JP7570246B2 - Production process control system and production process control method - Google Patents
Production process control system and production process control method Download PDFInfo
- Publication number
- JP7570246B2 JP7570246B2 JP2021016723A JP2021016723A JP7570246B2 JP 7570246 B2 JP7570246 B2 JP 7570246B2 JP 2021016723 A JP2021016723 A JP 2021016723A JP 2021016723 A JP2021016723 A JP 2021016723A JP 7570246 B2 JP7570246 B2 JP 7570246B2
- Authority
- JP
- Japan
- Prior art keywords
- production process
- worker
- production
- information
- position information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Landscapes
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
本発明は、生産工程管理システム及び生産工程管理方法に関する。 The present invention relates to a production process management system and a production process management method.
一般的に、土木工事及び建設現場において、コンクリート部材を用いる際、建設現場でコンクリートを打設してコンクリート部材を完成させる現場打ち工法、又は工場でコンクリート部材を生産して建設現場に持ち込むプレキャスト工法が採用されている。 Generally, when concrete components are used in civil engineering and construction work, either the cast-in-place method, in which concrete is poured at the construction site to complete the concrete components, or the precast method, in which concrete components are produced in a factory and brought to the construction site, is used.
プレキャスト工法は、工場で生産されたコンクリート部材を建設現場まで運搬しなければならないが、建設現場においてコンクリートを打設する必要がない。また、プレキャスト工法は、適切な設備及び検査環境を有する工場でコンクリート部材を生産することにより、高品質、品質の安定性及び作業の安全性が期待でき、建設現場等での工期短縮や作業員の省人化が可能となる。 With the precast method, concrete components produced in a factory must be transported to the construction site, but there is no need to pour the concrete at the construction site. In addition, by producing concrete components in a factory with appropriate equipment and an inspection environment, the precast method is expected to ensure high quality, stable quality, and work safety, and it can shorten construction times and reduce the number of workers required at construction sites.
ところで、土木工事、建設現場及び工場等に限らず、製品の製造が行われる作業現場等においては、様々な工夫により生産効率の向上が図られている。 By the way, in civil engineering works, construction sites, factories, and other workplaces where products are manufactured, various efforts are being made to improve production efficiency.
例えば、特許文献1では、作業現場での作業内容を容易に把握可能な作業データ管理システム等に関する技術が開示されている。具体的には、特許文献1に開示されている作業データ管理システムは、作業現場の映像データに基づいて、作業現場で作業者によって行われる作業を複数の時系列的な詳細工程に分類し、当該映像データ及び詳細工程を可視化している。このように各詳細工程における作業内容を把握することによって、製品の品質や生産性の向上を図っている。 For example, Patent Document 1 discloses technology relating to a work data management system that makes it easy to grasp the work content at a work site. Specifically, the work data management system disclosed in Patent Document 1 classifies the work performed by workers at the work site into multiple chronological detailed processes based on video data of the work site, and visualizes the video data and the detailed processes. In this way, by grasping the work content at each detailed process, product quality and productivity are improved.
しかしながら、特許文献1に記載の作業データ管理システムでは、作業現場の映像データに基づいて詳細工程に分類したり、種々のデータ分析を行なったりしているため、作業現場において、広範囲に、かつ死角が生じないように、適切な位置に複数のカメラを設置しなければならないという問題がある。 However, the work data management system described in Patent Document 1 classifies work site video data into detailed processes and performs various data analyses, which creates the problem that multiple cameras must be installed in appropriate locations at the work site to cover a wide area and avoid blind spots.
また、プレキャストコンクリートを生産する工場では、大型の設備、機材及び部材が配置されているため、複数のカメラを設置したとしても、工場内の広範囲において、映像データに基づいて種々の分析を行うことは容易ではない。また、工場が半屋外である場合には、埃等により、カメラのメンテナスも大変となる。 In addition, because precast concrete factories are equipped with large facilities, equipment, and components, even if multiple cameras are installed, it is not easy to perform various analyses based on video data over a wide area of the factory. In addition, if the factory is semi-outdoors, dust, etc. can make camera maintenance difficult.
そこで、本発明は、適切に生産工程を管理できる生産工程管理システム及び生産工程管理方法を提供することを目的とする。 The present invention aims to provide a production process management system and a production process management method that can appropriately manage the production process.
本発明の一態様に係る生産工程管理システムは、建設部材の生産工程に関する生産工程情報を取得する生産工程情報取得部と、建設部材の生産工程に用いられる建設機器の位置情報を取得する第1位置情報取得部と、生産工程のうち、建設機器の位置情報に基づいて建設機器を用いる機器使用工程期間を判定する工程判定部と、を備える。 A production process management system according to one embodiment of the present invention includes a production process information acquisition unit that acquires production process information related to the production process of construction materials, a first position information acquisition unit that acquires position information of construction equipment used in the production process of the construction materials, and a process determination unit that determines the equipment use process period in the production process that uses the construction equipment based on the position information of the construction equipment.
この態様によれば、工程判定部が、生産工程のうち、建設機器の位置情報に基づいて建設機器を用いる機器使用工程期間を判定するため、適切に生産工程を管理することができる。 According to this aspect, the process determination unit determines the equipment use process period during the production process in which construction equipment is used based on the location information of the construction equipment, so that the production process can be managed appropriately.
上記態様において、第1位置情報取得部は、建設機器が第1領域に第1閾値以上の間、継続して滞留しているか否かに関する建設機器の位置情報を取得してもよい。 In the above aspect, the first location information acquisition unit may acquire location information of the construction equipment regarding whether the construction equipment has been continuously present in the first area for a period of time equal to or longer than a first threshold.
この態様によれば、第1位置情報取得部が、建設機器が第1領域に第1閾値以上の間、継続して滞留しているか否かに基づいて、当該建設機械の位置情報を取得し、第1領域に建設機械が滞留しているか否かを適切に把握する。そして、工程判定部は、生産工程のうち、適切に機器使用工程期間を判定するため、より適切に生産工程を管理することができる。 According to this aspect, the first location information acquisition unit acquires location information of the construction machine based on whether the construction machine has been continuously present in the first area for a period of time equal to or longer than the first threshold, and appropriately determines whether the construction machine is present in the first area. The process determination unit then appropriately determines the equipment use process period within the production process, thereby enabling more appropriate management of the production process.
上記態様において、工程判定部は、生産工程情報に基づいて、生産工程のうち、少なくとも1つ以上の機器使用工程以外の工程期間を判定してもよい。 In the above aspect, the process determination unit may determine the process period of at least one or more equipment use processes among the production processes based on the production process information.
この態様によれば、工程判定部は、生産工程情報に基づいて、生産工程のうち、少なくとも1つ以上の機器使用工程以外の工程期間を判定するため、機器使用工程のみならず他の工程期間を判定でき、より適切に生産工程を管理することができる。 According to this aspect, the process determination unit determines the process duration of at least one or more equipment use processes among the production processes based on the production process information, so that it is possible to determine the process durations of not only the equipment use processes but also other processes, and to more appropriately manage the production process.
上記態様において、作業者が生産工程のうち担当可能な生産工程を含む作業者情報を取得する作業者情報取得部と、作業者の位置情報を取得する第2位置情報取得部と、をさらに備え、工程判定部は、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の開始時及び終了時を判定してもよい。 In the above aspect, the system further includes a worker information acquisition unit that acquires worker information including production processes that the worker can take charge of among the production processes, and a second location information acquisition unit that acquires location information of the worker, and the process determination unit may determine the start and end times of at least one or more process periods included in the production process based on the location information of the worker and the worker information.
この態様によれば、工程判定部は、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の開始時及び終了時を判定するため、各工程期間を、より詳細に、実態に沿って把握することができ、より適切に生産工程を管理することができる。 According to this aspect, the process determination unit determines the start and end times of at least one or more process periods included in the production process based on the worker's location information and worker information, so that each process period can be grasped in more detail and in line with the actual situation, and the production process can be managed more appropriately.
上記態様において、工程判定部は、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の作業実績を判定してもよい。 In the above aspect, the process determination unit may determine the work performance for at least one process period included in the production process based on the worker's location information and the worker information.
この態様によれば、工程判定部は、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の作業実績を判定するため、各工程の作業実績を把握しつつ、より適切に生産工程を管理することができる。 According to this aspect, the process determination unit determines the work performance for at least one or more process periods included in the production process based on the worker's location information and worker information, so that the production process can be managed more appropriately while understanding the work performance of each process.
上記態様において、第2位置情報取得部は、作業者が第2領域に第2閾値以上の間、継続して滞留しているか否かに関する作業者の位置情報を取得してもよい。 In the above aspect, the second location information acquisition unit may acquire location information of the worker regarding whether the worker has been continuously present in the second area for a period of time equal to or longer than the second threshold.
この態様によれば、第2位置情報取得部が、作業者が第2領域に第2閾値以上の間、継続して滞留しているか否かに基づいて、当該作業者の位置情報を取得し、第2領域に作業者が滞留しているか否かを適切に把握する。そして、工程判定部は、生産工程の工程期間の作業実績を判定するため、より適切に生産工程を管理することができる。 According to this aspect, the second location information acquisition unit acquires location information of the worker based on whether the worker has been continuously in the second area for a period equal to or longer than the second threshold, and appropriately determines whether the worker is in the second area. Then, the process determination unit determines the work performance during the process period of the production process, and thus can more appropriately manage the production process.
上記態様において、第2領域及び第2閾値は、生産工程の各工程に応じて設定されてもよい。 In the above embodiment, the second region and the second threshold value may be set according to each step of the production process.
この態様によれば、第2領域及び第2閾値は、生産工程の各工程に応じて設定されるため、第2位置情報取得部は、各工程に応じた適切な領域及び閾値に基づいて、作業者の位置情報を取得し、当該領域に作業者が滞留しているか否かを適切に把握する。これにより、工程判定部は、生産工程の工程期間の実績を工程毎に適切に判定するため、より適切に生産工程を管理することができる。 According to this aspect, the second area and the second threshold are set according to each process in the production process, so that the second location information acquisition unit acquires the location information of the worker based on the appropriate area and threshold according to each process, and appropriately determines whether the worker is staying in that area. This allows the process determination unit to appropriately determine the actual process period of the production process for each process, and therefore allows for more appropriate management of the production process.
上記態様において、建設機器は、コンクリート打設機又は生コンホッパーであり、機器使用工程は、打設工程であってもよい。 In the above embodiment, the construction equipment may be a concrete pouring machine or a ready-mixed concrete hopper, and the equipment use process may be a pouring process.
この態様によれば、工程判定部は、コンクリート打設機又は生コンホッパーの位置情報に基づいて、当該コンクリート打設機又は生コンホッパーを用いる機器使用工程である打設工程の期間を判定することができる。これにより、コンクリート部材の生産工程において、適切に生産工程を管理することができる。 According to this aspect, the process determination unit can determine the duration of the pouring process, which is an equipment use process that uses a concrete pouring machine or a ready-mixed concrete hopper, based on the position information of the concrete pouring machine or the ready-mixed concrete hopper. This makes it possible to appropriately manage the production process in the production process of concrete members.
上記態様において、機器使用工程以外の工程は、セット工程及び脱型工程のうち、少なくともいずれかの工程を含んでもよい。 In the above embodiment, the steps other than the device use step may include at least one of a setting step and a demolding step.
この態様によれば、工程判定部は、打設工程の前後であるセット工程及び脱型工程のうち、少なくともいずれかの工程の期間を判定することができる。これにより、コンクリート部材の生産工程において、より適切に生産工程を管理することができる。 According to this aspect, the process determination unit can determine the duration of at least one of the setting process and the demolding process, which are performed before and after the casting process. This allows for more appropriate management of the production process of concrete members.
上記態様において、建設部材は、プレキャストコンクリートであってもよい。 In the above embodiment, the construction member may be precast concrete.
この態様によれば、プレキャスト工場におけるプレキャストコンクリートの生産工程において、適切に生産工程を管理することができる。 According to this aspect, the production process of precast concrete in a precast factory can be appropriately managed.
本発明の一態様に係る生産工程管理方法は、プロセッサを含む生産工程管理システムが実行する生産工程管理方法であって、建設部材の生産工程に関する生産工程情報を取得する生産工程情報取得ステップと、建設部材の生産工程に用いられる建設機器の位置情報を取得する第1位置情報取得ステップと、生産工程のうち、建設機器の位置情報に基づいて建設機器を用いる機器使用工程期間を判定する工程判定ステップと、を含む。 A production process management method according to one aspect of the present invention is a production process management method executed by a production process management system including a processor, and includes a production process information acquisition step of acquiring production process information related to the production process of a construction member, a first position information acquisition step of acquiring position information of construction equipment used in the production process of the construction member, and a process determination step of determining an equipment use process period in the production process that uses the construction equipment based on the position information of the construction equipment.
この態様によれば、工程判定ステップにおいて、生産工程のうち、建設機器の位置情報に基づいて建設機器を用いる機器使用工程期間が判定されるため、適切に生産工程を管理することができる。 According to this aspect, in the process determination step, the equipment use process period during the production process in which construction equipment is used is determined based on the location information of the construction equipment, so that the production process can be managed appropriately.
上記態様において、工程判定ステップは、生産工程情報に基づいて、生産工程のうち、少なくとも1つ以上の機器使用工程以外の工程期間を、機器使用工程期間を判定する前、後、又は共に、判定してもよい。 In the above aspect, the process determination step may determine the process duration of at least one or more equipment use processes among the production processes based on the production process information before, after, or both determining the equipment use process duration.
この態様によれば、工程判定ステップは、生産工程情報に基づいて、生産工程のうち、少なくとも1つ以上の機器使用工程以外の工程期間を判定するため、機器使用工程のみならず他の工程期間を判定でき、より適切に生産工程を管理することができる。 According to this aspect, the process determination step determines the process duration of at least one or more equipment use processes among the production processes based on the production process information, so that it is possible to determine the process duration of not only the equipment use process but also other processes, and to more appropriately manage the production process.
上記態様において、作業者が生産工程のうち担当可能な生産工程を含む作業者情報を取得する作業者情報取得ステップと、作業者の位置情報を取得する第2位置情報取得ステップと、をさらに含み、工程判定ステップは、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の開始時及び終了時を、機器使用工程期間を判定する前、後、又は共に、判定してもよい。 The above aspect further includes a worker information acquisition step of acquiring worker information including production processes that the worker can take charge of among the production processes, and a second location information acquisition step of acquiring location information of the worker, and the process determination step may determine the start and end times of at least one or more process periods included in the production process based on the worker location information and the worker information before, after, or both of determining the equipment use process period.
この態様によれば、工程判定部は、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の開始時及び終了時を判定するため、各工程期間を、より詳細に、実態に沿って把握することができ、より適切に生産工程を管理することができる。 According to this aspect, the process determination unit determines the start and end times of at least one or more process periods included in the production process based on the worker's location information and worker information, so that each process period can be grasped in more detail and in line with the actual situation, and the production process can be managed more appropriately.
本発明によれば、適切に生産工程を管理できる生産工程管理システム及び生産工程管理方法を提供することができる。 The present invention provides a production process management system and a production process management method that can appropriately manage the production process.
以下、本発明の好適な実施形態について、添付図面を参照しながら具体的に説明する。なお、以下で説明する実施形態は、あくまで、本発明を実施するための具体的な一例を挙げるものであって、本発明を限定的に解釈させるものではない。また、説明の理解を容易にするため、各図面において同一の構成要素に対しては可能な限り同一の符号を付して、重複する説明は省略する場合がある。 Below, a preferred embodiment of the present invention will be described in detail with reference to the attached drawings. Note that the embodiment described below is merely a specific example for implementing the present invention, and is not intended to limit the interpretation of the present invention. In addition, to facilitate understanding of the description, the same components in each drawing will be given the same reference numerals as much as possible, and duplicate descriptions may be omitted.
<一実施形態>
[生産工程管理システムの構成]
図1は、本発明の一実施形態に係る生産工程管理システム10を示すシステム概要図である。図1に示されるように、生産工程管理システム10は、位置測位システム20及び生産管理システム30等からデータを収集するデータ収集システム100と、当該データ収集システム100からのデータを分析するデータ分析システム200とから構成されている。
<One embodiment>
[Configuration of production process control system]
Fig. 1 is a system overview diagram showing a production
データ収集システム100は、位置情報取得部110と、生産工程情報取得部120と、作業者情報取得部130と、データ記録部140と、送信部150とを備え、データ分析システム200は、受信部210と、工程判定部220と、表示部230とを備える。
The
なお、本実施形態では、プレキャストコンクリートの生産工程を一例に挙げて、データ収集システム100はプレキャスト工場に配置され、データ分析システム200はクラウドに構築されているが、これに限定されるものではない。例えば、1つの生産工程管理システム10として、プレキャスト工場に配置しても構わないし、クラウドに構築しても構わないし、又は、サーバシステム等を管理する別の場所に配置及び構築しても構わない。
In this embodiment, the production process of precast concrete is taken as an example, and the
位置情報取得部110は、建設部材の生産工程に用いられる建設機器の位置情報を取得する。本実施形態では、建設部材をプレキャストコンクリート、及び建設機器をコンクリート打設機であるため、具体的には、位置情報取得部110は、コンクリート打設機の位置情報を取得する(第1位置情報取得部)。
The location
例えば、プレキャスト工場に、リアルタイム位置情報システム(RTLS:Real Time Location System)及び屋内測位システム(IPS:Indoor Positioning System)等の位置測位システムを構築し、位置情報(測位データ)を収集するロケータを配置する。ロケータは、典型的には、コンクリート打設機に取り付けられた発信機から、Bluetooth(登録商標)、UWB(Ultra Wide Band)、及びWi-Fi(登録商標)等の無線通信を介して、当該コンクリート打設機の位置情報(測位データ)を受信する。さらに、GNSS等を利用して測位データを取得するようにしても構わない。 For example, a positioning system such as a real-time location system (RTLS) and an indoor positioning system (IPS) is constructed in a precast factory, and a locator is placed to collect position information (positioning data). The locator typically receives the position information (positioning data) of the concrete pouring machine from a transmitter attached to the concrete pouring machine via wireless communication such as Bluetooth (registered trademark), UWB (Ultra Wide Band), and Wi-Fi (registered trademark). Furthermore, the positioning data may be acquired using GNSS or the like.
また、位置情報取得部110は、プレキャスト工場で作業する作業者の位置情報を取得しても構わない(第2位置情報取得部)。例えば、作業者が装着するヘルメット、作業着、靴又はベルトに発信機を取り付けても構わないし、その他、作業者に発信機を携帯させたり、作業者が携帯する通信機器(例えば、スマートフォンやタブレット等)に専用のアプリケーションを備えたりしても構わない。基本的には、発信機は、作業者が絶えず身に着けられる態様であって実装されている。ロケータは、作業者の位置情報(測位データ)も収集することができる。
The location
なお、コンクリート打設機及び作業者に取り付けられた発信機は、例えば、0.1~5秒毎に、測位データをロケータに発信すればよい。なお、発信機から測位データが発信される間隔は、0.1~5秒毎に限定されるものではなく、例えば、コンクリート打設機及び作業者の位置情報について、システム上、要求される精度に基づいて、適宜設定するようにしても構わない。また、建設機器及び作業者毎に異なる設定にしても構わない。 The transmitters attached to the concrete pouring machine and the worker may transmit positioning data to the locator, for example, every 0.1 to 5 seconds. The interval at which the transmitter transmits positioning data is not limited to every 0.1 to 5 seconds, and may be set appropriately based on the accuracy required by the system, for example, for the location information of the concrete pouring machine and the worker. Also, different settings may be used for each construction machine and worker.
このように、位置情報取得部110は、プレキャスト工場内において、コンクリート打設機及び各作業者がどこに位置しているかについて、各発信機の識別情報(ID)及び座標、時間等で示される位置情報を取得する。
In this way, the location
生産工程情報取得部120は、プレキャストコンクリートの生産工程に関する生産工程情報を取得する。例えば、生産工程情報取得部120は、生産管理システム30にて管理されている生産工程情報を取得する。ここで、生産工程情報とは、例えば、プレキャストコンクリートを含む建設部材について、各部材の詳細な部材情報、打設日、打設場所、及びその他生産工程に関する情報等が含まれる。
The production process
なお、生産工程情報取得部120は、生産工程情報を生産管理システム30から取得することに限定されるものではなく、例えば、生産工程管理システム10に構築されたデータベースに予め記録された生産工程情報を取得しても構わないし、その他、別システムに記録されている生産工程情報を取得しても構わない。
The production process
作業者情報取得部130は、作業者が生産工程のうち担当可能な生産工程を含む作業者情報を取得する。例えば、作業者情報取得部130は、生産工程管理システム10に構築されたデータベースに予め記録された作業者情報を取得しても構わないし、作業者情報が記録されている別システムから取得しても構わない。例えば、上述した生産管理システム30に作業者情報が記録されていれば、当該生産管理システム30から取得しても構わない。
The worker
ここで、作業者情報とは、プレキャスト工場で作業する作業者に関する情報であって、例えば、識別情報(ID)や氏名に紐づけて、少なくとも生産工程のうちどの工程を担当可能かに関する情報が含まれ、当該作業者が属する業種、性別、年齢、経験、スキル、国籍及び住所等に関する様々な個人情報が含まれても構わない。 Here, worker information refers to information about workers working in a precast factory, and includes, for example, information about which production process the worker is available to handle, linked to identification information (ID) or name, and may also include various personal information about the worker's industry, gender, age, experience, skills, nationality, address, etc.
データ記録部140には、位置情報取得部110によって取得されたコンクリート打設機及び作業者の位置情報(測位データ)、生産工程情報取得部120によって取得された生産工程情報、及び作業者情報取得部130によって取得された作業者情報が記録され、さらに蓄積されても構わない。なお、コンクリート打設機及び作業者の位置情報(測位データ)、生産工程情報、及び作業者情報は、当該データ記録部140に蓄積されず、直接、送信部150によってデータ分析システム200に送信されても構わない。その場合、データ記録部140は、データ分析システム200に含まれても構わない。
The
送信部150は、データ記録部140に記録(蓄積)された各種情報を、例えば、インターネット等を介してデータ分析システム200に送信する。
The
受信部210は、データ収集システム100の送信部150によって送信された各種情報を受信する。
The receiving
工程判定部220は、受信部210によって受信された各種情報に基づいて、プレキャストコンクリートの生産工程を分析する。具体的には、工程判定部220は、生産工程のうち、コンクリート打設機の位置情報に基づいて当該コンクリート打設機を用いる機器使用工程期間を判定する。コンクリート打設機を用いる機器使用工程とは、コンクリートをセットされた型枠に打ち込む打設工程である。一般的には、打設工程の期間、コンクリート打設機は、所定の領域に滞留しているため、工程判定部220は、コンクリート打設機の位置情報に基づいて、コンクリート打設機が継続して滞留していると把握すれば、打設工程期間を判定することができる。
The
また、工程判定部220は、生産工程情報に基づいて、生産工程のうち、打設工程以外の工程期間を判定する。例えば、工程判定部220は、一般的に、打設工程の前に実施されるセット工程及び検査工程、打設工程と並行して実施される仕上げ工程、及び打設工程の後に実施される脱型工程を判定する。
The
ここで、セット工程とは、打設工程を実施するための準備であり、典型的には、型枠を組み立てたり、当該型枠に鉄筋を入れ込む工程であり、検査工程とは、当該型枠や鉄筋の検査を実施する工程である。仕上げ工程とは、プレキャストコンクリートのコンクリート打設面を平滑にする工程であり、脱型工程とは、プレキャストコンクリートを型枠から抜き出す(型枠を外す)工程であり、鍛冶工程とは、形状や穴の位置などを部材に合わせて鋼製型枠を加工する工程である。 The setting process is a preparation for the casting process, typically involving assembling a formwork and inserting rebar into the formwork, and the inspection process is a process involving inspecting the formwork and rebar. The finishing process is a process for smoothing the concrete casting surface of the precast concrete, the demolding process is a process for removing the precast concrete from the formwork (removing the formwork), and the forging process is a process for machining the steel formwork to match the shape, hole positions, etc. to the components.
なお、工程判定部220が判定する工程は、これらに限定されるものではなく、例えば、鉄筋工程、製品検査工程及び養生工程等を含めるようにしても構わないし、さらに、細分化された工程等であっても構わない。
The processes determined by the
このように、工程判定部220は、コンクリート打設機の位置情報に基づいて当該コンクリート打設機を用いる打設工程期間を判定し、当該打設工程期間、及びプレキャストコンクリートを含む建設部材について、各部材の詳細な部材情報、打設日、打設場所、及びその他生産工程に関する情報等が含まれる生産工程情報に基づいて、生産工程における各工程期間を判定することができる。
In this way, the
また、工程判定部220は、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の開始時及び終了時を判定しても構わない。一般的に、生産工程に含まれる各工程は、それぞれプレキャスト工場内における作業領域が決められており、各工程を担当できる作業者の業種も決められている。工程判定部220は、作業者情報に基づいて各作業者がどの工程を担当可能であるか、作業者の位置情報に基づいて各作業者がどの領域に継続して滞留しているかについて、その滞留の開始時と終了時とを確認する。これにより、工程判定部は、各工程期間を、より詳細に、実態に沿って把握することができる。
The
なお、工程判定部220は、打設工程以外の各工程期間を、打設工程期間を判定し、当該判定された打設工程期間を基準にして判定しても構わないし、作業者の位置情報及び作業者情報に基づいて、打設工程期間の判定とともに、又は前に判定するようにしても構わない。例えば、工程判定部220は、作業者の位置情報及び作業者情報に基づいて脱型工程期間を判定し、コンクリート打設機の位置情報に基づいて打設工程期間を判定する。そして、判定された脱型工程期間及び打設工程期間を基準にして、その他の工程(セット工程、検査工程及び仕上げ等)期間を判定しても構わない。
The
さらに、工程判定部220は、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の作業実績を判定する。工程判定部220は、作業者情報に基づいて各作業者がどの工程を担当可能であるか、作業者の位置情報に基づいて各作業者がどの領域に継続して滞留しているかを確認することによって、各工程期間の作業実績を判定することができる。
Furthermore, the
上述した工程判定部220が判定する工程期間及び作業実績に関して、具体的な詳細については、後述する。
Specific details regarding the process period and work performance determined by the
表示部230は、工程判定部220によって判定された工程期間及び作業実績を表示する。例えば、生産工程管理を視覚的に理解し易くするために、表形式で画面に表示したり、工程毎に異なる色で表示したり、作業実績を作業者毎に表示したり、グラフ形式で表示したりしても構わない。さらに、生産工程管理システム10における表示部230に限定されるものではなく、例えば、Eメール等で通知したり、別システムの表示部に表示するようにしても構わない。
The
[工程期間及び作業実績の詳細]
次に、工程期間及び作業実績について、具体例を挙げながら詳細に説明する。
図2は、本発明の一実施形態に係る生産工程管理システム10において、生産工程のうち打設工程(機器使用工程)期間が判定される様子を示す図である。図2に示されるように、生産工程のうち、プレキャストコンクリート(PC部材)Bの打設工程期間が判定されている。
[Details of process period and work performance]
Next, the process period and work results will be described in detail with specific examples.
2 is a diagram showing how the duration of a pouring process (a process using equipment) in a production process is determined in a production
工程判定部220は、コンクリート打設機の位置情報に基づいて、当該コンクリート打設機を用いる打設工程期間を判定する。具体的には、工程判定部220は、PC部材Bを打設するためのコンクリート打設機が、当該打設工程を実施する領域に継続して滞留していることを確認し、打設工程期間(2020年2月1日11時~2月2日4時)を判定している。
The
ここで、コンクリート打設機が滞留しているか否かについては、全く同一位置に留まっていることのみならず、所定の領域(第1領域)において所定の時間(第1閾値)に留まっていることも滞留していることとして判定しても構わない。例えば、コンクリート打設機の調整、位置情報の検出誤差、及び突発的な事象等によって発生する位置情報の誤差(変化)に応じて、打設工程期間が誤判定されることを回避することができる。また、第1閾値は、少なくとも打設工程に必要な滞留時間であって、例えば、所定時間留まっている期間があれば、その期間は、滞留していることを意味する。 Here, whether or not the concrete pouring machine is stalled can be determined not only when it remains in the exact same position, but also when it remains in a specified area (first area) for a specified time (first threshold). For example, it is possible to avoid erroneous determination of the pouring process period depending on errors (changes) in the position information caused by adjustments to the concrete pouring machine, detection errors in the position information, and unexpected events. In addition, the first threshold is at least the dwell time required for the pouring process, and if there is a period in which the machine remains stalled for a specified time, that period means that the machine is stalled.
さらに、工程判定部220は、生産工程情報等に基づいて、スケジュールとして前部材(PC部材A)の脱型工程が終了していることを確認した上で、打設工程期間を判定するようにしても構わない。
Furthermore, the
図3は、本発明の一実施形態に係る生産工程管理システム10において、生産工程のうち打設工程以外の工程期間が判定される様子を示す図である。図3に示されるように、生産工程のうち、プレキャストコンクリート(PC部材)Bのセット工程、検査工程、脱型工程、仕上げ工程、及び鍛冶工程が判定されている。
Figure 3 is a diagram showing how the process durations of the production process other than the pouring process are determined in the production
工程判定部220は、生産工程情報等に基づいて、脱型工程期間(2020年2月2日4時~2月2日8時)を判定している。なお、工程判定部220は、コンクリート打設機が、当該打設工程を実施する領域に継続して滞留していないことを確認した上で、脱型工程期間を判定するようにしても構わない。
The
工程判定部220は、生産工程情報等に基づいて、前部材(PC部材A)の脱型工程の終了後で、PC部材Bの打設工程の開始前に、セット工程期間及び検査工程期間(2020年2月1日8時~2月1日11時)を判定する。
The
工程判定部220は、生産工程情報等に基づいて、PC部材Bの打設工程開始から脱型工程の開始前に、仕上げ工程期間(2020年2月1日11時~2月2日4時)を判定する。
The
さらに、工程判定部220は、生産工程情報等に基づいて、PC部材Aの脱型工程終了からPC部材Bの打設工程終了後に、鍛冶工程期間(2020年2月1日8時~2月2日4時)を判定しても構わない。
Furthermore, the
このように、工程判定部220は、PC部材Bについて、コンクリート打設機の位置情報に基づいて打設工程期間を判定し、当該打設工程期間及び生産工程情報等に基づいて、打設工程以外の工程期間を判定することによって、生産工程の各工程期間を判定している。生産工程情報には、PC部材毎の詳細な部材情報、打設日、打設場所、及びその他生産工程に関する情報等が含まれているため、PC部材毎の生産工程における各工程期間を判定することができ、それらを組み合わせることによって、複数のPC部材やプロジェクト全体の生産工程における各工程期間を判定することができる。さらには、1箇所のプレキャスト工場のみならず、複数のプレキャスト工場、さらには、建設現場やその他の場所で実施されている生産工程の各工程期間を判定することもできる。
In this way, the
なお、ここでは、PC部材Bの生産工程のうち打設工程期間を判定し、当該打設工程期間、生産工程情報等、及び前部材であるPC部材Aの生産工程(脱型工程の終了)に基づいて、打設工程以外の工程期間を判定したが、これに限定されるものではない。例えば、前部材であるPC部材Aの脱型工程終了日時が取得できない場合には、PC部材Aの打設工程日(例えば、2020年1月31日)の翌日(2020年2月1日)の8時をPC部材Aの脱型工程終了日時として、PC部材Bのセット工程期間、検査工程期間及び鍛冶工程期間等を判定しても構わないし、それ以外にも生産工程情報等に予め判定条件を設定しておき、それらの条件に基づいて判定するようにしても構わない。 Here, the casting process period of the production process of PC component B is determined, and the process periods other than the casting process are determined based on the casting process period, production process information, etc., and the production process of the previous component PC component A (end of the demolding process), but this is not limited to this. For example, if the end date and time of the demolding process of the previous component PC component A cannot be obtained, the setting process period, inspection process period, blacksmithing process period, etc. of PC component B may be determined using 8:00 a.m. on the day after the casting process date of PC component A (for example, January 31, 2020) (February 1, 2020) as the end date and time of the demolding process of PC component A, or judgment conditions may be set in advance in the production process information, etc., and judgment may be made based on those conditions.
上述のように、工程判定部220は、コンクリート打設機の位置情報に基づいて打設工程期間を判定し、生産工程情報等に基づいて打設工程以外の各工程期間を判定したが、これらの判定に際して、作業者の位置情報及び作業者情報を用いて、各工程期間の開始時及び終了時を判定するようにしても構わない。
As described above, the
例えば、工程判定部220は、生産工程のうち担当可能な工程の作業者が、当該工程が実施される領域に継続して滞留を開始する時、及び滞留を終了する時を判定し、当該工程期間の開始時及び終了時を判定する。各工程において、作業者の位置情報に応じて開始時及び終了時を判定することによって、より詳細に、実態に沿った工程期間を判定することができる。換言すれば、各工程の間には、いずれの工程期間にも属さない空白期間が存在する場合もあり(存在しない場合もあり)、それらを把握することもできる。なお、作業者が担当可能な工程、及び各工程が実施する領域に滞留していると判定する方法についての詳細は、後述する。
For example, the
また、工程判定部220は、コンクリート打設機の位置情報に基づいて打設工程期間を判定し、その後、生産管理情報、作業者の位置情報及び作業者情報、又はこれらの組み合わせに基づいて、打設工程以外の各工程期間を判定しても構わないし、打設工程期間を判定する前、又は共に、打設工程以外の各工程期間のうち一部又は全部を判定しても構わない。例えば、工程判定部220は、作業者の位置情報及び作業者情報に基づいて脱型工程期間を判定し、コンクリート打設機の位置情報に基づいて打設工程期間を判定する。そして、判定された脱型工程期間及び打設工程期間を基準にして、その他の工程(セット工程、検査工程及び仕上げ等)期間を判定しても構わない。
The
図4Aは、本発明の一実施形態に係る生産工程管理システム10において、生産工程に含まれる工程期間が判定された様子を示す図であり、図4Bは、本発明の一実施形態に係る生産工程管理システム10において、生産工程に含まれる工程期間の作業実績が判定される様子を示す図である。図4Aには、上述したように、PC部材毎の生産工程における各工程期間が判定された様子が示されており、図4Bには、作業者aの脱型工程期間及びセット工程期間における作業実績、及び作業者bの検査工程期間における作業実績が判定されている。ここでは、生産工程に含まれる工程期間について、作業者毎の作業実績を判定する様子について詳しく説明する。
Figure 4A is a diagram showing how the process periods included in the production process are determined in a production
工程判定部220は、作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の作業実績を判定する。工程判定部220は、作業者aの位置情報と作業者情報とに基づいて、PC部材Aの脱型工程期間の作業実績(2020年2月1日4時~2月1日7時)、PC部材Bのセット工程期間の作業実績(2020年2月1日8時~2月1日10時)及び脱型工程期間の作業実績(2020年2月2日4時~2月2日7時)を判定している。また、工程判定部220は、作業者bの位置情報と作業者情報とに基づいて、PC部材Bの検査工程期間の作業実績(2020年2月1日8時~2月1日9時)を判定している。
The
具体的には、工程判定部220は、作業者aの作業者情報に基づいて、作業者aが脱型工程を担当可能であること、及び作業者aの位置情報に基づいて、作業者aがPC部材Aの脱型工程を実施する領域に継続して滞留していることを確認し、当該作業者aがPC部材Aの脱型工程における作業をしていると判定している。同様に、工程判定部220は、PC部材Bのセット工程及び脱型工程における作業をしていると判定している。
Specifically, the
また、工程判定部220は、作業者bの作業者情報に基づいて、作業者bが検査工程を担当可能であること、及び作業者bの位置情報に基づいて、作業者bがPC部材Bの検査工程を実施する領域に継続して滞留していることを確認し、当該作業者bがPC部材Bの検査工程における作業をしていると判定している。
The
ここで、各作業者が生産工程のうちどの工程を担当可能であるかについては、作業者情報に含まれる、例えば、各作業者が属する業種に対応する担当可能工程に関する情報等に基づいて判定すればよい。 Here, which production processes each worker is capable of taking charge of can be determined based on information contained in the worker information, such as information about the processes each worker is capable of taking charge of that correspond to the industry to which each worker belongs.
図5は、作業者が属する業種に対応する担当可能な生産工程を示す一例である。図5に示されるように、業種「セット」の作業者は、セット工程及び脱型工程を担当可能であり、業種「打設」の作業者は、セット工程、打設工程及び脱型工程を担当可能であり、業種「仕上げ」の作業者は、セット工程、打設工程、仕上げ工程及び脱型工程を担当可能であり、業種「検査員」の作業者は、検査工程を担当可能であり、業種「鍛冶工」の作業者は、鍛冶工程を担当可能である。本実施形態では、作業者aは、業種「セット」であり、作業者bは、業種「検査員」である。 Figure 5 is an example showing the production processes that a worker can be responsible for, corresponding to the industry to which the worker belongs. As shown in Figure 5, a worker in the "set" industry can be responsible for the setting process and the demolding process, a worker in the "casting" industry can be responsible for the setting process, the casting process and the demolding process, a worker in the "finishing" industry can be responsible for the setting process, the casting process, the finishing process and the demolding process, a worker in the "inspector" industry can be responsible for the inspection process, and a worker in the "blacksmith" industry can be responsible for the blacksmithing process. In this embodiment, worker a is in the "set" industry, and worker b is in the "inspector" industry.
さらに、各作業者が各工程を実施する領域に滞留しているか否かについては、全く同一位置に留まっていることのみならず、各工程を実施するそれぞれ所定の領域(第2領域)において所定の時間(第2閾値)に留まっていることも滞留していることとして判定しても構わない。 Furthermore, with regard to whether or not each worker is staying in the area where each process is performed, it may be determined that the worker is staying not only when the worker remains in the exact same position, but also when the worker remains in a specific area (second area) where each process is performed for a specific period of time (second threshold value).
例えば、作業者が各工程における作業を実施する場合、各工程を実施する領域において動いたり、位置情報の検出誤差、及び突発的な事象等によって発生する位置情報の誤差(変化)に応じて、当該作業者の作業実績の判定が誤判定されることを回避することができる。また、当該工程の作業を実施していないにもかかわらず、一時的に、当該領域に侵入したり、通過したりする作業者等も存在する可能性があり、このような作業者等の行動による誤判定も回避することができる。なお、第2閾値は、少なくとも各工程にそれぞれ必要な滞留時間であって、例えば、所定時間留まっている期間があれば、その期間は、滞留していることを意味する。 For example, when a worker performs work in each process, it is possible to avoid erroneous judgments of the worker's work performance due to movement in the area where each process is performed, detection errors in the location information, and errors (changes) in the location information caused by sudden events, etc. Also, there may be workers who temporarily enter or pass through the area even though they are not performing the work in that process, and it is possible to avoid erroneous judgments due to the behavior of such workers, etc. The second threshold value is at least the residence time required for each process, and for example, if there is a period during which a certain period of time is spent, it means that the period is spent.
図6は、各工程における、(1)担当可能業種と、(2)当該担当可能業種の作業者が当該工程における作業を実施していると判定するために必要な滞留時間(第2閾値)とを示す一例である。図6に示されるように、セット工程、検査工程、打設工程、仕上げ工程、脱型工程、及び鍛冶工程それぞれにおいて、担当可能な業種が設定されており、各工程に応じて当該工程を実施していると判定するための滞留時間(第2閾値)が設定されている。 Figure 6 is an example showing (1) the possible trades for each process, and (2) the residence time (second threshold) required to determine that a worker of that possible trade is performing work in that process. As shown in Figure 6, the possible trades are set for each of the setting process, inspection process, pouring process, finishing process, demolding process, and blacksmithing process, and the residence time (second threshold) for determining that the process is being performed is set for each process.
上述したように、本実施形態では、作業者aは、業種「セット」であって、セット工程及び脱型工程を担当可能であり、作業者bは、業種「検査員」であって、検査工程を担当可能である。 As described above, in this embodiment, worker a is in the "set" category and is responsible for the setting process and the demolding process, and worker b is in the "inspector" category and is responsible for the inspection process.
工程判定部220は、作業者aの位置情報に基づいて、PC部材Aの脱型工程を実施する領域に、12秒以上留まっている期間が最初に確認できる「2020年2月1日4時」から最後に確認できる「2020年2月1日7時」の範囲のうち、1分間に12秒以上滞留している時間をPC部材Aの脱型工程期間の作業実績として集計する。
Based on the position information of worker a, the
図7は、PC部材Aの脱型工程期間の作業者aの作業実績を集計する様子を示す図である。図7に示されるように、作業者aがPC部材Aの脱型工程を実施する領域に1分間に12秒以上滞留していれば、滞留していると判定し、その時間を作業実績として計上する。 Figure 7 shows how the work performance of worker a during the demolding process of PC component A is tallied. As shown in Figure 7, if worker a remains in the area where the demolding process of PC component A is carried out for 12 seconds or more per minute, he or she is determined to be in the area, and that time is recorded as work performance.
同様に、工程判定部220は、作業者aの位置情報に基づいて、PC部材Bのセット工程を実施する領域に、12秒以上留まっている期間が最初に確認できる「2020年2月1日8時」から最後に確認できる「2020年2月1日10時」の範囲のうち、1分間に12秒以上滞留している時間をPC部材Bのセット工程期間の作業実績として判定し、PC部材Bの脱型工程を実施する領域に、12秒以上留まっている期間が最初に確認できる「2020年2月2日4時」から最後に確認できる「2020年2月2日7時」の範囲のうち、1分間に12秒以上滞留している時間をPC部材Bの脱型工程期間の作業実績として判定する。 Similarly, based on the position information of worker a, the process determination unit 220 determines the time during which worker a stayed in the area where the setting process of PC component B is performed for 12 seconds or more per minute within the range from "February 1, 2020, 8:00," when the time period during which worker a stayed in the area where the setting process of PC component B is performed was first confirmed to be 12 seconds or more, to "February 1, 2020, 10:00," when the time period during which worker a stayed in the area where the setting process of PC component B is performed was last confirmed to be 12 seconds or more, as the work performance during the setting process period of PC component B, and determines the time during which worker a stayed in the area where the demolding process of PC component B is performed for 12 seconds or more per minute within the range from "February 2, 2020, 4:00," when the time period during which worker a stayed in the area where the demolding process of PC component B was performed was first confirmed to be 12 seconds or more, to "February 2, 2020, 7:00," when the time period during which worker a stayed in the area where the demolding process of PC component B is performed was last confirmed to be 12 seconds or more, as the work performance during the demolding process period of PC component B.
また、工程判定部220は、作業者bの位置情報に基づいて、PC部材Bの検査工程を実施する領域に、26秒以上留まっている期間が最初に確認できる「2020年2月1日8時」から最後に確認できる「2020年2月1日9時」の範囲のうち、1分間に26秒以上滞留している時間をPC部材Bの検査工程期間の作業実績として判定する。
In addition, based on the position information of worker b, the
なお、作業者a及び作業者bの各PC部材の各工程における作業実績は、図4Aに示されるような工程判定部220が判定した生産工程における各工程期間と紐づけて判定しても構わないし、コンクリート打設機の位置情報も考慮して判定しても構わない。例えば、作業者が担当可能な工程期間が重なる場合、コンクリート打設機が滞留している場合は、打設工程の作業実績として判定し、コンクリート打設機が滞留していない場合は、仕上げ工程の作業実績として判定する。
The work performance of worker a and worker b in each process of each PC component may be determined by linking it to the process period of each process in the production process determined by the
さらに、ここでは、各工程における滞留時間(第2閾値)を図6に示される値で設定されているが、これらに限定されるものではなく、例えば、作業者のスキル、PC部材の大きさ、形状及び種類等、各工程で用いられる機器や環境、その他種々の事情に応じて、適宜、各工程に応じて適切な滞留時間(第2閾値)を設定すればよい。 Furthermore, here, the dwell time (second threshold) in each process is set to the value shown in FIG. 6, but is not limited to these. For example, an appropriate dwell time (second threshold) may be set for each process depending on the skill of the worker, the size, shape, and type of the PC component, the equipment and environment used in each process, and various other factors.
このように、工程判定部220は、各作業者の担当可能工程に関する情報を含む作業者情報を確認しつつ、各作業者の位置情報に基づいて、各担当者がどの領域に継続して滞留しているかを把握することによって、生産工程に含まれる少なくとも1つ以上の工程期間の作業実績を判定している。これにより、作業者毎に、各PC部材の各工程期間における作業実績を判定することができ、それらを組み合わせることによって、複数のPC部材やプロジェクト全体の生産工程における各工程期間における作業実績を判定することができる。さらには、1箇所のプレキャスト工場のみならず、複数のプレキャスト工場、さらには、建設現場やその他の場所で実施されている生産工程の各工程期間における作業実績を判定することもできる。
In this way, the
[生産工程管理方法]
次に、生産工程管理を実行する手順について、具体的に詳しく説明する。
[Production process control method]
Next, the procedure for carrying out production process management will be specifically described in detail.
図8は、本発明の一実施形態に係る生産工程管理システム10が実行する生産工程管理方法M10を示すフローチャートである。図8に示されるように、生産工程管理方法M10は、ステップS110~S150を含み、各ステップは、生産工程管理システム10に含まれるプロセッサによって実行される。
Figure 8 is a flowchart showing a production process management method M10 executed by a production
ステップS110では、生産工程管理システム10は、各種情報を取得する。具体例としては、位置情報取得部110が位置測位システム20からコンクリート打設機及び作業者の位置情報(測位データ)を取得したり、生産工程情報取得部120が生産管理システム30から生産管理情報を取得したりする。また、作業者情報取得部130が作業者情報を取得する。なお、これらの各種情報は、例えば、データ記録部140に蓄積される。
In step S110, the production
ステップS120では、生産工程管理システム10は、機器使用工程期間を判定する。具体例としては、工程判定部220がコンクリート打設機の位置情報に基づいて打設工程期間を判定する。
In step S120, the production
ステップS130では、生産工程管理システム10は、機器使用工程以外の工程期間を判定する。具体例としては、工程判定部220が、生産工程情報、作業者の位置情報及び作業者情報、又はこれらの組み合わせに基づいて、打設工程以外の工程期間を判定する。例えば、工程判定部220は、打設工程の前に実施されるセット工程及び検査工程、打設工程と並行して実施される仕上げ工程、及び打設工程の後に実施される脱型工程を判定する。
In step S130, the production
なお、ここでは、生産工程管理システム10は、ステップS130で機器使用工程以外の工程期間を判定しているが、機器使用工程以外の工程のうち一部又は全部を、ステップS120の判定の前又は共に判定しても構わない。
Note that, here, the production
ステップS140では、生産工程管理システム10は、各工程期間における作業実績を判定する。具体例としては、工程判定部220が作業者の位置情報と作業者情報とに基づいて、生産工程に含まれる少なくとも1つ以上の工程期間の作業実績を判定する。
In step S140, the production
ステップS150では、生産工程管理システム10は、各工程期間及び作業実績を表示する。具体例としては、表示部230がステップS120~ステップS140で判定された各工程期間及び作業実績をモニタ等に表示する。例えば、表示部230は、図4A及び図4Bに示されたような形式で各工程期間及び作業実績を表示する。また、表示形式は、その他、表、グラフ及びデータ等であっても構わない。
In step S150, the production
以上のように、本発明の一実施形態に係る生産工程管理システム10及び生産工程管理方法M10によれば、工程判定部220は、コンクリート打設機の位置情報に基づいて打設工程期間を判定し、生産工程情報、作業者の位置情報及び作業者情報、又はこれらの組み合わせに基づいて打設工程以外の工程期間を判定する。そして、工程判定部220は、作業者の位置情報と作業者情報とに基づいて、各工程期間における作業実績を判定する。その結果、工程期間を適切に判定することによって生産工程を管理することができ、また、作業実績も考慮して、より適切に生産工程を管理することもできる。
As described above, according to the production
なお、本実施形態では、主に、一部材(PC部材B)の生産工程を中心に、概ね1日(24時間)単位の処理として説明したが、生産工程管理システム10が処理する単位としては、例えば、複数の部材の生産工程を対象(前提)として、1週間単位、1ヶ月単位、又は所定期間のプロジェクト単位等で処理するようにしても構わない。具体的には、生産工程管理システム10は、データ記録部140に蓄積された1ヶ月分のデータに基づいて、複数の部材それぞれの打設工程期間を判定し、その後、複数の部材それぞれの打設工程以外の工程期間を判定するようにしても構わない。
In this embodiment, the processing has been described mainly in terms of the production process of one component (PC component B) and is generally performed on a daily (24 hour) basis. However, the production
なお、本実施形態では、建設機器をコンクリート打設機として説明したが、これに限定されるものではなく、例えば、建設機器は、コンクリートポンプ車及び生コンホッパー等であっても構わない。また、建設部材もコンクリート部材に限定されるものではなく、その他の建設部材であっても構わないし、その場合、建設機器もコンクリート打設機又は生コンホッパーではなく、当該その他の建設部材に対応する建設機器であっても構わない。 In this embodiment, the construction equipment is described as a concrete pouring machine, but is not limited to this, and may be, for example, a concrete pump truck and a ready-mixed concrete hopper. Furthermore, the construction members are not limited to concrete members, and may be other construction members. In that case, the construction equipment is not limited to a concrete pouring machine or ready-mixed concrete hopper, but may be construction equipment corresponding to the other construction members.
また、本発明をコンクリート部材以外の建設部材の生産工程管理に適用する場合には、機器使用工程も打設工程ではなく、当該建設機器を使用する工程であっても構わないし、機器使用工程以外の工程も、コンクリート部材以外の建設部材の生産工程に応じた工程であっても構わない。 In addition, when the present invention is applied to the production process management of construction members other than concrete members, the equipment use process does not have to be a pouring process, but may be a process that uses the construction equipment in question, and the process other than the equipment use process may be a process corresponding to the production process of construction members other than concrete members.
また、コンクリート部材を建設現場ではなく、プレキャスト工場で生産するプレキャスト工法を一例に挙げたが、これに限定されるものではなく、建設現場でコンクリートを打設する現場打ち工法でも、本発明に係る生産工程管理システム10を適用することが可能である。
In addition, a precast construction method in which concrete components are produced in a precast factory rather than at the construction site has been given as an example, but this is not limited to this, and the production
さらに、本発明は、コンクリート部材の生産工程管理に限定されるものではなく、その他建設部材の生産工程、土木工事現場、建設現場、ALC工場、及びGRC工場、さらには、その他業種における生産工程の管理に適用することも可能である。 Furthermore, the present invention is not limited to the management of production processes for concrete components, but can also be applied to the management of production processes for other construction components, civil engineering work sites, construction sites, ALC factories, and GRC factories, as well as production processes in other industries.
以上説明した実施形態は、本発明の理解を容易にするためのものであり、本発明を限定して解釈するためのものではない。実施形態が備える各要素並びにその配置、材料、条件、形状及びサイズ等は、例示したものに限定されるわけではなく適宜変更することができる。また、異なる実施形態で示した構成同士を部分的に置換し又は組み合わせることが可能である。 The above-described embodiments are intended to facilitate understanding of the present invention, and are not intended to limit the present invention. The elements of the embodiments, as well as their arrangements, materials, conditions, shapes, sizes, etc., are not limited to those exemplified, and may be modified as appropriate. Furthermore, configurations shown in different embodiments may be partially substituted or combined.
10…生産工程管理システム、20…位置測位システム、30…生産管理システム、100…データ収集システム、110…位置情報取得部、120…生産工程情報取得部、130…作業者情報取得部、140…データ記録部、150…送信部、200…データ分析システム、210…受信部、220…工程判定部、230…表示部、M10…生産工程管理方法、S110~S150…生産工程管理方法M10の各ステップ 10...production process management system, 20...positioning system, 30...production management system, 100...data collection system, 110...position information acquisition unit, 120...production process information acquisition unit, 130...worker information acquisition unit, 140...data recording unit, 150...transmission unit, 200...data analysis system, 210...reception unit, 220...process judgment unit, 230...display unit, M10...production process management method, S110 to S150...each step of the production process management method M10
Claims (13)
前記建設部材の生産工程に用いられる建設機器の位置情報を取得する第1位置情報取得部と、
前記生産工程のうち、前記建設機器の位置情報に基づいて前記建設機器を用いる機器使用工程期間を判定する工程判定部と、を備え、
前記建設機器は、コンクリート打設機又は生コンホッパーであり、
前記機器使用工程は、打設工程である、
生産工程管理システム。 a production process information acquisition unit for acquiring production process information relating to a production process of a construction material;
A first position information acquisition unit that acquires position information of construction equipment used in the production process of the construction member;
a process determination unit that determines a period during which the construction equipment is used in the production process based on the position information of the construction equipment,
The construction equipment is a concrete pouring machine or a ready-mixed concrete hopper,
The equipment use process is a concrete pouring process.
Production process control system.
前記建設部材の生産工程に用いられる建設機器の位置情報を取得する第1位置情報取得部と、A first position information acquisition unit that acquires position information of construction equipment used in the production process of the construction member;
前記生産工程のうち、前記建設機器の位置情報に基づいて前記建設機器を用いる機器使用工程期間を判定する工程判定部と、を備え、a process determination unit that determines a period during which the construction equipment is used in the production process based on the position information of the construction equipment,
前記建設部材は、プレキャストコンクリートである、The construction member is precast concrete;
生産工程管理システム。Production process control system.
請求項1又は2に記載の生産工程管理システム。 The first position information acquisition unit acquires position information of the construction equipment regarding whether or not the construction equipment has been continuously present in the first area for a period of time equal to or longer than a first threshold value.
The production process control system according to claim 1 or 2 .
請求項1から3のいずれか一項に記載の生産工程管理システム。 The process determination unit determines a process period of at least one process other than the equipment usage process among the production processes based on the production process information.
The production process control system according to any one of claims 1 to 3 .
前記作業者の位置情報を取得する第2位置情報取得部と、
をさらに備え、
前記工程判定部は、前記作業者の位置情報と作業者情報とに基づいて、前記生産工程に含まれる少なくとも1つ以上の工程期間の開始時及び終了時を判定する、
請求項4に記載の生産工程管理システム。 a worker information acquisition unit that acquires worker information including a production process that the worker can take charge of among the production processes;
A second position information acquisition unit that acquires position information of the worker;
Further equipped with
the process determination unit determines a start time and an end time of at least one process period included in the production process based on the location information of the worker and the worker information;
The production process control system according to claim 4 .
請求項5に記載の生産工程管理システム。 the process determination unit determines the work performance of at least one process period included in the production process based on the location information of the worker and the worker information;
The production process control system according to claim 5 .
請求項5又は6に記載の生産工程管理システム。 the second position information acquisition unit acquires position information of the worker regarding whether the worker has been continuously present in the second area for a period equal to or longer than a second threshold;
The production process control system according to claim 5 or 6 .
請求項7に記載の生産工程管理システム。 the second region and the second threshold value are set according to each step of the production process;
The production process control system according to claim 7 .
請求項1に記載の生産工程管理システム。 The process other than the equipment use process includes at least one of a setting process and a demolding process.
The production process control system according to claim 1 .
建設部材の生産工程に関する生産工程情報を取得する生産工程情報取得ステップと、
前記建設部材の生産工程に用いられる建設機器の位置情報を取得する第1位置情報取得ステップと、
前記生産工程のうち、前記建設機器の位置情報に基づいて前記建設機器を用いる機器使用工程期間を判定する工程判定ステップと、を含み、
前記建設機器は、コンクリート打設機又は生コンホッパーであり、
前記機器使用工程は、打設工程である、
生産工程管理方法。 A production process control method executed by a production process control system including a processor,
A production process information acquisition step of acquiring production process information related to a production process of a construction material;
A first position information acquisition step of acquiring position information of construction equipment used in the production process of the construction member;
and a process determination step of determining a period during which the construction equipment is used based on the position information of the construction equipment in the production process ,
The construction equipment is a concrete pouring machine or a ready-mixed concrete hopper,
The equipment use process is a concrete pouring process.
Production process control methods.
建設部材の生産工程に関する生産工程情報を取得する生産工程情報取得ステップと、A production process information acquisition step of acquiring production process information related to a production process of a construction material;
前記建設部材の生産工程に用いられる建設機器の位置情報を取得する第1位置情報取得ステップと、A first position information acquisition step of acquiring position information of construction equipment used in the production process of the construction member;
前記生産工程のうち、前記建設機器の位置情報に基づいて前記建設機器を用いる機器使用工程期間を判定する工程判定ステップと、を含み、and a process determination step of determining a period during which the construction equipment is used based on the position information of the construction equipment in the production process,
前記建設部材は、プレキャストコンクリートである、The construction member is precast concrete;
生産工程管理方法。Production process control methods.
請求項10又は11に記載の生産工程管理方法。 The process determination step determines a process period of at least one or more of the production processes other than the equipment use process, before, after, or both of the process periods of the equipment use process and the production process, based on the production process information.
The production process control method according to claim 10 or 11 .
前記作業者の位置情報を取得する第2位置情報取得ステップと、
をさらに含み、
前記工程判定ステップは、前記作業者の位置情報と作業者情報とに基づいて、前記生産工程に含まれる少なくとも1つ以上の工程期間の開始時及び終了時を、前記機器使用工程期間を判定する前、後、又は共に、判定する、
請求項10から12のいずれか一項に記載の生産工程管理方法。 a worker information acquisition step of acquiring worker information including a production process that the worker can take charge of among the production processes;
a second position information acquisition step of acquiring position information of the worker;
Further comprising:
The process determination step determines the start and end times of at least one or more process periods included in the production process before, after, or both of the start and end times of the equipment use process period based on the location information and the worker information of the worker.
The production process control method according to any one of claims 10 to 12 .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2021016723A JP7570246B2 (en) | 2021-02-04 | 2021-02-04 | Production process control system and production process control method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2021016723A JP7570246B2 (en) | 2021-02-04 | 2021-02-04 | Production process control system and production process control method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2022119526A JP2022119526A (en) | 2022-08-17 |
| JP7570246B2 true JP7570246B2 (en) | 2024-10-21 |
Family
ID=82848320
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2021016723A Active JP7570246B2 (en) | 2021-02-04 | 2021-02-04 | Production process control system and production process control method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7570246B2 (en) |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000357010A (en) | 1999-06-16 | 2000-12-26 | Hitachi Plant Eng & Constr Co Ltd | Tool management system |
| JP2008046721A (en) | 2006-08-11 | 2008-02-28 | Mitsui Precon Co Ltd | Production management system for precast member |
| WO2020162435A1 (en) | 2019-02-08 | 2020-08-13 | 三菱電機株式会社 | Production improvement assistance system, method, and program |
-
2021
- 2021-02-04 JP JP2021016723A patent/JP7570246B2/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000357010A (en) | 1999-06-16 | 2000-12-26 | Hitachi Plant Eng & Constr Co Ltd | Tool management system |
| JP2008046721A (en) | 2006-08-11 | 2008-02-28 | Mitsui Precon Co Ltd | Production management system for precast member |
| WO2020162435A1 (en) | 2019-02-08 | 2020-08-13 | 三菱電機株式会社 | Production improvement assistance system, method, and program |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2022119526A (en) | 2022-08-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP6824838B2 (en) | Work data management system and work data management method | |
| Navon et al. | Assessing research issues in automated project performance control (APPC) | |
| US20210233186A1 (en) | Method for monitoring processes and progress at a construction site | |
| DE112017001435T5 (en) | DEVICE FOR REAL-TIME DEVICE PURCHASE ON A SITE | |
| Reinbold et al. | Integrating indoor positioning systems and BIM to improve situational awareness | |
| WO2011058894A1 (en) | Work progress estimating apparatus and method which utilize id medium and sensor | |
| Abdelalim et al. | Dynamic labor tracking system in construction project using BIM technology | |
| JP7474303B2 (en) | Management System | |
| CN113793000A (en) | Liangchang information processing system, method, computer device and storage medium | |
| JP7570246B2 (en) | Production process control system and production process control method | |
| Waqar et al. | Enhancing construction management outcomes through the mitigation of robotics implementation barriers: A sustainable practice model | |
| KR20120075567A (en) | Production management method | |
| JP5451166B2 (en) | Production improvement support system | |
| JP7460233B2 (en) | Information processing device, information processing method, program, and data structure | |
| JP2020160507A (en) | Production control system and computer program | |
| CN113743897A (en) | Concrete test system, method, computer device and storage medium | |
| CN119105464A (en) | Vehicle production inspection methods and electronic equipment | |
| Ibarra et al. | A lean six sigma project to reduce waste and variability in a confectionery manufacturing | |
| Radman et al. | Real-time project productivity tracking system: Practical case in smart construction projects | |
| CN105446289A (en) | Collecting by a MES system time-stamps of working-statuses | |
| KR101787509B1 (en) | Web and mobile-based automated process improvement monitoring system | |
| Mohamed et al. | Leading indicators for safety management: Understanding the impact of project performance data on safety performance | |
| JP2020057090A (en) | data structure | |
| Moragane et al. | Application of computer vision for construction progress monitoring | |
| JP2016035620A (en) | How to store quality-related information |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20231031 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20240816 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20240820 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20240910 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20240926 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20241008 |
|
| R150 | Certificate of patent or registration of utility model |