JP7414658B2 - How to repair existing rails - Google Patents
[go: Go Back, main page]

JP7414658B2 - How to repair existing rails - Google Patents

How to repair existing rails Download PDF

Info

Publication number
JP7414658B2
JP7414658B2 JP2020117914A JP2020117914A JP7414658B2 JP 7414658 B2 JP7414658 B2 JP 7414658B2 JP 2020117914 A JP2020117914 A JP 2020117914A JP 2020117914 A JP2020117914 A JP 2020117914A JP 7414658 B2 JP7414658 B2 JP 7414658B2
Authority
JP
Japan
Prior art keywords
existing rail
temporary lining
running
concrete
removal step
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020117914A
Other languages
Japanese (ja)
Other versions
JP2022015215A (en
Inventor
茂広 松田
賢司 南出
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2020117914A priority Critical patent/JP7414658B2/en
Publication of JP2022015215A publication Critical patent/JP2022015215A/en
Application granted granted Critical
Publication of JP7414658B2 publication Critical patent/JP7414658B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Description

本発明は、既設軌条の改修方法に関する。 The present invention relates to a method for repairing an existing rail.

列車が走行する軌条を改修するに際しては、例えば特許文献1に示すような方法があった。かかる改修方法は、コンクリート基礎の上面を斫った後、型枠を設置し、型枠内にベースプレート、鉄筋及びアンカーを配設した状態で、当該型枠内であって軌条と既設のコンクリート基礎との間に、グラウトを打設するものである。グラウトは、鉄筋及びアンカーが配設された状態で自己流動するフロー値を有し、且つコンクリートと同等以上の強度を有するものであり、ベースプレートとコンクリート基礎との間に充填される。 When repairing the rails on which trains run, there is a method as shown in Patent Document 1, for example. This repair method involves cutting down the top surface of the concrete foundation, installing a formwork, and installing base plates, reinforcing bars, and anchors inside the formwork, and removing the rails and existing concrete foundation within the formwork. Grout is placed between the two. Grout has a flow value that allows it to self-flow when reinforcing bars and anchors are installed, and has strength equal to or higher than concrete, and is filled between the base plate and the concrete foundation.

特開2015-71892号公報Japanese Patent Application Publication No. 2015-71892

特許文献1の改修方法では、グラウトが硬化するまでに多くの時間を要する。通常、軌条の改修工事は、夜間の線閉時間(線路閉鎖時間)内に行われることが多いため、グラウトの硬化時間を確保しようとすると、一日に実施できる作業内容が限られてしまい、工事を効率的に行うのが困難であるという問題があった。 In the repair method of Patent Document 1, it takes a long time for the grout to harden. Normally, track repair work is often carried out during nighttime track closure hours, so if you try to secure enough time for the grout to harden, the amount of work that can be done in a day is limited. There was a problem that it was difficult to carry out construction efficiently.

このような観点から、本発明は、夜間の線閉時間内での工事を効率的に行うことができる既設軌条の改修方法を提供することを課題とする。 From this point of view, it is an object of the present invention to provide a method for repairing existing rails that allows construction work to be carried out efficiently during nighttime line closing hours.

前記課題を解決するための本発明は、底板上に敷設された道床コンクリートの上に走行層が形成された既設軌条の改修方法である。かかる既設軌条の改修方法は、前記既設軌条の上部を撤去する撤去工程と、前記桁体を設置する前の前記既設軌条の上部に、既設の前記走行層の表面高さと同等の高さの表面部を有する仮覆工を設置する仮覆工設置工程と、上部が撤去された前記既設軌条の上に、既設軌条の延在方向に間隔をあけて複数の支承体を設置する支承体設置工程と、複数の前記支承体に、上面が走行面となる桁体を架け渡す桁体設置工程とを備え、前記撤去工程および前記仮覆工設置工程は、昼間の鉄道営業を挟んで複数回行われ、前記撤去工程は、前記支承体が設置される部分の前記既設軌条を撤去して凹部を形成する第一撤去工程と、前記第一撤去工程で形成された前記凹部同士の間の前記既設軌条を撤去する第二撤去工程とを備え、前記第二撤去工程は、前記支承体設置工程の後、または前記支承体設置工程と並行して行われ、前記撤去工程では、前記道床コンクリートを斫ることで前記既設軌条の上部を撤去し、前記第一撤去工程以降の前記仮覆工設置工程では、前記撤去工程で形成された前記凹部に設置された前記支承体と前記仮覆工の表面部の設置位置との間にブロック状の高さ調整材を設置した後に、前記仮覆工を被せることを特徴とする。 The present invention for solving the above problems is a method for repairing an existing rail in which a running layer is formed on track bed concrete laid on a bottom plate. Such a method for repairing an existing rail includes a removal step of removing the upper part of the existing rail, and a surface having a height equivalent to the surface height of the existing running layer on the upper part of the existing rail before installing the girder. a temporary lining installation step in which a temporary lining having a section is installed; and a support installation step in which a plurality of supports are installed at intervals in the extending direction of the existing rail on the existing rail whose upper part has been removed. and a girder installation step of bridging girder bodies whose upper surfaces serve as running surfaces over a plurality of the support bodies, and the removal step and the temporary lining installation step are performed multiple times during daytime railway operations. The removal step includes a first removal step of removing the existing rail in the part where the support is installed to form a recess, and a removal step of removing the existing rail between the recesses formed in the first removal step. a second removal step of removing the rail, the second removal step is performed after the support installation step or in parallel with the support installation step, and in the removal step, the track bed concrete is removed. The upper part of the existing rail is removed by After a block-shaped height adjusting material is installed between the installation position of the section and the installation position of the section, the temporary lining is covered .

本発明の既設軌条の改修方法によれば、支承体設置工程で設置された支承体に、桁体設置工程で桁体を架け渡すことで走行面を形成できるので、施工スピードを速くすることができ、夜間の線閉時間内での工事を効率的に行うことができる。また、施工途中の支承体を覆うように仮覆工を設ければ、桁体の設置前であっても工事を一旦中断できるので、列車の運行に支障を来すことなく改修工事を進めることができる。さらに、仮覆工を設けることで、昼間の営業時間内は列車を走行させることができる。したがって、数日に渡る夜間の線閉時間内で工事を順次進めていくことができる。 According to the method for repairing an existing rail of the present invention, a running surface can be formed by spanning the girders installed in the girder installation process over the supports installed in the support installation process, so the construction speed can be increased. This allows construction work to be carried out efficiently during line closing hours at night. Additionally, if a temporary lining is installed to cover the support that is currently under construction, construction can be temporarily interrupted even before the girder is installed, allowing the repair work to proceed without disrupting train operations. Can be done. Furthermore, by installing a temporary lining, trains can run during daytime business hours. Therefore, the construction work can be carried out one by one during the line closing hours at night over several days.

さらに、前記仮覆工設置工程では、断面門型の仮覆工を施工途中の前記道床コンクリートに被せることが好ましい。このような方法によれば、既設軌条と同じ高さの仮覆工を容易に設置することができる。 Furthermore, in the temporary lining installation step, it is preferable that a temporary lining having a gate-shaped cross section be placed over the concrete track bed that is currently being constructed. According to such a method, it is possible to easily install a temporary lining of the same height as the existing rail.

また、本発明の既設軌条の改修方法においては、前記仮覆工設置工程では、前記仮覆工の上部にアスファルトを敷設して走行面とすることが好ましい。このような方法によれば、軌道の連続性を確保できる。 Further, in the method for repairing an existing rail according to the present invention, it is preferable that in the temporary lining installation step, asphalt is laid on top of the temporary lining to form a running surface. According to such a method, continuity of the trajectory can be ensured.

本発明によれば、夜間の線閉時間内での工事を効率的に行うことができるという優れた効果を発揮する。 Advantageous Effects of Invention According to the present invention, an excellent effect is achieved in that construction work can be efficiently carried out during line closing hours at night.

本発明の実施形態に係る既設軌条の改修構造を示した断面図である。FIG. 1 is a sectional view showing a repair structure for an existing rail according to an embodiment of the present invention. 本発明の実施形態に係る既設軌条の改修構造を示した要部拡大断面図である。FIG. 1 is an enlarged sectional view of a main part showing a repair structure for an existing rail according to an embodiment of the present invention. 本発明の実施形態に係る既設軌条の改修構造を走行方向に沿って切断した断面図である。FIG. 1 is a cross-sectional view of an existing rail repair structure according to an embodiment of the present invention taken along the running direction. 本発明の実施形態に係る既設軌条の改修構造を示した要部拡大斜視図である。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is an enlarged perspective view of main parts showing a repair structure for an existing rail according to an embodiment of the present invention. (a)は既設軌条を示した断面図、(b)は本発明の実施形態に係る既設軌条の改修方法の撤去工程で排水溝の側壁の一部を撤去した状態を示した断面図である。(a) is a sectional view showing an existing rail, and (b) is a sectional view showing a state in which a part of the side wall of a drainage ditch is removed in a removal step of a method for repairing an existing rail according to an embodiment of the present invention. . (a)は本発明の実施形態に係る既設軌条の改修方法の撤去工程で走行層を撤去した状態を示した断面図、(b)は仮覆工設置工程を示した断面図である。(a) is a sectional view showing a state in which the running layer has been removed in the removal process of the existing rail repair method according to the embodiment of the present invention, and (b) is a sectional view showing the temporary lining installation process. 仮覆工を設置した状態を示した断面斜視図である。It is a cross-sectional perspective view showing the state where temporary lining was installed. (a)は本発明の実施形態に係る既設軌条の改修方法の第一撤去工程で道床コンクリートを部分的に撤去して凹部を形成した状態を示した断面図、(b)は図8(a)を走行方向に沿って切断した断面図、(c)は支承体設置工程を示した断面図である。(a) is a sectional view showing a state in which trackbed concrete is partially removed to form a recess in the first removal step of the existing rail repair method according to the embodiment of the present invention, and (b) is a cross-sectional view showing a state in which a recess is formed by partially removing trackbed concrete ) is a cross-sectional view taken along the running direction, and (c) is a cross-sectional view showing the support body installation process. (a)は本発明の実施形態に係る既設軌条の改修方法の仮覆工設置工程で道床コンクリートの上部に高さ調整材を敷設して仮覆工を設置した状態を示した断面図、(b)は図9(a)を走行方向に沿って切断した断面図である。(a) is a sectional view showing a state in which a temporary lining is installed by laying a height adjustment material on top of track bed concrete in the temporary lining installation step of the method for repairing existing rails according to an embodiment of the present invention; b) is a sectional view of FIG. 9(a) taken along the running direction. (a)は本発明の実施形態に係る既設軌条の改修方法の第二撤去工程で道床コンクリートの凹部間を撤去する状態を示した断面図、(b)は図10(a)を走行方向に沿って切断した断面図、(c)は道床コンクリートの凹部間をさらに撤去した状態を示した断面図である。(a) is a cross-sectional view showing the state in which the grooves in the trackbed concrete are removed in the second removal step of the method for repairing existing rails according to the embodiment of the present invention, and (b) is a cross-sectional view of FIG. 10(a) in the traveling direction. (c) is a cross-sectional view taken along the track, and (c) is a cross-sectional view showing a state in which the space between the concave portions of the track bed concrete has been further removed. (a)は本発明の実施形態に係る既設軌条の改修方法の桁体設置工程で支承体に桁体を掛け渡し桁体に仮設の走行路を形成した状態を示した断面図、(b)は図11(a)を走行方向に沿って切断した断面図である。(a) is a sectional view showing a state in which the girder is spanned over the support body and a temporary running path is formed on the girder body in the girder installation step of the method for repairing an existing rail according to an embodiment of the present invention; (b) 11(a) is a cross-sectional view taken along the running direction.

本発明の実施形態に係る既設軌条の改修構造および改修方法について、添付した図面を参照しながら説明する。まず、既設軌条の構成を説明する。図5の(a)は、既設軌条を示した断面図である。図5の(a)に示すように、本実施形態の既設軌条1は、ゴムタイヤ走行輪を備えた列車(電動車両)が走行するものであって、底版コンクリート(底板)2と、底版コンクリート2上に敷設された道床コンクリート3と、道床コンクリート3上に敷設された走行層4とを備えている。底版コンクリート2は、既設軌条1を支持する基礎部分であって、列車よりも広い幅に形成されている。 A repair structure and method for repairing an existing rail according to an embodiment of the present invention will be described with reference to the attached drawings. First, the configuration of the existing rail will be explained. FIG. 5(a) is a sectional view showing the existing rail. As shown in FIG. 5(a), the existing rail 1 of this embodiment is one on which a train (electric vehicle) equipped with rubber tire running wheels runs, and includes a concrete bottom plate (bottom plate) 2 and a concrete bottom plate 2. It includes a track bed concrete 3 laid on top and a running layer 4 laid on the track bed concrete 3. The concrete bottom slab 2 is a foundation part that supports the existing rail 1, and is formed to have a width wider than the train.

道床コンクリート3は、断面矩形を呈しており、ゴムタイヤ走行輪が走行する位置に設けられている。道床コンクリート3は、車幅方向に間隔をあけて一対設けられており、左右一対の道床コンクリート3,3は走行方向に沿って延在している。走行層4は、ゴムタイヤが接触する面であり、道床コンクリート3の上面を保護する。走行層4は、例えばエポキシ舗装にて構成されている。道床コンクリート3,3の間で車幅方向の中間部には、案内軌条5が設けられている。案内軌条5は、車両に設けられた一対の案内輪(図示せず)に両側から挟まれ、車両を所定の方向に安全かつ円滑に誘導する。案内軌条5は、電気の負極としての役目も果たす。道床コンクリート3の左右両側には、排水溝6a,6bが形成されている。排水溝6a,6bは、底版コンクリート2の表面に形成された溝状の凹部である。一対の道床コンクリート3の内側に設けられた排水溝6aの溝幅は、外側に設けられた排水溝6bの溝幅よりも小さくなっている。なお、底版コンクリート2上に道床コンクリート3を敷設することは一例であって、道床コンクリート3に代えて、鋼板を敷設する場合もある。 The trackbed concrete 3 has a rectangular cross section and is provided at a position where the rubber tire running wheels run. A pair of concrete trackbeds 3 are provided at intervals in the vehicle width direction, and the pair of left and right trackbed concretes 3, 3 extend along the traveling direction. The running layer 4 is a surface that the rubber tires come into contact with, and protects the upper surface of the concrete track bed 3. The running layer 4 is made of, for example, epoxy pavement. A guide rail 5 is provided at an intermediate portion in the vehicle width direction between the track bed concrete 3, 3. The guide rail 5 is sandwiched from both sides by a pair of guide wheels (not shown) provided on the vehicle, and safely and smoothly guides the vehicle in a predetermined direction. The guide rail 5 also serves as an electrical negative pole. Drainage channels 6a and 6b are formed on both left and right sides of the concrete track bed 3. The drainage grooves 6a and 6b are groove-shaped recesses formed on the surface of the concrete bottom slab 2. The groove width of the drainage groove 6a provided on the inside of the pair of trackbed concrete 3 is smaller than the groove width of the drainage groove 6b provided on the outside. Note that laying the trackbed concrete 3 on the bottom slab concrete 2 is just one example, and instead of the trackbed concrete 3, a steel plate may be laid.

次に、既設軌条1の改修構造を説明する。図1は、本実施形態に係る既設軌条の改修構造を示した断面図、図2は同じく要部拡大断面図、図3は走行方向に沿って切断した断面図、図4は要部拡大斜視図である。なお、図3は図4のA-A線で切断した断面図である。本実施形態の既設軌条1の改修構造7は、経年劣化した既設軌条1の改修により形成されるものであり、既設軌条1よりも高い耐久性を有している。改修構造7は、図1乃至図4に示すように、支承体10と桁体20とを備えている。 Next, the repair structure of the existing rail 1 will be explained. FIG. 1 is a sectional view showing the repair structure of an existing rail according to this embodiment, FIG. 2 is an enlarged sectional view of the main part, FIG. 3 is a sectional view taken along the running direction, and FIG. 4 is an enlarged perspective view of the main part. It is a diagram. Note that FIG. 3 is a cross-sectional view taken along line AA in FIG. 4. The repair structure 7 for the existing rail 1 of this embodiment is formed by repairing the existing rail 1 that has deteriorated over time, and has higher durability than the existing rail 1. The repair structure 7 includes a support body 10 and a girder body 20, as shown in FIGS. 1 to 4.

支承体10は、桁体20を支持する部材であって、既設軌条1の延在方向(列車の走行方向)に沿って間隔をあけて複数設けられている。支承体10は、H型鋼にて構成されており、ウエブ11の上下でフランジ12,12がそれぞれ水平になり、且つウエブ11が車幅方向に延在するように配置されている。支承体10は、道床コンクリート3の幅寸法と同等の長さを有し、道床コンクリート3が存在していた空間に配置されている。具体的には、道床コンクリート3を撤去することで露出した底版コンクリート2の表面に、下側のフランジ12が載置されている。支承体10は、下側のフランジ12に挿通されたアンカー部材13により、底版コンクリート2に固定されている。なお、支承体10はH型鋼に限定されるものではなく、例えば、角型鋼やプレキャストコンクリート等の他の部材で構成してもよい。 The support bodies 10 are members that support the girder body 20, and are provided in plurality at intervals along the extending direction of the existing rail 1 (the running direction of the train). The support body 10 is made of H-shaped steel, and is arranged so that the flanges 12, 12 above and below the web 11 are horizontal, and the web 11 extends in the vehicle width direction. The support body 10 has a length equivalent to the width dimension of the trackbed concrete 3, and is arranged in the space where the trackbed concrete 3 existed. Specifically, the lower flange 12 is placed on the surface of the bottom slab concrete 2 exposed by removing the track bed concrete 3. The support body 10 is fixed to the bottom slab concrete 2 by an anchor member 13 inserted through a lower flange 12. Note that the support body 10 is not limited to H-shaped steel, and may be made of other members such as square steel or precast concrete.

桁体20は、列車の走行方向に沿って延在しており、複数の支承体10,10・・に架け渡されている。桁体20は、桁材21と走行板22とを備えて構成されている。 The girder body 20 extends along the running direction of the train, and spans the plurality of support bodies 10, 10, . . . . The girder body 20 includes a girder member 21 and a running plate 22.

桁材21は、支承体10,10・・上に架け渡される部材であって、鋼製の長尺材にて構成され、断面H形状を呈している。桁材21は、横板23と側壁板24と補強板25とを備えて構成されており、いわゆるワッフル構造となっている。横板23は、列車の走行方向に沿って延在している。横板23の幅寸法は、道床コンクリート3の幅寸法と同等である。横板23には、後記する座ぐり31(図4参照)に対応する位置にボルト孔(図示せず)が形成されている。ボルト孔には、走行板22を桁材21に固定するためのボルト32(図4参照)の軸部が挿通される。ボルト32の軸部は、ボルト孔を挿通して横板23の下方に向かって延出する。側壁板24は、横板23の幅方向両端部にそれぞれ設けられている。側壁板24は、横板23に直交しており、横板23の端部において上下に延出している、つまり、桁材21は、上方に向かって開口する溝部26aと、下方に向かって開口する溝部26bとを備えている。 The girder member 21 is a member that spans over the supports 10, 10, and is made of a long steel member and has an H-shaped cross section. The beam member 21 includes a horizontal plate 23, a side wall plate 24, and a reinforcing plate 25, and has a so-called waffle structure. The horizontal plate 23 extends along the running direction of the train. The width dimension of the horizontal board 23 is equivalent to the width dimension of the track bed concrete 3. A bolt hole (not shown) is formed in the horizontal plate 23 at a position corresponding to a counterbore 31 (see FIG. 4), which will be described later. The shaft portion of a bolt 32 (see FIG. 4) for fixing the traveling plate 22 to the beam member 21 is inserted into the bolt hole. The shaft portion of the bolt 32 extends downward from the horizontal plate 23 through the bolt hole. The side wall plates 24 are provided at both ends of the horizontal plate 23 in the width direction. The side wall plate 24 is perpendicular to the horizontal plate 23 and extends vertically at the end of the horizontal plate 23. In other words, the beam member 21 has a groove 26a that opens upward and a groove 26a that opens downward. A groove portion 26b is provided.

補強板25は、横板23の下側において横板23に直交する板材であって、車幅方向に沿って広がっている。すなわち、補強板25は、下側の溝部26bを走行方向に分割するように配置されている。補強板25は、上縁部が横板23と接続され、左右両端縁部が左右の側壁板24とそれぞれ接続されている。補強板25の下端は、側壁板24の下端と同じ高さである。補強板25は、支承体10に対応する位置に配置されており、支承体10の上部に設置される。支承体10の上部に設置された補強板25は、L字アングル27を介して支承体10の上側のフランジ12に固定されている。支承体10に接続される補強板25,25の間にも、他の補強板25が等間隔ピッチで平行に配置されている(図3参照)。なお、桁材21は、ワッフル構造に限定されるものではなく、例えば、複数のH桁を幅員方向に並べて配置することで構成してもよい。 The reinforcing plate 25 is a plate member located below the horizontal plate 23 and perpendicular to the horizontal plate 23, and extends along the vehicle width direction. That is, the reinforcing plate 25 is arranged so as to divide the lower groove portion 26b in the running direction. The reinforcing plate 25 has an upper edge connected to the horizontal plate 23, and both left and right end edges connected to the left and right side wall plates 24, respectively. The lower end of the reinforcing plate 25 is at the same height as the lower end of the side wall plate 24. The reinforcing plate 25 is disposed at a position corresponding to the support 10 and is installed on the top of the support 10. A reinforcing plate 25 installed on the upper part of the support body 10 is fixed to the upper flange 12 of the support body 10 via an L-shaped angle 27. Also between the reinforcing plates 25, 25 connected to the support body 10, other reinforcing plates 25 are arranged in parallel at equal intervals (see FIG. 3). Note that the girder material 21 is not limited to the waffle structure, and may be configured by, for example, arranging a plurality of H girders side by side in the width direction.

走行板22は、列車のゴムタイヤ走行輪が走行する板状部材である。走行板の上面は、既設軌条1の走行面(走行層4の上面)と同じ高さになり、走行板22の上面が列車の走行面となる。走行板22は、桁材21の上側の溝部26a内に設置されている。走行板22は、桁材21の上側の溝部26aに嵌り、拘束されている。走行板22は、プレキャストのコンクリート板にて構成されている。なお、走行板22は、コンクリート板に限定されるものではなく、鋼板等の他のもので構成されていてもよい。走行板22は、ゴムタイヤの幅寸法より大きい幅寸法を備えており、走行方向に所定長さで延在している。走行板22の上側表面には、座ぐり31が形成されている。座ぐり31は、ボルト32の頭部が収容される空間となる。座ぐり31は、走行板22の幅方向両端縁部に、走行方向に所定間隔をあけて形成されており、座ぐり31上を走行輪が走行しないようになっている。なお、座ぐり31の位置は、走行輪が走行する位置にあってもよい。座ぐり31の底部には、走行板の下面に至る貫通孔(図示せず)が形成されている。貫通孔には、ボルト32の軸部が挿通される。 The running plate 22 is a plate-like member on which the rubber tire running wheels of the train run. The upper surface of the running plate is at the same height as the running surface of the existing rail 1 (the upper surface of the running layer 4), and the upper surface of the running plate 22 becomes the running surface of the train. The running plate 22 is installed in the groove portion 26a on the upper side of the beam member 21. The running plate 22 fits into the groove 26a on the upper side of the beam member 21 and is restrained. The running plate 22 is made of a precast concrete plate. Note that the running plate 22 is not limited to a concrete plate, and may be made of other materials such as a steel plate. The running plate 22 has a width larger than the width of the rubber tire, and extends a predetermined length in the running direction. A counterbore 31 is formed on the upper surface of the running plate 22. The counterbore 31 becomes a space in which the head of the bolt 32 is accommodated. The counterbore 31 is formed at both ends of the running plate 22 in the width direction at a predetermined interval in the running direction, so that the running wheels do not run on the counterbore 31. Note that the position of the counterbore 31 may be at a position where the running wheels run. A through hole (not shown) is formed in the bottom of the counterbore 31 and reaches the lower surface of the running plate. The shaft portion of the bolt 32 is inserted into the through hole.

次に、図5の(a)に示す既設軌条1を改修する方法(改修構造7の構築方法)を説明する。本実施形態の既設軌条1の改修方法は、例えば、列車が走行し営業している路線において、夜間の線閉時間内に行われる工事に適用される。かかる既設軌条1の改修方法は、準備工程、撤去工程、仮覆工設置工程、支承体設置工程、桁体設置工程、仮設走行面形成工程などを備えている。 Next, a method for repairing the existing rail 1 shown in FIG. 5(a) (method for constructing the repaired structure 7) will be explained. The method for repairing the existing rail 1 according to the present embodiment is applied, for example, to construction work performed during line closing hours at night on a route where trains are running and in operation. This method of repairing the existing rail 1 includes a preparation process, a removal process, a temporary lining installation process, a support installation process, a girder installation process, a temporary running surface formation process, and the like.

準備工程は、仮覆工50を設置するための準備を行う工程である。既設軌条1では、図5の(a)に示すように、道床コンクリート3の左右両側に、排水溝6a,6bが形成されている。道床コンクリート3,3の内側に設けられた排水溝6aは溝幅が小さく、このままの状態では後記する仮覆工50を設置することができない。そこで、準備工程では、図5の(b)に示すように、内側の排水溝6aの側壁を、既設軌条1の中心側に向かって切削して溝幅を広げる作業を行う。排水溝6aの溝幅は、仮覆工50の鍔部52(図6の(b)参照)を設置可能な幅とする。なお、外側の排水溝6bの溝幅が仮覆工50の鍔部52の幅よりも小さい場合には、排水溝6bについても溝幅を広げる作業を行う。なお、仮覆工50の形状を排水溝6bの溝幅に合わせた場合や、排水溝6b以外の場所に仮覆工50を設置する場合等、仮覆工50の構造によっては排水溝6の拡幅が不要の場合もあり得る。 The preparation process is a process of preparing for installing the temporary lining 50. In the existing rail 1, as shown in FIG. 5(a), drainage grooves 6a and 6b are formed on both the left and right sides of the track bed concrete 3. The drain groove 6a provided inside the trackbed concrete 3, 3 has a small groove width, and in this state, a temporary lining 50, which will be described later, cannot be installed therein. Therefore, in the preparation process, as shown in FIG. 5B, the side wall of the inner drain groove 6a is cut toward the center of the existing rail 1 to widen the groove width. The groove width of the drainage groove 6a is set to a width that allows the flange 52 (see FIG. 6(b)) of the temporary lining 50 to be installed. In addition, when the groove width of the outer drain groove 6b is smaller than the width of the flange part 52 of the temporary lining 50, the work of widening the groove width of the drain groove 6b is also performed. Note that depending on the structure of the temporary lining 50, the width of the drain 6 may vary, such as when the shape of the temporary lining 50 is matched to the groove width of the drain 6b, or when the temporary lining 50 is installed in a location other than the drain 6b. There may be cases where widening is not necessary.

撤去工程は、既設軌条1の上部を撤去する工程である。撤去工程は、走行層撤去工程と第一撤去工程と第二撤去工程とを備えている。走行層撤去工程は、走行層4(図5参照)を撤去する工程である。第一撤去工程は、支承体10が設置される部分の既設軌条1を撤去して凹部15を形成する工程である。第二撤去工程は、第一撤去工程で形成された凹部15,15同士の間の既設軌条1を撤去する工程である。 The removal process is a process of removing the upper part of the existing rail 1. The removal process includes a running layer removal process, a first removal process, and a second removal process. The running layer removal process is a process of removing the running layer 4 (see FIG. 5). The first removal step is a step of removing the existing rail 1 in the portion where the support body 10 is installed to form the recess 15. The second removal process is a process of removing the existing rail 1 between the recesses 15, 15 formed in the first removal process.

撤去工程では、図6の(a)に示すように、まず、走行層4を撤去する(走行層撤去工程)。走行層4を撤去すると、道床コンクリート3の上端表面が露出する。本実施形態では、準備工程から撤去工程の走行層撤去工程までで一夜の線閉時間が終わるように工程が組まれて、走行層4の撤去が完了したところで、仮覆工設置工程が行われる。 In the removal process, as shown in FIG. 6(a), first, the running layer 4 is removed (running layer removal process). When the running layer 4 is removed, the upper end surface of the track bed concrete 3 is exposed. In this embodiment, the process is arranged so that one night's line closing time ends from the preparation process to the running layer removal process of the removal process, and when the removal of the running layer 4 is completed, the temporary lining installation process is performed. .

仮覆工設置工程は、夜間の線閉時間が過ぎた後に列車が走行できるように、仮覆工50を設置する工程である。仮覆工設置工程は、本実施形態で例示したタイミングだけでなく、他の工程の進捗状況に応じて適宜行われる。仮覆工50は、図6の(b)および図7に示すように、断面門型の溝部51と、溝部51の下端部に形成された鍔部52とを備えている。溝部51は、断面門型で下向きに開口した溝形状を呈している。溝部51は、表面部53と側壁部54とを備えている。表面部53は、仮覆工50の上端表面を構成する部位であり、走行方向に沿って延在している。表面部53の厚さ寸法は、走行層4の厚さ寸法と同等である。仮覆工50を所定位置に設置した際に、表面部53の表面高さは、既設軌条1の走行層4の表面高さと同等になる。側壁部54は、左右一対に設けられており、表面部53の幅方向両端部からそれぞれ下方に向かって延出している。左右の側壁部54,54は、互いに平行である。なお、表面部53の厚さ寸法と、走行層4の厚さ寸法とは、必ずしも同等でなくてもよい。この場合、表面部53と走行層4との間に段差が発生するが、車両の走行に支障のない程度であれば問題はない。また、仮覆工50は、断面門型に限定されるものではない。さらに、仮覆工50は、道床に隣接する支障物の有無・配置により適宜、形状を最適化する。 The temporary lining installation process is a process of installing the temporary lining 50 so that trains can run after the line is closed at night. The temporary lining installation process is performed not only at the timing exemplified in this embodiment but also as appropriate depending on the progress status of other processes. As shown in FIGS. 6(b) and 7, the temporary lining 50 includes a groove 51 having a gate-shaped cross section and a flange 52 formed at the lower end of the groove 51. The groove portion 51 has a gate-shaped cross section and a groove shape that opens downward. The groove portion 51 includes a surface portion 53 and a side wall portion 54 . The surface portion 53 is a portion that constitutes the upper end surface of the temporary lining 50, and extends along the traveling direction. The thickness of the surface portion 53 is equal to the thickness of the running layer 4. When the temporary lining 50 is installed at a predetermined position, the surface height of the surface portion 53 becomes equivalent to the surface height of the running layer 4 of the existing rail 1. The side wall portions 54 are provided in a pair on the left and right, and extend downward from both ends of the surface portion 53 in the width direction. The left and right side wall portions 54, 54 are parallel to each other. Note that the thickness of the surface portion 53 and the thickness of the running layer 4 do not necessarily have to be equal. In this case, a level difference occurs between the surface portion 53 and the running layer 4, but there is no problem as long as it does not hinder the running of the vehicle. Further, the temporary lining 50 is not limited to a gate-shaped cross section. Further, the shape of the temporary lining 50 is appropriately optimized depending on the presence/absence and arrangement of obstacles adjacent to the trackbed.

鍔部52は、左右一対に設けられており、側壁部54の下端からそれぞれ外側に向かって張り出している。鍔部52には、走行方向に沿って所定間隔をあけてボルト貫通孔55,55・・が形成されている。ボルト貫通孔55には、仮覆工50を底版コンクリート2に固定するためのボルト部材56が挿通される。 The collar portions 52 are provided in a pair on the left and right, and each protrudes outward from the lower end of the side wall portion 54. Bolt through holes 55, 55, . . . are formed in the flange portion 52 at predetermined intervals along the running direction. A bolt member 56 for fixing the temporary lining 50 to the bottom slab concrete 2 is inserted into the bolt through hole 55 .

仮覆工設置工程では、走行層4が撤去された施工途中の道床コンクリート3に仮覆工50を被せる。すると、仮覆工50の鍔部52が排水溝6a,6bにそれぞれ配置されるとともに、表面部53が道床コンクリート3の上端表面に載置される。そして、ボルト貫通孔55から排水溝6a,6bの底面に向けてボルト部材56を螺入することで、仮覆工50が設置される。表面部53の厚さ寸法は撤去された走行層4と同じ厚さなので、表面部53の表面高さは、既設軌条1の走行層4の表面高さと同等になる。 In the temporary lining installation process, a temporary lining 50 is placed over the concrete roadbed 3 that is currently under construction and from which the running layer 4 has been removed. Then, the collar portions 52 of the temporary lining 50 are placed in the drains 6a and 6b, respectively, and the surface portion 53 is placed on the upper end surface of the track bed concrete 3. Then, the temporary lining 50 is installed by screwing the bolt members 56 through the bolt through holes 55 toward the bottom surfaces of the drain grooves 6a, 6b. Since the thickness of the surface portion 53 is the same as that of the removed running layer 4, the surface height of the surface portion 53 is equivalent to the surface height of the running layer 4 of the existing rail 1.

鉄道営業が終了し、次の線閉時間が始まると、図8の(a)および(b)に示すように、仮覆工50を取り外して、撤去工程の続き(第一撤去工程)を行う。第一撤去工程では、既設軌条1を部分的に撤去して凹部15を形成する。凹部15は、道床コンクリート3の高さ全体を撤去して形成されている。つまり、凹部15の底面は、底版コンクリート2の表面にて構成されている。凹部15は、カッター等を用いて、凹部15の走行方法両端部の位置にスリットを設けた後、スリット間の道床コンクリート3を斫ることで形成する。凹部15を形成する際には、道床コンクリート3の左右両側の排水溝6a,6bの一部も道床コンクリート3の下端まで撤去される。凹部15を形成すると、支承体設置工程を行う。 When the railway service ends and the next line closing time begins, the temporary lining 50 is removed and the removal process continues (first removal process), as shown in FIGS. 8(a) and (b). . In the first removal step, the existing rail 1 is partially removed to form the recess 15. The recess 15 is formed by removing the entire height of the track bed concrete 3. In other words, the bottom surface of the recess 15 is formed by the surface of the bottom slab concrete 2. The recess 15 is formed by providing slits at both ends of the recess 15 using a cutter or the like, and then scraping the track bed concrete 3 between the slits. When forming the recess 15, parts of the drainage grooves 6a and 6b on both the left and right sides of the concrete trackbed 3 are also removed to the lower end of the concrete trackbed 3. Once the recess 15 is formed, a support installation process is performed.

支承体設置工程は、凹部15の底面(上部が撤去された既設軌条1)に支承体10を設置する工程である。支承体10は、既設軌条1が存在していた空間(凹部15)に配置する。図8の(c)に示すように、支承体設置工程では、各凹部15の底面にアンカー部材13を介して支承体10を固定する。つまり、支承体10は、既設軌条1の延在方向に間隔をあけて複数配置される。支承体設置工程が完了したところで、2回目の仮覆工設置工程が行われる。 The support body installation process is a process of installing the support body 10 on the bottom surface of the recess 15 (the existing rail 1 from which the upper part has been removed). The support body 10 is placed in the space (the recess 15) where the existing rail 1 existed. As shown in FIG. 8C, in the support installation step, the support 10 is fixed to the bottom surface of each recess 15 via the anchor member 13. That is, a plurality of supporting bodies 10 are arranged at intervals in the extending direction of the existing rail 1. When the support installation process is completed, a second temporary lining installation process is performed.

2回目の仮覆工設置工程では、図9の(a)および(b)に示すように、支承体10の上に、高さ調整材16を設置する。高さ調整材16は、例えばコンクリート製のブロック状部材にて構成されている。高さ調整材16の厚さ寸法は、高さ調整材16を支承体10の上に設置した状態で、高さ調整材16の上面が道床コンクリート3の上端高さ、つまり仮覆工50の表面部53の下面の高さと同じになるように設定されている。高さ調整材16を設置した後、高さ調整材16と、凹部15,15間の道床コンクリート3とを覆うように仮覆工50を被せる。すると、仮覆工50の鍔部52が排水溝6a,6bにそれぞれ配置されるとともに、表面部53が高さ調整材16および道床コンクリート3の上に載置される。そして、ボルト貫通孔55から排水溝6a,6bの底面に向けてボルト部材56を螺入することで、仮覆工50が設置される。 In the second temporary lining installation process, the height adjustment material 16 is installed on the support body 10, as shown in FIGS. 9(a) and 9(b). The height adjusting member 16 is made of a block-shaped member made of concrete, for example. The thickness dimension of the height adjustment material 16 is such that when the height adjustment material 16 is installed on the support 10, the top surface of the height adjustment material 16 is at the upper end height of the track bed concrete 3, that is, the temporary lining 50. The height is set to be the same as the height of the lower surface of the surface portion 53. After installing the height adjustment material 16, a temporary lining 50 is placed so as to cover the height adjustment material 16 and the trackbed concrete 3 between the recesses 15, 15. Then, the collar portions 52 of the temporary lining 50 are placed in the drains 6a and 6b, respectively, and the surface portion 53 is placed on the height adjustment material 16 and the trackbed concrete 3. Then, the temporary lining 50 is installed by screwing the bolt members 56 through the bolt through holes 55 toward the bottom surfaces of the drain grooves 6a, 6b.

