JP7655722B2 - Gas separation systems, and hydrocarbon production systems - Google Patents
[go: Go Back, main page]

JP7655722B2 - Gas separation systems, and hydrocarbon production systems - Google Patents

Gas separation systems, and hydrocarbon production systems Download PDF

Info

Publication number
JP7655722B2
JP7655722B2 JP2020211017A JP2020211017A JP7655722B2 JP 7655722 B2 JP7655722 B2 JP 7655722B2 JP 2020211017 A JP2020211017 A JP 2020211017A JP 2020211017 A JP2020211017 A JP 2020211017A JP 7655722 B2 JP7655722 B2 JP 7655722B2
Authority
JP
Japan
Prior art keywords
adsorber
carbon dioxide
gas
desorption
purge gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020211017A
Other languages
Japanese (ja)
Other versions
JP2022097832A (en
Inventor
教文 小宅
靖樹 廣田
征治 山本
隆太 神谷
哲治 永田
伸光 堀部
佳道 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toyota Industries Corp
Denso Corp
Toyota Motor Corp
Toyota Central R&D Labs Inc
Aisin Corp
Original Assignee
Toyota Industries Corp
Aisin Seiki Co Ltd
Denso Corp
Toyota Motor Corp
Toyota Central R&D Labs Inc
Aisin Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyota Industries Corp, Aisin Seiki Co Ltd, Denso Corp, Toyota Motor Corp, Toyota Central R&D Labs Inc, Aisin Corp filed Critical Toyota Industries Corp
Priority to JP2020211017A priority Critical patent/JP7655722B2/en
Publication of JP2022097832A publication Critical patent/JP2022097832A/en
Application granted granted Critical
Publication of JP7655722B2 publication Critical patent/JP7655722B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Separation Of Gases By Adsorption (AREA)
  • Organic Low-Molecular-Weight Compounds And Preparation Thereof (AREA)
  • Low-Molecular Organic Synthesis Reactions Using Catalysts (AREA)

Description

本発明は、二酸化炭素含有ガスから二酸化炭素を分離するガス分離システムに関する。 The present invention relates to a gas separation system that separates carbon dioxide from a carbon dioxide-containing gas.

従来、二酸化炭素と水素からメタンを製造するメタン製造装置において、二酸化炭素吸着性能を有する吸着材を収容する吸着塔を2つ備え、それぞれの吸着塔が二酸化炭素の吸着・脱離を繰り返して、二酸化炭素含有ガスから二酸化炭素を分離し、分離された二酸化炭素と離脱の際に用いられた水素とを用いてメタンを製造する技術が提案されている(例えば、特許文献1参照)。 In a conventional methane production apparatus that produces methane from carbon dioxide and hydrogen, a technology has been proposed in which two adsorption towers containing an adsorbent with carbon dioxide adsorption properties are provided, and each adsorption tower repeatedly adsorbs and desorbs carbon dioxide to separate the carbon dioxide from a carbon dioxide-containing gas, and methane is produced using the separated carbon dioxide and the hydrogen used during the desorption (see, for example, Patent Document 1).

特開2019-142806号公報JP 2019-142806 A

特許文献1に記載の技術によれば、水素で吸着塔内部をパージして二酸化炭素を脱離させ、その後に、パージで用いられた水素を利用してメタンを生成するため、パージに用いられる水素の量が限られる。そのため、パージガスによる吸着塔からの二酸化炭素の脱離効率を十分に得ることができない場合がある。このような問題は、パージガスとして水素を利用するメタン製造装置に限らず、吸着材を用いて二酸化炭素を分離する二酸化炭素分離システムに共通する課題である。 According to the technology described in Patent Document 1, the inside of the adsorption tower is purged with hydrogen to desorb carbon dioxide, and then the hydrogen used in the purge is used to generate methane, so the amount of hydrogen used for purging is limited. As a result, there are cases where the efficiency of desorption of carbon dioxide from the adsorption tower by the purge gas cannot be sufficiently achieved. This problem is not limited to methane production devices that use hydrogen as a purge gas, but is a common issue with carbon dioxide separation systems that separate carbon dioxide using an adsorbent.

本発明は、上述した課題を解決するためになされたものであり、ガス分離システムにおいて、パージガスによる二酸化炭素の脱離効率を向上させる技術を提供することを目的とする。 The present invention has been made to solve the above-mentioned problems, and aims to provide a technology that improves the efficiency of carbon dioxide desorption by purge gas in a gas separation system.

本発明は、上述の課題の少なくとも一部を解決するためになされたものであり、以下の形態として実現することが可能である。 The present invention has been made to solve at least some of the above problems, and can be realized in the following form.

(1)本発明の一形態によれば、二酸化炭素を吸着可能な吸着材を内部に収容する複数の吸着器を備えるガス分離システムが提供される。このガス分離システムは、前記複数の吸着器のうち、第1吸着器と第2吸着器とを直列に接続可能な接続流路と、前記第1吸着器にパージガスを供給可能なパージガス供給流路と、前記第1吸着器と前記第2吸着器に二酸化炭素が吸着された状態で、前記パージガス供給流路を介して、前記第1吸着器に前記パージガスを供給させ、前記第1吸着器から二酸化炭素を脱離させる第1脱離工程と、前記接続流路を介して前記第1吸着器に前記第2吸着器を接続させ、前記第1吸着器内を流通したパージガスを、前記接続流路を介して前記第2吸着器に流入させ、前記第2吸着器から二酸化炭素を脱離させる第2脱離工程を、同時に実行可能な制御部と、を備える。 (1) According to one aspect of the present invention, a gas separation system is provided that includes a plurality of adsorbers that house an adsorbent capable of adsorbing carbon dioxide. The gas separation system includes a connection flow path that can connect a first adsorber and a second adsorber in series among the plurality of adsorbers, a purge gas supply flow path that can supply a purge gas to the first adsorber, and a control unit that can simultaneously execute a first desorption process in which, in a state in which carbon dioxide is adsorbed in the first adsorber and the second adsorber, the purge gas is supplied to the first adsorber through the purge gas supply flow path to desorb carbon dioxide from the first adsorber, and a second desorption process in which the second adsorber is connected to the first adsorber through the connection flow path, the purge gas that has circulated in the first adsorber is flowed into the second adsorber through the connection flow path, and the carbon dioxide is desorbed from the second adsorber.

この構成によれば、第1吸着器を通過したパージガスを第2吸着器に流入させることができるため、第2吸着器も同時に脱離させることができる。第1吸着器内の二酸化炭素を脱離させたパージガスを含む混合ガスは、脱離工程開始直後は二酸化炭素の濃度が高いが、その後徐々に二酸化炭素濃度が下がる。この混合ガスを第2吸着器に流入させると、第2吸着器内の二酸化炭素も脱離が可能になる。そのため、パージガスによる二酸化炭素の脱離効率を向上させることができる。 According to this configuration, the purge gas that has passed through the first adsorber can be made to flow into the second adsorber, so that the second adsorber can also be desorbed at the same time. The mixed gas containing the purge gas from which the carbon dioxide in the first adsorber has been desorbed has a high carbon dioxide concentration immediately after the start of the desorption process, but the carbon dioxide concentration thereafter gradually decreases. By making this mixed gas flow into the second adsorber, the carbon dioxide in the second adsorber can also be desorbed. Therefore, the efficiency of desorption of carbon dioxide by the purge gas can be improved.

(2)上記形態のガス分離システムであって、二酸化炭素を含有する二酸化炭素含有ガスを、前記第1吸着器および前記第2吸着器と異なる第3吸着器に供給可能な、二酸化炭素含有ガス供給流路をさらに備え、前記制御部は、前記二酸化炭素含有ガス供給流路を介して、前記第3吸着器に前記二酸化炭素含有ガスを供給させて、二酸化炭素を吸着させる吸着工程を、前記第1脱離工程と同時に実行可能であり、同時に実行される前記第1脱離工程、前記第2脱離工程、および前記吸着工程を含む吸脱着工程を、前記第1脱離工程、前記第2脱離工程、および前記吸着工程のそれぞれが実行される前記第1吸着器、前記第2吸着器、および前記第3吸着器を変更して繰り返し実行可能であってもよい。 (2) The gas separation system of the above embodiment further includes a carbon dioxide-containing gas supply flow path capable of supplying a carbon dioxide-containing gas containing carbon dioxide to a third adsorber different from the first adsorber and the second adsorber, and the control unit is capable of simultaneously executing an adsorption process for adsorbing carbon dioxide by supplying the carbon dioxide-containing gas to the third adsorber via the carbon dioxide-containing gas supply flow path and the first desorption process, and may be capable of repeatedly executing the adsorption/desorption process including the first desorption process, the second desorption process, and the adsorption process, which are simultaneously executed, by changing the first adsorber, the second adsorber, and the third adsorber in which the first desorption process, the second desorption process, and the adsorption process are executed, respectively.

この構成によれば、第3吸着器に二酸化炭素含有ガスを供給して、第3吸着器に二酸化炭素を吸着させている間に、第1吸着器および第2吸着器内に吸着された二酸化炭素を脱離させることができる。すなわち、吸着工程の時間の間に、第1吸着器および第2吸着器の脱離工程を行うため、疑似的にパージガス量を増やし、脱離時間も長くすることが可能になる。その結果、限られた量のパージガスにより、限られた時間における二酸化炭素の脱離効率を向上させることができる。 According to this configuration, the carbon dioxide adsorbed in the first and second adsorbers can be desorbed while the carbon dioxide-containing gas is being supplied to the third adsorber and the carbon dioxide is being adsorbed in the third adsorber. In other words, since the desorption process of the first and second adsorbers is performed during the adsorption process, it is possible to artificially increase the amount of purge gas and lengthen the desorption time. As a result, the carbon dioxide desorption efficiency in a limited time can be improved by using a limited amount of purge gas.

(3)上記形態のガス分離システムであって、前記制御部は、前記第2脱離工程の一部の期間において、前記第1吸着器内を流通したパージガスを、前記接続流路を介して前記第2吸着器に流入させてもよい。このようにすると、例えば、第1吸着器から排出される混合ガスの二酸化炭素濃度が低く、第1吸着器内を流通したパージガスによる第2吸着器の二酸化炭素脱離が十分に行われると予想される期間にのみ、1吸着器内を流通したパージガスを、第2吸着器に流入させる等、適切にパージガスの再利用を行うことができる。 (3) In the gas separation system of the above embodiment, the control unit may cause the purge gas that has circulated through the first adsorber to flow into the second adsorber via the connecting flow path during a portion of the second desorption process. In this way, the purge gas can be appropriately reused, for example, by causing the purge gas that has circulated through the first adsorber to flow into the second adsorber only during a period when the carbon dioxide concentration of the mixed gas discharged from the first adsorber is low and it is expected that the purge gas that has circulated through the first adsorber will adequately desorb carbon dioxide from the second adsorber.

(4)上記形態のガス分離システムであって、前記パージガスは、水素でもよい。このようにすると、例えば、吸着器から出てきたパージガスとしての水素と、脱離された二酸化炭素とを用いて、炭化水素を製造することができる。このようにすると、他のパージガスを用いる場合と比較して、炭化水素の純度を向上させることができる。 (4) In the gas separation system of the above embodiment, the purge gas may be hydrogen. In this way, for example, hydrocarbons can be produced using hydrogen as the purge gas coming out of the adsorber and the desorbed carbon dioxide. In this way, the purity of the hydrocarbons can be improved compared to the case where other purge gases are used.

(5)本発明の別の形態によれば、炭化水素製造システムが提供される。この炭化水素製造システムは、上記形態のガス分離システムと、前記ガス分離システムと接続され、前記ガス分離システムにより分離された二酸化炭素と、前記パージガスとして用いられた水素との混合ガスを用いて、炭化水素化合物を生成する炭化水素生成部と、を備える。この構成によれば、炭化水素生成部は、二酸化炭素と水素の濃度が高い混合ガスを用いて炭化水素化合物を生成することができる。これにより、純度の高い炭化水素化合物を生成することができる。また、ガス分離システムは、パージガスを再利用することによりパージガスによる二酸化炭素の脱離効率が向上されているため、炭化水素生成部における炭化水素生成効率を向上させることができる。また、炭化水素生成部のメタンの生成における余剰の水素量を低減させることができる。 (5) According to another aspect of the present invention, a hydrocarbon production system is provided. This hydrocarbon production system includes the gas separation system of the above aspect, and a hydrocarbon production unit connected to the gas separation system, which produces hydrocarbon compounds using a mixed gas of carbon dioxide separated by the gas separation system and hydrogen used as the purge gas. According to this configuration, the hydrocarbon production unit can produce hydrocarbon compounds using a mixed gas having a high concentration of carbon dioxide and hydrogen. This makes it possible to produce hydrocarbon compounds with high purity. In addition, the gas separation system can improve the efficiency of carbon dioxide desorption by the purge gas by reusing the purge gas, thereby improving the efficiency of hydrocarbon production in the hydrocarbon production unit. In addition, the amount of excess hydrogen in the production of methane in the hydrocarbon production unit can be reduced.

なお、本発明は、種々の態様で実現することが可能であり、例えば、ガス分離方法、炭化水素製造方法、ガス分離システムの制御方法、炭化水素製造システムの制御方法、これらの制御方法をコンピュータに実行させるコンピュータプログラム、そのコンピュータプログラムを配布するためのサーバ装置、そのコンピュータプログラムを記憶した一時的でない記憶媒体等、二酸化炭素循環システム、炭化水素を燃料とする燃料製造システムなどの形態で実現することができる。 The present invention can be realized in various forms, such as a gas separation method, a hydrocarbon production method, a method for controlling a gas separation system, a method for controlling a hydrocarbon production system, computer programs for causing a computer to execute these control methods, a server device for distributing the computer program, a non-transitory storage medium storing the computer program, a carbon dioxide circulation system, a fuel production system using hydrocarbons as fuel, etc.

第1実施形態のガス分離システムの概略構成を示す説明図である。1 is an explanatory diagram showing a schematic configuration of a gas separation system according to a first embodiment. ガス分離システムにおける吸着器の切替タイミングの説明図である。FIG. 4 is an explanatory diagram of the timing of switching the adsorber in the gas separation system. ガス分離システムにおける工程1の説明図である。FIG. 1 is an illustration of step 1 in a gas separation system. ガス分離システムにおける工程2の説明図である。FIG. 2 is an explanatory diagram of step 2 in the gas separation system. ガス分離システムにおける工程3の説明図である。FIG. 2 is an illustration of step 3 in the gas separation system. 工程1~工程3の開始時の二酸化炭素の吸着量を概念的に示す説明図である。FIG. 2 is an explanatory diagram conceptually showing the amount of carbon dioxide adsorption at the start of steps 1 to 3. 比較例のガス分離システムの概略構成を示す説明図である。FIG. 2 is an explanatory diagram showing a schematic configuration of a gas separation system of a comparative example. 比較例のガス分離システムにおける吸着器の切替タイミングの説明図である。FIG. 4 is an explanatory diagram of the switching timing of the adsorber in the gas separation system of the comparative example. 第1実施形態のガス分離システムの脱離工程における二酸化炭素吸着量の変化を示す図である。FIG. 4 is a diagram showing a change in the amount of carbon dioxide adsorption in the desorption process of the gas separation system of the first embodiment. 比較例のガス分離システムの脱離工程における二酸化炭素吸着量の変化を示す図である。FIG. 4 is a graph showing the change in the amount of carbon dioxide adsorbed in the desorption process of the gas separation system of the comparative example. 第2実施形態のガス分離システムの概略構成を示す説明図である。FIG. 4 is an explanatory diagram showing a schematic configuration of a gas separation system according to a second embodiment. 第2実施形態のガス分離システムにおける吸着器の切替タイミングの説明図である。FIG. 11 is an explanatory diagram of the switching timing of the adsorber in the gas separation system of the second embodiment. 第2実施形態のガス分離システムにおける工程1Aの説明図である。FIG. 1 is an explanatory diagram of step 1A in a gas separation system according to a second embodiment. 第3実施形態のガス分離システムにおける吸着器の切替タイミングの説明図である。FIG. 11 is an explanatory diagram of the switching timing of the adsorber in the gas separation system of the third embodiment. 第3実施形態の工程1Bの第2脱離工程の説明図である。FIG. 13 is an explanatory diagram of the second desorption step of step 1B of the third embodiment. 第4実施形態のガス分離システムの概略構成を示す説明図である。FIG. 13 is an explanatory diagram showing a schematic configuration of a gas separation system according to a fourth embodiment. 第4実施形態のガス分離システムにおける吸着器の切替タイミングの説明図である。FIG. 13 is an explanatory diagram of the switching timing of the adsorber in the gas separation system of the fourth embodiment. 第4実施形態の工程1Cの第2脱離工程の説明図である。FIG. 13 is an explanatory diagram of the second desorption step of step 1C of the fourth embodiment. 第5実施形態の炭化水素製造システムの概略構成を示す説明図である。FIG. 13 is an explanatory diagram showing a schematic configuration of a hydrocarbon production system according to a fifth embodiment.

<第1実施形態>
図1は、第1実施形態のガス分離システム1の概略構成を示す説明図である。ガス分離システム1は、燃焼炉や内燃機関などから排出される排ガスに含まれる二酸化炭素を、分離し、回収する。ガス分離システム1は、複数の吸着器11、12、13(吸着器11、12、13を区別しない場合は、単に、吸着器10とも呼ぶ)と、二酸化炭素含有ガス供給流路20と、パージガスとしての水素を供給するパージガス供給流路70と、2つの吸着器10を直列に接続する接続流路80(接続流路81、接続流路82、および接続流路83)と、熱媒流路30と、混合ガス流路60と、サージタンク40と、制御部55とを備える。
First Embodiment
1 is an explanatory diagram showing a schematic configuration of a gas separation system 1 of the first embodiment. The gas separation system 1 separates and recovers carbon dioxide contained in exhaust gas discharged from a combustion furnace, an internal combustion engine, etc. The gas separation system 1 includes a plurality of adsorbers 11, 12, and 13 (when the adsorbers 11, 12, and 13 are not distinguished from each other, they are also simply called adsorbers 10), a carbon dioxide-containing gas supply flow path 20, a purge gas supply flow path 70 that supplies hydrogen as a purge gas, a connection flow path 80 (connection flow path 81, connection flow path 82, and connection flow path 83) that connects two adsorbers 10 in series, a heat medium flow path 30, a mixed gas flow path 60, a surge tank 40, and a control unit 55.

複数の吸着器11、12、13は、筒状に形成され、それぞれの内部に吸着材11a、12a、13aが収容されている。吸着材11a、12a、13aは、二酸化炭素吸蔵性能を有する材料、例えば、ゼオライト、活性炭、シリカゲルなどである。吸着器11、12、13のそれぞれには、二酸化炭素含有ガス供給流路20と、パージガス供給流路70と、混合ガス流路60と、熱媒流路30と、が接続されている。複数の吸着器11、12、13のそれぞれには、図示しない冷媒流路も形成されている。 The multiple adsorbers 11, 12, 13 are formed in a cylindrical shape and contain adsorbents 11a, 12a, 13a, respectively. The adsorbents 11a, 12a, 13a are materials having carbon dioxide occlusion performance, such as zeolite, activated carbon, silica gel, etc. Each of the adsorbers 11, 12, 13 is connected to a carbon dioxide-containing gas supply flow path 20, a purge gas supply flow path 70, a mixed gas flow path 60, and a heat medium flow path 30. Each of the multiple adsorbers 11, 12, 13 also has a refrigerant flow path (not shown).

二酸化炭素含有ガス供給流路20は、二酸化炭素含有ガスとしての排ガスを排出する外部の排ガス供給装置(例えば、燃焼炉や内燃機関など)に接続されており、排ガス供給装置が排出する排ガスが流れる。二酸化炭素含有ガス供給流路20を流れる排ガスは、排ガス分流路21、22、23を介して、吸着器11、12、13に供給される。排ガス分流路21、22、23には、排ガス入口弁21a、22a、23aが、それぞれ、設けられている。排ガス入口弁21a、22a、23aのそれぞれは、制御部55の指令に応じて、吸着器11、12、13の内部への排ガスの供給を制御する。本実施形態において、二酸化炭素含有ガスとして、排ガスを例示しているが、二酸化炭素含有ガスは、排ガスでなくてもよい。 The carbon dioxide-containing gas supply flow path 20 is connected to an external exhaust gas supply device (e.g., a combustion furnace or an internal combustion engine) that discharges exhaust gas as carbon dioxide-containing gas, and the exhaust gas discharged by the exhaust gas supply device flows through the carbon dioxide-containing gas supply flow path 20. The exhaust gas flowing through the carbon dioxide-containing gas supply flow path 20 is supplied to the adsorbers 11, 12, and 13 via exhaust gas branch flow paths 21, 22, and 23. Exhaust gas inlet valves 21a, 22a, and 23a are provided in the exhaust gas branch flow paths 21, 22, and 23, respectively. Each of the exhaust gas inlet valves 21a, 22a, and 23a controls the supply of exhaust gas to the inside of the adsorbers 11, 12, and 13 in response to a command from the control unit 55. In this embodiment, exhaust gas is exemplified as the carbon dioxide-containing gas, but the carbon dioxide-containing gas does not have to be exhaust gas.

混合ガス流路60は、図1に示すように、混合ガス分流路61、62、63を介して、吸着器11、12、13のそれぞれに接続されている。混合ガス流路60には、吸着材11a、12a、13aから脱離した二酸化炭素と、パージガスとしての水素を含む混合ガスが流れる。混合ガスには、例えば、窒素、酸素等が含まれる場合がある。混合ガス分流路61、62、63には、混合ガス出口弁61a、62a、63aが設けられている。混合ガス出口弁61a、62a、63aのそれぞれは、制御部55の指令に応じて、吸着器11、12、13からの混合ガスの流れを制御する。 As shown in FIG. 1, the mixed gas flow path 60 is connected to each of the adsorbers 11, 12, and 13 via mixed gas branch paths 61, 62, and 63. A mixed gas containing carbon dioxide desorbed from the adsorbents 11a, 12a, and 13a and hydrogen as a purge gas flows through the mixed gas flow path 60. The mixed gas may contain, for example, nitrogen, oxygen, etc. The mixed gas branch paths 61, 62, and 63 are provided with mixed gas outlet valves 61a, 62a, and 63a. The mixed gas outlet valves 61a, 62a, and 63a each control the flow of mixed gas from the adsorbers 11, 12, and 13 in response to a command from the control unit 55.

パージガス供給流路70は、吸着器11、12、13の内部に、パージガスを供給する。外部のパージガス供給部(例えば、水素タンク)に接続しているパージガス供給流路70には、制御部55の指令に応じて、パージガス供給流路70を流れる水素の流量を調整する流量制御器70aが設けられている。パージガス供給流路70を流れる水素は、パージガス分流路71、72、73を介して、吸着器11、12、13に供給される。パージガス分流路71、72、73には、それぞれ、パージガス入口弁71a、72a、73aが設けられている。パージガス入口弁71a、72a、73aのそれぞれは、制御部55の指令に応じて、吸着器11、12、13の内部への水素の流れを制御する。 The purge gas supply passage 70 supplies purge gas to the inside of the adsorbers 11, 12, and 13. The purge gas supply passage 70, which is connected to an external purge gas supply unit (e.g., a hydrogen tank), is provided with a flow rate controller 70a that adjusts the flow rate of hydrogen flowing through the purge gas supply passage 70 in response to a command from the control unit 55. The hydrogen flowing through the purge gas supply passage 70 is supplied to the adsorbers 11, 12, and 13 via purge gas branch passages 71, 72, and 73. The purge gas branch passages 71, 72, and 73 are provided with purge gas inlet valves 71a, 72a, and 73a, respectively. The purge gas inlet valves 71a, 72a, and 73a each control the flow of hydrogen into the inside of the adsorbers 11, 12, and 13 in response to a command from the control unit 55.

接続流路80は、2つの吸着器10を直列に接続し、一方の吸着器10から排出される混合ガス(パージガスと二酸化炭素を含む混合ガス)を他方の吸着器10に供給する。詳しくは、接続流路81は、混合ガス分流路61とパージガス分流路72とを接続して、吸着器11と吸着器12とを直列に接続する。接続流路82は、混合ガス分流路62とパージガス分流路73とを接続して、吸着器12と吸着器13とを直列に接続する。接続流路83は、混合ガス分流路63とパージガス分流路71とを接続して、吸着器13と吸着器11とを直列に接続する。すなわち、接続流路80はバイパス流路である。接続流路81、82、83には、それぞれ、接続流路弁81a、82a、83aが設けられている。接続流路弁81a、82a、83aのそれぞれは、制御部55の指令に応じて、接続流路80内のガスの流れを制御する。 The connection flow path 80 connects two adsorbers 10 in series, and supplies the mixed gas (mixed gas containing purge gas and carbon dioxide) discharged from one adsorber 10 to the other adsorber 10. In detail, the connection flow path 81 connects the mixed gas branch path 61 and the purge gas branch path 72 to connect the adsorber 11 and the adsorber 12 in series. The connection flow path 82 connects the mixed gas branch path 62 and the purge gas branch path 73 to connect the adsorber 12 and the adsorber 13 in series. The connection flow path 83 connects the mixed gas branch path 63 and the purge gas branch path 71 to connect the adsorber 13 and the adsorber 11 in series. In other words, the connection flow path 80 is a bypass flow path. The connection flow paths 81, 82, and 83 are provided with connection flow path valves 81a, 82a, and 83a, respectively. The connection flow path valves 81a, 82a, and 83a each control the flow of gas in the connection flow path 80 in response to a command from the control unit 55.

熱媒流路30は、図示せざる熱媒タンクに接続され、熱媒流路30内を熱媒が流れる。熱媒流路30を流れる熱媒は、熱媒分流路31、32、33を介して、吸着器11、12、13に供給される。これにより、熱媒により吸着器11、12、13に熱が投入される。熱媒流路30には、熱媒を加熱するヒータ30aが設けられており、制御部55がヒータ30aを制御することにより、熱媒の温度が制御される。本実施形態では、熱媒としてオイルを用いているが、他の実施形態では、水、スチーム、およびガスなどを用いてもよい。 The heat medium flow path 30 is connected to a heat medium tank (not shown), and the heat medium flows through the heat medium flow path 30. The heat medium flowing through the heat medium flow path 30 is supplied to the adsorbers 11, 12, and 13 via the heat medium distribution paths 31, 32, and 33. This causes heat to be input to the adsorbers 11, 12, and 13 by the heat medium. The heat medium flow path 30 is provided with a heater 30a that heats the heat medium, and the temperature of the heat medium is controlled by the control unit 55 controlling the heater 30a. In this embodiment, oil is used as the heat medium, but in other embodiments, water, steam, gas, etc. may be used.

熱媒分流路31、32、33には、熱媒入口弁31a、32a、33aが設けられている。熱媒入口弁31a、32a、33aのそれぞれは、制御部55の指令に応じて、吸着器11、12、13への熱媒の流れを制御する。本実施形態における吸着器11、12、13は、二重殻タンク(二重管)であり、熱媒は、外殻と内殻との間の間隙に流入する。これにより、熱媒により熱が吸着器11、12、13内に投入される。他の実施形態では、例えば、熱媒分流路31、32、33が、それぞれ、吸着器11、12、13の外周に巻き付けられていてもよい。このようにしても、熱媒により吸着器11、12、13内に熱を投入することができる。他の実施形態では、吸着器10に設けられたヒータ(例えば、電熱線、温風、光照射等)を用いて、吸着器10を加熱してもよい。 The heat medium distribution paths 31, 32, and 33 are provided with heat medium inlet valves 31a, 32a, and 33a. The heat medium inlet valves 31a, 32a, and 33a each control the flow of the heat medium to the adsorbers 11, 12, and 13 in response to a command from the control unit 55. In this embodiment, the adsorbers 11, 12, and 13 are double-shell tanks (double pipes), and the heat medium flows into the gap between the outer shell and the inner shell. As a result, heat is input into the adsorbers 11, 12, and 13 by the heat medium. In other embodiments, for example, the heat medium distribution paths 31, 32, and 33 may be wound around the outer periphery of the adsorbers 11, 12, and 13, respectively. Even in this way, heat can be input into the adsorbers 11, 12, and 13 by the heat medium. In other embodiments, the adsorber 10 may be heated using a heater (for example, a heating wire, hot air, light irradiation, etc.) provided in the adsorber 10.

サージタンク40には、混合ガス流路60が接続されている。サージタンク40は、混合ガス流路60を流れる混合ガスを貯蔵する。 The surge tank 40 is connected to the mixed gas flow path 60. The surge tank 40 stores the mixed gas flowing through the mixed gas flow path 60.

制御部55は、ROM、RAM、および、CPUを含んで構成されるコンピュータであり、後述するガス分離処理における吸着器11、12、13の切り替えや、弁の開閉制御など、ガス分離システム1の全体の制御をおこなう。制御部55の制御内容の詳細は、後述する。 The control unit 55 is a computer including a ROM, a RAM, and a CPU, and performs overall control of the gas separation system 1, including switching between the adsorbers 11, 12, and 13 in the gas separation process described below, and controlling the opening and closing of valves. The details of the control performed by the control unit 55 will be described later.

上述のガス分離処理を実現するプログラムは、制御部55に、予め記憶されていてもよい。また、プログラムはプログラム提供者側から通信ネットワークを介して、提供されてもよい。また、プログラムは、市販され、流通している可搬型記憶媒体に格納されていてもよい。この場合、この可搬型記憶媒体は外付け又は内蔵の読取装置にセットされて、制御部55によってそのプログラムが読み出されて、実行されてもよい。可搬型記憶媒体としてはCD-ROM、DVD-ROM、フレキシブルディスク、光ディスク、光磁気ディスク、ICカード、USBメモリ装置など様々な形式の記憶媒体を使用することができる。このような記憶媒体に格納されたプログラムが読取装置によって読み取られる。 The program for realizing the above-mentioned gas separation process may be pre-stored in the control unit 55. The program may also be provided by a program provider via a communication network. The program may also be stored in a commercially available portable storage medium. In this case, the portable storage medium may be set in an external or built-in reading device, and the program may be read and executed by the control unit 55. Various types of storage media can be used as the portable storage medium, such as CD-ROM, DVD-ROM, flexible disk, optical disk, magneto-optical disk, IC card, and USB memory device. The program stored in such a storage medium is read by the reading device.

図2は、本実施形態のガス分離システム1における吸着器10の切替タイミングの説明図である。本実施形態のガス分離処理では、図示するように、工程1、工程2、および工程3を1サイクルとして、このサイクルが、複数回繰り返される。各工程では、吸着工程、第2脱離工程(加熱+脱離)、および第1脱離工程のそれぞれが、3つの吸着器11、12、および13のいずれかにおいて実行される。具体的には、工程1では、吸着器13において吸着工程が実行され、吸着器11において第1脱離工程が実行され、吸着器12において第2脱離工程が実行される。工程2では、吸着器11において吸着工程が実行され、吸着器12において第1脱離工程が実行され、吸着器13において第2脱離工程が実行される。工程3では、吸着器12において吸着工程が実行され、吸着器13において第1脱離工程が実行され、吸着器11において第2脱離工程が実行される。本実施形態のガス分離システム1では、このようにして、いずれか1つの吸着器において排ガス中の二酸化炭素を吸着すると同時に、他の2つの吸着器において、吸着された二酸化炭素を脱離する。これにより、定常的に、二酸化炭素含有ガス(排ガス)を供給することが可能である。本実施形態における工程1、2、3のそれぞれを「吸脱着工程」とも呼ぶ。 Figure 2 is an explanatory diagram of the switching timing of the adsorber 10 in the gas separation system 1 of this embodiment. In the gas separation process of this embodiment, as shown in the figure, step 1, step 2, and step 3 constitute one cycle, and this cycle is repeated multiple times. In each step, the adsorption step, the second desorption step (heating + desorption), and the first desorption step are each performed in one of the three adsorber 11, 12, and 13. Specifically, in step 1, the adsorption step is performed in the adsorber 13, the first desorption step is performed in the adsorber 11, and the second desorption step is performed in the adsorber 12. In step 2, the adsorption step is performed in the adsorber 11, the first desorption step is performed in the adsorber 12, and the second desorption step is performed in the adsorber 13. In step 3, the adsorption step is performed in the adsorber 12, the first desorption step is performed in the adsorber 13, and the second desorption step is performed in the adsorber 11. In this manner, in the gas separation system 1 of this embodiment, carbon dioxide in the exhaust gas is adsorbed in one of the adsorbers, while the adsorbed carbon dioxide is desorbed in the other two adsorbers. This makes it possible to steadily supply carbon dioxide-containing gas (exhaust gas). Each of steps 1, 2, and 3 in this embodiment is also referred to as an "adsorption/desorption step."

1つの吸着器10に注目すると、吸着工程、第2脱離工程、第1脱離工程が、この順に繰り返し行われる。以下に、吸着器13を例に、説明する。吸着工程では、吸着器13に二酸化炭素含有ガスとしての排ガスが供給されると共に、冷媒が供給される。吸着器13を冷却することにより、排ガス中の二酸化炭素が吸着材13aに吸着される。所定の吸着時間が経過すると、第2脱離工程に移行する。本実施形態において、吸着時間は、吸着器13の吸着材13aに満量の二酸化炭素が吸着されるのに要する時間に設定されている。吸着時間は、実験的、計算、シミュレーション等によって、求めることができる。本実施形態のガス分離処理において、各工程の長さは、同一の吸着時間に設定されている。 Focusing on one adsorber 10, the adsorption process, the second desorption process, and the first desorption process are repeated in this order. The following describes the adsorber 13 as an example. In the adsorption process, exhaust gas as a carbon dioxide-containing gas is supplied to the adsorber 13, and a refrigerant is also supplied. By cooling the adsorber 13, the carbon dioxide in the exhaust gas is adsorbed by the adsorbent 13a. When a predetermined adsorption time has elapsed, the process moves to the second desorption process. In this embodiment, the adsorption time is set to the time required for the full amount of carbon dioxide to be adsorbed by the adsorbent 13a of the adsorber 13. The adsorption time can be obtained by experiment, calculation, simulation, etc. In the gas separation process of this embodiment, the length of each process is set to the same adsorption time.

第2脱離工程では、吸着器13に熱媒が供給されると共に、パージガスとしての水素が供給される。吸着器13に熱媒が供給され、吸着材13aが昇温されると、吸着材13aにトラップされている二酸化炭素が吸着材13aから脱離しやすくなる。第2脱離工程では、第1脱離工程が行われている吸着器12(図2の工程2)から排出された二酸化炭素とパージガス(本実施形態では水素)とを含む混合ガスが吸着器13に供給される。すなわち、接続流路82(図1)を介してパージガスが供給される。吸着器13にパージガスを含む混合ガスが供給されると、吸着器13の内部の二酸化炭素の分圧が低下するため、吸着材13aに吸着されている二酸化炭素が吸着材13aから脱離する。吸着時間が経過すると、第1脱離工程に移行する。 In the second desorption step, the adsorber 13 is supplied with a heat medium and hydrogen as a purge gas. When the adsorber 13 is supplied with a heat medium and the adsorbent 13a is heated, the carbon dioxide trapped in the adsorbent 13a is easily desorbed from the adsorbent 13a. In the second desorption step, a mixed gas containing carbon dioxide discharged from the adsorber 12 (step 2 in FIG. 2) in which the first desorption step is being performed and a purge gas (hydrogen in this embodiment) is supplied to the adsorber 13. That is, the purge gas is supplied through the connection flow path 82 (FIG. 1). When the mixed gas containing the purge gas is supplied to the adsorber 13, the partial pressure of carbon dioxide inside the adsorber 13 decreases, so that the carbon dioxide adsorbed to the adsorbent 13a is desorbed from the adsorbent 13a. After the adsorption time has elapsed, the process proceeds to the first desorption step.

第1脱離工程では、吸着器13に、パージガス供給流路70を介してパージガスが供給される。すなわち、第1脱離工程では、外部のパージガス供給部(例えば、水素タンク)からパージガスが供給される。吸着器13は、第2脱離工程において加熱されているため(図2)、吸着材13aから二酸化炭素が脱離しやすい状態になっている。吸着器13にパージガスが供給されると、吸着器13の内部の二酸化炭素の分圧が低下するため、吸着材13aに吸着されている二酸化炭素が吸着材13aから脱離する。吸着時間が経過すると、吸着工程に戻る。 In the first desorption step, purge gas is supplied to the adsorber 13 via the purge gas supply passage 70. That is, in the first desorption step, purge gas is supplied from an external purge gas supply unit (e.g., a hydrogen tank). Since the adsorber 13 is heated in the second desorption step (FIG. 2), it is in a state in which carbon dioxide is easily desorbed from the adsorbent 13a. When the purge gas is supplied to the adsorber 13, the partial pressure of carbon dioxide inside the adsorber 13 decreases, and the carbon dioxide adsorbed to the adsorbent 13a is desorbed from the adsorbent 13a. After the adsorption time has elapsed, the process returns to the adsorption step.

図3は、ガス分離システム1における工程1の説明図であり、図4は、ガス分離システム1における工程2の説明図であり、図5は、ガス分離システム1における工程3の説明図である。ガス分離システム1では、3つの吸着器11、12、13のそれぞれに、順番に排ガス(二酸化炭素含有ガス)を供給することにより、排ガスから二酸化炭素を分離する。ガス分離システム1では、2つの吸着器10が、接続流路80を介して直列に接続される。そして、第1脱離工程が実行される吸着器10を流通したパージガスが第2脱離工程が実行される吸着器10に供給される。ここで、第2脱離工程の吸着器10では、熱媒が供給されて加熱されると共に、パージガス(混合ガス)が供給される。図3~5において、排ガス、熱媒、パージガス(水素)の流れを太い実線で示している。 Figure 3 is an explanatory diagram of step 1 in the gas separation system 1, Figure 4 is an explanatory diagram of step 2 in the gas separation system 1, and Figure 5 is an explanatory diagram of step 3 in the gas separation system 1. In the gas separation system 1, exhaust gas (carbon dioxide-containing gas) is supplied to each of the three adsorbers 11, 12, and 13 in order to separate carbon dioxide from the exhaust gas. In the gas separation system 1, the two adsorbers 10 are connected in series via a connecting flow path 80. Then, the purge gas that has flowed through the adsorber 10 in which the first desorption step is performed is supplied to the adsorber 10 in which the second desorption step is performed. Here, in the adsorber 10 in the second desorption step, a heat medium is supplied and heated, and a purge gas (mixed gas) is supplied. In Figures 3 to 5, the flows of the exhaust gas, heat medium, and purge gas (hydrogen) are indicated by thick solid lines.

図3に示すように、工程1(図2)では、吸着器13で吸着工程が行われ、吸着器13に排ガスが供給される。具体的には、制御部55により排ガス入口弁23aが開弁されると共に、排ガス入口弁21aおよび排ガス入口弁22aが閉弁され、二酸化炭素含有ガス供給流路20および排ガス分流路23を介して、吸着器13に排ガスが供給される。吸着器13では、排ガスに含まれる二酸化炭素が吸着材13aによってトラップされ、吸着材13aにトラップされなかった窒素や水分などの大部分のガスは、オフガスとして、ガス分離システム1の外部、例えば、大気に放出される。 As shown in FIG. 3, in step 1 (FIG. 2), an adsorption process is performed in the adsorber 13, and exhaust gas is supplied to the adsorber 13. Specifically, the controller 55 opens the exhaust gas inlet valve 23a, closes the exhaust gas inlet valve 21a and the exhaust gas inlet valve 22a, and supplies exhaust gas to the adsorber 13 via the carbon dioxide-containing gas supply passage 20 and the exhaust gas branch passage 23. In the adsorber 13, the carbon dioxide contained in the exhaust gas is trapped by the adsorbent 13a, and most of the gases such as nitrogen and moisture that are not trapped by the adsorbent 13a are released as off-gas to the outside of the gas separation system 1, for example, to the atmosphere.

吸着器11で第1脱離工程が行われ、吸着器11にパージガスが供給される。具体的には、制御部55によりパージガス入口弁71aが開弁されると共に、パージガス入口弁72aおよびパージガス入口弁73aが閉弁され、パージガス供給流路70およびパージガス分流路71を介して、吸着器11にパージガスが供給される。吸着器11においてパージガスが供給されると、吸着材11aに吸着されている二酸化炭素が吸着材11aから脱離する。吸着材11aから脱離した二酸化炭素は、吸着器11の内部においてパージガス(水素)と混合される。工程1において、混合ガス出口弁61aが閉弁されると共に、接続流路弁81aが開弁されているため、吸着器11から排出される混合ガスは、混合ガス分流路61、接続流路81、およびパージガス分流路72を通って、吸着器12に流入する。 The first desorption step is performed in the adsorber 11, and purge gas is supplied to the adsorber 11. Specifically, the control unit 55 opens the purge gas inlet valve 71a, closes the purge gas inlet valve 72a and the purge gas inlet valve 73a, and supplies the purge gas to the adsorber 11 through the purge gas supply passage 70 and the purge gas branch passage 71. When the purge gas is supplied to the adsorber 11, the carbon dioxide adsorbed to the adsorbent 11a is desorbed from the adsorbent 11a. The carbon dioxide desorbed from the adsorbent 11a is mixed with the purge gas (hydrogen) inside the adsorber 11. In step 1, the mixed gas outlet valve 61a is closed, and the connection passage valve 81a is opened, so that the mixed gas discharged from the adsorber 11 flows into the adsorber 12 through the mixed gas branch passage 61, the connection passage 81, and the purge gas branch passage 72.

吸着器12で第2脱離工程が行われ、吸着器12に熱媒と上述の混合ガスが供給される。具体的には、制御部55により熱媒が所定の温度(投入熱量)になるようにヒータ30aが制御されると共に、熱媒入口弁32aが開弁される。これにより、熱媒流路30を流れる熱媒は、熱媒分流路32を介して、吸着器12に供給される。吸着器12において、熱媒が供給されると共に、パージガスを含む混合ガスが供給されると、吸着材12aに吸着されている二酸化炭素が吸着材12aから脱離する。吸着材12aから脱離した二酸化炭素は、吸着器12の内部においてパージガスを含む混合ガスと混合される。工程1において、混合ガス出口弁62aが開弁されているため、吸着器12から排出される混合ガスは、混合ガス分流路62および混合ガス流路60を通ってサージタンク40に貯留される。第1脱離工程が行われる吸着器10を「第1吸着器」、第2脱離工程が行われる吸着器10を「第2吸着器」、吸着工程が行われる吸着器10を「第3吸着器」と呼ぶとき、工程1において、吸着器11が「第1吸着器」、吸着器12が「第2吸着器」、吸着器13が「第3吸着器」である。 The second desorption step is performed in the adsorber 12, and the heat medium and the above-mentioned mixed gas are supplied to the adsorber 12. Specifically, the control unit 55 controls the heater 30a so that the heat medium reaches a predetermined temperature (input heat amount), and the heat medium inlet valve 32a is opened. As a result, the heat medium flowing through the heat medium flow path 30 is supplied to the adsorber 12 via the heat medium branch flow path 32. When the heat medium is supplied to the adsorber 12 and the mixed gas containing the purge gas is supplied, the carbon dioxide adsorbed to the adsorbent 12a is desorbed from the adsorbent 12a. The carbon dioxide desorbed from the adsorbent 12a is mixed with the mixed gas containing the purge gas inside the adsorber 12. In step 1, since the mixed gas outlet valve 62a is open, the mixed gas discharged from the adsorber 12 passes through the mixed gas branch flow path 62 and the mixed gas flow path 60 and is stored in the surge tank 40. When the adsorber 10 in which the first desorption step is performed is called the "first adsorber," the adsorber 10 in which the second desorption step is performed is called the "second adsorber," and the adsorber 10 in which the adsorption step is performed is called the "third adsorber," in step 1, adsorber 11 is the "first adsorber," adsorber 12 is the "second adsorber," and adsorber 13 is the "third adsorber."

図4に示すように、工程2では、吸着器11で吸着工程が行われ、吸着器11に、二酸化炭素含有ガス供給流路20および排ガス分流路21を介して、排ガスが供給される。吸着器12で第1脱離工程が行われ、吸着器12には、パージガス供給流路70およびパージガス分流路72を介してパージガスが供給される。吸着器13で第2脱離工程が行われ、吸着器13に、混合ガス分流路62、接続流路82、およびパージガス分流路73を介して、吸着器12から排出される二酸化炭素とパージガスを含む混合ガスが、供給される。吸着器13から排出される混合ガスは、混合ガス分流路63および混合ガス流路60を通ってサージタンク40に貯留される。工程2において、吸着器11が「第3吸着器」、吸着器12が「第1吸着器」、吸着器13が「第2吸着器」である。 As shown in FIG. 4, in step 2, the adsorption step is performed in the adsorber 11, and exhaust gas is supplied to the adsorber 11 through the carbon dioxide-containing gas supply flow path 20 and the exhaust gas branch flow path 21. The first desorption step is performed in the adsorber 12, and purge gas is supplied to the adsorber 12 through the purge gas supply flow path 70 and the purge gas branch flow path 72. The second desorption step is performed in the adsorber 13, and the adsorbent 13 is supplied with a mixed gas containing carbon dioxide and purge gas discharged from the adsorber 12 through the mixed gas branch flow path 62, the connection flow path 82, and the purge gas branch flow path 73. The mixed gas discharged from the adsorber 13 is stored in the surge tank 40 through the mixed gas branch flow path 63 and the mixed gas flow path 60. In step 2, the adsorber 11 is the "third adsorber", the adsorber 12 is the "first adsorber", and the adsorber 13 is the "second adsorber".

図5に示すように、工程3では、吸着器12で吸着工程が行われ、吸着器12に、二酸化炭素含有ガス供給流路20および排ガス分流路22を介して、排ガスが供給される。吸着器13で第1脱離工程が行われ、吸着器13には、パージガス供給流路70およびパージガス分流路73を介してパージガスが供給される。吸着器11で第2脱離工程が行われ、吸着器11には、混合ガス分流路63、接続流路83、およびパージガス分流路71を介して、吸着器13から排出される二酸化炭素とパージガスを含む混合ガスが供給される。吸着器11から排出される混合ガスは、混合ガス分流路61および混合ガス流路60を通ってサージタンク40に貯留される。工程3において、吸着器11が「第2吸着器」、吸着器12が「第3吸着器」、吸着器13が「第1吸着器」である。すなわち、本実施形態のガス分離システム1において、制御部55は、第1吸着器、第2吸着器、および第3吸着器を変更して、吸脱着工程を繰り返し実行している。 As shown in FIG. 5, in step 3, the adsorption step is performed in the adsorber 12, and exhaust gas is supplied to the adsorber 12 through the carbon dioxide-containing gas supply flow path 20 and the exhaust gas branch flow path 22. The first desorption step is performed in the adsorber 13, and purge gas is supplied to the adsorber 13 through the purge gas supply flow path 70 and the purge gas branch flow path 73. The second desorption step is performed in the adsorber 11, and the adsorber 11 is supplied with a mixed gas containing carbon dioxide and purge gas discharged from the adsorber 13 through the mixed gas branch flow path 63, the connection flow path 83, and the purge gas branch flow path 71. The mixed gas discharged from the adsorber 11 is stored in the surge tank 40 through the mixed gas branch flow path 61 and the mixed gas flow path 60. In step 3, the adsorber 11 is the "second adsorber", the adsorber 12 is the "third adsorber", and the adsorber 13 is the "first adsorber". That is, in the gas separation system 1 of this embodiment, the control unit 55 repeatedly performs the adsorption and desorption process by changing the first adsorption device, the second adsorption device, and the third adsorption device.

図6は、工程1~工程3の開始時の二酸化炭素の吸着量を概念的に示す説明図である。図6では、二酸化炭素の吸着量をドットハッチングを付して示している。図6において、吸着器10の全体にハッチングが付してあると、二酸化炭素の吸着量が100%であることを示し、吸着器10にハッチングが付してないと、二酸化炭素の吸着量が0%であることを示す。ここで、100%とは、吸着工程終了時時に吸着器10に吸着されている量である。上述の通り、本実施形態のガス分離システム1では、1つの吸着器10に注目してみると、吸着工程→第2脱離工程→脱離工程を1サイクルとして、複数サイクルが繰り返される(図2)。図6では、複数サイクルが行われた後の1サイクルを例示している。 Figure 6 is an explanatory diagram conceptually showing the amount of carbon dioxide adsorption at the start of steps 1 to 3. In Figure 6, the amount of carbon dioxide adsorption is shown with dot hatching. In Figure 6, if the entire adsorber 10 is hatched, it indicates that the amount of carbon dioxide adsorption is 100%, and if the adsorber 10 is not hatched, it indicates that the amount of carbon dioxide adsorption is 0%. Here, 100% is the amount adsorbed in the adsorber 10 at the end of the adsorption step. As described above, in the gas separation system 1 of this embodiment, when focusing on one adsorber 10, multiple cycles are repeated, with one cycle being the adsorption step → second desorption step → desorption step (Figure 2). Figure 6 illustrates one cycle after multiple cycles have been performed.

図6(A)に示すように、工程1の開始時、吸着器13の吸着材13aには二酸化炭素が吸着されておらず(二酸化炭素の吸着量0%)、吸着器11の吸着材11aと吸着器12の吸着材12aには二酸化炭素が吸着されている。吸着器12における二酸化炭素の吸着量は100%であり、吸着器11における吸着量は、吸着器12より少ない(例えば、10%程度)。吸着器11は直前の工程3で第2脱離工程が行われており、吸着材11aが昇温された状態で、かつ一部の二酸化炭素が脱離された状態である。 As shown in FIG. 6(A), at the start of step 1, no carbon dioxide is adsorbed to the adsorbent 13a of the adsorber 13 (0% carbon dioxide adsorption), and carbon dioxide is adsorbed to the adsorbent 11a of the adsorber 11 and the adsorbent 12a of the adsorber 12. The amount of carbon dioxide adsorbed in the adsorber 12 is 100%, and the amount of carbon dioxide adsorbed in the adsorber 11 is less than that of the adsorber 12 (for example, about 10%). The adsorber 11 has undergone the second desorption step in the immediately preceding step 3, and is in a state in which the adsorbent 11a has been heated and some of the carbon dioxide has been desorbed.

工程1では、吸着器11にパージガスが供給され、吸着器13に二酸化炭素含有ガスが供給される。吸着器11と吸着器12が直列に接続されており、吸着器11内を流通したパージガスと、吸着器11内の吸着材11aから脱離した二酸化炭素を含む混合ガスが、吸着器12に流入する。 In step 1, a purge gas is supplied to the adsorber 11, and a carbon dioxide-containing gas is supplied to the adsorber 13. The adsorber 11 and the adsorber 12 are connected in series, and a mixed gas containing the purge gas that has flowed through the adsorber 11 and the carbon dioxide desorbed from the adsorbent 11a in the adsorber 11 flows into the adsorber 12.

工程1において、吸着器11の吸着材11aに吸着されている二酸化炭素が全て脱離されるため、工程2の開始時、吸着器11における二酸化炭素の吸着量は0%である。すなわち、吸着器11には二酸化炭素が吸着されていない(図6(B))。また、工程1において吸着器12に供給される混合ガスにはパージガスが含まれおり、工程1において吸着器12の吸着材12aに吸着されている二酸化炭素の一部が脱離されるため、工程2の開始時、吸着器12における二酸化炭素の吸着量は少量(例えば、10%程度)である(図6(B))。また、工程1では、吸着器13に二酸化炭素含有ガスが供給され、吸着材13aに二酸化炭素が吸着されるため、工程2の開始時、吸着器13における二酸化炭素の吸着量は100%である(図6(B))。 In step 1, all of the carbon dioxide adsorbed to the adsorbent 11a of the adsorber 11 is desorbed, so that at the start of step 2, the amount of carbon dioxide adsorbed in the adsorber 11 is 0%. That is, no carbon dioxide is adsorbed in the adsorber 11 (FIG. 6(B)). In addition, the mixed gas supplied to the adsorber 12 in step 1 contains purge gas, and some of the carbon dioxide adsorbed to the adsorbent 12a of the adsorber 12 in step 1 is desorbed, so that at the start of step 2, the amount of carbon dioxide adsorbed in the adsorber 12 is small (for example, about 10%) (FIG. 6(B)). In addition, in step 1, a carbon dioxide-containing gas is supplied to the adsorber 13, and carbon dioxide is adsorbed to the adsorbent 13a, so that at the start of step 2, the amount of carbon dioxide adsorbed in the adsorber 13 is 100% (FIG. 6(B)).

図6(B)に示すように、工程2では、吸着器12にパージガスが供給され、吸着器11に二酸化炭素含有ガスが供給される。吸着器12と吸着器13が直列に接続されており、吸着器12内を流通したパージガスと、吸着器12内の吸着材12aから脱離した二酸化炭素を含む混合ガスが、吸着器13に流入する。 As shown in FIG. 6(B), in step 2, purge gas is supplied to the adsorber 12, and carbon dioxide-containing gas is supplied to the adsorber 11. The adsorber 12 and the adsorber 13 are connected in series, and the purge gas that has flowed through the adsorber 12 and the mixed gas containing carbon dioxide desorbed from the adsorbent 12a in the adsorber 12 flow into the adsorber 13.

工程2において、吸着器12の吸着材12aに吸着されている残りの二酸化炭素の全てが脱離されるため、工程3の開始時、吸着器12における二酸化炭素の吸着量は0%である。すなわち、吸着器12には二酸化炭素が吸着されていない(図6(C))。また、工程2において吸着器13に供給される混合ガスにはパージガスが含まれおり、工程2において吸着器13の吸着材13aに吸着されている二酸化炭素の一部が脱離されるため、工程3の開始時、吸着器13における二酸化炭素の吸着量は少量(例えば、10%程度)である(図6(C))。また、工程2では、吸着器11に二酸化炭素含有ガスが供給され、吸着材11aに二酸化炭素が吸着されるため、工程3の開始時、吸着器11における二酸化炭素の吸着量は100%である(図6(C))。

In step 2, all of the remaining carbon dioxide adsorbed in the adsorbent 12a of the adsorber 12 is desorbed, so that at the start of step 3, the amount of carbon dioxide adsorbed in the adsorber 12 is 0%. That is, no carbon dioxide is adsorbed in the adsorber 12 (FIG. 6(C)). In addition, the mixed gas supplied to the adsorber 13 in step 2 contains purge gas, and a part of the carbon dioxide adsorbed in the adsorbent 13a of the adsorber 13 in step 2 is desorbed, so that at the start of step 3, the amount of carbon dioxide adsorbed in the adsorber 13 is small (for example, about 10%) (FIG. 6(C)). In addition, in step 2, a carbon dioxide-containing gas is supplied to the adsorber 11, and carbon dioxide is adsorbed in the adsorbent 11a, so that at the start of step 3, the amount of carbon dioxide adsorbed in the adsorber 11 is 100% (FIG. 6(C)).

このように、工程1、2、3を1サイクルとして繰り返すことにより、各吸着器10において、吸着工程→第2脱離工程(加熱+脱離)→第1脱離工程が繰り返し行われる。上述の通り、第2脱離工程(加熱+脱離)において、吸着器10に吸着された二酸化炭素の多くを脱離させることができ、続く第1脱離工程により、残りの二酸化炭素を脱離させることができるため、各吸着材に吸着された二酸化炭素の全てを脱離させることができる。 In this way, by repeating steps 1, 2, and 3 as one cycle, the adsorption step → second desorption step (heating + desorption) → first desorption step are repeated in each adsorber 10. As described above, most of the carbon dioxide adsorbed in the adsorber 10 can be desorbed in the second desorption step (heating + desorption), and the remaining carbon dioxide can be desorbed in the subsequent first desorption step, so that all of the carbon dioxide adsorbed in each adsorbent can be desorbed.

以上説明したように、本実施形態のガス分離システム1では、2つの吸着器10を直列に接続し、1つの吸着器10内を流通して二酸化炭素を脱離させたパージガスを用いて、後段の吸着器10内の二酸化炭素を脱離させている。すなわち、パージガスを再利用しているため、パージガスによる二酸化炭素脱離効率を向上させることができる。 As described above, in the gas separation system 1 of this embodiment, two adsorbers 10 are connected in series, and the purge gas that has been circulated through one of the adsorbers 10 and desorbed carbon dioxide is used to desorb carbon dioxide in the subsequent adsorber 10. In other words, because the purge gas is reused, the efficiency of carbon dioxide desorption by the purge gas can be improved.

次に、本実施形態の効果について、比較例と比較して説明する。
図7は、比較例のガス分離システム1Pの概略構成を示す説明図である。比較例のガス分離システム1Pは、本実施形態のガス分離システム1における接続流路80(接続流路81、82、83)を有さない。ガス分離システム1Pは、他の構成は本実施形態のガス分離システム1と同一である。以下、ガス分離システム1と同一の構成には同一の符号を付し、先行する説明を参照する。
Next, the effects of this embodiment will be described in comparison with a comparative example.
7 is an explanatory diagram showing a schematic configuration of a gas separation system 1P of a comparative example. The gas separation system 1P of the comparative example does not have the connection flow path 80 (connection flow paths 81, 82, 83) in the gas separation system 1 of the present embodiment. The gas separation system 1P has the same configuration as the gas separation system 1 of the present embodiment in other respects. Hereinafter, the same reference numerals are used for the same configuration as the gas separation system 1, and the preceding description will be referred to.

図8は、比較例のガス分離システム1Pにおける吸着器10の切替タイミングの説明図である。比較例のガス分離処理では、上記実施形態と同様に、工程1P、工程2P、および工程3Pを1サイクルとして、このサイクルが、複数回繰り返される。比較例のガス分離システム1Pにおいて行われる各工程では、吸着工程、加熱工程、および脱離工程のそれぞれが、3つの吸着器11、12、および13のいずれかにおいて実行される。具体的には、工程1Pでは、吸着器13において吸着工程が実行され、吸着器12において加熱工程が実行され、吸着器11において脱離工程が実行される。工程2Pでは、吸着器11において吸着工程が実行され、吸着器13において加熱工程が実行され、吸着器12において脱離工程が実行される。工程3Pでは、吸着器12において吸着工程が実行され、吸着器11において加熱工程が実行され、吸着器13において脱離工程が実行される。比較例のガス分離システム1Pでは、このようにして、いずれか1つの吸着器10において二酸化炭素含有ガス(排ガス)中の二酸化炭素を吸着すると同時に、他の1つの吸着器10を加熱して吸着材を昇温させ、加熱済みの他の1つの吸着器10において、吸着された二酸化炭素を脱離する。 Figure 8 is an explanatory diagram of the switching timing of the adsorber 10 in the gas separation system 1P of the comparative example. In the gas separation process of the comparative example, as in the above embodiment, step 1P, step 2P, and step 3P are one cycle, and this cycle is repeated multiple times. In each step performed in the gas separation system 1P of the comparative example, the adsorption step, heating step, and desorption step are each performed in one of the three adsorber 11, 12, and 13. Specifically, in step 1P, the adsorption step is performed in the adsorber 13, the heating step is performed in the adsorber 12, and the desorption step is performed in the adsorber 11. In step 2P, the adsorption step is performed in the adsorber 11, the heating step is performed in the adsorber 13, and the desorption step is performed in the adsorber 12. In step 3P, the adsorption step is performed in the adsorber 12, the heating step is performed in the adsorber 11, and the desorption step is performed in the adsorber 13. In this way, in the comparative gas separation system 1P, carbon dioxide in the carbon dioxide-containing gas (exhaust gas) is adsorbed in one of the adsorbers 10, while the other adsorber 10 is heated to raise the temperature of the adsorbent, and the adsorbed carbon dioxide is desorbed in the other heated adsorber 10.

図9は、本実施形態のガス分離システム1の脱離工程における二酸化炭素吸着量の変化を示す図である。図9では、図2に示す工程1における吸着器11(第1脱離工程)と、吸着器12(第2脱離工程)における二酸化炭素吸着量を例示する。図9において、第1脱離工程を実線で示し、第2脱離工程を破線で示す。この例では、1工程の時間を2000秒として設計している。吸着器12は、前の工程(工程3)において、吸着工程が行われているため、図9に示す工程1の開始時の吸着量は、100%である。吸着器11は、前の工程(工程3)において、第2脱離工程(加熱+脱離)が行われており、90%程度が脱離されているため、二酸化炭素吸着量は、10%程度である。この例では、吸着器11に、満量の二酸化炭素と過不足なく反応する量のパージガスを流入させた。吸着器11と吸着器12とを直列に接続し、吸着器11から排出された混合ガスを吸着器12に供給し、排出させた。その結果、図示するように、吸着器11の二酸化炭素吸着量は、ほぼ0になり、吸着器12の二酸化炭素吸着量は、約10%になった。 Figure 9 is a diagram showing the change in the amount of carbon dioxide adsorption in the desorption process of the gas separation system 1 of this embodiment. Figure 9 illustrates the amount of carbon dioxide adsorption in the adsorber 11 (first desorption process) and the adsorber 12 (second desorption process) in process 1 shown in Figure 2. In Figure 9, the first desorption process is shown by a solid line, and the second desorption process is shown by a dashed line. In this example, the time for one process is designed to be 2000 seconds. Since the adsorber 12 has undergone the adsorption process in the previous process (process 3), the amount of adsorption at the start of process 1 shown in Figure 9 is 100%. Since the adsorber 11 has undergone the second desorption process (heating + desorption) in the previous process (process 3), and about 90% has been desorbed, the amount of carbon dioxide adsorption is about 10%. In this example, a purge gas in an amount that reacts with the full amount of carbon dioxide without excess or deficiency was flowed into the adsorber 11. Adsorbers 11 and 12 were connected in series, and the mixed gas discharged from adsorber 11 was supplied to adsorber 12 and discharged. As a result, as shown in the figure, the amount of carbon dioxide adsorbed by adsorber 11 was almost 0, and the amount of carbon dioxide adsorbed by adsorber 12 was about 10%.

このように、吸着器11における二酸化炭素の脱離に用いられたパージガスを再利用して吸着器12内の二酸化炭素を脱離させることにより、全ての二酸化炭素を吸着器12から脱離させることができた。 In this way, all of the carbon dioxide was desorbed from the adsorber 12 by reusing the purge gas used to desorb the carbon dioxide in the adsorber 11.

図10は、比較例のガス分離システム1Pの脱離工程における二酸化炭素吸着量の変化を示す図である。図10では、図8に示す工程1Pにおける吸着器11の二酸化炭素吸着量を例示する。この例でも、図9に示す例と同様に、1工程の時間を2000秒として設計している。吸着器11は、工程2において吸着工程が行われた後、工程3において加熱工程が行われており、図10に示す工程1の開始時の吸着量は、100%であり、二酸化炭素が脱離しやすい状態になっている。この例では、吸着器11に、満量の二酸化炭素と過不足なく反応する量のパージガスを、1工程の時間(2000秒)で流入させ、引き続き、1工程の時間(2000秒)、同量のパージガスを流して、排出させた。図示するように、吸着器11の二酸化炭素吸着量は、3500秒から4000秒で0%になるものの、2000秒(1工程終了時)では、7%程度の二酸化炭素が残留している。上記の通り、比較例のガス分離システム1Pは、各吸着器10において、1~3工程が順次実行されるため(図8)、脱離工程の時間を延長することができない。そのため、脱離工程の終了時、吸着器10には7%程度の二酸化炭素が残留する。1工程の時間を変更せず、脱離工程において全ての二酸化炭素を脱離させるには、例えば、外部から吸着器10を加熱するエネルギーを増加させる、吸着器10の出口を真空ポンプにつなぐ等、さらに外部エネルギーを投入して脱離を早めなければならない。 Figure 10 is a diagram showing the change in the amount of carbon dioxide adsorption in the desorption process of the gas separation system 1P of the comparative example. Figure 10 illustrates the amount of carbon dioxide adsorption in the adsorber 11 in the process 1P shown in Figure 8. In this example, as in the example shown in Figure 9, the time for one process is designed to be 2000 seconds. In the adsorber 11, the adsorption process is performed in process 2, and then the heating process is performed in process 3. The amount of adsorption at the start of process 1 shown in Figure 10 is 100%, and the state is such that carbon dioxide is easily desorbed. In this example, a purge gas in an amount that reacts with the full amount of carbon dioxide without excess or deficiency is flowed into the adsorber 11 for one process time (2000 seconds), and the same amount of purge gas is subsequently flowed and discharged for one process time (2000 seconds). As shown in the figure, the amount of carbon dioxide adsorption in the adsorber 11 becomes 0% from 3500 seconds to 4000 seconds, but about 7% of carbon dioxide remains at 2000 seconds (at the end of one process). As described above, in the gas separation system 1P of the comparative example, steps 1 to 3 are performed sequentially in each adsorber 10 (FIG. 8), so the time for the desorption step cannot be extended. Therefore, at the end of the desorption step, about 7% of the carbon dioxide remains in the adsorber 10. In order to desorb all of the carbon dioxide in the desorption step without changing the time for one step, it is necessary to input further external energy to hasten the desorption, for example by increasing the energy used to heat the adsorber 10 from the outside or by connecting the outlet of the adsorber 10 to a vacuum pump.

以上説明したように、本実施形態のガス分離システム1によれば、1つの吸着器10を通過したパージガスを再利用して、別の吸着器10に流入させることができるため、2つの吸着器10を、同時に脱離させることができる。1つめの吸着器10内の二酸化炭素を脱離させて排出された、パージガスと二酸化炭素を含む混合ガスは、脱離工程開始直後は二酸化炭素の濃度が高いが、その後徐々に二酸化炭素濃度が下がる。この混合ガスを2つめの吸着器10に流入させると、2つめの吸着器10内の二酸化炭素も脱離が可能になる。1つの吸着器10に注目すると、第2脱離工程と第1脱離工程の2工程で二酸化炭素の脱離を行うことにより、疑似的にパージガス量を増やし、脱離時間を長くすることができた。本実施形態のガス分離システム1において、実際には、パージガス量も1工程の時間も比較例と同じであるため、比較例と比べてパージガスによる二酸化炭素の脱離効率を向上させることができたといえる。 As described above, according to the gas separation system 1 of this embodiment, the purge gas that has passed through one adsorber 10 can be reused and flowed into another adsorber 10, so that the two adsorber 10 can be desorbed simultaneously. The mixed gas containing the purge gas and carbon dioxide that is discharged after desorbing the carbon dioxide in the first adsorber 10 has a high carbon dioxide concentration immediately after the start of the desorption process, but the carbon dioxide concentration gradually decreases thereafter. When this mixed gas is flowed into the second adsorber 10, the carbon dioxide in the second adsorber 10 can also be desorbed. Focusing on one adsorber 10, the amount of purge gas was increased artificially and the desorption time was extended by desorbing carbon dioxide in two steps, the second desorption step and the first desorption step. In the gas separation system 1 of this embodiment, the amount of purge gas and the time for one step are actually the same as in the comparative example, so it can be said that the efficiency of desorption of carbon dioxide by the purge gas has been improved compared to the comparative example.

また、本実施形態のガス分離システム1によれば、2つの吸着器10を接続し、パージガスを再利用することにより、外部から吸着器10を加熱するエネルギーを増加させる、吸着器10の出口を真空ポンプにつなぐ等、追加で外部エネルギーを投入することなく、二酸化炭素の脱離効率を向上させることができるため、エネルギー効率の低下を抑制することができる。 In addition, according to the gas separation system 1 of this embodiment, by connecting two adsorbers 10 and reusing the purge gas, the carbon dioxide desorption efficiency can be improved without inputting additional external energy, such as by increasing the energy for heating the adsorber 10 from the outside or connecting the outlet of the adsorber 10 to a vacuum pump, thereby suppressing a decrease in energy efficiency.

本実施形態のガス分離システム1によれば、限られた量のパージガスを用いて、二酸化炭素の脱離を効率的かつ短時間で終わらせることができるため、ガス分離システム1のサイズの小型化、省エネルギー化を実現することができる。 According to the gas separation system 1 of this embodiment, carbon dioxide desorption can be completed efficiently and in a short time using a limited amount of purge gas, thereby making it possible to reduce the size of the gas separation system 1 and achieve energy savings.

<第2実施形態>
図11は、第2実施形態のガス分離システム1Aの概略構成を示す説明図である。本実施形態のガス分離システム1Aは、第1実施形態のガス分離システム1の構成に加え、さらに2つの吸着器14、15と、2つの接続流路84、85を備える。吸着器14、15は、吸着器11~13と同様の構成を有する。吸着器13は接続流路83を介して吸着器14と接続され、吸着器14は接続流路84を介して吸着器15と接続され、吸着器15は接続流路85を介して吸着器11と接続される。以下に説明する実施形態において、ガス分離システム1と同一の構成には同一の符号を付し、先行する説明を参照する。
Second Embodiment
FIG. 11 is an explanatory diagram showing a schematic configuration of a gas separation system 1A of the second embodiment. In addition to the configuration of the gas separation system 1 of the first embodiment, the gas separation system 1A of this embodiment further includes two adsorbers 14, 15 and two connection flow paths 84, 85. The adsorbers 14, 15 have the same configuration as the adsorbers 11 to 13. The adsorber 13 is connected to the adsorber 14 via a connection flow path 83, the adsorber 14 is connected to the adsorber 15 via a connection flow path 84, and the adsorber 15 is connected to the adsorber 11 via a connection flow path 85. In the embodiment described below, the same components as those of the gas separation system 1 are denoted by the same reference numerals, and the preceding description is referred to.

図12は、第2実施形態のガス分離システム1Aにおける吸着器10の切替タイミングの説明図である。本実施形態のガス分離処理では、図示するように、工程1A、工程2A、工程3A、工程4A、および工程5Aを1サイクルとして、このサイクルが、複数回繰り返される。各工程では、吸着工程、加熱工程、第1脱離工程、第2脱離工程、および冷却工程のそれぞれが、5つの吸着器11、12、13、14、および15のいずれかにおいて実行される。本実施形態における工程1A、2A、3A、4Aおよび5Aのそれぞれを「吸脱着工程」とも呼ぶ。また、第1脱離工程が行われる吸着器10を「第1吸着器」、第2脱離工程が行われる吸着器10を「第2吸着器」、吸着工程が行われる吸着器10を「第3吸着器」とも呼ぶ。 Figure 12 is an explanatory diagram of the switching timing of the adsorber 10 in the gas separation system 1A of the second embodiment. In the gas separation process of this embodiment, as shown in the figure, one cycle is composed of steps 1A, 2A, 3A, 4A, and 5A, and this cycle is repeated multiple times. In each step, the adsorption step, heating step, first desorption step, second desorption step, and cooling step are each performed in one of the five adsorber 11, 12, 13, 14, and 15. In this embodiment, steps 1A, 2A, 3A, 4A, and 5A are also called "adsorption/desorption steps." In addition, the adsorber 10 in which the first desorption step is performed is also called the "first adsorber," the adsorber 10 in which the second desorption step is performed is also called the "second adsorber," and the adsorber 10 in which the adsorption step is performed is also called the "third adsorber."

具体的には、工程1Aでは、吸着器11において吸着工程が実行され、吸着器12において加熱工程が実行され、吸着器13において第1脱離工程が実行され、吸着器14において第2脱離工程が実行され、吸着器15において冷却工程が実行される。工程2A、3A、4Aおよび5Aでは、吸着工程、加熱工程、第1脱離工程、第2脱離工程、および冷却工程のそれぞれが対象とする吸着器10を変更して、吸脱着工程が行われる。本実施形態のガス分離システム1Aでは、いずれか1つの吸着器10において排ガス中の二酸化炭素を吸着すると同時に、他の1つの吸着器10を加熱し、他の2つの吸着器10において、吸着された二酸化炭素を脱離し、他の1つの吸着器10を冷却する。 Specifically, in step 1A, an adsorption step is performed in adsorber 11, a heating step is performed in adsorber 12, a first desorption step is performed in adsorber 13, a second desorption step is performed in adsorber 14, and a cooling step is performed in adsorber 15. In steps 2A, 3A, 4A, and 5A, the adsorber 10 targeted for each of the adsorption step, heating step, first desorption step, second desorption step, and cooling step is changed, and the adsorption and desorption steps are performed. In the gas separation system 1A of this embodiment, carbon dioxide in the exhaust gas is adsorbed in one of the adsorber 10, while the other adsorber 10 is heated, and the adsorbed carbon dioxide is desorbed in the other two adsorber 10, and the other adsorber 10 is cooled.

1つの吸着器10に注目すると、吸着工程、加熱工程、第1脱離工程、第2脱離工程、冷却工程が、この順に繰り返し行われる。本実施形態では、加熱工程が脱離工程と独立して設けられており、第2脱離工程では、加熱は行われない。また、冷却工程が吸着工程と独立して設けられている。 Focusing on one adsorber 10, the adsorption process, heating process, first desorption process, second desorption process, and cooling process are repeated in this order. In this embodiment, the heating process is provided independently of the desorption process, and heating is not performed in the second desorption process. In addition, the cooling process is provided independently of the adsorption process.

図13は、ガス分離システム1Aにおける工程1Aの説明図である。ガス分離システム1Aでは、5つの吸着器11、12、13、14、15のそれぞれに、順番に排ガス(二酸化炭素含有ガス)を供給することにより、排ガスから二酸化炭素を分離する。ガス分離システム1Aでも、第1実施形態と同様に、2つの吸着器10が、接続流路80を介して直列に接続され、第1脱離工程が実行される第1吸着器としての吸着器10を流通したパージガスが、第2脱離工程が実行される第2吸着器としての吸着器10に供給される。図13において、排ガス、熱媒、パージガス(水素)の流れを太い実線で示している。 Figure 13 is an explanatory diagram of step 1A in gas separation system 1A. In gas separation system 1A, exhaust gas (carbon dioxide-containing gas) is supplied to each of five adsorbers 11, 12, 13, 14, and 15 in sequence to separate carbon dioxide from the exhaust gas. In gas separation system 1A, as in the first embodiment, two adsorbers 10 are connected in series via a connection flow path 80, and purge gas that has flowed through adsorber 10 as the first adsorber in which the first desorption step is performed is supplied to adsorber 10 as the second adsorber in which the second desorption step is performed. In Figure 13, the flows of exhaust gas, heat transfer medium, and purge gas (hydrogen) are indicated by thick solid lines.

図13に示すように、工程1A(図12)では、吸着器11で吸着工程が行われ、吸着器11に排ガスが供給される。具体的には、制御部55により排ガス入口弁21aが開弁されると共に、排ガス入口弁22a~25aが閉弁され、二酸化炭素含有ガス供給流路20および排ガス分流路21を介して、吸着器11に排ガスが供給される。吸着器11では、排ガスに含まれる二酸化炭素が吸着材11aによってトラップされ、吸着材11aにトラップされなかった窒素や水分などの大部分のガスは、オフガスとして、ガス分離システム1の外部、例えば、大気に放出される。 As shown in FIG. 13, in step 1A (FIG. 12), an adsorption process is performed in the adsorber 11, and exhaust gas is supplied to the adsorber 11. Specifically, the controller 55 opens the exhaust gas inlet valve 21a and closes the exhaust gas inlet valves 22a to 25a, and exhaust gas is supplied to the adsorber 11 via the carbon dioxide-containing gas supply flow path 20 and the exhaust gas branch flow path 21. In the adsorber 11, the carbon dioxide contained in the exhaust gas is trapped by the adsorbent 11a, and most of the gases such as nitrogen and moisture that are not trapped by the adsorbent 11a are released as off-gas to the outside of the gas separation system 1, for example, to the atmosphere.

吸着器12で加熱工程が行われ、吸着器12に熱媒が供給される。具体的には、制御部55により熱媒が所定の温度(投入熱量)になるようにヒータ30aが制御されると共に、熱媒入口弁32aが開弁され、熱媒入口弁31a、33a、34aおよび35aが閉弁され、熱媒が供給される。これにより、熱媒流路30を流れる熱媒は、熱媒分流路32を介して、吸着器12に供給される。吸着器12において、熱媒が供給されると吸着材12aの温度が上昇し、吸着材12aに吸着された二酸化炭素が脱離しやすい状態になる。 The heating process is carried out in the adsorber 12, and the heat medium is supplied to the adsorber 12. Specifically, the control unit 55 controls the heater 30a so that the heat medium reaches a predetermined temperature (amount of heat input), while the heat medium inlet valve 32a is opened and the heat medium inlet valves 31a, 33a, 34a, and 35a are closed to supply the heat medium. As a result, the heat medium flowing through the heat medium flow path 30 is supplied to the adsorber 12 via the heat medium branch flow path 32. When the heat medium is supplied to the adsorber 12, the temperature of the adsorbent 12a rises, and the carbon dioxide adsorbed in the adsorbent 12a becomes easily desorbed.

吸着器13で第1脱離工程が行われ、吸着器13にパージガスが供給される。具体的には、制御部55によりパージガス入口弁73aが開弁されると共に、パージガス入口弁71a、72a、74aおよび75aが閉弁され、パージガス供給流路70およびパージガス分流路73を介して、吸着器13にパージガスが供給される。吸着器13にパージガスが供給されると、吸着材13aに吸着されている二酸化炭素が吸着材13aから脱離する。吸着材13aから脱離した二酸化炭素は、吸着器13の内部においてパージガス(水素)と混合される。工程1Aにおいて、混合ガス出口弁63aが閉弁されると共に、接続流路弁83aが開弁されているため、吸着器13から排出される混合ガスは、混合ガス分流路63、接続流路83、およびパージガス分流路74を通って、吸着器14に流入する。 The first desorption step is performed in the adsorber 13, and the purge gas is supplied to the adsorber 13. Specifically, the control unit 55 opens the purge gas inlet valve 73a and closes the purge gas inlet valves 71a, 72a, 74a, and 75a, and the purge gas is supplied to the adsorber 13 through the purge gas supply passage 70 and the purge gas branch passage 73. When the purge gas is supplied to the adsorber 13, the carbon dioxide adsorbed in the adsorbent 13a is desorbed from the adsorbent 13a. The carbon dioxide desorbed from the adsorbent 13a is mixed with the purge gas (hydrogen) inside the adsorber 13. In step 1A, the mixed gas outlet valve 63a is closed and the connection passage valve 83a is open, so that the mixed gas discharged from the adsorber 13 flows into the adsorber 14 through the mixed gas branch passage 63, the connection passage 83, and the purge gas branch passage 74.

吸着器14で第2脱離工程が行われ、吸着器14に上述の混合ガスが供給される。吸着器14にパージガスを含む混合ガスが供給されると、吸着材14aに吸着されている二酸化炭素が吸着材14aから脱離する。吸着材14aから脱離した二酸化炭素は、吸着器14の内部においてパージガスを含む混合ガスと混合される。工程1Aにおいて、混合ガス出口弁64aが開弁されているため、吸着器14から排出される混合ガスは、混合ガス分流路64および混合ガス流路60を通ってサージタンク40に貯留される。 The second desorption step is performed in the adsorber 14, and the above-mentioned mixed gas is supplied to the adsorber 14. When the mixed gas containing the purge gas is supplied to the adsorber 14, the carbon dioxide adsorbed to the adsorbent 14a is desorbed from the adsorbent 14a. The carbon dioxide desorbed from the adsorbent 14a is mixed with the mixed gas containing the purge gas inside the adsorber 14. In step 1A, since the mixed gas outlet valve 64a is open, the mixed gas discharged from the adsorber 14 passes through the mixed gas branch passage 64 and the mixed gas passage 60 and is stored in the surge tank 40.

吸着器15で冷却工程が行われ、吸着器15に冷媒が供給される(不図示)。比較的温度が低い熱媒体が吸着器15の熱媒体流路に供給されると、吸着材15aが冷却され、15aの温度が低下する。これにより、吸着材15aは、二酸化炭素を吸着しやすい状態となる。本実施形態の工程1Aにおいて、吸着器11が「第3吸着器」、吸着器13が「第1吸着器」、吸着器13が「第2吸着器」である。本実施形態のガス分離システム1Aにおいても、制御部55は、第1吸着器、第2吸着器、および第3吸着器を変更して、吸脱着工程を繰り返し実行している。 The cooling process is performed in the adsorber 15, and a refrigerant is supplied to the adsorber 15 (not shown). When a relatively low-temperature heat medium is supplied to the heat medium flow path of the adsorber 15, the adsorbent 15a is cooled and the temperature of 15a decreases. This makes the adsorbent 15a more likely to adsorb carbon dioxide. In step 1A of this embodiment, the adsorber 11 is the "third adsorber", the adsorber 13 is the "first adsorber", and the adsorber 13 is the "second adsorber". In the gas separation system 1A of this embodiment, the control unit 55 also changes the first adsorber, the second adsorber, and the third adsorber to repeatedly perform the adsorption and desorption process.

以上説明したように、本実施形態のガス分離システム1Aによっても、1つの吸着器10を通過したパージガスを再利用して、別の吸着器10に流入させることができるため、パージガスによる二酸化炭素の脱離効率を向上させることができる。 As described above, the gas separation system 1A of this embodiment also allows the purge gas that has passed through one adsorber 10 to be reused and flowed into another adsorber 10, thereby improving the efficiency of carbon dioxide desorption by the purge gas.

<第3実施形態>
第3実施形態のガス分離システムは、第2実施形態のガス分離システム1Aと同じ構成であるものの、制御部55によるガス分離処理が第2実施形態と異なる。
Third Embodiment
The gas separation system of the third embodiment has the same configuration as the gas separation system 1A of the second embodiment, but the gas separation process by the control unit 55 is different from that of the second embodiment.

図14は、第3実施形態のガス分離システムにおける吸着器10の切替タイミングの説明図である。本実施形態のガス分離処理では、第2実施形態と同様に、工程1B、工程2B、工程3B、工程4B、および工程5Bを1サイクルとして、このサイクルが、複数回繰り返される。各工程では、吸着工程、加熱工程、第1脱離工程、第2脱離工程、および冷却工程のそれぞれが、5つの吸着器11、12、13、14、および15のいずれかにおいて実行される。本実施形態における工程1B、2B、3B、4Bおよび5Bのそれぞれを「吸脱着工程」とも呼ぶ。また、第1脱離工程が行われる吸着器10を「第1吸着器」、第2脱離工程が行われる吸着器10を「第2吸着器」、吸着工程が行われる吸着器10を「第3吸着器」とも呼ぶ。 Figure 14 is an explanatory diagram of the switching timing of the adsorber 10 in the gas separation system of the third embodiment. In the gas separation process of this embodiment, as in the second embodiment, steps 1B, 2B, 3B, 4B, and 5B constitute one cycle, and this cycle is repeated multiple times. In each step, the adsorption step, heating step, first desorption step, second desorption step, and cooling step are each performed in one of the five adsorber 11, 12, 13, 14, and 15. In this embodiment, steps 1B, 2B, 3B, 4B, and 5B are also called "adsorption/desorption steps." In addition, the adsorber 10 in which the first desorption step is performed is also called the "first adsorber," the adsorber 10 in which the second desorption step is performed is also called the "second adsorber," and the adsorber 10 in which the adsorption step is performed is also called the "third adsorber."

本実施形態のガス分離処理が第2実施形態のガス分離処理と異なる点は、第2脱離工程の一部の期間において、第1吸着器内を流通したパージガスを、接続流路80を介して第2吸着器に流入させる点である。本実施形態では、第2脱離工程の後半のみ、第1吸着器内を流通したパージガスを、接続流路80を介して第2吸着器に流入させている。図14では、第2脱離工程の前半に「非接続」と図示しており、第1吸着器と第2吸着器とが接続されておらず、第2吸着器にパージガスが供給されないことを示している。また、第2脱離工程の後半に「接続」と図示しており、第1吸着器と第2吸着器とが接続され、第2吸着器にパージガスが供給されることを示している。 The gas separation process of this embodiment differs from the gas separation process of the second embodiment in that, during a portion of the second desorption process, the purge gas that has flowed through the first adsorption device is caused to flow into the second adsorption device through the connection flow path 80. In this embodiment, only during the latter half of the second desorption process, the purge gas that has flowed through the first adsorption device is caused to flow into the second adsorption device through the connection flow path 80. In FIG. 14, the first half of the second desorption process is shown as "disconnected," indicating that the first and second adsorption devices are not connected and that purge gas is not supplied to the second adsorption device. In addition, the second half of the second desorption process is shown as "connected," indicating that the first and second adsorption devices are connected and that purge gas is supplied to the second adsorption device.

図15は、第3実施形態の工程1Bの第2脱離工程の説明図である。図15では、第3実施形態のガス分離システムの一部を図示している。図15(A)は、第2脱離工程の前半(非接続工程)を図示し、図15(B)は第2脱離工程の後半(接続工程)を図示している。図15において、パージガス(水素)の流れを太い実線で示している。 Figure 15 is an explanatory diagram of the second desorption step of step 1B of the third embodiment. Figure 15 illustrates a part of the gas separation system of the third embodiment. Figure 15 (A) illustrates the first half of the second desorption step (disconnection step), and Figure 15 (B) illustrates the second half of the second desorption step (connection step). In Figure 15, the flow of purge gas (hydrogen) is indicated by a thick solid line.

図14に示すように、工程1Bでは、吸着器13で第1脱離工程が行われ、吸着器14で第2脱離工程が行われる。第2実施形態と同様に、吸着器13にパージガスが供給される(図15)。吸着器13にパージガスが供給されると、吸着材13aに吸着されている二酸化炭素が吸着材13aから脱離し、吸着材13aから脱離した二酸化炭素は、吸着器13の内部においてパージガス(水素)と混合される。図15(A)に示すように、工程1Bの第2脱離工程の前半では、混合ガス出口弁63aが開弁されると共に、接続流路弁83aが閉弁されている。すなわち、第1吸着器としての吸着器13と第2吸着器としての吸着器14とが接続されていないため、吸着器13から排出される混合ガスは、混合ガス分流路63、および混合ガス流路60を通って、サージタンク40に貯留される。 As shown in FIG. 14, in step 1B, the first desorption step is performed in the adsorber 13, and the second desorption step is performed in the adsorber 14. As in the second embodiment, a purge gas is supplied to the adsorber 13 (FIG. 15). When the purge gas is supplied to the adsorber 13, the carbon dioxide adsorbed in the adsorbent 13a is desorbed from the adsorbent 13a, and the carbon dioxide desorbed from the adsorbent 13a is mixed with the purge gas (hydrogen) inside the adsorber 13. As shown in FIG. 15(A), in the first half of the second desorption step of step 1B, the mixed gas outlet valve 63a is opened and the connection flow path valve 83a is closed. That is, since the adsorber 13 as the first adsorber and the adsorber 14 as the second adsorber are not connected, the mixed gas discharged from the adsorber 13 passes through the mixed gas branch flow path 63 and the mixed gas flow path 60 and is stored in the surge tank 40.

工程1Bにおいて、所定の時間が経過すると第2脱離工程の接続工程に移行する。図15(B)に示すように、工程1Bの第2脱離工程の後半では、混合ガス出口弁63aが閉弁されると共に、接続流路弁83aが開弁されている。すなわち、第1吸着器としての吸着器13と第2吸着器としての吸着器14とが接続されているため、吸着器13から排出される混合ガスは、混合ガス分流路63、接続流路83、およびパージガス分流路74を通って、吸着器14に流入する。吸着器14にパージガスを含む混合ガスが供給されると、吸着材14aに吸着されている二酸化炭素が吸着材14aから脱離され、吸着器14の内部においてパージガスを含む混合ガスと混合される。工程1Bの後半において、混合ガス出口弁64aが開弁されているため、吸着器14から排出される混合ガスは、混合ガス分流路64および混合ガス流路60を通ってサージタンク40に貯留される。 In step 1B, when a predetermined time has elapsed, the process moves to the connection step of the second desorption step. As shown in FIG. 15(B), in the latter half of the second desorption step of step 1B, the mixed gas outlet valve 63a is closed and the connection flow path valve 83a is opened. That is, since the adsorber 13 as the first adsorber and the adsorber 14 as the second adsorber are connected, the mixed gas discharged from the adsorber 13 flows into the adsorber 14 through the mixed gas branch flow path 63, the connection flow path 83, and the purge gas branch flow path 74. When the adsorber 14 is supplied with the mixed gas containing the purge gas, the carbon dioxide adsorbed in the adsorbent 14a is desorbed from the adsorbent 14a and mixed with the mixed gas containing the purge gas inside the adsorber 14. In the latter half of step 1B, since the mixed gas outlet valve 64a is opened, the mixed gas discharged from the adsorber 14 passes through the mixed gas branch flow path 64 and the mixed gas flow path 60 and is stored in the surge tank 40.

第1脱離工程の前半は、第1吸着器から排出される混合ガスの二酸化炭素濃度が高いため、混合ガスを第2吸着器に流しても、二酸化炭素の脱離効果が小さい。そのため、本実施形態のガス分離処理のように、第2脱離工程の前半では、第1吸着器と第2吸着器とを接続せず、二酸化炭素濃度が高い混合ガスをサージタンク40に貯留し、第1吸着器から排出される混合ガスの二酸化炭素濃度が低下した後半において第1吸着器と第2吸着器とを接続し、パージガスを再利用してもよい。このようにしても、パージガスによる二酸化炭素の脱離効率を向上させることができる。 In the first half of the first desorption step, the carbon dioxide concentration of the mixed gas discharged from the first adsorption device is high, so even if the mixed gas is passed through the second adsorption device, the carbon dioxide desorption effect is small. Therefore, as in the gas separation process of this embodiment, in the first half of the second desorption step, the first and second adsorption devices are not connected, and the mixed gas with a high carbon dioxide concentration is stored in the surge tank 40, and in the second half, when the carbon dioxide concentration of the mixed gas discharged from the first adsorption device has decreased, the first and second adsorption devices are connected and the purge gas is reused. In this way, the efficiency of carbon dioxide desorption by the purge gas can be improved.

<第4実施形態>
図16は、第4実施形態のガス分離システム1Cの概略構成を示す説明図である。本実施形態のガス分離システム1Cは、第2実施形態のガス分離システム1Aの構成に加え、真空ポンプ45を備える。以下に説明する実施形態において、ガス分離システム1、1Aと同一の構成には同一の符号を付し、先行する説明を参照する。
Fourth Embodiment
16 is an explanatory diagram showing a schematic configuration of a gas separation system 1C of the fourth embodiment. The gas separation system 1C of the present embodiment includes a vacuum pump 45 in addition to the configuration of the gas separation system 1A of the second embodiment. In the embodiments described below, the same components as those of the gas separation systems 1 and 1A are denoted by the same reference numerals, and the preceding description is referred to.

真空ポンプ45は、吸着器15とサージタンク40との間の混合ガス流路60に両端が接続する減圧流路46に、設けられている。減圧流路46には、制御部55の指令に応じて、減圧流路46の流れを制御する切換弁47が設けられている。また、図16に示すように、混合ガス流路60の、減圧流路46の両端が接続する間には、制御部55の指令に応じて、混合ガス流路60の流れを制御する切換弁48が設けられている。真空ポンプ45は、切換弁48が閉じられ、切換弁47が開かれているとき、制御部55の指令に応じて駆動し、吸着器10の内部を減圧する。本実施形態のガス分離システム1Cでは、第2脱離工程の一部の期間において、真空ポンプ45による吸着器10内の減圧が行われる。 The vacuum pump 45 is provided in the pressure reduction flow passage 46, both ends of which are connected to the mixed gas flow passage 60 between the adsorber 15 and the surge tank 40. The pressure reduction flow passage 46 is provided with a switching valve 47 that controls the flow of the pressure reduction flow passage 46 in response to a command from the control unit 55. As shown in FIG. 16, a switching valve 48 that controls the flow of the mixed gas flow passage 60 in response to a command from the control unit 55 is provided between the two ends of the pressure reduction flow passage 46 of the mixed gas flow passage 60. When the switching valve 48 is closed and the switching valve 47 is open, the vacuum pump 45 is driven in response to a command from the control unit 55 to reduce the pressure inside the adsorber 10. In the gas separation system 1C of this embodiment, the vacuum pump 45 reduces the pressure inside the adsorber 10 during a part of the second desorption process.

第4実施形態では、第3実施形態と同様に、第2脱離工程の一部の期間において、第1吸着器内を流通したパージガスを、接続流路80を介して第2吸着器に流入させる。本実施形態では、第3実施形態と異なり、第2脱離工程の前半のみ、第1吸着器内を流通したパージガスを、接続流路80を介して第2吸着器に流入させている。 In the fourth embodiment, similar to the third embodiment, during a portion of the second desorption process, the purge gas that has flowed through the first adsorption device is caused to flow into the second adsorption device via the connecting flow path 80. In this embodiment, unlike the third embodiment, the purge gas that has flowed through the first adsorption device is caused to flow into the second adsorption device via the connecting flow path 80 only during the first half of the second desorption process.

図17は、第4実施形態のガス分離システムにおける吸着器10の切替タイミングの説明図である。本実施形態のガス分離処理では、第3実施形態と同様に、工程1C、工程2C、工程3C、工程4C、および工程5Cを1サイクルとして、このサイクルが、複数回繰り返される。各工程では、吸着工程、加熱工程、第1脱離工程、第2脱離工程、および冷却工程のそれぞれが、5つの吸着器11、12、13、14、および15のいずれかにおいて実行される。本実施形態における工程1C、2C、3C、4Cおよび5Cのそれぞれを「吸脱着工程」とも呼ぶ。また、第1脱離工程が行われる吸着器10を「第1吸着器」、第2脱離工程が行われる吸着器10を「第2吸着器」、吸着工程が行われる吸着器10を「第3吸着器」とも呼ぶ。 Figure 17 is an explanatory diagram of the switching timing of the adsorber 10 in the gas separation system of the fourth embodiment. In the gas separation process of this embodiment, as in the third embodiment, steps 1C, 2C, 3C, 4C, and 5C constitute one cycle, and this cycle is repeated multiple times. In each step, the adsorption step, heating step, first desorption step, second desorption step, and cooling step are each performed in one of the five adsorber 11, 12, 13, 14, and 15. In this embodiment, steps 1C, 2C, 3C, 4C, and 5C are also called "adsorption/desorption steps." In addition, the adsorber 10 in which the first desorption step is performed is also called the "first adsorber," the adsorber 10 in which the second desorption step is performed is also called the "second adsorber," and the adsorber 10 in which the adsorption step is performed is also called the "third adsorber."

図17では、図14と同様に、第2吸着器にパージガスが供給される工程に「接続」と図示し、第2吸着器にパージガスが供給されない工程に「非接続」と図示している。本実施形態では、上述の通り、第2脱離工程の前半に第1吸着器と第2吸着器とが接続されて、第2吸着器にパージガスが供給される。このとき、真空ポンプ45は駆動されない。第2脱離工程の後半は第1吸着器と第2吸着器とが接続されておらず、第2吸着器にパージガスが供給されない。このとき、真空ポンプ45が駆動される。このように、本実施形態では、第2脱離工程の前半は真空ポンプ45が駆動されず、第2脱離工程の後半に真空ポンプ45が駆動される。 In FIG. 17, as in FIG. 14, the process in which purge gas is supplied to the second adsorber is indicated as "connected" and the process in which purge gas is not supplied to the second adsorber is indicated as "disconnected". In this embodiment, as described above, the first adsorber and the second adsorber are connected in the first half of the second desorption process, and purge gas is supplied to the second adsorber. At this time, the vacuum pump 45 is not driven. In the second half of the second desorption process, the first adsorber and the second adsorber are not connected, and purge gas is not supplied to the second adsorber. At this time, the vacuum pump 45 is driven. Thus, in this embodiment, the vacuum pump 45 is not driven in the first half of the second desorption process, and the vacuum pump 45 is driven in the second half of the second desorption process.

図18は、第4実施形態の工程1Cの第2脱離工程の説明図である。図18では、ガス分離システム1Cの一部を図示している。図18(A)は、第2脱離工程の前半(接続工程)を図示し、図18(B)は第2脱離工程の後半(非接続工程)を図示している。図示するように、第2脱離工程の前半では、真空ポンプ45が駆動されず、第2脱離工程の後半では、真空ポンプ45が駆動される。図18において、パージガス(水素)の流れを太い実線で示している。 Figure 18 is an explanatory diagram of the second desorption step of step 1C of the fourth embodiment. Figure 18 illustrates a part of the gas separation system 1C. Figure 18 (A) illustrates the first half of the second desorption step (connection step), and Figure 18 (B) illustrates the second half of the second desorption step (disconnection step). As shown, in the first half of the second desorption step, the vacuum pump 45 is not driven, and in the second half of the second desorption step, the vacuum pump 45 is driven. In Figure 18, the flow of purge gas (hydrogen) is indicated by a thick solid line.

図17に示すように、工程1Cでは、吸着器13で第1脱離工程が行われ、吸着器14で第2脱離工程が行われる。第2実施形態と同様に、吸着器13にパージガスが供給される(図18)。吸着器13にパージガスが供給されると、吸着材13aに吸着されている二酸化炭素が吸着材13aから脱離し、吸着材13aから脱離した二酸化炭素は、吸着器13の内部においてパージガス(水素)と混合される。図18(A)に示すように、工程1Cの第2脱離工程の前半では、混合ガス出口弁63aが閉弁されると共に、接続流路弁83aが開弁されている。また、切換弁47が閉弁され、真空ポンプ45が停止されており、切換弁48が開弁されている。すなわち、第1吸着器としての吸着器13と第2吸着器としての吸着器14とが接続されているため、吸着器13から排出される混合ガスは、混合ガス分流路63、接続流路83、およびパージガス分流路74を通って、吸着器14に流入する。吸着器14にパージガスを含む混合ガスが供給されると、吸着材14aに吸着されている二酸化炭素が吸着材14aから脱離され、吸着器14の内部においてパージガスを含む混合ガスと混合される。工程1Cの前半において、混合ガス出口弁64aが開弁されているため、吸着器14から排出される混合ガスは、混合ガス分流路64および混合ガス流路60を通ってサージタンク40に貯留される。 As shown in FIG. 17, in step 1C, the first desorption step is performed in the adsorber 13, and the second desorption step is performed in the adsorber 14. As in the second embodiment, a purge gas is supplied to the adsorber 13 (FIG. 18). When the purge gas is supplied to the adsorber 13, the carbon dioxide adsorbed in the adsorbent 13a is desorbed from the adsorbent 13a, and the carbon dioxide desorbed from the adsorbent 13a is mixed with the purge gas (hydrogen) inside the adsorber 13. As shown in FIG. 18(A), in the first half of the second desorption step of step 1C, the mixed gas outlet valve 63a is closed and the connection flow path valve 83a is opened. In addition, the switching valve 47 is closed, the vacuum pump 45 is stopped, and the switching valve 48 is opened. That is, since the adsorber 13 as the first adsorber and the adsorber 14 as the second adsorber are connected, the mixed gas discharged from the adsorber 13 flows into the adsorber 14 through the mixed gas branch passage 63, the connection passage 83, and the purge gas branch passage 74. When the mixed gas containing the purge gas is supplied to the adsorber 14, the carbon dioxide adsorbed to the adsorbent 14a is desorbed from the adsorbent 14a and mixed with the mixed gas containing the purge gas inside the adsorber 14. In the first half of step 1C, since the mixed gas outlet valve 64a is open, the mixed gas discharged from the adsorber 14 passes through the mixed gas branch passage 64 and the mixed gas passage 60 and is stored in the surge tank 40.

工程1Cにおいて、所定の時間が経過すると第2脱離工程の接続工程に移行する。図18(B)に示すように、工程1Cの第2脱離工程の後半では、混合ガス出口弁63aが開弁されると共に、接続流路弁83aが閉弁されている。また、切換弁47が開弁され、真空ポンプ45が駆動され、切換弁48が閉弁されている。すなわち、第1吸着器としての吸着器13と第2吸着器としての吸着器14とが接続されていないため、吸着器13から排出される混合ガスは、混合ガス分流路63、混合ガス流路60、減圧流路46を通って、サージタンク40に貯留される。 In step 1C, when a predetermined time has elapsed, the process moves to the connection step of the second desorption step. As shown in FIG. 18(B), in the latter half of the second desorption step of step 1C, the mixed gas outlet valve 63a is opened and the connection flow path valve 83a is closed. In addition, the switching valve 47 is opened, the vacuum pump 45 is driven, and the switching valve 48 is closed. In other words, since the adsorber 13 as the first adsorber and the adsorber 14 as the second adsorber are not connected, the mixed gas discharged from the adsorber 13 passes through the mixed gas branch flow path 63, the mixed gas flow path 60, and the pressure reduction flow path 46 and is stored in the surge tank 40.

本実施形態において、第2脱離工程の後半では、真空ポンプ45を用いて二酸化炭素の脱離をアシストしている。この場合に、吸着器13と吸着器14とを接続すると、第2吸着器としての吸着器14における二酸化炭素の脱離をアシストすることになり、第1吸着器としての吸着器13における二酸化炭素の脱離を効率的に行うことができない。本実施形態では、第2脱離工程の前半では、第1吸着器と第2吸着器とを接続して、パージガスを再利用してパージガスによる二酸化炭素の脱離効率を向上させ、第2脱離工程の後半では、第1吸着器と第2吸着器とを接続せず、真空ポンプ45を用いて第1吸着器の二酸化炭素脱離率を向上させている。このようにしても、パージガスによる二酸化炭素の脱離効率を向上させることができる。 In this embodiment, in the latter half of the second desorption process, the vacuum pump 45 is used to assist the desorption of carbon dioxide. In this case, if the adsorber 13 and the adsorber 14 are connected, the desorption of carbon dioxide in the adsorber 14 as the second adsorber is assisted, and the desorption of carbon dioxide in the adsorber 13 as the first adsorber cannot be performed efficiently. In this embodiment, in the first half of the second desorption process, the first adsorber and the second adsorber are connected to reuse the purge gas and improve the desorption efficiency of carbon dioxide by the purge gas, and in the second half of the second desorption process, the first adsorber and the second adsorber are not connected, and the carbon dioxide desorption rate of the first adsorber is improved using the vacuum pump 45. Even in this way, the desorption efficiency of carbon dioxide by the purge gas can be improved.

<第5実施形態>
図19は、第5実施形態の炭化水素製造システム5の概略構成を示す説明図である。本実施形態の炭化水素製造システム5は、二酸化炭素(CO2)と水素(H2)との混合ガスを用いて、メタン(CH4)を製造する装置であり、ガス分離システム1と炭化水素生成部8を備える。なお、本実施形態は、メタン以外の炭化水素化合物を製造する炭化水素製造装置にも適用可能であり、例えば、エタンやプロパンなどの炭素と水素とから構成される化合物やメタノールなどの主に炭素と水素とから構成される化合物を「炭化水素化合物」として製造する「炭化水素製造装置」にも適用可能である。
Fifth Embodiment
19 is an explanatory diagram showing a schematic configuration of a hydrocarbon production system 5 of the fifth embodiment. The hydrocarbon production system 5 of this embodiment is an apparatus for producing methane ( CH4 ) using a mixed gas of carbon dioxide ( CO2 ) and hydrogen ( H2 ), and includes a gas separation system 1 and a hydrocarbon production unit 8. Note that this embodiment is also applicable to a hydrocarbon production apparatus for producing hydrocarbon compounds other than methane, and is also applicable to a "hydrocarbon production apparatus" for producing, for example, compounds composed of carbon and hydrogen such as ethane and propane, and compounds mainly composed of carbon and hydrogen such as methanol, as "hydrocarbon compounds".

本実施形態において、サージタンク40は、混合ガス流路60を流れる混合ガスを一時的に貯蔵する。サージタンク40に貯蔵された混合ガスは、炭化水素生成部8に送られる。炭化水素生成部8は、サージタンク40が供給する二酸化炭素と水素との混合ガスを用いて、メタンを生成する。生成されたメタンは、炭化水素製造システム5の外部の装置に供給される。 In this embodiment, the surge tank 40 temporarily stores the mixed gas flowing through the mixed gas flow passage 60. The mixed gas stored in the surge tank 40 is sent to the hydrocarbon production unit 8. The hydrocarbon production unit 8 produces methane using the mixed gas of carbon dioxide and hydrogen supplied by the surge tank 40. The produced methane is supplied to a device external to the hydrocarbon production system 5.

以上説明したように、本実施形態の炭化水素製造システム5は、ガス分離システム1を備え、ガス分離システム1によって排ガスから分離された二酸化炭素と、パージガスとしての水素を用いて、炭化水素としてのメタンを生成している。そのため、純度の高い炭化水素化合物を生成することができる。また、上述の通り、ガス分離システム1は、パージガスを再利用することによりパージガスによる二酸化炭素の脱離効率が向上されているため、炭化水素生成部8における炭化水素生成効率を向上させることができる。また、炭化水素生成部8のメタンの生成における余剰の水素量を低減させることができる。 As described above, the hydrocarbon production system 5 of this embodiment includes the gas separation system 1, and produces methane as a hydrocarbon using carbon dioxide separated from the exhaust gas by the gas separation system 1 and hydrogen as a purge gas. This makes it possible to produce hydrocarbon compounds with high purity. As described above, the gas separation system 1 improves the efficiency of carbon dioxide desorption by the purge gas by reusing the purge gas, thereby improving the efficiency of hydrocarbon production in the hydrocarbon production unit 8. In addition, the amount of excess hydrogen in the production of methane in the hydrocarbon production unit 8 can be reduced.

<本実施形態の変形例>
本発明は上記の実施形態に限られるものではなく、その要旨を逸脱しない範囲において種々の態様において実施することが可能であり、例えば次のような変形も可能である。
<Modifications of this embodiment>
The present invention is not limited to the above-described embodiment, and can be embodied in various forms without departing from the spirit and scope of the invention. For example, the following modifications are also possible.

・上記実施形態において、パージガスとして、水素以外のガスを用いてもよい。例えば、ヘリウム、ネオン等の希ガス、水蒸気、メタン、およびそれらの少なくとも一つを含む混合ガス等を用いることができる。第5実施形態の炭化水素製造システム5においてパージガスとして水素以外のガスを用いる場合には、炭化水素生成部8に水素を供給する水素供給部を備えればよい。但し、パージガスとして水素を用いると、炭化水素生成部8において高純度の炭化水素を生成することができるため、好ましい。 - In the above embodiment, a gas other than hydrogen may be used as the purge gas. For example, rare gases such as helium and neon, water vapor, methane, and mixed gases containing at least one of these may be used. When a gas other than hydrogen is used as the purge gas in the hydrocarbon production system 5 of the fifth embodiment, a hydrogen supply unit that supplies hydrogen to the hydrocarbon production unit 8 may be provided. However, using hydrogen as the purge gas is preferable because it allows the hydrocarbon production unit 8 to produce high-purity hydrocarbons.

・吸着器10の数は、上記実施形態に限定されず、4つ以下でもよいし、6つ以上でもよい。 - The number of adsorbents 10 is not limited to the above embodiment and may be four or less, or six or more.

・上記実施形態において、第1吸着器にパージガスが供給され、第1吸着器から排出されるパージガスと二酸化炭素を含む混合ガスが第2吸着器に供給され、第2吸着器から排出される混合ガスがサージタンク40に貯留される例を示したが、第2吸着器にさらに複数の吸着器が直列に接続される構成にしてもよい。例えば、第2吸着器の後段に、第4吸着器、第5吸着器、および第6吸着器を直列に接続した場合、第2吸着器から排出された混合ガスが第4吸着器に供給され、第4吸着器において脱離された二酸化炭素を含み第4吸着器から排出される混合ガスが第5吸着器に供給され、第5吸着器において脱離された二酸化炭素を含み第5吸着器から排出される混合ガスが第6吸着器に供給され、第6吸着器において脱離された二酸化炭素を含み第6吸着器から排出される混合ガスがサージタンク40に貯留される。このようにすると、後段になるほど、1工程における二酸化炭素脱離量は少なくなるものの、パージガスを再利用して吸着器10内の二酸化炭素を脱離することができるため、パージガスによる二酸化炭素の脱離効率を向上させることができる。但し、上段の吸着器10から排出される混合ガスが二酸化炭素で飽和状態である場合には、後段の吸着器10において、二酸化炭素の脱離ができないため、脱離工程において直列に接続する吸着器10の数は、パージガスの供給量、1工程の時間に応じて、後段の吸着器10においても二酸化炭素を脱離可能なように、適宜設定することが好ましい。 - In the above embodiment, an example was shown in which the purge gas was supplied to the first adsorbent, the mixed gas containing the purge gas and carbon dioxide discharged from the first adsorbent was supplied to the second adsorbent, and the mixed gas discharged from the second adsorbent was stored in the surge tank 40, but a configuration in which multiple adsorbents are further connected in series to the second adsorbent may be used. For example, when the fourth adsorbent, the fifth adsorbent, and the sixth adsorbent are connected in series to the rear stage of the second adsorbent, the mixed gas discharged from the second adsorbent is supplied to the fourth adsorbent, the mixed gas discharged from the fourth adsorbent containing the carbon dioxide desorbed in the fourth adsorbent is supplied to the fifth adsorbent, the mixed gas discharged from the fifth adsorbent containing the carbon dioxide desorbed in the fifth adsorbent is supplied to the sixth adsorbent, and the mixed gas discharged from the sixth adsorbent containing the carbon dioxide desorbed in the sixth adsorbent is stored in the surge tank 40. In this way, the amount of carbon dioxide desorbed in one step decreases in the later stages, but the carbon dioxide in the adsorber 10 can be desorbed by reusing the purge gas, improving the efficiency of carbon dioxide desorption by the purge gas. However, if the mixed gas discharged from the upper stage adsorber 10 is saturated with carbon dioxide, the later stage adsorber 10 cannot desorb carbon dioxide, so it is preferable to appropriately set the number of adsorber 10 connected in series in the desorption step so that the later stage adsorber 10 can also desorb carbon dioxide, depending on the supply amount of purge gas and the time for one step.

・上記実施形態において、パージガスを流すことに加えて、吸着材の温度を上昇させる、いわゆる温度スイングを行って、二酸化炭素を脱離させる例を示したが、温度スイングを行わず、パージガスを流すことのみで二酸化炭素の脱離を行ってもよい。また、パージガスの供給に加えて、真空ポンプを用いて減圧してもよいし、さらに、温度スイングを行ってもよい。 - In the above embodiment, an example was shown in which the temperature of the adsorbent was increased, in addition to flowing a purge gas, by performing a so-called temperature swing, to desorb carbon dioxide. However, carbon dioxide may be desorbed only by flowing a purge gas without performing a temperature swing. In addition to supplying a purge gas, the pressure may be reduced using a vacuum pump, and a temperature swing may also be performed.

・上記第3実施形態において、第2脱離工程の後半において、第1吸着器内を流通したパージガスを、接続流路を介して第2吸着器に流入させる例を示し、上記第4実施形態において、第2脱離工程の前半において、第1吸着器内を流通したパージガスを、接続流路を介して第2吸着器に流入させる例を示したが、第1吸着器と第2吸着器とを接続してパージガスを再利用する期間は、上記実施形態に限定されない。例えば、第2脱離工程を、前期、中期、後期の3つの期間に分け、前期では、第1吸着器と第2吸着器とを接続せず、第1吸着器のみで二酸化炭素の脱離を行い、中期で第1吸着器と第2吸着器とを接続して(多段化し)、第1吸着器および第2吸着器で二酸化炭素の脱離を行い、後期で再び第1吸着器と第2吸着器との接続を解除して、第1吸着器のみで二酸化炭素の脱離を行ってもよい。 - In the third embodiment, in the latter half of the second desorption process, the purge gas that has flowed through the first adsorbent is made to flow into the second adsorbent through the connecting flow path, and in the fourth embodiment, in the first half of the second desorption process, the purge gas that has flowed through the first adsorbent is made to flow into the second adsorbent through the connecting flow path. However, the period during which the first and second adsorbents are connected to each other to reuse the purge gas is not limited to the above embodiment. For example, the second desorption process may be divided into three periods, an early period, a middle period, and a late period, in which the first and second adsorbents are not connected to each other and carbon dioxide is desorbed only by the first adsorbent, in the early period, the first and second adsorbents are connected (multi-staged) and carbon dioxide is desorbed by the first and second adsorbents, and in the late period, the connection between the first and second adsorbents is again disconnected and carbon dioxide is desorbed only by the first adsorbent.

・上記第3、4実施形態では、第2脱離工程における吸着器の接続有無を、時間の経過に応じて切替える例を示したが、これに限定されない。例えば、第1吸着器から排出される混合ガスの二酸化炭素濃度が低いときに接続する(多段化する)等、第1吸着器から排出される混合ガスの二酸化炭素濃度に応じて接続有無を切替えてもよい。また、吸着器からの二酸化炭素の脱離速度が速いときに接続を解除する(単一吸着器)等、二酸化炭素の脱離速度に応じて接続有無を切替えてもよい。 - In the above third and fourth embodiments, an example was shown in which the connection/non-connection of the adsorber in the second desorption step was switched over time, but this is not limiting. For example, the connection/non-connection may be switched over depending on the carbon dioxide concentration of the mixed gas discharged from the first adsorber, such as connecting when the carbon dioxide concentration of the mixed gas discharged from the first adsorber is low (multi-stage). Also, the connection/non-connection may be switched over depending on the carbon dioxide desorption rate, such as disconnecting when the carbon dioxide desorption rate from the adsorber is high (single adsorber).

・上記実施形態では、混合ガス分流路とパージガス分流路とをバイパス流路としての接続流路80により接続する例をしめしたが、接続流路は上記実施形態に限定されない。例えば、接続流路80を、混合ガス分流路とパージガス分流路と別個に設けてもよい。接続流路80を、混合ガス分流路とパージガス分流路と別個に設ける場合、上記実施形態と同様に、第1吸着器内のパージガスの流通方向と第2吸着器内のパージガスの流通方向とが同じになるように接続してもよいし(例えば、第1吸着器と第2吸着器の図面下側を接続流路80によって接続する)、第1吸着器内のパージガスの流通方向と第2吸着器内のパージガスの流通方向とが異なり、ターンするように接続してもよい(例えば、第1吸着器の図面下側と、第2吸着器の図面下側を接続流路80により接続する)。 - In the above embodiment, the mixed gas branch path and the purge gas branch path are connected by the connection flow path 80 as a bypass flow path, but the connection flow path is not limited to the above embodiment. For example, the connection flow path 80 may be provided separately from the mixed gas branch path and the purge gas branch path. When the connection flow path 80 is provided separately from the mixed gas branch path and the purge gas branch path, they may be connected so that the flow direction of the purge gas in the first adsorber is the same as that in the above embodiment (for example, the first adsorber and the lower side of the second adsorber are connected by the connection flow path 80), or the flow direction of the purge gas in the first adsorber and the flow direction of the purge gas in the second adsorber are different and connected to turn (for example, the lower side of the first adsorber and the lower side of the second adsorber are connected by the connection flow path 80).

・上記実施形態におけるサージタンクを備えなくてもよい。サージタンクがある場合、混合ガスの水素と二酸化炭素の比率を安定させることができるほか、水素の流量を逐次調整しなくても水素と二酸化炭素の比率を目標の範囲内とすることができるため、好ましい。 - The surge tank in the above embodiment does not need to be provided. If a surge tank is provided, it is preferable because it can stabilize the ratio of hydrogen to carbon dioxide in the mixed gas and also allows the ratio of hydrogen to carbon dioxide to be within a target range without having to continually adjust the flow rate of hydrogen.

・他の実施形態として、二酸化炭素循環システムや、炭化水素を燃料とする燃料製造システムを構成してもよい。例えば、二酸化炭素循環システムは、上記第5実施形態の炭化水素製造システム5と、炭化水素製造システム5の炭化水素生成部8から供給されるメタンと、炭化水素製造システム5のサージタンク40から供給される二酸化炭素と、大気中の空気とを用いる燃焼器を備え、燃焼器から排出される排ガスを炭化水素製造システム5に供給することにより、二酸化炭素を循環させる。また、燃料製造システムは、上記第5実施形態の炭化水素製造システム5と、燃料製造部を備え、炭化水素製造システム5により製造された炭化水素を用いて、燃料を製造する。 - As other embodiments, a carbon dioxide circulation system or a fuel production system using hydrocarbons as fuel may be configured. For example, the carbon dioxide circulation system includes the hydrocarbon production system 5 of the fifth embodiment described above, a combustor that uses methane supplied from the hydrocarbon generation unit 8 of the hydrocarbon production system 5, carbon dioxide supplied from the surge tank 40 of the hydrocarbon production system 5, and air in the atmosphere, and circulates carbon dioxide by supplying exhaust gas discharged from the combustor to the hydrocarbon production system 5. In addition, the fuel production system includes the hydrocarbon production system 5 of the fifth embodiment described above, and a fuel production unit, and produces fuel using the hydrocarbons produced by the hydrocarbon production system 5.

以上、実施形態、変形例に基づき本発明について説明してきたが、上記した態様の実施の形態は、本発明の理解を容易にするためのものであり、本発明を限定するものではない。本発明は、その趣旨並びに特許請求の範囲を逸脱することなく、変更、改良され得ると共に、本発明にはその等価物が含まれる。また、その技術的特徴が本明細書中に必須なものとして説明されていなければ、適宜、削除することができる。 The present invention has been described above based on the embodiments and modifications, but the embodiments of the above-mentioned aspects are intended to facilitate understanding of the present invention and do not limit the present invention. The present invention may be modified or improved without departing from the spirit and scope of the claims, and the present invention includes equivalents. Furthermore, if a technical feature is not described as essential in this specification, it may be deleted as appropriate.

1、1A、1C、1P…ガス分離システム
5…炭化水素製造システム
8…炭化水素生成部
10、11、12、13、14、15…吸着器
11a、12、13a、14a、15a…吸着材
20…二酸化炭素含有ガス供給流路
21、22、23…排ガス分流路
21a、22a、23a…排ガス入口弁
30…熱媒流路
30a…ヒータ
31、32…熱媒分流路
31a、32a…熱媒入口弁
40…サージタンク
45…真空ポンプ
46…減圧流路
47、48…切換弁
55…制御部
60…混合ガス流路
61、62、63、64…混合ガス分流路
61a、62a、63a、64a…混合ガス出口弁
70…パージガス供給流路
70a…流量制御器
71、72、73、74…パージガス分流路
71a、72a、73a…パージガス入口弁
80、81、82、83、84、85…接続流路
81a、82a、83a、84a、85a…接続流路弁
1, 1A, 1C, 1P... Gas separation system 5... Hydrocarbon production system 8... Hydrocarbon production section 10, 11, 12, 13, 14, 15... Adsorber 11a, 12, 13a, 14a, 15a... Adsorbent 20... Carbon dioxide-containing gas supply flow path 21, 22, 23... Exhaust gas branch flow path 21a, 22a, 23a... Exhaust gas inlet valve 30... Heat medium flow path 30a... Heater 31, 32... Heat medium branch flow path 31a, 32a... Heat medium inlet valve 40... Surge tank 45... Vacuum pump 46... Pressure reduction flow path 47, 48... Switching valve 55... Control section 60... Mixed gas flow path 61, 62, 63, 64... Mixed gas branch flow path 61a, 62a, 63a, 64a... Mixed gas outlet valve 70... Purge gas supply flow path 70a... Flow rate controller 71, 72, 73, 74... Purge gas branch passages 71a, 72a, 73a... Purge gas inlet valves 80, 81, 82, 83, 84, 85... Connection passages 81a, 82a, 83a, 84a, 85a... Connection passage valves

Claims (4)

二酸化炭素を吸着可能な吸着材を内部に収容する複数の吸着器を備えるガス分離システムであって、
前記複数の吸着器のうち、第1吸着器と第2吸着器とを直列に接続可能な接続流路と、
前記第1吸着器にパージガスを供給可能なパージガス供給流路と、
前記第1吸着器と前記第2吸着器に二酸化炭素が吸着された状態で、前記パージガス供給流路を介して、前記第1吸着器に前記パージガスを供給させ、前記第1吸着器から二酸化炭素を脱離させる第1脱離工程と、工程の少なくとも一部の期間において前記接続流路を介して前記第1吸着器に前記第2吸着器を接続させ、前記第1吸着器内を流通したパージガスを、前記接続流路を介して前記第2吸着器に流入させ、前記第2吸着器から二酸化炭素を脱離させる第2脱離工程を、同時に実行可能な制御部と、
を備え
前記パージガスは、水素である、
ガス分離システム。
A gas separation system including a plurality of adsorbers each containing an adsorbent capable of adsorbing carbon dioxide,
a connection flow path capable of connecting a first adsorption unit and a second adsorption unit in series among the plurality of adsorption units;
a purge gas supply passage capable of supplying a purge gas to the first adsorption device;
a control unit capable of simultaneously executing a first desorption step of supplying the purge gas to the first adsorber via the purge gas supply flow path in a state in which carbon dioxide is adsorbed in the first adsorber and the second adsorber, and desorbing carbon dioxide from the first adsorber, and a second desorption step of connecting the second adsorber to the first adsorber via the connecting flow path during at least a portion of the step, causing the purge gas that has circulated inside the first adsorber to flow into the second adsorber via the connecting flow path, and desorbing carbon dioxide from the second adsorber;
Equipped with
The purge gas is hydrogen .
Gas separation systems.
請求項1に記載のガス分離システムであって、
二酸化炭素を含有する二酸化炭素含有ガスを、前記第1吸着器および前記第2吸着器と異なる第3吸着器に供給可能な、二酸化炭素含有ガス供給流路をさらに備え、
前記制御部は、
前記二酸化炭素含有ガス供給流路を介して、前記第3吸着器に前記二酸化炭素含有ガスを供給させて、二酸化炭素を吸着させる吸着工程を、前記第1脱離工程と同時に実行可能であり、
同時に実行される前記第1脱離工程、前記第2脱離工程、および前記吸着工程を含む吸脱着工程を、前記第1脱離工程、前記第2脱離工程、および前記吸着工程のそれぞれが実行される前記第1吸着器、前記第2吸着器、および前記第3吸着器を変更して繰り返し実行可能である、
ガス分離システム。
2. The gas separation system of claim 1,
a carbon dioxide-containing gas supply flow path capable of supplying a carbon dioxide-containing gas to a third adsorption device different from the first adsorption device and the second adsorption device;
The control unit is
An adsorption step of supplying the carbon dioxide-containing gas to the third adsorption device through the carbon dioxide-containing gas supply passage to adsorb carbon dioxide can be carried out simultaneously with the first desorption step,
an adsorption/desorption process including the first desorption process, the second desorption process, and the adsorption process, which are simultaneously performed, can be repeatedly performed by changing the first adsorption device, the second adsorption device, and the third adsorption device in which the first desorption process, the second desorption process, and the adsorption process are performed, respectively;
Gas separation systems.
請求項1または請求項2に記載のガス分離システムであって、
前記制御部は、
前記第2脱離工程の一部の期間において、前記第1吸着器内を流通したパージガスを、前記接続流路を介して前記第2吸着器に流入させる、
ガス分離システム。
3. A gas separation system according to claim 1 or claim 2,
The control unit is
during a part of the second desorption step, the purge gas that has circulated through the first adsorption device is caused to flow into the second adsorption device via the connecting flow path;
Gas separation systems.
炭化水素製造システムであって、
請求項1から請求項3のいずれか一項に記載のガス分離システムと、
前記ガス分離システムと接続され、前記ガス分離システムにより分離された二酸化炭素と、前記パージガスとして用いられた水素との混合ガスを用いて、炭化水素化合物を生成する炭化水素生成部と、を備える、
炭化水素製造システム。

1. A hydrocarbon production system comprising:
A gas separation system according to any one of claims 1 to 3 ;
A hydrocarbon production unit is connected to the gas separation system and produces a hydrocarbon compound using a mixed gas of carbon dioxide separated by the gas separation system and hydrogen used as the purge gas.
Hydrocarbon production systems.

JP2020211017A 2020-12-21 2020-12-21 Gas separation systems, and hydrocarbon production systems Active JP7655722B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020211017A JP7655722B2 (en) 2020-12-21 2020-12-21 Gas separation systems, and hydrocarbon production systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020211017A JP7655722B2 (en) 2020-12-21 2020-12-21 Gas separation systems, and hydrocarbon production systems

Publications (2)

Publication Number Publication Date
JP2022097832A JP2022097832A (en) 2022-07-01
JP7655722B2 true JP7655722B2 (en) 2025-04-02

Family

ID=82165928

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020211017A Active JP7655722B2 (en) 2020-12-21 2020-12-21 Gas separation systems, and hydrocarbon production systems

Country Status (1)

Country Link
JP (1) JP7655722B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024057593A1 (en) * 2022-09-14 2024-03-21 株式会社Ihi Hydrocarbon production system and hydrocarbon production method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012005920A (en) 2010-06-22 2012-01-12 Jfe Steel Corp Gas separation method by pressure swing adsorption method
US20150007726A1 (en) 2013-07-08 2015-01-08 Exxonmobil Research And Engineering Company Simulated moving bed system for co2 separation, and method of same
JP2019108290A (en) 2017-12-18 2019-07-04 株式会社豊田中央研究所 Manufacturing device of methane and manufacturing method of methane using the same
JP2019142806A (en) 2018-02-20 2019-08-29 株式会社豊田中央研究所 Methane production apparatus and methane production method
JP2020531272A (en) 2017-08-28 2020-11-05 カサーレ ソシエテ アノニム Temperature swing adsorption method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012005920A (en) 2010-06-22 2012-01-12 Jfe Steel Corp Gas separation method by pressure swing adsorption method
US20150007726A1 (en) 2013-07-08 2015-01-08 Exxonmobil Research And Engineering Company Simulated moving bed system for co2 separation, and method of same
JP2020531272A (en) 2017-08-28 2020-11-05 カサーレ ソシエテ アノニム Temperature swing adsorption method
JP2019108290A (en) 2017-12-18 2019-07-04 株式会社豊田中央研究所 Manufacturing device of methane and manufacturing method of methane using the same
JP2019142806A (en) 2018-02-20 2019-08-29 株式会社豊田中央研究所 Methane production apparatus and methane production method

Also Published As

Publication number Publication date
JP2022097832A (en) 2022-07-01

Similar Documents

Publication Publication Date Title
CN112312993B (en) Method and apparatus for adsorption/desorption of carbon dioxide from a gas stream using a heat recovery unit
KR102912565B1 (en) Method for operating a hydrogen production device and a hydrogen production device
JP2025021536A (en) Adsorption tower control device, gas separation device, method for controlling multiple adsorption towers, and computer program
JP7825479B2 (en) Gas adsorption apparatus and gas adsorption method
US20130061750A1 (en) Method and apparatus for concentrating ozone gas
JP7465126B2 (en) Gas separation apparatus, methane production apparatus, gas separation method, and method for controlling gas separation apparatus
JP7655722B2 (en) Gas separation systems, and hydrocarbon production systems
JPH0565206B2 (en)
JP7356885B2 (en) Gas separation device and control method for gas separation device
JP7263882B2 (en) Carbon dioxide recovery device, hydrocarbon production device, and carbon dioxide recovery method
JP5665120B2 (en) Argon gas purification method and purification apparatus
CN103224225B (en) The purification process of argon gas and purification devices
JP5427412B2 (en) Ozone gas concentration method and apparatus
CN112827317B (en) Temperature swing adsorption system without purified gas loss and purified gas recovery method
JP2005103335A (en) Thermal desorption type oxygen concentrating apparatus
JP2015163393A (en) Method and equipment for oxygen separation
JP2020163247A (en) Carbon dioxide recovery equipment, hydrocarbon production equipment, and carbon dioxide recovery method
JP2024150018A (en) Hydrocarbon Production Equipment
CN109173568B (en) Active carbon level difference adsorption safe concentration method
CN222076254U (en) Carbon dioxide recovery system in boiler flue gas
JPH05277325A (en) Helium gas refining apparatus and operating method thereof
CN113614026B (en) Method for operating hydrogen production device and hydrogen production device
CN118543224B (en) A low energy consumption combined carbon capture method
CN102807199B (en) Purifying method and purifying device for argon gas
KR101823154B1 (en) Purifying method and purifying apparatus for argon gas

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230720

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20240417

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240423

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240621

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20241001

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20241128

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20250305

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20250321

R150 Certificate of patent or registration of utility model

Ref document number: 7655722

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150