JP7486778B2 - Piping processing tools - Google Patents
Piping processing tools Download PDFInfo
- Publication number
- JP7486778B2 JP7486778B2 JP2020022294A JP2020022294A JP7486778B2 JP 7486778 B2 JP7486778 B2 JP 7486778B2 JP 2020022294 A JP2020022294 A JP 2020022294A JP 2020022294 A JP2020022294 A JP 2020022294A JP 7486778 B2 JP7486778 B2 JP 7486778B2
- Authority
- JP
- Japan
- Prior art keywords
- base
- existing
- pipe
- blade
- piping
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000012545 processing Methods 0.000 title claims description 172
- 238000000034 method Methods 0.000 claims description 134
- 230000008569 process Effects 0.000 claims description 110
- 238000005520 cutting process Methods 0.000 claims description 53
- 238000003780 insertion Methods 0.000 claims description 16
- 230000037431 insertion Effects 0.000 claims description 16
- 230000002093 peripheral effect Effects 0.000 claims description 5
- 239000000463 material Substances 0.000 description 66
- 230000001681 protective effect Effects 0.000 description 52
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 26
- 239000011347 resin Substances 0.000 description 6
- 229920005989 resin Polymers 0.000 description 6
- 238000010276 construction Methods 0.000 description 5
- 238000002788 crimping Methods 0.000 description 5
- 239000004698 Polyethylene Substances 0.000 description 4
- 238000003754 machining Methods 0.000 description 4
- 230000008859 change Effects 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- -1 polyethylene Polymers 0.000 description 3
- 229920000573 polyethylene Polymers 0.000 description 3
- 229910000838 Al alloy Inorganic materials 0.000 description 2
- 238000013459 approach Methods 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 2
- 229920003020 cross-linked polyethylene Polymers 0.000 description 2
- 238000009408 flooring Methods 0.000 description 2
- 229910052751 metal Inorganic materials 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 230000032683 aging Effects 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 239000004703 cross-linked polyethylene Substances 0.000 description 1
- 230000006866 deterioration Effects 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000011810 insulating material Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 229920001083 polybutene Polymers 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000007779 soft material Substances 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Landscapes
- Details Of Cutting Devices (AREA)
- Nonmetal Cutting Devices (AREA)
Description
本発明は、既設配管を新配管に更新する際に用いられる配管加工用具に関する。 The present invention relates to a piping processing tool used when replacing existing piping with new piping.
特許文献1に、既設配管を新配管に更新する際の配管更新方法、および配管更新方法に用いられる既設配管の加工具としての切断工具が開示されている。なお、特許文献1では、既設配管として給水用配管を用いている。 Patent Document 1 discloses a pipe renewal method for replacing existing pipes with new pipes, and a cutting tool used in the pipe renewal method to process existing pipes. In Patent Document 1, water supply pipes are used as the existing pipes.
特許文献1の配管更新方法では、給水本管側である既設配管の分岐側に、ワイヤを巻き取ったウインチを準備するとともに、家屋側であるメーター側に切断工具を準備する。続いて、既設配管の内部の分岐側からメーター側にワイヤを通し、メーター側に露出したワイヤに切断工具を取付ける。そして、ウインチを操作し、ワイヤを巻き取ることにより、切断工具によって既設配管を分割し、その後に既設配管を抜き取って新配管に更新される。 In the pipe renewal method of Patent Document 1, a winch with a wound wire is prepared at the branch side of the existing pipe, which is the main water supply pipe, and a cutting tool is prepared at the meter side, which is the house side. Next, the wire is passed from the branch side inside the existing pipe to the meter side, and the cutting tool is attached to the wire exposed on the meter side. Then, the winch is operated to wind up the wire, and the existing pipe is divided with the cutting tool, after which the existing pipe is removed and renewed with new pipe.
ところで、既設配管の種類によっては、上記した切断工具では既設配管を一度に分割できないこともあり得、また、異なる加工をする必要もあり得る。そうなると、既設配管に対して複数の異なる加工をする必要がある。 However, depending on the type of existing piping, it may not be possible to divide the existing piping in one go using the cutting tools described above, and different processing may be required. In such cases, multiple different processing steps may need to be performed on the existing piping.
しかしながら、特許文献1の配管更新方法に用いられる加工具では、分岐側からメーター側(一方側から他方側)への引張り施工であるため、既設配管に対して複数の加工を行う毎に既設配管にワイヤを通したうえで、ウインチと反対側に、加工毎に異なる加工具を配置しなければならない。このような場合では、配管更新方法の施工に手間がかかる。 However, the tool used in the pipe renewal method of Patent Document 1 involves pulling from the branch side to the meter side (from one side to the other), so each time multiple processes are performed on the existing pipe, a wire must be passed through the existing pipe, and a different tool must be placed on the opposite side of the winch for each process. In such cases, the pipe renewal method is time-consuming to perform.
そこで本発明は、既設配管を新配管に更新するのにかかる手間を低減した配管加工用具の提供を目的とする。 Therefore, the present invention aims to provide a piping processing tool that reduces the effort required to replace existing piping with new piping.
本発明にかかる配管加工用具は、両側端部に入口と出口とが形成された既設配管に進入可能な本体部と、前記本体部を既設配管内に案内する索状体に前記本体部を接続する接続部と、を備え、前記本体部は既設配管の内径よりも外径が小さい基部と、前記基部から径外方向に突出し、既設配管に作用することで既設配管を加工する加工手段と、を備え、前記接続部は、前記基部における径方向と直交する方向の両端から索状体が延びるように前記基部を索状体に接続するよう構成され、前記加工手段は、前記基部の径方向と直交する方向の一端側から既設配管に進入して既設配管を加工する場合と前記基部の径方向と直交する方向の他端側から既設配管に進入して既設配管を加工する場合とで異なる加工ができるよう構成されている。 The pipe processing tool according to the present invention comprises a main body portion capable of entering an existing pipe having an inlet and an outlet formed at both ends, and a connection portion that connects the main body portion to a rope-like body that guides the main body portion into the existing pipe, the main body portion comprises a base portion having an outer diameter smaller than the inner diameter of the existing pipe, and a processing means that protrudes radially outward from the base portion and acts on the existing pipe to process the existing pipe, the connection portion is configured to connect the base portion to the rope-like body so that the rope-like body extends from both ends of the base portion in a direction perpendicular to the radial direction, and the processing means is configured to perform different processing when entering the existing pipe from one end side of the base in a direction perpendicular to the radial direction to process the existing pipe and entering the existing pipe from the other end side of the base in a direction perpendicular to the radial direction to process the existing pipe.
上記構成によれば、基部の両端から索状体が延び、かつ、基部の一端側から既設配管に進入する場合と基部の他端側から既設配管に進入する場合とで異なる加工ができるから、両端の索状体で牽引することによる既設配管内での往復運動を利用して、既設配管の入口から出口へ基部の一端側が先頭で進入する往動の場合と、既設配管の出口から入口に基部の他端側が先頭で進入する復動の場合とで異なる加工をすることができ、既設配管に対して効率のいい加工が可能である。 With the above configuration, the rope-like bodies extend from both ends of the base, and different processing can be performed when entering the existing piping from one end of the base and when entering the existing piping from the other end of the base. Therefore, by utilizing the reciprocating motion within the existing piping caused by pulling with the rope-like bodies at both ends, different processing can be performed in the case of a forward movement in which one end of the base enters the existing piping from the inlet to the outlet of the existing piping, and in the case of a return movement in which the other end of the base enters the existing piping from the outlet to the inlet of the existing piping, making it possible to perform efficient processing of the existing piping.
また、前記基部は、径方向と直交する方向の両端部分にそれぞれの端部に向かうにつれて先細りとなる小径部を備えるよう構成されてもよい。 The base may also be configured to have a small diameter portion at each end in a direction perpendicular to the radial direction that tapers toward each end.
かかる構成によれば、基部の両端が先細り形状とされるので、基部の一端側が先頭で既設配管に進入する往動の場合も基部の他端側が先頭で既設配管に進入する復動の場合も本体部を既設配管に挿入しやすくなる。 With this configuration, both ends of the base are tapered, making it easier to insert the main body into the existing piping, both in the case of forward movement where one end of the base enters the existing piping at the front, and in the case of return movement where the other end of the base enters the existing piping at the front.
また、前記接続部は、前記基部における径方向と直交する方向を軸として前記基部が索状体に対して回転可能であるように前記基部を索状体に接続するよう構成されていてもよい。 The connection portion may be configured to connect the base to the cord-like body so that the base can rotate relative to the cord-like body about an axis perpendicular to the radial direction of the base.
上記構成によれば、基部は、既設配管内で基部における径方向と直交する方向を軸として回転可能となるため、既設配管加工作業中に既設配管から受ける抵抗によって加工手段が既設配管の管軸中心に回転する方向に力を受けたとしても、力に従って基部が回転し、力を逃がすので、加工手段にかかる力が少なくなる。また、索状体がねじれており、索状体がねじれを解くように回転した場合でも、索状体のみが回転し、基部に索状体の回転力が伝わらないため、加工手段に力がかかることを防ぐことができる。そのため、既設配管加工作業中に加工手段が破損することを防ぐことができる。 According to the above configuration, the base can rotate within the existing piping around an axis perpendicular to the radial direction of the base. Therefore, even if the processing means receives a force in a direction that rotates around the axis of the existing piping due to resistance from the existing piping during processing of the existing piping, the base rotates according to the force and releases the force, so that the force applied to the processing means is reduced. Also, even if the rope-like body is twisted and rotates to untwist it, only the rope-like body rotates and the rotational force of the rope-like body is not transmitted to the base, so that it is possible to prevent force from being applied to the processing means. Therefore, it is possible to prevent damage to the processing means during processing of the existing piping.
また、前記加工手段は、前記基部から径外方向に突出し、かつ、前記基部における径方向と直交する方向まわりである周方向の異なる位置に配置される複数の加工部を含んでもよい。 The processing means may also include a plurality of processing parts that protrude radially outward from the base and are arranged at different positions in a circumferential direction about the base, the direction being perpendicular to the radial direction.
上記構成によれば、複数の加工部が基部から径外方向に突出し、かつ、基部の周方向の異なる位置に配置されるため、本体部を既設配管の入口側から出口側へ、又は出口側から入口側へ往復移動させることで、既設配管の周方向の複数の位置を同時に加工することができ、既設配管加工作業の効率が高まる。 According to the above configuration, multiple processing parts protrude radially outward from the base and are arranged at different circumferential positions of the base. Therefore, by moving the main body back and forth from the inlet side to the outlet side of the existing piping, or from the outlet side to the inlet side, multiple circumferential positions of the existing piping can be processed simultaneously, improving the efficiency of the existing piping processing work.
本発明の配管加工用具によれば、既設配管を新配管に更新するための手間を低減できる。 The piping processing tool of the present invention can reduce the effort required to replace existing piping with new piping.
以下、本発明の一実施形態に係る配管加工用具を用いた配管加工装置を説明する。第一の実施形態の配管加工用具を用いた配管加工装置は、既設配管を切断して撤去したうえで新たなフレキシブルな新配管を設置する配管更新工法に用いるものである。既設配管の一例は、給水配管、給湯配管である。はじめに、一般的な建築物(家屋)に用いられる給湯配管および給水配管の概略について説明する。 A pipe processing device using a pipe processing tool according to one embodiment of the present invention will be described below. The pipe processing device using the pipe processing tool of the first embodiment is used in a pipe renewal method in which an existing pipe is cut and removed, and then a new flexible pipe is installed. An example of an existing pipe is a water supply pipe or a hot water supply pipe. First, an overview of hot water supply pipes and water supply pipes used in a typical building (house) will be described.
図1に示すように、一般的に、家屋における給湯配管Yおよび給水配管は、床材Fによって、管軸方向(管の軸方向に沿った方向)の少なくとも途中部分が覆われている。また、管軸方向の、給湯および給水方向を基準とした入口5および出口6が、床材Fから露出されている。 As shown in FIG. 1, hot water pipes Y and cold water pipes in a house are generally covered at least partway along the pipe axis (the direction along the pipe axis) with flooring F. In addition, the inlet 5 and outlet 6 based on the hot water and cold water supply directions in the pipe axis direction are exposed from the flooring F.
給湯配管Yおよび給水配管については同様の構成であるので、給湯配管Yを給水配管に兼用して説明すると、給湯配管Yは、保護材G(断熱材)に、例えばポリエチレン管(PE管)、架橋ポリエチレン管(PE-X管)、ポリブテン管(PB管)、また、金属強化樹脂管等、アルミニウム合金等の金属層を挟んだ多層管とすることもできる。また、給湯配管Yは、床材Fの下側に配置されたスラブB等に、バンドI等によって管軸方向に固定されている。 The hot water supply pipe Y and the water supply pipe have the same configuration, so if we explain how the hot water supply pipe Y also serves as a water supply pipe, the hot water supply pipe Y can be a multi-layer pipe in which a metal layer such as an aluminum alloy or the like is sandwiched between protective material G (insulating material), for example a polyethylene pipe (PE pipe), a cross-linked polyethylene pipe (PE-X pipe), a polybutene pipe (PB pipe), or a metal-reinforced resin pipe. The hot water supply pipe Y is fixed in the pipe axial direction by a band I or the like to a slab B or the like arranged under the floor material F.
第一の実施形態の配管加工用具に係る配管更新工法、および配管加工用具を備えた配管加工装置を具体的に説明する。配管更新工法は、
(1)溝付け工程…既設配管Poの内周面に管軸方向に沿う溝Sを形成する工程、
(2)既設配管分割工程…既設配管Poを径方向および管軸方向に切断することにより、複数の切断片Psに分割する工程、
(3)引抜工程…切断片Psを保護材Gから引き抜くようにする工程、
(4)新配管挿入工程…新配管Pnを保護材Gの内周面に沿わせて保護材Gの内部に通す工程、
を有する。また、既設配管Poの管軸方向は、直線に延長される場合、あるいは、既設配管Poに湾曲部分が存在した場合でも、この配管更新工法が行われる。
A pipe renewal method according to the first embodiment of the present invention and a pipe processing device including the pipe processing tool will be specifically described.
(1) Grooving process: a process of forming a groove S along the pipe axis direction on the inner peripheral surface of the existing pipe Po;
(2) Existing pipe dividing process: A process of dividing the existing pipe Po into a plurality of cut pieces Ps by cutting the existing pipe Po in the radial direction and the pipe axial direction;
(3) Pulling-out process: A process of pulling out the cut piece Ps from the protective material G;
(4) New pipe insertion process: a process of passing the new pipe Pn through the inside of the protective material G along the inner circumferential surface of the protective material G;
This pipe renewal method is also performed when the axial direction of the existing pipe Po is extended in a straight line or when the existing pipe Po has a curved portion.
配管更新工法に先立ち、説明の便宜上、配管加工装置を説明する。なお、以下における「左右」は説明の便宜上用いており、方向が以下説明のものに限定されることはない。 Before describing the pipe renewal method, we will explain the pipe processing equipment for the sake of convenience. Note that the terms "left" and "right" below are used for the sake of convenience, and the directions are not limited to those described below.
配管加工装置は、図2に示すように、入口側索状体と、入口側牽引部(巻上機である右ウインチ1R)と、出口側索状体と、出口側牽引部(巻上機である左ウインチ1L)と、配管加工用具9と、を備える。配管加工用具9は、本体部7と、接続部12と、を備える。 As shown in FIG. 2, the piping processing device includes an inlet side rope-like body, an inlet side traction unit (right winch 1R, which is a hoist), an outlet side rope-like body, an outlet side traction unit (left winch 1L, which is a hoist), and a piping processing tool 9. The piping processing tool 9 includes a main body 7 and a connection unit 12.
入口側牽引部、出口側牽引部は、施工対象、すなわち給湯配管Yの入口5側、出口6側に一台ずつ配置される。入口側牽引部は、給湯配管Yの入口5側に配置された右ウインチ1Rを備え、出口側牽引部は、給湯配管Yの出口6側に配置された左ウインチ1Lを備える。また、右ウインチ1Rには、入口側索状体である右ワイヤ11が巻解き自在に巻回され、左ウインチ1Lには、出口側索状体である左ワイヤ11が巻解き自在に巻回されている。このように、右ウインチ1R、左ウインチ1Lは二台で一組として用いられる。 The inlet side towing unit and the outlet side towing unit are arranged one by one on the inlet 5 side and outlet 6 side of the work target, i.e., the hot water supply pipe Y. The inlet side towing unit has a right winch 1R arranged on the inlet 5 side of the hot water supply pipe Y, and the outlet side towing unit has a left winch 1L arranged on the outlet 6 side of the hot water supply pipe Y. In addition, a right wire 11, which is an inlet side rope-like body, is wound around the right winch 1R so as to be freely wound and unwound, and a left wire 11, which is an outlet side rope-like body, is wound around the left winch 1L so as to be freely wound and unwound. In this way, the right winch 1R and the left winch 1L are used as a pair.
右ウインチ1R、左ウインチ1Lは、右ワイヤ11および左ワイヤ11がつながった状態(基部2等を介して連結された状態)で、一組中の一台はワイヤ11に引張力を発し、他の一台は引張力を受けてワイヤ11が引き出される。なお、何れのウインチであっても、その駆動方式は手動であってもいいし、電動等、原動機の動力を利用するものであってもよい。 When the right and left wires 11 of the right winch 1R and left winch 1L are connected (connected via the base 2, etc.), one winch in the pair exerts a pulling force on the wire 11, while the other winch receives the pulling force and pulls out the wire 11. Note that the drive system for either winch may be manual or may be electric or use the power of a prime mover.
基部2の側面視の半断面形状を、図3(a)に示す。基部2は、略円柱形状であり、長手方向両端には、縮径された小径部23を備える。即ち、基部2の径方向と直交する方向の両端部分には、それぞれの端部に向かうにつれて先細りとなる小径部23が備えられる。基部2の最大径部分における外径寸法は、工事対象の既設配管Poの内径よりも小さい。そのため、基部2は既設配管Poから受ける抵抗が少なく、既設配管Po内をスムーズに移動できる。また、基部2の径方向と直交する方向の両端部分にそれぞれ小径部23が備えられるので、基部2を、一端側を先頭にして既設配管Poに進入させる場合と、他端側を先頭にして既設配管Poに進入させる場合とのいずれの場合にも基部2を既設配管Poに進入させやすくなる。さらに、基部2は、加工手段4が装着される加工手段装着部22を備える。 The half-sectional shape of the base 2 in a side view is shown in FIG. 3(a). The base 2 is substantially cylindrical, and has a small diameter portion 23 at both ends in the longitudinal direction. That is, the both ends of the base 2 in the direction perpendicular to the radial direction are provided with a small diameter portion 23 that tapers toward each end. The outer diameter dimension of the maximum diameter portion of the base 2 is smaller than the inner diameter of the existing pipe Po to be worked on. Therefore, the base 2 receives less resistance from the existing pipe Po, and can move smoothly inside the existing pipe Po. In addition, since the small diameter portion 23 is provided at both ends in the direction perpendicular to the radial direction of the base 2, the base 2 can easily enter the existing pipe Po in both cases, whether the base 2 is entered into the existing pipe Po with one end side at the front or the other end side at the front. Furthermore, the base 2 has a processing means mounting portion 22 to which the processing means 4 is attached.
基部2の長手方向両端の径方向中央に、接続受部21が設けられている。接続受部21は、後述する接続部12と接続可能に構成されており、本実施形態において、接続受部21は、雌ねじであり、後述する接続部12の雄ねじ部162と螺合可能に構成されている。 A connection receiving portion 21 is provided at the radial center of both longitudinal ends of the base 2. The connection receiving portion 21 is configured to be connectable to the connection portion 12 described below, and in this embodiment, the connection receiving portion 21 is a female thread and configured to be screwed into the male thread portion 162 of the connection portion 12 described below.
基部2の側面には、加工手段4を取り付け可能な加工手段装着部22が備えられる。加工手段装着部22は、基部2の側面から基部2の略軸心を通り裏側の側面まで貫通するよう形成された貫通孔221と、貫通孔221から周方向に90度ずれて形成されるねじ穴222と、を備える。また、本実施形態において、ねじ穴222は雌ねじであり、雄ねじである固定ねじ(図示しない)がねじ穴222に嵌め込まれることで、加工手段4を固定可能である。 The side surface of the base 2 is provided with a processing means attachment section 22 to which the processing means 4 can be attached. The processing means attachment section 22 is provided with a through hole 221 formed so as to penetrate from the side surface of the base 2 through approximately the axis of the base 2 to the rear side surface, and a screw hole 222 formed 90 degrees offset in the circumferential direction from the through hole 221. In this embodiment, the screw hole 222 is female-threaded, and a male-threaded fixing screw (not shown) is fitted into the screw hole 222 to fix the processing means 4.
基部2は基部2における径方向と直交する軸方向にずれて2か所に、加工手段装着部22を備える。具体的に、加工手段装着部22は、それぞれの加工手段装着部22の貫通孔221が基部2における軸方向視で直交するように備えられる。 The base 2 has two processing means mounting parts 22, offset in an axial direction perpendicular to the radial direction of the base 2. Specifically, the processing means mounting parts 22 are provided so that the through holes 221 of each processing means mounting part 22 are perpendicular to each other when viewed in the axial direction of the base 2.
ここで、本体部7を構成する一部であって、加工手段装着部22に装着される加工手段4について説明する。本実施形態で、この加工手段4は、平面状(扁平状)であって基部2に取付けた状態で径外方向に突出し、既設配管Poに対して切断を行う刃41を有している。本実施形態では、既設配管Poを内径側から切削加工する加工刃として、刃41を備えたもの、具体的には、両端部に刃41を備えたものが加工手段4に含まれており、既設配管Poへの切込みの深さに応じ、加工手段装着部22への装着時に径方向の長さが異なる第一刃物4A(図3(b))、第二刃物4B(図3(c))、第三刃物4C(図3(d))の3種を用いている。即ち、加工手段4は、既設配管Poに対して異なる加工ができるように、複数種類の加工部材を含む。 Here, the processing means 4, which is a part constituting the main body 7 and is attached to the processing means mounting part 22, will be described. In this embodiment, the processing means 4 is planar (flat) and protrudes radially outward when attached to the base 2, and has a blade 41 that cuts the existing pipe Po. In this embodiment, the processing means 4 includes a blade 41, specifically, a blade 41 at both ends, as a processing blade that cuts the existing pipe Po from the inner diameter side, and three types of blades, a first blade 4A (FIG. 3(b)), a second blade 4B (FIG. 3(c)), and a third blade 4C (FIG. 3(d)), which have different radial lengths when attached to the processing means mounting part 22, are used depending on the depth of the cut into the existing pipe Po. In other words, the processing means 4 includes multiple types of processing members so that different processing can be performed on the existing pipe Po.
各刃物4A~4Cは扁平状に形成され、刃板8の両側に刃41が配置される。この刃41は、刃板8を基準にした高さに相違がある。すなわち、刃41の低い側が刃先42となり、高い側が刃元43となって刃板8が加工手段装着部22に装着される。刃先42の先端421は刃41のうち最も刃板8を基準にした高さが最も低く、その高さは各刃物4A~4Cを基部に装着した際に、基部2の側面と略同じ高さである。また、刃先42は刃元43に近づくにつれて高さが増すよう構成されている。 Each of the blades 4A to 4C is formed in a flat shape, with the blades 41 disposed on both sides of the blade plate 8. The blades 41 have different heights based on the blade plate 8. That is, the lower side of the blade 41 becomes the cutting edge 42, and the higher side becomes the cutting base 43, and the blade plate 8 is attached to the processing means attachment part 22. The tip 421 of the cutting edge 42 has the lowest height based on the blade plate 8 of all the blades 41, and its height is approximately the same as the side of the base 2 when each of the blades 4A to 4C is attached to the base. The cutting edge 42 is configured so that its height increases as it approaches the cutting base 43.
刃板8には、中央部分に取付孔8aが形成されている。ねじ穴222に固定ねじが嵌め込まれることで、取付孔8aに固定ねじの先端が嵌り、刃物4A~4Cは基部2に取り付けられる。つまり、各刃物としての加工刃は、中央部に加工手段装着部への装着部と、両端部に刃と、を備える。両端部の刃は刃先が同じ方向、具体的には、刃板の幅方向一方側の方向に向けて設けられている。 The blade plate 8 has an attachment hole 8a formed in the center. When a fixing screw is fitted into the threaded hole 222, the tip of the fixing screw fits into the attachment hole 8a, and the blades 4A to 4C are attached to the base 2. In other words, each processing blade as a blade has an attachment part for the processing means attachment part in the center, and blades at both ends. The tips of the blades at both ends are provided in the same direction, specifically, facing in the direction of one side in the width direction of the blade plate.
このように本実施形態では、加工手段4は、既設配管Poに加工される切込みの深さを変更可能とするよう構成されている。なお、各刃物4A~4Cの使い分けについては後述する。 In this embodiment, the processing means 4 is configured to be able to change the depth of the cut made in the existing pipe Po. The use of each of the blades 4A to 4C will be described later.
ワイヤ11の先端には接続部12が設けられている。接続部には、索状体に接続される索状体側接続部と、基部に接続される基部側接続部と、索状体側接続部に対して基部側接続部が回転可能となるように両接続部を連結する回転連結部と、を備える。接続部12は、ワイヤ11の先端を外嵌する索状体側接続部としての接続部本体13と、接続部本体13に内蔵された回転連結部としてのベアリング14と、軸部15と、軸部15と同軸に備えられる基部側接続部としてのねじ部16とを備えており、ねじ部16はねじ部16を回転操作するための操作部161と、基部2の接続受部21に接続可能な雄ねじ部162と、を備える。具体的に、接続部本体13は、ベアリング14の外輪141に取り付けられ、軸部15は、ベアリング14の内輪142に取り付けられる。また操作部161は、雄ねじ部162よりも大径に備えられる。本実施形態の接続部12は、基部2の軸方向一端側と軸方向他端側とに各々設けられ、一方の接続部12が一方のワイヤ11を基部2の一端側に接続し、他方の接続部12が他方のワイヤ11を基部2の他端側に接続する。接続されたワイヤ11は、基部2に対して同軸上に延出する。 A connection part 12 is provided at the tip of the wire 11. The connection part includes a cable-like body side connection part connected to the cable-like body, a base side connection part connected to the base, and a rotational connection part that connects both connection parts so that the base side connection part can rotate with respect to the cable-like body side connection part. The connection part 12 includes a connection part main body 13 as a cable-like body side connection part that fits the tip of the wire 11, a bearing 14 as a rotational connection part built into the connection part main body 13, a shaft part 15, and a threaded part 16 as a base side connection part that is provided coaxially with the shaft part 15. The threaded part 16 includes an operating part 161 for rotating the threaded part 16, and a male threaded part 162 that can be connected to the connection receiving part 21 of the base 2. Specifically, the connection part main body 13 is attached to the outer ring 141 of the bearing 14, and the shaft part 15 is attached to the inner ring 142 of the bearing 14. The operating part 161 is provided with a larger diameter than the male threaded part 162. In this embodiment, the connection parts 12 are provided at one axial end side and the other axial end side of the base 2, and one connection part 12 connects one wire 11 to one end side of the base 2, and the other connection part 12 connects the other wire 11 to the other end side of the base 2. The connected wires 11 extend coaxially relative to the base 2.
次に、配管更新工法を順次説明する。図4に示すように、既設配管(給湯用の配管)Poは、外周が管状の保護材Gにより覆われている。既設配管Poおよび新配管Pnは樹脂管であって、例えばポリエチレン管である。樹脂管は、アルミニウム合金等の金属層を挟んだ多層管とすることもできる。保護材Gは、既設配管Poおよび新配管Pnの外径寸法以上の内径寸法を有しており、発泡樹脂等の柔軟な材料、例えば発泡ポリエチレンから形成されていて、径方向において断熱および保温の機能を有している。各配管Po,Pnから保護材Gが径外方向への外力を受けた場合に、保護材Gは、内径の軸線がずれるように変形、または内径部が径外方向へ圧縮変形される程度の柔軟性を有していればよい。 Next, the pipe renewal method will be described in order. As shown in FIG. 4, the outer periphery of the existing pipe (pipe for hot water supply) Po is covered with a tubular protective material G. The existing pipe Po and the new pipe Pn are resin pipes, for example, polyethylene pipes. The resin pipes can also be multi-layer pipes with a metal layer such as an aluminum alloy sandwiched between them. The protective material G has an inner diameter dimension equal to or larger than the outer diameter dimensions of the existing pipe Po and the new pipe Pn, is made of a flexible material such as foamed resin, for example, foamed polyethylene, and has the function of insulating and retaining heat in the radial direction. When the protective material G is subjected to an external force in the radial outward direction from each pipe Po, Pn, it is sufficient that the protective material G has a degree of flexibility such that the axis of the inner diameter is deformed to be shifted, or the inner diameter portion is compressed and deformed in the radial outward direction.
本実施形態においては、保護材Gは、既設配管Poおよび新配管Pnの抜き差しに際して各配管Po,Pnから保護材Gが外力を受けた場合に、軸線がずれるような変形、または、径方向への圧縮変形がなされる程度の柔軟性を有していればよい。ちなみに、従来の工法(例えば特開2004-150145号公報)では、保護材から既設配管を引き抜く際、また、既設の保護材に新配管を通す際に、発泡樹脂等の柔軟な材料から形成された保護材が用いられていると、コーナー部やバンド固定部で配管が保護材を突き破って破損してしまう。すなわち、柔軟な材料から形成された保護材に対して、従来の工法では施工できなかった。 In this embodiment, the protective material G only needs to have enough flexibility to deform so that its axis is displaced or it is compressed in the radial direction when the protective material G receives an external force from each of the pipes Po and Pn when inserting or removing the existing pipe Po and new pipe Pn. Incidentally, in conventional construction methods (e.g., JP 2004-150145 A), when the existing pipe is pulled out of the protective material or when the new pipe is passed through the existing protective material, if a protective material made of a flexible material such as foamed resin is used, the pipe breaks through the protective material at the corners or the band fixing parts and is damaged. In other words, conventional construction methods could not be used on protective materials made of flexible materials.
なお、配管更新後の新配管Pnも建築物Cに対して既設配管Poと同じ形態で配置される。また、既設配管Poにおいて管軸方向の入口5および出口6が、床材Fから上方に露出されており、既設配管Poの入口5は例えば給湯器(図示しない)にヘッダーHを介して接続され、出口6は、例えば浴室の水栓Vに接続されている。既設配管Poは、通水時の水圧で挙動しない(暴れない)よう、床材Fの下方に位置するスラブBに、バンドI等によって管軸方向において所定間隔で固定されている。なお、この固定に際しては、保護材GはバンドとスラブBにより径内方向への外力を受け、柔軟な材料で形成された保護材Gの外径は外力によって圧縮されて縮径されている。 The new pipes Pn after the pipe renewal are arranged in the same form as the existing pipes Po in the building C. The inlet 5 and outlet 6 in the axial direction of the existing pipes Po are exposed above the floor material F, and the inlet 5 of the existing pipes Po is connected to, for example, a water heater (not shown) via a header H, and the outlet 6 is connected to, for example, a bathroom faucet V. The existing pipes Po are fixed to the slab B located below the floor material F at a predetermined interval in the axial direction by bands I or the like so that they do not behave (do not move wildly) due to the water pressure when water flows through them. During this fixing, the protective material G is subjected to an external force in the radial inward direction by the bands and slab B, and the outer diameter of the protective material G, which is made of a flexible material, is compressed and reduced by the external force.
上記(1)溝付け工程は、既設配管Poの内周面に管軸方向に沿う溝(スリット)Sを形成する工程である。溝付け工程前は、既設配管Poには何ら加工は施されていない。溝付け工程に先立ち、図4(a)に示すように、右ウインチ(図示せず)から、接続部12付きの右ワイヤ11が既設配管Poに通される。この際、右ワイヤ11は作業者の手により、図示右方から左方に押し込まれ、既設配管Poの図示左端から出される。 The above-mentioned (1) groove forming process is a process of forming a groove (slit) S along the pipe axis direction on the inner peripheral surface of the existing pipe Po. Before the groove forming process, no processing is performed on the existing pipe Po. Prior to the groove forming process, as shown in FIG. 4(a), a right wire 11 with a connection part 12 is passed from a right winch (not shown) through the existing pipe Po. At this time, the right wire 11 is pushed from the right to the left by the worker's hand, and is taken out from the left end of the existing pipe Po.
図4(b)は溝付け工程の1段階目を示す。図4(a)に示す状態で、右ワイヤ11の先端と左ワイヤ11の先端とは、それぞれ右ワイヤ11と左ワイヤ11に設けられた接続部12,12の雄ねじ部162を、基部2の接続受部21,21に螺合させることで、基部2によって接続される(図6(a)参照)。この時、雄ねじ部162と接続受部21とを螺合させる際に、雄ねじ部162よりも大径に備えられる操作部161を回転させることで、雄ねじ部162を接続受部21とを螺合することができる。ここで、操作部161は雄ねじ部162よりも大径に備えられるため、ねじ部16の回転操作を容易にすることができる。 Figure 4 (b) shows the first stage of the groove forming process. In the state shown in Figure 4 (a), the tip of the right wire 11 and the tip of the left wire 11 are connected by the base 2 by screwing the male threaded portion 162 of the connection portion 12, 12 provided on the right wire 11 and the left wire 11, respectively, into the connection receiving portion 21, 21 of the base 2 (see Figure 6 (a)). At this time, when screwing the male threaded portion 162 and the connection receiving portion 21, the male threaded portion 162 can be screwed into the connection receiving portion 21 by rotating the operating portion 161, which is provided with a larger diameter than the male threaded portion 162. Here, since the operating portion 161 is provided with a larger diameter than the male threaded portion 162, the rotation operation of the screw portion 16 can be easily performed.
また、溝付け工程の1段階目では、基部2には、第一刃物4Aが一枚取付けられる。図6(a)に、第一刃物4Aが加工手段4として取り付けられた基部2と接続部12,12との接続状態を示す。第一刃物4Aは、刃41(刃先42)が既設配管Poの肉厚に至らない溝切断刃である。そして、前述したように、貫通孔221に第一刃物4Aを装着し、刃板8の取付孔8aに対し固定ねじで押さえることで、貫通孔221に第一刃物4Aが装着される。このように、加工手段4に含まれる加工部としての刃物は、基部2に対して着脱可能であり、基部2に取り付けられた状態では、両端部の刃41が基部2に対して径外方向に突出する。 In the first stage of the groove forming process, a first blade 4A is attached to the base 2. FIG. 6(a) shows the connection state between the base 2 to which the first blade 4A is attached as the processing means 4 and the connection parts 12, 12. The first blade 4A is a groove cutting blade whose blade 41 (blade tip 42) does not reach the thickness of the existing pipe Po. As described above, the first blade 4A is attached to the through hole 221 and is held down by a fixing screw against the mounting hole 8a of the blade plate 8, so that the first blade 4A is attached to the through hole 221. In this way, the blade as the processing part included in the processing means 4 is detachable from the base 2, and when attached to the base 2, the blades 41 at both ends protrude radially outward from the base 2.
この状態で右ウインチ1Rを操作し(回転させ)、第一刃物4Aの刃41を既設配管Poの内面(入口5)に接するようにして本体部7を既設配管Poの図示左端から図示右端まで移動させる。この結果、図4(c)に示すように、径方向に対向する二本の溝Sが既設配管Poの内周部に形成される。 In this state, the right winch 1R is operated (rotated) to move the main body 7 from the left end to the right end of the existing pipe Po in the figure so that the blade 41 of the first blade 4A comes into contact with the inner surface (inlet 5) of the existing pipe Po. As a result, as shown in Figure 4(c), two radially opposing grooves S are formed on the inner circumference of the existing pipe Po.
さらに、このとき、接続部12には、索状体接続部に対して基部側接続部が回転可能となるように回転連結部で連結されている。具体的には、接続部12にベアリング14が内蔵されており、軸部15と、軸部15と同軸で回転可能なねじ部16がワイヤ11に対して回転可能に取り付けられているため、ねじ部16と接続される基部2もワイヤ11に対して回転可能となり、ワイヤ11がねじれており、ワイヤ11がねじれを解くように回転した場合でも、ワイヤ11のみが回転し、基部2にワイヤ11の回転力が伝わらないため、第一刃物4Aに力がかかることを防ぐことができる。 At this time, the connection part 12 is connected to the cable-like body connection part by a rotation coupling part so that the base side connection part can rotate relative to the cable-like body connection part. Specifically, a bearing 14 is built into the connection part 12, and a shaft part 15 and a threaded part 16 that can rotate coaxially with the shaft part 15 are attached rotatably relative to the wire 11, so that the base part 2 connected to the threaded part 16 can also rotate relative to the wire 11. Even if the wire 11 is twisted and rotates to untwist it, only the wire 11 rotates, and the rotational force of the wire 11 is not transmitted to the base part 2, so that it is possible to prevent force from being applied to the first blade 4A.
また、基部2は、既設配管Poで基部2における径方向と直交する方向を軸として回転可能となるため、溝付け工程中に既設配管Poから受ける抵抗によって第一刃物4Aが既設配管Poの管軸中心に回転する方向に力を受けたとしても、力に従って基部2が回転し、力を逃がすので、第一刃物4Aにかかる力が少なくなる。 In addition, since the base 2 can rotate around an axis perpendicular to the radial direction of the base 2 in the existing piping Po, even if the first blade 4A receives a force in a direction that rotates around the pipe axis of the existing piping Po due to resistance from the existing piping Po during the grooving process, the base 2 rotates in accordance with the force and releases the force, so the force applied to the first blade 4A is reduced.
図4(d)は溝付け工程の2段階目を示す。基部2には第一刃物4Aが二枚、軸方向視で直交するように取付けられる。第一刃物4Aの刃先42の向きは1段階目と管軸方向において逆にされる。つまり、加工手段(加工部)は、基部2に対して加工方向を基部2の軸方向一端側向きと軸方向他端側向きとに付け替え可能に構成されている。具体的には、加工手段装着部22から一度第一刃物4Aを取り外し、刃先42の向きを管軸方向において逆に向けてから再度加工手段装着部22に取り付けることで刃先42の向きを変更する。ここで、刃板8の中央部分に取付孔8aが備えられるので、第一刃物4Aの刃先の向きを逆に向けたとしても、取付孔8aの位置は刃先を逆に向ける前と同じままになるため、容易に加工手段装着部22に刃先を逆に向けた第一刃物4Aを取り付けることができる。基部2に第一刃物4Aが二枚取付けられた状態で、左ウインチ1Lを操作して本体部7を既設配管Poの図示右端から図示左端まで移動させる。 Figure 4 (d) shows the second stage of the groove forming process. Two first blades 4A are attached to the base 2 so that they are perpendicular to each other when viewed in the axial direction. The orientation of the cutting edge 42 of the first blade 4A is reversed in the tube axial direction from the first stage. In other words, the processing means (processing part) is configured so that the processing direction can be switched between one axial end side of the base 2 and the other axial end side of the base 2. Specifically, the first blade 4A is once removed from the processing means mounting part 22, the direction of the cutting edge 42 is reversed in the tube axial direction, and then reattached to the processing means mounting part 22 to change the direction of the cutting edge 42. Here, since the mounting hole 8a is provided in the center part of the blade plate 8, even if the cutting edge of the first blade 4A is reversed, the position of the mounting hole 8a remains the same as before the cutting edge was reversed, so that the first blade 4A with the cutting edge reversed can be easily attached to the processing means mounting part 22. With the two first blades 4A attached to the base 2, operate the left winch 1L to move the main body 7 from the illustrated right end of the existing piping Po to the illustrated left end.
この際、第一刃物4Aのうち一枚は1段階目で形成した溝Sに沿わせるようにする。つまり、この第一刃物4Aのうち一枚は、この刃41では既設配管Poを積極的には切断せず、本体部7(特に、装着されたもう一枚の第一刃物4A)を既設配管Poに対して周方向にずれることを防止する「ガイド」として機能する。 At this time, one of the first blades 4A is aligned with the groove S formed in the first stage. In other words, the blade 41 of one of the first blades 4A does not actively cut the existing pipe Po, but functions as a "guide" that prevents the main body 7 (particularly the other attached first blade 4A) from shifting circumferentially relative to the existing pipe Po.
そして、第一刃物4Aのうち他の一枚における刃41を既設配管Poの内面であって、1段階目で形成した溝Sに対して周方向で90度ずれた位置に接するようにして移動させる。つまり、2つの第一刃物4Aのうち、一の第一刃物4Aをガイドとして溝Sに沿わせることで、基部2に、第一刃物4Aと周方向で90度ずれて備えられる他の第一刃物4Aは、一の第一刃物の軌道、すなわち1段階目で形成した溝Sと周方向で90度ずれた位置を移動する。この結果、図4(e)に示すように、周方向で90度おきに四本の溝Sが既設配管Poの内周部に形成される。以上、第一刃物4Aのうち一枚を「ガイド」として機能させることにより、四本の溝Sを確実に形成することができる。このように、第一刃物4Aは、既設配管Poには何ら加工が施されていない状態から、次の加工である溝Sを形成する加工を行う。また、第一刃物4Aは二本の溝Sから、次の加工(先の加工とは異なる加工)である四本の溝Sを形成する加工を行う。 Then, the blade 41 of the other one of the first blades 4A is moved so as to contact the inner surface of the existing pipe Po at a position shifted by 90 degrees in the circumferential direction from the groove S formed in the first stage. In other words, by making one of the two first blades 4A follow the groove S as a guide, the other first blade 4A provided on the base 2 at a position shifted by 90 degrees in the circumferential direction from the first blade 4A moves along the trajectory of the one first blade, that is, a position shifted by 90 degrees in the circumferential direction from the groove S formed in the first stage. As a result, as shown in FIG. 4(e), four grooves S are formed on the inner periphery of the existing pipe Po at 90 degree intervals in the circumferential direction. As described above, by making one of the first blades 4A function as a "guide", the four grooves S can be reliably formed. In this way, the first blade 4A performs the next processing to form the groove S from a state in which no processing has been performed on the existing pipe Po. In addition, the first blade 4A performs the next process (different from the previous process) to form four grooves S from the two grooves S.
さらに、このとき、接続部12に備えられたベアリング14によって、基部2は、既設配管Poで基部2における径方向と直交する方向を軸として回転可能となるため、1段階目で形成した溝Sが、既設配管Poがうねっていたとしても、基部2が回転することで、1段階目で形成したうねった溝Sに沿って一の第一刃物4Aが移動し、本体部7をガイドすることができるため、安定して溝付け工程の2段階目を行うことができる。 Furthermore, at this time, the bearing 14 provided in the connection portion 12 allows the base 2 to rotate about an axis perpendicular to the radial direction of the base 2 in the existing piping Po. Therefore, even if the groove S formed in the first stage is wavy in the existing piping Po, the base 2 rotates and the first blade 4A moves along the wavy groove S formed in the first stage, guiding the main body portion 7, so that the second stage of the grooving process can be performed stably.
図5(a)は溝付け工程の3段階目を示す。基部2には第二刃物4Bが一枚取付けられる。第二刃物4Bもまた、刃41(刃先42)が既設配管Poの肉厚に至らない溝切断刃であり、しかしながら第二刃物4Bは、第一刃物4Aよりも径外方向への刃41の突出量が大きい。図6(b)に、第二刃物4Bが加工手段4として取り付けられた基部2と接続部12,12との接続状態を示す。そして、既設配管Poの外側で、貫通孔221に第二刃物4Bを装着し、刃板8の取付孔8aを固定ねじでさえることで、貫通孔221に第二刃物4Bが装着され、これによって、基部2に取り付けられる加工手段4は、第一刃物4Aから第二刃物4Bに交換(変更)できる。 Figure 5 (a) shows the third stage of the groove forming process. One second blade 4B is attached to the base 2. The second blade 4B is also a groove cutting blade whose blade 41 (blade tip 42) does not reach the thickness of the existing pipe Po, but the second blade 4B has a larger protrusion in the radial outward direction than the first blade 4A. Figure 6 (b) shows the connection state between the base 2 to which the second blade 4B is attached as the processing means 4 and the connection parts 12, 12. Then, the second blade 4B is attached to the through hole 221 on the outside of the existing pipe Po, and the mounting hole 8a of the blade plate 8 is held by a fixing screw, so that the second blade 4B is attached to the through hole 221. This allows the processing means 4 attached to the base 2 to be replaced (changed) from the first blade 4A to the second blade 4B.
この状態で右ウインチ1Rを操作し、第二刃物4Bの刃41を1段階目または2段階目で形成した溝Sに沿わせつつ、本体部7を既設配管Poの図示左端から図示右端まで移動させる。ここで、刃41の刃先42の先端421は、基部2と略同じ高さであり、刃元43に向かうにつれて高さが増すので、溝Sに第二刃物4Bの刃41の先端421が嵌り、第二刃物4Bを溝Sに沿わせやすい。第二刃物4Bの移動の結果、図5(b)に示すように、径方向に対向する二本の溝Sが深くなる。 In this state, the right winch 1R is operated to move the main body 7 from the left end to the right end of the existing pipe Po while aligning the blade 41 of the second blade 4B with the groove S formed in the first or second stage. Here, the tip 421 of the cutting edge 42 of the blade 41 is at approximately the same height as the base 2, and the height increases toward the blade base 43, so that the tip 421 of the blade 41 of the second blade 4B fits into the groove S, making it easy to align the second blade 4B with the groove S. As a result of the movement of the second blade 4B, the two radially opposing grooves S become deeper, as shown in FIG. 5(b).
図5(c)は溝付け工程の4段階目を示す。ここでも、基部2には第二刃物4Bが一枚取付けられる。第二刃物4Bの向きは3段階目と逆にされる。この状態で左ウインチ1Lを操作し、第二刃物4Bの刃41を3段階目で沿わせた溝Sとは別の溝Sに沿わせつつ、を既設配管Poの図示右端(入口5)から図示左端(出口6)まで移動させる。この結果、図5(d)に示すように、前記別の溝Sであって、径方向に対向する二本の溝Sが深くなる。これによって、四本の溝Sが同等の深さになる。溝付け工程はこれで終了となる。 Figure 5 (c) shows the fourth stage of the groove forming process. Here again, one second blade 4B is attached to the base 2. The orientation of the second blade 4B is reversed from that in the third stage. In this state, the left winch 1L is operated to move the blade 41 of the second blade 4B from the illustrated right end (inlet 5) to the illustrated left end (outlet 6) of the existing piping Po while aligning it along a groove S other than the groove S aligned in the third stage. As a result, as shown in Figure 5 (d), the other grooves S, two grooves S that are radially opposed, become deeper. This makes the four grooves S the same depth. This completes the groove forming process.
また、基部2の外径が既設配管Poの内径に近いことから、第一刃物4A、第二刃物4Bのガイドになり易く、したがって、溝Sの深さや距離が均等になる。そして上記溝付け工程においては、複数の溝Sのうち、先に一部の溝Sを形成し、該溝Sをガイドにして残りの溝Sを形成することで、複数の溝どうしの間隔を軸方向に一定にすることができる。また、溝Sの形成を複数段階に分け、溝Sを徐々に深くすることで、加工抵抗を小さくして、軸方向に真っすぐな溝を形成することができる。さらに、既設配管Poの種類や大きさに合わせて、基部2の外径を変更することもできる。 In addition, since the outer diameter of the base 2 is close to the inner diameter of the existing piping Po, it easily serves as a guide for the first blade 4A and the second blade 4B, and therefore the depth and distance of the grooves S are uniform. In the above-mentioned grooving process, some of the multiple grooves S are formed first, and then the remaining grooves S are formed using these grooves as a guide, thereby making it possible to make the spacing between the multiple grooves constant in the axial direction. In addition, by dividing the formation of the grooves S into multiple stages and gradually deepening the grooves S, it is possible to reduce the processing resistance and form straight grooves in the axial direction. Furthermore, the outer diameter of the base 2 can be changed according to the type and size of the existing piping Po.
上記溝付け工程においては、複数の溝Sのうち、先に一部の溝Sを形成し、先に形成した溝Sをガイドにして残りの溝Sを形成することで、複数の溝S同士の間隔を軸方向に一定にすることができる。また、溝Sの形成を複数段階に分け、溝Sを徐々に深くすることで、加工抵抗を小さくして、管軸方向に真っすぐな溝を形成することができる。以上の溝付け工程により既設配管Poに溝Sを形成した状態で、既設配管Poを切断することで、既設配管分割工程において切断に失敗すること(例えば、切断片Psの幅が長手方向の途中で狭くなって切れてしまうこと)がなく、管軸方向の確実な切断が可能である。さらに、下記の既設配管分割工程において、溝Sに沿って切断することで、切断における抵抗を小さくすることができる。 In the above groove forming process, some of the grooves S are formed first, and the remaining grooves S are formed using the previously formed grooves S as a guide, so that the spacing between the multiple grooves S can be made constant in the axial direction. In addition, by dividing the formation of the grooves S into multiple stages and gradually deepening the grooves S, it is possible to reduce the processing resistance and form straight grooves in the pipe axial direction. By cutting the existing pipe Po in a state in which grooves S are formed in the existing pipe Po by the above groove forming process, cutting does not fail in the existing pipe division process (for example, the width of the cut piece Ps narrows midway in the longitudinal direction and is cut), and reliable cutting in the pipe axial direction is possible. Furthermore, by cutting along the grooves S in the existing pipe division process described below, it is possible to reduce the resistance to cutting.
上記(2)既設配管分割工程は、溝付け工程を終了した次工程である。既設配管分割工程は、既設配管Poを、径方向および管軸方向に切断することにより、既設配管Poを径方向で間隔をあけて複数個所で管軸方向に切断して、複数の切断片Psに分割する工程である。本実施形態では、径方向の切断が、周方向に一定の距離(角度で90度ごと)をおいて4箇所でなされ、この切断が管軸方向に連続して行われる。 The above (2) existing pipe dividing process is the process that follows after the groove forming process. The existing pipe dividing process is a process in which the existing pipe Po is cut in the radial and axial directions to divide the existing pipe Po into multiple cut pieces Ps by cutting the existing pipe Po in the axial direction at multiple locations spaced apart in the radial direction. In this embodiment, the radial cuts are made at four locations spaced at regular intervals in the circumferential direction (every 90 degrees), and these cuts are made continuously in the axial direction.
図5(e)は既設配管分割工程を示す。基部2には第三刃物4Cが二枚取付けられる。第三刃物4Cは、刃41(刃先42)が既設配管Poの肉厚を超えた分割切断刃である。これには、既設配管Poの外側でねじ穴222に第三刃物4Cを装着し、固定ねじで刃板8の取付孔8aを押さえることで、貫通孔221に第三刃物4Cが装着され、第二刃物4Bから第三刃物4Cに交換できる。第三刃物4Cの方が第二刃物4Bよりも径方向への刃41の突出量が大きい。図6(c)に、第三刃物4Cが加工手段4として取り付けられた基部2と接続部12,12との接続状態を示す。 Figure 5 (e) shows the existing pipe division process. Two third blades 4C are attached to the base 2. The third blade 4C is a dividing and cutting blade whose blade 41 (blade tip 42) exceeds the thickness of the existing pipe Po. For this, the third blade 4C is attached to the screw hole 222 on the outside of the existing pipe Po, and the third blade 4C is attached to the through hole 221 by pressing the mounting hole 8a of the blade plate 8 with a fixing screw, and the second blade 4B can be replaced with the third blade 4C. The third blade 4C has a larger radial projection of the blade 41 than the second blade 4B. Figure 6 (c) shows the connection state between the base 2 to which the third blade 4C is attached as the processing means 4 and the connection parts 12, 12.
そして右ウインチ1Rを操作し、第三刃物4Cの刃41を溝付け工程の3段階目および4段階目を経て深くなった溝Sに沿わせつつ、本体部7を既設配管Poの図示左端から図示右端まで移動させる。ここで、刃41の刃先42の先端421は、基部2と略同じ高さであり、刃元43に向かうにつれて高さが増すので、溝Sに第三刃物4Cの刃41の先端421が嵌り、第三刃物4Cを溝Sに沿わせやすい。第三刃物4Cの移動の結果、図5(f)に示すように、既設配管Poが周方向で四分割される。このように、第二刃物4Bで深く形成された溝Sに対し、その後に交換された第三刃物4Cにより、既設配管Poの次の加工として、既設配管Poを周方向で割ることができる。上記既設配管分割工程において、溝付工程で形成した複数の溝Sに対応するように刃41を沿わせることにより、切断時の抵抗を小さくすることができる。さらに、本実施形態では、既設配管を周方向に一定の間隔で複数に分割することで、各切断片Psの形状は略同じ形状にできる。よって、新配管挿入時の挿入抵抗を、周方向で偏りなく均一なものとでき、新配管Pnを真っすぐ挿入しやすくなる。 Then, the right winch 1R is operated, and the main body 7 is moved from the left end to the right end of the existing pipe Po while aligning the blade 41 of the third blade 4C with the groove S that has become deeper through the third and fourth stages of the groove forming process. Here, the tip 421 of the cutting edge 42 of the blade 41 is approximately the same height as the base 2, and the height increases toward the blade base 43, so that the tip 421 of the blade 41 of the third blade 4C fits into the groove S, making it easy to align the third blade 4C with the groove S. As a result of the movement of the third blade 4C, the existing pipe Po is divided into four in the circumferential direction as shown in FIG. 5(f). In this way, the existing pipe Po can be divided in the circumferential direction by the third blade 4C that was replaced after the groove S formed deeply by the second blade 4B as the next processing of the existing pipe Po. In the above-mentioned existing pipe dividing process, the blade 41 is aligned to correspond to the multiple grooves S formed in the groove forming process, thereby reducing the resistance during cutting. Furthermore, in this embodiment, by dividing the existing pipe into multiple pieces at regular intervals in the circumferential direction, the shape of each cut piece Ps can be made approximately the same. Therefore, the insertion resistance when inserting the new pipe can be made uniform in the circumferential direction without bias, making it easier to insert the new pipe Pn straight.
なお、第三刃物4Cは、既設配管Poの肉厚を超えた分割切断刃である。したがって、既設配管Poに湾曲部分が存在する場合には、湾曲部分がひしゃげて断面が歪になる場合もあるので、第三刃物4Cの刃41は、その高さを考慮して、既設配管Poの肉厚を超えることが望ましい。 The third blade 4C is a dividing cutting blade that exceeds the thickness of the existing pipe Po. Therefore, if the existing pipe Po has a curved portion, the curved portion may be distorted and the cross section may become distorted. Therefore, it is desirable that the blade 41 of the third blade 4C exceeds the thickness of the existing pipe Po, taking into account its height.
このように、本実施形態では、本体部7の構成部分の一部であり、刃41の形状が異なる第一刃物4Aから第三刃物4Cを変更可能なように基部2に取付け、右ワイヤ11又は左ワイヤ11の一方を、既設配管Poを通した状態で基部2の一端に接続し、他方を既設配管Poに通す前の状態で基部2の他端に接続することで、既設配管Poに対し、本体部7は既設管Po内を基部2の一端側を先頭として進む往動と基部2の他端側を先頭として進む復動とで異なる加工ができる。 In this embodiment, the first blade 4A to the third blade 4C, which are part of the components of the main body 7 and have different blade 41 shapes, are attached to the base 2 so that they can be changed, and one of the right wire 11 or the left wire 11 is connected to one end of the base 2 while passing through the existing piping Po, and the other is connected to the other end of the base 2 before passing through the existing piping Po. By doing this, the main body 7 can perform different processing on the existing piping Po by moving forward through the existing pipe Po with one end of the base 2 as the leader, and moving backward with the other end of the base 2 as the leader.
上記(3)引抜工程は、複数の切断片Psを保護材Gから引き抜くようにした工程である。これにより、保護材Gの内部から既設配管Poが除去される。引き抜きは、作業者が各切断片Psを手やペンチ等の工具でつかんで行う。基本的には一本ずつ引き抜くが、場合によっては複数本をまとめて引き抜くこともできる。各切断片Psは幅方向で湾曲した帯状であって、周方向に沿って4枚並んでいる。 The above-mentioned (3) pulling out process is a process in which multiple cut pieces Ps are pulled out from the protective material G. This removes the existing piping Po from inside the protective material G. The worker pulls out each cut piece Ps by hand or with a tool such as pliers. Basically, they are pulled out one by one, but in some cases, multiple pieces can be pulled out at once. Each cut piece Ps is a band-like shape curved in the width direction, and four pieces are lined up along the circumferential direction.
各切断片Psの断面形状は保護材Gの内部空間の断面形状に比べて小さく、当該内部空間において各切断片Psの径方向および周方向への移動の自由度が高いことから、既設配管Poを切断することなく管の状態のままで保護材Gから引き抜くことに比べ、はるかに小さな引張力で引き抜きが可能である。また、引き抜きに伴い、保護材Gを破損してしまう可能性も小さいため、既設の保護材Gを引き続き使用することができる。このように、本実施形態の引抜工程は、発泡樹脂等の柔軟な材料(破損しやすい材料)で形成された保護材Gに対して有効である。そして、保護材Gがバンド等とスラブBにより径内方向への外力を受け、圧縮されて縮径されている場合に有効である。 The cross-sectional shape of each cut piece Ps is smaller than the cross-sectional shape of the internal space of the protective material G, and each cut piece Ps has a high degree of freedom of movement in the radial and circumferential directions in the internal space. Therefore, it is possible to pull out the existing piping Po from the protective material G with a much smaller pulling force than if the existing piping Po were pulled out of the protective material G in its pipe state without cutting it. In addition, since there is little possibility that the protective material G will be damaged during pulling out, the existing protective material G can continue to be used. In this way, the pulling process of this embodiment is effective for protective material G made of a soft material (material that is easily damaged) such as foamed resin. It is also effective when the protective material G is subjected to an external force in the radial inward direction by a band or the like and a slab B, and is compressed and reduced in diameter.
上記(4)新配管挿入工程は、新配管Pnを保護材Gの内周面に沿わせつつ保護材Gの内部に通す工程である。既設配管Poが除去された保護材Gの内部に、新配管Pnが沿うように、保護材Gの一端側から他端側に向けて新配管Pnを挿入する。配管の更新はこれで終了であって、その後、新配管Pnの両端部を給湯器や水栓Vに接続して工事を完了する。 The above-mentioned (4) new pipe insertion process is a process of passing the new pipe Pn through the inside of the protective material G while aligning it with the inner circumferential surface of the protective material G. The new pipe Pn is inserted from one end side of the protective material G to the other end side so that the new pipe Pn fits inside the protective material G from which the existing pipe Po has been removed. This completes the pipe renewal, and then both ends of the new pipe Pn are connected to the water heater and faucet V to complete the work.
このように、本実施形態の工法では、既設配管Poおよび保護材Gが建築物Cの外部に露出した端部で作業可能である。このため、既設配管Poを新配管Pnに取り換える作業を、既設配管Poの設置対象物(本実施形態では建築物CのスラブBや床材F)から保護材Gを取り外さない状態で行うことができる。また、各ウインチ1の操作、既設配管Poの保護材Gからの引き抜き、新配管Pnの保護材Gへの挿入が全て建築物Cの外部(詳しくは、建築物Cにおける床材FとスラブBとの間の閉鎖空間に対する外部)にて行える。このため、建築物Cの解体の必要がないので、工事の低コスト化に貢献できる。 In this way, in the construction method of this embodiment, work can be performed at the ends of the existing piping Po and the protective material G exposed to the outside of the building C. Therefore, the work of replacing the existing piping Po with the new piping Pn can be performed without removing the protective material G from the object on which the existing piping Po is to be installed (in this embodiment, the slab B or floor material F of the building C). In addition, the operation of each winch 1, the pulling out of the existing piping Po from the protective material G, and the insertion of the new piping Pn into the protective material G can all be performed outside the building C (more specifically, outside the closed space between the floor material F and the slab B in the building C). Therefore, there is no need to dismantle the building C, which contributes to reducing the cost of construction.
以上、本実施形態の配管更新工法によると、既設配管Poを覆っていた保護材Gを建築物CにバンドIなどで固定したままとしておき、この保護材Gを、新配管Pnを敷設する際のガイドとして利用できる。しかも、既設配管分割工程と引抜工程とにより、配管の引き抜き作業を、配管の敷設形状に影響されにくく容易にできる。 As described above, according to the pipe renewal method of this embodiment, the protective material G that covered the existing pipe Po is left fixed to the building C with a band I or the like, and this protective material G can be used as a guide when laying the new pipe Pn. Furthermore, the existing pipe division process and the pulling-out process make the pipe pulling-out work easy and less affected by the pipe laying shape.
また、配管の更新の際に建築物Cの解体を極力不要とし、また、配管新設時の施工に格段の配慮が不要である。この「格段の配慮」とは、配管に折損が生じるような急な曲がりを形成しないという最低限の配慮を超えた配慮を意味する。このように本実施形態の配管更新工法を採用することで、配管新設時における配管経路をラフに設定してもよく、しかも、配管新設時に、現場にて保護材Gに配管が抜き差しできるか否かのテストを行うことも不要であるから、配管新設時の工数が従来よりも増加することがない。 In addition, dismantling of building C is made as unnecessary as possible when updating the piping, and no special consideration is required when installing new piping. This "special consideration" means consideration that goes beyond the minimum consideration of not creating sharp bends that could cause the piping to break. By adopting the piping renewal method of this embodiment in this way, the piping route can be roughly set when installing new piping, and there is also no need to test on-site whether the piping can be inserted and removed from the protective material G when installing new piping, so the labor required when installing new piping does not increase compared to the conventional method.
さらに、配管更新工法に用いる配管加工装置によれば、左右のウインチ1R,1Lは、給湯配管Yの入口5側、出口6側に一台ずつ配置され、各ワイヤ11の途中で、既設配管Poにおける加工状況に応じて既設配管Poの外側で加工手段4を変更する。すなわち、基部2において装着されていた加工手段4を、第一刃物4Aから第二刃物4Bに変更し、さらに第二刃物4Bから第三刃物4Cに変更する。そして、左右ウインチ1R,1Lとの間で既設配管Poの内側で各ワイヤ11を移動させることで、既設配管Poにおける加工状態に応じて、既に行った加工とは異なる、次の加工をすることができる。このため、既設配管Poに対して効率のよい加工をすることができる。 Furthermore, according to the pipe processing device used in the pipe renewal method, the left and right winches 1R, 1L are arranged one each on the inlet 5 side and the outlet 6 side of the hot water supply pipe Y, and the processing means 4 is changed outside the existing pipe Po midway along each wire 11 depending on the processing status of the existing pipe Po. That is, the processing means 4 attached to the base 2 is changed from the first blade 4A to the second blade 4B, and further changed from the second blade 4B to the third blade 4C. Then, by moving each wire 11 inside the existing pipe Po between the left and right winches 1R, 1L, it is possible to perform the next processing, which is different from the processing already performed, depending on the processing status of the existing pipe Po. This allows efficient processing of the existing pipe Po.
配管加工用具9が、基部2及び加工手段4を有する本体部7と、本体部7を索状体に接続する接続部12を備え、加工手段4が、基部2がその軸方向一端側から既設配管Poに進入して加工する場合と、軸方向他端側から既設配管Poに進入して加工する場合とで、異なる加工できる。具体的には、溝付け工程の1段階目ないし4段階目や、既設配管分割工程のように刃41の向きを変更することや、刃物4A~4Cの種類を基部2に対して付け替えることにより変更することで、既設配管の入口から出口へ基部の一端側が先頭で進入する往動の場合と、既設配管の出口から入口に基部の他端側が先頭で進入する復動の場合とで異なる加工をすることができるので、既設配管Poに対して効率よく加工ができる。 The pipe processing tool 9 includes a main body 7 having a base 2 and processing means 4, and a connection part 12 that connects the main body 7 to the cord-like body. The processing means 4 can perform different processing when the base 2 enters the existing pipe Po from one axial end side and when the processing means 4 enters the existing pipe Po from the other axial end side. Specifically, by changing the orientation of the blade 41 or by changing the type of the blades 4A to 4C to the base 2, as in the first to fourth stages of the groove forming process and the existing pipe division process, different processing can be performed in the case of a forward movement in which one end of the base enters from the inlet to the outlet of the existing pipe at the front, and in the case of a return movement in which the other end of the base enters from the outlet to the inlet of the existing pipe at the front, so that the existing pipe Po can be processed efficiently.
また、既設配管Poの経年等による老朽化に応じて、新配管Pnを更新する際に、保護材Gおよび既設配管Poを全て取換えていることに比べ、新配管Pnの設置に手間がかからない。 In addition, when updating new piping Pn in response to deterioration of the existing piping Po due to aging, etc., installing the new piping Pn requires less effort than replacing all of the protective material G and the existing piping Po.
さらに、本実施形態にかかる配管加工用具9は、基部2が既設配管Po内で基部2における径方向と直交する方向を軸として回転可能となるため、加工作業中に既設配管Poから受ける抵抗によって加工手段4が既設配管Poの管軸中心に回転する方向に力を受けたとしても、力に従って基部2が回転し、力を逃がすので、加工手段4にかかる力が少なくなる。また、ワイヤ11がねじれており、ワイヤ11がねじれを解くように回転した場合でも、ワイヤ11のみが回転し、基部2にワイヤ11の回転力が伝わらないため、加工手段4に力がかかることを防ぐことができる。そのため、加工作業中に加工手段4が破損することを防ぐことができる。 Furthermore, in the piping processing tool 9 according to this embodiment, the base 2 can rotate within the existing piping Po around an axis perpendicular to the radial direction of the base 2. Therefore, even if the processing means 4 receives a force in a direction that rotates around the axis of the existing piping Po due to resistance from the existing piping Po during processing work, the base 2 rotates in accordance with the force and releases the force, so that the force applied to the processing means 4 is reduced. Also, even if the wire 11 is twisted and rotates to untwist the wire 11, only the wire 11 rotates and the rotational force of the wire 11 is not transmitted to the base 2, so that the force applied to the processing means 4 can be prevented. Therefore, the processing means 4 can be prevented from being damaged during processing work.
また、加工手段4である刃41が、基部2における周方向の異なる位置に複数配置されているため、本体部7を既設配管Poの入口5側から出口6側へ、又は出口6側から入口5側へ往復移動させることで、既設配管Poの周方向の複数の位置を同時に加工することができ、加工作業の効率が高まる。 In addition, since the blades 41, which are the processing means 4, are arranged at multiple different circumferential positions on the base 2, multiple circumferential positions of the existing piping Po can be processed simultaneously by moving the main body 7 back and forth from the inlet 5 side to the outlet 6 side of the existing piping Po, or from the outlet 6 side to the inlet 5 side, thereby improving the efficiency of the processing work.
さらには、加工手段4である刃41の先端421が、刃板8を基準とした高さにおいて、基部2の側面と同じ高さから始まり、刃元43に近づくにつれて高くなるため、一段階目の溝付け工程の際に、基部2が既設配管Po内で径方向にずれたとしても、刃先42が既設配管Poの内周に確実に切込みを入れることができる。また、2段階目以降の溝付け工程と、既設配管分割工程の際に、刃先42の先端部分が、以前の工程で形成された溝Sに嵌るため、基部2が溝Sにガイドされやすくなる。 Furthermore, the tip 421 of the blade 41, which is the processing means 4, starts at the same height as the side of the base 2, based on the blade plate 8, and becomes higher as it approaches the blade base 43. Therefore, even if the base 2 shifts radially within the existing piping Po during the first groove forming process, the blade tip 42 can reliably make a cut into the inner circumference of the existing piping Po. Furthermore, during the second and subsequent groove forming processes and the existing piping division process, the tip of the blade tip 42 fits into the groove S formed in the previous process, making it easier for the base 2 to be guided into the groove S.
また、接続部12に備えられたベアリング14によって、基部2は、既設配管Poで基部2における径方向と直交する方向を軸として回転可能となるため、形成した溝Sがうねっていたとしても、基部2が回転することで、うねった溝Sに沿って刃41が移動し、本体部7をガイドすることができるため、安定して溝付け工程の2段階目以降および既設配管分割工程を行うことができる。 In addition, the bearing 14 provided in the connection portion 12 allows the base 2 to rotate around an axis perpendicular to the radial direction of the base 2 in the existing piping Po. Therefore, even if the groove S formed is wavy, the blade 41 moves along the wavy groove S as the base 2 rotates, and the main body portion 7 can be guided. This allows the second and subsequent stages of the groove forming process and the existing piping division process to be carried out stably.
次に、本発明の第二実施形態を、図7ないし図12に基づいて説明する。はじめに、配管加工装置は、入口側索状体と、入口側牽引部(巻上機である右ウインチ1R)と、出口側索状体と、出口側牽引部(巻上機である左ウインチ1L)と、本体部7と、接続部12とを備える。入口側索状体と、入口側牽引部と、出口側索状体と、出口側牽引部と、接続部12と、は、上記第一の実施形態と同様である。 Next, a second embodiment of the present invention will be described with reference to Figures 7 to 12. First, the piping processing device includes an inlet side rope-like body, an inlet side traction section (right winch 1R which is a hoist), an outlet side rope-like body, an outlet side traction section (left winch 1L which is a hoist), a main body 7, and a connection section 12. The inlet side rope-like body, the inlet side traction section, the outlet side rope-like body, the outlet side traction section, and the connection section 12 are the same as those in the first embodiment.
第二の実施形態が第一の実施形態と異なる配管加工装置の構成は、本体部7における加工手段4が異なる。 The configuration of the piping processing device in the second embodiment differs from the first embodiment in that the processing means 4 in the main body 7 is different.
加工手段4について説明する。第一の実施形態では、刃板8の両側に刃41が配置されたが、第二の実施形態では、刃板8の片側にのみ刃41が形成されている。また、基部2は第一の実施形態と同様の構成であり、刃板8と貫通孔221とは、相対形状に形成されている。図12(a)~(c)に示すように、本体部7としては、このような第一刃物4A、第二刃物4B、第三刃物4Cを含む加工手段4を備えている。第一刃物4A、第二刃物4B、第三刃物4Cにおける基部2への取付け状態は、第一の実施形態と同様である。 The processing means 4 will now be described. In the first embodiment, the blades 41 were arranged on both sides of the blade plate 8, but in the second embodiment, the blades 41 are formed on only one side of the blade plate 8. The base 2 has the same configuration as in the first embodiment, and the blade plate 8 and the through hole 221 are formed in a relative shape. As shown in Figures 12(a) to (c), the main body 7 is provided with the processing means 4 including the first blade 4A, second blade 4B, and third blade 4C. The attachment state of the first blade 4A, second blade 4B, and third blade 4C to the base 2 is the same as in the first embodiment.
図7ないし図9、および図12(d)を参照して、既設配管Poの内径を拡径する加工をする加工手段の一つである拡径具44の説明をする。拡径具44は、基部2に対して周方向全周にわたって径外方向に突出し、既設配管Poに対して拡径という加工を行うものであり、表面が一方側から他方側に向けて傾斜された傾斜面48を有した円錐台形状に形成されている。一方側は、既設配管Poの内径よりも小径に形成された外径面であり、他方側は既設配管Poの内径よりも大径に形成された外径面である。 With reference to Figures 7 to 9 and Figure 12 (d), the diameter expansion tool 44, which is one of the processing means for processing the existing pipe Po to expand its inner diameter, will be described. The diameter expansion tool 44 protrudes radially outward over the entire circumference of the base 2, and performs processing to expand the diameter of the existing pipe Po. The surface is formed in a truncated cone shape with an inclined surface 48 that is inclined from one side to the other. One side is an outer diameter surface formed with a smaller diameter than the inner diameter of the existing pipe Po, and the other side is an outer diameter surface formed with a larger diameter than the inner diameter of the existing pipe Po.
具体的に、拡径具44は、半円錐台形状の拡径部品44aと、拡径部品44aと後述する切り欠き471の位置が異なる拡径部品44bと、を備える。拡径部品44aは、基部2から径外方向に突出し、既設配管Poを拡径する拡径部45と、拡径部品44aを基部2に取り付けるための取付部49と、を備え、拡径部45は、軸方向の一端側に既設配管Poの内径よりも外径が小さい小径部46と、既設配管Poの内径よりも外径が大きい大径部47と、小径部46と大径部47とをつなぐ傾斜面48と、を備える。取付部49は板状の板部81を備え、板部の中央には取付孔81aが形成されている。また、板部81の厚さは、貫通孔221の厚さの半分以下に設定される。さらに、大径部47には、切り欠き471が形成され、切り欠き471は、拡径具44を基部2に取り付けた際に、ねじ穴222と切り欠き471の位置が軸方向及び周方向で一致する様に形成される。切り欠き471の形状は、半円状であり、拡径部品44aと44bとを合わせたとき、2つの切り欠き471が合わさって固定ねじが挿入可能な大きさの孔になる形状である。 Specifically, the expanding tool 44 includes a semi-frustum-shaped expanding part 44a and an expanding part 44b in which the position of a notch 471 described later is different from that of the expanding part 44a. The expanding part 44a includes an expanding part 45 that protrudes radially outward from the base 2 and expands the existing pipe Po, and an attachment part 49 for attaching the expanding part 44a to the base 2. The expanding part 45 includes a small diameter part 46 whose outer diameter is smaller than the inner diameter of the existing pipe Po at one end in the axial direction, a large diameter part 47 whose outer diameter is larger than the inner diameter of the existing pipe Po, and an inclined surface 48 that connects the small diameter part 46 and the large diameter part 47. The attachment part 49 includes a plate-shaped plate part 81, and an attachment hole 81a is formed in the center of the plate part. The thickness of the plate part 81 is set to be half or less of the thickness of the through hole 221. Furthermore, a notch 471 is formed in the large diameter portion 47, and the notch 471 is formed so that when the diameter expansion tool 44 is attached to the base 2, the screw hole 222 and the notch 471 are aligned in the axial and circumferential directions. The shape of the notch 471 is semicircular, and when the diameter expansion parts 44a and 44b are mated, the two notches 471 come together to form a hole large enough to insert a fixing screw.
拡径部品44bは、拡径部品44aと切り欠き471の位置が異なり、板部の長手方向を軸に対称の位置に切り欠き471が形成される。そのため、基部2に拡径部品44a及び拡径部品44bを取り付けた際に、切り欠き471同士が向き合うように拡径具44が基部2に取り付けられる。 The position of the notch 471 of the expansion part 44b is different from that of the expansion part 44a, and the notch 471 is formed at a position symmetrical about the longitudinal direction of the plate part. Therefore, when the expansion part 44a and the expansion part 44b are attached to the base 2, the expansion tool 44 is attached to the base 2 so that the notches 471 face each other.
拡径部品44a、44bを基部2に取り付ける際には、それぞれの板部81を貫通孔221に挿入し、固定ねじを切り欠き471とねじ穴222とに通し固定ねじの先端で取付孔81aを固定することにより、基部2に拡径具44が取り付けられる。ここで、取付孔81aは、板部81の中央に備えられるため、貫通孔221の一端側から板部81を挿入した場合と、貫通孔221の他端側から板部81を挿入した場合とで同じ位置に取付孔81aが現れる。そのため拡径部品44aを貫通孔221の一端側から挿入し、拡径部品44bを貫通孔221の他端側から挿入した場合でも、拡径部品44aを貫通孔221の他端側から挿入し、拡径部品44bを貫通孔221の一端側から挿入した場合でも、拡径具44を基部2に取り付けることができるため、取付の向きを気にしなくてよい。 When attaching the expansion parts 44a and 44b to the base 2, the expansion tool 44 is attached to the base 2 by inserting each plate part 81 into the through hole 221, passing a fixing screw through the notch 471 and the screw hole 222, and fixing the mounting hole 81a with the tip of the fixing screw. Here, since the mounting hole 81a is provided in the center of the plate part 81, the mounting hole 81a appears in the same position when the plate part 81 is inserted from one end side of the through hole 221 and when the plate part 81 is inserted from the other end side of the through hole 221. Therefore, even if the expansion part 44a is inserted from one end side of the through hole 221 and the expansion part 44b is inserted from the other end side of the through hole 221, or even if the expansion part 44a is inserted from the other end side of the through hole 221 and the expansion part 44b is inserted from one end side of the through hole 221, the expansion tool 44 can be attached to the base 2, so there is no need to worry about the direction of attachment.
このように第二の実施形態では、加工手段4に加工刃と拡径具とが含まれる。 In this way, in the second embodiment, the processing means 4 includes a processing blade and an expanding tool.
第二の実施形態に係る配管更新工法について説明する。本実施形態に係る配管更新工法は、
(1)溝付け工程…既設配管Poの内周面に管軸方向に沿う溝Sを形成する工程、
(2)既設配管切断工程…溝Sを用いて既設配管Poを径方向で切断する工程、
(3)拡径工程…既設配管Poを拡径する工程、
(4)新配管挿入工程…新配管Pnを既設配管Poの内部に通す工程、
とを有する。
A piping renewal method according to the second embodiment will be described. The piping renewal method according to this embodiment is as follows:
(1) Grooving process: a process of forming a groove S along the pipe axis direction on the inner peripheral surface of the existing pipe Po;
(2) Existing pipe cutting process: a process of cutting the existing pipe Po in the radial direction using the groove S;
(3) Diameter expansion process: a process of expanding the diameter of the existing pipe Po;
(4) New pipe insertion process: a process of passing the new pipe Pn through the inside of the existing pipe Po;
and
溝付け工程に先立ち、図10(a)に示すように、右ウインチ1R(図示していない)から、右ワイヤ11が図示右方(入口5)から左方(出口6)に押し込まれ、既設配管Poの図示左端から出される。これは作業者の手によって行われる。 Prior to the groove forming process, as shown in FIG. 10(a), the right wire 11 is pushed from the right (inlet 5) to the left (outlet 6) from the right winch 1R (not shown) and is taken out from the left end of the existing pipe Po. This is done manually by the worker.
図10(b)は溝付け工程の1段階目を示す。図10(a)に示す状態で、右ワイヤ11の先端と左ワイヤ11の先端とは、それぞれ右ワイヤ11と左ワイヤ11に設けられた接続部12,12の雄ねじ部162を、基部2の接続受部21,21に螺合させることで、基部2によって接続される。また、溝付け工程の1段階目では、基部2には、図12(a)で示す第一刃物4Aが一枚取付けられる。 Figure 10(b) shows the first stage of the groove forming process. In the state shown in Figure 10(a), the tip of the right wire 11 and the tip of the left wire 11 are connected by the base 2 by screwing the male threaded portion 162 of the connection portion 12, 12 provided on the right wire 11 and the left wire 11, respectively, into the connection receiving portion 21, 21 of the base 2. Also, in the first stage of the groove forming process, a first blade 4A shown in Figure 12(a) is attached to the base 2.
この状態で右ウインチ1Rを操作し、第一刃物4Aの刃41を既設配管Poの内面(入口5)に接するようにして本体部7を既設配管Poの図示左端から図示右端まで移動させる。この結果、図10(c)に示すように、径方向に1本の溝Sが既設配管Poの内周部に形成される。 In this state, the right winch 1R is operated to move the main body 7 from the left end to the right end of the existing pipe Po in the figure so that the blade 41 of the first blade 4A comes into contact with the inner surface (inlet 5) of the existing pipe Po. As a result, as shown in Figure 10 (c), one radial groove S is formed on the inner circumference of the existing pipe Po.
図10(d)は溝付け工程の2段階目を示す。基部2には第二刃物4Bが一枚取付けられる(図12(b))。第二刃物4Bの向きは1段階目と管軸方向において逆にされる。基部2に第二刃物4Bが一枚取付けられた状態で、左ウインチ1Lを操作して本体部7を既設配管Poの図示右端から図示左端まで移動させる。この際、第二刃物4Bは1段階目で形成した溝Sに沿わせるようにする。このように加工手段4は、刃物を取り替えることで、既設配管の入口から出口へ基部の一端側が先頭で進入する往動の場合と、既設配管の出口から入口に基部の他端側が先頭で進入する復動の場合とで異なる加工をすることができるように構成されている。 Figure 10 (d) shows the second stage of the groove forming process. A second blade 4B is attached to the base 2 (Figure 12 (b)). The orientation of the second blade 4B is reversed in the pipe axial direction from the first stage. With one second blade 4B attached to the base 2, the left winch 1L is operated to move the main body 7 from the right end of the existing pipe Po to the left end of the existing pipe Po. At this time, the second blade 4B is made to align with the groove S formed in the first stage. In this way, the processing means 4 is configured to be able to perform different processing by replacing the blades in a forward movement in which one end of the base enters from the inlet to the outlet of the existing pipe at the front, and in a return movement in which the other end of the base enters from the outlet to the inlet of the existing pipe at the front.
つまり、この第二刃物4Bでは、これを利用することで、1段階目で形成した溝Sをガイドとして、図10(e)で示すように、1段階目より深い溝Sを形成させるものである。このようにして、既設配管Poの内周面に管軸方向に沿う溝Sを形成する。以上で、上記した(1)溝付け工程を終了する。 In other words, by using the second blade 4B, the groove S formed in the first stage is used as a guide to form a deeper groove S than in the first stage, as shown in FIG. 10(e). In this way, the groove S is formed along the pipe axis direction on the inner surface of the existing pipe Po. This completes the above-mentioned (1) groove forming process.
図11(a)(b)は、既設配管切断工程を示す。基部2には第三刃物4Cが一枚取り付けられる。第三刃物4Cの方が第二刃物4Bよりも径方向への刃41の突出量が大きい。この状態で右ウインチ1Rを操作し、第三刃物4Cの刃41を溝付工程の2段階目を経て深くなった溝Sに沿わせつつ、本体部7を既設配管Poの図示左端から図示右端まで移動させる。この結果、図11(b)に示すように径方向断面に、一箇所の分断部S1が形成される。 Figures 11(a) and 11(b) show the existing pipe cutting process. A third blade 4C is attached to the base 2. The blade 41 of the third blade 4C protrudes radially greater than that of the second blade 4B. In this state, the right winch 1R is operated to move the main body 7 from the left end to the right end of the existing pipe Po as shown in the figure, while aligning the blade 41 of the third blade 4C with the groove S that has become deeper through the second stage of the groove making process. As a result, a single disconnection portion S1 is formed in the radial cross section as shown in Figure 11(b).
次に、(3)拡径工程を説明する。拡径工程では、加工手段4を、第三刃物3Cから図12(d)で示す、拡径具44に変更する。既設配管切断工程で用いた加工手段4である第三刃物4Cを基部2から取り外し、2つの拡径部品44a、44bの板部8を小径部46が既設配管Poと向かい合いように貫通孔221に貫通孔221の一端側と他端側からそれぞれ挿入し、切り欠き471を通して、ねじ穴222に固定ねじを嵌め、取付孔81aとねじの先端とを係止することで、第三刃物4Cを拡径具44に容易に取替えられる。このとき、板部81の厚さは、貫通孔221の厚さの半分以下に設定されるため、2枚の板部81を貫通孔221に入れることができる。 Next, the (3) diameter expansion process will be described. In the diameter expansion process, the processing means 4 is changed from the third blade 3C to the diameter expansion tool 44 shown in FIG. 12(d). The third blade 4C, which is the processing means 4 used in the existing pipe cutting process, is removed from the base 2, and the plate parts 8 of the two diameter expansion parts 44a and 44b are inserted into the through hole 221 from one end side and the other end side of the through hole 221 so that the small diameter part 46 faces the existing pipe Po. The third blade 4C can be easily replaced with the diameter expansion tool 44 by fitting a fixing screw into the screw hole 222 through the notch 471 and engaging the tip of the screw with the mounting hole 81a. At this time, the thickness of the plate part 81 is set to half or less of the thickness of the through hole 221, so that two plate parts 81 can be inserted into the through hole 221.
図11(c)の状態においては、本体部7が図示右端にあるので、本体部7の一方側を図示右端(入口5)に配置することになる。このとき、本体部7に取り付けられた拡径具44の一方側は、既設配管Poの内径よりも小径に形成された小径部46であるから、左ワイヤ11を操作して、既設配管Poの内側に拡径具44を確り嵌合し、拡径具44を備える本体部7を図示右端から図示左端まで移動させる。そして、拡径具44の他方側は傾斜面48を介して既設配管Poの内径よりも大径に形成された外径面であるから、図11(d)で示すように、既設配管Poにおける径方向の一箇所において、分断部S1の間隔が広げられる。なお、この加工(変形)は、保護材Gの内部空間の範囲内で行われる。以上で、拡径工程を終了する。このように、加工手段4は、刃物を拡径具44に交換することで、既設配管の入口から出口へ基部の一端側が先頭で進入する往動の場合と、既設配管の出口から入口に基部の他端側が先頭で進入する復動の場合とで異なる加工をすることができる。 In the state of FIG. 11(c), the main body 7 is at the right end in the figure, so one side of the main body 7 is placed at the right end (inlet 5) in the figure. At this time, one side of the diameter expansion tool 44 attached to the main body 7 is a small diameter part 46 formed with a diameter smaller than the inner diameter of the existing pipe Po, so the left wire 11 is operated to firmly fit the diameter expansion tool 44 inside the existing pipe Po, and the main body 7 equipped with the diameter expansion tool 44 is moved from the right end to the left end in the figure. Then, since the other side of the diameter expansion tool 44 is an outer diameter surface formed with a diameter larger than the inner diameter of the existing pipe Po via the inclined surface 48, the interval of the divided part S1 is widened at one point in the radial direction of the existing pipe Po, as shown in FIG. 11(d). Note that this processing (deformation) is performed within the range of the internal space of the protective material G. This completes the diameter expansion process. In this way, by replacing the cutting tool with the diameter expansion tool 44, the processing means 4 can perform different processing in a forward movement in which one end of the base enters the existing pipe from the inlet to the outlet, and in a return movement in which the other end of the base enters the existing pipe from the outlet to the inlet.
次に、(4)新配管挿入工程を説明する。新配管挿入工程では、拡径された既設配管Poの内部に新配管Pnを挿入する。既設配管Poに沿って既設配管Poの一端側から他端側まで新配管Pnを挿入することで本工程は終了する。このとき、既設配管切断工程において既設配管Poが、径方向断面の一箇所の分断部S1で割られているから、既設配管Poの内部に新配管Pnが容易に通る。 Next, (4) the new pipe insertion process will be described. In the new pipe insertion process, the new pipe Pn is inserted into the enlarged existing pipe Po. This process ends when the new pipe Pn is inserted along the existing pipe Po from one end to the other end of the existing pipe Po. At this time, since the existing pipe Po was split at a dividing portion S1 at one location on the radial cross section in the existing pipe cutting process, the new pipe Pn can easily pass through the existing pipe Po.
本実施形態の配管更新工法に用いる配管加工装置では、加工手段4を刃41から拡径具44に変更され、拡径具44によって既設配管Poを内側から拡大されるから、既設配管Poに対して新配管Pnを通り易くすることができる。 In the pipe processing device used in the pipe renewal method of this embodiment, the processing means 4 is changed from a blade 41 to an expansion tool 44, and the existing pipe Po is expanded from the inside by the expansion tool 44, making it easier to pass the new pipe Pn through the existing pipe Po.
以上、本発明の実施形態について一例を挙げて説明したが、本発明は前記実施形態に限定されるものではなく、本発明の要旨を逸脱しない範囲内において種々の変更を加えることができる。 The above describes an embodiment of the present invention by way of example, but the present invention is not limited to the above embodiment, and various modifications can be made without departing from the spirit of the present invention.
例えば別の実施形態として、右ワイヤ11と左ワイヤ11の途中部分に加工手段4の異なる複数の本体部7、例えば第一刃物4Aを備える本体部7と、第二刃物4Bを備える本体部7と、を離間して設けておき、第一刃物4Aを既設配管Poの入口5側又は出口6側へ向かう方向の二方向で異なる加工(角度を変えてを溝を加工)するようにする。続いて第二刃物4Bを既設配管Poの入口5側又は出口6側へ向かう方向の二方向で異なる加工(角度を変えて溝を加工)するようにしてもよい。あるいは、第二刃物4Bを拡径具44に代えることもできる。このようにすることで、加工手段4の交換が、複数の本体部7の内の一つの加工手段4から、別な加工手段4に変更できる。そして、この構成によれば、一つの加工手段4から別な加工手段4に変更して、目的の加工に適した多様な形態変更をすることができる。 For example, in another embodiment, a plurality of body parts 7 with different processing means 4, for example, a body part 7 with a first blade 4A and a body part 7 with a second blade 4B, are provided at a distance from each other in the middle part of the right wire 11 and the left wire 11, and the first blade 4A is made to perform different processing (machining a groove at a different angle) in two directions toward the inlet 5 side or the outlet 6 side of the existing piping Po. Next, the second blade 4B may be made to perform different processing (machining a groove at a different angle) in two directions toward the inlet 5 side or the outlet 6 side of the existing piping Po. Alternatively, the second blade 4B may be replaced with a diameter expanding tool 44. In this way, the processing means 4 can be replaced from one processing means 4 of the plurality of body parts 7 to another processing means 4. And according to this configuration, by changing from one processing means 4 to another processing means 4, various shape changes suitable for the target processing can be made.
また、第一及び第二の実施形態において、加工手段4の変更は、刃41を交換することにより変更していたが、加工手段4の変更は、部品の交換のよる変更に限られない。例えば、刃が繰り出し式であり、突出量を変更することにより加工手段4を変更してもよいし、刃板8を固定する位置を変更可能にすることで、刃の突出量を変更可能としてもよい。いずれにしても、加工手段が既設配管に加工する加工部を含み、加工部が取替え可能、付替え可能、形態変更可能などによって加工の種類が選択可能であることにより、既設配管Poに対して異なる加工ができる。 In the first and second embodiments, the processing means 4 is changed by replacing the blade 41, but the processing means 4 is not limited to being changed by replacing parts. For example, the blade may be extendable, and the processing means 4 may be changed by changing the amount of protrusion, or the position at which the blade plate 8 is fixed may be made changeable, making it possible to change the amount of protrusion of the blade. In any case, the processing means includes a processing section that processes existing piping, and the type of processing can be selected by making the processing section replaceable, interchangeable, or changeable in shape, etc., so that different processing can be performed on the existing piping Po.
さらに、第一実施形態では、既設配管の切断片Psを引き抜いてから新配管Pnを挿入したが、これに限られない。例えば、既設配管分割工程で基部2に第三刃物4Cを二枚取付け、既設配管Poが周方向で四分割された状態から、保護材Gの内部と切断片Psとに、新配管Pnが沿うように、保護材Gの一端側から他端側に向けて新配管Pnを挿入してもよい。なお、既設配管Poの分割は二分割以上であればよく、上記のように四分割に限定されない。 Furthermore, in the first embodiment, the cut pieces Ps of the existing pipe are pulled out and then the new pipe Pn is inserted, but this is not limited to this. For example, in the existing pipe dividing process, two third blades 4C may be attached to the base 2, and the existing pipe Po may be divided into four in the circumferential direction. Then, the new pipe Pn may be inserted from one end side of the protective material G toward the other end side so that the new pipe Pn is aligned with the inside of the protective material G and the cut pieces Ps. Note that the division of the existing pipe Po may be divided into two or more parts, and is not limited to the above-mentioned four parts.
上記の工法の場合には、引抜工程を省いた分だけ新配管Pnの設置に手間がかからない。さらに、分割された既設配管Poが新配管Pnを取巻くため、新配管Pnが補強される利点もある。また、保護材Gが、柔軟な素材であれば、保護材Gの内径が変化可能となるため、新配管Pnの挿入による、切断片Psの径外方向に押し広げを保護材Gの内径が変化することで吸収することができるので挿入がスムーズになる。さらに、保護材Gが柔軟な素材であれば、保護材GがバンドIで締め付けられ縮径している部分を新配管Pnが通過する際にも、保護材Gの内径が変化することで、挿入抵抗を緩和することができる。さらに、既設配管Poが周方向に一定の間隔で分割されていれば、各切断片Psの形状は略同じ形状にできるため新配管Pnの挿入時の挿入抵抗を周方向で偏りなく均一なものとでき、新配管Pnをまっすぐ挿入しやすい。 In the case of the above construction method, the installation of the new pipe Pn is less laborious because the extraction process is omitted. Furthermore, since the divided existing pipe Po surrounds the new pipe Pn, there is also the advantage that the new pipe Pn is reinforced. In addition, if the protective material G is made of a flexible material, the inner diameter of the protective material G can be changed, so that the expansion of the cut pieces Ps in the radial outward direction due to the insertion of the new pipe Pn can be absorbed by changing the inner diameter of the protective material G, making the insertion smoother. Furthermore, if the protective material G is made of a flexible material, even when the new pipe Pn passes through a part where the protective material G is tightened by the band I and reduced in diameter, the inner diameter of the protective material G can be changed, so that the insertion resistance can be reduced. Furthermore, if the existing pipe Po is divided at regular intervals in the circumferential direction, the shape of each cut piece Ps can be made approximately the same shape, so that the insertion resistance when inserting the new pipe Pn can be made uniform without bias in the circumferential direction, making it easier to insert the new pipe Pn straight.
また、第一及び第二の実施形態において、本体部7とワイヤ11との接続は、螺合により行っていたが、これに限られない。例えば、図13に示すように、ワイヤ11と、2つのかしめリング18と、ワイヤ11が軸方向に貫通可能な穴24が形成された基部2を備える本体部7と、を備える構成としてもよい。このような構成によれば、ワイヤ11を基部2の穴24に通し、ワイヤ11において基部2の両端側に基部2をはさむようにかしめリング18を備えれば、ワイヤ11の基部2に近接した位置でかしめリング18をかしめることで、基部2のワイヤ11における長手方向への移動を規制することができ、基部2をワイヤ11に取り付けることができる。これにより、基部2は、その両端部からワイヤ11が延びるようにワイヤ11に接続される。 In the first and second embodiments, the main body 7 and the wire 11 are connected by screwing, but this is not limited thereto. For example, as shown in FIG. 13, the main body 7 may be configured to include the wire 11, two crimping rings 18, and the base 2 having a hole 24 through which the wire 11 can pass in the axial direction. With this configuration, the wire 11 is passed through the hole 24 of the base 2, and the crimping rings 18 are provided on both ends of the base 2 so as to sandwich the base 2. By crimping the crimping rings 18 at a position close to the base 2 of the wire 11, the movement of the base 2 in the longitudinal direction of the wire 11 can be restricted, and the base 2 can be attached to the wire 11. As a result, the base 2 is connected to the wire 11 so that the wire 11 extends from both ends of the base 2.
さらに、加工手段を基部に取り付ける方法は、ねじ穴とねじを使った固定に限られず、別の固定方法により加工手段を基部に取り付けてもよい。例えば、基部と加工手段が嵌合することで、加工手段を基部に取り付ける構成としてもよいし、基部にロック機構を備えることで、加工手段を取り付け可能としてもよい。 Furthermore, the method of attaching the processing means to the base is not limited to fixing using screw holes and screws, and the processing means may be attached to the base by another fixing method. For example, the processing means may be attached to the base by fitting the base and the processing means together, or the processing means may be attached by providing a locking mechanism to the base.
例えば、前記各実施形態において、保護材Gは断熱および保温の機能を有したものであっても、断熱および保温の機能を有しておらず単に配管(既設配管Poまたは新配管Pn)を覆うに過ぎないものであってもよい。また、保護材Gは配管の管軸方向の全部を覆っている必要はなく、管軸方向の一部が覆われていてもよい。また保護材Gでは、径方向断面が、周方向において分断部S1に対向する切れ目を有していてもよい。 For example, in each of the above embodiments, the protective material G may have the function of insulating and retaining heat, or it may not have the function of insulating and retaining heat and may simply cover the piping (the existing piping Po or the new piping Pn). In addition, the protective material G does not need to cover the entire piping in the axial direction, and may cover only a part of the piping in the axial direction. In addition, the protective material G may have a radial cross section that has a slit in the circumferential direction that faces the dividing portion S1.
また、前記各実施形態では、牽引部として左右ウインチ1R,1Lを使用したが、ウインチ(巻上機)に該当しない装置であっても、ワイヤ11や鎖等の索状材料を長手方向に引っ張ることのできる種々の装置を用いることができる。 In addition, in each of the above embodiments, the left and right winches 1R and 1L are used as the towing section, but various devices that can pull a cord-like material such as a wire 11 or a chain in the longitudinal direction can be used, even if they are not winches (hoists).
また、前記各実施形態では、基部2は略円柱状であったが、既設配管Po内での管軸方向の移動に支障がなく、既設配管Poを加工する加工手段4を支持することが可能であれば、他の形状であってよい。また、基部2に装着される刃41は、固定刃、回転刃のいずれであってもよい。また、刃41の形状も特に限定されない。前記実施形態では、管軸方向の片方向で切断できる刃41であったが、管軸方向の両方向で切断できる刃41であってもよい。 In addition, in each of the above embodiments, the base 2 is generally cylindrical, but may have other shapes as long as it is possible to support the processing means 4 for processing the existing piping Po without impeding movement in the axial direction within the existing piping Po. The blade 41 attached to the base 2 may be either a fixed blade or a rotary blade. The shape of the blade 41 is not particularly limited. In the above embodiments, the blade 41 is capable of cutting in one direction in the axial direction of the pipe, but the blade 41 may be capable of cutting in both directions in the axial direction of the pipe.
また、第一の実施形態において、溝付け工程および既設配管分割工程を経た既設配管Poの分割数は、前記実施形態の四分割に限られるものでなく、三分割以下、または五分割以上であってもよい。特に、既設配管Poの径および長さに応じ、引抜工程における切断片Psの保護材Gからの引き抜きやすさを考慮して、分割数を適宜決定してよい。また、切断軌跡を管軸方向に対して傾斜させることにより、螺旋状の切断片Psを形成してもよい。 In the first embodiment, the number of divisions of the existing pipe Po that has undergone the groove forming process and the existing pipe dividing process is not limited to four as in the above embodiment, but may be three or less, or five or more. In particular, the number of divisions may be appropriately determined depending on the diameter and length of the existing pipe Po, taking into consideration the ease of pulling out the cut pieces Ps from the protective material G in the pulling out process. In addition, the cutting trajectory may be inclined with respect to the pipe axis direction to form a spiral cut piece Ps.
また、第一の実施形態、第二の実施形態において、溝付け工程内の段階に関する、段階の数および加工内容は前記実施形態で示したもの(1段階目~4段階目)に限らず、種々に変更できる。さらに、溝付け工程で形成した溝Sに沿って既設配管を切断する場合について説明したが、これに限らず、溝Sには、第1刃物4A又は第2刃物4Bの刃41を嵌め込み、これをガイドとして、溝S以外の部分を刃41で切断するようにしてもよい。いずれにしても、溝Sをガイドにして既設配管Poを切断することにより、切断に失敗することなく、確実に分割することができる。 In the first and second embodiments, the number of stages and the processing contents in the groove forming process are not limited to those shown in the above embodiments (first to fourth stages), but can be changed in various ways. Furthermore, the case where the existing pipe is cut along the groove S formed in the groove forming process has been described, but this is not limited to this, and the blade 41 of the first blade 4A or the second blade 4B may be fitted into the groove S and used as a guide to cut the parts other than the groove S with the blade 41. In any case, by cutting the existing pipe Po using the groove S as a guide, it is possible to reliably divide it without cutting failure.
また、第二の実施形態において、拡径具44の切り欠き471は、拡径部品44a及び44bの双方に備えられたが、これに限らず、拡径部品の一方側にねじ穴222と軸方向及び周方向で位置が一致する個所に固定ねじを挿入可能な切り欠きが備えられてもよい。 In the second embodiment, the notch 471 of the expansion tool 44 is provided on both the expansion parts 44a and 44b, but this is not limited thereto. A notch into which a fixing screw can be inserted may be provided on one side of the expansion part at a position that coincides with the screw hole 222 in the axial and circumferential directions.
さらに、第二の実施形態において、拡径具44は、半割れ形状の拡径部品を合わせることで、一つの拡径具を構成することとしていたが、これに限らず、基部2に装着し、既設配管Poを拡径できる形状であれば、どのような構成であってもかまわない。 In addition, in the second embodiment, the expansion tool 44 is configured as a single expansion tool by combining two half-split expansion parts, but this is not limited to this, and any configuration is acceptable as long as it can be attached to the base 2 and has a shape that can expand the diameter of the existing piping Po.
また、実施形態において、加工手段として刃物及び拡径具を例示したが、これに限らず、基部に装着し、既設配管に対して加工可能な種々の手段が加工手段に含まれる。 In addition, in the embodiment, a blade and an expanding tool are exemplified as processing means, but the processing means are not limited to these, and various means that can be attached to the base and used to process existing piping are included in the processing means.
1L…左ウインチ、1R…右ウインチ、11…ワイヤ、12…接続部、13…接続部本体、14…ベアリング、15…軸部、16…ねじ部、161…操作部、162…雄ねじ部、18…かしめリング、2…基部、21…接続受部、22…加工手段装着部、221…貫通孔、222…ねじ穴、23…小径部、4…加工手段、4A…第一刃物、4B…第二刃物、4C…第三刃物、41…刃、42…刃先、421…先端、43…刃元、44…拡径具、44a…拡径部品、44b…拡径部品、45…拡径部、46…小径部、47…大径部、471…切り欠き、48…傾斜面、49…取付部、5…入口、6…出口、7…本体部、8…刃板・板部、8a…取付孔、81…板部、81a…取付孔、9…配管加工用具、B…スラブ、C…建築物、F…床材、G…保護材、Pn…新配管、Po…既設配管、Ps…切断片、S…溝、S1…分断部、Y…給湯配管 1L...left winch, 1R...right winch, 11...wire, 12...connection part, 13...connection part main body, 14...bearing, 15...shaft part, 16...screw part, 161...operation part, 162...male threaded part, 18...crimping ring, 2...base, 21...connection receiving part, 22...machining means mounting part, 221...through hole, 222...screw hole, 23...small diameter part, 4...machining means, 4A...first blade, 4B...second blade, 4C...third blade, 41...blade, 42...blade tip, 421...tip, 43 ...Blade base, 44...expansion tool, 44a...expansion part, 44b...expansion part, 45...expansion section, 46...small diameter section, 47...large diameter section, 471...notch, 48...inclined surface, 49...mounting section, 5...inlet, 6...outlet, 7...main body, 8...blade plate/plate section, 8a...mounting hole, 81...plate section, 81a...mounting hole, 9...piping processing tool, B...slab, C...building, F...floor material, G...protective material, Pn...new pipe, Po...existing pipe, Ps...cut piece, S...groove, S1...separation section, Y...hot water pipe
Claims (3)
前記本体部は既設配管の内径よりも外径が小さい基部と、前記基部から径外方向に突出し、既設配管に作用することで既設配管を加工する加工手段と、を備え、
前記接続部は、前記基部における径方向と直交する方向の両端から索状体が延びるように前記基部を索状体に接続するよう構成され、
前記加工手段は、前記既設配管の内部を移動しながら前記既設配管を加工するように構成されるとともに、前記基部の径方向と直交する方向の一端側から既設配管に進入して既設配管を加工する場合と前記基部の径方向と直交する方向の他端側から既設配管に進入して既設配管を加工する場合とで異なる加工ができるよう構成され、
前記加工手段が前記既設配管に対してする加工は、前記既設配管の内周面に管軸方向に沿う溝を形成する溝付け、前記既設配管を径方向及び管軸方向に切断する切断、又は、前記既設配管の内径を拡径する拡径、であり、
前記基部は、径方向と直交する軸方向の両端部に縮径された縮径部を備え、
前記加工手段は、前記溝付け又は前記切断をするための刃先を有する刃物と、前記拡径をするための拡径具と、を備え、
前記刃物は、前記基部に対して前記刃先が軸方向一端側を向くように取付け及び取外し可能であり、
前記拡径具は、前記既設配管の内径よりも外径が小さい小径部と、前記既設配管の内径よりも外径が大きい大径部と、を備え、前記基部に対して前記小径部が軸方向他端側を向くように取付け及び取外し可能に構成されている配管加工用具。 The device includes a main body portion having an inlet and an outlet formed at both ends thereof and capable of entering an existing pipe, and a connecting portion for connecting the main body portion to a cord-like body that guides the main body portion into the existing pipe,
The main body includes a base having an outer diameter smaller than an inner diameter of the existing piping, and a processing means protruding radially outward from the base and acting on the existing piping to process the existing piping,
The connecting portion is configured to connect the base portion to the cord-like body such that the cord-like body extends from both ends of the base portion in a direction perpendicular to a radial direction,
The processing means is configured to process the existing pipe while moving inside the existing pipe, and is configured to perform different processing when entering the existing pipe from one end side in a direction perpendicular to the radial direction of the base and processing the existing pipe from the other end side in a direction perpendicular to the radial direction of the base,
The processing performed by the processing means on the existing pipe is a grooving process for forming a groove along a pipe axis direction on an inner peripheral surface of the existing pipe, a cutting process for cutting the existing pipe in a radial direction and a pipe axis direction, or a diameter expanding process for expanding an inner diameter of the existing pipe,
The base portion includes a reduced diameter portion at both ends in an axial direction perpendicular to a radial direction,
The processing means includes a blade having a cutting edge for performing the grooving or the cutting, and a diameter expanding tool for performing the diameter expansion,
The blade can be attached and detached to the base such that the blade tip faces one end in the axial direction,
The expansion tool has a small diameter portion having an outer diameter smaller than the inner diameter of the existing piping, and a large diameter portion having an outer diameter larger than the inner diameter of the existing piping, and is a piping processing tool that is configured to be attached and detached to the base so that the small diameter portion faces toward the other axial end .
前記本体部は既設配管の内径よりも外径が小さい基部と、前記基部から径外方向に突出し、既設配管に作用することで既設配管を加工する加工手段と、を備え、
前記接続部は、前記基部における径方向と直交する方向の両端から索状体が延びるように前記基部を索状体に接続するよう構成され、
前記加工手段は、前記基部に対して着脱可能であるとともに、前記基部の径方向と直交する方向の一端側から既設配管に進入して既設配管を加工する場合と前記基部の径方向と直交する方向の他端側から既設配管に進入して既設配管を加工する場合とで異なる加工ができるよう構成され、
前記基部は、径方向と直交する軸方向の両端部に縮径された縮径部を備え、
前記加工手段は、前記既設配管の内周面に管軸方向に沿う溝を形成する溝付け、又は、前記既設配管を径方向及び管軸方向に切断する切断をするための刃先を有する刃物を備え、
前記刃物は、前記基部に対して前記刃先が軸方向一端側を向くように取付け及び取外し可能であり、かつ、前記基部に対して前記刃先が軸方向他端側を向くように取付け及び取外し可能に構成されている配管加工用具。 The device includes a main body portion having an inlet and an outlet formed at both ends thereof and capable of entering an existing pipe, and a connecting portion for connecting the main body portion to a cord-like body that guides the main body portion into the existing pipe,
The main body includes a base having an outer diameter smaller than an inner diameter of the existing piping, and a processing means protruding radially outward from the base and acting on the existing piping to process the existing piping,
The connecting portion is configured to connect the base portion to the cord-like body such that the cord-like body extends from both ends of the base portion in a direction perpendicular to a radial direction,
The processing means is detachable from the base and is configured to perform different processing when entering the existing piping from one end side in a direction perpendicular to the radial direction of the base to process the existing piping and when entering the existing piping from the other end side in a direction perpendicular to the radial direction of the base to process the existing piping ,
The base portion includes a reduced diameter portion at both ends in an axial direction perpendicular to a radial direction,
The processing means includes a blade having a cutting edge for forming a groove along a pipe axis direction on an inner peripheral surface of the existing pipe, or for cutting the existing pipe in a radial direction and a pipe axis direction,
The blade is a piping processing tool that is configured so that it can be attached and removed from the base with the cutting edge facing one axial end, and so that it can be attached and removed from the base with the cutting edge facing the other axial end .
前記本体部は既設配管の内径よりも外径が小さい基部と、前記基部から径外方向に突出し、既設配管に作用することで既設配管を加工する加工手段と、を備え、
前記基部は、前記加工手段を取り付け可能な加工手段装着部を備え、
前記加工手段装着部は、前記基部を貫通するように形成された貫通孔が形成されており、
前記加工手段は、前記貫通孔に挿入可能な挿入部と、該挿入部の両端に設けられた刃と、を有し、前記貫通孔に挿入した前記挿入部が前記加工手段装着部に固定されることで、前記加工手段装着部に装着され、
前記挿入部の両端に設けられた刃は、刃先が同じ方向を向くように設けられ、前記挿入部が前記加工手段装着部に固定された状態で前記基部に対して径外方に突出する配管加工用具。 The device includes a main body portion having an inlet and an outlet formed at both ends thereof and capable of entering an existing pipe, and a connecting portion for connecting the main body portion to a cord-like body that guides the main body portion into the existing pipe,
The main body includes a base having an outer diameter smaller than an inner diameter of the existing piping, and a processing means protruding radially outward from the base and acting on the existing piping to process the existing piping,
the base portion includes a processing means mounting portion to which the processing means can be attached,
The processing means mounting portion has a through hole formed so as to penetrate the base portion,
the processing means has an insertion portion that can be inserted into the through hole and blades provided on both ends of the insertion portion, and the insertion portion inserted into the through hole is fixed to the processing means mounting portion, whereby the processing means is mounted to the processing means mounting portion ;
The blades on both ends of the insertion portion are arranged so that the cutting edges face in the same direction, and the piping processing tool protrudes radially outward from the base when the insertion portion is fixed to the processing means mounting portion .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020022294A JP7486778B2 (en) | 2020-02-13 | 2020-02-13 | Piping processing tools |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020022294A JP7486778B2 (en) | 2020-02-13 | 2020-02-13 | Piping processing tools |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2021126728A JP2021126728A (en) | 2021-09-02 |
| JP7486778B2 true JP7486778B2 (en) | 2024-05-20 |
Family
ID=77487550
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020022294A Active JP7486778B2 (en) | 2020-02-13 | 2020-02-13 | Piping processing tools |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7486778B2 (en) |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20010018007A1 (en) | 1998-07-11 | 2001-08-30 | Franz-Josef Puttmann | Apparatus and method for the longitudinal splitting of pipes laid underground |
| JP3094269U (en) | 2002-11-25 | 2003-06-13 | 義明 工藤 | Wire for extracting buried lead pipe |
| JP2003340776A (en) | 2002-05-21 | 2003-12-02 | Kansai Kogyosho:Kk | Cutting apparatus for tube inner surface lining tube |
-
2020
- 2020-02-13 JP JP2020022294A patent/JP7486778B2/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20010018007A1 (en) | 1998-07-11 | 2001-08-30 | Franz-Josef Puttmann | Apparatus and method for the longitudinal splitting of pipes laid underground |
| JP2003340776A (en) | 2002-05-21 | 2003-12-02 | Kansai Kogyosho:Kk | Cutting apparatus for tube inner surface lining tube |
| JP3094269U (en) | 2002-11-25 | 2003-06-13 | 義明 工藤 | Wire for extracting buried lead pipe |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2021126728A (en) | 2021-09-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101653238B1 (en) | Pipe joint | |
| US6851726B2 (en) | Radial conduit coupling system and method | |
| EP2189699A1 (en) | Duplex pipe fitting, exclusive tool for the duplex pipe fitting, refrigeration system employing the duplex pipe fitting, and separation type air conditioner | |
| HU209196B (en) | Joint of tubes and pipe unions and method for forming the joint | |
| JP7486777B2 (en) | Pipe Processing Equipment | |
| JP7486778B2 (en) | Piping processing tools | |
| EP3647648B1 (en) | Pipeline reinstatement tool | |
| US8109694B2 (en) | Replacement of underground pipes | |
| US10851915B2 (en) | Pullhead device and method of use | |
| JP2007232286A (en) | Refrigerant piping method | |
| JP7429947B2 (en) | Piping renewal method | |
| JP7591823B2 (en) | Pipe cutting method | |
| JP2021095946A (en) | Pipe renewal construction method | |
| EP2149734A1 (en) | Bite type pipe coupling, refrigeration device, and water heating device | |
| JP2021085502A (en) | Piping renewal method | |
| JP7750504B2 (en) | Pipe cutting method, pipe cutting device | |
| JP7603321B2 (en) | Pipe removal method | |
| JP3373396B2 (en) | Propulsion method and pipe joint structure | |
| JP2019066020A (en) | Pipe joint structure | |
| JP2002320308A (en) | Rehabilitation method and rehabilitation pipe of existing pipeline | |
| JP7684685B2 (en) | pipe cutting tool | |
| JP5833080B2 (en) | Cutting method of cable housing tube | |
| RU2700570C9 (en) | Corrugated pipe for conduit (versions), coupling for connection of corrugated pipes and method of installation of conduit | |
| CN118933989A (en) | An integrated pipeline for underground gas extraction and a method of use thereof | |
| CN120269323A (en) | Dismounting device and method for cooler |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20221202 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20230726 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20230804 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20231003 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20240119 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20240318 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20240405 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20240426 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7486778 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |