JP7601997B2 - Cost budget/actual management device, cost budget/actual management method, and cost budget/actual management program - Google Patents
Cost budget/actual management device, cost budget/actual management method, and cost budget/actual management program Download PDFInfo
- Publication number
- JP7601997B2 JP7601997B2 JP2023208907A JP2023208907A JP7601997B2 JP 7601997 B2 JP7601997 B2 JP 7601997B2 JP 2023208907 A JP2023208907 A JP 2023208907A JP 2023208907 A JP2023208907 A JP 2023208907A JP 7601997 B2 JP7601997 B2 JP 7601997B2
- Authority
- JP
- Japan
- Prior art keywords
- cost
- data
- manufacturing number
- classification
- actual
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Financial Or Insurance-Related Operations Such As Payment And Settlement (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
本発明は、原価予実管理装置、原価予実管理方法、及び原価予実管理プログラムに関する。 The present invention relates to a cost budget/actual management device, a cost budget/actual management method, and a cost budget/actual management program.
例えば、大型機械の製造を行う業界では個別原価管理を行う企業が多く、発生する直接費に対して間接費を計算して予定原価を算出し、実際発生原価と対比して原価の予実を管理している。原価の予実管理を行うシステムとして、例えば、特許文献1がある。
For example, many companies in the large machinery manufacturing industry use individual cost management, calculating indirect costs against direct costs to determine planned costs, and comparing these with the actual costs incurred to manage the actual versus forecast costs. For example,
しかしながら、上記特許文献1では、間接費を細分化して計上することで原価予実管理を高精度に行うことに関して何等記載されていない。
However, the above-mentioned
本発明は、上記に鑑みてなされたものであって、間接費を細分化して計上することで原価予実管理を高精度に行うことが可能な原価予実管理装置、原価予実管理方法、及び原価予実管理プログラムを提供することを目的とする。 The present invention has been made in consideration of the above, and aims to provide a cost budget/actual management device, a cost budget/actual management method, and a cost budget/actual management program that are capable of performing cost budget/actual management with high accuracy by breaking down and recording indirect costs.
上述した課題を解決し、目的を達成するために、本発明は、記憶部及び制御部を備えた原価予実管理装置であって、前記記憶部には、製番分類、製番管理部門、及び製番原価科目毎に、間接費率を設定したマスタが格納されており、前記制御部は、各種データについて、製番、製番分類、製番管理部門、製番原価科目、及び原価を含む直接費データを入力する入力手段と、前記直接費データを製番分類、製番管理部門、製番原価科目毎に原価を集約し、集約した原価に、前記マスタから製番分類、製番管理部門、及び製番原価科目をキーとして取得した間接費率を乗算して間接費データを算出する原価計算処理手段と、前記直接費データ及び前記間接費データを含む予定原価データについて、所定分類の仕訳を作成する仕訳作成手段と、実際発生原価を取得し、前記予定原価データと取得した実際発生原価について、前記所定分類の原価差額集計表を作成する原価差額集計手段と、を備えている。 In order to solve the above problems and achieve the objective, the present invention provides a cost forecast/actual management device equipped with a storage unit and a control unit, the storage unit stores master data in which an overhead rate is set for each serial number classification, serial number management department, and serial number cost item, and the control unit includes an input unit for inputting direct cost data including serial numbers, serial number classifications, serial number management departments, serial number cost items, and costs for various data, a cost calculation processing unit for aggregating the direct cost data for each serial number classification, serial number management department, and serial number cost item, and multiplying the aggregated costs by the overhead rate obtained from the master data using the serial number classification, serial number management department, and serial number cost item as keys to calculate overhead data, a journal entry creation unit for creating journal entries for a specified classification for planned cost data including the direct cost data and the overhead cost data, and a cost difference aggregation unit for acquiring actual costs, and creating a cost difference aggregation table for the specified classification for the planned cost data and the acquired actual costs.
また、本発明の一態様によれば、前記製番分類は、製品製番、試作製番、修理製番、経費製番、及び工事製番を含むことにしてもよい。 According to one aspect of the present invention, the serial number classification may include a product serial number, a prototype serial number, a repair serial number, an expense serial number, and a construction serial number.
また、本発明の一態様によれば、製番管理部門は、製造部と設計部を含むことにしてもよい。 According to one aspect of the present invention, the serial number management department may include a manufacturing department and a design department.
また、本発明の一態様によれば、前記製番原価科目は、直接労務費、材料費、及び外注加工費を含むことにしてもよい。 Furthermore, according to one aspect of the present invention, the manufacturing cost items may include direct labor costs, material costs, and outsourced processing costs.
また、本発明の一態様によれば、前記所定分類は、製番管理部門、製番、及び製番分類を含むことにしてもよい。 According to one aspect of the present invention, the predetermined classification may include a serial number management department, a serial number, and a serial number classification.
また、本発明の一態様によれば、前記各種データは、仕入、出庫、及び作業実績のデータを含むことにしてもよい。 According to one aspect of the present invention, the various data may include data on purchases, shipments, and work results.
また、上述した課題を解決し、目的を達成するために、本発明は、記憶部及び制御部を備えた情報処理装置で実行される原価予実管理方法であって、前記記憶部には、製番分類、製番管理部門、及び製番原価科目毎に、間接費率を設定したマスタが格納されており、前記制御部において実行される、各種データについて、製番、製番分類、製番管理部門、製番原価科目、及び原価を含む直接費データを入力する入力工程と、前記直接費データを製番分類、製番管理部門、製番原価科目毎に原価を集約し、集約した原価に、前記マスタから製番分類、製番管理部門、及び製番原価科目をキーとして取得した間接費率を乗算して間接費データを算出する原価計算処理工程と、前記直接費データ及び前記間接費データを含む予定原価データについて、所定分類の仕訳を作成する仕訳作成工程と、実際発生原価を取得し、前記予定原価データと取得した実際発生原価について、前記所定分類の原価差額集計表を作成する原価差額集計工程と、を含むことを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the present invention provides a cost budget/actual management method executed by an information processing device equipped with a storage unit and a control unit, the storage unit stores master data in which an overhead rate is set for each serial number classification, serial number management department, and serial number cost item, and the control unit executes an input process for inputting direct cost data including serial numbers, serial number classifications, serial number management departments, serial number cost items, and costs for various data, a cost calculation process for aggregating the direct cost data for each serial number classification, serial number management department, and serial number cost item, and multiplying the aggregated costs by the overhead rate obtained from the master data using the serial number classification, serial number management department, and serial number cost item as keys to calculate overhead data, a journal entry creation process for creating journal entries for a specified classification for planned cost data including the direct cost data and the overhead cost data, and a cost difference aggregation process for acquiring actual costs and creating a cost difference summary table for the specified classification for the planned cost data and the acquired actual costs.
また、上述した課題を解決し、目的を達成するために、本発明は、制御部及び記憶部を備えた情報処理装置に実行させるための原価予実管理プログラムであって、前記記憶部には、製番分類、製番管理部門、及び製番原価科目毎に、間接費率を設定したマスタが格納されており、前記制御部において、各種データについて、製番、製番分類、製番管理部門、製番原価科目、及び原価を含む直接費データを入力する入力工程と、前記直接費データを製番分類、製番管理部門、製番原価科目毎に原価を集約し、集約した原価に、前記マスタから製番分類、製番管理部門、及び製番原価科目をキーとして取得した間接費率を乗算して間接費データを算出する原価計算処理工程と、前記直接費データ及び前記間接費データを含む予定原価データについて、所定分類の仕訳を作成する仕訳作成工程と、実際発生原価を取得し、前記予定原価データと取得した実際発生原価について、前記所定分類の原価差額集計表を作成する原価差額集計工程と、を実行するための原価予実管理プログラムであることを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the present invention provides a cost budget/actual management program to be executed by an information processing device having a control unit and a storage unit, the storage unit stores a master in which an indirect cost rate is set for each manufacturing number classification, manufacturing number management department, and manufacturing number cost item, and the control unit includes an input process for inputting direct cost data including manufacturing numbers, manufacturing number classifications, manufacturing number management departments, manufacturing number cost items, and costs for various data, and aggregating the direct cost data into costs for each manufacturing number classification, manufacturing number management department, and manufacturing number cost item. It is characterized by being a cost budget/actual management program for executing a cost calculation process that calculates overhead data by multiplying the aggregated costs by overhead rates obtained from the master using the production number classification, production number management department, and production number cost item as keys, a journal entry creation process that creates journal entries for a specified classification for planned cost data including the direct cost data and the overhead cost data, and a cost difference aggregation process that acquires actual costs and creates a cost difference summary table for the specified classification for the planned cost data and the acquired actual costs.
本発明によれば、間接費を細分化して計上することで原価予実管理を高精度に行うことが可能になるという効果を奏する。 The present invention has the effect of enabling highly accurate cost budget/actual management by breaking down and recording indirect costs.
本発明の実施形態を図面に基づいて詳細に説明する。なお、本発明は本実施形態により限定されるものではない。 An embodiment of the present invention will be described in detail with reference to the drawings. Note that the present invention is not limited to this embodiment.
[1:概要]
例えば、大型機械の製造を行う業界では個別原価管理を行う企業が多く、発生する直接費に対して間接費を計算して予定原価を算出し、実際発生原価と対比して原価の予実を管理している。
[1: Overview]
For example, in industries that manufacture large machinery, many companies practice individual cost management, calculating indirect costs against direct costs incurred to arrive at planned costs, and managing the actual costs by comparing them with the planned costs.
しかしながら、従来、予定原価の計算において、部門毎の一定比率であったため、会計システム側で手仕訳を行う必要があり、担当者の作業負担が大きかった。また、予定原価の精度が低いため、予実の差が大きく乖離していた。 However, previously, the calculation of planned costs was based on a fixed ratio for each department, which required manual entry into the accounting system, placing a heavy burden on the person in charge. In addition, the accuracy of planned costs was low, resulting in a large discrepancy between the actual and forecasted costs.
そこで、本実施の形態では、間接費を細分化して計上することで原価予実管理を高精度に行う。具体的には、直接費に対して、予めマスタ設定した間接費比率(例えば、製番分類、製番原価科目、及び製番管理部門毎に設定した間接費率)を掛けて、間接費の予定原価を計算し、計算した予定原価を会計システムと連携し、実際発生原価と対比して原価の予実管理を実現する。 In this embodiment, therefore, overhead costs are broken down and recorded to achieve highly accurate budget-to-actual cost management. Specifically, the planned overhead cost is calculated by multiplying direct costs by an overhead rate preset in the master (for example, an overhead rate set for each serial number classification, serial number cost item, and serial number management department), and the calculated planned cost is linked to the accounting system to achieve budget-to-actual cost management by comparing it with the actual costs incurred.
これにより、製番分類、製番管理部門、及び製番原価科目毎に間接費を計上し、予定原価と実際発生原価の予実管理をより高い精度で行うことが可能となる。また、手作業による間接費の計上が不要となり、担当者の負担を軽減することが可能となる。 This allows overhead costs to be recorded for each production number classification, production number management department, and production number cost item, making it possible to more accurately manage planned costs and actual costs incurred. It also makes it unnecessary to record overhead costs manually, reducing the burden on staff.
本発明は、例えば、個別原価管理を行う大型機械製造など個別受注製造の業界などにおいて有用である。 The present invention is useful, for example, in industries where individual order manufacturing is carried out, such as large machinery manufacturing, where individual cost management is carried out.
[2.構成]
本実施形態に係る原価予実管理装置の構成の一例について、図1を参照して説明する。図1は、原価予実管理装置の構成の一例を示すブロック図である。
2. Configuration
An example of the configuration of a cost budget/actual management device according to this embodiment will be described with reference to Fig. 1. Fig. 1 is a block diagram showing an example of the configuration of a cost budget/actual management device.
原価予実管理装置100は、市販のデスクトップ型パーソナルコンピュータである。なお、原価予実管理装置100は、デスクトップ型パーソナルコンピュータのような据置型情報処理装置に限らず、市販されているノート型パーソナルコンピュータ、PDA(Personal Digital Assistants)、スマートフォン、タブレット型パーソナルコンピュータなどの携帯型情報処理装置であってもよい。
The cost forecast/
原価予実管理装置100は、制御部102と通信インターフェース部104と記憶部106と入出力インターフェース部108と、を備えている。原価予実管理装置100が備えている各部は、任意の通信路を介して通信可能に接続されている。
The cost forecast/
通信インターフェース部104は、ルータ等の通信装置及び専用線等の有線又は無線の通信回線を介して、原価予実管理装置100をネットワーク300に通信可能に接続する。通信インターフェース部104は、他の装置と通信回線を介してデータを通信する機能を有する。ここで、ネットワーク300は、原価予実管理装置100と、サーバ200や端末400・・・とを相互に通信可能に接続する機能を有し、例えばインターネットやLAN(Local Area Network)等である。端末400・・・は、経理担当者、購買担当者、及び製造担当者等が使用する端末装置である。経理担当者、購買担当者、及び製造担当者等は、端末400・・・を使用して、原価予実管理装置100とデータ通信を行うことができ、例えば、原価予実管理装置100にデータの入力(マスタの設定、仕入入力、出庫入力、作業実績入力、実際発生原価入力等)等が可能になっている。
The
入出力インターフェース部108には、入力装置112及び出力装置114が接続されている。出力装置114には、モニタ(家庭用テレビを含む)の他、スピーカやプリンタを用いることができる。入力装置112には、キーボード、マウス、及びマイクの他、マウスと協働してポインティングデバイス機能を実現するモニタを用いることができる。なお、以下では、出力装置114をモニタ114とし、入力装置112をキーボード112またはマウス112として記載する場合がある。 An input device 112 and an output device 114 are connected to the input/output interface unit 108. The output device 114 may be a monitor (including a home television), a speaker, or a printer. The input device 112 may be a keyboard, a mouse, a microphone, or a monitor that works with a mouse to provide a pointing device function. In the following, the output device 114 may be referred to as the monitor 114, and the input device 112 may be referred to as the keyboard 112 or the mouse 112.
