JP7616772B2 - On-site construction method for foundation piles - Google Patents
On-site construction method for foundation piles Download PDFInfo
- Publication number
- JP7616772B2 JP7616772B2 JP2021075432A JP2021075432A JP7616772B2 JP 7616772 B2 JP7616772 B2 JP 7616772B2 JP 2021075432 A JP2021075432 A JP 2021075432A JP 2021075432 A JP2021075432 A JP 2021075432A JP 7616772 B2 JP7616772 B2 JP 7616772B2
- Authority
- JP
- Japan
- Prior art keywords
- tunneling machine
- ground
- steel pipe
- soil
- improved body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
コンクリート建造物又はマンション・ビル等の大重量のコンクリート大型建築物を地上に構築する場合、その工事現場の地面にこれら重量ある建造物・大型建築物を支持するため、基礎工として所要杭径の杭をその地面下方の地盤の支持層に届くまでの所定長さの基礎杭を多数本打設している。本発明は、この基礎杭を地下埋設管工事で使用する横孔用の掘進機を利用して鉛直な削孔を掘削し、及び発生した排土を再利用して固化材を添加して改良土を形成させ、削孔内に撹拌充填させることで場所打杭を構築する技術に関する。 When constructing a concrete structure or a large, heavy concrete building such as an apartment building or a building on the ground, a large number of foundation piles of the required diameter and a specified length are driven into the ground at the construction site as foundation work to support the heavy structure or large building. This invention relates to a technology for constructing these foundation piles by excavating vertical holes using a horizontal hole boring machine used in underground pipe construction, reusing the generated waste soil, adding a solidifying material to form improved soil, and mixing and filling the drilled holes.
特許文献1,2に示すように、従来の基礎杭打設作業は、現場地面に10mを超える垂直の長いリーダーを備えたPC打撃機又は杭打機を現場に設置して、PCパイル打撃工法,プレボーリング工法によって地上から長尺の基礎杭を地盤下方に向って打撃振動を与えながら打ち込んで、その支持層に届くまで打設して基礎杭を構築するものである。
又、場所打杭の構築においても大型のクローラクレーンを用いた削孔機械で掘削し、削孔内にベントナイト溶液等を充填させ、その後トレミー管を使って下方よりコンクリートに置き替える施工法もあった。
As shown in
Also, when constructing cast-in-place piles, one method involves digging with a boring machine using a large crawler crane, filling the hole with a bentonite solution or the like, and then replacing it with concrete from below using a tremie pipe.
この従来の基礎杭打設工法では、現場に高い大型のPC打撃機・杭打機及び削孔機等を安全に設置せねばならず、そのための広い設置空間を確保しなければならない。又、PC打撃機・杭打機が地震・風によって転倒して周囲建築物を破壊する危険があり、しかも施工現場に大きい振動と騒音を発生させていた。 This conventional foundation pile installation method requires the safe installation of large, tall PC hammers, pile drivers, drilling machines, etc., at the site, and a large installation space must be secured for these. In addition, there is a risk that the PC hammers and pile drivers will tip over due to earthquakes or wind, destroying surrounding buildings, and they also generate large vibrations and noise at the construction site.
加えて、従来の基礎杭の打設工法では下方の地盤の性状やその変化に応じて現場でその杭径や杭長を変更することが難しいものであった。又、地盤掘削作業で地上に排出した掘削土粒子の排土残土量が多く、その後処理にコストを費やすこととなっていた。 In addition, with conventional foundation pile installation methods, it was difficult to change the pile diameter or length on-site in response to changes in the properties of the ground below. Also, a large amount of excavated soil particles was discharged to the ground during ground excavation work, resulting in costs being incurred for subsequent disposal.
本発明が解決しようとする課題は、従来の下記の問題点を解決し、下記のイ~ヘの利点がある新しい発想の基礎杭の構築工法を提供することにある。
イ:地盤性状やその変化に応じて杭径や杭長を現場で変更可能として、適切な基礎杭を構築できるようにする。
ロ:地上に排出される掘削粒子の排土を現場で固化材を添加することで改良体として再投入し、有効利用して、排土残土量を低減して排土後処理工数を低減する。
ハ:基礎杭打設作業に大きな振動・騒音が発生しないようにできるようにする。
ニ:従来の基礎杭作業に必要な上方に長いリーダーを有する大型のPC打撃機・杭打機や削孔機の現場までの移動とその使用コスト及び現場での杭・鋼材の打設や吊り込みのためのクレーン作業の工数と作業負担を大巾に削減できるようにする。
ホ:使用する掘進機や機材が狭路な一般道でも搬入・搬出が可能で、省力化が実現できるようにする。
ヘ:長尺なコンクリート二次製品や鋼材等を不必要にして、それらの搬出入作業を大巾に省けるようにする。
The problem to be solved by the present invention is to provide a new construction method for foundation piles which solves the following conventional problems and has the following advantages A to F.
(i) The pile diameter and length can be changed on-site in response to ground conditions and changes, enabling the construction of appropriate foundation piles.
(b) The excavated soil particles discharged to the ground are re-introduced as an improved soil by adding solidification material on-site, making effective use of the soil, reducing the amount of waste soil discharged and reducing the labor required for post-discharge soil processing.
C: Make it possible to prevent large vibrations and noise from occurring during the foundation pile driving process.
2) To significantly reduce the labor and workload required for transporting and using large PC impact machines, pile drivers, and drilling machines with long upward leaders that are necessary for conventional foundation pile work, to the site, as well as the labor and workload required for crane work to drive and hoist piles and steel materials on site.
E: The tunneling machines and other equipment used will be able to be transported in and out through narrow public roads, thereby realizing labor savings.
F: Eliminate the need for long secondary concrete products, steel materials, etc., and significantly reduce the work of transporting them in and out.