鉄道営業が終了し、次の線閉時間が始まると、図10の(a)に示すように、仮覆工50を取り外して、第二撤去工程を行う。第二撤去工程は、隣り合う凹部15,15間の道床コンクリート3(既設軌条1の上部)を撤去する工程である。道床コンクリート3を撤去するに際しては、図10の(b)に示すように、カッター等を用いて、所定ピッチでスリットを設けてスリット間にブロック3a,3a・・を形成する。その後、スリット間のブロック3aを順次斫る。道床コンクリート3の撤去高さは、道床コンクリート3の全体となっており、道床コンクリート3下の底版コンクリート2が露出する。なお、改修構造の施工規模によっては、走行層撤去工程、第一撤去工程、第二撤去工程とを分けずに同時に行う選択肢もあり得る。 When the railway service ends and the next line closing time begins, the temporary lining 50 is removed and a second removal process is performed, as shown in FIG. 10(a). The second removal step is a step of removing the trackbed concrete 3 (the upper part of the existing rail 1) between the adjacent recesses 15, 15. When removing the trackbed concrete 3, as shown in FIG. 10(b), slits are provided at a predetermined pitch using a cutter or the like to form blocks 3a, 3a, . . . between the slits. Thereafter, the blocks 3a between the slits are successively removed. The removal height of the trackbed concrete 3 is the entire trackbed concrete 3, and the bottom slab concrete 2 below the trackbed concrete 3 is exposed. Note that depending on the construction scale of the repaired structure, there may be an option to perform the running layer removal process, the first removal process, and the second removal process simultaneously without separating them.

次に、桁体設置工程を行う。桁体設置工程は、複数の支承体10,10・・に桁体20を架け渡す工程である。本実施形態の桁材設置工程は、桁材設置工程と走行板設置工程とを備えている。桁材設置工程は、桁材21を支承体10,10上に掛け渡す工程である。走行板設置工程は、走行板22を桁材21上に設置する工程である。 Next, a girder installation process is performed. The girder installation process is a process in which the girder 20 is spanned over a plurality of supports 10, 10, . The girder installation process of this embodiment includes a girder installation process and a traveling plate installation process. The girder material installation process is a process in which the girder material 21 is laid over the supports 10, 10. The running plate installation process is a process of installing the running plate 22 on the girder 21.

図11の(a)および(b)に示すように、まず、桁材設置工程を行う。桁材設置工程では、支承体10の上に桁材21を設置し、ウエブ11と桁材21の補強板25とが同一面上となるように桁材21の位置を調整する。その後、補強板25を挟むようにL字アングル27,27を配置する。そして、L字アングル27の縦板を補強板25にボルト止めするとともに、L字アングル27の横板を支承体10の上側のフランジ12にボルト止めする。これによって、桁材21が支承体10,10・・に固定される。桁材21の設置が完了した後に、仮設走行面形成工程を行う。 As shown in FIGS. 11(a) and 11(b), first, a girder installation step is performed. In the girder installation step, the girder 21 is installed on the support 10, and the position of the girder 21 is adjusted so that the web 11 and the reinforcing plate 25 of the girder 21 are on the same plane. Thereafter, the L-shaped angles 27, 27 are arranged so as to sandwich the reinforcing plate 25 therebetween. Then, the vertical plate of the L-shaped angle 27 is bolted to the reinforcing plate 25, and the horizontal plate of the L-shaped angle 27 is bolted to the upper flange 12 of the support body 10. As a result, the beam members 21 are fixed to the supports 10, 10, . . . . After the installation of the beam members 21 is completed, a temporary running surface forming process is performed.

仮設走行面形成工程は、桁材21上に仮設の走行面を形成する工程である。仮設走行面形成工程では、仮覆工を設置するのではなく、桁材21の上側の溝部26aにアスファルトを敷設してアスファルト舗装30を形成することで、走行路を形成する。アスファルト舗装30の上面が仮設の走行面となる。 The temporary running surface forming step is a step of forming a temporary running surface on the girder material 21. In the temporary running surface forming step, a running road is formed by laying asphalt in the grooves 26a above the girders 21 to form an asphalt pavement 30 instead of installing a temporary lining. The upper surface of the asphalt pavement 30 becomes a temporary running surface.

鉄道営業が終了し、次の線閉時間が始まると、アスファルト舗装30を撤去して、走行板設置工程を行う。走行板設置工程では、図1乃至図4に示すように、上側の溝部26aに走行板22を載置する。走行板22は、溝部26aに嵌り、拘束される。そして、図3および図4に示すように、座ぐり11からボルト32を挿入し、ボルト32の軸部を走行板22の貫通孔および桁材21のボルト孔に挿通する。そして、下方に延出したボルト32の軸部にナットを螺合させて締め付ける。これによって、走行板22が桁材21に固定される。走行板設置工程が完了すれば、既設軌条1の改修工事が完了し、走行板22の上面がゴムタイヤ走行輪の走行面となる。 When the railway business ends and the next line closing time begins, the asphalt pavement 30 is removed and a running board installation process is performed. In the running plate installation step, as shown in FIGS. 1 to 4, the running plate 22 is placed in the upper groove portion 26a. The running plate 22 fits into the groove 26a and is restrained. Then, as shown in FIGS. 3 and 4, the bolt 32 is inserted through the counterbore 11, and the shaft portion of the bolt 32 is inserted into the through hole of the traveling plate 22 and the bolt hole of the beam member 21. Then, a nut is screwed onto the shaft portion of the bolt 32 extending downward and tightened. Thereby, the running plate 22 is fixed to the beam member 21. When the running plate installation process is completed, the repair work on the existing rail 1 is completed, and the upper surface of the running plate 22 becomes the running surface for the rubber tire running wheels.

なお、本実施形態に係る既設軌条1の改修方法においては、状況に応じ、各種資材の搬出入のための専用のウインチ・搬入走路(斜面・レール)のホーム端部の階段部への設置や、ホームから路線への資材荷下ろし・荷上げを目的とした専用の簡易クレーンのホームへの設置等を行う。同様に、路線内では、トロッコや台車を用いた資材の搬送等により、資材運搬の効率化を図る。 In addition, in the method for repairing the existing rail 1 according to the present embodiment, depending on the situation, a dedicated winch and a carry-in track (slope/rail) for carrying in and out of various materials may be installed on the stairs at the end of the platform. , a special simple crane will be installed on the platform for the purpose of unloading and unloading materials from the platform to the line. Similarly, along the route, materials will be transported more efficiently using trolleys and trolleys.

本実施形態の既設軌条1の改修構造7では、複数の支承体10,10・・に架け渡した桁体20が新たな軌条の走行面となるので、施工スピードが速くなる。さらに、支承体10,10の間は隙間とすることができるので、改修構造7の重量を低減することができる。 In the repair structure 7 for the existing rail 1 of this embodiment, the girder 20 spanning the plurality of supports 10, 10, . Furthermore, since a gap can be provided between the supporting bodies 10, 10, the weight of the repaired structure 7 can be reduced.

本実施形態の桁体20は、桁材21と走行板22とを備えて構成されている。このようにすると、桁材21と走行板22とを別工程で設置できるので、部材の搬送や設置作業を容易に行うことができる。 The girder body 20 of this embodiment includes a girder member 21 and a running plate 22. In this way, the girder 21 and the traveling plate 22 can be installed in separate steps, making it easier to transport and install the members.

桁材21は、剛性の確保された鋼板にて構成され、断面H形状を呈するとともに複数の補強板25を備えているので、強度を大きくできるとともに、長期に渡って高い耐久性を確保できる。 The girder member 21 is made of a steel plate with guaranteed rigidity, has an H-shaped cross section, and is provided with a plurality of reinforcing plates 25, so that it can increase its strength and ensure high durability over a long period of time.