記憶部106には、各種のデータベース、テーブル、及びファイルなどが格納される。記憶部106には、OS(Operating System)と協働してCPU(Central Processing Unit)に命令を与えて各種処理を行うためのコンピュータプログラムが記録される。記憶部106として、例えば、RAM(Random Access Memory)・ROM(Read Only Memory)等のメモリ装置、ハードディスクのような固定ディスク装置、フレキシブルディスク、及び光ディスク等を用いることができる。 The storage unit 106 stores various databases, tables, files, and the like. The storage unit 106 records computer programs that work in cooperation with the OS (Operating System) to give instructions to the CPU (Central Processing Unit) to perform various processes. As the storage unit 106, for example, memory devices such as RAM (Random Access Memory) and ROM (Read Only Memory), fixed disk devices such as hard disks, flexible disks, and optical disks can be used.
また、記憶部106は、間接費率マスタ106aと、製番分類マスタ106bと、データファイル106cとを備えている。
The memory unit 106 also includes an overhead rate master 106a, a manufacturing
間接費率マスタ106aは、製番分類、製番管理部門、及び製番原価科目(直接費の種類)毎に、間接費の種類とその間接費率を設定するためのマスタであり、すなわち、間接費を細分化して設定するためのマスタである。間接費率マスタ106aは、製番分類、製番管理部門、対象の製番原価科目(直接費の種類)、製番原価科目(間接費の種類)、及び間接費率を関連づけて登録したテーブル等で構成されている(図2参照)。 The overhead rate master 106a is a master for setting the type of overhead and its overhead rate for each manufacturing number classification, manufacturing number management department, and manufacturing number cost item (type of direct cost), that is, a master for setting overhead by subdividing it. The overhead rate master 106a is composed of tables that associate and register the manufacturing number classification, manufacturing number management department, target manufacturing number cost item (type of direct cost), manufacturing number cost item (type of indirect cost), and overhead rate (see Figure 2).
製番分類マスタ106bは、製番を分類したマスタであり、例えば、試作製番、修理製番、経費製番、工事製番が登録されている(図2参照)。
The serial
データファイル106cは、仕入入力データ、出庫入力データ、作業実績入力データ等の直接費データ(予定直接費)、間接費データ(予定間接費)、仕訳データ、原価差異額集計表等の各種データを格納するためのファイルである。 Data file 106c is a file for storing various data such as direct cost data (planned direct costs), indirect cost data (planned indirect costs), journal data, cost variance summary tables, etc., such as purchase input data, shipment input data, and work performance input data.
制御部102は、原価予実管理装置100を統括的に制御するCPU等である。制御部102は、OS等の制御プログラム・各種の処理手順等を規定したプログラム・所要データなどを格納するための内部メモリを有し、格納されているこれらのプログラムに基づいて種々の情報処理を実行する。制御部102は、機能概念的に、マスタメンテ部102aと、仕入入力部102bと、出庫入力部102cと、作業実績入力部102dと、原価計算処理部102eと、仕訳連携処理部102fと、会計システム(原価差額集計部)102gと、を備えている。
The control unit 102 is a CPU or the like that controls the cost forecast/
マスタメンテ部102aは、間接費率マスタ106a及び製番分類マスタ106bのデータの追加・削除・変更等の編集を行うためのものである。
The
仕入入力部102bは、データ種類「仕入」、製番、製番分類、製番原価科目、製番管理部門、及び原価を含む仕入入力データを入力してデータファイル106cに格納する。 The purchase input unit 102b inputs purchase input data including the data type "purchase", serial number, serial number classification, serial number cost item, serial number management department, and cost, and stores the data in the data file 106c.
出庫入力部102cは、データ種類「出庫」、製番、製番分類、製番原価科目、製番管理部門、及び原価を含む出庫入力データを入力してデータファイル106cに格納する。
The
作業実績入力部102dは、データ種類「作業実績」、製番、製番分類、製番原価科目、製番管理部門、原価を含む作業実績入力データを入力してデータファイル106cに格納する。
The work
仕入入力データ、出庫入力データ、及び作業実績入力データを総称して直接費データと称し、仕入入力部102b、出庫入力部102c、及び作業実績入力部102dは、直接費データを入力する入力手段を構成する。
The purchase input data, the shipment input data, and the work performance input data are collectively referred to as direct cost data, and the purchase input section 102b, the
原価計算処理部102eは、直接費データについて、製番分類、製番管理部門、製番原価科目毎に原価を集約(集計)し、集約した原価に、間接費率マスタ106aから製番分類、製番管理部門、及び製番原価科目をキーとして取得した間接費率を乗算して間接費データを算出して、データファイル106cに格納する。 The cost calculation processing unit 102e aggregates (tallys up) the costs of the direct cost data by production number classification, production number management department, and production number cost item, multiplies the aggregated costs by the overhead rate obtained from the overhead rate master 106a using the production number classification, production number management department, and production number cost item as keys, calculates the overhead data, and stores it in the data file 106c.
仕訳連携処理部102fは、会計システム(原価差額集計部)102gと連携して、直接費データ及び間接費データを含む予定原価データについて、所定分類の仕訳を作成して、データファイル106cに格納する。
The journal entry linking
会計システム(原価差額集計部)102gは、実際発生原価を取得し、予定原価データと取得した実際発生原価について、所定分類の原価差額集計表を作成して、データファイル106cに格納する。 The accounting system (cost difference calculation section) 102g acquires the actual costs incurred, creates a cost difference calculation table for a specified classification for the planned cost data and the acquired actual costs incurred, and stores it in the data file 106c.
製番分類は、製品製番、試作製番、修理製番、経費製番、及び工事製番を含んでいてもよい。製番管理部門は、製造部と設計部を含んでいてもよい。製番原価科目(直接費の種類)は、直接労務費、材料費、及び外注加工費を含んでいてもよい。製番原価科目(間接費の種類)は、間接労務費、間接経費、間接材料費を含んでいてもよい。所定分類は、製番管理部門、製番、及び製番分類を含んでいてもよい。 The serial number classification may include product serial number, prototype serial number, repair serial number, expense serial number, and construction serial number. The serial number management department may include the manufacturing department and the design department. The serial number cost item (type of direct cost) may include direct labor cost, material cost, and outsourced processing cost. The serial number cost item (type of indirect cost) may include indirect labor cost, indirect expense, and indirect material cost. The specified classification may include the serial number management department, serial number, and serial number classification.
[3.具体例]
図1~図4を参照して、本実施の形態における原価予実管理装置100の処理の具体例を説明する。まず、図2~図4は、本実施の形態における原価予実管理装置100の制御部102の処理の具体例を説明するための図である。以下の説明では、金額の単位は全て「千円」とし、その表記を省略する。
3. Specific Examples
A specific example of the processing of the cost forecast/
(マスタメンテ処理)
図2において、マスタメンテ部102aは、マスタメンテ処理を実行する(ステップS1)。具体的には、マスタメンテ処理では、マスタメンテ部102aは、例えば、経理担当者の端末400のリクエストに応じて端末400にマスタメンテ画面を提供し、マスタメンテ画面上での経理担当者の端末400の操作等に応じて、間接費率マスタ106aや製番分類マスタ106bのデータの設定を行う。
(Master maintenance processing)
2, the
図2(A)は、間接費率マスタ106aの登録例を示す図である。図2(A)に示す間接費率マスタ106aの例では、1行目は、製番分類「製品製番」、製番管理部門「製造部」、製番原価科目「間接労務費」、対象製番原価科目「直接労務費」、間接費率「2.0%」、2行目は、製番分類「製品製番」、製番管理部門「製造部」、製番原価科目「間接経費」、対象製番原価科目「材料費、外注加工費」、間接費率「3.0%」が登録されている。 Figure 2 (A) is a diagram showing an example of the registration of the overhead rate master 106a. In the example of the overhead rate master 106a shown in Figure 2 (A), the first line has the production number classification "product production number", production number management department "manufacturing department", production number cost item "indirect labor cost", target production number cost item "direct labor cost", and overhead rate "2.0%". The second line has the production number classification "product production number", production number management department "manufacturing department", production number cost item "indirect cost", target production number cost item "material cost, outsourced processing cost", and overhead rate "3.0%".
3行目は、製番分類「試作製番」、製番管理部門「設計部」、製番原価科目「間接労務費」、対象製番原価科目「直接労務費」、間接費率「2.0%」、4行目は、製番分類「試作製番」、製番管理部門「設計部」、製番原価科目「間接経費」、対象製番原価科目「材料費、外注加工費」、間接費率「4.0%」が登録されている。 The third line has the production number classification "Prototype number", production number management department "Design department", production number cost item "Indirect labor costs", target production number cost item "Direct labor costs", and overhead rate "2.0%". The fourth line has the production number classification "Prototype number", production number management department "Design department", production number cost item "Indirect expenses", target production number cost item "Material costs, outsourced processing costs", and overhead rate "4.0%".
図2(B)は、製番分類マスタ106bの登録例を示す図である。図2(B)に示す製番分類マスタ106bの例では、試作製番、修理製番、経費製番、工事製番が登録されている。
Figure 2 (B) is a diagram showing an example of registration of the manufacturing
(直接費データ入力処理(仕入入力処理、出庫入力処理、作業実績入力処理)
図3において、仕入入力部102bは、仕入入力処理を実行する(ステップS2)。具体的には、仕入入力処理では、例えば、仕入入力部102bは、購買担当者の端末400のリクエストに応じて端末400に仕入入力画面を提供し、仕入入力画面上での購買担当者の端末400の操作等に応じて、仕入入力データを入力してデータファイル106cに格納する。
(Direct cost data entry processing (purchase entry processing, shipment entry processing, work performance entry processing)
3, the purchase input unit 102b executes a purchase input process (step S2). Specifically, in the purchase input process, for example, the purchase input unit 102b provides a purchase input screen to the terminal 400 of the purchasing clerk in response to a request from the terminal 400, and inputs purchase input data in response to operations of the terminal 400 of the purchasing clerk on the purchase input screen, and stores the data in the data file 106c.
出庫入力部102cは、出庫入力処理を実行する(ステップS3)。具体的には、出庫入力処理では、出庫入力部102cは、例えば、購買担当者の端末400のリクエストに応じて端末400に出荷入力画面を提供し、出荷入力画面上での購買担当者の端末400の操作等に応じて、出庫入力データを入力してデータファイル106cに格納する。
The
作業実績入力部102dは、作業実績入力処理を実行する(ステップS4)。具体的には、作業実績入力処理では、作業実績入力部102dは、例えば、製造担当者の端末400のリクエストに応じて端末400に製造実績入力画面を提供し、製造実績入力画面上での製造担当者の端末400の操作等に応じて、作業実績入力データを入力してデータファイル106cに格納する。
The work
図3(A)は、各入力処理より計上される直接費データ(原価明細)の一例を示す図である。図3(A)において、1行目は、データ種類「仕入」、製番「F1010095」、製番分類「製品製番」、製番原価科目「材料費」、製番管理部門「製造部」、原価「1,000」、2行目は、データ種類「仕入」、製番「F9010002」、製番分類「試作製番」、製番原価科目「外注加工費」、製番管理部門「設計部」、原価「1,500」、3行目は、データ種類「仕入」、製番「F9010002」、製番分類「試作製番」、製番原価科目「材料費」、製番管理部門「設計部」、原価「2,000」、4行目は、データ種類「出庫」、製番「F1010095」、製番分類「製品製番」、製番原価科目「材料費」製番管理部門「製造部」、原価「1,000」となっている。 Figure 3 (A) is a diagram showing an example of direct cost data (cost details) recorded by each input process. In Figure 3 (A), the first line shows data type "Purchase", serial number "F1010095", serial number classification "Product serial number", serial number cost item "Material cost", serial number management department "Manufacturing department", and cost "1,000". The second line shows data type "Purchase", serial number "F9010002", serial number classification "Prototype serial number", serial number cost item "Outsourced processing cost", serial number management department "Design department", and cost "1,500". 0", the third line has data type "Purchase", serial number "F9010002", serial number classification "Prototype No.", serial number cost item "Materials Cost", serial number management department "Design Department", cost "2,000", the fourth line has data type "Shipping", serial number "F1010095", serial number classification "Product serial number", serial number cost item "Materials Cost", serial number management department "Manufacturing Department", cost "1,000".
5行目は、データ種類「出庫」、製番「F9010002」、製番分類「試作製番」、製番原価科目「材料費」、製番管理部門「設計部」、原価「1,000」、6行目は、データ種類「出庫」、製番「F9010002」、製番分類「試作製番」、製番原価科目「材料費」、製番管理部門「設計部」、原価「1,500」、7行目は、データ種類「作業実績」、製番「F9010002」、製番分類「試作製番」、製番原価科目「直接労務費」、製番管理部門「設計部」、原価「5,000」となっている。 The fifth line has the data type "shipping", serial number "F9010002", serial number classification "prototype number", serial number cost item "material cost", serial number management department "design department", cost "1,000", the sixth line has the data type "shipping", serial number "F9010002", serial number classification "prototype number", serial number cost item "material cost", serial number management department "design department", cost "1,500", the seventh line has the data type "work performance", serial number "F9010002", serial number classification "prototype number", serial number cost item "direct labor cost", serial number management department "design department", cost "5,000".
(原価計算処理)
原価計算処理部102eは、原価計算処理を実行する(ステップS5)。具体的には、原価計算処理では、原価計算処理部102eは、直接費データ(仕入入力データ、出庫入力データ、作業実績入力データ)について、製番、製番分類、製番管理部門、及び製番原価科目(直接費の種類)毎に原価を集計し、製番分類、製番管理部門、及び製番原価科目(直接費の種類)をキーとして間接費率マスタ106aから間接費率を取得して直接費の原価に乗算することで、間接費を算出する。
(Cost accounting process)
The cost calculation processing unit 102e executes the cost calculation process (step S5). Specifically, in the cost calculation process, the cost calculation processing unit 102e aggregates the costs for each production number, production number classification, production number management department, and production number cost item (type of direct cost) for the direct cost data (purchase input data, delivery input data, and work performance input data), obtains the overhead rate from the overhead rate master 106a using the production number classification, production number management department, and production number cost item (type of direct cost) as keys, and multiplies the overhead rate by the cost of the direct cost to calculate the overhead cost.
図3(B)は、原価計算過程を示しており、直接費の原価に間接費率を乗算したものを示している。図3(B)において、1行目は、図3(A)の1行目と4行目を集計し、製番分類「製品製番」、製番原価科目「材料費」、製番管理部門「製造部」をキーとして、図2(A)の間接費率マスタ106aから間接費率「3.0%」を取得し、製番「F1010095」、製番分類「製品製番」、製番原価科目「材料費」、製番管理部門「製造部」、原価「2,000」×間接費率「3.0%」となっている。 Figure 3 (B) shows the cost calculation process, showing the direct cost multiplied by the overhead rate. In Figure 3 (B), the first line is the sum of the first and fourth lines of Figure 3 (A), and the overhead rate "3.0%" is obtained from the overhead rate master 106a in Figure 2 (A) using the production number classification "product production number", production number cost item "material cost", and production number management department "Manufacturing Department" as keys, resulting in production number "F1010095", production number classification "product production number", production number cost item "material cost", production number management department "Manufacturing Department", cost "2,000" x overhead rate "3.0%".
2行目は、図3(A)の2行目に対応しており、製番分類「試作製番」、製番原価科目「外注加工費」、製番管理部門「設計部」をキーとして、図2(A)の0間接費率マスタ106aから間接費率「4.0%」を取得し、製番「F9010002」、製番分類「試作製番」、製番原価科目「外注加工費」、製番管理部門「設計部」、原価「1,500」×間接費率「4.0%」となっている。 The second line corresponds to the second line in Figure 3 (A), and using the production number classification "trial production number", production number cost item "outsourced processing cost", and production number management department "design department" as keys, the overhead rate "4.0%" is obtained from the overhead rate master 106a in Figure 2 (A), resulting in production number "F9010002", production number classification "trial production number", production number cost item "outsourced processing cost", production number management department "design department", cost "1,500" x overhead rate "4.0%".
3行目は、図3(A)の3行目、5行目、6行目を集計し、製番分類「試作製番」、製番原価科目「材料費」、製番管理部門「設計部」をキーとして、図2(A)の間接費率マスタ106aから間接費率「4.0%」を取得し、製番「F9010002」、製番分類「試作製番」、製番原価科目「材料費」、製番管理部門「設計部」、原価「4,500」×間接費率「4.0%」となっている。 The third line is calculated by aggregating the third, fifth, and sixth lines in FIG. 3(A), and obtaining the overhead rate of "4.0%" from the overhead rate master 106a in FIG. 2(A) using the production number classification "trial production number", production number cost item "material cost", and production number management department "design department" as keys, resulting in production number "F9010002", production number classification "trial production number", production number cost item "material cost", production number management department "design department", cost "4,500" x overhead rate "4.0%".
4行目は、図3(A)の7行目に対応しており、製番分類「試作製番」、製番原価科目「直接労務費」、製番管理部門「設計部」をキーとして、図2(A)の間接費率マスタ106aから間接費率「2.0%」を取得し、製番「F9010002」、製番分類「試作製番」、製番原価科目「直接労務費」、製番管理部門「設計部」、原価「5,000」×間接費率「2.0%」となっている。 The fourth line corresponds to the seventh line in Figure 3 (A), and using the serial number classification "trial production number", serial number cost item "direct labor cost", and serial number management department "design department" as keys, the overhead rate "2.0%" is obtained from the overhead rate master 106a in Figure 2 (A), resulting in serial number "F9010002", serial number classification "trial production number", serial number cost item "direct labor cost", serial number management department "design department", cost "5,000" x overhead rate "2.0%".
図4(C)は、間接費の原価計算結果を示しており、間接費率マスタ106aを参照して、製番及び製番原価科目(間接費の種類)毎に、間接費を集計した結果を示している。1行目は、製番「F1010095」、製番原価科目「間接経費」、製造間接費「60」、2行目は、製番「F9010002」、製番原価科目「間接経費」、製造間接費「240」、3行目は、製番「F9010002」、製番原価科目「間接労務費」、製造間接費「100」となっている。 Figure 4 (C) shows the result of overhead cost calculation, and shows the result of totaling overhead by serial number and serial number cost item (type of overhead) by referring to the overhead rate master 106a. The first line shows serial number "F1010095", serial number cost item "indirect expenses", and manufacturing overhead "60", the second line shows serial number "F9010002", serial number cost item "indirect expenses", and manufacturing overhead "240", and the third line shows serial number "F9010002", serial number cost item "indirect labor costs", and manufacturing overhead "100".
図4(D)は、図3(A)と図4(C)を纏めたもので、製番毎の直接費と間接費の内訳を示している。 Figure 4 (D) combines Figure 3 (A) and Figure 4 (C) and shows the breakdown of direct and indirect costs by serial number.
(仕訳連携処理)
仕訳連携処理部102fは、仕訳連携処理を実行する(ステップS6)。具体的には、仕訳連携処理では、仕訳連携処理部102fは、会計システム(原価差額集計部)102gと連携して、予定原価データ(直接費データと間接費データ)について、所定分類(例えば、部門毎)の仕訳を作成して、データファイル106cに格納する。
(Journal entry linkage processing)
The journal entry
図4(E)は、製造部と設計部の仕訳の例を示している。製造部については、材料費「2,000」/仮勘定(直接材料費予定額)「2,000」、外注加工費「0」/仮勘定(直接経費予定額)「0」、間接経費「60」/仮勘定(間接経費予定額)「60」、直接労務費「0」/仮勘定(直接労務費予定額)「0」、間接労務費「0」/仮勘定(間接労務費予定額)「0」となっている。 Figure 4 (E) shows an example of accounting for the manufacturing department and the design department. For the manufacturing department, material costs are "2,000" / temporary account (planned direct material costs) "2,000", outsourced processing costs "0" / temporary account (planned direct expenses) "0", indirect expenses "60" / temporary account (planned indirect expenses) "60", direct labor costs "0" / temporary account (planned direct labor costs) "0", indirect labor costs "0" / temporary account (planned indirect labor costs) "0".
設計部については、材料費「4,500」/仮勘定(直接材料費予定額)「4,500」、外注加工費「1,500」/仮勘定(直接経費予定額)「1,500」、間接経費「240」/仮勘定(間接経費予定額)「240」、直接労務費「5,000」/仮勘定(直接労務費予定額)「5,000」、間接労務費「100」/仮勘定(間接労務費予定額)「100」となっている。 For the design department, material costs are "4,500" / provisional account (estimated direct material costs) "4,500", outsourced processing costs are "1,500" / provisional account (estimated direct expenses) "1,500", indirect expenses are "240" / provisional account (estimated indirect expenses) "240", direct labor costs are "5,000" / provisional account (estimated direct labor costs) "5,000", indirect labor costs are "100" / provisional account (estimated indirect labor costs) "100".
(原価差額集計処理)
会計システム(原価差額集計部)102gは、原価差額集計処理を実行する(ステップS7)。具体的には、原価差額集計処理では、会計システム(原価差額集計部)102gは、実際発生原価(例えば、材料費実際発生額、労務費実際発生額、経費実際発生額)を取得し、予定原価と実際発生原価に基づいて、所定分類毎(例えば、部門毎)の原価差額集計表を作成して、データファイル106cに格納する。なお、会計システム(原価差額集計部)102gでは、例えば、経理担当者の端末400のリクエストに応じて端末400に実際発生原価入力画面を提供し、実際発生原価入力画面上での経理担当者の端末400の操作等に応じて、実際発生原価を入力してもよい。
(Cost difference aggregation process)
The accounting system (cost difference tallying unit) 102g executes a cost difference tallying process (step S7). Specifically, in the cost difference tallying process, the accounting system (cost difference tallying unit) 102g acquires the actual incurred costs (e.g., the actual amount of material costs, the actual amount of labor costs, and the actual amount of expenses), creates a cost difference tally table for each predetermined classification (e.g., each department) based on the planned cost and the actual incurred costs, and stores the table in the data file 106c. In addition, the accounting system (cost difference tallying unit) 102g may provide an actual incurred cost input screen to the terminal 400 in response to a request from the accounting staff member's terminal 400, and input the actual incurred costs in response to the operation of the accounting staff member's terminal 400 on the actual incurred cost input screen.
図4(F)は、部門別の原価差額集計表の一例を示す図である。材料費原価差異=材料費実際発生額-(直接材料費予定額+間接材料費予定額)、労務費原価差異=労務費実際発生額-(直接労務費予定額+間接労務費予定額)、経費原価差異=経費実際発生額-(直接経費予定額+間接経費予定額)で算出することができる。 Figure 4 (F) is a diagram showing an example of a cost variance summary table by department. It can be calculated as follows: Material cost variance = actual material cost incurred - (planned direct material cost + planned indirect material cost), Labor cost variance = actual labor cost incurred - (planned direct labor cost + planned indirect labor cost), Expense cost variance = actual expense incurred - (planned direct expense + planned indirect expense).
製番管理部門「製造部」については、材料費実際発生額「2,000」、直接材料費予定額「2,000」、間接材料費予定額「0」、材料費原価差異「0」、労務費実際発生額「0」、直接労務費予定額「0」、間接労務費予定額「0」、労務費原価差異「0」、経費実際発生額「50」、直接経費予定額「0」、間接経費予定額「60」、経費原価差異「-10」となっている。 For the manufacturing department, which is responsible for managing serial numbers, the actual material costs incurred are "2,000", the planned direct material costs are "2,000", the planned indirect material costs are "0", the material cost variance is "0", the actual labor costs incurred are "0", the planned direct labor costs are "0", the planned indirect labor costs are "0", the labor cost variance is "0", the actual expenses incurred are "50", the planned direct expenses are "0", the planned indirect expenses are "60", and the expense cost variance is "-10".
製番管理部門「設計部」については、材料費実際発生額「4,600」、直接材料費予定額「4,500」、間接材料費予定額「0」、材料費原価差異「100」、労務費実際発生額「5,000」、直接労務費予定額「5,000」、間接労務費予定額「100」、労務費原価差異「-100」、経費実際発生額「1,740」、直接経費予定額「1,500」、間接経費予定額「240」、経費原価差異「0」となっている。なお、ここでは、部門別で集計しているが、製番別や製番分類別に集計してもよい。 For the serial number management department "Design Department", the actual material costs incurred are "4,600", the planned direct material costs are "4,500", the planned indirect material costs are "0", the material cost variance is "100", the actual labor costs incurred are "5,000", the planned direct labor costs are "5,000", the planned indirect labor costs are "100", the labor cost variance is "-100", the actual expenses incurred are "1,740", the planned direct expenses are "1,500", the planned indirect expenses are "240", and the expense cost variance is "0". Note that although the data is tabulated by department here, it may also be tabulated by serial number or serial number classification.
以上説明したように、本実施の形態によれば、製番分類、製番管理部門、及び製番原価科目毎に、間接費率を設定した間接費率マスタ106aと、各種データについて、製番、製番分類、製番管理部門、製番原価科目、及び原価を含む直接費データを入力する入力手段(仕入入力部102b、出庫入力部102c、作業実績入力部102d)と、前記直接費データについて、製番分類、製番管理部門、製番原価科目毎に原価を集約し、集約した原価に、間接費率マスタ106aから製番分類、製番管理部門、及び製番原価科目をキーとして取得した間接費率を乗算して間接費データを算出する原価計算処理部102eと、前記直接費データ及び前記間接費データを含む予定原価データについて、所定分類の仕訳を作成する仕訳連携処理部102fと、実際発生原価を取得し、前記予定原価データと取得した実際発生原価について、前記所定分類の原価差額集計表を作成する会計システム(原価差額集計部)102gと、を備えているので、間接費を細分化して計上することで原価予実管理を高精度に行うことが可能となる。
As described above, according to this embodiment, there is an overhead rate master 106a in which overhead rates are set for each serial number classification, serial number management department, and serial number cost item, and input means (purchase input section 102b,
[4.他の実施形態]
本発明は、上述した実施形態以外にも、特許請求の範囲に記載した技術的思想の範囲内において種々の異なる実施形態にて実施されてよいものである。
4. Other embodiments
The present invention may be embodied in various different embodiments other than those described above within the scope of the technical concept set forth in the claims.
例えば、実施形態において説明した各処理のうち、自動的に行われるものとして説明した処理の全部または一部を手動的に行うこともでき、あるいは、手動的に行われるものとして説明した処理の全部または一部を公知の方法で自動的に行うこともできる。 For example, among the processes described in the embodiments, all or part of the processes described as being performed automatically can be performed manually, or all or part of the processes described as being performed manually can be performed automatically using a known method.
また、本明細書中や図面中で示した処理手順、制御手順、具体的名称、各処理の登録データや検索条件等のパラメータを含む情報、画面例、データベース構成については、特記する場合を除いて任意に変更することができる。 In addition, the processing procedures, control procedures, specific names, registered data for each process, information including search conditions and other parameters, screen examples, and database configurations shown in this specification and drawings may be changed as desired unless otherwise specified.
また、原価予実管理装置100に関して、図示の各構成要素は機能概念的なものであり、必ずしも物理的に図示の如く構成されていることを要しない。
In addition, with regard to the cost budget/
例えば、原価予実管理装置100が備える処理機能、特に制御部にて行われる各処理機能については、その全部または任意の一部を、CPUおよび当該CPUにて解釈実行されるプログラムにて実現してもよく、また、ワイヤードロジックによるハードウェアとして実現してもよい。尚、プログラムは、本実施形態で説明した処理を情報処理装置に実行させるためのプログラム化された命令を含む一時的でないコンピュータ読み取り可能な記録媒体に記録されており、必要に応じて原価予実管理装置100に機械的に読み取られる。すなわち、ROMまたはHDD(Hard Disk Drive)などの記憶部などには、OSと協働してCPUに命令を与え、各種処理を行うためのコンピュータプログラムが記録されている。このコンピュータプログラムは、RAMにロードされることによって実行され、CPUと協働して制御部を構成する。
For example, the processing functions of the cost forecast/
また、このコンピュータプログラムは、原価予実管理装置100に対して任意のネットワークを介して接続されたアプリケーションプログラムサーバに記憶されていてもよく、必要に応じてその全部または一部をダウンロードすることも可能である。
This computer program may also be stored in an application program server connected to the cost budget/
また、本実施形態で説明した処理を実行するためのプログラムを、一時的でないコンピュータ読み取り可能な記録媒体に格納してもよく、また、プログラム製品として構成することもできる。ここで、この「記録媒体」とは、メモリーカード、USB(Universal Serial Bus)メモリ、SD(Secure Digital)カード、フレキシブルディスク、光磁気ディスク、ROM、EPROM(Erasable Programmable Read Only Memory)、EEPROM(登録商標)(Electrically Erasable and Programmable Read Only Memory)、CD-ROM(Compact Disk Read Only Memory)、MO(Magneto-Optical disk)、DVD(Digital Versatile Disk)、および、Blu-ray(登録商標) Disc等の任意の「可搬用の物理媒体」を含むものとする。 In addition, the program for executing the processing described in this embodiment may be stored on a non-transitory computer-readable recording medium, or may be configured as a program product. Here, the term "recording medium" refers to a memory card, a USB (Universal Serial Bus) memory, a SD (Secure Digital) card, a flexible disk, a magneto-optical disk, a ROM, an EPROM (Erasable Programmable Read Only Memory), an EEPROM (registered trademark) (Electrically Erasable and Programmable Read Only Memory), a CD-ROM (Compact Disk Read Only Memory), an MO (Magneto-Optical disk), a DVD (Digital Versatile This includes any "portable physical media" such as a Blu-ray (registered trademark) Disc, and a Blu-ray (registered trademark) Disc.
また、「プログラム」とは、任意の言語または記述方法にて記述されたデータ処理方法であり、ソースコードまたはバイナリコード等の形式を問わない。なお、「プログラム」は必ずしも単一的に構成されるものに限られず、複数のモジュールやライブラリとして分散構成されるものや、OSに代表される別個のプログラムと協働してその機能を達成するものをも含む。なお、実施形態に示した各装置において記録媒体を読み取るための具体的な構成および読み取り手順ならびに読み取り後のインストール手順等については、周知の構成や手順を用いることができる。 A "program" is a data processing method written in any language or description method, and may be in any format, such as source code or binary code. Note that a "program" is not necessarily limited to a single configuration, but also includes a distributed configuration consisting of multiple modules or libraries, and a program that works in conjunction with a separate program, such as an OS, to achieve its function. Note that the specific configuration and reading procedure for reading a recording medium in each device shown in the embodiments, as well as the installation procedure after reading, can use well-known configurations and procedures.
記憶部に格納される各種のデータベース等は、RAM、ROM等のメモリ装置、ハードディスク等の固定ディスク装置、フレキシブルディスク、及び、光ディスク等のストレージ手段であり、各種処理やウェブサイト提供に用いる各種のプログラム、テーブル、データベース、及び、ウェブページ用ファイル等を格納する。 The various databases stored in the memory unit are storage devices such as RAM, ROM, etc., fixed disk devices such as hard disks, flexible disks, and optical disks, and store various programs, tables, databases, and web page files used for various processes and providing websites.
また、原価予実管理装置100は、既知のパーソナルコンピュータまたはワークステーション等の情報処理装置として構成してもよく、また、任意の周辺装置が接続された当該情報処理装置として構成してもよい。また、原価予実管理装置100は、当該装置に本実施形態で説明した処理を実現させるソフトウェア(プログラムまたはデータ等を含む)を実装することにより実現してもよい。
The cost budget/
更に、装置の分散・統合の具体的形態は図示するものに限られず、その全部または一部を、各種の付加等に応じてまたは機能負荷に応じて、任意の単位で機能的または物理的に分散・統合して構成することができる。すなわち、上述した実施形態を任意に組み合わせて実施してもよく、実施形態を選択的に実施してもよい。 Furthermore, the specific form of distribution and integration of the devices is not limited to that shown in the figures, and all or part of them can be functionally or physically distributed and integrated in any unit depending on various additions or functional loads. In other words, the above-mentioned embodiments can be implemented in any combination, or the embodiments can be implemented selectively.
100 原価予実管理装置
102 制御部
102a マスタメンテ部
102b 仕入入力部
102c 出庫入力部
102d 作業実績入力部
102e 原価計算処理部
102f 仕訳連携処理部
102g 会計システム(原価差額集計部)
104 通信インターフェース部
106 記憶部
106a 間接費率マスタ
106b 製番分類マスタ
106c データファイル
108 入出力インターフェース部
112 入力装置
114 出力装置
200 サーバ
300 ネットワーク
400 端末
100 Cost forecast/actual management device 102
104 Communication interface unit 106 Storage unit 106a Overhead
Claims (5)
前記制御部は、
製番分類、製番管理部門、及び製番原価科目毎に、間接費率を設定したマスタにアクセス可能に構成されており、
各種データについて、製番、製番分類、製番管理部門、製番原価科目、及び原価を含む直接費データを入力する入力手段と、
前記直接費データを製番分類、製番管理部門、製番原価科目毎に原価を集約し、集約した原価に、前記マスタから製番分類、製番管理部門、及び製番原価科目をキーとして取得した間接費率を乗算して間接費データを算出する原価計算処理手段と、
を備えたことを特徴とする原価予実管理装置。 A cost budget/actual management device having a control unit,
The control unit is
It is structured so that master data with overhead rates set for each manufacturing number classification, manufacturing number management department, and manufacturing number cost item can be accessed.
An input means for inputting direct cost data including a production number, a production number classification, a production number management department, a production number cost item, and a cost with respect to various data;
a cost calculation processing means for aggregating the direct cost data by manufacturing number classification, manufacturing number management department, and manufacturing number cost item, and multiplying the aggregated cost by an indirect cost rate obtained from the master using the manufacturing number classification, manufacturing number management department, and manufacturing number cost item as keys to calculate indirect cost data;
A cost budget/actual management device comprising:
前記直接費データ及び前記間接費データを含む予定原価データについて、所定分類の仕訳を作成する仕訳作成手段を備えたことを特徴とする請求項1に記載の原価予実管理装置。 The control unit further includes:
2. The cost forecast/actual management device according to claim 1, further comprising a journal entry creating means for creating journal entries of a predetermined classification for planned cost data including said direct cost data and said indirect cost data.
実際発生原価を取得し、前記直接費データ及び前記間接費データを含む予定原価データと取得した実際発生原価について、所定分類の原価差額集計表を作成する原価差額集計手段を備えたことを特徴とする請求項1に記載の原価予実管理装置。 The control unit further includes:
The cost forecast/actual management device according to claim 1, further comprising a cost difference aggregation means for acquiring actual incurred costs, and creating a cost difference aggregation table for a specified classification for the planned cost data including the direct cost data and the indirect cost data and the acquired actual incurred costs.
前記制御部は、
製番分類、製番管理部門、及び製番原価科目毎に、間接費率を設定したマスタにアクセス可能に構成されており、
前記制御部において実行される、
各種データについて、製番、製番分類、製番管理部門、製番原価科目、及び原価を含む直接費データを入力する入力工程と、
前記直接費データを製番分類、製番管理部門、製番原価科目毎に原価を集約し、集約した原価に、前記マスタから製番分類、製番管理部門、及び製番原価科目をキーとして取得した間接費率を乗算して間接費データを算出する原価計算処理工程と、
を含むことを特徴とする原価予実管理方法。 A cost budget/actual management method executed by an information processing device having a control unit,
The control unit is
It is structured so that master data with overhead rates set for each manufacturing number classification, manufacturing number management department, and manufacturing number cost item can be accessed.
Executed in the control unit,
An input process for inputting direct cost data including a production number, a production number classification, a production number management department, a production number cost item, and a cost for each type of data;
a cost calculation process for aggregating the direct cost data by manufacturing number classification, manufacturing number management department, and manufacturing number cost item, and multiplying the aggregated cost by an indirect cost rate obtained from the master using the manufacturing number classification, manufacturing number management department, and manufacturing number cost item as keys to calculate indirect cost data;
A cost budget/actual management method comprising:
前記制御部は、
製番分類、製番管理部門、及び製番原価科目毎に、間接費率を設定したマスタにアクセス可能に構成されており、
前記制御部において、
各種データについて、製番、製番分類、製番管理部門、製番原価科目、及び原価を含む直接費データを入力する入力工程と、
前記直接費データを製番分類、製番管理部門、製番原価科目毎に原価を集約し、集約した原価に、前記マスタから製番分類、製番管理部門、及び製番原価科目をキーとして取得した間接費率を乗算して間接費データを算出する原価計算処理工程と、
を実行させるための原価予実管理プログラム。 A cost budget/actual management program to be executed by an information processing device having a control unit,
The control unit is
It is structured so that master data with overhead rates set for each manufacturing number classification, manufacturing number management department, and manufacturing number cost item can be accessed.
In the control unit,
An input process for inputting direct cost data including a production number, a production number classification, a production number management department, a production number cost item, and a cost for each type of data;
a cost calculation process for aggregating the direct cost data by manufacturing number classification, manufacturing number management department, and manufacturing number cost item, and multiplying the aggregated cost by an indirect cost rate obtained from the master using the manufacturing number classification, manufacturing number management department, and manufacturing number cost item as keys to calculate indirect cost data;
A cost budget/actual management program to implement the above.
Applications Claiming Priority (3)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020046420 | 2020-03-17 | ||
| JP2020046420 | 2020-03-17 | ||
| JP2020173587A JP7404215B2 (en) | 2020-03-17 | 2020-10-14 | Cost budget and actual management device, cost budget and actual management method, and cost budget and actual management program |
Related Parent Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020173587A Division JP7404215B2 (en) | 2020-03-17 | 2020-10-14 | Cost budget and actual management device, cost budget and actual management method, and cost budget and actual management program |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2024015351A JP2024015351A (en) | 2024-02-01 |
| JP7601997B2 true JP7601997B2 (en) | 2024-12-17 |
Family
ID=77849170
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020173587A Active JP7404215B2 (en) | 2020-03-17 | 2020-10-14 | Cost budget and actual management device, cost budget and actual management method, and cost budget and actual management program |
| JP2023208907A Active JP7601997B2 (en) | 2020-03-17 | 2023-12-12 | Cost budget/actual management device, cost budget/actual management method, and cost budget/actual management program |
Family Applications Before (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020173587A Active JP7404215B2 (en) | 2020-03-17 | 2020-10-14 | Cost budget and actual management device, cost budget and actual management method, and cost budget and actual management program |
Country Status (1)
| Country | Link |
|---|---|
| JP (2) | JP7404215B2 (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7296510B1 (en) | 2022-07-27 | 2023-06-22 | 株式会社オービック | Business support device, business support method, and business support program |
| JP2024049901A (en) * | 2022-09-29 | 2024-04-10 | 株式会社オービック | Budget/actual management device, budget/actual management method, and budget/actual management program |
| JP7824203B2 (en) * | 2022-11-30 | 2026-03-04 | 株式会社オービック | Business support device, business support method, and business support program |
| JP7723372B2 (en) * | 2023-04-13 | 2025-08-14 | 株式会社Niコンサルティング | Automatic journal entry program |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004213236A (en) | 2002-12-27 | 2004-07-29 | Hitachi Ltd | Cost calculation method and form of cost calculation result, cost calculation program and method of outputting form in medical institution |
| JP2004258717A (en) | 2003-02-24 | 2004-09-16 | Toyo Business Engineering Corp | Cost management system and method |
| JP2007102376A (en) | 2005-09-30 | 2007-04-19 | Being:Kk | Integration device |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6881930B2 (en) * | 2015-11-05 | 2021-06-02 | 株式会社オービック | Project accounting management device, project accounting management method, and project accounting management program |
-
2020
- 2020-10-14 JP JP2020173587A patent/JP7404215B2/en active Active
-
2023
- 2023-12-12 JP JP2023208907A patent/JP7601997B2/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004213236A (en) | 2002-12-27 | 2004-07-29 | Hitachi Ltd | Cost calculation method and form of cost calculation result, cost calculation program and method of outputting form in medical institution |
| JP2004258717A (en) | 2003-02-24 | 2004-09-16 | Toyo Business Engineering Corp | Cost management system and method |
| JP2007102376A (en) | 2005-09-30 | 2007-04-19 | Being:Kk | Integration device |
Non-Patent Citations (2)
| Title |
|---|
| 岩橋 秀年,第1回 企業の競争力を支える基幹システムの導入,工場管理,日刊工業新聞社,2015年01月01日,Vol.61 No.1,pp.113-118 |
| 田畑 正英,原価会計システムの実務,初版,株式会社中央経済社,1997年08月15日,p.65,81 |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2024015351A (en) | 2024-02-01 |
| JP7404215B2 (en) | 2023-12-25 |
| JP2021149926A (en) | 2021-09-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7601997B2 (en) | Cost budget/actual management device, cost budget/actual management method, and cost budget/actual management program | |
| JP7654857B2 (en) | Project management device, project management method, and project management program | |
| JP7481541B2 (en) | Information generating device, information generating program, and information generating method | |
| JP7085304B2 (en) | Cost calculator, cost calculation method and cost calculation program | |
| JP7093267B2 (en) | Data generator, data generation method and data generation program | |
| JP2024044063A (en) | Income and expenditure management device, income and expenditure management method, and income and expenditure management program | |
| JP6923408B2 (en) | Retroactive unit price correction device, retroactive unit price correction method, and retroactive unit price correction program | |
| JP6798856B2 (en) | Amount calculation device, amount calculation method and amount calculation program | |
| JP2020166538A (en) | Base material costing device, base material costing method, and base material costing program | |
| JP2019168980A (en) | Progress rate calculation device, progress rate calculation method and progress rate calculation program | |
| JP2022039638A (en) | Business support device, business support program, and business support method | |
| JP2021144344A (en) | Cost output device, cost output method, and cost output program | |
| JP2021047912A (en) | Work completion control device, work completion control method, and work completion control program | |
| JP7579139B2 (en) | Inspection management device, inspection management method, and inspection management program | |
| JP7410843B2 (en) | Sales recording device, sales recording method, and sales recording program | |
| JP7550714B2 (en) | Payment processing device, payment processing method, and payment processing program | |
| JP7535074B2 (en) | Cost transfer device, cost transfer method, and cost transfer program | |
| JP7733043B2 (en) | Project management system, project management method, and project management program | |
| JP7642461B2 (en) | Substitute processing device, substitute processing method, and substitute processing program | |
| JP7568564B2 (en) | Cost management support device, cost management support method, and cost management support program | |
| JP7783206B2 (en) | Sales processing device, sales processing method, and sales processing program | |
| JP7543032B2 (en) | Business support device, business support program, and business support method | |
| JP7636961B2 (en) | Income and expenditure management device, income and expenditure management method, and income and expenditure management program | |
| JP7498066B2 (en) | Information processing device, information processing method, and information processing program | |
| JP7538700B2 (en) | Manufacturing instruction/repair instruction slip creation device, manufacturing instruction/repair instruction slip creation method, and manufacturing instruction/repair instruction slip creation program |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20231212 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20241112 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20241205 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7601997 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |