JP7549541B2 - Construction method of CFT pillars - Google Patents
[go: Go Back, main page]

JP7549541B2 - Construction method of CFT pillars - Google Patents

Construction method of CFT pillars Download PDF

Info

Publication number
JP7549541B2
JP7549541B2 JP2021010900A JP2021010900A JP7549541B2 JP 7549541 B2 JP7549541 B2 JP 7549541B2 JP 2021010900 A JP2021010900 A JP 2021010900A JP 2021010900 A JP2021010900 A JP 2021010900A JP 7549541 B2 JP7549541 B2 JP 7549541B2
Authority
JP
Japan
Prior art keywords
concrete
cft column
space
steel pipe
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021010900A
Other languages
Japanese (ja)
Other versions
JP2022114575A (en
Inventor
嵩広 藤井
豪人 熊野
太志 大堀
隆 岩清水
藍 山田
憲二 星隈
浩二 瀬之口
誠 浦瀬
秀行 山下
嘉志 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2021010900A priority Critical patent/JP7549541B2/en
Publication of JP2022114575A publication Critical patent/JP2022114575A/en
Application granted granted Critical
Publication of JP7549541B2 publication Critical patent/JP7549541B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

本発明は、上下方向に連続する下方側CFT柱と上方側CFT柱とを構築するCFT柱の施工方法に関する。 The present invention relates to a method for constructing CFT columns that construct a lower CFT column and an upper CFT column that are continuous in the vertical direction.

上記のCFT柱の施工方法として、下方側CFT柱と上方側CFT柱とを上下に並べて配設し、下方側CFT柱の上端部と上方側CFT柱の下端部とを溶接した後、下方側CFT柱の上端面と上方側CFT柱の下端面との間の隙間に圧縮力伝達材を充填して硬化させて下方側CFT柱と上方側CFT柱とを接合することで、上下方向に連続する下方側CFT柱と上方側CFT柱とを構築する施工方法が知られている(例えば、特許文献1参照)。 As a construction method for the above-mentioned CFT columns, a construction method is known in which a lower CFT column and an upper CFT column are arranged vertically, the upper end of the lower CFT column is welded to the lower end of the upper CFT column, and then a compressive force transmission material is filled in the gap between the upper end surface of the lower CFT column and the lower end surface of the upper CFT column, which is then hardened to join the lower CFT column and the upper CFT column, thereby constructing a lower CFT column and an upper CFT column that are continuous in the vertical direction (see, for example, Patent Document 1).

この特許文献1に記載の施工方法では、下方側CFT柱の下方側鋼管、及び、上方側CFT柱の上方側鋼管の夫々に対して、その内部にコンクートを予め充填させた後、下方側CFT柱と上方側CFT柱とを上下に並べて配設している。 In the construction method described in Patent Document 1, the lower steel pipe of the lower CFT column and the upper steel pipe of the upper CFT column are filled with concrete beforehand, and then the lower CFT column and the upper CFT column are arranged one above the other.

それに対して、他の施工方法として、下方側CFT柱の下方側鋼管と上方側CFT柱の上方側鋼管とを上下方向に連続する状態で配設した上で、下方側鋼管及び上方側鋼管の内部にコンクリートを充填することで、上下方向に連続する下方側CFT柱と上方側CFT柱とを構築する施工方法も知られている(例えば、特許文献2参照)。 In contrast, another construction method is known in which the lower steel pipe of the lower CFT column and the upper steel pipe of the upper CFT column are arranged in a vertically continuous state, and then concrete is filled inside the lower steel pipe and the upper steel pipe to construct a vertically continuous lower CFT column and upper CFT column (see, for example, Patent Document 2).

この特許文献2に記載の施工方法では、下方側鋼管と上方側鋼管とをその内部同士が連通する状態で接合し、下方側鋼管に備えられた圧入口にコンクリート供給管を接続して、下方側鋼管及び上方側鋼管の内部に下方側から上方側に向かってコンクリートを圧入していくことで、下方側鋼管及び上方側鋼管の内部にコンクリートを充填している。 In the construction method described in Patent Document 2, the lower steel pipe and the upper steel pipe are joined in a state in which their interiors are connected to each other, a concrete supply pipe is connected to an injection port provided in the lower steel pipe, and concrete is injected from the bottom to the top into the lower steel pipe and the upper steel pipe, filling the insides of the lower steel pipe and the upper steel pipe with concrete.

特許第3322652号Patent No. 3322652 特許第3518334号Patent No. 3518334

上記特許文献1、2の何れに記載の施工方法でも、上下方向に連続する下方側CFT柱と上方側CFT柱を施工するに当たり、下方側CFT柱を先行して施工し、その後、上方側CFT柱を施工するという施工順序となっている。 In both of the construction methods described in Patent Documents 1 and 2, when constructing the lower CFT column and the upper CFT column that are continuous in the vertical direction, the construction order is such that the lower CFT column is constructed first, and then the upper CFT column is constructed.

しかしながら、例えば、下方側CFT柱の設置箇所に工事の運搬車等の動線を確保しなければならない等、各種の施工条件によっては、先行して施工した下方側CFT柱が邪魔になって、工事用スペースを確保できずに他の工事等が行えなくなるので、そのための対応策が求められている。 However, depending on various construction conditions, for example, the need to ensure a clear route for construction vehicles to move around the installation site of the lower CFT pillars, the lower CFT pillars that were installed earlier can get in the way, making it impossible to secure construction space and making it impossible to carry out other construction work, so a solution is needed.