かかる課題を解決した本発明の構成は、
1) 建造物の基礎杭を打設する現場において、密閉型の掘進機を現場地面に対し鉛直方向に掘進させて所定径で所定深さの削孔を掘削し、その後掘削された排土と固化材を撹拌し、同削孔内に充填して前記削孔位置に固化された基礎杭を構築する基礎杭の現場構築工法であって、
前記掘進機は、鉛直な筒状の外殻の下端に隔壁を設け,同隔壁の下方に掘削用カッター部を有し,更に前記隔壁には掘削された土砂を取り込む排土口を設け且つ隔壁の上方の外殻内部には前記カッター部を回動させる回動装置と排土口からの排土を上方へ送る途中に開閉バルブを備えた排土管とを有し、しかも同掘進機の外殻の口径は構築する基礎杭の杭径と同径とし且つ前記掘進機の後端口縁及び覆工体として連結された鋼管の口縁同士とは同径でフランジで互に脱着自在に連結できる鋼管を複数本用意し、しかも前記排土管は前記鋼管内部に通して地上へ送られるように配置し、更に打設する現場地面には掘進機を鉛直方向に向けて支持でき且つ同掘進機の上方に所要段数の鋼管を連結可能とし及び掘進機の上方にフランジ連結された複数段の鋼管からフランジを解いて最上段の鋼管を撤去作業ができる発進台と、同発進台に装置され掘進機にフランジ連結された最上段の鋼管を鉛直方向に押圧して掘進機と前記鋼管に鉛直方向の推進力を発生させ、且つ掘進機にフランジ連結された最上段の鋼管を上方に押圧して掘進機とこれと連結した鋼管を地上の発進台まで持ち上げることができる油圧ジャッキ装置と、更に掘進機から排土管を介して地上に送られ、ストックタンク内に貯留された排土又は別現場で発生して運送されてきた排土に所定割合で固化材を混練して改良体を作製する改良体製造装置と、作製された前記改良体を地上に露出した排土管の管内部へ圧送する改良体圧送装置とを配置し、
掘進時は前記発進台に掘進機を下向きに保持し、同掘進機の上方に所定段の鋼管をフランジ連結して前記油圧ジャッキ装置で最上段の鋼管に対して鉛直方向に押圧力を与えながら掘進機を作動させることで、しかも掘進機で鉛直方向に掘削させながら発進台で上方に鋼管を所要段数継ぎ足すことで基礎杭に要求される地盤の所定深さまで覆工を行いながら掘削する掘削工程と、
前記掘削工程で掘進機の排土管から地上に送り出される排土又は別現場の排土を使用して地上にて固化材を所定割合混練して改良体製造装置で改良体を作製する改良体製造工程と、作製した改良体を改良体圧送装置で地上に露出した排土管の管内に圧送して改良体を排土管を通して地中の掘進機先端のカッター隔壁から削孔内に圧入しながら掘進機とフランジ連結した鋼管を前記油圧ジャッキで持ち上げながら掘進機のカッター部で撹拌することで改良体を削孔内に均一に充填する改良体充填撹拌工程と、掘進機とその上方の鋼管を油圧ジャッキによって発進台の地上位置まで持ち上げてフランジ連結した鋼管を分離して掘進機を地上に回収する回収工程と、掘進機を上方に回収中に撹拌された改良体が固化して所定外径で支持地盤まで届いた所定深さを有して削孔壁に付着し、支持地盤で支持されたコンクリート現場構築の基礎杭が完成する固化工程とからなる、基礎杭の現場構築工法
2) 掘進機の外殻後方口縁とその直上の覆工体としての鋼管の下端口縁とを連結するフランジ及び上下の鋼管の上下端の口縁とを連結するフランジとして、前記掘進機の前記外殻後方口縁から外殻内側に張り出した環状の内フランジを設け、及び鋼管の上下端それぞれの口縁から管内側に張り出した環状の内フランジを設け、同一鉛直方向に直列に配置された掘進機とその上方の鋼管の対向する口縁の上下に重なる内フランジ同士を前記発進台でボルトナットで脱着自在に連結する構造としたものである、前記1)記載の基礎杭の現場構築工法
3) 前記発進台は現場地面に固定され、前記掘進機とこれに連結される前記鋼管とを構築予定の基礎杭の杭中心の位置の同一鉛直方向となるように前記掘進機と前記鋼管とを保持し、しかも前記掘進機と鋼管とは前記同一鉛直方向に上下動できるように発進台には掘進機と鋼管を保持するフレーム構造を有し、又前記油圧ジャッキ装置の構造は前記の最上段となる鋼管の管端を押圧できる押輪と前記同一鉛直方向に上下動可能に発進台に取付け、同押輪と地面上に設置される発進台のベースとの間に両引きの複数本の油圧ジャッキを設けられて、しかも複数の前記油圧ジャッキのシリンダーロッドの先端は前記押輪に取付けられ、前記油圧ジャッキのシリンダー筒体側を前記発進台のベースに取付け、更に最上段の鋼管の上縁の内フランジに固定ナットを設け、前記押輪に前記固定ナットと螺合できる吊りボルトの上部を前記押輪に係止できる構造とし、前記掘進機と鋼管とを押し下げる場合は前記押輪が最上段の鋼管の上縁に当接して下方向に両引きの前記油圧ジャッキを作動させ、掘進機と鋼管を持ち上げる場合は前記吊りボルトの下部ネジ部を最上段の鋼管の内フランジの前記固定ナットと螺合して押輪と最上段の鋼管とを連結して両引きの前記油圧ジャッキのシリンダーロッドが上方へ伸長するように作動させて、掘進機とその上方の連結された鋼管とを上方へ持ち上げられる構造のものとした、前記2)記載の基礎杭の現場構築工法
4) 前記3)記載の基礎杭の現場構築工法において、
前記現場の地上には、前記排土管を通して排土を地上側へ吸引する真空ポンプと、同真空ポンプで地上に送られた排土を一時貯える排土貯留槽と、前記固化材を貯えた固化材ホッパーと、前記排土貯留槽内の排土と前記固化材ホッパー内の前記固化材とを所定割合で混練して前記改良体を作製する改良体製造装置と、同改良体製造装置で作製された前記改良体を前記掘進機の前記排土管内に送り込む改良体圧送装置とその配管と、現場に作製する予定の基礎杭の地上の地面に対して前記掘進機と複数本の前記鋼管とを鉛直に配置でき、しかも対向する各フランジをボルトで脱着可能に連結した推進体を鉛直に保持し且つ同推進体を地盤に向けて下方又は地上に向けて上方にも移動できるようにした発進台と、同発進台で支持された前記推進体の最上段の鋼管を下方に押下げ又は地上側に向けて上方に持ち上げることができる前記発進台に取付けられた油圧ジャッキ装置とを現場地面に配置し、
まず前記発進台に同一鉛直方向に打設予定の基礎杭の杭口と略同じ外殻口径の掘進機とその上方に外殻口径と略同じ外径を有する複数の鋼管を配置し、鉛直の掘進機とその上方の鋼管とを互にフランジで連結した後前記発進台に取付けた前記油圧ジャッキ装置を作動させて前記掘進機と複数の連結された前記鋼管に前記油圧ジャッキ装置によって最上位となる前記押輪に押下げ力を荷重しながら前記掘進機の前記回動装置を作動させることで、前記掘進機は地盤に対してその前記カッター部で鉛直方向に掘削し且つ掘削した地盤の土砂を前記隔壁の前記排土口から取り込んで前記排土管を介して地上の前記真空ポンプを介して排土を前記排土貯留槽へ一時貯え、又前記掘進機が連結された鋼管を複数本分だけ下方に掘進すると発進台の地盤中に覆工体として挿入された最上段の鋼管の上端口縁上に必要な段数の複数本分の鋼管を前記発進台に地盤に圧入された鋼管と同一鉛直線上になるように補充配置して前記鋼管をフランジで互に連結し、その後前記油圧ジャッキ装置で補充した鋼管の最上段の管端を前記押輪で同一鉛直線下方に前記油圧ジャッキ装置で押付けながら同時に前記掘進機を掘削するように作動させることを繰り返して、掘進機を地盤強度の高い所定深さまで掘削すると油圧ジャッキ装置と掘進機の作動を停止し、前記排土貯留槽の排土と固化材ホッパー内の固化材とを改良体製造装置で所定割合で混練して改良体を作製した後、その混練した改良体を前記改良体圧送装置で地上に露出した排土管の内部へ圧送させて改良体を下端の前記排土口から噴出しながら前記掘進機を作動させてそのカッター部で撹拌する状態で、発進台にある最上段の鋼管を前記油圧ジャッキ装置によって上方に持ち上げるようにすることで、掘進機の排土口から改良体を切羽に向けて噴出して削孔内に充填撹拌させながらフランジ連結された掘進機と鋼管を上昇させ、地上の発進台に複数の鋼管と掘進機とが移動すると前記発進台でフランジ連結を解いて、前記鋼管と掘進機とを発進台から撤去し、掘進機と上方の鋼管を地上に回収して再使用可能とするとともに、削孔内に充填撹拌された改良体は固化されて掘進機の口径で支持層まで到達した掘削深さの長さの強度の高い支持杭と周辺地山と密状態の摩擦杭の双方の利点を有した基礎杭となり、しかも地盤に根固めされた基礎杭を構築できる、前記3)記載の基礎杭の現場構築工法
5) 前記改良体に使用する排土が、前記掘進機が掘削してその排土管で地上に送られた排土を使用することで、排土を処理場まで運送することを不要にした、前記1)
~4)いずれか記載の基礎杭の現場構築工法
にある。
The configuration of the present invention that solves such problems is as follows:
1) A method for constructing foundation piles at a site where foundation piles for a building are to be driven, in which a closed tunneling machine is driven vertically into the ground at the site to excavate a hole of a specified diameter and depth, and then the excavated soil and solidification material are mixed and filled into the hole to construct a solidified foundation pile at the drilled hole position,
The tunneling machine has a partition wall at the bottom end of a vertical cylindrical outer shell, and has an excavation cutter section below the partition wall, and further has an earth discharge port for taking in excavated earth and sand, and inside the outer shell above the partition wall has a rotating device for rotating the cutter section and an earth discharge pipe equipped with an opening and closing valve in the middle for sending the earth discharged from the earth discharge port upward, and the diameter of the outer shell of the tunneling machine is the same as the diameter of the foundation pile to be constructed, and a plurality of steel pipes are prepared which have the same diameter as the rear end edge of the tunneling machine and the edges of the steel pipes connected as the lining body and can be freely connected to each other detachably with flanges, and the earth discharge pipes are arranged so as to be passed through the inside of the steel pipes and sent to the ground, and further the tunneling machine can be supported vertically on the ground at the site where concrete is poured, and the required number of steel pipes can be connected above the tunneling machine, a launching platform capable of removing the topmost steel pipe by releasing the flanges from the multiple tiers of steel pipes connected to the tunneling machine with flanges; a hydraulic jack device mounted on the launching platform and capable of vertically pushing the topmost steel pipe connected to the tunneling machine with flanges to generate a vertical thrust on the tunneling machine and the steel pipes, and pushing the topmost steel pipe connected to the tunneling machine with flanges upward to lift the tunneling machine and the steel pipes connected thereto to the launching platform on the ground; an improved body manufacturing device that mixes a prescribed ratio of solidification material with the waste soil transported from the tunneling machine to the ground via the soil discharge pipe and stored in a stock tank or with the waste soil generated at another site and transported; and an improved body pumping device that pumps the improved body thus produced into the inside of the soil discharge pipe exposed on the ground.
an excavation process in which, during excavation, the tunneling machine is held facing downward on the launching platform, a predetermined number of steel pipes are flange-connected above the tunneling machine, and the tunneling machine is operated while applying a vertical pressing force to the topmost steel pipe with the hydraulic jack device, and while the tunneling machine is excavating vertically, the required number of steel pipes are added upward on the launching platform, thereby lining the ground to the required depth required for the foundation piles;
A
On the ground of the site, a vacuum pump that sucks the discharged soil to the ground side through the soil discharge pipe, a soil discharge storage tank that temporarily stores the discharged soil sent to the ground by the vacuum pump, a solidification material hopper that stores the solidification material, an improved body manufacturing device that produces the improved body by kneading the discharged soil in the soil discharge storage tank and the solidification material in the solidification material hopper at a predetermined ratio, an improved body pressure feeding device and its piping that feeds the improved body produced by the improved body manufacturing device into the soil discharge pipe of the tunneling machine, a launching platform that can vertically arrange the tunneling machine and multiple steel pipes relative to the ground above the foundation piles to be produced at the site, and that can vertically hold a propellant having opposing flanges detachably connected by bolts and can also move the propellant downward toward the ground or upward toward the ground, and a hydraulic jack device attached to the launching platform that can push down the top steel pipe of the propellant supported by the launching platform or lift it upward toward the ground side,
First, a tunneling machine with an outer diameter approximately the same as the pile opening of the foundation pile to be driven in the same vertical direction is placed on the launch platform, and multiple steel pipes with an outer diameter approximately the same as the outer diameter are placed above it. The vertical tunneling machine and the steel pipe above it are connected to each other with flanges, and then the hydraulic jack device attached to the launch platform is operated to apply a downward force to the uppermost push wheel by the hydraulic jack device to the tunneling machine and the multiple connected steel pipes. The tunneling machine then excavates the ground in the vertical direction with its cutter section, and the excavated soil and sand are discharged from the ground to the soil discharge port of the bulkhead. The soil is taken in from the tunnel and temporarily stored in the soil storage tank via the soil discharge pipe and the vacuum pump on the ground. When the tunneling machine excavates the steel pipes connected to it downwards by the length of several pipes, the necessary number of steel pipes are added to the upper end rim of the topmost steel pipe inserted into the ground of the launch pad as a lining so that they are on the same vertical line as the steel pipes pressed into the ground on the launch pad, and the steel pipes are connected to each other with flanges. After that, the topmost pipe end of the steel pipes added by the hydraulic jack device is pressed downward on the same vertical line with the pressure ring by the hydraulic jack device, while the tunneling machine is operated to excavate at the same time. This is repeated, and when the tunneling machine excavates to a predetermined depth where the ground strength is high, the operation of the hydraulic jack device and the tunneling machine is stopped, and the waste soil from the soil storage tank and the solidification material in the solidification material hopper are mixed in a predetermined ratio in the improved body manufacturing device to produce an improved body, and then the improved body that has been mixed is pumped into the soil discharge pipe exposed above ground by the improved body pumping device, and the improved body is ejected from the soil discharge port at the bottom while the tunneling machine is operated and stirred with its cutter section, and the topmost steel pipe on the starting platform is lifted upward by the hydraulic jack device, and the improved body is directed from the soil discharge port of the tunneling machine toward the face. and when the multiple steel pipes and the tunneling machine are moved to a launching platform on the ground, the flange connection at the launching platform is released , the steel pipes and the tunneling machine are removed from the launching platform, and the tunneling machine and the upper steel pipes are returned to the ground and can be reused. The improved body filled and mixed in the drilled hole is solidified to become a foundation pile having the advantages of both a high-strength support pile with a long excavation depth that reaches the supporting layer with the diameter of the tunneling machine, and a friction pile in a dense state with the surrounding ground, and further, a foundation pile with its base secured to the ground can be constructed. 5) A method for constructing foundation piles on site as described in 3) above. The soil used for the improved body is the soil excavated by the tunneling machine and sent to the ground by its soil discharge pipe, eliminating the need to transport the soil to a treatment plant. 1)
4) The on-site construction method of foundation piles is described in any one of the following.
本発明によれば、現場の地面に基礎杭の杭孔をトンネル推進工法で用いられている掘進機と、その上方に後続させる複数段の鋼管を地上の発進台でフランジ連結させて、発進台から鉛直に設置して油圧シリンダーで押し下げながら掘進機を作動させて、掘進機の下端のカッター部で地盤に削孔を掘削する。従って、本発明の工法では狭所施工が可能となり、地上で感知される振動・騒音が大巾に低減される。切羽の土砂の排土は掘進機の下端の隔壁の排土口から掘進機内部の排土バルブを通して排土管内に取り込まれ、鋼管内を介して地上側の排土コンテナタンク内へ搬送される。 According to the present invention, a tunnel boring machine used in tunnel jacking method is used to drill holes for foundation piles in the ground at the site, and multiple stages of steel pipes that follow it above are flange-connected to a launch pad on the ground. The boring machine is set vertically from the launch pad and pushed down by a hydraulic cylinder while operating, and a hole is excavated in the ground with the cutter at the bottom of the boring machine. Therefore, the method of the present invention makes it possible to carry out work in narrow spaces, and vibrations and noises detected on the ground are greatly reduced. The soil discharged from the face is taken into the soil discharge pipe through the soil discharge valve inside the boring machine from the soil discharge port in the bulkhead at the bottom of the boring machine, and is transported through the steel pipe to a soil discharge container tank on the ground side.
又、掘進機が支持強度の高い地層に到達したか否かは、カッター部にかかる回転負荷によって又は掘削深度計等の計測装置又は掘進機の長さと打ち込んだ鋼管の数でもって正確に確認でき、掘進機による支持地層に到達させることは掘進機に所要数の鋼管をフランジで追加できることで必要深さに確実にできる。本発明では、掘進機・鋼管の下方推進・上昇持ち上げ作業は油圧ジャッキを使用するので、騒音・振動の発生はない。又、高い機械装置を用いないので、狭地での作業が容易である。 In addition, whether the tunneling machine has reached a layer of soil with high supporting strength can be accurately confirmed by the rotational load on the cutter section, or by measuring devices such as an excavation depth gauge, or by the length of the tunneling machine and the number of steel pipes driven in, and the tunneling machine can be made to reach the supporting layer to the required depth by adding the required number of steel pipes to the tunneling machine with flanges. In this invention, hydraulic jacks are used for the downward pushing and lifting of the tunneling machine and steel pipes, so no noise or vibration is generated. In addition, since no expensive machinery is used, it is easy to work in narrow areas.
そして、掘進機を所定の深さの支持層に到達すると掘進機と鋼管を停止させた後、地上側に送り出された土砂の排土と地上側に設置した固化材ホッパーの固化材とを所定割合で混練装置で混練させる。混練されて製造された改良体はその圧送ポンプで地上に露出した排土管の内部へ圧送される。掘削で発生する排土を使用すれば地上で固化材と混練して再び削孔に戻されるので、排土量のほとんどが再利用され削減される。 When the tunneling machine reaches the supporting layer at a specified depth, the tunneling machine and steel pipe are stopped, and the discharged soil that has been sent to the ground side is mixed in a specified ratio with the solidification material from the solidification material hopper installed on the ground side in a mixer. The improved soil produced by mixing is pressure-fed by the pressure pump into the inside of the soil discharge pipe exposed above ground. If the discharged soil generated during excavation is used, it is mixed with the solidification material on the ground and returned to the drilling hole, so most of the discharged soil volume is reused and reduced.
圧送された改良体は排土管内を通過して、掘進機の下端の隔壁の排土口から切羽へ吐出され、切羽空間を改良体で加圧充填できる。 The pressurized improvement body passes through the drainage pipe and is discharged to the face from the drainage port in the bulkhead at the bottom of the tunneling machine, allowing the face space to be pressurized and filled with the improvement body.
しかも、この状態で掘進機を作動させて下端のカッター部の回転刃を回動させると、このカッター部が切羽の充填された改良体を再混合撹拌でき、挿入時の注入圧とによって杭孔の孔壁の凹凸・亀裂等によく充填できる。このカッター部の回転刃の回動をさせながら地上の油圧ジャッキ装置でもってフランジで連結された鋼管及びその下方の掘進機全体をゆっくりと地上方向に持ち上げて上昇させる。これで固化した基礎杭のコンクリート強度は高く、良質であり高品質が確保され、しかも杭径・深さも正確に施工できる。 Furthermore, when the tunneling machine is operated in this state and the rotating blade of the cutter section at the bottom is rotated, this cutter section can remix and stir the improvement material filled into the face, and the injection pressure during insertion allows it to thoroughly fill any irregularities or cracks in the pile hole wall. While the rotating blade of the cutter section is rotating, the steel pipes connected by flanges and the entire tunneling machine below it are slowly raised above ground by a hydraulic jack device on the ground. This ensures that the concrete strength of the hardened foundation pile is high and of good quality, and the pile diameter and depth can also be accurately constructed.
この掘進機の上昇で、排土口からの改良体は徐々に上方位置から噴出されながらカッター部で撹拌され、杭孔内に均等に充填され、その撹拌力と改良体の注入圧によって孔壁へよく浸透させていく。この掘進機とその上方の鋼管全体を地上の発進台の油圧ジャッキ装置で持ち上げる。本工法では掘進機とその上方の鋼管の地中への推進及び発進台への持ち上げ作業には、掘進機の掘削力と油圧ジャッキ装置による推進力,持ち上げ力が使用されることで打撃音・振動音の発生がなく、これらによる公害がほとんどない。 As the tunneling machine rises, the improvement material from the soil discharge port is gradually ejected from above while being stirred by the cutter section, filling the pile hole evenly, and the stirring force and injection pressure of the improvement material allow it to penetrate well into the hole wall. The tunneling machine and the steel pipe above it are then lifted by a hydraulic jack device on a launch pad on the ground. With this method, the tunneling machine and the steel pipe above it are advanced into the ground and lifted to the launch pad using the digging force of the tunneling machine and the propulsion and lifting forces of the hydraulic jack device, so no impact or vibration noises are generated and there is almost no pollution caused by these.
この工程によって、改良体は掘り出した地盤の土砂の排土とよく混合され且つ杭孔内に隈なく加圧撹拌充填された状態で固化していく。掘進機と鋼管とを地上の発進台まで持ち上げると、地上側では掘進機と上方の鋼管とのフランジ連結を解いて分離して、又は分離しないまま次の基礎杭の打設位置の発進台まで移動させる。 Through this process, the improved material is thoroughly mixed with the excavated soil and sand, and is pressurized, mixed, and filled thoroughly inside the pile hole, allowing it to solidify. Once the tunneling machine and steel pipe are lifted up to a launch pad on the ground, the flange connection between the tunneling machine and the upper steel pipe is released and separated, or they are moved without being separated to the launch pad for the driving position of the next foundation pile.
改良体が削孔に充填されて固化した杭は、削孔の空間の中央の固化体と杭孔の外周の改良体が充填圧とカッター部による撹拌によってその削孔壁の亀裂・凹凸に密着して、枝状に拡がった固化した外周固化体が一体化した基礎杭となり、掘進機の外殻の直径の杭口径で、しかも周囲の地盤と強力に一体化された基礎杭が作製される。 When the improvement material is filled into the drilled hole and solidified, the solidified material in the center of the drilled space and the improvement material on the periphery of the pile hole adhere to the cracks and unevenness in the drilled hole wall due to the filling pressure and stirring by the cutter, and the solidified outer periphery solidified material spreads out like branches to become an integrated foundation pile. A foundation pile with a pile diameter of the outer shell of the tunneling machine and which is strongly integrated with the surrounding ground is created.
本発明の基礎杭の現場構築工法によれば、下記の利点(1)~(13)が発生する。
(1)使用する建設機械をすべて小型化して大型機械と同様の強度の高い構造体や高い品質が得られる施工技術である。
(2)狭路な一般道でも、機材の搬入・搬出が可能で、小型化が実現できる。
(3)騒音・振動が非常に少ない施工法である。
(4)鋼材やコンクリート二次製品の杭は不使用である。
(5)掘進機本体の重量は(外径φ1000mmで掘進機先導体は2.5t程度、φ800mmで2t程度のために、一度掘進機を縦吊りして設置する場合は移動式クレーン(10T吊)が必要となるが、その後は鋼管の吊り込みのために4Tトラック(吊トラ)程度の車両で施工が可能となるため、施工機械の省力化が可能である。
(6)上部の建築構造物の重量等への支持力確保や地盤の変化に対しても削孔径を自由に変更する(掘進機を交換する)ことが可能なため、現場の地盤変状にも臨機な対応ができる。この点は、従来型の基礎杭で問題になっている課題や懸念事項でもあり、地盤の変状や支持層までの杭長や杭断面積の対応性が高い施工法である。
(7)掘進機引き上げ時は、改良体が切羽に充填されるため、孔壁と周辺地盤の密着度が高く、周辺摩擦力が向上する杭構築技術(支持杭と摩擦杭の双方の利点を活用)である。
(8)掘削した土砂を、地表のストックタンク内に一時滞留させ、後に小型撹拌機でセメント系材料(固化材)と混合・撹拌を行って塑性流動性の高い改良体に変換し、その改良体を杭材料として地盤内に再充填させることで改良杭を構築する施工法の為、最終的な残土処理量が大幅に削減可能となる環境負荷の低減が大きい構築技術である。
(9)掘進機が地盤を削孔しながら先行掘削を行う際、追従する管体は再利用可能なフランジ締結型の鋼管を使用し、最下部の掘進機切羽に改良体を充填しながら、同時に鋼管及び掘進機を地上に加圧充填分だけ引き上げ杭を形成させることができ、掘進機や全鋼管は地上に回収でき、次の工事にも転用可能なコスト縮減工法となる。
(10)掘進時の排土システムは、縦型にした掘進機の後続胴管内に、横型で管路を構築する場合の掘進機排土バルブ(エアー+ゴムバルブ)を使用し、通常の吸引排土装置(真空力発生装置)にて排土を地表まで引き上げる。その場合、鋼管内は無人化のため供給する空気量の調整が必要となるため、給気鋼管と排土管を鋼管内に並列に設置する。
また、供給される空気量の調整のために地表に開閉可能なバルブを設ける。
(11)掘削時に発生した排土(地山土砂と切羽泥水の混合流動体)にセメント系固化材を添加する。その場合、混合撹拌装置を用いて流動性がある改良体を形成させ、圧送ポンプで掘進機排土バルブ内に逆注入し、切羽の固結を図る。その時、掘進機のカッター部は回転させ、一層の混練を図り、均一性の高い杭を構築できる。
(12)本発明の工法は、掘進機による削孔、追従する鋼管等で掘削断面、再注入断面の形状寸法が明確で、充填する改良土の品質もその都度のテストピースで品質管理が可能となる。
(13)縦方式の掘進機使用のため、切羽加圧状態で掘進を行うことで、周辺地盤への影響(地盤の緩み等)が非常に少なく、隣接する家屋等への被害や影響は最小限止めることができる。
The on-site foundation pile construction method of the present invention provides the following advantages (1) to (13).
