Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP7386824B2 - Girder replacement method and pier removal method - Google Patents
[go: Go Back, main page]

JP7386824B2 - Girder replacement method and pier removal method - Google Patents

Girder replacement method and pier removal method Download PDF

Info

Publication number
JP7386824B2
JP7386824B2 JP2021024523A JP2021024523A JP7386824B2 JP 7386824 B2 JP7386824 B2 JP 7386824B2 JP 2021024523 A JP2021024523 A JP 2021024523A JP 2021024523 A JP2021024523 A JP 2021024523A JP 7386824 B2 JP7386824 B2 JP 7386824B2
Authority
JP
Japan
Prior art keywords
girder
existing
pier
newly installed
sleeper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021024523A
Other languages
Japanese (ja)
Other versions
JP2022126444A (en
Inventor
雄介 井出
新一 田島
宏延 林
弘之 伊藤
政幸 神田
進 中島
太亮 佐名川
達貴 藤本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Railway Technical Research Institute
Original Assignee
Kajima Corp
Railway Technical Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp, Railway Technical Research Institute filed Critical Kajima Corp
Priority to JP2021024523A priority Critical patent/JP7386824B2/en
Publication of JP2022126444A publication Critical patent/JP2022126444A/en
Application granted granted Critical
Publication of JP7386824B2 publication Critical patent/JP7386824B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30Flood prevention; Flood or storm water management, e.g. using flood barriers

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本開示は、河川横断橋の桁架け替え方法及び橋脚撤去方法に関する。 The present disclosure relates to a girder replacement method and a bridge pier removal method for a river crossing bridge.

特許文献1には、河川橋梁の桁下空間拡大工法が記載されている。この河川橋梁は、河床面に設置された複数の橋脚と、複数の橋脚を跨ぐように設けられた橋桁と、橋桁の下方に設けられた堤防とを備える。この桁下空間拡大工法では、堤防及び河床面を掘削すると共に、橋脚の耐震補強を実施する。続いて、四角形に枠組みした鋼製の支柱であるベントの建て込みを行うと共に、橋脚の近傍に枠組足場を設置し、ベントの上部に鋼製サンドルと油圧ジャッキを設置する。 Patent Document 1 describes a construction method for expanding the space under the girder of a river bridge. This river bridge includes a plurality of piers installed on the riverbed surface, a bridge girder provided so as to straddle the plurality of piers, and an embankment provided below the bridge girder. This method of expanding the space under the girder involves excavating the embankment and river bed, as well as implementing seismic reinforcement of the bridge piers. Next, we will erect a vent, which is a rectangular steel column, and install a scaffolding near the piers, and install a steel sandal and a hydraulic jack on top of the vent.

鋼製サンドルは、井桁状に組み上げられた仮設の支台である。鋼製サンドルと油圧ジャッキを設置した後には、架線橋梁の交通遮断を行う。交通遮断を行った後には、油圧ジャッキを作動させて鋼製サンドルで盛り替えながら橋桁を徐々にジャッキアップする。すなわち、油圧ジャッキで橋桁をジャッキアップして橋桁が所定の高さまで上昇したときに、鋼製サンドルで受け替える。 The steel sandals are temporary supports constructed in the shape of a parallel grid. After installing the steel sandals and hydraulic jacks, the overhead line bridge will be closed to traffic. After blocking traffic, hydraulic jacks are activated and the bridge girders are gradually jacked up while being replaced with steel sandals. That is, when the bridge girder is jacked up with a hydraulic jack and the bridge girder rises to a predetermined height, it is replaced with a steel sandal.

橋脚の上に設置されていた既設の支承を切断及び撤去し、鋼製枠を橋脚の上部に固定した後に、鋼製枠の上部に新たな支承を設置する。続いて、油圧ジャッキを作動させて橋桁を再度ジャッキアップし、橋桁の荷重を仮設の鋼製サンドルから新たな支承に盛り替える。そして、架線橋梁の両端のそれぞれの道路舗装等を行った後に、交通遮断を解除して一連の工程が完了する。 After cutting and removing the existing supports installed on the piers and fixing the steel frame to the top of the pier, new supports will be installed on top of the steel frame. Next, the hydraulic jacks will be activated to jack up the bridge girder again, and the load on the bridge girder will be transferred from the temporary steel sandals to the new bearings. After paving the roads at both ends of the overhead wire bridge, the traffic blockade is lifted and the series of processes is completed.

特開2009-228300号公報JP2009-228300A

前述したようにジャッキアップによって橋桁を上げながら鋼製サンドルの受け替え、及び新設の支承への盛り替えを行う場合、ジャッキアップの量が扛上能力によって左右されるので、桁の架け替えの作業性の点において改善の余地がある。また、鋼製サンドルは仮設されるものであるため、橋桁を鋼製サンドルで仮受けするときにおける耐震性に懸念がある。 As mentioned above, when raising the bridge girder by jacking up and replacing the steel sandals and replacing it with a newly installed support, the amount of jacking depends on the lifting capacity, so the work of replacing the girder is difficult. There is room for improvement in terms of gender. Furthermore, since the steel sandals are temporarily installed, there are concerns about earthquake resistance when the bridge girder is temporarily supported with the steel sandals.

本開示は、架け替えの作業の作業性を向上させることができると共に、耐震性を向上させることができる桁架け替え方法及び橋脚撤去方法を提供することを目的とする。 An object of the present disclosure is to provide a girder replacement method and a pier removal method that can improve the workability of rebuilding work and improve seismic resistance.

本開示に係る桁架け替え方法は、既設の河川横断橋の桁架け替え方法であって、既設の橋脚の上に基礎の嵩上げを行う新設主桁台座を設置する工程と、新設主桁台座の上に新設桁を架設する工程と、新設桁に新設の枕木受桁を設置する工程と、既設の橋脚に取り付けられていた既設桁を撤去する工程と、を備える。 The girder replacement method according to the present disclosure is a girder replacement method for an existing river crossing bridge, and includes the steps of installing a new main girder pedestal for raising the foundation on the existing piers, and installing the new main girder pedestal. The method includes a process of erecting a new girder on top of the bridge, a process of installing a new sleeper support girder on the new girder, and a process of removing the existing girder attached to the existing bridge pier.

この桁架け替え方法では、既設の河川横断橋が架け替えられ、既設の河川横断橋を構成する既設の橋脚の上に新設主桁台座が設置される。新設主桁台座は、橋脚の上において基礎の嵩上げを行うためのものである。新設主桁台座の上には新設桁が架設され、新設桁には新設の枕木受桁が設置される。その後、既設の橋脚に取り付けられていた既設桁が撤去される。この桁架け替え方法では、ジャッキアップを不要とすることができるので、扛上能力によって作業性が左右されることを回避して作業性を向上させることができる。基礎の嵩上げを行う新設主桁台座は仮設のものではなく、この桁架け替え方法では、仮設構造物を用いずに作業を進めることができるので、作業途中においても高い耐震性を確保することができる。 In this girder replacement method, an existing river crossing bridge is replaced, and a new main girder pedestal is installed on the existing piers that make up the existing river crossing bridge. The new main girder pedestal is used to raise the foundation on top of the pier. A new girder will be erected on top of the new main girder pedestal, and a new sleeper support girder will be installed on the new girder. The existing girders attached to the existing piers will then be removed. This girder replacement method can eliminate the need for jacking up, so it is possible to improve workability by avoiding that the workability is affected by the lifting ability. The new main girder pedestal used to raise the foundation is not temporary, and with this girder replacement method, work can proceed without the use of temporary structures, making it possible to ensure high seismic resistance even during work. can.

前述した桁架け替え方法では、枕木受桁を設置する工程の前に、既設の橋脚から、既設のレール、及び既設の枕木を外す工程を備えてもよい。この場合、新設桁を設置して新設桁に枕木受桁を設置する前に、既設のレール及び既設の枕木を外すことができる。 The girder replacement method described above may include a step of removing an existing rail and an existing sleeper from an existing pier before the step of installing a sleeper support girder. In this case, before installing a new girder and installing a sleeper support girder on the new girder, the existing rail and the existing sleeper can be removed.

前述した桁架け替え方法は、枕木受桁を設置する工程の後に、枕木受桁に既設の枕木、及び既設のレールを設置する工程を備えてもよい。この場合、枕木受桁を設置した後に外した既設の枕木、及び既設のレールを再利用することができる。従って、既設の枕木、及び既設のレールを有効活用することができる。 The girder replacement method described above may include a step of installing an existing sleeper and an existing rail on the sleeper support girder after the step of installing the sleeper support girder. In this case, the existing sleepers and the existing rails that were removed after installing the sleeper support beams can be reused. Therefore, existing sleepers and existing rails can be effectively utilized.

既設桁は、上路桁であってもよく、新設桁は、下路桁又は中路桁であってもよい。この場合、既設桁の下面の高さよりも新設桁の下面の高さを高くすることが可能となる。従って、河川の水面に対する新設桁の高さを高くすることができるので、豪雨災害等が生じた場合であっても河川横断橋が流される事態をより確実に抑制できる。このように、災害に対する河川横断橋の耐性を高めることができる。 The existing girder may be an upper girder, and the newly installed girder may be a lower girder or a middle girder. In this case, it becomes possible to make the height of the lower surface of the newly installed girder higher than the height of the lower surface of the existing girder. Therefore, since the height of the newly installed girder relative to the river water surface can be increased, even in the event of a heavy rain disaster, it is possible to more reliably prevent the river crossing bridge from being washed away. In this way, the resistance of river crossing bridges to disasters can be increased.