この実情に鑑み、本発明の主たる課題は、上下方向に連続する下方側CFT柱と上方側CFT柱を施工するに当たり、下方側CFT柱を先行して施工できない状況であっても、その状況に柔軟に対応しながら、下方側CFT柱と上方側CFT柱とを施工することができるCFT柱の施工方法を提供する点にある。 In view of this situation, the main objective of the present invention is to provide a method for constructing CFT columns that can flexibly respond to situations in which it is not possible to construct the lower CFT column first, and the upper CFT column, when constructing the lower CFT column and the upper CFT column that are continuous in the vertical direction.

本発明の第1特徴構成は、上下方向に連続する下方側CFT柱と上方側CFT柱とを構築するCFT柱の施工方法において、
下方側に下方側CFT柱設置空間及び接合空間を確保する状態で上方側鋼管を設置し、その上方側鋼管の内部にコンクリートを充填させて上方側CFT柱を先行して施工する先行工程を行い、
その後、前記下方側CFT設置空間に下方側鋼管を設置し、その下方側鋼管の内部にコンクリートを充填させて下方側CFT柱を施工し、前記接合空間にて前記上方側CFT柱の下端部と前記下方側CFT柱の上端部とを接合する後行工程を行う点にある。
The first characteristic configuration of the present invention is a construction method for a CFT column that constructs a lower CFT column and an upper CFT column that are continuous in the vertical direction,
The upper steel pipe is installed in a state where the lower CFT column installation space and the joint space are secured on the lower side, and the upper steel pipe is filled with concrete to carry out the preliminary process of constructing the upper CFT column in advance.
Then, a lower steel pipe is installed in the lower CFT installation space, concrete is filled inside the lower steel pipe to construct the lower CFT column, and a subsequent process is carried out to join the lower end of the upper CFT column and the upper end of the lower CFT column in the joining space.

本構成によれば、まず、先行工程を行うので、上方側CFT柱の下方側に、接合空間を確保するだけでなく、下方側CFT柱設置空間を確保しているので、それらの空間を、工事の運搬車等の動線等の工事用スペースとして確保しながら、上方側CFT柱を施工することができる。そして、先行工程を行った後、後行工程を行うことで、下方側柱設置空間に下方側CFTを施工し、接合空間にて上方側CFT柱と下方側CFT柱とを接合して、上下方向に連続する下方側CFT柱と上方側CFT柱を施工することができる。このように、先行工程、後行工程を順次行うことで、工事の運搬車等の動線等の工事用スペースを確保して、他の工事を行うことができながら、上下方向に連続する下方側CFT柱と上方側CFT柱を好適に施工することができる。 According to this configuration, the preceding process is performed first, so that not only is a joining space secured below the upper CFT column, but also a lower CFT column installation space is secured, so that the upper CFT column can be constructed while securing these spaces as construction space such as the traffic lines of construction transport vehicles, etc. Then, by performing the following process after the preceding process, the lower CFT is constructed in the lower column installation space, and the upper CFT column and the lower CFT column are joined in the joining space, so that the lower CFT column and the upper CFT column that are continuous in the vertical direction can be constructed. In this way, by performing the preceding process and the following process in sequence, construction space such as the traffic lines of construction transport vehicles, etc. can be secured, and the lower CFT column and the upper CFT column that are continuous in the vertical direction can be suitably constructed while other construction work can be performed.

本発明の第2特徴構成は、前記後行工程では、前記下方側鋼管及び前記接合空間にコンクリートを充填して、前記下方側CFT柱の施工、及び、前記上方側CFT柱の下端部と前記下方側CFT柱の上端部との接合を行うコンクリート充填工程を行い、
そのコンクリート充填工程では、前記上方側鋼管の下端部と前記下方側鋼管の上端部との間に、基準充填動作を行ったときの基準充填量を基準としてそれ以上のコンクリートを充填可能な基準充填空間を予め確保しておき、コンクリートがその基準充填空間に到達するまでコンクリートを圧入充填させる第1圧入工程を行い、
その後、コンクリートが基準充填空間に到達すると、基準充填動作にて基準充填空間にコンクリートを圧入充填させる第2圧入工程を行う点にある。
The second characteristic configuration of the present invention is that in the subsequent process, a concrete filling process is carried out in which concrete is filled into the lower steel pipe and the joint space to construct the lower CFT column and join the lower end of the upper CFT column to the upper end of the lower CFT column,
In the concrete filling step, a standard filling space is secured in advance between the lower end of the upper steel pipe and the upper end of the lower steel pipe, which is capable of filling a standard amount of concrete based on a standard filling amount when a standard filling operation is performed, and a first pressing step is performed to press and fill the concrete until it reaches the standard filling space,
Thereafter, when the concrete reaches the reference filling space, a second pressing step is performed in which the concrete is pressed into the reference filling space by a reference filling operation.

下方側鋼管及び接合空間にコンクリートを充填するに当たり、コンクリートの充填量や圧入する圧力が過大になると、鋼管が膨れ上がる等の不都合を生じることになる。逆に、コンクリートの充填量が過小になると、隙間を埋めるために充填するグラウト等の充填材の注入量が増大してしまい、手間が掛かる等の施工性の面での不利が生じることになる。 When filling the lower steel pipe and the joint space with concrete, if the amount of concrete filled or the pressure applied is too high, it can cause problems such as the steel pipe swelling. Conversely, if the amount of concrete filled is too low, the amount of grout and other fillers that need to be injected to fill the gaps will increase, resulting in disadvantages in terms of workability, such as increased effort.

そこで、本構成によれば、下方側鋼管及び接合空間にコンクリートを充填するに当たり、まずは、第1圧入工程を行うことで、コンクリートが基準充填空間に到達するまでコンクリートをスムーズに圧入充填させることができる。その後、第2圧入工程を行い、基準充填動作を行うだけで、基準充填空間に対して基準充填量のコンクリートを充填させて、基準充填空間に対しても適切にコンクリートを充填させることができる。 Therefore, according to this configuration, when filling the lower steel pipe and the joint space with concrete, the first pressing step is first performed, which allows the concrete to be smoothly pressed in and filled until it reaches the standard filling space. After that, the second pressing step is performed, and by simply performing the standard filling operation, the standard filling amount of concrete can be filled into the standard filling space, and concrete can be appropriately filled into the standard filling space.