(1) It is a construction technique that allows all construction machinery to be miniaturized, thereby achieving the same high strength structures and high quality as those made by larger machinery.
(2) Equipment can be brought in and taken out even on narrow public roads, and compactness can be achieved.
(3) This construction method produces very little noise and vibration.
(4) Piles made of steel or concrete prefabricated products are not used.
(5) The weight of the tunneling machine itself (outer diameter φ1000mm for the tunneling machine tip is about 2.5t, and for φ800mm it is about 2t) means that a mobile crane (10T hoisting) is required to hoist the tunneling machine vertically once and set it up, but after that a vehicle of about a 4T truck (hoisting truck) can be used to hoist the steel pipe, which makes it possible to reduce the amount of labor required for construction machinery.
(6) It is possible to respond flexibly to changes in the ground at the site, since it is possible to freely change the drilling diameter (by replacing the tunneling machine) to ensure the bearing capacity for the weight of the building structure above and to changes in the ground. This is also an issue or concern that has been a problem with conventional foundation piles, and this construction method is highly adaptable to changes in the ground, the pile length to the supporting layer, and the pile cross-sectional area.
(7) When the tunneling machine is pulled up, the improvement body is filled into the tunnel face, which strengthens the adhesion between the hole wall and the surrounding ground and increases the surrounding friction force (utilizing the advantages of both support piles and friction piles).
(8) The excavated soil and sand are temporarily stored in a storage tank on the ground surface, and then later mixed and stirred with a cement-based material (solidification material) using a small mixer to convert it into an improved mass with high plastic fluidity. This improved mass is then refilled into the ground as pile material to construct improved piles. This construction method significantly reduces the amount of soil and sand that is ultimately disposed of, making it a construction technology that greatly reduces the environmental burden.
(9) When the tunneling machine performs preliminary excavation by boring a hole in the ground, a reusable flange-fastened steel pipe is used for the following pipe, and while filling the improvement body into the lowest tunneling machine face, the steel pipe and the tunneling machine are simultaneously pulled up to the ground by the amount of pressure filling to form a pile. The tunneling machine and all of the steel pipes can be recovered to the ground, making it a cost-reducing construction method that can be reused for the next construction project.
(10) The soil discharge system during excavation uses the tunneling machine soil discharge valve (air + rubber valve) used when constructing a horizontal pipeline inside the vertical tunneling machine's subsequent body pipe, and pulls the discharged soil up to the ground surface with a normal suction soil discharge device (vacuum force generator). In this case, since the steel pipe is unmanned, it is necessary to adjust the amount of air supplied, so the air supply steel pipe and soil discharge pipe are installed in parallel inside the steel pipe.
In addition, an openable and closable valve is installed on the ground surface to adjust the amount of air supplied.
(11) Add a cement-based solidification material to the soil discharged during excavation (a mixture of natural soil and muddy water at the face). In this case, a mixing and stirring device is used to form a fluid improved mass, which is then back-injected into the drainage valve of the tunneling machine using a pressure pump to solidify the face. At this time, the cutter part of the tunneling machine is rotated to further mix the material, allowing the construction of highly uniform piles.
(12) The construction method of the present invention clearly defines the shape and dimensions of the excavation cross section and the reinjection cross section using a tunneling machine and following steel pipes, etc., and the quality of the improved soil to be filled can be controlled using test pieces each time.
(13) Because a vertical tunneling machine is used, tunneling is carried out with the face pressurized, which means that the impact on the surrounding ground (loosening of the ground, etc.) is very small, and damage and impact to adjacent houses, etc. can be kept to a minimum.
本発明の掘進機は、トンネル工事の推進工法で使用される掘進機がそのまま使用可能である。 The tunneling machine of the present invention can be the same as the tunneling machine used in the tunnel jacking method.
本発明を図1~19に示す実施例をもって説明する。 The present invention will be explained using the examples shown in Figures 1 to 19.
(実施例の符号の説明)
図中、Gは実施例の基礎杭の現場構築工法を示す。予定の基礎杭の地面に設置される1は発進台、10は同発進台を地面に設置する接地フレーム、11は同接地フレームに固着した縦フレーム、12は複数の同縦フレームを連結する横フレーム、13は接地フレームに係留して接地フレームを地盤に固定するため地中に打設されたアンカー部材、14は接地フレームの中央部に設けた掘進機3,鋼管4の鉛直方向への地中進入のための筒状ガイド、15は同ガイドの沈下防止用ジャッキ、16は上方の横フレーム12に取付けた掘進機3,鋼管4の上下動の案内をする垂直なガイドレール、17は鋼管に推進力と持ち上げ力を伝達する円盤状押輪、171は同押輪の上下動を制動するガイドレール16と係合するガイド突起、2は発進台1に取付けられた油圧ジャッキ装置、20は同油圧ジャッキ装置を構成する複数本設けた引き専用の油圧ジャッキ、21は同油圧ジャッキのシリンダーロッド、22は油圧ジャッキのシリンダー筒体、220はシリンダーロッド21の先端を押輪17と連結するリンク部であり、シリンダー筒体22は接地フレームに連結させている。23は押輪17と最上段の鋼管とを連結する押輪側に係止された吊りボルト、24は同吊りボルトの下端に螺合する鋼管の内フランジに設けた固定ナット、3は掘進機、30は掘進機の外殻、31は同外殻の上端の口縁に設けられた内フランジ、32は同フランジに設けられた複数のボルト孔、33は掘進機3の下端の隔壁、34は同隔壁の中央外側に設けられた公転自転する回転刃を用いたカッター部、341は同カッター部の回転軸、342は隔壁33の上方の外殻30内に設けられたカッター部34の回動装置、35は隔壁中央に設けられた排土口、36は同排土口と連通した排土管、37は同排土管36の途中に設けたゴムバルブとエアを使った開閉用排土バルブ、38は地上から自然吸気を取り込む給気鋼管、39は外殻30の後縁に設けた内フランジ、391は外殻30の内フランジ31に設けたボルト孔、392は同ボルト孔と鋼管4の下端の内フランジ41のボルト孔42とを連結する連結ボルト、4は口径が外殻30の口径と同じ鋼管、41は同鋼管4の上下端の口縁に設けた内フランジ、42は同フランジに設けられたボルト孔、43は鋼管4の上下口縁の内フランジ41のボルト孔42を連結する連結ボルト、50は現場地上に配置された排土管と接続して排土管36に送られてくる排土を負圧によって吸引する真空ポンプ、51は排土管を介して地上に送られて排土を地上で貯える排土貯留槽、52は固化材を貯える固化材ホッパー、53は排土貯留槽の排土と固化材ホッパーに貯えた固化材を所定割合でスクリュー混練機で混練して作製する改良体製造装置、54は同改良体製造装置で作製された改良体を改良体注入配管540を介して掘進機の地上に配置された排土管36内に圧送する改良体圧送ポンプ、55は発進台1をクレーンアームの先端で掴んで発進台1を移動するクローラクレーン、56はエアタンク、57はエアコンプレッサー、59は油圧を送り出す油圧ユニット、60はその他の添加材を貯える添加材プラント、61は同添加材プラントの添加材を送り出す添加材ポンプである。
(Explanation of symbols in the embodiment)
In the figure, G indicates the on-site construction method for foundation piles of the embodiment. 1 is a launching platform installed on the ground of the planned foundation pile, 10 is a ground frame that installs the launching platform on the ground, 11 is a vertical frame fixed to the ground frame, 12 is a horizontal frame that connects multiple vertical frames, 13 is an anchor member driven into the ground to anchor the ground frame to the ground, 14 is a cylindrical guide installed in the center of the ground frame for the
(施工工程/作業手順)
以下、図18,19の施工図に従って作業を説明する。
1:地表面の杭位置に小型ピットを掘削し、坑口金物(エントランス)であるガイド14と発進台1の接地フレーム10を設置する(図5,18参照)。
2:エントランスの接地フレーム10の上部に縦型の発進台1を設置する(図3~5,18参照)。
3:発進台1内部に掘進機3と上方の鋼管4とを固定する(図5,6,7,8,9,18参照)。
4:坑外に掘削添加材プラント60(泥水プラント)、排土貯留槽51等を設置する。
5:遠隔操作盤により、縦型の発進台1内の油圧ジャッキ装置2を使用して、掘進機3のカッター部34の回転刃を回転させながら下方に掘削作業を行う(図5~9,18参照)。
6:同時に油圧ジャッキ(引きジャッキ)20で掘進機3を地中に押込む(掘進速度は2cm/分~10cm/分程度)(図5~9,18参照)。
7:掘進機3が地面に挿入後、掘進機3の上方に鋼管(仮に80cm~100cm程度)を接続する(図6~9の繰り返し,図18参照)。
8:管接続工が終了次第、再掘進を行う(図6~9,18参照)。
9:No.1鋼管長分の掘削が終了次第、段取り替えを行って、No.2鋼管を接続する(図6~9,18,19参照)。
10:鋼管を継ぎ足しての順次繰返し作業(図6~9,18,19参照)
11:強固な支持地盤SRまで掘削が完了した後に、地表に設置された排土貯留槽51内に貯留された排土に、撹拌・混合をする改良体製造装置53を用いてセメント系等の固化材ホッパー52内の固化材を混練し流動化した改良体を作る(図1,2,19参照)。
12:作製された改良体を改良体圧送ポンプ54によって掘進機3の排土管36を輸送管として再利用し、地表から掘進機切羽内まで改良体を圧送して削孔内に改良体を充填させる(図19参照)。
13:掘進機3の油圧ジャッキ装置2の引上げ速度に応じて、改良体圧送ポンプ54によって改良体を引き戻した孔壁内に連続的に加圧充填する(図19参照)。
14:鋼管1本毎の充填が出来次第、油圧ジャッキ装置2によって引き上げて、地表の発進台1に突出した鋼管4を1本ずつ撤去し、掘削最下端から連続した場所打杭を形成させる(図19参照)。
15:以上の11:~13:の作業を繰り返し行って、掘進機3の後部を地表の発進台1まで引き上げる(図19参照)。
16:掘進機3を撤去した後に、縦型の発進台1を解体撤去する。
17:最後に、地表に設置した坑口金物等を撤去すると無筋での場所打杭の基礎が1本完了する。
(Construction process/work procedure)
The work will be explained below with reference to the construction drawings in Figures 18 and 19.
1: A small pit is excavated at the pile position on the ground surface, and a
2: Install a
3: Fix the
4: An excavation additive plant 60 (mud plant), waste
5: Using the remote control panel, the
6: At the same time, the hydraulic jack (pull jack) 20 is used to push the
7: After the
8: Once the pipe connection work is completed, re-excavation will be carried out (see Figures 6-9 and 18).
9: Once the excavation of the No. 1 steel pipe length is completed, change the setup and connect the No. 2 steel pipe (see Figures 6 to 9, 18, and 19).
10: Repeat the process of adding steel pipes (see Figures 6 to 9, 18, and 19)
11: After excavation has been completed down to the solid supporting ground SR, the waste soil stored in the waste
12: The improved body is pumped from the ground surface to the tunneling face by the improvement body
13: Depending on the lifting speed of the
14: As soon as each steel pipe has been filled, it is pulled up using the
15: Repeat steps 11 to 13 above to pull the rear of the
16: After removing the
17: Finally, the tunnel head hardware installed on the surface is removed and one unreinforced cast-in-place pile foundation is completed.
このように、基礎杭を構築する現場には背の低い発進台・油圧ジャッキ装置が設置できれば工事可能であるので、狭い現場でも容易・迅速に施工できる。安全で騒音・振動が少ないので、公害の少ない工事となる。 As such, construction is possible at the site where the foundation piles are to be constructed as long as a low launch platform and hydraulic jack equipment can be installed, making construction easy and quick even in small sites. It is safe and produces little noise and vibration, resulting in less pollution.
本発明では基礎杭は複数の発進台・油圧ジャッキ装置を用いて、複数本並行に同時に現場構築でき、作業性もよく、又杭径の変更も容易となっている。 In this invention, multiple foundation piles can be constructed on-site in parallel using multiple launch platforms and hydraulic jack devices, making it easy to work with and to change the pile diameter.
G 実施例の基礎杭の現場構築工法
SR 支持地盤
1 発進台
10 接地フレーム
11 縦フレーム
12 横フレーム
13 アンカー部材
14 ガイド
15 沈下防止用ジャッキ
16 ガイドレール
17 押輪
171 ガイド突起
2 油圧ジャッキ装置
20 引き専用の油圧ジャッキ
21 シリンダーロッド
22 シリンダー筒体
220 リンク部
23 吊りボルト
24 固定ナット
3 掘進機
30 外殻
31 内フランジ
32 ボルト孔
33 隔壁
34 カッター部
341 回転軸
342 回動装置
35 排土口
36 排土管
37 排土バルブ
38 給気鋼管
39 内フランジ
391 ボルト孔
392 連結ボルト
4 鋼管
41 内フランジ
42 ボルト孔
43 連結ボルト
50 真空ポンプ
51 排土貯留槽
52 固化材ホッパー
53 改良体製造装置
54 改良体圧送ポンプ
540 改良体注入配管
55 クローラクレーン
56 エアタンク
57 エアコンプレッサー
59 油圧ユニット
60 添加材プラント
61 添加材ポンプ
G On-site construction method for foundation piles according to an embodiment
Claims (5)
前記掘進機は、鉛直な筒状の外殻の下端に隔壁を設け,同隔壁の下方に掘削用カッター部を有し,更に前記隔壁には掘削された土砂を取り込む排土口を設け且つ隔壁の上方の外殻内部には前記カッター部を回動させる回動装置と排土口からの排土を上方へ送る途中に開閉バルブを備えた排土管とを有し、しかも同掘進機の外殻の口径は構築する基礎杭の杭径と同径とし且つ前記掘進機の後端口縁及び覆工体として連結された鋼管の口縁同士とは同径でフランジで互に脱着自在に連結できる鋼管を複数本用意し、しかも前記排土管は前記鋼管内部に通して地上へ送られるように配置し、更に打設する現場地面には掘進機を鉛直方向に向けて支持でき且つ同掘進機の上方に所要段数の鋼管を連結可能とし及び掘進機の上方にフランジ連結された複数段の鋼管からフランジを解いて最上段の鋼管を撤去作業ができる発進台と、同発進台に装置され掘進機にフランジ連結された最上段の鋼管を鉛直方向に押圧して掘進機と前記鋼管に鉛直方向の推進力を発生させ、且つ掘進機にフランジ連結された最上段の鋼管を上方に押圧して掘進機とこれと連結した鋼管を地上の発進台まで持ち上げることができる油圧ジャッキ装置と、更に掘進機から排土管を介して地上に送られ、ストックタンク内に貯留された排土又は別現場で発生して運送されてきた排土に所定割合で固化材を混練して改良体を作製する改良体製造装置と、作製された前記改良体を地上に露出した排土管の管内部へ圧送する改良体圧送装置とを配置し、
掘進時は前記発進台に掘進機を下向きに保持し、同掘進機の上方に所定段の鋼管をフランジ連結して前記油圧ジャッキ装置で最上段の鋼管に対して鉛直方向に押圧力を与えながら掘進機を作動させることで、しかも掘進機で鉛直方向に掘削させながら発進台で上方に鋼管を所要段数継ぎ足すことで基礎杭に要求される地盤の所定深さまで覆工を行いながら掘削する掘削工程と、
前記掘削工程で掘進機の排土管から地上に送り出される排土又は別現場の排土を使用して地上にて固化材を所定割合混練して改良体製造装置で改良体を作製する改良体製造工程と、作製した改良体を改良体圧送装置で地上に露出した排土管の管内に圧送して改良体を排土管を通して地中の掘進機先端のカッター隔壁から削孔内に圧入しながら掘進機とフランジ連結した鋼管を前記油圧ジャッキで持ち上げながら掘進機のカッター部で撹拌することで改良体を削孔内に均一に充填する改良体充填撹拌工程と、掘進機とその上方の鋼管を油圧ジャッキによって発進台の地上位置まで持ち上げてフランジ連結した鋼管を分離して掘進機を地上に回収する回収工程と、掘進機を上方に回収中に撹拌された改良体が固化して所定外径で支持地盤まで届いた所定深さを有して削孔壁に付着し、支持地盤で支持されたコンクリート現場構築の基礎杭が完成する固化工程とからなる、基礎杭の現場構築工法。 A method for constructing foundation piles on site, in which a closed tunneling machine is driven vertically into the ground at the site to drive foundation piles for a building, to excavate a hole of a specified diameter and depth, and then the excavated soil and solidification material are mixed and filled into the hole to construct a solidified foundation pile at the drilled hole position,
The tunneling machine has a partition wall at the bottom end of a vertical cylindrical outer shell, and has an excavation cutter section below the partition wall, and further has an earth discharge port for taking in excavated earth and sand, and inside the outer shell above the partition wall has a rotating device for rotating the cutter section and an earth discharge pipe equipped with an opening and closing valve in the middle for sending the earth discharged from the earth discharge port upward, and the diameter of the outer shell of the tunneling machine is the same as the diameter of the foundation pile to be constructed, and a plurality of steel pipes are prepared which have the same diameter as the rear end edge of the tunneling machine and the edges of the steel pipes connected as the lining body and can be freely connected to each other detachably with flanges, and the earth discharge pipes are arranged so as to be passed through the inside of the steel pipes and sent to the ground, and further the tunneling machine can be supported vertically on the ground at the site where concrete is poured, and the required number of steel pipes can be connected above the tunneling machine, a launching platform capable of removing the topmost steel pipe by releasing the flanges from the multiple tiers of steel pipes connected to the tunneling machine with flanges; a hydraulic jack device mounted on the launching platform and capable of vertically pushing the topmost steel pipe connected to the tunneling machine with flanges to generate a vertical thrust on the tunneling machine and the steel pipes, and pushing the topmost steel pipe connected to the tunneling machine with flanges upward to lift the tunneling machine and the steel pipes connected thereto to the launching platform on the ground; an improved body manufacturing device that mixes a prescribed ratio of solidification material with the waste soil transported from the tunneling machine to the ground via the soil discharge pipe and stored in a stock tank or with the waste soil generated at another site and transported; and an improved body pumping device that pumps the improved body thus produced into the inside of the soil discharge pipe exposed on the ground.
an excavation process in which, during excavation, the tunneling machine is held facing downward on the launching platform, a predetermined number of steel pipes are flange-connected above the tunneling machine, and the tunneling machine is operated while applying a vertical pressing force to the topmost steel pipe with the hydraulic jack device, and while the tunneling machine is excavating vertically, the required number of steel pipes are added upward on the launching platform, thereby lining the ground to the required depth required for the foundation piles;
This on-site construction method for foundation piles comprises the steps of: an improved body manufacturing process in which the excavation process uses the waste soil discharged to the ground from the soil discharge pipe of the tunneling machine in the excavation process, and a predetermined ratio of solidification material is mixed on the ground with the improved body manufacturing device to produce an improved body; an improved body filling and mixing process in which the improved body prepared is pressure-fed into the tube of the soil discharge pipe exposed to the ground by an improved body pressure-feeding device, and the improved body is pressed through the soil discharge pipe into the drilled hole from the cutter partition at the tip of the tunneling machine underground while the steel pipe connected to the flange of the tunneling machine is lifted by the hydraulic jack while being stirred by the cutter part of the tunneling machine, thereby filling the drilled hole evenly with the improved body; a recovery process in which the tunneling machine and the steel pipe above it are lifted to the ground position of the launch pad by the hydraulic jack, the flange-connected steel pipe is separated, and the tunneling machine is recovered to the ground; and a solidification process in which the improved body stirred while the tunneling machine is recovered upward solidifies and adheres to the drilled hole wall with a predetermined outer diameter and a predetermined depth that reaches the supporting ground, completing a concrete on-site foundation pile supported by the supporting ground.
前記現場の地上には、前記排土管を通して排土を地上側へ吸引する真空ポンプと、同真空ポンプで地上に送られた排土を一時貯える排土貯留槽と、前記固化材を貯えた固化材ホッパーと、前記排土貯留槽内の排土と前記固化材ホッパー内の前記固化材とを所定割合で混練して前記改良体を作製する改良体製造装置と、同改良体製造装置で作製された前記改良体を前記掘進機の前記排土管内に送り込む改良体圧送装置とその配管と、現場に作製する予定の基礎杭の地上の地面に対して前記掘進機と複数本の前記鋼管とを鉛直に配置でき、しかも対向する各フランジをボルトで脱着可能に連結した推進体を鉛直に保持し且つ同推進体を地盤に向けて下方又は地上に向けて上方にも移動できるようにした発進台と、同発進台で支持された前記推進体の最上段の鋼管を下方に押下げ又は地上側に向けて上方に持ち上げることができる前記発進台に取付けられた油圧ジャッキ装置とを現場地面に配置し、
まず前記発進台に同一鉛直方向に打設予定の基礎杭の杭口と略同じ外殻口径の掘進機とその上方に外殻口径と略同じ外径を有する複数の鋼管を配置し、鉛直の掘進機とその上方の鋼管とを互にフランジで連結した後前記発進台に取付けた前記油圧ジャッキ装置を作動させて前記掘進機と複数の連結された前記鋼管に前記油圧ジャッキ装置によって最上位となる前記押輪に押下げ力を荷重しながら前記掘進機の前記回動装置を作動させることで、前記掘進機は地盤に対してその前記カッター部で鉛直方向に掘削し且つ掘削した地盤の土砂を前記隔壁の前記排土口から取り込んで前記排土管を介して地上の前記真空ポンプを介して排土を前記排土貯留槽へ一時貯え、又前記掘進機が連結された鋼管を複数本分だけ下方に掘進すると発進台の地盤中に覆工体として挿入された最上段の鋼管の上端口縁上に必要な段数の複数本分の鋼管を前記発進台に地盤に圧入された鋼管と同一鉛直線上になるように補充配置して前記鋼管をフランジで互に連結し、その後前記油圧ジャッキ装置で補充した鋼管の最上段の管端を前記押輪で同一鉛直線下方に前記油圧ジャッキ装置で押付けながら同時に前記掘進機を掘削するように作動させることを繰り返して、掘進機を地盤強度の高い所定深さまで掘削すると油圧ジャッキ装置と掘進機の作動を停止し、前記排土貯留槽の排土と固化材ホッパー内の固化材とを改良体製造装置で所定割合で混練して改良体を作製した後、その混練した改良体を前記改良体圧送装置で地上に露出した排土管の内部へ圧送させて改良体を下端の前記排土口から噴出しながら前記掘進機を作動させてそのカッター部で撹拌する状態で、発進台にある最上段の鋼管を前記油圧ジャッキ装置によって上方に持ち上げるようにすることで、掘進機の排土口から改良体を切羽に向けて噴出して削孔内に充填撹拌させながらフランジ連結された掘進機と鋼管を上昇させ、地上の発進台に複数の鋼管と掘進機とが移動すると前記発進台でフランジ連結を解いて、前記鋼管と掘進機とを発進台から撤去し、掘進機と上方の鋼管を地上に回収して再使用可能とするとともに、削孔内に充填撹拌された改良体は固化されて掘進機の口径で支持層まで到達した掘削深さの長さの強度の高い支持杭と周辺地山と密状態の摩擦杭の双方の利点を有した基礎杭となり、しかも地盤に根固めされた基礎杭を構築できる、請求項3記載の基礎杭の現場構築工法。 In the on-site construction method of foundation piles according to claim 3 ,
On the ground of the site, a vacuum pump that sucks the discharged soil to the ground side through the soil discharge pipe, a soil discharge storage tank that temporarily stores the discharged soil sent to the ground by the vacuum pump, a solidification material hopper that stores the solidification material, an improved body manufacturing device that produces the improved body by kneading the discharged soil in the soil discharge storage tank and the solidification material in the solidification material hopper at a predetermined ratio, an improved body pressure feeding device and its piping that feeds the improved body produced by the improved body manufacturing device into the soil discharge pipe of the tunneling machine, a launching platform that can vertically arrange the tunneling machine and multiple steel pipes relative to the ground above the foundation piles to be produced at the site, and that can vertically hold a propellant having opposing flanges detachably connected by bolts and can also move the propellant downward toward the ground or upward toward the ground, and a hydraulic jack device attached to the launching platform that can push down the top steel pipe of the propellant supported by the launching platform or lift it upward toward the ground side,
First, a tunneling machine with an outer diameter approximately the same as the pile mouth of the foundation pile to be driven in the same vertical direction is placed on the starting platform, and multiple steel pipes with an outer diameter approximately the same as the outer diameter are placed above it. The vertical tunneling machine and the steel pipe above it are connected to each other with flanges, and then the hydraulic jack device attached to the starting platform is operated to apply a downward force to the uppermost push wheel by the hydraulic jack device to the tunneling machine and the multiple connected steel pipes. By operating the rotating device of the tunneling machine, the tunneling machine excavates the ground in the vertical direction with its cutter part, and the excavated soil and sand are removed from the ground by the soil removal device of the bulkhead. The soil is taken in from the opening and temporarily stored in the soil storage tank via the soil discharge pipe and the vacuum pump on the ground, and when the tunneling machine excavates the steel pipe connected to it downward by the length of several pipes, the necessary number of steel pipes are added to the upper end lip of the topmost steel pipe inserted into the ground of the launching platform as a lining so that they are on the same vertical line as the steel pipe pressed into the ground on the launching platform, and the steel pipes are connected to each other with flanges, and then the topmost pipe end of the steel pipe added by the hydraulic jack device is pressed downward on the same vertical line with the pressure ring by the hydraulic jack device while simultaneously operating the tunneling machine to excavate. This is repeated, and when the tunneling machine is driven to a predetermined depth where the ground strength is high, the operation of the hydraulic jack device and the tunneling machine is stopped, and the soil discharged from the soil discharge storage tank and the solidification material in the solidification material hopper are mixed in a predetermined ratio in an improved body manufacturing device to produce an improved body, and then the improved body that has been mixed is pumped into the soil discharge pipe exposed above ground by the improved body pumping device, and the improved body is ejected from the soil discharge port at the lower end while the tunneling machine is operated and stirred with its cutter section, and the topmost steel pipe on the starting platform is lifted upward by the hydraulic jack device, and the improved body is directed from the soil discharge port of the tunneling machine to the face. a flange-connected tunneling machine and steel pipe are raised while the improved material is ejected and mixed into the drilled hole, filling and mixing the drilled hole; when the multiple steel pipes and the tunneling machine have moved to a launching platform on the ground, the flange connection at the launching platform is released, the steel pipes and the tunneling machine are removed from the launching platform, and the tunneling machine and the upper steel pipes are recovered to the ground and can be reused; and the improved material filled and mixed into the drilled hole solidifies to become a foundation pile having the advantages of both a high-strength support pile with a length of excavation depth that reaches the supporting layer with the diameter of the tunneling machine and a friction pile that is dense with the surrounding ground, and which also allows the construction of a foundation pile with its base secured to the ground.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2021075432A JP7616772B2 (en) | 2021-04-27 | 2021-04-27 | On-site construction method for foundation piles |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2021075432A JP7616772B2 (en) | 2021-04-27 | 2021-04-27 | On-site construction method for foundation piles |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2022169393A JP2022169393A (en) | 2022-11-09 |
| JP7616772B2 true JP7616772B2 (en) | 2025-01-17 |
Family
ID=83943883
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2021075432A Active JP7616772B2 (en) | 2021-04-27 | 2021-04-27 | On-site construction method for foundation piles |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7616772B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118911100B (en) * | 2024-09-02 | 2025-10-03 | 中交第二航务工程勘察设计院有限公司 | A small offshore platform for offshore piling operations |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3069203U (en) | 1999-11-24 | 2000-06-06 | 株式会社進成建設 | Pipe propulsion device |
| JP2003342946A (en) | 2002-05-27 | 2003-12-03 | Epokoramu Kiko Kk | Soil improvement apparatus and soil improvement construction method |
| JP2005146541A (en) | 2003-11-11 | 2005-06-09 | Alpha Civil Engineering:Kk | Small-diameter pipe driving equipment, and method for constructing small-diameter pipeline by using it |
| JP2016196734A (en) | 2015-04-02 | 2016-11-24 | 株式会社エスエスティー協会 | Method for creating ground improvement foundation |
-
2021
- 2021-04-27 JP JP2021075432A patent/JP7616772B2/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3069203U (en) | 1999-11-24 | 2000-06-06 | 株式会社進成建設 | Pipe propulsion device |
| JP2003342946A (en) | 2002-05-27 | 2003-12-03 | Epokoramu Kiko Kk | Soil improvement apparatus and soil improvement construction method |
| JP2005146541A (en) | 2003-11-11 | 2005-06-09 | Alpha Civil Engineering:Kk | Small-diameter pipe driving equipment, and method for constructing small-diameter pipeline by using it |
| JP2016196734A (en) | 2015-04-02 | 2016-11-24 | 株式会社エスエスティー協会 | Method for creating ground improvement foundation |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2022169393A (en) | 2022-11-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102803616B (en) | Method and apparatus for manufacturing underwater foundations of buildings | |
| CN110984852B (en) | Triaxial stirring stake machine with function of rectifying | |
| CN115478543B (en) | Artificial hole digging pile foundation pit supporting structure and construction method | |
| CN102888839A (en) | Construction method of static-pressure sleeve rotary digging filling pile | |
| JP7616772B2 (en) | On-site construction method for foundation piles | |
| KR20080112453A (en) | Ground Improvement Method Using Ground Improvement Equipment | |
| JPH01260117A (en) | Pile driving work | |
| CN114875925B (en) | Construction method of oversized deep foundation pit of subway tunnel adjacent to sea-filling stratum | |
| CN113047843B (en) | Large-diameter pile or vertical shaft hole-forming soil excavation device | |
| CN112160754B (en) | Large-diameter pile or vertical shaft hole forming construction method | |
| WO2008072950A2 (en) | Foundation system for the forming of a foundation pile in the ground | |
| JP4074198B2 (en) | How to remove existing piles | |
| JP2684531B2 (en) | Vertical shaft or structure foundation pile construction method and construction apparatus | |
| CN118531786A (en) | A kind of artificial excavated pile wall protection construction method | |
| KR100829872B1 (en) | Manhole propulsion replacement method and device | |
| EP4103785B1 (en) | Method for introducing a soil penetrating tool into a soil and underground construction device | |
| CN116335174A (en) | Installation method of pressure sinking system of ultra-deep segmental large-diameter working well | |
| GB2132667A (en) | Method of installing precast concrete piles | |
| JP2011202429A (en) | Construction device of columnar ground improving pile, and construction method of columnar ground improving pile | |
| JPH06193061A (en) | Pile driving method and walling method, and hollow pile and pump used therefor | |
| JP5238092B2 (en) | Wall construction method and hollow pile used therefor | |
| JP3577360B2 (en) | Construction method of underground wall and trunk pipe used for it | |
| JPS598827A (en) | Large-diameter foundation work | |
| CN115450216A (en) | Pile foundation demolition underwater platform and construction method | |
| JPS62233329A (en) | Forming work of in-situ mortar pile and pile driver therefor |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20240312 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20240917 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20240919 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20241111 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20241203 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20241226 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7616772 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |