JP7435136B2 - Insulation testing equipment and insulation testing method - Google Patents
[go: Go Back, main page]

JP7435136B2 - Insulation testing equipment and insulation testing method - Google Patents

Insulation testing equipment and insulation testing method Download PDF

Info

Publication number
JP7435136B2
JP7435136B2 JP2020056075A JP2020056075A JP7435136B2 JP 7435136 B2 JP7435136 B2 JP 7435136B2 JP 2020056075 A JP2020056075 A JP 2020056075A JP 2020056075 A JP2020056075 A JP 2020056075A JP 7435136 B2 JP7435136 B2 JP 7435136B2
Authority
JP
Japan
Prior art keywords
phase
wire
terminal
insulation
core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020056075A
Other languages
Japanese (ja)
Other versions
JP2020169986A (en
Inventor
祐章 小坂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Denso Corp
Original Assignee
Denso Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Denso Corp filed Critical Denso Corp
Priority to US16/839,212 priority Critical patent/US11821933B2/en
Priority to CN202010258412.0A priority patent/CN111796168B/en
Publication of JP2020169986A publication Critical patent/JP2020169986A/en
Application granted granted Critical
Publication of JP7435136B2 publication Critical patent/JP7435136B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/12Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing
    • G01R31/1227Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials
    • G01R31/1263Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials of solid or fluid materials, e.g. insulation films, bulk material; of semiconductors or LV electronic components or parts; of cable, line or wire insulation
    • G01R31/1272Testing dielectric strength or breakdown voltage ; Testing or monitoring effectiveness or level of insulation, e.g. of a cable or of an apparatus, for example using partial discharge measurements; Electrostatic testing of components, parts or materials of solid or fluid materials, e.g. insulation films, bulk material; of semiconductors or LV electronic components or parts; of cable, line or wire insulation of cable, line or wire insulation, e.g. using partial discharge measurements

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Testing Relating To Insulation (AREA)
  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)
  • Testing Electric Properties And Detecting Electric Faults (AREA)
  • Tests Of Circuit Breakers, Generators, And Electric Motors (AREA)

Description

本発明は、回転電機のコイルを形成する線材の皮膜の絶縁状態を検査する絶縁検査装置およびその方法に関するものである。 The present invention relates to an insulation testing device and method for testing the insulation state of a coating on a wire forming a coil of a rotating electric machine.

従来、電動車両に搭載されるモータジェネレータなどに用いられる回転電機が知られている。その回転電機の製造過程には、電機子のコアの有するスロットに挿入されたコイルを形成する線材の皮膜の絶縁状態を検査する工程が含まれる。 2. Description of the Related Art Rotating electric machines used in motor generators and the like mounted on electric vehicles have been known. The manufacturing process of the rotating electric machine includes a step of inspecting the insulation state of the coating of the wire forming the coil inserted into the slot of the armature core.

特許文献1に記載の絶縁検査装置は、ステータコアのスロットに挿入されたU相、V相およびW相の線材が中性点で結線される前の状態で相間の絶縁検査を行うものである。相間の絶縁検査とは、所定の相の線材と別の相の線材との絶縁検査をいう。具体的には、例えば、U相の線材とV相の線材との絶縁検査では、絶縁検査装置の一方のプローブとU相の線材とを接続し、他方のプローブとV相の線材とを接続し、絶縁検査装置からU相とV相の線材に交流電圧を印加して部分放電による放電電荷量を測定する。 The insulation testing device described in Patent Document 1 tests the insulation between the phases before the U-phase, V-phase, and W-phase wires inserted into the slots of the stator core are connected at a neutral point. The interphase insulation test refers to an insulation test between a wire of a given phase and a wire of another phase. Specifically, for example, in an insulation test between a U-phase wire and a V-phase wire, one probe of the insulation testing device is connected to the U-phase wire, and the other probe is connected to the V-phase wire. Then, an AC voltage is applied to the U-phase and V-phase wires from an insulation testing device to measure the amount of discharged charge due to partial discharge.

特開2005-257549号公報Japanese Patent Application Publication No. 2005-257549

しかしながら、特許文献1に記載の絶縁検査装置は、相間の絶縁検査を行う際、その絶縁検査を行っている箇所(以下、「測定部位」という)と、絶縁検査を行っていない箇所(以下、「非測定部位」という)が生じる。そのため、非測定部位に浮遊電位が存在すると、その非測定部位から測定部位へ放電が誘発され、放電が増える傾向にある。例えば、U相の線材とV相の線材との絶縁検査を行っている際、W相の線材とステータコアにはプローブが接続されていない。そのため、非測定部位であるW相の線材またはステータコアから、測定部位であるU相の線材またはV相の線材へ放電が誘発される。その場合、所定の品質基準を満たしている規格内の線材を誤って品質基準を満たさない規格外の線材と判定するといった過検知が生じることで、絶縁検査の精度が低下するおそれがある。 However, when performing an insulation test between phases, the insulation testing device described in Patent Document 1 distinguishes between a location where the insulation test is performed (hereinafter referred to as a "measurement location") and a location where the insulation test is not performed (hereinafter referred to as "measurement site"). (referred to as "non-measurement area"). Therefore, when a floating potential exists in a non-measurement area, a discharge is induced from the non-measurement area to the measurement area, and the discharge tends to increase. For example, when testing the insulation between a U-phase wire and a V-phase wire, no probe is connected to the W-phase wire and the stator core. Therefore, a discharge is induced from the W-phase wire or the stator core, which is the non-measurement region, to the U-phase wire or V-phase wire, which is the measurement region. In that case, there is a risk that the accuracy of the insulation test will decrease due to over-detection, such as erroneously determining that a wire rod within the standard that meets the predetermined quality standards is a wire rod that does not meet the quality standards and is out of the standard.

本発明は上記点に鑑みて、検査精度を向上することの可能な絶縁検査装置および絶縁検査方法を提供することを目的とする。 In view of the above-mentioned points, an object of the present invention is to provide an insulation testing device and an insulation testing method that can improve testing accuracy.

上記目的を達成するため、請求項1に係る発明によると、絶縁検査装置は、回転電機の電機子のコア(2)の有するスロット(21)に挿入された複数の線材の皮膜の絶縁状態をU相の線材とV相の線材とW相の線材とが結線される前の状態で検査する。この絶縁検査装置は、電源部(3)、切替部(4)、放電量計測部(5)、絶縁判定部(6)および制御部(7)を備える。電源部は、第1端子(31)と第2端子(32)とを有する。切替部は、U相、V相、W相の各線材およびコアそれぞれと第1端子との間における複数の電気的な接続状態と遮断状態を切り替え可能、且つ、U相、V相、W相の各線材およびコアそれぞれと第2端子との間における複数の電気的な接続状態と遮断状態を切り替え可能である。放電量計測部は、U相、V相、W相の各線材およびコアのうち第1端子に電気的に接続された部材と第2端子に電気的に接続された部材との間に生じる放電量を計測する。絶縁判定部は、放電量計測部により計測された放電量に基づき、線材の皮膜が所定の品質基準を満たす規格内の製品であるか否かを判定する。制御部は、U相、V相、W相の各線材およびコアのいずれも第1端子および第2端子の両方に対し電気的な遮断状態になることなく、U相、V相、W相の各線材およびコアの全てが第1端子または第2端子と電気的に接続されるように切替部を制御する。 In order to achieve the above object, according to the invention according to claim 1, an insulation inspection device checks the insulation state of a coating of a plurality of wire rods inserted into a slot (21) of a core (2) of an armature of a rotating electric machine. Inspect the U-phase wire, V-phase wire, and W-phase wire before they are connected. This insulation testing device includes a power supply section (3), a switching section (4), a discharge amount measuring section (5), an insulation determining section (6), and a control section (7). The power supply section has a first terminal (31) and a second terminal (32). The switching unit is capable of switching between a plurality of electrical connection states and disconnection states between each of the U-phase, V-phase, and W-phase wires and cores and the first terminal, and It is possible to switch between a plurality of electrical connection states and disconnection states between each of the wires and cores and the second terminal . The discharge amount measurement unit measures the discharge that occurs between a member electrically connected to the first terminal and a member electrically connected to the second terminal among the U-phase, V-phase, and W-phase wires and cores. Measure the amount. The insulation determining section determines whether the coating of the wire is a product that meets predetermined quality standards and is within specifications based on the amount of discharge measured by the amount of discharge measuring section. The control unit controls the U-phase, V-phase, and W-phase wires and cores of the U-phase, V-phase, and W-phase without electrically cutting off both the first terminal and the second terminal. The switching unit is controlled so that all of the wires and cores are electrically connected to the first terminal or the second terminal.

これによれば、U相、V相、W相の各線材およびコアの全てを第1端子または第2端子と電気的に接続することで、浮遊電位を無くすことが可能である。そのため、絶縁検査を行っていない非測定部位から絶縁検査を行っている測定部位へ放電が誘発されることが無い。したがって、この絶縁検査装置は、所定の品質基準を満たす規格内の線材を誤って品質基準を満たさない規格外の線材と判定する過検知を防ぎ、絶縁検査の精度を向上することができる。
なお、放電量とは、放電量計測部により測定される電荷量に基づいて放電と見做された回数を所定時間ごとに計測したものいう。
また、電機子のスロットに挿入された線材は、セグメントコイルとも呼ばれる。
According to this, floating potential can be eliminated by electrically connecting all of the U-phase, V-phase, and W-phase wires and cores to the first terminal or the second terminal. Therefore, no discharge is induced from the non-measurement area where the insulation test is not being performed to the measurement area where the insulation test is being performed. Therefore, this insulation testing device can prevent over-detection of erroneously determining a wire rod within the standard that meets a predetermined quality standard as a wire rod outside the standard that does not meet the quality standard, and can improve the accuracy of the insulation test.
Note that the discharge amount refers to the number of times that a discharge is considered to have occurred, which is measured every predetermined time based on the amount of charge measured by the discharge amount measuring section.
Further, the wire inserted into the slot of the armature is also called a segment coil.

ところで、絶縁検査は、環境湿度または線材の皮膜の吸湿度(以下、それらを単に「湿度」ということがある)が高い状態の中で行われることがある。その場合、U相、V相、W相の各線材およびコアのうち第1端子に電気的に接続された部材と第2端子に電気的に接続された部材との間に放電が発生し続けるといった自続放電が起こりやすい傾向がある。その理由は、湿度の高い環境下では、空気や皮膜などが水分を多く含むため、気体原子の電離が発生しやすく、電子なだれが継続しやすい傾向にあるためと考える。そのため、一般に、絶縁検査では、部分放電開始電圧(PDIV: Partial Discharge Inception Voltage)を、湿度上昇率に対して一定の割合で低下させる対策が取られている。しかし、その対策によっても、湿度が所定の値を超えると、自続放電がより発生しやすくなり、過検知が生じる割合が増加し、絶縁検査の精度が低下するという問題がある。 By the way, the insulation test is sometimes performed in a state where the environmental humidity or the moisture absorption of the film of the wire material (hereinafter, these may be simply referred to as "humidity") is high. In that case, discharge continues to occur between the U-phase, V-phase, and W-phase wires and cores that are electrically connected to the first terminal and those that are electrically connected to the second terminal. There is a tendency for self-sustaining discharges to occur. The reason for this is thought to be that in a humid environment, air and films contain a lot of moisture, which tends to cause ionization of gas atoms, making it easier for electron avalanches to continue. Therefore, in general, in insulation inspection, measures are taken to reduce the partial discharge inception voltage (PDIV) at a constant rate with respect to the rate of increase in humidity. However, even with this measure, there is a problem that when the humidity exceeds a predetermined value, self-sustaining discharge becomes more likely to occur, the rate of over-detection increases, and the accuracy of insulation inspection decreases.