このように、第1圧入工程では、コンクリートの充填量が基準充填空間に到達するか否かだけを監視していればよく、第2圧入工程でも、単に、基準充填動作を行うだけでよいので、施工性の面で効果的な向上を図ることができる。しかも、基準充填動作を行ったときの基準充填量は予め把握しておくことができるので、予め把握した基準充填量を基準として基準充填空間の大きさを設定することで、基準充填空間に形成される隙間を無くす又はその隙間の大きさをより小さなものとすることができる。よって、基準充填空間に形成される隙間を無くす又はその隙間も小さくでき、その隙間を埋めるためのグラウト等の充填材を不要とする又はその充填材の注入量を少なくすることができ、この点からも、施工性の向上を図ることができる。 In this way, in the first pressing step, it is only necessary to monitor whether the filling amount of concrete reaches the standard filling space, and in the second pressing step, it is only necessary to simply perform the standard filling operation, so that effective improvements can be made in terms of workability. Moreover, since the standard filling amount when the standard filling operation is performed can be known in advance, by setting the size of the standard filling space based on the previously known standard filling amount, it is possible to eliminate gaps formed in the standard filling space or to make the size of the gap smaller. Thus, it is possible to eliminate gaps formed in the standard filling space or to make the gap smaller, and it is possible to eliminate the need for filler such as grout to fill the gap or to reduce the amount of filler injected, which also improves workability.

本発明の第3特徴構成は、コンクリートが基準充填空間に到達したか否かを確認するための第1確認孔部と、基準充填空間に対して充填材を注入するためであり、且つ、基準充填空間の隙間に充填材が注入されたか否かを確認するための第2確認孔部とが備えられている点にある。 The third characteristic feature of the present invention is that it is provided with a first confirmation hole for checking whether the concrete has reached the reference filling space, and a second confirmation hole for injecting the filler into the reference filling space and for checking whether the filler has been injected into the gap in the reference filling space.

本構成によれば、第1圧入工程において、第1確認孔部を用いることで、コンクリートが基準充填空間に到達したか否かを容易に確認することができ、コンクリートの充填量が過大又は過小になることなく、基準充填空間に到達するまでのコンクリートの充填を適切に行うことができる。しかも、第2確認孔部を用いることで、基準充填空間の隙間に対して適切な量のグラウト等の充填材を注入することができる。これにより、下方側鋼管及び接合空間に対して、コンクリートの充填量が過大又は過小となることなく、適切な量のコンクリートを充填することができる。 According to this configuration, by using the first confirmation hole in the first pressing step, it is possible to easily confirm whether the concrete has reached the standard filling space, and concrete can be appropriately filled until it reaches the standard filling space without filling the amount of concrete too much or too little. Furthermore, by using the second confirmation hole, an appropriate amount of grout or other filler can be injected into the gap in the standard filling space. This allows an appropriate amount of concrete to be filled into the lower steel pipe and the joint space, without filling the amount of concrete too much or too little.

本発明の第4特徴構成は、前記後行工程では、前記上方側CFT柱の下端部から下方側に延びる接合部を前記下方側鋼管の上端部に溶接接合して、その接合部にて前記接合空間を覆う溶接接合工程を行い、その後、前記コンクリート充填工程を行う点にある。 The fourth characteristic feature of the present invention is that in the subsequent process, the joint extending downward from the lower end of the upper CFT column is welded to the upper end of the lower steel pipe, and the welding process is performed to cover the joint space with the joint, and then the concrete filling process is performed.

本構成によれば、溶接接合工程を行うことで、接合部を用いて、上方側CFT柱の下端部と下方側鋼管の上端部とを溶接に適切に接合することができる。しかも、接合部は、上方側CFT柱の下端部から下方側に延びるので、接合部と下方側鋼管の上端部とを溶接する際に、下方側CFT柱に充填されたコンクリートに熱を与えてしまうのを防止して、そのコンクリートに悪影響が及ぶのを適切に防止することができる。 According to this configuration, by performing the welding joining process, the lower end of the upper CFT column and the upper end of the lower steel pipe can be appropriately welded together using the joint. Moreover, since the joint extends downward from the lower end of the upper CFT column, when welding the joint and the upper end of the lower steel pipe, it is possible to prevent heat from being applied to the concrete filled in the lower CFT column, and appropriately prevent adverse effects on the concrete.

上下方向に連続するCFT柱を示す図A diagram showing continuous CFT columns in the vertical direction 先行工程を示す図A diagram showing the preceding process 溶接接合工程を示す図Diagram showing the welding process 第1圧入工程を示す図FIG. 1 is a diagram showing a first press-in step. 第2圧入工程を示す図FIG. 2 shows a second press-in process. 隙間埋め工程を示す図Diagram showing the gap filling process

本発明に係るCFT柱の施工方法の実施形態について図面に基づいて説明する。
このCFT柱の施工方法は、図1に示すように、上下方向に連続する下方側CFT柱1と上方側CFT柱2とを構築するためのものである。下方側CFT柱1は、下方側鋼管11の内部の中空空間にコンクリート12を充填させたものであり、上方側CFT柱2も、上方側鋼管21の内部の中空空間にコンクリート22を充填させたものである。下方側鋼管11と上方側鋼管21は、同一の断面形状となっており、例えば、矩形状や円形状に形成されている。
An embodiment of a construction method for a CFT column according to the present invention will be described with reference to the drawings.
This CFT column construction method is for constructing a lower CFT column 1 and an upper CFT column 2 that are continuous in the vertical direction, as shown in Fig. 1. The lower CFT column 1 is formed by filling the hollow space inside a lower steel pipe 11 with concrete 12, and the upper CFT column 2 is formed by filling the hollow space inside an upper steel pipe 21 with concrete 22. The lower steel pipe 11 and the upper steel pipe 21 have the same cross-sectional shape, for example, rectangular or circular.

このようなCFT柱を施工するに当たり、通常、下方側CFT柱1を先行して施工し、その後、上方側CFT柱2を施工するという施工順序とすることが考えられる。しかしながら、例えば、下方側CFT柱1の設置箇所に工事の運搬車等の動線を確保しなければならない等、各種の施工条件によっては、先行して施工した下方側CFT柱1が邪魔になって、工事用スペースを確保できずに他の工事等が行えなくなる可能性がある。 When constructing such CFT columns, it is usually considered that the construction order is to construct the lower CFT column 1 first, followed by the upper CFT column 2. However, depending on various construction conditions, for example, the need to ensure a traffic route for construction transport vehicles at the installation location of the lower CFT column 1, the lower CFT column 1 that was constructed first may get in the way, making it impossible to secure construction space and making it impossible to carry out other construction work.

そこで、この実施形態では、上方側CFT柱2を先行して施工する先行工程を行い、その後、上方側鋼管21と下方側鋼管11とを接合して下方側CFT柱1を施工する後行工程を行うようにしている。 Therefore, in this embodiment, a preceding process is carried out in which the upper CFT column 2 is constructed first, and then a succeeding process is carried out in which the upper steel pipe 21 and the lower steel pipe 11 are joined to construct the lower CFT column 1.

建物等では、上下方向に連続する下方側CFT柱1と上方側CFT柱2とのCFT柱組が、水平方向に間隔を隔てて複数備えられている。そこで、複数のCFT柱組のうちから、工事用スペースを確保するために、適用対象となるCFT柱組を選定し、その選定したCFT柱組を構築するに当たり、上述の先行工程、後行工程を順次行うようにしている。適用対象とするCFT柱組は、1組でもよく、複数組でもよく、確保すべき工事用スペースの大きさや場所に応じて、適用対象とするCFT柱組を選定することができる。 In buildings, etc., multiple CFT column assemblies are provided with a horizontal gap between them, each consisting of a lower CFT column 1 and an upper CFT column 2 that are continuous in the vertical direction. Therefore, in order to secure work space, the target CFT column assembly is selected from among the multiple CFT column assemblies, and the above-mentioned preceding and following processes are carried out in sequence when constructing the selected CFT column assembly. The target CFT column assembly may be one set or multiple sets, and the target CFT column assembly can be selected depending on the size and location of the work space to be secured.

以下、先行工程及び後行工程について説明するが、図1に示すように、上下方向に連続する下方側CFT柱1と上方側CFT柱2との1組のCFT柱組を構築する場合について説明する。 The preceding and following processes are explained below, but we will explain the case of constructing a set of CFT columns consisting of a lower CFT column 1 and an upper CFT column 2 that are continuous in the vertical direction, as shown in Figure 1.

先行工程では、図2に示すように、下方側に下方側CFT柱設置空間3及び接合空間4を確保する状態で上方側鋼管21を設置し、その上方側鋼管21の内部にコンクリート22を充填させて上方側CFT柱2を先行して施工する。 In the preceding process, as shown in Figure 2, the upper steel pipe 21 is installed while securing the lower CFT column installation space 3 and the joint space 4 on the lower side, and the upper steel pipe 21 is filled with concrete 22 to construct the upper CFT column 2 in advance.

上方側鋼管21において下端部に相当する位置には、プレート等にて内部空間を閉塞する底壁部23が備えられている。上方側鋼管21は、建物の躯体等に連結されたトラス等の仮設材31にて支持されており、上方側鋼管21の底壁部23と下方側CFT柱1を設置する地面等の設置面5との間に、下方側CFT柱設置空間3と接合空間4とを上下方向に並べる状態で確保している。上方側鋼管21の内部へのコンクリート22の充填については、トレミー管またはフレキシブルホース等を用いて、上方側鋼管21の上端部からその内部にコンクリート22を打設する落とし込み工法により、上方側鋼管21の内部にコンクリート22を充填している。 At a position corresponding to the lower end of the upper steel pipe 21, a bottom wall portion 23 is provided that closes the internal space with a plate or the like. The upper steel pipe 21 is supported by temporary materials 31 such as trusses connected to the building frame, etc., and the lower CFT column installation space 3 and the joint space 4 are secured in a vertically aligned state between the bottom wall portion 23 of the upper steel pipe 21 and the installation surface 5 such as the ground on which the lower CFT column 1 is installed. The concrete 22 is filled into the interior of the upper steel pipe 21 by a drop-in method in which the concrete 22 is poured into the interior of the upper steel pipe 21 from its upper end using a tremie pipe or flexible hose, etc.

後行工程では、まず、図3に示すように、上方側鋼管21の下端部と下方側鋼管11の上端部とを溶接接合する溶接接合工程を行い、その後、図4及び図5に示すように、下方側鋼管11の内部及び接合空間4にコンクリート12を充填するコンクリート充填工程を行っている。 In the subsequent process, first, as shown in FIG. 3, a welding joining process is performed in which the lower end of the upper steel pipe 21 and the upper end of the lower steel pipe 11 are welded together, and then, as shown in FIG. 4 and FIG. 5, a concrete filling process is performed in which concrete 12 is filled inside the lower steel pipe 11 and into the joint space 4.

溶接接合工程では、図3に示すように、上方側鋼管21の下端部から下方側に延びる接合部41(図2参照)を下方側鋼管11の上端部に溶接接合して、その接合部41にて接合空間4を覆うようにしている。接合部41は、上方側鋼管21と同一の断面形状を有する中空状に形成され、その内部の周囲を覆う状態で下方側に延びる板状体にて構成されている。下方側鋼管11の上端部には、上方側に延びる裏当て部42が備えられ、その裏当て部42を接合部41の内壁部に当接させる状態で、下方側鋼管11の上端部と接合部41の下端部とが溶接接合されている。 In the welding process, as shown in FIG. 3, the joint 41 (see FIG. 2) extending downward from the lower end of the upper steel pipe 21 is welded to the upper end of the lower steel pipe 11 so that the joint 41 covers the joint space 4. The joint 41 is formed in a hollow shape with the same cross-sectional shape as the upper steel pipe 21, and is composed of a plate-like body extending downward while covering the inside periphery. The upper end of the lower steel pipe 11 is provided with a backing part 42 extending upward, and the upper end of the lower steel pipe 11 and the lower end of the joint 41 are welded together with the backing part 42 abutting against the inner wall of the joint 41.

コンクリート充填工程では、図4及び図5に示すように、下方側鋼管11及び接合空間4にコンクリート12を充填して、下方側CFT柱1の施工、及び、上方側CFT柱2の下端部と下方側CFT柱1の上端部との接合を行っている。このときの下方側鋼管11及び接合空間4へのコンクリート12の充填については、図4及び図5における矢印に示すように、圧送配管47を下方側鋼管11の柱脚部等の圧入口46に接続して、ポンプ車等のコンクリートポンプから圧送配管47及び誘導管48を通してコンクリート12を圧入する圧入工法により、コンクリート12を充填している。 In the concrete filling process, as shown in Figures 4 and 5, concrete 12 is filled into the lower steel pipe 11 and the joint space 4, and the lower CFT column 1 is constructed and the lower end of the upper CFT column 2 is joined to the upper end of the lower CFT column 1. At this time, concrete 12 is filled into the lower steel pipe 11 and the joint space 4 by a pressurization method in which a pressure feed pipe 47 is connected to a pressure inlet 46 at the base of the lower steel pipe 11, and concrete 12 is pressed in from a concrete pump such as a pump truck through the pressure feed pipe 47 and guide pipe 48, as shown by the arrows in Figures 4 and 5.

接合空間4には、図3に示すように、上方側鋼管21側の上端部位(上方側鋼管21の底壁部23に隣接する部位)に、基準充填空間43が予め確保されている。この基準充填空間43は、圧入工法にて基準充填動作を行ったときの基準充填量を基準としてそれ以上のコンクリート12を充填可能な空間として設定されている。基準充填動作は、例えば、コンクリートポンプにてコンクリート12を圧入する動作を1回行う動作(ワンプッシュ)としている。基準充填動作を行ったときの基準充填量は、実験やコンクリートポンプの能力等により予め求めておくことができる。 As shown in FIG. 3, a standard filling space 43 is secured in advance in the upper end portion of the upper steel pipe 21 (the portion adjacent to the bottom wall portion 23 of the upper steel pipe 21) in the joint space 4. This standard filling space 43 is set as a space that can be filled with more concrete 12 than the standard filling amount when a standard filling operation is performed by the pressing method. The standard filling operation is, for example, an operation of pressing in concrete 12 once with a concrete pump (one push). The standard filling amount when the standard filling operation is performed can be obtained in advance by experiment, the capacity of the concrete pump, etc.

そこで、基準充填空間43の大きさについては、基準充填空間43に基準充填量のコンクリート12を充填したときに多少の隙間47(図5参照)ができるように、基準充填量に、隙間47を埋めるための充填材46(例えば、グラウト)の充填量分を加えた量に設定されている。このように、予め求めた基準充填量を基準にして基準充填空間43の大きさを設定しているので、充填材46の充填量が大きくなり過ぎるのを防止できるとともに、コンクリート12を充填するための動作としても、基準充填動作を行うだけでよく、施工性の向上を図ることができる。 The size of the standard filling space 43 is therefore set to the standard filling amount plus the amount of filler 46 (e.g., grout) used to fill the gaps 47, so that some gaps 47 (see FIG. 5) will be created when the standard filling amount of concrete 12 is filled into the standard filling space 43. In this way, the size of the standard filling space 43 is set based on the standard filling amount determined in advance, so that the amount of filler 46 to be filled can be prevented from becoming too large, and the operation for filling the concrete 12 can be improved by simply performing the standard filling operation.

接合空間4における接合部41には、図3に示すように、基準充填空間43の下端部に相当する位置に、コンクリート12が基準充填空間43に到達したか否かを確認するための第1確認孔44が配設されている。図4に示すように、圧入工法によりコンクリート12を充填するので(図4の矢印参照)、下方側から上方側に向けてコンクリート12が充填されていく。よって、第1確認孔44からコンクリート12が噴出することで、基準充填空間43の下端部に相当する位置までコンクリート12が充填されたことを認識することができ、コンクリート12が基準充填空間43に到達したことを確認することができる。 As shown in Fig. 3, the joint 41 in the joint space 4 has a first confirmation hole 44 at a position corresponding to the lower end of the reference filling space 43 to confirm whether the concrete 12 has reached the reference filling space 43. As shown in Fig. 4, the concrete 12 is filled by the pressing method (see the arrow in Fig. 4), so that the concrete 12 is filled from the lower side to the upper side. Therefore, by the concrete 12 being ejected from the first confirmation hole 44, it is possible to recognize that the concrete 12 has been filled up to the position corresponding to the lower end of the reference filling space 43, and it is possible to confirm that the concrete 12 has reached the reference filling space 43.

接合空間4における接合部41には、図3に示すように、第1確認孔44に加えて、第2確認孔45が備えられている。第2確認孔45は、基準充填空間43の上端部に相当する位置(上方側鋼管21の底壁部23に隣接する位置)に配設されている。第2確認孔45は、図6に示すように、基準充填空間43に対して充填材46を注入するためであり(図6の矢印参照)、且つ、基準充填空間43の隙間47(図5参照)に充填材46が注入されたか否かを確認するために用いられている。図5に示すように、圧入工法により下方側から上方側に向けてコンクリート12が充填されていくので、基準充填空間43の上方側に隙間47が形成される。よって、図6に示すように、基準充填空間43の上端部に相当する位置に配設された第2確認孔45から充填材46を注入することで、基準充填空間43の上方側に形成された隙間47を埋めることができる。また、第2確認孔45から充填材46が噴出することで、基準充填空間43の隙間47に充填材46が注入されたことを確認することができる。 As shown in FIG. 3, the joint 41 in the joint space 4 is provided with a second confirmation hole 45 in addition to the first confirmation hole 44. The second confirmation hole 45 is arranged at a position corresponding to the upper end of the reference filling space 43 (a position adjacent to the bottom wall portion 23 of the upper steel pipe 21). As shown in FIG. 6, the second confirmation hole 45 is used to inject the filler 46 into the reference filling space 43 (see the arrow in FIG. 6), and to check whether the filler 46 has been injected into the gap 47 (see FIG. 5) of the reference filling space 43. As shown in FIG. 5, the concrete 12 is filled from the lower side to the upper side by the press-in method, so that a gap 47 is formed on the upper side of the reference filling space 43. Therefore, as shown in FIG. 6, the gap 47 formed on the upper side of the reference filling space 43 can be filled by injecting the filler 46 from the second confirmation hole 45 arranged at a position corresponding to the upper end of the reference filling space 43. In addition, by ejecting the filler 46 from the second confirmation hole 45, it is possible to confirm that the filler 46 has been injected into the gap 47 of the reference filling space 43.

このように、接合空間4に基準充填空間43を予め確保しておき、第1確認孔44及び第2確認孔45を接合部41に備えさせた状態において、コンクリート充填工程を行っている。コンクリート充填工程では、第1圧入工程(図4参照)、第2圧入工程(図5参照)の順に行うことで、下方側鋼管11及び接合空間4にコンクリート12を充填しており、最後に、隙間埋め工程(図6参照)を行うことで、基準充填空間43に形成される隙間47を充填材46にて埋めるようにしている。 In this way, the standard filling space 43 is secured in advance in the joint space 4, and the first confirmation hole 44 and the second confirmation hole 45 are provided in the joint 41, and then the concrete filling process is carried out. In the concrete filling process, the first pressing process (see FIG. 4) and the second pressing process (see FIG. 5) are carried out in that order to fill the lower steel pipe 11 and the joint space 4 with concrete 12, and finally, the gap filling process (see FIG. 6) is carried out to fill the gap 47 formed in the standard filling space 43 with the filler material 46.

第1圧入工程では、図4に示すように、圧入工法により基準充填空間43に到達するまでコンクリート12を圧入充填させている(図4の矢印参照)。コンクリート12が基準充填空間43に到達したか否かは、第1確認孔44からコンクリート12が噴出するか否かによって確認している。基準充填空間43に到達したことを確認すると、閉塞体等により第1確認孔44を閉塞させる。 In the first pressing step, as shown in FIG. 4, concrete 12 is pressed in by a pressing method until it reaches the reference filling space 43 (see the arrow in FIG. 4). Whether or not the concrete 12 has reached the reference filling space 43 is confirmed by whether or not the concrete 12 erupts from the first confirmation hole 44. Once it is confirmed that the concrete 12 has reached the reference filling space 43, the first confirmation hole 44 is blocked by a blocking body or the like.

第2圧入工程では、図5に示すように、圧入工法により基準充填動作にて基準充填空間43にコンクリート12を圧入充填させている(図4の矢印参照)。これにより、第2圧入工程では、単に、基準充填動作を行うだけでよいので、施工性の面で効果的な向上を図ることができる。 In the second pressing step, as shown in FIG. 5, concrete 12 is pressed into the standard filling space 43 by the standard filling operation using the pressing method (see the arrow in FIG. 4). As a result, in the second pressing step, it is sufficient to simply perform the standard filling operation, which effectively improves workability.

隙間埋め工程では、図6に示すように、基準充填空間43の上方側に充填材46(例えば、グラウト)を注入して、基準充填空間43の上方側に形成される隙間47(図5参照)を充填材46にて埋めている(図6の矢印参照)。このとき、第2確認孔45を通して基準充填空間43に充填材46を注入することで、隙間47が形成される基準充填空間43の上方側に充填材46を注入することができる。また、基準充填空間43の隙間47に充填材46を注入してその隙間47を埋めることができたか否かは、第2確認孔45から充填材46が噴出するか否かによって確認している。隙間47を埋めることができたことを確認すると、閉塞体等により第2確認孔45を閉塞させる。 In the gap filling process, as shown in FIG. 6, a filler 46 (e.g., grout) is injected into the upper side of the reference filling space 43 to fill the gap 47 (see FIG. 5) formed on the upper side of the reference filling space 43 with the filler 46 (see the arrow in FIG. 6). At this time, by injecting the filler 46 into the reference filling space 43 through the second confirmation hole 45, the filler 46 can be injected into the upper side of the reference filling space 43 where the gap 47 is formed. In addition, whether or not the filler 46 has been injected into the gap 47 of the reference filling space 43 and the gap 47 has been filled is confirmed by whether or not the filler 46 has been sprayed out from the second confirmation hole 45. When it is confirmed that the gap 47 has been filled, the second confirmation hole 45 is blocked by a blocking body or the like.

このようにして、第1圧入工程にて基準充填空間43の下端部までコンクリート12を充填し、第2圧入工程にて基準充填空間43において基準充填量だけのコンクリート12を充填し、隙間埋め工程にて基準充填空間43の上方側の隙間47を充填材46にて埋めている。 In this way, concrete 12 is filled up to the lower end of the reference filling space 43 in the first pressing process, the reference filling space 43 is filled with only the reference filling amount of concrete 12 in the second pressing process, and the gap 47 above the reference filling space 43 is filled with the filling material 46 in the gap filling process.

上下方向に連続する下方側CFT柱1と上方側CFT柱2との1組のCFT柱組を構築する場合を説明したが、複数組のCFT柱組を構築する場合には、例えば、複数組に対して、先行工程及び後行工程の夫々を併行して同時に施工することができる。また、優先順位等に応じて施工順序を設定し、先行工程、後行工程を順次行う形態で設定した施工順序にしたがって施工することもできる。 The above describes the construction of one CFT column assembly consisting of a lower CFT column 1 and an upper CFT column 2 that are continuous in the vertical direction, but when constructing multiple CFT column assemblies, for example, the preceding and following processes can be carried out simultaneously for multiple sets. In addition, the construction order can be set according to priorities, etc., and construction can be carried out according to the set construction order in which the preceding and following processes are carried out in sequence.

〔別実施形態〕
本発明の他の実施形態について説明する。尚、以下に説明する各実施形態の構成は、夫々単独で適用することに限らず、他の実施形態の構成と組み合わせて適用することも可能である。
[Another embodiment]
Other embodiments of the present invention will be described below. Note that the configurations of the embodiments described below are not limited to being applied alone, but may also be applied in combination with the configurations of other embodiments.

(1)上記実施形態では、第1圧入工程において、第1確認孔44を用いて、基準充填空間43に到達したことを確認しているが、第1確認孔44に限らず、別途、基準充填空間43に到達したことを確認するための構成を採用することもできる。 (1) In the above embodiment, the first confirmation hole 44 is used to confirm that the reference filling space 43 has been reached in the first pressing step, but it is not limited to the first confirmation hole 44, and a separate configuration for confirming that the reference filling space 43 has been reached can also be adopted.

(2)上記実施形態では、隙間埋め工程において、第2確認孔45を用いて、基準充填空間43の隙間47に充填材46を注入してその隙間47を埋めることができたかを確認しているが、第2確認孔45に限らず、別途、基準充填空間43の隙間47を埋めることができたかを確認するための構成を採用することもできる。 (2) In the above embodiment, in the gap filling process, the second confirmation hole 45 is used to inject the filler 46 into the gap 47 in the reference filling space 43 to confirm whether the gap 47 has been filled. However, it is not limited to the second confirmation hole 45, and a separate configuration can also be adopted to confirm whether the gap 47 in the reference filling space 43 has been filled.

(3)上記実施形態では、基準充填空間43の大きさを、基準充填量に充填材46(例えば、グラウト)の充填量分を加えた量に設定して、基準充填量よりも大きく設定している。これに代えて、基準充填空間43の大きさを基準充填量と同一の大きさに設定することもできる。この場合には、第2確認孔45を不要とすることができる。 (3) In the above embodiment, the size of the reference filling space 43 is set to the reference filling amount plus the amount of filling material 46 (e.g., grout), which is set to be larger than the reference filling amount. Alternatively, the size of the reference filling space 43 can be set to the same size as the reference filling amount. In this case, the second confirmation hole 45 can be eliminated.

1 下方側CFT柱
2 上方側CFT柱
3 下方側CFT柱設置空間
4 接合空間
11 下方側鋼管
12 コンクリート
21 上方側鋼管
22 コンクリート
41 接合部
43 基準充填空間
44 第1確認孔
45 第2確認孔
46 充填材
47 隙間

1 Lower CFT column 2 Upper CFT column 3 Lower CFT column installation space 4 Joint space 11 Lower steel pipe 12 Concrete 21 Upper steel pipe 22 Concrete 41 Joint 43 Standard filling space 44 First confirmation hole 45 Second confirmation hole 46 Filling material 47 Gap

Claims (4)

上下方向に連続する下方側CFT柱と上方側CFT柱とを構築するCFT柱の施工方法において、
下方側に下方側CFT柱設置空間及び接合空間を確保する状態で上方側鋼管を設置し、その上方側鋼管の内部にコンクリートを充填させて上方側CFT柱を先行して施工する先行工程を行い、
その後、前記下方側CFT設置空間に下方側鋼管を設置し、その下方側鋼管の内部にコンクリートを充填させて下方側CFT柱を施工し、前記接合空間にて前記上方側CFT柱の下端部と前記下方側CFT柱の上端部とを接合する後行工程を行うCFT柱の施工方法。
In a construction method for a CFT column, a lower CFT column and an upper CFT column that are continuous in the vertical direction are constructed,
The upper steel pipe is installed in a state where the lower CFT column installation space and the joint space are secured on the lower side, and the upper steel pipe is filled with concrete to carry out the preliminary process of constructing the upper CFT column in advance.
This is a CFT column construction method in which a lower steel pipe is then installed in the lower CFT installation space, the inside of the lower steel pipe is filled with concrete to construct the lower CFT column, and a subsequent process is performed to join the lower end of the upper CFT column and the upper end of the lower CFT column in the joint space.
前記後行工程では、前記下方側鋼管及び前記接合空間にコンクリートを充填して、前記下方側CFT柱の施工、及び、前記上方側CFT柱の下端部と前記下方側CFT柱の上端部との接合を行うコンクリート充填工程を行い、
そのコンクリート充填工程では、前記上方側鋼管の下端部と前記下方側鋼管の上端部との間に、基準充填動作を行ったときの基準充填量を基準としてそれ以上のコンクリートを充填可能な基準充填空間を予め確保しておき、コンクリートがその基準充填空間に到達するまでコンクリートを圧入充填させる第1圧入工程を行い、
その後、コンクリートが基準充填空間に到達すると、基準充填動作にて基準充填空間にコンクリートを圧入充填させる第2圧入工程を行う請求項1のCFT柱の施工方法。
In the subsequent process, a concrete filling process is carried out in which concrete is filled into the lower steel pipe and the joint space to construct the lower CFT column and join the lower end of the upper CFT column to the upper end of the lower CFT column,
In the concrete filling step, a standard filling space is secured in advance between the lower end of the upper steel pipe and the upper end of the lower steel pipe, which is capable of filling a standard amount of concrete based on a standard filling amount when a standard filling operation is performed, and a first pressing step is performed to press and fill the concrete until it reaches the standard filling space,
The construction method for a CFT column according to claim 1, wherein when the concrete reaches the reference filling space, a second pressing step is performed in which the concrete is pressed into the reference filling space by a reference filling operation.
コンクリートが基準充填空間に到達したか否かを確認するための第1確認孔部と、基準充填空間に対して充填材を注入するためであり、且つ、基準充填空間の隙間に充填材が注入されたか否かを確認するための第2確認孔部とが備えられている請求項2に記載のCFT柱の施工方法。 The construction method for a CFT column according to claim 2, which is provided with a first confirmation hole for confirming whether the concrete has reached the reference filling space, and a second confirmation hole for injecting a filler into the reference filling space and for confirming whether the filler has been injected into the gap in the reference filling space. 前記後行工程では、前記上方側CFT柱の下端部から下方側に延びる接合部を前記下方側鋼管の上端部に溶接接合して、その接合部にて前記接合空間を覆う溶接接合工程を行い、その後、前記コンクリート充填工程を行う請求項2又は3に記載のCFT柱の施工方法。 The construction method for CFT columns according to claim 2 or 3, in which, in the subsequent process, a joint extending downward from the lower end of the upper CFT column is welded to the upper end of the lower steel pipe, and a welding joining process is performed in which the joint covers the joint space, and then the concrete filling process is performed.
JP2021010900A 2021-01-27 2021-01-27 Construction method of CFT pillars Active JP7549541B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021010900A JP7549541B2 (en) 2021-01-27 2021-01-27 Construction method of CFT pillars

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021010900A JP7549541B2 (en) 2021-01-27 2021-01-27 Construction method of CFT pillars

Publications (2)

Publication Number Publication Date
JP2022114575A JP2022114575A (en) 2022-08-08
JP7549541B2 true JP7549541B2 (en) 2024-09-11

Family

ID=82747272

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021010900A Active JP7549541B2 (en) 2021-01-27 2021-01-27 Construction method of CFT pillars

Country Status (1)

Country Link
JP (1) JP7549541B2 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150113913A1 (en) 2012-05-29 2015-04-30 Ajou University Industry-Academic Cooperation Foundation Hollow structure, and preparation method thereof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150113913A1 (en) 2012-05-29 2015-04-30 Ajou University Industry-Academic Cooperation Foundation Hollow structure, and preparation method thereof

Also Published As

Publication number Publication date
JP2022114575A (en) 2022-08-08

Similar Documents

Publication Publication Date Title
KR101582173B1 (en) The structure assembly for building a tunnel and building method thereof
KR102075165B1 (en) Concrete filled tubular column and connecting structure of the same and construction method thereof
KR101672924B1 (en) Fire proof reinforced panel using high strength steel plate and construction method of the same
KR101453407B1 (en) Non-welding type seismic reinforcing method for column using key hole type bolt jointed double C-type steels
JP7186017B2 (en) Joint structure between column and beam, and construction method for joint structure between column and beam
KR20050065915A (en) Steel plate shear wall with precast concrete panel
JP6888970B2 (en) Construction method of joint structure between column and beam and joint structure between column and beam
JP7549541B2 (en) Construction method of CFT pillars
KR101567742B1 (en) PHC pile and construction method of underground structure using the same
KR101939949B1 (en) Half-pc column based on framed rebar column
WO2009025406A1 (en) Structure of retaining wall and method for construction of the same
JP2007277880A (en) Fill structure and its construction method
JP5498295B2 (en) Construction method for underground structures
KR101805434B1 (en) Sturcture of composite beam using wire tensioning and Construction method thereof
KR101781264B1 (en) Structure of self-stand retaining wall and its installation method
JP6256383B2 (en) Column and pile joining method and structure
KR102768491B1 (en) Multi-Stage Pressure Maintaining Device for Pressurized Ground Reinforcement Method and Pressurized Ground Reinforcement Method Using the Same
JP6766468B2 (en) Segment wall and tunnel lining
JP3826348B2 (en) Construction method of composite wall with mountain retaining core and underground outer wall
JP6871493B2 (en) Pile head reinforcement structure
KR102522455B1 (en) Grouting messer shield method using messer shield pannel and square tube plate
JP4673244B2 (en) Method of joining steel columns and ready-made piles
JP5245856B2 (en) Concrete filled steel segment
KR101657880B1 (en) Assembling method of underground structure and underground structure thereby
JP4077460B2 (en) Concrete block products

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20231221

TRDD Decision of grant or rejection written
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20240724

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240807

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240830

R150 Certificate of patent or registration of utility model

Ref document number: 7549541

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150