また、走行板22がプレキャストのコンクリート板にて構成されているので、表面(走行面)の平滑性が高い。そして、走行板22を桁材21に設置するだけで走行路を形成できるので、従来の方法とは異なり、グラウト材の硬化時間を必要としない。したがって、施工時間を大幅に低減できる。さらに、本実施形態では、走行板22の表面に座ぐり31が形成されているので、走行板22の表面からボルト32が突出しない。したがって、列車の車輪が走行する位置でもボルト32を設置でき、ボルト32の位置が制限されない。 Further, since the running plate 22 is made of a precast concrete plate, the surface (running surface) has high smoothness. Further, since the running path can be formed simply by installing the running plate 22 on the girder 21, unlike the conventional method, there is no need for hardening time of the grout material. Therefore, construction time can be significantly reduced. Furthermore, in this embodiment, since the counterbore 31 is formed on the surface of the running plate 22, the bolt 32 does not protrude from the surface of the running plate 22. Therefore, the bolt 32 can be installed even at a position where the wheels of a train run, and the position of the bolt 32 is not limited.

さらに、桁材21の溝部26a内に走行板22を敷設するので、走行板22の位置決めと設置を容易に行うことができる。また、走行板22は、桁材21の溝部26aに嵌合されて拘束されるので、より一層耐久性を高くできる。 Furthermore, since the running plate 22 is laid in the groove 26a of the girder 21, the running plate 22 can be easily positioned and installed. Moreover, since the traveling plate 22 is fitted into and restrained by the groove portion 26a of the beam member 21, durability can be further increased.

本実施形態の既設軌条1の改修方法によれば、複数の支承体10,10・・に桁体20を架け渡すことで改修構造7が形成される。したがって、従来のようにグラウト材を硬化させる場合と比較して、施工時間を短くすることができる。 According to the method for repairing the existing rail 1 of this embodiment, the repair structure 7 is formed by spanning the girder 20 over a plurality of supports 10, 10, . Therefore, the construction time can be shortened compared to the conventional case of hardening the grout material.

また、本実施形態では、施工途中においても、桁体20を設置する前の既設軌条1および支承体10,10・・の上部に仮覆工50を設けるができるので、列車の運行に支障を来さず改修工事を進めることができる。したがって、数日に渡る夜間の線閉時間内で工事を順次進めていくことができるとともに、夜間の線閉時間内での工事を効率的に行うことができる。 Furthermore, in this embodiment, even during construction, the temporary lining 50 can be provided above the existing rail 1 and the supports 10, 10, etc. before the girder 20 is installed, so that the train operation is not hindered. It is possible to proceed with the renovation work without having to come. Therefore, the construction work can be carried out sequentially during the line closing hours at night over several days, and the construction work can be carried out efficiently during the line closing hours at night.

さらに、本実施形態では、桁体21を設置した後においても、桁材21の溝部26aにアスファルト舗装30を形成することで、仮設の走行路を形成することができる。したがって、夜間の線閉時間内での工事をより一層効率的に行うことができる。なお、アスファルトの敷設及び撤去は容易に行うことができるので、施工手間が大幅に増えることはない。 Furthermore, in this embodiment, even after the girder 21 is installed, a temporary running path can be formed by forming the asphalt pavement 30 in the groove portion 26a of the girder 21. Therefore, construction work can be carried out even more efficiently during the line closing hours at night. Furthermore, since the asphalt can be easily laid and removed, the construction effort will not increase significantly.

また、撤去工程を、第一撤去工程と第二撤去工程とに分け、凹部15を形成した後に、支承体10を順次設置するので、既設軌条1の撤去完了を待つことなく、支承体10の設置を早期に行える。よって、全体の施工スピードが速くなる。 Furthermore, the removal process is divided into a first removal process and a second removal process, and the supports 10 are sequentially installed after the recesses 15 are formed. Installation can be done quickly. Therefore, the overall construction speed becomes faster.

仮覆工50とアスファルト舗装30は、既設の走行層4の表面高さと同等の高さの表面部を有するので、工事前の既設軌条1と、工事途中の仮覆工50またはアスファルト舗装30と、工事後の新たな軌条(走行板22)とが延長方向に混在する場合であっても、車両を円滑に走行させることができる。 Since the temporary lining 50 and the asphalt pavement 30 have a surface portion with the same height as the surface height of the existing running layer 4, the existing rail 1 before construction and the temporary lining 50 or asphalt pavement 30 during construction are different from each other. Even if new rails (running plates 22) after construction are mixed in the extension direction, the vehicle can run smoothly.

以上、本発明を実施するための形態について説明したが、本発明は前記実施形態に限定する趣旨ではなく、本発明の趣旨を逸脱しない範囲で適宜設計変更が可能である。たとえば、前記実施形態では、隣り合う支承体10,10の間の道床コンクリート3の全体を撤去しているが、これに限定されるものではない。支承体10,10・・に架け渡される桁体20に干渉しないように、道床コンクリート3の上部のみを撤去してもよい。このような構成にすれば、第二撤去工程の手間と時間を短縮でき、施工スピードがより一層早くなる。 Although the embodiments for carrying out the present invention have been described above, the present invention is not intended to be limited to the above-described embodiments, and design changes can be made as appropriate without departing from the spirit of the present invention. For example, in the embodiment described above, the entire track bed concrete 3 between the adjacent support bodies 10, 10 is removed, but the present invention is not limited to this. Only the upper part of the trackbed concrete 3 may be removed so as not to interfere with the girder 20 spanned over the supports 10, 10, . With such a configuration, the effort and time of the second removal process can be shortened, and the construction speed can be further increased.

また、前記実施形態では、凹部15,15間の道床コンクリート3を撤去する第二撤去工程を、支承体設置工程の後に行っているが、支承体設置工程と並行して行ってもよい。このようにすれば、施工時間をより一層短縮することができる。 Further, in the embodiment, the second removal step of removing the track bed concrete 3 between the recesses 15, 15 is performed after the support installation step, but it may be performed in parallel with the support installation step. In this way, the construction time can be further shortened.

さらに、前記実施形態では、走行板10がプレキャストのコンクリート板にて構成されているがこれに限定されるものではない。走行板10は、鋼板や、複数の樹脂製のガラス長繊維強化プラスチック発泡体(FFU:Fiber reinforced Foamed Urethane)にて構成してもよい。FFUは、硬質ウレタン樹脂からなるプラスチック発泡体を無機繊維としてのガラス長繊維で補強して構成されており、例えばエスロンネオランバーFFU(積水化学工業株式会社製)を挙げることができる。鋼板やFFUによっても、強度と精度が高い走行板10を得られる。さらに、摩耗した走行板や劣化した桁材21および支承体10をそれぞれ独立して取り換えることが可能になるので、メンテナンスが容易になる。 Further, in the embodiment, the traveling plate 10 is made of a precast concrete plate, but the present invention is not limited to this. The running plate 10 may be made of a steel plate or a plurality of resin-made glass fiber reinforced plastic foams (FFU: Fiber reinforced Foamed Urethane). FFU is constructed by reinforcing a plastic foam made of hard urethane resin with long glass fibers as inorganic fibers, and examples include Eslon Neo Lumber FFU (manufactured by Sekisui Chemical Co., Ltd.). The running plate 10 with high strength and precision can also be obtained by using a steel plate or FFU. Furthermore, since worn running plates, deteriorated girders 21, and support bodies 10 can be replaced independently, maintenance becomes easier.

1 既設軌条
2 底版コンクリート(底板)
3 道床コンクリート
4 走行層
7 改修構造
10 支承体
15 凹部
20 桁体
21 桁材
22 走行板
26a 溝部
50 仮覆工
1 Existing rail 2 Concrete bottom slab (bottom plate)
3 Road bed concrete 4 Running layer 7 Repair structure 10 Support body 15 Recessed part 20 Girder body 21 Girder material 22 Running plate 26a Groove part 50 Temporary lining

Claims (4)

底板上に敷設された道床コンクリートの上に走行層が形成された既設軌条の改修方法であって、
前記既設軌条の上部を撤去する撤去工程と、
桁体を設置する前の前記既設軌条の上部に、既設の前記走行層の表面高さと同等の高さの表面部を有する仮覆工を設置する仮覆工設置工程と、
上部が撤去された前記既設軌条の上に、既設軌条の延在方向に間隔をあけて複数の支承体を設置する支承体設置工程と、
複数の前記支承体に、上面が走行面となる桁体を架け渡す桁体設置工程とを備え、
前記撤去工程および前記仮覆工設置工程は、昼間の鉄道営業を挟んで複数回行われ、
前記撤去工程は、前記支承体が設置される部分の前記既設軌条を撤去して凹部を形成する第一撤去工程と、前記第一撤去工程で形成された前記凹部同士の間の前記既設軌条を撤去する第二撤去工程とを備え、前記第二撤去工程は、前記支承体設置工程の後、または前記支承体設置工程と並行して行われ、
前記撤去工程では、前記道床コンクリートを斫ることで前記既設軌条の上部を撤去し、
前記第一撤去工程以降の前記仮覆工設置工程では、前記撤去工程で形成された前記凹部に設置された前記支承体と前記仮覆工の表面部の設置位置との間にブロック状の高さ調整材を設置した後に、前記仮覆工を被せる
ことを特徴とする既設軌条の改修方法。
A method for repairing an existing rail in which a running layer is formed on a concrete track bed laid on a bottom plate, the method comprising:
a removal step of removing the upper part of the existing rail;
A temporary lining installation step of installing a temporary lining having a surface portion with a height equivalent to the surface height of the existing running layer on the top of the existing rail before girder installation;
a support installation step of installing a plurality of supports at intervals in the extending direction of the existing rail on the existing rail from which the upper part has been removed;
a girder body installation step of bridging a girder body whose upper surface serves as a running surface over a plurality of the supporting bodies;
The removal process and the temporary lining installation process are performed multiple times during daytime railway operations,
The removal step includes a first removal step of removing the existing rail in the part where the support is installed to form a recess, and a removal step of removing the existing rail between the recesses formed in the first removal step. and a second removal step of removing, the second removal step being performed after the support installation step or in parallel with the support installation step,
In the removal step, the upper part of the existing rail is removed by scraping the track bed concrete,
In the temporary lining installation step after the first removal step, a block-shaped height is formed between the support installed in the recess formed in the removal step and the installation position of the surface part of the temporary lining. After installing the height adjustment material, cover with the temporary lining.
A method for repairing existing rails characterized by the following.
前記撤去工程では、前記道床コンクリートに所定ピッチでスリットを設けた後に、スリット間を斫ることで前記道床コンクリートを撤去する
ことを特徴とする請求項に記載の既設軌条の改修方法。
The method for repairing an existing rail according to claim 1 , wherein in the removal step, slits are provided in the trackbed concrete at a predetermined pitch, and then the trackbed concrete is removed by cutting between the slits.
前記仮覆工設置工程では、断面門型の仮覆工を施工途中の前記道床コンクリートに被せる
ことを特徴とする請求項に記載の既設軌条の改修方法。
2. The method for repairing an existing rail according to claim 1 , wherein in the temporary lining installation step, a temporary lining with a gate-shaped cross section is placed over the concrete track bed that is currently being constructed.
前記仮覆工設置工程では、前記仮覆工の上部にアスファルトを敷設して走行面とする
ことを特徴とする請求項1乃至請求項3のいずれか一項に記載の既設軌条の改修方法。
The method for repairing an existing rail according to any one of claims 1 to 3, wherein in the temporary lining installation step, asphalt is laid on top of the temporary lining to form a running surface.
JP2020117914A 2020-07-08 2020-07-08 How to repair existing rails Active JP7414658B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020117914A JP7414658B2 (en) 2020-07-08 2020-07-08 How to repair existing rails

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020117914A JP7414658B2 (en) 2020-07-08 2020-07-08 How to repair existing rails

Publications (2)

Publication Number Publication Date
JP2022015215A JP2022015215A (en) 2022-01-21
JP7414658B2 true JP7414658B2 (en) 2024-01-16

Family

ID=80120636

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020117914A Active JP7414658B2 (en) 2020-07-08 2020-07-08 How to repair existing rails

Country Status (1)

Country Link
JP (1) JP7414658B2 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011052458A (en) 2009-09-02 2011-03-17 Niigata Transys Co Ltd Method for constructing resin-fixed track
JP2012082622A (en) 2010-10-12 2012-04-26 Yokogawa Koji Kk Construction method of bridge floor slab and joint structure of precast floor slab
JP2013060710A (en) 2011-09-12 2013-04-04 Nakanihon Highway Engineering Nagoya Kk Bridge joint structure
JP2020007765A (en) 2018-07-06 2020-01-16 高橋土建株式会社 Repairing method of catch basin cover for bridge

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS50118601U (en) * 1974-03-12 1975-09-27
JPH0545924Y2 (en) * 1989-12-27 1993-11-30
JP2896115B2 (en) * 1996-03-11 1999-05-31 日本鉄道建設公団 Girder erection method and bearing part construction method used for it

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011052458A (en) 2009-09-02 2011-03-17 Niigata Transys Co Ltd Method for constructing resin-fixed track
JP2012082622A (en) 2010-10-12 2012-04-26 Yokogawa Koji Kk Construction method of bridge floor slab and joint structure of precast floor slab
JP2013060710A (en) 2011-09-12 2013-04-04 Nakanihon Highway Engineering Nagoya Kk Bridge joint structure
JP2020007765A (en) 2018-07-06 2020-01-16 高橋土建株式会社 Repairing method of catch basin cover for bridge

Also Published As

Publication number Publication date
JP2022015215A (en) 2022-01-21

Similar Documents

Publication Publication Date Title
AU2011351482B2 (en) Method for producing a slab trackway
KR102200955B1 (en) Road way construction method for mountain railway
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
US20060117504A1 (en) Bridge construction system and method
KR101158466B1 (en) Easily replaceable track block having three dimensions solid shape and method for manufacturing the same, method for laying concrete track and method for laying track of automated guideway type light rail transit using the same track block
JP2004538401A (en) Method of continuously supporting rails on fixed tracks, as well as adjusting devices and fixed tracks
KR102171763B1 (en) Mold for constructing embedded rail track
CA2323977A1 (en) Travel way for land transport systems
WO2011120186A1 (en) Track system for magnetic suspension passenger traffic line
JP4689272B2 (en) Construction method of fixed track for railway transportation
EP3263766B1 (en) Concrete slab for a railway vehicle and/or guided tyre vehicle
JP7414658B2 (en) How to repair existing rails
CN116770647A (en) Spliced track and construction method thereof
KR102276570B1 (en) Lower part separating type mold for constructing embedded rail track
SK363092A3 (en) Rail body
JP7414657B2 (en) How to repair existing rails
JP4162291B2 (en) Railway work girder cradle and rail work girder cradle construction method
KR100603901B1 (en) Structure and construction method of plate girder bridge using part of existing girder
JP3665909B2 (en) Bridge reconstruction method
KR100729844B1 (en) Repair method and structure for guided fire of railway bridge
KR20120138620A (en) Easily replaceable track block having three dimensions solid shape and method for manufacturing the same, method for laying concrete track and method for laying track of automated guideway type light rail transit using the same track block
CN220847057U (en) Hoisting construction railway simply supported beam
JP6229827B2 (en) Resin fixed track and its construction method
KR100729842B1 (en) Repair method and structure for guided fire of railway bridge
EP1496156A2 (en) Railway construction

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220920

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230522

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230530

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20230728

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230807

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231003

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231128

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231219

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231228

R150 Certificate of patent or registration of utility model

Ref document number: 7414658

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150