Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP7399608B2 - Meter device, meter system, and command reception method for meter device - Google Patents
[go: Go Back, main page]

JP7399608B2 - Meter device, meter system, and command reception method for meter device - Google Patents

Meter device, meter system, and command reception method for meter device Download PDF

Info

Publication number
JP7399608B2
JP7399608B2 JP2018165616A JP2018165616A JP7399608B2 JP 7399608 B2 JP7399608 B2 JP 7399608B2 JP 2018165616 A JP2018165616 A JP 2018165616A JP 2018165616 A JP2018165616 A JP 2018165616A JP 7399608 B2 JP7399608 B2 JP 7399608B2
Authority
JP
Japan
Prior art keywords
emergency
meter
meter device
signal
communication
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018165616A
Other languages
Japanese (ja)
Other versions
JP2020038516A (en
Inventor
英俊 横田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Landis and Gyr Japan KK
Original Assignee
Landis and Gyr Japan KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Landis and Gyr Japan KK filed Critical Landis and Gyr Japan KK
Priority to JP2018165616A priority Critical patent/JP7399608B2/en
Priority to PCT/JP2019/032297 priority patent/WO2020049990A1/en
Publication of JP2020038516A publication Critical patent/JP2020038516A/en
Application granted granted Critical
Publication of JP7399608B2 publication Critical patent/JP7399608B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING SYSTEMS, e.g. PERSONAL CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B25/00Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems
    • G08B25/01Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems characterised by the transmission medium
    • G08B25/10Alarm systems in which the location of the alarm condition is signalled to a central station, e.g. fire or police telegraphic systems characterised by the transmission medium using wireless transmission systems
    • GPHYSICS
    • G08SIGNALLING
    • G08CTRANSMISSION SYSTEMS FOR MEASURED VALUES, CONTROL OR SIMILAR SIGNALS
    • G08C19/00Electric signal transmission systems
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04MTELEPHONIC COMMUNICATION
    • H04M11/00Telephonic communication systems specially adapted for combination with other electrical systems
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q9/00Arrangements in telecontrol or telemetry systems for selectively calling a substation from a main station, in which substation desired apparatus is selected for applying a control signal thereto or for obtaining measured values therefrom

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Arrangements For Transmission Of Measured Signals (AREA)
  • Alarm Systems (AREA)
  • Selective Calling Equipment (AREA)
  • Telephonic Communication Services (AREA)

Description

本発明はメータ装置、メータシステム、およびメータ装置の指令受信方法に関する。 The present invention relates to a meter device, a meter system, and a command receiving method for a meter device.

従来から、ガスメータ、水道メータ等のメータ装置は、各家屋の外に設置され、電源からの電力が供給されないことが多い。この場合、メータ装置自体がバッテリーを備えており、当該バッテリーのみによってメータ装置が作動する。また、バッテリーは、規格等に準じて、10年等の長期に亘ってメータ装置に電力を供給する必要がある。このため、バッテリーの寿命を出来るだけ長くするために、メータ装置が他の装置と間欠的な無線通信を行うように構成されている。例えば、使用量のデータを上位の装置に無線通信するために、メータ装置は10分に1回、数十分に1回等のタイミングで通信要求を送信し、通信要求の後の数秒間だけ受信可能な状態となる。(例えば、特許文献1参照。) Conventionally, meter devices such as gas meters and water meters have been installed outside each house, and are often not supplied with power from a power source. In this case, the meter device itself is equipped with a battery, and the meter device operates only by the battery. Furthermore, the battery needs to supply power to the meter device for a long period of time, such as 10 years, in accordance with standards and the like. Therefore, in order to extend the life of the battery as long as possible, the meter device is configured to perform intermittent wireless communication with other devices. For example, in order to wirelessly communicate usage data to a higher-level device, the meter device sends a communication request once every 10 minutes, once every several tens of minutes, etc., and only for a few seconds after the communication request. It becomes ready to receive. (For example, see Patent Document 1.)

特開2001-016663号公報Japanese Patent Application Publication No. 2001-016663

前述のように、メータ装置の無線通信部が、10分に1回、数十分に1回等のタイミングで数秒間だけ起動するので、バッテリーの消費電力が有効に抑制される。
一方、上流側の装置、例えば管理センタのサーバから各メータ装置への緊急指令の送信が必要になる場合がある。前記緊急指令は、例えば、大規模な地震、火災、水害等の非常事態が発生した際に、ある地域の全てのメータ装置に一斉に同じ動作を要求する指令である。
As described above, since the wireless communication section of the meter device is activated for only a few seconds at a timing such as once every 10 minutes or once every several tens of minutes, power consumption of the battery is effectively suppressed.
On the other hand, it may be necessary to send an emergency command from an upstream device, such as a server in a management center, to each meter device. The emergency command is, for example, a command that requests all meter devices in a certain area to perform the same operation at the same time when an emergency situation such as a large-scale earthquake, fire, or flood occurs.

しかし、メータ装置の無線通信部は、10分に1回、数十分に1回等のタイミングだけ起動しており、殆どの期間は起動していない。このため、上流側の装置が緊急指令を出来るだけ早く各メータ装置に通信したい時でも、上流側の装置はメータ装置と当該通信を行うことができない。 However, the wireless communication section of the meter device is activated only once every 10 minutes, once every several tens of minutes, and is not activated most of the time. Therefore, even when the upstream device wants to communicate an emergency command to each meter device as quickly as possible, the upstream device cannot perform the communication with the meter device.

本発明は、前述の事情に鑑みてなされている。本発明の目的の一つは、緊急指令の迅速な伝達を可能とするメータ装置、メータシステム、およびメータ装置の指令受信方法の提供である。 The present invention has been made in view of the above-mentioned circumstances. One of the objects of the present invention is to provide a meter device, a meter system, and a command receiving method for a meter device that enable prompt transmission of emergency commands.

上記課題を解決するために、本発明は以下の手段を採用する。
本発明の第1態様のメータ装置は、電気、ガス、および水の少なくとも何れかの使用量を計る計測部と、無線通信部と、制御部と、を備え、前記制御部が、前記計測部によって計測された前記使用量を他のメータ装置又はメータネットワーク上の無線機能付き装置に送る時に、前記無線通信部に、前記他のメータ装置又は前記無線機能付き装置に対する所定の間欠周期での通信要求の送信又は前記所定の間欠周期での同期要求の送信を行わせる通常通信処理と、非常事態を検出するセンサからの信号又は前記非常事態を通知する信号を受付けると、前記無線通信部を、前記他のメータ装置又は前記無線機能付き装置に対して前記所定の間欠周期よりも短い非常時間欠周期で通信要求を送信する状態、又は、前記非常時間欠周期での受信が可能な状態とする非常時通信処理と、を行う。
In order to solve the above problems, the present invention employs the following means.
A meter device according to a first aspect of the present invention includes a measurement unit that measures the amount of at least one of electricity, gas, and water used, a wireless communication unit, and a control unit, and the control unit is configured to control the measurement unit. When sending the usage amount measured by the above to another meter device or a device with a wireless function on the meter network, the wireless communication unit is configured to communicate with the other meter device or the device with a wireless function at a predetermined intermittent cycle. Upon receiving a normal communication process for transmitting a request or a synchronization request at the predetermined intermittent cycle, and receiving a signal from a sensor detecting an emergency situation or a signal notifying the emergency situation, the wireless communication unit: A state in which a communication request is transmitted to the other meter device or the device with a wireless function at an emergency intermittent period shorter than the predetermined intermittent period, or a state in which communication requests can be received at the emergency intermittent period. Performs emergency communication processing.

当該態様では、非常事態を検出するセンサからの信号又は非常事態を通知する信号を受付けると、制御部が、無線通信部を、他のメータ装置又は無線機能付き装置に対して所定の間欠周期よりも短い非常時間欠周期で通信要求を送信する状態、又は、非常時間欠周期での受信が可能な状態とする。 In this aspect, upon receiving a signal from a sensor that detects an emergency situation or a signal that notifies an emergency situation, the control unit causes the wireless communication unit to communicate with other meter devices or devices with wireless functionality at predetermined intermittent intervals. A state in which communication requests can be transmitted in a short emergency period, or a state in which communication requests can be received in an emergency period.

例えば、メータ装置が、通常通信処理において、その無線通信部を10分に1回、数十分に1回等のタイミングで数秒間だけ起動するものであっても、非常事態を検出するセンサからの信号又は非常事態を通知する信号を受付けた後は、短い非常時間欠周期で通信要求の送信が行われ、又は、短い非常時間欠周期で受信可能な状態となる。
このため、管理センタのサーバ等の無線機能付き装置、サーバから緊急指令を受付けた他のメータ装置等から、緊急指令を迅速に受信することが可能となる。
For example, even if a meter device activates its wireless communication section for only a few seconds at a timing such as once every 10 minutes or once every several tens of minutes during normal communication processing, a sensor that detects an emergency situation may After receiving a signal or a signal notifying an emergency situation, a communication request is transmitted in a short emergency period, or becomes ready to be received in a short emergency period.
Therefore, it is possible to quickly receive an emergency command from a device with a wireless function such as a server in the management center, or from another meter device that has received an emergency command from the server.

上記態様において、好ましくは、前記制御部が、当該メータ装置の周囲に存在する他のメータ装置の数を推定する数推定処理を行い、前記制御部が、推定された前記数に応じて、前記信号を受付けてから前記非常時間欠周期での通信要求の送信の開始までの待機時間、又は、前記信号を受付けてから前記非常時間欠周期での受信を開始するまでの待機時間を変化させる。
このため、当該メータ装置の周囲に存在する他のメータ装置の数が多い場合に、当該数に応じて待機時間を変化させることができる。このため、当該メータ装置の周囲に存在する他のメータ装置の通信と当該メータ装置の通信との干渉の可能性が低減される。
In the above aspect, preferably, the control unit performs a number estimation process of estimating the number of other meter devices existing around the meter device, and the control unit performs a number estimation process to estimate the number of other meter devices existing around the meter device, and the control unit A waiting time from receiving a signal to starting transmission of a communication request in the emergency interruption period, or a waiting time from receiving the signal to starting reception in the emergency interruption period, is changed.
Therefore, when there are many other meter devices around the meter device, the standby time can be changed depending on the number of other meter devices. Therefore, the possibility of interference between communication of other meter devices existing around the meter device and communication of the meter device is reduced.

上記態様において、好ましくは、前記数推定処理において、前記制御部が、前記通信要求の送信又は前記同期要求の送信の後の間欠的な受信可能状態時に検出した信号の数を用いて、前記数を推定する。
当該態様では、非常時に当該メータ装置の周囲に存在する他のメータ装置の数を推定するためのデータを集める場合と比較し、非常時の処理が速くなる。これは、緊急指令を速く確実に各メータ装置に送信する上で有利である。
In the above aspect, preferably, in the number estimation process, the control unit uses the number of signals detected during the intermittent receivable state after the transmission of the communication request or the transmission of the synchronization request, to estimate the number of signals. Estimate.
In this aspect, the processing speed in an emergency is faster than in the case of collecting data for estimating the number of other meter devices existing around the meter device in an emergency. This is advantageous in quickly and reliably transmitting emergency commands to each meter device.

上記態様において、好ましくは、前記信号が前記非常事態の程度を示すものであり、前記制御部が、前記信号に基づき、前記非常時間欠周期での前記通信要求の送信又は前記非常時間欠周期での受信が可能な状態の継続時間を決定する。
当該態様では、非常事態の程度に応じて継続時間が変化する。例えば、非常事態の程度が重大である場合、非常事態の規模が大きい場合、非常事態による影響が大きい場合等に、制御部は継続時間を長くする。これにより、緊急指令の各メータ装置への伝達がより確実になる。
In the above aspect, preferably, the signal indicates the degree of the emergency situation, and the control unit transmits the communication request in the emergency interruption period or transmits the communication request in the emergency interruption period based on the signal. Determine the duration of the state in which the data can be received.
In this aspect, the duration changes depending on the degree of the emergency situation. For example, when the degree of the emergency is serious, when the scale of the emergency is large, when the impact of the emergency is large, etc., the control unit increases the duration. This makes the transmission of the emergency command to each meter device more reliable.

上記態様において、好ましくは、前記信号が前記非常事態の程度を示すものであり、前記制御部が、前記信号に基づき、前記非常時間欠周期を決定する。
当該態様では、非常事態の程度に応じて非常時間欠周期が変化する。例えば、非常事態の程度が重大である場合、非常事態の規模が大きい場合、非常事態による影響が大きい場合等に、制御部は非常時間欠周期を短くする。これは、重要度が高い緊急指令を迅速に各メータ装置に送信するために有利である。
In the above aspect, preferably, the signal indicates the degree of the emergency situation, and the control unit determines the emergency interruption period based on the signal.
In this aspect, the emergency downtime period changes depending on the degree of the emergency situation. For example, when the degree of the emergency is serious, when the scale of the emergency is large, when the influence of the emergency is large, the control unit shortens the emergency interruption period. This is advantageous for quickly transmitting emergency commands of high importance to each meter device.

上記態様において、好ましくは、前記センサは、前記メータ装置に設けられた地震計である。
当該態様では、地震計からの信号を受付けると、制御部が、無線通信部を、非常時間欠周期で通信要求を送信する状態、又は、前記非常時間欠周期での受信が可能な状態とする。このように、大地震等が発生した際に各メータ装置がその装置内の構成のみによって非常時通信モードになる。当該構成は、非常時通信モードへの遷移を確実に行うために有利である。
In the above aspect, preferably the sensor is a seismometer provided in the meter device.
In this aspect, upon receiving the signal from the seismograph, the control unit puts the wireless communication unit into a state where it transmits a communication request in an emergency period, or into a state where it can receive a signal in the emergency period. . In this way, when a major earthquake or the like occurs, each meter device enters the emergency communication mode depending only on the internal configuration of the meter device. This configuration is advantageous for reliably transitioning to the emergency communication mode.

上記態様において、好ましくは、前記非常事態を通知する信号が火災報知器又は水害報知器からの信号である。
当該態様では、火災報知器又は水害報知器からの信号をメータ装置の制御部が受付けると、制御部が、無線通信部を、非常時間欠周期で通信要求を送信する状態、又は、前記非常時間欠周期での受信が可能な状態とする。このように、火災又は水害が発生した際に各メータ装置が非常時通信モードとなる。当該構成は、火災又は水害が発生した際に非常時通信モードへの遷移を行うために有利である。
In the above aspect, preferably, the signal notifying the emergency situation is a signal from a fire alarm or a water damage alarm.
In this aspect, when the control unit of the meter device receives a signal from a fire alarm or a water damage alarm, the control unit sets the wireless communication unit to a state in which a communication request is transmitted at an emergency period, or during the emergency period. A state is established in which reception is possible even during missed periods. In this way, each meter device goes into emergency communication mode when a fire or water disaster occurs. This configuration is advantageous for transitioning to an emergency communication mode in the event of fire or water damage.

本発明の第2態様のメータ装置は、電気、ガス、および水の少なくとも何れかの使用量を計る計測部と、無線通信部と、制御部と、を備え、前記制御部が、前記無線通信部に間欠的な受信を行わせる通常通信処理と、非常事態を検出するセンサからの信号又は前記非常事態を通知する信号を受付けると、前記間欠的な受信の合間の寝ている状態の前記無線通信部を、他のメータ装置又はメータネットワーク上の無線機能付き装置との通信のために起動させる非常時通信処理と、を行う。 A meter device according to a second aspect of the present invention includes a measurement unit that measures the usage amount of at least one of electricity, gas, and water, a wireless communication unit, and a control unit, and the control unit is configured to communicate with the wireless communication unit. normal communication processing that causes the unit to perform intermittent reception; and upon receiving a signal from a sensor that detects an emergency situation or a signal that notifies the emergency situation, the wireless communication unit is in a sleeping state between the intermittent receptions. An emergency communication process is performed in which the communication unit is activated for communication with another meter device or a device with a wireless function on the meter network.

当該態様では、非常事態を検出するセンサからの信号又は非常事態を通知する信号を受付けると、通常通信処理の間欠的な受信の合間の寝ている状態の無線通信部が、他のメータ装置又はメータネットワーク上の無線機能付き装置との通信のために起動する。 In this aspect, when receiving a signal from a sensor that detects an emergency situation or a signal that notifies an emergency situation, the wireless communication unit, which is in a sleeping state between intermittent receptions in normal communication processing, communicates with other meter devices or Activated for communication with wireless-capable devices on the meter network.

例えば、メータ装置が、通常通信処理において、その無線通信部を10分に1回、数十分に1回等のタイミングで数秒間だけ起動するものであっても、非常事態を検出するセンサからの信号又は非常事態を通知する信号を受付けると、他のメータ装置又はメータネットワーク上の無線機能付き装置との通信のために起動する。
このため、管理センタのサーバ等の無線機能付き装置、サーバから緊急指令を受付けた他のメータ装置等から、緊急指令を迅速に受信することが可能となる。
For example, even if a meter device activates its wireless communication section for only a few seconds at a timing such as once every 10 minutes or once every several tens of minutes during normal communication processing, a sensor that detects an emergency situation may signal or a signal notifying an emergency situation, it is activated for communication with other meter devices or devices with wireless functionality on the meter network.
Therefore, it is possible to quickly receive an emergency command from a device with a wireless function such as a server in the management center, or from another meter device that has received an emergency command from the server.

本発明の第3態様のメータシステムは、前記メータ装置と、前記他のメータ装置又は前記無線機能付き装置と、を備える。 A meter system according to a third aspect of the present invention includes the meter device, and the other meter device or the wireless function device.

本発明の第4態様のメータシステムは、前記メータ装置と、前記他のメータ装置又は前記無線機能付き装置と、を備え、前記他のメータ装置又は前記無線機能付き装置が、非常事態の程度に関する情報を受信し、前記メータ装置の制御部が、前記継続時間又は前記非常時間欠周期の決定に用いた前記非常事態の程度を前記他のメータ装置又は前記無線機能付き装置に送信する処理を行い、前記他のメータ装置又は前記無線機能付き装置が、前記非常事態の程度よりも前記非常事態の程度に関する情報が正確であるか否かを判断し、前記非常事態の程度に関する情報が正確である場合に前記非常事態の程度に関する情報を前記メータ装置に送信する処理を行い、前記メータ装置の制御部が、前記非常事態の程度に関する情報を用いて前記継続時間又は前記非常時間欠周期を決定する。 A meter system according to a fourth aspect of the present invention includes the meter device and the other meter device or the device with wireless function, wherein the other meter device or the device with wireless function is connected to the level of the emergency situation. Upon receiving the information, the control unit of the meter device performs a process of transmitting the degree of the emergency situation used to determine the duration or the emergency interruption period to the other meter device or the device with wireless function. , the other meter device or the device with wireless function determines whether information regarding the degree of the emergency situation is more accurate than the degree of the emergency situation, and determines whether the information regarding the degree of the emergency situation is accurate. the control unit of the meter device determines the duration time or the emergency interruption period using the information regarding the degree of the emergency situation. .

各メータ装置の設置状態等によって、センサが十分な精度で測定を行えない場合もある。このような場合に、メータ装置は非常事態の程度に関する情報を用いて継続時間又は非常時間欠周期を決定できるので、決定された継続時間又は非常時間欠周期が適切なものとなる。 Depending on the installation status of each meter device, the sensor may not be able to measure with sufficient accuracy. In such a case, the meter device can determine the duration or emergency interruption period using information regarding the degree of the emergency, so that the determined duration or emergency interruption period is appropriate.

本発明の第5態様は、サーバからの指令を受信するためのメータ装置の指令受信方法であって、電気、ガス、および水の少なくとも何れかの使用量を他のメータ装置又はメータネットワーク上の無線機能付き装置に送るために、前記メータ装置の無線通信部に、前記他のメータ装置又は前記無線機能付き装置に対する所定の間欠周期での通信要求の送信又は前記所定の間欠周期での同期要求の送信を行わせる通常通信ステップと、非常事態を検出するセンサからの信号又は前記非常事態を通知する信号を前記メータ装置が受付けた時に、前記無線通信部を、前記他のメータ装置又は前記無線機能付き装置に対して前記所定の間欠周期よりも短い非常時間欠周期で通信要求を送信する状態、又は、前記非常時間欠周期での受信が可能な状態とする非常時通信ステップと、を有する。 A fifth aspect of the present invention is a command receiving method of a meter device for receiving a command from a server, the method comprising: determining the usage amount of at least one of electricity, gas, and water on another meter device or a meter network. Sending a communication request to the other meter device or the device with wireless function at a predetermined intermittent cycle, or a synchronization request at the predetermined intermittent cycle, to the wireless communication unit of the meter device in order to send it to the device with wireless function. and when the meter device receives a signal from a sensor detecting an emergency situation or a signal notifying the emergency situation, the wireless communication unit is connected to the other meter device or the wireless communication unit. an emergency communication step of transmitting a communication request to the functional device at an emergency intermittent period shorter than the predetermined intermittent period, or enabling reception at the emergency intermittent period; .

本発明の第6態様は、サーバからの指令を受信するためのメータ装置の指令受信方法であって、電気、ガス、および水の少なくとも何れかの使用量を他のメータ装置又はメータネットワーク上の無線機能付き装置に送るために、前記メータ装置の無線通信部に間欠的な受信を行わせる通常通信ステップと、非常事態を検出するセンサからの信号又は前記非常事態を通知する信号に応じて、前記間欠的な受信の合間の寝ている状態の前記無線通信部を、前記他のメータ装置又は前記無線機能付き装置との通信のために起動させる非常時通信ステップと、を有する。 A sixth aspect of the present invention is a command receiving method of a meter device for receiving a command from a server, the method comprising: determining the usage amount of at least one of electricity, gas, and water on another meter device or a meter network. a normal communication step of causing the wireless communication unit of the meter device to perform intermittent reception in order to send the signal to a device with a wireless function, and a signal from a sensor that detects an emergency situation or a signal that notifies the emergency situation, and an emergency communication step of activating the wireless communication unit, which is in a sleeping state between the intermittent receptions, for communication with the other meter device or the device with wireless function.

本発明の一実施形態のメータシステムの概略構成を示す図である。1 is a diagram showing a schematic configuration of a meter system according to an embodiment of the present invention. 本実施形態のメータ装置の制御部のブロック図である。It is a block diagram of the control part of the meter device of this embodiment. 本実施形態のメータシステムの動作の例を示すタイムチャートである。It is a time chart showing an example of the operation of the meter system of this embodiment. 本実施形態のメータシステムの動作の例を示すタイムチャートである。It is a time chart showing an example of the operation of the meter system of this embodiment. 本実施形態のメータシステムの動作の例を示すタイムチャートである。It is a time chart showing an example of the operation of the meter system of this embodiment. 本実施形態のメータシステムの動作の例を示すタイムチャートである。It is a time chart showing an example of the operation of the meter system of this embodiment. 本実施形態のメータシステムの動作の例を示すタイムチャートである。It is a time chart showing an example of the operation of the meter system of this embodiment. 本実施形態のメータシステムの動作の例を示すタイムチャートである。It is a time chart showing an example of the operation of the meter system of this embodiment.

本発明の一実施形態に係るメータシステムについて、図面を用いながら以下説明する。
本実施形態のメータシステムは、図1に示されるように、ガス事業者、水道事業者、電気事業者等の事業者が有するサーバ(無線機能付き装置)100と、アクセスポイントである複数の中継装置(無線機能付き装置)110と、各中継装置110に対してデータ通信の下流側に配置された複数のメータ装置10a,10b,10c,・・・10nと、を備えている。図1は複数のメータ装置10a~10n、中継装置110、およびサーバ100を有するメータネットワークとも言える。
A meter system according to an embodiment of the present invention will be described below with reference to the drawings.
As shown in FIG. 1, the meter system of this embodiment includes a server (a device with a wireless function) 100 owned by a gas company, a water company, an electric company, etc., and a plurality of relays that are access points. The device includes a device (a device with a wireless function) 110, and a plurality of meter devices 10a, 10b, 10c, . FIG. 1 can also be said to be a meter network having a plurality of meter devices 10a to 10n, a relay device 110, and a server 100.

サーバ100は、CPU等のプロセッサ101と、サーバ100の設定、メニュー等を表示する表示部102と、不揮発性ストレージ、ROM、RAM等を有する記憶部103と、キーボード等を有する入力部104と、無線通信部105とを有する。記憶部103には緊急指令を送信するための緊急指令送信プログラム103aが格納されている。サーバ100は事業者が有する所定の電源装置に接続されている。 The server 100 includes a processor 101 such as a CPU, a display unit 102 that displays settings of the server 100, menus, etc., a storage unit 103 that includes nonvolatile storage, ROM, RAM, etc., and an input unit 104 that includes a keyboard and the like. It has a wireless communication section 105. The storage unit 103 stores an emergency command transmission program 103a for transmitting emergency commands. The server 100 is connected to a predetermined power supply device owned by the operator.

各中継装置110は、CPU等のプロセッサ111と、中継装置110の設定、メニュー等を表示する表示部112と、不揮発性ストレージ、ROM、RAM等を有する記憶部113と、キーボード等を有する入力部114と、無線通信部115とを有する。記憶部103には無線通信プログラム113aが格納されている。中継装置110は例えば電柱等に取付けられ、当該電柱に存在する電線の一つから電力が供給される。表示部112および入力部114は事業者の従業員等が使うものである。 Each relay device 110 includes a processor 111 such as a CPU, a display section 112 that displays the settings of the relay device 110, a menu, etc., a storage section 113 that includes nonvolatile storage, ROM, RAM, etc., and an input section that includes a keyboard and the like. 114 and a wireless communication section 115. A wireless communication program 113a is stored in the storage unit 103. The relay device 110 is attached to, for example, a utility pole, and is supplied with power from one of the electric wires present on the utility pole. The display section 112 and the input section 114 are used by employees of the business.

各メータ装置10a~10nは、電気、ガス、および水の少なくとも何れかの使用量を計る計測部20と、制御部30と、制御部30に有線で接続されており、非常事態を検出するセンサ40とを有する(図2)。計測部20は、流量センサ21と、流量センサ21の検出値を蓄積する蓄積部22と、蓄積部22に蓄積されたデータを制御部30に送信する送信部23とを有する。センサ40は、加速度センサを有する振動計、地震計等であり、地震の発生、震度等を検出することができる。メータ装置10a~10nは、それぞれ住宅、事務所等に取付けられ、住宅、事務所等における電気、ガス、および水の少なくとも何れかの使用量を計測する。 Each of the meter devices 10a to 10n is connected by wire to a measuring section 20 that measures the usage of at least one of electricity, gas, and water, a control section 30, and a sensor that detects an emergency situation. 40 (Figure 2). The measurement section 20 includes a flow rate sensor 21 , an accumulation section 22 that accumulates the detected value of the flow rate sensor 21 , and a transmission section 23 that transmits the data accumulated in the accumulation section 22 to the control section 30 . The sensor 40 is a vibration meter, a seismometer, or the like having an acceleration sensor, and can detect the occurrence of an earthquake, its intensity, and the like. The meter devices 10a to 10n are each installed in a house, an office, etc., and measure the usage amount of at least one of electricity, gas, and water in the house, office, etc.

制御部30は、図2に示されるように、CPU等のプロセッサ31と、メータ装置10a~10nの設定、メニュー等を表示する表示部32と、不揮発性ストレージ、ROM、RAM等を有する記憶部33と、キーボード等を有する入力部34とを有する。本実施形態では、制御部30に無線通信部35が設けられているが、無線通信部35が制御部30とは別に設けられていてもよい。表示部32および入力部34は事業者の従業員等が使うものである。記憶部33には無線通信プログラム33aおよび非常時通信プログラム33bが格納されている。メータ装置10a~10n又は無線通信部35はノードと称される場合もある。 As shown in FIG. 2, the control unit 30 includes a processor 31 such as a CPU, a display unit 32 that displays settings for the meter devices 10a to 10n, menus, etc., and a storage unit that includes nonvolatile storage, ROM, RAM, etc. 33, and an input section 34 having a keyboard or the like. In this embodiment, the wireless communication unit 35 is provided in the control unit 30, but the wireless communication unit 35 may be provided separately from the control unit 30. The display section 32 and the input section 34 are used by employees of the business. The storage unit 33 stores a wireless communication program 33a and an emergency communication program 33b. The meter devices 10a to 10n or the wireless communication unit 35 may also be referred to as nodes.

図1に示されるように、中継装置110のデータ通信の下流側には複数のメータ装置10a~10nが存在する。なお、複数のメータ装置10a~10nがメッシュ状に情報伝達を行ってもよいし、直列に情報伝達を行ってもよく、その他の態様で情報伝達を行ってもよい。 As shown in FIG. 1, a plurality of meter devices 10a to 10n exist on the data communication downstream side of the relay device 110. Note that the plurality of meter devices 10a to 10n may transmit information in a mesh pattern, may transmit information in series, or may transmit information in other manners.

本実施形態の各メータ装置10a~10nの制御部30の動作について図3~図8を参照して説明する。図3~図8において、典型的には、「通信要求」および「同期要求」にかかる時間は1秒未満であり、「応答受信」および「受信可能状態」は2~3秒程度である。制御部30は、センサ40によって所定の大きさ以上の地震(振動)が検出されていない時は、図3、図4、および図6に示される通常通信処理を行い、センサ40によって所定の大きさ以上の地震(振動)が検出されると、図5、図7、および図8に示される非常時通信処理を行う。また、通常通信処理および非常時通信処理の各々には、非同期方式と同期方式がある。 The operation of the control section 30 of each of the meter devices 10a to 10n of this embodiment will be explained with reference to FIGS. 3 to 8. In FIGS. 3 to 8, the time required for "communication request" and "synchronization request" is typically less than 1 second, and the time required for "response reception" and "receivable state" is typically about 2 to 3 seconds. When the sensor 40 does not detect an earthquake (vibration) of a predetermined magnitude or more, the control unit 30 performs the normal communication processing shown in FIGS. When an earthquake (vibration) of a magnitude greater than or equal to 100 is detected, the emergency communication processing shown in FIGS. 5, 7, and 8 is performed. Further, each of the normal communication processing and the emergency communication processing includes an asynchronous method and a synchronous method.

(非同期方式の通常通信処理)
非同期方式の通常通信処理では、図3に示されるように、制御部30のプロセッサ31は、無線通信プログラム33aに基づき、所定の間欠周期Tごとに通信要求を他のメータ装置又は中継装置110に無線通信部35によって送信する。例えば、図1におけるメータ装置(受信ノード)10gはその上流側のメータ装置(送信ノード)10cに所定の間欠周期Tごとに通信要求を送信する。所定の間欠周期Tは数分の場合もあり、数十分の場合もあり、それ以上の場合もあり得る。
(Normal communication processing using asynchronous method)
In the asynchronous normal communication processing, as shown in FIG. 3, the processor 31 of the control unit 30 sends a communication request to another meter device or relay device 110 at every predetermined intermittent period T I based on the wireless communication program 33a. is transmitted by the wireless communication unit 35. For example, the meter device (receiving node) 10g in FIG. 1 transmits a communication request to the upstream meter device (transmitting node) 10c at every predetermined intermittent period TI . The predetermined intermittent period T I may be several minutes, several tens of minutes, or longer.

この時、上位層からのデータ送信要求に従って、上流側のメータ装置10cの制御部30がその無線通信部35をデータ受信モードにした時に、上流側のメータ装置10cの無線通信部35が受信状態となる。この期間に下流側のメータ装置10gから通信要求が送信されると、上流側のメータ装置10cが通信要求を受信し、それに対する応答送信を行う。応答送信には、応答送信から最初のデータ送信までの時間T、データの個数(データ送信の回数)N、データ送信の間隔T等の送信条件データが含まれている。 At this time, when the control section 30 of the upstream meter device 10c puts its wireless communication section 35 into the data reception mode in accordance with the data transmission request from the upper layer, the wireless communication section 35 of the upstream meter device 10c is in the reception state. becomes. When a communication request is sent from the downstream meter device 10g during this period, the upstream meter device 10c receives the communication request and sends a response thereto. The response transmission includes transmission condition data such as the time T 0 from the response transmission to the first data transmission, the number of data (number of data transmissions) N, and the data transmission interval T.

下流側のメータ装置10gは、無線通信プログラム33aに基づき、受取った送信条件データに応じた間欠受信を行い、上流側のメータ装置10cからN個のデータを受信する(図4)。N個のデータの受信が終了すると、下流側のメータ装置10gは、所定の間欠周期Tごとに通信要求を再開する。
なお、上流側のメータ装置10cからのN個のデータの受信が完了した後、メータ装置10gは下流側のメータ装置10l、10mに対して送信ノード若しくは受信ノードになり得る。その他のタイミング、トリガー等に応じてメータ装置10a~10nがデータ受信モードになってもよい。
The downstream meter device 10g performs intermittent reception according to the received transmission condition data based on the wireless communication program 33a, and receives N pieces of data from the upstream meter device 10c (FIG. 4). When the reception of the N pieces of data is completed, the downstream meter device 10g restarts the communication request at every predetermined intermittent period TI .
Note that after the reception of N pieces of data from the upstream meter device 10c is completed, the meter device 10g can become a transmitting node or a receiving node for the downstream meter devices 10l and 10m. The meter devices 10a to 10n may enter the data reception mode depending on other timings, triggers, etc.

一方、下流側のメータ装置10gから上流側のメータ装置10cにN個のデータが送信される場合もある。この場合、例えば応答送信の後に、下流側のメータ装置10gから上流側のメータ装置10cに、応答送信から最初のデータ送信までの時間T、データの個数(データ送信の回数)N、データ送信の間隔T等の送信条件データが送信され、送信条件データに応じたデータ送信が行われる。当該データ送信では、計測部20に蓄積された使用量のデータ等が送信される。 On the other hand, N pieces of data may be transmitted from the downstream meter device 10g to the upstream meter device 10c. In this case, for example, after sending a response, the meter device 10g on the downstream side sends the data to the meter device 10c on the upstream side, including the time T 0 from the response sending to the first data transmission, the number of data pieces (number of data transmissions) N, and the data transmission. Transmission condition data such as the interval T is transmitted, and data transmission is performed according to the transmission condition data. In the data transmission, the usage data accumulated in the measurement unit 20 and the like are transmitted.

(同期方式の通常通信処理)
同期方式の通常通信処理では、図6に示されるように、制御部30のプロセッサ31は、無線通信プログラム33aに基づき、所定の間欠周期Tでの同期要求を中継装置110又は他のメータ装置に無線通信部35によって送信する。例えば、図1におけるメータ装置(受信ノード)10cは、その上流側の中継装置(送信ノード)110に送信する同期要求に、同期の確立およびその継続のために、データの同期送受信のタイミングを示す所定の間欠周期Tのデータを含める。所定の間欠周期Tは数分の場合もあり、数十分の場合もあり、それ以上の場合もあり得る。本実施形態では、同期要求は中継装置110に送信されるが、データ受信モードを維持できるメータ装置に同期要求が送信されてもよい。
(Normal communication processing using synchronous method)
In the normal communication process of the synchronous method, as shown in FIG. 6, the processor 31 of the control unit 30 sends a synchronization request at a predetermined intermittent period T to the relay device 110 or other meter device based on the wireless communication program 33a. is transmitted by the wireless communication unit 35. For example, the meter device (receiving node) 10c in FIG. 1 indicates the timing of synchronous transmission and reception of data in order to establish and continue synchronization in a synchronization request sent to the upstream relay device (transmission node) 110. Data of a predetermined intermittent period T I is included. The predetermined intermittent period T I may be several minutes, several tens of minutes, or longer. In this embodiment, the synchronization request is sent to the relay device 110, but the synchronization request may be sent to a meter device that can maintain the data reception mode.

この時、上流側の中継装置110は、一例として、その無線通信部115を常にデータ受信モードとしており、中継装置110の無線通信部115が常に受信状態となっている。この状態で下流側のメータ装置10cから同期要求が送信されると、間欠周期Tのデータを用いて同期を確立し、中継装置110は間欠周期Tごとに同期信号を送信し、メータ装置10cは間欠周期Tごとに同期信号を受信する。 At this time, the upstream relay device 110, for example, always has its wireless communication unit 115 in the data reception mode, and the wireless communication unit 115 of the relay device 110 is always in the reception state. When a synchronization request is sent from the meter device 10c on the downstream side in this state, synchronization is established using the data of the intermittent period TI , and the relay device 110 transmits a synchronization signal every intermittent period TI , and the meter device 10c receives a synchronization signal every intermittent period TI .

この状態で、上位層からのデータ送信要求に従って、中継装置110からメータ装置10cへのデータ送信を開始する場合、中継装置110は、同期信号に、その同期信号から最初のデータ送信までの時間T、データの個数(データ送信の回数)N、データ送信の間隔T等の送信条件データを含める。
下流側のメータ装置10cは、無線通信プログラム33aに基づき、受取った送信条件データに応じた間欠受信を行い、上流側の中継装置110からN個のデータを受信する。N個のデータの受信が終了すると、下流側のメータ装置10cは、前記の同期の確立およびその維持を再開する。
In this state, when starting data transmission from the relay device 110 to the meter device 10c in accordance with a data transmission request from the upper layer, the relay device 110 includes a synchronization signal with a time T from the synchronization signal to the first data transmission. 0 , the number of data (number of data transmissions) N, and the data transmission interval T.
The meter device 10c on the downstream side performs intermittent reception according to the received transmission condition data based on the wireless communication program 33a, and receives N pieces of data from the relay device 110 on the upstream side. When the reception of the N pieces of data is completed, the downstream meter device 10c resumes establishing and maintaining the synchronization described above.

また、下流側のメータ装置10cから上流側の中継装置110にN個のデータが送信される場合もある。この場合、例えば同期要求に、同期要求から最初のデータ送信までの時間T、データの個数(データ送信の回数)N、データ送信の間隔T等の送信条件データが含まれており、送信条件データに応じたデータ送信が行われる。当該データ送信では、計測部20に蓄積された使用量のデータ等が送信される。なお、中継装置110が連続受信可能な状態である場合は、送信側は任意のタイミングでデータ送信を行うことができるので、T、N、T等のパラメータを送信せずにデータ送信が開始されてもよい。 Further, N pieces of data may be transmitted from the meter device 10c on the downstream side to the relay device 110 on the upstream side. In this case, for example, the synchronization request includes transmission condition data such as the time T 0 from the synchronization request to the first data transmission, the number of data (number of data transmissions) N, and the data transmission interval T, and the transmission conditions Data transmission is performed according to the data. In the data transmission, the usage data accumulated in the measurement unit 20 and the like are transmitted. Note that when the relay device 110 is in a state where continuous reception is possible, the transmitting side can transmit data at any timing, so data transmission can be started without transmitting parameters such as T 0 , N, T, etc. may be done.

(非同期方式の非常時通信処理)
非同期方式の非常時通信処理では、図5に示されるように、通常通信処理中にセンサ40から制御部30に地震の発生を示す信号が送信されると、制御部(通信上位層)30は、無線通信部(通信下位層)35に、非常時通信の開始を要求する。
具体的に、先ず、制御部30および無線通信部35が寝ている状態であっても、地震の発生を示す信号が制御部30に送信されると、当該信号によって制御部30が起動される。当該信号によって制御部30内の起動用の半導体スイッチがONになるように構成されていてもよい。
(Asynchronous emergency communication processing)
In the asynchronous emergency communication process, as shown in FIG. , requests the wireless communication unit (lower communication layer) 35 to start emergency communication.
Specifically, first, even if the control unit 30 and the wireless communication unit 35 are asleep, when a signal indicating the occurrence of an earthquake is transmitted to the control unit 30, the control unit 30 is activated by the signal. . It may be configured such that a semiconductor switch for starting in the control unit 30 is turned on by the signal.

続いて、制御部30のプロセッサ31は、非常時通信プログラム33bに基づき、間欠周期Tよりも短い非常時間欠周期TIeでの通信要求を開始する。例えば、地震の発生を示す信号を受信してから非常時通信開始時間(待機時間)Tが経過した後、メータ装置10gはその上流側のメータ装置10cに非常時間欠周期TIeごとに通信要求を送信する。一例では、非常時通信開始時間Tは、地震の発生を示す信号を受信した時に、制御部30内で生成される乱数を用いて、一定の時間内でランダムに決定される。なお、制御部30の各々に予め設定されている値に基づいて、隣接するメータ装置と異なる非常時通信開始時間Tをプロセッサ31が決定してもよい。予め設定されている値としてメータ装置のID等が用いられる場合もある。 Subsequently, the processor 31 of the control unit 30 starts a communication request in the emergency intermittent period T Ie , which is shorter than the intermittent period T I , based on the emergency communication program 33b. For example, after the emergency communication start time (standby time) Tr has elapsed after receiving a signal indicating the occurrence of an earthquake, the meter device 10g communicates with the upstream meter device 10c every emergency interruption period T Ie. Submit your request. In one example, the emergency communication start time T r is randomly determined within a certain period of time using a random number generated within the control unit 30 when a signal indicating the occurrence of an earthquake is received. Note that the processor 31 may determine an emergency communication start time T r that is different from that of an adjacent meter device based on a value preset in each of the control units 30 . The ID of the meter device or the like may be used as the preset value.

プロセッサ31は、非常時通信プログラム33bに基づき、前記一定の時間の長さを隣接ノードの数に応じて変化させる。具体的には、隣接ノードの数が多いほど前記一定の時間を長くする。隣接ノードは対象(メータ装置10g)の周囲に存在する他のメータ装置である。これにより、隣接ノードが多い場合でも、非常時間欠周期TIeでの通信要求が隣接ノードのそれと干渉する可能性が低減される。
また、プロセッサ31は、通常通信処理の受信状態の時に、受信する隣接ノードからの信号に基づいて隣接ノードの数を推定する。例えば、飛来する信号に含まれる送信元ノードの識別子に基づいて、隣接ノードの数の推定が行われる。
後述の同期方式の非常時通信処理でも、同様に隣接ノードの数が推定される。
The processor 31 changes the length of the certain period of time according to the number of adjacent nodes based on the emergency communication program 33b. Specifically, the greater the number of adjacent nodes, the longer the predetermined time period is. Adjacent nodes are other meter devices existing around the target (meter device 10g). Thereby, even if there are many adjacent nodes, the possibility that a communication request in the emergency interruption period T Ie will interfere with that of the adjacent nodes is reduced.
Further, the processor 31 estimates the number of adjacent nodes based on signals received from the adjacent nodes during the reception state of normal communication processing. For example, the number of adjacent nodes is estimated based on the source node identifier included in the incoming signal.
In the synchronous emergency communication process described later, the number of adjacent nodes is similarly estimated.

非常時間欠周期TIeは典型的には数秒であるが、1秒以下の場合もあり、数秒の場合もあり、数十秒分の場合もあり、それ以上の場合もあり得る。また、非常時間欠周期TIeごとの通信要求は非常時間欠通信区間(継続時間)Tだけ継続される。非常時間欠通信区間Tは十数秒の場合もあり、数分の場合もあり、それ以外の場合もあり得る。 The emergency interruption period T Ie is typically several seconds, but may be less than one second, several seconds, several tens of seconds, or longer. Furthermore, the communication request for each emergency interruption period T Ie is continued for an emergency interruption communication period (duration time) Te . The emergency communication period T e may be several tens of seconds, several minutes, or other times.

一例では、非常時間欠周期Tleごとの通信要求が開始された後間もなく、上位層からのデータ送信要求に従って、上流側のメータ装置10cの制御部30は、その無線通信部35をデータ受信モードにする。これは、サーバ100のプロセッサ101が、緊急指令送信プログラム103aに基づき、各中継装置110を介して各メータ装置10a~10nに向かって緊急指令を伝達したことに基づく。 In one example, soon after a communication request is started for each emergency interruption period T le , the control unit 30 of the upstream meter device 10c sets the wireless communication unit 35 to the data reception mode in accordance with a data transmission request from an upper layer. Make it. This is based on the fact that the processor 101 of the server 100 transmits the emergency command to each of the meter devices 10a to 10n via each relay device 110 based on the emergency command transmission program 103a.

この期間に下流側のメータ装置10gから通信要求が送信されると、上流側のメータ装置10cが通信要求を受信し、それに対する応答送信を行う。応答送信には、応答送信から最初のデータ送信までの時間T、データの個数(データ送信の回数)N、データ送信の間隔T等の送信条件データが含まれている。 When a communication request is sent from the downstream meter device 10g during this period, the upstream meter device 10c receives the communication request and sends a response thereto. The response transmission includes transmission condition data such as the time T 0 from the response transmission to the first data transmission, the number of data (number of data transmissions) N, and the data transmission interval T.

下流側のメータ装置10gは、無線通信プログラム33aに基づき、受取った送信条件データに応じた間欠受信を行い、上流側のメータ装置10cからN個のデータを受信する。N個のデータ、つまり緊急指令の受信が終了すると、下流側のメータ装置10gの制御部30のプロセッサ31は、緊急指令に応じた処理を行う。例えば、緊急指令が閉栓指令である場合、プロセッサ31はメータ装置10g内のバルブを閉鎖する処理を行う。そして、下流側のメータ装置10gは、所定の間欠周期Tごとの通信要求を再開する。 The downstream meter device 10g performs intermittent reception according to the received transmission condition data based on the wireless communication program 33a, and receives N pieces of data from the upstream meter device 10c. When the reception of the N pieces of data, that is, the emergency command, is completed, the processor 31 of the control unit 30 of the meter device 10g on the downstream side performs processing according to the emergency command. For example, when the emergency command is a stopper command, the processor 31 performs processing to close the valve in the meter device 10g. Then, the downstream meter device 10g restarts the communication request at every predetermined intermittent period TI .

なお、上流側のメータ装置10cからのN個のデータの受信が完了した時に、通常通信処理の場合と同様に、メータ装置10gが下流側のメータ装置10l、10mからデータを間欠受信可能なデータ受信モードになる。その他のタイミング、トリガー等に応じてメータ装置10a~10nがデータ受信モードになってもよい。 Note that when the reception of N pieces of data from the upstream meter device 10c is completed, the meter device 10g can receive data intermittently from the downstream meter devices 10l and 10m, as in the case of normal communication processing. Enters reception mode. The meter devices 10a to 10n may enter the data reception mode depending on other timings, triggers, etc.

(同期方式の非常時通信処理)
同期方式の非常時通信処理では、図7に示されるように、通常通信処理中にセンサ40から制御部30に地震の発生を示す信号が送信されると、制御部(通信上位層)30は、無線通信部(通信下位層)35に、非常時通信の開始を要求する。
非同期方式の場合と同様に、先ず、制御部30および無線通信部35が寝ている状態であっても、地震の発生を示す信号が制御部30に送信されると、当該信号によって制御部30が起動される。当該信号によって制御部30内の起動用の半導体スイッチがONになるように構成されていてもよい。
(Synchronous emergency communication processing)
In the synchronous emergency communication process, as shown in FIG. 7, when a signal indicating the occurrence of an earthquake is transmitted from the sensor 40 to the control unit 30 during normal communication processing, the control unit (communication upper layer) 30 , requests the wireless communication unit (lower communication layer) 35 to start emergency communication.
As in the case of the asynchronous method, first, even if the control unit 30 and the wireless communication unit 35 are asleep, when a signal indicating the occurrence of an earthquake is transmitted to the control unit 30, the signal causes the control unit 30 to is started. The signal may be configured to turn on a semiconductor switch for activation within the control unit 30.

続いて、制御部30のプロセッサ31は、非常時通信プログラム33bに基づき、間欠周期Tよりも短い非常時間欠周期Tleでの同期要求を中継装置110又は他のメータ装置に送信する。例えば、図1におけるメータ装置10cは、その上流側の中継装置110に同期要求を送信する。同期要求には、中継装置110から送信される同期応答から非常時間欠周期Tleでの受信の開始までの時間である非常時通信開始時間T、受信のタイミングを示す非常時間欠周期TIe、および同期の継続時間である非常時間欠通信区間(継続時間)Tを示すデータが含まれている。この場合、地震の発生を示す信号を受信してから非常時間欠周期Tleでの受信の開始までの待機時間は、非常時通信開始時間Tに同期応答の送受信の時間を加えた時間となる。 Subsequently, the processor 31 of the control unit 30 transmits a synchronization request at the emergency intermittent period T le shorter than the intermittent period T I to the relay device 110 or other meter device based on the emergency communication program 33b. For example, the meter device 10c in FIG. 1 transmits a synchronization request to the relay device 110 on the upstream side thereof. The synchronization request includes an emergency communication start time T r which is the time from the synchronization response transmitted from the relay device 110 to the start of reception at the emergency interruption period T le , and an emergency communication start time T Ie indicating the reception timing. , and data indicating the emergency interrupted communication period (duration time) T e which is the duration of synchronization. In this case, the waiting time from receiving the signal indicating the occurrence of an earthquake to the start of reception in the emergency interruption period Tle is the time equal to the emergency communication start time Tr plus the time for sending and receiving the synchronous response. Become.

一例では、非常時通信開始時間Tは、地震の発生を示す信号を受信した時に、制御部30内で生成される乱数を用いて、一定の時間内でランダムに決定される。プロセッサ31は、非常時通信プログラム33bに基づき、前記一定の時間の長さを隣接ノードの数に応じて変化させる。 In one example, the emergency communication start time T r is randomly determined within a certain period of time using a random number generated within the control unit 30 when a signal indicating the occurrence of an earthquake is received. The processor 31 changes the length of the certain period of time according to the number of adjacent nodes based on the emergency communication program 33b.

これにより、非常時間欠周期TIeのデータを用いて同期が確立され、中継装置110は非常時間欠周期TIeごと、又は、非常時間欠周期TIeの整数倍の周期ごとに同期信号を送信し、メータ装置10cは非常時間欠周期TIeごとに受信が可能な状態となる。
本実施形態では、メータ装置10cから中継装置110に同期要求が送信されるが、常にデータ受信モードを維持できる他のメータ装置に同期要求が送信されてもよい。
As a result, synchronization is established using the data of the emergency interruption period T Ie , and the relay device 110 transmits a synchronization signal every emergency interruption period T Ie or every cycle that is an integral multiple of the emergency interruption period T Ie . However, the meter device 10c becomes ready for reception every emergency interruption period T Ie .
In this embodiment, the synchronization request is sent from the meter device 10c to the relay device 110, but the synchronization request may be sent to another meter device that can always maintain the data reception mode.

一例では、非常時通信開始時間Tは、地震の発生を示す信号を受信した時に、制御部30内で生成される乱数を用いて、一定の時間内でランダムに決定される。この時、プロセッサ31は、非常時通信プログラム33bに基づき、前記一定の時間の長さを隣接ノードの数に応じて変化させる。なお、制御部30の各々に予め設定されている値に基づいて、隣接するメータ装置と異なる非常時通信開始時間Tをプロセッサ31が決定してもよい。予め設定されている値としてメータ装置のID等が用いられる場合もある。非常時間欠周期TIeは典型的には数秒であるが、1秒以下の場合もあり、数十秒分の場合もあり、それ以上の場合もあり得る。また、非常時間欠通信区間Tは十数秒の場合もあり、数分の場合もあり、それ以外の場合もあり得る。なお、他の例では、非常時通信開始時間Tがメータ装置10a~10nのそれぞれに予め設定されており、非常時通信開始時間Tが複数種類存在していてもよい。 In one example, the emergency communication start time T r is randomly determined within a certain period of time using a random number generated within the control unit 30 when a signal indicating the occurrence of an earthquake is received. At this time, the processor 31 changes the length of the certain time according to the number of adjacent nodes based on the emergency communication program 33b. Note that the processor 31 may determine an emergency communication start time T r that is different from that of an adjacent meter device based on a value preset in each of the control units 30 . The ID of the meter device or the like may be used as the preset value. The emergency interruption period T Ie is typically several seconds, but it may be less than one second, it may be several tens of seconds, or it may be longer. Further, the emergency communication period T e may be several tens of seconds, several minutes, or other times. In another example, the emergency communication start time T r is set in advance for each of the meter devices 10a to 10n, and a plurality of types of emergency communication start times T r may exist.

一例では、非常時間欠周期Tleごとの通信要求が開始された後間もなく、上流側の中継装置110は、緊急指令を下流側のメータ装置10cに送信するモードとなる。これは、サーバ100のプロセッサ101が、緊急指令送信プログラム103aに基づき、各中継装置110を介して各メータ装置10a~10nに向かって緊急指令を伝達したことに基づく。 In one example, shortly after a communication request is started for each emergency interruption period T le , the relay device 110 on the upstream side enters a mode for transmitting an emergency command to the meter device 10c on the downstream side. This is based on the fact that the processor 101 of the server 100 transmits the emergency command to each of the meter devices 10a to 10n via each relay device 110 based on the emergency command transmission program 103a.

上位層からのデータ送信要求に従って、中継装置110からメータ装置10cへのデータ送信を開始する場合、中継装置110は、同期信号に、その同期信号から最初のデータ送信までの時間T、データの個数(データ送信の回数)N、データ送信の間隔T等の送信条件データを含める。
下流側のメータ装置10cは、無線通信プログラム33aに基づき、受取った送信条件データに応じた間欠受信を行い、上流側の中継装置110からN個のデータを受信する。N個のデータ、つまり緊急指令の受信が終了すると、下流側のメータ装置10cの制御部30のプロセッサ31は、緊急指令に応じた処理を行う。例えば、緊急指令が閉栓指令である場合、プロセッサ31はメータ装置10g内のバルブを閉鎖する処理を行う。そして、下流側のメータ装置10cは、通常通信処理の同期の確立およびその維持を再開する。
When starting data transmission from the relay device 110 to the meter device 10c in accordance with a data transmission request from an upper layer, the relay device 110 adds the time T 0 from the synchronization signal to the first data transmission to the synchronization signal, and the time T 0 of the data. It includes transmission condition data such as the number (number of data transmissions) N, data transmission interval T, etc.
The meter device 10c on the downstream side performs intermittent reception according to the received transmission condition data based on the wireless communication program 33a, and receives N pieces of data from the relay device 110 on the upstream side. When the reception of the N pieces of data, that is, the emergency command, is completed, the processor 31 of the control unit 30 of the meter device 10c on the downstream side performs processing according to the emergency command. For example, when the emergency command is a stopper command, the processor 31 performs processing to close the valve in the meter device 10g. The downstream meter device 10c then resumes establishing and maintaining the synchronization of the normal communication process.

なお、上流側の中継装置110からのN個のデータの受信が完了した時に、通常通信処理の場合と同様に、メータ装置10cが下流側のメータ装置10g、10hからのデータ受信モードになる。その他のタイミング、トリガー等に応じてメータ装置10a~10nがデータ受信モードになってもよい。 Note that when the reception of N pieces of data from the upstream relay device 110 is completed, the meter device 10c enters the data reception mode from the downstream meter devices 10g and 10h, as in the case of normal communication processing. The meter devices 10a to 10n may enter the data reception mode depending on other timings, triggers, etc.

このように、本実施形態では、非常事態を検出するセンサ40からの信号を受付けると、制御部30が、無線通信部35を、他のメータ装置又は中継装置110に対して、所定の間欠周期Tよりも短い非常時間欠周期TIeで通信要求を送信する状態、又は、非常時間欠周期TIeでの受信が可能な状態とする。 As described above, in this embodiment, upon receiving a signal from the sensor 40 that detects an emergency situation, the control unit 30 transmits the wireless communication unit 35 to another meter device or the relay device 110 at a predetermined intermittent cycle. A state is set in which a communication request is transmitted in an emergency interruption period T Ie shorter than T I , or a state in which it is possible to receive a communication request in an emergency interruption period T Ie .

例えば、各メータ装置10a~10nが、通常通信処理において、その無線通信部を10分に1回、数十分に1回等のタイミングで数秒間だけ起動するものであっても、非常事態を検出するセンサ40からの信号を受付けた後は、短い非常時間欠周期TIeで通信要求の送信が行われ、又は、短い非常時間欠周期TIeで受信可能な状態となる。
このため、管理センタのサーバ100、中継装置110等の無線機能付き装置、サーバ100から緊急指令を受付けた他のメータ装置等から、各メータ装置10a~10nが緊急指令を迅速に受信することが可能となる。
For example, even if each meter device 10a to 10n activates its wireless communication section for only a few seconds at a timing such as once every 10 minutes or once every several tens of minutes during normal communication processing, it is possible to prevent emergency situations. After receiving the signal from the sensor 40 to be detected, a communication request is transmitted in a short emergency interruption period T Ie , or becomes ready to be received in a short emergency interruption period T Ie .
Therefore, each of the meter devices 10a to 10n can quickly receive emergency commands from the management center server 100, devices with wireless functions such as the relay device 110, and other meter devices that have received emergency commands from the server 100. It becomes possible.

また、本実施形態では、制御部30が、隣接ノード(隣接する他のメータ装置)の数を推定する数推定処理を行い、制御部30が、推定された前記数を用いて、センサ40からの信号を受付けてから非常時間欠周期TIeでの通信要求の送信の開始までの非常時通信開始時間(待機時間)T、又は、センサ40からの信号を受付けてから非常時間欠周期TIeでの受信を開始するまでの待機時間を変化させる。
このため、隣接ノードが多い場合でも、非常時間欠周期TIeでの通信要求が隣接ノードのそれと干渉する可能性が低減される。
なお、センサ40からの信号に応じた非常事態の程度に更に基づいて前記待機時間を変化させてもよい。
Further, in this embodiment, the control unit 30 performs a number estimation process to estimate the number of adjacent nodes (other adjacent meter devices), and the control unit 30 uses the estimated number to Emergency communication start time (standby time) T r from reception of the signal from the reception of the signal from the emergency interruption period T Ie to the start of transmission of the communication request, or from reception of the signal from the sensor 40 to the emergency interruption period T Change the waiting time until starting reception on Ie .
Therefore, even if there are many adjacent nodes, the possibility that a communication request in the emergency interruption period T Ie will interfere with that of the adjacent nodes is reduced.
Note that the waiting time may be changed further based on the degree of emergency according to the signal from the sensor 40.

また、本実施形態では、制御部30が、通信要求の送信又は同期要求の送信の後の間欠的な受信可能状態時に検出した信号の数を用いて、隣接ノードの数を推定する。
このため、非常時に隣接ノードの数を推定するためのデータを集める場合と比較し、非常時の処理が速くなる。これは、緊急指令を速く確実に各メータ装置10a~10nに送信する上で有利である。
Further, in the present embodiment, the control unit 30 estimates the number of adjacent nodes using the number of signals detected during an intermittent receivable state after transmission of a communication request or transmission of a synchronization request.
Therefore, compared to collecting data for estimating the number of adjacent nodes in an emergency, processing in an emergency becomes faster. This is advantageous in quickly and reliably transmitting the emergency command to each meter device 10a to 10n.

なお、制御部30が、センサ40からの信号又は非常事態を通知する信号に応じた非常事態の程度に基づき、非常時間欠周期TIeでの通信要求の送信又は非常時間欠周期TIeで受信が可能な状態を継続する継続時間(非常時間欠通信区間T)を決定してもよい。
例えば、センサ40から送信される震度が大きい場合、非常事態の規模が大きい場合、非常事態による影響が大きい場合等は、制御部30は継続時間(非常時間欠通信区間T)を長くする。これは、緊急指令を確実に各メータ装置10a~10nに送信する上で有利である。なお、制御部30は、サーバ100、中継装置110、他のメータ装置、家屋又は事務所内の災害情報受信装置等から、非常事態の発生および規模を示す情報、非常事態の発生およびその影響を示す情報等を受信するものとし、以下同様である。災害情報受信装置は、有線又は無線によって、地震直前の警報、地震情報、火災情報、水害情報、その他の災害情報を公的機関等から受信するものである。
Note that the control unit 30 transmits the communication request in the emergency interruption period T Ie or receives it in the emergency interruption period T Ie based on the degree of the emergency situation according to the signal from the sensor 40 or the signal notifying the emergency situation. It is also possible to determine the duration time during which the state in which the communication is possible continues (the emergency interrupted communication section T e ).
For example, when the seismic intensity transmitted from the sensor 40 is large, when the scale of the emergency situation is large, when the influence of the emergency situation is large, etc., the control unit 30 lengthens the duration (emergency interruption communication section T e ). This is advantageous in ensuring that the emergency command is sent to each meter device 10a-10n. Note that the control unit 30 receives information indicating the occurrence and scale of an emergency situation, the occurrence of an emergency situation, and its effects from the server 100, the relay device 110, other meter devices, disaster information receiving devices in a house or office, etc. Information etc. shall be received, and the same shall apply hereinafter. The disaster information receiving device receives warnings immediately before an earthquake, earthquake information, fire information, flood damage information, and other disaster information from public institutions, etc., by wire or wirelessly.

また、制御部30が、センサ40からの信号又は非常事態を通知する信号に応じた非常事態の程度に基づき、非常時間欠周期TIeを決定してもよい。
例えば、センサ40から送信される震度(非常事態の程度)が大きい場合、非常事態の規模(非常事態の程度)が大きい場合、非常事態による影響(非常事態の程度)が大きい場合等は、非常時間欠周期TIeを短くする。これは、重要度が高い緊急指令を迅速に各メータ装置10a~10nに送信するために有利である。一例では、センサ40から送信される震度が大きい場合、緊急指令は閉栓指令となり、センサ40から送信される震度が小さい場合、緊急指令はメータ装置10a~10nの各センサの検出値等のサーバ100への送信等となる。震度が大きい場合、緊急指令は各メータ装置10a~10nにより早く伝達されることになる。
Further, the control unit 30 may determine the emergency interruption period T Ie based on the degree of the emergency situation according to the signal from the sensor 40 or the signal notifying the emergency situation.
For example, if the seismic intensity (degree of emergency situation) transmitted from the sensor 40 is large, the scale of the emergency situation (degree of emergency situation) is large, or the impact of the emergency situation (degree of emergency situation) is large, etc. Shorten the interruption period T Ie . This is advantageous for quickly transmitting emergency commands of high importance to each of the meter devices 10a to 10n. In one example, when the seismic intensity transmitted from the sensor 40 is large, the emergency command is a closure command, and when the seismic intensity transmitted from the sensor 40 is small, the emergency command is sent to the server 100 such as the detection value of each sensor of the meter devices 10a to 10n. etc. If the seismic intensity is large, the emergency command will be transmitted to each of the meter devices 10a to 10n more quickly.

なお、中継装置110から受信する震度情報(非常事態の程度に関する情報)I’に基づき待機時間の変更、継続時間(非常時間欠通信区間T)の変更、又は非常時間欠周期TIeの変更を行うことも可能である。メータ装置10a~10nの設置状態等によって、センサ40が十分な精度で震度を測定できない場合もあり、このような場合に震度情報I’が有用となる。 In addition, based on the seismic intensity information (information regarding the degree of emergency situation) I' received from the relay device 110, the standby time, the duration time (emergency interruption communication section T e ), or the emergency interruption period T Ie can be changed. It is also possible to do this. Depending on the installation conditions of the meter devices 10a to 10n, the sensor 40 may not be able to measure the seismic intensity with sufficient accuracy, and in such cases, the seismic intensity information I' becomes useful.

中継装置110がサーバ100等から公的機関等で測定された震度情報I’を受信する場合、中継装置110は例えばその下流のメータ装置10a,10b,10cに震度情報I’を送信することができる。
または、各メータ装置10a,10b,10cから中継装置110にセンサ40の測定結果が送信され、中継装置110が受信した測定結果に基づき震度情報I’が作成される場合、中継装置110はその下流のメータ装置10a,10b,10cに震度情報I’を送信することができる。
When the relay device 110 receives seismic intensity information I' measured by a public institution etc. from the server 100 etc., the relay device 110 may transmit the seismic intensity information I' to the downstream meter devices 10a, 10b, 10c, for example. can.
Alternatively, when the measurement results of the sensor 40 are transmitted from each meter device 10a, 10b, 10c to the relay device 110, and seismic intensity information I' is created based on the measurement results received by the relay device 110, the relay device 110 is The seismic intensity information I' can be transmitted to the meter devices 10a, 10b, and 10c.

このように構成すると、受信ノードであるメータ装置10a,10b,10cを共通且つ高い精度で作動させることが可能となる。このように中継装置110が震度情報I’を下流側のメータ装置10a,10b,10cに送信する構成を「集中制御型」と称することが可能である。一方、メータ装置10a,10b,10cが各々のセンサ40で検出された震度Iを用いる構成を「自立制御型」と称することができる。 With this configuration, it becomes possible to operate the meter devices 10a, 10b, and 10c, which are receiving nodes, in common and with high accuracy. The configuration in which the relay device 110 transmits seismic intensity information I' to the downstream meter devices 10a, 10b, and 10c in this manner can be referred to as a "centralized control type." On the other hand, a configuration in which the meter devices 10a, 10b, and 10c use the seismic intensity I detected by each sensor 40 can be referred to as an "independent control type."

同期方式の非常時通信処理を示す図8の例を以下説明する。図8は前述の集中制御型の一例を示している。
先ず、通常通信処理中にセンサ40から制御部30に地震の発生を示す信号が送信されると、メータ装置10cの制御部(通信上位層)30は、無線通信部(通信下位層)35に、非常時通信の開始を要求する。
The example of FIG. 8 showing synchronous emergency communication processing will be described below. FIG. 8 shows an example of the above-mentioned centralized control type.
First, when a signal indicating the occurrence of an earthquake is transmitted from the sensor 40 to the control unit 30 during normal communication processing, the control unit (communication upper layer) 30 of the meter device 10c sends a signal to the wireless communication unit (communication lower layer) 35. , requesting initiation of emergency communications.

一方、中継装置110はサーバ100から公的機関等の信用できる組織の管理の下で測定された震度情報I’を受信する。
この状態で、メータ装置10cの制御部30のプロセッサ31は、非常時通信プログラム33bに基づき、間欠周期Tよりも短い非常時間欠周期Tleでの同期要求を無線通信部35によって中継装置110に送信する。同期要求には、中継装置110から送信される同期応答から非常時間欠周期Tleでの受信の開始までの時間である非常時通信開始時間T、受信のタイミングを示す非常時間欠周期TIe、同期の継続時間である非常時間欠通信区間(継続時間)T、およびセンサ40で検出された震度Iを示すデータが含まれている。
On the other hand, the relay device 110 receives seismic intensity information I' measured under the management of a trusted organization such as a public institution from the server 100.
In this state, the processor 31 of the control unit 30 of the meter device 10c sends a synchronization request to the relay device 110 via the wireless communication unit 35 at an emergency intermittent period T le shorter than the intermittent period T I based on the emergency communication program 33 b. Send to. The synchronization request includes an emergency communication start time T r which is the time from the synchronization response transmitted from the relay device 110 to the start of reception at the emergency interruption period T le , and an emergency communication start time T Ie indicating the reception timing. , an emergency interruption communication section (duration time) T e which is the duration of synchronization, and data indicating the seismic intensity I detected by the sensor 40.

中継装置110は、メータ装置10cから受信した震度Iと震度情報I’とを比較し、震度情報I’の方が正確であるか否かを判断する。そして、震度情報I’の方が正確であると判断されると、同期応答に震度情報I’を含めて送信する。
メータ装置10cが震度情報I’を受信すると、メータ装置10cの制御部30のプロセッサ31は震度情報I’を用いて上述の計算を再度行い、再計算結果である非常時通信開始時間T’、非常時間欠周期TIe’、および非常時間欠通信区間(継続時間)T’を示すデータを有する同期要求を中継装置110に送信する。当該同期要求に、計算に使用した震度を示すために震度情報I’が含まれていてもよい。
The relay device 110 compares the seismic intensity information I' received from the meter device 10c and determines whether the seismic intensity information I' is more accurate. If the seismic intensity information I' is determined to be more accurate, the seismic intensity information I' is included in the synchronization response and transmitted.
When the meter device 10c receives the seismic intensity information I', the processor 31 of the control unit 30 of the meter device 10c performs the above calculation again using the seismic intensity information I', and calculates the emergency communication start time T r ' as the recalculation result. , an emergency interruption period T Ie ′, and a synchronization request having data indicating an emergency interruption communication interval (duration time) T e ′ is transmitted to the relay device 110 . The synchronization request may include seismic intensity information I' to indicate the seismic intensity used for calculation.

これにより、非常時間欠周期TIe’のデータを用いて同期が確立され、中継装置110は非常時間欠周期TIe’ごと、又は、非常時間欠周期TIe’の整数倍の周期ごとに同期信号を送信し、メータ装置10cは非常時間欠周期TIe’ごとに受信が可能な状態となる。
本実施形態では、メータ装置10cから中継装置110に同期要求が送信されるが、常にデータ受信モードを維持できる他のメータ装置に同期要求が送信されてもよい。この場合、他のメータ装置が震度情報I’を持っている。
As a result, synchronization is established using the data of the emergency interruption period TIe ', and the relay device 110 synchronizes every emergency interruption period TIe ' or every cycle that is an integral multiple of the emergency interruption period TIe '. The signal is transmitted, and the meter device 10c becomes ready to receive the signal every emergency interruption period T Ie '.
In this embodiment, the synchronization request is sent from the meter device 10c to the relay device 110, but the synchronization request may be sent to another meter device that can always maintain the data reception mode. In this case, another meter device has seismic intensity information I'.

また、上記状態において、中継装置110がサーバ100から公的機関等の信用できる組織の管理の下で測定された別の震度情報I’’を受信する場合、中継装置110は、震度情報I’と震度情報I’’とを比較し、震度情報I’’の方が正確であるか否かを判断する。そして、震度情報I’’の方が正確であると判断されると、中継装置110は同期信号に震度情報I’’を含めて送信する。 Further, in the above state, when the relay device 110 receives from the server 100 another seismic intensity information I'' measured under the management of a trusted organization such as a public institution, the relay device 110 receives the seismic intensity information I' and the seismic intensity information I'' to determine whether or not the seismic intensity information I'' is more accurate. If it is determined that the seismic intensity information I'' is more accurate, the relay device 110 transmits the synchronization signal including the seismic intensity information I''.

メータ装置10cが震度情報I’’を受信すると、メータ装置10cの制御部30のプロセッサ31は震度情報I’’を用いて上述の計算を再度行い、再計算結果である非常時通信開始時間T’’、非常時間欠周期TIe’’、および非常時間欠通信区間(継続時間)T’’を示すデータを有する同期要求を中継装置110に送信する。当該同期要求に、計算に使用した震度を示すために、震度情報I’’が含まれていてもよい。 When the meter device 10c receives the seismic intensity information I'', the processor 31 of the control unit 30 of the meter device 10c performs the above calculation again using the seismic intensity information I'', and calculates the emergency communication start time T which is the recalculation result. r '', an emergency interruption period T Ie '', and an emergency interruption communication period (duration time) T e ''. The synchronization request may include seismic intensity information I'' to indicate the seismic intensity used for calculation.

これにより、非常時間欠周期TIe’’のデータを用いて同期が確立され、中継装置110は非常時間欠周期TIe’’ごと、又は、非常時間欠周期TIe’’の整数倍の周期ごとに同期信号を送信し、メータ装置10cは非常時間欠周期TIe’’ごとに受信が可能な状態となる。 As a result, synchronization is established using the data of the emergency interruption period T Ie '', and the relay device 110 performs synchronization every emergency interruption period T Ie '' or at a period that is an integral multiple of the emergency interruption period T Ie ''. A synchronizing signal is transmitted every time, and the meter device 10c becomes ready to receive every emergency interruption period T Ie ''.

なお、上記各実施形態において、前記待機時間、継続時間(非常時間欠通信区間T,T’,T’’)、又は非常時間欠周期TIe,TIe’,TIe’’を中継装置110が計算してもよいし、サーバ100が計算してもよい。
また、上記各実施形態において、サーバ100と各メータ装置10a~10nとが中継装置110を介さずに通信してもよい。この場合、例えばメータ装置10a,10b,10cがサーバ100と上述の方法で通信することになる。
In addition, in each of the above embodiments, the standby time, the duration time (emergency interruption communication period T e , T e ', T e ''), or the emergency interruption period T Ie , T Ie ', T Ie '' The relay device 110 may perform the calculation, or the server 100 may perform the calculation.
Further, in each of the embodiments described above, the server 100 and each of the meter devices 10a to 10n may communicate without using the relay device 110. In this case, for example, the meter devices 10a, 10b, and 10c will communicate with the server 100 in the above-described manner.

また、上記各実施形態において、家屋内に設置された火災報知器からの信号が制御部30に送信された時に、制御部30が無線通信部35に非常時通信の開始を要求してもよい。また、家屋内又は所定の施設に設けられた水害報知器からの信号が制御部30に送信された時に、制御部30が無線通信部35に非常時通信の開始を要求してもよい。 Further, in each of the above embodiments, when a signal from a fire alarm installed in the house is transmitted to the control unit 30, the control unit 30 may request the wireless communication unit 35 to start emergency communication. . Further, when a signal from a flood alarm installed in a house or a predetermined facility is transmitted to the control unit 30, the control unit 30 may request the wireless communication unit 35 to start emergency communication.

上記各実施形態の各メータ装置10a~10nは、電気、ガス、および水の少なくとも何れかの使用量を計る計測部20と、無線通信部35と、制御部30と、を備え、制御部30が、無線通信部35に間欠的な受信を行わせる通常通信処理と、非常事態を検出するセンサ40からの信号又は非常事態を通知する信号を受付けると、間欠的な受信の合間の寝ている状態の無線通信部35を、他のメータ装置又はメータネットワーク上の中継装置110等の無線機能付き装置との通信のために起動させる非常時通信処理と、を行う。 Each of the meter devices 10a to 10n of the above-described embodiments includes a measurement section 20 that measures the usage amount of at least one of electricity, gas, and water, a wireless communication section 35, and a control section 30. However, when the wireless communication unit 35 performs normal communication processing to perform intermittent reception and receives a signal from the sensor 40 that detects an emergency situation or a signal that notifies the emergency situation, it is possible to An emergency communication process is performed in which the wireless communication unit 35 in the state is activated for communication with another meter device or a device with a wireless function such as the relay device 110 on the meter network.

上記各実施形態の各メータ装置10a~10nでは、非常事態を検出するセンサ40からの信号又は非常事態を通知する信号を受付けると、通常通信処理の間欠的な受信の合間の寝ている状態の無線通信部35が、他のメータ装置又はメータネットワーク上の中継装置110等の無線機能付き装置との通信のために起動する。 In each of the meter devices 10a to 10n of the above-described embodiments, when a signal from the sensor 40 that detects an emergency situation or a signal that notifies an emergency situation is received, the meter device 10a to 10n of the meter device 10a to 10n, which is in a sleeping state between intermittent receptions of normal communication processing, The wireless communication unit 35 is activated for communication with other meter devices or devices with wireless functionality such as the relay device 110 on the meter network.

例えば、メータ装置10cが、通常通信処理において、その無線通信部35を10分に1回、数十分に1回等のタイミングで数秒間だけ起動するものであっても、非常事態を検出するセンサ40からの信号又は非常事態を通知する信号を受付けると、上流側の装置との通信のために起動する。このため、管理センタのサーバ100、中継装置110等の無線機能付き装置、サーバ100から緊急指令を受付けた他のメータ装置等から、緊急指令を迅速に受信することが可能となる。 For example, even if the meter device 10c activates its wireless communication unit 35 for only a few seconds at a timing such as once every 10 minutes or once every several tens of minutes during normal communication processing, the meter device 10c can detect an emergency situation. When receiving a signal from the sensor 40 or a signal notifying an emergency situation, it is activated for communication with an upstream device. Therefore, it is possible to quickly receive emergency commands from the server 100 of the management center, devices with wireless functions such as the relay device 110, and other meter devices that have received emergency commands from the server 100.

10a~10n メータ装置
20 計測部
21 流量センサ
22 蓄積部
30 制御部
31 プロセッサ
32 表示部
33 記憶部
33a 無線通信プログラム
33b 非常時通信プログラム
34 入力部
35 無線通信部
100 サーバ(無線機能付き装置)
101 プロセッサ
102 表示部
103 記憶部
103a 緊急指令送信プログラム
104 入力部
105 無線通信部
110 中継装置(無線機能付き装置)
111 プロセッサ
112 表示部
113 記憶部
113a 無線通信プログラム
114 入力部
115 無線通信部
10a to 10n Meter device 20 Measuring unit 21 Flow rate sensor 22 Storage unit 30 Control unit 31 Processor 32 Display unit 33 Storage unit 33a Wireless communication program 33b Emergency communication program 34 Input unit 35 Wireless communication unit 100 Server (device with wireless function)
101 Processor 102 Display unit 103 Storage unit 103a Emergency command transmission program 104 Input unit 105 Wireless communication unit 110 Relay device (device with wireless function)
111 Processor 112 Display unit 113 Storage unit 113a Wireless communication program 114 Input unit 115 Wireless communication unit

Claims (8)

メータ装置であって、
電気、ガス、および水の少なくとも何れかの使用量を計る計測部と、
無線通信部と、
制御部と、を備え、前記制御部が、
前記計測部によって計測された前記使用量を他のメータ装置又はメータネットワーク上の無線機能付き装置に送る時に、前記無線通信部に、前記他のメータ装置又は前記無線機能付き装置に対する所定の間欠周期での通信要求の送信又は前記所定の間欠周期での同期要求の送信を行わせる通常通信処理と、
非常事態を検出するセンサからの信号又は前記非常事態を通知する信号を受付けると、前記無線通信部を、前記他のメータ装置又は前記無線機能付き装置に対して前記所定の間欠周期よりも短い非常時間欠周期で通信要求を送信する状態、又は、前記非常時間欠周期での受信が可能な状態とする非常時通信処理と、を行い、
前記制御部が、当該メータ装置の周囲に存在する前記他のメータ装置の数を推定する数推定処理を行い、
前記制御部が、推定された前記数に応じて、前記信号を受付けてから前記非常時間欠周期での通信要求の送信の開始までの待機時間、又は、前記信号を受付けてから前記非常時間欠周期での受信を開始するまでの待機時間を変化させる、メータ装置。
A meter device,
a measuring unit that measures the usage of at least one of electricity, gas, and water;
Wireless communication department,
a control section, the control section comprising:
When transmitting the usage amount measured by the measuring unit to another meter device or a device with a wireless function on the meter network, the wireless communication unit is configured to transmit a predetermined intermittent period to the other meter device or the device with a wireless function on the meter network. normal communication processing for transmitting a communication request or transmitting a synchronization request at the predetermined intermittent cycle;
When receiving a signal from a sensor that detects an emergency situation or a signal that notifies the emergency situation, the wireless communication unit transmits an emergency signal to the other meter device or the device with wireless function that is shorter than the predetermined intermittent period. Performing emergency communication processing to enable communication requests to be sent in the emergency interruption period, or to enable reception in the emergency interruption period;
The control unit performs a number estimation process to estimate the number of other meter devices existing around the meter device,
The control unit determines, depending on the estimated number, a waiting time from receiving the signal to starting transmission of a communication request in the emergency period, or a waiting time from receiving the signal to starting transmission of a communication request in the emergency period. A meter device that changes the waiting time before starting periodic reception.
前記数推定処理において、前記制御部が、前記通信要求の送信又は前記同期要求の送信の後の間欠的な受信可能状態時に検出した信号の数を用いて、前記数を推定する、請求項に記載のメータ装置。 2. In the number estimation process, the control unit estimates the number using the number of signals detected during an intermittent receivable state after the transmission of the communication request or the transmission of the synchronization request. The meter device described in . 電気、ガス、および水の少なくとも何れかの使用量を計る計測部と、
無線通信部と、
制御部と、を備え、前記制御部が、
前記計測部によって計測された前記使用量を他のメータ装置又はメータネットワーク上の無線機能付き装置に送る時に、前記無線通信部に、前記他のメータ装置又は前記無線機能付き装置に対する所定の間欠周期での通信要求の送信又は前記所定の間欠周期での同期要求の送信を行わせる通常通信処理と、
非常事態を検出するセンサからの信号又は前記非常事態を通知する信号を受付けると、前記無線通信部を、前記他のメータ装置又は前記無線機能付き装置に対して前記所定の間欠周期よりも短い非常時間欠周期で通信要求を送信する状態、又は、前記非常時間欠周期での受信が可能な状態とする非常時通信処理と、を行い、
前記信号が前記非常事態の程度を示すものであり、
前記制御部が、前記信号に基づき、前記非常時間欠周期での前記通信要求の送信又は前記非常時間欠周期での受信が可能な状態の継続時間を決定する、メータ装置。
a measuring unit that measures the usage of at least one of electricity, gas, and water;
Wireless communication department,
a control section, the control section comprising:
When transmitting the usage amount measured by the measuring unit to another meter device or a device with a wireless function on the meter network, the wireless communication unit is configured to transmit a predetermined intermittent period to the other meter device or the device with a wireless function on the meter network. normal communication processing for transmitting a communication request or transmitting a synchronization request at the predetermined intermittent cycle;
When receiving a signal from a sensor that detects an emergency situation or a signal that notifies the emergency situation, the wireless communication unit transmits an emergency signal to the other meter device or the device with wireless function that is shorter than the predetermined intermittent period. Performing emergency communication processing to enable communication requests to be sent in the emergency interruption period, or to enable reception in the emergency interruption period;
the signal indicates the degree of the emergency;
The meter device, wherein the control unit determines, based on the signal, a duration of a state in which the communication request can be transmitted in the emergency interruption period or received in the emergency interruption period.
電気、ガス、および水の少なくとも何れかの使用量を計る計測部と、
無線通信部と、
制御部と、を備え、前記制御部が、
前記計測部によって計測された前記使用量を他のメータ装置又はメータネットワーク上の無線機能付き装置に送る時に、前記無線通信部に、前記他のメータ装置又は前記無線機能付き装置に対する所定の間欠周期での通信要求の送信又は前記所定の間欠周期での同期要求の送信を行わせる通常通信処理と、
非常事態を検出するセンサからの信号又は前記非常事態を通知する信号を受付けると、前記無線通信部を、前記他のメータ装置又は前記無線機能付き装置に対して前記所定の間欠周期よりも短い非常時間欠周期で通信要求を送信する状態、又は、前記非常時間欠周期での受信が可能な状態とする非常時通信処理と、を行い、
前記信号が前記非常事態の程度を示すものであり、
前記制御部が、前記信号に基づき、前記非常時間欠周期を決定する、メータ装置。
a measuring unit that measures the usage of at least one of electricity, gas, and water;
Wireless communication department,
a control section, the control section comprising:
When transmitting the usage amount measured by the measuring unit to another meter device or a device with a wireless function on the meter network, the wireless communication unit is configured to transmit a predetermined intermittent period to the other meter device or the device with a wireless function on the meter network. normal communication processing for transmitting a communication request or transmitting a synchronization request at the predetermined intermittent cycle;
When receiving a signal from a sensor that detects an emergency situation or a signal that notifies the emergency situation, the wireless communication unit transmits an emergency signal to the other meter device or the device with wireless function that is shorter than the predetermined intermittent period. Performing emergency communication processing to enable communication requests to be sent in the emergency interruption period, or to enable reception in the emergency interruption period;
the signal indicates the degree of the emergency;
The meter device, wherein the control unit determines the emergency interruption period based on the signal.
前記センサは、前記メータ装置に設けられた地震計である、請求項1~の何れかに記載のメータ装置。 The meter device according to any one of claims 1 to 4 , wherein the sensor is a seismometer provided in the meter device. 前記非常事態を通知する信号が火災報知器又は水害報知器からの信号である、請求項1~の何れかに記載のメータ装置。 The meter device according to any one of claims 1 to 5 , wherein the signal notifying the emergency situation is a signal from a fire alarm or a water damage alarm. 請求項1~の何れかに記載のメータ装置と、
前記他のメータ装置又は前記無線機能付き装置と、を備えるメータシステム。
A meter device according to any one of claims 1 to 6 ,
A meter system comprising the other meter device or the wireless function device.
請求項又はに記載のメータ装置と、
前記他のメータ装置又は前記無線機能付き装置と、を備え、
前記他のメータ装置又は前記無線機能付き装置が、非常事態の程度に関する情報を受信し、
前記メータ装置の前記制御部が、前記継続時間又は前記非常時間欠周期の決定に用いた前記非常事態の程度を前記他のメータ装置又は前記無線機能付き装置に送信する処理を行い、
前記他のメータ装置又は前記無線機能付き装置が、前記非常事態の程度よりも前記非常事態の程度に関する情報が正確であるか否かを判断し、前記非常事態の程度に関する情報が正確である場合に前記非常事態の程度に関する情報を前記メータ装置に送信する処理を行い、
前記メータ装置の前記制御部が、前記非常事態の程度に関する情報を用いて前記継続時間又は前記非常時間欠周期を決定する、メータシステム。
A meter device according to claim 3 or 4 ,
The other meter device or the device with wireless function,
the other meter device or the device with wireless functionality receives information regarding the degree of the emergency situation;
The control unit of the meter device performs a process of transmitting the degree of the emergency situation used to determine the duration time or the emergency interruption period to the other meter device or the device with wireless function,
If the other meter device or the device with wireless function determines whether the information regarding the degree of the emergency situation is more accurate than the degree of the emergency situation, and the information regarding the degree of the emergency situation is accurate. transmitting information regarding the degree of the emergency situation to the meter device;
The meter system, wherein the control unit of the meter device determines the duration or the emergency interruption period using information regarding the degree of the emergency.
JP2018165616A 2018-09-05 2018-09-05 Meter device, meter system, and command reception method for meter device Active JP7399608B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2018165616A JP7399608B2 (en) 2018-09-05 2018-09-05 Meter device, meter system, and command reception method for meter device
PCT/JP2019/032297 WO2020049990A1 (en) 2018-09-05 2019-08-19 Meter device, meter system, and method for receiving directive of meter device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018165616A JP7399608B2 (en) 2018-09-05 2018-09-05 Meter device, meter system, and command reception method for meter device

Publications (2)

Publication Number Publication Date
JP2020038516A JP2020038516A (en) 2020-03-12
JP7399608B2 true JP7399608B2 (en) 2023-12-18

Family

ID=69722905

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018165616A Active JP7399608B2 (en) 2018-09-05 2018-09-05 Meter device, meter system, and command reception method for meter device

Country Status (2)

Country Link
JP (1) JP7399608B2 (en)
WO (1) WO2020049990A1 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007227105A (en) 2006-02-22 2007-09-06 Matsushita Electric Works Ltd Earthquake detection lighting device
JP2013102263A (en) 2011-11-07 2013-05-23 Mitsubishi Electric Corp Radio network system, control method and program
JP2013192105A (en) 2012-03-14 2013-09-26 Nec Commun Syst Ltd Node device, node device control method, and node device control program
JP2015019315A (en) 2013-07-12 2015-01-29 株式会社ナカヨ Communication path establishment method, radio relay device and communication terminal
JP2015128199A (en) 2013-12-27 2015-07-09 三菱電機株式会社 Node device, wireless multi-hop network, and time synchronization method
KR20180050841A (en) 2016-11-07 2018-05-16 (주)대한가스기기 Wireless communication method of metering system
JP2018125748A (en) 2017-02-02 2018-08-09 パナソニックIpマネジメント株式会社 Meter and meter system

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3502481B2 (en) * 1995-07-13 2004-03-02 松下電器産業株式会社 Automatic meter reading device
JP3376470B2 (en) * 1997-07-18 2003-02-10 矢崎総業株式会社 Gas meter with gas shut-off valve
DK3431931T3 (en) * 2017-07-18 2021-06-14 Kamstrup As INTELLIGENT MEASURING DEVICE WITH ADAPTIVE SERVICE LEVEL

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007227105A (en) 2006-02-22 2007-09-06 Matsushita Electric Works Ltd Earthquake detection lighting device
JP2013102263A (en) 2011-11-07 2013-05-23 Mitsubishi Electric Corp Radio network system, control method and program
JP2013192105A (en) 2012-03-14 2013-09-26 Nec Commun Syst Ltd Node device, node device control method, and node device control program
JP2015019315A (en) 2013-07-12 2015-01-29 株式会社ナカヨ Communication path establishment method, radio relay device and communication terminal
JP2015128199A (en) 2013-12-27 2015-07-09 三菱電機株式会社 Node device, wireless multi-hop network, and time synchronization method
KR20180050841A (en) 2016-11-07 2018-05-16 (주)대한가스기기 Wireless communication method of metering system
JP2018125748A (en) 2017-02-02 2018-08-09 パナソニックIpマネジメント株式会社 Meter and meter system

Also Published As

Publication number Publication date
JP2020038516A (en) 2020-03-12
WO2020049990A1 (en) 2020-03-12

Similar Documents

Publication Publication Date Title
AU2018348163B2 (en) Fire detection system
CN104641245A (en) Method for detecting electric quantity of equipment, equipment, and system
CN104597858A (en) An oilfield management system and management method
KR101178669B1 (en) APPARATUS AND METHOD FOR ASSET TRACKING BASED ON Ubiquitous Sensor Network USING MOTION SENSING
JPWO2016021395A1 (en) Device monitoring system, device monitoring program, and device monitoring method
JP6350652B2 (en) Communication apparatus, method, and program
JP7399608B2 (en) Meter device, meter system, and command reception method for meter device
JP2009258063A (en) Damage monitoring system and measuring device
JP6807240B2 (en) Transmission system
JP2018092232A (en) Compound type measurement system
JP6282955B2 (en) Unauthorized connection detection system, method and program
JP2017151802A (en) Inspection system for alarm device using portable terminal, and inspection method using the same
JP2008181458A (en) Remote monitoring system
CN102735450B (en) For assessing the system and method for the operation of combustor
CA3004773C (en) Detecting an error condition by monitoring a resource flow at a premises
JP6593745B2 (en) Data driven processor
KR20090024858A (en) Ubiquitous Sensor Network Node Module and Its System
US20180152323A1 (en) Relay device and communication system
EP3273628A1 (en) Communication system and communication device
KR20160013964A (en) Time synchronization system
JP2009017393A (en) Traffic monitoring system
JP2011030094A (en) Radio communication system for traveling body and failure processing method of the same
JP2005309488A (en) Security device and program
JP2019509531A5 (en)
CN110031134A (en) Pipe stress monitors system, method, apparatus, storage medium and electronic device

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210902

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220920

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20221117

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230119

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230425

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20230626

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230817

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231107

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231206

R150 Certificate of patent or registration of utility model

Ref document number: 7399608

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150