本開示に係る橋脚撤去方法は、既設の河川横断橋から複数の既設の橋脚のいずれかを撤去する橋脚撤去方法であって、既設の橋脚の上に基礎の嵩上げを行う新設主桁台座を設置する工程と、新設主桁台座の上に橋脚を跨ぐように新設桁を架設する工程と、新設桁に新設の枕木受桁を設置する工程と、橋脚に取り付けられていた既設桁を撤去する工程と、新設桁に跨がれている橋脚を撤去する工程と、を備える。 The pier removal method according to the present disclosure is a pier removal method in which one of a plurality of existing piers is removed from an existing river crossing bridge, and a new main girder pedestal is installed on top of the existing pier to raise the foundation level. The process of erecting the new girder so as to straddle the pier on the new main girder pedestal, the process of installing the new sleeper support girder on the new girder, and the process of removing the existing girder that was attached to the pier. and the process of removing the bridge pier that spans the newly constructed girder.

この橋脚撤去方法では、既設の河川横断橋を構成する既設の橋脚の上に新設主桁台座が設置され、新設主桁台座の上に新設桁が架設される。新設桁には枕木受桁が設置され、その後、既設の橋脚に取り付けられていた既設桁が撤去される。従って、前述した桁架け替え方法と同様、ジャッキアップを不要とすることができるので、作業性を向上させることができると共に、作業途中においても高い耐震性を確保することができる。更に、この橋脚撤去方法では、複数の橋脚のうちのいずれかであって、且つ新設桁が跨いでいる橋脚が撤去される。従って、河川横断橋における橋脚の数を減らすことができるので、豪雨災害等の発生時であっても河川横断橋が流される事態をより確実に抑制できる。よって、災害に対する河川横断橋の耐性を高めることができる。 In this pier removal method, a new main girder pedestal is installed on top of the existing pier that makes up the existing river crossing bridge, and a new girder is erected on top of the new main girder pedestal. Sleeper support girders will be installed on the new girders, and then the existing girders attached to the existing piers will be removed. Therefore, like the girder replacement method described above, jacking up is not required, so work efficiency can be improved and high earthquake resistance can be ensured even during the work. Furthermore, in this pier removal method, one of the plurality of pier piers, which is straddled by a newly installed girder, is removed. Therefore, since the number of piers in the river crossing bridge can be reduced, it is possible to more reliably prevent the river crossing bridge from being washed away even in the event of a heavy rain disaster or the like. Therefore, the resistance of the river crossing bridge to disasters can be increased.

本開示によれば、架け替えの作業の作業性を向上させることができると共に、耐震性を向上させることができる。 According to the present disclosure, it is possible to improve the workability of rebuilding the bridge, and it is also possible to improve earthquake resistance.

第1実施形態に係る桁架け替え方法が適用される河川横断橋を示す側面図である。It is a side view showing a river crossing bridge to which the girder replacement method according to the first embodiment is applied. 図1の河川横断橋の縦断面図である。FIG. 2 is a longitudinal cross-sectional view of the river crossing bridge in FIG. 1; 図1の河川横断橋のレールが短尺化された状態を示す側面図である。FIG. 2 is a side view showing a state in which the rails of the river crossing bridge in FIG. 1 are shortened. 図3の河川横断橋の縦断面図である。FIG. 4 is a longitudinal cross-sectional view of the river crossing bridge in FIG. 3; 図3の河川横断橋の橋脚に新設主桁台座が載せられた状態を示す側面図である。FIG. 4 is a side view showing a newly installed main girder pedestal placed on the piers of the river crossing bridge shown in FIG. 3; 図5の河川横断橋の縦断面図である。6 is a longitudinal sectional view of the river crossing bridge in FIG. 5. FIG. 図5の河川横断橋の新設主桁台座に新設桁が載せられた状態を示す側面図である。FIG. 6 is a side view showing a newly installed girder placed on the newly installed main girder pedestal of the river crossing bridge shown in FIG. 5; 図7の河川横断橋の縦断面図である。8 is a longitudinal sectional view of the river crossing bridge in FIG. 7. FIG. 図7の河川横断橋に枕木受桁が載せられた状態を示す側面図である。FIG. 8 is a side view showing a state in which sleeper support girders are placed on the river crossing bridge in FIG. 7; 図9の河川横断橋の縦断面図である。10 is a longitudinal sectional view of the river crossing bridge in FIG. 9. FIG. 図9の枕木受桁に枕木が設置された状態を示す縦断面図である。10 is a longitudinal cross-sectional view showing a state in which sleepers are installed on the sleeper support girder of FIG. 9. FIG. 図11のA-A線断面図である。12 is a cross-sectional view taken along the line AA in FIG. 11. 図9の河川横断橋から既設桁が撤去された状態を示す側面図である。10 is a side view showing a state in which the existing girder has been removed from the river crossing bridge in FIG. 9. FIG. 図13の河川横断橋の縦断面図である。FIG. 14 is a longitudinal sectional view of the river crossing bridge in FIG. 13; 第2実施形態に係る桁架け替え方法が適用される河川横断橋において新設桁が設置される状態を示す側面図である。It is a side view which shows the state in which the new girder is installed in the river crossing bridge to which the girder replacement method based on 2nd Embodiment is applied. 図15の河川横断橋の縦断面図である。16 is a longitudinal sectional view of the river crossing bridge in FIG. 15. FIG. 図15の河川横断橋の新設桁に枕木受桁が設置された状態を示す側面図である。FIG. 16 is a side view showing a state in which sleeper support girders are installed on the newly installed girders of the river crossing bridge shown in FIG. 15; 図17の河川横断橋の縦断面図である。FIG. 18 is a longitudinal cross-sectional view of the river crossing bridge in FIG. 17; 図17の河川横断橋から既設桁が撤去された状態を示す側面図である。FIG. 18 is a side view showing a state in which the existing girder has been removed from the river crossing bridge in FIG. 17. 図19の河川横断橋の縦断面図である。FIG. 20 is a longitudinal cross-sectional view of the river crossing bridge in FIG. 19; 第3実施形態に係る河川横断橋において新設桁が設置された状態を示す縦断面図である。It is a longitudinal cross-sectional view showing a state in which newly installed girders are installed in a river crossing bridge according to a third embodiment. 図21の新設桁に枕木受桁が設置された状態を示す縦断面図である。FIG. 22 is a longitudinal sectional view showing a state in which a sleeper support girder is installed on the newly installed girder shown in FIG. 21; 図22の河川横断橋から既設桁が撤去された状態を示す縦断面図である。FIG. 23 is a longitudinal cross-sectional view showing a state in which the existing girder has been removed from the river crossing bridge in FIG. 22. 第4実施形態に係る桁架け替え方法及び橋脚撤去方法が適用される河川横断橋を示す側面図である。It is a side view which shows the river crossing bridge to which the girder replacement method and bridge pier removal method which concern on 4th Embodiment are applied. 図24の河川横断橋の縦断面図である。25 is a longitudinal sectional view of the river crossing bridge in FIG. 24. FIG. 図24の河川横断橋の新設桁に枕木受桁が設置された状態を示す側面図である。FIG. 25 is a side view showing a state in which sleeper support girders are installed on the newly installed girders of the river crossing bridge shown in FIG. 24; 図26の河川横断橋の縦断面図である。27 is a longitudinal sectional view of the river crossing bridge of FIG. 26. FIG. 図26の河川横断橋から既設桁が撤去された状態を示す側面図である。FIG. 27 is a side view showing a state in which the existing girder has been removed from the river crossing bridge in FIG. 26. 図28の河川横断橋の縦断面図である。FIG. 29 is a longitudinal cross-sectional view of the river crossing bridge in FIG. 28;

以下では、図面を参照しながら本開示に係る桁架け替え方法の種々の実施形態について説明する。図面の説明において、同一又は相当する要素には同一の符号を付し、重複する説明を適宜省略する。また、図面は、理解の容易化のため、一部を簡略化又は誇張して描いている場合があり、寸法比率等は図面に記載のものに限定されない。 Below, various embodiments of the girder replacement method according to the present disclosure will be described with reference to the drawings. In the description of the drawings, the same or corresponding elements are denoted by the same reference numerals, and redundant description will be omitted as appropriate. In addition, some parts of the drawings may be simplified or exaggerated for ease of understanding, and the dimensional ratios and the like are not limited to those shown in the drawings.

(第1実施形態)
図1は、第1実施形態に係る桁架け替え方法が実行される前の状態の河川横断橋1を示す側面図である。河川横断橋1は、河川Rに設けられた鉄道橋である。図2は、河川横断橋1の第1方向D1に直交する平面によって河川横断橋1を切断した縦断面図である。第1方向D1は、例えば、河川横断橋1の長手方向であり、又は河川Rの幅方向である。
(First embodiment)
FIG. 1 is a side view showing a river crossing bridge 1 in a state before the girder replacement method according to the first embodiment is executed. The river crossing bridge 1 is a railway bridge installed over the river R. FIG. 2 is a longitudinal sectional view of the river crossing bridge 1 cut along a plane orthogonal to the first direction D1 of the river crossing bridge 1. The first direction D1 is, for example, the longitudinal direction of the river crossing bridge 1 or the width direction of the river R.

図1及び図2に示されるように、河川横断橋1は、第1方向D1に沿って並ぶ複数の橋脚2と、複数の橋脚2の上面2bに固定された既設桁3と、既設桁3の上に載せられた枕木4と、枕木4の上に載せられたレール5とを備える。本実施形態において、既設桁3は、上路桁である。複数の橋脚2は、第1方向D1に沿って一定間隔おきに並んでおり、当該一定間隔は例えば10m程度である。既設桁3の長さは、例えば、10m程度であり、既設桁3の一端3f及び他端3gの位置は橋脚2の鉛直上方に一致する。 As shown in FIGS. 1 and 2, the river crossing bridge 1 includes a plurality of piers 2 lined up along a first direction D1, an existing girder 3 fixed to the upper surface 2b of the plurality of piers 2, and an existing girder 3. It includes a sleeper 4 placed on the sleeper 4 and a rail 5 placed on the sleeper 4. In this embodiment, the existing girder 3 is an upper girder. The plurality of piers 2 are lined up at regular intervals along the first direction D1, and the regular intervals are, for example, about 10 m. The length of the existing girder 3 is, for example, about 10 m, and the positions of one end 3f and the other end 3g of the existing girder 3 correspond to the vertically upper part of the pier 2.

レール5は、橋脚2を跨ぐように設置されており、例えば、3本の橋脚2の上部に1本のレール5が設けられる。例えばレール5の一端5b及び他端5cの位置は橋脚2の鉛直上方に一致する。既設のレール5の長さは、例えば、20m程度である。第1方向に沿って並ぶ一対のレール5の上において第1方向D1に鉄道車両が走行する。 The rails 5 are installed so as to straddle the piers 2, and for example, one rail 5 is provided on top of three piers 2. For example, the positions of one end 5b and the other end 5c of the rail 5 correspond to vertically above the pier 2. The length of the existing rail 5 is, for example, about 20 m. A railway vehicle runs in a first direction D1 on a pair of rails 5 lined up along the first direction.

例えば、河川Rには、河川水Wと、河川水Wから見て第1方向D1の両側のそれぞれに設けられた堤防E1,E2とが設けられている。河川水Wの底に対する既設桁3の下端の高さは、例えば、4m程度である。桁架け替えが実行される前の河川横断橋1は、河川Rに対する既設桁3の高さが低いため、河川横断橋1が設けられる部分における堤防E1の高さが抑えられている。 For example, the river R is provided with river water W and embankments E1 and E2 provided on both sides of the river water W in the first direction D1, respectively. The height of the lower end of the existing girder 3 with respect to the bottom of the river water W is, for example, about 4 m. In the river crossing bridge 1 before the girder replacement is performed, the height of the existing girder 3 with respect to the river R is low, so the height of the embankment E1 in the part where the river crossing bridge 1 is installed is suppressed.

河川横断橋1は、第1方向D1に直交する第2方向D2に沿って並ぶ一対の既設桁3を備える。第2方向D2は、例えば、河川横断橋1の幅方向であり、又は河川Rが流れる方向である。例えば、既設桁3は、H形鋼である。なお、本開示において、「H形鋼」は、H形とは若干異なる形状の形鋼も含んでおり、例えば、I形鋼も含まれる。既設桁3は、橋脚2の上面2bに固定される下フランジ3bと、枕木4及びレール5に連結される上フランジ3cと、下フランジ3b及び上フランジ3cの間で鉛直方向D3に延在するウェブ3dとを有する。 The river crossing bridge 1 includes a pair of existing girders 3 arranged along a second direction D2 orthogonal to the first direction D1. The second direction D2 is, for example, the width direction of the river crossing bridge 1 or the direction in which the river R flows. For example, the existing girder 3 is made of H-beam steel. Note that in the present disclosure, "H-shaped steel" also includes shaped steel that is slightly different from the H-shaped steel, and includes, for example, I-shaped steel. The existing girder 3 extends in the vertical direction D3 between a lower flange 3b fixed to the upper surface 2b of the pier 2, an upper flange 3c connected to the sleeper 4 and the rail 5, and the lower flange 3b and the upper flange 3c. Web 3d.

枕木4は、第1方向D1に沿って一定間隔おきに並ぶように配置されており、各枕木4は、第2方向D2に延在している。当該一定間隔は、例えば、0.6m程度である。河川横断橋1は、既設桁3の上フランジ3cに枕木4を連結する連結部材6を更に備える。例えば、第2方向D2に沿って並ぶ一対の連結部材6が設けられる。 The sleepers 4 are arranged at regular intervals along the first direction D1, and each sleeper 4 extends in the second direction D2. The fixed interval is, for example, about 0.6 m. The river crossing bridge 1 further includes a connecting member 6 that connects the sleeper 4 to the upper flange 3c of the existing girder 3. For example, a pair of connecting members 6 are provided along the second direction D2.

連結部材6は、枕木4に挿通されるフックボルト6bを備える。フックボルト6bの下端には、既設桁3の上フランジ3cに掛けられるフック部6cが設けられる。河川横断橋1は、第2方向D2に沿って並ぶ一対のレール5を備える。レール5は、例えば、タイプレート7を介して枕木4の上に固定されており、タイプレート7は枕木4の上面に犬釘8によって固定されている。 The connecting member 6 includes a hook bolt 6b that is inserted into the sleeper 4. A hook portion 6c that is hooked onto the upper flange 3c of the existing girder 3 is provided at the lower end of the hook bolt 6b. The river crossing bridge 1 includes a pair of rails 5 lined up along the second direction D2. The rail 5 is fixed onto the sleeper 4 via a tie plate 7, for example, and the tie plate 7 is fixed to the upper surface of the sleeper 4 with dog nails 8.

以上のように構成された河川横断橋1の桁架け替え方法について説明する。まず、図3及び図4に示されるよう、レールを短尺化する(レールを短尺化する工程)。レールの短尺化では、例えば、既設の約20mの長さのレール5を、既設桁3及び枕木4に対する作業を一日で行うことが可能な長さのレール15に交換する。レール15への交換、及び以降の作業は、例えば、橋脚2の周囲に足場を設置して行われる。 A method for replacing the girder of the river crossing bridge 1 configured as described above will be explained. First, as shown in FIGS. 3 and 4, the rail is shortened (step of shortening the rail). In shortening the rail, for example, the existing rail 5 having a length of about 20 m is replaced with a rail 15 long enough to work on the existing girders 3 and sleepers 4 in one day. Replacement with the rail 15 and subsequent work are performed, for example, by installing scaffolding around the pier 2.

上記のレールの短尺化は、鉄道車両が通っていない夜間に行われ、例えば、1日で1本のレール5を撤去して2本のレール15を設置する。レール15は、2本の橋脚2の上に設置され、レール15の一端15b及び他端15cの位置は橋脚2の鉛直上方に一致する。例えば、レール15の長さは10m程度である。しかしながら、レール15の長さは、例えば5m程度であってもよく、特に限定されない。 The shortening of the rails described above is performed at night when no railway vehicles are passing, and for example, one rail 5 is removed and two rails 15 are installed in one day. The rail 15 is installed on the two piers 2, and the positions of one end 15b and the other end 15c of the rail 15 are aligned vertically above the piers 2. For example, the length of the rail 15 is about 10 m. However, the length of the rail 15 may be, for example, about 5 m, and is not particularly limited.

レール15の設置によるレールの短尺化が行われた後には、図5及び図6に示されるように、橋脚2に新設主桁台座10を設置する(新設主桁台座を設置する工程)。新設主桁台座10は、既設の橋脚2において基礎の嵩上げを行うために設けられる。新設主桁台座10は、例えば、コンクリート構造体であり、ロウソク基礎とも称される。 After the rails are shortened by installing the rails 15, as shown in FIGS. 5 and 6, a new main girder pedestal 10 is installed on the pier 2 (step of installing a new main girder pedestal). The new main girder pedestal 10 is provided to raise the foundation of the existing pier 2. The newly installed main girder pedestal 10 is, for example, a concrete structure, and is also referred to as a candle foundation.

このとき、橋脚2の上面2bにおける既設桁3の両側のそれぞれに新設主桁台座10を構築する。すなわち、既設桁3の第2方向D2の両側のそれぞれに新設主桁台座10を構築する。新設主桁台座10の高さは、例えば、1m程度である。新設主桁台座10の構築では、例えば、橋脚2の上面2bにおいて型枠を設置し、設置した型枠にコンクリートを打設することによって新設主桁台座10が構築される。例えば、新設主桁台座10の構築は、鉄道車両が通る日中も行える作業である。一例として、全ての橋脚2に対して新設主桁台座10の構築が完了する期間は1月半程度である。 At this time, new main girder pedestals 10 are constructed on both sides of the existing girder 3 on the upper surface 2b of the pier 2. That is, new main girder pedestals 10 are constructed on both sides of the existing girder 3 in the second direction D2. The height of the newly installed main girder pedestal 10 is, for example, about 1 m. In constructing the new main girder pedestal 10, for example, a formwork is installed on the upper surface 2b of the pier 2, and concrete is poured into the installed formwork, thereby constructing the new main girder pedestal 10. For example, construction of the newly installed main girder pedestal 10 is work that can be done even during the day when railroad cars are passing by. As an example, the period for completing construction of the new main girder pedestals 10 for all the piers 2 is about one and a half months.

橋脚2に対して新設主桁台座10の構築が完了した後には、図7及び図8に示されるように、新設桁13を架設する(新設桁を架設する工程)。このとき、構築した新設主桁台座10の上面に新設桁13を設置する。本実施形態において、新設桁13は下路桁である。新設桁13は、既設桁3と同様、例えば、H形鋼であり、下フランジ13b、上フランジ13c及びウェブ13dを有する。 After the construction of the new main girder pedestal 10 on the pier 2 is completed, the new girder 13 is erected as shown in FIGS. 7 and 8 (step of erecting a new girder). At this time, the newly installed girder 13 is installed on the upper surface of the newly constructed main girder pedestal 10. In this embodiment, the newly installed girder 13 is a lower girder. Like the existing girder 3, the new girder 13 is made of, for example, H-beam steel, and has a lower flange 13b, an upper flange 13c, and a web 13d.

新設桁13の長さは、例えば、10m程度である。新設桁13の架設は、例えば、鉄道車両が通っていない夜間に行われ、一例として、1日1スパン(本実施形態では10m)の2本の新設桁13が架設される。新設桁13の一端13f及び他端13gは橋脚2(新設主桁台座10)の鉛直上方に一致する。 The length of the newly installed girder 13 is, for example, about 10 m. The construction of the new girders 13 is performed, for example, at night when no railroad cars are passing, and as an example, two new girders 13 with one span (10 m in this embodiment) are constructed per day. One end 13f and the other end 13g of the newly installed girder 13 correspond to vertically above the pier 2 (newly installed main girder pedestal 10).

新設桁13の設置が完了した後には、図9及び図10に示されるように、新設桁13に新設の枕木受桁11を設置する(枕木受桁を設置する工程)。具体的には、既設桁3から連結部材6、枕木4及びレール15を外し(既設のレール、及び既設の枕木を外す工程)、その後、新設桁13に枕木受桁11を設置する。 After the installation of the newly installed girder 13 is completed, as shown in FIGS. 9 and 10, a newly installed sleeper support girder 11 is installed on the newly installed girder 13 (step of installing a sleeper support girder). Specifically, the connecting member 6, sleeper 4, and rail 15 are removed from the existing girder 3 (step of removing the existing rail and the existing sleeper), and then the sleeper support girder 11 is installed on the newly installed girder 13.

枕木受桁11の設置は、例えば、鉄道車両が通っていない夜間において、第1方向D1に沿って徐々に行われる。例えば、河川Rの状況によっては、吊り足場を設置して枕木受桁11の設置を行う。また、河川水Wの上方における枕木受桁11の設置を行うときに吊り足場を設置してもよい。枕木受桁11の設置は、例えば、1日1スパンで(第1方向D1に沿って並ぶ一対の新設主桁台座20の間の部分が)行われる。枕木受桁11を設置した後には、枕木受桁11に既設の枕木4、及び既設のレール15を設置する(既設の枕木、及び既設のレールを設置する工程)。 The sleeper support beams 11 are installed gradually along the first direction D1, for example, at night when no railroad cars are passing. For example, depending on the situation of the river R, hanging scaffolding is installed and the sleeper support beams 11 are installed. Moreover, when installing the sleeper support girder 11 above the river water W, a hanging scaffold may be installed. The sleeper support girder 11 is installed, for example, in one span per day (in the portion between the pair of newly installed main girder pedestals 20 lined up along the first direction D1). After installing the sleeper support girder 11, the existing sleeper 4 and the existing rail 15 are installed on the sleeper support girder 11 (step of installing the existing sleeper and the existing rail).

枕木受桁11は、第2方向D2に延在する鋼材であり、例えば、枕木受桁11の一端部及び他端部のそれぞれが新設桁13の下フランジ13bの上面に載せられて新設桁13に固定(一例としてボルト固定)される。図11及び図12に示されるように、枕木受桁11は、枕木4が鉛直上方から挿入されて、挿入された枕木4を保持する鋼材である。枕木受桁11からは設置された枕木4の上部が露出している。 The sleeper support girder 11 is a steel material extending in the second direction D2, and for example, each of one end and the other end of the sleeper support girder 11 is placed on the upper surface of the lower flange 13b of the newly installed girder 13. (for example, bolted). As shown in FIGS. 11 and 12, the sleeper support girder 11 is a steel material into which the sleeper 4 is inserted from vertically above and holds the inserted sleeper 4. The upper part of the installed sleeper 4 is exposed from the sleeper support girder 11.

第1方向D1及び鉛直方向D3に延在する平面で切断した枕木受桁11の断面は、上方を向く開口11gを有するコの字状とされている。開口11gには上方から枕木4が嵌め込まれ、枕木受桁11は嵌め込まれた枕木4を保持する。枕木受桁11は、嵌め込まれた枕木4の下面が対向する下板部11dと、嵌め込まれた枕木4の側面が対向すると共に第1方向D1に沿って並ぶ一対の側板部11fとを有する。 A cross section of the sleeper support girder 11 cut along a plane extending in the first direction D1 and the vertical direction D3 has a U-shape with an opening 11g facing upward. A sleeper 4 is fitted into the opening 11g from above, and the sleeper support girder 11 holds the fitted sleeper 4. The sleeper support girder 11 has a lower plate part 11d where the lower surfaces of the fitted sleepers 4 face each other, and a pair of side plate parts 11f where the side faces of the fitted sleepers 4 face each other and are lined up along the first direction D1.

以上のように、枕木受桁11に枕木4を設置した後には、図13及び図14に示されるように、既設桁3を撤去する(既設桁を撤去する工程)。このとき、既設桁3を切断し、切断した既設桁3を下方から抜くことによって橋脚2から既設桁3を撤去する。以上の工程を経て、河川横断橋1に対する桁架け替え方法の一連の工程が完了する。 After installing the sleepers 4 on the sleeper support girders 11 as described above, the existing girders 3 are removed as shown in FIGS. 13 and 14 (step of removing the existing girders). At this time, the existing girder 3 is removed from the pier 2 by cutting the existing girder 3 and pulling out the cut existing girder 3 from below. Through the above steps, a series of steps of the girder replacement method for the river crossing bridge 1 is completed.

次に、本実施形態に係る桁架け替え方法から得られる作用効果について詳細に説明する。本実施形態に係る桁架け替え方法では、既設の河川横断橋1が架け替えられ、既設の河川横断橋1を構成する既設の橋脚2の上に新設主桁台座10が設置される。新設主桁台座10は、橋脚2の上において基礎の嵩上げを行うためのものである。新設主桁台座10の上には新設桁13が架設され、新設桁13には新設の枕木受桁11が設置される。その後、既設の橋脚2に取り付けられていた既設桁3が撤去される。 Next, the effects obtained from the girder replacement method according to this embodiment will be explained in detail. In the girder replacement method according to the present embodiment, an existing river crossing bridge 1 is replaced, and a new main girder pedestal 10 is installed on the existing piers 2 that constitute the existing river crossing bridge 1. The newly installed main girder pedestal 10 is for raising the foundation on the pier 2. A newly installed girder 13 is constructed on the newly installed main girder pedestal 10, and a newly installed sleeper support girder 11 is installed on the newly installed girder 13. After that, the existing girder 3 attached to the existing pier 2 is removed.

この桁架け替え方法では、ジャッキアップを不要とすることができるので、扛上能力によって作業性が左右されることを回避して作業性を向上させることができる。基礎の嵩上げを行う新設主桁台座10は仮設のものではなく、この桁架け替え方法では、仮設構造物を用いずに作業を進めることができるので、作業途中においても高い耐震性を確保することができる。 This girder replacement method can eliminate the need for jacking up, so it is possible to improve workability by avoiding that the workability is affected by the lifting ability. The new main girder pedestal 10 used to raise the foundation is not a temporary one, and with this girder replacement method, the work can proceed without using temporary structures, so high seismic resistance can be ensured even during the work. Can be done.

更に、本実施形態に係る桁架け替え方法では、レール15の短尺化を行ってレール15の長さを一日(一晩)で作業可能な長さに変更するので、作業を一層効率よく行うことができる。また、レール15の短尺化、新設桁13の架設、及び枕木受桁11の設置を夜間に行うことが可能であるため、鉄道車両の既存の営業に影響を与えずに短期間で工事を完了させることができ、工期の短縮に寄与する。例えば、交通制限が不可能で架け替えを行う場合に比べて、短期間で工事を完了させることができる。 Furthermore, in the girder replacement method according to the present embodiment, the length of the rail 15 is changed to a length that can be completed in one day (overnight) by shortening the length of the rail 15, so that the work can be performed more efficiently. be able to. In addition, because it is possible to shorten the rail 15, erect the new girder 13, and install the sleeper girder 11 at night, the construction work can be completed in a short period of time without affecting the existing operation of the railway vehicle. This contributes to shortening the construction period. For example, construction work can be completed in a shorter period of time than when rebuilding a bridge where traffic restrictions are not possible.

本実施形態に係る桁架け替え方法では、枕木受桁11を設置する工程の前に、既設の橋脚2から、既設のレール15、及び既設の枕木4を外す工程を備えてもよい。この場合、新設桁13に枕木受桁11を設置する前に、既設のレール15及び既設の枕木4を外すことができる。 The girder replacement method according to the present embodiment may include a step of removing the existing rail 15 and the existing sleeper 4 from the existing pier 2 before the step of installing the sleeper support girder 11. In this case, before installing the sleeper support girder 11 on the newly installed girder 13, the existing rail 15 and the existing sleeper 4 can be removed.

本実施形態に係る桁架け替え方法は、枕木受桁11を設置する工程の後に、枕木受桁11に既設の枕木4、及び既設のレール15を設置する工程を備えてもよい。この場合、枕木受桁11を設置した後に外した既設の枕木4、及び既設のレール15を再利用することができる。従って、既設の枕木4、及び既設のレール15を有効活用することができる。 本実施形態に係る桁架け替え方法では、新設主桁台座10、枕木受桁11及び新設桁13は新設のものを用いる一方で、橋脚2、枕木4及びレール15については既設のものを用いることができる。従って、既設の部材を有効活用することができる。 The girder replacement method according to the present embodiment may include, after the step of installing the sleeper support girder 11, a step of installing the existing sleeper 4 and the existing rail 15 on the sleeper support girder 11. In this case, the existing sleepers 4 and the existing rails 15, which were removed after installing the sleeper support girders 11, can be reused. Therefore, the existing sleepers 4 and the existing rails 15 can be effectively utilized. In the girder replacement method according to the present embodiment, newly constructed main girder pedestals 10, sleeper support girders 11, and newly installed girders 13 are used, while existing ones are used for the piers 2, sleepers 4, and rails 15. Can be done. Therefore, existing members can be effectively utilized.

本実施形態において、既設桁3は上路桁であり、新設桁13は下路桁である。この場合、既設桁3の下面の高さよりも新設桁13の下面の高さを高くすることが可能となる。従って、河川Rの水面に対する新設桁13の高さを高くすることができるので、豪雨災害等が生じた場合であっても河川横断橋1が流される事態をより確実に抑制できる。このように、災害に対する河川横断橋1の耐性を高めることができる。 In this embodiment, the existing girder 3 is an upper girder, and the newly installed girder 13 is a lower girder. In this case, the height of the lower surface of the newly installed girder 13 can be made higher than the height of the lower surface of the existing girder 3. Therefore, the height of the newly installed girder 13 relative to the water surface of the river R can be increased, so even if a heavy rain disaster or the like occurs, it is possible to more reliably prevent the river crossing bridge 1 from being washed away. In this way, the resistance of the river crossing bridge 1 to disasters can be increased.

本実施形態では、橋脚2の上面に載せられていた既設桁3を、橋脚2の上面の新設主桁台座10の上面に載せられる新設桁13に架け替えるので、新設主桁台座10の高さ分だけ桁の下端の高さを高くすることができる。本実施形態では、新設主桁台座10の高さが1m程度であって、河川水Wの底に対する既設桁3の下端の高さが4m程度であったため、新設桁13の下端の高さを1m程度高くして河川水Wの底に対する新設桁13の下端の高さを5m程度とすることができる。その結果、例えば、堤防E1の最も高い部分よりも新設桁13の下端を高くすることができるので、堤防E1の高さを抑える必要性を無くすことができる。 In this embodiment, since the existing girder 3 placed on the top surface of the pier 2 is replaced with a new girder 13 placed on the top surface of the new main girder pedestal 10 on the top surface of the pier 2, the height of the new main girder pedestal 10 is The height of the lower end of the girder can be increased by the same amount. In this embodiment, the height of the new main girder pedestal 10 is about 1 m, and the height of the lower end of the existing girder 3 with respect to the bottom of the river water W is about 4 m. By increasing the height by about 1 m, the height of the lower end of the newly installed girder 13 relative to the bottom of the river water W can be set to about 5 m. As a result, for example, the lower end of the newly installed girder 13 can be made higher than the highest part of the embankment E1, thereby eliminating the need to suppress the height of the embankment E1.

(第2実施形態)
次に、第2実施形態に係る桁架け替え方法について説明する。第2実施形態に係る桁架け替え方法の一部は、第1実施形態の桁架け替え方法の一部と重複するため、以降では、第1実施形態の内容と重複する説明を適宜省略する。図15及び図16に示されるように、第2実施形態では、第1実施形態の橋脚2よりも幅(第2方向D2の長さ)が狭い橋脚22における桁の架け替えを行う。
(Second embodiment)
Next, a girder replacement method according to the second embodiment will be explained. Since a part of the girder replacement method according to the second embodiment overlaps with a part of the girder replacement method of the first embodiment, descriptions that overlap with the content of the first embodiment will be appropriately omitted hereinafter. As shown in FIGS. 15 and 16, in the second embodiment, the girders in the pier 22 having a narrower width (length in the second direction D2) than the pier 2 of the first embodiment are replaced.

まず、第1実施形態の場合と同様、短尺化されたレール15の設置を終えた後に新設主桁台座20を設置する(新設主桁台座を設置する工程)。新設主桁台座20は、橋脚22の上面22bにおける一対の既設桁3の両側のそれぞれに構築される。新設主桁台座20の第2方向D2の長さは、前述した新設主桁台座10の第2方向D2の長さよりも短い。 First, as in the case of the first embodiment, after completing the installation of the shortened rail 15, the newly installed main girder pedestal 20 is installed (step of installing the newly installed main girder pedestal). The new main girder pedestals 20 are constructed on both sides of the pair of existing girders 3 on the upper surface 22b of the pier 22. The length of the newly installed main spar pedestal 20 in the second direction D2 is shorter than the length of the newly installed main spar pedestal 10 in the second direction D2 described above.

橋脚22に対する新設主桁台座20の構築が完了した後には新設桁23を架設する(新設桁を架設する工程)。このとき、新設主桁台座20の上面に新設桁23を設置する。新設桁23の形状は、前述した新設桁13の形状とは異なっている。新設桁23は、例えば、高さの制約を受けていて新設桁13の高さよりも低い。本実施形態において、新設桁23は中路桁である。新設桁23は、下フランジ23b、上フランジ23c及びウェブ23dを有する。 After the construction of the new main girder pedestal 20 for the pier 22 is completed, the new girder 23 is erected (step of erecting a new girder). At this time, the newly installed girder 23 is installed on the upper surface of the newly installed main girder pedestal 20. The shape of the newly installed girder 23 is different from the shape of the newly installed girder 13 described above. The newly installed girder 23 is, for example, subject to height restrictions and is lower than the height of the newly installed girder 13. In this embodiment, the newly installed girder 23 is a middle girder. The newly installed girder 23 has a lower flange 23b, an upper flange 23c, and a web 23d.

新設桁23の設置と共に、又は新設桁23の設置後には、新設桁23に受け台24を設置する(受け台を設置する工程)。受け台24は、新設桁23の下フランジ23bの上面に固定される。具体的には、一対の新設桁23の下フランジ23bにおける第2方向D2の内側に固定される。 At the same time as installing the newly installed girder 23, or after installing the newly installed girder 23, the pedestal 24 is installed on the newly installed girder 23 (step of installing the pedestal). The pedestal 24 is fixed to the upper surface of the lower flange 23b of the newly installed girder 23. Specifically, it is fixed inside the lower flanges 23b of the pair of newly installed girders 23 in the second direction D2.

受け台24の設置が完了した後には、図17及び図18に示されるように、受け台24に枕木受桁11を設置する(枕木受桁を設置する工程)。具体的には、既設桁3から枕木4及びレール15を外し(既設のレール、及び既設の枕木を外す工程)。その後、一対の受け台24の上に一対の受け台24を跨ぐように枕木受桁11を設置する。そして、枕木受桁11に既設の枕木4、及び既設のレール15を設置する(既設の枕木、及び既設のレールを設置する工程)。 After the installation of the cradle 24 is completed, as shown in FIGS. 17 and 18, the sleeper holder 11 is installed on the cradle 24 (step of installing a sleeper holder). Specifically, the sleeper 4 and rail 15 are removed from the existing girder 3 (step of removing the existing rail and the existing sleeper). Thereafter, the sleeper support girder 11 is installed on the pair of support stands 24 so as to straddle the pair of support stands 24. Then, the existing sleepers 4 and the existing rails 15 are installed on the sleeper support girder 11 (step of installing the existing sleepers and the existing rails).

枕木受桁11に枕木4を設置した後には、図19及び図20に示されるように、既設桁3を撤去する(既設桁を撤去する工程)。具体的には、既設桁3を切断し、切断した既設桁3を下方から抜くことによって橋脚22から既設桁3を撤去する。以上の工程を経て、桁架け替え方法の一連の工程が完了する。 After installing the sleepers 4 on the sleeper support girders 11, as shown in FIGS. 19 and 20, the existing girders 3 are removed (step of removing the existing girders). Specifically, the existing girder 3 is removed from the pier 22 by cutting the existing girder 3 and pulling out the cut existing girder 3 from below. Through the above steps, a series of steps of the girder replacement method are completed.

以上、第2実施形態に係る桁架け替え方法では、新設主桁台座20の上に新設桁23が架設され、新設桁23に新設の枕木受桁11が設置され、その後、既設桁3が撤去される。この一連の工程において、ジャッキアップを不要とできるので、作業性を向上させることができ、作業途中においても高い耐震性を確保することができる。 As described above, in the girder replacement method according to the second embodiment, the newly installed girder 23 is installed on the newly installed main girder pedestal 20, the newly installed sleeper support girder 11 is installed on the newly installed girder 23, and then the existing girder 3 is removed. be done. In this series of steps, since jacking up is not required, work efficiency can be improved and high earthquake resistance can be ensured even during the work.

本実施形態において、新設桁23は中路桁である。よって、既設桁3の下面の高さよりも新設桁23の下面の高さを高くすることができ、河川Rの水面に対する新設桁23の高さを高くすることができる。従って、豪雨災害等が生じた場合であっても河川横断橋が流される事態をより確実に抑制でき、災害に対する河川横断橋の耐性を高めることができる。従って、第1実施形態と同様の作用効果が得られる。 In this embodiment, the newly installed girder 23 is a middle girder. Therefore, the height of the lower surface of the newly installed girder 23 can be made higher than the height of the lower surface of the existing girder 3, and the height of the newly installed girder 23 relative to the water surface of the river R can be increased. Therefore, even if a heavy rain disaster or the like occurs, it is possible to more reliably prevent the river crossing bridge from being washed away, and the resistance of the river crossing bridge to disasters can be increased. Therefore, the same effects as in the first embodiment can be obtained.

(第3実施形態)
続いて、第3実施形態に係る桁架け替え方法について説明する。図21に示されるように、第3実施形態に係る桁架け替え方法では、既設桁3よりも高い新設桁33を設置する点、及び既設桁3を完全に撤去せずに、既設桁3の一部を残置する点が前述した各実施形態とは異なる。第3実施形態では、短尺化されたレール15の設置を終えた後に橋脚32の上面32bに新設主桁台座30を構築する(新設主桁台座を構築する工程)。
(Third embodiment)
Next, a girder replacement method according to the third embodiment will be explained. As shown in FIG. 21, in the girder replacement method according to the third embodiment, the new girder 33 is installed higher than the existing girder 3, and the existing girder 3 is not completely removed. This differs from each of the above-described embodiments in that a portion is left. In the third embodiment, after completing the installation of the shortened rail 15, a new main girder pedestal 30 is constructed on the upper surface 32b of the pier 32 (step of constructing a new main girder pedestal).

続いて、新設主桁台座30に新設桁33を設置する(新設桁を架設する工程)。新設桁33の高さは、前述した新設桁13の高さよりも高い。新設桁33は、中路桁であり、下フランジ33b、上フランジ33c及びウェブ33dを有する。図22に示されるように、新設桁33に鋼材34b,34c,34dを設置する(鋼材を設置する工程)。鋼材34b,34c,34dは、新設桁33(下フランジ33b)と既設桁3(既設桁の上フランジ)との間に挟み込まれる台座である。 Subsequently, the newly installed girder 33 is installed on the newly installed main girder pedestal 30 (a process of erecting a newly installed girder). The height of the newly installed girder 33 is higher than the height of the newly installed girder 13 described above. The newly installed girder 33 is a middle girder and has a lower flange 33b, an upper flange 33c, and a web 33d. As shown in FIG. 22, steel materials 34b, 34c, and 34d are installed on the newly installed girder 33 (step of installing steel materials). The steel members 34b, 34c, and 34d are pedestals that are sandwiched between the new girder 33 (lower flange 33b) and the existing girder 3 (upper flange of the existing girder).

具体的には、一対の新設桁33の一方の下フランジ33b、及び一方の既設桁3の上フランジの下面に鋼材34cをボルトナット又は溶接によって固定し、一対の新設桁33の他方の下フランジ33b、及び他方の既設桁3の上フランジの下面に鋼材34dをボルトナット又は溶接によって固定する。そして、一対の既設桁3の上フランジの下面に鋼材34bを固定して、既設桁3及び新設桁33に対する鋼材34b,34c,34d(3つの鋼材)の設置を行う。 Specifically, the steel material 34c is fixed to the lower surface of the lower flange 33b of one of the pair of new girders 33 and the upper flange of one of the existing girders 3 by bolts and nuts or welding, and the lower flange of the other of the pair of newly installed girders 33 is fixed. 33b, and the steel material 34d is fixed to the lower surface of the upper flange of the other existing girder 3 by bolts and nuts or welding. Then, the steel materials 34b are fixed to the lower surfaces of the upper flanges of the pair of existing girders 3, and the steel materials 34b, 34c, and 34d (three steel materials) are installed on the existing girders 3 and the new girders 33.

鋼材34b,34c,34dを設置した後には、既設桁3及び鋼材34b,34c,34dに枕木受桁11を設置し(枕木受桁を設置する工程)、枕木受桁11に既設の枕木4及びレール15を設置する(既設の枕木、及び既設のレールを設置する工程)。そして、図23に示されるように、既設桁3を撤去する(既設桁を撤去する工程)。 After installing the steel members 34b, 34c, and 34d, install the sleeper support girder 11 on the existing girder 3 and the steel members 34b, 34c, and 34d (step of installing the sleeper support girder), and install the existing sleeper 4 and the sleeper support girder 11 on the sleeper support girder 11. Install the rails 15 (process of installing existing sleepers and existing rails). Then, as shown in FIG. 23, the existing girder 3 is removed (step of removing the existing girder).

このとき、既設桁3の一部を撤去する。具体的には、既設桁3の鋼材34b,34c,34dから下方に突出する部分を切断して、当該切断した部分を撤去する。鋼材34b,34c,34dの間に位置する既設桁3の部分は残置しておく。以上のように既設桁3の一部を撤去した後に、桁架け替え方法の一連の工程が完了する。 At this time, a part of the existing girder 3 will be removed. Specifically, the portions protruding downward from the steel materials 34b, 34c, and 34d of the existing girder 3 are cut, and the cut portions are removed. The portion of the existing girder 3 located between the steel members 34b, 34c, and 34d will remain. After removing a part of the existing girder 3 as described above, a series of steps of the girder replacement method are completed.

以上、第3実施形態に係る桁架け替え方法では、新設主桁台座30の上に新設桁33が架設され、新設桁33に枕木受桁11が設置され、その後、既設桁3の下部が撤去される。従って、ジャッキアップを不要とできるので、作業性を向上させることができ、作業途中においても高い耐震性を確保することができる。本実施形態において、既設桁3は、完全に撤去されることなく、既設桁3の上部が残置される。従って、鋼材34b,34c,34dを用いて既設桁3の一部を枕木受桁11及び枕木4の設置に活かすことができる。 As described above, in the girder replacement method according to the third embodiment, the newly installed girder 33 is installed on the newly installed main girder pedestal 30, the sleeper support girder 11 is installed on the newly installed girder 33, and then the lower part of the existing girder 3 is removed. be done. Therefore, since jacking up is not necessary, work efficiency can be improved and high earthquake resistance can be ensured even during the work. In this embodiment, the existing girder 3 is not completely removed, and the upper part of the existing girder 3 is left in place. Therefore, a part of the existing girder 3 can be utilized for installing the sleeper support girder 11 and the sleeper 4 using the steel materials 34b, 34c, and 34d.

(第4実施形態)
次に、第4実施形態に係る桁架け替え方法及び橋脚撤去方法について説明する。図24及び図25に示されるように、第4実施形態に係る桁架け替え方法では、第3実施形態の新設桁33よりも更に高く且つ長い新設桁43を設置する点、複数の橋脚42の一部を補強する点、及び複数の橋脚42を撤去する点、が前述した各実施形態とは異なる。
(Fourth embodiment)
Next, a girder replacement method and pier removal method according to the fourth embodiment will be described. As shown in FIGS. 24 and 25, in the girder replacement method according to the fourth embodiment, a new girder 43 that is higher and longer than the newly installed girder 33 of the third embodiment is installed, and a plurality of piers 42 are installed. This embodiment differs from each of the embodiments described above in that a portion is reinforced and a plurality of piers 42 are removed.

まず、前述した各実施形態と同様、レール15の短尺化、及び、橋脚42の上面42bにおける新設主桁台座40の構築を行う(新設主桁台座を構築する工程)。そして、新設主桁台座40の上面に新設桁43を架設する(新設桁を架設する工程)。新設桁43の高さ及び強度は、前述した新設桁33の高さ及び強度よりも大きい。 First, as in each of the embodiments described above, the rail 15 is shortened and a new main girder pedestal 40 is constructed on the upper surface 42b of the pier 42 (step of constructing a new main girder pedestal). Then, a newly installed girder 43 is installed on the upper surface of the newly installed main girder pedestal 40 (step of installing a newly installed girder). The height and strength of the newly installed girder 43 are greater than the height and strength of the newly installed girder 33 described above.

新設桁43は、下路桁であり、下フランジ43b、上フランジ43c及びウェブ43dを有する。新設桁43は、橋脚42を第1方向D1に跨ぐように設置され、3本の橋脚42の上部に1本の新設桁43が設けられる。新設桁43の一端43f及び他端43gの位置は橋脚42の鉛直上方に一致する。新設桁43の長さは、例えば、20m程度である。 The newly installed girder 43 is a lower girder and has a lower flange 43b, an upper flange 43c, and a web 43d. The newly installed girder 43 is installed so as to straddle the piers 42 in the first direction D1, and one newly installed girder 43 is provided above the three piers 42. The positions of one end 43f and the other end 43g of the newly installed girder 43 correspond to the vertically upper part of the pier 42. The length of the newly installed girder 43 is, for example, about 20 m.

