JP7412673B2 - Hydropower plant construction plan optimization support server, hydropower plant construction plan optimization support system, and hydropower plant construction plan optimization support method - Google Patents
[go: Go Back, main page]

JP7412673B2 - Hydropower plant construction plan optimization support server, hydropower plant construction plan optimization support system, and hydropower plant construction plan optimization support method - Google Patents

Hydropower plant construction plan optimization support server, hydropower plant construction plan optimization support system, and hydropower plant construction plan optimization support method Download PDF

Info

Publication number
JP7412673B2
JP7412673B2 JP2019160601A JP2019160601A JP7412673B2 JP 7412673 B2 JP7412673 B2 JP 7412673B2 JP 2019160601 A JP2019160601 A JP 2019160601A JP 2019160601 A JP2019160601 A JP 2019160601A JP 7412673 B2 JP7412673 B2 JP 7412673B2
Authority
JP
Japan
Prior art keywords
construction
amount
power generation
equipment
construction plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019160601A
Other languages
Japanese (ja)
Other versions
JP2021039550A (en
Inventor
悟 徳永
貴道 佐藤
友之 八重沢
彰仁 勝又
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Tokyo Electric Power Co Holdings Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc, Tokyo Electric Power Co Holdings Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP2019160601A priority Critical patent/JP7412673B2/en
Publication of JP2021039550A publication Critical patent/JP2021039550A/en
Application granted granted Critical
Publication of JP7412673B2 publication Critical patent/JP7412673B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、水力発電所の工事計画の最適化支援サーバ、水力発電所の工事計画の最適化支援システムおよび水力発電所の工事計画の最適化支援方法に関する。 The present invention relates to a hydropower plant construction plan optimization support server, a hydropower plant construction plan optimization support system, and a hydropower plant construction plan optimization support method.

原子力や火力等の発電所における設備管理、作業管理などを実施するために、各種管理業務で使用される予算件名や工事件名などの情報をデータベースにより管理する管理システムが提案されている(特許文献1参照)。従来の管理システムにおいては、システムごとにその用途によって独立した件名が割り当てられ、管理されている。特許文献1では、別々のシステムで管理されていたデータを統合する際に現場の機器との照合がつきやすく管理しやすくしたことにより、作業や処理の上で効率よく、誤りも発生しにくい管理システムが提案されている。 In order to implement equipment management, work management, etc. at nuclear power plants, thermal power plants, etc., a management system has been proposed that uses a database to manage information such as budget subject names and construction project names used in various management tasks (Patent Document (see 1). In conventional management systems, each system is assigned an independent subject depending on its purpose and managed. In Patent Document 1, when integrating data that has been managed in separate systems, it is easier to check with on-site equipment and manage it, making work and processing more efficient and less likely to cause errors. system is proposed.

特開2003-143759号公報Japanese Patent Application Publication No. 2003-143759

発電所においては機器に対して工事が計画され、特許文献1のような管理システムを用いて管理することができる。発電所の機器に対する工事は、場合によっては発電所の停止が必要になることがある。 At a power plant, construction work is planned for equipment and can be managed using a management system such as that disclosed in Patent Document 1. Construction work on power plant equipment may require the power plant to be shut down in some cases.

ところで、近年では、電力取引の自由化が導入され、各種発電所において効率よく発電を行うことが求められている。効率よく発電を行うためには、発電所の停止を伴う工事計画を適切な時期に予定することが好ましいといえる。 Incidentally, in recent years, liberalization of power trading has been introduced, and various power plants are required to efficiently generate power. In order to efficiently generate power, it is preferable to schedule construction plans that involve shutting down the power plant at an appropriate time.

原子力や火力等の発電所では、何らかの燃料を用いて発電を行っているので、たとえば、夏の昼間などのように電力消費量が増加する場合は燃料を増加し、夜間などの電力消費量が低下する時期には燃料を抑制することにより、需要に合わせて発電量を調整することは容易である。ところが水力発電所では、自然に存在する水を用いて発電を行っているため、貯水池や調整池を持つ一部の水力発電所以外では、需要に応じた発電量の調整は困難といえる。 Nuclear power plants, thermal power plants, and other power plants use some kind of fuel to generate electricity, so when power consumption increases, such as during the daytime in summer, the amount of fuel is increased, and power consumption at night increases. During times of decline, it is easy to adjust the amount of power generated to meet demand by reducing fuel consumption. However, since hydroelectric power plants generate electricity using naturally occurring water, it is difficult to adjust the amount of power generated according to demand, except for some hydropower plants that have reservoirs or regulating ponds.

したがって、水力発電所においては、原子力や火力等の発電所とは異なる観点から工事計画を予定することが求められているといえる。 Therefore, it can be said that construction plans for hydroelectric power plants are required to be planned from a different perspective than for nuclear power plants, thermal power plants, and other power plants.

そこで本発明は、上記課題に鑑みてなされたものであり、発電効率が高くなるように水力発電所における工事計画を設定することを支援することができる水力発電所の工事計画の最適化支援サーバ、水力発電所の工事計画の最適化支援システムおよび水力発電所の工事計画の最適化支援方法を提供することを目的とする。 The present invention has been made in view of the above-mentioned problems, and is an optimization support server for construction plans for hydroelectric power plants that can support setting construction plans for hydroelectric power plants so as to increase power generation efficiency. The purpose of this paper is to provide a support system for optimizing construction plans for hydropower plants and a method for supporting optimization of construction plans for hydropower plants.

上記課題を解決するために、一実施形態に記載された水力発電所の工事計画の最適化支援サーバは、水力発電所の設備内の機器に対して工事を希望する工事時期である希望工事時期を含む希望の工事計画の入力を受け付ける工事計画入力部と、前記入力を受け付けた希望の工事計画の対象となる機器を停止させた場合に、発電の停止を必要とする発電設備を判定する停止設備判定部と、前記停止設備判定部において停止が必要と判定された発電設備がある場合に、停止が必要と判定された発電設備に関する水量実績に基づいて発電設備の停止による溢水量を算出する溢水量算出部と、前記算出した溢水量に基づいて、前記希望工事時期を別の工事時期に変更することを提案する提案部と、前記提案部で提案された別の工事時期に応じた工事時期の変更を確定する入力を受け付けて、該確定を受け付けた工事時期を確定工事時期として工事計画を確定する工事計画確定部と、前記工事計画確定部で確定された工事計画を出力する工事計画出力部と、を備えたことを特徴とする。 In order to solve the above problem, the optimization support server for the construction plan of a hydroelectric power plant described in one embodiment is configured to implement a desired construction period that is the desired construction period for the equipment in the equipment of the hydroelectric power plant. a construction plan input section that accepts input of a desired construction plan including a construction plan; and a shutdown section that determines power generation equipment that requires power generation to be stopped when equipment targeted by the desired construction plan that has received the input is stopped. If there is a power generation facility that is determined to need to be shut down by the equipment determination unit and the shutdown equipment determination unit, the amount of overflow due to the shutdown of the power generation equipment is calculated based on the water volume record of the power generation equipment that has been determined to need to be shut down. an overflow amount calculation section, a proposal section that proposes changing the desired construction period to another construction period based on the calculated overflow amount, and construction according to the different construction period proposed by the proposal section. a construction plan confirmation section that accepts an input to confirm a change in timing and finalizes the construction plan by setting the construction period for which the confirmation has been accepted as the final construction period; and a construction plan that outputs the construction plan finalized by the construction plan confirmation section. It is characterized by comprising an output section.

本実施形態にかかる水力発電所の工事計画の最適化支援サーバを備えた水力発電所の工事計画の最適化支援システムを示す図である。1 is a diagram illustrating a hydropower plant construction plan optimization support system including a hydropower plant construction plan optimization support server according to the present embodiment. FIG. 水力発電所の工事計画の最適化支援システムの機能ブロックを示す図である。FIG. 2 is a diagram showing functional blocks of a support system for optimizing construction plans for a hydroelectric power plant. 年間の工事計画を概観的に表示する例を示すブロック図である。FIG. 2 is a block diagram illustrating an example of an overview of annual construction plans; FIG. 年間の工事計画を概観的に表示する例を示すブロック図である。FIG. 2 is a block diagram illustrating an example of an overview of annual construction plans; FIG. 特定の発電所の特定の時期における工事計画を詳細に表示する例を示す図である。FIG. 3 is a diagram illustrating an example of displaying detailed construction plans for a specific power plant at a specific time. 発電量実績額の表示例を示す図である。It is a figure which shows the example of a display of a power generation amount actual amount. 予定する工事計画に基づく発電量と実際の発電量との比較表示の例を示す図である。FIG. 3 is a diagram illustrating an example of a comparative display of the amount of power generated based on a planned construction plan and the amount of actual power generated. 停止情報提供サーバに格納される停止項目テーブルの一例を示す図である。It is a figure showing an example of a suspension item table stored in a suspension information provision server. 実績データベースに格納された水量実績データの一例を示す図である。It is a figure showing an example of water quantity performance data stored in a performance database. 実績データベースに格納された水量実績データの一例を示す図である。It is a figure showing an example of water quantity performance data stored in a performance database. 本実施形態にかかる水力発電所の工事計画の最適化支援サーバの動作を示すフローチャートである。It is a flowchart which shows the operation of the optimization support server of the construction plan of the hydroelectric power plant concerning this embodiment. ワークオーダ入力画面の一例を示す図である。It is a figure which shows an example of a work order input screen.

1.実施の形態の概要
先ず、本願において開示される発明の代表的な実施の形態について概要を説明する。なお、以下の説明では、一例として、発明の構成要素に対応する図面上の参照符号を、括弧を付して記載している。
1. Overview of Embodiments First, an overview of typical embodiments of the invention disclosed in this application will be described. In the following description, as an example, reference numerals on the drawings corresponding to constituent elements of the invention are written in parentheses.

〔1〕本発明の代表的な実施の形態に係る水力発電所の工事計画の最適化支援サーバ(10)は、水力発電所の設備内の機器に対して工事を希望する工事時期である希望工事時期を含む希望の工事計画の入力を受け付ける工事計画入力部(11)と、前記入力を受け付けた希望の工事計画の対象となる機器を停止させた場合に、発電の停止を必要とする発電設備を判定する停止設備判定部(12)と、前記停止要設備判定部(12)において停止が必要と判定された発電設備がある場合に、停止が必要と判定された発電設備に関する水量実績に基づいて発電設備の停止による溢水量を算出する溢水量算出部(13)と、前記算出した溢水量に基づいて、前記希望工事時期を別の工事時期に変更することを提案する提案部(14)と、前記提案部(14)で提案された別の工事時期に応じた工事時期の変更を確定する入力を受け付けて、該確定を受け付けた工事時期を確定工事時期として工事計画を確定する工事計画確定部(15)と、前記工事計画確定部(15)で確定された工事計画を出力する工事計画出力部(16)と、を備えたことを特徴とする。 [1] The optimization support server (10) for the construction plan of a hydroelectric power plant according to a typical embodiment of the present invention is configured to provide a request for a construction period in which construction is desired to be performed on equipment in the equipment of a hydroelectric power plant. A construction plan input unit (11) that accepts input of a desired construction plan including construction schedule, and a power generation unit that requires power generation to be stopped when equipment targeted by the desired construction plan for which the input has been received is stopped. If there is a power generation facility that is determined to need to be shut down by the shutdown equipment determination unit (12) that determines the equipment and the equipment requiring shutdown determination unit (12), the water amount record regarding the power generation equipment that has been determined to need to be shut down is an overflow amount calculation unit (13) that calculates the overflow amount due to the stoppage of power generation equipment based on the above-mentioned overflow amount; and a proposal unit (14) that proposes changing the desired construction period to another construction period based on the calculated overflow amount. ), and receives an input to confirm a change in the construction period according to another construction period proposed by the proposal section (14), and finalizes the construction plan by setting the construction period for which the confirmation has been accepted as the final construction period. It is characterized by comprising a plan confirmation section (15) and a construction plan output section (16) that outputs the construction plan decided by the construction plan confirmation section (15).

〔2〕上記水力発電所の工事計画の最適化支援サーバにおいて、前記工事計画確定部(15)は、前記停止設備判定部において発電の停止を必要とする発電設備がないと判定した場合に、前記工事計画入力部で入力を受け付けた工事計画を確定することを特徴とする。 [2] In the construction plan optimization support server for the hydroelectric power plant, when the construction plan determination unit (15) determines that there is no power generation equipment that requires the suspension of power generation, the construction plan determination unit (15): The present invention is characterized in that the construction plan input by the construction plan input section is finalized.

〔3〕上記水力発電所の工事計画の最適化支援サーバにおいて、停止設備判定部は、工事計画の対象となる機器と、該機器を停止する場合に発電の停止が必要となる発電設備とを対応付けた停止項目テーブルを参照することにより停止が必要となる設備の判定を行うことを特徴とする。 [3] In the above-mentioned hydroelectric power plant construction plan optimization support server, the equipment to be shut down determination unit identifies the equipment that is the target of the construction plan and the power generation equipment whose power generation needs to be stopped when the equipment is shut down. It is characterized in that equipment that needs to be stopped is determined by referring to the associated stop item table.

〔4〕上記水力発電所の工事計画の最適化支援サーバにおいて、前記溢水量算出部は、前記発電設備に関する水量の所定年数に亘る実績を格納した水量データベースを参照することにより前記発電設備に関する水量実績を取得することを特徴とする。 [4] In the above-mentioned hydroelectric power plant construction plan optimization support server, the overflow amount calculation unit calculates the amount of water related to the power generation facility by referring to a water amount database that stores the actual amount of water related to the power generation facility over a predetermined number of years. It is characterized by obtaining achievements.

〔5〕上記水力発電所の工事計画の最適化支援サーバにおいて、前記提案部は、溢水量が小さい工事時期を優先的に提案し、溢水量が同じ複数の工事時期がある場合は、当該複数の工事時期のうちで前記希望工事時期に最も近い工事時期を優先的に提案することを特徴とする。 [5] In the above-mentioned hydroelectric power plant construction plan optimization support server, the proposal section preferentially proposes a construction period with a small amount of overflow, and if there are multiple construction periods with the same amount of overflow, The present invention is characterized in that the construction period closest to the desired construction period among the construction periods is preferentially proposed.

〔6〕上記水力発電所の工事計画の最適化支援サーバにおいて、前記水力発電所における所定年数に亘る発電量の実績である発電量実績を金額に換算した発電量実績額と、前記工事計画出力部から出力された工事計画に含まれる工事費用である予想工事費用とを取得して、当該工事計画の確定工事時期に対応する時期の前記発電量実績額に、前記取得した予想工事費用を加えた値を予想の発電所評価指標として提供する発電所評価指標提供部とをさらに備えることを特徴とする。 [6] In the construction plan optimization support server for the hydroelectric power plant, the actual power generation amount, which is the amount of power generated at the hydropower plant over a predetermined number of years, is converted into a monetary amount, and the output of the construction plan. The estimated construction cost, which is the construction cost included in the construction plan output from the department, is obtained, and the obtained estimated construction cost is added to the actual power generation amount for the period corresponding to the final construction period of the construction plan. The power plant evaluation index providing unit provides the predicted power plant evaluation index as a predicted power plant evaluation index.

〔7〕上記水力発電所の工事計画の最適化支援サーバにおいて、前記発電所評価指標提供部は、前記水力発電所における実際の発電量である実際発電量を金額に換算した発電量実際額を取得し、該発電量実際額と前記発電量実績額との比較表示を、評価指標として提供することを特徴とする。 [7] In the above-mentioned hydropower plant construction plan optimization support server, the power plant evaluation index providing unit converts the actual power generation amount, which is the actual power generation amount at the hydropower plant, into a monetary value. A comparative display of the actual power generation amount and the actual power generation amount is provided as an evaluation index.

〔8〕本発明の他の実施の形態に係る水力発電所の工事計画の最適化支援システムは、上記された水力発電所の工事計画の最適化支援サーバと、工事計画の対象となる機器と、該機器を停止する場合に発電の停止が必要となる発電設備とを対応付けた停止項目テーブルを格納した停止情報提供サーバと、前記発電設備に関する水量の所定年数に亘る実績を格納した実績データベースを格納した実績管理サーバとを備えたことを特徴とする。 [8] A hydroelectric power plant construction plan optimization support system according to another embodiment of the present invention includes the above-mentioned hydroelectric power plant construction plan optimization support server, and equipment targeted for construction planning. , a shutdown information providing server that stores a shutdown item table that associates power generation equipment with power generation equipment that requires power generation shutdown when the equipment is stopped; and a performance database that stores the performance of water volume related to the power generation equipment over a predetermined number of years. The system is characterized by comprising a track record management server that stores.

〔9〕本発明の他の実施の形態に係る水力発電所の工事計画の最適化支援方法は、水力発電所の設備内の機器に対して工事を希望する工事時期である希望工事時期を含む希望の工事計画の入力を受け付ける工事計画入力工程と、前記入力を受け付けた希望の工事計画の対象となる機器を停止させた場合に、発電の停止を必要とする発電設備があるか否かを判定する停止設備判定工程と、前記停止設備判定工程において停止が必要と判定された発電設備がある場合に、停止が必要と判定された発電設備に関する水量実績に基づいて発電設備の停止による溢水量を算出する溢水量算出工程と、前記算出した溢水量に基づいて、前記希望工事時期を別の工事時期に変更することを提案する提案工程と、前記提案工程で提案された別の工事時期に応じた工事時期の変更を確定する入力を受け付けて、該確定を受け付けた工事時期を確定工事時期として工事計画を確定する工事計画確定工程と、前記工事計画確定工程で確定された工事計画を出力する工事計画出力工程と、を含むことを特徴とする。 [9] A method for optimizing a construction plan for a hydroelectric power plant according to another embodiment of the present invention includes a desired construction period that is a desired construction period for equipment in the equipment of a hydroelectric power plant. A construction plan input step that accepts the input of the desired construction plan, and a process that determines whether there is any power generation equipment that requires power generation to be stopped when the equipment that is the target of the desired construction plan that has received the input is stopped. If there is a power generation facility that is determined to need to be shut down in the shutdown equipment determination step, the amount of water overflow due to the shutdown of the power generation facility is determined based on the actual water volume of the power generation facility that is determined to need to be shut down. an overflow amount calculation step that calculates the amount of overflow; a proposal step that proposes changing the desired construction period to another construction period based on the calculated overflow amount; and a proposal step that proposes changing the desired construction period to another construction period proposed in the proposal step. A construction plan confirmation process that accepts an input to confirm the change in the construction schedule according to the request, and finalizes the construction plan by setting the construction date for which the confirmation has been accepted as the final construction date, and outputs the construction plan finalized in the construction plan confirmation process. and a construction plan output process.

〔10〕上記水力発電所の工事計画の最適化支援方法において、前記工事計画確定工程は、前記停止設備判定工程において発電の停止を必要とする発電設備がないと判定した場合に、前記工事計画入力工程で入力を受け付けた工事計画を確定することを特徴とする。 [10] In the above-mentioned method for supporting optimization of a construction plan for a hydroelectric power plant, the construction plan confirmation step may be performed when determining that there is no power generation equipment requiring suspension of power generation in the suspension equipment determination step. It is characterized by finalizing the construction plan for which input is received in the input process.

〔11〕上記水力発電所の工事計画の最適化支援方法において、停止設備判定工程は、工事計画の対象となる機器と、該機器を停止する場合に発電の停止が必要となる発電設備とを対応付けた停止項目テーブルを参照することにより停止が必要となる設備の判定を行うことを特徴とする。 [11] In the above-mentioned method for supporting optimization of construction plans for hydroelectric power plants, the equipment to be shut down determination step identifies the equipment that is the target of the construction plan and the power generation equipment whose power generation needs to be stopped when the equipment is shut down. It is characterized in that equipment that needs to be stopped is determined by referring to the associated stop item table.

〔12〕上記水力発電所の工事計画の最適化支援方法において、前記溢水量算出工程は、前記発電設備に関する水量の所定年数に亘る実績を格納した水量データベースを参照することにより前記発電設備に関する水量実績を取得することを特徴とする。 [12] In the above-mentioned method for supporting the optimization of construction plans for a hydroelectric power plant, the overflow amount calculation step calculates the amount of water related to the power generation facility by referring to a water amount database that stores the actual amount of water related to the power generation facility over a predetermined number of years. It is characterized by obtaining achievements.

〔13〕上記水力発電所の工事計画の最適化支援方法において、前記提案工程は、溢水量が小さくなる工事時期を優先的に提案し、溢水量が同じ複数の工事時期がある場合は、当該複数の工事時期のうちで前記希望工事時期に最も近い工事時期を優先的に提案することを特徴とする。 [13] In the above method for supporting the optimization of construction plans for hydroelectric power plants, the proposal process preferentially proposes the construction period in which the amount of overflow will be small, and if there are multiple construction periods with the same amount of overflow, the relevant The present invention is characterized in that a construction period closest to the desired construction period among a plurality of construction periods is proposed preferentially.

〔14〕上記水力発電所の工事計画の最適化支援方法において、前記水力発電所における所定年数に亘る発電量の実績である発電量実績を金額に換算した発電量実績額と、前記工事計画出力工程において出力された工事計画に含まれる工事費用である予想工事費用とを取得して、当該工事計画の確定工事時期に対応する時期の前記発電量実績額に、前記取得した予想工事費用を加えた値を予想の発電所評価指標として提供する発電所評価指標提供工程とをさらに含むことを特徴とする。 [14] In the above-mentioned method for supporting the optimization of construction plans for a hydroelectric power plant, the amount of actual power generation amount obtained by converting the actual amount of power generation, which is the actual amount of power generation over a predetermined number of years at the hydropower plant, into a monetary amount, and the output of the construction plan. Obtain the estimated construction cost, which is the construction cost included in the construction plan output in the process, and add the obtained estimated construction cost to the actual power generation amount for the period corresponding to the final construction period of the construction plan. The method further includes a power plant evaluation index providing step of providing the predicted power plant evaluation index.

〔15〕上記水力発電所の工事計画の最適化支援方法において、前記発電所評価指標提供工程は、前記水力発電所における実際の発電量である実際発電量を金額に換算した発電量実際額を取得し、該発電量実際額と前記発電量実績額との比較表示を、評価指標として提供することを特徴とする。 [15] In the hydropower plant construction plan optimization support method, the power plant evaluation index providing step converts the actual power generation amount, which is the actual power generation amount at the hydropower plant, into a monetary amount. A comparative display of the actual power generation amount and the actual power generation amount is provided as an evaluation index.

2.実施の形態の具体例
以下、本発明の実施の形態の具体例について図を参照して説明する。なお、以下の説明において、各実施の形態において共通する構成要素には同一の参照符号を付し、繰り返しの説明を省略する。
2. Specific Examples of Embodiments Hereinafter, specific examples of embodiments of the present invention will be described with reference to the drawings. In addition, in the following description, the same reference numerals are given to the same component in each embodiment, and repeated description is omitted.

(第1の実施形態)
図1は、本実施形態にかかる水力発電所の工事計画の最適化支援サーバを備えた水力発電所の工事計画の最適化支援システムを示す図である。本実施形態にかかる水力発電所の工事計画の最適化支援システムは、工事計画の最適化支援サーバ10と、停止情報提供サーバ20と、実績管理サーバ30とを備えて構成される。工事計画の最適化支援サーバ10と、停止情報提供サーバ20と、実績管理サーバ30とはそれぞれ記憶装置や演算処理装置を備えたコンピュータによって構成することができる。
(First embodiment)
FIG. 1 is a diagram illustrating a hydropower plant construction plan optimization support system including a hydropower plant construction plan optimization support server according to the present embodiment. The construction plan optimization support system for a hydroelectric power plant according to the present embodiment includes a construction plan optimization support server 10, an outage information providing server 20, and a performance management server 30. The construction plan optimization support server 10, the outage information providing server 20, and the performance management server 30 can each be configured by a computer equipped with a storage device and an arithmetic processing device.

工事計画の最適化支援サーバ10は、停止情報提供サーバ20および実績管理サーバ30と協働することにより、水力発電所の工事計画の最適化支援サーバとして機能するサーバである。水力発電所において発電設備が停止する作業計画としては、保全計画と工事計画とがある。水力発電においては、保全計画は、設備の保守・保全を目的として定期的に点検や補修を行う計画であり、必要に応じて突発的に計画される工事計画とは区別されている。工事計画の最適化支援サーバ10では、水力発電所の工事計画を最適な時期に計画する支援をする。 The construction plan optimization support server 10 is a server that functions as a construction plan optimization support server for a hydroelectric power plant by cooperating with the outage information providing server 20 and the performance management server 30. Work plans for shutting down power generation equipment at a hydroelectric power plant include a maintenance plan and a construction plan. In hydroelectric power generation, a maintenance plan is a plan for periodically inspecting and repairing equipment for the purpose of maintenance and maintenance, and is distinguished from a construction plan that is suddenly planned as needed. The construction plan optimization support server 10 supports construction planning for a hydroelectric power plant at an optimal time.

停止情報提供サーバ20は、工事計画の対象となる機器と、工事計画の対象とした機器を停止する場合に発電の停止が必要となる発電設備とを対応付けた停止項目テーブルを格納したデータベースを有している。停止情報提供サーバ20は、工事計画の最適化支援サーバ10に接続されており、工事計画の最適化支援サーバ10の要求に基づいて必要な情報データを提供する。 The outage information providing server 20 stores a database that stores a outage item table that associates equipment targeted by the construction plan with power generation equipment whose power generation needs to be stopped when the equipment targeted by the construction plan is shut down. have. The outage information providing server 20 is connected to the construction plan optimization support server 10 and provides necessary information data based on requests from the construction plan optimization support server 10.

実績管理サーバ30は、発電設備に関する水量の所定年数に亘る水量実績データと発電設備における発電量の実績である発電量実績データとを格納した実績データベースを有している。実績管理サーバ30は、工事計画の最適化支援サーバ10に接続されており、工事計画の最適化支援サーバ10の要求に基づいて実績データベースに格納した情報データを提供する。 The performance management server 30 has a performance database that stores water volume performance data related to the power generation equipment over a predetermined number of years and power generation performance data that is the performance of the power generation amount in the power generation equipment. The performance management server 30 is connected to the construction plan optimization support server 10, and provides information data stored in the performance database based on a request from the construction plan optimization support server 10.

図2は水力発電所の工事計画の最適化支援システムの機能ブロックを示す図である。図2に示すように、工事計画の最適化支援サーバ10は、入力部11と、停止設備判定部12と、溢水量算出部13と、提案部14と、工事計画確定部15と、出力部16と、発電所評価指標提供部17と、保全・工事・停止計画格納部18とを有している。 FIG. 2 is a diagram showing functional blocks of a support system for optimizing construction plans for a hydroelectric power plant. As shown in FIG. 2, the construction plan optimization support server 10 includes an input section 11, a stopped equipment determination section 12, an overflow amount calculation section 13, a proposal section 14, a construction plan confirmation section 15, and an output section. 16, a power plant evaluation index providing section 17, and a maintenance/construction/shutdown plan storage section 18.

入力部11は、水力発電所の設備内の機器に対して工事を希望する工事時期である希望工事時期を含む希望の工事計画の入力を受け付ける工事計画入力部として機能することができる。入力部11としては、キーボード、マウス、マイクなどの任意のユーザインタフェースとこれらを制御して入力された情報を適宜処理するプロセッサなどの処理装置とを用いることができる。入力された希望の工事計画は、保全・工事・停止計画格納部18に一時的に格納し、必要に応じて参照することができる。 The input unit 11 can function as a construction plan input unit that receives an input of a desired construction plan including a desired construction period, which is a desired construction period for the equipment in the equipment of the hydroelectric power plant. As the input unit 11, any user interface such as a keyboard, mouse, or microphone, and a processing device such as a processor that controls these and appropriately processes input information can be used. The input desired construction plan is temporarily stored in the maintenance/construction/shutdown plan storage section 18 and can be referenced as needed.

停止設備判定部12は、入力を受け付けた希望の工事計画の対象となる機器を停止させた場合に、発電の停止を必要とする発電設備を判定する。停止設備判定部12は、対象となる機器を工事する場合に、停止すべき発電設備が何になるかを停止情報提供サーバ20に問い合わせる。問い合わせの結果、停止すべき発電設備がある場合は、停止設備判定部12は、溢水量算出部13に停止すべき発電設備についての情報を送る。問い合わせの結果、停止すべき発電設備がない場合は、停止設備判定部12は、工事計画確定部15に停止すべき発電設備がないことを送る。 The shutdown equipment determining unit 12 determines the power generation equipment that needs to stop generating power when the equipment targeted by the desired construction plan that has been input is stopped. The shutdown equipment determination unit 12 inquires of the shutdown information providing server 20 as to which power generation equipment should be shut down when performing construction on the target equipment. As a result of the inquiry, if there is power generation equipment that should be shut down, the shutdown equipment determination unit 12 sends information about the power generation equipment that should be shut down to the overflow amount calculation unit 13 . As a result of the inquiry, if there is no power generating equipment to be shut down, the shut down equipment determining unit 12 sends to the construction plan determining unit 15 that there is no power generating equipment to be shut down.

溢水量算出部13は、停止設備判定部12において停止が必要と判定された発電設備がある場合に、停止が必要と判定された発電設備に関する水量実績に基づいて発電設備の停止による溢水量を算出する。溢水量算出部13は、停止すべき発電設備があることを受け取ると、入力を受け付けた希望の工事計画を参照して、工事計画の期間を取得し、取得した期間(日数)において溢水量を算出する。溢水量算出部13は、停止すべき発電設備に関する水量実績データを実績管理サーバ30に問い合わせて、停止すべき発電設備に関する水量実績データを取得する。水量実績データはたとえば水量を発電量に換算したものが用いられる。 When there is a power generation facility for which the stoppage determination section 12 determines that the stoppage is necessary, the overflow amount calculation unit 13 calculates the overflow amount due to the stoppage of the power generation facility based on the water volume record of the power generation facility for which the stoppage is determined to be necessary. calculate. When the overflow amount calculation unit 13 receives that there is a power generation facility to be stopped, it refers to the desired construction plan that has received input, acquires the period of the construction plan, and calculates the overflow amount during the acquired period (number of days). calculate. The overflow amount calculation unit 13 inquires of the performance management server 30 for water amount performance data regarding the power generation equipment to be stopped, and acquires water amount performance data regarding the power generation equipment to be stopped. The actual water amount data is, for example, the amount of water converted into the amount of power generation.

停止すべき発電設備を収容した発電所に複数の発電設備が存在する場合などでは、水量実績データが個々の発電設備に直接的に対応していないことがある。この場合、溢水量算出部13は、発電所内の発電設備の能力を考慮して、溢水量を算出することができる。たとえば、A発電所には発電出力が等しい1号機と2号機とが設けられており、1号機と2号機共に最大発電量は1000kw/日であるA発電所において、5月10日から5月14日の5日間の期間において1号機の停止を必要とする工事計画について溢水量を算出することを考える。この場合、溢水量算出部13は、A発電所の水量実績データを実績管理サーバ30から取得して、連続する5日間ごとの溢水量を算出する。たとえば、希望する工事計画どおりの日程における溢水量を算出するときは、取得した水量実績データが、5月10日から5月12日は1300kw/日であり、5月13日から5月14日が1500kw/日であった場合、1000kw/日は2号機で消費可能であるので、溢水量は、300kw×3+500kw×2=1900kwと算出することができる。 In cases where a plurality of power generation facilities exist in a power plant that accommodates the power generation facility that should be shut down, water amount performance data may not directly correspond to each power generation facility. In this case, the overflow amount calculation unit 13 can calculate the overflow amount in consideration of the capacity of the power generation equipment in the power station. For example, Power Plant A has Units 1 and 2 that have the same power generation output, and the maximum power generation capacity of both Units 1 and 2 is 1000kw/day. Consider calculating the amount of overflow for a construction plan that requires the shutdown of Unit 1 during a five-day period on the 14th. In this case, the overflow amount calculation unit 13 acquires the water amount performance data of power plant A from the performance management server 30, and calculates the overflow amount for every five consecutive days. For example, when calculating the overflow amount for the schedule according to the desired construction plan, the acquired water amount actual data is 1300kw/day from May 10th to May 12th, and 1300kw/day from May 13th to May 14th. If it is 1500kw/day, 1000kw/day can be consumed by the second unit, so the amount of overflow can be calculated as 300kw x 3 + 500kw x 2 = 1900kw.

溢水量算出部13は、保全・工事・停止計画格納部18に格納されている保全・工事・停止計画を参照して溢水量を算出することができる。この場合、保全・工事・停止計画を参照して停止すべき発電設備の停止計画がすでに計画されている発電設備の溢水量は「0」として計算することができる。保全計画による溢水時期(停止が予定されている時期)に合わせて工事計画を計画しやすくなる。 The overflow amount calculation unit 13 can calculate the overflow amount by referring to the maintenance/construction/shutdown plan stored in the maintenance/work/shutdown plan storage unit 18. In this case, the overflow amount of the power generation equipment for which a shutdown plan has already been planned for the power generation equipment to be shut down with reference to the maintenance/construction/shutdown plan can be calculated as "0". It will be easier to plan construction plans to match the flooding period (when outages are scheduled) according to the conservation plan.

溢水量算出部13は、算出した溢水量を提案部14に出力する。
提案部14は、溢水量算出部13において算出した溢水量に基づいて、希望工事時期を別の工事時期に変更することを提案する。別の工事時期としては、溢水量が小さい順番で工事時期を提案することができる。提案部14は、溢水量が一番小さくなる時期が希望工事時期と一致する場合は、別の工事時期に変更することの提案は行わなくてもよい。溢水量が複数の工事時期で同じである場合は、希望工事時期に近い工事時期を別の工事時期として提案することができる。したがって、最初は溢水量が最も小さい工事時期を提案することができる。溢水量が最も小さい工事時期をすでに提案しており、再度の提案の場合は、次に溢水量が小さい工事時期を提案することができる。たとえば、希望工事時期である5月10日から5月14日までの5日間の溢水量が1900kwであるのに対し、10月3日から10月7日までの5日間の溢水量が0kwであり、最も小さい場合について考える。この場合、提案部14は、10月3日から10月7日までの5日間を別の工事時期としてこの工事時期に変更することを提案する。提案部14による提案は、出力部16のディスプレイに表示することなどによって行ってもよい。
図3は提案部14により、出力部16に表示される提案の表示例である。図3の例では、変更後の工事時期によって発電所の停止期間が短くなることを示すことによって提案がなされている。すなわち、図3において、当初の工事時期による発電所の停止が「ベースプラン」、変更後の工事時期が「変更プラン」とそれぞれ表示されており、変更プランの工事時期がベースプランの工事時期よりも短くなることが一目でわかる。この表示を参照することにより、視覚的に確認しながら工事時期を変更することができる。
The overflow amount calculation unit 13 outputs the calculated overflow amount to the proposal unit 14.
The proposal section 14 proposes changing the desired construction period to another construction period based on the amount of overflow calculated by the overflow amount calculation section 13. As another construction period, it is possible to propose construction periods in order of decreasing amount of overflow. If the period when the amount of overflow is the smallest coincides with the desired construction period, the proposal unit 14 does not need to propose changing to another construction period. If the amount of overflow is the same for multiple construction periods, a construction period closer to the desired construction period can be proposed as another construction period. Therefore, it is possible to initially suggest the construction period when the amount of overflow will be the smallest. We have already proposed the construction period when the amount of overflow will be the smallest, and if we make another proposal, we can suggest the construction period when the amount of overflow will be the next smallest. For example, the amount of water overflowing in the five days from May 10th to May 14th, which is the desired construction period, is 1,900kw, but the amount of flooding in the five days from October 3rd to October 7th is 0kw. Consider the smallest case. In this case, the proposal unit 14 proposes changing the five days from October 3rd to October 7th to another construction period. The proposal by the proposal unit 14 may be made by displaying the proposal on the display of the output unit 16.
FIG. 3 is a display example of a proposal displayed on the output unit 16 by the proposal unit 14. In the example of FIG. 3, the proposal is made by indicating that the power plant outage period will be shortened depending on the construction period after the change. In other words, in Figure 3, the shutdown of the power plant due to the original construction period is shown as the "base plan", and the construction period after the change is shown as the "changed plan", and the construction period of the changed plan is displayed as the construction period of the base plan. You can see at a glance that the length is also shorter. By referring to this display, the construction period can be changed while visually confirming it.

工事計画確定部15は、提案部14で提案された別の工事時期に応じた工事時期の変更を確定する入力を受け付けて、確定を受け付けた工事時期を確定工事時期として工事計画を確定する。工事時期の変更を確定する入力は、入力部11を用いて行うことができる。 A construction plan confirmation unit 15 receives an input for confirming a change in the construction period according to another construction period proposed by the proposal unit 14, and finalizes the construction plan by setting the construction period for which the confirmation has been accepted as the final construction period. An input to confirm a change in the construction period can be made using the input unit 11.

工事計画確定部15は、停止すべき発電設備がないことを停止設備判定部12から受け取った場合にも、工事計画を確定することができる。停止すべき発電設備がない場合は、工事計画確定部15は、当初の工事計画に含まれる希望工事時期で工事計画を確定する入力を受け付けると、確定を受け付けた工事時期を確定工事時期として工事計画を確定する。希望工事時期で確定する場合は、確定の受付を省略してもよい。確定した工事計画は、保全・工事・停止計画格納部18に格納することができる。 Even when the construction plan determination unit 15 receives from the shutdown equipment determination unit 12 that there is no power generation equipment to be shut down, the construction plan determination unit 15 can finalize the construction plan. If there is no power generating equipment to be shut down, the construction plan confirmation unit 15 receives an input to confirm the construction plan with the desired construction period included in the original construction plan, and then starts the construction work using the confirmed construction period as the final construction period. Finalize your plan. If the desired construction period is confirmed, the confirmation process may be omitted. The confirmed construction plan can be stored in the maintenance/construction/shutdown plan storage section 18.

出力部16は、工事計画確定部で確定された工事計画を出力する工事計画出力部として機能することができる。出力部16としては、ディスプレイ、スピーカなどの任意のユーザインタフェースとこれらを制御して所定の情報を適宜処理してユーザインタフェースに出力するプロセッサなどの処理装置とを用いることができる。 The output unit 16 can function as a construction plan output unit that outputs the construction plan determined by the construction plan determination unit. As the output unit 16, an arbitrary user interface such as a display or a speaker, and a processing device such as a processor that controls these, appropriately processes predetermined information, and outputs it to the user interface can be used.

図4、5はディスプレイである出力部16における出力表示例を示す図である。図4は、年間の工事計画を概観的に表示する例であり、図5は、特定の発電所の特定の時期における工事計画を詳細に表示する例である。図4において、「A発電所」と「B発電所」が示されており、「A発電所」には発電設備として「1号機」と「2号機」とがあり、その発電設備はそれぞれ「機器a」、「機器b」、「機器c」、「機器d」を有していることがわかる。図4によれば、例えば「A発電所」の「1号機」には、5月に「機器b」、「機器c」について作業(保全作業か工事作業)が計画されており、発電が停止することが計画されていることが示されている。さらにこの5月の作業内容・停止時期を参照したい場合は、入力部11であるマウスなどを用いてこの「A発電所」の5月を選択すると、図5に示す詳細表示に切り替わり、5月の2日から12日に発電停止が計画されており(濃く塗りつぶしたバーで図示)、そのうち5月2日から5月9日には「機器b」に保全計画が予定されており(薄く塗りつぶしたバーで図示)、「機器c」には5月2日から7日までは工事計画が予定され(塗りつぶしなしのバーで図示)、5月8日から5月12日には保全計画が予定されている(薄く塗りつぶしたバーで図示)ことが示されている。 4 and 5 are diagrams showing examples of output display on the output unit 16, which is a display. FIG. 4 is an example of an overview of the annual construction plan, and FIG. 5 is an example of a detailed display of the construction plan of a specific power plant at a specific time. In Figure 4, "Power Plant A" and "Power Plant B" are shown, and "Power Plant A" has "Unit 1" and "Unit 2" as power generation facilities, and their power generation facilities are " It can be seen that there are "device a", "device b", "device c", and "device d". According to Figure 4, for example, work (maintenance work or construction work) is planned for "equipment b" and "equipment c" in May at "unit 1" of "power plant A", and power generation will be halted. It has been shown that it is planned to do so. Furthermore, if you want to refer to the work details and stoppage times for this May, select May for this "A power plant" using the mouse, which is the input section 11, and the detailed display will change to the one shown in Figure 5. A power generation outage is planned for May 2nd to May 12th (indicated by a darkly filled bar), and a maintenance plan is scheduled for "Equipment B" from May 2nd to May 9th (indicated by a lightly filled bar). A construction plan is scheduled for "equipment c" from May 2nd to 7th (indicated by a solid bar), and a maintenance plan is scheduled for May 8th to May 12th. (indicated by a thinly filled bar).

発電所評価指標提供部17は、発電量実績額と予想工事費用とを取得して、予想の発電所評価指標を提供する。発電量実績額は、水力発電所における所定年数に亘る発電量の実績である発電量実績を金額に換算した値を用いることができる。予想工事費用は、工事計画出力部から出力された工事計画に含まれる工事費用を用いることができる。 The power plant evaluation index providing unit 17 obtains the actual power generation amount and the expected construction cost, and provides a predicted power plant evaluation index. As the actual power generation amount, a value obtained by converting the power generation amount performance, which is the actual amount of power generation over a predetermined number of years at a hydroelectric power plant, into a monetary amount can be used. As the expected construction cost, the construction cost included in the construction plan output from the construction plan output section can be used.

発電所評価指標提供部17は、工事計画の確定工事時期に対応する時期の発電量実績額に、前記取得した予想工事費用を加えた値を予想の発電所評価指標として出力することができる。この発電所評価指標は、工事時期に本来は発電できたであろう発電量実績を溢水量として考えて、損失として計上し、それに工事費用を損失として加えて計上するものである。 The power plant evaluation index providing unit 17 can output, as a predicted power plant evaluation index, a value obtained by adding the acquired expected construction cost to the actual power generation amount for the period corresponding to the fixed construction period of the construction plan. This power plant evaluation index considers the amount of power that could have been generated during the construction period as the amount of overflow and records it as a loss, and then adds the construction cost as a loss and records it.

図6は発電量実績額の表示例を示す図であり、図7は予定する発電量実績額と実際の発電量を金額に換算した値との比較表示の例を示す図である。図6に示すように、発電所評価指標提供部17は、発電量の実績を表示することによって、発電所の採算性などを評価する指標を発電所評価指標として提供することができる。また、図7に示すように、発電所評価指標提供部17は、予定の発電量(発電量実績額)と実際の発電量(発電量実際額)とを比較表示させて評価指標として表示することによって、工事計画が効率よく設定されたかなどを評価することができる。ここで発電量実際額は、実際の発電量である実際発電量を金額に換算した値である。図6、7に示すように、発電量を金額に換算して表示してもよいし、発電量をMWなどの電力量のまま表示してもよい。 FIG. 6 is a diagram illustrating an example of displaying the actual power generation amount, and FIG. 7 is a diagram illustrating an example of displaying a comparison between the expected power generation amount actual amount and the value obtained by converting the actual power generation amount into a monetary amount. As shown in FIG. 6, the power plant evaluation index providing unit 17 can provide an index for evaluating the profitability of the power plant as a power plant evaluation index by displaying the actual power generation amount. Further, as shown in FIG. 7, the power plant evaluation index providing unit 17 compares and displays the planned power generation amount (actual power generation amount) and the actual power generation amount (actual power generation amount) and displays the result as an evaluation index. By doing so, it is possible to evaluate whether the construction plan has been set efficiently. Here, the actual power generation amount is a value obtained by converting the actual power generation amount, which is the actual power generation amount, into a monetary amount. As shown in FIGS. 6 and 7, the amount of power generation may be converted into a monetary amount and displayed, or the amount of power generation may be displayed as a power amount such as MW.

保全・工事・停止計画格納部18は、水力発電所の保全計画、工事計画、停止計画の情報を格納する格納部である。確定する前の工事計画である希望工事計画を一時的に格納することもできる。また、水力発電所には、発電が止まる要素として、工事計画と保全計画とがある。工事計画は、突発的に発生する故障などを原因とした設備に対する作業の計画である。保全計画は、設備の定期点検などのあらかじめスケジュールされた設備に対する作業の計画である。 The maintenance/construction/shutdown plan storage unit 18 is a storage unit that stores information on maintenance plans, construction plans, and shutdown plans for the hydroelectric power plant. It is also possible to temporarily store a desired construction plan, which is a construction plan before it is finalized. Furthermore, in a hydroelectric power plant, there are construction plans and maintenance plans as factors that stop power generation. The construction plan is a plan for work on equipment due to unexpected failures. A maintenance plan is a plan for pre-scheduled work on equipment, such as periodic inspection of equipment.

図8は、停止情報提供サーバ20に格納される停止項目テーブルの一例を示す図である。図8に示すように、停止項目テーブルは、工事計画の対象となる機器と、工事計画の対象とした機器を停止する場合に発電の停止が必要となる発電設備とを対応付けたテーブルである。停止情報提供サーバ20は、停止設備判定部12の要求に応じて、停止項目テーブルを参照して必要な情報を渡す。たとえば、停止設備判定部12から、「1号機配電盤」を工事する場合に停止対象機器が何になるかを問い合わせる要求を受け取ると、図3のテーブルを参照して、停止対象の機器が「1号機停止」であるということを停止設備判定部12に渡す。 FIG. 8 is a diagram showing an example of a suspension item table stored in the suspension information providing server 20. As shown in FIG. 8, the shutdown item table is a table that associates the equipment targeted by the construction plan with the power generation equipment whose power generation needs to be stopped when the equipment targeted by the construction plan is shut down. . The outage information providing server 20 refers to the outage item table and passes necessary information in response to a request from the outage equipment determination unit 12. For example, when receiving a request from the shutdown equipment determination unit 12 to inquire about the equipment to be shut down when construction is performed on the "Unit 1 switchboard," the table in FIG. The information that "the machine is stopped" is passed to the stopped equipment determination section 12.

図2に戻って、実績管理サーバ30は、水量実績データ31と発電量実績データ32とを格納した実績データベースを有している。 Returning to FIG. 2, the performance management server 30 has a performance database that stores water volume performance data 31 and power generation performance data 32.

図9、10は、実績データベースに格納された水量実績データ31の一例を示す図である。水量実績データ31は、水力発電所において利用可能な水量が過去どのぐらいであったかを示す水量の変動実績である。変動実績は、時間軸に対して水量がどのように変動したかがわかればよく、日ごとの実績でもよいし、時間ごとの実績でもよい。また、変動実績は複数年の水量の平均値を用いることが好ましい。
水量実績データは、溢水量算出部13において取得した際に、ディスプレイである出力部16において表示してもよい。表示する場合、図9に示すように年間を通じた水量の変動実績(河川自流)を1つの画面で表示した後に、選択した月における日ごとの水量の変動実績の詳細を図10に示すようにしてもよい。
9 and 10 are diagrams showing an example of the water amount performance data 31 stored in the performance database. The water amount record data 31 is a record of water amount fluctuations indicating how much water was available in the past at the hydroelectric power plant. The fluctuation performance only needs to show how the amount of water fluctuates with respect to the time axis, and may be a daily performance or an hourly performance. In addition, it is preferable to use the average value of water amount over multiple years as the fluctuation record.
The water amount performance data may be displayed on the output section 16, which is a display, when acquired by the overflow amount calculation section 13. When displaying, as shown in Figure 9, after displaying the actual water volume fluctuations throughout the year (river flow) on one screen, the details of the daily water volume fluctuations in the selected month can be displayed as shown in Figure 10. You can.

次に、本実施形態にかかる水力発電所の工事計画の最適化支援サーバの動作について説明する。図11は本実施形態にかかる水力発電所の工事計画の最適化支援サーバの動作を示すフローチャートである。図12はワークオーダ入力画面の一例を示す図である。
工事計画の最適化支援サーバ10は、入力部11においてワークオーダの入力を受け付けることができる(ステップS91)。ワークオーダとは、希望する工事計画を入力するフォーマットであり、たとえば、作業件名、発電所名、対象機器、要求日時などの項目を入力することができる。工事計画の最適化支援サーバ10は、ワークオーダの入力を受け付ける際に、図12に示すように、これらの項目を入力するフォーマットを出力部16において表示することができる。
Next, the operation of the optimization support server for construction plans for a hydroelectric power plant according to this embodiment will be explained. FIG. 11 is a flowchart showing the operation of the construction plan optimization support server for a hydroelectric power plant according to this embodiment. FIG. 12 is a diagram showing an example of a work order input screen.
The construction plan optimization support server 10 can receive input of a work order at the input unit 11 (step S91). A work order is a format for inputting a desired construction plan, and for example, items such as a work title, power plant name, target equipment, requested date and time can be input. When receiving the input of a work order, the construction plan optimization support server 10 can display a format for inputting these items on the output unit 16, as shown in FIG.

ワークオーダの入力を受け付けると、停止設備判定部12は、発電の停止が必要となる発電設備があるかを判定する(ステップS92)。停止設備判定部12は、発電の停止が必要となる発電設備があると判定した場合(ステップS92:Yes)は、停止すべき発電設備の情報を溢水量算出部13に送る。一方で、停止設備判定部12は、発電の停止が必要となる発電設備がないと判定した場合(ステップS92:Yes)は、停止すべき発電設備がないことを工事計画確定部15に送る。 Upon receiving the input of the work order, the shutdown equipment determination unit 12 determines whether there is any power generation equipment that requires stopping power generation (step S92). If the shutdown equipment determination unit 12 determines that there is a power generation equipment whose power generation needs to be stopped (step S92: Yes), it sends information on the power generation equipment to be stopped to the overflow amount calculation unit 13. On the other hand, if the shutdown equipment determining unit 12 determines that there is no power generation equipment whose power generation needs to be stopped (step S92: Yes), it sends to the construction plan determining unit 15 that there is no power generation equipment to be stopped.

発電の停止が必要となる発電設備があると判定された場合(ステップS92:Yes)、溢水量算出部13は、停止が必要とされた発電設備に関する水量実績に基づいて発電設備の停止による溢水量を算出する(ステップS93)。溢水量算出部13は、算出した溢水量を提案部14に渡す。 If it is determined that there is a power generation facility whose power generation needs to be stopped (step S92: Yes), the overflow amount calculation unit 13 calculates the overflow due to the stoppage of the power generation facility based on the actual water amount related to the power generation facility whose power generation needs to be stopped. The amount of water is calculated (step S93). The overflow amount calculation unit 13 passes the calculated overflow amount to the proposal unit 14.

提案部14は、溢水量算出部13で算出した溢水量に基づいて希望の工事時期を別の工事時期に変更することを提案する(ステップS94)。提案部14は、溢水量が小さい順に別の工事時期を提案することができる。提案の順番は効率よく工事計画を設定できるものであればよい。 The proposal unit 14 proposes changing the desired construction period to another construction period based on the overflow amount calculated by the overflow amount calculation unit 13 (step S94). The proposal unit 14 can propose different construction periods in descending order of the amount of overflow. The order of proposals may be such that the construction plan can be set efficiently.

工事計画確定部15は、工事時期の変更を確定する入力を受け付けることができる(ステップS95)。確定する入力を受け付けた場合(ステップS95:Yes)、工事計画確定部15は、確定した工事時期で入力された工事計画を確定する(ステップS96)。工事計画確定部15は、確定した工事計画を保全・工事・停止計画格納部18に格納することができる。一方で、確定する入力を受けなかった場合(ステップS95:No)は、工事計画確定部15は、提案部14に再度の提案を実行するように指示する。 The construction plan confirmation unit 15 can receive an input to confirm a change in the construction period (step S95). If the input to be finalized is received (step S95: Yes), the construction plan determination unit 15 finalizes the input construction plan with the determined construction period (step S96). The construction plan confirmation unit 15 can store the confirmed construction plan in the maintenance/construction/stoppage plan storage unit 18. On the other hand, if no finalizing input is received (step S95: No), the construction plan finalizing unit 15 instructs the proposing unit 14 to execute the proposal again.

以上説明した水力発電所の工事計画の最適化支援サーバを備えた水力発電所の工事計画の最適化支援システムによれば、水力発電所における工事計画を管理する際に、水力発電において発電効率低下の要因として考えられる溢水量を算出して、算出結果に基づいて最適な時期を提案することができるので、効率的な発電を行うための工事計画を設定することを支援することができる。 According to the hydropower plant construction plan optimization support system equipped with the hydropower plant construction plan optimization support server described above, when managing the construction plan at the hydropower plant, it is possible to reduce the power generation efficiency in hydropower generation. It is possible to calculate the amount of overflow that is considered to be a factor, and to propose the optimal timing based on the calculation results, supporting the setting of construction plans for efficient power generation.

なお、以上の実施形態では、提案部14は、別の工事時期を提案する手法として、溢水量が小さい順番で工事時期を提案していたが、これとは異なる手法で提案してもよい。たとえば、溢水量算出部13で算出した複数の時期における溢水量を出力部16において視覚的に表現(ディスプレイ表示)することもできる。 In addition, in the above embodiment, the proposal unit 14 proposed construction times in descending order of the amount of overflow as a method of proposing different construction times, but a method different from this may be used. For example, the overflow amount calculated by the overflow amount calculating section 13 at a plurality of periods can be visually expressed (displayed) on the output section 16.

なお、以上の実施形態では、水力発電所の工事計画の最適化支援システムを複数のサーバで構成した例を示したが、これに限定されない。停止項目テーブルと水量実績データおよび発電量実績データとを格納した実績データベースとを工事計画の最適化支援サーバ内に設けてもよい。 In addition, although the above embodiment showed the example which comprised the optimization support system of the construction plan of a hydroelectric power plant by several servers, it is not limited to this. A performance database storing the stop item table, water amount performance data, and power generation amount performance data may be provided in the construction plan optimization support server.

10 工事計画の最適化支援サーバ
11 入力部
12 停止設備判定部
13 溢水量算出部
14 提案部
15 工事計画確定部
16 出力部
17 発電所評価指標提供部
18 保全・工事・停止計画格納部
20 停止情報提供サーバ
30 実績管理サーバ
10 Construction plan optimization support server 11 Input section 12 Shutdown equipment determination section 13 Overflow amount calculation section 14 Proposal section 15 Construction plan confirmation section 16 Output section 17 Power plant evaluation index provision section 18 Maintenance/construction/shutdown plan storage section 20 Shutdown Information provision server 30 Performance management server

Claims (11)

水力発電所の設備内の機器に対して工事を希望する工事時期である希望工事時期を含む希望の工事計画の入力を受け付ける工事計画入力部と、
前記入力を受け付けた希望の工事計画の対象となる機器を停止させた場合に、発電の停止を必要とする発電設備を判定する停止設備判定部と、
前記停止設備判定部において停止が必要と判定された発電設備がある場合に、停止が必要と判定された発電設備に関する水量実績に基づいて発電設備の停止による溢水量を算出する溢水量算出部と、
前記算出した溢水量に基づいて、前記希望工事時期を別の工事時期に変更することを提案する提案部と、
前記提案部で提案された別の工事時期に応じた工事時期の変更を確定する入力を受け付けて、該確定を受け付けた工事時期を確定工事時期として工事計画を確定する工事計画確定部と、
前記工事計画確定部で確定された工事計画を出力する工事計画出力部と、
を備え
停止設備判定部は、工事計画の対象となる機器と、当該機器を停止する場合に発電の停止が必要となる発電設備とを対応付けた停止項目テーブルを参照することにより停止が必要となる設備の判定を行い、
前記提案部は、希望工事時期における溢水量より溢水量が小さくなる工事時期を優先的に提案し、溢水量が小さいと判断した溢水量と同じ溢水量の工事時期が複数ある場合は、当該複数の工事時期のうちで前記希望工事時期に最も近い工事時期を優先的に提案することを特徴とする水力発電所の工事計画の最適化支援サーバ。
a construction plan input unit that accepts input of a desired construction plan including a desired construction period, which is the desired construction period for the equipment in the equipment of the hydroelectric power plant;
a shutdown equipment determination unit that determines power generation equipment that requires power generation to be stopped when equipment targeted by the desired construction plan that has received the input is stopped;
an overflow amount calculation unit that calculates the amount of water overflow due to the stoppage of the power generation equipment based on the water volume record of the power generation equipment that has been determined to need to be stopped, when the stop equipment determination unit determines that the power generation equipment needs to be stopped; ,
a proposal department that proposes changing the desired construction period to another construction period based on the calculated overflow amount;
a construction plan confirmation unit that accepts an input to confirm a change in the construction period according to another construction period proposed by the proposal unit, and finalizes the construction plan by setting the construction period for which the confirmation has been accepted as the final construction period;
a construction plan output unit that outputs the construction plan determined by the construction plan determination unit;
Equipped with
The shutdown equipment determination unit identifies equipment that needs to be shut down by referring to a shutdown item table that associates the equipment targeted by the construction plan with the power generation equipment whose power generation needs to be stopped when the equipment is shut down. make a judgment,
The proposal department shall prioritize the construction period in which the amount of overflow will be smaller than the amount of overflow in the desired construction period, and if there are multiple construction periods with the same amount of overflow as the amount of overflow judged to be small, the proposal department shall A support server for optimizing a construction plan for a hydroelectric power plant, characterized in that it preferentially proposes a construction period that is closest to the desired construction period among the construction periods .
前記工事計画確定部は、前記停止設備判定部において発電の停止を必要とする発電設備がないと判定した場合に、前記工事計画入力部で入力を受け付けた工事計画を確定することを特徴とする請求項1に記載の水力発電所の工事計画の最適化支援サーバ。 The construction plan confirmation unit is characterized in that when the shutdown equipment determination unit determines that there is no power generation equipment that requires stopping power generation, the construction plan determination unit determines the construction plan input by the construction plan input unit. The optimization support server for a construction plan for a hydroelectric power plant according to claim 1. 前記溢水量算出部は、前記発電設備に関する水量の所定年数に亘る実績を格納した水量データベースを参照することにより前記発電設備に関する水量実績を取得することを特徴とする請求項1または2に記載の水力発電所の工事計画の最適化支援サーバ。 3. The overflow amount calculation unit obtains the water amount performance regarding the power generation equipment by referring to a water amount database that stores the water amount performance over a predetermined number of years regarding the power generation equipment. Optimization support server for construction plans for hydroelectric power plants. 前記水力発電所における所定年数に亘る発電量の月ごとの実績である発電量実績を金額に換算した月ごとの発電量実績額と、前記工事計画出力部から出力された工事計画に含まれる工事費用である予想工事費用とを取得して、前記月ごとの発電量実績額から換算された当該工事計画の確定工事時期に対応する時期の発電量実績額に、前記取得した予想工事費用を加えた値を予想の発電所評価指標として提供する発電所評価指標提供部とをさらに備えることを特徴とする請求項1からのいずれか1項に記載の水力発電所の工事計画の最適化支援サーバ。 The actual amount of power generated each month, which is the monthly amount of power generated over a predetermined number of years at the hydroelectric power station, converted into a monetary amount, and the construction work included in the construction plan output from the construction plan output section. Obtain the estimated construction cost, which is the cost, and add the estimated construction cost obtained above to the actual power generation amount for the period corresponding to the final construction period of the construction plan, which is converted from the actual power generation amount for each month. 4. Optimization support for a construction plan for a hydroelectric power plant according to any one of claims 1 to 3 , further comprising a power plant evaluation index providing unit that provides the estimated value as a predicted power plant evaluation index. server. 前記発電所評価指標提供部は、前記水力発電所における実際の発電量である月ごとの実際発電量を金額に換算した月ごとの発電量実際額を取得し、月ごとの発電量実際額と前記月ごとの発電量実績額との比較表示を、評価指標として提供することを特徴とする請求項に記載の水力発電所の工事計画の最適化支援サーバ。 The power plant evaluation index providing unit obtains the actual amount of power generated each month, which is the actual amount of power generated each month , which is the actual amount of power generated at the hydroelectric power station, converted into a monetary amount, and calculates the actual amount of power generated each month. 5. The optimization support server for a construction plan for a hydroelectric power plant according to claim 4, wherein a comparative display of the amount and the actual amount of power generation amount for each month is provided as an evaluation index. 請求項1からのいずれか1項に記載された水力発電所の工事計画の最適化支援サーバと、
工事計画の対象となる機器と、該機器を停止する場合に発電の停止が必要となる発電設備とを対応付けた停止項目テーブルを格納した停止情報提供サーバと、
前記発電設備に関する水量の所定年数に亘る実績を格納した実績データベースを格納した実績管理サーバとを備えたことを特徴とする水力発電所の工事計画の最適化支援システム。
A support server for optimizing construction plans for a hydroelectric power plant according to any one of claims 1 to 5 ;
an outage information providing server that stores a outage item table that associates equipment targeted by the construction plan with power generation equipment whose power generation needs to be stopped when the equipment is stopped;
1. A support system for optimizing construction plans for a hydroelectric power plant, comprising: a performance management server that stores a performance database that stores water volume performance over a predetermined number of years regarding the power generation equipment.
水力発電所の工事計画の最適化支援サーバが各工程を実行する水力発電所の工事計画の最適化支援方法であって、
水力発電所の設備内の機器に対して工事を希望する工事時期である希望工事時期を含む希望の工事計画の入力を受け付ける工事計画入力工程と、
前記入力を受け付けた希望の工事計画の対象となる機器を停止させた場合に、発電の停止を必要とする発電設備があるか否かを判定する停止設備判定工程と、
前記停止設備判定工程において停止が必要と判定された発電設備がある場合に、停止が必要と判定された発電設備に関する水量実績に基づいて発電設備の停止による溢水量を算出する溢水量算出工程と、
前記算出した溢水量に基づいて、前記希望工事時期を別の工事時期に変更することを提案する提案工程と、
前記提案工程で提案された別の工事時期に応じた工事時期の変更を確定する入力を受け付けて、該確定を受け付けた工事時期を確定工事時期として工事計画を確定する工事計画確定工程と、
前記工事計画確定工程で確定された工事計画を出力する工事計画出力工程と、
を含み、
停止設備判定工程は、工事計画の対象となる機器と、当該機器を停止する場合に発電の停止が必要となる発電設備とを対応付けた停止項目テーブルを参照することにより停止が必要となる設備の判定を行い、
前記提案工程は、希望工事時期における溢水量より溢水量が小さくなる工事時期を優先的に提案し、溢水量が小さいと判断した溢水量と同じ溢水量の工事時期が複数ある場合は、当該複数の工事時期のうちで前記希望工事時期に最も近い工事時期を優先的に提案することを特徴とする水力発電所の工事計画の最適化支援方法。
A method for supporting the optimization of a construction plan for a hydroelectric power plant, wherein a support server for optimizing the construction plan for a hydroelectric power plant executes each process, the method comprising:
a construction plan input step that receives an input of a desired construction plan including a desired construction period, which is the desired construction period for the equipment in the equipment of the hydroelectric power plant;
A stopped equipment determination step of determining whether there is any power generation equipment that requires stopping power generation when the equipment targeted by the desired construction plan that has received the input is stopped;
an overflow amount calculation step of calculating the amount of overflow due to the shutdown of the power generation equipment based on the water volume record of the power generation equipment determined to be required to be shut down, when there is power generation equipment that is determined to need to be shut down in the shutdown equipment determination step; ,
a proposal step of proposing to change the desired construction period to another construction period based on the calculated overflow amount;
a construction plan confirmation step of accepting an input to confirm a change in the construction period according to another construction period proposed in the proposal step, and finalizing the construction plan by setting the construction period for which the confirmation has been accepted as the final construction period;
a construction plan output step that outputs the construction plan determined in the construction plan determination step;
including;
The equipment to be shut down determination process is performed by referring to a shutdown item table that associates the equipment targeted by the construction plan with the power generation equipment whose power generation needs to be stopped if the equipment is to be shut down. make a judgment,
The above proposal process prioritizes the construction period in which the amount of overflow is smaller than the amount of overflow in the desired construction period, and if there are multiple construction periods with the same amount of overflow as the amount of overflow judged to be small, the construction period is A method for supporting the optimization of a construction plan for a hydroelectric power plant , the method comprising: preferentially proposing a construction period that is closest to the desired construction period among the construction periods .
前記工事計画確定工程は、前記停止設備判定工程において発電の停止を必要とする発電設備がないと判定した場合に、前記工事計画入力工程で入力を受け付けた工事計画を確定することを特徴とする請求項に記載の水力発電所の工事計画の最適化支援方法。 The construction plan confirmation step is characterized in that, when it is determined in the shutdown equipment determination step that there is no power generation equipment that requires the suspension of power generation, the construction plan input in the construction plan input step is determined. The method for supporting optimization of a construction plan for a hydroelectric power plant according to claim 7 . 前記溢水量算出工程は、前記発電設備に関する水量の所定年数に亘る実績を格納した水量データベースを参照することにより前記発電設備に関する水量実績を取得することを特徴とする請求項7または8のいずれか1項に記載の水力発電所の工事計画の最適化支援方法。 9. The overflow amount calculating step includes obtaining the actual water amount regarding the power generation facility by referring to a water amount database that stores the amount of water over a predetermined number of years regarding the power generation facility. A method for supporting optimization of a construction plan for a hydroelectric power plant as described in Section 1. 前記水力発電所における所定年数に亘る発電量の月ごとの実績である発電量実績を金額に換算した月ごとの発電量実績額と、前記工事計画出力工程において出力された工事計画に含まれる工事費用である予想工事費用とを取得して、前記月ごとの発電量実績額から換算された当該工事計画の確定工事時期に対応する時期の前記発電量実績額に、前記取得した予想工事費用を加えた値を予想の発電所評価指標として提供する発電所評価指標提供工程とをさらに含むことを特徴とする請求項からのいずれか1項に記載の水力発電所の工事計画の最適化支援方法。 The actual amount of power generated each month, which is the monthly amount of power generated over a specified number of years at the hydroelectric power station, converted into a monetary amount, and the construction work included in the construction plan output in the construction plan output process. Obtain the estimated construction cost, which is the cost, and add the obtained estimated construction cost to the actual power generation amount for the period corresponding to the final construction period of the construction plan converted from the actual power generation amount for each month. Optimization of a construction plan for a hydroelectric power plant according to any one of claims 7 to 9 , further comprising a power plant evaluation index providing step of providing the added value as a predicted power plant evaluation index. How to help. 前記発電所評価指標提供工程は、前記水力発電所における実際の発電量である月ごとの実際発電量を金額に換算した月ごとの発電量実際額を取得し、月ごとの発電量実際額と前記月ごとの発電量実績額との比較表示を、評価指標として提供することを特徴とする請求項10に記載の水力発電所の工事計画の最適化支援方法。 In the power plant evaluation index providing step, the actual power generation amount for each month is obtained by converting the actual power generation amount for each month , which is the actual power generation amount at the hydroelectric power plant, into a monetary amount, and the actual amount of power generation for each month is obtained. 11. The method for supporting optimization of a construction plan for a hydroelectric power plant according to claim 10 , further comprising providing a comparative display of the amount and the actual amount of power generation for each month as an evaluation index.
JP2019160601A 2019-09-03 2019-09-03 Hydropower plant construction plan optimization support server, hydropower plant construction plan optimization support system, and hydropower plant construction plan optimization support method Active JP7412673B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019160601A JP7412673B2 (en) 2019-09-03 2019-09-03 Hydropower plant construction plan optimization support server, hydropower plant construction plan optimization support system, and hydropower plant construction plan optimization support method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019160601A JP7412673B2 (en) 2019-09-03 2019-09-03 Hydropower plant construction plan optimization support server, hydropower plant construction plan optimization support system, and hydropower plant construction plan optimization support method

Publications (2)

Publication Number Publication Date
JP2021039550A JP2021039550A (en) 2021-03-11
JP7412673B2 true JP7412673B2 (en) 2024-01-15

Family

ID=74848820

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019160601A Active JP7412673B2 (en) 2019-09-03 2019-09-03 Hydropower plant construction plan optimization support server, hydropower plant construction plan optimization support system, and hydropower plant construction plan optimization support method

Country Status (1)

Country Link
JP (1) JP7412673B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114139873A (en) * 2021-11-03 2022-03-04 北京华能新锐控制技术有限公司 Method and device for judging the commissioning of power generation equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007241869A (en) 2006-03-10 2007-09-20 Chugoku Electric Power Co Inc:The Work information providing system, server and work information providing method
JP2008202983A (en) 2007-02-16 2008-09-04 Matsushita Electric Works Ltd Electric power monitoring system
JP2013125369A (en) 2011-12-14 2013-06-24 Chugoku Electric Power Co Inc:The Power generating/transforming equipment repair planning support system and repair planning support method thereof
JP2014186503A (en) 2013-03-22 2014-10-02 Toshiba Corp Profit analyzer for power generation facility, method and program
JP2015146065A (en) 2014-01-31 2015-08-13 中国電力株式会社 Forecasting system and forecasting method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007241869A (en) 2006-03-10 2007-09-20 Chugoku Electric Power Co Inc:The Work information providing system, server and work information providing method
JP2008202983A (en) 2007-02-16 2008-09-04 Matsushita Electric Works Ltd Electric power monitoring system
JP2013125369A (en) 2011-12-14 2013-06-24 Chugoku Electric Power Co Inc:The Power generating/transforming equipment repair planning support system and repair planning support method thereof
JP2014186503A (en) 2013-03-22 2014-10-02 Toshiba Corp Profit analyzer for power generation facility, method and program
JP2015146065A (en) 2014-01-31 2015-08-13 中国電力株式会社 Forecasting system and forecasting method

Also Published As

Publication number Publication date
JP2021039550A (en) 2021-03-11

Similar Documents

Publication Publication Date Title
Eslami et al. A new formulation to reduce the number of variables and constraints to expedite SCUC in bulky power systems
Zhang et al. Hourly electricity demand response in the stochastic day-ahead scheduling of coordinated electricity and natural gas networks
Joung et al. Assessing demand response and smart metering impacts on long-term electricity market prices and system reliability
KR101698224B1 (en) Building energy consumption analysis system
US20170207629A1 (en) Industrial demand response enabling system, industrial demand response enabling method, and program
JP2010114968A (en) Apparatus, method, and control program for periodical inspection planning
JP6936117B2 (en) Power planning equipment, power supply and demand control system, and power planning method
US20150051938A1 (en) Systems, methods and apparatus for optimizing fuel mix, fuel allocation and scheduling of generator resources
JP5078128B2 (en) Operation method, prediction error compensation device, meteorological power generation planning device, and program
JP2008245374A (en) Generator output amount determination system, method and program
Valenzuela et al. Cournot prices considering generator availability and demand uncertainty
JP7412673B2 (en) Hydropower plant construction plan optimization support server, hydropower plant construction plan optimization support system, and hydropower plant construction plan optimization support method
Chang et al. Efficiency and deregulation of the electricity market in Singapore
JP2017182399A (en) Electric power system operation control system, and method and program
JP2017173945A (en) Contract power optimizer
Andrianesis et al. The" hidden cost" of renewable energy sources in electricity pool markets
Thomas et al. An advanced security constrained opf that produces correct market-based pricing
Kicherer et al. Heat4Future: A strategic planning tool for decarbonizing district heating systems
JP2017084347A (en) Plan creation device, plan creation method, program, data, and generator control device
Dai et al. Calculating wind variability costs with considering ramping costs of conventional power plants
JP2003235158A (en) Energy supply management system, energy supply management method, and program
JP4726724B2 (en) Generator output amount determination device, method, and program
JP7552373B2 (en) Power system power flow prediction system and power flow prediction method
Dalvi THE VALUE OF FLEXIBILITY IN ELECTRICITY MARKETS FROM GAS TURBINE UPGRADES: A STOCHASTIC MIXED INTEGER PROGRAMMING APPROACH
JP4721666B2 (en) Generator output amount determination device, generator output amount determination method, and program

Legal Events

Date Code Title Description
RD07 Notification of extinguishment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7427

Effective date: 20220204

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220715

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230627

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230704

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20230828

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230919

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231127

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231210

R150 Certificate of patent or registration of utility model

Ref document number: 7412673

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150