JP7348136B2 - Driving plan creation device and driving plan creation method - Google Patents
Driving plan creation device and driving plan creation method Download PDFInfo
- Publication number
- JP7348136B2 JP7348136B2 JP2020096420A JP2020096420A JP7348136B2 JP 7348136 B2 JP7348136 B2 JP 7348136B2 JP 2020096420 A JP2020096420 A JP 2020096420A JP 2020096420 A JP2020096420 A JP 2020096420A JP 7348136 B2 JP7348136 B2 JP 7348136B2
- Authority
- JP
- Japan
- Prior art keywords
- block
- construction
- blocks
- driving
- group
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Description
本発明は、コンクリートの打込み計画作成装置および打込み計画作成方法に関する。 The present invention relates to a concrete pouring plan creation device and a concrete pouring plan creation method.
通常、コンクリート工事の施工者は、打込み計画を手作業で作成し、その計画に沿ってコンクリートの打込みを行う。施工対象物が高さのある部材の場合、数層(例えば、一つの層が数十cm程度)に分けてコンクリートの打込みを行うので、打込み計画は、「打重ね計画」などと呼ばれる場合がある。コンクリート工事において、コンクリートを打重ねる時間の間隔(打重ね時間間隔)は、重要な管理項目である。打重ねに時間を要した場合、コールドジョイント等の初期欠陥の発生を招き、所定の品質を確保できなくなる。 Usually, a concrete contractor manually creates a pouring plan and pours concrete in accordance with the plan. When the object to be constructed is a tall member, concrete is poured in several layers (for example, each layer is about several tens of centimeters), so the pouring plan is sometimes called a "layered pouring plan." be. In concrete work, the time interval between pouring concrete (overlap time interval) is an important control item. If it takes time to repeat the hammering, initial defects such as cold joints may occur, making it impossible to maintain the desired quality.
従来、コンクリート工事における打重ね時間間隔を管理するための技術として、例えば以下のものが提案されている。
特許文献1には、型枠の上方に配置された形状センサを用いて打重ね面の形状に関する情報を取得することにより、型枠によって目視困難な場所におけるコンクリートの打込み状況を確認することが記載されている。
また、特許文献2には、コンクリート打設現場の上方側から撮影した映像をメッシュ状に細分化し、打込み完了時からの経過時間に応じてメッシュを段階毎に色分けすることが記載されている。これにより、打重ね時間間隔を視覚的に把握することができる。
Conventionally, for example, the following techniques have been proposed as techniques for managing pouring time intervals in concrete construction.
Further,
しかし、特許文献1,2に記載された技術は、何れもコンクリートの打込みを行っている最中に打重ね時間間隔を管理するための技術であるので、依然として打込み計画を手作業で作成する必要があった。そのため、施工対象物の形状が複雑な場合には、打込み計画の作成に多くの時間を費やしてしまうという問題があった。また、作成した打込み計画が最適かどうかの判断は、施工者の裁量によるところが大きいので、打込み計画が最適であるか否かを客観的に評価することが難しいという問題があった。
However, the techniques described in
このような観点から、本発明は、コンクリートの好適な打込み計画を作成することができる打込み計画作成装置および打込み計画作成方法を提供する。 From this viewpoint, the present invention provides a pouring plan creation device and a pouring plan creation method that can create a suitable concrete pouring plan.
本発明に係る打込み計画作成装置は、コンクリート打設における打込み計画を作成する打込み計画作成装置である。前記打込み計画は、施工対象物を分割した施工ブロックにコンクリートを打ち込む順番を設定した施工ブロック単位での打込み順序である。
この打込み計画作成装置は、連続して打込みを行う施工ブロックのまとまりである候補ブロック群を前記施工対象物に対して順番に設定するブロック群設定部と、前記候補ブロック群内の打込み順序を決定する群内順序決定部とを備える。
前記候補ブロック群は、当該候補ブロック群の基準となる前記施工ブロックである着目ブロックに隣接する打重ねブロック、および前記打重ねブロックの周辺に位置する拡張ブロックで構成される。
前記ブロック群設定部は、一つ前の前記候補ブロック群内の打込み順序が決定された時点で、打込み済みの前記施工ブロックの中から、隣接する前記施工ブロックに対する打込みが未完了かつ打込み完了時刻が最も早い打込み済みの施工ブロックを選択し、選択された施工ブロックを新たな前記着目ブロックとして前記候補ブロック群を新たに設定する。
A pouring plan creating device according to the present invention is a pouring plan creating device that creates a pouring plan for concrete pouring. The pouring plan is a pouring order for each construction block, which sets the order in which concrete is poured into construction blocks into which the construction target is divided.
This driving plan creation device includes a block group setting unit that sequentially sets a candidate block group, which is a group of construction blocks to be successively driven, for the construction target, and a block group setting unit that determines the driving order within the candidate block group. and an intra-group order determining unit.
The candidate block group is composed of a stacked block adjacent to the block of interest, which is the construction block serving as a reference for the candidate block group, and an expansion block located around the stacked block.
The block group setting unit determines, at the time when the driving order in the previous candidate block group is determined, that the driving for the adjacent construction block among the already driven construction blocks is incomplete and the driving completion time. selects the construction block that has already been driven in the earliest, and sets the candidate block group anew with the selected construction block as the new target block.
本発明に係る打込み計画作成方法は、コンピュータが、コンクリート打設における打込み計画を作成する打込み計画作成方法である。前記打込み計画は、施工対象物を分割した施工ブロックにコンクリートを打ち込む順番を設定した施工ブロック単位での打込み順序である。
このコンピュータは、連続して打込みを行う施工ブロックのまとまりである候補ブロック群を前記施工対象物に対して順番に設定するブロック群設定ステップと、前記候補ブロック群内の打込み順序を決定する群内順序決定ステップとを実行する。前記ブロック群設定ステップと前記群内順序決定ステップとを繰り返し実行することで、前記施工対象物を構成する前記施工ブロックの打込み順序を決定する。
前記候補ブロック群は、当該候補ブロック群の基準となる前記施工ブロックである着目ブロックに隣接する打重ねブロック、および前記打重ねブロックの周辺に位置する拡張ブロックで構成される。
前記ブロック群設定ステップでは、一つ前の前記候補ブロック群内の打込み順序が決定された時点で、打込み済みの前記施工ブロックの中から、隣接する前記施工ブロックに対する打込みが未完了かつ打込み完了時刻が最も早い打込み済みの施工ブロックを選択し、選択された施工ブロックを新たな前記着目ブロックとして前記候補ブロック群を新たに設定する。
A pouring plan creation method according to the present invention is a pouring plan creation method in which a computer creates a pouring plan for pouring concrete. The pouring plan is a pouring order for each construction block, which sets the order in which concrete is poured into construction blocks into which the construction target is divided.
This computer performs a block group setting step of sequentially setting a candidate block group, which is a group of construction blocks to be successively driven, for the construction object, and a block group setting step of determining the driving order within the candidate block group. and performing an ordering step. By repeatedly performing the block group setting step and the intra-group order determining step, the driving order of the construction blocks constituting the construction target is determined.
The candidate block group is composed of a stacked block adjacent to the block of interest, which is the construction block serving as a reference for the candidate block group, and an expansion block located around the stacked block.
In the block group setting step, when the driving order in the previous candidate block group is determined, it is determined that among the already driven construction blocks, the driving to the adjacent construction block is not completed and the driving completion time is determined. selects the construction block that has already been driven in the earliest, and sets the candidate block group anew with the selected construction block as the new target block.
前記拡張ブロックは、前記着目ブロックの一つ下の段の前記施工ブロックであって、前記打重ねブロックよりも外側に位置するのがよい。 The expansion block is the construction block one level below the target block, and is preferably located outside the stacked block.
本発明に係る打込み計画作成装置および打込み計画作成方法においては、着目ブロックの打重ねブロックが早期に打込み完了となるように候補ブロック群を設定する。すなわち、打重ねブロックの打込み制約条件がより早期に整うように、着目ブロックの打重ねに直接関係のない施工ブロックについても候補ブロック群に含めている。そのため、着目ブロックに対する打重ねブロックだけを候補ブロックとした場合と比べて、最大打重ね時間の短縮に有効である。その結果、コンクリートの好適な打込み計画を作成することができる。 In the driving plan creation device and driving plan creation method according to the present invention, the candidate block group is set so that the driving of the overlapping block of the block of interest is completed early. That is, construction blocks that are not directly related to the stacking of the block of interest are also included in the candidate block group so that the driving constraint conditions for the stacked blocks can be set more quickly. Therefore, compared to the case where only the overlapping blocks for the block of interest are used as candidate blocks, this method is effective in shortening the maximum overlapping time. As a result, a suitable concrete placement plan can be created.
本発明によれば、コンクリートの好適な打込み計画を作成することができる打込み計画作成装置および打込み計画作成方法を提供できる。 According to the present invention, it is possible to provide a pouring plan creation device and a pouring plan creation method that can create a suitable concrete pouring plan.
以下、本発明の実施をするための形態を、適宜図面を参照しながら詳細に説明する。各図は、本発明を十分に理解できる程度に、概略的に示してあるに過ぎない。よって、本発明は、図示例のみに限定されるものではない。なお、各図において、共通する構成要素や同様な構成要素については、同一の符号を付し、それらの重複する説明を省略する。 DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments for carrying out the present invention will be described in detail with reference to the drawings as appropriate. The figures are only shown schematically to provide a thorough understanding of the invention. Therefore, the present invention is not limited to the illustrated example. In each figure, common or similar components are designated by the same reference numerals, and their overlapping explanations will be omitted.
<実施形態に係る打込み計画作成装置の構成>
図1を参照して、実施形態に係る打込み計画作成装置100の構成について説明する。図1は、実施形態に係る打込み計画作成装置100の概略構成図である。打込み計画作成装置100は、コンクリート打設における打込み計画を作成する装置である。打込み計画作成装置100は、コンクリートを打設する様々な場面で使用することができ、施工対象物の種類、形状、サイズや、コンクリートを打設する工法などは特に限定されるものではない。打込み計画は、コンクリートの打込みを行う順番を示すものであり、例えば、施工対象物の部分(例えば、ブロック)を識別する情報と打ち込む順番とを対応付けたものである。
<Configuration of driving plan creation device according to embodiment>
With reference to FIG. 1, the configuration of a driving
図2を参照して、コンクリート工事を行う施工対象物について説明する。図2は、コンクリート工事を行う施工対象物の例示であり、(a)は施工対象物であるコンクリート構造物Aの施工が完成した状態のイメージ図であり、(b)はコンクリート構造物Aを正面から観た状態を示している。本実施形態では、図2(a)に示すように、施工対象物として、横、奥行き、高さの方向に広がりのるコンクリート構造物Aを想定し、打込み計画作成装置100がコンクリート構造物Aの打込み計画を作成する。なお、コンクリート構造物Aは、横、奥行き、高さの何れかの方向の長さが卓越したもの(柱や梁など長尺な形状の構造物)や、横、奥行き、高さの何れか二方向の長さが卓越したもの(壁体や床体など面状の構造物)であってもよい。
Referring to FIG. 2, a construction target for concrete work will be described. Figure 2 shows an example of the object to be concreted, where (a) is an image of the completed concrete structure A, and (b) is the concrete structure A shown in front. It shows the state as seen from. In this embodiment, as shown in FIG. 2(a), a concrete structure A that expands in the width, depth, and height directions is assumed as the construction target, and the pouring
コンクリート構造物Aは、複数の領域に分割されており、分割された最小単位の領域を「施工ブロックB」と呼ぶことにする。施工ブロックBは、施工を管理する最小単位の領域である。施工ブロックBは、隣接する施工ブロックBとの境界が型枠、金網、目地材などによって物理的に決められた領域であってもよいし、隣接する施工ブロックBとの境界が物理的に決められていない仮想の領域であってもよい。以下では、特定の施工ブロックBを示して説明する場合に、「施工ブロックB(k,l,m)」と表記する場合がある。「k,l,m」は、施工ブロックBを識別するための識別情報であり、ここでは「k」が横方向の並び順を示し、「l」が奥行き方向の並び順を示し、「m」が高さ方向の並び順を示している。なお、一つの施工ブロックB(k,l,m)のサイズは、例えばコンクリート打設の施工条件(特に、コンクリートの打込みに使用されるポンプ車の性能など)によって決めることができる。 Concrete structure A is divided into a plurality of areas, and the divided minimum unit area will be referred to as "construction block B". Construction block B is the minimum unit area for managing construction. Construction block B may be an area whose boundary with adjacent construction block B is physically determined by formwork, wire mesh, joint material, etc., or where the boundary with adjacent construction block B is physically determined. It may also be a virtual area that has not been created. Below, when showing and explaining a specific construction block B, it may be written as "construction block B (k, l, m)". "k,l,m" is identification information for identifying construction block B. Here, "k" indicates the arrangement order in the horizontal direction, "l" indicates the arrangement order in the depth direction, and "m ” indicates the arrangement order in the height direction. Note that the size of one construction block B (k, l, m) can be determined, for example, depending on the construction conditions for concrete pouring (in particular, the performance of the pump truck used for concrete pouring).
図1に示す打込み計画作成装置100は、仮想的な三次元空間を用いてコンクリート構造物Aの打込み計画をシミュレーションによって作成する。打込み計画のシミュレーションでは、コンクリート構造物Aを抽象化(モデル化)した施工モデルC(図1参照)を使用して打込み計画を作成する。施工モデルCは、コンクリート構造物Aと同様に施工ブロックB(k,l,m)に対応して分割されている。
A placing
図1に示すように、実施形態に係る打込み計画作成装置100は、記憶部30と、制御部40とを備える。打込み計画作成装置100は、例えば、打込み計画の作成を担当する者(以下では、「作成者」と呼ぶ)が操作するパーソナルコンピュータ(PC:Personal Computer)や当該パーソナルコンピュータと通信可能に接続されたアプリケーションサーバである。ここでの作成者は、例えば、コンクリート工事の施工者である。
As shown in FIG. 1, the implantation
記憶部30は、RAM(Random Access Memory)、ROM(Read Only Memory)、HDD(Hard Disk Drive)、フラッシュメモリ等の記憶媒体から構成される。制御部40は、CPU(Central Processing Unit)によるプログラム実行処理や、専用回路等により実現される。制御部40がプログラム実行処理により実現する場合、記憶部30には、制御部40の機能を実現するためのプログラムが格納される。なお、打込み計画作成装置100が、図示しない外部の記憶手段から記憶部30に記憶される情報を必要に応じて取得してもよい。
The
記憶部30には、打込み計画の作成に必要な情報(ここでは、打込み条件情報31と、施工モデルC)が記憶されている。打込み条件情報31には、コンクリートポンプ車が備えるポンプの性能に関する情報、打重ね時間間隔に関する情報などが含まれる。また、複数のコンクリートポンプ車を用いてコンクリートの打込みを行う場合、打込み条件情報31には、コンクリートを打ち込む打込み口の数などが含まれる。施工モデルCは、施工対象物を抽象化(モデル化)したものである。施工モデルCは、施工対象物と同様に施工ブロックB(k,l,m)に対応して分割されている。施工モデルCには、各々の施工ブロックB(k,l,m)の位置関係やサイズが設定される。
The
制御部40は、主に、条件設定部41と、打込み順序作成部42と、順序評価部45と、を備える。なお、図1に示す制御部40の各機能は、説明の便宜上分けたものであり、当該機能の分け方は本発明の一例に過ぎない。
The
条件設定部41は、打込み条件情報31や施工モデルCの登録を受け付け、記憶部30にこれらの情報を格納する。
The
打込み順序作成部42は、施工モデルCを用いて打込み計画を作成する。打込み順序作成部42は、ブロック群設定部43と、群内順序決定部44とを備える。
ブロック群設定部43は、連続して打込みを行う施工ブロックBのまとまりである候補ブロック群Q(図4参照)を施工モデルC(施工対象物)に対して順番に設定する。
群内順序決定部44は、施工モデルC(施工対象物)に対して設定された候補ブロック群Q内の打込み順序を決定する。
The driving
The block
The intra-group
図4に候補ブロック群Qの一例を示す。図4は、候補ブロック群Qを説明するための図であり、(a)は候補ブロック群Qの斜視図であり、(b)は候補ブロック群Qの平面図である。図4に示す候補ブロック群Qは、候補ブロック群Qの基準となる施工ブロックBaの周辺における幾何学的な位置関係によって定義される。以下では、候補ブロック群Qの基準となる施工ブロックBaのことを「着目ブロックBa」と表現する場合がある。ブロック群設定部43は、例えば候補ブロック群Qを設定する時点において、隣接する施工ブロックBaの少なくとも一つの打込みが未完了であり、かつ、打込み完了時刻が最も早い打込み済みの施工ブロックBを着目ブロックBaとして選択する。
FIG. 4 shows an example of the candidate block group Q. FIG. 4 is a diagram for explaining the candidate block group Q, in which (a) is a perspective view of the candidate block group Q, and (b) is a plan view of the candidate block group Q. The candidate block group Q shown in FIG. 4 is defined by the geometric positional relationship around the construction block Ba, which is the reference of the candidate block group Q. In the following, the construction block Ba that serves as a reference for the candidate block group Q may be expressed as a "target block Ba." For example, at the time of setting the candidate block group Q, the block
図3を参照して、施工ブロックBの打重ねを説明する。図3は、施工ブロックBの打重ねを説明するための図である。図3に示すように、着目ブロックBaの打重ねを完了するためには、着目ブロックBaの前に位置する施工ブロックBb1、後ろに位置する施工ブロックBa2、左に位置する施工ブロックBa3、右に位置する施工ブロックBa4、直上に位置する施工ブロックBa5の全てを打込む必要がある。なお、空中への打設はできないので、着目ブロックBaの直下には他の施工ブロックB(または土台など)があることが前提となり、ここでは着目ブロックBaの直下の施工ブロックBを問題にしないことにする。以下の説明では、これらの施工ブロックBb1~Bb5を、着目ブロックBaに対する「打重ねブロックBb」と呼ぶ場合がある。言い換えると、ブロック群設定部43は、打重ねが完了しておらず(打重ねブロックBbの何れかの打込みが完了しておらず)、かつ、打込み完了時刻が最も早い打込み済みの施工ブロックBを着目ブロックBaとして選択する。
Referring to FIG. 3, stacking of construction blocks B will be described. FIG. 3 is a diagram for explaining the stacking of construction blocks B. As shown in FIG. 3, in order to complete the stacking of the target block Ba, construction block Bb1 located in front of the target block Ba, construction block Ba2 located behind, construction block Ba3 located on the left, construction block Bb3 located on the right, It is necessary to drive all of the construction block Ba4 located there and the construction block Ba5 located directly above it. In addition, since pouring in the air is not possible, it is assumed that there is another construction block B (or a foundation, etc.) directly below the target block Ba, and the construction block B directly below the target block Ba is not considered here. I'll decide. In the following description, these construction blocks Bb1 to Bb5 may be referred to as "stacked blocks Bb" for the target block Ba. In other words, the block
図4に示すように、本実施形態における候補ブロック群Qは、着目ブロックBaに隣接する打重ねブロックBbと、打重ねブロックBbの下層周辺に位置する拡張ブロックBcとで構成される。なお、本実施形態では着目ブロックBa自身並びに着目ブロックBaおよび打重ねブロックBb1~Bb4の直下の施工ブロックBは、候補ブロック群Qに含まれないことにする。これらの施工ブロックBは、後述する打込みの制約条件によって既に打込みが完了していることを前提としているためである。なお、打重ねブロックBb1~Bb4の直下の施工ブロックBを候補ブロック群Qに含めてもよい。本実施形態における候補ブロック群Qは、五つの打重ねブロックBbと八つの拡張ブロックBcとで構成される。なお、図5に示す拡張ブロックBcの配置はあくまで例示であり、他の配置にすることもできる。打重ねブロックBbおよび拡張ブロックBcを区別せずに候補ブロック群Qを構成する施工ブロックBaを説明する場合に「候補ブロックP」と呼ぶ場合がある。つまり、本実施形態における候補ブロック群Qは、十三個の候補ブロックPで構成される。 As shown in FIG. 4, the candidate block group Q in this embodiment is composed of an overlapping block Bb adjacent to the block of interest Ba, and an extended block Bc located around the lower layer of the overlapping block Bb. In this embodiment, the target block Ba itself and the construction blocks B directly below the target block Ba and the stacked blocks Bb1 to Bb4 are not included in the candidate block group Q. This is because it is assumed that these construction blocks B have already been driven due to the driving constraints described below. Note that the construction blocks B directly below the stacked blocks Bb1 to Bb4 may be included in the candidate block group Q. The candidate block group Q in this embodiment is composed of five overlapping blocks Bb and eight extended blocks Bc. Note that the arrangement of the expansion blocks Bc shown in FIG. 5 is merely an example, and other arrangements are also possible. When describing the construction blocks Ba constituting the candidate block group Q, they may be referred to as "candidate blocks P" without distinguishing between the stacked blocks Bb and the expanded blocks Bc. That is, the candidate block group Q in this embodiment is composed of thirteen candidate blocks P.
着目ブロックBaに対する打重ねブロックBb(図4では5ブロック)だけを候補ブロックPとした場合、着目ブロックBaの最短打重ねを志向することになる。しかしながら、そのような候補ブロックPの設定方法では全ての施工ブロックBの打込み順序が確定したときに、最大打重ね時間が必ずしも短くならない場合がある。そのため、本実施形態では図4に示すように、着目ブロックBaの打重ねブロックBbが早期に打込み完了となるように、すなわち打重ねブロックBbの打込み制約条件がより早期に整うように、着目ブロックBaの打重ねに直接関係のない施工ブロックB(拡張ブロックBc)を追加することで候補ブロックPを拡張している(「5+8」で全13ブロック)。この追加された八つの拡張ブロックBcは、着目ブロックBaの最短打重ねに関してはノイズとなるが、最大打重ね時間の短縮には有効である。 If only the overlapping blocks Bb (5 blocks in FIG. 4) with respect to the block Ba of interest are set as candidate blocks P, the aim is to overlap the block Ba of interest in the shortest possible time. However, in such a method of setting candidate blocks P, when the driving order of all construction blocks B is determined, the maximum stacking time may not necessarily be shortened. Therefore, in this embodiment, as shown in FIG. 4, driving of the overlapping block Bb of the focused block Ba is completed early, that is, so that the driving constraint conditions of the overlapping block Bb are satisfied earlier. Candidate block P is expanded by adding construction block B (expansion block Bc) that is not directly related to the overlapping of Ba (total 13 blocks (5+8)). These eight additional expansion blocks Bc become noise when it comes to the shortest stacking time of the target block Ba, but are effective in shortening the maximum stacking time.
群内順序決定部44は、候補ブロック群Q内の打込み順序を決定する。群内順序決定部44による順序の決定方法は特に限定されず、種々の方法を用いることができる。群内順序決定部44は、決められた規則に従って施工ブロックBの打込み順序を決定してもよいし、ランダムで施工ブロックBの打込み順序を決定してもよい。また、群内順序決定部44は、施工ブロックBの打込みが予め設定した制約条件に適合しているか否かを判定する機能を有する。打込みの制約条件は、任意のものであってよく、その内容は限定されるものではない。群内順序決定部44は、例えば、施工ブロックBの打込みが実現可能であるか否かを判定する。
The intra-group
打込み順序作成部42は、例えば以下のようにして全ての施工ブロックBの打込みが完了するまで、打込み順序を探索する。
(1) 打込み完了時刻により着目ブロックBaを選択する。
(2) 打込みが完了していない候補ブロックPの中から1箇所選択して、打込み制約条件に適合しているかどうかを判定する。打込み可能であれば選択された施工ブロックBを打込み済とする。
(3) 工程(2)の操作を順次、候補ブロック群Q内の全ての候補ブロックPの打込みが完了するまで繰り返す。
(4) 全ての候補ブロックPの打込みが完了した場合、次の着目ブロックBaを探索して、工程(2),(3)の処理を行う。つまり、候補ブロック群Qの打込みが終わるまで次の着目ブロックBaの処理には移行しない。
ここで、本実施形態では打込み制約条件として、高さ方向に二段突出した形では打込みができないものとした。例えば、図3における着目ブロックBaの直上の打重ねブロックBb5を打込むためには、図3の着目ブロックBaとその前後左右の打重ねブロックBb1~Bb4が打込み済みでなければならない。
The driving
(1) Select the target block Ba based on the driving completion time.
(2) Select one location from among the candidate blocks P for which implantation has not been completed, and determine whether or not the implantation constraints are met. If it is possible to drive, the selected construction block B is considered to have been driven.
(3) Repeat the operation in step (2) in sequence until all candidate blocks P in the candidate block group Q are completed.
(4) When the implantation of all candidate blocks P is completed, search for the next target block Ba and perform the processes of steps (2) and (3). In other words, the process does not proceed to the next target block Ba until the candidate block group Q has been implanted.
Here, in this embodiment, as a driving constraint condition, it is assumed that driving cannot be performed in a shape that protrudes in two steps in the height direction. For example, in order to drive the stacked block Bb5 directly above the block of interest Ba in FIG. 3, the block of interest Ba in FIG. 3 and the stacked blocks Bb1 to Bb4 on its front, rear, left and right sides must have been driven.
図1に示す順序評価部45は、打込み順序作成部42によって作成された打込み順序を評価する。打込み順序を評価する方法は、特に限定されずに種々の方法を用いることができる。順序評価部45は、例えば打重ね時間によって打込み順序を評価する。本実施形態では、打重ね時間の評価を簡潔に表現するために、相互結合型ニューラルネットワークの計算手法を応用する。
The
相互結合型ニューラルネットワークの計算手法を用いた打重ね時間の評価について説明する。まず、想定打込み範囲をいくつかの施工ブロック(以下の説明では、単に「ブロック」と表記する場合がある)に区分する。施工ブロックの打込み順序は、幾何学的な制約がなければどこから始めてもどのような順序を辿ってもよい。施工ブロックを「○(白抜きの円)」で表し、経路を線で表す場合、例えば施工ブロックが3箇所の例では、図5に示すような3つのユニットで構成される相互結合型ニューラルネットワークとなる。図5は、相互結合型ニューラルネットワークのイメージ図である。経路の候補は2つを組合わせした全ての施工ブロック間で可能であり、両方向の向きが可能である。ただし、各施工ブロックは一度しか通過せず、一度に1つの施工ブロックにしか打ち込まれない(打込み口が1箇所の場合)。 We will explain the evaluation of overlapping time using a mutually coupled neural network calculation method. First, the expected driving range is divided into several construction blocks (in the following explanation, they may be simply referred to as "blocks"). As long as there are no geometrical restrictions, the driving blocks may be driven in any order starting from any point. If construction blocks are represented by "○ (white circles)" and routes are represented by lines, for example, in an example where there are three construction blocks, an interconnected neural network consisting of three units as shown in Figure 5 will be used. becomes. FIG. 5 is an image diagram of a mutually coupled neural network. Route candidates are possible between all construction blocks that are a combination of two, and can be oriented in both directions. However, each construction block passes through only once, and it is driven into only one construction block at a time (if there is only one driving hole).
図6に示すように、相互結合型ニューラルネットワークをブロックと順序というマトリクス状の階層型ネットワークで表現するとホップフィールド型ニューラルネットワークとなる。図6は、ホップフィールド型ニューラルネットワークのイメージ図である。このマトリクス状のネットワークにおいても各施工ブロックが相互に結合していることになり、情報の流れはもとの相互結合型ニューラルネットワークと同じとみなすことができる。図6中の「○(白抜きの円)」はユニットと呼ばれる情報処理部を表す。ユニットは、ニューラルネットワークで使用される用語であり、他のユニットの出力を受けて何らかの値(例えば、「-1~+1」)を返す(出力する)関数の名称として一般的に使用される。各打込み順序において施工ブロックに対応するユニットは全て同じ数(3ブロック)だけある。全ての施工ブロックを打込むので、縦も横も同数の3ユニットになる(imax=jmax)。図において各打込み順序列を層と呼ぶ。このネットワークでは、隣り合う層のユニットは結合しているが同じ層内のユニットや連続しない層のユニットは結合していない。本実施形態においては、このようなマトリクスを用いて打重ね時間を表現する場合について説明する。 As shown in FIG. 6, when a mutually coupled neural network is expressed as a matrix-like hierarchical network of blocks and orders, it becomes a Hopfield neural network. FIG. 6 is an image diagram of a Hopfield neural network. In this matrix-like network, the construction blocks are also interconnected, and the flow of information can be considered to be the same as the original interconnected neural network. “○ (white circle)” in FIG. 6 represents an information processing section called a unit. Unit is a term used in neural networks, and is generally used as the name of a function that receives the output of another unit and returns (outputs) a certain value (for example, "-1 to +1"). In each driving order, there are the same number of units (3 blocks) corresponding to the construction blocks. Since all construction blocks are driven, there will be 3 units, the same number both vertically and horizontally (imax=jmax). In the figure, each implant sequence is called a layer. In this network, units in adjacent layers are connected, but units in the same layer or units in non-consecutive layers are not connected. In this embodiment, a case will be described in which the overlapping time is expressed using such a matrix.
以下では、定式化について説明する。図7に示すように、縦にブロック番号「i」、横に打込み順序「j」をとり、上述の通りマトリクスを作成する。このマトリクスは、どの層も同じユニット数で(縦方向にブロック数だけユニットを用意し、また横方向にブロック数だけ層を用意する)、情報の流れが左から右に限定された階層型ネットワークである。 The formulation will be explained below. As shown in FIG. 7, a matrix is created as described above, with the block number "i" listed vertically and the implantation order "j" listed horizontally. This matrix is a hierarchical network in which every layer has the same number of units (units are prepared for the number of blocks in the vertical direction, and layers are prepared for the number of blocks in the horizontal direction), and the flow of information is limited from left to right. It is.
ユニットの出力は、対応するブロック番号のブロックが打ち込まれているとき「1(xij = 1)」を出力し、打ち込まれていないとき「0(xij = 0)」を出力する。ユニット間の重みは、出力側ユニット「i(j-1)」に相当するブロックの打込みに要する時間とした(wi(j-1)→i(j) = wi( j-1))。
前層の各ユニットの出力に対して各ユニットと着目ユニットとの経路の重みを乗じたものの総和を打込み開始から順次計算する。総和をとる層の深さによって各施工ブロックの打込み開始時刻と打込み完了時刻は、式(1)および式(2)で表される。
The output of the unit is ``1 (x ij = 1)'' when a block with the corresponding block number is written, and ``0 (x ij = 0)'' when it is not written. The weight between units is determined by the time required to insert the block corresponding to output unit "i(j-1)" (w i(j-1)→i(j) = w i( j-1) ) .
The sum of the outputs of each unit in the previous layer multiplied by the weight of the path between each unit and the unit of interest is calculated sequentially from the start of implantation. The driving start time and driving completion time of each construction block are expressed by equations (1) and (2) according to the depth of the layer to be summed.
打ち重ね時間間隔は、着目ブロックの打込み完了時刻と打重ねブロックの打込み完了時刻との差として式(3)で評価される。ここで、図8に示すように、ブロックの幾何学的な連結性から、着目ブロックに対して打重ねの関係になる施工ブロック(打重ねブロック)とならない施工ブロックとを判別する指標として式(4)を導入した。一つの着目ブロックに対する打重ねブロックの数は、最大で5ブロックである。ここで、対象ブロックとは、着目ブロックと対になり、打重ね時間を計算する相手先の施工ブロックである。 The overlapping time interval is evaluated using equation (3) as the difference between the driving completion time of the block of interest and the driving completion time of the overlapping block. Here, as shown in FIG. 8, from the geometric connectivity of the blocks, we use the formula ( 4) was introduced. The maximum number of overlapping blocks for one block of interest is 5 blocks. Here, the target block is a partner construction block that is paired with the block of interest and for which the overlap time is to be calculated.
<本発明の実施形態に係る打込み計画の作成方法について>
図9を参照して(適宜、図1ないし図8を参照)、実施形態に係る打込み計画作成装置100を用いた打込み計画の作成方法について説明する。図9は、実施形態に係る打込み計画の作成方法を示すフローチャートの例示である。打込み計画は、例えば、施工対象物を分割した施工ブロックBにコンクリートを打ち込む順番を設定した施工ブロックB単位での打込み順序である。
<About the method for creating a driving plan according to the embodiment of the present invention>
A method for creating a driving plan using the driving
最初に、作成者は、条件設定部41を介して、施工条件やコンクリート構造物Aを抽象化した施工モデルCなどを打込み計画作成装置100に設定する(ステップS101)。なお、条件設定部41は、作成者の入力操作によらずに、または作成者が入力した他の情報からこれらの情報を算出してもよい。
First, the creator sets construction conditions, a construction model C that is an abstraction of the concrete structure A, etc. in the pouring
作成者は、例えば、施工ブロックB(k,l,m)を抽象化した仮想ブロックD(k,l,m)を三次元の仮想空間上に配置する。具体的には、施工ブロックB(k,l,m)の位置を三次元の仮想空間に設定される直交座標系の座標値(X,Y,Z)として仮想ブロックD(k,l,m)に設定する。ここで、「X」は、例えば施工ブロックB(k,l,m)の横方向の位置に対応しており、「Y」は、例えば施工ブロックB(k,l,m)の奥行き方向の位置に対応しており、「Z」は、例えば施工ブロックB(k,l,m)の高さ方向の位置に対応している。これにより、施工ブロックB(k,l,m)の相対的な位置関係が、仮想ブロックD(k,l,m)に設定された座標値によって三次元の仮想空間上で再現される。以下の説明で施工ブロックBといった場合には、抽象化した仮想ブロックDのことである。 For example, the creator places a virtual block D (k, l, m), which is an abstraction of the construction block B (k, l, m), in a three-dimensional virtual space. Specifically, the position of the construction block B (k, l, m) is set as the coordinate value (X, Y, Z) of the orthogonal coordinate system set in the three-dimensional virtual space, and the virtual block D (k, l, m ). Here, "X" corresponds to, for example, the horizontal position of construction block B (k, l, m), and "Y" corresponds to, for example, the depth direction of construction block B (k, l, m). "Z" corresponds to the position of the construction block B (k, l, m) in the height direction, for example. Thereby, the relative positional relationship of the construction block B (k, l, m) is reproduced on the three-dimensional virtual space using the coordinate values set for the virtual block D (k, l, m). In the following explanation, construction block B refers to abstracted virtual block D.
また、作成者は、例えば、一つの施工ブロックB(k,l,m)を作成するのに要する時間(つまり、一つの施工ブロックB(k,l,m)の打込みに要する時間)を設定する。この時間は、例えば、施工ブロックB(k,l,m)のサイズやポンプ性能から算出されてもよい。
また、作成者は、例えば、コンクリートを打ち込む打込み口の数(ポンプ車を用いてコンクリートの打込みを行う場合ではポンプ車の台数に相当)を設定する。
また、作成者は、例えば、打込みを開始する一番目の施工ブロックB(開始ブロック)を設定する。作成者は、例えば地面に接した施工ブロックB(つまり空中への打込みにならない施工ブロックB)の中から任意に一つを開始ブロックとして設定する。なお、打込み口の数が複数である場合、その数に応じた開始ブロックを設定する。
In addition, the creator can set, for example, the time required to create one construction block B (k, l, m) (that is, the time required to drive one construction block B (k, l, m)). do. This time may be calculated, for example, from the size of the construction block B (k, l, m) and pump performance.
The creator also sets, for example, the number of pouring holes into which concrete is poured (corresponding to the number of pump trucks in the case of pouring concrete using pump trucks).
Further, the creator sets, for example, the first construction block B (starting block) at which driving starts. For example, the creator arbitrarily sets one of the construction blocks B that are in contact with the ground (that is, the construction blocks B that are not driven into the air) as the start block. Note that if there is a plurality of slots, a start block is set according to the number of slots.
次に、作成者は、打込み計画作成装置100に対して打込み順序の計算の開始を指示する。これにより、打込み計画作成装置100は、ステップS102以降の処理を実行する。なお、打込み計画作成装置100は、ステップS101での設定が済み次第に打込み順序の計算を開始してもよい。
Next, the creator instructs the driving
打込み順序作成部42は、ステップS101で設定した一番目の施工ブロックB(開始ブロック)の打込みを実行する(ステップS102)。具体的には、打込み順序作成部42は、一番目の施工ブロックB(開始ブロック)に対して例えばコンクリートを打ち込む順番が一番であることを示す情報を設定するなどして、開始ブロックを打込み済にする。これにより、当該施工ブロックB(開始ブロック)の打込みが完了する。
The driving
次に、ブロック群設定部43は、着目ブロックBa(図4参照)の探索を行う(ステップS103)。着目ブロックBaは、打込みが完了している施工ブロックB(打込み済みブロック)の内、打重ねが未完了であって打込み完了時刻が最も早い施工ブロックBである。打重ねが未完了とは、打込みが完了している施工ブロックBに隣接する施工ブロックBの少なくとも何れか一つの打込みが完了していない状態である。つまり、施工ブロックBに隣接する全ての施工ブロックBの打込みが完了した場合に、当該施工ブロックBの打重ねが完了した状態となる。ブロック群設定部43は、前述した条件に該当する施工ブロックBを着目ブロックBaとして選択する。
Next, the block
選択できる着目ブロックBaがあって一つの施工ブロックBを着目ブロックBaとして選択した場合(ステップS104で“Yes”)、群内順序決定部44は、ステップS105~ステップS110の処理を繰り返し行い、候補ブロック群Q(図4参照)に含まれる施工ブロックB(つまり、候補ブロックP(図4参照))の打込み順序を決定する。なお、図9に示す候補ブロックPの打込み順序を決定する処理はあくまで一例であって、候補ブロックPの打込み順序を決定する処理はここで説明するものに限定されない。
When there is a target block Ba that can be selected and one construction block B is selected as the target block Ba (“Yes” in step S104), the intra-group
群内順序決定部44は、次に打ち込む候補ブロックP(図4参照)の探索を行う(ステップS105)。群内順序決定部44は、未打込みの候補ブロックPの中から1箇所を選択する。候補ブロックPを選択する方法は特に限定されない。選択できる候補ブロックPがあった場合(ステップS106で“Yes”)、群内順序決定部44は、選択した候補ブロックPが打込み制約条件に適合するか否かを判定する(ステップS107)。
The intra-group
打込み制約条件に適合しない場合(ステップS107で“No”)、群内順序決定部44は、他の候補ブロックPの探索を行い(ステップS109)、探索した他の候補ブロックPを新たに選択する(ステップS105)。一方、打込み制約条件に適合する場合(ステップS107で“Yes”)、群内順序決定部44は、コンクリートを打ち込む順番を示す情報を設定するなどして、選択した候補ブロックPを打込み済みにする(ステップS108)。その後、群内順序決定部44は、次の候補ブロックPの探索を行い(ステップS110)、探索した次の候補ブロックPを新たに選択する(ステップS105)。
If the driving constraint conditions are not met (“No” in step S107), the intra-group
候補ブロック群Q内に選択できる候補ブロックPがない(なくなったときも含む)場合(ステップS106で“No”)、ブロック群設定部43は、次の着目ブロックBaを選択し、新たな着目ブロックBaでの処理に移行する(ステップS111)。具体的には、ブロック群設定部43が新たな着目ブロックBa(図4参照)の探索を行う(ステップS103)。そして、群内順序決定部44が、ステップS105~ステップS110の処理を繰り返し行い、新たに選択した着目ブロックBaに基づく候補ブロック群Q(図4参照)に含まれる候補ブロックPの打込み順序を決定する。
If there is no candidate block P that can be selected in the candidate block group Q (including when there is no candidate block P) (“No” in step S106), the block
選択できる着目ブロックBaがない(なくなったときも含む)場合(ステップS104で“No”)、全ての施工ブロックBの打込み順序が決定されているので、順序評価部45は、作成された打込み順序における最大打重ね時間を計算する(ステップS112)。作成者は、計算された最大打重ね時間に基づいて、打込み順序を再度作成するか判断する。作成者は、例えば最大打重ね時間が許容する範囲に収まっている場合には、作成した打込み順序で施工を行い、また、許容する範囲に収まっていない場合には、施工条件などを変更して打込み順序を再度作成する。なお、最大打重ね時間の許容範囲は、コールドジョイントが発生しない時間であり、例えば、公益社団法人土木学会が発行する「コンクリート標準示方書」に記載される許容打重ね時間間隔を超えない時間である。
If there is no target block Ba that can be selected (including when there is no target block Ba) (“No” in step S104), the driving order of all the construction blocks B has been determined, so the
以上のように、実施形態に係る打込み計画作成装置100は、図4に示すように、着目ブロックBaの打重ねブロックBbが早期に打込み完了となるように候補ブロック群Qを設定する。すなわち、打重ねブロックBbの打込み制約条件がより早期に整うように、着目ブロックBaの打重ねに直接関係のない施工ブロックB(拡張ブロックBc)についても候補ブロック群Qに含めている。そのため、着目ブロックBaに対する打重ねブロックBb(図4では5ブロック)だけを候補ブロックPとした場合と比べて、最大打重ね時間の短縮に有効である。その結果、コンクリートの好適な打込み計画を作成することができる。
As described above, as shown in FIG. 4, the driving
図10および図11を参照して、実施形態に係る打込み計画作成装置100の効果について補足する。発明者は、候補ブロックPを拡張しない場合(候補ブロック群Qが打重ねブロックBbのみで構成される場合)と候補ブロックPを拡張した場合(候補ブロック群Qが打重ねブロックBbおよび拡張ブロックBcで構成される場合)とでそれぞれシミュレーションを実行し、その結果を比較検討した。シミュレーションでは、壁スラブで構成される構造物(図10参照)を3層で打込む場合を想定した。
With reference to FIGS. 10 and 11, the effects of the driving
図10は、シミュレーションで用いた構造物の概略図であり、図10(a)は、1層目の構造を示し、図10(b)は、2層目の構造を示し、図10(c)は、3層目の構造を示している。図10中の四角形は各施工ブロックBであり、四角形内の数字はブロック番号を示している。空中には打込みを行えないので、図10(a)に示す1層目の21ブロックが当該シミュレーショにおける開始ブロックの候補となる。1層目と2層目には、打込みを行わない4つの領域が存在する。 FIG. 10 is a schematic diagram of the structure used in the simulation. FIG. 10(a) shows the first layer structure, FIG. 10(b) shows the second layer structure, and FIG. 10(c) shows the structure of the second layer. ) indicates the third layer structure. The squares in FIG. 10 are each construction block B, and the numbers inside the squares indicate block numbers. Since implantation cannot be performed in the air, the 21 blocks of the first layer shown in FIG. 10(a) are candidates for the starting block in the simulation. There are four regions in the first and second layers where implantation is not performed.
図11を参照して、シミュレーション結果について説明する。図11は、シミュレーション結果を説明するための図であり、図11(a)は、候補ブロックPを拡張しない場合のシミュレーション結果を示し、図11(b)は、候補ブロックPを拡張した場合のシミュレーション結果を示している。 The simulation results will be explained with reference to FIG. 11. FIG. 11 is a diagram for explaining the simulation results. FIG. 11(a) shows the simulation result when the candidate block P is not expanded, and FIG. 11(b) shows the simulation result when the candidate block P is expanded. Simulation results are shown.
図11(a),(b)は、ともに1層目の構造に対応しており、四角形内の数字は当該施工ブロックBから打込みを開始した場合の最大打重ね時間を示している。例えば、図11(a)の候補ブロックPを拡張しない場合では、ブロック番号「1」の施工ブロックBから打込みを開始した場合に最大打重ね時間は「120分」であり、ブロック番号「2」の施工ブロックBから打込みを開始した場合に最大打重ね時間は「130分」である。ここで、図11(a)に示す候補ブロックPを拡張しない場合において、各施工ブロックBから打込みを開始したときの最大打重ね時間の平均は「153.3分」であった。一方、図11(b)に示す候補ブロックPを拡張した場合において、各施工ブロックBから打込みを開始したときの最大打重ね時間の平均は「148.1分」であった。 11(a) and 11(b) both correspond to the structure of the first layer, and the numbers inside the rectangles indicate the maximum overlapping time when driving starts from the construction block B concerned. For example, in the case where candidate block P in FIG. 11(a) is not expanded, the maximum stacking time is "120 minutes" when starting from construction block B with block number "1", and the maximum stacking time is "120 minutes"; When starting pouring from construction block B, the maximum overlapping time is "130 minutes." Here, in the case where the candidate block P shown in FIG. 11(a) is not expanded, the average maximum overlapping time when starting driving from each construction block B was "153.3 minutes". On the other hand, when the candidate blocks P shown in FIG. 11(b) are expanded, the average maximum overlapping time when starting driving from each construction block B was "148.1 minutes".
図11(a),(b)を比較検証した結果、図11(b)に示す候補ブロックPを拡張した場合には必ずしも最大打重ね時間が短くなるわけではないが、各施工ブロックBから打込みを開始したときの最大打重ね時間の平均値は短く抑えられている。また、図11(b)に示す候補ブロックPを拡張した場合には、中央付近から打ち始めたときに最大打重ね時間が減少する傾向がある(つまり、最大打重ね時間のピークを抑える傾向がある)。例えば、ブロック番号「11」の施工ブロックBから打込みを開始した場合では、図11(a)に示す候補ブロックPを拡張しないときの最大打重ね時間が「220分」であったのに対して、図11(b)に示す候補ブロックPを拡張したときの最大打重ね時間が「200分」であった。 As a result of comparing and verifying Figs. 11(a) and (b), we found that if the candidate block P shown in Fig. 11(b) is expanded, the maximum stacking time will not necessarily be shortened, but The average value of the maximum overlapping time when starting the process is kept short. Furthermore, when the candidate block P shown in FIG. 11(b) is expanded, there is a tendency for the maximum overlapping time to decrease when starting from near the center (in other words, there is a tendency to suppress the peak of the maximum overlapping time). be). For example, when starting pouring from construction block B with block number "11", the maximum pouring time is "220 minutes" when candidate block P shown in FIG. 11(a) is not expanded. , the maximum overlapping time when expanding the candidate block P shown in FIG. 11(b) was "200 minutes".
以上、本発明の実施形態について説明したが、本発明はこれに限定されるものではなく、特許請求の範囲の趣旨を変えない範囲で実施することができる。 Although the embodiments of the present invention have been described above, the present invention is not limited thereto, and can be implemented without changing the spirit of the claims.
30 記憶部
31 打込み条件情報
40 制御部
41 条件設定部
42 打込み順序作成部
43 ブロック群設定部
44 群内順序決定部
45 順序評価部
100 打込み計画作成装置
B 施工ブロック
Ba 着目ブロック
Bb 打重ねブロック
Bc 拡張ブロック
P 候補ブロック
Q 候補ブロック群
30
Claims (4)
前記打込み計画は、施工対象物を分割した施工ブロックにコンクリートを打ち込む順番を設定した施工ブロック単位での打込み順序であり、
連続して打込みを行う施工ブロックのまとまりである候補ブロック群を前記施工対象物に対して順番に設定するブロック群設定部と、
前記候補ブロック群内の打込み順序を決定する群内順序決定部と、を備え、
前記候補ブロック群は、当該候補ブロック群の基準となる前記施工ブロックである着目ブロックに隣接する打重ねブロック、および前記打重ねブロックの周辺に位置する拡張ブロックで構成され、
前記ブロック群設定部は、一つ前の前記候補ブロック群内の打込み順序が決定された時点で、打込み済みの前記施工ブロックの中から、隣接する前記施工ブロックに対する打込みが未完了かつ打込み完了時刻が最も早い打込み済みの施工ブロックを選択し、選択された施工ブロックを新たな前記着目ブロックとして前記候補ブロック群を新たに設定する、
ことを特徴とする打込み計画作成装置。 A pouring plan creation device for creating a pouring plan in concrete pouring,
The pouring plan is a pouring order for each construction block that sets the order in which concrete is poured into construction blocks into which the construction target is divided;
a block group setting unit that sequentially sets a candidate block group, which is a group of construction blocks to be successively driven, for the construction target;
an intra-group order determining unit that determines the implantation order within the candidate block group;
The candidate block group is composed of stacked blocks adjacent to the block of interest, which is the construction block serving as a reference for the candidate block group, and expansion blocks located around the stacked blocks,
The block group setting unit determines, at the time when the driving order in the previous candidate block group is determined, that the driving for the adjacent construction block among the already driven construction blocks is incomplete and the driving completion time. selects the earliest driven construction block, and newly sets the candidate block group with the selected construction block as the new block of interest;
A driving plan creation device characterized by the following.
ことを特徴とする請求項1に記載の打込み計画作成装置。 The expansion block is the construction block one step below the block of interest, and is located outside the stacked block.
2. The implantation plan creation device according to claim 1.
前記打込み計画は、施工対象物を分割した施工ブロックにコンクリートを打ち込む順番を設定した施工ブロック単位での打込み順序であり、
前記コンピュータは、
連続して打込みを行う施工ブロックのまとまりである候補ブロック群を前記施工対象物に対して順番に設定するブロック群設定ステップと、
前記候補ブロック群内の打込み順序を決定する群内順序決定ステップと、を実行し、
前記ブロック群設定ステップと前記群内順序決定ステップとを繰り返し実行することで、前記施工対象物を構成する前記施工ブロックの打込み順序を決定するものであり、
前記候補ブロック群は、当該候補ブロック群の基準となる前記施工ブロックである着目ブロックに隣接する打重ねブロック、および前記打重ねブロックの周辺に位置する拡張ブロックで構成され、
前記ブロック群設定ステップでは、一つ前の前記候補ブロック群内の打込み順序が決定された時点で、打込み済みの前記施工ブロックの中から、隣接する前記施工ブロックに対する打込みが未完了かつ打込み完了時刻が最も早い打込み済みの施工ブロックを選択し、選択された施工ブロックを新たな前記着目ブロックとして前記候補ブロック群を新たに設定する、
ことを特徴とする打込み計画作成方法。 A pouring plan creation method for creating a pouring plan for concrete pouring by a computer ,
The pouring plan is a pouring order for each construction block that sets the order in which concrete is poured into construction blocks into which the construction target is divided;
The computer includes:
a block group setting step of sequentially setting a candidate block group, which is a group of construction blocks to be successively driven, for the construction target;
performing an intra-group order determining step of determining an implantation order within the candidate block group;
By repeatedly performing the block group setting step and the intra-group order determining step, the driving order of the construction blocks constituting the construction target is determined,
The candidate block group is composed of stacked blocks adjacent to the block of interest, which is the construction block serving as a reference for the candidate block group, and expansion blocks located around the stacked blocks,
In the block group setting step, when the driving order in the previous candidate block group is determined, it is determined that among the already driven construction blocks, the driving to the adjacent construction block is not completed and the driving completion time is determined. selects the earliest driven construction block, and newly sets the candidate block group with the selected construction block as the new block of interest;
A method for creating a driving plan, which is characterized by the following.
ことを特徴とする請求項3に記載の打込み計画作成方法。 The expansion block is the construction block one step below the block of interest, and is located outside the stacked block.
4. The method for creating a driving plan according to claim 3.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020096420A JP7348136B2 (en) | 2020-06-02 | 2020-06-02 | Driving plan creation device and driving plan creation method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020096420A JP7348136B2 (en) | 2020-06-02 | 2020-06-02 | Driving plan creation device and driving plan creation method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2021188419A JP2021188419A (en) | 2021-12-13 |
| JP7348136B2 true JP7348136B2 (en) | 2023-09-20 |
Family
ID=78849076
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020096420A Active JP7348136B2 (en) | 2020-06-02 | 2020-06-02 | Driving plan creation device and driving plan creation method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7348136B2 (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7393461B2 (en) * | 2022-03-29 | 2023-12-06 | 株式会社奥村組 | Concrete placement management device, concrete placement management method, and concrete placement management program |
| JP7312292B1 (en) | 2022-03-29 | 2023-07-20 | 株式会社奥村組 | Concrete placement management device, concrete placement management method, and concrete placement management program |
| JP7410999B2 (en) * | 2022-03-29 | 2024-01-10 | 株式会社奥村組 | Concrete placement management device, concrete placement management method, and concrete placement management program |
| JP7291265B1 (en) | 2022-03-29 | 2023-06-14 | 株式会社奥村組 | Concrete placement management device, concrete placement management method, and concrete placement management program |
| JP7823999B2 (en) * | 2022-04-14 | 2026-03-04 | 大成建設株式会社 | Concrete pouring planning method and pouring planning support device |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003160926A (en) | 2001-11-26 | 2003-06-06 | Maeda Corp | Lift scheduling method for placing block |
| JP2011202383A (en) | 2010-03-25 | 2011-10-13 | Toda Constr Co Ltd | Concrete placing management system |
| JP2013209801A (en) | 2012-03-30 | 2013-10-10 | Kajima Corp | System for supporting concrete placing and program |
| JP2017036607A (en) | 2015-08-11 | 2017-02-16 | 清水建設株式会社 | Concrete overlay time management device and concrete overlay time management method |
-
2020
- 2020-06-02 JP JP2020096420A patent/JP7348136B2/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2003160926A (en) | 2001-11-26 | 2003-06-06 | Maeda Corp | Lift scheduling method for placing block |
| JP2011202383A (en) | 2010-03-25 | 2011-10-13 | Toda Constr Co Ltd | Concrete placing management system |
| JP2013209801A (en) | 2012-03-30 | 2013-10-10 | Kajima Corp | System for supporting concrete placing and program |
| JP2017036607A (en) | 2015-08-11 | 2017-02-16 | 清水建設株式会社 | Concrete overlay time management device and concrete overlay time management method |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2021188419A (en) | 2021-12-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7348136B2 (en) | Driving plan creation device and driving plan creation method | |
| JP7178330B2 (en) | Placement plan creation device and placement plan creation method | |
| US11243510B2 (en) | Computer aided generative design with tool size control to facilitate 2.5-axis subtractive manufacturing processes | |
| US10635088B1 (en) | Hollow topology generation with lattices for computer aided design and manufacturing | |
| CN116628828B (en) | A method, medium and system for determining demolition points of large buildings | |
| CA2729240A1 (en) | System and method for designing a building | |
| EP4154156B1 (en) | Computer aided generative design with layer boundary determination to facilitate 2.5-axis subtractive manufacturing processes | |
| CN119990498A (en) | Workshop inspection task allocation method, control system and medium based on ant colony algorithm | |
| CN119067261A (en) | Construction site layout optimization method, system, readable storage medium and electronic device | |
| Riggs | Simulation of construction operations | |
| RU2689803C1 (en) | Method for automatized construction of three-dimensional model of heterogeneous structure of composite material with fibers | |
| CN111475878B (en) | Method and device for generating ground depot anti-collision plate based on BIM technology and terminal | |
| van der Blom et al. | A super-structure based optimisation approach for building spatial designs | |
| JP2025063778A (en) | Driving plan creation device, driving plan creation program, and driving plan creation method | |
| CN117828718B (en) | Bridge layout and layout optimization method based on BIM | |
| CN119918123A (en) | Method, device, electronic equipment, medium and program product for calculating lateral displacement of deep foundation pit | |
| US7339584B1 (en) | Method of generating a surface mesh | |
| Huang | Algorithms for mixed continuous-discrete variable problems in structural optimization | |
| CN120068548B (en) | Model construction method, device and equipment for steel tube concrete structure considering random corrosion | |
| CN111310261A (en) | Method and device for generating interior wall facing brick model, computer equipment and storage medium | |
| CN120354480B (en) | Quick establishment method of earthquake damage building dismantling scheme based on genetic algorithm and reinforcement learning | |
| De Vries et al. | Construction analysis during the design process | |
| Bauke et al. | Construction Analysis during the Design Process | |
| CN119398684A (en) | Visual verification method, equipment and storage medium for post-cast strip reinforcement | |
| CN120882942A (en) | Information processing device, information processing method and program |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20220809 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20230529 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20230704 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20230822 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20230905 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20230907 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7348136 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |