JP7500209B2 - Project management system, project management method and project management program - Google Patents
[go: Go Back, main page]

JP7500209B2 - Project management system, project management method and project management program - Google Patents

Project management system, project management method and project management program Download PDF

Info

Publication number
JP7500209B2
JP7500209B2 JP2020018817A JP2020018817A JP7500209B2 JP 7500209 B2 JP7500209 B2 JP 7500209B2 JP 2020018817 A JP2020018817 A JP 2020018817A JP 2020018817 A JP2020018817 A JP 2020018817A JP 7500209 B2 JP7500209 B2 JP 7500209B2
Authority
JP
Japan
Prior art keywords
project
management
evaluation
items
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020018817A
Other languages
Japanese (ja)
Other versions
JP2021125027A (en
Inventor
正寿 道岡
正一 大木
浩一 吉見
正光 柳川
弘毅 河島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP2020018817A priority Critical patent/JP7500209B2/en
Publication of JP2021125027A publication Critical patent/JP2021125027A/en
Application granted granted Critical
Publication of JP7500209B2 publication Critical patent/JP7500209B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本開示は、プロジェクト管理システム及びそのプロジェクト管理方法並びにプロジェクト管理プログラムに関するものである。 This disclosure relates to a project management system, a project management method, and a project management program.

例えば火力発電プラントの建設等のプロジェクトでは、設計、調達、製造、建設など様々な工程があり、プロジェクト責任者や各工程における担当者により進捗等の管理がされている(例えば、特許文献1)。 For example, a project such as the construction of a thermal power plant involves various processes such as design, procurement, manufacturing, and construction, and progress is managed by the project manager and the person in charge of each process (for example, Patent Document 1).

特許文献2では、プロジェクトの構成情報を複数の担当部門で情報共有することが記載されている。 Patent document 2 describes how project configuration information is shared among multiple departments.

特開2003-67547号公報JP 2003-67547 A 特開2012-141788号公報JP 2012-141788 A

しかしながら、プロジェクトには複数の担当部門が関係する場合が多く存在し、プロジェクト全体の管理をするために担当部門毎に実行される工程、および複数の担当部門間にわたって実行される工程の進捗状況を容易に把握することが困難であった。 However, projects often involve multiple departments, making it difficult to easily grasp the progress of the processes being carried out by each department and across multiple departments in order to manage the entire project.

また、複数のプロジェクトにおける各責任者は、各作業工程および各担当部門の進捗状況を把握して評価し、適切に管理する必要があるが、各責任者の経験等によって統一的な評価が困難である。このため、全体管理のためにも管理・評価方法の統一化が求められている。 In addition, each person in charge of multiple projects needs to understand and evaluate the progress of each work process and each department in charge, and manage them appropriately, but it is difficult to standardize evaluations due to the experience of each person in charge. For this reason, there is a need to standardize management and evaluation methods for the sake of overall management.

本開示は、このような事情に鑑みてなされたものであって、プロジェクト管理をより効率的に行うことのできるプロジェクト管理システム及びそのプロジェクト管理方法並びにプロジェクト管理プログラムを提供することを目的とする。 The present disclosure has been made in light of these circumstances, and aims to provide a project management system, a project management method, and a project management program that enable more efficient project management.

本開示の第1態様は、プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける受付部と、前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う個別評価部と、前記個別評価に基づいて、前記プロジェクトの総合的な評価を行う総合評価部と、前記プロジェクト及び前記担当区分のそれぞれに対応して、評価結果を表示する表示部と、を備え、前記表示部は、前記プロジェクト及び該プロジェクトに関わる前記担当区分のそれぞれに対応した前記進捗状況の個別評価の評価結果を行列位置に表示する、プロジェクト管理システムである。 A first aspect of the present disclosure is a project management system comprising: a reception unit that receives input for management items that are pre-set commonly to projects; an individual evaluation unit that performs an individual evaluation of the progress for each of the responsibility categories related to the project based on the input information received for the management items; an overall evaluation unit that performs an overall evaluation of the project based on the individual evaluations; and a display unit that displays evaluation results corresponding to each of the project and the responsibility categories, wherein the display unit displays the evaluation results of the individual evaluation of the progress corresponding to the project and each of the responsibility categories related to the project in matrix positions .

本開示の第2態様は、プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける工程と、前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う工程と、前記個別評価に基づいて前記プロジェクトの総合的な評価を行う工程と、前記プロジェクト及び前記担当区分のそれぞれに対応して、評価結果を表示する工程と、を有し、前記表示する工程は、前記プロジェクト及び該プロジェクトに関わる前記担当区分のそれぞれに対応した前記進捗状況の個別評価の評価結果を行列位置に表示する、コンピュータが実行するプロジェクト管理方法である。 A second aspect of the present disclosure is a computer-implemented project management method comprising the steps of: accepting input for management items that are preset commonly to projects; making an individual evaluation of progress for each of the responsibility categories related to the project based on the input information accepted for the management items; making a comprehensive evaluation of the project based on the individual evaluations ; and displaying evaluation results corresponding to the project and each of the responsibility categories, wherein the displaying step displays the evaluation results of the individual evaluations of progress corresponding to the project and each of the responsibility categories related to the project in row and column positions .

本開示の第3態様は、プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける処理と、前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う処理と、前記個別評価に基づいて、前記プロジェクトの総合的な評価を行う処理と、前記プロジェクト及び前記担当区分のそれぞれに対応して、評価結果を表示する処理と、をコンピュータに実行させ、前記表示する処理は、前記プロジェクト及び該プロジェクトに関わる前記担当区分のそれぞれに対応した前記進捗状況の個別評価の評価結果を行列位置に表示する、プロジェクト管理プログラムである。 A third aspect of the present disclosure is a project management program that causes a computer to execute the following processes: accepting input for management items that are preset commonly to projects; making an individual evaluation of the progress for each of the responsibility categories related to the project based on the input information accepted for the management items; making a comprehensive evaluation of the project based on the individual evaluations; and displaying evaluation results corresponding to the project and each of the responsibility categories, wherein the displaying process displays the evaluation results of the individual evaluations of the progress corresponding to the project and each of the responsibility categories related to the project in row and column positions .

本開示によれば、プロジェクト管理をより効率的に行うことができるという効果を奏する。 This disclosure has the effect of enabling more efficient project management.

本開示の一実施形態に係るプロジェクト管理システムの概略構成を示した図である。1 is a diagram illustrating a schematic configuration of a project management system according to an embodiment of the present disclosure. 本開示の一実施形態に係るプロジェクト管理システムのハードウェア構成の一例を示した図である。FIG. 1 is a diagram illustrating an example of a hardware configuration of a project management system according to an embodiment of the present disclosure. 本開示の一実施形態に係るプロジェクト管理システムが備える機能を示した機能ブロック図である。FIG. 1 is a functional block diagram illustrating functions of a project management system according to an embodiment of the present disclosure. 本開示の一実施形態に係るメニュー画面の一例を示す図である。FIG. 13 is a diagram illustrating an example of a menu screen according to an embodiment of the present disclosure. 本開示の一実施形態に係るプロジェクト管理画面の一例を示す図である。FIG. 13 is a diagram illustrating an example of a project management screen according to an embodiment of the present disclosure. 本開示の一実施形態に係るプロジェクト通信簿の一例を示す図である。FIG. 13 is a diagram illustrating an example of a project report card according to an embodiment of the present disclosure. 本開示の一実施形態に係る評価処理のフローチャートを示した図である。FIG. 11 is a flowchart showing an evaluation process according to an embodiment of the present disclosure.

以下に、本開示に係るプロジェクト管理システム及びそのプロジェクト管理方法並びにプロジェクト管理プログラムの一実施形態について、図面を参照して説明する。 Below, an embodiment of the project management system, project management method, and project management program according to the present disclosure will be described with reference to the drawings.

本実施形態でのプロジェクトに対して、プロジェクト管理システム1は、プロジェクトの管理のための評価や情報管理等を行う。プロジェクト管理システム1は、図1に示すように、通信網8を介して、例えばPC等の各情報処理装置9と接続されている。情報処理装置9は、例えば、プロジェクト責任者や各工程の担当者などのプロジェクトメンバー等によって使用される。接続される情報処理装置9の数は、図1に限定されない。そして、情報処理装置9に対してプロジェクトの管理に必要となる後述するメニュー画面等を表示したり、情報処理装置9から各種情報を受け付ける。プロジェクト管理システム1は情報処理装置9から受け付けた情報を統合管理する。 For the project in this embodiment, the project management system 1 performs evaluation and information management for project management. As shown in FIG. 1, the project management system 1 is connected to each information processing device 9, such as a PC, via a communication network 8. The information processing device 9 is used by project members such as the project manager and the person in charge of each process. The number of connected information processing devices 9 is not limited to FIG. 1. Then, the project management system 1 displays menu screens, which will be described later, that are necessary for project management on the information processing device 9, and receives various information from the information processing device 9. The project management system 1 manages the information received from the information processing device 9 in an integrated manner.

図2は、本実施形態に係るプロジェクト管理システム1のハードウェア構成の一例を示した図である。
図2に示すように、プロジェクト管理システム1は、コンピュータシステム(計算機システム)であり、例えば、CPU11と、CPU11が実行するプログラム等を記憶するためのROM(Read Only Memory)12と、各プログラム実行時のワーク領域として機能するRAM(Random Access Memory)13と、大容量記憶装置としてのハードディスクドライブ(HDD)14と、ネットワーク等に接続するための通信部15とを備えている。また、大容量記憶装置としては、ソリッドステートドライブ(SSD)を用いることとしてもよい。これら各部は、バス18を介して接続されている。
FIG. 2 is a diagram showing an example of a hardware configuration of the project management system 1 according to the present embodiment.
2, the project management system 1 is a computer system including, for example, a CPU 11, a ROM (Read Only Memory) 12 for storing programs and the like executed by the CPU 11, a RAM (Random Access Memory) 13 that functions as a work area when each program is executed, a hard disk drive (HDD) 14 as a large-capacity storage device, and a communication unit 15 for connecting to a network or the like. A solid state drive (SSD) may also be used as the large-capacity storage device. These units are connected via a bus 18.

また、プロジェクト管理システム1は、図示しないキーボードやマウス等からなる入力部や、データを表示する液晶表示装置等からなる表示手段などを備えていてもよい。 The project management system 1 may also include an input section consisting of a keyboard, mouse, etc. (not shown), and a display means consisting of a liquid crystal display device or the like for displaying data.

なお、CPU11が実行するプログラム等を記憶するための記憶媒体は、ROM12に限られない。例えば、磁気ディスク、光磁気ディスク、半導体メモリ等の他の補助記憶装置であってもよい。 The storage medium for storing the programs executed by the CPU 11 is not limited to the ROM 12. For example, it may be other auxiliary storage devices such as a magnetic disk, a magneto-optical disk, or a semiconductor memory.

後述の各種機能を実現するための一連の処理の過程は、プログラムの形式でハードディスクドライブ14等に記録されており、このプログラムをCPU11がRAM13等に読み出して、情報の加工・演算処理を実行することにより、後述の各種機能が実現される。なお、プログラムは、ROM12やその他の記憶媒体に予めインストールしておく形態や、コンピュータ読み取り可能な記憶媒体に記憶された状態で提供される形態、有線又は無線による通信手段を介して配信される形態等が適用されてもよい。コンピュータ読み取り可能な記憶媒体とは、磁気ディスク、光磁気ディスク、CD-ROM、DVD-ROM、半導体メモリ等である。 A series of processing steps for realizing the various functions described below are recorded in the form of a program on the hard disk drive 14, etc., and the CPU 11 reads this program into the RAM 13, etc., and executes information processing and arithmetic processing to realize the various functions described below. The program may be pre-installed in the ROM 12 or other storage medium, provided in a state stored in a computer-readable storage medium, or distributed via wired or wireless communication means. Computer-readable storage media include magnetic disks, magneto-optical disks, CD-ROMs, DVD-ROMs, semiconductor memories, etc.

図3は、プロジェクト管理システム1が備える機能を示した機能ブロック図である。図3に示すように、本実施形態に係るプロジェクト管理システム1は、表示部2と、受付部3と、区分け部4と、個別評価部5と、総合評価部6とを主な構成として備えている。 Figure 3 is a functional block diagram showing the functions of the project management system 1. As shown in Figure 3, the project management system 1 according to this embodiment mainly comprises a display unit 2, a reception unit 3, a classification unit 4, an individual evaluation unit 5, and a comprehensive evaluation unit 6.

(プロジェクト管理システム1の表示部2)
図3に示した、表示部2は、表示手段を制御して表示制御を行う。例えば、情報処理装置9等における表示を制御する。
(Display unit 2 of project management system 1)
3, the display unit 2 controls display means to perform display control, for example, controlling display in an information processing device 9 or the like.

具体的には、表示部2は、図4に示すように、全体管理画面(以下、「メニュー画面」という)を表示する。メニュー画面では、各プロジェクトの管理に関する各種メニュー(ボタン等)を表示する。本実施形態では、各プロジェクトの一例として、発電所の建設に係るプロジェクトとする場合について説明する。なお、プロジェクトの種類については、発電所の建設に限定されない。 Specifically, the display unit 2 displays an overall management screen (hereinafter referred to as the "menu screen") as shown in FIG. 4. The menu screen displays various menus (buttons, etc.) related to the management of each project. In this embodiment, a project related to the construction of a power plant will be described as an example of each project. Note that the type of project is not limited to the construction of a power plant.

図4に示すようにメニュー画面には、複数のプロジェクトに対して、例えばグルーピングするテーマとして“地域”が選定されており、複数のプロジェクトが地域ごとにグルーピングされて表示されている。具体的には、建設現地の所在地が属する地域ごとにグルーピングが行われる。例えば、日本国内において進行している各プロジェクトが、日本国内に対応してグルーピングされている。図4の例では、各地域を、日本国内、アジア、ヨーロッパ、北米、中南米、アフリカとしている。そして、図4では、例えば日本国内において、進行しているプロジェクトであるA発電所からL発電所が表示される。グルーピングする地域の設定やグルーピングするテーマについては、図4の例に限定されない。 As shown in FIG. 4, on the menu screen, for example, "region" is selected as a grouping theme for multiple projects, and multiple projects are displayed grouped by region. Specifically, grouping is performed by the region to which the construction site belongs. For example, each project underway in Japan is grouped corresponding to Japan. In the example of FIG. 4, the regions are Japan, Asia, Europe, North America, Central and South America, and Africa. And in FIG. 4, for example, Power Plant A to Power Plant L, which are projects underway in Japan, are displayed. The setting of the regions to be grouped and the themes to be grouped are not limited to the example of FIG. 4.

表示部2は、表示されるプロジェクトが指定されると、指定されたプロジェクトに対応する管理画面を、例えば図5に示すように表示する。例えば、A発電所が指定された場合には、A発電所のプロジェクトに関する管理画面を表示する。図5については後述する。 When a project to be displayed is specified, the display unit 2 displays a management screen corresponding to the specified project, for example as shown in FIG. 5. For example, when power plant A is specified, a management screen relating to the project of power plant A is displayed. FIG. 5 will be described later.

また、メニュー画面では、拠点工場ごとに表示画面を切り替えることとしてもよい。本実施形態では、工場(1)、工場(2)、工場(3)を切り替え可能として表示しており、図4の例は工場(1)が選択されてメニュー画面を表示いる場合を示している。拠点工場とは、各プロジェクトに対して、設計拠点が存在する工場や主要な機器等を製造する工場などである。 The menu screen may also be configured to switch display screens for each base factory. In this embodiment, Factory (1), Factory (2), and Factory (3) are displayed as switchable options, and the example in FIG. 4 shows a case where Factory (1) is selected and the menu screen is displayed. A base factory is a factory where a design base is located for each project, or a factory where major equipment, etc. are manufactured.

メニュー画面には、システムに対する変更履歴や更新履歴を下部領域に掲示することで、メニュー画面において更新情報の有無を確認可能とすることもできる。また、関連システムや関連ツール、関連リンク等を表示することとしてもよい。使用者が頻繁に利用するプロジェクトへとリンク可能な表示ボタンを特定位置に配置させて作業性を向上させてもよい。 The menu screen can also display the change history and update history for the system in the lower area, making it possible to check whether there is any update information on the menu screen. Related systems, related tools, related links, etc. may also be displayed. Display buttons that can link to projects that the user frequently uses may be placed in specific positions to improve operability.

また、後述する各プロジェクトの評価結果を表示するプロジェクト通信簿の表示ボタンも表示される。プロジェクト通信簿については図6を用いて後述する。 A button to display the project report card, which shows the evaluation results of each project (described later), is also displayed. The project report card will be described later using Figure 6.

そして、表示部2は、プロジェクトのそれぞれに対応した管理画面(プロジェクト管理画面)を表示する。図5は、プロジェクト管理画面の一例を示す図である。図5は、図4のメニュー画面において、A発電所が指定された場合を例として、A発電所に関するプロジェクト管理画面を示している。 Then, the display unit 2 displays a management screen (project management screen) corresponding to each project. Figure 5 is a diagram showing an example of a project management screen. Figure 5 shows a project management screen related to power plant A, taking as an example a case where power plant A is specified on the menu screen of Figure 4.

プロジェクト管理画面では、ジャンルで分類した機能ボタンが整理されており、例えば、各プロジェクトに共通するボタン(共通ボタン)、調達に関するボタン(調達ボタン)、設計に関するボタン(設計ボタン)、及び施工(建設)に関するボタン(建設ボタン)など、それぞれのジャンルが区別して表示されている。各ジャンルは、視認性を向上させるためにボタンを色分けすることとしてもよい。 On the project management screen, function buttons are organized by category, and each category is displayed separately, for example, buttons common to all projects (common buttons), buttons related to procurement (procurement buttons), buttons related to design (design buttons), and buttons related to construction (construction buttons). Buttons for each category may be color-coded to improve visibility.

各ジャンルには、関係する各機能ボタンが設けられている。各機能ボタンは、主要機能と付随機能とを区別して表示することとしてもよい。図5では、例えば、主要機能のボタンを四角形として、付随機能のボタンを角なし四角形として表示する。このように重要度によってボタンの表示形式を区別することとして視認性を向上させてもよい。各ジャンルの機能ボタンによって各種入力が受け付けられる。入力は後述する受付部3において受け付けされる。 Each genre is provided with a function button associated with it. The function buttons may be displayed to distinguish between main functions and auxiliary functions. In FIG. 5, for example, the buttons for main functions are displayed as squares, and the buttons for auxiliary functions are displayed as squares without corners. In this way, the display format of the buttons may be differentiated according to importance to improve visibility. Various inputs are accepted by the function buttons for each genre. The inputs are accepted by the acceptance unit 3, which will be described later.

図5に示すように、共通のジャンルには、プロジェクト情報管理MI1、及び営業文書管理MI3に関するボタンがそれぞれ表示される。なお、その他管理項目のボタンも複数が表示されていて、各々が具体的な管理名称で表示されることとしてもよい。 As shown in FIG. 5, buttons related to project information management MI1 and sales document management MI3 are displayed in the common genre. Note that multiple buttons for other management items may also be displayed, and each may be displayed with a specific management name.

本実施形態では、調達のジャンルには、例えば、購入品スケジュール管理MI5に関するボタンが表示される。なお、その他管理項目のボタンも複数が表示されていて、各々が具体的な管理名称で表示されることとしてもよい。 In this embodiment, for example, a button related to purchase schedule management MI5 is displayed in the procurement category. Note that multiple buttons for other management items may also be displayed, each of which may be displayed with a specific management name.

設計のジャンルには、例えば、設計懸案管理MI2、出図管理MI4、設計時間管理MI6、及び設計週報管理MI7に関するボタンがそれぞれ表示される。なお、その他管理項目のボタンも複数が表示されていて、各々が具体的な管理名称で表示されることとしてもよい。 In the design category, for example, buttons related to design pending management MI2, drawing release management MI4, design time management MI6, and design weekly report management MI7 are displayed. Note that multiple buttons for other management items may also be displayed, and each may be displayed with a specific management name.

建設のジャンルには、例えば、出張者派遣管理MI8、現地懸案管理MI9、及び現地週報管理MI10に関するボタンがそれぞれ表示される。なお、その他管理項目のボタンも複数が表示されていて、各々が具体的な管理名称で表示されることとしてもよい。 In the construction category, for example, buttons related to business trip dispatch management MI8, local issue management MI9, and local weekly report management MI10 are displayed. Note that multiple buttons for other management items may also be displayed, and each may be displayed with a specific management name.

また、プロジェクト管理画面では、上部右側領域に例えば、問合せ先ボタンが配置されており、各機器や各工程に関する問合せ先などを容易に確認できるようになっている。右側領域には、例えば、レポート表示用ボタンが配置されており、各種進捗レポートを確認できるようになっている。進捗レポートは、プロジェクトの進捗管理として重要となる出図進捗や設計費コストなどを対象とし、その他必要に応じて、購入品の調達進捗や出張費進捗など表示できるようにしてもよい。下部右側領域には、現地工事進捗写真やプロジェクト責任者の顔写真を掲載して、工事進捗やプロジェクト対象を一目で認識できるようにしてもよい。その他には、プロジェクト個別項目や、関連システム、関連ツール、関連リンクに関する表示がされてもよい。 In addition, on the project management screen, for example, a contact button is located in the upper right area, making it possible to easily check the contact information for each device and each process. For example, a report display button is located in the right area, making it possible to check various progress reports. The progress report covers the progress of drawing releases and design costs, which are important for project progress management, and may also display the progress of procurement of purchased items and progress of travel expenses, as necessary. The lower right area may display photos of the on-site construction progress and a photo of the project manager, making it possible to recognize the construction progress and project targets at a glance. In addition, individual project items, related systems, related tools, and related links may be displayed.

そして、表示部2は、プロジェクト及び担当区分のそれぞれに対応して、評価結果(プロジェクト通信簿)を表示する。図6は、プロジェクト通信簿の一例を示す図である。図6は、図4のメニュー画面において、プロジェクト通信簿のボタンが指定された場合に表示される。 Then, the display unit 2 displays the evaluation results (project report card) corresponding to each project and each division of responsibility. FIG. 6 is a diagram showing an example of a project report card. FIG. 6 is displayed when the project report card button is selected on the menu screen of FIG. 4.

プロジェクト通信簿では、各プロジェクトのそれぞれに対して、進捗状況が表示されている。すなわち、プロジェクト通信簿によって各プロジェクトの進捗状況の見える化がされている。 The project report card shows the progress of each project. In other words, the project report card makes it possible to visualize the progress of each project.

図6の例では、各プロジェクト(各発電所)を縦軸方向に示している。そして、プロジェクトに対応して関係する担当区分を横軸方向に表示している。担当区分とは、プロジェクトにおける各工程の処理・作業等をそれぞれ担当する区分である。本実施形態での例では担当区分を部署(課)として説明する。なお、担当区分としては部署に限定されない。図6のプロジェクト通信簿では、各行がプロジェクトに対応しており、各列が各部署(課)に対応している。 In the example of Figure 6, each project (each power plant) is shown on the vertical axis. The division of responsibility associated with each project is displayed on the horizontal axis. A division of responsibility is a division in charge of the processing and work of each step in a project. In the example of this embodiment, the division of responsibility is explained as a department (section). Note that the division of responsibility is not limited to a department. In the project report card of Figure 6, each row corresponds to a project, and each column corresponds to a department (section).

そして、各行列位置には、プロジェクト及び部署のそれぞれに対応して、進捗状況(遅延状況)の評価結果が表示されている。図6の例では、評価を5段階評価とし、天気マークとして、一見でプロジェクトの進捗状態を確認できるようにしている。すなわち、1点を雷マーク、2点を雨マーク、3点を傘マーク(小雨マーク)、4点を曇りマーク、5点を晴れマークとして、遅延しているほど点数が低いマークが表示される。また、プロジェクトに対して部署が関係しない場合には、マークを表示せず、横線(-)を表示している。各部署に対応する評価は個別評価として、後述する個別評価部5において評価が行われる。これにより、各プロジェクト及び各部署の進捗状況の評価への表示は、数値の点数ではなくマークを用いることで視認性を向上させている。 At each row and column position, the evaluation result of the progress (delay) is displayed for each project and department. In the example of FIG. 6, the evaluation is on a 5-point scale, and the progress of the project is checked at a glance using weather marks. That is, 1 point is a lightning mark, 2 points is a rain mark, 3 points is an umbrella mark (light rain mark), 4 points is cloudy mark, and 5 points is sunny mark, and the more delayed the mark, the lower the score is displayed. Also, if a department is not involved in a project, no mark is displayed, and a horizontal line (-) is displayed. The evaluation corresponding to each department is performed as an individual evaluation in the individual evaluation unit 5 described later. In this way, the evaluation of the progress of each project and each department is displayed using marks instead of numerical scores, improving visibility.

プロジェクト通信簿では、各プロジェクトに対する総合評価についてもマークで表示されている。総合評価は後述する総合評価部6において評価が行われる。なお、図6に示す例のように、各プロジェクトを示している縦軸方向の一項目に各部署に対しても総合評価(課総合)が表示されることとしてもよい。 In the project report card, the overall evaluation for each project is also displayed with a mark. The overall evaluation is performed in the overall evaluation section 6, which will be described later. As shown in the example in Figure 6, an overall evaluation (section overall) for each department may also be displayed in one item along the vertical axis showing each project.

図6のようにプロジェクト通信簿において各プロジェクト及び各部署に対して一覧的に進捗を確認することができるため、さらには進捗状況を視認性の良いマークで確認することができるため、各プロジェクトの統合的な管理に役立てることが可能となる。 As shown in Figure 6, the project report card allows you to check the progress of each project and each department at a glance, and you can also check the progress status with easily visible marks, making it useful for integrated management of each project.

(プロジェクト管理システム1の受付部3)
図3に示した、受付部3は、プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける。受付部3は、図5に示すプロジェクト管理画面を用いて各ジャンルの機能ボタンによって各種入力が受け付けられてもよい。表示部2によって表示される各画面から入力を受け付ける。このため、例えば各情報処理装置9を用いて入力が行われる。特に、それぞれのプロジェクトに対応した管理画面である図5のようなプロジェクト管理画面において、プロジェクトに対応する情報(管理項目に対する情報)を受け付ける。図5に一例を示すプロジェクト管理画面から、プロジェクト情報管理MI1、設計懸案管理MI2、営業文書管理MI3、出図管理MI4、購入品スケジュール管理MI5などに各管理項目に関するボタンから、各ジャンルに区分けされた各種関連する情報を確認できるとともに、各種関連する入力が可能である。受け付けた情報は、データベースとして格納される。格納された情報は、表示部2によって各画面に情報が表示されたり検索されたりする。
(Reception section 3 of project management system 1)
The reception unit 3 shown in FIG. 3 receives inputs for management items that are set in advance and commonly used for projects. The reception unit 3 may receive various inputs by function buttons for each category using a project management screen shown in FIG. 5. The reception unit 3 receives inputs from each screen displayed by the display unit 2. For this reason, inputs are made using, for example, each information processing device 9. In particular, information corresponding to the project (information for management items) is received in a project management screen such as FIG. 5, which is a management screen corresponding to each project. From the project management screen shown as an example in FIG. 5, various related information classified into each category can be confirmed from buttons related to each management item such as project information management MI1, design pending management MI2, business document management MI3, drawing release management MI4, and purchase schedule management MI5, and various related inputs can be made. The received information is stored as a database. The stored information is displayed on each screen or searched by the display unit 2.

管理項目とは、プロジェクトの進捗管理で重要となる項目であり、予め設定されている。管理項目は、各プロジェクトに対して統一的に設定されている。すなわち、複数のプロジェクトを同時に推進するケースであっても、プロジェクト責任者やプロジェクトメンバーの経験に左右されず、各プロジェクトの運営方法を統一化し、管理を行うことができる。これにより、各プロジェクトで一定水準以上の成功を収めることが期待できる。 Management items are important items for project progress management, and are set in advance. Management items are set uniformly for each project. In other words, even in cases where multiple projects are being promoted simultaneously, the management methods for each project can be standardized and managed regardless of the experience of the project manager or project members. This makes it possible to expect a certain level of success for each project.

管理項目は、プロジェクトに関する基本情報に関する項目、設計段階において発生した懸案事項に関する項目、社外文書に関する項目、図面の作成状況に関する項目、及び購入品の調達に関する項目である。なお、各項目には、後述するように進捗状況(遅延状況)を把握するための情報が含まれている。上記のように管理項目を設定することによって、QCD(Q:品質管理、C:原価管理、D:スケジュール管理)をより効率的に達成することが可能となる。 The management items are items related to basic information about the project, items related to issues that arose during the design stage, items related to external documents, items related to the status of drawing creation, and items related to the procurement of purchased items. Each item contains information for understanding the progress (delay status), as described below. By setting management items as described above, it is possible to achieve QCD (Q: quality control, C: cost control, D: schedule control) more efficiently.

プロジェクトに関する基本情報に関する項目とは、プロジェクトに関する基本情報として予め設定された各カテゴリに係る項目である(プロジェクト情報管理MI1)。カテゴリは、例えば、プロジェクト概要、体制表、連絡先、日程、議事録、出張情報、契約前後各種情報、海外調達(少なくともいずれか1つ)などである。なお、プロジェクト情報管理MI1には、各種基本情報が含まれており、進捗評価において適宜用いられる。カテゴリは、例えば、プラント管理の従来の慣習に則して設定される。各カテゴリには、情報が入力されたり、資料の格納がされる。プロジェクトの様々な情報を一元管理することで、プロジェクト関係者間での情報の共有化及び視える化を実現し、効率的なプロジェクト遂行を目的とする。また、情報の改訂が刻々と行われるので、登録・更新した情報を関係先へ配布することとしてもよい。情報周知及び最新情報の共有化を図り、旧情報を使用することによって発生する問題を防止できる。 The items related to basic information about the project are items related to each category that is preset as basic information about the project (Project Information Management MI1). The categories are, for example, project overview, organizational chart, contact information, schedule, minutes, business trip information, various information before and after the contract, overseas procurement (at least one of them), etc. Note that Project Information Management MI1 includes various basic information and is used appropriately in progress evaluation. The categories are set, for example, in accordance with the conventional practices of plant management. Information is entered and documents are stored in each category. By centrally managing various project information, the sharing and visualization of information among project stakeholders is realized, and the aim is to carry out the project efficiently. In addition, since information is revised every moment, registered and updated information may be distributed to related parties. By promoting information dissemination and sharing of the latest information, problems caused by using old information can be prevented.

設計段階において発生した懸案事項に関する項目とは、建設工事等の実作業前における設計(計画)段階において発生した課題(解決を要するが解決されていない課題)を管理するための事項である(設計懸案管理MI2)。設計懸案管理MI2としては、例えば、懸案名称、具体的な懸案内容、期限情報、担当区分情報、懸案が顕在化した場合の影響度情報(追加発生コスト、性能や工程への影響度など)、処理の進捗状況、及び完了/未完了のステータス情報などが入力される。すなわち、設計懸案管理MI2には、進捗評価のための情報として、懸案事項の期限情報と処理状況とが含まれる。プロジェクトの設計段階で発生した懸案事項を登録していくことにより、プロジェクトの懸案情報を共有化し、対策等が可能となる。また、登録された情報を蓄積し知見として活用することにより、類似プロジェクト(特に後続プロジェクト)へ懸案事項への予防対策の水平展開を図ることとしてもよい。 Items related to pending issues that have arisen in the design phase are items for managing issues (issues that need to be resolved but have not been resolved) that have arisen in the design (planning) phase before actual work such as construction work (design pending issue management MI2). For example, pending issue names, specific pending issue content, deadline information, responsibility category information, impact information when pending issues become apparent (additional costs incurred, impact on performance and process, etc.), progress of processing, and completed/incomplete status information are input as design pending issue management MI2. In other words, pending issue management MI2 includes deadline information and processing status of pending issues as information for progress evaluation. By registering pending issues that have arisen in the design phase of a project, it becomes possible to share pending issue information in the project and take measures. In addition, by accumulating registered information and utilizing it as knowledge, it is also possible to horizontally deploy preventive measures against pending issues in similar projects (especially subsequent projects).

社外文書に関する項目とは、客先や共販先等の社外関係各所との文書(例えば、技術や商務に関する社外文書)のやり取り(受発信)に関する項目である(営業文書管理MI3)。コレポン(コレスポンデンス)情報とも呼ばれる。営業文書管理MI3としては、やり取りした文書が格納される。また、営業文書管理MI3には、進捗評価のための情報として、発信または返信(質問事項への回答など)を要する文書に関する、少なくとも期限情報、処理状況及び担当区分とが含まれる。社外文書の検索が行なえ、最新の情報を用いた各プロジェクトの管理ができる。 Items related to external documents are items related to the exchange (sending and receiving) of documents (for example, external documents related to technology or business) with various external parties such as customers and joint sales partners (Sales Document Management MI3). They are also called correspondence information. Sales Document Management MI3 stores exchanged documents. In addition, Sales Document Management MI3 contains at least deadline information, processing status, and responsibility category for documents that require sending or replying (such as responses to questions) as information for progress evaluation. External documents can be searched, and each project can be managed using the latest information.

図面の作成状況に関する項目とは、プロジェクトにおいて作成を要する設計図書(図面)作成状況に関する項目である(出図管理MI4)。出図管理MI4には、進捗評価のための情報として、図面の作成や関係先配布(出図)に関する期限情報と処理状況とが含まれる。プロジェクトでは、多くの図面が作成・出図されるため、各種の図面等の出図進捗を、担当区分(プロジェクト関係先の各部署)相互で状況をフォローすることにより、出図遅延発生の抑制と最新情報の共有化が可能となる。プロジェクトで管理すべき図面の初回出図から(改訂図の出図を経て)完成図の出図までの出図状況を見える化して、最新の改訂図を参照可能とする。また、出図に際しての社内関係者への承認及び客先への電子メール等での発信機能を設けることとしてもよい。 Items related to the drawing creation status are items related to the creation status of design documents (drawings) that need to be created in the project (Drawing Management MI4). Drawing Management MI4 includes deadline information and processing status regarding drawing creation and distribution to related parties (drawing release) as information for progress evaluation. Since many drawings are created and released in a project, by following up on the status of the release progress of various drawings, etc. among the responsible divisions (each project related department), it is possible to prevent delays in drawing release and share the latest information. The drawing status from the first release of drawings to be managed in the project (through the release of revised drawings) to the release of completed drawings is made visible, and the latest revised drawings can be referenced. In addition, a function for approval of internal related parties and sending to customers by e-mail, etc. when releasing a drawing may be provided.

購入品の調達に関する項目とは、プロジェクト(例えば発電プラントの建設)に必要な各購入品の調達状況に関する項目である(購入品スケジュール管理MI5)。購入品スケジュール管理MI5には、進捗評価のための情報として、購入品の発注期限や納入期限、購入仕様書発行期限等の期限情報と処理状況とが含まれる。購入品の納入遅れはプロジェクト全体のスケジュールに影響を与える可能性があるため、情報を共有することで購入品の納入遅れ等に対する早期対策が可能となる。 Items related to the procurement of purchased items are items related to the procurement status of each purchased item required for a project (for example, the construction of a power plant) (Purchased Item Schedule Management MI5). Purchased Item Schedule Management MI5 includes deadline information such as the order deadline for purchased items, delivery deadline, and deadline for issuing purchase specifications, as well as the processing status, as information for progress evaluation. Since delays in the delivery of purchased items can affect the schedule of the entire project, sharing information makes it possible to take early measures against delays in the delivery of purchased items, etc.

上記の管理項目に加えて、設計時間に関する項目、設計段階における業務報告書に関する項目、出張者状況に関する項目、施工段階において発生した懸案事項に関する項目、及び施工段階における業務報告書に関する項目の少なくともいずれか1つの項目を用いることとしてもよい。 In addition to the above management items, at least one of the following items may be used: items related to design time, items related to business reports during the design phase, items related to the status of business travelers, items related to issues that arise during the construction phase, and items related to business reports during the construction phase.

設計時間に関する項目とは、設計費用状況の管理のための項目である(設計時間管理MI6)。設計時間管理MI6としては、例えば、人件費用単価、従事人員数、計画工数(計画情報)、実績工数(実績情報)等が入力される。設計時間管理MI6には、進捗評価のための情報として、計画工数に対する実績工数等の情報が含まれる。各部署の計画工数及び実績工数等の情報により設計費使用状況を管理可能とする。また、人件費単価、従事人員数、計画工数に対する実績工数の推移などを把握して、適正に予算管理を行うことも可能である。 Items related to design time are items for managing the status of design costs (design time management MI6). For example, personnel cost unit price, number of employees, planned man-hours (planned information), actual man-hours (actual information), etc. are input into design time management MI6. Information such as actual man-hours against planned man-hours is included in design time management MI6 as information for progress evaluation. It is possible to manage the status of design cost usage using information such as the planned man-hours and actual man-hours for each department. It is also possible to appropriately manage the budget by understanding the trends in personnel cost unit price, number of employees, and actual man-hours against planned man-hours.

設計段階における業務報告書に関する項目とは、設計段階において作成された業務報告書の管理のための項目である(設計週報管理MI7)。業務報告書は、例えばプロジェクト責任者やプロジェクトメンバーが作成した週次報告書(週報)等の設計業務に関する報告書である。設計週報管理MI7には、作成された業務報告書が格納される。また、設計週報管理MI7には、進捗評価のための情報として、週報の提出有無や遅延有無(週報の提出遅延状況)が含まれる。各業務報告書が集約され、参照可能となる。 Items related to work reports in the design phase are items for managing work reports created in the design phase (design weekly report management MI7). Work reports are reports on design work, such as weekly reports (weekly reports) created by the project manager or project members. Design weekly report management MI7 stores the work reports that have been created. In addition, design weekly report management MI7 includes information for progress evaluation, such as whether or not a weekly report has been submitted and whether or not there has been a delay (delay in submitting weekly reports). Each work report is consolidated and can be referenced.

出張者状況に関する項目とは、出張者の状況を管理するための項目である(出張者派遣管理MI8)。出張者派遣管理MI8としては、例えば、出張者、出張状況(安着情報や帰国情報等)等が入力される。また、出張者派遣管理MI8には、進捗評価のための情報として、例えば出張計画に対する出張実績等の情報が含まれる。出張者の動静把握を行うことや出張費抑制を図ることも期待できる。また、連絡作業の効率化も期待できる。 Items related to the status of business travelers are items for managing the status of business travelers (Business Traveler Dispatch Management MI8). For example, business travelers and business trip status (safe arrival information, return information, etc.) are input into Business Traveler Dispatch Management MI8. Business Traveler Dispatch Management MI8 also includes information for progress evaluation, such as business trip results against business trip plans. It is expected that business travelers' movements will be kept track of and business trip expenses will be reduced. It is also expected that communication work will be made more efficient.

施工段階において発生した懸案事項に関する項目とは、設計段階後における施工(現地工事)段階において発生した課題(解決を要するが解決されていない課題)を管理するための事項である(現地懸案管理MI9)。現地懸案管理MI9としては、例えば、懸案名称、具体的な懸案内容、期限情報、担当区分情報、懸案が顕在化した場合の影響度情報、処理の進捗状況、及び完了/未完了のステータス情報が入力される。すなわち、現地懸案管理MI9には、進捗評価のための情報として、懸案事項の期限情報と処理状況とが含まれる。プロジェクトの施工段階で発生した懸案事項を登録していくことにより、プロジェクト懸案情報を共有化し、対策等が可能となる。また、登録された懸案情報を蓄積し知見として活用することにより、類似プロジェクト(特に後続プロジェクト)へ懸案事項への予防対策の水平展開を図ることとしてもよい。 Items related to pending issues that have arisen in the construction phase are items for managing issues that have arisen in the construction (on-site construction) phase after the design phase (issues that need to be resolved but have not been resolved) (on-site pending issue management MI9). For example, pending issue names, specific pending issue content, deadline information, responsibility category information, impact information when pending issues become apparent, progress of processing, and completed/incomplete status information are input as on-site pending issue management MI9. That is, on-site pending issue management MI9 includes pending issue deadline information and processing status as information for progress evaluation. By registering pending issues that have arisen in the construction phase of a project, project pending issue information can be shared and measures can be taken. In addition, by accumulating registered pending issue information and utilizing it as knowledge, it may be possible to horizontally deploy preventive measures against pending issues in similar projects (especially subsequent projects).

施工段階における業務報告書に関する項目とは、施工段階において作成された業務報告書の管理のための項目である(現地週報管理MI10)。業務報告書は、例えばプロジェクト責任者やプロジェクトメンバーが作成した週次報告書(週報)等の現地施工に関する報告書である。現地週報管理MI10には、作成された業務報告書が格納される。また、現地週報管理MI10には、進捗評価のための情報として、週報の提出有無や遅延有無(週報の提出遅延状況)が含まれる。各業務報告書が集約され、参照可能となる。 Items related to work reports during the construction phase are items for managing work reports created during the construction phase (local weekly report management MI10). Work reports are reports on local construction, such as weekly reports (weekly reports) created by the project manager or project members. Local weekly report management MI10 stores the created work reports. Local weekly report management MI10 also includes information for progress evaluation, such as whether a weekly report has been submitted and whether there has been a delay (delay in submitting weekly reports). Each work report is consolidated and can be referenced.

このように、図5に一例を示すプロジェクト管理画面から、プロジェクト情報管理MI1、設計懸案管理MI2、営業文書管理MI3、出図管理MI4、購入品スケジュール管理MI5などの各管理項目に関するボタンから、各種管理情報が入力可能である。各管理情報には、進捗評価のための情報として、処理期限情報と処理状況情報などが含まれているため、後述するように、進捗評価がされ、図6のようにプロジェクト通信簿が作成可能となる。 In this way, various management information can be entered from the project management screen, an example of which is shown in Figure 5, using buttons related to each management item, such as project information management MI1, design pending management MI2, sales document management MI3, drawing release management MI4, and purchasing schedule management MI5. Each piece of management information contains processing deadline information and processing status information as information for progress evaluation, so progress is evaluated as described below, and a project report card can be created as shown in Figure 6.

また、各管理情報は部署と紐づけて入力されることで、各部署に対する進捗評価が可能となる。 In addition, each piece of management information is linked to a department and entered, making it possible to evaluate the progress of each department.

各管理項目に対応して受け付けた情報は、データベースに格納される。格納された情報は、各利用者に参照されたり、処理に用いられたりする。各プロジェクトのそれぞれに対応する情報が各管理項目に基づいてデータベース化されるため、各プロジェクトの運営方法の統一化や、各プロジェクトのあらゆる情報の見える化が可能となる。進捗、課題、スケジュール、コスト、品質などのプロジェクトで発生するあらゆる情報を関係者間で相互に視える化し、プロジェクト責任者によるプロジェクトマネジメントを支援することができる。 The information received corresponding to each management item is stored in a database. The stored information can be referenced by each user and used for processing. Since the information corresponding to each project is stored in a database based on each management item, it is possible to standardize the management methods of each project and visualize all information for each project. All information generated in a project, such as progress, issues, schedule, cost, and quality, can be made mutually visible to all involved parties, supporting project management by the project manager.

(プロジェクト管理システム1の区分け部4)
図3に示した、区分け部4は、管理項目に対して受付部3で受け付けた入力情報を、対象機器、担当区分、情報の発生原因、及びクレーム対象の少なくともいずれか1つに基づいて区分けする。各プロジェクトに対応して入力された情報はデータ量が大きくなるため、データベースから必要な情報を速やかに検索等することができるように、区分を設定する。
(Division 4 of Project Management System 1)
3, the classification unit 4 classifies the input information received by the reception unit 3 for the management items based on at least one of the target device, the division of responsibility, the cause of the information, and the subject of the complaint. Since the amount of data input for each project is large, the classification is set so that the required information can be quickly searched for from the database.

対象機器に基づく区分け(対象機器区分)とは、プロジェクトに必要な機器ごとに区分けすることである。例えば、火力発電プラントを構成する機器毎にデータベースが区分される。対象機器による区分けは、管理項目として、出図管理MI4や購入品スケジュール管理MI5などに対して効果的である。このようにすることで、対象機器から迅速かつ容易に必要な情報を検索できる。 Categorization based on target equipment (target equipment classification) means categorizing according to the equipment required for the project. For example, the database is divided according to the equipment that makes up a thermal power plant. Categorization by target equipment is effective for management items such as drawing release management MI4 and purchasing schedule management MI5. This allows you to quickly and easily search for the required information from the target equipment.

担当区分に基づく区分けとは、プロジェクトに関係している部署ごとに区分けすることである。部署としては、例えば、起票部署(起票部署区分)や責任部署(責任部署区分)とすることができる。起票部署とは、各情報を登録または社内承認作業で書類を起票した部署である。起票部署による区分けは、管理項目として、出図管理MI4や設計時間管理MI6、設計週報管理MI7、出張者派遣管理MI8、現地週報管理MI10などに対して効果的である。このようにすることで、関連部署から迅速かつ容易に必要な情報を検索できる。 Categorizing based on responsibility means categorizing by department related to the project. The department can be, for example, the issuing department (issuing department category) or the responsible department (responsible department category). The issuing department is the department that registers each piece of information or issues documents for internal approval work. Categorizing by issuing department is effective for management items such as drawing release management MI4, design time management MI6, design weekly report management MI7, business trip worker dispatch management MI8, and local weekly report management MI10. This allows the required information to be searched for quickly and easily from related departments.

責任部署とは、各情報が関連する機器や作業等に対して責任を負う部署である。責任部署による区分けは、管理項目として、プロジェクト情報管理MI1や設計懸案管理MI2、現地懸案管理MI9などに対して効果的である。このようにすることで、関連部署から迅速かつ容易に必要な情報を検索できる。 The responsible department is the department that is responsible for the equipment, work, etc. to which each piece of information relates. Categorizing by responsible department is effective for management items such as project information management MI1, design pending management MI2, and on-site pending management MI9. This allows the relevant departments to quickly and easily search for the necessary information.

情報の発生原因に基づく区分け(発生原因区分)とは、客先要求や不適合対策など情報の発生原因ごとに区分けすることである。情報の発生原因に基づく区分けは、管理項目として、設計懸案管理MI2、営業文書管理MI3、現地懸案管理MI9などに対して効果的である。このようにすることで、発生原因から迅速かつ容易に必要な情報を検索できる。 Categorizing information based on the cause of its generation (cause classification) means categorizing information according to the cause of its generation, such as customer requests or non-conformance countermeasures. Categorizing information based on the cause of its generation is effective for management items such as design pending management MI2, sales document management MI3, and local pending management MI9. This allows you to quickly and easily search for the required information based on the cause of its generation.

クレーム対象に基づく区分け(クレーム対象区分)とは、客先等からのクレームや不具合が起きた機器や内容ごとに区分けすることである。クレーム対象に基づく区分けは、設計懸案管理MI2、営業文書管理MI3、現地懸案管理MI9などに対して効果的である。このようにすることで、クレーム対象から迅速かつ容易に必要な情報を検索できる。 Categorization based on the complaint subject (complaint subject classification) is categorization based on the equipment or content in which a complaint or defect has occurred from a customer, etc. Categorization based on the complaint subject is effective for design pending issue management MI2, sales document management MI3, local pending issue management MI9, etc. This allows you to quickly and easily search for the required information from the complaint subject.

区分け部4では、このように入力された情報を、その内容に応じてデータベースを区分けて格納する。区分けによってデータベースに格納された情報の検索性・管理性が向上する。 The classification unit 4 classifies the information entered in this way into a database according to its contents and stores it. Classification improves the searchability and manageability of the information stored in the database.

(プロジェクト管理システム1の個別評価部5)
図3に示した、個別評価部5は、管理項目に対して受け付けた入力情報に基づいて、プロジェクトに関わる各部署のそれぞれに対して進捗状況の個別評価を行う。すなわち、個別評価とは部署ごとの進捗状況の評価である。個別評価部5は、各管理項目のデータベースを参照して、評価を行う。
(Individual evaluation section 5 of project management system 1)
The individual evaluation unit 5 shown in Fig. 3 performs an individual evaluation of the progress status for each department involved in the project based on the input information received for the management items. In other words, the individual evaluation is an evaluation of the progress status for each department. The individual evaluation unit 5 performs the evaluation by referring to the database for each management item.

個別評価部5は、受付部3で受け付けた入力情報に基づいて、例えば、遅延状態について評価を行う。個別評価部5は、懸案事項に関する遅延状態、社外文書に関する遅延状態、図面の作成状況に関する遅延状態、及び購入品の調達状況に関する遅延状態の少なくともいずれか1つを評価指標として、各部署のそれぞれに対して進捗状況の個別評価を行う。遅延状態は、期限に対する遅延の状態を示す指標であり、例えば、各評価項目の個別遅延率である。 The individual evaluation unit 5 performs an evaluation of, for example, the state of delay based on the input information received by the reception unit 3. The individual evaluation unit 5 performs an individual evaluation of the progress status for each department using at least one of the following evaluation indicators: the state of delay regarding pending issues, the state of delay regarding external documents, the state of delay regarding the status of drawing creation, and the state of delay regarding the status of procurement of purchased items. The state of delay is an indicator that indicates the state of delay relative to the deadline, and is, for example, the individual delay rate for each evaluation item.

懸案事項に関する遅延状態とは、設計懸案管理MI2のデータベースに格納された情報に基づく遅延状態である。社外文書に関する遅延状態とは、営業文書管理MI3のデータベースに格納された情報に基づく遅延状態である。図面の作成状況に関する遅延状態とは、出図管理MI4のデータベースに格納された情報に基づく遅延状態である。購入品の調達状況に関する遅延状態とは、購入品スケジュール管理MI5のデータベースに格納された情報に基づく遅延状態である。 A delay state related to pending issues is a delay state based on information stored in the database of design pending issues management MI2. A delay state related to external documents is a delay state based on information stored in the database of sales document management MI3. A delay state related to the drawing creation status is a delay state based on information stored in the database of drawing release management MI4. A delay state related to the procurement status of purchased items is a delay state based on information stored in the database of purchased item schedule management MI5.

なお、遅延状態は前述の各データベースに格納された情報に基づく遅延状態の他にも、設計時間管理MI6のデータベースに格納された情報に基づく遅延状態、設計週報管理MI7のデータベースに格納された情報に基づく遅延状態、出張者派遣管理MI8のデータベースに格納された情報に基づく遅延状態、現地懸案管理MI9のデータベースに格納された情報に基づく遅延状態、及び現地週報管理MI10のデータベースに格納された情報に基づく遅延状態の少なくともいずれか1つについても用いることとしてもよい。 In addition to the delay state based on the information stored in each of the aforementioned databases, the delay state may also be based on at least one of the following: a delay state based on information stored in the design time management MI6 database, a delay state based on information stored in the design weekly report management MI7 database, a delay state based on information stored in the business traveler dispatch management MI8 database, a delay state based on information stored in the local issue management MI9 database, and a delay state based on information stored in the local weekly report management MI10 database.

本実施形態では、例えば遅延状態について、個別評価部5は、各評価項目の個別遅延率として、初回出図の個別遅延率、改訂出図の個別遅延率、購入仕様書発行の個別遅延率、購入品の正式発注の個別遅延率、懸案処理の個別遅延率、文書回答の個別遅延率の6つを評価項目として個別評価を行う場合を説明する。なお、各評価項目の少なくともいずれか1つを評価項目とすることとしてもよい。さらに個別遅延率の評価項目を追加して、7つ以上を評価項目として個別評価を行ってもよい。また、進捗評価に関する項目であれば他の評価項目を用いることとしてもよい。 In this embodiment, for example, regarding the delay state, the individual evaluation unit 5 performs individual evaluation using six evaluation items as the individual delay rate for each evaluation item: the individual delay rate for the initial drawing release, the individual delay rate for the revised drawing release, the individual delay rate for the issuance of the purchase specification, the individual delay rate for the official order of the purchased item, the individual delay rate for the pending issue processing, and the individual delay rate for the document response. Note that at least one of the evaluation items may be used as an evaluation item. Furthermore, an evaluation item for the individual delay rate may be added, and individual evaluation may be performed using seven or more evaluation items. Also, other evaluation items may be used as long as they are related to progress evaluation.

初回出図の個別遅延率は、初回出図の予定数に対する初回出図の遅延数の比(遅延数/予定数)である。初回出図とは、プロジェクトのために関係先配布された初期図面(改訂前の初回関係先配布の図面)である。初回出図の遅延数は、例えば出図管理MI4のデータベースの情報(出図状況)より導出される。初回出図の予定数は、例えばプロジェクト情報管理MI1のデータベースや、出図管理MI4のデータベースの情報(予定出図数)より導出される。なお、予定数や遅延数は、評価時点における予定数及び遅延数である。 The individual delay rate for first-time drawings is the ratio of the number of delayed first-time drawings to the planned number of first-time drawings (delays/planned number). First-time drawings are the initial drawings distributed to the relevant parties for the project (drawings first distributed to the relevant parties before revisions). The number of delayed first-time drawings is derived, for example, from information in the Drawing Management MI4 database (drawing status). The planned number of first-time drawings is derived, for example, from information in the Project Information Management MI1 database or the Drawing Management MI4 database (planned number of drawings). Note that the planned number and the number of delays are the planned number and the number of delays at the time of evaluation.

改訂出図の個別遅延率は、改訂出図が必要になり計画された予定数に対する改訂出図の遅延数(改訂未出図数)の比(遅延数/予定数)である。改訂出図とは、プロジェクトのために関係先配布された初期図面に対して、例えばプロジェクトの進捗に伴う状況の変化等により改訂が必要となる図面である。改訂出図の遅延数は、例えば出図管理MI4のデータベースの情報(出図状況)より導出される。改訂出図の予定数は、例えばプロジェクト情報管理MI1のデータベースや、出図管理MI4のデータベースの情報(予定出図数)より導出される。なお、予定数や遅延数は、評価時点における予定数及び遅延数である。 The individual delay rate of revised drawings is the ratio of the number of delayed revised drawings (number of revised drawings not issued) to the planned number for which revised drawings are required (number of delays/planned number). Revised drawings are drawings that require revision to the initial drawings distributed to relevant parties for the project, for example, due to changes in the situation as the project progresses. The number of delayed revised drawings is derived, for example, from information (drawing status) in the Drawing Release Management MI4 database. The planned number of revised drawings is derived, for example, from information (planned number of drawings) in the Project Information Management MI1 database or the Drawing Release Management MI4 database. Note that the planned number and delays are the planned number and delays at the time of evaluation.

購入仕様書発行の個別遅延率は、購入仕様書発行の予定数に対する購入仕様書発行の遅延数の比(遅延数/予定数)である。購入仕様書とは、必要な機器の購入のための仕様書である。購入仕様書の遅延数は、例えば購入品スケジュール管理MI5のデータベースの情報(購入仕様書発行状況)より導出される。購入仕様書発行の予定数は、例えばプロジェクト情報管理MI1のデータベースや、購入品スケジュール管理MI5のデータベースの情報(購入仕様書発行予定数)より導出される。なお、予定数や遅延数は、評価時点における予定数及び遅延数である。 The individual delay rate for issuance of purchase specifications is the ratio of the number of delays in issuance of purchase specifications to the planned number of issuance of purchase specifications (number of delays/planned number). Purchase specifications are specifications for purchasing necessary equipment. The number of delays in purchase specifications is derived, for example, from information in the Purchase Schedule Management MI5 database (purchase specification issuance status). The planned number of purchase specifications to be issued is derived, for example, from information in the Project Information Management MI1 database or the Purchase Schedule Management MI5 database (planned number of purchase specifications to be issued). Note that the planned number and the number of delays are the planned number and the number of delays at the time of evaluation.

購入品の正式発注の個別遅延率は、購入品の正式発注の予定数に対する購入品の正式発注の遅延数の比(遅延数/予定数)である。購入品の正式発注とは、対象の購入品を正式注文したことである。購入品の正式発注の遅延数は、例えば購入品スケジュール管理MI5のデータベースの情報(購入品の正式発注状況)より導出される。購入品の正式発注の予定数は、例えばプロジェクト情報管理MI1のデータベースや、購入品スケジュール管理MI5のデータベースの情報(購入品の正式発注予定数)より導出される。なお、予定数や遅延数は、評価時点における予定数及び遅延数である。 The individual delay rate of formal orders of purchased items is the ratio of the number of delayed formal orders of purchased items to the planned number of formal orders of purchased items (number of delays/planned number). A formal order of a purchased item means that the target purchased item has been formally ordered. The number of delayed formal orders of purchased items is derived, for example, from information in the Purchase Schedule Management MI5 database (formal order status of purchased items). The planned number of formal orders of purchased items is derived, for example, from information in the Project Information Management MI1 database or the Purchase Schedule Management MI5 database (planned number of formal orders of purchased items). Note that the planned number and the number of delays are the planned number and the number of delays at the time of evaluation.

懸案処理の個別遅延率は、懸案事項の完了予定件数に対する懸案事項の未完了件数の比(未完了件数/完了予定件数)である。懸案事項の完了予定件数や懸案事項の未完了件数は、例えば設計懸案管理MI2のデータベースの情報(懸案事項の処理状況)より導出される。なお、完了予定件数や未完了件数は、評価時点における完了予定件数及び未完了件数である。なお、懸案処理の遅延率は、設計懸案管理MI2及び/または現地懸案管理MI9のデータベースの情報を用いることとしてもよい。 The individual delay rate of pending issues is the ratio of the number of pending issues that are incomplete to the number of pending issues that are scheduled to be completed (number of incomplete issues/number of scheduled to be completed). The number of pending issues that are scheduled to be completed and the number of pending issues that are incomplete are derived, for example, from information in the Design Pending Issue Management MI2 database (pending issue processing status). Note that the number of pending issues that are scheduled to be completed and the number of incomplete issues are the number of pending issues that are scheduled to be completed and the number of incomplete issues at the time of evaluation. Note that the delay rate of pending issues may be calculated using information in the Design Pending Issue Management MI2 and/or On-site Pending Issue Management MI9 database.

文書回答の個別遅延率は、回答を要する文書の回答必要件数に対する未回答件数の比(未回答件数/回答必要件数)である。なお、遅延率は、回答を要する文書の回答必要件数と回答期限未入力の件数との合算件数に対する未回答件数の比としてもよい。回答必要件数や未回答件数は、例えば営業文書管理MI3のデータベースの情報(文書回答状況)より導出される。なお、回答必要件数や未回答件数は、評価時点における回答必要件数や未回答件数である。 The individual lateness rate of document responses is the ratio of the number of unanswered documents to the number of documents requiring responses (unanswered documents/number of responses required). The lateness rate may also be the ratio of the number of unanswered documents to the combined number of documents requiring responses and the number of documents for which a response deadline has not been entered. The number of responses required and the number of unanswered documents are derived, for example, from information in the database of sales document management MI3 (document response status). The number of responses required and the number of unanswered documents are the number of responses required and the number of unanswered documents at the time of evaluation.

管理項目のデータベースでは、プロジェクト及び部署に対応して各情報が格納されているため、6つの各評価項目に対する遅延率は、プロジェクト及び部署ごとに導出される。 In the database of management items, information is stored corresponding to projects and departments, so the delay rate for each of the six evaluation items is derived for each project and department.

個別評価部5は、導出された各評価項目に対する個別遅延率の平均をとることによって、6つの各評価項目をまとめたプロジェクト及び部署の各遅延率(各遅延率)を導出する。具体的には、6つの各評価項目に対する個別遅延率は各プロジェクト及び各部署に対して導出されるため、同じプロジェクト及び部署に対して導出された各評価項目の個別遅延率(6つ)を平均することによって、該プロジェクト及び部署の各遅延率が算出される。例えば、A発電所プロジェクトのc課に対応して6つの各評価項目に対する個別遅延率が導出され、平均されることによって、A発電所プロジェクトのc課におけるプロジェクト及び部署の各遅延率が導出される。 The individual evaluation unit 5 derives the delay rate (individual delay rate) for the project and department that combines the six evaluation items by averaging the individual delay rates for each derived evaluation item. Specifically, since the individual delay rate for each of the six evaluation items is derived for each project and each department, the delay rate for the project and department is calculated by averaging the individual delay rates (six) for each evaluation item derived for the same project and department. For example, the individual delay rates for each of the six evaluation items corresponding to Section c of the A power plant project are derived and averaged to derive the delay rates for the projects and departments in Section c of the A power plant project.

そして、個別評価部5は、所定の評価基準に基づいて、進捗状況を段階評価する。すなわち、各評価項目の個別遅延率から平均して算出したプロジェクト及び部署の各遅延率を段階評価に変換する。評価基準は、例えばプロジェクト及び部署の各遅延率に基づいて予め設定されている。例えば、プロジェクト及び部署の各遅延率の全体範囲(0%から100%)を評価の段階数分の領域に分け、プロジェクト及び部署の各遅延率がどの領域に属するかで段階評価する。例えば、5段階評価の場合には、各遅延率5%未満を5点とし、各遅延率5%以上25%未満を4点とし、各遅延率25%以上50%未満を3点とし、各遅延率50%以上60%未満を2点とし、各遅延率60%以上を1点とする。このようにして、プロジェクト及び部署の各遅延率に基づいて段階評価(点数付け)を行うことができる。なお、対象項目が発生しなかった場合は対象外とすることとしてもよい。 Then, the individual evaluation unit 5 evaluates the progress status in stages based on a predetermined evaluation criterion. That is, the delay rates of the projects and departments calculated by averaging the individual delay rates of each evaluation item are converted into stage evaluations. The evaluation criterion is set in advance, for example, based on the delay rates of the projects and departments. For example, the entire range of the delay rates of the projects and departments (0% to 100%) is divided into areas equal to the number of evaluation stages, and the delay rates of the projects and departments are evaluated in stages according to which area they belong to. For example, in the case of a five-stage evaluation, each delay rate of less than 5% is given 5 points, each delay rate of 5% or more but less than 25% is given 4 points, each delay rate of 25% or more but less than 50% is given 3 points, each delay rate of 50% or more but less than 60% is given 2 points, and each delay rate of 60% or more is given 1 point. In this way, stage evaluation (scoring) can be performed based on each delay rate of the projects and departments. Note that if the target item does not occur, it may be excluded.

進捗管理への影響が少ない項目は、評価点を例えば2段階かつ小点数(2点または1点)としてもよい。すなわち、進捗管理への影響度に応じて評価項目の評価に重み付けをしてもよい。このようにすることで、複数の評価項目の評価を統合するときに、進捗管理への影響度を反映することができる。 For items that have little impact on progress management, the evaluation points may be, for example, two-level decimal points (2 points or 1 point). In other words, the evaluation of the evaluation item may be weighted according to the degree of impact on progress management. In this way, the degree of impact on progress management can be reflected when integrating the evaluations of multiple evaluation items.

このように個別評価がされることによって、各プロジェクトの各部署に対して、図6のように天気マークが設定される。図6の例では、評価を例えば5段階評価とし、天気マークとして、一見でプロジェクトの進捗状態を確認できるようにしている。 By performing individual evaluations in this way, a weather mark is set for each department of each project, as shown in Figure 6. In the example of Figure 6, the evaluation is, for example, on a five-point scale, and the weather mark allows the progress of the project to be checked at a glance.

(プロジェクト管理システム1の総合評価部6)
図3に示した、総合評価部6は、個別評価に基づいて、プロジェクト全体の総合的な評価を行う。総合評価部6は、各担当区分に対する評価に基づいて、プロジェクト全体のそれぞれに対応して総合的な段階評価を行う。
(Comprehensive evaluation section 6 of project management system 1)
The overall evaluation unit 6 shown in Fig. 3 performs a comprehensive evaluation of the entire project based on the individual evaluations. The overall evaluation unit 6 performs a comprehensive stage evaluation corresponding to each of the entire project based on the evaluations for each division in charge.

具体的には、総合評価部6は、プロジェクト全体に対応するプロジェクト及び部署の各遅延率を平均することによって、全体プロジェクトの総合遅延率(総合遅延率)を算出する。換言すると、図6のようなプロジェクト通信簿において行方向に平均をとることで、各プロジェクトに対応するプロジェクト全体の総合遅延率を算出する。そして、算出した総合遅延率を前述のように評価基準に従って段階評価(例えば、5段階評価)に変換する。このようにすることで、各プロジェクト全体に対して図6のようにPJ総合として、天気マークが設定され、総合評価がされる。なお、平均を算出する際、例えば、各部署が行う業務量やプロジェクトへの影響度等によって、各部署に対応するプロジェクト及び部署の各遅延率に対して、重み付けを行ってもよい。 Specifically, the overall evaluation unit 6 calculates the overall delay rate (total delay rate) of the entire project by averaging the delay rates of the projects and departments corresponding to the entire project. In other words, the overall delay rate of the entire project corresponding to each project is calculated by taking the average along the rows in a project report card like that in Figure 6. The calculated overall delay rate is then converted into a graded evaluation (for example, a five-grade evaluation) according to the evaluation criteria as described above. In this way, a weather mark is set for the entire project as the PJ total as in Figure 6, and an overall evaluation is performed. Note that when calculating the average, the delay rates of the projects and departments corresponding to each department may be weighted, for example, according to the amount of work each department does and the impact on the project.

また、総合評価部6は、各部署に対応する各プロジェクトのプロジェクト及び部署の各遅延率を平均することによって、各部署に対応するプロジェクト全体の総合遅延率を算出する。換言すると、図6のようなプロジェクト通信簿において列方向に平均をとることで、各部署に対応するプロジェクト全体の総合遅延率を算出する。そして、算出した各部署に対応するプロジェクト全体の総合遅延率を前述のように評価基準に従って段階評価(例えば、5段階評価)に変換する。このようにすることで、各部署に対して図6のように天気マークが設定され、各部署に対応する総合評価がされる。なお、平均を算出する際、例えば、各プロジェクトに要する業務量や社内におけるプロジェクトの重要度等によって、各プロジェクトの各部署に対応するプロジェクト全体の総合遅延率に重み付けを行ってもよい。 The overall evaluation unit 6 also calculates the overall delay rate of the entire project corresponding to each department by averaging the delay rates of the projects and departments of each project corresponding to each department. In other words, the overall delay rate of the entire project corresponding to each department is calculated by taking the average in the column direction in a project report card like that in FIG. 6. Then, the calculated overall delay rate of the entire project corresponding to each department is converted into a graded evaluation (for example, a 5-grade evaluation) according to the evaluation criteria as described above. In this way, a weather mark is set for each department as shown in FIG. 6, and an overall evaluation corresponding to each department is performed. Note that when calculating the average, the overall delay rate of the entire project corresponding to each department of each project may be weighted, for example, according to the amount of work required for each project or the importance of the project within the company.

個別評価部5及び総合評価部6における評価によって、図6のようなプロジェクト通信簿の各天気マークが設定される。各評価は統一的な指標によって、個別遅延率、各遅延率、総合遅延率の算出へと進め、評価基準に従って段階評価に変換が行われるため、各プロジェクト間等においてより正確に比較を行うことが可能となる。図6のようにプロジェクト通信簿を表示できるため、統括的に進捗状況を把握することができる。また、例えば評価を5段階評価とし、天気マークとして、一見でプロジェクトの進捗状態を確認できるようにしている。 The evaluations in the Individual Evaluation Section 5 and Overall Evaluation Section 6 result in the setting of each weather mark on the project report card as shown in Figure 6. Each evaluation is used to calculate the individual delay rate, each delay rate, and overall delay rate using a unified indicator, and is converted into a graded evaluation according to the evaluation criteria, making it possible to make more accurate comparisons between projects, etc. Since the project report card can be displayed as in Figure 6, the progress can be grasped comprehensively. In addition, for example, the evaluation can be set on a five-point scale, and the progress of the project can be confirmed at a glance as a weather mark.

次に、上述のプロジェクト管理システム1による評価処理の一例について図7を参照して説明する。図7は、本実施形態に係る評価処理の手順の一例を示すフローチャートである。図7に示すフローは、例えば、所定の制御周期で繰り返し実行される。なお、図6のようなプロジェクト通信簿を表示する場合に都度実行されてもよい。 Next, an example of evaluation processing by the above-mentioned project management system 1 will be described with reference to FIG. 7. FIG. 7 is a flowchart showing an example of the procedure of evaluation processing according to this embodiment. The flow shown in FIG. 7 is executed repeatedly at a predetermined control period, for example. Note that it may be executed each time a project report card such as that shown in FIG. 6 is displayed.

まず、管理項目のデータベースを参照し、各プロジェクト及び各部署に対して、各評価項目に対して個別遅延率を算出する(S101)。 First, the database of management items is referenced, and individual delay rates for each evaluation item are calculated for each project and each department (S101).

次に、各評価項目の平均値を算出して、各プロジェクト及び各部署の各遅延率(各遅延率)を算出する(S102)。 Next, the average value of each evaluation item is calculated to calculate the delay rate (each delay rate) for each project and each department (S102).

次に、各プロジェクト及び各部署の各遅延率を段階評価(例えば、5段階評価)に変換する(S103)。そして、段階評価に対応して天気マークを設定する(S104)。 Next, the delay rates for each project and each department are converted into a scale (for example, a 5-scale scale) (S103). Then, a weather mark is set corresponding to the scale (S104).

次に、各プロジェクト及び各部署の各遅延率において、プロジェクトに含まれる各部署の各遅延率を平均することによって、各プロジェクト全体の総合遅延率(総合遅延率)を算出する(S105)。次に、各プロジェクト全体の総合遅延率を段階評価(例えば、5段階評価)に変換する(S106)。そして、段階評価に対応して天気マークを設定する(S107)。 Next, for each delay rate of each project and each department, the delay rates of each department included in the project are averaged to calculate an overall delay rate for each project (total delay rate) (S105). Next, the overall delay rate for each project is converted into a scale (for example, a 5-scale scale) (S106). Then, a weather mark is set corresponding to the scale (S107).

次に、各プロジェクト及び各部署に対応した各プロジェクト全体の総合遅延率において、部署に対応する各プロジェクト全体の総合遅延率を平均することによって、各部署に対応する総合遅延率を算出する(S108)。次に、各部署に対応する総合遅延率を段階評価(例えば、5段階評価)に変換する(S109)。そして、段階評価に対応して天気マークを設定する(S110)。 Next, the overall delay rate for each project corresponding to each project and each department is averaged to calculate the overall delay rate for each department (S108). Next, the overall delay rate for each department is converted into a scale (e.g., a 5-scale scale) (S109). Then, a weather mark is set corresponding to the scale (S110).

次に、各天気マークを設定してプロジェクト通信簿を作成する(S111)。このようにして、プロジェクト通信簿が完成される。 Next, each weather mark is set to create the project report card (S111). In this way, the project report card is completed.

なお、図7のフローの各処理の順番は図7の順番に限定されない。例えば、S105からS107の処理と、S108からS110の処理とは順序を逆としてもよいし並列としてもよい。また、段階評価への変換処理(S103、S106、S109)及び天気マークの設定処理(S104、S107、S110)は、もとの各遅延率、総合遅延率が算出されていれば、図7の段階で処理を行う場合に限定されない。 The order of the processes in the flow of FIG. 7 is not limited to that shown in FIG. 7. For example, the processes from S105 to S107 and the processes from S108 to S110 may be in the opposite order or may be performed in parallel. In addition, the process of converting to a graded rating (S103, S106, S109) and the process of setting weather marks (S104, S107, S110) are not limited to being performed at the stage shown in FIG. 7, as long as the original delay rates and the total delay rate have been calculated.

なお、プロジェクト管理ツールを有効活用するには、必要情報のインプット、評価方法などノウハウが必要となる。従って、プロジェクト管理ツールの使用方法やプロジェクト責任者、工程管理者、コスト管理者、一般プロジェクトメンバーなどの各役割を示すガイダンスや、各プロジェクト内のルールをデータベースに格納して、インプット情報の過不足や評価結果が適切に活用され、表示されるように支援する機能を持たせるようにしてもよい。データベースに蓄積したデータをAIを用いて分析・学習して、プロジェクトの進捗評価として、適切な評価項目の選定等を行うようにしてもよい。 To effectively utilize a project management tool, know-how is required, such as inputting the necessary information and evaluation methods. Therefore, a database may be provided with guidance on how to use the project management tool and the roles of each person, such as project manager, process manager, cost manager, and general project member, as well as rules for each project, to provide a function to assist in the appropriate use and display of input information and evaluation results, as well as excesses and deficiencies. The data stored in the database may be analyzed and learned using AI to select appropriate evaluation items for project progress evaluation.

以上説明したように、本実施形態に係るプロジェクト管理システム及びそのプロジェクト管理方法並びにプロジェクト管理プログラムによれば、管理項目に対して受け付けた入力情報に基づいて部署ごとに進捗状況の個別評価を行い、そして、個別評価に基づいてプロジェクト全体としての進捗状況を評価する。このため、プロジェクト全体としての総合評価と、部署ごとの個別評価とを得て、プロジェクト管理により効率的に用いることが可能となる。 As described above, according to the project management system, project management method, and project management program of this embodiment, an individual evaluation of progress is performed for each department based on the input information received for the management items, and the progress of the project as a whole is evaluated based on the individual evaluations. This makes it possible to obtain an overall evaluation of the project as a whole and individual evaluations for each department, which can be used more efficiently in project management.

また、管理項目は、プロジェクトに対して共通して予め設定されているため、プロジェクト間における評価の統一化を行うことができる。すなわち、プロジェクト責任者やプロジェクトメンバー等の経験によってプロジェクトごとに評価方法がばらついてしまうことを抑制して、より正確にプロジェクト間の状況比較を行うことが可能となる。また、各プロジェクトの統一管理を行うことが可能となる。 In addition, because the management items are set in advance as common items for each project, it is possible to standardize evaluations between projects. In other words, it is possible to suppress variations in evaluation methods for each project due to the experience of the project manager or project members, etc., and to more accurately compare the status between projects. It also makes it possible to unify management of each project.

また、プロジェクトに関する基本情報に関する項目、設計段階において発生した懸案事項に関する項目、社外文書に関する項目、図面の作成状況に関する項目、及び購入品の調達に関する項目を管理項目とすることで、より効率的にプロジェクトの管理のための情報入力を受け付けることが可能となる。設計時間に関する項目、設計段階における業務報告書に関する項目、出張者状況に関する項目、施工段階において発生した懸案事項に関する項目、及び施工段階における業務報告書に関する項目の少なくともいずれか1つの項目を用いることによって、より効果的に、進捗状況の評価を行うことが可能となる。 In addition, by managing items such as basic project information, issues that arose during the design phase, external documents, the status of drawing creation, and procurement of purchased items, it becomes possible to more efficiently accept information input for project management. By using at least one of the items related to design time, work reports during the design phase, traveler status, issues that arose during the construction phase, and work reports during the construction phase, it becomes possible to more effectively evaluate progress.

入力情報に基づいて、懸案事項に関する個別遅延率、社外文書に関する個別遅延率、図面の作成状況に関する個別遅延率、及び購入品の調達状況に関する個別遅延率の少なくともいずれか1つを評価指標とすることによって、より正確に、部署のそれぞれに対して進捗状況の個別評価を行うことができる。 Based on the input information, at least one of the following evaluation indicators can be used: individual delay rate for pending issues, individual delay rate for external documents, individual delay rate for drawing creation status, and individual delay rate for procurement status of purchased items. This allows for more accurate individual evaluation of the progress of each department.

プロジェクト及び部署のそれぞれに対応して評価結果が表示されるため、プロジェクト間の進捗状況の比較や、部署間の進捗状況の比較等を容易に認識することができる。すなわち、各情報を総合的に把握して各プロジェクトを管理することが可能となる。プロジェクトに対応した管理画面において、各プロジェクトに共通するボタン、調達に関するボタン、設計に関するボタン、及び施工に関するボタンのそれぞれが区別して表示されているため、各段階に対応して使用性を向上させることができる。複数のプロジェクトが地域ごとにグルーピングされて表示されており、指定されたプロジェクトに対応する管理画面が表示されるため、利便性を向上させることができる。 Since the evaluation results are displayed for each project and department, it is easy to compare progress between projects or between departments. In other words, it is possible to comprehensively grasp each piece of information and manage each project. On the management screen for a project, buttons common to each project, buttons related to procurement, buttons related to design, and buttons related to construction are displayed separately, improving usability for each stage. Multiple projects are grouped and displayed by region, and the management screen corresponding to the specified project is displayed, improving convenience.

本開示は、上述の実施形態のみに限定されるものではなく、発明の要旨を逸脱しない範囲において、種々変形実施が可能である。 This disclosure is not limited to the above-described embodiments, and various modifications are possible without departing from the spirit of the invention.

以上説明した各実施形態に記載のプロジェクト管理システム及びそのプロジェクト管理方法並びにプロジェクト管理プログラムは例えば以下のように把握される。
本開示に係るプロジェクト管理システム(1)は、プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける受付部(3)と、前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う個別評価部(5)と、前記個別評価に基づいて、前記プロジェクトの総合的な評価を行う総合評価部(6)と、を備える。
The project management system, the project management method, and the project management program described in each of the above-described embodiments can be understood, for example, as follows.
A project management system (1) according to the present disclosure includes a receiving unit (3) that receives input for management items that are preset commonly to projects, an individual evaluation unit (5) that performs an individual evaluation of the progress status for each of the responsibility categories related to the project based on the input information received for the management items, and a comprehensive evaluation unit (6) that performs a comprehensive evaluation of the project based on the individual evaluations.

本開示に係るプロジェクト管理システム(1)によれば、管理項目に対して受け付けた入力情報に基づいて担当区分(例えば部署)ごとに進捗状況の個別評価を行い、そして、個別評価に基づいてプロジェクト全体としての進捗状況を評価する。このため、プロジェクト全体としての総合評価と、担当区分ごとの個別評価とを得て、プロジェクト管理により効率的に用いることが可能となる。 According to the project management system (1) disclosed herein, an individual evaluation of progress is performed for each responsible category (e.g., department) based on the input information received for the management items, and the progress of the project as a whole is evaluated based on the individual evaluations. This makes it possible to obtain an overall evaluation of the project as a whole and individual evaluations for each responsible category, which can be used more efficiently in project management.

また、管理項目は、プロジェクトに対して共通して予め設定されているため、プロジェクト間における評価の統一化を行うことができる。すなわち、プロジェクト責任者やプロジェクトメンバー等の経験によってプロジェクトごとに評価方法がばらついてしまうことを抑制して、より正確にプロジェクト間の状況比較を行うことが可能となる。また、各プロジェクトの統一管理を行うことが可能となる。 In addition, because the management items are set in advance as common items for each project, it is possible to standardize evaluations between projects. In other words, it is possible to suppress variations in evaluation methods for each project due to the experience of the project manager or project members, etc., and to more accurately compare the status between projects. It also makes it possible to unify management of each project.

本開示に係るプロジェクト管理システム(1)は、前記受付部(3)は、前記プロジェクトに関する基本情報に関する項目(MI1)、設計段階において発生した懸案事項に関する項目(MI2)、社外文書に関する項目(MI3)、図面の作成状況に関する項目(MI4)、及び購入品の調達に関する項目(MI5)の少なくともいずれか一つの項目に対して入力を受け付け可能であることとしてもよい。 In the project management system (1) disclosed herein, the reception unit (3) may be capable of receiving input for at least one of items related to basic information about the project (MI1), items related to pending issues that arose during the design stage (MI2), items related to external documents (MI3), items related to the status of drawing creation (MI4), and items related to procurement of purchased items (MI5).

本開示に係るプロジェクト管理システム(1)によれば、プロジェクトに関する基本情報に関する項目、設計段階において発生した懸案事項に関する項目、社外文書に関する項目、図面の作成状況に関する項目、及び購入品の調達に関する項目を管理項目とすることで、より効率的に業務に則したプロジェクトの管理のために必要な情報入力を受け付けることが可能となる。 According to the project management system (1) disclosed herein, by managing items related to basic information about the project, items related to issues that arose during the design stage, items related to external documents, items related to the status of drawing creation, and items related to procurement of purchased items, it becomes possible to accept input of information necessary for more efficient management of projects in line with business operations.

本開示に係るプロジェクト管理システム(1)は、前記受付部(3)は、設計時間に関する項目(MI6)、設計段階における業務報告書に関する項目(MI7)、出張者状況に関する項目(MI8)、施工段階において発生した懸案事項に関する項目(MI9)、及び施工段階における業務報告書に関する項目(MI10)の少なくともいずれか一つの項目に対して入力を受け付け可能であることとしてもよい。 In the project management system (1) according to the present disclosure, the reception unit (3) may be capable of receiving input for at least one of the items related to design time (MI6), items related to work reports in the design phase (MI7), items related to the status of business travelers (MI8), items related to issues that arise in the construction phase (MI9), and items related to work reports in the construction phase (MI10).

本開示に係るプロジェクト管理システム(1)によれば、設計時間に関する項目、設計段階における業務報告書に関する項目、出張者状況に関する項目、施工段階において発生した懸案事項に関する項目、及び施工段階における業務報告書に関する項目の少なくともいずれか1つの項目を用いることによって、より効果的に、進捗状況の評価を行うことが可能となる。 According to the project management system (1) disclosed herein, by using at least one of the items related to design time, items related to work reports in the design phase, items related to the status of business travelers, items related to issues that arise in the construction phase, and items related to work reports in the construction phase, it becomes possible to more effectively evaluate the progress status.

本開示に係るプロジェクト管理システム(1)は、前記管理項目に対して受け付けた前記入力情報を、対象機器、前記担当区分、情報の発生原因、及びクレーム対象の少なくともいずれか一つに基づいて区分けする区分け部(4)を備えることとしてもよい。 The project management system (1) according to the present disclosure may include a classification unit (4) that classifies the input information received for the management items based on at least one of the target equipment, the division of responsibility, the cause of the information, and the subject of the complaint.

本開示に係るプロジェクト管理システム(1)によれば、入力情報としてのデータベースを、対象機器、担当区分、情報の発生原因、及びクレーム対象の少なくともいずれか1つに基づいて区分けすることによって、データベースを効率的に整理することが可能となる。例えば、検索を効率的に行うことが可能となる。 According to the project management system (1) disclosed herein, the database as input information can be efficiently organized by classifying the database based on at least one of the target equipment, the division of responsibility, the cause of the information, and the subject of the complaint. For example, it becomes possible to efficiently perform searches.

本開示に係るプロジェクト管理システム(1)は、前記個別評価部(5)は、前記入力情報に基づいて、前記懸案事項に関する遅延状態、前記社外文書に関する遅延状態、前記図面の作成状況に関する遅延状態、及び前記購入品の調達状況に関する遅延状態の少なくともいずれか一つを評価指標として、前記担当区分のそれぞれに対して進捗状況の個別評価を行うこととしてもよい。 In the project management system (1) according to the present disclosure, the individual evaluation unit (5) may perform an individual evaluation of the progress status for each of the responsibility categories based on the input information, using at least one of the delay status regarding the pending issues, the delay status regarding the external documents, the delay status regarding the drawing creation status, and the delay status regarding the procurement status of the purchased items as an evaluation index.

本開示に係るプロジェクト管理システム(1)によれば、入力情報に基づいて、懸案事項に関する遅延状態、社外文書に関する遅延状態、図面の作成状況に関する遅延状態、及び購入品の調達状況に関する遅延状態の少なくともいずれか1つを評価指標とすることによって、より正確に、担当区分のそれぞれに対して進捗状況の個別評価を行うことができる。 According to the project management system (1) disclosed herein, by using at least one of the following as an evaluation index based on input information: delay status regarding pending issues, delay status regarding external documents, delay status regarding the creation status of drawings, and delay status regarding the procurement status of purchased items, it is possible to more accurately perform individual evaluation of the progress status for each responsibility category.

本開示に係るプロジェクト管理システム(1)は、前記個別評価部(5)は、所定の評価基準に基づいて、各前記担当区分に対して進捗状況を段階評価することとしてもよい。 In the project management system (1) according to the present disclosure, the individual evaluation unit (5) may perform a staged evaluation of the progress status for each of the sections in charge based on a predetermined evaluation criterion.

本開示に係るプロジェクト管理システム(1)によれば、所定の評価基準に基づくことで、進捗状況を段階評価することができる。段階評価(例えば5段階評価)によって各担当区分の評価をより判断の容易性を向上し、より簡便に比較することが可能となる。また、プロジェクト責任者やプロジェクトメンバー等の経験によって評価がばらついてしまうことを抑制して、より正確にプロジェクトの状況を評価して把握することが可能となる。 According to the project management system (1) disclosed herein, progress can be graded based on a predetermined evaluation standard. Graded evaluation (e.g., a five-point scale) improves the ease of judgment for each division of responsibility and allows for easier comparison. In addition, it is possible to suppress variation in evaluation due to the experience of the project manager, project members, etc., and to more accurately evaluate and grasp the project status.

本開示に係るプロジェクト管理システム(1)は、各前記担当区分に対する進捗状況に基づいて、前記プロジェクトのそれぞれに対応して総合的な進捗状況を評価し、段階評価を行うこととしてもよい。 The project management system (1) according to the present disclosure may evaluate the overall progress status for each of the projects based on the progress status for each of the responsibility categories, and perform a staged evaluation.

本開示に係るプロジェクト管理システム(1)によれば、段階評価(例えば5段階評価)によりプロジェクト全体の総合評価をより判断の容易性を向上し、各プロジェクト間の全体評価をより簡便に比較することが可能となる。 According to the project management system (1) disclosed herein, the overall evaluation of the entire project can be more easily judged by using a scale (e.g., a five-scale scale), and the overall evaluation of each project can be more easily compared.

本開示に係るプロジェクト管理システム(1)は、前記プロジェクト及び前記担当区分のそれぞれに対応して、評価結果を表示する表示部(2)を備えることとしてもよい。 The project management system (1) according to the present disclosure may include a display unit (2) that displays the evaluation results corresponding to each of the projects and the divisions of responsibility.

本開示に係るプロジェクト管理システム(1)によれば、プロジェクト及び担当区分のそれぞれに対応して評価結果が表示されるため、プロジェクトの迅速な選定や、プロジェクト間の進捗状況の比較や、担当区分間の進捗状況の比較等を容易に認識することができる。すなわち、各情報を総合的に把握して各プロジェクトを管理することが可能となる。 According to the project management system (1) disclosed herein, the evaluation results are displayed for each project and each division in charge, making it easy to quickly select projects, compare progress between projects, and compare progress between divisions in charge. In other words, it becomes possible to comprehensively grasp each piece of information and manage each project.

本開示に係るプロジェクト管理システム(1)は、前記表示部(2)は、前記プロジェクトのそれぞれに対応した管理画面を表示し、前記管理画面には、各前記プロジェクトに共通するボタン、調達に関するボタン、設計に関するボタン、及び施工に関するボタンのそれぞれが区別して表示されていることとしてもよい。 In the project management system (1) according to the present disclosure, the display unit (2) may display a management screen corresponding to each of the projects, and the management screen may display buttons common to each of the projects, buttons related to procurement, buttons related to design, and buttons related to construction in a differentiated manner.

本開示に係るプロジェクト管理システム(1)によれば、プロジェクトに対応した管理画面において、各プロジェクトに共通するボタン、調達に関するボタン、設計に関するボタン、及び施工に関するボタンのそれぞれが区別して表示されているため、選択するにあたり視認性も向上して、各段階に対応して使用性を向上させることができる。 According to the project management system (1) disclosed herein, on the management screen corresponding to a project, buttons common to each project, buttons related to procurement, buttons related to design, and buttons related to construction are displayed separately, improving visibility when making a selection and improving usability for each stage.

本開示に係るプロジェクト管理システム(1)は、前記表示部(2)は、全体管理画面を表示し、前記全体管理画面には、複数の前記プロジェクトが地域ごとにグルーピングされて表示されており、前記プロジェクトが指定されると、指定された前記プロジェクトに対応する前記管理画面を表示することとしてもよい。 In the project management system (1) according to the present disclosure, the display unit (2) displays an overall management screen, and the overall management screen displays a plurality of the projects grouped by region, and when a project is specified, the management screen corresponding to the specified project may be displayed.

本開示に係るプロジェクト管理システム(1)によれば、複数のプロジェクトが地域ごとにグルーピングされて表示されており、指定されたプロジェクトに対応する管理画面が表示されるため、プロジェクトを選択して指定するにあたり迅速な操作と利便性を向上させることができる。 According to the project management system (1) disclosed herein, multiple projects are grouped by region and displayed, and a management screen corresponding to a specified project is displayed, thereby improving the speed and convenience of selecting and specifying a project.

本開示に係るプロジェクト管理方法は、プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける工程と、前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う工程と、前記個別評価に基づいて前記プロジェクトの総合的な評価を行う工程と、を有する。 The project management method disclosed herein includes a step of accepting input for management items that are preset commonly for a project, a step of making an individual evaluation of the progress status for each of the divisions responsible for the project based on the input information accepted for the management items, and a step of making a comprehensive evaluation of the project based on the individual evaluations.

本開示に係るプロジェクト管理プログラムは、プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける処理と、前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う処理と、前記個別評価に基づいて、前記プロジェクトの総合的な評価を行う処理と、をコンピュータに実行させる。 The project management program disclosed herein causes a computer to execute the following processes: accepting input for management items that are preset commonly for a project; making an individual evaluation of the progress status for each of the divisions responsible for the project based on the input information accepted for the management items; and making a comprehensive evaluation of the project based on the individual evaluations.

1 :プロジェクト管理システム
2 :表示部
3 :受付部
4 :区分け部
5 :個別評価部
6 :総合評価部
8 :通信網
9 :情報処理装置
11 :CPU
12 :ROM
13 :RAM
14 :ハードディスクドライブ
15 :通信部
18 :バス
MI1 :プロジェクト情報管理
MI2 :設計懸案管理
MI3 :営業文書管理
MI4 :出図管理
MI5 :購入品スケジュール管理
MI6 :設計時間管理
MI7 :設計週報管理
MI8 :出張者派遣管理
MI9 :現地懸案管理
MI10 :現地週報管理

1: Project management system 2: Display unit 3: Reception unit 4: Classification unit 5: Individual evaluation unit 6: Overall evaluation unit 8: Communication network 9: Information processing device 11: CPU
12: ROM
13: RAM
14: Hard disk drive 15: Communication unit 18: Bus MI1: Project information management MI2: Design pending management MI3: Sales document management MI4: Drawing release management MI5: Purchase schedule management MI6: Design time management MI7: Design weekly report management MI8: Business trip dispatch management MI9: Local pending management MI10: Local weekly report management

Claims (11)

プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける受付部と、
前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う個別評価部と、
前記個別評価に基づいて、前記プロジェクトの総合的な評価を行う総合評価部と、
前記プロジェクト及び前記担当区分のそれぞれに対応して、評価結果を表示する表示部と、
を備え
前記表示部は、前記プロジェクト及び該プロジェクトに関わる前記担当区分のそれぞれに対応した前記進捗状況の個別評価の評価結果を行列位置に表示する、
プロジェクト管理システム。
a reception unit that receives input for management items that are set in advance commonly to the project;
an individual evaluation unit that performs individual evaluation of the progress status for each of the divisions in charge of the project based on input information received for the management items;
a comprehensive evaluation unit that performs a comprehensive evaluation of the project based on the individual evaluations;
a display unit that displays an evaluation result corresponding to each of the projects and the divisions in charge;
Equipped with
the display unit displays evaluation results of the individual evaluations of the progress status corresponding to each of the projects and the divisions in charge related to the projects in matrix positions.
Project management systems.
前記受付部は、前記プロジェクトに関する基本情報に関する項目、設計段階において発生した懸案事項に関する項目、社外文書に関する項目、図面の作成状況に関する項目、及び購入品の調達に関する項目の少なくともいずれか一つの項目に対して入力を受け付け可能である請求項1に記載のプロジェクト管理システム。 The project management system according to claim 1, wherein the reception unit is capable of receiving input for at least one of the following items: basic information about the project, issues that arose during the design stage, external documents, the status of drawing creation, and procurement of purchased items. 前記受付部は、設計時間に関する項目、設計段階における業務報告書に関する項目、出張者状況に関する項目、施工段階において発生した懸案事項に関する項目、及び施工段階における業務報告書に関する項目の少なくともいずれか一つの項目に対して入力を受け付け可能である請求項2に記載のプロジェクト管理システム。 The project management system according to claim 2, wherein the reception unit is capable of receiving input for at least one of the following items: items related to design time, items related to business reports in the design phase, items related to the status of business travelers, items related to issues that arise in the construction phase, and items related to business reports in the construction phase. 前記管理項目に対して受け付けた前記入力情報を、対象機器、前記担当区分、情報の発生原因、及びクレーム対象の少なくともいずれか一つに基づいて区分けする区分け部を備える請求項1から3のいずれか1項に記載のプロジェクト管理システム。 The project management system according to any one of claims 1 to 3, further comprising a classification unit that classifies the input information received for the management item based on at least one of the target device, the division of responsibility, the cause of the information, and the subject of the complaint. 前記個別評価部は、前記入力情報に基づいて、前記懸案事項に関する遅延状態、前記社外文書に関する遅延状態、前記図面の作成状況に関する遅延状態、及び前記購入品の調達状況に関する遅延状態の少なくともいずれか一つを評価指標として、前記担当区分のそれぞれに対して進捗状況の個別評価を行う請求項2に記載のプロジェクト管理システム。 The project management system according to claim 2, wherein the individual evaluation unit performs an individual evaluation of the progress status for each of the responsibility categories based on the input information, using at least one of the delay status regarding the pending issues, the delay status regarding the external documents, the delay status regarding the drawing creation status, and the delay status regarding the procurement status of the purchased items as an evaluation index. 前記個別評価部は、所定の評価基準に基づいて、各前記担当区分に対して進捗状況を段階評価する請求項5に記載のプロジェクト管理システム。 The project management system according to claim 5, wherein the individual evaluation unit evaluates the progress status of each of the sections in charge based on a predetermined evaluation criterion. 前記総合評価部は、各前記担当区分に対する進捗状況に基づいて、前記プロジェクトのそれぞれに対応して総合的な進捗状況を評価し、段階評価を行う請求項6に記載のプロジェクト管理システム。 The project management system according to claim 6, wherein the overall evaluation unit evaluates the overall progress status for each of the projects based on the progress status for each of the responsibility categories, and performs a staged evaluation. 前記表示部は、前記プロジェクトのそれぞれに対応した管理画面を表示し、
前記管理画面には、各前記プロジェクトに共通するボタン、調達に関するボタン、設計に関するボタン、及び施工に関するボタンのそれぞれが区別して表示されている請求項1から7のいずれか一項に記載のプロジェクト管理システム。
the display unit displays a management screen corresponding to each of the projects;
The project management system according to claim 1 , wherein the management screen displays, in a distinct manner, buttons common to each of the projects, buttons relating to procurement, buttons relating to design, and buttons relating to construction.
前記表示部は、全体管理画面を表示し、
前記全体管理画面には、複数の前記プロジェクトが地域ごとにグルーピングされて表示されており、前記プロジェクトが指定されると、指定された前記プロジェクトに対応する前記管理画面を表示する請求項に記載のプロジェクト管理システム。
The display unit displays an overall management screen,
9. A project management system according to claim 8, wherein the overall management screen displays a plurality of the projects grouped by region, and when a project is specified, the management screen corresponding to the specified project is displayed.
プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける工程と、
前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う工程と、
前記個別評価に基づいて前記プロジェクトの総合的な評価を行う工程と、
前記プロジェクト及び前記担当区分のそれぞれに対応して、評価結果を表示する工程と、
を有し、
前記表示する工程は、前記プロジェクト及び該プロジェクトに関わる前記担当区分のそれぞれに対応した前記進捗状況の個別評価の評価結果を行列位置に表示する、
コンピュータが実行するプロジェクト管理方法。
receiving input for management items that are set in advance commonly to the project;
A step of individually evaluating the progress of each of the divisions in charge of the project based on the input information received for the management items;
conducting a comprehensive evaluation of the project based on the individual evaluations;
displaying an evaluation result corresponding to each of the projects and the divisions in charge;
having
The display step displays evaluation results of the individual evaluations of the progress status corresponding to the project and each of the divisions in charge related to the project in a row and column position.
A computer implemented method of project management.
プロジェクトに対して共通して予め設定された管理項目に対して入力を受け付ける処理と、
前記管理項目に対して受け付けた入力情報に基づいて、前記プロジェクトに関わる担当区分のそれぞれに対して進捗状況の個別評価を行う処理と、
前記個別評価に基づいて、前記プロジェクトの総合的な評価を行う処理と、
前記プロジェクト及び前記担当区分のそれぞれに対応して、評価結果を表示する処理と、
をコンピュータに実行させ、
前記表示する処理は、前記プロジェクト及び該プロジェクトに関わる前記担当区分のそれぞれに対応した前記進捗状況の個別評価の評価結果を行列位置に表示する、
プロジェクト管理プログラム。
A process of accepting input for management items that are set in advance commonly for a project;
A process of individually evaluating the progress of each of the divisions in charge of the project based on the input information received for the management items;
performing a comprehensive evaluation of the project based on the individual evaluations;
A process of displaying an evaluation result corresponding to each of the projects and the divisions of responsibility;
Run the following on your computer:
the display process displays evaluation results of the individual evaluations of the progress status corresponding to the project and each of the divisions in charge related to the project in a row and column position.
Project management program.
JP2020018817A 2020-02-06 2020-02-06 Project management system, project management method and project management program Active JP7500209B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020018817A JP7500209B2 (en) 2020-02-06 2020-02-06 Project management system, project management method and project management program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020018817A JP7500209B2 (en) 2020-02-06 2020-02-06 Project management system, project management method and project management program

Publications (2)

Publication Number Publication Date
JP2021125027A JP2021125027A (en) 2021-08-30
JP7500209B2 true JP7500209B2 (en) 2024-06-17

Family

ID=77459112

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020018817A Active JP7500209B2 (en) 2020-02-06 2020-02-06 Project management system, project management method and project management program

Country Status (1)

Country Link
JP (1) JP7500209B2 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003122892A (en) 2001-10-18 2003-04-25 Matsushita Electric Ind Co Ltd Task management system, homepage server, and computer-readable recording medium for task management system
JP2016048543A (en) 2014-07-30 2016-04-07 明豊ファシリティワークス株式会社 Project progress management system and computer program
JP2016118832A (en) 2014-12-18 2016-06-30 株式会社野村総合研究所 Project management system and project management program

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003122892A (en) 2001-10-18 2003-04-25 Matsushita Electric Ind Co Ltd Task management system, homepage server, and computer-readable recording medium for task management system
JP2016048543A (en) 2014-07-30 2016-04-07 明豊ファシリティワークス株式会社 Project progress management system and computer program
JP2016118832A (en) 2014-12-18 2016-06-30 株式会社野村総合研究所 Project management system and project management program

Also Published As

Publication number Publication date
JP2021125027A (en) 2021-08-30

Similar Documents

Publication Publication Date Title
KR102211437B1 (en) Production of orders with forecasts, inventory management, integrated planning operating methods
Tsai Quality cost measurement under activity‐based costing
JP6781602B2 (en) Business support system and business support method
CN112766780A (en) Advanced plan scheduling system and method based on big data machine learning
JP6370757B2 (en) Profit / loss prediction apparatus and profit / loss prediction program
Lea Management accounting in ERP integrated MRP and TOC environments
JP2004021364A (en) Management decision support system
Danilczuk et al. Computer-aided material demand planning using ERP systems and business intelligence technology
JP2007323680A (en) Management decision support system
Ambrosio-Flores et al. Warehouse management model integrating BPM-Lean Warehousing to increase order fulfillment in SME distribution companies
JP2018085013A (en) Company information system and company information providing method
Milliken Transforming big data into supply chain analytics.
Gil-Goyzueta et al. Process improvement proposal storage to increase the service level using lean warehousing in commerce companies
JP7500209B2 (en) Project management system, project management method and project management program
JP2016033704A (en) Profit / loss prediction apparatus and profit / loss prediction program
KR20200076554A (en) System for Progress Rate Roll-Up from Lower Level to Upper Level for the Engineering Control System of Power Plant Construction Project
Prakash et al. Effects of inventory classifications on CONWIP system: a case study
JP6242362B2 (en) Profit / loss prediction apparatus and profit / loss prediction program
Labarta-García et al. Application of Lean Manufacturing and SLP tools to increase productivity in an SME in the textile sector
CN101681162A (en) Computer system for managing part order placement
JP2005267337A (en) Business activity support system
JP2023153586A (en) Inventory management device, inventory management method, and inventory management program
Andia et al. Model for the Optimization of the Supply Process in a MYPE Associated with the Consortium of the Metalworking Sector
JP2022081318A (en) Sales plan formulation support device, and sales plan formulation support method
Pranatio et al. Design of rice logistic geographic information systems using SCOR, FMEA, and AHP method to support national food security risk mitigation system

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20220121

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20221226

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20231114

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231114

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240111

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240507

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240605

R150 Certificate of patent or registration of utility model

Ref document number: 7500209

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150