ltd
Original Assignee
IHI Infrastructure Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Infrastructure Systems Co Ltd filed Critical IHI Infrastructure Systems Co Ltd
Priority to JP2020031503A priority Critical patent/JP7323480B2/en
Publication of JP2021134559A publication Critical patent/JP2021134559A/en
Application granted granted Critical
Publication of JP7323480B2 publication Critical patent/JP7323480B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、橋梁下に設置される恒久足場の設置方法および裏面パネルに関する。 The present invention relates to a permanent scaffolding installation method and a back panel installed under a bridge.

特許文献1などに記載されているように、橋梁点検では、通行止めや車線規制を極力少なくし、作業の手間と設置コスト低減のため、橋梁下に恒久足場を設置することが行われている。例えば、特許文献1に記載された恒久足場の設置方法では、先ず、縦梁と横梁で構成された格子状のフレームにルーバや折板を固定して、所定の大きさを有したパネル状にユニット化した恒久足場パネルを組み立てる。次いで、恒久足場パネルに単管パイプを架け渡して補強し、これを高所作業車や揚重装置を用いて鋼桁に仮吊りする。そして、恒久足場パネルを足場として利用して本設の吊材に盛り替えることで橋梁下に恒久足場を設置するようにしている。また、既に仮吊りされた恒久足場パネルに対して橋軸方向に新たな恒久足場パネルを送り出すようにしている。 As described in Patent Document 1, etc., in bridge inspections, permanent scaffolding is installed under the bridge to minimize traffic closures and lane restrictions, and to reduce labor and installation costs. For example, in the method of installing a permanent scaffold described in Patent Document 1, first, louvers and folded plates are fixed to a grid-like frame composed of vertical and horizontal beams, and a panel having a predetermined size is formed. Assemble unitized permanent scaffolding panels. Next, the permanent scaffolding panel is reinforced with a single pipe, and temporarily suspended from a steel girder using an aerial work vehicle or a lifting device. Then, permanent scaffolding is installed under the bridge by using the permanent scaffolding panel as a scaffolding and replacing it with the permanent suspension material. In addition, a new permanent scaffolding panel is sent out in the direction of the bridge axis to the already temporarily suspended permanent scaffolding panel.

特開2019-7206号公報JP 2019-7206 A

恒久足場の設置にあたっては、通行止めや車線規制が必要な作業時間を一層短くして、工期短縮が可能な工法が望まれている。例えば、通行止めをして高所作業車や揚重装置を用いた作業を短期化することが望まれている。 When installing permanent scaffolding, there is a demand for a construction method that can shorten the construction period by further shortening the work time required for traffic closures and lane restrictions. For example, it is desired to shorten the work using aerial work vehicles and lifting equipment by closing traffic.

本発明は、上記課題を解決するためになされたものであり、その目的は、通行止めや車線規制の日数、および、工期短縮を可能とした恒久足場の設置方法および裏面パネルを提供することにある。 The present invention has been made to solve the above problems, and its purpose is to provide a permanent scaffolding installation method and a back panel that can shorten the number of days of road closures and lane restrictions and the construction period. .

上記課題を解決するための恒久足場の設置方法は、橋梁下に恒久足場を設置する設置方法であって、橋軸方向に延びる隣り合う縦梁に対して仮設条材を橋軸直角方向に架け渡して仮固定して構成されたフレームを、前記橋梁を構成する主桁から仮設線材で吊り下げる工程と、前記フレームの吊り下げ後、前記縦梁の間に裏面パネルを設置する工程と、前記裏面パネルの設置後、前記主桁と前記縦梁との間に吊材を本設する工程と、前記吊材の本設後、前記仮設条材と前記仮設線材を撤去する工程とを備える。上記構成によれば、フレームを、裏面パネルを設置していない状態で上荷し、その後、仮吊りすることから、当該作業が容易となり作業時間を短期化できる。 A method of installing a permanent scaffolding to solve the above problems is an installation method of installing a permanent scaffolding under a bridge. A step of suspending the frame configured by passing and temporarily fixing the frame from the main girder constituting the bridge with a temporary wire rod, installing a back panel between the vertical beams after suspending the frame, and After installing the back panel, a step of permanently installing a suspension member between the main girder and the vertical beam; and a step of removing the temporary strip member and the temporary wire member after permanently installing the suspension member. According to the above configuration, the frame is loaded without the back panel installed and then temporarily suspended, which facilitates the work and shortens the work time.

上記恒久足場の設置方法において、前記フレームは、第1フレームと、前記橋軸方向において、前記第1フレームの次に配置される第2フレームとを備え、前記第1フレームを前記仮設線材で吊り下げ前記裏面パネルを設置した後、前記第1フレームに前記第2フレームを仮置きする工程と、前記第2フレームを前記仮設線材で吊り下げて、前記橋軸方向における前記第1フレームに対して隣接する位置に送り出し、前記第1フレームの前記縦梁および前記第2フレームの前記縦梁を連結する工程と、前記第2フレームに前記裏面パネルを設置する工程とを備えるようにしてもよい。上記構成によれば、第1フレームの裏面パネルを足場として、第2フレームを裏面パネルが設置されていない軽量な状態で順次橋軸方向に送り出すことができる。したがって、当該作業が容易となり通行止めや車線規制の日数も短くできる。 In the method for installing a permanent scaffold, the frame includes a first frame and a second frame arranged next to the first frame in the bridge axis direction, and the first frame is suspended by the temporary wire. a step of temporarily placing the second frame on the first frame after installing the back panel; The steps of delivering to adjacent positions and connecting the longitudinal beams of the first frame and the longitudinal beams of the second frame and installing the back panel on the second frame may be provided. According to the above configuration, the second frame can be successively sent out in the direction of the bridge axis in a lightweight state without the rear panel installed, using the rear panel of the first frame as a scaffold. Therefore, the work concerned is facilitated, and the number of days of road closures and lane restrictions can be shortened.