新設桁43の設置と共に、又は新設桁43の設置の前までに、橋脚42を補強する(橋脚を補強する工程)。この補強は、全ての橋脚42に対して行うのではなく、例えば、撤去対象外の橋脚42に対して行う。本実施形態では、第1方向D1に沿って並ぶ複数の橋脚42のうち、新設桁43の一端43f及び他端43gが上方に位置する橋脚42を補強する。 The pier 42 is reinforced at the same time as the installation of the new girder 43 or before the installation of the new girder 43 (step of reinforcing the pier). This reinforcement is not performed for all piers 42, but for example, for piers 42 that are not targeted for removal. In this embodiment, among the plurality of piers 42 lined up along the first direction D1, one end 43f and the other end 43g of the newly installed girder 43 reinforce the piers 42 located above.

橋脚42の補強は、例えば、補強部材50を橋脚42の外周面に構築する巻き立て補強によって行われる。巻き立て補強は、鋼板巻き立て補強であってもよいし、RC(Reinforced Concrete)巻き立て補強であってもよい。また、橋脚42の補強は、巻き立て補強以外の方法によって行われてもよい。 The reinforcement of the pier 42 is performed, for example, by rolling reinforcement in which a reinforcing member 50 is constructed on the outer peripheral surface of the pier 42. The rolling reinforcement may be steel plate rolling reinforcement or RC (Reinforced Concrete) rolling reinforcement. Moreover, the reinforcement of the pier 42 may be performed by a method other than rolling reinforcement.

一例として、鉛直上方から橋脚42に掘削孔を形成して当該掘削孔に鋼棒を挿入する鋼棒挿入によって橋脚42を補強してもよい。この場合、橋脚42の外周面の肥大化を抑制できる。しかしながら、コストの増大を抑えて早く且つ一層確実に橋脚42を補強する観点では、巻き立て補強によって橋脚42を補強することが好ましい。 As an example, the pier 42 may be reinforced by inserting a steel rod by forming an excavation hole in the pier 42 from vertically above and inserting a steel rod into the excavation hole. In this case, enlargement of the outer peripheral surface of the pier 42 can be suppressed. However, from the viewpoint of quickly and more reliably reinforcing the pier 42 while suppressing an increase in cost, it is preferable to reinforce the pier 42 by rolling reinforcement.

新設桁43の架設、及び橋脚42の補強の後には、図26及び図27に示されるように、新設桁43に枕木受桁11を設置する(枕木受桁を設置する工程)。このとき、前述と同様、既設桁3から連結部材6、枕木4及びレール15を外し、(既設のレール、及び既設の枕木を外す工程)、その後、一対の新設桁43のそれぞれの下フランジ43b上に枕木受桁11を設置する(枕木受桁を設置する工程)。新設桁43に枕木受桁11を設置した後には、枕木受桁11に既設の枕木4、及び既設のレール15を設置する(既設の枕木、及び既設のレールを設置する工程)。 After constructing the new girder 43 and reinforcing the bridge pier 42, as shown in FIGS. 26 and 27, the sleeper support girder 11 is installed on the new girder 43 (step of installing a sleeper support girder). At this time, as described above, the connecting member 6, sleeper 4, and rail 15 are removed from the existing girder 3 (step of removing the existing rail and the existing sleeper), and then the lower flanges 43b of each of the pair of new girders 43 are removed. A sleeper support girder 11 is installed on top (step of installing a sleeper support girder). After installing the sleeper support girder 11 on the newly installed girder 43, the existing sleeper 4 and the existing rail 15 are installed on the sleeper support girder 11 (step of installing the existing sleeper and existing rail).

その後、図28及び図29に示されるように、既設桁3を撤去する(既設桁を撤去する工程)。既設桁3の撤去と共に、又は既設桁3の撤去の後に、橋脚42を撤去する(橋脚を撤去する工程)。このとき、補強されていない橋脚42を新設桁43から撤去する。具体的には、第1方向D1に沿って並ぶ一対の補強された(補強部材50が設けられた)橋脚42の間に位置する補強されていない橋脚42を撤去する。以上の工程を経て、桁架け替え方法及び橋脚撤去方法の一連の工程が完了する。 Thereafter, as shown in FIGS. 28 and 29, the existing girder 3 is removed (step of removing the existing girder). The pier 42 is removed along with or after the removal of the existing girder 3 (a step of removing the pier). At this time, the unreinforced pier 42 is removed from the newly installed girder 43. Specifically, the unreinforced piers 42 located between the pair of reinforced piers 42 (provided with the reinforcing members 50) arranged along the first direction D1 are removed. Through the above steps, a series of steps for girder replacement and bridge pier removal are completed.

以上、第4実施形態に係る桁架け替え方法では、新設主桁台座40の上に新設桁43が架設され、新設桁43に枕木受桁11が設置され、その後、既設桁3が撤去される。従って、前述した各実施形態と同様、作業性を向上させることができ、作業途中においても高い耐震性を確保することができる。また、本実施形態では、既設桁3よりも大きく且つ剛性が高い新設桁43を架設する。従って、複数の橋脚42のうちの一部の補強、及び残部の撤去を行うことによって、橋脚42の数を減らすことができる。 As described above, in the girder replacement method according to the fourth embodiment, the newly installed girder 43 is installed on the newly installed main girder pedestal 40, the sleeper support girder 11 is installed on the newly installed girder 43, and then the existing girder 3 is removed. . Therefore, like each of the embodiments described above, workability can be improved and high earthquake resistance can be ensured even during work. Furthermore, in this embodiment, a new girder 43 that is larger and more rigid than the existing girder 3 is constructed. Therefore, the number of piers 42 can be reduced by reinforcing some of the piers 42 and removing the remaining parts.

すなわち、本実施形態に係る橋脚撤去方法では、既設の河川横断橋を構成する既設の橋脚42の上に新設主桁台座40が設置され、新設主桁台座40の上に新設桁43が架設される。新設桁43には枕木受桁11が設置され、その後、既設の橋脚42に取り付けられれていた既設桁3が撤去される。そして、複数の橋脚42のうちのいずれかであって、且つ新設桁43が跨いでいる橋脚42(新設桁43の一端及び他端が鉛直上方に位置しない橋脚42)が撤去される。 That is, in the bridge pier removal method according to the present embodiment, the new main girder pedestal 40 is installed on the existing pier 42 constituting the existing river crossing bridge, and the newly installed girder 43 is installed on the new main girder pedestal 40. Ru. The sleeper support girder 11 is installed on the new girder 43, and then the existing girder 3 attached to the existing pier 42 is removed. Then, one of the plurality of piers 42 and over which the newly installed girder 43 straddles (the pier 42 in which one end and the other end of the newly installed girder 43 are not located vertically above) is removed.

従って、河川横断橋における橋脚42の数を減らすことができるので、豪雨災害の発生時であっても河川横断橋が流される事態をより確実に抑制できる。すなわち、桁架け替えの前と比較して橋脚42のスパンを広げることができ、河川横断橋が受ける河川Rの流れの抵抗を低減させることができるので、豪雨災害等に対する河川横断橋の耐性をより強くすることができる。 Therefore, since the number of piers 42 in the river crossing bridge can be reduced, it is possible to more reliably prevent the river crossing bridge from being washed away even in the event of a heavy rain disaster. In other words, the span of the piers 42 can be expanded compared to before the girder replacement, and the resistance of the flow of the river R that the river crossing bridge receives can be reduced, so the resistance of the river crossing bridge to heavy rain disasters etc. can be increased. It can be made stronger.

以上、本開示に係る桁架け替え方法及び橋脚撤去方法の種々の実施形態について説明した。しかしながら、本開示は、前述した実施形態に限定されるものではなく、各請求項に記載した要旨を変更しない範囲において変形し、又は他のものに適用したものであってもよい。すなわち、桁架け替え方法及び橋脚撤去方法の工程の内容及び順序は、上記の要旨を逸脱しない範囲において適宜変更可能である。 Various embodiments of the girder replacement method and pier removal method according to the present disclosure have been described above. However, the present disclosure is not limited to the embodiments described above, and may be modified or applied to other things without changing the gist of each claim. That is, the content and order of the steps in the girder replacement method and the pier removal method can be changed as appropriate without departing from the above gist.

例えば、前述では、第4実施形態の桁架け替え方法において複数の橋脚42の一部を撤去する橋脚撤去方法について説明した。しかしながら、本開示に係る橋脚撤去方法は、前述した第1実施形態、第2実施形態又は第3実施形態の桁架け替え方法において行われるものであってもよい。この場合、第1~第3実施形態の場合でも、橋脚のスパンを広げて豪雨災害に強い河川横断橋を構築できる。 For example, in the above description, a pier removal method for removing a portion of the plurality of pier piers 42 in the girder replacement method of the fourth embodiment has been described. However, the pier removal method according to the present disclosure may be performed in the girder replacement method of the first embodiment, second embodiment, or third embodiment described above. In this case, even in the first to third embodiments, a river crossing bridge that is resistant to heavy rain disasters can be constructed by widening the span of the piers.

1…河川横断橋、2,22,32,42…橋脚、2b,22b,32b,42b…上面、3…既設桁、3b…下フランジ、3c…上フランジ、3d…ウェブ、3f…一端、3g…他端、4…枕木、5…レール、5b…一端、5c…他端、6…連結部材、6b…フックボルト、6c…フック部、7…タイプレート、8…犬釘、10,20,30,40…新設主桁台座、11…枕木受桁、11d…下板部、11f…側板部、11g…開口、13,23,33,43…新設桁、13b,23b,33b,43b…下フランジ、13c,23c,33c,43c…上フランジ、13d,23d,33d,43d…ウェブ、13f,43f…一端、13g,43g…他端、15…レール、15b…一端、15c…他端、24…受け台、34b,34c,34d…鋼材、50…補強部材、D1…第1方向、D2…第2方向、D3…鉛直方向、E1…堤防、E2…堤防、R…河川、W…河川水。

1... River crossing bridge, 2, 22, 32, 42... Pier, 2b, 22b, 32b, 42b... Top surface, 3... Existing girder, 3b... Lower flange, 3c... Upper flange, 3d... Web, 3f... One end, 3g ...Other end, 4...Sleeper, 5...Rail, 5b...One end, 5c...Other end, 6...Connecting member, 6b...Hook bolt, 6c...Hook portion, 7...Tie plate, 8...Dog nail, 10, 20, 30 , 40... Newly installed main girder pedestal, 11... Sleeper support girder, 11d... Lower plate part, 11f... Side plate part, 11g... Opening, 13, 23, 33, 43... Newly installed girder, 13b, 23b, 33b, 43b... Lower flange , 13c, 23c, 33c, 43c...upper flange, 13d, 23d, 33d, 43d...web, 13f, 43f...one end, 13g, 43g...other end, 15...rail, 15b...one end, 15c...other end, 24... cradle, 34b, 34c, 34d... steel material, 50... reinforcing member, D1... first direction, D2... second direction, D3... vertical direction, E1... embankment, E2... embankment, R... river, W... river water.

Claims (5)

既設の河川横断橋の桁架け替え方法であって、
既設の橋脚の上に基礎の嵩上げを行う新設主桁台座を設置する工程と、
前記新設主桁台座の上に新設桁を架設する工程と、
前記新設桁に新設の枕木受桁を設置する工程と、
前記既設の橋脚に取り付けられていた既設桁を撤去する工程と、を備える、
桁架け替え方法。
A girder replacement method for an existing river crossing bridge, the method comprising:
The process of installing a new main girder pedestal to raise the foundation on top of the existing pier;
a step of erecting a new girder on the new main girder pedestal;
a step of installing a newly installed sleeper support girder on the newly installed girder;
a step of removing an existing girder attached to the existing bridge pier;
How to replace the girder.
前記枕木受桁を設置する工程の前に、前記既設の橋脚から、既設のレール、及び既設の枕木を外す工程を備える、
請求項1に記載の桁架け替え方法。
Before the step of installing the sleeper support girder, a step of removing the existing rail and the existing sleeper from the existing bridge pier,
The girder replacement method according to claim 1.
前記枕木受桁を設置する工程の後に、前記枕木受桁に前記既設の枕木、及び前記既設のレールを設置する工程を備える、
請求項2に記載の桁架け替え方法。
After the step of installing the sleeper support girder, a step of installing the existing sleeper and the existing rail on the sleeper support girder,
The girder replacement method according to claim 2.
前記既設桁は、上路桁であり、
前記新設桁は、下路桁又は中路桁である、
請求項1~3のいずれか一項に記載の桁架け替え方法。
The existing girder is an upper girder,
The newly installed girder is a lower girder or a middle girder,
The girder replacement method according to any one of claims 1 to 3.
既設の河川横断橋から複数の既設の橋脚のいずれかを撤去する橋脚撤去方法であって、
既設の橋脚の上に基礎の嵩上げを行う新設主桁台座を設置する工程と、
前記新設主桁台座の上に前記橋脚を跨ぐように新設桁を架設する工程と、
前記新設桁に新設の枕木受桁を設置する工程と、
前記橋脚に取り付けられていた既設桁を撤去する工程と、
前記新設桁に跨がれている前記橋脚を撤去する工程と、
を備える橋脚撤去方法。

A pier removal method for removing one of a plurality of existing piers from an existing river crossing bridge, the method comprising:
The process of installing a new main girder pedestal to raise the foundation on top of the existing pier;
erecting a new girder on the new main girder pedestal so as to straddle the pier;
a step of installing a newly installed sleeper support girder on the newly installed girder;
a step of removing the existing girder attached to the pier;
a step of removing the bridge pier that spans the newly constructed girder;
Bridge pier removal method.

JP2021024523A 2021-02-18 2021-02-18 Girder replacement method and pier removal method Active JP7386824B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021024523A JP7386824B2 (en) 2021-02-18 2021-02-18 Girder replacement method and pier removal method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021024523A JP7386824B2 (en) 2021-02-18 2021-02-18 Girder replacement method and pier removal method

Publications (2)

Publication Number Publication Date
JP2022126444A JP2022126444A (en) 2022-08-30
JP7386824B2 true JP7386824B2 (en) 2023-11-27

Family

ID=83059041

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021024523A Active JP7386824B2 (en) 2021-02-18 2021-02-18 Girder replacement method and pier removal method

Country Status (1)

Country Link
JP (1) JP7386824B2 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000008304A (en) 1998-06-18 2000-01-11 West Japan Railway Co Pedestal for rail road work beam and execution method of pedestal for rail road work beam
JP2002097608A (en) 2000-09-26 2002-04-02 Shimizu Corp How to replace a railway bridge
JP2002194704A (en) 2000-12-26 2002-07-10 Taisei Corp How to build digits
JP2009228301A (en) 2008-03-24 2009-10-08 Maeda Corp Elongation method for bridge pier
JP2009228300A (en) 2008-03-24 2009-10-08 Maeda Corp Construction method of enlarging space under girder of river bridge
US20190016568A1 (en) 2017-07-12 2019-01-17 Da Pan Gantry assembly and a system for replacing single or double railway bridges
JP2020002670A (en) 2018-06-29 2020-01-09 株式会社ナベカヰ Bridge pier removal method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3665909B2 (en) * 1994-11-21 2005-06-29 西日本旅客鉄道株式会社 Bridge reconstruction method
JP3432347B2 (en) * 1996-01-25 2003-08-04 東日本旅客鉄道株式会社 Short span overpass or overpass, long span renovation method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000008304A (en) 1998-06-18 2000-01-11 West Japan Railway Co Pedestal for rail road work beam and execution method of pedestal for rail road work beam
JP2002097608A (en) 2000-09-26 2002-04-02 Shimizu Corp How to replace a railway bridge
JP2002194704A (en) 2000-12-26 2002-07-10 Taisei Corp How to build digits
JP2009228301A (en) 2008-03-24 2009-10-08 Maeda Corp Elongation method for bridge pier
JP2009228300A (en) 2008-03-24 2009-10-08 Maeda Corp Construction method of enlarging space under girder of river bridge
US20190016568A1 (en) 2017-07-12 2019-01-17 Da Pan Gantry assembly and a system for replacing single or double railway bridges
JP2020002670A (en) 2018-06-29 2020-01-09 株式会社ナベカヰ Bridge pier removal method

Also Published As

Publication number Publication date
JP2022126444A (en) 2022-08-30

Similar Documents

Publication Publication Date Title
CN106351132B (en) A kind of bridge using corrugated sheet steel connector spells wide construction and its construction method
KR101256130B1 (en) ease precast girder and bridge using the same
CN206887794U (en) A kind of supporting apparatus system during the segmentation dismounting for Continuous Bridge
CN113832875A (en) Existing bridge pier column deviation rectifying construction system and construction method thereof
CN115748413A (en) Continuous steel truss web-plate truss double-layer combined swivel bridge structure
KR101187282B1 (en) Railway bridge constructing method using 2 post type abutment structure
KR101527782B1 (en) Management and reverse displacement of composite bridge composite inclined support installation method
CN115928608A (en) A reverse construction method of continuous steel truss web-plate truss double-layer combined swivel bridge
CN213805443U (en) Steel construction, frame beam structure, side slope reinforced structure and reinforcement and support structure
JP4585614B1 (en) Method for constructing synthetic steel slab bridge, ribbed steel slab, and synthetic steel slab bridge
CN103205930B (en) Structure for continuous transformation of existing simply supported hollow slab girder bridge and construction method of structure
CN210049103U (en) High-grade high-speed highway bracket spanned by large-span cast-in-place box girder
JP4477467B2 (en) Bridge structure and its replacement method
JP7386824B2 (en) Girder replacement method and pier removal method
KR20060099484A (en) Upper slab raising method using chemical anchor and buried high tension bolt and integral steel shelf structure embedded with block out on the pier coping surface
CN111218893B (en) Construction method of reinforcing steel truss beams with new piers and columns to reinforce bridges across existing lines
JP2019199711A (en) Method for rebuilding bridge
CN112302033A (en) Pile anchor type cover plate foundation pit support structure and construction method thereof
JP4901178B2 (en) Steel / concrete composite rigid frame bridge construction method
CN115094788B (en) A steel tube lattice pier for bridge pier and bridge repair work and a construction method thereof
CN203583343U (en) Support type frame bridge
CN114541275A (en) Steel beam pushing cylindrical high pier without embedded support platform and quick installation and dismantling method
JP7650838B2 (en) How to replace the girder
GangaRao et al. Development of economical low-volume road bridges
CN116608324B (en) Underground pipeline reinforcing structure below river-crossing bridge under tunnel construction

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230203

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230921

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231107

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231114

R150 Certificate of patent or registration of utility model

Ref document number: 7386824

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150