そこで、請求項6に係る発明では、回転電機の電機子のコア(2)の有するスロット(21)に挿入された複数の線材の皮膜の絶縁状態をU相の線材とV相の線材とW相の線材とが結線される前の状態で検査する絶縁検査装置は、電源部(3)、切替部(4)、制御部(7)、放電量計測部(5)、絶縁判定部(6)および湿度検出部(12)を備える。電源部は、第1端子(31)と第2端子(32)とを有する。切替部は、U相、V相、W相の各線材およびコアそれぞれと第1端子との間における複数の電気的な接続状態と遮断状態を切り替え可能、且つ、U相、V相、W相の各線材およびコアそれぞれと第2端子との間における複数の電気的な接続状態と遮断状態を切り替え可能である。制御部は、U相、V相、W相の各線材およびコアのいずれも第1端子および第2端子の両方に対し電気的な遮断状態になることなく、U相、V相、W相の各線材およびコアの全てが第1端子または第2端子と電気的に接続されるように切替部を制御する。放電量計測部は、U相、V相、W相の各線材およびコアのうち第1端子に電気的に接続された部材と第2端子に電気的に接続された部材との間に生じる放電量を計測する。絶縁判定部は、放電量計測部により計測された放電量に基づき、線材の皮膜が所定の品質基準を満たす規格内の製品であるか否かを判定する。湿度検出部は、U相、V相、W相の各線材およびコアが設置される環境湿度を検出する。そして、この絶縁検査装置は、電源部から線材に対する電圧の印加開始から絶縁判定部が線材の絶縁状態の良否を判定するまでの判定時間に関し、環境湿度が所定の値に一致するときの判定時間を線材の絶縁状態の良否を判定可能な所定時間に設定し、環境湿度が所定の値より低いときの判定時間を前記所定時間より短く設定し、環境湿度が所定の値より高いときの判定時間を前記所定時間より長く設定するように構成されている。 Therefore, in the invention according to claim 6, the insulation state of the coating of a plurality of wire rods inserted into the slot (21) of the core (2) of the armature of a rotating electric machine is changed between the U-phase wire rod, the V-phase wire rod and the W-phase wire rod. The insulation inspection device that inspects the state before the phase wire is connected includes a power supply section (3), a switching section (4), a control section (7), a discharge amount measurement section (5), and an insulation judgment section (6). ) and a humidity detection section (12). The power supply section has a first terminal (31) and a second terminal (32). The switching unit is capable of switching between a plurality of electrical connection states and disconnection states between each of the U-phase, V-phase, and W-phase wires and cores and the first terminal, and It is possible to switch between a plurality of electrical connection states and disconnection states between each of the wires and cores and the second terminal. The control unit controls the U-phase, V-phase, and W-phase wires and cores of the U-phase, V-phase, and W-phase without electrically cutting off both the first terminal and the second terminal. The switching unit is controlled so that all of the wires and cores are electrically connected to the first terminal or the second terminal. The discharge amount measurement unit measures the discharge that occurs between a member electrically connected to the first terminal and a member electrically connected to the second terminal among the U-phase, V-phase, and W-phase wires and cores. Measure the amount. The insulation determining section determines whether the coating of the wire is a product that meets predetermined quality standards and is within specifications based on the amount of discharge measured by the amount of discharge measuring section. The humidity detection unit detects the environmental humidity in which the U-phase, V-phase, and W-phase wire rods and the core are installed. This insulation testing device makes a judgment when the environmental humidity matches a predetermined value regarding the judgment time from the start of applying voltage from the power supply section to the wire until the insulation judgment section judges whether the insulation state of the wire is good or bad. The time is set to a predetermined time for determining whether the insulation state of the wire is good or bad, and the determination time is set shorter than the predetermined time when the environmental humidity is lower than a predetermined value, and when the environmental humidity is higher than the predetermined value. The determination time is set to be longer than the predetermined time.

これによれば、湿度が所定の値より高いときは、判定時間を長く設定することで、放電量計測部で計測される放電回数が時間経過とともに収束する。そのため、この絶縁検査装置は、湿度の影響を受けることなく、過検知を防ぎ、検査精度を向上することができる。一方、湿度が所定の値より低いときは、判定時間を短く設定することで、絶縁検査にかかる時間を短くすることができる。 According to this, when the humidity is higher than a predetermined value, by setting the determination time longer, the number of discharges measured by the discharge amount measuring section converges over time. Therefore, this insulation testing device can prevent over-detection and improve testing accuracy without being affected by humidity. On the other hand, when the humidity is lower than a predetermined value, the time required for the insulation test can be shortened by setting the determination time short.

請求項7に係る発明は、回転電機の電機子のコア(2)の有するスロット(21)に挿入された複数の線材の皮膜の絶縁状態をU相の線材とV相の線材とW相の線材とが結線される前の状態で検査する絶縁検査方法に関する発明である。この検査方法は、電源部(3)が有する第1端子(31)および第2端子(32)の両方に対しU相、V相、W相の各線材およびコアのいずれも絶縁状態になることなく、U相、V相、W相の各線材およびコアの全てが第1端子または第2端子と電気的に接続されている状態にする。そして、電源部からU相、V相、W相の各線材およびコアに電圧を印加し、U相、V相、W相の各線材およびコアのうち第1端子に電気的に接続された部材と第2端子に電気的に接続された部材との間に生じる放電量を計測する。 The invention according to claim 7 is characterized in that the insulation state of the coating of a plurality of wire rods inserted into the slot (21) of the core (2) of the armature of a rotating electric machine is determined by determining the insulation state of the coating of the wire rod of the U phase, the wire rod of the V phase, and the wire rod of the W phase. This invention relates to an insulation testing method for testing a wire before it is connected. This inspection method ensures that the U-phase, V-phase, and W-phase wires and cores are insulated from both the first terminal (31) and second terminal (32) of the power supply section (3). Instead, all of the U-phase, V-phase, and W-phase wires and cores are electrically connected to the first terminal or the second terminal. Then, a voltage is applied from the power supply unit to the U-phase, V-phase, and W-phase wires and the core, and the member electrically connected to the first terminal among the U-phase, V-phase, and W-phase wires and the core The amount of discharge generated between the terminal and the member electrically connected to the second terminal is measured.

この検査方法によれば、請求項1に係る発明と同様に、浮遊電位を無くすことで過検知を防ぎ、絶縁検査の精度を向上することができる。 According to this inspection method, as in the invention according to claim 1, by eliminating floating potential, over-detection can be prevented and the accuracy of insulation inspection can be improved.

請求項8に係る発明も、回転電機の電機子のコア(2)の有するスロット(21)に挿入された複数の線材の皮膜の絶縁状態をU相の線材とV相の線材とW相の線材とが結線される前の状態で検査する絶縁検査方法に関する発明である。この方法は、電源部(3)が有する第1端子(31)または第2端子(32)に対しU相、V相、W相の各線材およびコアが電気的に接続されている状態にする。U相、V相、W相の各線材およびコアが設置される環境湿度を検出する。そして、電源部から線材に対する電圧の印加開始から絶縁判定部が線材の絶縁状態の良否を判定するまでの判定時間に関し、環境湿度が所定の値に一致するときの判定時間を線材の絶縁状態の良否を判定可能な所定時間に設定し、環境湿度が所定の値より低いときの判定時間を所定時間より短く設定し、環境湿度が所定の値より高いときの判定時間を所定時間より長く設定する。そして、電源部からU相、V相、W相の各線材およびコアに電圧を印加し、U相、V相、W相の各線材およびコアのうち第1端子に電気的に接続された部材と第2端子に電気的に接続された部材との間に生じる放電量を計測する。 The invention according to claim 8 also determines the insulation state of the coating of a plurality of wire rods inserted into the slot (21) of the core (2) of the armature of a rotating electrical machine by determining the insulation state of the coating of the wire rod of the U phase, the wire rod of the V phase, and the wire rod of the W phase. This invention relates to an insulation testing method for testing a wire before it is connected. In this method, the U-phase, V-phase, and W-phase wires and cores are electrically connected to the first terminal (31) or second terminal (32) of the power supply section (3). . The environmental humidity in which the U-phase, V-phase, and W-phase wire rods and cores are installed is detected. Regarding the determination time from the start of voltage application from the power supply unit to the wire until the insulation determination unit determines whether the insulation state of the wire is good or bad, the determination time when the environmental humidity matches a predetermined value is the time required to determine whether the insulation state of the wire is good or not. Set a predetermined time for determining pass/fail, set the determination time shorter than the predetermined time when the environmental humidity is lower than the predetermined value, and set the determination time longer than the predetermined time when the environmental humidity is higher than the predetermined value. Set. Then, a voltage is applied from the power supply unit to the U-phase, V-phase, and W-phase wires and the core, and the member electrically connected to the first terminal among the U-phase, V-phase, and W-phase wires and the core The amount of discharge generated between the terminal and the member electrically connected to the second terminal is measured.

この検査方法によれば、請求項6に係る発明と同様に、湿度の影響を受けることなく、過検知を防ぎ、絶縁検査の精度を向上することができる。一方、湿度が所定の値より低いときは、判定時間を短く設定することで、絶縁検査にかかる時間を短くすることができる。 According to this testing method, as with the invention according to claim 6, it is possible to prevent over-detection and improve the accuracy of insulation testing without being affected by humidity. On the other hand, when the humidity is lower than a predetermined value, the time required for the insulation test can be shortened by setting the determination time short.

なお、各構成要素等に付された括弧付きの参照符号は、その構成要素等と後述する実施形態に記載の具体的な構成要素等との対応関係の一例を示すものである。 Note that the reference numerals in parentheses attached to each component etc. indicate an example of the correspondence between the component etc. and specific components etc. described in the embodiments to be described later.

第1実施形態に係る絶縁検査装置の回路構成を示す概略図である。FIG. 1 is a schematic diagram showing a circuit configuration of an insulation testing device according to a first embodiment. ステータコアのスロットに挿入された複数の線材の一部を示す模式図である。FIG. 3 is a schematic diagram showing a portion of a plurality of wire rods inserted into slots of a stator core. 回転電機の各相の線材が直列結線されている状態を示す模式図である。FIG. 2 is a schematic diagram showing a state in which wires of each phase of a rotating electric machine are connected in series. 第1比較例と第1実施形態の絶縁検査方法を比較した表である。It is a table comparing the insulation testing methods of the first comparative example and the first embodiment. 第1比較例と第2実施形態の絶縁検査方法を比較した表である。It is a table comparing the insulation testing methods of the first comparative example and the second embodiment. 第3実施形態の絶縁検査の対象となる回転電機の各相の線材が並列結線される状態を示す模式図である。FIG. 7 is a schematic diagram showing a state in which wires of each phase of a rotating electric machine to be subjected to an insulation test according to a third embodiment are connected in parallel. 第2比較例と第3実施形態の絶縁検査方法を比較した表である。It is a table comparing the insulation testing methods of the second comparative example and the third embodiment. 第4実施形態に係る絶縁検査装置の回路構成を示す概略図である。It is a schematic diagram showing the circuit configuration of the insulation testing device concerning a 4th embodiment. 湿度の影響による放電回数の変化を示した実験結果である。These are experimental results showing changes in the number of discharges due to the influence of humidity.

以下、本発明の実施形態について図面を参照しつつ説明する。なお、以下の各実施形態相互において、互いに同一もしくは均等である部分には、同一符号を付し、その説明を省略する。 Embodiments of the present invention will be described below with reference to the drawings. Note that in each of the following embodiments, parts that are the same or equivalent to each other will be denoted by the same reference numerals, and the description thereof will be omitted.

(第1実施形態)
第1実施形態について図面を参照しつつ説明する。図1~図3に示すように、本実施形態の絶縁検査装置1は、図示しない回転電機のステータコア2の有するスロット21に挿入された複数の線材の皮膜の絶縁状態を検査する装置である。なお、回転電機は、例えば、電動車両に搭載されるモータジェネレータなどに用いられる。
(First embodiment)
A first embodiment will be described with reference to the drawings. As shown in FIGS. 1 to 3, the insulation testing device 1 of this embodiment is a device that tests the insulation state of the coatings of a plurality of wire rods inserted into slots 21 of a stator core 2 of a rotating electrical machine (not shown). Note that the rotating electrical machine is used, for example, as a motor generator mounted on an electric vehicle.

図1に示すように、絶縁検査装置1は、電源部3、切替部4、放電量計測部5、絶縁判定部6および制御部7などを備えている。
電源部3は、交流電源により構成されている。電源部3は、第1端子31と第2端子32を有する。第1端子31は、一方の配線8を経由して切替部4に接続されている。第2端子32は、他方の配線9を経由して切替部4に接続されている。
As shown in FIG. 1, the insulation testing device 1 includes a power supply section 3, a switching section 4, a discharge amount measuring section 5, an insulation determining section 6, a control section 7, and the like.
The power supply section 3 is constituted by an AC power supply. The power supply section 3 has a first terminal 31 and a second terminal 32. The first terminal 31 is connected to the switching unit 4 via one wiring 8. The second terminal 32 is connected to the switching unit 4 via the other wiring 9.

切替部4には、U相、V相、W相の各線材とステータコア2が電気的に接続されている。図2に示すように、U相、V相、W相の各線材は、ステータコア2の有するスロット21に挿入された状態となっている。図2では、ステータコア2の一部と、そのスロット21に挿入された、U相、V相、W相を構成する複数の線材の一部を模式的に示している。なお、線材は、セグメントコイルとも呼ばれる。 The switching unit 4 is electrically connected to the U-phase, V-phase, and W-phase wires and the stator core 2 . As shown in FIG. 2, the U-phase, V-phase, and W-phase wires are inserted into slots 21 of the stator core 2. FIG. 2 schematically shows a part of the stator core 2 and a part of a plurality of wire rods that are inserted into the slots 21 and constitute the U phase, V phase, and W phase. Note that the wire is also called a segment coil.

また、図3に示すように、U相の線材、V相の線材、および、W相の線材はそれぞれ直列結線されている。そして、U相の線材とV相の線材とW相の線材は、Y結線における中性点で結線される前の状態となっている。 Moreover, as shown in FIG. 3, the U-phase wire, the V-phase wire, and the W-phase wire are each connected in series. The U-phase wire, the V-phase wire, and the W-phase wire are in a state before being connected at the neutral point in the Y connection.

図1に示すように、切替部4は、U相、V相、W相の各線材およびステータコア2に対し、第1端子31に接続された一方の配線8と第2端子32に接続された他方の配線9との電気的な接続状態と遮断状態とを切り替えることの可能な切替スイッチである。 As shown in FIG. 1, the switching unit 4 connects the U-phase, V-phase, and W-phase wires and the stator core 2 to one wiring 8 connected to the first terminal 31 and the second terminal 32. This is a changeover switch that can switch between an electrically connected state and an electrically disconnected state with the other wiring 9.

第1端子31と切替部4とを接続する配線8に設けられたブロッキングコイル10は、線材またはステータコア2に生じる部分放電により発生した放電パルス信号(高調波成分)が電源部3に逆流することを防止するためのものである。また、電源部3と切替部4に対して並列に接続される配線13に設けられた結合コンデンサ11は、線材またはステータコア2に生じる部分放電により発生した放電パルス信号のみを流すためのものである。 The blocking coil 10 provided in the wiring 8 connecting the first terminal 31 and the switching unit 4 prevents a discharge pulse signal (harmonic component) generated by partial discharge occurring in the wire or the stator core 2 from flowing back to the power supply unit 3. This is to prevent Further, the coupling capacitor 11 provided in the wiring 13 connected in parallel to the power supply section 3 and the switching section 4 is for passing only the discharge pulse signal generated by the partial discharge occurring in the wire or the stator core 2. .

放電量計測部5は、結合コンデンサ11と直列に設けられている。放電量計測部5は、U相、V相、W相の各線材およびステータコア2のうち、切替部4を介して第1端子31に電気的に接続された部材と、切替部4を介して第2端子32に電気的に接続された部材との間に生じる放電量を計測する。具体的には、放電量計測部5は、部分放電が発生する際に結合コンデンサ11を流れる微小な電流を検出し、その電流値を基に放電電荷量を算出する。そして、放電量計測部5は、その放電電荷量に基づいて放電と見做された回数を所定時間ごとに計測したものを放電量とする。 The discharge amount measuring section 5 is provided in series with the coupling capacitor 11. The discharge amount measuring section 5 is configured to measure the U-phase, V-phase, and W-phase wires and members of the stator core 2 that are electrically connected to the first terminal 31 via the switching section 4 . The amount of discharge generated between the second terminal 32 and a member electrically connected to it is measured. Specifically, the discharge amount measuring section 5 detects a minute current flowing through the coupling capacitor 11 when a partial discharge occurs, and calculates the amount of discharged charge based on the current value. Then, the discharge amount measurement unit 5 measures the number of times that the discharge is considered to be a discharge based on the amount of discharged charge, and determines the amount of discharge as the amount of discharge.

本実施形態では、放電量計測部5は、例えば、下記の2つのパラメータにより放電量を測定している。具体的には、放電量計測部5は、電荷量が所定の大きさ以上であり、且つ、交流により電荷が移動する頻度が所定の頻度以上となるときに、放電が発生していると見做す。そして、放電量計測部5は、その放電の回数を所定時間ごとに計測したものを放電量とする。 In this embodiment, the discharge amount measurement unit 5 measures the discharge amount using, for example, the following two parameters. Specifically, the discharge amount measurement unit 5 determines that a discharge is occurring when the amount of charge is greater than a predetermined value and the frequency of charge movement due to alternating current is greater than or equal to a predetermined frequency. I do. Then, the discharge amount measuring section 5 measures the number of times of the discharge every predetermined time and sets it as the discharge amount.

絶縁判定部6は、放電量計測部5により計測された放電量に基づき、線材の皮膜が所定の品質基準を満たす規格内の製品であるか否かを判定する。具体的には、絶縁判定部6は、放電開始から一定時間経過したときに放電量計測部5により計測される放電量が所定の閾値より小さい場合、線材の皮膜が所定の品質基準を満たす規格内の製品であると判定する。一方、絶縁判定部6は、放電開始から一定時間経過したときに放電量計測部5により計測される放電量が所定の閾値より大きい場合、線材の皮膜が所定の品質基準を満たさない規格外の製品であると判定する。 The insulation determination unit 6 determines whether the coating of the wire is a product that meets predetermined quality standards and is within specifications based on the amount of discharge measured by the amount of discharge measurement unit 5. Specifically, if the discharge amount measured by the discharge amount measuring section 5 after a certain period of time has elapsed from the start of discharge is smaller than a predetermined threshold value, the insulation determination section 6 determines that the coating of the wire meets a predetermined quality standard. It is determined that the product is within the range. On the other hand, if the amount of discharge measured by the amount of discharge measuring section 5 after a certain period of time has elapsed from the start of discharge is greater than a predetermined threshold, the insulation determination section 6 determines that the coating of the wire does not meet the predetermined quality standards. Determine that it is a product.

絶縁判定部6による判定結果に関する情報は、制御部7に伝送される。制御部7は、絶縁検査装置1の各部の動作を制御する。具体的には、制御部7は、電源部3の出力電圧を制御する。また、制御部7は、切替部4の動作を制御することが可能である。 Information regarding the determination result by the insulation determination section 6 is transmitted to the control section 7. The control section 7 controls the operation of each section of the insulation testing device 1. Specifically, the control section 7 controls the output voltage of the power supply section 3. Further, the control unit 7 can control the operation of the switching unit 4.

本実施形態では、制御部7は、U相、V相、W相の各線材およびステータコア2の全てが第1端子31または第2端子32と電気的に接続されるように切替部4の動作を制御する。また、制御部7は、U相、V相、W相の各線材およびステータコア2のいずれも第1端子31および第2端子32の両方に対し絶縁状態にならないように切替部4の動作を制御する。 In the present embodiment, the control unit 7 operates the switching unit 4 so that all of the U-phase, V-phase, and W-phase wires and the stator core 2 are electrically connected to the first terminal 31 or the second terminal 32. control. Further, the control unit 7 controls the operation of the switching unit 4 so that none of the U-phase, V-phase, and W-phase wires and the stator core 2 are insulated from both the first terminal 31 and the second terminal 32. do.

これにより、絶縁検査装置1は、絶縁検査を行う際、U相、V相、W相の各線材およびステータコア2の全てを第1端子31または第2端子32と電気的に接続することで、浮遊電位を無くすことが可能である。そのため、絶縁検査を行っていない非測定部位から絶縁検査を行っている測定部位へ放電が誘発されることが無い。したがって、この絶縁検査装置1は、所定の品質基準を満たす規格内の線材を誤って品質基準を満たさない規格外の線材と判定する過検知を防ぎ、絶縁検査の精度を向上することができる。 As a result, when performing an insulation test, the insulation testing device 1 electrically connects all of the U-phase, V-phase, and W-phase wires and the stator core 2 to the first terminal 31 or the second terminal 32. It is possible to eliminate floating potential. Therefore, no discharge is induced from the non-measurement area where the insulation test is not being performed to the measurement area where the insulation test is being performed. Therefore, this insulation testing device 1 can prevent over-detection of erroneously determining a wire rod within the standard that meets a predetermined quality standard as a wire rod outside the standard that does not meet the quality standard, and can improve the accuracy of the insulation test.

さらに、第1実施形態の絶縁検査装置1は、相間および対地の絶縁検査に関し、複数の部位を同時に検査することが可能である。そのため、一般的な絶縁検査の方法に比べて、検査回数が少なくなり、絶縁検査にかかる時間を短くすることができる。 Furthermore, the insulation testing device 1 of the first embodiment is capable of simultaneously testing a plurality of parts regarding phase-to-phase and ground-to-earth insulation testing. Therefore, compared to a general insulation testing method, the number of testing times is reduced, and the time required for insulation testing can be shortened.

以下、図4の表を参照しつつ、第1実施形態の絶縁検査装置1による絶縁検査の方法と、第1比較例の絶縁検査の方法を対比して説明する。なお、第1比較例は、U相の線材、V相の線材、W相の線材がそれぞれ直列結線されている線材に対する一般的な絶縁検査の方法を示している。なお、図4の表に記載した絶縁検査の順番は任意に変更することが可能である。このことは、後述する第2、第3実施形態で参照する図5、図7の表についても同じである。 Hereinafter, with reference to the table of FIG. 4, the insulation testing method by the insulation testing device 1 of the first embodiment and the insulation testing method of the first comparative example will be explained in comparison. Note that the first comparative example shows a general insulation testing method for a wire in which a U-phase wire, a V-phase wire, and a W-phase wire are connected in series. Note that the order of the insulation tests listed in the table of FIG. 4 can be changed arbitrarily. This also applies to the tables in FIGS. 5 and 7 that will be referred to in the second and third embodiments described later.

まず、第1比較例による絶縁検査の方法を説明する。
第1比較例では、1回目~3回目で相間の絶縁検査が行われ、4回目で対地の絶縁検査が行われる。
具体的には、1回目で、U相の線材とV相の線材との絶縁検査が行われる。1回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とU相の線材とが電気的に接続され、電源部3の第2端子32とV相の線材とが電気的に接続される。そして、電源部3からU相の線材とV相の線材とに交流電圧が印加され、U相の線材とV相の線材との間に生じる放電量が放電量計測部5により計測される。
First, an insulation inspection method according to a first comparative example will be explained.
In the first comparative example, the insulation test between the phases is performed in the first to third tests, and the ground insulation test is performed in the fourth test.
Specifically, at the first time, an insulation test is performed between the U-phase wire rod and the V-phase wire rod. In the first insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the U-phase wire, and to connect the second terminal 32 of the power supply unit 3 to the V-phase wire. electrically connected. Then, an AC voltage is applied from the power supply unit 3 to the U-phase wire and the V-phase wire, and the amount of discharge generated between the U-phase wire and the V-phase wire is measured by the discharge amount measurement unit 5.

なお、1回目の絶縁検査では、W相の線材とステータコア2が非測定部位となる。そのため、その非測定部位に浮遊電位が存在すると、そこから測定部位へ放電が誘発され、放電が増える傾向にある。そのため、第1比較例では、所定の品質基準を満たしている規格内の線材を誤って品質基準を満たさない規格外の線材と判定するといった過検知が生じることで、絶縁検査の精度が低下するおそれがある。 Note that in the first insulation test, the W-phase wire rod and the stator core 2 are not measured. Therefore, if a floating potential exists in the non-measurement area, a discharge is induced from there to the measurement area, and the discharge tends to increase. Therefore, in the first comparative example, over-detection occurs, such as erroneously determining a within-standard wire material that meets predetermined quality standards as a non-standard wire material that does not meet the quality standards, resulting in a decrease in the accuracy of insulation inspection. There is a risk.

続いて、2回目で、V相の線材とW相の線材との絶縁検査が行われる。3回目で、W相の線材とU相の線材との絶縁検査が行われる。なお、2回目と3回目の絶縁検査は、1回目の絶縁検査の説明に対し、U、V、Wが異なるのみであるので、説明を省略する。 Subsequently, in the second time, an insulation test is performed between the V-phase wire and the W-phase wire. At the third time, an insulation test is performed between the W-phase wire rod and the U-phase wire rod. Note that the second and third insulation tests differ only in U, V, and W from the description of the first insulation test, so the description will be omitted.

4回目で、U相、V相、W相の線材とステータコア2との絶縁検査が行われる。4回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とU相、V相、W相の線材とが電気的に接続され、電源部3の第2端子32とステータコア2とが電気的に接続される。そして、電源部3からU相、V相、W相の線材とステータコア2とに交流電圧が印加され、U相、V相、W相の線材とステータコア2との間に生じる放電量が放電量計測部5により計測される。 In the fourth test, the insulation between the U-phase, V-phase, and W-phase wires and the stator core 2 is inspected. In the fourth insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the U-phase, V-phase, and W-phase wires, and connect the second terminal 32 of the power supply unit 3 to the wires of the U, V, and W phases. Stator core 2 is electrically connected. Then, AC voltage is applied from the power supply section 3 to the U-phase, V-phase, and W-phase wires and the stator core 2, and the amount of discharge generated between the U-phase, V-phase, and W-phase wires and the stator core 2 is the amount of discharge. Measured by the measuring section 5.

第1比較例では、1回目~4回目の絶縁検査において、U相、V相、W相のいずれかの線材の皮膜が所定の品質基準を満たさない規格外の製品であると判定された場合、その製品は廃却されることとなる。 In the first comparative example, in the first to fourth insulation inspections, it was determined that the coating of the U-phase, V-phase, or W-phase wire rod was a substandard product that did not meet the predetermined quality standards. , the product will be discarded.

次に、第1実施形態による絶縁検査の方法を説明する。
第1実施形態では、1回目と2回目で相間の絶縁検査と対地の絶縁検査とが同時に行われ、3回目で対地の絶縁検査が行われる。
具体的には、1回目で、U相の線材と、V相、W相の線材およびステータコア2との絶縁検査が行われる。1回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とU相の線材とが電気的に接続され、電源部3の第2端子32とV相、W相の線材およびステータコア2とが電気的に接続される。そして、電源部3からU相の線材と、V相、W相の線材およびステータコア2とに交流電圧が印加され、U相の線材と、V相、W相の線材およびステータコア2との間に生じる放電量が放電量計測部5により計測される。
Next, an insulation testing method according to the first embodiment will be explained.
In the first embodiment, the inter-phase insulation test and the ground insulation test are performed simultaneously in the first and second times, and the ground insulation test is performed in the third time.
Specifically, at the first time, an insulation test is performed between the U-phase wire rod, the V-phase and W-phase wire rods, and the stator core 2. In the first insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the U-phase wire, and connect the second terminal 32 of the power supply unit 3 to the V-phase and W-phase wires. The wire and stator core 2 are electrically connected. Then, an AC voltage is applied from the power supply unit 3 to the U-phase wire, the V-phase, W-phase wire, and the stator core 2, and between the U-phase wire, the V-phase, W-phase wire, and the stator core 2. The amount of discharge that occurs is measured by the amount of discharge measuring section 5.

次に、2回目で、V相の線材と、W相、U相の線材およびステータコア2との絶縁検査が行われる。2回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とV相の線材とが電気的に接続され、電源部3の第2端子32とW相、U相の線材およびステータコア2とが電気的に接続される。そして、電源部3からV相の線材と、W相、U相の線材およびステータコア2とに交流電圧が印加され、V相の線材と、W相、U相の線材およびステータコア2との間に生じる放電量が放電量計測部5により計測される。 Next, an insulation test is performed for the second time between the V-phase wire rod, the W-phase and U-phase wire rods, and the stator core 2. In the second insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the V-phase wire, and connect the second terminal 32 of the power supply unit 3 to the W-phase and U-phase wires. The wire and stator core 2 are electrically connected. Then, an AC voltage is applied from the power supply unit 3 to the V-phase wire, the W-phase, U-phase wire, and the stator core 2, and between the V-phase wire, the W-phase, U-phase wire, and the stator core 2. The amount of discharge that occurs is measured by the amount of discharge measuring section 5.

最後に、3回目で、U相、V相、W相の線材と、ステータコア2との絶縁検査が行われる。3回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とU相、V相、W相の線材とが電気的に接続され、電源部3の第2端子32とステータコア2とが電気的に接続される。そして、電源部3からU相、V相、W相の線材と、ステータコア2とに交流電圧が印加され、U相、V相、W相の線材と、ステータコア2との間に生じる放電量が放電量計測部5により計測される。 Finally, at the third time, an insulation test is performed between the U-phase, V-phase, and W-phase wires and the stator core 2. In the third insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the U-phase, V-phase, and W-phase wires, and connect the second terminal 32 of the power supply unit 3 to the wires of the U phase, V phase, and W phase. Stator core 2 is electrically connected. Then, AC voltage is applied from the power supply unit 3 to the U-phase, V-phase, W-phase wires and the stator core 2, and the amount of discharge generated between the U-phase, V-phase, W-phase wires and the stator core 2 is increased. It is measured by the discharge amount measuring section 5.

第1実施形態では、1回目~3回目の絶縁検査において、U相、V相、W相のいずれかの線材の皮膜が所定の品質基準を満たさない規格外の製品であると判定された場合、その製品は廃却されることとなる。 In the first embodiment, in the first to third insulation inspections, if it is determined that the coating of any of the U-phase, V-phase, and W-phase wires is a substandard product that does not meet the predetermined quality standards. , the product will be discarded.

このように、第1実施形態による絶縁検査の方法は、第1比較例の絶縁検査の方法と比べて、検査回数が少なくなるので、絶縁検査にかかる時間を短くすることができる。このことは、絶縁検査装置1の台数低減、すなわち、設備投資の低減にも繋がることになる。 In this way, the insulation testing method according to the first embodiment requires fewer tests compared to the insulation testing method of the first comparative example, so the time required for insulation testing can be shortened. This also leads to a reduction in the number of insulation testing devices 1, that is, a reduction in equipment investment.

なお、上述した第1実施形態の1回目と2回目の配線の接続状態を、第1の直列結線用測定状態と呼ぶこととする。すなわち、第1の直列結線用測定状態とは、U相、V相、W相のうちいずれか1つの相の線材と第1端子31とが電気的に接続され、且つ、他の2つの相の線材およびステータコア2と第2端子32とが電気的に接続された状態である。 Note that the first and second wiring connection states in the first embodiment described above will be referred to as the first series connection measurement state. In other words, the first series connection measurement state means that the wire of one of the U-phase, V-phase, and W-phase is electrically connected to the first terminal 31, and the wire of the other two phases is electrically connected to the first terminal 31. The stator core 2 and the second terminal 32 are electrically connected to each other.

また、上述した第1実施形態の3回目の配線の接続状態を、第2の直列結線用測定状態と呼ぶこととする。すなわち、第2の直列結線用測定状態とは、U相、V相、W相の全ての線材と第1端子31とが電気的に接続され、且つ、ステータコア2と第2端子32とが電気的に接続された状態である。
第1の直列結線用測定状態と第2の直列結線用測定状態のいずれの状態も、非測定部位が生じることが無い。
Furthermore, the third wiring connection state in the first embodiment described above will be referred to as the second series connection measurement state. That is, the second series connection measurement state means that all the U-phase, V-phase, and W-phase wires are electrically connected to the first terminal 31, and the stator core 2 and the second terminal 32 are electrically connected. connected.
In both the first series connection measurement state and the second series connection measurement state, no non-measurement portion occurs.

以上説明した第1実施形態の絶縁検査装置1およびその方法は、次の作用効果を奏するものである。
(1)第1実施形態では、絶縁検査の際、制御部7が切替部4を制御し、U相、V相、W相の各線材およびステータコア2のいずれも第1端子31および第2端子32の両方に対し絶縁状態にならないようにする。また、その際、制御部7は切替部4を制御し、U相、V相、W相の各線材およびステータコア2の全てが第1端子31または第2端子32と電気的に接続されるようにする。これにより、絶縁検査の際、非測定部位を無くすことが可能である。そのため、第1実施形態は、第1比較例のように非測定部位から測定部位へ放電が誘発されることが無い。したがって、第1実施形態の絶縁検査装置1およびその方法は、過検知を防ぎ、絶縁検査の精度を向上することができる。
The insulation testing device 1 and its method of the first embodiment described above have the following effects.
(1) In the first embodiment, during an insulation test, the control unit 7 controls the switching unit 4, and all of the U-phase, V-phase, and W-phase wires and the stator core 2 are connected to the first terminal 31 and the second terminal. 32 so as not to be in an insulated state with respect to both. In addition, at this time, the control unit 7 controls the switching unit 4 so that all of the U-phase, V-phase, and W-phase wires and the stator core 2 are electrically connected to the first terminal 31 or the second terminal 32. Make it. This makes it possible to eliminate non-measurable parts during insulation testing. Therefore, in the first embodiment, unlike the first comparative example, discharge is not induced from the non-measurement site to the measurement site. Therefore, the insulation testing device 1 and its method of the first embodiment can prevent over-detection and improve the accuracy of insulation testing.

(2)第1実施形態では、絶縁検査の際、制御部7が切替部4を制御し、上述した第1の直列結線用測定状態と第2の直列結線用測定状態とする。これにより、第1実施形態の絶縁検査装置1およびその方法は、第1比較例として説明した一般的な検査方法に比べて、検査回数を少なくすることが可能である。したがって、第1実施形態の絶縁検査装置1およびその方法は、浮遊電位を無くすことで絶縁検査の精度を向上すると共に、絶縁検査にかかる時間を短くすることができる。 (2) In the first embodiment, during the insulation test, the control unit 7 controls the switching unit 4 to set the above-described first series connection measurement state and second series connection measurement state. Thereby, the insulation testing device 1 and its method of the first embodiment can reduce the number of tests compared to the general testing method described as the first comparative example. Therefore, the insulation testing device 1 and its method of the first embodiment can improve the accuracy of insulation testing by eliminating floating potentials, and can shorten the time required for insulation testing.

(第2実施形態)
第2実施形態について説明する。第2実施形態は、第1実施形態に対して絶縁検査装置1による検査方法の一部を変更したものであり、その他については第1実施形態と同様であるため、第1実施形態と異なる部分についてのみ説明する。
なお、第2実施形態においても、第1実施形態と同様に、U相の線材、V相の線材、および、W相の線材はそれぞれ直列結線されているものとする。
(Second embodiment)
A second embodiment will be described. The second embodiment differs from the first embodiment in that a part of the inspection method by the insulation inspection device 1 is changed, and the other parts are the same as the first embodiment. I will only explain about.
In addition, in the second embodiment, similarly to the first embodiment, it is assumed that the U-phase wire, the V-phase wire, and the W-phase wire are each connected in series.

第2実施形態の絶縁検査装置1による絶縁検査の方法を、図5の表に示す。なお、図5の表に記載されている第1比較例の絶縁検査の方法は、第1実施形態の説明の中で記載したものと同一であるので、説明を省略する。 The table of FIG. 5 shows an insulation testing method using the insulation testing apparatus 1 of the second embodiment. Note that the insulation testing method of the first comparative example described in the table of FIG. 5 is the same as that described in the description of the first embodiment, so the description will be omitted.

第2実施形態では、1回目と2回目で相間の絶縁検査と対地の絶縁検査とが同時に行われる。
具体的には、1回目で、V相、W相の線材と、U相の線材およびステータコア2との絶縁検査が行われる。1回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とV相、W相の線材とが電気的に接続され、電源部3の第2端子32とU相の線材およびステータコア2とが電気的に接続される。そして、電源部3からV相、W相の線材と、U相の線材およびステータコア2とに交流電圧が印加され、V相、W相の線材と、U相の線材およびステータコア2との間に生じる放電量が放電量計測部5により計測される。
In the second embodiment, the inter-phase insulation test and the ground insulation test are performed simultaneously in the first and second times.
Specifically, at the first time, an insulation test is performed between the V-phase and W-phase wire rods, the U-phase wire rod, and the stator core 2. In the first insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the V-phase and W-phase wires, and to connect the second terminal 32 of the power supply unit 3 to the U-phase wires. The wire and stator core 2 are electrically connected. Then, AC voltage is applied from the power supply unit 3 to the V-phase and W-phase wires, the U-phase wire and the stator core 2, and the voltage is applied between the V-phase and W-phase wires, the U-phase wire and the stator core 2. The amount of discharge that occurs is measured by the amount of discharge measuring section 5.

次に、2回目で、W相、U相の線材と、V相の線材およびステータコア2との絶縁検査が行われる。2回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とW相、U相の線材とが電気的に接続され、電源部3の第2端子32とV相の線材およびステータコア2とが電気的に接続される。そして、電源部3からW相、U相の線材と、V相の線材およびステータコア2とに交流電圧が印加され、W相、U相の線材と、V相の線材およびステータコア2との間に生じる放電量が放電量計測部5により計測される。 Next, the insulation of the W-phase and U-phase wire rods, the V-phase wire rod, and the stator core 2 is inspected for the second time. In the second insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the W-phase and U-phase wires, and to connect the second terminal 32 of the power supply unit 3 to the V-phase wires. The wire and stator core 2 are electrically connected. Then, AC voltage is applied from the power supply section 3 to the W-phase and U-phase wires, the V-phase wire and the stator core 2, and the AC voltage is applied between the W-phase and U-phase wires, the V-phase wire and the stator core 2. The amount of discharge that occurs is measured by the amount of discharge measuring section 5.

第2実施形態では、1回目と2回目の絶縁検査において、U相、V相、W相のいずれかの線材の皮膜が所定の品質基準を満たさない規格外の製品であると判定された場合、その製品は廃却されることとなる。 In the second embodiment, in the case where it is determined in the first and second insulation tests that the coating of any of the U-phase, V-phase, and W-phase wires is a substandard product that does not meet the predetermined quality standards. , the product will be discarded.

以上説明したように、第2実施形態では、絶縁検査の際、U相、V相、W相のうちいずれか2つの相の線材と第1端子31とが電気的に接続され、且つ、他の1つの相の線材およびステータコア2と第2端子32とが電気的に接続された状態となるようにする。これにより、U相、V相、W相の各線材およびステータコア2の全てを第1端子31または第2端子32と電気的に接続することで、浮遊電位を無くすことが可能である。そのため、第2実施形態の絶縁検査装置1およびその方法も、第1実施形態と同様に、過検知を防ぎ、絶縁検査の精度を向上することができる。 As explained above, in the second embodiment, during an insulation test, the wires of any two phases among the U phase, V phase, and W phase are electrically connected to the first terminal 31, and The wire of one phase and the stator core 2 and the second terminal 32 are electrically connected. Thereby, floating potential can be eliminated by electrically connecting all of the U-phase, V-phase, and W-phase wires and the stator core 2 to the first terminal 31 or the second terminal 32. Therefore, similarly to the first embodiment, the insulation testing device 1 and method of the second embodiment can prevent overdetection and improve the accuracy of insulation testing.

また、第2実施形態による絶縁検査の方法は、第1比較例の絶縁検査の方法と比べて、検査回数が少なくなるので、絶縁検査にかかる時間を短くすることができる。
さらに、第2実施形態による絶縁検査の方法は、第1実施形態の絶縁検査の方法と比べても、検査回数をより少なくすることができる。
Furthermore, the insulation testing method according to the second embodiment requires fewer tests compared to the insulation testing method of the first comparative example, so the time required for insulation testing can be shortened.
Furthermore, the insulation testing method according to the second embodiment can reduce the number of times of testing even compared to the insulation testing method according to the first embodiment.

(第3実施形態)
第3実施形態について説明する。第3実施形態は、第1実施形態等に対して絶縁検査装置1による検査方法の一部を変更したものであり、その他については第1実施形態等と同様であるため、第1実施形態等と異なる部分についてのみ説明する。
(Third embodiment)
A third embodiment will be described. The third embodiment differs from the first embodiment etc. in that part of the inspection method by the insulation testing device 1 is changed, and the other aspects are the same as in the first embodiment etc. Only the different parts will be explained.

なお、図6に示すように、第3実施形態では、U相の線材、V相の線材、および、W相の線材はそれぞれ並列結線されるものとする。以下の説明において、U相の線材のうち、並列結線される一方の線材をU1の線材と呼び、他方の線材をU2の線材と呼ぶ。V相の線材のうち、並列結線される一方の線材をV1の線材と呼び、他方の線材をV2の線材と呼ぶ。W相の線材のうち、並列結線される一方の線材をW1の線材と呼び、他方の線材をW2の線材と呼ぶ。 In addition, as shown in FIG. 6, in the third embodiment, the U-phase wire, the V-phase wire, and the W-phase wire are each connected in parallel. In the following description, among the U-phase wire rods, one of the wire rods connected in parallel will be referred to as the U1 wire rod, and the other wire rod will be referred to as the U2 wire rod. Among the V-phase wire rods, one wire rod connected in parallel is called a V1 wire rod, and the other wire rod is called a V2 wire rod. Among the W-phase wire rods, one wire rod connected in parallel is called a W1 wire rod, and the other wire rod is called a W2 wire rod.

図7を参照しつつ、第3実施形態の絶縁検査装置1による絶縁検査の方法と、第2比較例の絶縁検査の方法を対比して説明する。なお、第2比較例は、U相の線材、V相の線材、W相の線材がそれぞれ並列結線されている線材に対する一般的な絶縁検査の方法を示している。 Referring to FIG. 7, the insulation testing method by the insulation testing device 1 of the third embodiment and the insulation testing method of the second comparative example will be explained in comparison. Note that the second comparative example shows a general insulation inspection method for a wire in which a U-phase wire, a V-phase wire, and a W-phase wire are connected in parallel.

まず、第2比較例による絶縁検査の方法を説明する。
第2比較例では、1回目~3回目で相間の絶縁検査が行われ、4回目~6回目で相内の絶縁検査が行われ、7回目で対地の絶縁検査が行われる。
具体的には、1回目で、U1、U2の線材とV1、V2の線材との絶縁検査が行われる。1回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とU1、U2の線材とが電気的に接続され、電源部3の第2端子32とV1、V2の線材とが電気的に接続される。そして、電源部3からU1、U2の線材とV1、V2の線材とに交流電圧が印加され、U1、U2の線材とV1、V2の線材との間に生じる放電量が放電量計測部5により計測される。
First, an insulation inspection method according to a second comparative example will be explained.
In the second comparative example, an insulation test between phases is performed in the first to third times, an insulation test within a phase is performed in the fourth to sixth times, and a ground insulation test is performed in the seventh time.
Specifically, at the first time, an insulation test is performed between the wires U1 and U2 and the wires V1 and V2. In the first insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the wires of U1 and U2, and connect the second terminal 32 of the power supply unit 3 to the wires of V1 and V2. are electrically connected. Then, an AC voltage is applied from the power supply section 3 to the wires U1 and U2 and the wires V1 and V2, and the amount of discharge generated between the wires U1 and U2 and the wires V1 and V2 is measured by the discharge amount measuring section 5. be measured.

なお、1回目の絶縁検査では、W1、W2の線材とステータコア2が非測定部位となる。そのため、その非測定部位に浮遊電位が存在すると、そこから測定部位へ放電が誘発され、放電が増える傾向にある。 Note that in the first insulation test, the wires W1 and W2 and the stator core 2 are not measured. Therefore, if a floating potential exists in the non-measurement area, a discharge is induced from there to the measurement area, and the discharge tends to increase.

続いて、2回目で、V1、V2の線材とW1、W2相の線材との絶縁検査が行われる。3回目で、W1、W2の線材とU1、U2の線材との絶縁検査が行われる。なお、2回目と3回目の絶縁検査は、1回目の絶縁検査の説明に対し、U、V、Wが異なるのみであるので、説明を省略する。 Subsequently, an insulation test is performed for the second time between the V1 and V2 wires and the W1 and W2 phase wires. At the third time, an insulation test is performed between the wires W1 and W2 and the wires U1 and U2. Note that the second and third insulation tests differ only in U, V, and W from the description of the first insulation test, so the description will be omitted.

4回目で、U1の線材とU2の線材との絶縁検査が行われる。4回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とU1の線材とが電気的に接続され、電源部3の第2端子32とU2の線材とが電気的に接続される。そして、電源部3からU1の線材とU2の線材とに交流電圧が印加され、U1の線材とU2の線材との間に生じる放電量が放電量計測部5により計測される。
なお、4回目の絶縁検査では、V1、V2、W1、W2の線材とステータコア2が非測定部位となる。そのため、その非測定部位に浮遊電位が存在すると、そこから測定部位へ放電が誘発され、放電が増える傾向にある。
At the fourth time, an insulation test is performed between the wire rod U1 and the wire rod U2. In the fourth insulation test, the first terminal 31 of the power supply section 3 and the wire of U1 are electrically connected by the operation of the switching section 4, and the second terminal 32 of the power supply section 3 and the wire of U2 are electrically connected. connected to. Then, an AC voltage is applied from the power supply section 3 to the wire rod U1 and the wire rod U2, and the amount of discharge generated between the wire rod U1 and the wire rod U2 is measured by the discharge amount measuring section 5.
In addition, in the fourth insulation test, the wires V1, V2, W1, and W2 and the stator core 2 are non-measured parts. Therefore, if a floating potential exists in the non-measurement area, a discharge is induced from there to the measurement area, and the discharge tends to increase.

続いて、5回目で、V1の線材とV2相の線材との絶縁検査が行われる。6回目で、W1の線材とW2の線材との絶縁検査が行われる。なお、5回目と6回目の絶縁検査は、4回目の絶縁検査の説明に対し、U、V、Wが異なるのみであるので、説明を省略する。 Subsequently, at the fifth time, an insulation test is performed between the V1 wire and the V2 phase wire. At the sixth time, an insulation test is performed between the wire rod W1 and the wire rod W2. Note that the fifth and sixth insulation tests differ only in U, V, and W from the description of the fourth insulation test, so the explanation will be omitted.

7回目で、U相、V相、W相の線材とステータコア2との絶縁検査が行われる。7回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とU1、U2、V1、V2、W1、W2の線材とが電気的に接続され、電源部3の第2端子32とステータコア2とが電気的に接続される。そして、電源部3からU1、U2、V1、V2、W1、W2の線材とステータコア2とに交流電圧が印加され、U1、U2、V1、V2、W1、W2の線材とステータコア2との間に生じる放電量が放電量計測部5により計測される。 At the seventh time, an insulation test between the U-phase, V-phase, and W-phase wires and the stator core 2 is performed. In the seventh insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the wires U1, U2, V1, V2, W1, and W2, and the second terminal of the power supply unit 3 Terminals 32 and stator core 2 are electrically connected. Then, AC voltage is applied from the power supply section 3 to the wires U1, U2, V1, V2, W1, W2 and the stator core 2, and between the wires U1, U2, V1, V2, W1, W2 and the stator core 2. The amount of discharge that occurs is measured by the amount of discharge measuring section 5.

第2比較例では、1回目~7回目の絶縁検査において、U1、U2、V1、V2、W1、W2のいずれかの線材の皮膜が所定の品質基準を満たさない規格外の製品であると判定された場合、その製品は廃却されることとなる。 In the second comparative example, in the first to seventh insulation tests, it was determined that the coating of any of the wires U1, U2, V1, V2, W1, and W2 was a substandard product that did not meet the predetermined quality standards. If so, the product will be discarded.

次に、第3実施形態による絶縁検査の方法を説明する。
第3実施形態では、1回目と2回目で相間の絶縁検査と対地の絶縁検査とが同時に行われ、3回目で相内の絶縁検査と対地の絶縁検査とが同時に行われる。
具体的には、1回目で、V相、W相の線材と、U相の線材およびステータコア2との絶縁検査が行われる。1回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とV1、V2、W1、W2の線材とが電気的に接続され、電源部3の第2端子32とU1、U2の線材およびステータコア2とが電気的に接続される。そして、電源部3からV1、V2、W1、W2の線材と、U1、U2の線材およびステータコア2とに交流電圧が印加され、V1、V2、W1、W2の線材と、U1、U2の線材およびステータコア2との間に生じる放電量が放電量計測部5により計測される。
Next, an insulation testing method according to the third embodiment will be described.
In the third embodiment, the inter-phase insulation test and the ground insulation test are performed simultaneously in the first and second times, and the intra-phase insulation test and the ground insulation test are performed simultaneously in the third time.
Specifically, at the first time, an insulation test is performed between the V-phase and W-phase wire rods, the U-phase wire rod, and the stator core 2. In the first insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the wires V1, V2, W1, and W2, and connect the second terminal 32 of the power supply unit 3 to the wires U1. , U2 and the stator core 2 are electrically connected. Then, an AC voltage is applied from the power supply section 3 to the wires V1, V2, W1, and W2, the wires U1 and U2, and the stator core 2, and the wires V1, V2, W1, and W2, the wires U1, U2, and the stator core 2 are The amount of discharge generated between the stator core 2 and the stator core 2 is measured by the amount measuring section 5 .

次に、2回目で、W1、W2、U1、U2の線材と、V1、V2の線材およびステータコア2との絶縁検査が行われる。2回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とW1、W2、U1、U2の線材とが電気的に接続され、電源部3の第2端子32とV1、V2の線材およびステータコア2とが電気的に接続される。そして、電源部3からW1、W2、U1、U2の線材と、V1、V2の線材およびステータコア2とに交流電圧が印加され、W1、W2、U1、U2の線材と、V1、V2の線材およびステータコア2との間に生じる放電量が放電量計測部5により計測される。 Next, at the second time, an insulation test is performed between the wires W1, W2, U1, and U2, the wires V1, V2, and the stator core 2. In the second insulation test, the first terminal 31 of the power supply section 3 and the wires W1, W2, U1, and U2 are electrically connected by the operation of the switching section 4, and the second terminal 32 of the power supply section 3 and the wires of V1 are electrically connected. , V2 and the stator core 2 are electrically connected. Then, an AC voltage is applied from the power supply section 3 to the wires W1, W2, U1, and U2, the wires V1 and V2, and the stator core 2, and the wires W1, W2, U1, and U2, the wires V1, V2, and the stator core 2 are connected to each other. The amount of discharge generated between the stator core 2 and the stator core 2 is measured by the amount measuring section 5 .

最後に、3回目で、U1、V1、W1の線材と、U2、V2、W2の線材およびステータコア2との絶縁検査が行われる。3回目の絶縁検査では、切替部4の動作により、電源部3の第1端子31とU1、V1、W1の線材とが電気的に接続され、電源部3の第2端子32とU2、V2、W2の線材およびステータコア2とが電気的に接続される。そして、電源部3からU1、V1、W1の線材と、U2、V2、W2の線材およびステータコア2とに交流電圧が印加され、U1、V1、W1の線材と、U2、V2、W2の線材およびステータコア2との間に生じる放電量が放電量計測部5により計測される。 Finally, at the third time, an insulation test is performed between the wires U1, V1, and W1, the wires U2, V2, and W2, and the stator core 2. In the third insulation test, the switching unit 4 operates to electrically connect the first terminal 31 of the power supply unit 3 to the wires U1, V1, and W1, and connect the second terminal 32 of the power supply unit 3 to the wires U2, V2. , W2 and the stator core 2 are electrically connected. Then, an AC voltage is applied from the power supply unit 3 to the wires U1, V1, W1, the wires U2, V2, W2, and the stator core 2, and the wires U1, V1, W1, the wires U2, V2, W2 and The amount of discharge generated between the stator core 2 and the stator core 2 is measured by the amount measuring section 5 .

第3実施形態では、1回目~3回目の絶縁検査において、U1、U2、V1、V2、W1、W2のいずれかの線材の皮膜が所定の品質基準を満たさない規格外の製品であると判定された場合、その製品は廃却されることとなる。 In the third embodiment, in the first to third insulation tests, it is determined that the coating of any of the wires U1, U2, V1, V2, W1, and W2 is a substandard product that does not meet the predetermined quality standards. If so, the product will be discarded.

このように、第3実施形態による絶縁検査の方法は、第2比較例の絶縁検査の方法と比べて、検査回数が少なくなるので、絶縁検査にかかる時間を短くすることができる。 In this manner, the insulation testing method according to the third embodiment requires fewer tests compared to the insulation testing method of the second comparative example, so the time required for insulation testing can be shortened.

なお、上述した第3実施形態の1回目と2回目の配線の接続状態を、第1の並列結線用測定状態と呼ぶこととする。すなわち、第1の並列結線用測定状態とは、U相、V相、W相のうちいずれか2つの相でそれぞれ並列結線された線材と第1端子31とが電気的に接続され、且つ、他の1つの相で並列結線された線材およびステータコア2と第2端子32とが電気的に接続された状態である。 Note that the first and second wiring connection states in the third embodiment described above will be referred to as the first parallel connection measurement state. That is, the first parallel connection measurement state means that the wire rods connected in parallel in any two of the U phase, V phase, and W phase are electrically connected to the first terminal 31, and The wires and stator core 2 connected in parallel in the other phase are electrically connected to the second terminal 32.

また、上述した第3実施形態の3回目の配線の接続状態を、第2の並列結線用測定状態と呼ぶこととする。すなわち、第2の並列結線用測定状態とは、U相、V相、W相の全ての相において並列結線された一方側の線材と第1端子31とが電気的に接続され、且つ、U相、V相、W相の全ての相において並列結線された他方側の線材およびステータコア2と第2端子32とが電気的に接続された状態である。
第1の並列結線用測定状態と第2の並列結線用測定状態のいずれも、非測定部位が生じることが無い。
Furthermore, the third wiring connection state in the third embodiment described above will be referred to as the second parallel connection measurement state. In other words, the second parallel connection measurement state is one in which the first terminal 31 is electrically connected to the wire rod on one side connected in parallel in all phases of the U phase, V phase, and W phase, and The second terminal 32 is electrically connected to the other wire rod and the stator core 2 connected in parallel in all the phases, the V phase, and the W phase.
In both the first parallel connection measurement state and the second parallel connection measurement state, no non-measurement portion occurs.

以上説明した第3実施形態では、絶縁検査の際、制御部7が切替部4を制御し、上述した第1の並列結線用測定状態と第2の並結線用測定状態とする。これにより、第3実施形態の絶縁検査装置1およびその方法は、第2比較例として説明した一般的な検査方法に比べて、検査回数を少なくすることが可能である。したがって、第3実施形態の絶縁検査装置1およびその方法は、浮遊電位を無くすことで絶縁検査の精度を向上すると共に、絶縁検査にかかる時間を短くすることができる。 In the third embodiment described above, during the insulation test, the control unit 7 controls the switching unit 4 to set the above-described first parallel connection measurement state and second parallel connection measurement state. Thereby, the insulation testing device 1 and its method according to the third embodiment can reduce the number of times of testing compared to the general testing method described as the second comparative example. Therefore, the insulation testing device 1 and method of the third embodiment can improve the accuracy of insulation testing by eliminating floating potentials, and can shorten the time required for insulation testing.

(第4実施形態)
第4実施形態について説明する。第4実施形態は、第1実施形態等に対して絶縁検査装置1の構成の一部と、その検査方法の一部を変更したものであり、その他については第1実施形態等と同様であるため、第1実施形態等と異なる部分についてのみ説明する。
(Fourth embodiment)
A fourth embodiment will be described. In the fourth embodiment, a part of the configuration of the insulation testing device 1 and a part of the testing method thereof are changed from the first embodiment etc., and the other parts are the same as the first embodiment etc. Therefore, only the parts that are different from the first embodiment etc. will be explained.

図8に示すように、第4実施形態の絶縁検査装置1は、湿度検出部12を備えている。湿度検出部12は、U相、V相、W相の各線材およびステータコア2が設置される環境湿度または線材の皮膜の吸湿度を検出するものである。以下の説明では、環境湿度または線材の皮膜の吸湿度を、単に「湿度」ということがある。また、湿度検出部12により検出された湿度を「検出湿度」ということがある。 As shown in FIG. 8, the insulation testing device 1 of the fourth embodiment includes a humidity detection section 12. The humidity detection unit 12 detects the environmental humidity in which the U-phase, V-phase, and W-phase wire rods and the stator core 2 are installed, or the moisture absorption of the coating of the wire rods. In the following description, the environmental humidity or the moisture absorption of the film of the wire may be simply referred to as "humidity." Furthermore, the humidity detected by the humidity detection unit 12 is sometimes referred to as "detected humidity."

第4実施形態の絶縁検査装置1では、その検出湿度に基づき、電源部3から線材に対する電圧の印加開始から絶縁判定部6が線材の絶縁状態の良否を判定するまでの判定時間が設定される。その判定時間は、検出湿度が所定の値より低いときの判定時間よりも、検出湿度が所定の値より高いときの判定時間が長く設定される。なお、所定の値は、実験などにより設定されるものであり、例えば40~60%の間に設定される。 In the insulation testing device 1 of the fourth embodiment, the determination time from the start of applying voltage to the wire from the power supply section 3 until the insulation determination section 6 determines whether the insulation state of the wire is good or bad is set based on the detected humidity. . The determination time is set longer than the determination time when the detected humidity is higher than a predetermined value than the determination time when the detected humidity is lower than a predetermined value. Note that the predetermined value is set through experiments and the like, and is set, for example, between 40% and 60%.

ここで、検出湿度に応じて判定時間を変える意義について、図9のグラフを参照して説明する。図9は、複数の線材について、湿度の影響による放電回数の変化を示した実験結果である。 Here, the significance of changing the determination time depending on the detected humidity will be explained with reference to the graph of FIG. 9. FIG. 9 shows experimental results showing changes in the number of discharges due to the influence of humidity for a plurality of wire rods.

図9の縦軸は、放電回数を示している。放電回数とは、第1実施形態で説明した放電量と同一である。すなわち、放電回数とは、放電量計測部5により算出された電荷量が所定の大きさ以上であり、且つ、交流により電荷が移動する頻度が所定の頻度以上となるものを放電と見做したとき、その放電の所定時間ごとの回数をいう。
図9の横軸は、電源部3から線材に対する電圧の印加開始から経過した時間を示している。なお、この実験において、電源部3から線材に対して印加する電圧は、湿度に応じて変化させていないものとする。
The vertical axis in FIG. 9 indicates the number of discharges. The number of discharges is the same as the amount of discharge explained in the first embodiment. In other words, the number of discharges is defined as a discharge when the amount of charge calculated by the discharge amount measurement unit 5 is equal to or greater than a predetermined value, and the frequency at which the charge is moved by alternating current is equal to or greater than a predetermined frequency. , the number of times the discharge occurs every predetermined period of time.
The horizontal axis in FIG. 9 indicates the time elapsed from the start of application of voltage from the power supply unit 3 to the wire. In this experiment, it is assumed that the voltage applied to the wire from the power supply section 3 is not changed in accordance with the humidity.

図9では、湿度検出部12により検出される「検出湿度」が低湿度の場合の放電回数の推移を、クロスハッチングを付した棒グラフにて示している。また、「検出湿度」が中湿度の場合の放電回数の推移を、ハッチングを付した棒グラフにて示している。また、「検出湿度」が高湿度の場合の放電回数の推移を、白抜きの棒グラフにて示している。 In FIG. 9, the transition of the number of discharges when the "detected humidity" detected by the humidity detection unit 12 is low humidity is shown in a cross-hatched bar graph. Further, the transition of the number of discharges when the "detected humidity" is medium humidity is shown in a hatched bar graph. In addition, the transition of the number of discharges when the "detected humidity" is high humidity is shown as a white bar graph.

クロスハッチングを付した棒グラフにて示されるように、低湿度の場合、時刻t1では、放電回数が所定の規格値に近い値となっている。時刻t2以降は、放電回数が非常に小さい値となっている。なお、所定の規格値は、例えば、回転電機の生涯寿命などを考慮して設定される値である。 As shown by the cross-hatched bar graph, in the case of low humidity, the number of discharges is close to a predetermined standard value at time t1. After time t2, the number of discharges is a very small value. Note that the predetermined standard value is a value that is set in consideration of, for example, the lifetime of the rotating electrical machine.

ハッチングを付した棒グラフと白抜きの棒グラフにて示されるように、中湿度または高湿度の場合、電圧の印加開始から時刻t5まで、放電回数が所定の規格値を超えている。時刻t6以降、放電回数が所定の規格値を下回り、時刻t10では、放電回数が非常に小さい値となっている。 As shown by the hatched bar graph and the white bar graph, in the case of medium humidity or high humidity, the number of discharges exceeds a predetermined standard value from the start of voltage application to time t5. After time t6, the number of discharges falls below a predetermined standard value, and at time t10, the number of discharges has a very small value.

図9のクロスハッチングを付した棒グラフにて示されるように、湿度が低いときは、放電開始から放電回数が小さくなるまでの時間が短い。それに対し、図9のハッチングを付した棒グラフと白抜きの棒グラフにて示されるように、湿度が高いときは、放電開始から放電回数が小さくなるまでの時間が長くなる。そこで、第4実施形態では、湿度が所定の値より低いときの判定時間よりも、湿度が所定の値より高いときの判定時間を長く設定する構成としている。これにより、湿度が所定の値より高いときであっても、放電量計測部5で計測される放電回数が時間経過とともに収束する。したがって、この絶縁検査装置1および方法は、湿度の影響を受けることなく、過検知を防ぎ、絶縁検査の精度を向上することができる。一方、湿度が所定の値より低いときは、判定時間を短く設定することで、絶縁検査にかかる時間を短くすることができる。 As shown by the cross-hatched bar graph in FIG. 9, when the humidity is low, the time from the start of discharge until the number of discharges decreases is short. On the other hand, as shown by the hatched bar graph and the white bar graph in FIG. 9, when the humidity is high, the time from the start of discharge until the number of discharges decreases becomes longer. Therefore, in the fourth embodiment, the determination time when the humidity is higher than a predetermined value is set longer than the determination time when the humidity is lower than the predetermined value. Thereby, even when the humidity is higher than a predetermined value, the number of discharges measured by the discharge amount measuring section 5 converges over time. Therefore, this insulation testing device 1 and method can prevent over-detection and improve the accuracy of insulation testing without being affected by humidity. On the other hand, when the humidity is lower than a predetermined value, the time required for the insulation test can be shortened by setting the determination time short.

(他の実施形態)
本発明は上記した実施形態に限定されるものではなく、特許請求の範囲に記載した範囲内において適宜変更が可能である。また、上記各実施形態は、互いに無関係なものではなく、組み合わせが明らかに不可な場合を除き、適宜組み合わせが可能である。また、上記各実施形態において、実施形態を構成する要素は、特に必須であると明示した場合および原理的に明らかに必須であると考えられる場合等を除き、必ずしも必須のものではないことは言うまでもない。また、上記各実施形態において、実施形態の構成要素の個数、数値、量、範囲等の数値が言及されている場合、特に必須であると明示した場合および原理的に明らかに特定の数に限定される場合等を除き、その特定の数に限定されるものではない。また、上記各実施形態において、構成要素等の形状、位置関係等に言及するときは、特に明示した場合および原理的に特定の形状、位置関係等に限定される場合等を除き、その形状、位置関係等に限定されるものではない。
(Other embodiments)
The present invention is not limited to the embodiments described above, and can be modified as appropriate within the scope of the claims. Furthermore, the embodiments described above are not unrelated to each other, and can be combined as appropriate, except in cases where combination is clearly impossible. Furthermore, in each of the above embodiments, it goes without saying that the elements constituting the embodiments are not necessarily essential, except in cases where it is specifically stated that they are essential or where they are clearly considered essential in principle. stomach. In addition, in each of the above embodiments, when numerical values such as the number, numerical value, amount, range, etc. of the constituent elements of the embodiment are mentioned, when it is clearly stated that it is essential, or when it is clearly limited to a specific number in principle. It is not limited to that specific number, except in cases where In addition, in each of the above embodiments, when referring to the shape, positional relationship, etc. of constituent elements, etc., the shape, It is not limited to positional relationships, etc.

(1)上記各実施形態では、絶縁検査装置1は、回転電機が備える電機子としてのステータコア2に組み付けられる線材の皮膜の絶縁状態を検査するものとして説明したが、これに限らない。絶縁検査装置1は、回転電機が備える電機子としてのロータコアに組み付けられる線材の皮膜の絶縁状態を検査するものであってもよい。 (1) In each of the above embodiments, the insulation testing device 1 was described as one that tests the insulation state of the coating of the wire rod assembled to the stator core 2 as an armature included in a rotating electric machine, but the invention is not limited to this. The insulation testing device 1 may be used to test the insulation state of a coating on a wire rod assembled to a rotor core serving as an armature included in a rotating electric machine.

(2)上記第1実施形態では、U相を構成する複数の線材と、V相を構成する複数の線材と、W相を構成する複数の線材は、いずれも直列結線された状態で、且つ、中性点で結線される前の状態で絶縁検査するものとして説明したが、これに限らない。U相を構成する複数の線材と、V相を構成する複数の線材と、W相を構成する複数の線材は、いずれも直列結線される前の状態で、且つ、中性点で結線される前の状態で絶縁検査してもよい。 (2) In the first embodiment, the plurality of wire rods forming the U phase, the plurality of wire rods forming the V phase, and the plurality of wire rods forming the W phase are all connected in series, and Although the explanation has been made assuming that the insulation is inspected before the wires are connected at the neutral point, the present invention is not limited to this. The plurality of wire rods constituting the U phase, the plurality of wire rods constituting the V phase, and the plurality of wire rods constituting the W phase are all connected at a neutral point before being connected in series. The insulation may be tested in the previous state.

(3)上記第3実施形態では、U相の線材、V相の線材、および、W相の線材がそれぞれ2並列結線されるものについて説明したが、これに限らず、3並列結線、4並列結線など、多数の並列結線に適用することができる。 (3) In the third embodiment, the U-phase wire, the V-phase wire, and the W-phase wire are each connected in two parallels, but the invention is not limited to this. It can be applied to many parallel connections such as wire connections.

(4)上記実施形態では、線材がY結線されるものについて説明したが、これに限らず、Δ結線、ΔY結線、YΔ結線、ΔΔ結線、YY結線などに適用することができる。 (4) In the above embodiment, the wires are Y-connected, but the present invention is not limited to this, and can be applied to Δ-connection, ΔY-connection, YΔ-connection, ΔΔ-connection, YY-connection, and the like.

(5)上記第4実施形態では、検出湿度が所定の値より低いときの判定時間よりも、検出湿度が所定の値より高いときの判定時間を長く設定したが、これに限らない。検出湿度が所定の値より低いときの印加電圧よりも、検出湿度が所定の値より高いときの印加電圧を低く設定してもよい。なお、そのときの印加電圧は、所定の湿度(例えば40~60%)を超えたときに、低下率を大きくしてもよい。 (5) In the fourth embodiment, the determination time when the detected humidity is higher than the predetermined value is set longer than the determination time when the detected humidity is lower than the predetermined value, but the present invention is not limited to this. The applied voltage when the detected humidity is higher than a predetermined value may be set lower than the applied voltage when the detected humidity is lower than a predetermined value. Note that the voltage applied at that time may be reduced at a higher rate when the humidity exceeds a predetermined humidity (for example, 40 to 60%).

1 絶縁検査装置
2 ステータコア
3 電源部
4 切替部
5 放電量計測部
6 絶縁判定部
7 制御部
21 スロット
31 第1端子
32 第2端子
1 Insulation inspection device 2 Stator core 3 Power supply unit 4 Switching unit 5 Discharge amount measurement unit 6 Insulation determination unit 7 Control unit 21 Slot 31 First terminal 32 Second terminal

Claims (8)

回転電機の電機子のコア(2)の有するスロット(21)に挿入された複数の線材の皮膜の絶縁状態をU相の線材とV相の線材とW相の線材とが結線される前の状態で検査する絶縁検査装置において、
第1端子(31)と第2端子(32)とを有する電源部(3)と、
U相、V相、W相の各線材および前記コアそれぞれと前記第1端子との間における複数の電気的な接続状態と遮断状態を切り替え可能、且つ、U相、V相、W相の各線材および前記コアそれぞれと前記第2端子との間における複数の電気的な接続状態と遮断状態を切り替え可能な切替部(4)と、
U相、V相、W相の各線材および前記コアのうち前記第1端子に電気的に接続された部材と前記第2端子に電気的に接続された部材との間に生じる放電量を計測する放電量計測部(5)と、
前記放電量計測部により計測された放電量に基づき、線材の皮膜が所定の品質基準を満たす規格内の製品であるか否かを判定する絶縁判定部(6)と、
U相、V相、W相の各線材および前記コアのいずれも前記第1端子および前記第2端子の両方に対し電気的な遮断状態になることなく、U相、V相、W相の各線材および前記コアの全てが前記第1端子または前記第2端子と電気的に接続されるように前記切替部を制御する制御部(7)と、を備える絶縁検査装置。
The insulation state of the coating of a plurality of wire rods inserted into the slot (21) of the core (2) of the armature of a rotating electrical machine is determined before the U-phase wire, V-phase wire, and W-phase wire are connected. In insulation inspection equipment that inspects conditions,
a power supply unit (3) having a first terminal (31) and a second terminal (32);
A plurality of electrical connection states and disconnection states can be switched between each of the U-phase, V-phase, and W-phase wires and each of the cores and the first terminal, and each of the U-phase, V-phase, and W-phase a switching unit (4) capable of switching between a plurality of electrical connection states and disconnection states between each of the wire and the core and the second terminal;
Measure the amount of discharge that occurs between the U-phase, V-phase, and W-phase wires and the core that is electrically connected to the first terminal and the second terminal. a discharge amount measuring section (5) to
an insulation determination unit (6) that determines whether or not the coating of the wire is a product that meets predetermined quality standards based on the discharge amount measured by the discharge amount measurement unit;
Each of the U-phase, V-phase, and W-phase wires and the core are electrically disconnected from both the first terminal and the second terminal. An insulation testing device comprising: a control unit (7) that controls the switching unit so that all of the wire and the core are electrically connected to the first terminal or the second terminal.
前記制御部は、U相、V相、W相のうちいずれか2つの相の線材と前記第1端子とが電気的に接続され、且つ、他の1つの相の線材および前記コアと前記第2端子とが電気的に接続された状態となるように前記切替部を制御する、請求項1に記載の絶縁検査装置。 The control unit is configured such that wires of any two phases among U-phase, V-phase, and W-phase are electrically connected to the first terminal, and the wire of another phase and the core are connected to the first terminal. The insulation testing device according to claim 1, wherein the switching unit is controlled so that the two terminals are electrically connected. U相の線材、V相の線材、W相の線材はそれぞれ並列結線されるものであり、
前記制御部は、
U相、V相、W相のうちいずれか2つの相でそれぞれ並列結線された線材と前記第1端子とが電気的に接続され、且つ、他の1つの相で並列結線された線材および前記コアと前記第2端子とが電気的に接続された状態となるように前記切替部を制御して第1の並列結線用測定状態とし、
U相、V相、W相の全ての相において並列結線された一方側の線材と前記第1端子とが電気的に接続され、且つ、U相、V相、W相の全ての相において並列結線された他方側の線材および前記コアと前記第2端子とが電気的に接続された状態となるように前記切替部を制御して第2の並列結線用測定状態とする、請求項1に記載の絶縁検査装置。
The U-phase wire, V-phase wire, and W-phase wire are each connected in parallel,
The control unit includes:
The wire rods connected in parallel in any two phases of the U phase, V phase, and W phase are electrically connected to the first terminal, and the wire rods connected in parallel in another phase and the controlling the switching unit so that the core and the second terminal are electrically connected to a first parallel connection measurement state;
The first terminal is electrically connected to the wire on one side that is connected in parallel in all the U, V, and W phases, and the wire is connected in parallel in all the U, V, and W phases. According to claim 1, the switching unit is controlled so that the wire rod on the other side of the wire and the core and the second terminal are electrically connected to each other, and a second parallel connection measurement state is set. Insulation testing equipment described.
U相の線材、V相の線材、W相の線材はそれぞれ直列結線されるものであり、
前記制御部は、
U相、V相、W相のうちいずれか1つの相の線材と前記第1端子とが電気的に接続され、且つ、他の2つの相の線材および前記コアと前記第2端子とが電気的に接続された状態となるように前記切替部を制御して第1の直列結線用測定状態とし、
U相、V相、W相の全ての線材と前記第1端子とが電気的に接続され、且つ、前記コアと前記第2端子とが電気的に接続された状態となるように前記切替部を制御して第2の直列結線用測定状態とする、請求項1に記載の絶縁検査装置。
The U-phase wire, V-phase wire, and W-phase wire are each connected in series,
The control unit includes:
The wire of any one of the U-phase, V-phase, and W-phase is electrically connected to the first terminal, and the wire of the other two phases and the core are electrically connected to the second terminal. controlling the switching unit so that the switching unit is in a first series connection measurement state;
The switching unit is configured such that all the wires of the U phase, V phase, and W phase are electrically connected to the first terminal, and the core and the second terminal are electrically connected. The insulation testing device according to claim 1, wherein the insulation testing device controls the voltage to set the second series connection measurement state.
前記絶縁検査装置は、U相、V相、W相の各線材および前記コアが設置される環境湿度を検出する湿度検出部(12)をさらに備え、
前記電源部から線材に対する電圧の印加開始から前記絶縁判定部が線材の絶縁状態の良否を判定するまでの判定時間に関し、環境湿度が所定の値に一致するときの判定時間を線材の絶縁状態の良否を判定可能な所定時間に設定し、環境湿度が所定の値より低いときの判定時間を前記所定時間より短く設定し、環境湿度が所定の値より高いときの判定時間を前記所定時間より長く設定するように構成されている、請求項1ないし4のいずれか1つに記載の絶縁検査装置。
The insulation testing device further includes a humidity detection unit (12) that detects the environmental humidity in which the U-phase, V-phase, and W-phase wires and the core are installed,
Regarding the determination time from the start of voltage application from the power supply section to the wire until the insulation determination section determines whether the insulation state of the wire is good or bad, the determination time when the environmental humidity matches a predetermined value is the insulation state of the wire. The determination time when the environmental humidity is lower than a predetermined value is set to be shorter than the predetermined time, and the determination time when the environmental humidity is higher than the predetermined value is set to a predetermined time for determining whether the The insulation testing device according to any one of claims 1 to 4, wherein the insulation testing device is configured to be set for a longer period of time.
回転電機の電機子のコア(2)の有するスロット(21)に挿入された複数の線材の皮膜の絶縁状態をU相の線材とV相の線材とW相の線材とが結線される前の状態で検査する絶縁検査装置において、
第1端子(31)と第2端子(32)とを有する電源部(3)と、
U相、V相、W相の各線材および前記コアそれぞれと前記第1端子との間における複数の電気的な接続状態と遮断状態を切り替え可能、且つ、U相、V相、W相の各線材および前記コアそれぞれと前記第2端子との間における複数の電気的な接続状態と遮断状態を切り替え可能な切替部(4)と、
U相、V相、W相の各線材および前記コアのいずれも前記第1端子および前記第2端子の両方に対し電気的な遮断状態になることなく、U相、V相、W相の各線材および前記コアの全てが前記第1端子または前記第2端子と電気的に接続されるように前記切替部を制御する制御部(7)と、
U相、V相、W相の各線材および前記コアのうち前記第1端子に電気的に接続された部材と前記第2端子に電気的に接続された部材との間に生じる放電量を計測する放電量計測部(5)と、
前記放電量計測部により計測された放電量に基づき、線材の皮膜が所定の品質基準を満たす規格内の製品であるか否かを判定する絶縁判定部(6)と、
U相、V相、W相の各線材および前記コアが設置される環境湿度を検出する湿度検出部(12)と、を備え、
前記電源部から線材に対する電圧の印加開始から前記絶縁判定部が線材の絶縁状態の良否を判定するまでの判定時間に関し、環境湿度が所定の値に一致するときの判定時間を線材の絶縁状態の良否を判定可能な所定時間に設定し、環境湿度が所定の値より低いときの判定時間を前記所定時間より短く設定し、環境湿度が所定の値より高いときの判定時間を前記所定時間より長く設定するように構成されている、絶縁検査装置。
The insulation state of the coating of a plurality of wire rods inserted into the slot (21) of the core (2) of the armature of a rotating electrical machine is determined before the U-phase wire, V-phase wire, and W-phase wire are connected. In insulation inspection equipment that inspects conditions,
a power supply unit (3) having a first terminal (31) and a second terminal (32);
A plurality of electrical connection states and disconnection states can be switched between each of the U-phase, V-phase, and W-phase wires and each of the cores and the first terminal, and each of the U-phase, V-phase, and W-phase a switching unit (4) capable of switching between a plurality of electrical connection states and disconnection states between each of the wire and the core and the second terminal;
Each of the U-phase, V-phase, and W-phase wires and the core are electrically disconnected from both the first terminal and the second terminal. a control unit (7) that controls the switching unit so that all of the wire and the core are electrically connected to the first terminal or the second terminal;
Measure the amount of discharge that occurs between the U-phase, V-phase, and W-phase wires and the core that is electrically connected to the first terminal and the second terminal. a discharge amount measuring section (5) to
an insulation determination unit (6) that determines whether or not the coating of the wire is a product that meets predetermined quality standards based on the discharge amount measured by the discharge amount measurement unit;
A humidity detection unit (12) that detects the environmental humidity in which the U-phase, V-phase, and W-phase wire rods and the core are installed,
Regarding the determination time from the start of applying voltage to the wire from the power supply section until the insulation determination section determines whether the insulation state of the wire is good or bad, the determination time when the environmental humidity matches a predetermined value is the insulation state of the wire. The determination time when the environmental humidity is lower than a predetermined value is set to be shorter than the predetermined time, and the determination time when the environmental humidity is higher than the predetermined value is set to a predetermined time during which the quality of the product can be determined. An insulation testing device configured to be set for a longer period of time.
回転電機の電機子のコア(2)の有するスロット(21)に挿入された複数の線材の皮膜の絶縁状態をU相の線材とV相の線材とW相の線材とが結線される前の状態で検査する絶縁検査方法において、
電源部(3)が有する第1端子(31)および第2端子(32)の両方に対しU相、V相、W相の各線材および前記コアのいずれも電気的な遮断状態になることなく、U相、V相、W相の各線材および前記コアの全てが前記第1端子または前記第2端子と電気的に接続されている状態にすることと、
前記電源部からU相、V相、W相の各線材および前記コアに電圧を印加し、U相、V相、W相の各線材および前記コアのうち前記第1端子に電気的に接続された部材と前記第2端子に電気的に接続された部材との間に生じる放電量を計測することを含む絶縁検査方法。
The insulation state of the coating of a plurality of wire rods inserted into the slot (21) of the core (2) of the armature of a rotating electrical machine is determined before the U-phase wire, V-phase wire, and W-phase wire are connected. In the insulation testing method, which tests the
With respect to both the first terminal (31) and the second terminal (32) of the power supply section (3), each of the U-phase, V-phase, and W-phase wires and the core are not electrically interrupted. , U-phase, V-phase, W-phase wires and the core are all electrically connected to the first terminal or the second terminal;
A voltage is applied from the power supply unit to each of the U-phase, V-phase, and W-phase wires and the core, and the U-phase, V-phase, and W-phase wires and the core are electrically connected to the first terminal. An insulation testing method comprising measuring the amount of discharge generated between a member electrically connected to the second terminal and a member electrically connected to the second terminal.
回転電機の電機子のコア(2)の有するスロット(21)に挿入された複数の線材の皮膜の絶縁状態をU相の線材とV相の線材とW相の線材とが結線される前の状態で検査する絶縁検査方法において、
電源部(3)が有する第1端子(31)または第2端子(32)に対しU相、V相、W相の各線材および前記コアが電気的に接続されている状態にすることと、
U相、V相、W相の各線材および前記コアが設置される環境湿度を検出することと、
前記電源部から線材に対する電圧の印加開始から絶縁判定部が線材の絶縁状態の良否を判定するまでの判定時間に関し、環境湿度が所定の値に一致するときの判定時間を線材の絶縁状態の良否を判定可能な所定時間に設定し、環境湿度が所定の値より低いときの判定時間を前記所定時間より短く設定し、環境湿度が所定の値より高いときの判定時間を前記所定時間より長く設定することと、
前記電源部からU相、V相、W相の各線材および前記コアに電圧を印加し、U相、V相、W相の各線材および前記コアのうち前記第1端子に電気的に接続された部材と前記第2端子に電気的に接続された部材との間に生じる放電量を計測することを含む絶縁検査方法。
The insulation state of the coating of a plurality of wire rods inserted into the slot (21) of the core (2) of the armature of a rotating electrical machine is determined before the U-phase wire, V-phase wire, and W-phase wire are connected. In the insulation testing method, which tests the
The U-phase, V-phase, and W-phase wires and the core are electrically connected to a first terminal (31) or a second terminal (32) of the power supply unit (3);
Detecting the environmental humidity in which the U-phase, V-phase, and W-phase wire rods and the core are installed;
Regarding the determination time from the start of voltage application to the wire from the power supply unit until the insulation determination unit determines whether the insulation state of the wire is good or bad, the determination time when the environmental humidity matches a predetermined value is the determination time of the insulation state of the wire. A predetermined time for determining pass/fail is set, a determination time when the environmental humidity is lower than a predetermined value is set shorter than the predetermined time, and a determination time is set for the predetermined time when the environmental humidity is higher than the predetermined value. By setting it longer and
A voltage is applied from the power supply unit to each of the U-phase, V-phase, and W-phase wires and the core, and the U-phase, V-phase, and W-phase wires and the core are electrically connected to the first terminal. An insulation testing method comprising measuring the amount of discharge generated between a member electrically connected to the second terminal and a member electrically connected to the second terminal.
JP2020056075A 2019-04-03 2020-03-26 Insulation testing equipment and insulation testing method Active JP7435136B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
US16/839,212 US11821933B2 (en) 2019-04-03 2020-04-03 Insulation testing apparatus and method of the same
CN202010258412.0A CN111796168B (en) 2019-04-03 2020-04-03 Insulation testing device and method thereof

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2019071458 2019-04-03
JP2019071458 2019-04-03

Publications (2)

Publication Number Publication Date
JP2020169986A JP2020169986A (en) 2020-10-15
JP7435136B2 true JP7435136B2 (en) 2024-02-21

Family

ID=72746664

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020056075A Active JP7435136B2 (en) 2019-04-03 2020-03-26 Insulation testing equipment and insulation testing method

Country Status (2)

Country Link
JP (1) JP7435136B2 (en)
CN (1) CN111796168B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115639446B (en) * 2022-12-23 2023-06-02 浙江杭可仪器有限公司 Selective capacitance testing device
JP2025186837A (en) * 2024-06-12 2025-12-24 日置電機株式会社 Test system, partial discharge test method, partial discharge test program, and switching device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005257549A (en) 2004-03-12 2005-09-22 Toyota Motor Corp Insulation inspection device and insulation inspection method
JP2012172985A (en) 2011-02-17 2012-09-10 Toyota Motor Corp Insulation inspection method
JP2013120096A (en) 2011-12-06 2013-06-17 Nippon Soken Inc Insulation inspection apparatus
JP2016161379A (en) 2015-03-02 2016-09-05 トヨタ自動車株式会社 Inspection method for inverter drive motor
JP7255322B2 (en) 2019-04-03 2023-04-11 株式会社デンソー Insulation inspection device and insulation inspection method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4418320B2 (en) * 2004-07-28 2010-02-17 株式会社日立産機システム Measuring method of partial discharge between motor winding turns
JP2010281673A (en) * 2009-06-04 2010-12-16 Toshiba Corp Partial discharge voltage measurement system and partial discharge voltage measurement method
JP6102672B2 (en) * 2013-10-11 2017-03-29 アイシン・エィ・ダブリュ株式会社 Insulation state determination device and insulation state determination method
JP6507767B2 (en) * 2015-03-23 2019-05-08 日立金属株式会社 Method of measuring partial discharge, partial discharge measuring device, and method of manufacturing insulated wire
KR101991910B1 (en) * 2016-11-16 2019-06-21 주식회사 엘지화학 Apparatus and method for measuring isolation resistance of battery

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005257549A (en) 2004-03-12 2005-09-22 Toyota Motor Corp Insulation inspection device and insulation inspection method
JP2012172985A (en) 2011-02-17 2012-09-10 Toyota Motor Corp Insulation inspection method
JP2013120096A (en) 2011-12-06 2013-06-17 Nippon Soken Inc Insulation inspection apparatus
JP2016161379A (en) 2015-03-02 2016-09-05 トヨタ自動車株式会社 Inspection method for inverter drive motor
JP7255322B2 (en) 2019-04-03 2023-04-11 株式会社デンソー Insulation inspection device and insulation inspection method

Also Published As

Publication number Publication date
CN111796168B (en) 2024-09-24
JP2020169986A (en) 2020-10-15
CN111796168A (en) 2020-10-20

Similar Documents

Publication Publication Date Title
US20060022679A1 (en) Apparatus for partial discharge detection of turn to turn insulation in motor
CN101910853B (en) Insulation covered conductor inspection method and device
CN110970872B (en) Apparatus for injection-based ground fault protection handling
JP7435136B2 (en) Insulation testing equipment and insulation testing method
CN111796169B (en) Insulation inspection device and method
JP5738511B2 (en) Insulation test method in manufacturing process of rotating electrical machine winding and manufacturing method of rotating electrical machine winding
JPWO2012147162A1 (en) Inverter-driven rotating electrical machine, insulation inspection method, and insulation inspection apparatus
US6496015B2 (en) Method of performing a dielectric voltage-withstand test on a wire harness
Verginadis et al. Diagnosis of stator faults in synchronous generators: Short review and practical case
JP2005257549A (en) Insulation inspection device and insulation inspection method
US12320836B2 (en) Insulation inspection method and insulation inspection apparatus
KR101977861B1 (en) Method for determining fault of motor
US10107852B2 (en) Interstrand short circuit testing of stator winding bars of electric machines
JP2008267929A (en) Motor short circuit inspection method
JPH09257862A (en) Winding insulation diagnostic device
JP6314875B2 (en) Inverter drive motor inspection method
JP5525768B2 (en) Rotating electrical machine test method and manufacturing method
Drif et al. The use of the stator instantaneous complex apparent impedance signature analysis for discriminating stator winding faults and supply voltage unbalance in three-phase induction motors
US11821933B2 (en) Insulation testing apparatus and method of the same
JP2010112755A (en) Method and device for diagnosing insulation of rotating machine stator coil
JP2975039B2 (en) Detecting device for abnormal winding of winding coil for motor
US6184690B1 (en) Pole to pole surge test for wound products
JP2009174872A (en) Insulation inspection method and apparatus for rotating electrical machine
JP2005214715A (en) Inspection apparatus and inspection method for rotating electrical machine
JP6110783B2 (en) Method for repeated impulse partial discharge test of motor winding and apparatus therefor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220810

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230322

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230425

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230613

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20230905

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231115

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20231127

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240109

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240122

R151 Written notification of patent or utility model registration

Ref document number: 7435136

Country of ref document: JP