JP7643237B2 - Work supply device - Google Patents
[go: Go Back, main page]

JP7643237B2 - Work supply device - Google Patents

Work supply device Download PDF

Info

Publication number
JP7643237B2
JP7643237B2 JP2021125270A JP2021125270A JP7643237B2 JP 7643237 B2 JP7643237 B2 JP 7643237B2 JP 2021125270 A JP2021125270 A JP 2021125270A JP 2021125270 A JP2021125270 A JP 2021125270A JP 7643237 B2 JP7643237 B2 JP 7643237B2
Authority
JP
Japan
Prior art keywords
workpieces
receiving table
storage box
workpiece
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021125270A
Other languages
Japanese (ja)
Other versions
JP2023020087A (en
Inventor
克明 阿南
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Denso Corp
Original Assignee
Denso Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Denso Corp filed Critical Denso Corp
Priority to JP2021125270A priority Critical patent/JP7643237B2/en
Publication of JP2023020087A publication Critical patent/JP2023020087A/en
Application granted granted Critical
Publication of JP7643237B2 publication Critical patent/JP7643237B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sheets, Magazines, And Separation Thereof (AREA)

Description

本発明は、ワークの供給装置に関する。 The present invention relates to a work supply device.

電気自動車等に使用される電力変換装置(PCU)に使われるスイッチング素子としてパワーカードが知られている。このパワーカードの製造工程において、製造途中の多数枚のパワーカードを一ロットとして格納装置に搬入し、格納装置からパワーカードを一枚ずつ搬出するとき、要求のあるそれぞれの目的地に対応するように一枚ずつ各パワーカードを搬出する。 Power cards are known as switching elements used in power conversion units (PCUs) used in electric vehicles and the like. In the manufacturing process of these power cards, a large number of power cards in the middle of production are loaded into a storage device as one lot, and when the power cards are removed from the storage device one by one, each power card is removed so that it corresponds to each required destination.

このパワーカードをワークとして積層して保管する格納装置は、要求に応じて必要なとき必要な枚数のワークを遅延なしに供給することが求められる。 The storage device that stores these power cards in stacks as work is required to supply the required number of work pieces when required, without delay, on demand.

積層された複数のワークから1枚のワークを供給するとき、1枚のワークを残りの積層されたワークから分離する、例えば、特許文献1に記載されるシステムは、複数のワークが積層された状態で蓄積されるストッカーと、1枚の前記ワークの両端をハの字型に挟み込んで把持する少なくとも一対のパッドを含む保持ユニットと、保持ユニットおよびストッカーの少なくとも一方を動かすことにより、少なくとも一対のパッドで1枚のワークを挟み込んだ状態の保持ユニットに対し、ストッカーを相対的に下に移動して1枚のワークを他のワークに対し分離する移動ユニットとを有する。 When supplying one workpiece from a number of stacked workpieces, the system described in Patent Document 1, for example, has a stocker in which a number of workpieces are stored in a stacked state, a holding unit including at least a pair of pads that clamp and hold both ends of one of the workpieces in a V-shape, and a moving unit that moves at least one of the holding unit and the stocker to move the stocker downward relative to the holding unit in a state in which the one workpiece is clamped between the at least a pair of pads, thereby separating the one workpiece from the other works.

特開2017-160055号公報JP 2017-160055 A

格納装置にワークを搬入するとき、例えば30枚の積層パワーカード(ワーク)を下からセットし、この格納装置の上から順にワークを一枚ずつ取り出し(搬出)していく方法を採用するものでは、格納装置に上段のワークの残数が無くなった後、次にワークの搬出を開始するまでの期間、通常は、次の30枚の積層ワークを搬入しセットする際に待機時間が長時間になるという問題がある。 When loading workpieces into a storage device, for example, 30 stacked power cards (workpieces) are set from the bottom, and the workpieces are removed (unloaded) one by one from the top of the storage device. In this case, after the remaining number of works on the top level of the storage device runs out, there is usually a long waiting time until the next workpiece can be unloaded, when the next 30 stacked workpieces are loaded and set.

また、格納装置にワークの残数が無くなったとき、次の多数枚の積層ワークを搬入し終えるまで経過する待機時間の損失を軽減する装置は知られていない。 Furthermore, there is no known device that can reduce the loss of waiting time that elapses when there are no more workpieces remaining in the storage device until the next large number of stacked workpieces can be brought in.

本発明は、上述に鑑みてなされたものであり、その目的は、多数枚のワークを、遅れることなしに、小空間から高効率に供給可能なワークの供給装置を提供することにある。 The present invention has been made in consideration of the above, and its purpose is to provide a work supply device that can supply a large number of workpieces from a small space with high efficiency and without delay.

本発明のワークの供給装置は、多数枚のワーク(2)を保管可能であって、前記多数枚のワークのうちの最上位のワークを順に外部に供給するワークの供給装置であって、
外部から多数枚のワークを搬入し積層可能な格納庫(14)と、
前記格納庫の上段に位置し、前記格納庫で積層される多数枚のワークを所定のタイミン
グに受け入れ可能な収納箱(12)と、
前記収容箱に設けられ、多数枚のワークを支持する第1の受台(10、22)と、
前記第1の受台上のワークの残枚数が所定枚数に減小したとき当該所定枚数の残ワークを前記第1の受台から受け渡される第2の受台(31)と、
前記収容箱で第1の受台又は第2の受台に積層されるワークのうちの最上位のワークを順に搬出する積込機(11)と、
前記積込機により最上位のワークを搬出する度に前記第1の受台上の搬出後の残ワークを上位にピッチ送りするピッチ送りユニット(6)と、
前記収容箱で積層される多数枚のワークが順に外部に搬出される際、前記第1の受台上のワークの残枚数が所定枚数に減小したとき、前記第2の受台上のワークの前記積込機によるワークの一枚毎の搬出を継続する期間中に、前記格納庫の多数枚のワークを前記収容箱内の前記第1の受台に搬入するロッド(13、18)と、を備え、
前記ロッドは、積層された多数のワークを第1の受台に受け渡した後に下降し、格納庫で次に積層される多数のワークを積込み、第2の受台から残ワークの最上位のワークを順に搬出する期間中に上昇し、積込まれた多数のワークを収納箱で第1の受台に受け渡す、構成を採用する。
The work supply device of the present invention is capable of storing a large number of workpieces (2) and supplies the topmost workpiece of the large number of workpieces to the outside in sequence,
A storage facility (14) capable of carrying in and stacking a large number of workpieces from the outside;
a storage box (12) located at the upper level of the storage facility and capable of receiving a large number of workpieces stacked in the storage facility at a predetermined timing;
A first receiving table (10, 22) provided in the storage box and supporting a large number of workpieces;
a second receiving table (31) to which the predetermined number of remaining workpieces is transferred from the first receiving table when the remaining number of workpieces on the first receiving table is reduced to a predetermined number;
a loader (11) for sequentially carrying out the topmost workpiece among the workpieces stacked on the first receiving table or the second receiving table in the storage box;
a pitch feed unit (6) that pitch-feeds the remaining workpieces on the first receiving table upward every time the top workpiece is carried out by the loader;
and a rod (13, 18) for loading the multiple workpieces from the storehouse onto the first receiving table in the storage box during a period in which the loader continues to unload the workpieces one by one from the second receiving table when the remaining number of workpieces on the first receiving table is reduced to a predetermined number when the multiple workpieces stacked in the storage box are unloaded to the outside in sequence,
The rod is configured to transfer a large number of stacked workpieces to the first receiving table, then descend to load the next large number of workpieces to be stacked in the storage facility, and rise during the period in which the topmost remaining workpieces are removed in order from the second receiving table, and transfer the loaded large number of workpieces to the first receiving table in a storage box .

ピッチ送りユニットがピッチ送りするワークの残枚数が所定枚数に減少している期間内に、昇降装置が稼働することで、格納庫の次の多数枚のワークを収容箱に搬入する。
したがって、ピッチ送りユニットがピッチ送りするワークの残存枚数が所定枚数以下の複数ある期間内に収容箱内に次の積層された多数枚のワークの搬入を完了するから、待ち時間の損失なしに、各ワークの各目的地への搬出(供給)を継続することができる。
During the period in which the remaining number of workpieces to be pitch-fed by the pitch feed unit is reduced to a predetermined number, the lifting device is operated to carry the next large number of workpieces from the storehouse into the storage box.
Therefore, since the pitch feed unit completes the transport of the next stacked multiple workpieces into the storage box within a period in which the number of remaining workpieces to be pitch fed is less than a predetermined number, the transport (supply) of each workpiece to its respective destination can be continued without any waiting time loss.

ワーク残数が所定枚数に減少したとき、ワーク残数がゼロになる前の期間内に、ワーク残数を載置する支持手段が第1の受台から第2の受台に切り替えられるから、第2の受台の残存枚数がゼロになる前に、ワーク供給を継続しつつ収容箱に次の段階の多数枚のワークを搬入することができる。 When the number of remaining workpieces has decreased to a predetermined number, the support means for placing the remaining workpieces is switched from the first receiving table to the second receiving table within the period before the number of remaining workpieces reaches zero, so that the next stage of multiple workpieces can be transported into the storage box while continuing to supply workpieces before the number of remaining workpieces on the second receiving table reaches zero.

本発明の一実施形態に係るワーク供給装置の斜視図。FIG. 1 is a perspective view of a work supply device according to an embodiment of the present invention. 本発明の一実施形態に係るワーク供給装置の取出しユニットの正面図。FIG. 2 is a front view of a take-out unit of the work supply device according to the embodiment of the present invention. 本発明の一実施形態に係るワーク供給装置の取出しユニット及びパワーカードピッチ送りユニットの斜視図。FIG. 2 is a perspective view of a take-out unit and a power card pitch feed unit of the work supply device according to the embodiment of the present invention. 本発明の一実施形態に係るワーク供給装置のピッチ送りユニットの斜視図。FIG. 2 is a perspective view of a pitch feed unit of the work supplying device according to the embodiment of the present invention. 本発明の一実施形態に係るワーク供給装置のパワーカードの平面図。FIG. 4 is a plan view of a power card of the work supply device according to the embodiment of the present invention. 本発明の一実施形態に係るワーク供給装置のパワーカードの平面図。FIG. 4 is a plan view of a power card of the work supply device according to the embodiment of the present invention. 本発明の一実施形態に係るワーク供給装置のストックユニットの斜視図。FIG. 2 is a perspective view of a stock unit of the workpiece supplying device according to the embodiment of the present invention. 本発明の一実施形態に係るワーク供給装置の作動の説明図。5A to 5C are explanatory diagrams illustrating an operation of the work supply device according to the embodiment of the present invention.

以下、本発明の一実施形態によるワークの供給装置を図面に基づいて説明する。 Below, a work supply device according to one embodiment of the present invention is described with reference to the drawings.

(第1実施形態)
本発明の第一実施形態について図1から図8に基づいて説明する。
First Embodiment
A first embodiment of the present invention will be described with reference to FIGS. 1 to 8. FIG.

図1は、本発明のワークの供給装置を、電気自動車の電力変換装置(パワーコントールユニット(PCU))のスイッチング素子等に用いられるパワーカードの供給装置に適用した実施形態を示す。 Figure 1 shows an embodiment in which the work supply device of the present invention is applied to a power card supply device used for switching elements of a power conversion device (power control unit (PCU)) of an electric vehicle.

パワーカード供給装置1は、搬送ユニット4と、取出しユニット5と、ピッチ送りユニット6と、ストックユニット7を備える。 The power card supply device 1 includes a transport unit 4, a removal unit 5, a pitch feed unit 6, and a stock unit 7.

搬送ユニット4は、搬入口から取り込んだパワーカードを取出しユニット5の下段にある格納庫14に搬入する。以下、明細書において「パワーカード」を「ワーク」という。
格納庫(マガジン)14には、搬送ユニット4からワーク30枚が1ロットとして搬入される。
The transport unit 4 transports the power card taken in from the carry-in entrance into the storage 14 located below the take-out unit 5. Hereinafter, in the specification, the "power card" will be referred to as the "work".
Thirty workpieces are carried into the magazine 14 from the transport unit 4 as one lot.

図2に示すように、ワーク供給装置1の取出しユニット5は、下段に格納庫14を備え、その上段に収容箱12を備える。
格納庫14は、多数枚のワークを30枚毎に外部から搬入する。格納庫14に収納されたワーク2は昇降装置13により矢印26の方向へ全数持ち上げられる。昇降装置13は、図示しない直動式サーボモータと、多数枚のワークを位置決めするチャックシリンダと、多数枚のワークを収納箱12まで持ち上げるロッド18とを備える。持上げた先には収納箱12があり、持上げ検出センサ15により上昇端が検出される。
As shown in FIG. 2, the take-out unit 5 of the work supply device 1 includes a storage 14 on the lower stage and a storage box 12 on the upper stage.
A large number of workpieces 2 are carried into the storage facility 14 from outside in batches of 30. All of the workpieces 2 stored in the storage facility 14 are lifted in the direction of arrow 26 by the lifting device 13. The lifting device 13 includes a linear servo motor (not shown), a chuck cylinder that positions the large number of workpieces, and a rod 18 that lifts the large number of workpieces up to the storage box 12. The storage box 12 is located at the end of the lift, and the lift end is detected by the lifting detection sensor 15.

図示しない直動式サーボモータにより駆動するロッド18を上昇するとき、30枚のワークを格納庫14から収容箱12にリフトする。 When the rod 18, driven by a linear servo motor (not shown), rises, it lifts 30 workpieces from the storage shed 14 into the storage box 12.

収容箱12の内部では、積層した30枚のワークを第1の受台10に相当するピッチ送りワーク受け22が最下位のワーク2の下面から支持する。 Inside the storage box 12, the 30 stacked workpieces are supported from the underside of the lowest workpiece 2 by a pitch-feed workpiece receiver 22, which corresponds to the first receiving table 10.

積層したワーク2を載置するピッチ送りワーク受け22は、直動式サーボ の駆動力により上昇するロッド18の上端で連結され、ワンピッチごとに収納箱12内のワークを 1枚ずつ上昇する。 The pitch-feed workpiece receiver 22 on which the stacked workpieces 2 are placed is connected to the upper end of the rod 18, which rises due to the driving force of a linear servo, and raises the workpieces in the storage box 12 one by one with each pitch.

収容箱12は、積層した多数枚のワークを持ち上げる昇降装置に相当する持上げリフタ13、積層されるワークの最上位のワークの存在の有無を検出する持上げ検出センサ15、ワークを持ち上げるピッチ送り用サーボ16、積層されたワークの1枚ずつを規制するピッチ送りクランプツメ17、及び、最上位のワークの上面を吸引し吸着する吸着ヘッド11、を備える。 The storage box 12 is equipped with a lifter 13, which is equivalent to a lifting device that lifts up the multiple stacked workpieces, a lifting detection sensor 15 that detects whether the topmost workpiece of the stack is present, a pitch feed servo 16 that lifts the workpiece, pitch feed clamp claws 17 that regulate each of the stacked workpieces, and a suction head 11 that sucks and adheres to the top surface of the topmost workpiece.

収容箱12は、ワークを30枚収容する。収容箱12に収容されワークに後述するように空が生じると、昇降装置13の駆動によりロッド18が矢印26方向に上昇し、第1の受台10の上に載せた30枚のワークを収容箱12の内部に収容する。
持上げ検出センサ15は、格納庫14から収納箱12へ持ち上げられるワークの上昇端を検出する。
The storage box 12 stores 30 workpieces. When the workpieces stored in the storage box 12 become empty as described below, the rod 18 is raised in the direction of the arrow 26 by the drive of the lifting device 13, and the 30 workpieces placed on the first receiving table 10 are stored inside the storage box 12.
The lifting detection sensor 15 detects the rising end of the workpiece being lifted from the storage facility 14 to the storage box 12 .

ピッチ送り機構を有するピッチ送りユニット6は、取出しユニット5から上段の収容箱12に移動されたワーク30枚について、ワークを1枚ずつ上位にピッチ送りする。 The pitch feed unit 6, which has a pitch feed mechanism, pitch-feeds each of the 30 workpieces moved from the removal unit 5 to the upper storage box 12 one by one.

図3に示すように、ワーク供給装置1のピッチ送りユニット6は、収容箱12、ピッチ送り用サーボモータ16、ピッチ送り検出センサ21、ピッチ送りワーク受け22、及び、ピッチ送りアーム23を備える。 As shown in FIG. 3, the pitch feed unit 6 of the work supply device 1 includes a storage box 12, a pitch feed servo motor 16, a pitch feed detection sensor 21, a pitch feed work receiver 22, and a pitch feed arm 23.

ピッチ送り用サーボモータ16は、ピッチ送りワーク受け22に積載されるワークのうちの最上位のワークが後述する吸着ヘッド11により搬出されることにより減少したワークの厚さ相当の分の上昇を行う。
ピッチ送り検出センサ21は、検出したピッチ送り信号を図示しない制御装置に送る。制御装置の演算処理結果に基づくピッチ送り用サーボモータ16の駆動により、相応のピッチ送りアーム23の動作に対応するピッチ送りワーク受け22がワークを持ち上げる。
The pitch feed servo motor 16 lifts the workpiece by an amount equivalent to the thickness of the workpiece that is reduced when the topmost workpiece among the works loaded on the pitch feed workpiece receiver 22 is carried out by the suction head 11, which will be described later.
The pitch feed detection sensor 21 sends the detected pitch feed signal to a control device (not shown). The pitch feed servo motor 16 is driven based on the calculation result of the control device, and the pitch feed workpiece receiver 22 corresponding to the operation of the corresponding pitch feed arm 23 lifts the workpiece.

図5及び図6に示すように、ワーク支え36はワークの下に入り、チャックシリンダ35がワークの落下を防ぐ。図示しないサーボモータによりワーク支え36が1ピッチごとにワークをリフトする。 As shown in Figures 5 and 6, the work support 36 goes under the work, and the chuck cylinder 35 prevents the work from falling. The work support 36 lifts the work at one pitch by a servo motor (not shown).

図4は、マガジン14に積層された30枚のワークが収容され、収容箱12に積層された30枚のワークが収容され、ストックユニット7に4枚のワークが収容された状態を示している。 Figure 4 shows a state in which 30 workpieces are stored stacked in the magazine 14, 30 workpieces are stored stacked in the storage box 12, and 4 workpieces are stored in the stock unit 7.

図7は、ロッド18の上端で接続されるアーム23のピッチ送りワーク受け22に支持されるワークの残枚数が5枚になった状態を示している。
ピッチ送りワーク受け22は、収容箱12の内部のワークの枚数が30枚から5枚になるまでの期間中に積層されたワークを支持する。
FIG. 7 shows a state in which the remaining number of workpieces supported by the pitch-feed workpiece receiver 22 of the arm 23 connected to the upper end of the rod 18 is five.
The pitch-feed workpiece receiver 22 supports the stacked workpieces during the period in which the number of workpieces inside the storage box 12 decreases from 30 to 5.

ストックユニット7は、ピッチ送り機構により1枚ずつ上位に送られるワークが残り5枚になったら収容するユニットで、ワーク最大例えば5枚を収容する。 The stock unit 7 is a unit that stores the remaining five workpieces that are sent one by one to the upper position by the pitch feed mechanism, and can store a maximum of five workpieces.

1枚毎にワークは、後述する積込機に相当する吸着ヘッド11により吸引され、外部へ搬出される。吸着ヘッド11はバキュームを使用している。 The workpieces are sucked up one by one by the suction head 11, which corresponds to a loader described later, and transported to the outside. The suction head 11 uses a vacuum.

図7に示すように、 ストック機構を備えるストックユニット7は、吸着ヘッド11、ピッチ送りワーク受け22、ピッチ送りアーム23、ストック受け31、及び、ストックアーム32を備える。
ピッチ送りアーム23は、ワークの一番下の下面に入り込みワーク全体を支える。
As shown in FIG. 7 , the stock unit 7 equipped with the stock mechanism includes a suction head 11 , a pitch feed workpiece receiver 22 , a pitch feed arm 23 , a stock receiver 31 , and a stock arm 32 .
The pitch feed arm 23 enters the underside of the bottom of the workpiece and supports the entire workpiece.

ピッチ送りの最後のワークより数枚のワーク2を収容箱12に上部に残せるようストックアーム32及びストック受け31を備えている。 It is equipped with a stock arm 32 and a stock receiver 31 so that several workpieces 2 from the last workpiece of the pitch feed can be left at the top of the storage box 12.

前述した30枚の積層したワークを載せるピッチ送りワーク受け22がピッチ送りアーム23とともに ワンピッチごとに上昇し、残りワークの枚数が5枚になったとき、図7に示すように、ストックアーム32の下端に固定される第2の受台に相当するストック受け31が残り5枚 に積層されたワークの最下位のワークの下面に入り込んで積載された5枚のワークを支持する。 The pitch feed workpiece receiver 22, which holds the 30 stacked workpieces mentioned above, rises together with the pitch feed arm 23 at one pitch intervals, and when the number of remaining workpieces becomes five, as shown in FIG. 7, the stock receiver 31, which corresponds to the second receiving platform and is fixed to the lower end of the stock arm 32, enters the underside of the lowest workpiece of the remaining five stacked workpieces and supports the five stacked workpieces.

ストックアーム32はワンピッチずつ上昇し、ワンピッチごとに吸着ヘッド11による最上位のワークの吸着、取り上げを経て、目的の場所に最上位のワークを搬送供給する。
ストック受け31に載置されるワークの残数が存在している期間中、昇降装置13の第1受台10に相当するものとロッド18は下降し、格納庫に積層された新たな30枚のワークを支持し、上昇し、新たな30枚のワークを収容箱12内に搬入する。
The stock arm 32 rises one pitch at a time, and with each pitch the suction head 11 picks up and picks up the topmost workpiece, and then transports and supplies the topmost workpiece to the desired location.
During the period when there are remaining works to be placed on the stock receiver 31, the rod 18, which corresponds to the first receiving platform 10 of the lifting device 13, descends to support 30 new works stacked in the storage cell, and then rises to transport the new 30 works into the storage box 12.

これにより、最終取出しワーク2の搬出を待つことなしに、格納庫から収容箱へのワーク2の持上げができるようになり、収容箱からのワーク2の供給中でもワーク2の持上げができるため待ち時間をなくすことができる。 This allows the work 2 to be lifted from the storage facility to the storage box without waiting for the final work 2 to be removed, and since the work 2 can be lifted even while the work 2 is being supplied from the storage box, waiting time can be eliminated.

吸着ヘッド11は、収容箱12に収容される最上位のワークを1枚ずつ吸引し、当該ワークより下位にあるワークから切り離す。具体的には、吸着ベッド11の真空を利用した吸引力により最上位のワークの上面をヘッド吸引部40に吸着し、リフトしたワークを搬出し、搬送部を経て目的地に供給する。吸着ヘッドが図示しない目的地に到達後、ストックユニット7に戻る期間中に、ストックユニット7内のワークは1枚の厚さ分だけ上昇し、ピッチ送りされる。 The suction head 11 sucks up the topmost workpiece contained in the storage box 12 one by one, and separates it from the workpieces below it. Specifically, the suction force utilizing the vacuum of the suction bed 11 is used to suck up the top surface of the topmost workpiece to the head suction section 40, and the lifted workpiece is carried out and supplied to the destination via the transport section. After the suction head reaches the destination (not shown), during the period when it returns to the stock unit 7, the workpiece in the stock unit 7 rises by the thickness of one workpiece and is pitch-fed.

収容箱12の上位のワークの枚数が5枚になったら、第1の受台10に代わって、ストックユニット7のストック受け31がワークの残枚数を支持し、その最上位のワークを吸着ヘッド11が1枚ずつ吸引し、リフトしたワークを搬送部を経て目的地に搬送する。
なお、目的地においては、例えばワークの後加工をし、ワークがパワーカードであれば上面と下面に絶縁材を表面処理などする。
When the number of uppermost workpieces in the storage box 12 reaches five, a stock receiver 31 of a stock unit 7 supports the remaining number of workpieces instead of the first receiving table 10, and the suction head 11 sucks the uppermost workpieces one by one, and the lifted workpieces are transported to a destination via a transport section.
At the destination, the workpiece is subjected to post-processing, for example, and if the workpiece is a power card, the upper and lower surfaces are surface-treated with insulating material.

取出しユニットについて説明する。
図7に示すように、収容箱12において、積層されたワークの残枚数が5枚になったとき、2枚のストックアーム32に固定されるピン状のストック受け31が、積層されたワークの最下位のワークの下面に両側から矢印27、28の方向に入り込み、5枚のワーク2を支持する。
The take-out unit will now be described.
As shown in Figure 7, when the remaining number of stacked workpieces in the storage box 12 becomes five, a pin-shaped stock receiver 31 fixed to two stock arms 32 penetrates into the underside of the lowest workpiece of the stack from both sides in the directions of arrows 27 and 28, and supports the five workpieces 2.

代わって積層されたワークの支持部材は、第1の受台10、ピッチ送りワーク受け22からストック受け31に切り替わる。第1の受台10を連結するロッド18は、収容箱12から下降し、収容箱12の下方のマガジン14に移動する。 Instead, the support members for the stacked workpieces are switched from the first receiving table 10 and the pitch-feed workpiece receiving table 22 to the stock receiving table 31. The rod 18 connecting the first receiving table 10 descends from the storage box 12 and moves to the magazine 14 below the storage box 12.

ストック受け31で持上げられたワーク2は、ピッチ送りされながら上昇し、最上位のワークの一が一定の高さまで上昇する。このとき、最上位のワークの上面に吸着ヘッド11が吸着し、下位のワークから切り離した最上位のワークを吸着ヘッド11が吸引し、最上位のワークを外部に供給する。 The workpieces 2 lifted by the stock receiver 31 rise while being pitch-fed, and the topmost workpiece rises to a certain height. At this time, the suction head 11 adheres to the top surface of the topmost workpiece, sucks in the topmost workpiece that has been separated from the lower works, and supplies the topmost workpiece to the outside.

ピッチ送り用サーボ16によりワーク2が減少した分の上昇を行い、最後の1枚のワークを取り出すと、ストック受け31が矢印27、28の反対方向に開いて、ワーク2の持上げができるようスペースを空ける。そのスペースに持上げられたワーク2が侵入して収容箱12へのワーク供給が完了する。 The pitch feed servo 16 raises the work 2 by the amount that has been removed, and when the last work is removed, the stock receiver 31 opens in the opposite direction of the arrows 27 and 28 to make space so that the work 2 can be lifted. The lifted work 2 enters this space, completing the supply of the work to the storage box 12.

次に、ワーク供給の動作を図8に基づいて説明する。
工程Aに示すように、初期状態では、収納箱12内で積層された例えば30枚のワークはピッチ送りワーク受け22に支持される。この状態で積層されたワークの最上位のワークは、Xに示す位置にある。この位置の最上位のワークから、順に、吸着ヘッド11で吸引されて搬出(供給)される。
Next, the work supply operation will be described with reference to FIG.
As shown in process A, in the initial state, for example, 30 workpieces stacked in the storage box 12 are supported by the pitch-feed workpiece receiver 22. The topmost workpiece of the stacked workpieces in this state is at the position indicated by X. Starting from the topmost workpiece at this position, the workpieces are sucked up by the suction head 11 and carried out (supplied) in order.

工程Bに示すように、ピッチ送りワーク受け22から最上位のワークが1枚毎に搬出される度に、ピッチ送りワーク受け22が残りのワークをワンピッチずつ上位に送る。 As shown in process B, each time the topmost workpiece is removed from the pitch-feed workpiece receiver 22, the pitch-feed workpiece receiver 22 sends the remaining works one pitch higher.

工程Cに示すように、積層されたワークの残数が5枚になると、第1の受け台10をリフトし、ピッチ送りワーク受け22に代わって第2の受台に相当するストック受け31が矢印27、28方向に入り込む。Yに示す位置でストック受け31とピッチ送りワーク受け22は共存する。 As shown in process C, when the remaining number of stacked workpieces is five, the first receiving table 10 is lifted, and the stock receiving table 31, which corresponds to the second receiving table, moves in the direction of the arrows 27 and 28, replacing the pitch-feed work receiving table 22. The stock receiving table 31 and the pitch-feed work receiving table 22 coexist at the position shown by Y.

その後、工程Dに示すように、ストック受け31が1ピッチ毎に上昇する。ワークの残数が5枚から1枚になる期間中、ピッチ送りワーク受け22は所定位置まで下降する。 Then, as shown in process D, the stock receiver 31 rises one pitch at a time. During the period when the remaining number of workpieces decreases from 5 to 1, the pitch-feed workpiece receiver 22 descends to a predetermined position.

次いで、工程Dから工程Eに示すように、ストック受け31の支持するワークの残数が5枚から1枚に減少していく期間中に、格納庫14から、新たな30枚のワークを積載したロッド18が上昇し、収容箱12内に新たな30枚のワークを搬入する。このとき、ストック受け31の支持するワークの残数が無くなった後、ストック受け31が矢印29、30の方向に開く。 Next, as shown in steps D and E, during the period in which the remaining number of workpieces supported by the stock receiver 31 decreases from 5 to 1, the rod 18 loaded with 30 new workpieces rises from the storage shed 14 and carries the new 30 workpieces into the storage box 12. At this time, after the remaining number of workpieces supported by the stock receiver 31 runs out, the stock receiver 31 opens in the directions of the arrows 29 and 30.

工程Fに示すように、ストック受け31に支持される最後のワークが吸着ヘッド11により収容箱12から搬出されるや否や、遅滞なしに、上記の新たな30枚の積層されたワークが収容箱12内に搬入される。ロッド18が上昇してもストック受け31には干渉しない。 As shown in process F, as soon as the last workpiece supported by the stock receiver 31 is removed from the storage box 12 by the suction head 11, the 30 new stacked workpieces are transferred into the storage box 12 without delay. Even if the rod 18 rises, it does not interfere with the stock receiver 31.

続いて工程Aの初期状態に戻って、上述した作動を繰り返す。収容箱12からのワークの搬出(供給)が連続的に遅れることなしに、待ち時間を生じることなしに、最上位の1枚のワークを順に吸着ヘッド11が吸着し、このワークを目的地に供給する。 Then, the process returns to the initial state of process A and repeats the above-mentioned operations. The suction head 11 picks up the topmost workpiece in sequence without any delay in the removal (supply) of the workpieces from the storage box 12 and without any waiting time, and supplies this workpiece to the destination.

上記実施形態によると、数枚のワークを収容箱12の上部に残せるようストックアーム32及びストック受け31を設けたことにより、最終取出しワークを待つことなくワークの持上げができるようになり、収容箱と格納庫からなる1個のレーンに追加のレーンを設けることなしに、ワーク供給中でもワークの持上げができるため、第1の受台のワーク残数がゼロになっても、吸着ヘッドによるワークの搬出を待ち時間を無しに搬出(供給)することができる。 According to the above embodiment, by providing a stock arm 32 and a stock receiver 31 so that several workpieces can be left on top of the storage box 12, it becomes possible to lift the workpieces without waiting for the last workpiece to be removed, and since the workpieces can be lifted even while they are being supplied without providing an additional lane to the single lane consisting of the storage box and the storage facility, even if the number of remaining works on the first receiving table becomes zero, the suction head can remove (supply) the workpieces without waiting.

従来は、ワーク収容箱12へのワーク搬入時刻がワーク取出しの工程作業時刻(生産工程における均等なタイミングを図るための工程作業時刻)を経過してしまうと、取出し待ちが発生した。この待ち時間をなくすために余分に1レーン使い、2個のレーンを交互に使うことで待ち時間を無しにしていた。 Conventionally, if the time the workpiece was delivered to the work storage box 12 passed the process operation time for removing the workpiece (the process operation time for ensuring equal timing in the production process), a wait occurred before the workpiece could be removed. To eliminate this wait time, an extra lane was used, and the two lanes were used alternately, eliminating the wait time.

これに対し、本実施形態では、供給レーン数を増やすことなしに、小空間でコスト増なしに高効率にワークを供給することができる。 In contrast, in this embodiment, work can be supplied efficiently in a small space without increasing the number of supply lanes and without increasing costs.

上記実施形態では、格納庫14から収容箱12へ移動するワークの枚数について30枚の例、第1の受台10から第2の受台相当のストック受け31に切り替わる残枚数が5枚の例を説明したが、本発明では、これらの枚数は限定されるものでない。
上記実施形態の吸着ヘッドに代えて、本発明では、ワークを把持し取出すチャック部であってもよい。
In the above embodiment, an example was described in which the number of workpieces moved from the storage facility 14 to the storage box 12 was 30, and an example was described in which the number of remaining workpieces when switching from the first receiving table 10 to the stock receiver 31 equivalent to the second receiving table was 5, but in the present invention, these numbers are not limited to these.
In place of the suction head in the above embodiment, in the present invention, a chuck portion that grips and removes a workpiece may be used.

上記実施形態では、パワーカードを本発明のワークに相当する実施形態について説明したが、本発明のワークは、パワーカード以外のものをワーク相当とする実施形態であってもよいことはもちろんである。 In the above embodiment, a power card is described as the workpiece of the present invention, but the workpiece of the present invention may of course be something other than a power card.

以上、本発明は、上記実施形態に限定されるものではなく、その要旨を逸脱しない範囲において種々の形態で実施可能である。 The present invention is not limited to the above-described embodiment, and can be implemented in various forms without departing from the spirit of the invention.

1 パワーカード供給装置(ワークの供給装置)、
2 ワーク、
5 取出しユニット、
6 ピッチ送りユニット、
7 ストックユニット、
10 第1の受台、
11 吸着ヘッド(積込機)、
12 収容箱、
13 持上げリフタ、
14 マガジン(格納庫)、
15 持上げ検出センサ、
16 ピッチ送り用サーボ、
17 ピッチ送りクランプツメ、
21 ピッチ送り検出センサ、
22 ピッチ送りワーク受け(第1の受台)、
23 ピッチ送りアーム、
31 ストック受け(第2の受台)、
32 ストックアーム、
34 ストック、
35 チャックシリンダ(チャック機構)。
1 Power card supply device (work supply device),
2 Work,
5. take-out unit,
6 pitch feed unit,
7 Stock Units,
10 First cradle,
11 suction head (loader),
12 storage box,
13 lifting lifter,
14 magazine (hangar),
15 lifting detection sensor,
16 Pitch feed servo,
17 Pitch feed clamp jaws,
21 pitch feed detection sensor,
22 Pitch feed workpiece receiver (first receiver),
23 pitch feed arm,
31 Stock receiver (second receiver),
32 stock arm,
34 Stock,
35 Chuck cylinder (chuck mechanism).

Claims (4)

多数枚のワーク(2)を保管可能であって、前記多数枚のワークのうちの最上位のワークを順に外部に供給するワークの供給装置であって、
外部から多数枚のワークを搬入し積層可能な格納庫(14)と、
前記格納庫の上段に位置し、前記格納庫で積層される多数枚のワークを所定のタイミングに受け入れ可能な収納箱(12)と、
前記収容箱に設けられ、多数枚のワークを支持する第1の受台(10、22)と、
前記第1の受台上のワークの残枚数が所定枚数に減小したとき当該所定枚数の残ワークを前記第1の受台から受け渡される第2の受台(31)と、
前記収容箱で第1の受台又は第2の受台に積層されるワークのうちの最上位のワークを順に搬出する積込機(11)と、
前記積込機により最上位のワークを搬出する度に前記第1の受台上の搬出後の残ワークを上位にピッチ送りするピッチ送りユニット(6)と、
前記収容箱で積層される多数枚のワークが順に外部に搬出される際、前記第1の受台上のワークの残枚数が所定枚数に減小したとき、前記第2の受台上のワークの前記積込機によるワークの一枚毎の搬出を継続する期間中に、前記格納庫の多数枚のワークを前記収容箱内の前記第1の受台に搬入するロッド(13、18)と、を備え、
前記ロッドは、積層された多数のワークを第1の受台に受け渡した後に下降し、格納庫で次に積層される多数のワークを積込み、第2の受台から残ワークの最上位のワークを順に搬出する期間中に上昇し、積込まれた多数のワークを収納箱で第1の受台に受け渡す、ワークの供給装置。
A work supply device capable of storing a large number of workpieces (2) and supplying the topmost workpiece of the large number of workpieces to the outside in sequence,
A storage facility (14) capable of carrying in and stacking a large number of workpieces from the outside;
a storage box (12) located at the upper level of the storage facility and capable of receiving a large number of workpieces stacked in the storage facility at a predetermined timing;
A first receiving table (10, 22) provided in the storage box and supporting a large number of workpieces;
a second receiving table (31) to which the predetermined number of remaining workpieces is transferred from the first receiving table when the remaining number of workpieces on the first receiving table is reduced to a predetermined number;
a loader (11) for sequentially carrying out the topmost workpiece among the workpieces stacked on the first receiving table or the second receiving table in the storage box;
a pitch feed unit (6) that pitch-feeds the remaining workpieces on the first receiving table upward every time the top workpiece is carried out by the loader;
and a rod (13, 18) for loading the multiple workpieces from the storehouse onto the first receiving table in the storage box during a period in which the loader continues to unload the workpieces one by one from the second receiving table when the remaining number of workpieces on the first receiving table is reduced to a predetermined number when the multiple workpieces stacked in the storage box are unloaded to the outside in sequence,
A work supply device in which the rod transfers a large number of stacked workpieces to a first receiving table, then descends to load the next large number of workpieces to be stacked in the storage facility, and rises during a period in which the topmost remaining workpieces are removed in order from the second receiving table, and transfers the loaded large number of workpieces to the first receiving table in a storage box .
前記積込機は、ワークを吸引し取出す吸着ヘッドと、当該ワークと吸着ヘッドを目的地
に搬送する搬送部と、を備えた請求項1に記載のワークの供給装置。
2. The work supply device according to claim 1, wherein the loader comprises a suction head that sucks up and picks up the work, and a transport section that transports the work and the suction head to a destination.
前記第2の受台は、前記収容箱の残枚数のワークを下面側から支持するチャック機構部
(35)である請求項1又は2記載のワークの供給装置。
3. The work supply device according to claim 1, wherein the second support table is a chuck mechanism (35) that supports the remaining number of workpieces in the storage box from below.
前記吸着ヘッドに代えて、ワークを把持し取出すチャック部である請求項2記載のワー
クの供給装置。
3. A work supplying device according to claim 2, wherein the suction head is replaced by a chuck portion for gripping and removing the work.
JP2021125270A 2021-07-30 2021-07-30 Work supply device Active JP7643237B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021125270A JP7643237B2 (en) 2021-07-30 2021-07-30 Work supply device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021125270A JP7643237B2 (en) 2021-07-30 2021-07-30 Work supply device

Publications (2)

Publication Number Publication Date
JP2023020087A JP2023020087A (en) 2023-02-09
JP7643237B2 true JP7643237B2 (en) 2025-03-11

Family

ID=85159627

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021125270A Active JP7643237B2 (en) 2021-07-30 2021-07-30 Work supply device

Country Status (1)

Country Link
JP (1) JP7643237B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000136004A (en) 1998-10-31 2000-05-16 Fujitac:Kk Automatic picking device
JP2018020375A (en) 2016-07-26 2018-02-08 アイダエンジニアリング株式会社 Material supply device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000136004A (en) 1998-10-31 2000-05-16 Fujitac:Kk Automatic picking device
JP2018020375A (en) 2016-07-26 2018-02-08 アイダエンジニアリング株式会社 Material supply device

Also Published As

Publication number Publication date
JP2023020087A (en) 2023-02-09

Similar Documents

Publication Publication Date Title
JP2016199399A (en) Part supply apparatus, robot system, and part supply method
CN112357589B (en) Full-automatic screen feeding machine
JP4516067B2 (en) Substrate carry-in / out device and substrate carry-in / out method
CN116281797B (en) Tray capping and uncapping conveying system for chip cleaning
CN107150906A (en) Workpiece piece-rate system and workpiece separation method
CN114641854B (en) Loading and unloading device for substrate material box and substrate material box system
TW202242432A (en) Handler for testing electronic components
JP7643237B2 (en) Work supply device
CN116913836A (en) Packaged chip batch processing equipment and method
KR100789292B1 (en) Handler and Tray Transfer Method for Semiconductor Device Testing
CN115722964A (en) Stacking device, automation module, manufacturing system and method for supplying machine tool
CN222273453U (en) Conveying line for PCB (printed Circuit Board) plates
JPS63202521A (en) Tray feeding/discharging device
WO2006123402A1 (en) Substrate loading/unloading device and substrate loading/unloading method
CN219030970U (en) Loading and unloading device
US20030113200A1 (en) Handling device and method for loading and unloading work pieces from trays
CN217023910U (en) Stock bin device and stock bin system
JP5531976B2 (en) Pallet change system
CN119894787A (en) Sorting device
CN103872173A (en) Stacking-inserting conversion system and method
JP2013170029A (en) Palletizing apparatus and palletizing method
CN216189168U (en) Feeding and discharging device
JPH10203611A (en) Conveyer for storage case
CN121590977A (en) Workpiece loading device
CN220331410U (en) Automatic feeding and discharging system of plate transfer device and processing equipment

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230907

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20240625

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240723

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240809

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20241105

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20241121

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20250128

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20250210

R150 Certificate of patent or registration of utility model

Ref document number: 7643237

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150