上記恒久足場の設置方法において、前記裏面パネルは、第1裏面パネルと、前記橋軸方向の前記第1裏面パネルの次に設置される第2裏面パネルと、前記橋軸方向の前記第2裏面パネルの次に設置される第3裏面パネルとを備え、前記縦梁の間に第1パネルを設置した後、前記第1裏面パネルに対して隣接する位置に前記第2裏面パネルを載置する工程と、前記第2裏面パネルを前記橋軸方向に送り出し、前記第1裏面パネルに対して隣接する位置を空き空間とする工程と、前記空き空間に前記第3裏面パネルを載置する工程とを備えるようにしてもよい。上記構成によれば、縦梁の間には、順次裏面パネルをスライドさせるようにして容易に橋軸方向に並設することができる。 In the method for installing a permanent scaffold, the back panel includes a first back panel, a second back panel installed next to the first back panel in the bridge axis direction, and the second back panel in the bridge axis direction. and a third back panel installed next to the panel, wherein after installing the first panel between the longitudinal beams, the second back panel is placed at a position adjacent to the first back panel. a step of sending out the second back panel in the bridge axis direction to make a space adjacent to the first back panel a vacant space; and a step of placing the third back panel in the vacant space. may be provided. According to the above configuration, the rear panels can be easily arranged side by side in the bridge axis direction between the vertical beams by sliding them one by one.

上記恒久足場の設置方法に用いる裏面パネルは、前記裏面パネルの前記縦梁に接して支持される部分であって、前記裏面パネルを送り出す方向に対して交差する辺の角部は、R面またはC面で構成されているようにしてもよい。上記構成によれば、縦梁に凸部などが存在していても、角部のR面またはC面によって容易に乗り越えることができ、円滑にスライドできる。 The back panel used in the permanent scaffolding installation method is a portion of the back panel that is supported in contact with the longitudinal beams, and the corner of the side that intersects the direction in which the back panel is sent out is an R surface or You may make it comprise by C surface. According to the above configuration, even if the longitudinal beam has a convex portion or the like, it can be easily overcome by the R surface or C surface of the corner, and can slide smoothly.

上記恒久足場の設置方法に用いる裏面パネルは、前記裏面パネルは、隣り合う前記縦梁の橋軸方向に延びる縁部に係合する脱落防止部を備えるようにしてもよい。上記構成によれば、裏面パネルをスライドさせるときにも、縦梁の間から脱落しにくくできる。 The back panel used in the method for installing the permanent scaffolding may include a drop-off prevention portion that engages edges extending in the bridge axis direction of the adjacent longitudinal beams. According to the above configuration, even when the back panel is slid, it can be made difficult to fall out from between the vertical beams.

上記恒久足場の設置方法において、互いに隣り合う前記縦梁のうちの1つは、端部縦梁であり、前記裏面パネルの設置後、前記端部縦梁に対して支柱を設置し前記支柱に対して側面パネルを設置する工程と、前記主桁と前記支柱とを腕材で連結する工程とを備え、前記主桁と前記支柱とを腕材で連結し、前記吊材を本設した後に、前記仮設条材と前記仮設線材を撤去するようにしてもよい。上記構成によれば、橋梁の橋軸直角方向の張出部にも、恒久足場が設置することができる。 In the method for installing a permanent scaffolding, one of the vertical beams adjacent to each other is an end vertical beam, and after installation of the back panel, a support is installed on the end vertical beam and attached to the support. and a step of connecting the main girder and the strut with an arm member. , the temporary strip and the temporary wire may be removed. According to the above configuration, a permanent scaffolding can be installed even on the projecting portion of the bridge in the direction perpendicular to the bridge axis.

本発明によれば、恒久足場を設置するための通行止めや車線規制の日数、および、工期を短縮できる。 According to the present invention, it is possible to shorten the number of days of road closures and lane restrictions for installing a permanent scaffolding, as well as the construction period.

支間部において、縦梁に対して単管パイプを橋軸直角方向に架け渡して仮固定して構成されたフレームをチェーンで仮吊りした状態を示す図。The figure which shows the state which suspended temporarily with the chain the frame comprised by extending the single pipe pipe over the longitudinal beam in the direction perpendicular to a bridge axis, and temporarily fixing in a span part. 図1の続きであって、縦梁間に裏面パネルを設置した状態を示す図。FIG. 2 is a continuation of FIG. 1 and shows a state in which a back panel is installed between longitudinal beams; 縦梁間に裏面パネルを設置した状態を示す斜視図。The perspective view which shows the state which installed the back panel between vertical beams. 図3の続きであって、第1フレームに次の第2フレームを仮置きした状態を示す斜視図。FIG. 4 is a continuation of FIG. 3 and is a perspective view showing a state in which the next second frame is temporarily placed on the first frame; 図4の続きであって、第2フレームに1つ目の裏面パネルを載置した状態を示す斜視図。FIG. 5 is a continuation of FIG. 4 and a perspective view showing a state in which the first back panel is placed on the second frame; 図5の続きであって、第2フレームに次の裏面パネルを載置した状態を示す斜視図。FIG. 6 is a continuation of FIG. 5 and is a perspective view showing a state in which the next back panel is placed on the second frame; 図2の続きであって、吊材を本設した状態を示す図。FIG. 3 is a continuation of FIG. 2 and shows a state in which the hanging member is permanently installed; 図7の続きであって、チェーンと単管パイプを撤去した状態を示す図。The figure which is a continuation of FIG. 7 and shows the state which removed the chain and the single pipe. 橋軸直角方向の両端に設けられる張出部において、フレームをチェーンで吊り下げた状態を示す図。The figure which shows the state which hung the frame with the chain in the overhang part provided in the both ends of the bridge axis right angle direction. 図9の続きであって、縦梁と端部縦梁との間に裏面パネルを設置するとともに、端部縦梁に支柱および側面パネルを設置した状態を示す図。FIG. 10 is a continuation of FIG. 9 and shows a state in which a back panel is installed between the longitudinal beam and the end longitudinal beam, and a support and a side panel are installed on the end longitudinal beam; 図10の続きであって、吊材および腕材を本設した状態を示す図。FIG. 11 is a continuation of FIG. 10 and shows a state in which the hanging member and the arm member are permanently installed; 図11の続きであって、チェーンと単管パイプを撤去した状態を示す図。FIG. 12 is a continuation of FIG. 11 and shows a state in which the chain and the single pipe are removed; 裏面パネルが縦梁に載置された状態を拡大して示す側面図。The side view which expands and shows the state where the back panel was mounted on the vertical beam. 縦梁の側縁部と裏面パネルの脱落防止部との位置関係を示す正面図。The front view which shows the positional relationship of the side edge part of a vertical beam, and the fall-off prevention part of a back panel.

以下、本発明が適用された恒久足場の設置方法について図面を参照して説明する。
図1に示すように、本発明が適用される恒久足場は、橋梁下に設置される足場であって、床版を支持する橋梁の主桁11に設置される。以下、恒久足場の設置方法を説明する。
Hereinafter, a method for installing a permanent scaffolding to which the present invention is applied will be described with reference to the drawings.
As shown in FIG. 1, the permanent scaffolding to which the present invention is applied is a scaffolding installed under a bridge and installed on the main girder 11 of the bridge that supports the floor slab. The following describes how to install a permanent scaffold.

〔第1実施形態〕
図1に示すように、ここでの主桁11は、橋軸方向に延在し、橋軸直角方向において互いに平行に3本配設されている。主桁11は、I形形状からなる鋼材などで構成されている。先ず、主桁11には、フレーム12が仮設線材であるチェーン15で吊り下げられる。フレーム12は、縦梁13と、仮設条材としての単管パイプ14とを備えている。縦梁13は、橋軸方向に延在する梁であって、一例としてH形鋼である。ここでは、縦梁13は、橋軸直角方向において3本配設されている。単管パイプ14は、複数本が縦梁13に架け渡され橋軸直角方向に延在される。そして、各単管パイプ14は、各縦梁13に対してクランプなどによって仮固定される。フレーム12は、縦梁13と単管パイプ14とによって格子状に構成されている。単管パイプ14は、主桁11に吊り下げる際に、各縦梁13が各々に揺動することを抑える。また、橋軸直角方向の間隔を一定にするとともに各縦梁13の高さを一定にする。互いに隣り合う縦梁13の間には、最終的には裏面パネル16が設置されることになるが、この段階では裏面パネル16は設置されていない。
[First Embodiment]
As shown in FIG. 1, the main girders 11 here extend in the direction of the bridge axis, and are arranged in parallel with each other in the direction perpendicular to the axis. The main girder 11 is made of I-shaped steel or the like. First, the frame 12 is suspended from the main girder 11 by the chain 15 which is a temporary wire rod. The frame 12 includes vertical beams 13 and single pipes 14 as temporary members. The vertical beams 13 are beams extending in the direction of the bridge axis, and are H-shaped steel as an example. Here, three vertical beams 13 are arranged in the direction perpendicular to the bridge axis. A plurality of single pipes 14 are bridged over the longitudinal beams 13 and extend in the direction perpendicular to the bridge axis. Each single pipe 14 is temporarily fixed to each vertical beam 13 by a clamp or the like. The frame 12 is configured in a grid pattern with vertical beams 13 and single pipes 14 . The single pipe 14 suppresses each vertical beam 13 from swinging when suspended from the main girder 11 . In addition, the intervals in the direction perpendicular to the bridge axis are made constant and the height of each longitudinal beam 13 is made constant. A back panel 16 will eventually be installed between the longitudinal beams 13 adjacent to each other, but the back panel 16 is not installed at this stage.

フレーム12は、橋梁下において、高所作業車、揚重装置または人力で既設恒久足場まで上荷され、主桁11からチェーン15によって吊り下げられる。チェーン15は、一端が主桁11に設けられた吊下具15aに接続され、他端が縦梁13または単管パイプ14に設けられた吊下具に接続される。なお、チェーン15の他端部は、縦梁13および単管パイプ14の両方に設けた吊下具に接続することもできる。チェーン15には、フレーム12および裏面パネル16が設置された状態を吊り下げできる強度を有するものが使用される。フレーム12は、この段階では裏面パネル16を設置しないことで軽量化が図られており、これにより、高所作業車、揚重装置または人力で既設恒久足場まで上荷する作業も短縮できる。 The frame 12 is lifted to an existing permanent scaffolding under the bridge by an aerial work vehicle, a lifting device, or manually, and suspended from the main girder 11 by the chain 15 . The chain 15 has one end connected to a suspender 15 a provided on the main girder 11 and the other end connected to a suspender provided on the longitudinal beam 13 or the single pipe 14 . The other end of the chain 15 can also be connected to a suspender provided on both the vertical beam 13 and the single pipe 14 . The chain 15 is strong enough to hang the frame 12 and the rear panel 16 in the installed state. The weight of the frame 12 is reduced by not installing the back panel 16 at this stage, and this makes it possible to shorten the work of loading the existing permanent scaffolding with an aerial work vehicle, a lifting device, or human power.

図2に示すように、主桁11からチェーン15によって仮吊りされたフレーム12には、互いに隣り合う縦梁13の間に裏面パネル16が設置される。図3に示すように、裏面パネル16は、矩形板状体であって、長手方向が橋軸直角方向となるように縦梁13の間に設置される。縦梁13は、H形鋼であり、下側フランジ13aに、裏面パネル16の短辺部が支持される。裏面パネル16は、縦梁13の間において橋軸方向に並設される。ここで、1つのフレーム12(以下、「第1フレーム12x」ともいう。)に裏面パネル16が設置されると、当該第1フレーム12xは、次のフレーム12(以下、「第2フレーム12y」ともいう。)が連結され、第2フレーム12yに裏面パネル16を設置するための足場となる。 As shown in FIG. 2, a back panel 16 is installed between the vertical beams 13 adjacent to each other on the frame 12 temporarily suspended from the main girder 11 by the chain 15 . As shown in FIG. 3, the back panel 16 is a rectangular plate and is installed between the vertical beams 13 so that its longitudinal direction is perpendicular to the bridge axis. The vertical beams 13 are H-shaped steel, and the short sides of the back panel 16 are supported by the lower flanges 13a. The back panels 16 are arranged side by side in the bridge axis direction between the longitudinal beams 13 . Here, when the back panel 16 is installed on one frame 12 (hereinafter also referred to as "first frame 12x"), the first frame 12x is attached to the next frame 12 (hereinafter referred to as "second frame 12y"). ) are connected to form a scaffolding for installing the back panel 16 on the second frame 12y.

第2フレーム12yは、第1フレーム12xと同様、縦梁13と、仮設条材としての単管パイプ14とを備えている。図4に示すように、第2フレーム12yは、組み立てられたものを主桁11にチェーン15xによって仮吊りされている第1フレーム12x上の仮置き位置まで高所作業車、揚重装置または人力で既設恒久足場まで上荷してもよいし、第1フレーム12x上において、人力で組み立ててもよい。そして、第2フレーム12yは、第1フレーム12x上に仮置きされ、チェーン15によって吊り下げられる。第2フレーム12yを吊り下げるチェーン15yの一端は、第1フレーム12xの橋軸方向に隣接する第2フレーム12yが配置されるべきフレーム隣接位置上の空間に存在する主桁11に設けられた吊下具15aに接続されている。チェーン15の他端は、第1フレーム12x上にある第2フレーム12yの吊下具に接続される。したがって、第2フレーム12yが第1フレーム12x上にあるとき、チェーン15yは、フレーム隣接位置上の空間に存在する主桁11に設けられた吊下具15aから第2フレーム12yの吊下具の方向へ斜めに延在することになる。 Like the first frame 12x, the second frame 12y includes vertical beams 13 and single pipes 14 as temporary members. As shown in FIG. 4, the assembled second frame 12y is temporarily suspended from the main girder 11 by chains 15x to a temporary placement position on the first frame 12x. , or may be manually assembled on the first frame 12x. The second frame 12y is temporarily placed on the first frame 12x and suspended by the chain 15. As shown in FIG. One end of the chain 15y for suspending the second frame 12y is provided on the main girder 11 existing in the space above the frame adjacent position where the second frame 12y adjacent to the first frame 12x in the bridge axis direction is to be arranged. It is connected to the lower fitting 15a. The other end of the chain 15 is connected to the hanger of the second frame 12y on the first frame 12x. Therefore, when the second frame 12y is on the first frame 12x, the chain 15y extends from the suspender 15a provided on the main girder 11 existing in the space above the frame adjacent position to the suspender of the second frame 12y. It extends diagonally in the direction

図5に示すように、第1フレーム12xを足場として用い、第2フレーム12yは、チェーン15yによって引っ張られるようにして、第1フレーム12x上の位置からフレーム隣接位置へと送り出される。その後、第1フレーム12xの縦梁13と第2フレーム12yの縦梁13とがボルト締結などで連結される。第2フレーム12yを送り出す作業は、第2フレーム12yが裏面パネル16が未設置で軽量であることから、ウィンチやトロリなどを設置するまでもなく人力で行うことができる。この状態では、まだ、第2フレーム12yに裏面パネル16は設置されていない。そこで、次に、第2フレーム12yに裏面パネル16が設置される。 As shown in FIG. 5, using the first frame 12x as a scaffold, the second frame 12y is pulled from a position on the first frame 12x to a position adjacent to the frame by being pulled by chains 15y. After that, the vertical beams 13 of the first frame 12x and the vertical beams 13 of the second frame 12y are connected by bolting or the like. Since the second frame 12y does not have the back panel 16 and is lightweight, the work of sending out the second frame 12y can be done manually without installing a winch or a trolley. In this state, the back panel 16 is not yet installed on the second frame 12y. Therefore, next, the back panel 16 is installed on the second frame 12y.

ここでは、第1フレーム12xに設置された裏面パネル16が第1裏面パネル16xである。第2フレーム12yの縦梁13の間であって、第1フレーム12xの中で最も第2フレーム12y側の第1裏面パネル16xに対して隣接する位置がパネル隣接位置である。第1フレーム12xの第1裏面パネル16xを足場に用いて、第2フレーム12yには、1つ目の第2裏面パネル16yが載置される。すなわち、縦梁13の下側フランジ13aに支持される。この後、第2裏面パネル16yは、橋軸方向にスライドされ、第2裏面パネル16yのあった位置を空き空間19とする。図6に示すように、この空き空間19に、次の第3裏面パネル16zが載置される。さらに多くの裏面パネル16を載置する場合はこの作業を繰り返すことになる。裏面パネル16を設置する作業は、裏面パネル16を1枚ずつ縦梁13の間に設置する作業であるから、ウィンチやトロリなどを設置するまでもなく人力で容易に行うことができる。 Here, the back panel 16 installed on the first frame 12x is the first back panel 16x. A position between the longitudinal beams 13 of the second frame 12y and adjacent to the first back panel 16x closest to the second frame 12y in the first frame 12x is the panel adjacent position. Using the first back panel 16x of the first frame 12x as a foothold, the first second back panel 16y is placed on the second frame 12y. That is, it is supported by the lower flange 13a of the longitudinal beam 13. As shown in FIG. After that, the second back panel 16y is slid in the direction of the bridge axis, and the position where the second back panel 16y was located becomes the empty space 19. As shown in FIG. As shown in FIG. 6, the next third back panel 16z is placed in this empty space 19. As shown in FIG. If more back panels 16 are to be placed, this operation is repeated. Since the work of installing the rear panels 16 is the work of installing the rear panels 16 one by one between the vertical beams 13, it can be easily done manually without installing a winch or a trolley.

なお、フレーム12の送り出しおよび裏面パネル16の設置は、以上のような工程を繰り返すことによって行われる。各裏面パネル16は、締付け金具などで縦梁13に対して順次固定される。 The delivery of the frame 12 and the installation of the back panel 16 are performed by repeating the above steps. Each back panel 16 is sequentially fixed to the longitudinal beam 13 with fasteners or the like.

図7に示すように、裏面パネル16が縦梁13の間に設置されたフレーム12の縦梁13に対しては腕材17を介して吊材18が本設され、チェーン15から盛り替えられる。具体的に、主桁11には、橋軸直角方向に延びる腕材17がボルト締結などで設置され、腕材17と縦梁13との間に吊材18がボルト締結などによって本設される。この後、図8に示すように、単管パイプ14およびチェーン15が撤去される。かくして、縦梁13に裏面パネル16が設置されることによって、恒久足場が設置されることになる。 As shown in FIG. 7, the vertical beams 13 of the frame 12 in which the back panel 16 is installed between the vertical beams 13 are permanently provided with hangers 18 via arms 17, and are rebuilt from the chains 15. . Specifically, an arm member 17 extending in a direction perpendicular to the bridge axis is installed on the main girder 11 by bolting or the like, and a hanging member 18 is permanently installed between the arm member 17 and the longitudinal beam 13 by bolting or the like. . After that, as shown in FIG. 8, the single pipe 14 and the chain 15 are removed. Thus, by installing the back panel 16 on the longitudinal beam 13, a permanent scaffold is installed.

以上のような第1実施形態は、以下に列挙する効果を得ることができる。
(1-1)フレーム12は、裏面パネル16を設置していない状態で上荷され、その後、仮吊りされる。フレーム12は、裏面パネル16されていない分軽量である。したがって、当該作業が容易となり短時間で行うことができる。結果として、通行止めや車両規制の時間も短くできる。
The above-described first embodiment can obtain the following effects.
(1-1) The frame 12 is loaded without the back panel 16 installed, and then suspended temporarily. The frame 12 is lighter because the back panel 16 is not attached. Therefore, the work concerned becomes easy and can be completed in a short time. As a result, the time for road closures and vehicle restrictions can be shortened.

(1-2)フレーム12は、先に設置したフレーム12の裏面パネル16を足場として、次のフレーム12を裏面パネル16が未設置の軽量な状態で順次橋軸方向に送り出すことができる。したがって、ウィンチやトロリなどを設置するまでもなく人力で行うことができる。そして、当該作業が容易となり通行止めや車線規制の日数も短くできる。また、河川の上などでも、橋梁の橋軸方向の端部から順次河川中央方向にフレーム12を送り出すことができる。 (1-2) The frame 12 can be sent out sequentially in the direction of the bridge axis in a lightweight state without the back panel 16 installed, using the back panel 16 of the previously installed frame 12 as a foothold. Therefore, it can be done manually without installing a winch or a trolley. This facilitates the work and shortens the number of days of traffic closures and lane restrictions. In addition, even on a river, the frame 12 can be delivered sequentially from the axial end of the bridge toward the center of the river.

(1-3)縦梁13の間には、順次裏面パネル16をスライドさせるようにして人力によって容易に橋軸方向に並設することができる。したがって、裏面パネル16を設置する作業も容易なものとなる。 (1-3) Between the vertical beams 13, the rear panels 16 can be slid one by one so that they can be easily arranged side by side in the bridge axis direction by human power. Therefore, the work of installing the back panel 16 is also facilitated.

〔第2実施形態〕
第2実施形態は、橋梁の橋軸直角方向の張出部における恒久足場の設置方法である。図9に示すように、ここでは、左端の縦梁が端部縦梁13xである。ここで、すなわち、フレーム12は、2本の縦梁13と左側の端部縦梁13xに対して複数本の単管パイプ14が架け渡されクランプによって仮固定される。そして、フレーム12は、橋梁下において、高所作業車、揚重装置または人力で既設恒久足場まで上荷され、主桁11からチェーン15によって吊り下げられる。主桁11からチェーン15によって仮吊りされたフレーム12には、互いに隣り合う縦梁13の間に裏面パネル16が設置される。
[Second embodiment]
2nd Embodiment is the installation method of the permanent scaffolding in the overhang|hanging part of the bridge axis right angle direction of a bridge. As shown in FIG. 9, here, the leftmost vertical beam is the end vertical beam 13x. Here, in the frame 12, a plurality of single pipes 14 are spanned over the two vertical beams 13 and the left end vertical beam 13x and temporarily fixed by clamps. Then, under the bridge, the frame 12 is lifted to an existing permanent scaffolding by an aerial work vehicle, a lifting device, or manually, and suspended from the main girder 11 by the chain 15 . A back panel 16 is installed between the longitudinal beams 13 adjacent to each other on the frame 12 temporarily suspended from the main girder 11 by the chain 15 .

図10に示すように、端部縦梁13xには、橋軸方向において、所定間隔をあけて支柱21が固定される。そして、図11に示すように、支柱21もチェーン15zによって主桁11と接続され補強される。また、支柱21は、主桁11と単管パイプ14xによって接続され補強される。そして、支柱21には、橋梁の側面パネル22が固定金具などを用いて順次設置される。 As shown in FIG. 10, struts 21 are fixed to the longitudinal end beams 13x at predetermined intervals in the bridge axis direction. Then, as shown in FIG. 11, the strut 21 is also connected to the main girder 11 by the chain 15z and reinforced. Also, the strut 21 is connected and reinforced by the main girder 11 and the single pipe 14x. Then, side panels 22 of the bridge are sequentially installed on the supports 21 using fixing metal fittings or the like.

次いで、フレーム12の縦梁13に対しては腕材17を介して吊材18が本設される。また、支柱21と主桁11とは、腕材23を介して接続される。これにより、チェーン15,15zから盛り替えられる。この後、図12に示すように、単管パイプ14,14xおよびチェーン15,15zが撤去される。かくして、縦梁13に裏面パネル16が設置されることによって、橋梁の橋軸直角方向の張出部にも、恒久足場が設置されることになる。 Next, suspension members 18 are permanently provided on the vertical beams 13 of the frame 12 via arms 17 . Also, the strut 21 and the main girder 11 are connected via an arm member 23 . As a result, the chains 15 and 15z are replaced. After that, as shown in FIG. 12, the single pipes 14, 14x and the chains 15, 15z are removed. Thus, by installing the back panel 16 on the vertical beam 13, a permanent scaffolding is also installed on the projecting portion of the bridge in the direction perpendicular to the bridge axis.

以上のような第2実施形態は、以下に列挙する効果を得ることができる。
(2-1)橋梁の橋軸直角方向の張出部にも、恒久足場を設置することができる。
(2-2)支柱21と主桁11とをチェーン15,15zおよび単管パイプ14,14xで繋ぐことによって、恒久足場の設置作業中において、支柱21や側面パネル22を補強することができる。
The above-described second embodiment can obtain the following effects.
(2-1) Permanent scaffolding can also be installed on overhangs in the direction perpendicular to the bridge axis.
(2-2) By connecting the strut 21 and the main girder 11 with the chains 15, 15z and the single pipes 14, 14x, the strut 21 and the side panel 22 can be reinforced during the installation work of the permanent scaffolding.

〔第3実施形態〕
第1実施形態および第2実施形態で使用する裏面パネル16は、互いに隣り合う縦梁13の間をスライドさせて並設される。具体的に、裏面パネル16は、縦梁13の下側フランジ13a上を滑らせるようにスライドさせる。図13に示すように、裏面パネル16は、長手方向の両側の短辺部分のうちで底面部分が下側フランジ13aと摺接する部分となる。そして、裏面パネル16を送り出す方向に対して交差する長辺の角部24がR面で構成されている。
[Third embodiment]
The back panels 16 used in the first embodiment and the second embodiment are arranged side by side by sliding between the longitudinal beams 13 adjacent to each other. Specifically, the back panel 16 is slid over the lower flange 13a of the vertical beam 13 . As shown in FIG. 13, the back panel 16 has a bottom portion of the short side portions on both sides in the longitudinal direction that is in sliding contact with the lower flange 13a. A corner portion 24 of a long side that intersects the feeding direction of the back panel 16 is formed of an R surface.

また、図14に示すように、裏面パネル16の底面には、下側フランジ13aの先端部の間に位置し、裏面パネル16が縦梁13の間から脱落することを防止する脱落防止部25を備える。脱落防止部25は、裏面パネル16の底面から突出した突出部である。ここで、裏面パネル16と下側フランジ13aとの重なった部分の長さbと、脱落防止部25と下側フランジ13aの先端部までの距離aとの関係は、a<bとなっている。 Further, as shown in FIG. 14, on the bottom surface of the back panel 16, a drop-off prevention portion 25 is positioned between the tips of the lower flanges 13a to prevent the back panel 16 from falling out from between the longitudinal beams 13. Prepare. The drop-off preventing portion 25 is a protruding portion that protrudes from the bottom surface of the back panel 16 . Here, the relationship between the length b of the overlapping portion of the back panel 16 and the lower flange 13a and the distance a between the drop-off prevention portion 25 and the tip of the lower flange 13a is a<b. .

以上のような第3実施形態は、以下に列挙する効果を得ることができる。
(3-1)裏面パネル16は、下側フランジ13aに凸部などが存在していても、長辺の角部24のR面によって容易に乗り越えることができ、円滑にスライドできる。
The above-described third embodiment can obtain the following effects.
(3-1) Even if the lower flange 13a has a projection or the like, the rear panel 16 can easily get over the curved surface of the corner 24 of the long side and slide smoothly.

(3-2)裏面パネル16は、脱落防止部25によって、縦梁13の間をスライドさせるときにも、縦梁13の間から脱落しにくくできる。恒久足場の設置後であっても、振動などによって裏面パネル16位置がずれて縦梁13の間から脱落することを防ぐこともできる。 (3-2) The back panel 16 can be prevented from falling out from between the vertical beams 13 by the falling-off preventing portion 25 even when it is slid between the vertical beams 13 . Even after the permanent scaffolding is installed, it is possible to prevent the back panel 16 from slipping out of the longitudinal beams 13 due to vibration or the like.

(3-3)裏面パネル16と下側フランジ13aとの重なった部分の長さbが脱落防止部25と下側フランジ13aの先端部までの距離aより大きいので、裏面パネル16が何れか一方の縦梁13の方向に偏ったとしても、縦梁13の間から裏面パネル16が脱落することを防ぐことができる。 (3-3) Since the length b of the overlapped portion of the back panel 16 and the lower flange 13a is greater than the distance a between the drop-off prevention portion 25 and the tip of the lower flange 13a, the back panel 16 can be It is possible to prevent the back panel 16 from falling out from between the vertical beams 13 even if it is biased toward the vertical beams 13.例文帳に追加

なお、上記第1実施形態~第3実施形態は、さらに、例えば以下のように適宜変更して実施することもできる。
・第1実施形態の支間部におけるフレーム12を仮吊りする工程と第2実施形態の張出部におけるフレーム12を仮吊りする工程とは同時並行で行ってもよいし、第1実施形態の工法で支間部に恒久足場を設置してから、第2実施形態における張出部の恒久足場を設置するようにしてもよい。これとは逆に、第2実施形態における張出部の恒久足場を設置してから第1実施形態の工法で支間部に恒久足場を設置するようにしてもよい。
Note that the first to third embodiments can be modified as appropriate, for example, as follows.
The step of temporarily suspending the frame 12 at the span portion of the first embodiment and the step of temporarily suspending the frame 12 at the projecting portion of the second embodiment may be performed in parallel, or the construction method of the first embodiment may be performed. After installing the permanent scaffolding on the span, the permanent scaffolding on the overhanging portion in the second embodiment may be installed. Conversely, after installing the permanent scaffolding of the overhanging portion in the second embodiment, the permanent scaffolding may be installed in the span portion by the construction method of the first embodiment.

・第2実施形態において、支柱21を補強する単管パイプ14xやチェーン15zを省略するようにしてもよいし、単管パイプ14x、チェーン15zの何れか一方を省略するようにしてもよい。 - In the second embodiment, the single pipe 14x and the chain 15z that reinforce the column 21 may be omitted, or either the single pipe 14x or the chain 15z may be omitted.

・裏面パネル16において、脱落防止部25は、下側フランジ13aの先端部の近傍に突起状に設ける構成でもよいし、下側フランジ13aの先端部の間の全域に亘って長辺に沿って延在する突片であってもよい。脱落防止部25を省略してもよい。 ・On the back panel 16, the drop-off prevention part 25 may be provided in a projecting shape near the tip of the lower flange 13a, or may be provided along the long side over the entire area between the tips of the lower flange 13a. It may be an extended protrusion. The drop-off preventing portion 25 may be omitted.

・裏面パネル16において、角部24は、C面であってもよい。
・裏面パネル16において、角部24は、R面またはC面を備えていなくてもよい。
・裏面パネル16は、縦梁13の間をスライドさせて空き空間19を設けて空き空間19に新たな裏面パネル16を設置する手順に従わなくてもよい。すなわち、橋軸方向に順に並べるように裏面パネル16を設置するようにしてもよい。
- In the back panel 16, the corner portion 24 may be a C surface.
- In the back panel 16, the corner portion 24 may not have the R surface or the C surface.
- The back panel 16 does not have to follow the procedure of sliding between the vertical beams 13 to provide an empty space 19 and installing a new back panel 16 in the empty space 19 . That is, the rear panels 16 may be installed so as to be arranged in order in the direction of the bridge axis.

・仮設線材としてのチェーン15,15zは、ワイヤロープなどの吊り下げ支持に必要な強度を有する線材を用いてもよい。
・仮設条材としての単管パイプ14,14xは、ワイヤロープなどに代えてもよい。また、縦梁13間に架け渡される単管パイプ14の本数や支柱21と主桁11とを繋ぐ単管パイプ14xの本数は、補強機能を果たす強度を有するのであれば、特に限定されるものではない。
- Chains 15 and 15z as temporary wires may be wire rods such as wire ropes that have the strength necessary for suspension support.
- The single pipe pipes 14, 14x as temporary materials may be replaced with wire ropes or the like. In addition, the number of the single pipes 14 that span between the longitudinal beams 13 and the number of the single pipes 14x that connect the struts 21 and the main girders 11 are particularly limited as long as they have sufficient strength to perform the reinforcing function. isn't it.

・腕材17は場所によって省略してもよいし、異なる構成であってもよい。 - The arm member 17 may be omitted depending on the location, or may have a different configuration.

11…主桁
12(12x,12y)…フレーム
13…縦梁
13a…下側フランジ
13x…端部縦梁
14,14x…単管パイプ
15(15x,15y),15z…チェーン
16(16x,16y,16z)…裏面パネル
17,23…腕材
18…吊材
19…空き空間
21…支柱
22…側面パネル
24…角部
25…脱落防止部
11 Main girder 12 (12x, 12y) Frame 13 Vertical beam 13a Lower flange 13x Vertical end beam 14, 14x Single pipe 15 (15x, 15y), 15z Chain 16 (16x, 16y, 16z) Back panels 17, 23 Arm member 18 Suspension member 19 Empty space 21 Strut 22 Side panel 24 Corner portion 25 Drop-off prevention portion

Claims (6)

橋梁下に恒久足場を設置する設置方法であって、
橋軸方向に延びる隣り合う縦梁に対して仮設条材を橋軸直角方向に架け渡して仮固定して構成されたフレームを、前記橋梁を構成する主桁から仮設線材で吊り下げる工程と、
前記フレームの吊り下げ後、前記縦梁の間に裏面パネルを設置する工程と、
前記裏面パネルの設置後、前記主桁と前記縦梁との間に吊材を本設する工程と、
前記吊材の本設後、前記仮設条材と前記仮設線材を撤去する工程と
を備える恒久足場の設置方法。
An installation method for installing a permanent scaffold under a bridge,
a step of suspending a frame, which is constructed by temporarily fixing temporary members across adjacent longitudinal beams extending in the direction of the bridge axis in a direction perpendicular to the bridge axis, from the main girder constituting the bridge with temporary wires;
installing a back panel between the longitudinal beams after hanging the frame;
After installing the back panel, a step of permanently installing hanging members between the main girder and the longitudinal beam;
A method for installing a permanent scaffolding, comprising removing the temporary material and the temporary wire after permanently installing the hanging material.
前記フレームは、第1フレームと、前記橋軸方向において、前記第1フレームの次に配置される第2フレームとを備え、
前記第1フレームを前記仮設線材で吊り下げ前記裏面パネルを設置した後、前記第1フレームに前記第2フレームを仮置きする工程と、
前記第2フレームを前記仮設線材で吊り下げて、前記橋軸方向における前記第1フレームに対して隣接する位置に送り出し、前記第1フレームの前記縦梁および前記第2フレームの前記縦梁を連結する工程と、
前記第2フレームに前記裏面パネルを設置する工程と
を備える請求項1に記載の恒久足場の設置方法。
The frame comprises a first frame and a second frame arranged next to the first frame in the bridge axis direction,
a step of temporarily placing the second frame on the first frame after suspending the first frame with the temporary wire and installing the back panel;
The second frame is suspended by the temporary wire rods, sent to a position adjacent to the first frame in the bridge axis direction, and the longitudinal beams of the first frame and the longitudinal beams of the second frame are connected. and
2. The method of installing a permanent scaffold according to claim 1, comprising installing the back panel on the second frame.
前記裏面パネルは、第1裏面パネルと、前記橋軸方向の前記第1裏面パネルの次に設置される第2裏面パネルと、前記橋軸方向の前記第2裏面パネルの次に設置される第3裏面パネルとを備え、
前記縦梁の間に前記第1裏面パネルを設置した後、前記第1裏面パネルに対して隣接する位置に前記第2裏面パネルを載置する工程と、
前記第2裏面パネルを前記橋軸方向に送り出し、前記第1裏面パネルに対して隣接する位置を空き空間とする工程と、
前記空き空間に前記第3裏面パネルを載置する工程と
を備える請求項1または2に記載の恒久足場の設置方法。
The back panel includes a first back panel, a second back panel installed next to the first back panel in the bridge axis direction, and a second back panel installed next to the second back panel in the bridge axis direction. 3 back panel,
After installing the first back panel between the longitudinal beams, placing the second back panel at a position adjacent to the first back panel;
a step of sending out the second back panel in the direction of the bridge axis to make a position adjacent to the first back panel empty space;
and placing the third rear panel in the empty space.
互いに隣り合う前記縦梁のうちの1つは、端部縦梁であり、
前記裏面パネルの設置後、前記端部縦梁に対して支柱を設置し前記支柱に対して側面パネルを設置する工程と、
前記主桁と前記支柱とを腕材で連結する工程とを備え、
前記主桁と前記支柱とを腕材で連結し、前記吊材を本設した後に、前記仮設条材と前記仮設線材を撤去する
請求項1ないし3のうち何れか1項に記載の恒久足場の設置方法。
one of the longitudinal beams adjacent to each other is an end longitudinal beam;
After installation of the back panel, installing a stanchion against the end longitudinal beam and installing a side panel against the stanchion;
A step of connecting the main girder and the strut with an arm member,
The permanent scaffolding according to any one of claims 1 to 3, wherein the main girder and the post are connected by arms, and the temporary members and the temporary wires are removed after the hanging members are permanently installed. installation method.
請求項3に記載の恒久足場の設置方法に用いる裏面パネルであって、
前記裏面パネルの前記縦梁に接して支持される部分であって、前記裏面パネルを送り出す方向に対して交差する辺の角部は、R面またはC面で構成されている裏面パネル。
A back panel used in the method for installing a permanent scaffold according to claim 3,
The back panel is a portion of the back panel that is supported in contact with the longitudinal beams, and a corner portion of a side that intersects the direction in which the back panel is sent out is formed of an R face or a C face.
請求項1ないし3のうち何れか1項に記載の恒久足場の設置方法に用いる裏面パネルであって、
前記裏面パネルは、隣り合う前記縦梁の橋軸方向に延びる縁部に係合する脱落防止部を備える裏面パネル。
A back panel used in the method for installing a permanent scaffold according to any one of claims 1 to 3,
The back panel is provided with a fall-off prevention part that engages with an edge portion extending in the bridge axis direction of the adjacent longitudinal beams.
JP2020031503A 2020-02-27 2020-02-27 Permanent scaffold installation method and back panel Active JP7323480B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020031503A JP7323480B2 (en) 2020-02-27 2020-02-27 Permanent scaffold installation method and back panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020031503A JP7323480B2 (en) 2020-02-27 2020-02-27 Permanent scaffold installation method and back panel

Publications (2)

Publication Number Publication Date
JP2021134559A JP2021134559A (en) 2021-09-13
JP7323480B2 true JP7323480B2 (en) 2023-08-08

Family

ID=77660553

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020031503A Active JP7323480B2 (en) 2020-02-27 2020-02-27 Permanent scaffold installation method and back panel

Country Status (1)

Country Link
JP (1) JP7323480B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2024057463A (en) * 2022-10-12 2024-04-24 株式会社Ihiインフラシステム Permanent bridge scaffolding

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000144641A (en) 1998-11-13 2000-05-26 Kobe Steel Ltd Execution method for combination scaffold and back plate of elevated structure
JP2015004213A (en) 2013-06-20 2015-01-08 株式会社ウインド19 Panel for suspension scaffold and construction method of panel for suspension scaffold and panel unit for suspension scaffold
JP2015028284A (en) 2013-07-02 2015-02-12 日鐵住金建材株式会社 Suspended scaffolding panel
JP2016017329A (en) 2014-07-09 2016-02-01 信和株式会社 Construction method of suspended scaffolding
JP2017020340A (en) 2016-11-02 2017-01-26 Jfeエンジニアリング株式会社 Scaffold structure
JP2019007206A (en) 2017-06-23 2019-01-17 日本橋梁株式会社 Method of installing non-scaffold for bridge inspection permanent scaffold

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5969357U (en) * 1982-10-31 1984-05-11 ナショナル住宅産業株式会社 scaffolding equipment
JPH1113275A (en) * 1997-06-27 1999-01-19 Kawatetsu Kizai Kogyo Kk Aerial expansion type suspended scaffold and its construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000144641A (en) 1998-11-13 2000-05-26 Kobe Steel Ltd Execution method for combination scaffold and back plate of elevated structure
JP2015004213A (en) 2013-06-20 2015-01-08 株式会社ウインド19 Panel for suspension scaffold and construction method of panel for suspension scaffold and panel unit for suspension scaffold
JP2015028284A (en) 2013-07-02 2015-02-12 日鐵住金建材株式会社 Suspended scaffolding panel
JP2016017329A (en) 2014-07-09 2016-02-01 信和株式会社 Construction method of suspended scaffolding
JP2017020340A (en) 2016-11-02 2017-01-26 Jfeエンジニアリング株式会社 Scaffold structure
JP2019007206A (en) 2017-06-23 2019-01-17 日本橋梁株式会社 Method of installing non-scaffold for bridge inspection permanent scaffold

Also Published As

Publication number Publication date
JP2021134559A (en) 2021-09-13

Similar Documents

Publication Publication Date Title
JP6004353B2 (en) Replacement method of concrete floor slab for elevated road
JP5097313B2 (en) Suspended scaffold and its installation method
JPH1113275A (en) Aerial expansion type suspended scaffold and its construction
JP6786070B2 (en) Permanent scaffolding installation method for bridge inspection
JP7265967B2 (en) Cantilever device for bridge construction and bridge construction and demolition method
CN217028088U (en) Cantilever tripod template support
JP7323480B2 (en) Permanent scaffold installation method and back panel
WO2020075511A1 (en) Mobile scaffold installation method
JP2000096819A (en) Temporary construction method of working scaffold for pedestrian bridge, overhead line beam and the like
JP2018003509A (en) Floor slab unit, floor slab basic assembly method and construction method of floor
JP5807883B1 (en) Suspended scaffolding
JP7139256B2 (en) Mobile work equipment, construction method of arch bridge
JPH09195228A (en) Build-up trestle for bridge pier reinforcing work and its using method
JP3752934B2 (en) Method for constructing annular concrete frame using slip form device
JP6053981B1 (en) Floor slab unit
JPH07103679B2 (en) Suspension scaffold assembly method and scaffold material used for it
JP3100574B2 (en) Suspended scaffold and its erection method
JP7708696B2 (en) How to remove the tunnel ceiling
JP6929180B2 (en) Temporary construction method for work scaffolding in a boiler
JPH10121713A (en) Loading stage and its mounting method
JP3048118B2 (en) Bracket support structure
JPH07217230A (en) Suspended stairs and temporary construction method
JPH0740594Y2 (en) Hanging scaffolding material
JPH11166207A (en) Form for floor slab
JPH0711771A (en) Reinforcing bar cage assembly / building equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20221019

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230623

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230627

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230705

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230725

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230727

R150 Certificate of patent or registration of utility model

Ref document number: 7323480

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150